Tasks Underway
• Foundations for Area A addition are currently underway, backfill expected to start next week
• Asbestos Abatement
• Courtyard site work has begun
• Demolition in various areas
• Photos• Top: Courtyard site work
• Bottom: Foundations in Area A
Status of Asbestos Abatement
• Area C asbestos abatement is underway, expected to be completed in the first week of August
• Area A asbestos abatement is complete
• Additional ACM discovered in exterior walls
Status of Demolition
• Area A Demolition Complete
• Area C Demolition 50% complete
• Crawlspace mechanical, electrical and plumbing demolition is underway
• Photos:
• Top left and bottom: taken during Area A demolition
• Top Right: taken during crawlspace demolition
Bus Loop Mock-Up / Transportation
• July 15th this area was simulated in the M&O parking lot
• Drivers navigated the proposed route and provided comments
• Overall route is feasible though several concerns were raised
• A/E is reviewing and will share possible solutions at next project meeting
Wetlands Work
• Storm drainage improvements from the school to the wetlands will be taking place this summer
• Photos• Top: existing conditions at storm drain outlet
• Bottom: Proposed site grading plan from Appel Osborne
Upcoming Work
• Structural Steel erection in Area A expected early August
• Plumbing rough in of Area A
• Excavation of crawl space
• Roofers expected to begin work by mid August
Potential Roadblocks
• COVID-19 impacts on material deliveries
• Shortage of manpower due to private/public work restarting simultaneously
Where We Expect to be Come September
• Steel super structure complete at the Kindergarten wing
• Roofing over Kindergarten wing
• Corridor between Area A and Area B complete
• Wetlands / drainage improvements complete
Brick Work at Junior/Senior High School• Brick work at flashings, expected to be complete in approximately 2 months
Playground Work
• Main St. Playground demo scheduled for next week
• Installation only a few weeks away
• Bear Rd Playground design completed, many thanks to committee members for all of their input and assistance
• Virtual tour is available on district website
https://www.youtube.com/watch?v=vliRBWy2AqM&feature=youtu.be