Belfast Hotel Project
6
Belfast Hotel Project • 141 Bedrooms • 15 VRF 3-Pipe Systems • 151 Indoor Units • Total Installed Capacity – 398 kW • Site time – 16 Weeks
-
Upload
yvonne-quinn -
Category
Documents
-
view
37 -
download
1
description
Belfast Hotel Project. 141 Bedrooms 15 VRF 3-Pipe Systems 151 Indoor Units Total Installed Capacity – 398 kW Site time – 16 Weeks. Design Stage. Design Calculations - Cymap Indoor Unit Type System Capacities Pipe runs and piping restrictions. Site Drawings. - PowerPoint PPT Presentation
Transcript of Belfast Hotel Project
Belfast Hotel Project
• 141 Bedrooms
• 15 VRF 3-Pipe Systems
• 151 Indoor Units
• Total Installed Capacity – 398 kW
• Site time – 16 Weeks
Design Stage• Design Calculations - Cymap• Indoor Unit Type• System Capacities• Pipe runs and piping restrictions
Site Drawings
5-Year Peace of Mind Warranty
• Design criteria met with regard to horizontal and vertical pipe runs
• Validated pressure tests and evacuation procedures
• Calculated refrigerant added to system
• Detailed commissioning reports by certified engineer returned to Toshiba
• Maintenance contract in place with an Accredited Installer
• 5-Year parts and labour warranty with manufacturer not contractor
Manufacturers Warranty