Bear Road Elementary School Additions and Renovations · 2020. 7. 19. · Bear Road Elementary...

11
Bear Road Elementary School Additions and Renovations

Transcript of Bear Road Elementary School Additions and Renovations · 2020. 7. 19. · Bear Road Elementary...

Bear Road Elementary School Additions and Renovations

Tasks Underway

• Foundations for Area A addition are currently underway, backfill expected to start next week

• Asbestos Abatement

• Courtyard site work has begun

• Demolition in various areas

• Photos• Top: Courtyard site work

• Bottom: Foundations in Area A

Status of Asbestos Abatement

• Area C asbestos abatement is underway, expected to be completed in the first week of August

• Area A asbestos abatement is complete

• Additional ACM discovered in exterior walls

Status of Demolition

• Area A Demolition Complete

• Area C Demolition 50% complete

• Crawlspace mechanical, electrical and plumbing demolition is underway

• Photos:

• Top left and bottom: taken during Area A demolition

• Top Right: taken during crawlspace demolition

Bus Loop Mock-Up / Transportation

• July 15th this area was simulated in the M&O parking lot

• Drivers navigated the proposed route and provided comments

• Overall route is feasible though several concerns were raised

• A/E is reviewing and will share possible solutions at next project meeting

Wetlands Work

• Storm drainage improvements from the school to the wetlands will be taking place this summer

• Photos• Top: existing conditions at storm drain outlet

• Bottom: Proposed site grading plan from Appel Osborne

Upcoming Work

• Structural Steel erection in Area A expected early August

• Plumbing rough in of Area A

• Excavation of crawl space

• Roofers expected to begin work by mid August

Potential Roadblocks

• COVID-19 impacts on material deliveries

• Shortage of manpower due to private/public work restarting simultaneously

Where We Expect to be Come September

• Steel super structure complete at the Kindergarten wing

• Roofing over Kindergarten wing

• Corridor between Area A and Area B complete

• Wetlands / drainage improvements complete

Brick Work at Junior/Senior High School• Brick work at flashings, expected to be complete in approximately 2 months

Playground Work

• Main St. Playground demo scheduled for next week

• Installation only a few weeks away

• Bear Rd Playground design completed, many thanks to committee members for all of their input and assistance

• Virtual tour is available on district website

https://www.youtube.com/watch?v=vliRBWy2AqM&feature=youtu.be