Bb.g Vsp Pve Ed 00 Pm Man 001 Rev 0

download Bb.g Vsp Pve Ed 00 Pm Man 001 Rev 0

of 20

Transcript of Bb.g Vsp Pve Ed 00 Pm Man 001 Rev 0

  • 7/31/2019 Bb.g Vsp Pve Ed 00 Pm Man 001 Rev 0

    1/20

    BLOCK B - O MON PIPELINEOPERATING COMPANY

    PROJECT BLOCK B O MON GAS PIPELINE

    PHASE EPC

    ENGINEERING QUALITY MANUAL

    0 28/03/12 Issued For Approval

    Rev. Date Description PVEVSP

    ApprovalBPOC

    ApprovalCA

    Approval

    EPC CONTRACTOR(VSP-PVC-PTSC)

    Document number:BB.G-VSP-PVE-ED-00-PM-MAN-001

    Number of pages: 20 (including this page)

  • 7/31/2019 Bb.g Vsp Pve Ed 00 Pm Man 001 Rev 0

    2/20

    PROJECT BLOCK B O MON GAS PIPELINE

    PHASE EPC

    ENGINEERING QUALITY MANUAL

    0 28/03/12 Issued For ApprovalN.N.T.A Izaham JB IAJ

    Rev. Date Description

    Preparedby

    Checkedby

    EM PM DisciplineTeam

    LeaderSPMB

    Sub-Contractor EPC Contractor

    EPC CONTRACTOR(VSP-PVC-PTSC CONSORTIUM)

    PV ENGINEERING J.S.CDocument number:

    BB.G-VSP-PVE-ED-00-PM-MAN-001

  • 7/31/2019 Bb.g Vsp Pve Ed 00 Pm Man 001 Rev 0

    3/20

    BLOCK B O MON GAS PIPELINE PROJECTEPC PHASE- ENGINEERING QUALITY MANUAL

    BB.G-VSP-PVE-ED-00-PM-MAN-001 Rev. 0 Page 3/20

    FOREWARD

    PVE is dedicated to instilling an emphasis on quality. Our goal is to integrate

    quality into everything we do, and the PROJECT QUALITY MANUAL (PQM) for

    Block B O Mon Gas Pipeline Project provides the framework for ensuring the

    desired outcome for this project.

    The PVEs Project Quality Manual (PQM) Block B - OMon Gas Pipeline Project

    provides integrated quality plan for the Engineering design services including all

    identified outsource activities Block B O Mon Gas Pipeline Project. This manual

    has been designed (a) to meet the contract requirements, and (b) to be compliant

    to the ISO 9001:2008 international standard for Quality Management, Quality

    Assurance and Quality Systems.

    This PQM shall address the PVEs project approach to quality planning, quality

    control, quality assurance and quality improvement for all elements in the scope

    of work Block B - O Mon Gas Pipeline Project. PQM document describes the

    quality system and focus on what is required to achieve quality in the context of

    project requirements and ISO international standards for quality systems. In

    addition to these requirements, the Document also contains supplemental quality

    provisions established by PVE for the Project.

    This PQM describes the procedures and guidelines necessary for PVEs, PVEs

    Sub-Contractor, 3rd Party and other identified interfacing organizations to work

    together in a collaborative effort to implement for compliance with the Contract

    Documents. As detailed in the Contract Documents, PVE personnel will play a

    Key role in project execution and work in progressing for engineering.

    Documentation of weekly progress, monthly progress, sub-contractor and

    supplier to ensure the end deliverables quality meets and/or exceeds the

    expectations of the client.

  • 7/31/2019 Bb.g Vsp Pve Ed 00 Pm Man 001 Rev 0

    4/20

    BLOCK B O MON GAS PIPELINE PROJECTEPC PHASE- ENGINEERING QUALITY MANUAL

    BB.G-VSP-PVE-ED-00-PM-MAN-001 Rev. 0 Page 4/20

    PROJECT QUALITY POLICY

  • 7/31/2019 Bb.g Vsp Pve Ed 00 Pm Man 001 Rev 0

    5/20

    BLOCK B O MON GAS PIPELINE PROJECTEPC PHASE- ENGINEERING QUALITY MANUAL

    BB.G-VSP-PVE-ED-00-PM-MAN-001 Rev. 0 Page 5/20

    ISO 9001: 2008 CERTIFICATE

  • 7/31/2019 Bb.g Vsp Pve Ed 00 Pm Man 001 Rev 0

    6/20

    BLOCK B O MON GAS PIPELINE PROJECTEPC PHASE- ENGINEERING QUALITY MANUAL

    BB.G-VSP-PVE-ED-00-PM-MAN-001 Rev. 0 Page 6/20

    Approval

    Prepared By:______________________________

    Izaham Bin Abdul ManapEngineering QA/QC ManagerBlock B O Mon Gas Pipeline Project

    Date:_________

    Approved By:_______________________________

    Joseph BlockEngineering ManagerBlock B O Mon Gas Pipeline Project

    Date:__________

    Approved By:_______________________________

    Ian JenkinsProject ManagerBlock B - O Mon Gas Pipeline Project

    Date:__________

    Approved By:_______________________________

    Ng Ngc ThngProject DirectorPetrovietnam Consultancy And Engineering JSC

    Date:__________

  • 7/31/2019 Bb.g Vsp Pve Ed 00 Pm Man 001 Rev 0

    7/20

    BLOCK B O MON GAS PIPELINE PROJECTEPC PHASE- ENGINEERING QUALITY MANUAL

    BB.G-VSP-PVE-ED-00-PM-MAN-001 Rev. 0 Page 7/20

    TABLE OF CONTENTS

    1 PROJECT OVERVIEW ............................................................................... 92 GENERAL INFORMATION AND REQUIREMENTS ................................... 92.1 Language and Units of Measurement ......................................................... 92.2 Purpose of Document ............................................................................... 102.3 Definitions and Abbreviations .................................................................... 10

    2.3.1 Definitions ...................................................................................... 102.3.2 Abbreviations ................................................................................. 11

    2.4 Codes and Standards ............................................................................... 112.5 Reference Documents .............................................................................. 113 BLANK ...................................................................................................... 114 PROJECT QUALITY MANAGEMENT SYSTEM REQUIREMENTS ......... 114.1 General Requirements .............................................................................. 114.2 Documentation Requirements ................................................................... 125 MANAGEMENT RESPONSIBILITY .......................................................... 125.1 Management Commitment ........................................................................ 125.2 Client Focus .............................................................................................. 135.3 Quality Policy ............................................................................................ 135.4 Planning .................................................................................................... 135.5 Responsibility, Authority and Communication ........................................... 145.6 Project Management Review .................................................................... 14

  • 7/31/2019 Bb.g Vsp Pve Ed 00 Pm Man 001 Rev 0

    8/20

    BLOCK B O MON GAS PIPELINE PROJECTEPC PHASE- ENGINEERING QUALITY MANUAL

    BB.G-VSP-PVE-ED-00-PM-MAN-001 Rev. 0 Page 8/20

    6 RESOURCE MANAGEMENT ................................................................... 15

    6.1

    Provision of Resources ............................................................................. 15

    6.2 Human Resources .................................................................................... 156.3 Infrastructure and Work Environment ........................................................ 157 PRODUCT REALIZATION (PROJECT EXECUTION) .............................. 157.1 Planning of Product Realization ................................................................ 167.2 Client-Related Processes .......................................................................... 167.3 Design and Development .......................................................................... 177.4 Purchasing ................................................................................................ 197.5 Production and Service Operations ........................................................... 197.6 Control of Measuring and Monitoring Devices .......................................... 198 MEASUREMENT, ANALYSIS AND IMPROVEMENT ............................... 208.1 General ..................................................................................................... 208.2 Monitoring and Measurement ................................................................... 20

  • 7/31/2019 Bb.g Vsp Pve Ed 00 Pm Man 001 Rev 0

    9/20

    BLOCK B O MON GAS PIPELINE PROJECTEPC PHASE- ENGINEERING QUALITY MANUAL

    BB.G-VSP-PVE-ED-00-PM-MAN-001 Rev. 0 Page 9/20

    1. PROJECT OVERVIEW

    PetroVietnam Gas Corporation Block B - O Mon Pipeline Operating Company

    (BPOC) is responsible for the development of the Block B - O Mon Gas Pipeline.

    This project will be implemented to transport natural gas from a proposed Central

    Processing Platform (CPP) located in Block B fields to Ca Mau, O Mon and

    Neighboring Industrial Zones in provinces along the pipeline route.

    The Block B-O Mon Gas Pipeline Project includes the following facilities:

    Approximately 246.4km subsea pipeline with DN 700 (28)

    Mui Tram, Ca Mau Landfall station (LFS)

    Approximately 152.4km onshore pipeline with DN 750 (30) from Mui TramLFS to O Mon GDC

    Nine Line Block Valve Stations (LBV)

    A pipeline lateral section from LBV#2 to Ca Mau GDS: approximately

    400m DN 250 (10)

    Ca Mau Gas Distribution Station (GDS)

    A pipeline section from O Mon Gas Distribution Centre (GDC) to each O

    Mon Power PlantThe project investment objective is to contribute to the economic development in

    Southwest provinces and to secure gas/power supply in Vietnam.

    2. GENERAL INFORMATION AND REQUIREMENTS

    The role of the EPC Contractor for the Block B O Mon Gas Pipeline Project

    shall be undertaken by VSP-PVC-PTSC Consortium and VSP shall be the

    Leader of Consortium.

    PV Engineering J.S.C (SUB-CONTRACTOR) is the nominated Contractor to

    carry out the Detailed Design of Offshore and Onshore Pipelines and Stations.

    2.1 Language and Units of Measurement

    The content, references, attachments and any supplementary information for all

    engineering documents shall be in English unless specified otherwise. After the

    engineering package has been approved, Vietnamese translations of the

    approved engineering documents will be provided.

    Units of measurement for all engineering documents shall be in the System

    International (SI).

  • 7/31/2019 Bb.g Vsp Pve Ed 00 Pm Man 001 Rev 0

    10/20

    BLOCK B O MON GAS PIPELINE PROJECTEPC PHASE- ENGINEERING QUALITY MANUAL

    BB.G-VSP-PVE-ED-00-PM-MAN-001 Rev. 0 Page 10/20

    2.2 Purpose of Document

    This Project Quality Manual is applicable to all quality activities in Block B O Mon

    Gas Pipeline Project. The manual's objective is to enable to:

    Demonstrate PVEs ability to consistently provide product that meets client

    and applicable statutory and regulatory requirements.

    Address client satisfaction through the effective application of this

    Engineering Quality Manual, including processes for continual

    improvement of the system and assurance of conformity to client and

    applicable statutory and regulatory requirements.

    The requirements of this project quality manual are specifically intended andapplicable to be generic and are intended to be applicable to Block B-O Mon Gas

    Pipeline Project and meeting the requirements of ISO9001: 2008 Quality

    Management System Requirements. Any exclusion from ISO9001:2008 shall be

    clearly identified and recorded. However, allowable exclusions are limited to those

    requirements stated in Section 7.0 only, which will not affect PVEs ability or

    responsibility to provide a product that fulfils client and applicable regulatory

    requirements.

    2.3 Definitions and Abbreviations

    2.3.1 Definitions

    BPOC Block B - O Mon Pipeline Operating Company (Client)

    COMPANY As defined in the ITB

    DNV Det Norske Veritas (Certify Agent)

    EPC CONTRACTOR A consortium of Vietsovpetro (VSP), PetroVietnam

    Construction Joint Stock Corporation (PVC), PetroleumTechnical Services Corporation (PTSC). (VSP as thealliance leader)

    SPMB Service Project Management Board - a subsidiary ofVSP who will work full time on the project

    PVE PV Engineering J.S.C - An entity subcontracted byVSP to perform the detailed engineering design.

  • 7/31/2019 Bb.g Vsp Pve Ed 00 Pm Man 001 Rev 0

    11/20

    BLOCK B O MON GAS PIPELINE PROJECTEPC PHASE- ENGINEERING QUALITY MANUAL

    BB.G-VSP-PVE-ED-00-PM-MAN-001 Rev. 0 Page 11/20

    2.3.2 Abbreviations

    CPP Central Processing Platform

    MOM Minutes Of Meeting

    QA Quality Assurance

    QMS Quality Management System

    PQP Project Quality Plan

    2.4 Codes and Standards

    ISO 9001:2008 Quality Management System Requirements

    2.5 Reference Documents

    The EPC contract between COMPANY and EPC CONTRACTOR for execution of

    EPC project works

    3. BLANK

    This section is intentionally left blank in order to maintain alignment with ISO 9001:

    2008 Quality Management System Requirements Standard.

    4. PROJECT QUALITY MANAGEMENT SYSTEM REQUIREMENTS

    4.1 General Requirements

    A specific Project Quality Management System has been established which has

    addressed the requirements of Clause 4.1 in ISO9001:2008, which are:

    The Project Team has determined the processes needed for the quality

    management system and their application throughout the Project Block B -

    O Mon Gas Pipeline Project

    Determine the sequence and interaction in execution Project Block B O

    Mon Gas Pipeline Project

    The criteria and method has been identified to ensure the the

    effectiveness and control of the execution of Project Block B O Mon Gas

    Pipeline Project

    The PVE Project team has to ensure the availability of resources andinformation necessary to support the the execution and monitoring the

    execution of Project Block BO Mon Gas Pipeline Project

  • 7/31/2019 Bb.g Vsp Pve Ed 00 Pm Man 001 Rev 0

    12/20

    BLOCK B O MON GAS PIPELINE PROJECTEPC PHASE- ENGINEERING QUALITY MANUAL

    BB.G-VSP-PVE-ED-00-PM-MAN-001 Rev. 0 Page 12/20

    To ensure the project results are achieved, the Project Team will monitor,

    measure and analyse all process in execution of Project Block B O Mon

    Gas Pipeline Project and focus on the continual improvement of theseprocesses

    Implement actions necessary to achieve planned result and continual

    improvement of the processes

    Where PVE Project Team chooses to outsource any process that affects product

    conformity with requirements, PVE Project Team shall ensure control over such

    processes. The type and extent of control to be applied of those outsourced

    process shall be defined within the Project Execution Plan. Methods for control of

    such outsourced processes shall be documented (i.e. in purchasing documents,

    work instructions, and/or project procedures) by the outsourcing organization.

    4.2 Documentation Requirements

    For Block BO Mon Gas Pipeline Project, PVE Project Team has established 2

    quality documents which each one shall be able to address the requirements of

    each single eliment of ISO 9001:2008 under Clause 4.2:

    1) Engineering Quality Manual BB.G-VSP-PVE-ED-00-PM-MAN-001

    2) Engineering Documentations &

    Data Control Procedure

    BB.G-VSP-PVE-ED-00-PM-PRO-003

    5. MANAGEMENT RESPONSIBILITY

    5.1 Management Commitment

    The implementation of Block B O Mon Gas Pipeline Project Quality Management

    System and continually improving shall be effective by the below action:

    All client requirements as well as statutory and regulatory requirements

    shall be communicated to every personnel in the project.

    PVE Quality Policy shall be adhered as Block B O Mon Gas Pipeline

    Project Quality Policy.

    Specific Block B O Mon Gas Pipeline Project Quality Objective shall be

    developed to achieve the project objective.

    As specified in the Coordination Procedure, Internal monthly meetings shall

    be a platform to review the performance of the project by ProjectManagement Board of PVEs Block B O Mon Gas Pipeline Project Team.

  • 7/31/2019 Bb.g Vsp Pve Ed 00 Pm Man 001 Rev 0

    13/20

    BLOCK B O MON GAS PIPELINE PROJECTEPC PHASE- ENGINEERING QUALITY MANUAL

    BB.G-VSP-PVE-ED-00-PM-MAN-001 Rev. 0 Page 13/20

    Planning and Progress report shall be a tool to ensure the resource is

    available for this project.

    5.2 Client Focus

    PVE Project Management shall ensure that client needs and expectations are

    determined, converted into requirements and fulfilled with the aim of achieving

    client expectation. When determining client needs and expectations, statutory

    and regulatory requirements will also be considered and taken into account. This

    is addressed in BB.G-VSP-PVE-ED-00-PM-PLN-001-Execution Plan of Detailed

    Enggineering Design for Onshore pipelines, Offshore pipelines and Stations.

    5.3 Quality Policy

    PVE management shall ensure that the quality policy:

    Is appropriate for the purpose of the project execution.

    Includes a commitment to comply with requirements and to continually

    improve the effectiveness of the quality management system.

    Provides a framework for establishing and reviewing quality objectives.

    Is communicated and understood within the project team.

    Is reviewed for continuing suitability.

    5.4 Planning

    a) Quality Objectives

    The PVE Project Management Team has established the project specific quality

    objective for this project and it has been laid in BB.G-VSP-PVE-ED-00-PM-PLN-

    001-Execution Plan of Detailed Engineering Design For Onshore Pipeline,

    Offshore Pipeline and Stations. The Project objectives are measurable andconsistent with the project quality policy.

    b) Quality Management System Planning

    Description on the execution of this project has been laid out in the BB.G-VSP-

    PVE-ED-00-PM-PLN-001-Execution Plan of Detailed Engineering Design For

    Onshore Pipeline, Offshore Pipeline and Stations which is complies with ISO

    9001:2008 requirements with the intent to ensure all project requirements and

    quality objectives are met.

    Any changes in Project Execution, which will give impact on the project quality

    system will be handle as accordance with BB.G-VSP-PVE-ED-00-PM-PLN-001-

  • 7/31/2019 Bb.g Vsp Pve Ed 00 Pm Man 001 Rev 0

    14/20

    BLOCK B O MON GAS PIPELINE PROJECTEPC PHASE- ENGINEERING QUALITY MANUAL

    BB.G-VSP-PVE-ED-00-PM-MAN-001 Rev. 0 Page 14/20

    Execution Plan of Detailed Engineering Design for Onshore Pipeline, Offshore

    Pipeline and Stations to ensure the integrity of the project quality management

    system is maintained.

    5.5 Responsibility, Authority and Communication

    Personnel selected to undertake work on this project shall be chosen on the basis

    that they have gained adequate experience and meet clients requirements. The

    Project Manager shall ensure these requirements are met. The organization chart

    and project specific responsibility and authority for this project are laid in BB.G-

    VSP-PVE-ED-00-PM-PLN-001-Execution Plan of Detailed Engineering Design For

    Onshore Pipeline, Offshore Pipeline and Stations.As part of management commitment, The Project Quality Manager has a sole

    responsibility in the implementation of the Project Quality Management System

    and is responsible as Project Quality Representative.

    As part of ISO 9001:2008- Quality Management System Requirements, the

    method and procedure for internal communication has been laid in BB.G-VSP-

    PVE-ED-00-PM-PRO-001-Engineering Coordination Procedure for Onshore

    Pipeline, Offshore Pipeline and Stations.

    5.6 Project Management Review

    In ensuring all the performance of Quality Management System implemented in

    this project is being monitored, the PVE Project Management Team will conduct a

    Monthly Management Review Meeting during Monthly Internal Meeting as part of

    Project Internal Monthly agenda during the meeting.

    a) Review Input

    Inputs to management review include current performance and improvement

    opportunities related to the following:

    Results of audits i.e. Internal and External audits.

    Client feedback.

    Process performance and product conformance.

    Status of preventive and corrective actions.

    Follow-up actions from previous management reviews.

    Planned changes that could affect the quality management system.

    Recommendations for improvement.

  • 7/31/2019 Bb.g Vsp Pve Ed 00 Pm Man 001 Rev 0

    15/20

    BLOCK B O MON GAS PIPELINE PROJECTEPC PHASE- ENGINEERING QUALITY MANUAL

    BB.G-VSP-PVE-ED-00-PM-MAN-001 Rev. 0 Page 15/20

    6. RESOURCE MANAGEMENT

    6.1 Provision of Resources

    For the purpose and the execution of this project, PVE has identified and

    nominated all qualified personnel to be involved in this project. Each nominated

    person is competent in their own field and has met the clients requirement. The

    Organization Chart of this project is laid in BB.G-VSP-PVE-ED-00-PM-PLN-001-

    Execution Plan of Detailed Engineering Design For Onshore Pipeline, Offshore

    Pipeline and Stations.

    6.2 Human Resources

    PVEs has committed to ensure that all personnel performing work affecting

    conformity to design requirements shall be competent on the basis of appropriate

    education, training, skills and experience. This has been materialized in the List of

    proposed personnel nominated in PVEs Tender document for Block B O Mon

    Gas Pipeline Project Team. Each personnel has been given their specific job

    description which are laid in BB.G-VSP-PVE-ED-00-PM-PLN-001-Execution Plan

    of Detailed Engineering Design For Onshore Pipeline, Offshore Pipeline and

    Stations.

    In the event of any personnel in the Block B O Mon Gas Pipeline Project being

    identified to attend any special training due to project need, PVE Coorporate

    Procedure shall be complied with. Reference:PVE-P6.2-2: Training Procedure.

    6.3 Infrastructure and Work Environment

    PVEs management will determine, provide and maintain the entire infrastructure

    and work environment required to achieve conformity to product requirements.

    These have been done during acception and clarification tender Block B O Mon

    Gas Pipeline Project.

    7. PRODUCT REALIZATION (PROJECT EXECUTION)

    PVEs principal method of product realization is through the execution of discrete

    projects associated with one or more client contracts or agreements. Processes

    required for effective project execution can be divided into 2 :

    i. Supporting processes. Supporting processes, such as quality, human

    resources, operations management, IT, etc. typically provide input to or

    receive output from the projects.

  • 7/31/2019 Bb.g Vsp Pve Ed 00 Pm Man 001 Rev 0

    16/20

    BLOCK B O MON GAS PIPELINE PROJECTEPC PHASE- ENGINEERING QUALITY MANUAL

    BB.G-VSP-PVE-ED-00-PM-MAN-001 Rev. 0 Page 16/20

    ii. Project specific processes typically are those used for management, control,

    development and/or production of product defined by the projects scope.

    Effective project execution requires that appropriate supporting and project specific

    processes be developed, planned, managed, and controlled.

    7.1 Planning of Product Realization

    The Planning to achieve the project objective for Block B O Mon Gas Pipeline

    Project has been detailed out in BB.G-VSP-PVE-ED-00-PM-PLN-001-Execution

    Plan of Detailed Engineering Design For Onshore Pipeline, Offshore Pipeline and

    Stations. This document has addressed all sequence of processes and sub-

    processes, organization executing and project plan. All project specific proceduresare consistent with the ISO 9001:2008 Quality Management System requirements,

    client and regulatory requirements. In order to achieve the requirement under the

    clause 7.1, PVE Team has performed the below actions:

    Establish processes, documents and provide resources specific to the

    design requirements.

    Identified all verification, validation and monitoring activities specific to the

    design process and the criteria for design acceptance.

    Identified records needed to provide evidence that the project execution

    processes and resulting product meet requirements.

    7.2 Client-Related Processes

    Project Manager and Engineering Manager are the mainly responsible for

    ensuring the success of these capital activities, being supported by the Project

    Coordinator and Project Quality Manager. Any changes to the Contract have to

    be approved by the Project Director and documented.

    Prior to final contract acceptance, the contract must be reviewed in detail by the

    management to ensure its entire compliance with the bid content and all specific

    requirements are to be identified.

    The main goal of the activity is to ensure PVE will be able to meet specified

    Contract requirements in time; including screening all technical and commercial

    aspects to ensure feasibility and constructability of its engineering services at the

    calculated cost and specified level of quality and avoid extra costs and delay in

    the progress of the work. Consequently, all the Inputs and the outputs of each

    process have to be very well identified. Reviewers shall consider previous similar

  • 7/31/2019 Bb.g Vsp Pve Ed 00 Pm Man 001 Rev 0

    17/20

    BLOCK B O MON GAS PIPELINE PROJECTEPC PHASE- ENGINEERING QUALITY MANUAL

    BB.G-VSP-PVE-ED-00-PM-MAN-001 Rev. 0 Page 17/20

    experience to determine what was good / strong and what has been problematic,

    where the project loss time and money.

    The reviewers shall ensure full compliance to the bid and financial

    consequences, schedule and all technical implications and specificities.

    Identification of special needs for human resources shall also be taken into

    account.

    Any changes to the Contract must be covered by a documented request. The

    implementation of all the above has been documented in PVE-P7.2-2:Contract

    Execution Procedure.

    All customer communication and any activities related to the communication has

    been detail out in BB.G-VSP-PVE-ED-00-PM-PRO-001-EngineeringCoordination Procedure.

    7.3 Design and Development

    a) Design and Development Planning

    PVEs PMT Block B O Mon Gas Pipeline Project shall carefully plan and control

    all design activities. The plan shall determine:

    Stages of design and/or development processes

    Review, verification and validation activities appropriate to each design

    development stage.

    Responsibilities and authorities for design development activities

    Interfaces between different groups involved in design development shall be

    managed to ensure effective communication and clear assignment of

    responsibility.

    Planning output shall be updated, as appropriate, as the design and/or

    development progresses.

    b) Design and Development Inputs

    All design inputs shall be determined and record of the design input requirement

    shall be maintained. These include:

    Functional and performance requirements.

    Applicable statutory and regulatory requirements.

    Where applicable, information derived from previous similar designs. Other requirements essential for design and/or development.

  • 7/31/2019 Bb.g Vsp Pve Ed 00 Pm Man 001 Rev 0

    18/20

    BLOCK B O MON GAS PIPELINE PROJECTEPC PHASE- ENGINEERING QUALITY MANUAL

    BB.G-VSP-PVE-ED-00-PM-MAN-001 Rev. 0 Page 18/20

    These inputs are reviewed for adequacy. Incomplete, ambiguous or conflicting

    requirements shall be resolved.

    c) Design and Development Outputs.

    The outputs of the design development process shall be provided to client in such

    a way that will meet the requirement of the client.

    PVEs PMT Block B O Mon Gas Pipeline Project shall ensure that design output:

    Meet the input requirements for design and development.

    Provides appropriate information for purchasing, production and service

    operations and meeting permitting documentation.

    Contains or references product acceptance criteria.

    Specifies the characteristics of the product that are essential for its safe

    and proper use.

    All design outputs shall be approved prior release to client.

    d) Design and Development Review.

    PVE has identifies a systematic process for review of design and development in

    accordance with planned arrangements. Competent personnel shall conduct thereview as per scheduled interval. The review shall:

    Evaluate the ability of design and/or development to fulfill requirements.

    Identify any problems and propose necessary actions.

    Participants in such reviews include representatives of functions concerned with

    the design development stage(s) being reviewed. Records of the results of the

    reviews and subsequent follow-up actions are maintained.

    e) Design and Development Verification.Design development verification shall be performed to ensure design outputs have

    satisfied the design development input requirements. Records of the results of the

    verification and subsequent follow-up actions are retained.

    f) Design and Development Validation

    If the contract requires, design validation shall be performed in accordance with

    planned arrangements to ensure that the resulting product is capable of meeting

    the requirements for the specified use or application. Wherever practicable,

    validation shall be completed before the delivery or implementation of the product.

  • 7/31/2019 Bb.g Vsp Pve Ed 00 Pm Man 001 Rev 0

    19/20

    BLOCK B O MON GAS PIPELINE PROJECTEPC PHASE- ENGINEERING QUALITY MANUAL

    BB.G-VSP-PVE-ED-00-PM-MAN-001 Rev. 0 Page 19/20

    Records of the results of the validation and subsequent follow-up actions are

    maintained.

    g) Control of Design and/or Development Changes

    Design changes are identified as it develops. All changes shall be recorded and

    records maintained. The changes are reviewed, verified and validated, as

    appropriate, and approved before implementation. The review shall include but not

    only limited to the evaluation of the effected area by the changes. Records of the

    change review and subsequent follow-up actions shall be made and maintained.

    All the above activities are being identified and controlled through project Specific

    Procedures for Block B - O Mon Gas Pipeline Project, namely:

    BB.G-VSP-PVE-ED-00-PM-PRO-001 Engineering Coordination Procedure

    BB.G-VSP-PVE-ED-00-PM-PRO-002 Engineering Progress ControlProcedure

    BB.G-VSP-PVE-ED-00-PM-PRO-003 Engineering Documentations & DataControl Procedure

    BB.G-VSP-PVE-ED-00-PM-PRO-006 Engineering Design ChangeProcedure

    BB.G-VSP-PVE-ED-00-PM-PRO-007 Technical Query Procedure

    7.4 Purchasing

    Not applicable. This clause is not part of scope of work for this project.

    7.5 Production and Service Operations

    Not Applicable This section applies specifically to organization performing,

    supervising or managing installation, construction, manufacturing, and operations

    and/or maintenance activities. Currently, these activities are excluded in

    Engineering Scope of Work for Block B O Mon Gas Pipeline Project.

    7.6 Control of Measuring and Monitoring Devices

    Not Applicable - This section applies specifically to all operations and support

    functions using measuring and monitoring devices to assure conformity of product

    to specified requirements. Currently, this activity is excluded from PVEs normal

    activity and Engineering Scope of Work for Block B O Mon Gas Pipeline Project.

  • 7/31/2019 Bb.g Vsp Pve Ed 00 Pm Man 001 Rev 0

    20/20

    BLOCK B O MON GAS PIPELINE PROJECTEPC PHASE- ENGINEERING QUALITY MANUAL

    8. MEASUREMENT, ANALYSIS AND IMPROVEMENT

    8.1 GeneralPVEs Block B O Mon Gas Pipeline Project PMT has established the project

    specific procedures with the intent to:

    Demonstrate conformity of the product requirements

    Ensure conformity with the quality management system

    Continually improve the effectiveness of the quality management system

    This shall include determination of applicable methods and the extent of their use

    Reference Project specific procedures to address these intents are

    8.2 Monitoring and Measurement

    The below procedures have been developed to address all ISO 9001:2008

    requirement under Clause 8.2.

    1 BB.G-VSP-PVE-ED-00-PM-PLN-001 Execution Plan of detailedengineering design for Onshorepipeline, Offshore pipeline andStations

    2 BB.G-VSP-PVE-ED-00-PM-SCH-001 Engineering Master Schedule

    3 BB.G-VSP-PVE-ED-00-PM-PRO-002 Engineering Progress ControlProcedure

    4 BB.G-VSP-PVE-ED-00-PM-PRO-004 Procedure for controlling non-conformity product, corrective andpreventive actions

    5 BB.G-VSP-PVE-ED-00-PM-PRO-005 Project Quality Audit & ManagementControl Procedure