Bear_Presentation.ppt

download Bear_Presentation.ppt

of 35

Transcript of Bear_Presentation.ppt

  • Abstract*Our project is about ( Foundation Design of Al-Maslamani Mall) which is located in the village of Beit Eba Nablus governorate.

    *The total plan area of this mall is about 3500 m2

    *The number of stories is 6; 4 stories above the ground surface & 2 stories are below the ground surface.

  • Literature Review

    Site Investigation is the first important step in any engineering work ; to determine type & depth of foundations , to evaluate bearing capacity , to identify construction methods & for many things

    Foundations are the part of an engineered system to receive & transmit loads from superstructure to the underlying soil or rock .

    There are two types of foundations : shallow & deep foundations.

    Many factors should be taken into consideration in choosing foundation types such as soil properties , economic factors, engineering practice, ....etc

  • Isolated footingsPilesCombined FoundationsMat

  • Isolated FootingsAre used to support single columns.

    This is one of the most economical types of footings and is used when columns are spaced at relatively long distances.

    Its function is to spread the column load to the soil , so that the stress intensity is reduced .

  • are used to spread the load from a structure over a large area, normally the entire are of the structure .They often needed on soft or loose soils with low bearing capacity as they can spread the loads over a larger area.They have the advantage of reducing differential settlements.Mat or Raft Foundations

  • Are used in the following cases:

    1) When there are two columns so close to each other & in turn the two isolated footing areas would overlap.

    2) When the combined stresses are more than the allowable bearing capacity of the soil.

    3) When columns are placed at the property line.

    Combined Foundations

  • Cantilever footing construction uses a strap beam to connect an eccentrically loaded column foundation to the foundation of an interior column .

    Are used when the allowable soil bearing capacity is high, and the distances between the columns are large .Strap or Cantilever Footings

  • Pile FoundationsThey are long & slender members that are used to carry & transfer the load of the structure to deeper soil or rocks of high bearing capacity, when the upper soil layer are too weak to support the loads from the structure.

    Piles costs more than shallow foundations; so the geotechnical engineer should know in depth the properties & conditions of the soil to decide whether piles are needed or not.

  • Classification of the pilesAccording to load transmission & functional behavior :1) End / Point bearing piles2) Friction piles3) Compaction piles

    According to type of material:1) Steel piles 2) Timber piles3) Concrete piles 4) Composite piles

    According to effect on the soil:1) Driven piles2) Bored piles

  • Bearing Capacity : is the ability of a soil to support the loads applied to the ground . Ultimate bearing capacity is the theoretical maximum pressure which can be supported without failure; Allowable bearing capacity is the ultimate bearing capacity qu divided by a factor of safety (F.S).

    There are three modes of failure that limit bearing capacity: general shear failure, local shear failure, and punching shear failure.

    Any structure built on soil is subject to settlement. Some settlement is inevitable, & depending on the situation, some settlements are tolerable.

    When building structures on top of soils, one needs to have some knowledge of how settlement occurs & how fast settlement will occur in a given situation.

    Bearing Capacity & Settlement

  • Geotechnical InvestigationThe studied area is approximately flat with slight difference in the three existing elevations. The general soil formation within the depths of the borings consists mostly of wadi deposits of boulders & silty clay followed by successive layers of hard boulders mixed with very little filling silty clay. The whole site is covered by grass.The geotechnical engineer decided to drill four boreholes trying to cover the whole construction area.

  • = 20 KN/m w = 7.6 % (avg.) C = 0 KN/m (average) LL = 44.5 % = 25 PI = 25 qall. = 3.0 kg/cm2 G = 2.73 a-Coefficient of active earth pressure: KA = 0.405 b- Coefficient of passive earth pressure: KP = 2.464 c- Coefficient of pressure at rest: Ko = 0.577

    The depths of the drilled boreholes were as follows:Summary of lab. test results:

    Borehole No.LocationDepth (m)1South-west7.02East7.03West6.04North10.0

  • After doing check on the bearing capacity value using FOUND software by using Terzaqi and Meyerhoff formulas, the value was ranging between 3.2 and 4.3 Kg/ cm2 respectively, SO we decided to use a value of 3.5 Kg/ cm2 in our project.

  • Load Calculations

  • Manual Design steps:Area of footing = Total service loads on column / net soil pressureDetermine footing dimensions B & H .Assume depth for footing.Check soil pressure.Check wide beam shear : Vc > Vult Check punching shear : Vcp > Pult, punching Determine reinforcement steel in the two directions.Check development length .Check load transfer from column to footing .

    Then, we compare manual design with SAP design in footings F4 & F8 .

    Isolated Footing Design

  • The solution of SAP is always smaller than manual one, since SAP uses Finite Element Method.

    There is no need to calculate the settlement of the isolated footings; since the soil is gravelly soil , & has a qall. of 3.5 kg/cm2 .

    The final results of isolated footings design are in the next table :

  • Wall Stair Footing

  • Dimensions and Reinforcement Details of Wall Stair Footing

    Depth of wall footing = 60 cm.Width of wall = 20 cm.Width of footing (B) = 2 m.

    Reinforcement:6 16 / m in short direction14 16 in long direction

  • Elevator Wall Footing

  • Dimensions and Reinforcement Details of Elevator Wall Footing Depth = 33cm, h=40cm

    4 16 / m For positive moment & negative momentIn both directions.

    Reinforcement details for elevator wall :

  • Pile Foundation

  • Design of pile foundation1-Estimating pile capacity

    The ultimate carrying capacity is equal to the sum of the ultimate resistance of the base of the pile and the ultimate skin friction over the embedded shaft length of the pile, this expressed by :

    Qu = Qp + Qs

  • 2-Determination of the point bearing capacityFor piles in rocky sand soil as in our case , the point bearing capacity may be estimated as :QP = Ap q' Nq* QlimitWhere:Ap : Area of the pile tip. q : effective stress at pile tip.Nq*: Factor depends on soil friction angle

    Qlimit =(0.5 Pa Nq* tan ) Ap

  • 3-Determination of skin resistance

    It can be calculated by using the following formula: QS = {P*L*f }Where:L : Length of the pileP : Perimeter of the pilef : Frictional factor

  • The following table presents the dimensions of piles and their capacities in (KN).

  • Summary of piles sizes, number of piles needed, cap dimensions:

  • The structural pile design depends on the nature of soil, which is either stiff or weak, the pile is to be designed as short column if the soil is stiff , and designed as along column if the soil is weak.

    The minimum area of steel is 0.5% of the gross area of the pile, also the ties are used starting with 5 cm spacing and ending by 30 cm spacing .the concrete cover must be not less than 7.5 cm. Asmin=0.005Ag

  • Efficiency of pile group The efficiency of the load-bearing capacity of a group pile may be defined as:M= Qg(u ) / QuWhere:Qg(u)= ultimate load bearing capacity of the group pile.Qu= ultimate load-bearing capacity of each pile without the group effect Using simplified analysis to obtain the group efficiency as shown in the following formula: = (2(m+n-2) + 4D) / (pmn)Where: m: # of piles in the direction of Lg. n:# of piles in the direction of Bg. d: Spacing between piles centers. D: Diameter of the pileP: Perimeter of pile cross section

  • Design of a pile cap:The minimum distance between two piles is 3D. Pile caps should extend at least 15 cm beyond the outside face of exterior face of exterior piles.The minimum thickness of pile cap above pile heads is 30 cm. The cover in pile caps commonly ranges between 20 & 25 cm .

    Design Steps:Assume depth (d)Check Punching shear : Vcp > Vult, punching Check wide beam shear : Vc > Vult Calculate area of steel needed Check min. < < max.

  • Retaining Wall Design:The retaining wall is designed by PROKON Program :

  • Conclusions:

    1) From soil report, we note that PI is 25 and cohesion is zero and this can be explained by the following:We have soil contains some clay between gravels, and when we take a sample of this soil to be tested for atterberg limits to determine PI,we use sieve #40 and we take the passing which are clay particles and in turn this leads to increase the magnitude of plasticity index.Cohesion is zero since the soil sample is almost gravel.

    2) After designing the two alternative choices (single footings and piles system) & surveying the quantities for concrete only, we find that it is more practical, realistic and economical to use single footings

    3) there is no need to make settlement calculations for footings and piles ,since we have a gravely soil with B.C of 3.5 kg/cm2(the settlements in our situation are tolerable, so we can ignore them)..

  • *