beam instrumentation.pdf
-
Upload
srivenu-chinna -
Category
Documents
-
view
217 -
download
0
Transcript of beam instrumentation.pdf
-
7/29/2019 beam instrumentation.pdf
1/17
Test Beam infrastructure
-
7/29/2019 beam instrumentation.pdf
2/17
Outline
1. beam momenta
2.intensities
3.PID
4.Experimental magnet5.Triggers
6.Detector manipulation and assembly
7.Electronics
8.Gas and HV sytems, DCS (slow control)9.First comments on cost, manpower, timescale
-
7/29/2019 beam instrumentation.pdf
3/17
Choice of beamline
Indicated momentum range: 100MeV/c to 20GeV/c
Best match, purely on the base of momentum,wouldbe the T9 beamline at the PS ...
but also a large and powerful magnet was desidered,so second-in-the-row is the H8 SPS beam line,located in the Nort Hall.
Lets be clear: what follows makes sense if and only if
we need to put a detector in a 1.5T B field
-
7/29/2019 beam instrumentation.pdf
4/17
H8 beam line
Secondary beamline of the primary T4 target, capable ofdelivering 5 GeV/c to 300 GeV/c secondaries
In our momentum range, 5 to 20 GeV/c is standard
1 to 5 GeV/c adaptation already studied for the Atlas
test-beam. It implies a secondary target and generationof a tertiary beam. To be discussed with experts,feasible.
100 MeV/c to 1 GeV/c might need additional equipmentand instrumentation (e.g. slow down particles in
absorbers)General rule: the lower the momentum, the lower theintensity
-
7/29/2019 beam instrumentation.pdf
5/17
.
TARGET
T4
Scale :
100
200 mm
0
0
2 4 86 10 m
B1T B3TB2T
P0 beam
H8 beam
H6
beam
450 GeV/cprotons
!prod
BEND
1
-
7/29/2019 beam instrumentation.pdf
6/17
i l
Concept of
tertiary beam(source:I. Efthymiopoulos
notes)
Possible addtions (t.b.d)
Absorber
(instrumented?)
Momentum
analysis + PID
~1 GeV/c ~100 MeV/c
-
7/29/2019 beam instrumentation.pdf
7/17
Intensity
Indicated statistics: n*10^4 events per setting
Need to know more precisely how many settings. How manyangles, particles/momenta, detector configurations?
My first guess is 10^7 events.
To fulfill this in 2 weeks (standard duration of a test-beam)one needs ~10^3 particles per spill.
No problem at higher momenta, lower momenta will be slower,but not quantified yet.
Time to modify/manipulate the detector not included.
This point is important: we have to state how much time weneed as primary users of the beam line.
-
7/29/2019 beam instrumentation.pdf
8/17
PID
Indicated particle ID at the 10^(-3) level. This is quitechallenging
Best match I could indicate is the NA56/SPYapproach (incidentally, located in H6 - the line
closeby H8)Very long instrumented beam line, designed toanalyze particle production from 7 to 60 GeV/c(hadron production for the WANF neutrino beam)
PID was at the % level. Is this enough?
Need studies and simulations if we need anythingbetter.
-
7/29/2019 beam instrumentation.pdf
9/17
T4-berylliumt
arget
0m 100m 500m400m300m200m
vertical plane
horizontal plane
hadroncalorimeter
T4
NA56 / SPY instrumented beam line
-
7/29/2019 beam instrumentation.pdf
10/17
Magnet
H8 is equipped with a large (1.6m bore) super-conducting dipole, the so-called Morpurgo magnet
1.56T is standardField maps exist, most recent are likely those of theAtlas test-beam
I assume that operational costs (He consumption) are
going to be included in some agreement with CERN
-
7/29/2019 beam instrumentation.pdf
11/17
Z slice
XY slice at the center
-
7/29/2019 beam instrumentation.pdf
12/17
Triggers
I do not expect this to be a problem in aninstrumented beam line
No cosmic triggers have been requested (... correct?)so no special coverage with large-area scintillatorplanes
Design of coincidences and particle tagging to bedone, but not urgent as of now
-
7/29/2019 beam instrumentation.pdf
13/17
Detector assembly and manipulation
Each detector type most likely need a specificplatform
At least one platform for detectors to be insertedinto the magnet (plus insertion/extraction rails)
Platform for magnetized iron types needs sliding/tilting mounting plates to accommodate the need for
data taking at different angles
changing active/passive materials and
configurationsCrane not a problem (single element weight belowmaximum at the NH)
-
7/29/2019 beam instrumentation.pdf
14/17
Electronics
From considerations about intensities, it follows thatthe electronics must cope with n*10^3 events per
spill - which I assume it is not a problem with theSPS long spills.
DAQ has to cope too. Again I do not expect this tobe a show stopper.
More specific issues not my duty ...
-
7/29/2019 beam instrumentation.pdf
15/17
Gas and HV systems, DCS
MIND/ECC/TASD detectors need fairly standard HV and gassystems. I assume these systems can be a common investmenttogether with the other users of the infrastructure
Same applies to DCS (slow control) system for detectorcontrol and environmental monitoring
Exceptions:
power supply for magnetized iron coils
L-Ar HV and gas system
... ?
I also assume that barracks and counting houses will beincluded in the common infrastructure or negotiated withCERN
-
7/29/2019 beam instrumentation.pdf
16/17
Cost
Main items to include in a cost analysis
beam line equipment and modifications
construction of assembly and manipulation
equipment for detectorsbeam line instrumentation
Total amount is going to be similar to infrastructurefor a small experiment
There will for sure be costs for cabling, piping andtechnicians during installations
-
7/29/2019 beam instrumentation.pdf
17/17
Time-scale
Physicists/engineers: 1 DAQ, 1 Electronics, 1mechanical engineer
First activities must be
discussion with beam line experts
simulation of the beam line
mechanical design
if time-scale is 2009-2012, these activities shouldstart rather soon.