Beam Commissioning Marco Oriunno (SLAC), May 14, 2014 ALCW 2014, Fermilab Engineering Issues.
-
Upload
griselda-small -
Category
Documents
-
view
213 -
download
0
Transcript of Beam Commissioning Marco Oriunno (SLAC), May 14, 2014 ALCW 2014, Fermilab Engineering Issues.
Beam Commissioning
Marco Oriunno (SLAC), May 14, 2014
ALCW 2014, Fermilab
Engineering Issues
2
Possible Commissioning Scenarios
The key requirements originate from a defined strategy for
the commissioning BDS Commissioning, set by the physics
requirements of the Machine and Detectors.
Meanwhile we look at three possible engineering options:
1. w/ Detector
2. w/o Detector, only QF1
3. w/o Detector, QD0 and QF1
3
Challenges and Opportunities
Challenges
• Safety Issues, mainly radiation shielding for a credible
beam loss scenario
• Engineering Issues: Cabling, supports of temporary Beam
Instrumentation.
Opportunities
• Detector-Machine Schedule decoupling
• Leverage on the Push-Pull concept
• Dedicated Machine Development phases
• Opportunity for additional small forward detectors: TOTEM
in the high pseudo-rapidity region ( =h 3÷5) of CMS
4
Option #1: w/ Detector
1. QD0s in place with the corresponding L*
2. Full set of forward detectors (Beamcal, Lumical, etc.)
3. Probably starting with the Vertex detector in place …..the
ATLAS and CMS experience need to be recalled
4. One of the two detectors must be always available for
commissioning and Machine Development:
• How to decide which one, case by case, strictly planned?
• Impact on assembly and maintenance schedule of the
detectors.
5
Option #2: w/o Detector, only QF1
1. Only QF1s with a commissioning optics
2. A basic set of beam instrumentation able to characterize the beam
delivery to the IP (BPM, Beam scanners, etc.)
Option A Permanently integrated in the QF1s regions: minimum impact
on schedule
Option B Movable light skid pre-assembled with the required diagnostic.
Option B cont. Services connection (Cables, Cooling, Cryo) set the
critical path.
Push-Pull : Engineering Concept (Option #1 and #2)
Detector Hall, Japanese Mountain Site
e-
LHe refrigerator and LHe2 for the QD0’s above level on metallic structure.
7
Option #3: w/o Detector, QD0 and QF1
1. Spares QD0s in place with only one L* possible
2. A basic set of beam instrumentation able to characterize
the beam delivery to the IP (BPM, Beam scanners, etc.)
1. Movable light skid pre-assembled with the required
diagnostic.
2. Services connection (Cables, Cooling, Cryo)
3. Possibility of a small-bore/high field MRI solenoid
around the IP for beam distortion studies.
8
Option #3: w/o Detector, QD0 and QF1
1. In normal operations the FFS push-pull with the detectors
together with interconnections (High Current Leads and
Cryogenic)
2. If dedicated QDOs for commissioning are installed, Power
supplies and Cryogenics require not trivial infrastructures.
3. The pumping and the cooling down define the critical path
4. It is eventually a place where the Hybrid FFS Design a-la
CLIC has a strategic advantage.
9
Interface QD0-QF1: Critical for Fast&Reliable Push-Pulls
1 m QF1QD0
Kicker
Cryogenic Penetration
Vacuum Instrumentation
MSL - SLAC 10
20 R.L. Cu target in IP-14 m. Large pacman.
µSv/1_train
Dos
e lim
its
Max
imum
do
se
- The maximum integrated dose per event is ~8 µSv << 30 mSv
- The corresponding peak dose rate is ~140 mSv/h < 250 mSv/h
9 MW
M.Santana, SLAC
11
Pacmen
500 mm Iron2,000 mm Concrete
12
Shielding Wall
13
IP
5 mrad
~40 mrad~85 m
rad
Challenges: High precision, high occupancy,high radiation dose, fast read-out!LumiCal, BeamCal: compact sampling calorimeters, RM~1 cm
Further Physics Opportunities
Precise measurement o the Integrated Luminosity (ΔL/L ~ 10-4).
Provide 2 photon veto.
BeamDiagnostics using beamstrahlung pairs.
Provide 2 photon veto.
BeamDiagnostics using beamstrahlung photons.
14
Summary
Need Machine and Detectors to work on the definition of
BDS commissioning, which in turn will define the set of
requirements for the engineering studies
Three options under study cover the full range of possibility.
1. w/ Detector
2. w/o Detector, only QF1
3. w/o Detector, QD0 and QF1
All options have different challenges and opportunities
EXTRA SLIDES
15
16
Cryogenic Layout : Two options
Plan A : Cold Boxes are stationary. Cold Transfer lines to
each detector. Reliability for push-pull. Not off-the-shelf.
Plan B : Cold Boxes on the platform. Warm Transfer lines to
each cold box. Vibrations, fringe field effects, space
CLID QD0 : Hybrid magnet
Permanent magnet
Why a an Hybrid magnet ?
•Limited space available for the magnet difficult to accommodate a cryostat
•Magnet aperture too small to wind a superconducting cables given the large forces and the small radius;
•Complex assembly, difficult to align and stabilize at the sub-nanometer level (different layers of coils, collars, thermal insulation, cryostat);
•Difficult integration of a conical post-collision line in a cryostat assembly.
ILC QD0 : Cold Mass 2K Helium (BNL)
~3.5 m
• Technology of the superconducting final focus magnets has been demonstratedby a series of short prototype multi-pole coils.
• QD0 magnet split into two coils to allow higher flexibility at lower energies.
• The quadrupoles closest to the IP are actually inside the detector solenoid.
• Actively shielded coil to control magnetic cross talk•Additional large aperture anti-solenoid in the endcap region to avoid luminosity loss due to
beam optics effects. • Large aperture Detector Integrated Dipole (DID) used to reduce detector background
at high beam energies or to minimize orbit deflections at low beam energies.
Magnetic Field compensations at IP, DID, antiDID
QD0
QD0
Pairs distributions at 3.5m from IP
anti-DID ONanti-DID OFF
IP
-1
0
1
2
3
4
-12 -10 -8 -6 -4 -2 0
ILD, l*=4.5 m
Bz (T)
z (m)
SF1 QF1 DIPSD0 QD0
-2
-1
0
1
2
3
4
5
6
-12 -10 -8 -6 -4 -2 0
SolenoidSolenoid+anti-solenoidanti-solenoid
SiD, l*=3.5 m
Bz (T)
z (m)
SF1 QF1 DIPSD0 QD0
-0.03
-0.02
-0.01
0
0.01
0.02
0.03
0.04
0.05
0.06
-12 -10 -8 -6 -4 -2 0
ILD Solenoid
Anti-DID
ILD Solenoid+anti-DID
z (m)
SF1 QF1 DIPSD0 QD0
Bx (T)
SF1 QF1 DIPSD0 QD0
-0.03
-0.02
-0.01
0
0.01
0.02
0.03
0.04
0.05
0.06
-12 -10 -8 -6 -4 -2 0
SiD Solenoid
Anti-DID
SiD Solenoid+anti-DID
Bx (T)
z (m)
• Longitudinal field of the solenoid + Fringe field extending over QD0 -> coupling (x, y) (E,y) => beam size growth• Radial field due to crossing angle -> orbit deviation, implying synchrotron radiation,• Fringe field extending over QD0 -> no compensation of radial and longitudinal components, => non zero orbit at the IP
• Anti-DID field -> additional radial field deviating incoming particles.
R. Versteegen
Site Delivery prior the start of the Detector Assembly