Baucau Cement Project - La'o Hamutuk
Transcript of Baucau Cement Project - La'o Hamutuk
TL CEMENT, LDA
Baucau Cement Project Cement Plant, Jetty and Other Associated Infrastructure Environmental Management Plan
Document No. 301012-02135-EMP-003
02 February 17
Venture Hotel - Rua Filomena De Camara Bidau Lecidere PO Box 7 Dili Timor Leste Telephone: +670 331 3238 & 331 3238 Facsimile: +670 772 8144 www.worleyparsons.com LPA 22548/MTCI/V/2011 © Copyright 2016 WorleyParsons (TL) LDA
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Disclaimer
This report has been prepared on behalf of and for the exclusive use of TL Cement, LDA, and is subject to and issued in accordance with the agreement between TL Cement, LDA and WorleyParsons. WorleyParsons accepts no liability or responsibility whatsoever for it in respect of any use of or reliance upon this report by any third party.
Copying this report without the permission of TL Cement, LDA and WorleyParsons is not permitted.
PROJECT 301012-02135 - BAUCAU CEMENT PROJECT
REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVAL
DATE CLIENT APPROVAL
DATE
1 Final Rev 1
A Jacobs A Mratovich D Hunter
2 Feb 2017
J Rhee
2 Feb 2017
Document No : 301012-02135-EMP-003 Page ii
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
CONTENTS A EXECUTIVE SUMMARY ................................................................................................. 10
1.1 Summary of key impact, responsibility and mitigation cost ............................................. 13
B INTRODUCTION .............................................................................................................. 19
1.2 Environmental Management Framework ......................................................................... 19
1.3 Environmental Management Plan .................................................................................... 19
1 PROJECT DESCRIPTION ............................................................................................... 20
1.1 Project Identification ......................................................................................................... 20
2 DETAILS OF PROJECT PROPONENT .......................................................................... 21
2.1 Project Environmental Impact Statement ......................................................................... 21
3 DETAILS OF EMP CONSULTANTS ............................................................................... 23
3.1.1 Local presence .................................................................................................... 23
4 DESCRIPTION OF THE PROJECT ................................................................................ 30
4.1.1 Project component equipment and technology ................................................... 30
4.1.2 Pre Construction .................................................................................................. 32
4.1.3 Construction ........................................................................................................ 34
4.1.4 Operation ............................................................................................................. 37
4.1.5 Decommissioning ................................................................................................ 41
4.2 Project Location ............................................................................................................... 43
4.2.1 Nature of the project location .............................................................................. 43
4.2.2 EMP Endorsement .............................................................................................. 44
5 LEGAL REQUIREMENTS................................................................................................ 47
5.1 Legislation and legal framework ...................................................................................... 47
5.1.1 Environmental Legislation ................................................................................... 47
5.1.2 Biodiversity and protected areas legislation ........................................................ 48
5.1.3 Land legislation ................................................................................................... 49
5.1.4 Agriculture and Fishing legislation ...................................................................... 49
Page iii 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
5.1.5 Ports Legislation .................................................................................................. 50
5.1.6 Labor legislation .................................................................................................. 50
5.2 Obligations ....................................................................................................................... 51
5.3 Summary of Project Approvals ........................................................................................ 51
5.4 Summary of Environmental Standards ............................................................................ 52
6 INSTITUTIONAL ROLES AND RESPONSIBILITIES ...................................................... 53
7 SUMMARY OF IMPACTS ................................................................................................ 58
8 DESCRIPTION OF PROPOSED MITIGATION MEASURES.......................................... 70
8.1 Climate ............................................................................................................................. 70
8.2 Topography, Geology and Soils ....................................................................................... 71
8.3 Air Quality (including dust) ............................................................................................... 72
8.4 Noise and vibration .......................................................................................................... 73
8.5 Surface Water .................................................................................................................. 73
8.6 Groundwater .................................................................................................................... 74
8.7 Coastal and Marine .......................................................................................................... 75
8.8 Flora ................................................................................................................................. 76
8.9 Fauna ............................................................................................................................... 77
8.10 Marine Fauna incl. Fisheries ....................................................................................... 78
8.11 Marine habitats (including Coral) ................................................................................. 79
8.12 Traffic ........................................................................................................................... 80
8.13 Infrastructure ................................................................................................................ 80
8.14 Employment ................................................................................................................. 81
8.15 Economic Use of Forestry and other Natural Resources ............................................ 82
8.16 Fishing ......................................................................................................................... 83
8.17 Socio Economic Agriculture ......................................................................................... 84
8.18 Population and Community ......................................................................................... 84
8.19 Community Health ....................................................................................................... 85
8.20 Institutions, Schools and Health Facilities ................................................................... 86
Page iv 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
8.21 Community and Family Structure ................................................................................ 86
8.22 Land Ownership and Land Rights ............................................................................... 87
8.23 Natural Resources Rights ............................................................................................ 87
8.24 Cultural Heritage, Archaeological and Sacred Sites ................................................... 88
8.25 Summary of Impacts and Mitigation Measures ........................................................... 88
9 GOVERNING PARAMETERS ....................................................................................... 199
9.1 Environmental Quality Standards .................................................................................. 199
9.2 International Best Practice ............................................................................................. 199
9.3 Governing parameters ................................................................................................... 199
9.3.1 Emissions .......................................................................................................... 199
9.3.2 Ambient Water Quality Standards ..................................................................... 199
9.3.3 Ambient Air Quality Standards .......................................................................... 201
9.3.4 Soil..................................................................................................................... 201
9.3.5 Occupational Health and Safety Standards ...................................................... 203
9.4 Modelling or Engineering Calculations ........................................................................... 205
10 MONITORING PROGRAM ............................................................................................ 206
10.1 Climate ....................................................................................................................... 206
10.2 Topography and Soil ................................................................................................. 207
10.3 Air Quality .................................................................................................................. 207
10.4 Noise and vibration .................................................................................................... 208
10.5 Surface water ............................................................................................................. 208
10.6 Groundwater .............................................................................................................. 209
10.7 Coastal and Marine ................................................................................................... 209
10.8 Flora ........................................................................................................................... 210
10.9 Fauna ......................................................................................................................... 210
10.10 Marine Fauna and Fisheries ...................................................................................... 210
10.11 Marine habitats and corals ........................................................................................ 211
10.12 Traffic ......................................................................................................................... 211
Page v 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
10.13 Infrastructure .............................................................................................................. 212
10.14 Employment ............................................................................................................... 212
10.15 Economic Use of Forestry and other Natural Resources .......................................... 212
10.16 Fishing ....................................................................................................................... 213
10.17 Socio-Economic Agriculture ...................................................................................... 213
10.18 Population and community ........................................................................................ 213
10.19 Community Health ..................................................................................................... 213
10.20 Institutions schools and health facilities .................................................................... 215
10.21 Community and Family Structure .............................................................................. 215
10.22 Land Ownership and Land Rights ............................................................................. 215
10.23 Natural Resources Rights .......................................................................................... 215
10.24 Cultural Heritage Archeological and Sacred Sites .................................................... 216
10.25 Summary of monitoring program ............................................................................... 217
11 REPORTING REQUIREMENTS .................................................................................... 222
12 RESPONSIBILITIES FOR MITIGATION AND MONITORING ...................................... 230
13 EMERGENCY PLAN ...................................................................................................... 236
13.1 Purpose ..................................................................................................................... 236
13.2 Objective .................................................................................................................... 236
13.3 Responsibilities .......................................................................................................... 236
13.4 Standards .................................................................................................................. 237
13.5 Incident Classification ................................................................................................ 237
13.6 Prevention .................................................................................................................. 238
13.7 Safety Data Sheets (SDS) ......................................................................................... 239
13.8 Spill Response ........................................................................................................... 240
13.8.1 Control ............................................................................................................... 240
13.8.2 Contain .............................................................................................................. 240
13.8.3 Clean Up ........................................................................................................... 240
13.9 Equipment .................................................................................................................. 241
Page vi 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
13.9.1 Spill Response .................................................................................................. 241
13.9.2 Marine Spill Response ...................................................................................... 241
13.9.3 First Aid Facilities and Personal Protective Equipment (PPE) .......................... 242
13.9.4 Fire Fighting Equipment .................................................................................... 242
13.10 Training ...................................................................................................................... 242
14 DECOMMISSIONING PLAN .......................................................................................... 243
14.1 Objectives .................................................................................................................. 243
14.2 Preliminary Decommissioning Plan ........................................................................... 243
15 CAPACITY DEVELOPMENT AND TRAINING .............................................................. 250
16 PUBLIC CONSULTATION AND INFORMATION DISCLOSURE ................................. 251
16.1 Purpose of the consultation during the preparation of the EMP ................................ 251
16.2 Methodology and Approach ....................................................................................... 251
16.2.1 Identified Stakeholders ...................................................................................... 251
16.2.2 Mechanism for Public Consultation ................................................................... 254
16.3 Summary of consultation activities carried out .......................................................... 254
16.4 Summary of main comments received from the public, community leaders, NGOs, local officials, other stakeholders ........................................................................................................... 258
16.5 Identify how those comments were taken into account ............................................. 262
16.6 Details of public participation activities ...................................................................... 262
16.7 Summarize the public acceptance or opinions on the proposed Project .................. 262
16.8 Related materials or activities .................................................................................... 263
16.9 Recommendations for future consultations ............................................................... 264
17 COMPLAINTS AND GRIEVANCES MECHANISM ....................................................... 265
18 WORK PLAN AND IMPLEMENTATION SCHEDULE ................................................... 268
19 COST ESTIMATES ........................................................................................................ 274
20 REVIEW OF THE EMP .................................................................................................. 283
21 NON-TECHNICAL SUMMARY ...................................................................................... 285
21.1 Introduction ................................................................................................................ 285
Page vii 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
21.2 Purpose of this document .......................................................................................... 285
21.3 Benefits of the project ................................................................................................ 285
21.4 Key Project Characteristics ....................................................................................... 287
21.5 Operations ................................................................................................................. 288
21.6 Project Phases........................................................................................................... 290
21.7 Key Potential Impacts and Mitigation Measures ....................................................... 294
21.8 Stakeholder Engagement Process ............................................................................ 300
22 REFERENCES ............................................................................................................... 303
23 ACRONYMS / ABBREVIATIONS .................................................................................. 307
Table of Figures
Figure 4-1 Cement Plant, Conveyor and Jetty for export – Flow diagram ........................................... 31
Figure 4-2 Conceptual view of the cement plant with components ...................................................... 32
Figure 4-3 Example of excavator to be used to clear vegetation during pre-construction ................... 33
Figure 4-4 Example of construction camp accommodation for workers .............................................. 34
Figure 4-5 Example of excavator loading a dump truck ....................................................................... 35
Figure 4-6 Example of jetty during construction (photo: marineandcivil.com) ..................................... 36
Figure 4-7 Example of a Material Offloading Facility (MOF) during construction (Photo: Inpex) ......... 37
Figure 4-8 Example of Cement Plant showing bituminsed surface for mitigation of dust .................... 38
Figure 4-9 Example of Conveyor showing covered conveyor for mitigation of dust ............................ 38
Figure 4-10 Example of power infrastructure showing housing for mitigation of noise ........................ 39
Figure 4-11 Example of crusher in the plant with mitigation (cover for dust) ....................................... 39
Figure 4-12 Example of crusher in plant (inside) – mitigation measure cover for dust ........................ 40
Figure 4-13 Example of raw mill grinding (Cement plant) – mitigation measure safety barriers ......... 40
Figure 4-14 Example of kiln area and heater tower ............................................................................. 41
Figure 4-15 Examples of Jetty infrastructure ........................................................................................ 41
Figure 4-16 Example of decommissioning process (implosion of a power station) (Photo: sandiegouniontribune.com) .................................................................................................................. 42
Page viii 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Figure 4-17 Example of revegetation process (Image : Google Images) ............................................ 42
Figure 18: Location of Cement Plant, Jetty and Conveyor Belt ........................................................... 43
Figure 19: Grievance resolution framework ....................................................................................... 267
Figure 20: Location of Baucau Cement Project components ............................................................. 286
Figure 21: Portland cement clinker ..................................................................................................... 287
Figure 22: Ordinary Portland cement ................................................................................................. 287
Figure 23: The Baucau Cement Plant Project once in operation ....................................................... 289
Figure 24: Stakeholder Engagement and Consultation ..................................................................... 300
Page ix 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
A EXECUTIVE SUMMARY
An Environmental Management Framework (EMF) sets the structure for managing environmental risks and impacts during the Project life cycle. The EMF for the TL Cement Project includes the following key approaches:
a. Select the Project option which has the lowest possible environmental footprint; b. Reduce the environmental impact, as far as possible, through engineering and design approaches; c. Mitigate environmental impact, as far as possible, through engineering and design approaches; d. Manage the direct impacts and the risk of ongoing impact through management measures and monitoring; and e. Continuously improve the environmental management and monitoring measures through the Project life cycle.
Two Environmental Management Plans (EMPs) were created for the TL Cement Project. One EMP addresses impacts associated with the limestone mine site and the other addresses impacts associated with the cement plant, jetty and other associated infrastructure. EMPs for the TL Cement Project address:
1. Environmental impacts which are identified as ‘Medium’ or greater in EIS document; 2. Mitigation measures for all aspects which are required in accordance with industry best practice; 3. Monitoring measures and standards to be followed; 4. Trigger values or target values of measurement criteria; 5. Reporting requirements; and 6. Continuous improvement process.
Key impacts
Of all the aspects associated with the Project, key aspects are those with impacts identified in the EIS as being ‘Medium’ or ‘High’ risk. These risks have been addressed through the Environmental Management Plans (EMPs).
1. Displacement / Resettlement: Local people will be displaced and will require relocation in order for this Project land to be acquired. This can cause a ‘High’ level of impact on local people. Mitigation measures including resettlement and ongoing stakeholder consultation to be undertaken by the Government of Timor-Leste will most likely result in a residual impact of ‘Medium’.
2. Cultural Heritage: Impacts of the mine on Cultural Heritage for the local area is significant with a number of sacred heritage sites directly impacted by clearing and activities within the Project footprint. Local area sites will be permanently impacted causing a ‘High’ impact, however with the implementation of controlled relocation and removal of unavoidable impacted sites, the residual impacts are ‘Medium’.
3. Traffic: An increase in heavy vehicle numbers and movements is likely to cause damage to the condition of the local road network and also poses a ‘Medium’ safety risk for the local road users and
Page 10 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
pedestrians. Mitigation measures including speed limits and road improvements reduces this risk to 'Low' which is an acceptable level.
4. Noise: In accordance with the equations provided in AS 2436-2010 (AS 2436, 2010) the predicted noise levels from a single 85dB at 1m emission source, is 45dB 100m away from the source. This falls below the noise standard of 55 dB (A) (UNTAET, 2001). This represents a ‘Medium’ level of impact. The residual impact from noise and vibration is ‘Medium’.
Monitoring
The monitoring requirements for the project have been developed to consider all the project phases, Pre-construction, construction, operation and decommissioning. Key monitoring requirements are as follows :
1. Air quality monitoring at key receptors in the neighbouring settlements 2. Noise and vibration monitoring at the Plant and Mine site and sensitive receptors at the neighbouring settlements 3. Water quality and quantity monitoring at rivers and groundwater sources including springs adjacent to the mine and plant site 4. Recording of flora and fauna information during land clearing activities and ongoing throughout the project life 5. Ongoing stakeholder and community consultation throughout the project life
Emergency Response Plan
The Emergency Plan (EP) outlines the approach for managing the handling, storage and leak / spillage of dangerous chemicals and hazardous wastes associated with the development and operation of the Baucau Cement Plant Project.
The following will be adopted by the Project to prevent spillages and leaks from occurring:
• No tanks are to be filled prior to checking available tank volume; • Tank filling and dispensing procedures shall be carried out only by appropriately trained personnel and within designated and bunded area; • The main outlet valve on tanks will be locked shut when unattended; • Each tank/storage facility will be gauged and monitored daily; • All chemical and hazardous materials are contained in bunded areas with an appropriate holding capacity; • Bunded compound shall be lined with low permeability (less than 10 - 9 m/s) material that is not adversely affected by contact with the stored chemicals. It should be constructed in such a way that permits full recovery of contents spilt from tanks and ensures that the lining material is not damaged. The bund itself should be constructed of waterproof membrane, reinforced concrete or an approved equivalent; • The bunded compound shall have a minimum capacity of 110% of the capacity of the largest tank. The compound shall also have sufficient capacity to retain spilt chemicals and not be affected during extreme rainfall events; and
Page 11 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
• All marine-based spills and emergencies are to be managed in accordance with Regulation 37 Annex 1 of the International Convention for the Prevention of Pollution from Ships 1973. This regulation deals with the management of accidental discharge and discharge of ballast to sea.
Training
Training is essential for ensuring that the provisions of the EMPs are implemented efficiently and effectively. Training needs will be identified based on the existing and available capacity of the site and Project personnel (including the proponent, contractors and subcontractors) to undertake the required management actions and monitoring activities.
EMP review
The EMP will be reviewed at the following key project milestones:
• Completion of the pre-construction phase and additional specialist studies; • Completion of the construction phase; • Award of the Operations contract to incorporate operator-specific information; • Every 5 years at minimum during Operations phase.; and • On finalization of the Closure Plan.
Page 12 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
1.1 Summary of key impact, responsibility and mitigation cost
Stage Activity Potential Key Impact
Mitigation Measure Responsibility Monitoring Measure Frequency of monitoring
Cost of Mitigation Measure USD
Pre Construction
Vehicles movement
Equipment operating
Clearing of vegetation
Limit area to be cleared TL Cement Construction contractor
Check that clearing is within the boundary
Weekly reconciliation
Compensation per the Resettlement Plan : $15,000 estimate
Monitoring and weed eradication costs: $5.6M
Fauna relocation and monitoring, re-introduction and elimination of pests: $670k
Rehabilitation costs (Labour and materials): $?
Vehicles movement
Equipment operating
Air quality and dust
Dust suppression techniques include water spraying and enclosing equipment
TL Cement Construction contractor
PM10 and PM2.5
3 monitoring stations
Measurements every 6 months
Compensation per the Resettlement Plan : $15,000 estimate
Dust suppression sprayer and labour: $? 2000/month
Cost of illness and loss of productivity: $?
Page 13 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Stage Activity Potential Key Impact
Mitigation Measure Responsibility Monitoring Measure Frequency of monitoring
Cost of Mitigation Measure USD
Vehicles movement
Equipment operating
Generating electricity
Noise Noise limitation techniques include aprons and enclosing equipment
TL Cement Construction contractor
Noise Levels
3 monitoring stations
Measurements every 6 months
Compensation per the Resettlement Plan : $15,000 estimate
Monitoring costs: $580k
Cost of illness and loss of productivity: $?
Vehicles movement
Equipment operating
Water quality and quantity
Rehabilitation in the event of a spill or contamination event
Spill and contamination mitigation measures
TL Cement Construction contractor
Every 6 months
Flow meters / stream gauges at the Bucoli River (1.6km west) and at Uaimatabai, Uaisa and Waino springs.
Monthly water quality and quantity measurements at monitoring boreholes, key spring receptors at Waiono, Uaimatabai and Uaisa.
Water Quality Monitoring costs: $1,4M
Water Quantity Monitoring costs : $970k
Rehabilitation costs in the event of a spill: $?
Construction
Vehicles movement
Equipment
Air quality and dust
Dust suppression techniques include water spraying and enclosing
TL Cement Construction contractor
PM10 and PM2.5
3 monitoring stations
Measurements every 6 months
Dust suppression sprayer and labour: $? 2000/month
Cost of illness and loss of productivity: $?
Page 14 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Stage Activity Potential Key Impact
Mitigation Measure Responsibility Monitoring Measure Frequency of monitoring
Cost of Mitigation Measure USD
operating
Generating electricity
equipment
Vehicles movement
Equipment operating
Generating electricity
Noise Noise limitation techniques include aprons and enclosing equipment
TL Cement Construction contractor
Noise Levels
3 monitoring stations
Measurements every 6 months
Monitoring costs: $580k
Cost of illness and loss of productivity: $?
Vehicles movement
Equipment operating
Water quality and quantity
Rehabilitation in the event of a spill or contamination event
Spill and contamination mitigation measures
TL Cement Construction contractor
Every 6 months
Flow meters / stream gauges at the Bucoli River (1.6km west) and at Uaimatabai, Uaisa and Waino springs.
Monthly water quality and quantity measurements at monitoring boreholes, key spring receptors at Waiono, Uaimatabai and Uaisa.
Water Quality Monitoring costs: $1,4M
Water Quantity Monitoring costs : $970k
Rehabilitation costs in the event of a spill: $?
Page 15 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Stage Activity Potential Key Impact
Mitigation Measure Responsibility Monitoring Measure Frequency of monitoring
Cost of Mitigation Measure USD
Operation
Vehicles movement
Equipment operating
Air quality and dust
Dust suppression techniques include water spraying and enclosing equipment
TL Cement Operator
PM10 and PM2.5
3 monitoring stations
Measurements every 12 months
Dust suppression sprayer and labour: $? 2000/month
Cost of illness and loss of productivity: $?
Vehicles movement
Equipment operating
Removal of buildings
Generating electricity
Cement Plant operating
Noise Noise limitation techniques include aprons and enclosing equipment
TL Cement Operator
Noise Levels
3 monitoring stations
Measurements every 6 months
Monitoring costs: $580k
Cost of illness and loss of productivity: $?
Vehicles movement
Equipment
Water quality and quantity
Rehabilitation in the event of a spill or contamination event
TL Cement Operator
Flow meters / stream gauges at the Bucoli River (1.6km west) and at Uaimatabai, Uaisa and
Every 6 months
Water Quality Monitoring costs: $1,4M
Water Quantity Monitoring costs : $970k
Page 16 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Stage Activity Potential Key Impact
Mitigation Measure Responsibility Monitoring Measure Frequency of monitoring
Cost of Mitigation Measure USD
operating Spill and contamination mitigation measures
Waino springs.
Monthly water quality and quantity measurements at monitoring boreholes, key spring receptors at Waiono, Uaimatabai and Uaisa.
Rehabilitation costs in the event of a spill: $?
Decommissioning
Vehicles movement
Equipment operating
Air quality and dust
Dust suppression techniques include water spraying and enclosing equipment
TL Cement Operator
PM10 and PM2.5
3 monitoring stations
Measurements every 6 months
Dust suppression sprayer and labour: $? 2000/month
Vehicles movement
Equipment operating
Removal of buildings
Generating electricity
Noise Noise limitation techniques include aprons and enclosing equipment
TL Cement Operator
Noise Levels
3 monitoring stations
Measurements every 6 months
Compensation per the Resettlement Plan : $15,000 estimate
Monitoring costs: $580k
Cost of illness and loss of productivity: $?
Page 17 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Stage Activity Potential Key Impact
Mitigation Measure Responsibility Monitoring Measure Frequency of monitoring
Cost of Mitigation Measure USD
Vehicles movement
Equipment operating
Revegetation activity
Water quality and quantity
Rehabilitation in the event of a spill or contamination event
Spill and contamination mitigation measures
TL Cement Operator
Flow meters / stream gauges at the Bucoli River (1.6km west) and at Uaimatabai, Uaisa and Waino springs.
Monthly water quality and quantity measurements at monitoring boreholes, key spring receptors at Waiono, Uaimatabai and Uaisa.
Every 6 months
Water Quality Monitoring costs: $1,4M
Water Quantity Monitoring costs : $970k
Rehabilitation costs in the event of a spill: $?
Page 18 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
B INTRODUCTION
The TL Cement Project will be managed through the implementation of two Environmental Management Plans. These plans are for the Cement Plant, Jetty and Other Supporting Infrastructure and the Limestone Mine. This EMP relates to the Cement Plant, Jetty and Other Supporting Infrastructure.
1.2 Environmental Management Framework
An Environmental Management Framework (EMF) sets the structure for managing environmental risks and impacts during the Project life cycle. The EMF for the TL Cement Project includes the following key approaches:
a. Select the Project option which has the lowest possible environmental footprint; b. Reduce the environmental impact, as far as possible, through engineering and design approaches; c. Mitigate environmental impact, as far as possible, through engineering and design approaches; d. Manage the direct impacts and the risk of ongoing impact through management measures and monitoring; and e. Continuously improve the environmental management and monitoring measures through the Project life cycle.
1.3 Environmental Management Plan
As required by the Environmental Licensing Law the Environmental Management Plan (EMP) is a separate stand-alone document from the Environmental Impact Statement (EIS).
The EMP is an essential tool for ensuring that mitigation of the negative impacts and enhancement of the positive impacts is carried out effectively throughout the life of the Project. An EMP should be systematically improved on a regular basis to ensure that best available technologies (BAT) and best environmental management practices are implemented in a manner that is pragmatic, efficient and cost-effective.
The EMP for the TL Cement Project Cement Plant, Jetty and Other Associated Infrastructure addresses:
1. Environmental impacts which are identified as ‘Medium’ or greater in EIS document; 2. Mitigation measures for all aspects which are required in accordance with industry best practice; 3. Monitoring measures and standards to be followed; 4. Trigger values or target values of measurement criteria; 5. Reporting requirements; and 6. Continuous improvement process.
It should be noted that the any resettlement or compensation matters are the responsibility of the Government of Timor-Leste and as such are not part of the EMP.
Page 19 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
1 PROJECT DESCRIPTION
1.1 Project Identification
TL Cement LDA, a privately-owned company, proposes to construct a greenfield cement manufacturing project in Baucau Municipality, Timor-Leste. The project will produce approximately 1.65 million tons per annum (mtpa) of Portland cement clinker. For the purposes of this EMP, the components of the Baucau Cement Plant Project that relate to the construction and operation of the cement plant, jetty and other associated infrastructure shall be referred to as the Project.
Page 20 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
2 DETAILS OF PROJECT PROPONENT
TL Cement LDA was registered in Timor-Leste as a new company to develop the Baucau Cement Clinker Plant project. The contact details of the Project Proponent are given below:
Name: TL Cement LDA
Dili Office
Address: Rua Complexo Hotel Ramelau Aimutin Comoro, Dom Aleixo Dili Timor Leste Phone: +670 331 1206
Perth Office
Address: Level 5, 22 Mount Street Perth, Western Australia 6000 Phone: +61 8 9261 1965
Contact Person Mr. James Rhee Managing Director Mob: +61 400 317 811
Email: [email protected]
Contact Person Mr. James Rhee Managing Director Mob : +61 400 317 811
Email: [email protected]
2.1 Project Environmental Impact Statement
The Environmental Authority for this Project is the National Directorate for Pollution Control and Environmental Impact (NDPCEI). WorleyParsons on behalf of the Project Proponent has consulted with the NDPCEI with regards to obtaining the Environmental Licensing Certificate for the Project. The Application for Environmental License and the Project Document were submitted to NDPCEI in June 2015. The Project Document was approved on 20 July 2015 and pursuant to Decree Law 5/2011, the NDPCEI categorized the Baucau Cement Project as Category A.
Page 21 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
TL Cement LDA and their EIA consultant, WorleyParsons TL have developed and delivered this EIS and the EMP under the guidance and instruction of the National Directorate for Pollution Control and Environmental Impact (NDPCEI). This document has been extensively reviewed by; and aligns with the expectations and direction of the advisors in the NDPCEI. WorleyParsons has compiled this document in good faith that the content will assist the NDPCEI in assessing the environmental and social impacts of the project in line with the requirements of Decreee Law 5/2011.
Page 22 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
3 DETAILS OF EMP CONSULTANTS
WorleyParsons is responsible for leading the environmental assessment process, conducting the environmental and social baseline studies, and preparing the Environmental Impact Statement (EIS) and Environmental Management Plans (EMPs).
Globally, WorleyParsons is a leading provider of professional services to the infrastructure and resource industries. WorleyParsons has been involved in environmental management for decades and has a proven track record of delivering innovative solutions for our customers. WorleyParsons offers a full suite of environmental services, which cover all aspects from planning to detailed design and implementation. Services include engineering and environmental services to assist in site selection, site analysis, site layout, and design. One of the key differentiators to WorleyParsons’ environmental assessment approach is our ability assemble multi-disciplinary, in-house teams, including but not limited to engineers, urban planners, GIS and mapping specialists, geotechnical engineers, environmental scientists, social impact specialists, and hydrological engineers. These teams are led by experienced environmental assessment professionals who are capable of integrating the technical aspects of all disciplines into a tailored solution. Our ability to draw upon all of these resources internally streamlines the project delivery process and ensures reliable quality for the customer.
3.1.1 Local presence
WorleyParsons established an office in Timor-Leste in 2010 to provide our customers with the advantages of local content and an ‘on-the-ground’ understanding of local conditions. WorleyParsons Timor-Leste has delivered several major projects nationwide for the Government of Timor-Leste, TIMOR GAP, and international development agencies, including engineering feasibility, engineering design, and environmental assessment projects.
As a local company employing local staff, WorleyParsons is intimately familiar with the Timorese environment and culture. Our local staff are fluent in Portuguese, Tetun, and other local languages and are experienced in community engagement. Our multi-disciplinary team has extensive experience in the delivery of environmental studies in Timor-Leste.
WorleyParsons is supported by the following specilst consultants, who have extensive experience in Timor-Leste, including:
• Bita Bina Semesta (BBS): BBS is based in Bandung, Indonesia and maintains a locally-registered project office in Dili, Timor-Leste. BBS specializes in 'front end' type works, including planning and environmental studies for transport, resources, urban development, infrastructure and industrial development. BBS has become a regional leader in the preparation of environmental impact assessments that meets international standards. BBS recently worked with WorleyParsons to deliver environmental studies in support of the Dili Drainage EIA for the Ministry of Public Works.
Page 23 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
• InSight Consulting: Insight is a Timorese-owned organization based in Dili conducting research into public attitudes in the country. Their work is intended to advance the mutual interest of stakeholders, civil society and the people of Timor-Leste. They have a proven record as a credible research agency, based on sound principles of investigation and an intimate knowledge of the country. Their greatest emphasis is on compiling accurate information in a fully accountable way. Insight recently worked with WorleyParsons and BBS on the Dili Drainage EIA environmental studies.
• Nuno Oliviera: Dr. Nuno Oliveira is currently the Cultural Heritage Adviser for the Timor-Leste Secretary of State for Arts and Culture where he has led development of cultural heritage management programs and policies including the National Cultural Policy, Cultural Strategic Plan, Resolution on Protection of Cultural Heritage and ratification of UNESCO’s main conventions on cultural heritage. Prior to this role, Dr. Oliveira conducted extensive research in Timor-Leste for the Australia National University (ANU), completing his dissertation on early subsistence practices and agriculture in Timor-Leste. His research included extensive fieldwork and excavations near the proposed project location.
• Dr Colin Trainor: During 1997-2002, Colin worked internationally as an ecologist with BirdLife International, leading biodiversity assessments, particularly of forest birds, in Indonesia and East Timor (Timor Leste) (Timor Leste) (Timor-Leste). In Timor-Leste (2002-2014), work included a PhD thesis involving systematic survey of birds, mammals, reptiles, ants and trees across a 2,000 km2 district, and consulting projects on transmission and proposed hydropower works at Baucau and Iralalaro in Timor-Leste; shorebird and waterbird assessments; bird species rediscoveries. In Timor-Leste has worked on establishment of a protected area, wrote and published a field guide to the birds of East Timor (Timor Leste) and a site priority guide.
The environmental assessment has been undertaken by a team of specialists with world-class expertise and extensive experience in Timor-Leste.
Page 24 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
The development of the EIS and EMP has been led by Mr Daniel Hunter.
Key Personnel Qualifications and Experience
Daniel Hunter EIA Specialist
B App Sci (Natural Resources Management), University of Melbourne Dan is a Project Manager and Scientist with over 20 years’ experience predominantly in the area of environmental assessment and management. He has extensive experience in managing multidisciplinary projects, including the assessment and management of cumulative environmental issues associated with large infrastructure projects such as mine and port developments, roads, rail corridors, land developments, pipelines and has worked pro-actively with environmental planning teams, project design teams, government regulators, construction personnel, consultants and the community to achieve environmental / sustainability objectives and the development of mitigation strategies and consents in accordance with regulatory requirements. One of Dan’s major roles on projects is to integrate environmental considerations into all aspects of decision making, planning, design, construction and operational processes and drive for sustainable outcomes. Dan has previously managed and led a study of the Timor-Leste local industry capability for ConocoPhillips.
The environmental assessment has been undertaken by a team of specialists with world-class expertise and extensive experience in Timor-Leste.
Key Personnel Qualifications and Experience
Chris Serjak Study Manager
MSc, Sustainable Development, University of London Chris is the Country Manager for WorleyParsons’ Timor-Leste operations. He has 18 years of experience in environmental management, infrastructure development, and sustainable international development. He has five years of experience in Timor-Leste working on environmental projects, community-driven development, local content, and offshore petroleum projects. Chris recently completed a year-long study of the environmental licensing process in Timor-Leste and is an expert on the local regulatory framework. He has led the Dili Airport Environmental and Social Scoping Study and provided consulting services on the environmental licensing process for the Suai Supply Base project. As a certified project-manager, Chris understands how to manage interdisciplinary teams to deliver projects that meet client expectations.
Page 25 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Key Personnel Qualifications and Experience
Annette Jacobs Lead Author
BSc (Hon) Earth Science, Dip Project Management, Rhodes University Annette is trained as an environmental scientist with 15 years’ experience in environment and social impact assessment (ESHIA), management plan development, geology and hydrogeology. Her technical experience includes numerical modelling, environmental hydrogeology and advanced spatial analysis using geographic information systems (GIS). Annette currently project manages all the large marine science projects at WorleyParsons and understands the complexities and issues often encountered. She has 10 years’ project management experience in all stages of the project life cycle. Her project specific experience includes marine environmental hydrology, environmental and groundwater management for the mining industry and infrastructure projects, contaminated sites groundwater quality investigations, ESHIA project development and implementation, and mitigation and management plans.
Alison Mratovich Community Consultation
BA Geography and Environment Management, University of Johannesburg Alison has over 10 years experience in stakeholder management providing consultancy and advisory services to government agencies and private companies on environmental and social impact assessments, community engagement and socio-economic baseline assessments. Her focus is on social and environmental impact assessments, stakeholder engagement programs and social investment strategies. Delivering assessments in accordance with WA, International Finance Corporation (IFC) and World Bank Standards.
Lindsay Furness Water Resources
MA, Hydrogeology and Engineering Geology Mr Lindsay Furness has over 38 years’ experience in groundwater and water resource management in 14 countries for ADB, WB, UNESCO, WHO, AusAID, NZAID. He is a Fellow of the Australian Institute of Geosciences (Registered Professional Geoscientist), a member of the International Association of Hydrogeologist and the National Association of Ground Water Scientists and Engineers (US). Lindsay Furness made a preliminary study of the caves and springs of the Baucau Aquifer in 2004 under an ADB water resources assessment for Timor-Leste in relation to Agricultural irrigation. In 2010 he was appointed as the Timor-Leste Water Resources and Climate Adaptation Specialist in the National Department of Water Resources (DNGRA), where he was responsible for carrying out several surveys of the Baucau geohydrology.
Page 26 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Key Personnel Qualifications and Experience
Stuart Atkinson Water Resources
MEngSc, BEng (Hons), MIEAust He has over 15 years’ experience in hydrology, hydrogeology and contaminated site assessment gained in Australia, Africa, the Middle East, UK and New Zealand. Stuart’s Master’s degree research included water balance modelling in wet and arid environments. He has worked as part of large multidisciplinary teams addressing all water resource issues on major projects, and also managing smaller projects requiring specialist technical expertise to resolve complex water resource problems. This has included working through all project phases using a variety of project delivery. Stuart’s technical experience includes numerous hydrological investigations aimed at designing flood protection measures for new mine sites, residential and commercial developments, mine water management, flood mapping, water balance modelling, environmental hydrology, dam design, drainage system design and the preparation of bridge and culvert schedules for railway, roads and pipelines with lengths in excess of 1,000km. Stuart’s experience solving complex surface and groundwater issues on mining projects allows him to identify and address project risks associated with surface and groundwater while also considering associated geotechnical and civil engineering issues.
Lekha Siraz Water Resources
PhD Hydrogeology, BSc Geology, MSc. Geology (Hydrogeology) Lekha’s fields of experience include groundwater assessments, environmental hydrogeology, hydrogeological and contaminated site assessments and groundwater modelling. She has worked on a number of hydrogeological reviews, feasibility / impact assessments and compliance monitoring for mining and industrial customers in Australia. Lekha’s expertise also includes hydrogeological Interpretation and conceptualisation leading towards flow and contaminant transport Modelling. She has project managed and reviewed hydrogeological and groundwater modelling projects for the Victorian and New South Wales Government agencies, mining clients and waste management facilities. Besides these, her other projects have included landfill liner and cover design using industry standards such as the US EPA HELP model and alternate cover conceptualisation and design for landfills using vadose zone modelling. She also assisted a WA based contaminated sites auditor in audits of several sites, reviewing assessments, reports and preparing contaminated sites audit reports.
Page 27 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Key Personnel Qualifications and Experience
Grant Hickson Air Quality
BSc (Hons) Physics and Computer Science
Grant Hickson has more than five years of air quality consulting and professional experience in environmental impact assessments. He is an Environmental Scientist specialising in pollutant and particulate matter dispersion modelling from major industrial works, emissions estimation / calculation, data analysis and management as well as data validation and quality control for reporting purposes. Grant has undertaken numerous air quality impact assessments in Australia and internationally. He has recently been the primary author for the air quality, meteorology and noise assessments for the Tasi Mane Environmental Impact Assessment project. In this assessment he was responsible for: the on-site collection of air quality samples; meteorological and noise measurements; location surveying; data management and interpretation; and reporting. All work was conducted to International Standards across multiple sites and allowed the client to assess any adverse environmental impacts from the proposed development.
Dr. Kania Dewi Air Quality
PhD, Environmental Engineering Dr. Kania has 10 years’ experience as an Air Quality Expert conducting monitoring and modelling of air quality impacts for EIAs and EMPs. She has extensive experience with mining and hydrocarbons projects throughout Indonesia. Dr Kania has conducted multiple pollutant and GHG emissions inventories and completed climate change assessments. She has also completed modelling and assessment of impacts from cement plants. Dr. Kania recently completed a baseline air quality assessment for the Dili Drainage EIA environmental studies in association with WorleyParsons.
Dr. IB Ardhana Putra Noise
PhD, Engineering Dr. Ardhana has 16 years of experience in noise impact assessment, modelling, and management. He has published nearly 40 papers on noise over the past 27 years and is a former Head of Academic Development Program at Bandung Institute of Technology and a current advisor to the Indonesian Ministry of Environment. He has extensive experience with measurement, analysis and mapping of noise condition at oil and gas facilities and power plants, as well as airports and roads.
Titi Liliani Soedirdjo Traffic
MSc, Highway and Traffic Engineering Ir Titi has 34 years of experience in traffic engineering, traffic surveys, and traffic impact assessments. He has been a lecturer at Bandung Institute of Technology since 1981 and a consultant on traffic and railways. He has been involved in several studies in Timor-Leste, including modelling the traffic signalization and signage for Dili in 2002 and a traffic impact assessment for the Dili Drainage EIA.
Page 28 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Key Personnel Qualifications and Experience
Dr. Hisyam Achmad Social Impact & Resettlement
PhD, Anthropology Dr. Hisyam has over 40 years’ experience in social sciences and anthropology. In the past 10 years, Dr. Hisyam has worked for BBS completing several socio-economic and resettlement impact studies for projects throughout Indonesia, including public consultation, field surveys, and resettlement planning. He has extensive experience with IFC Guidelines and Indonesian AMDAL. He recently completed a socio-economic and resettlement impact assessment for the Dili Drainage EIA project.
Joana Belo Public Consultation field officer
BSc, Environmental Science (Management) Joana is an HSE Professional with experience in Australia, Malaysia and Timor-Leste. She has 7 years of experience health, safety and environment (HSE) including conducting risk assessment, developing emergency procedures in hydrocarbon and infrastructure industry. She also is participating in many environmental impacts and social assessments including, Field Officer for Worley Parsons Timor-Leste working on Dili Airport Environmental and Social Scoping Study, and Field officer for Tasi Mane EIA Study.
These specialists are supported by a team of local Timorese staff including environmental specialists, social specialists, and field surveyors. Field assistants have also been hired from the local area to ensure access to local knowledge and to promote public consultation.
In addition, wherever possible, the environmental assessment process has involved participation from local communities and mentoring of Timor-Leste university students, especially during field survey activities.
Page 29 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
4 DESCRIPTION OF THE PROJECT
For the purposes of the Environmental Licensing process, the NDPCEI has divided the Baucau Cement Project into several major components, as follows:
1. Cement Plant, Conveyor Belt, Power Plant, Marine Jetty, and Associated Infrastructure; 2. Limestone Mine; 3. Clay Extraction; and 4. Road Improvements and New Roads.
All of the items included are critical to the success of the Baucau Cement Project. The Limestone Mine will supply the product to be processed and exported. The cement plant will process the raw materials to produce cement clinker for domestic use and international sale. The jetty will be used to import raw materials not available locally including coal, iron ore, and gypsum and to export the clinker product. The conveyor belt will be used to transport materials to and from the marine jetty. The cement plant also includes a 30MW CFB power plant to provide electrical power to the plant.
The area of a Future Industrial Precinct has been proposed, however is not included in this EIS assessment. The Future Industrial Precinct is pending further investigation and assessment and will be subject of a separate environmental approval.
4.1.1 Project component equipment and technology
A picture which shows the Cement Plant and export via the Jetty is included below.
Page 30 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Figure 1 Cement Plant, Conveyor and Jetty for export – Flow diagram
Page 31 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Figure 2 Conceptual view of the cement plant with components
4.1.2 Pre Construction
During pre construction, excavators and graders will be used to clear vegetation and level the ground for the construction phase.
Pre-construction also requires the establishment of a camp for workers.
Page 32 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Figure 3 Example of excavator to be used to clear vegetation during pre-construction
Page 33 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Figure 4 Example of construction camp accommodation for workers
4.1.3 Construction
During construction, heavy plant and equipment will be used to construct the Cement Plant, Jetty and Conveyor. Examples of this equipment is included below.
Page 34 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Figure 5 Example of excavator loading a dump truck
Page 35 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Figure 6 Example of jetty during construction (photo: marineandcivil.com)
Page 36 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Figure 7 Example of a Material Offloading Facility (MOF) during construction (Photo: Inpex)
4.1.4 Operation
During operation, the plant will be operational and the jetty will load ships for export. Trucks and other vehicles will be used around the site to transport material and people to and from the workplace.
Page 37 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Figure 8 Example of Cement Plant showing bituminsed surface for mitigation of dust
Figure 9 Example of Conveyor showing covered conveyor for mitigation of dust
Page 38 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Figure 10 Example of power infrastructure showing housing for mitigation of noise
Figure 11 Example of crusher in the plant with mitigation (cover for dust)
Page 39 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Figure 12 Example of crusher in plant (inside) – mitigation measure cover for dust
Figure 13 Example of raw mill grinding (Cement plant) – mitigation measure safety barriers
Page 40 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Figure 14 Example of kiln area and heater tower
Figure 15 Examples of Jetty infrastructure
4.1.5 Decommissioning
During decommissioning, equipment and buildings will be dismantled following consultation with the community and GoTL.
The area will be revegetated with native species.
Page 41 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Figure 16 Example of decommissioning process (implosion of a power station) (Photo: sandiegouniontribune.com)
Figure 17 Example of revegetation process (Image : Google Images)
Page 42 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
4.2 Project Location
The proposed Baucau Cement Project is located in Suco Tirilolo, Aldeia Osso-ua, in the Baucau administrative post of Baucau Municipality, Timor-Leste. The location is about 120 km east of Dili and approximately 16 km west of Baucau.
Figure 18: Location of Cement Plant, Jetty and Conveyor Belt
4.2.1 Nature of the project location
The Jetty and Conveyor Belt area is located at the nearby beach and is flat and already highly modified by temporary dwellings, grazing and some agriculture. The general environment is characterised by sandy soils and established breadfruit Artocarpus altilis and Corypha sp. palm groves. The area is also severely infested with weeds. The Jetty area starts at the beach which slopes gently towards the ocean with a slightly steep beach before projecting into the ocean. The overall site is dominated by a relatively uniform coastal Closed Tropical Forest (70%) which is most likely a combination of existing forest and mature plantation trees. The remaining area (30%) is cleared grazing land and residential farms. Overall, the site is a heavily modified plantation environment with a severe infestation of Lantana camara throughout. The
Page 43 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
biological diversity at these sites was very low and overall the site was not representative of a pristine coastal/beach forest (Trainor & Easton, 2015).
The Cement Plant site is located on NNE facing slopes and plains relatively close to the beach, road and proposed Jetty area. The site is characterized as hilly and slopes up away from the coast, with shallow limestone soils and scattered limestone rock outcrops, minor ridges and gullies sloping towards the beach. The site consists predominantly of very open savannah woodland (95%) which has been extensively modified for agriculture and grazing in places. The remaining areas were isolated patches of Closed Tropical Forest systems (5%), occurring in depressions and drainage floors and often surrounded by introduced Lantana camara (Trainor & Easton, 2015).
No permanent rivers exist within the Project site. Some small ephemeral watercourses flow through the area, mainly during the wet season. These tend to stop flowing in the dry season and are not considered suitable as full time water sources. The closest ephemeral stream is the Manulede River located approximately 9 km from the proposed Cement Plant site (WorleyParsons, 2015c).
The Project is located near the Caisido community of the Aldeias Parlemento, Caisido, Lialaileso, and Osso-Ua. The total population of the Caisido area (the Project Site) is 2,387 or 38% of the Suco Tirilolo population. There are 532 households in Caisido and the average size of a household is 5 people. Economic employment is mainly focused on agricultural sector. Most of the local populations in the areas surrounding Baucau Cement Project site are farmers. A small number of these farmers are also teachers, drivers and owners of small kiosks (vendors) within their villages/hamlets (BBS, 2015c).
4.2.2 EMP Endorsement
The Baucau Cement Project proponent, TL Cement, has endorsed this EIS in writing. A copy of their written endorsement is included below.
Page 44 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Page 45 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
The geographical coordinates of the Bacau Cement Project components are detailed in Table 4-1 below.
Table 4-1: Coordinates of Project components
Component Latitude Longitude
Cement Plant -8.4520 126.3424
Marine Jetty -8.4438 126.3433
Conveyor belt -8.4520 to -8.4438 126.3424 to 126.3433
Construction camp and Residential area
Adjacent to cement plant Adjacent to cement plant
Page 46 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
5 LEGAL REQUIREMENTS
5.1 Legislation and legal framework
This section identifies the legislation and guidelines governing the conduct of the Environmental Impact Assessment studies and preparation of the EIS and EMP. This section also identifies other applicable laws, regulations, guidelines, and standards governing environmental quality, health and safety, protection of protected areas and sensitive areas, protection of vulnerable and endangered species, land use control, and other environmental and social issues.
5.1.1 Environmental Legislation
Decree Law 26/2012 Environment Basic Law (EBL)
The EBL (also sometimes called the Environmental Framework Law) sets the overall framework for environmental protection in Timor-Leste. Articles 14, 15 and 16 of the Decree define the instruments for environmental standards, environmental assessment and licensing and environmental monitoring respectively for Environmental Assessment (EA).
Decree Law 5/2011 Environmental Licensing Law (ELL)
The object of the Decree Law is to create a system of environmental licensing for public and private projects likely to produce environmental and social impacts. This system of licensing is based on assessing the size of the potential impacts of projects taking account of their nature, size, technical characteristics and location. Decree-Law No. 5/2011 elaborates the licensing requirement and the EIA procedure in Timor-Leste. Article 4 of the Decree defines the categories of projects and the Type of EA procedure required. The classification of projects is made in accordance with Annex I and II of the Decree. The proposed project has been classified by the NDE as a ‘Category A’ project “that may potentially cause significant environmental impacts, and [is] subject to the procedure of Environmental Impact Assessment (EIA) and Environmental Management Plan (EMP).”
Draft Ministerial Diploma for General Regulations for Environmental Assessment
The Asian Development Bank (ADB) has prepared detailed requirements for Screening, Scoping and the Terms of Reference, Environmental Impact Statements and Environmental Management Plans for Environmental Assessment. Although these guidelines have not been formally adopted, they are in practical use by NDPCEI.
Draft Ministerial Diploma Regulation on the Public Consultation Procedures
The ADB has prepared detailed requirements for Public Consultation Procedures and Requirements during the Environmental Assessment Process. Although these guidelines have not been formally adopted,
Page 47 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
they are in practical use by NDPCEI.
5.1.2 Biodiversity and protected areas legislation
UNTAET Regulation 2000/19 on Protected Places
UNTAET Regulation 2000/19 is still in force and used by the Forestry Department, although it is intended to be replaced by a draft Decree Law on Protected Areas, a draft Decree Law on Forestry, and the draft Decree Law on Biodiversity. Section 3 provides for the protection of endangered species and their habitats. The killing, injuring, harming, taking or disturbing of any endangered species is prohibited. The destruction in any way of the habitat of an endangered species is also prohibited.
UNTAET Regulation 2000/17 on the Prohibition of Logging Operations and the Export of Wood from East Timor
UNTAET Regulation 2000/17 also remains in force at present. Section 2 prohibits the cutting, removal, and logging of wood from land in East Timor. It also prohibits the burning or any other destruction of forests. These prohibitions are subject to Section 3 which allow for exemption to be authorised for certain logging activities.
Draft Decree Law on Forest Management, draft 7, received August 2013
The cutting of “forest trees” and harvesting of other forest products in any zone is prohibited unless specifically authorized by the National Director of Forestry (Article 61). The Director may give authorization for such cutting and harvesting if it would be in accordance with this law and other legislation, any community guideline agreements or with the forest management plan. The Director must take into consideration the forest management plan, conservation of the soil and water of the area, ecology and biodiversity of the area, and any other technical specifications determined by the National Director. Article 61.2 allows for community cutting of trees and harvesting other forest products without authorization, when used for traditional purposes.
Article 67 provides for measures to prevent deforestation. No-one is allowed to cut, damage, destroy, remove, transport, purchase, sell, donate or otherwise acquire or dispose of any tree, unless that tree is private property or the person has a Community Forestry Management Agreement or a permit/authorization from the National Director.
It is an offence under Article 86 for any person to pollute or contaminate land in any Protected Area with chemicals, industrial waste or organic or other polluting substances.
Draft Decree Law on Biodiversity, dated March 2012
When preparing an SEA, EIS, EMP or any other environmental assessment, the proponent must include an assessment of the potential impacts of the proposal on biodiversity and biological resources. This
Page 48 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
assessment must include: (a) Impacts on any natural ecosystems and habitats located within or near the proposed site, in particular the habitat of any protected species and critical habitat; (b) Impacts on any legally protected areas, as well as any areas the subject of cultural or traditional protection mechanisms such as Tara Bandu; (c) Impacts associated with invasive alien species on or near the proposed site; (d) The sustainability of any proposed use of biological resources; and (e) Proposed measures to avoid, minimize, or mitigate identified impacts, and measures to offset or compensate for any affected biological resources and impacts on biodiversity.
In analyzing any environmental assessment and before deciding to grant an environmental license, the decision-maker must take into account whether granting approval for the proposed activity would be consistent with the purpose and principles of the draft Biodiversity Decree Law. In particular, the Decision-maker must be satisfied that: (a) Any adverse impacts and risks identified in the assessment are deemed satisfactory; (b) Adequate measures to avoid, minimize, or mitigate identified adverse impacts have been identified and will be implemented; (c) As a last resort, adequate compensatory measures, which are designed to achieve no net loss of biodiversity, have been identified and will be implemented by the proponent to offset or compensate for any impacts on biodiversity and affected biological resources; (d) The proponent has prepared, in close consultation with affected local communities, a comprehensive plan that includes details about all necessary remedial and restoration efforts, and is satisfied that the plan will be implemented at the proponent’s expense.
5.1.3 Land legislation
Draft Expropriation Law Property may only be expropriated for the public interest and upon timely payment of fair compensation (Article 1). Only the State can order expropriation (Article 5).
There must be public consultation on any project requiring expropriation of private or community property (Article 13), and the documents made available to the public for consultation and public hearings must include any environmental, social or economic impact assessment studies (Article 15.4).
5.1.4 Agriculture and Fishing legislation
Decree Law 6/2004 On General The Decree-Law responds to the need of regulating fishing activities so
Page 49 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Bases of the Legal Regime for Fisheries and Aquaculture Management and Regulation (amended by Decree Law 4/2005)
as to contribute to the attainment of objectives on the economic and social development policies of the country while simultaneously ensuring the protection and conservation of species, as well as their continuous and sustainable exploitation. It also establishes the legal regime for aquaculture. Prohibits the introduction into national maritime waters and hydrographical basis of Timor-Leste of any substances or toxic objects likely to cause infection, and which poisons or destroys fishing resources, algae or any aquatic flora species. Any person, entity, factory or company is prohibited from discharging wastewaters originating from industrial or commercial activities into national waters if such wastewaters are likely to stun, poison or lead to the destruction of fishing resources or any other aquatic species. Any facility which intends to discharge wastewaters into maritime waters or hydrographical basins requires the prior opinion from the Minister responsible for fishing and aquaculture. The prior opinion from the Minister responsible for fishing and aquaculture is required for any intended works or installation in national maritime waters, on the seafront up to 100m from the coastline or in hydrographical basins where there are fishing or aquaculture activities.
5.1.5 Ports Legislation
Decree Law 3/2003
Port Authority establishment
The Decree Law 3/2003 on the establishment of the Port Authority and on the approval of the bylaws thereof details the structure, nature and responsibilities of the Administração dos Portos de Timor-Leste or Port Authority of Timor-Leste (APORTIL). The annex to this law requires APORTIL to grant licences for works carried out within their jurisdiction. The marine facilities associated with the project will require the issuing of a port licence from APORTIL prior to commencement of construction.
5.1.6 Labor legislation
Law 4/2012 Labor Code The duties of the employer include providing workers with good working conditions, prevention of risks from diseases and occupational accidents, providing workers with information and equipment necessary to prevent such risks.
The employer is under a general obligation to provide appropriate health and safety conditions, to prevent accidents and dangers, and to reduce risks.
Page 50 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Employers must ensure that workers are not exposed to risks that are harmful to their health, and must promote awareness programs. Where necessary, employers must provide safety equipment to workers.
5.2 Obligations
TL Cement is committed to developing this project in the region and complying with the regulations of Timor Leste. Negotiations and discussions with stakeholders and regulators are ongoing.
5.3 Summary of Project Approvals
Project Activities Statutory
Requirement Relevant Legislation
Cement Plant, Conveyor and Jetty Jetty, Plant and Conveyor
Marine facilities Environment licence Decree law 5/2011 on environment licensing law
Port licence from APORTIL
Decree law 3/2003 on the establishment of the Port Authority and on the approval of the bylaws thereof
Prior opinion from the Minister (APORTIL)
Decree Law 6/2004 On General Bases of the Legal Regime for Fisheries and Aquaculture Management and Regulation (amended by Decree Law 4/2005)
Land facilities Environment licence from DNSMA
Decree law 5/2011 on environment licensing law
Cement Plant Mining License Ministerial Diploma 01/2008 on Licensing of Mining Activities
Borehole Water Supply Water Supply for Public use
Decree Law 4/2004 Water Supply for public consumption
Internal roads Decree law 2/2003 on basic law on the road transport system
Water Decree law 4/2004 on water supply for public consumption
Telecommunications
Decree law 11/2003 on establishing the bases for the telecommunications sector
Electricity Decree law 13/2003 on establishing the bases for the national electricity system
Page 51 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
5.4 Summary of Environmental Standards
Phase Aspect Standard Pre Construction Air Quality World Health Organization (WHO), 2006: Air
Quality Guidelines (AQGs) for PM10 Noise UNTAET Guideline on Ambient Noise (2002) Water Quality WHO Drinking Water Standards (2000)
Construction Air Quality World Health Organization (WHO), 2006: Air Quality Guidelines (AQGs) for PM10
Noise UNTAET Guideline on Ambient Noise (2002) Water Quality WHO Drinking Water Standards (2000)
Operation Air Quality World Health Organization (WHO), 2006: Air Quality Guidelines (AQGs) for PM10
Noise UNTAET Guideline on Ambient Noise (2002) Water Quality WHO Drinking Water Standards (2000) Vibration Regulation 11
Environmental Protection (Noise) Regulations 1997
Decommissioning Air Quality World Health Organization (WHO), 2006: Air Quality Guidelines (AQGs) for PM10
Noise UNTAET Guideline on Ambient Noise (2002) Water Quality WHO Drinking Water Standards (2000) Vibration Regulation 11
Environmental Protection (Noise) Regulations 1997
Page 52 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
6 INSTITUTIONAL ROLES AND RESPONSIBILITIES
Phase Item Develop/Author Implement
Detailed Engineering Design
Environmental Management Plans
Lead Engineer from the Engineering provider with approval by Project Manager – TL Cement LDA
Lead Engineer from the Engineering provider
Mitigation Measures Lead Engineer from the Engineering provider with approval by Project Manager – TL Cement LDA
Lead Engineer from the Engineering provider
Monitoring Plans Lead Engineer from the Engineering provider with approval by Project Manager – TL Cement LDA
Lead Engineer from the Engineering provider
Construction Tender Phase
Develop construction specific Environmental Management Plans
Civil works contractor with approval by Project Manager – TL Cement LDA
Civil works contractor
Develop construction specific
Mitigation Measures
Civil works contractor with approval by Project Manager – TL Cement LDA
Civil works contractor
Develop construction specific
Monitoring Plans
Civil works contractor with approval by Project Manager – TL Cement LDA
Civil works contractor
Page 53 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Phase Item Develop/Author Implement External Review
Pre-Construction Environmental Management Plans
Civil works contractor with approval by Project Manager – TL Cement LDA
TL Cement nominated EPC management firm Health, Safety Quality Manager/Officer
Mitigation Measures
Civil works contractor with approval by Project Manager – TL Cement LDA
TL Cement nominated EPC management firm Health, Safety Quality Manager/Officer
Monitoring activities
Civil works contractor with approval by Project Manager – TL Cement LDA
TL Cement nominated EPC management firm Health, Safety Quality Manager/Officer
Compliance monitoring
Project Manager – TL Cement LDA
TL Cement nominated EPC management firm Health, Safety Quality Manager/Officer
Compliance reporting
Civil works contractor with approval by Project Manager – TL Cement LDA
TL Cement nominated EPC management firm Health, Safety Quality Manager/Officer
Autoridade Nacional do Petróleo e Minerais (ANPM)
Minister of Commerce and Environment
NDPCEI
Construction Environmental Management Plans
Civil works contractor with approval by Project Manager – TL Cement LDA
TL Cement nominated EPC management firm Health, Safety Quality Manager/Officer
Page 54 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Mitigation Measures
Civil works contractor with approval by Project Manager – TL Cement LDA
TL Cement nominated EPC management firm Health, Safety Quality Manager/Officer
Monitoring activities
Civil works contractor with approval by Project Manager – TL Cement LDA
TL Cement nominated EPC management firm Health, Safety Quality Manager/Officer
Compliance monitoring
Site Supervisor from TL Cement LDA
TL Cement nominated EPC management firm Health, Safety Quality Manager/Officer
Compliance reporting
Civil works contractor with approval by Project Manager – TL Cement LDA
TL Cement nominated EPC management firm (Cement-Holtec, Jetty Royal Haskoning) Health, Safety Quality Manager/Officer
Autoridade Nacional do Petróleo e Minerais (ANPM)
Minister of Commerce and Environment
NDPCEI
Operations Year 1 to 5
Environmental Management Plans
Environmental Engineer supervised by the Plant Manager – TL Cement LDA
TL Cement nominated EPC firm Health, Safety Quality Manager/Officer
Year 6-end: TL Cement Health, Safety Quality Manager/Officer
Mitigation Measures
Environmental Engineer supervised by the Plant Manager – TL Cement LDA
TL Cement nominated EPC firm Health, Safety Quality Manager/Officer
Year 6-end: TL Cement Health, Safety Quality
Page 55 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Manager/Officer
Monitoring activities
Environmental Engineer supervised by the Plant Manager – TL Cement LDA
TL Cement nominated EPC firm Health, Safety Quality Manager/Officer
Year 6-end: TL Cement Health, Safety Quality Manager/Officer
Compliance monitoring
Environmental Engineer supervised by the Plant Manager – TL Cement LDA
TL Cement nominated EPC firm Health, Safety Quality Manager/Officer
Year 6-end: TL Cement Health, Safety Quality Manager/Officer
Compliance Reporting
Environmental Engineer supervised by the Project Manager – TL Cement LDA
TL Cement nominated EPC firm Health, Safety Quality Manager/Officer
Year 6-end: TL Cement Health, Safety Quality Manager/Officer
Autoridade Nacional do Petróleo e Minerais (ANPM)
Minister of Commerce and Environment
NDPCEI
Decommissioning#1 Environmental Management Plans
Environmental Engineer supervised by the Project Manager – TL Cement LDA
TL Cement Health, Safety Quality Manager/Officer
Mitigation Measures
Environmental Engineer supervised by the
TL Cement Health Engineering Manager
1 Assuming that TL Cement LDA undertake all the Decommissioning works and do not contract the bulk earthworks or civil works to a sub contractor
Page 56 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Project Manager – TL Cement LDA
Monitoring activities
Environmental Engineer supervised by the Project Manager – TL Cement LDA
TL Cement Health, Safety Quality Manager/Officer
Compliance monitoring
Site Supervisor from TL Cement LDA
TL Cement Health, Safety Quality Manager/Officer supervising the Civil works contractor
Compliance Reporting
Environmental Engineer supervised by the Project Manager – TL Cement LDA
TL Cement Health, Safety Quality Manager/Officer
Autoridade Nacional do Petróleo e Minerais (ANPM)
Minister of Commerce and Environment
NDPCEI
Page 57 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
7 SUMMARY OF IMPACTS
There are a number of aspects to the Project that have the potential to cause environmental and social impacts during different phases of the Project. The Impacts have been outlined in the table below.
Page 58 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Table 7-1: Activity and Potential Impacts
Activity Impact Pre construction
Construction Operations Decommissioning
Vehicles movement
Operating heavy machinery
Power generation from Power Plant
Climate Limited impact on climate change from greenhouse gases.
Limited impact on climate change from greenhouse gases.
Some impact from operation of a power plant for operations.
Reduction in impact with decommissioning of plant
Vehicles movement
Digging and excavating
Clearing of vegetation using equipment
Construction of roads and buildings
Vehicles travelling on site
Topography Geology and Soil
Reshaping and excavation of landforms in order to prepare for construction will impact the current topography
Vegetation clearing resulting in increased erosion and run-off
Plant and equipment may leak oils and hydrocarbons which pollute the soil
Increased erosion and run-off from a bituminised Cement Plant area will likely change the water quality of the ocean, springs and rivers
Plant and equipment may leak oils and hydrocarbons which pollute the soil
Increased erosion and run-off from a bituminised Cement Plant area will likely change the water quality of the ocean, springs and rivers
Plant and equipment may leak oils and hydrocarbons which pollute the soil
Decommissioning will involve the rehabilitation of the
This is expected to have a positive impact on the soil resources at the site.
Vehicles Air Quality Dust from Dust from earth Direct Direct emissions
Page 59 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Activity Impact Pre construction
Construction Operations Decommissioning
movement
Digging and excavating
Clearing of vegetation using equipment
Construction of roads and buildings
Vehicles travelling on site
earth moving and vegetation clearing activities;
Direct emissions from vehicles and plant in the form of fuel combustion (i.e. exhaust fumes) and brake wear.
moving and vegetation clearing activities;
Direct emissions from vehicles and plant in the form of fuel combustion (i.e. exhaust fumes) and brake wear.
emissions from vehicles and plant in the form of fuel combustion (i.e. exhaust fumes)
from vehicles and plant in the form of fuel combustion (i.e. exhaust fumes)
Vehicles movement
Digging and excavating
Construction of roads and buildings
Vehicles travelling on site
Plant processing
Operating conveyor belt
Vessels loading at the jetty
Noise and Vibration
Impact from Vehicle movements and earthworks
Impact from Vehicle movements and earthworks
Noise Impact from processing plant activities
Impact from Vehicle movements and earthworks
Page 60 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Activity Impact Pre construction
Construction Operations Decommissioning
Vehicles movement
Digging and excavating
Operating a borehole for water supply
Surface Water
Changes to drainage behavior and quality from earthworks
Changes to drainage behavior and quality from earthworks
Changes to drainage behavior and quality from earthworks
Changes to drainage behavior and quality from earthworks
Vehicles movement
Digging and excavating
Operating a borehole for water supply
Groundwater
Changes to spring flow and quality from earthworks
Changes to spring flow and quality from earthworks
Changes to spring flow and quality from earthworks
Long term changes to spring flow and quality after decommissioning
Vehicles movement
Digging and excavating
Construction of roads and buildings
Vehicles travelling on site
Vessels loading at the jetty
Coastal and Marine
Development of the MOF resulting in changes to coastal processes
Development of the Jetty resulting in changes to coastal processes
Shipping impacts to water quality
Decommissioning returning the beach to pre-development condition
Vehicles Flora Direct loss of Positive impact Indirect loss Positive impact
Page 61 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Activity Impact Pre construction
Construction Operations Decommissioning
movement
Digging and excavating
Construction of roads and buildings
Vehicles travelling on site
vegetation due to clearing
due to revegetation activity
of vegetation cover due to depletion of water sources
due to revegetation activity
Vehicles movement
Digging and excavating
Construction of roads and buildings
Vehicles travelling on site
Plant processing
Operating conveyor belt
Vessels loading at the jetty
Fauna Direct loss of habitat through vegetation clearing;
Harm/death/displacement of individual IUCN listed species;
.
Direct loss of habitat through vegetation clearing;
Harm/death/displacement of individual IUCN listed species
Increased susceptibility of native fauna to predation
Soil disturbance and potential refuge destruction for ground dwelling animals
Changes to natural drainage affecting fauna and their habitat;
Disturbance fauna activities due to noise, vibration and lightning
Direct loss of habitat through vegetation clearing;
Harm/death/displacement of individual IUCN listed species
Increased susceptibility of native fauna to predation
Soil disturbance and potential refuge destruction for ground dwelling animals
Changes to natural drainage
Positive impact with rehabilitation
Page 62 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Activity Impact Pre construction
Construction Operations Decommissioning
impacts. affecting fauna and their habitat;
Disturbance fauna activities due to noise, vibration and lightning impacts.
Use of MOF and road infrastructure
Vessels travelling to/from jetty
Operating conveyor belt
Vessels loading at the jetty
Marine Fauna inc. Fisheries
Construction and operation of the MOF is likely to have an impact on local fish populations and invertebrates
The Jetty and shipping operations has the potential to affect marine life and marine habitats, including fish and marine fauna
The Jetty and shipping operations has the potential to affect marine life and marine habitats, including fish and marine fauna
Positive impact due to decommissioning rehabilitation
Use of MOF and road infrastructure
Vessels travelling to/from jetty
Operating conveyor belt
Vessels loading at the jetty
Marine Habitat
The movement of ships and machinery within the project footprint has the potential to introduce marine pests and disease which impacts coral health
The movement of ships and machinery within the project footprint has the potential to introduce marine pests and disease which impacts coral health
The movement of ships and machinery within the project footprint has the potential to introduce marine pests and disease which impacts coral health
Positive impact due to decommissioning rehabilitation
Page 63 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Activity Impact Pre construction
Construction Operations Decommissioning
Vehicles movement
Digging and excavating
Construction of roads and buildings
Vehicles travelling on site
Plant processing
Operating conveyor belt
Vessels loading at the jetty
Traffic Increase in traffic to the area due to pre-construction
Increase in traffic due to construction
Limited traffic increase during operations, mainly on the project site
Increase in traffic due to decommissioning
Development of the project resulting in economic participation
Employment Some short term employment and training opportunities
Longer term employment and training opportunities
Long term employment and training opportunities
Reduction in employment opportunities as the project decommissions
Development of the project resulting in infrastructure development
Development of a training centre
Infrastructure
Increasing pressure on existing infrastructure e.g. roads and water
Reduced impact on existing infrastructure as project infrastructure construction has commenced
Positive impact on local infrastructure
Long term positive impact on local infrastructure
Development of the project resulting in
Economic Use of Forestry
Loss of access to land by community
No further impact during construction
No further impact during
Positive impact on community who get access to the
Page 64 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Activity Impact Pre construction
Construction Operations Decommissioning
infrastructure development
operations revegetated and rehabilitated forests
Vessels loading at the jetty
Access restrictions due to site fencing
Fishing Access control excludes a portion of the ocean from access by local fishermen
Ongoing access control to sections of the beach and ocean
Ongoing access control to sections of the beach and ocean
Positive impact as access controls are lifted and the jetty becomes available for community use
Access restrictions due to site fencing
People and vehicles movement
Digging and excavating
Relocation of people
Socio Economic Agriculture
Access controls and reduction in available agricultural land
Access controls and reduction in available agricultural land
Access controls and reduction in available agricultural land
Positive impact with removal of access controls and increase available agricultural land
Access restrictions due to site fencing
People movement
Digging and excavating
Relocation of people
Population and Community
Resettlement of affected families
Influx of workers to the pre-construction site
Influx of workers to the construction site
Daily movement of some employee during operations
Changes to the income source of people in the community due to project decommissioning
Vehicles movement
Community Health
Increase in respiratory
Increase in respiratory
Increase in respiratory
Positive reduction in prevalence of
Page 65 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Activity Impact Pre construction
Construction Operations Decommissioning
Digging and excavating
Construction of roads and buildings
Vehicles travelling on site
Plant processing
Operating conveyor belt
ailments due to an influx of people
Increase in the level of respiratory ailments due to increased dust
Increase in vector-related ailments such as malaria due to increase in population density;
Increase in sexually transmitted infections such as the human immunodeficiency virus due to population influx
ailments due to an influx of people
Increase in the level of respiratory ailments due to increased dust
Increase in vector-related ailments such as malaria due to increase in population density;
Increase in sexually transmitted infections such as the human immunodeficiency virus due to population influx
ailments due to an influx of people
Increase in the level of respiratory ailments due to increased dust
Increase in vector-related ailments such as malaria due to increase in population density;
Increase in sexually transmitted infections such as the human immunodeficiency virus due to population influx
diseases and dust-related ailments.
Vehicles movement
Digging and excavating
Construction of roads and buildings
Institutions Schools and Health Facilities
Increased pressure on health services infrastructure
Increase in the level of
Increased pressure on health services infrastructure due to population influx
Increased pressure on health services infrastructure due to population influx
Positive impact on community health with legacy investments
Page 66 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Activity Impact Pre construction
Construction Operations Decommissioning
Vehicles travelling on site
Plant processing
Operating conveyor belt
respiratory ailments due to increased dust
Increase in the level of respiratory ailments due to increased dust
Vehicles movement
Digging and excavating
Construction of roads and buildings
Vehicles travelling on site
Plant processing
Operating conveyor belt
Community and Family Structure
The acquisition of land for the Cement Plant and Jetty and the construction of internal roads may cause impacts on the community and family structure
Impacts to household subsistence and ability to generate income
Impacts to household subsistence and ability to generate income
Change of employment status may affect the households income
Access restrictions due to site fencing
People and vehicles movement
Digging and excavating
Land Ownership and Land Rights
The acquisition of land for the Cement Plant and Jetty and the construction of internal roads may cause conflict around
Limited ongoing impact on land rights during construction
Limited ongoing impact on land rights during construction
The change in land use and decommissioning of the Cement Plant and Jetty and the may potentially cause conflict around land owners and communities.
Page 67 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Activity Impact Pre construction
Construction Operations Decommissioning
Relocation of people
land owners and communities.
Access restrictions due to site fencing
People and vehicles movement
Clearing, Digging and excavating
Relocation of people
Natural Resources Rights
Limited impact due to limited use of the vegetation area of the Plant and Jetty.
The acquisition of land for the Cement Plant and Jetty and the construction of internal roads may potentially cause conflict around land use and harvesting of wood before clearing.
No additional impact once construction commences and resettlement has occurred.
No additional impact once operations commences and resettlement has occurred.
The change in land use and decommissioning of the Cement Plant and Jetty and the may potentially cause conflict around land owners and communities.
Access restrictions due to site fencing
People and vehicles movement
Relocation of people
Cultural Heritage and Archeology
No sites destroyed as a result of the Cement Plant, Jetty and Conveyor
Access to sites may be restricted for safety reasons
No sites destroyed as a result of the Cement Plant, Jetty and Conveyor
Access to sites may be restricted for safety reasons
No sites destroyed as a result of the Cement Plant, Jetty and Conveyor
Access to sites may be restricted for safety
Positive impact, Sites with restricted access for safety reasons will be lifted
Page 68 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Activity Impact Pre construction
Construction Operations Decommissioning
reasons
Page 69 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
8 DESCRIPTION OF PROPOSED MITIGATION MEASURES
The following section outlines the proposed mitigation measures for each of the aspect identified in the EIS. The proposed mitigation measures are considered for each of the different Project phases; i.e.:
• Pre-construction; • Construction; • Operation; and • Decommissioning.
8.1 Climate
Objective To ensure the atmospheric emissions (i.e. carbon monoxide) are minimised as much as practicable;
To ensure design of Project components accommodate climate change, including sea level rise and severe weather events
Impacts Carbon dioxide emissions
Sea level rise impacts on infrastructure
Pre-construction Construction Operations Decommissioning
Design reviews to consider
equipment selection
Design reviews to implement
Alternative Fuels in
consideration of climate
change impacts
Adoption and
implementation of clean
technology
Ensure vehicles and
equipment are regular
serviced and maintained
Limit vehicle idling and keep
vehicles well maintained
Adoption and
implementation of clean
technology
Use of substitute Alternative
fuels (Biomass, RDF, used
tyres and solvents instead of
fossil based fuels in both
cement and power plant
Ensure vehicles and
equipment are regular
serviced and maintained
Limit vehicle idling and keep
vehicles well maintained
Limit vehicle idling and keep
vehicles well maintained
Page 70 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
8.2 Topography, Geology and Soils
Objective Maintain the integrity, ecological functions and environmental values of landforms, geology and soil
Minimise permanent landform alterations
Ensure that the modifications to landforms are physically and environmentally stable and sustainable
Impacts Soil contamination
Erosion and loss of value
Landform shape change
Pre-construction Construction Operations
Soil contamination should be
monitored through
maintaining records of spill
events
Contouring and establishing
drainage systems during
pre-construction phase
Off-site contamination
should be monitored as part
of the Water Quality
Monitoring Programme
Minimizing of excavation
during construction
Soil contamination should be
monitored through
maintaining records of spill
events
Management measures to
control run off and erosion at
the Topsoil Stockpile
Soil contamination should be
monitored through
maintaining records of spill
events
Off-site contamination
should be monitored as part
of the Water Quality
Monitoring Programme
Page 71 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
8.3 Air Quality (including dust)
Objective To ensure that atmospheric emissions do not impact on the health, welfare and amenity of the population and land uses and the environment.
To use all reasonable and practicable measures to minimise airborne dust
Impacts Dust impacts on human health
Combustion emissions impacts on human health
Emissions from vehicles
Pre-construction Construction Operations Decommissioning
All raw materials storage will be in enclosed structures
All materials transport will be by fully covered conveyor belts
All areas with vehicle traffic shall be watered or have dust palliative applied as necessary for
regular stabilization of dust emissions.
All on-site vehicle traffic shall be limited to a speed of 15 mph on unpaved roads.
All material transported off-site shall be either sufficiently watered or securely covered to
prevent public nuisance, and there must be a minimum of six (6) inches of freeboard in the
bed of the transport vehicle.
No vehicles or plant will be left idling unnecessarily.
Reduce the number of vehicle movements through better planning.
Set an appropriate speed limit on haul routes.
All heavy duty vehicles should meet certain emission regulation from local Environmental
Protection Agency.
Use a good quality of fuel (e.g. with low sulphur content).
Engines and exhaust systems should be regularly serviced according to manufacturer’s
recommendations and maintained to meet statutory limits/opacity tests.
All workers onsite will undertake environmental awareness training to highlight potential
issues specific to air quality impacts associated with the project.
The contractor will provide appropriate personal protective equipment (PPE) to the workers
based on the nature of the work.
Ensure correct working methods are employed for the Project.
Page 72 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
8.4 Noise and vibration
Objective To ensure that noise emissions do not impact on the health, welfare and amenity of the population, land uses and environmental values.
To ensure that noise emissions, both individually and cumulatively, comply with the appropriate statutory requirements
Impacts Amenity
Human Health
Fauna
Pre-construction Construction Operations Decommissioning
Storage areas should be located away from sensitive receptors.
Haulage of goods and movement of vehicles/people and equipment can be scheduled.
Where required, noise barriers can be constructed to abate the noise impacts.
Alternative construction methods and selection of less noisy equipment to do the tasks.
8.5 Surface Water
Objective Maintain the integrity, ecological functions and environmental values of surface water.
Impacts Flooding behaviour.
Spring flows.
Water quality changes
Uncontrolled discharge of waste water
Pre-construction Construction Operations Decommissioning
Drains down-gradient from the site to capture potentially contaminated surface water run-off.
Storm water design will be incorporated to manage extreme weather events
Monitoring of surface water features for water quality impacts.
Page 73 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Spills management and pollution control through the Emergency Plan.
8.6 Groundwater
Objective Maintain the integrity, ecological functions and environmental values of groundwater
Minimise the impact on the flow and quality of springs
Impacts Spring flows
Vegetation impacts
Water quality
Pre-construction Construction Operations Decommissioning
Detailed hydrological study
to establish baseline
groundwater monitoring
network including boreholes,
spring flow gauging and
water quality analysis
Groundwater modelling of
Water Supply borehole to
quantify drawdown impacts
Design for handling and
storage of potential
contaminants (including
fuels and chemicals) to
eliminate risk
Emergency Plan to deal with
spills and contaminants
Substitute ground water use
with make- up sea water
systems
Emergency Plan to deal with
spills and contaminants
Page 74 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
8.7 Coastal and Marine
Objective Maintain the integrity, ecological functions and environmental values of the marine environment;
Minimise the impact on bathymetry and sediment transport from the jetty and Materials Offloading Facility (MOF); and
Minimise the impact on coastal zone including beaches.
Impacts Sedimentation
Shore erosion
Marine Pests from Ballast water (Vessels)
Pre-construction Construction Operations Decommissioning
Control of spills and discharge of material or fuels to the
beach or marine environment;
Contouring and movement of vehicles on the beach to
minimize scour and erosion;
Vessel approach to minimize discharge of ballast and spread
of marine pests; and
Storage of construction materials to minimize disturbance of
beach processes.
Control of spills and
discharge of material or
fuels to the beach or marine
environment;
Vessel approach to the Jetty
to minimize discharge of
ballast and spread of marine
pests.
Control of spills and
discharge of material or
fuels to the beach or marine
environment;
Vessel approach to the Jetty
to minimize discharge of
ballast and spread of marine
pests
Page 75 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
8.8 Flora
Objective Maintain the abundance, diversity, geographic distribution and productivity of flora at the species and ecosystem levels through the avoidance or management of adverse
impacts.
Impacts Clearing
Soil erosion
Weeds
Pre-construction Construction Operations Decommissioning
Optimize design to prevent
un-necessary excavation
Undertake stripping and
stockpiling of topsoil
Dust suppression measures
(e.g. water sprinkling) at all
dust generating sites
Weed management
activities including spraying
Minimize site excavation as
much as possible
Dust suppression measures
(e.g. water sprinkling) at all
dust generating sites
Weed management
activities including spraying
Planting Green aprons
around developed areas
where possible
Dust suppression measures
(e.g. water sprinkling) at all
dust generating sites
Weed management
activities including spraying
Sequential rehabilitation
Afforestation and plantation
of local species in areas
degraded during the pre-
construction, construction
and operation phases of the
Project
Revegetation using native
vegetation types typical of
the Project area pre-
construction.
Page 76 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
8.9 Fauna
Objective Maintain the abundance, diversity, geographic distribution and productivity of native fauna at the species and ecosystem levels through the avoidance or management of
adverse impacts
Impacts Clearing
Displacement of fauna
Pre-construction Construction Operations Decommissioning
Site clearing to be
conducted sequentially and
from one corner of the site to
the other, enabling highly
mobile fauna species to
leave the construction area
Monthly recording of fauna
impacts and mortality as a
result of project construction.
6-monthly reporting of fauna
impact data and
interpretation
Control of feral and pest
animals including frogs
Monthly recording of fauna
impacts and mortality as a
result of project operation.
6-monthly reporting of fauna
impact data and
interpretation
Control of feral and pest
animals including frogs
Sequential rehabilitation
Afforestation and plantation
of local species in areas
degraded during the pre-
construction, construction
and operation phases of the
project
Page 77 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
8.10 Marine Fauna incl. Fisheries
Objective Minimise the impact on marine fauna, fisheries and habitats from the jetty and MOF
Impacts Habitat loss due to construction of MOF and Jetty
Displacement of marine fauna
Noise, vibration and light
Spills and ballast water
Introduced marine pests
Pre-construction Construction Operations Decommissioning
Collection of additional
baseline environmental data
including large marine
mammal, turtle nesting,
seagrass and crocodile
habitat.
Collection of baseline
environmental data
pertaining to sea water
quality to provide
background data.
Identification of water quality
reference and impact sites
to be sited within and
adjacent to the project
impact area.
Implementation of Emergency Plan (EP) including Spills and
ballast
Project scheduling to limit shipping movements during the
key mammal migration period typically June, August and
November annually, particularly in November of each year.
Implementation of EP including Spills and ballast
Project scheduling to limit shipping movements during the
key mammal migration period typically June, August and
November annually, particularly in November of each year
EP including Spills and
ballast
Page 78 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
8.11 Marine habitats (including Coral)
Objective Maintain the integrity, ecological functions and environmental values of the marine environment
Minimise the impact on marine habitats including corals from the jetty and MOF
Impacts Direct impact on hard and soft coral coverage from infrastructure footprint
Indirect impacts on hard and soft coral from marine pests, disease, shipping, spills
Pre-construction Construction Operations Decommissioning
Ballast water management
and Introduced Marine Pests
monitoring and controls;
Identification of coral
locations on engineering
drawings and construction
plans;
Identification of impact zone
sites, nearby sites and
reference (background) sites
for the coral health
monitoring program.
Ballast water management and Introduced Marine Pests
monitoring and controls;
Identification of coral locations on engineering drawings and
construction plans;
Management of waste
materials during
decommissioning.
Post decommissioning
marine habitat survey within
5 years post-closure
Page 79 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
8.12 Traffic
Objective To protect the amenity and safety of nearby residents
Minimise disturbance to local traffic
Impacts Traffic volumes
Traffic types increased trucks and heavy machinery
Pre-construction Construction Operations Decommissioning
Planning to minimize vehicle movements (e.g. use of buses to transport workers and house in camps)
Limit reversing requirements
Traffic signage implementation
Speed limits and enforcement
Road widening
8.13 Infrastructure
Objective Prospective employees are provided with the necessary and appropriate skills training
The expectation of employment clearly outlined minimising any potential conflicts
Existing employment sectors/source of livelihood are not adversely impacted.
Impacts Long term beneficial impact on local communities
Pre-construction Construction Operations Decommissioning
Identify and prioritize the upgrades and construction of new infrastructure required for the
construction and operation of the Project (e.g. water treatment and wastewater facilities;
roads and accommodation facilities).
Ongoing inspection, monitoring and maintenance programmes will be developed and
implemented for the relevant infrastructure during the operational phase of the Project to
ensure optimal operation.
Prior to decommissioning
and closure, consultation
with all stakeholders
(relevant authorities,
government and local
community)
Page 80 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
8.14 Employment
Objective Upgrades to existing or construction of new infrastructure for the project are designed and built fit for purpose
Existing infrastructure are not adversely impacted by the development and operation of the Project
Impacts Short term to long term finite increase in income
Training and development
Conflict as a result of employment practices
Pre-construction Construction Operations Decommissioning
Selection and management of employee applications by a specialist employee management
institution formed through a consultative process with sub-district and suco leadership
Prior to decommissioning
and closure, consultation
with all stakeholders
(relevant authorities,
government and local
community)
Page 81 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
8.15 Economic Use of Forestry and other Natural Resources
Objective Ensure the local communities access to forest and other natural resources for economic usage are not adversely affected with the development of the Project; and
Maintain the abundance, diversity, geographic distribution and productivity of flora and fauna at the species and ecosystem levels through the avoidance or management
of adverse impacts
Impacts Loss of firewood sources
Loss of income
Pre-construction Construction Operations Decommissioning
Minimise the disturbance footprint as far as practicable.
Undertake stripping and stockpiling of vegetation and topsoil
for reuse in the decommissioning and rehabilitation phase.
Preserve topsoil for rehabilitation by stripping soil during
construction.
Site clearing to be conducted sequentially.
Topsoil to be stock piled separately from
overburden/interburden for rehabilitation purposes and
protected against loss of run-off.
Control of alien invasive plants i.e. weed control
Control of alien invasive
plants
Sequential rehabilitation to
be conducted as soon as
possible at the completion of
operation.
Afforestation and plantation
of local species in areas
degraded during the pre-
construction, construction
and operation phases of the
Project.
Page 82 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
8.16 Fishing
Objective Ensure the local communities’ access to fishing grounds for economic and subsistence use are not adversely affected by the development of the Project;
Ensure that the communities near the Project are able to contribute to the protection and maintenance of fishing resources
Impacts Access
Fish stocks
Pre-construction Construction Operations Decommissioning
Providing alternative access locations,
Providing safe passage zones across the conveyor corridor crossing the beach between the
Jetty and the Plant sites; and
Ensuring that the timeline for implementation of access controls is communicated to the
families who are directly impacted by the access restrictions.
Good construction measures that will reduce impact on fish stock such as piling which does
not interfere with the marine ecology
Implement measures to ensure coral growth (artificial reefs etc)
Providing alternative access
locations,
Providing safe passage
zones across the conveyor
corridor crossing the beach
between the Jetty and the
Plant sites; and
Ensuring that the timeline for
removal of access controls
is communicated to the
families who are directly
impacted by the access
restrictions.
Page 83 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
8.17 Socio Economic Agriculture
Objective Ensure the local communities access to agricultural land economic usage are not adversely affected with the development of the Project
Impacts Loss of agricultural land
Pre-construction Construction Operations Decommissioning
The impact on community access to farmland during the
project will be addressed by resettlement and compensation
to be undertaken by the GoTL.
Sequential rehabilitation to
be conducted as soon as
possible at the completion of
operation.
The areas degraded during
the pre-construction and
construction phases shall be
restored to their natural, pre-
construction condition.
Afforestation and plantation
of local species in areas
degraded during the pre-
construction, construction
and operation phases of the
Project.
8.18 Population and Community
Objective Maintain communities and limit secondary impacts of population increase due to the Project
Impacts Increase in population locally
Fragmentation of communities
Pre-construction Construction Operations Decommissioning
The impact on community during the project will be addressed by resettlement and compensation to be undertaken by the
GoTL.
Page 84 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
8.19 Community Health
Objective No adverse impacts to community health from the project
Impacts Illness and disease
Lifestyle diseases
Health services infrastructure
Pre-construction Construction Operations Decommissioning
Facilitate education and awareness programs throughout the lifespan of the Project;
Design roads and implement driver training to improve traffic safety.
Internal Project roads will be designed and constructed for all-weather, 24 hr capability.
Establish a secure buffer zone from activities posing safety risks to villages or scattered dwellings.
Develop an employee wellness programme
Page 85 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
8.20 Institutions, Schools and Health Facilities
Objective No adverse effects on community institutions, schools, and health facilities
Impacts 1 Air quality and noise impacts on local primary school, aldeia hall, and church.
2 Influx of jobseekers impacts on capacity of institutions, schools, and health facilities
Pre-construction Construction Operations Decommissioning
1 Refer to Section 0 [Air Quality] and Section 8.4 [Noise and vibration] for relevant mitigation measures
2 The impact on community access to institutions during the project will be addressed by
resettlement and compensation to be undertaken by the GoTL.
Decommissioning will
reduce demand for services
and should be coordinated
with the relevant line
Ministries in advance of
closure to address any
reduction in resources.
8.21 Community and Family Structure
Objective Avoid adverse effects on community and family structure
Impacts Conflicts over the status of land, conflicts over compensation values and systems, conflicts over the dismantling of graves and customary / traditional houses,
population resettlement, and potential damage to local landowners’ subsistence
resources
Pre-construction Construction Operations Decommissioning
Implementation of the Complaints and Grievance mechanism Implementation of the
Complaints and Grievance
mechanism
Advance coordination with
stakeholders with respect to
land transfer
Advance coordination with
potential land users to
maximize productive use of
rehabilitated land
Page 86 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
8.22 Land Ownership and Land Rights
Objective Limit the long term impact of the project on Land Ownership / Land Rights
Impacts People financially and physically excluded from traditional lands
Pre-construction Construction Operations Decommissioning
TL Cement is currently working with the Directorate of Land, Property and Cadastral Services (DLPCS) to map affected
households, farmland, and other property. Once TL Cement has secured the mining license and environmental licenses
required for the Project, the GoTL will enter into discussions with those affected households and property owners.
8.23 Natural Resources Rights
Objective Maintain and protect natural resource rights near the Project site and/or within new site as a part of resettlement plan.
Minimize potential impacts on surrounding environment
Impacts Reduced availability or quality of natural resources
Pre-construction Construction Operations Decommissioning
Implementation of the Complaints and Grievance
mechanism
An environmental education
programme to be developed
and implemented for all
employees
Implementation of the
Complaints and Grievance
mechanism
Implementation of the
Complaints and Grievance
mechanism
Page 87 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
8.24 Cultural Heritage, Archaeological and Sacred Sites
Objective Minimise the number of recorded heritage sites which are directly impacted by the project
Ensure that the management of the relocation of known sites is undertaken in accordance with best practice standards
Ensure transparency and consultation occurs in relation to the unavoidable impacts on known heritage sites in the project area
Impacts Permanent loss of sites
Temporary loss of access to sites for safety reasons
Pre-construction Construction Operations Decommissioning
First to minimize encroachment on such sites identified by field surveys by revising boundary parameters- If site cannot be
avoided then initiate relocation.
Where safe access cannot be guaranteed, those sites which are located adjacent to the project should be fenced off, access
restricted for the project life or relocated.
All archaeological excavations within or adjacent to the study area should be authorised by the State Secretariat of Tourism,
Art and Culture and undertaken by a team of professional archaeologists
Ceremonial platforms or altars should be properly documented and eventually relocated to a different location;
Burial sites should be properly documented, excavated and relocated to an agreed upon site; and
Archaeological sites should be test excavated.
8.25 Summary of Impacts and Mitigation Measures
Page 88 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Table 8-1 Description of proposed mitigation measures
Pre-Construction Stage –
Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp
Impact Mitigation Performance and Impact Monitoring
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
Climate Atmospheric
emissions (i.e.
carbon monoxide)
increase from use
of vehicles
Design reviews to
consider
equipment
selection
Design reviews to
implement
Alternative Fuels in
consideration of
climate change
impacts
Design
Contractor
Prior to
construction
Throughout
project site
Incl. in
construction
contract cost
Automated Weather
Station (AWS)
recording
measurements of:
Station identification
number;
Date and time of
record/observation;
Air, wet bulb and wet
dew point
temperatures.
Precipitation and
Daily
measurements
TL Cement
Annual
reporting for all
project phases
of Greenhouse
Gas emissions in
accordance with
National
Greenhouse and
Energy
Reporting Act
2007.
$500,000 for
Automated
Weather
station
Monitoring
Costs $580k
Page 89 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Pre-Construction Stage –
Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp
Impact Mitigation Performance and Impact Monitoring
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
evaporation;
Relative humidity;
Wind speed and
direction;
Solar radiation;
Barometric pressure ;
Visibility;
Cloud cover; and
Cloud ceiling height, if
practicable.
Topography,
Geology and
Changes to
topography and
Soil contamination
should be
TL Cement /
Design
Prior to
construction
Throughout
project site and
Incl. in
construction
Weed growth and
drainage behaviour on
As required Construction
Contractor
Incl. in
construction
Page 90 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Pre-Construction Stage –
Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp
Impact Mitigation Performance and Impact Monitoring
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
Soils increase in soil
erosion
monitored through
maintaining
records of spill
events
Contouring and
establishing
drainage systems
during pre-
construction phase
Consultant where spills
occur
contract cost the topsoil stockpile contract cost
Air Quality Increase in levels
of dust
All raw materials
storage will be in
enclosed
structures
All materials
transport will be
TL Cement /
Design
Consultant
Prior to
construction
Throughout
project site and
outside of site
where materials
are being
transported
Incl. in
construction
contract cost
At sensitive receptors:
AQ3 – At the Jetty
AQ4 – Settlement area
at Aldeia Osso-Ua
AQ5 - representing the
Every 6 months
measurements
at sensitive
receptors i.e.
Results
interpretation
TL Cement
Contractor
$500,000
Page 91 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Pre-Construction Stage –
Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp
Impact Mitigation Performance and Impact Monitoring
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
by fully covered
conveyor belts
Dust and bag
filters will be
installed at all
critical emissions
hoppers
All areas with
vehicle traffic shall
be watered or
have dust
palliative applied
as necessary for
regular
stabilization of
construction area.
and review of
the EMP as
required.
Collation of
results into
semi-annual
Environmental
Report to
NDCPEI
Page 92 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Pre-Construction Stage –
Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp
Impact Mitigation Performance and Impact Monitoring
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
dust emissions.
All on-site vehicle
traffic shall be
limited to a speed
of 15 mph on
unpaved roads.
No vehicles or
plant will be left
idling
unnecessarily.
Reduce the
number of vehicle
movements
through better
planning.
Page 93 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Pre-Construction Stage –
Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp
Impact Mitigation Performance and Impact Monitoring
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
Set an appropriate
speed limit on haul
routes.
All heavy duty
vehicles should
meet certain
emission
regulation from
local
Environmental
Protection Agency.
Use a good quality
of fuel (e.g. with
low sulphur
content).
Page 94 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Pre-Construction Stage –
Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp
Impact Mitigation Performance and Impact Monitoring
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
Engines and
exhaust systems
should be regularly
serviced according
to manufacturer’s
recommendations
and maintained to
meet statutory
limits/opacity
tests.
Ensure correct
working methods
are employed for
the Project.
Noise and Increase in levels Storage areas
TL Cement / Design Phase Throughout Incl. in At sensitive receptors: Every 6 months TL Cement $500,000
Page 95 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Pre-Construction Stage –
Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp
Impact Mitigation Performance and Impact Monitoring
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
Vibration of noise should be located
away from
sensitive
receptors.
Haulage of goods
and movement of
vehicles/people
and equipment
can be scheduled.
Where required,
noise barriers can
be constructed to
abate the noise
impacts.
Design
Consultant
project site and
in particular in
the vicinity of
sensitive
receptors.
Local road
networks.
construction
contract cost NO3 – At the Jetty
NO4 – Settlement area
at Aldeia Osso-Ua
NO5 - representing
the construction area.
measurements
at sensitive
receptors i.e.
Results
interpretation
and review of
the EMP as
required.
Collation of
results into
semi-annual
Environmental
Report to
NDCPEI
Contractor
Page 96 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Pre-Construction Stage –
Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp
Impact Mitigation Performance and Impact Monitoring
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
Alternative
construction
methods and
selection of less
noisy equipment
to do the tasks.
Surface
Water
Decrease in flows
in streams
Changes in water
quality of
streamflow
Drains down-
gradient from the
site to capture
potentially
contaminated
surface water run-
off.
TL Cement /
Design
Consultant
Design Phase /
Prior to
construction
Throughout
project site
Incl. in
construction
contract cost
Flow meters / stream
gauges at the Bucoli
River (1.6km west)
and at Uaimatabai,
Uaisa and Waino
springs
Monthly water
quality and
quantity
measurements
at monitoring
boreholes, key
spring receptors
at Waiono,
TL Cement -
Collation of
results into
Annual
Environmental
Report to
NDCPEI
$970,000
Page 97 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Pre-Construction Stage –
Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp
Impact Mitigation Performance and Impact Monitoring
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
Storm water
design will be
incorporated to
manage extreme
weather events
Monitoring of
surface water
features for water
quality impacts.
Spills management
and pollution
control through
the Emergency
Plan.
Uaimatabai and
Uaisa.
Interpretation of
data every 6
months.
Groundwater Decrease in flows Detailed TL Cement / Design Phase / Monitoring at Incl. in Quality and quantity Monthly water TL Cement - Inc. Above
Page 98 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Pre-Construction Stage –
Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp
Impact Mitigation Performance and Impact Monitoring
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
in springs
Changes in water
quality of springs
hydrological study
to establish
baseline
groundwater
monitoring
network including
boreholes, spring
flow gauging and
water quality
analysis
Groundwater
modelling of
Water Supply
borehole to
quantify
drawdown impacts
Design
Consultant
Prior to
construction
water supply
boreholes,
design for
handling and
storage to be
implemented
across site.
construction
contract cost
measurements at key
spring receptors at
Uaimatabai, Uaisa and
Uaino.
quality and
quantity
measurements
Reporting and
interpretation of
data quarterly
Collation of
results into
Annual
Environmental
Report to
NDCPEI
Page 99 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Pre-Construction Stage –
Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp
Impact Mitigation Performance and Impact Monitoring
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
Design for
handling and
storage of
potential
contaminants
(including fuels
and chemicals) to
eliminate risk
Coastal and
Marine
Pollution of sea
water
Increase in
turbidity of sea
water
Spread of marine
Control of spills
and discharge of
material or fuels to
the beach or
marine
environment;
Contouring and
TL Cement /
Design
Consultant
Design Phase /
Prior to
construction
Across beach
and marine
environment
within and in
the vicinity of
project site.
Incl. in
construction
contract cost
A sediment transport
model should be
developed in order to
qualify the volume,
duration and
distribution of
sediment and
NA TL Cement -
Collation of
results into
semi-annual
Environmental
Report to
NDCPEI
$500,000
Page 100 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Pre-Construction Stage –
Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp
Impact Mitigation Performance and Impact Monitoring
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
pests from ships movement of
vehicles on the
beach to minimize
scour and erosion;
Vessel approach to
minimize discharge
of ballast and
spread of marine
pests; and
Storage of
construction
materials to
minimize
disturbance of
beach processes.
erosion/scour
associated with the
MOF and Jetty.
Page 101 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Pre-Construction Stage –
Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp
Impact Mitigation Performance and Impact Monitoring
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
Flora Removal of
threatened plants
Optimize design to
prevent un-
necessary
excavation
Undertake
stripping and
stockpiling of
topsoil
Dust suppression
measures (e.g.
water sprinkling)
at all dust
generating sites
Weed
TL Cement /
Design
Consultant
Design phase /
prior to
construction
Throughout
project site
Incl. in
construction
contract cost
The total area of
vegetation cleared
(habitat destruction)
at the end of phase
TL Cement -
Collation of
results into
Annual
Environmental
Report to
NDCPEI
Construction
contractor
$5.6M
Page 102 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Pre-Construction Stage –
Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp
Impact Mitigation Performance and Impact Monitoring
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
management
activities including
spraying
Fauna Removal of
threatened
animals
Site clearing to be
conducted
sequentially and
from one corner of
the site to the
other, enabling
highly mobile
fauna species to
leave the
construction area
TL Cement /
Construction
Contractor
Clearing Throughout
project site
Incl. in
construction
contract cost
Any incidents of fauna
injury and death
should be recorded.
TL Cement -
Collation of
results into
semi-annual
Environmental
Report to
NDCPEI
TL Cement $670k
Marine
Fauna
Loss of fishing
habitat and coral
Collection of
additional baseline
TL Cement /
Contractor
Prior to
construction
Throughout and
surrounding
Incl. in
construction
Regular community
engagement surveys
Annual review
and reporting of
TL Cement Inc. above
Page 103 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Pre-Construction Stage –
Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp
Impact Mitigation Performance and Impact Monitoring
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
including
fisheries
reefs environmental
data including
large marine
mammal, turtle
nesting, seagrass
and crocodile
habitat.
Collection of
baseline
environmental
data pertaining to
sea water quality
to provide
background data.
Identification of
project site contract cost around fisheries
Survey of coral health,
sedimentation and
fisheries.
Collection of water
quality measurements
at reference and
impact sites to be
sited within and
adjacent to the project
impact area.
coral habitats
around Jetty and
MOR.
Water Quality
measurements
are to be taken
at least twice
per calendar
year, outside of
and during the
monsoon
season.
Page 104 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Pre-Construction Stage –
Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp
Impact Mitigation Performance and Impact Monitoring
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
water quality
reference and
impact sites to be
sited within and
adjacent to the
project impact
area.
Marine
habitats
including
coral
Loss of fishing
habitat and coral
reefs
Ballast water
management and
Introduced Marine
Pests monitoring
and controls;
Identification of
coral locations on
engineering
TL Cement /
Contractor
Design phase Throughout
project site and
surrounding
local area
Incl. in
construction
contract cost
Undertake a pre-
construction survey of
the identified sites to
develop the reference
imagery and GPS
database.
Reporting and
recording of baseline
Pre construction
survey
TL Cement -
Collation of
results into
semi-annual
Environmental
Report to
NDCPEI
Inc. above
Page 105 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Pre-Construction Stage –
Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp
Impact Mitigation Performance and Impact Monitoring
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
drawings and
construction plans;
Identification of
impact zone sites,
nearby sites and
reference
(background) sites
for the coral health
monitoring
program.
coral health
monitoring data.
Traffic Increase in amount
of traffic on the
roads
Planning to
minimize vehicle
movements (e.g.
use of buses to
transport workers
and house in
Construction
Contractor /
Mine Operator
During planning
prior to
construction
Throughout
project site and
on local road
networks
Incl. in
construction
contract cost
Traffic incidents and
mitigation measures
implemented
Update Safety
Management
System to
record and
document traffic
Construction
Contractor
$2000/mont
h
Page 106 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Pre-Construction Stage –
Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp
Impact Mitigation Performance and Impact Monitoring
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
camps)
Limit reversing
requirements
Traffic signage
implementation
Speed limits and
enforcement
Road widening
incidents and
mitigation
measures
implemented as
and when they
occur.
Infrastructur
e
Increased pressure
on existing
infrastructure
Identify and
prioritize the
upgrades and
construction of
new infrastructure
TL Cement /
Design
Consultant
Design phase,
ongoing
throughout
construction and
operation
Throughout
project site
Incl. in
construction
contract cost
Complaints and
Grievance records
review
Stakeholder
Regular review
of Complaints
and Grievance
record
TL Cement N/A
Page 107 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Pre-Construction Stage –
Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp
Impact Mitigation Performance and Impact Monitoring
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
required for the
construction and
operation of the
Project (e.g. water
treatment and
wastewater
facilities; roads
and
accommodation
facilities).
Ongoing
inspection,
monitoring and
maintenance
programmes will
be developed and
consultation to check
progress Regular
stakeholder
consultation
Page 108 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Pre-Construction Stage –
Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp
Impact Mitigation Performance and Impact Monitoring
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
implemented for
the relevant
infrastructure
during the
operational phase
of the Project to
ensure optimal
operation.
Employment Training and
development of
local people
Selection and
management of
employee
applications by a
specialist
employee
TL Cement Prior to
construction
Selected
employment
management
institution
offices
Incl. in
construction
contract cost
Complaints and
Grievance records
review
Stakeholder
consultation to check
progress
Regular review
of Complaints
and Grievance
record
Regular
stakeholder
TL Cement N/A
Page 109 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Pre-Construction Stage –
Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp
Impact Mitigation Performance and Impact Monitoring
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
management
institution formed
through a
consultative
process with sub-
district and suco
leadership
consultation
Economic
Use of
Forestry and
other Natural
Resources
Training and
development of
local people
Minimise the
disturbance
footprint as far as
practicable.
Site clearing to be
conducted
sequentially.
TL Cement /
Construction
Contractor
Design phase,
planning phase
for site clearing
sequencing
Throughout
project site.
Incl. in
construction
contract cost
Complaints and
Grievance records
review
Stakeholder
consultation to check
progress
Regular review
of Complaints
and Grievance
record
Regular
stakeholder
consultation
TL Cement N/A
Page 110 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Pre-Construction Stage –
Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp
Impact Mitigation Performance and Impact Monitoring
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
Fishing Decrease in people
who fish
Providing
alternative access
locations,
Providing safe
passage zones
across the
conveyor corridor
crossing the beach
between the Jetty
and the Plant sites;
and
Ensuring that the
timeline for
TL Cement/
Design
Consultant
Design phase,
prior to
construction
Throughout
project site and
surrounding
area
Incl. in
construction
contract cost
Fisheries assessment
is a component of the
Marine Habitats and
Coral monitoring
Per the
Grievance
mechanism
TL Cement
Manager
N/A
Page 111 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Pre-Construction Stage –
Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp
Impact Mitigation Performance and Impact Monitoring
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
implementation of
access controls is
communicated to
the families who
are directly
impacted by the
access restrictions.
Good construction
measures that will
reduce impact on
fish stock such as
piling which does
not interfere with
the marine ecology
Implement
Page 112 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Pre-Construction Stage –
Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp
Impact Mitigation Performance and Impact Monitoring
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
measures to
ensure coral
growth (artificial
reefs etc)
Socio
Economic
Agriculture
Relocation to an
area where people
can farm
The impact on
community access
to farmland during
the project will be
addressed by
resettlement and
compensation to
be undertaken by
the GoTL.
GoTL Design phase,
prior to
construction
Throughout
project site and
surrounding
area
Incl. in
construction
contract cost
Complaints and
Grievance records
review
Per the
Grievance
mechanism
TL Cement
Manager
N/A
Population
and
Influx of new
people to the area
The impact on
community during
GoTL Prior to
construction
As determined
by resettlement
Incl. in
construction
Maintain communities
and limit secondary
Per the
Grievance
TL Cement
Manager
N/A
Page 113 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Pre-Construction Stage –
Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp
Impact Mitigation Performance and Impact Monitoring
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
Community from outside
Baucau
the project will be
addressed by
resettlement and
compensation to
be undertaken by
the GoTL.
facilitated by
GoTL
contract cost impacts of population
increase due to the
Project
mechanism
Community
Health
Increase in injury,
disease and
infections due to
more people in the
area
Facilitate
education and
awareness
programs
throughout the
lifespan of the
Project;
Design roads and
implement driver
TL Cement Prior to
construction and
ongoing
Throughout
project site
Incl. in
construction
contract cost
Complaints and
Grievance records
Per the
Grievance
mechanism
TL Cement
Manager
N/A
Page 114 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Pre-Construction Stage –
Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp
Impact Mitigation Performance and Impact Monitoring
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
training to improve
traffic safety.
Internal Project
roads will be
designed and
constructed for all-
weather, 24 hr
capability.
Establish a secure
buffer zone from
activities posing
safety risks to
villages or
scattered
dwellings.
Page 115 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Pre-Construction Stage –
Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp
Impact Mitigation Performance and Impact Monitoring
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
Develop an
employee wellness
programme
Institutions,
Schools and
Health
Facilities
No impact
anticipated
The impact on
community access
to institutions
during the project
will be addressed
by resettlement
and compensation
to be undertaken
by the GoTL. Refer
to Air Quality and
Noise and
vibration for
GoTL / TL
Cement
Prior to
construction and
ongoing noise
and air
monitoring
during
construction,
operation and
decommissionin
g stage
Throughout
local region
Incl. in
construction
contract cost
Complaints and
Grievance records
Per the
Grievance
mechanism
TL Cement
Manager
N/A
Page 116 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Pre-Construction Stage –
Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp
Impact Mitigation Performance and Impact Monitoring
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
relevant mitigation
measures
Community
and Family
Structure
Relocation of
families may
impact structure
Implementation of
the Complaints
and Grievance
mechanism
TL Cement Prior to design
phase, during
design and prior
to construction
Throughout
wider area
Incl. in
construction
contract cost
Complaints and
Grievance records
Per the
Grievance
mechanism
TL Cement
Manager
N/A
Land
ownership
and Land
Rights
Relocation of land
users will not
impact land rights
TL Cement is
currently working
with the
Directorate of
Land, Property and
Cadastral Services
(DLPCS) to map
affected
households,
GoTL / TL
Cement
Prior to
construction
Throughout
project area
and in
surrounding
vicinity
Incl. in
construction
contract cost
Complaints and
Grievance records
Regular review
of records
To be addressed
by resettlement
and
compensation
to be addressed
by GoTL
Page 117 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Pre-Construction Stage –
Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp
Impact Mitigation Performance and Impact Monitoring
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
farmland, and
other property.
Once TL Cement
has secured the
mining license and
environmental
licenses required
for the Project, the
GoTL will enter
into discussions
with those
affected
households and
property owners.
Natural
Resources
Relocation of land
users will not
Implementation of
the Complaints
TL Cement /
GoTL
Prior to design
phase and
Throughout
project site and
Incl. in
construction
Complaints and
Grievance records
Regular review
of records
To be addressed
by resettlement
Page 118 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Pre-Construction Stage –
Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp
Impact Mitigation Performance and Impact Monitoring
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
Rights impact resources
rights
and Grievance
mechanism
ongoing surrounding
environment, in
particular at
identified
natural
resources
within and near
the project site
contract cost
and
compensation
to be addressed
by GoTL
Cultural
Heritage,
Archaelogical
and Sacred
Sites
Relocation of land
users will not
cultural heritage
sites
First to minimize
encroachment on
such sites
identified by field
surveys by revising
boundary
parameters- If site
cannot be avoided
Construction
Contractor
(during
construction
stage), Mine
Operator
Prior to
construction and
ongoing
throughout
construction,
operation and
decommissionin
g
Heritage sites
identified
through the EIA
as well as any
additional sites
discovered
during
construction,
Incl. in
construction
contract cost
Any and all
occurrences of
damage sites is to be
recorded.
Records to be
reviewed every
6 months.
TL Cement.
Process
improvements
are to be
implemented
where there has
been
unauthorised
Page 119 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Pre-Construction Stage –
Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp
Impact Mitigation Performance and Impact Monitoring
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
then initiate
relocation.
Where safe access
cannot be
guaranteed, those
sites which are
located adjacent to
the project should
be fenced off,
access restricted
for the project life
or relocated.
All archaeological
excavations within
or adjacent to the
operation or
decommissionin
g phase
impact on
cultural heritage
sites.
Page 120 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Pre-Construction Stage –
Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp
Impact Mitigation Performance and Impact Monitoring
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
study area should
be authorised by
the State
Secretariat of
Tourism, Art and
Culture and
undertaken by a
team of
professional
archaeologists
Ceremonial
platforms or altars
should be properly
documented and
eventually
relocated to a
Page 121 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Pre-Construction Stage –
Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp
Impact Mitigation Performance and Impact Monitoring
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
different location;
Burial sites should
be properly
documented,
excavated and
relocated to an
agreed upon site;
and
Archaeological
sites should be test
excavated.
Page 122 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Construction Stage
Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
Climate Atmospheric
emissions (i.e.
carbon monoxide)
increase from use
of vehicles
Design reviews to
consider
equipment
selection
Design reviews to
implement
Alternative Fuels in
consideration of
climate change
impacts
Construction
Contractor
During
construction
Throughout
project site and
on road
networks
Incl. in
construction
contract cost
Automated Weather
Station (AWS)
recording
measurements of:
Station identification
number;
Date and time of
record/observation;
Air, wet bulb and wet
dew point
temperatures.
Precipitation and
evaporation;
Relative humidity;
Daily
measurements
TL Cement
Annual
reporting for all
project phases
of Greenhouse
Gas emissions in
accordance with
National
Greenhouse and
Energy
Reporting Act
2007.
$500,000 for
Automated
Weather
station
Monitoring
Costs $580k
Page 123 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Construction Stage
Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
Wind speed and
direction;
Solar radiation;
Barometric pressure ;
Visibility;
Cloud cover; and
Cloud ceiling height, if
practicable.
Topography,
Geology and
Soils
Changes to
topography and
increase in soil
erosion
Soil contamination
should be
monitored through
maintaining
records of spill
events
Construction
Contractor
During
construction
Throughout
project site and
in surrounding
area
Incl. in
construction
contract cost
Weed growth and
drainage behaviour on
the topsoil stockpile
As required Construction
Contractor
Incl. in
construction
contract cost
Page 124 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Construction Stage
Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
Contouring and
establishing
drainage systems
during pre-
construction phase
Air Quality Increase in levels
of dust
All raw materials
storage will be in
enclosed
structures
All materials
transport will be
by fully covered
conveyor belts
Dust and bag
filters will be
installed at all
Construction
Contractor
During
construction
Throughout
project site and
on local road
networks when
materials are
being
transported
Incl. in
construction
contract cost
A monitoring and
reporting program
implemented to
monitor the air quality
in the following
sensitive receptors:
• AQ4 -
settlement area in
Aldeia Osso-ua.
• AQ5 -
representing the
Once every six
months during
construction and
operation
Construction
Contractor: The
monitoring
stations are
derived from
the BBS
Baseline Air
Quality
monitoring
survey (BBS,
2015b).
Page 125 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Construction Stage
Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
critical emissions
hoppers
All areas with
vehicle traffic shall
be watered or
have dust
palliative applied
as necessary for
regular
stabilization of
dust emissions.
All on-site vehicle
traffic shall be
limited to a speed
of 15 mph on
unpaved roads.
construction area.
The monitoring
program should assess
and report on the
following air quality
parameters:
• PM10; and
PM2.5
• CO
• NO2
• SO2; and
• Ozone.
Page 126 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Construction Stage
Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
No vehicles or
plant will be left
idling
unnecessarily.
Reduce the
number of vehicle
movements
through better
planning.
Set an appropriate
speed limit on haul
routes.
All heavy duty
vehicles should
meet certain
emission
Page 127 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Construction Stage
Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
regulation from
local
Environmental
Protection Agency.
Use a good quality
of fuel (e.g. with
low sulphur
content).
Engines and
exhaust systems
should be regularly
serviced according
to manufacturer’s
recommendations
and maintained to
meet statutory
limits/opacity
Page 128 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Construction Stage
Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
tests.
Ensure correct
working methods
are employed for
the Project.
Noise and
Vibration
Increase in levels
of noise
Storage areas
should be located
away from
sensitive
receptors.
Haulage of goods
and movement of
vehicles/people
and equipment
can be scheduled.
Construction
Contractor
During
construction and
pre construction
(scheduling)
Throughout
project site and
in particular in
the vicinity of
sensitive
receptors.
Local road
networks
Incl. in
construction
contract cost
At sensitive receptors:
AQ4 – Settlement area
at Aldeia Osso-Ua
AQ5 - representing the
construction area.
Every 6 months
measurements
at sensitive
receptors i.e.
Results
interpretation
and review of
the EMP as
required.
Collation of
results into
Construction
Contractor
Incl. in
construction
contract cost
Page 129 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Construction Stage
Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
Where required,
noise barriers can
be constructed to
abate the noise
impacts.
Alternative
construction
methods and
selection of less
noisy equipment
to do the tasks.
semi-annual
Environmental
Report to
NDCPEI
Surface
Water
Decrease in flows
in streams
Changes in water
quality of
Drains down-
gradient from the
site to capture
potentially
Construction
Contractor
During
construction
Throughout
project site and
down gradient
of project site
Incl. in
construction
contract cost
Flow meters / stream
gauges at the Bucoli
River (1.6km west)
and at Uaimatabai,
Monthly water
quality and
quantity
measurements
TL Cement -
Collation of
results into
Annual
Page 130 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Construction Stage
Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
streamflow contaminated
surface water run-
off.
Monitoring of
surface water
features for water
quality impacts.
Spills management
and pollution
control through
the Emergency
Plan.
to capture
contaminated
surface run off
Uaisa and Waino
springs
at monitoring
boreholes, key
spring receptors
at Waiono,
Uaimatabai and
Uaisa.
Interpretation of
data every 6
months.
Environmental
Report to
NDCPEI
Groundwater Decrease in flows
in springs
Changes in water
quality of springs
Detailed
hydrological study
to establish
baseline
groundwater
Construction
Contractor
During
construction
Throughout
project site
Incl. in
construction
contract cost
Water quality and
quantity
measurements at key
spring receptors at
Uaimatabai, Uaisa and
Monthly water
quality and
quantity
measurements
TL Cement -
Collation of
results into
Annual
Environmental
Page 131 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Construction Stage
Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
monitoring
network including
boreholes, spring
flow gauging and
water quality
analysis
Groundwater
modelling of
Water Supply
borehole to
quantify
drawdown impacts
Uaino.
Reporting and
interpretation of
data quarterly
Report to
NDCPEI
Coastal and
Marine
Pollution of sea
water
Increase in
turbidity of sea
Control of spills
and discharge of
material or fuels to
the beach or
marine
Construction
Contractor
During
construction
Throughout
project site and
in local marine
environment
Incl. in
construction
contract cost
Sedimentation effects. Monitoring
should be
undertaken at a
frequency to be
determined
TL Cement -
Collation of
results into
Annual
Environmental
Page 132 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Construction Stage
Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
water
Spread of marine
pests from ships
environment;
Contouring and
movement of
vehicles on the
beach to minimize
scour and erosion;
Vessel approach to
minimize discharge
of ballast and
spread of marine
pests; and
Storage of
construction
materials to
minimize
disturbance of
once the
sediment
transport
associated with
the MOF has
been quantified;
and Jetty
construction has
been completed.
Report to
NDCPEI
Page 133 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Construction Stage
Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
beach processes.
Flora Removal of
threatened plants
Dust suppression
measures (e.g.
water sprinkling)
at all dust
generating sites
Weed
management
activities including
spraying
Construction
Contractor
During
excavation and
construction
Throughout
project site
Incl. in
construction
contract cost
The total area of
vegetation cleared
(habitat destruction)
at the end of phase
End of phase TL Cement -
Collation of
results into
Annual
Environmental
Report to
NDCPEI
Fauna Removal of
threatened
animals
Site clearing to be
conducted
sequentially and
from one corner of
the site to the
other, enabling
Construction
Contractor
During
construction
Throughout
project site
Incl. in
construction
contract cost
All fauna injury and
death records.
Reporting and
interpretation
every six months
TL Cement -
Collation of
results into
Annual
Environmental
Report to
Page 134 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Construction Stage
Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
highly mobile
fauna species to
leave the
construction area
NDCPEI
Marine fauna
(including
fisheries)
Loss of fishing
habitat and coral
reefs
Collection of
additional baseline
environmental
data including
large marine
mammal, turtle
nesting, seagrass
and crocodile
habitat.
Construction
Contractor
During
construction and
planning
(scheduling).
Limit shipping
movements
during mammal
migration.
Throughout
project site ,in
particular at the
jetty and MOF
and in wider
area as required
in case of spills
Incl. in
construction
contract cost
Regular community
engagement surveys
around fisheries
Survey of coral health,
sedimentation and
fisheries.
Collection of water
quality measurements
at reference and
impact sites to be
sited within and
adjacent to the project
Annual review
and reporting of
coral habitats
around Jetty and
MOR.
Water Quality
measurements
are to be taken
at least twice
per calendar
year, outside of
and during the
monsoon season
TL Cement -
Collation of
results into
Annual
Environmental
Report to
NDCPEI
Page 135 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Construction Stage
Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
impact area.
Marine
Habitats
(including
Coral)
Loss of fishing
habitat and coral
reefs
Ballast water
management and
Introduced Marine
Pests monitoring
and controls;
Identification of
coral locations on
engineering
drawings and
construction plans;
Identification of
impact zone sites,
nearby sites and
reference
Construction
Contractor
Pre-construction
planning and
during
construction
In marine
environment
bordering
project site and
within project
area
Incl. in
construction
contract cost
Undertake a post-
construction survey of
the identified sites to
compare the coral
health to the
reference imagery and
GPS database.
Reporting and
recording of post-
construction coral
health monitoring
data.
Make
recommendations on
One post
construction
survey.
Frequency of
monitoring
based on results
TL Cement -
Collation of
results into
Annual
Environmental
Report to
NDCPEI
Page 136 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Construction Stage
Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
(background) sites
for the coral health
monitoring
program.
the frequency of
operations coral
health surveys.
Traffic Increase in amount
of traffic on the
roads
Planning to
minimize vehicle
movements (e.g.
use of buses to
transport workers
and house in
camps)
Limit reversing
requirements
Traffic signage
implementation
Construction
Contractor /
Mine Operator
During planning
prior to
construction and
during
construction
Throughout
project site and
on local road
networks
Incl. in
construction
contract cost
Traffic incidents and
mitigation measures
implemented
Update Safety
Management
System to
record and
document traffic
incidents and
mitigation
measures
implemented as
and when they
occur
Construction
Contractor /
Mine Operator
Costs to
Construction
Contractor /
Mine
Operator
Page 137 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Construction Stage
Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
Speed limits and
enforcement
Road widening
Infrastructur
e
Increased pressure
on existing
infrastructure
Identify and
prioritize the
upgrades and
construction of
new infrastructure
required for the
construction and
operation of the
Project (e.g. water
treatment and
wastewater
facilities; roads
and
TL Cement Update
priorities for
upgrade if
required
Throughout
project site
Incl. in
construction
contract cost
Complaints and
Grievance records
review
Stakeholder
consultation to check
progress
Regular review
of Complaints
and Grievance
record
Regular
stakeholder
consultation
TL Cement
Page 138 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Construction Stage
Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
accommodation
facilities).
Ongoing
inspection,
monitoring and
maintenance
programmes will
be developed and
implemented for
the relevant
infrastructure
during the
operational phase
of the Project to
ensure optimal
operation.
Page 139 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Construction Stage
Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
Employment Training and
development of
local people
Selection and
management of
employee
applications by a
specialist
employee
management
institution formed
through a
consultative
process with sub-
district and suco
leadership
Construction
Contractor
During
construction
At Employee
Management
Institution
Offices
Incl. in
construction
contract cost
Complaints and
Grievance records
review
Stakeholder
consultation to check
progress
Regular review
of Complaints
and Grievance
record
Regular
stakeholder
consultation
TL Cement
Economic
Use of
Training and
development of
Minimise the
disturbance
TL Cement /
Construction
Stripping soil
and site
Throughout
project site
Incl. in
construction
Control of weed and
pathogen hygiene
NA TL Cement /
Construction
Page 140 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Construction Stage
Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
Forestry and
other Natural
Resources
local people footprint as far as
practicable.
Site clearing to be
conducted
sequentially.
Contractor clearing.
Stockpile topsoil
immediately
following
clearing.
Ongoing weed
control during
construction
contract cost practices Contractor
Fishing Decrease in people
who fish
Providing
alternative access
locations,
Providing safe
passage zones
across the
conveyor corridor
crossing the beach
between the Jetty
TL Cement /
Construction
Contractor
During
construction
Throughout
project site and
in wider area
(alternative
access
locations, safe
passage zones,
artificial reef
placement)
Incl. in
construction
contract cost
Fisheries assessment
is a component of the
Marine Habitats and
Coral monitoring
Per the
Grievance
mechanism
TL Cement
Manager
N/A
Page 141 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Construction Stage
Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
and the Plant sites;
and
Ensuring that the
timeline for
implementation of
access controls is
communicated to
the families who
are directly
impacted by the
access restrictions.
Good construction
measures that will
reduce impact on
fish stock such as
piling which does
not interfere with
Page 142 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Construction Stage
Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
the marine ecology
Implement
measures to
ensure coral
growth (artificial
reefs etc)
Socio
Economic
Agriculture
Relocation to an
area where people
can farm
The impact on
community access
to farmland during
the project will be
addressed by
resettlement and
compensation to
be undertaken by
the GoTL.
GoTL Access
established prior
to construction
and managed /
mantained as
required
As determined
by resettlement
facilitated by
GoTL
Incl. in
construction
contract cost
Control of weed and
pathogen hygiene
practices
Per the
Grievance
mechanism
TL Cement
Manager
N/A
Population Influx of new The impact on GoTL Prior to As determined Incl. in Complaints and Per the TL Cement N/A
Page 143 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Construction Stage
Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
and
Community
people to the area
from outside
Baucau
community during
the project will be
addressed by
resettlement and
compensation to
be undertaken by
the GoTL.
construction and
managed /
maintained as
required
by resettlement
facilitated by
GoTL
construction
contract cost
Grievance records
Grievance
mechanism
Manager
Community
Health
Increase in injury,
disease and
infections due to
more people in the
area
Facilitate
education and
awareness
programs
throughout the
lifespan of the
Project;
Design roads and
implement driver
training to improve
TL Cement Ongoing Throughout
project site and
in surrounding
area (secure
buffer zones)
Incl. in
construction
contract cost
Complaints and
Grievance records
Per the
Grievance
mechanism
TL Cement
Manager
N/A
Page 144 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Construction Stage
Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
traffic safety.
Internal Project
roads will be
designed and
constructed for all-
weather, 24 hr
capability.
Establish a secure
buffer zone from
activities posing
safety risks to
villages or
scattered
dwellings.
Develop an
employee wellness
Page 145 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Construction Stage
Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
programme
Institutions,
Schools and
Health
Facilities
No impact
anticipated
The impact on
community access
to institutions
during the project
will be addressed
by resettlement
and compensation
to be undertaken
by the GoTL. Refer
to Air Quality and
Noise and
vibration for
relevant mitigation
measures
GoTL / TL
Cement /
Construction
Contractor
Impact on
community
access
addressed prior
to construction.
Noise and
vibration
monitoring
ongoing
throughout
construction,
operation and
decommissionin
g phases
As determined
by resettlement
facilitated by
GoTL. Air and
Noise
monitoring at
selected
appropriate
locations and
near sensitive
receptors
Incl. in
construction
contract cost
Complaints and
Grievance records
Per the
Grievance
mechanism
TL Cement
Manager
N/A
Community
and Family
Relocation of
families may
Implementation of
the Complaints
TL Cement /
Mine Operator
Impact on
community
Throughout
project site and
Incl. in
construction
Complaints and
Grievance records
Per the
Grievance
TL Cement
Manager
N/A
Page 146 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Construction Stage
Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
Structure impact structure and Grievance
mechanism
addressed
construction but
complaints and
grievance
records to be
maintained
throughout
project
wider area as
required
contract cost
mechanism
Land
ownership
and Land
Rights
Relocation of land
users will not
impact land rights
TL Cement is
currently working
with the
Directorate of
Land, Property and
Cadastral Services
(DLPCS) to map
affected
households,
GoTL / TL
Cement
Ongoing Affected
households and
property
owners
Incl. in
construction
contract cost
Complaints and
Grievance records
Regular review
of records
To be addressed
by resettlement
and
compensation
to be addressed
by GoTL
Page 147 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Construction Stage
Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
farmland, and
other property.
Once TL Cement
has secured the
mining license and
environmental
licenses required
for the Project, the
GoTL will enter
into discussions
with those
affected
households and
property owners.
Natural
Resources
Rights
Relocation of land
users will not
impact resources
Implementation of
the Complaints
and Grievance
TL Cement /
GoTL
Ongoing Throughout
project site and
surrounding
Incl. in
construction
contract cost
Complaints and
Grievance records
Regular review
of records
To be addressed
by resettlement
and
Page 148 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Construction Stage
Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
rights mechanism
environment, in
particular at
identified
natural
resources
within and near
the project site
compensation
to be addressed
by GoTL
Cultural
Heritage,
Archaelogical
and Sacred
Sites
Relocation of land
users will not
cultural heritage
sites
Where safe access
cannot be
guaranteed, those
sites which are
located adjacent to
the project should
be fenced off,
access restricted
for the project life
or relocated.
Construction
Contractor
Prior to
construction for
planning and
design of
project, sites to
be fenced and
protected
throughout life
of project
Heritage sites
identified
through the EIA
as well as any
additional sites
discovered
during
construction,
operation or
decommissionin
Incl. in
construction
contract cost
Any and all
occurrences of
damage sites is to be
recorded.
Records to be
reviewed every
6 months.
TL Cement.
Process
improvements
are to be
implemented
where there has
been
unauthorised
impact on
cultural heritage
Page 149 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Construction Stage
Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
g phase sites
Page 150 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Operations
Activity : Vehicle movement, operating the jetty, conveyor belt and cement plant, operating the power plant, people moving and working on site, ships moving to/from the jetty, cement transport to/from Baucau
Environmental
Concern
Potential
Impact
Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
Climate Atmospheric
emissions (i.e.
carbon
monoxide)
increase from
use of vehicles
TL Cement During operation Throughout
project site and
on local road
networks
Incl. in
Operations
contract cost
Automated Weather
Station (AWS)
recording
measurements of:
Station identification
number;
Date and time of
record/observation;
Air, wet bulb and wet
dew point
temperatures.
Precipitation and
evaporation;
Relative humidity;
Daily
measurements
TL Cement
Annual
reporting for all
project phases
of Greenhouse
Gas emissions in
accordance with
National
Greenhouse and
Energy
Reporting Act
2007.
$500,000 for
Automated
Weather
station
Monitoring
Costs $580k
Page 151 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Operations
Activity : Vehicle movement, operating the jetty, conveyor belt and cement plant, operating the power plant, people moving and working on site, ships moving to/from the jetty, cement transport to/from Baucau
Environmental
Concern
Potential
Impact
Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
Wind speed and
direction;
Solar radiation;
Barometric pressure ;
Visibility;
Cloud cover; and
Cloud ceiling height, if
practicable.
Topography,
Geology and Soils
Changes to
topography
and increase
in soil erosion
Soil
contamination
should be
monitored
through
maintaining
TL Cement During operation Throughout
project site and
surrounding
area
Incl. in
Operations
contract cost
Water quality and
quantity
measurements at key
spring receptors,
Uaino, and in the
Water Reserve area.
Monthly
measurements.
Reporting and
interpretation of
data every 6
months.
Page 152 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Operations
Activity : Vehicle movement, operating the jetty, conveyor belt and cement plant, operating the power plant, people moving and working on site, ships moving to/from the jetty, cement transport to/from Baucau
Environmental
Concern
Potential
Impact
Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
records of spill
events
Contouring and
establishing
drainage
systems during
pre-construction
phase
Air Quality Increase in
levels of dust
All raw materials
storage will be
in enclosed
structures
All materials
transport will be
by fully covered
conveyor belts
TL Cement During operation Throughout
project site
Incl. in
Operations
contract cost
A monitoring and
reporting program
implemented to
monitor the air quality
in the following
sensitive receptors:
• AQ4 -
settlement area in
Once every six
months during
construction and
operation
TL Cement: The
monitoring
stations are
derived from
the BBS
Baseline Air
Quality
monitoring
survey (BBS,
Page 153 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Operations
Activity : Vehicle movement, operating the jetty, conveyor belt and cement plant, operating the power plant, people moving and working on site, ships moving to/from the jetty, cement transport to/from Baucau
Environmental
Concern
Potential
Impact
Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
Dust and bag
filters will be
installed at all
critical
emissions
hoppers
All areas with
vehicle traffic
shall be watered
or have dust
palliative
applied as
necessary for
regular
stabilization of
dust emissions.
Aldeia Osso-ua.
• AQ5 -
representing the
construction area.
The monitoring
program should assess
and report on the
following air quality
parameters:
• PM10; and
PM2.5
• CO
• NO2
• SO2; and
2015b).
Page 154 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Operations
Activity : Vehicle movement, operating the jetty, conveyor belt and cement plant, operating the power plant, people moving and working on site, ships moving to/from the jetty, cement transport to/from Baucau
Environmental
Concern
Potential
Impact
Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
All on-site
vehicle traffic
shall be limited
to a speed of 15
mph on unpaved
roads.
No vehicles or
plant will be left
idling
unnecessarily.
Reduce the
number of
vehicle
movements
through better
planning.
• Ozone.
Page 155 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Operations
Activity : Vehicle movement, operating the jetty, conveyor belt and cement plant, operating the power plant, people moving and working on site, ships moving to/from the jetty, cement transport to/from Baucau
Environmental
Concern
Potential
Impact
Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
Set an
appropriate
speed limit on
haul routes.
All heavy duty
vehicles should
meet certain
emission
regulation from
local
Environmental
Protection
Agency.
Use a good
quality of fuel
(e.g. with low
Page 156 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Operations
Activity : Vehicle movement, operating the jetty, conveyor belt and cement plant, operating the power plant, people moving and working on site, ships moving to/from the jetty, cement transport to/from Baucau
Environmental
Concern
Potential
Impact
Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
sulphur
content).
Engines and
exhaust systems
should be
regularly
serviced
according to
manufacturer’s
recommendatio
ns and
maintained to
meet statutory
limits/opacity
tests.
Ensure correct
working
Page 157 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Operations
Activity : Vehicle movement, operating the jetty, conveyor belt and cement plant, operating the power plant, people moving and working on site, ships moving to/from the jetty, cement transport to/from Baucau
Environmental
Concern
Potential
Impact
Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
methods are
employed for
the Project.
Noise and
Vibration
Increase in
levels of noise
Haulage of
goods and
movement of
vehicles/people
and equipment
can be
scheduled.
Where required,
noise barriers
can be
constructed to
abate the noise
impacts.
TL Cement During operation Throughout
project site and
in particular in
the vicinity of
sensitive
receptors.
Local road
networks
Incl. in
Operations
contract cost
At sensitive receptors
(as per construction)
Once per year
measurements
Results
interpretation
and review of
the EMP as
required.
Collation of
results into
Annual
Environmental
Report to
NDCPEI
Page 158 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Operations
Activity : Vehicle movement, operating the jetty, conveyor belt and cement plant, operating the power plant, people moving and working on site, ships moving to/from the jetty, cement transport to/from Baucau
Environmental
Concern
Potential
Impact
Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
Alternative
construction
methods and
selection of less
noisy equipment
to do the tasks.
Surface Water Decrease in
flows in
streams
Changes in
water quality
of streamflow
Drains down-
gradient from
the site to
capture
potentially
contaminated
surface water
run-off.
Storm water
design will be
TL Cement During operation Throughout
project site and
drains down
gradient of site
Incl. in
Operations
contract cost
Flow meters / stream
gauges at the Bucoli
River (1.6km west)
and at Uaimatabai,
Uaisa and Waino
springs
Monthly water
quality and
quantity
measurements
at monitoring
boreholes, key
spring receptors
at Waiono,
Uaimatabai and
Uaisa.
TL Cement -
Collation of
results into
Annual
Environmental
Report to
NDCPEI
$1.4M
Page 159 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Operations
Activity : Vehicle movement, operating the jetty, conveyor belt and cement plant, operating the power plant, people moving and working on site, ships moving to/from the jetty, cement transport to/from Baucau
Environmental
Concern
Potential
Impact
Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
incorporated to
manage extreme
weather events
Monitoring of
surface water
features for
water quality
impacts.
Spills
management
and pollution
control through
the Emergency
Plan.
Interpretation of
data every 6
months.
Groundwater Decrease in
flows in
springs
Detailed
hydrological
study to
TL Cement During operation Throughout
project site
Incl. in
Operations
contract cost
Flow meters / stream
gauges at the Bucoli
River (1.6km west)
Monthly water
quality and
quantity
TL Cement -
Collation of
results into
$1.4M
Page 160 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Operations
Activity : Vehicle movement, operating the jetty, conveyor belt and cement plant, operating the power plant, people moving and working on site, ships moving to/from the jetty, cement transport to/from Baucau
Environmental
Concern
Potential
Impact
Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
Changes in
water quality
of springs
establish
baseline
groundwater
monitoring
network
including
boreholes,
spring flow
gauging and
water quality
analysis
Groundwater
modelling of
Water Supply
borehole to
quantify
drawdown
and at Uaimatabai,
Uaisa and Waino
springs
measurements
at monitoring
boreholes, key
spring receptors
at Waiono,
Uaimatabai and
Uaisa.
Interpretation of
data every 6
months.
Annual
Environmental
Report to
NDCPEI
Page 161 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Operations
Activity : Vehicle movement, operating the jetty, conveyor belt and cement plant, operating the power plant, people moving and working on site, ships moving to/from the jetty, cement transport to/from Baucau
Environmental
Concern
Potential
Impact
Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
impacts
Design for
handling and
storage of
potential
contaminants
(including fuels
and chemicals)
to eliminate risk
Coastal and
Marine
Pollution of
sea water
Increase in
turbidity of
sea water
Spread of
marine pests
Control of spills
and discharge of
material or fuels
to the beach or
marine
environment;
Vessel approach
TL Cement During operation Throughout
project site and
in local marine
environment
Incl. in
Operations
contract cost
Sedimentation effects Should be
monitored at a
frequency to be
determined
once the
sediment
transport
associated with
TL Cement -
Collation of
results into
Annual
Environmental
Report to
NDCPEI
$1.4M
Page 162 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Operations
Activity : Vehicle movement, operating the jetty, conveyor belt and cement plant, operating the power plant, people moving and working on site, ships moving to/from the jetty, cement transport to/from Baucau
Environmental
Concern
Potential
Impact
Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
from ships to minimize
discharge of
ballast and
spread of
marine pests
the MOF has
been quantified;
and Jetty
construction has
been completed.
Flora Removal of
threatened
plants
Dust
suppression
measures (e.g.
water sprinkling)
at all dust
generating sites
Weed
management
activities
including
TL Cement Ongoing Throughout
project site
Incl. in
Operations
contract cost
The total area of
vegetation cleared
(habitat destruction)
at the end of phase
End of phase TL Cement -
Collation of
results into
Annual
Environmental
Report to
NDCPEI
Page 163 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Operations
Activity : Vehicle movement, operating the jetty, conveyor belt and cement plant, operating the power plant, people moving and working on site, ships moving to/from the jetty, cement transport to/from Baucau
Environmental
Concern
Potential
Impact
Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
spraying
Fauna Removal of
threatened
animals
Vehicles obey
speed limits.
TL Cement Ongoing Throughout and
surrounding
project site
Incl. in
Operations
contract cost
All fauna injury and
death records.
Reporting and
interpretation
every six months
TL Cement -
Collation of
results into
Annual
Environmental
Report to
NDCPEI
Marine Fauna
(including
fisheries)
Loss of fishing
habitat and
coral reefs
Identification of
water quality
reference and
impact sites to
be sited within
and adjacent to
the project
impact area.
TL Cement During operation.
Limit shipping
during mammal
migration
Throughout
project site ,in
particular at the
jetty and MOF
and in wider
area as required
in case of spills
Incl. in
Operations
contract cost
Regular community
engagement surveys
around fisheries
Survey of coral health,
sedimentation and
fisheries.
Collection of water
quality measurements
Annual review
and reporting of
coral habitats
around Jetty and
MOR.
Water Quality
measurements
are to be taken
TL Cement -
Collation of
results into
Annual
Environmental
Report to
NDCPEI
Page 164 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Operations
Activity : Vehicle movement, operating the jetty, conveyor belt and cement plant, operating the power plant, people moving and working on site, ships moving to/from the jetty, cement transport to/from Baucau
Environmental
Concern
Potential
Impact
Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
at reference and
impact sites to be
sited within and
adjacent to the project
impact area.
at least twice
per calendar
year, outside of
and during the
monsoon
season.
Marine habitats
(including coral)
Loss of fishing
habitat and
coral reefs
Ballast water
management
and Introduced
Marine Pests
monitoring and
controls;
Identification of
impact zone
sites, nearby
TL Cement During operation In marine
environment
bordering
project site and
within project
area
Incl. in
Operations
contract cost
Compare the coral
health to the
reference imagery and
GPS database
Undertake
regular,
scheduled
surveys of the
identified sites.
The frequency
(e.g. 1x per year)
should be
confirmed
during the
TL Cement -
Collation of
results into
Annual
Environmental
Report to
NDCPEI
Page 165 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Operations
Activity : Vehicle movement, operating the jetty, conveyor belt and cement plant, operating the power plant, people moving and working on site, ships moving to/from the jetty, cement transport to/from Baucau
Environmental
Concern
Potential
Impact
Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
sites and
reference
(background)
sites for the
coral health
monitoring
program.
Construction
phase.
Traffic Increase in
amount of
traffic on the
roads
Planning to
minimize vehicle
movements (e.g.
use of buses to
transport
workers and
house in camps)
Limit reversing
requirements
Traffic signage
TL Cement Throughout life of
project
Throughout
project site and
on local road
networks
Incl. in
Operations
contract cost
Traffic incidents and
mitigation measures
implemented
Update Safety
Management
System to
record and
document traffic
incidents and
mitigation
measures
implemented as
and when they
Construction
Contractor /
Mine Operator
Costs to
Construction
Contractor /
Mine
Operator
Page 166 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Operations
Activity : Vehicle movement, operating the jetty, conveyor belt and cement plant, operating the power plant, people moving and working on site, ships moving to/from the jetty, cement transport to/from Baucau
Environmental
Concern
Potential
Impact
Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
implementation
Speed limits and
enforcement
Road widening
occur.
Infrastructure Increased
pressure on
existing
infrastructure
Ongoing
inspection,
monitoring and
maintenance
programmes will
be developed
and
implemented for
the relevant
infrastructure
during the
TL Cement Ongoing Throughout
project site
Incl. in
Operations
contract cost
Complaints and
Grievance records
review
Stakeholder
consultation to check
progress
Regular review
of Complaints
and Grievance
record
Regular
stakeholder
consultation
TL Cement
Page 167 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Operations
Activity : Vehicle movement, operating the jetty, conveyor belt and cement plant, operating the power plant, people moving and working on site, ships moving to/from the jetty, cement transport to/from Baucau
Environmental
Concern
Potential
Impact
Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
operational
phase of the
Project to
ensure optimal
operation.
Employment Training and
development
of local
people
Selection and
management of
employee
applications by a
specialist
employee
management
institution
formed through
a consultative
process with
TL Cement Ongoing as
required
Selected
Employment
Management
Institution
Offices
Incl. in
Operations
contract cost
Complaints and
Grievance records
review
Stakeholder
consultation to check
progress
Regular review
of Complaints
and Grievance
record
Regular
stakeholder
consultation
TL Cement
Page 168 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Operations
Activity : Vehicle movement, operating the jetty, conveyor belt and cement plant, operating the power plant, people moving and working on site, ships moving to/from the jetty, cement transport to/from Baucau
Environmental
Concern
Potential
Impact
Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
sub-district and
suco leadership
Economic Use of
Forestry and
other Natural
Resources
Training and
development
of local
people
Minimise the
disturbance
footprint as far
as practicable.
Site clearing to
be conducted
sequentially.
TL Cement Ongoing Throughout
project site and
surrounding
area
Incl. in
Operations
contract cost
Control of weed and
pathogen hygiene
practices
NA TL Cement
Fishing Decrease in
people who
fish
Providing
alternative
access locations,
Providing safe
TL Cement Ongoing Throughout
wider region
Incl. in
Operations
contract cost
Fisheries assessment
is a component of the
Marine Habitats and
Coral monitoring
NA NA
Page 169 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Operations
Activity : Vehicle movement, operating the jetty, conveyor belt and cement plant, operating the power plant, people moving and working on site, ships moving to/from the jetty, cement transport to/from Baucau
Environmental
Concern
Potential
Impact
Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
passage zones
across the
conveyor
corridor crossing
the beach
between the
Jetty and the
Plant sites; and
Ensuring that
the timeline for
implementation
of access
controls is
communicated
to the families
who are directly
impacted by the
Page 170 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Operations
Activity : Vehicle movement, operating the jetty, conveyor belt and cement plant, operating the power plant, people moving and working on site, ships moving to/from the jetty, cement transport to/from Baucau
Environmental
Concern
Potential
Impact
Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
access
restrictions.
Good
construction
measures that
will reduce
impact on fish
stock such as
piling which
does not
interfere with
the marine
ecology
Implement
measures to
ensure coral
growth (artificial
Page 171 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Operations
Activity : Vehicle movement, operating the jetty, conveyor belt and cement plant, operating the power plant, people moving and working on site, ships moving to/from the jetty, cement transport to/from Baucau
Environmental
Concern
Potential
Impact
Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
reefs etc)
Socio Economic
Agriculture
Relocation to
an area where
people can
farm
The impact on
community
access to
farmland during
the project will
be addressed by
resettlement
and
compensation to
be undertaken
by the GoTL.
TL Cement At completion of
operation
Throughout
wider region
Incl. in
Operations
contract cost
Control of weed and
pathogen hygiene
practices
Population and
Community
Influx of new
people to the
area from
outside
Baucau
The impact on
community
during the
project will be
addressed by
GoTL Impact on
community
addressed
construction but
complaints and
Incl. in
Operations
contract cost
Complaints and
Grievance records
Regular review
of records
Page 172 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Operations
Activity : Vehicle movement, operating the jetty, conveyor belt and cement plant, operating the power plant, people moving and working on site, ships moving to/from the jetty, cement transport to/from Baucau
Environmental
Concern
Potential
Impact
Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
resettlement
and
compensation to
be undertaken
by the GoTL.
grievance records
to be maintained
throughout
project
Community
Health
Increase in
injury, disease
and infections
due to more
people in the
area
Facilitate
education and
awareness
programs
throughout the
lifespan of the
Project;
Design roads
and implement
driver training to
improve traffic
safety.
TL Cement Impact on
community
addressed
construction but
complaints and
grievance records
to be maintained
throughout
project
Incl. in
Operations
contract cost
Complaints and
Grievance records
Regular review
of records
Page 173 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Operations
Activity : Vehicle movement, operating the jetty, conveyor belt and cement plant, operating the power plant, people moving and working on site, ships moving to/from the jetty, cement transport to/from Baucau
Environmental
Concern
Potential
Impact
Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
Internal Project
roads will be
designed and
constructed for
all-weather, 24
hr capability.
Establish a
secure buffer
zone from
activities posing
safety risks to
villages or
scattered
dwellings.
Develop an
employee
Page 174 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Operations
Activity : Vehicle movement, operating the jetty, conveyor belt and cement plant, operating the power plant, people moving and working on site, ships moving to/from the jetty, cement transport to/from Baucau
Environmental
Concern
Potential
Impact
Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
wellness
programme
Institutions,
Schools and
Health Facilities
No impact
anticipated
The impact on
community
access to
institutions
during the
project will be
addressed by
resettlement
and
compensation to
be undertaken
by the GoTL.
Refer to Air
Quality and
Noise and
GoTL Impact on
community
addressed
construction but
complaints and
grievance records
to be maintained
throughout
project
Throughout
local region
Incl. in
Operations
contract cost
Complaints and
Grievance records
Regular review
of records
Page 175 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Operations
Activity : Vehicle movement, operating the jetty, conveyor belt and cement plant, operating the power plant, people moving and working on site, ships moving to/from the jetty, cement transport to/from Baucau
Environmental
Concern
Potential
Impact
Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
vibration for
relevant
mitigation
measures
Community and
Family Structure
Transient
workers
families may
impact family
structures
Implementation
of the
Complaints and
Grievance
mechanism
TL Cement Impact on
community
addressed
construction but
complaints and
grievance records
to be maintained
throughout
project
Throughout
local region
Incl. in
Operations
contract cost
Complaints and
Grievance records
Regular review
of records
Land ownership
and Land Rights
No impact
during
operations
Complaints and
Grievance records
Regular review
of records
Page 176 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Operations
Activity : Vehicle movement, operating the jetty, conveyor belt and cement plant, operating the power plant, people moving and working on site, ships moving to/from the jetty, cement transport to/from Baucau
Environmental
Concern
Potential
Impact
Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
Natural Resources
Rights
No impact
during
operations
Cultural Heritage,
Archaeological
and Sacred Sites
No impact
during
operations
Page 177 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Decommissioning Stage
Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
Climate Atmospheric
emissions (i.e.
carbon monoxide)
increase from use
of vehicles
Select equipment
with lowest
practical
emissions.
TL Cement /
Decommissionin
g Contractor
During
decommissionin
g
Throughout
project site and
on local road
networks
Incl. in
Decommissionin
g contract cost
Maintain Automated
Weather Station
(AWS) per Operations
Phase
Daily
measurements.
TL Cement -
Annual
reporting for all
project phases
of Greenhouse
Gas emissions in
accordance with
National
Greenhouse and
Energy
Reporting Act
2007.
Page 178 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Decommissioning Stage
Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
Topography,
Geology and
Soils
Changes to
topography and
increase in soil
erosion
Soil contamination
should be
monitored through
maintaining
records of spill
events
Contouring and
establishing
drainage systems
during
decommissioning
phase
TL Cement /
Decommissionin
g Contractor
During
decommissionin
g
Throughout
project site
Incl. in
Decommissionin
g contract cost
Post closure
assessment of
rehabilitation success
and soil health
5 years after
closure
Page 179 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Decommissioning Stage
Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
Air Quality Increase in levels
of dust
All raw materials
storage will be in
enclosed
structures
All materials
transport will be
by fully covered
conveyor belts
Dust and bag
filters will be
installed at all
critical emissions
hoppers
All areas with
vehicle traffic shall
be watered or
have dust
palliative applied
as necessary for
regular
stabilization of
TL Cement /
Decommissionin
g Contractor
During
decommissionin
g, in particular
during
excavation,
stockpiling and
grading of
materials.
Throughout
project site
Incl. in
Decommissionin
g contract cost
Install Automated
Weather Station
(AWS) recording daily
measurements of:
Station identification
number;
Date and time of
record/observation;
Air, wet bulb and wet
dew point
temperatures.
Precipitation and
evaporation;
Relative humidity;
Wind speed and
direction;
Solar radiation;
Barometric pressure ;
Daily
measurements
TL Cement -
Annual
reporting for all
project phases
of Greenhouse
Gas emissions in
accordance with
National
Greenhouse and
Energy
Reporting Act
2007.
Page 180 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Decommissioning Stage
Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
Noise and
Vibration
Increase in levels
of noise
Storage areas
should be located
away from
sensitive
receptors.
Haulage of goods
and movement of
vehicles/people
and equipment
can be scheduled.
Where required,
noise barriers can
be constructed to
abate the noise
impacts.
Alternative
construction
methods and
selection of less
noisy equipment
TL Cement /
Decommissionin
g Contractor
During
decommissionin
g
Throughout
project site and
in particular in
the vicinity of
sensitive
receptors.
Local road
networks
Incl. in
Decommissionin
g contract cost
At sensitive receptors
(as per construction)
Once per year
measurements
Results
interpretation
and review of
the EMP as
required.
Collation of
results into
semi-annual
Environmental
Report to
NDCPEI
Page 181 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Decommissioning Stage
Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
Surface
Water
Decrease in flows
in streams
Changes in water
quality of
streamflow
Drains down-
gradient from the
site to capture
potentially
contaminated
surface water run-
off.
Storm water
design will be
incorporated to
manage extreme
weather events
Monitoring of
surface water
features for water
quality impacts.
Spills management
and pollution
control through
the Emergency
Plan.
TL Cement /
Decommissionin
g Contractor
During
decommissionin
g
Drains down
gradient of site.
Other measures
throughout
project site
Incl. in
Decommissionin
g contract cost
Flow meters / stream
gauges at the Bucoli
River (1.6km west)
and at Uaimatabai,
Uaisa and Waino
springs
Monthly water
quality and
quantity
measurements
at monitoring
boreholes, key
spring receptors
at Waiono,
Uaimatabai and
Uaisa.
Interpretation of
data every 6
months.
TL Cement -
Collation of
results into
Annual
Environmental
Report to
NDCPEI
Page 182 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Decommissioning Stage
Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
Groundwater Decrease in flows
in springs
Changes in water
quality of springs
Design for
handling and
storage of
potential
contaminants
(including fuels
and chemicals) to
eliminate risk
TL Cement /
Decommissionin
g Contractor
During
decommissionin
g
Throughout
project site
Incl. in
Decommissionin
g contract cost
NA NA NA NA
Page 183 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Decommissioning Stage
Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
Coastal and
Marine
Pollution of sea
water
Increase in
turbidity of sea
water
Spread of marine
pests from ships
Control of spills
and discharge of
material or fuels to
the beach or
marine
environment;
Contouring and
movement of
vehicles on the
beach to minimize
scour and erosion;
Vessel approach to
minimize discharge
of ballast and
spread of marine
pests; and
Storage of
decommissioning
materials to
minimize
disturbance of
TL Cement /
Decommissionin
g Contractor
During
decommissionin
g
Throughout
project site and
in local marine
environment
Incl. in
Decommissionin
g contract cost
Monitoring during the
decommissioning
period shall be limited
to surveying and
reporting on the final
post-decommissioning
beach and coastal
processes.
Where any structure
or deviation from the
pre-construction
landform is proposed
as the final footprint
post-
decommissioning, this
shall be modelled (not
costed)
NA TL Cement -
Collation of
results into
semi-annual
Environmental
Report to
NDCPEI
Page 184 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Decommissioning Stage
Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
Flora Growth and
spread of weeds
Dust suppression
measures (e.g.
water sprinkling)
at all dust
generating sites
Weed
management
activities including
spraying
TL Cement /
Decommissionin
g Contractor
During
decommissionin
g
Areas degraded
during the life
of the project.
Incl. in
Decommissionin
g contract cost
Monitoring and
reporting of flora
species abundance
and coverage
5 years after
mine closure
TL Cement -
Collation of
results into
semi-annual
Environmental
Report to
NDCPEI
Fauna Removal of
threatened
animals
Planting of habitat
mimicking natural
environment.
TL Cement /
Decommissionin
g Contractor
During
decommissionin
g
Areas degraded
during the life
of the project
Incl. in
Decommissionin
g contract cost
Monitoring and
reporting of fauna
species abundance
5 years after
mine closure
TL Cement -
Collation of
results into
semi-annual
Environmental
Report to
NDCPEI
Page 185 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Decommissioning Stage
Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
Marine
Fauna
(including
fisheries)
Loss of fishing
habitat and coral
reefs
Rehabilitation of
coral areas where
practical through
artificial reefs
TL Cement /
Decommissionin
g Contractor
During
decommissionin
g
Throughout
project site, in
particular in the
vicinity of the
jetty and MOF
Incl. in
Decommissionin
g contract cost
Post decommissioning
marine habitat survey
Within 5 years
post-closure
TL Cement -
Collation of
results into
semi-annual
Environmental
Report to
NDCPEI
Page 186 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Decommissioning Stage
Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
Marine
habitats
(including
coral)
Loss of fishing
habitat and coral
reefs
Ballast water
management and
Introduced Marine
Pests monitoring
and controls
TL Cement /
Decommissionin
g Contractor
During
decommissionin
g and post
decommissionin
g for habitat
survey
Throughout
project site, in
particular in the
vicinity of the
jetty and MOF.
Survey to be
undertaken at
identified sites.
Incl. in
Decommissionin
g contract cost
Undertake post-
decommissioning
survey of the
identified sites to
compare the coral
health to the
reference imagery and
GPS database.
Reporting and
recording of post-
decommissioning
coral health
monitoring data.
Single post
decommissionin
g survey unless
findings suggest
otherwise.
TL Cement -
Collation of
results into
semi-annual
Environmental
Report to
NDCPEI
Page 187 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Decommissioning Stage
Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
Traffic Increase in amount
of traffic on the
roads
Planning to
minimize vehicle
movements (e.g.
use of buses to
transport workers
and house in
camps)
Limit reversing
requirements
Traffic signage
implementation
Speed limits and
enforcement
TL Cement /
Decommissionin
g Contractor
During
decommissionin
g
Througout
project site and
on local road
networks
Incl. in
Decommissionin
g contract cost
Traffic incidents and
mitigation measures
implemented
Update Safety
Management
System to
record and
document traffic
incidents and
mitigation
measures
implemented as
and when they
occur.
Construction
Contractor /
Mine Operator
Costs to
Construction
Contractor /
Mine
Operator
Page 188 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Decommissioning Stage
Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
Infrastructur
e
Increased pressure
on existing
infrastructure
Ongoing
inspection,
monitoring and
maintenance
programmes will
be developed and
implemented for
the relevant
infrastructure
during the
decommissioning
phase
TL Cement Prior to
decommissionin
g
Throughout
project site and
wider area
Incl. in
Decommissionin
g contract cost
Complaints and
Grievance records
reviewed regularly
Regular Stakeholder
consultation to check
progress
Regular review
of Complaints
and Grievance
record
Regular
stakeholder
consultation
TL Cement N/A
Page 189 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Decommissioning Stage
Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
Employment Training and
development of
local people
Redeployment and
training
opportunities to
offset loss of
employment on
closure
TL Cement Prior to
decommissionin
g
Throughout
project site and
wider area
Incl. in
Decommissionin
g contract cost
Complaints and
Grievance records
review
Stakeholder
consultation to check
progress
Regular review
of Complaints
and Grievance
record
Regular
stakeholder
consultation
TL Cement
Economic
Use of
Forestry and
other Natural
Resources
Training and
development of
local people
Rehabilitation with
native species
TL Cement /
Decommissionin
g Contractor
Immediately
following
completion of
operation
Areas degraded
during life of
project
Incl. in
Decommissionin
g contract cost
The total area of re-
vegetation and the
species used for
rehabilitation should
be recorded and
monitored
For a period of 5
years following
decommissionin
g.
TL Cement /
Decommissionin
g Contractor
Page 190 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Decommissioning Stage
Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
Fishing Increase in people
who fish
Rehabilitation of
beach accesses
TL Cement /
Decommissionin
g Contractor
During
decommissionin
g
At all locations
impacted by
access
restrictions
Incl. in
Decommissionin
g contract cost
Fisheries assessment
is a component of the
Marine Habitats and
Coral monitoring
Regular review
of Complaints
and Grievance
record
Regular
stakeholder
consultation
TL Cement N/A
Page 191 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Decommissioning Stage
Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
Socio
Economic
Agriculture
Returning to the
area
The impact on
community access
to farmland during
the project will be
addressed by
resettlement and
compensation to
be undertaken by
the GoTL.
TL Cement /
Decommissionin
g Contractor
During
decommissionin
g
Areas degraded
during life of
project
Incl. in
Decommissionin
g contract cost
The total area of re-
vegetation and the
species used for
rehabilitation should
be recorded and
monitored
For a period of 5
years following
decommissionin
g.
Page 192 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Decommissioning Stage
Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
Population
and
Community
Influx of new
people to the area
from outside
Baucau
The impact on
community during
the project will be
addressed by
resettlement and
compensation to
be undertaken by
the GoTL.
GoTL Impact on
community
addressed
construction but
complaints and
grievance
records to be
maintained
throughout
project
As determined
by resettlement
facilitated by
GoTL
Incl. in
Decommissionin
g contract cost
Complaints and
Grievance records
Regular review
of records
Page 193 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Decommissioning Stage
Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
Community
Health
Increase in injury,
disease and
infections due to
more people in the
area
Facilitate
education and
awareness
programs
throughout the
lifespan of the
Project;
TL Cement Impact on
community
addressed
construction but
complaints and
grievance
records to be
maintained
throughout
project
Throughout
local region
Incl. in
Decommissionin
g contract cost
Complaints and
Grievance records
Regular review
of Complaints
and Grievance
record
Regular
stakeholder
consultation
TL Cement N/A
Page 194 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Decommissioning Stage
Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
Institutions,
Schools and
Health
Facilities
No impact
anticipated
The impact on
community access
to institutions
during the project
will be addressed
by resettlement
and compensation
to be undertaken
by the GoTL.
TL Cement /
Decommissionin
g Contractor
Prior to
decommissionin
g . Air quality
and noise
monitoring
during
decommissionin
g.
Throughout
local region
Incl. in
Decommissionin
g contract cost
Complaints and
Grievance records
Regular review
of Complaints
and Grievance
record
Regular
stakeholder
consultation
TL Cement N/A
Page 195 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Decommissioning Stage
Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
Community
and Family
Structure
Relocation of
families may
impact structure
Implementation of
the Complaints
and Grievance
mechanism
TL Cement Impact on
community
addressed
construction but
complaints and
grievance
records to be
maintained
throughout
project
Throughout
local region
Incl. in
Decommissionin
g contract cost
Complaints and
Grievance records
Regular review
of Complaints
and Grievance
record
Regular
stakeholder
consultation
TL Cement N/A
Land
ownership
and Land
Rights
Relocation of land
users will not
impact land rights
Implementation of
the Complaints
and Grievance
mechanism
TL Cement /
GoTL
Ongoing Affected
households and
property
owners
Incl. in
Decommissionin
g contract cost
Complaints and
Grievance records
Regular review
of records
To be addressed
by resettlement
and
compensation
to be addressed
by GoTL
Page 196 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Decommissioning Stage
Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
Natural
Resources
Rights
Relocation of land
users will not
impact resources
rights
Implementation of
the Complaints
and Grievance
mechanism
TL Cement /
GoTL
Ongoing Throughout
project site and
surrounding
environment, in
particular at
identified
natural
resources
within and near
the project site
Incl. in
Decommissionin
g contract cost
Complaints and
Grievance records
Regular review
of records
To be addressed
by resettlement
and
compensation
to be addressed
by GoTL
Page 197 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Decommissioning Stage
Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF
Environment
al Concern
Potential Impact Mitigation
Measures (MM)
Responsible to
implement MM
Timing to
implement MM
Locations of
MM
Mitigation Cost Parameter to Monitor Frequency and
Variation
Responsible to
Monitor
Cost of
Monitoring
Cultural
Heritage,
Archaeologic
al and Sacred
Sites
Relocation of land
users will not
cultural heritage
sites
TL Cement Prior to
construction and
ongoing
throughout
construction,
operation and
decommissionin
g
Heritage sites
identified
through the EIA
as well as any
additional sites
discovered
during
construction,
operation or
decommissionin
g phase
Incl. in
Decommissionin
g contract cost
Any and all
occurrences of
damage sites is to be
recorded.
Records to be
reviewed every
6 months.
TL Cement.
Process
improvements
are to be
implemented
where there has
been
unauthorised
impact on
cultural heritage
sites.
Page 198 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
9 GOVERNING PARAMETERS
9.1 Environmental Quality Standards
The monitoring plan has been developed taking into account the best available measurement standard for the relevant criteria. The standard is detailed in Section 9.3 (Governing Parameters) below, alongside the applicable parameter.
9.2 International Best Practice
Where possible, the monitoring plan has been developed utilizing internationally-recognized standards and emissions criteria. Standards used by the World Health Organization and the International Finance Corporation have been used as first priority, followed by standards used in Australia and elsewhere.
9.3 Governing parameters
9.3.1 Emissions
Emissions standards are determined based on the medium of transmission i.e. water or air and are detailed further under Sections 9.3.2 and 9.3.3.
9.3.2 Ambient Water Quality Standards
Parameter International best practice standard
Proposed limit value Comments
Fresh Water (Springs and streams)
e.Coli or Thermotolerant coliform bacteria
WHO Drinking Water Standards (2000)
0 mg/L in 100ml sample All water directly intended for drinking
Nitrate WHO Drinking Water Standards (2000)
50 mg/L All water directly intended for drinking
Nitrite WHO Drinking Water Standards (2000)
3 mg/L All water directly intended for drinking
Chlorine WHO Drinking Water Standards (2000)
5 mg/L All water directly intended for drinking
Page 199 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Parameter International best practice standard
Proposed limit value Comments
Copper WHO Drinking Water Standards (2000)
2 mg/L All water directly intended for drinking
Lead WHO Drinking Water Standards (2000)
0.01 mg/L All water directly intended for drinking
Nickel WHO Drinking Water Standards (2000)
0.07 mg/L All water directly intended for drinking
Manganese WHO Drinking Water Standards (2000)
0.4 mg/L All water directly intended for drinking
Marine Water
Salinity Australian Water Quality Guidelines for Fresh and Marine Waters (ANZECC, 1992)
<5% variation from background
Copper Australian Water Quality Guidelines for Fresh and Marine Waters (ANZECC, 1992)
4 µg/L Table 2.7 Guidelines for the protection of human consumers of fish and other aquatic organisms
Lead Australian Water Quality Guidelines for Fresh and Marine Waters (ANZECC, 1992)
1.3 µg/L Table 2.7 Guidelines for the protection of human consumers of fish and other aquatic organisms
Page 200 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
9.3.3 Ambient Air Quality Standards
Parameter International best practice standard Proposed interim target limit (µg/m3)
Carbon monoxide
International Ambient Air Quality Standards (IAAQS)
http://www3.epa.gov/ttn/naaqs/criteria.html
1 hour = 40,000 µg/m3
Not to be exceeded more than once per year
Nitrogen dioxide
International Ambient Air Quality Standards (IAAQS)
http://whqlibdoc.who.int/hq/2006/WHO_SDE_PHE_OEH_06.02_eng.pdf
1 hour = 200 µg/m3
Annual = 40 µg/m3
Photochemical oxidants (as ozone)
International Ambient Air Quality Standards (IAAQS)
1 hour = 235 µg/m3
Sulfur dioxide International Ambient Air Quality Standards (IAAQS)
1 hour = 350 µg/m3
24 hour = 125 µg/m3
Particles as PM2.5
International Ambient Air Quality Standards (IAAQS)
24 hour = 75 µg/m3
Annual = 70 µg/m3
9.3.4 Soil
All the parameters below are obtained from the National Environment Protection Measure (Assessment of Contamination) 1999 for the Groundwater Investigation Levels in Fresh Waters “Table 1C”. The measurement of soil contamination is typically taken from groundwater monitoring boreholes located down-gradient from the suspected contamination.
Parameter Proposed discharge limit value
µg/L
Aluminium 55 µgL
Chromium IV 1 µgL
Page 201 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Parameter Proposed discharge limit value
µg/L
Nickel 11 µgL
Benzene 950 µgL
Phenol 320 µgL
Lead 3.4 µgL
Manganese 1900 µgL
Mercury (total) 0.06 µgL
Zinc 8 µgL
Ammonia (NH3-N) 900 µgL
Ethanol 1400 µgL
Page 202 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
9.3.5 Occupational Health and Safety Standards
9.3.5.1 WORKPLACE NOISE AND VIBRATION
Parameter International best practice standard
Proposed discharge limit value
Comments
Blasting
(Airblast level)
Regulation 11
Environmental Protection (Noise) Regulations 1997
120 dBLz peak at sensitive receptor
125 dBLz peak at non sensitive receptor
Blasting carried out between 7am and 6pm on any day of the week
Noise and Vibration UNTAET, 2001
Residential, Institutional and Educational Receptors
50 – 55 dB(A)
9.3.5.2 DRINKING WATER
These standards are applicable for fresh water springs and streams.
Parameter International best practice standard
Proposed limit value
E.Coli or Thermotolerant coliform bacteria
WHO Drinking Water Standards (2000)
0 mg/L in 100ml sample
Nitrate WHO Drinking Water Standards (2000)
50 mg/L
Nitrite WHO Drinking Water Standards (2000)
3 mg/L
Chlorine WHO Drinking Water Standards (2000)
5 mg/L
Copper WHO Drinking Water Standards (2000)
2 mg/L
Page 203 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Parameter International best practice standard
Proposed limit value
Lead WHO Drinking Water Standards (2000)
0.01 mg/L
Nickel WHO Drinking Water Standards (2000)
0.07 mg/L
Manganese WHO Drinking Water Standards (2000)
0.4 mg/L
9.3.5.3 SAFETY MANAGEMENT
Safety Management shall be undertaken in accordance with local labour laws and regulations.
9.3.5.4 COMMUNICATIVE DISEASES
Data and statistics on Communicative diseases will be confidentially collected through surveying of the health providers to determine if adjustments to the Workplace Health and Safety Standard are required. Communicative diseases include:
Infection control in the workplace aims to prevent pathogens from coming into contact with a person in the first place. The basis of good infection control in the workplace is to assume that everyone is potentially infectious. Proper procedures have to be followed at all times.
Good marketing of personal hygiene is the first line of defense. Infection control procedures relating to good personal hygiene include:
• Hand washing; • Covering cuts or abrasions with a waterproof dressing; and • Gloves.
Many infections are food-borne. When preparing food, it is important to:
• Wash hands before and after handling food; • Keep hot food hot and cold food cold; • Use separate storage, utensils and preparation surfaces for cooked and uncooked foods; and • Wash all utensils and preparation surfaces thoroughly with hot water and detergent after use.
Frequently, workplace illnesses are spread by droplet infection. Colds and flu are transmitted in this way, and sharing telephones is an infection risk. If at all possible, users should have personal headsets, and telephones should be regularly cleaned and sterilized.
Page 204 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
9.4 Modelling or Engineering Calculations
Trigger values and monitoring upper limit guideline values have been based on published standard and guideline values and no modelling was undertaken to derive them.
Page 205 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
10 MONITORING PROGRAM
In designing the monitoring programme for each aspect identified in the EIS, this section details:
• the specific parameters; • monitoring protocols; • sampling locations and frequencies of monitoring; and • how compliance with implementation of the EMP and sub-EMPs will be checked and reported.
The above information has been presented in table format for each phase of the Project; i.e. Pre-construction; Construction; Operation; and Decommissioning.
10.1 Climate
Monitoring Programme : Climate
Pre-construction Construction Operations Decommissioning
Install Automated Weather Station (AWS) recording daily measurements of:
• Station identification number;
• State and time of record/observation;
• Air, wet bulb and wet dew point temperatures.
• Precipitation and evaporation;
• Relative humidity;
• Wind speed and direction;
• Solar radiation;
• Barometric pressure ;
• Visibility;
• Cloud cover; and
• Cloud ceiling height, if practicable.
Annual reporting for all project phases of Greenhouse Gas emissions in accordance with National Greenhouse and Energy Reporting Act 2007.
Page 206 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
10.2 Topography and Soil
Monitoring Programme : Topography, Geology and Soil
Pre-construction Construction Operations Decommissioning
Weed growth and drainage behaviour on the topsoil stockpile
Monthly water quality and quantity measurements at key spring receptors, Uaino, and in the Water Reserve area.
Reporting and interpretation of data every 6 months.
5 years post closure assessment of rehabilitation success and soil health
10.3 Air Quality
Monitoring Programme : Air Quality
Pre-construction Construction Operations Decommissioning
A monitoring and reporting program (once every six months during construction and operation) should be implemented to monitor the air quality in the following sensitive receptors:
• AQ4 - settlement area in Aldeia Osso-ua.
• AQ5 - representing the construction area.
The monitoring stations are derived from the BBS Baseline Air Quality monitoring survey (BBS, 2015b).
The monitoring program should assess and report on the following air quality parameters:
• PM10; and PM2.5
• CO
• NO2
• SO2; and
• Ozone.
Page 207 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
10.4 Noise and vibration
Monitoring Programme : Noise and Vibration
Pre-construction Construction Operations Decommissioning
Every 6 months measurements at sensitive receptors i.e.
1. AQ4 – Settlement area at Aldeia Osso-Ua 2. AQ5 - representing the construction area.
Results interpretation and review of the EMP as required.
Collation of results into semi-annual Environmental Report to NDCPEI
Once per year measurements at sensitive receptors (as per Construction)
Results interpretation and review of the EMP as required.
Collation of results into Annual Environmental Report to NDCPEI
Once per year measurements at sensitive receptors (as per Operations)
Results interpretation and review of the EMP as required.
Collation of results into semi-annual Environmental Report to NDCPEI
10.5 Surface water
Monitoring Programme : Surface Water
Pre-construction Construction Operations Decommissioning
Flow meters / stream gauges at the Bucoli River (1.6km west) and at Uaimatabai, Uaisa and Waino springs.
Monthly water quality and quantity measurements at monitoring boreholes, key spring receptors at Waiono, Uaimatabai and Uaisa.
Interpretation of data every 6 months.
Collation of results into Annual Environmental Report to NDCPEI
Page 208 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
10.6 Groundwater
Monitoring Programme : Surface Water
Pre-construction Construction Operations Decommissioning
Monthly water quality and quantity measurements at key spring receptors at Uaimatabai, Uaisa and Uaino.
Reporting and interpretation of data quarterly
Monthly water quality and quantity measurements at key spring receptors at Uaimatabai, Uaisa and Uaino.
Reporting and interpretation of data quarterly
Collation of results into Annual Environmental Report to NDCPEI
10.7 Coastal and Marine
Monitoring Programme : Coastal and Marine
Pre-construction Construction Operations Decommissioning
A sediment transport model should be developed in order to qualify the volume, duration and distribution of sediment and erosion/scour associated with the MOF and Jetty.
Collation of results into semi-annual Environmental Report to NDCPEI
Monitoring of sedimentation effects should be undertaken at a frequency to be determined once the sediment transport associated with the MOF has been quantified; and Jetty construction has been completed.
Collation of results into Annual Environmental Report to NDCPEI
Monitoring during the decommissioning period shall be limited to surveying and reporting on the final post-decommissioning beach and coastal processes.
Where any structure or deviation from the pre-construction landform is proposed as the final footprint post-decommissioning, this shall be modelled (not costed)
Collation of results into semi-annual Environmental Report to NDCPEI
Page 209 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
10.8 Flora
Monitoring Programme : Flora
Pre-construction Construction Operations Decommissioning
The total area of vegetation cleared (habitat destruction) at the end of phase
Collation of results into Annual Environmental Report to NDCPEI
Monitoring and reporting of flora species abundance and coverage 5 years after mine closure
Collation of results into semi-annual Environmental Report to NDCPEI
10.9 Fauna
Monitoring Programme : Fauna
Pre-construction Construction Operations Decommissioning
Any incidents of fauna injury and death should be recorded.
Collation of results into semi-annual Environmental Report to NDCPEI
Reporting and interpretation of fauna injury and death records every 6 months.
Collation of results into Annual Environmental Report to NDCPEI
Monitoring and reporting of fauna species abundance 5 years after mine closure
Collation of results into semi-annual Environmental Report to NDCPEI
10.10 Marine Fauna and Fisheries
Monitoring Programme : Marine Fauna incl. Fisheries
Pre-construction Construction Operations Decommissioning
Page 210 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Regular community engagement surveys around fisheries
Annual review and reporting of coral habitats around the Jetty and MOF with a survey of coral health, sedimentation and fisheries.
Collection of water quality measurements at reference and impact sites to be sited within and adjacent to the project impact area.
Measurements are to be taken at least twice per calendar year, outside of and during the monsoon season.
Collation of results into Annual Environmental Report to NDCPEI
Post decommissioning marine habitat survey within 5 years post-closure
Collation of results into semi-annual Environmental Report to NDCPEI
10.11 Marine habitats and corals
Monitoring Programme : Marine habitat and corals
Pre-construction Construction Operations Decommissioning
Undertake a pre-construction survey of the identified sites to develop the reference imagery and GPS database.
Reporting and recording of baseline coral health monitoring data.
Collation of results into semi-annual Environmental Report to NDCPEI
Undertake a post-construction survey of the identified sites to compare the coral health to the reference imagery and GPS database.
Reporting and recording of post-construction coral health monitoring data.
Make recommendations on the frequency of operations coral health surveys.
Collation of results into Annual Environmental Report to NDCPEI
Undertake regular, scheduled surveys of the identified sites to compare the coral health to the reference imagery and GPS database. The frequency (e.g. 1x per year) should be confirmed during the Construction phase.
Collation of results into Annual Environmental Report to NDCPEI
Undertake post-decommissioning survey of the identified sites to compare the coral health to the reference imagery and GPS database.
Reporting and recording of post-decommissioning coral health monitoring data.
Collation of results into semi-annual Environmental Report to NDCPEI
10.12 Traffic
Page 211 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Monitoring Programme : Traffic
Pre-construction Construction Operations Decommissioning
Safety Management System to record and document traffic incidents and mitigation measures implemented
10.13 Infrastructure
Monitoring Programme : Infrastructure
Pre-construction Construction Operations Decommissioning
Complaints and Grievance records reviewed regularly
Regular Stakeholder consultation to check progress
10.14 Employment
Monitoring Programme : Employment
Pre-construction Construction Operations Decommissioning
Complaints and Grievance records reviewed regularly
Regular Stakeholder consultation to check progress
10.15 Economic Use of Forestry and other Natural Resources
Monitoring Programme : Economic Use of Forestry and other Natural Resources
Pre-construction Construction Operations Decommissioning
The total area of vegetation cleared during the pre-construction and construction phase should be recorded.
Control of weed and pathogen hygiene practices The total area of re-vegetation and the species used for rehabilitation should be recorded and monitored for a period of 5 years following decommissioning.
Page 212 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
10.16 Fishing
Monitoring Programme : Fishing
Pre-construction Construction Operations Decommissioning
Fisheries assessment is a component of the Marine Habitats and Coral monitoring
10.17 Socio-Economic Agriculture
Monitoring Programme : Socio Economic Agriculture
Pre-construction Construction Operations Decommissioning
Complaints and Grievance records reviewed regularly
Control of weed and pathogen hygiene practices The total area of re-vegetation and the species used for rehabilitation should be recorded and monitored for a period of 5 years following decommissioning.
10.18 Population and community
Monitoring Programme : Population and Community
Pre-construction Construction Operations Decommissioning
Maintain communities and limit secondary impacts of population increase due to the Project
Complaints and Grievance records reviewed regularly
10.19 Community Health
Page 213 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Monitoring Programme : Community Health
Pre-construction Construction Operations Decommissioning
Complaints and Grievance records reviewed regularly
Page 214 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
10.20 Institutions schools and health facil ities
Monitoring Programme : Institutions, Schools and Health Facilities
Pre-construction Construction Operations Decommissioning
Complaints and Grievance records reviewed regularly
10.21 Community and Family Structure
Monitoring Programme : Community and Family Structure
Pre-construction Construction Operations Decommissioning
Complaints and Grievance records reviewed regularly
10.22 Land Ownership and Land Rights
Monitoring Programme : Land Ownership and Land Rights
Pre-construction Construction Operations Decommissioning
Complaints and Grievance records reviewed regularly
To be addressed by resettlement and compensation to be addressed by GoTL
10.23 Natural Resources Rights
Monitoring Programme : Natural Resources Rights
Pre-construction Construction Operations Decommissioning
Complaints and Grievance records reviewed regularly
To be addressed by resettlement and compensation to be addressed by GoTL
Page 215 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
10.24 Cultural Heritage Archeological and Sacred Sites
Monitoring Programme : Cultural Heritage, Archaeological and Sacred Sites
Pre-construction Construction Operations Decommissioning
Any and all occurrences of damage sites is to be recorded and the records to be reviewed every 6 months. Process improvements are to be implemented where there has been unauthorised impact on cultural heritage sites.
Page 216 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
10.25 Summary of monitoring program
Pre - Construction Environmental Concern Parameter to Monitor Frequency and Variation Climate Automated Weather Station (AWS) recording measurements of:
Station identification number; Date and time of record/observation; Air, wet bulb and wet dew point temperatures. Precipitation and evaporation; Relative humidity; Wind speed and direction; Solar radiation; Barometric pressure ; Visibility; Cloud cover; and Cloud ceiling height, if practicable.
Daily measurements for project life
Topography, Geology and Soils
Weed growth and drainage behaviour on the topsoil stockpile As required
Air Quality At sensitive receptors: AQ3 – At the Jetty AQ4 – Settlement area at Aldeia Osso-Ua AQ5 - representing the construction area.
Every 6 months measurements at sensitive receptors i.e. Results interpretation and review of the EMP as required. Collation of results into semi-annual Environmental Report to NDCPEI
Noise and Vibration At sensitive receptors: NO3 – At the Jetty NO4 – Settlement area at Aldeia Osso-Ua NO5 - representing the construction area.
Every 6 months measurements at sensitive receptors i.e. Results interpretation and review of the EMP as required. Collation of results into semi-annual Environmental Report to NDCPEI
Water Flow meters / stream gauges at the Bucoli River (1.6km west) and at Uaimatabai, Uaisa and Waino springs
Monthly water quality and quantity measurements at monitoring boreholes, key spring receptors at Waiono, Uaimatabai and Uaisa. Interpretation of data every 6 months.
Coastal and Marine A sediment transport model should be developed in order to qualify the volume, duration and distribution of sediment and erosion/scour associated with the MOF and Jetty.
Before construction commences
Flora The total area of vegetation cleared (habitat destruction) at the end of phase
TL Cement - Collation of results into Annual Environmental Report to NDCPEI
Fauna Any incidents of fauna injury and death should be recorded.
TL Cement - Collation of results into semi-annual Environmental Report to NDCPEI
Marine Fauna including fisheries
Regular community engagement surveys around fisheries Survey of coral health, sedimentation and fisheries. Collection of water quality measurements at reference and impact sites to be sited within and adjacent to the project impact area.
Annual review and reporting of coral habitats around Jetty and MOR. Water Quality measurements are to be taken at least twice per calendar year, outside of and during the monsoon season.
Marine habitats including coral
Undertake a pre-construction survey of the identified sites to develop the reference imagery and GPS database. Reporting and recording of baseline coral health monitoring data.
Pre construction survey
Page 217 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Traffic Traffic incidents and mitigation measures implemented Update Safety Management System to record and document traffic incidents and mitigation measures implemented as and when they occur.
Social Complaints and Grievance records review Stakeholder consultation to check progress
Regular review of Complaints and Grievance record Regular stakeholder consultation
Cultural Heritage, Archaelogical and Sacred Sites
Any and all occurrences of damage sites is to be recorded. Records to be reviewed every 6 months.
Construction Environmental Concern Parameter to Monitor Frequency and Variation Climate Automated Weather Station (AWS) recording measurements of:
Station identification number; Date and time of record/observation; Air, wet bulb and wet dew point temperatures. Precipitation and evaporation; Relative humidity; Wind speed and direction; Solar radiation; Barometric pressure ; Visibility; Cloud cover; and Cloud ceiling height, if practicable.
Daily measurements for project life
Air Quality A monitoring and reporting program implemented to monitor the air quality in the following sensitive receptors: • AQ4 - settlement area in Aldeia Osso-ua. • AQ5 - representing the construction area. The monitoring program should assess and report on the following air quality parameters: • PM10; and PM2.5 • CO • NO2 • SO2; and • Ozone.
Once every six months during construction
Noise and Vibration At sensitive receptors: AQ4 – Settlement area at Aldeia Osso-Ua AQ5 - representing the construction area.
Every 6 months measurements at sensitive receptors i.e. Results interpretation and review of the EMP as required. Collation of results into semi-annual Environmental Report to NDCPEI
Surface Water Flow meters / stream gauges at the Bucoli River (1.6km west) and at Uaimatabai, Uaisa and Waino springs
Monthly water quality and quantity measurements at monitoring boreholes, key spring receptors at Waiono, Uaimatabai and Uaisa. Interpretation of data every 6 months.
Groundwater Water quality and quantity measurements at key spring receptors at Uaimatabai, Uaisa and Uaino.
Monthly water quality and quantity measurements Reporting and interpretation of data quarterly
Coastal and Marine Sedimentation effects Monitoring should be undertaken at a frequency to be determined once the sediment transport associated with the MOF has been quantified; and Jetty construction has been completed.
Page 218 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Flora The total area of vegetation cleared (habitat destruction) at the end of phase
End of phase
Fauna All fauna injury and death records. Reporting and interpretation every six months Marine fauna (including fisheries)
Regular community engagement surveys around fisheries Survey of coral health, sedimentation and fisheries. Collection of water quality measurements at reference and impact sites to be sited within and adjacent to the project impact area.
Annual review and reporting of coral habitats around Jetty and MOR. Water Quality measurements are to be taken at least twice per calendar year, outside of and during the monsoon season
Marine Habitats (including Coral)
Undertake a post-construction survey of the identified sites to compare the coral health to the reference imagery and GPS database. Reporting and recording of post-construction coral health monitoring data. Make recommendations on the frequency of operations coral health surveys.
One post construction survey. Frequency of monitoring based on results
Traffic Traffic incidents and mitigation measures implemented Update Safety Management System to record and document traffic incidents and mitigation measures implemented as and when they occur
Social Complaints and Grievance records review Stakeholder consultation to check progress
Regular review of Complaints and Grievance record Regular stakeholder consultation
Cultural Heritage, Archaelogical and Sacred Sites
Any and all occurrences of damage sites is to be recorded. Records to be reviewed every 6 months.
Operations Climate Air Quality A monitoring and reporting program implemented to monitor the
air quality in the following sensitive receptors: • AQ4 - settlement area in Aldeia Osso-ua. • AQ5 - representing the construction area. The monitoring program should assess and report on the following air quality parameters: • PM10; and PM2.5 • CO • NO2 • SO2; and • Ozone.
Once every six months during construction and operation
Noise and Vibration At sensitive receptors (as per construction) Once per year measurements Results interpretation and review of the EMP as required. Collation of results into Annual Environmental Report to NDCPEI
Water Flow meters / stream gauges at the Bucoli River (1.6km west) and at Uaimatabai, Uaisa and Waino springs
Monthly water quality and quantity measurements at monitoring boreholes, key spring receptors at Waiono, Uaimatabai and Uaisa. Interpretation of data every 6 months.
Coastal and Marine Sedimentation effects Should be monitored at a frequency to be determined once the sediment transport associated with the MOF has been quantified; and Jetty construction has been completed.
Page 219 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Marine Fauna (including fisheries)
Regular community engagement surveys around fisheries Survey of coral health, sedimentation and fisheries. Collection of water quality measurements at reference and impact sites to be sited within and adjacent to the project impact area.
Annual review and reporting of coral habitats around Jetty and MOR. Water Quality measurements are to be taken at least twice per calendar year, outside of and during the monsoon season.
Marine habitats (including coral)
Compare the coral health to the reference imagery and GPS database
Undertake regular, scheduled surveys of the identified sites. The frequency (e.g. 1x per year) should be confirmed during the Construction phase.
Traffic Traffic incidents and mitigation measures implemented Update Safety Management System to record and document traffic incidents and mitigation measures implemented as and when they occur.
Social Complaints and Grievance records review Stakeholder consultation to check progress
Regular review of Complaints and Grievance record Regular stakeholder consultation
Cultural Heritage, Archaeological and Sacred Sites
Any and all occurrences of damage sites is to be recorded. Records to be reviewed every 6 months.
Decommissioning Topography, Geology and Soils
Post closure assessment of rehabilitation success and soil health 5 years after closure
Air Quality A monitoring and reporting program implemented to monitor the air quality in the following sensitive receptors: • AQ4 - settlement area in Aldeia Osso-ua. • AQ5 - representing the construction area. The monitoring program should assess and report on the following air quality parameters: • PM10; and PM2.5 • CO • NO2 • SO2; and • Ozone.
Once every six months
Noise and Vibration At sensitive receptors (as per construction) Once per year measurements Results interpretation and review of the EMP as required. Collation of results into semi-annual Environmental Report to NDCPEI
Water Flow meters / stream gauges at the Bucoli River (1.6km west) and at Uaimatabai, Uaisa and Waino springs
Monthly water quality and quantity measurements at monitoring boreholes, key spring receptors at Waiono, Uaimatabai and Uaisa. Interpretation of data every 6 months.
Coastal and Marine Monitoring during the decommissioning period shall be limited to surveying and reporting on the final post-decommissioning beach and coastal processes. Where any structure or deviation from the pre-construction landform is proposed as the final footprint post-decommissioning, this shall be modelled (not costed)
NA
Flora Monitoring and reporting of flora species abundance and coverage
5 years after mine closure
Fauna Monitoring and reporting of fauna species abundance 5 years after mine closure
Page 220 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Marine Fauna (including fisheries)
Post decommissioning marine habitat survey Within 5 years post-closure
Marine habitats (including coral)
Undertake post-decommissioning survey of the identified sites to compare the coral health to the reference imagery and GPS database. Reporting and recording of post-decommissioning coral health monitoring data.
Single post decommissioning survey unless findings suggest otherwise.
Traffic Traffic incidents and mitigation measures implemented Update Safety Management System to record and document traffic incidents and mitigation measures implemented as and when they occur.
Social Complaints and Grievance records review Stakeholder consultation to check progress
Regular review of Complaints and Grievance record Regular stakeholder consultation
Cultural Heritage, Archaelogical and Sacred Sites
Any and all occurrences of damage sites is to be recorded. On completion of closure
Page 221 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
11 REPORTING REQUIREMENTS
Based on the monitoring programs outlined in Section 10 (Monitoring Program), this section (Table 11-1) outlines the reporting frequencies and types of reports to be prepared for each aspect identified in the EIS. Details of the reporting requirements include:
1. Monitoring limit or trigger which would dictate the need for reporting; 2. Frequency of reporting for internal and/or external purposes; 3. Incident, accident and emergency reporting; 4. Identification of the appropriate authorities/regulator to which the report is to be provided; 5. Measuring performance indicators and interpreting and acting on the indicators; and 6. Training programs required for employees/contractors.
Page 222 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Table 11-1 Monitoring reporting requirements
Aspect Frequency of monitoring
Limit / Trigger Method/Standard for monitoring
Method of monitoring Frequency of Internal Reporting
External reporting
(Authority/Regulator)
Climate Daily N/A Automated Weather Station
National Meteorological Service
NDPCEI
Minister of Commerce and Environment
Soil Monthly, in the event of leak / spillage of dangerous chemicals and hazardous wastes
Various AS/NZS 5667:1:1998 Water Quality Sampling
Water samples
Laboratory Analysis
6-monthly NDPCEI
Minister of Commerce and Environment
Page 223 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Aspect Frequency of monitoring
Limit / Trigger Method/Standard for monitoring
Method of monitoring Frequency of Internal Reporting
External reporting
(Authority/Regulator)
Air Quality (including Dust)
6-monthly 25 µg/m3 (Maximum concentration in 24 hours, 1 day averaging period)
AS/NZS 3580.1.1:2007 Methods for the sampling and analysis of ambient air – Guide to siting air monitoring equipment.
Air monitoring equipment and dust fall out containers
Annually Local suco chief
NDPCEI
Minister of Commerce and Environment
Noise and Vibration
6-monthly 50dB Exceedance greater than 10% of the time not permitted (LA10)
AS/NZS 1269.1
Occupational noise management
Noise and vibration monitors
Annually Local suco chief
NDPCEI
Minister of Commerce and Environment
Page 224 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Aspect Frequency of monitoring
Limit / Trigger Method/Standard for monitoring
Method of monitoring Frequency of Internal Reporting
External reporting
(Authority/Regulator)
Groundwater – springs
Monthly during pre-construction, construction and operations.
Flows <10% variance pre-development
Quality – below limits
AS/NZS 5667:1:1998 Water Quality Sampling
Water samples
Laboratory Analysis
Every 3 months, subject to stabilizing, then potentially every 6 months.
DWRQC
NDPCEI
Minister of Commerce and Environment
Groundwater – monitoring boreholes
Monthly Levels <10% variance pre-development
Quality – below limits
AS/NZS 5667:1:1998 Water Quality Sampling
Water samples
Laboratory Analysis
Every 3 months, subject to stabilising
Results collation every 6 months, reporting annually to NDPCEI
DWRQC
NDPCEI
Minister of Commerce and Environment
Page 225 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Aspect Frequency of monitoring
Limit / Trigger Method/Standard for monitoring
Method of monitoring Frequency of Internal Reporting
External reporting
(Authority/Regulator)
Groundwater – supply boreholes
Monthly Levels <10% variance pre-development
Quality – below limits
AS/NZS 5667:1:1998 Water Quality Sampling
Water samples
Laboratory Analysis
Every 3 months, subject to stabilizing
Results collation every 6 months, reporting annually to NDPCEI
DWRQC
NDPCEI
Minister of Commerce and Environment
Coastal and Marine
One off Sediment transport model
NDPCEI
Minister of Commerce and Environment
Page 226 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Aspect Frequency of monitoring
Limit / Trigger Method/Standard for monitoring
Method of monitoring Frequency of Internal Reporting
External reporting
(Authority/Regulator)
Flora Monthly during pre-construction, construction
<55ha Surveyor standard Accurate survey of cleared lands
Monthly reconciliation against planned clearing, clearing below approved limit
NDPCEI
Directorate of Mines
Minister of Commerce and Environment
Fauna Monthly during pre-construction and construction
Annually during operations
Fauna Fatalities < 1 per month
Data capture in the EMS Monthly reconciliation and adjustment of clearing approach if exceeded
NDPCEI
Directorate of Mines
Minister of Commerce and Environment
Minister of Commerce and Environment
Page 227 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Aspect Frequency of monitoring
Limit / Trigger Method/Standard for monitoring
Method of monitoring Frequency of Internal Reporting
External reporting
(Authority/Regulator)
Fisheries Annually N/A N/A Fisheries assessment survey and consultation
Annually Ministry of Agriculture and Fisheries
Minister of Commerce and Environment
Coral Every 2 years Coral mortality < 40%
TBC Tow camera and vessel Every 2 years and 5 years post-closure
NDPCEI
Ministry of Agriculture and Fisheries
Minister of Commerce and Environment
Traffic 4 weeks at the start of each phase
N/A Traffic enumerators At conclusion of survey, continuous improvement
MOPW DBRFC
Minister of Commerce and Environment
Page 228 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Aspect Frequency of monitoring
Limit / Trigger Method/Standard for monitoring
Method of monitoring Frequency of Internal Reporting
External reporting
(Authority/Regulator)
Health Annually Stakeholder survey
Grievances mechanism
Year on year variance
Continuous improvement process
Ministry of Health
Minister of Commerce and Environment
Cultural Heritage Monthly during pre-construction and construction
Zero incidents of non-agreed disturbance
Escalation and reporting of every instance of unknown sites encountered
N/A Cultural Heritage Monitors / Supervisors
Grievances mechanism
Monthly pre-construction and construction
Secretariat of Arts and Culture
Minister of Commerce and Environment
Page 229 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
12 RESPONSIBILITIES FOR MITIGATION AND MONITORING
This section clearly identifies the responsibilities of the various parties involved in the implementation of mitigation and monitoring requirements as outlined in Sections 8 and 10, respectively, of this EMP.
The following are the key managerial roles applicable to the Project during the following phases:
• Pre-Construction and Construction: o Project Manager – TL Cement LDA; o Project Engineer – Detailed Design and Planning; • Operation: o Plant Manager; o Engineering Manager
The Plant manager may delegate to his personnel for various functions, including the Health, Safety Quality Manager/Officer function.
The responsibility for the development, implementation and monitoring of the success of ; and review and update of mitigation measures is illustrated in the table below.
Table 12-1 Responsibility for implementation of this EMP
Phase Item Develop/Author Implement Monitoring
Detailed Engineering Design
Environmental Management Plans
Lead Engineer from the Engineering provider with approval by Project Manager – TL Cement LDA
Lead Engineer from the Engineering provider
Mitigation Measures Lead Engineer from the Engineering provider with approval by Project Manager – TL Cement LDA
Lead Engineer from the Engineering provider
Monitoring Plans Lead Engineer from the Engineering provider with approval by Project Manager – TL Cement LDA
Lead Engineer from the Engineering provider
Construction Tender Phase
Develop construction specific Environmental Management Plans
Civil works contractor with approval by Project Manager – TL Cement
Civil works contractor
Page 230 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
LDA
Develop construction specific
Mitigation Measures
Civil works contractor with approval by Project Manager – TL Cement LDA
Civil works contractor
Develop construction specific
Monitoring Plans
Civil works contractor with approval by Project Manager – TL Cement LDA
Civil works contractor
Phase Item Develop/Author Implement External review
Pre-Construction Civil works contractor with approval by Project Manager – TL Cement LDA
TL Cement nominated EPC management firm Health, Safety Quality Manager/Officer
Civil works contractor with approval by Project Manager – TL Cement LDA
TL Cement nominated EPC management firm Health, Safety Quality Manager/Officer
Monitoring activities
Civil works contractor with approval by Project Manager – TL Cement LDA
TL Cement nominated EPC management firm Health, Safety Quality Manager/Officer
Compliance monitoring
Project Manager – TL Cement LDA
TL Cement nominated EPC management firm Health, Safety Quality Manager/Officer
Compliance reporting
Civil works contractor with approval by
TL Cement nominated EPC management firm Health, Safety Quality
Minister of Commerce and Environment
NDPCEI
Page 231 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Project Manager – TL Cement LDA
Manager/Officer
Construction Environmental Management Plans
Civil works contractor with approval by Project Manager – TL Cement LDA
TL Cement nominated EPC management firm Health, Safety Quality Manager/Officer
Mitigation Measures
Civil works contractor with approval by Project Manager – TL Cement LDA
TL Cement nominated EPC management firm Health, Safety Quality Manager/Officer
Monitoring activities
Civil works contractor with approval by Project Manager – TL Cement LDA
TL Cement nominated EPC management firm Health, Safety Quality Manager/Officer
Compliance monitoring
Site Supervisor from TL Cement LDA
TL Cement nominated EPC management firm Health, Safety Quality Manager/Officer
Compliance reporting
Civil works contractor with approval by Project Manager – TL Cement LDA
TL Cement nominated EPC management firm Health, Safety Quality Manager/Officer
Minister of Commerce and Environment
NDPCEI
Operations (Year 1 to 5, Year 6 to end)
Environmental Management Plans
Environmental Engineer supervised by the Plant Manager – TL Cement LDA
TL Cement nominated EPC management firm Health, Safety Quality Manager/Officer
Page 232 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Year 6-end: TL Cement Health, Safety Quality Manager/Officer
Mitigation Measures
Environmental Engineer supervised by the Plant Manager – TL Cement LDA
TL Cement nominated EPC management firm Health, Safety Quality Manager/Officer
Year 6-end: TL Cement Health, Safety Quality Manager/Officer
Monitoring activities
Environmental Engineer supervised by the Plant Manager – TL Cement LDA
TL Cement nominated EPC management firm Health, Safety Quality Manager/Officer
Year 6-end: TL Cement Health, Safety Quality Manager/Officer
Compliance monitoring
Environmental Engineer supervised by the Plant Manager – TL Cement LDA
TL Cement nominated EPC management firm Health, Safety Quality Manager/Officer
Year 6-end: TL Cement Health, Safety Quality Manager/Officer
Compliance Reporting
Environmental Engineer supervised by the Project Manager – TL Cement LDA
TL Cement nominated EPC management firm Health, Safety Quality Manager/Officer
Year 6-end: TL Cement Health, Safety Quality Manager/Officer
Minister of Commerce and Environment
NDPCEI
Decommissioning Environmental Management Plans
Environmental Engineer supervised by the
TL Cement Health, Safety Quality Manager/Officer
Page 233 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Project Manager – TL Cement LDA
Mitigation Measures
Environmental Engineer supervised by the Project Manager – TL Cement LDA
TL Cement Health Engineering Manager
Monitoring activities
Environmental Engineer supervised by the Project Manager – TL Cement LDA
TL Cement Health, Safety Quality Manager/Officer
Compliance monitoring
Site Supervisor from TL Cement LDA
TL Cement Health, Safety Quality Manager/Officer supervising the Civil works contractor
Compliance Reporting
Environmental Engineer supervised by the Project Manager – TL Cement LDA
TL Cement Health, Safety Quality Manager/Officer
Minister of Commerce and Environment
NDPCEI
Page 234 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
This page has been intentionally left blank.
Page 235 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
13 EMERGENCY PLAN
13.1 Purpose
The Emergency Plan (EP) outlines the approach for managing the handling, storage and leak / spillage of dangerous chemicals and hazardous wastes associated with the development and operation of the Cement Plant, Jetty and Other Associated Infrastructure associated with the Baucau Cement Plant Project.
The purpose of the EP is to identify appropriate management strategies, procedures and processes to ensure that in the event of a spill / leak it is dealt with quickly and efficiently to ensure it is:
• Stopped at the source; • Contained and collected; and • If necessary, the site is remediated.
13.2 Objective
The objective of the EP is to:
• Reduce the risk of contamination and pollution to water and land from any dangerous chemicals or hazardous wastes; • Respond effectively and quickly to all spills and leaks, regardless of the size / volume; and • Minimise the risk exposure of any dangerous chemicals or hazardous wastes to all employees and contractors and subsequent health impacts.
13.3 Responsibilities
TL Cement Safety and Quality Officer/Manager:
• Regular review and updating of the EP; • Ensure the EP is effective and drills are conducted; • Notify the regulatory authority of any major spills within the required timeframes; • Ensure all employees are provided with the necessary training, PPE and equipment to deal with spills; • Notify and coordinate emergency services, if required; • Oversee incident reporting and investigation process and ensure an adequate investigation is undertaken, if required; • Ensure the Safety Data Sheets (SDS) is maintained and current for all of the chemicals and hazardous materials used and stored on the Project site; and • Ensure spill kit materials are adequately stored and restocked following any spill or leak.
All employees and contractors are responsible for:
Page 236 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
• Cleanup and removal of spills, if it is safe to do so; • Reporting all spills to the TL Cement Plant Manager using the appropriate procedure; • Participate in emergency drills; and • Ensure appropriate PPE is used when dealing with the cleanup and removal of spills.
13.4 Standards
The storage, management of and handling of all dangerous chemicals or hazardous wastes will be undertaken in accordance with the requirements of the following standards and legislation:
• Australian National Standard for the Storage and Handling of Workplace Dangerous Goods [NOHSC: 1015 (2001)]; and • Australian Standards AS 1940-2004: The storage and handling of flammable and combustible liquids. • Regulation 37 Annex 1 of the International Convention for the Prevention of Pollution from Ships 1973 • Guidelines for development of Shipboard Oil Pollution Emergency Plan (MEPC, 86:44)
13.5 Incident Classification
All spills, leaks and or uncontrolled release of materials, regardless of the size / volume are classified as an event, which needs to be reported to the TL Cement Environment Manager/Officer.
An incident includes a spill, leak or uncontrolled release of any of the following substances to water sources, ground; bitumen; bunded areas (concrete or plastic lined); concrete pads; and spill trays:
• Hydrocarbons; • Chemicals; • Saline water; • Powdered chemicals; • Oily waste water; • Sewage; • Ships ballast water; • Concrete washout; and • Bitumen.
The following table outlines the potential ‘Incident Types’ which may be applicable to the Project.
Page 237 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Table 13-1: Incident Classifications
Level 1
Minor
Level 2
Moderate
Level 3
Medium
Level 4
Major
Minor uncontrolled spill or release of materials within a bunded or contained area* including on board a ship that may:
• Impact disturbed land but not vegetation; • Does not impact water (surface or groundwater); • Does not reach the water in the case of spills on a vessel; • Does not harm fauna; and • Can be easily cleaned up.
Moderate uncontrolled spill or release of materials contained within bunded or contained area that may:
• Reaches the water as a result of washdown or spill overboard; • Has minor impacts on soil, fauna and flora but not priority flora/fauna or significant species; and • Minor impacts to surface or groundwater.
Uncontained spill or release of materials that may:
• Has impact on sea water, fauna and flora and is uncontrolled and extensive in its release; • Impacts on native vegetation including priority / rare flora; • Moderate impacts on soil requiring soil treatment or replacement • Has moderate impacts on low value surface / groundwater sources; and • Has reasonable probability of being detrimental to fauna.
Major uncontained spill or release of materials that may:
• Has impact on sea water, fauna and flora and is major, uncontrolled and time extensive in its release; • Impact soil, requiring significant treatment and soil replacement; • Major impacts on surface and/or groundwater sources; • Impacts on vegetation over an extensive area that causes loss of priority / rare flora; • Results in fauna deaths of rare / priority species; and • Has a reasonable probability of being detrimental to public health.
* Contained area can include: surface of the vessel; concrete bunds; plastic lined bunds; concrete pads; and spill trays.
13.6 Prevention
The following are some simple techniques that shall be adopt and implemented on the Project to prevent spillages and leaks from occurring:
• No tanks are to be filled prior to checking available tank volume; • Tank filling and dispensing procedures shall be carried out only by appropriately trained personnel and within designated and bunded area;
Page 238 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
• The main outlet valve on tanks will be locked shut when unattended; • Each tank/storage facility will be gauged and monitored daily; • All chemical and hazardous materials are contained in bunded areas with an appropriate holding capacity; • Bunded compound shall be lined with low permeability (less than 10 - 9 m/s) material that is not adversely affected by contact with the stored chemicals. It should be constructed in such a way that permits full recovery of contents spilt from tanks and ensures that the lining material is not damaged. The bund itself should be constructed of waterproof membrane, reinforced concrete or an approved equivalent; • The bunded compound shall have a minimum capacity of 110% of the capacity of the largest tank. The compound shall also have sufficient capacity to retain spilt chemicals and not be affected during extreme rainfall events; • After a rainfall event, pumping should be used to empty the compound, provided the water is not contaminated. The water should be checked by a suitably qualified and experienced person; • Under no circumstances shall contaminated water be allowed to discharge to the environment, but shall be pumped into a tanker for appropriate disposal; • Emptying of the compound should not be achieved through a valved (i.e. gravity flow) outlet as this may be inadvertently be left open; • Vehicle refueling and maintenance will only be conducted in the designated Vehicle Maintenance and Refueling areas; • Tanks; vehicles and equipment will be regularly inspected and maintained as per the required specifications; • The network of storm water drains, diversion ditches and drains will be regularly inspected to ensure there are no blockages; • All spills and leaks will be cleaned up immediately and reported to the TL Cement Plant Manager; • All vessels and vessel activities are to operate in accordance with Regulation 37 Annex 1 of the International Convention for the Prevention of Pollution from Ships 1973 and Guidelines for development of Shipboard Oil Pollution Emergency Plan (MEPC, 86:44) • Shovels, drip pans and absorbent materials will be strategically located throughout the Project site; and • Ensure that all chemical and hazardous materials are stored appropriately. Substances may escape from storage facilities through various means, including, but not limited to:
o Absence of containment facilities;
o Poor construction or deterioration of containment facilities;
o Inappropriate equipment maintenance operations; and
o Poor ‘house-keeping’ practices.
13.7 Safety Data Sheets (SDS) Before a contractor can bring a chemical onto site, they must inform and receive approval from the TL Cement HSE Department / Environmental Manager.
Page 239 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
All chemicals which have been approved for use on site by the TL Cement HSE Department/ Environment Manager will be stored in accordance with the SDS and in a designated bunded / contained area.
13.8 Spill Response
In the event of a spill and/or leak TL Cement shall adopted the following ‘3C Response Policy’:
• Control; • Contain; and • Clean-up.
The following sections provide an outline of the ‘3C Response Policy’.
13.8.1 Control
The ‘Control’ aspect of the response policy includes, but is not limited to; the following steps for all spills / leaks (i.e. Minor to Major):
• Identification of the source and material involved of the spill / leak. • If required, get help / advice from the TL Cement Safety and Quality Officer. • Ensure the appropriate personal protective equipment (PPE) is used. • If it is safe to do so, control the spill / leak at the source by: o Shut off valves; o Stop the pump process; o Upright the container. • Clear the area of people and equipment not directly involved in the clean-up process. • Complete the appropriate Form estimating the quantity spilled and submit to the TL Cement Safety and Quality Officer.
13.8.2 Contain
The ‘Contain’ aspect of the response policy includes, but is not limited to; the following steps for all spills / leaks (i.e. Minor to Major):
• Ensuring that the appropriate PPE is in place, it is essential for spills on or over water for the edge of the spill to be contained with booms. For land spills, sand, rags or other like materials should be used. • Block or divert the flow of the spill / leak from entering any stormwater drain. • Place appropriate spill kit material over the body of the spill to ensure it does not disperse further.
13.8.3 Clean Up
The ‘Clean Up’ aspect of the response policy includes, but is not limited to; the following steps:
Page 240 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
• Ensuring that the appropriate PPE is in place; spills / leaks should be cleaned up using appropriate absorbent materials which should then be disposed of to a suitably labelled “Contaminated Material Bin” for storage and eventual transportation via a licenced contractor to a licenced disposal facility. • Any equipment used from spill kits must be recorded and the TL Cement Environment Manager / Environment Officer is to ensure the spill kit is restocked. • For spills on soil, they may be either remediated in-situ or the contaminated soil may need to be removed for appropriate disposal.
13.9 Equipment
13.9.1 Spill Response The following spill response equipment will be stored in the fuel and other chemical storage areas:
• 55 gallon drum of absorbent granules;
• 100 absorbent pads;
• 30 metres of absorbent pigs;
• Shovels;
• Two (2) empty 55-gallon drums (steel) for collecting used absorbent;
• A hand pump and 10 metres of plastic hose;
• All PPE to safely handle spills (e.g. gloves and eye protection).
In the case of soil contaminated by a fuel or chemical spill, the soil should be excavated and taken to the volatilisation pad, before being disposed of in the approved solid waste landfill. This also applies to any sorbent material used to clean up spills.
13.9.2 Marine Spill Response
The following spill prevention measures are to be carried out for general ship operations:
Before bunker handling commences, all deck scuppers and open drains must be effectively plugged to prevent spilled oil from escaping from the vessel.
All water accumulation on deck should be periodically drained and scupper plugs replaced
All collected water is to be transferred to a slop tank or other suitable receptacle ready for proper disposal;
When not in use, sea and overboard discharge valves connected to the bunker and ballast system must be securely closed;
All emergencies at sea which have the potential to cause pollution are to be managed in accordance with Regulation 37 Annex 1 of the International Convention for the Prevention of Pollution from Ships 1973.
Page 241 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
13.9.3 First Aid Facilit ies and Personal Protective Equipment (PPE)
First aid facilities will be located in every site office and work vehicle. The location of first aid kits in the site offices will be clearly displayed. The first aid kits will be kept clean and restocked on a three monthly basis.
TL Cement will provide all employees with the necessary PPE, including but not limited to:
• Ear plugs; • Eye protection; and • Gloves.
13.9.4 Fire Fighting Equipment
Firefighting equipment (i.e. extinguishers) will be located in every site office and work vehicle. The extinguishers will be easily accessible and clearly displayed. All employees will be provided with the necessary training on the appropriate usage of extinguishers.
The firefighting equipment will be tested and tagged by a competent person every six months. Used or expired extinguishers will be removed from site and will be immediately replaced.
A complete firefighting hydrant system will be built for the plant.
13.10 Training
All personnel will receive environmental training as part of a mandatory induction for the Project. The environmental induction will include as a minimum the requirements of this EP.
All personnel will be trained in the use of the spill response kit and fire fighting equipment required for the implementation of this EP.
Environmental notices will be developed and placed on the Project site notice boards on a regular basis and in response to non-compliance and environmental incidents.
The training register will be kept onsite in an easily accessible location for inspection and auditing.
Page 242 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
14 DECOMMISSIONING PLAN
Sections 8 and 10 of this EMP contains details of the mitigation and monitoring requirements for the Decommissioning Phase of the Project.
TL Cement’s vision for closure is to:
- To ensure a self-sustaining vegetative cover on areas disturbed by mining activities where this is appropriate; - Provide sustainable end land uses in keeping with the needs of local communities; and - Ensure economic sustainability for affected communities.
14.1 Objectives The primary objective of the reclamation plan will be to return, where practical, all areas disturbed by mining operations to acceptable land use and capability.
The closure objectives for the cement plant operations are:
- Adhere to all statutory and other legal requirements; - Ensure safety & health of all stakeholders during closure and post closure and that communities using the site after closure are not exposed to unacceptable risks; - Ensure that closure supports productive uses considering pre-operational conditions and are in agreement with commitments to and requirements of stakeholders - Physically and chemically stabilize remaining structures, if required, to minimize residual risks; - Promote bio-diversity and biological sustainability; and - Utilize closure strategies that promote a self-sustaining condition with little or no need for on-going care and maintenance.
14.2 Preliminary Decommissioning Plan
In order to meet the vision for closure, a preliminary decommissioning plan has been outlined below, including impacts of the project and mitigation and monitoring measures to be undertaken during the decommissioning phase of the project (Holtec 2015).
Sections 8 and 10 of this EMP also contain details of the mitigation and monitoring requirements for the Decommissioning Phase of the Project.
Page 243 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Ecology and Biodiversity
Aspect / Impact Mitigation Measures
Re-establishment of habitats or creation of new habitats via rehabilitation
Sequential reclamation and rehabilitation is proposed; Afforestation by plantation is proposed to be carried out;
The top soil stored separately during the operation phase shall be used for afforestation and plantation only. Local species shall be planted in the area; The buildings shall be dismantled. The machinery shall be sold to other industries for use or to authorized scrap dealers. The area shall be brought to its original state.
Introduction of alien invasive flora and fauna Invasive alien species control programme implemented as a component of the EMP, including adaptive management measures; EMP should be reviewed every five years with emphasis on control of alien invasive flora and fauna;
All invasive alien species control measures specified in the EMP must be implemented.
Loss or disturbance of fauna species of special concern due to collisions and noise disturbance
Sequential rehabilitation to be conducted as soon as possible at the completion of operation; Reclamation and rehabilitation of the area to restore the area in natural, pre- construction condition; Environmental education training program, including refresher sessions, for all employees, contractors and their families;
EMP should be reviewed every five years.
Increased hunting/ poaching of wildlife and loss of habitats for crop production
No fauna are to be hunted or destroyed by any project personnel;
Effective penalties (e.g. fines) must be imposed for the hunting or harm to fauna by any
Page 244 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Ecology and Biodiversity
Aspect / Impact Mitigation Measures employee of TL Cement; The locals should be encouraged to utilize the cash income, during employment for investments that will assist with increasing productivity of the local agricultural sector; An environmental education programme to be developed and implemented for all TLC employees, their families and villages within the concession.
Water Resources
Aspect / Impact Mitigation Measures
Chemical contamination of surface water resulting from accidental spills during transportation and handling and seepage from waste
Emergency contaminant and mitigation measures must be developed to minimize impacts should accidental spillages occur along the transport routes;
Equip all trucks and equipment carrying fuels or oil with spill response materials and train personnel in the use of such materials; Store all potential sources of contamination in secure facilities with appropriate Storm Water management systems in place to ensure that contaminants are not released to the water resource through Storm Water runoff.
Sedimentation of surface water resulting from erosion and runoff from exposed surfaces and roads
Minimize disturbance of soil and vegetation; Implement rehabilitation and re-vegetation as soon as possible;
Refer to dust and erosion suppression measures listed above.
Contamination of groundwater resulting from seepage from hazardous materials and waste
Manage waste in accordance with Waste Management Plan;
Waste Management
Page 245 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Aspect / Impact Mitigation Measures
Generation of debris from p r o j e c t infrastructure
The buildings shall be dismantled. The machinery shall be sold to other industries for use or to authorized scrap dealers; The office equipment like table, chairs, computers etc. can be donated or auctioned for its use; The debris generated from dismantling of building shall be used in backfilling of exploited pits.
Socio-economic Impacts
Aspect / Impact Mitigation Measures
Direct impacts on project employees and their families
Communication with internal stakeholders i.e. employees to discuss the implications of closure;
Phased programme of retrenchments and retirements to ensure that the full impact of reduction in employment is spread over several years to ensure that the impact is absorbed as far as possible; Career counseling and capacity building;
Development of a skills register and dissemination of the register to alternative employers, government etc.
Loss of economic benefits to the project supply chain
Early communication with stakeholders i.e. service providers including local service providers, bulk service providers and the business community to discuss the implications of closure; Liaison with other industries to discuss opportunities for service providers within their supply chain.
Loss of support to the local government and other government levels with respect to taxes and royalty incomes
Timely engagement of local, regional and national government to advise of closure and the implications this will have on the government revenue from taxes and royalties; Gradual transfer/return of responsibilities to local government with respect to service
Page 246 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Socio-economic Impacts
Aspect / Impact Mitigation Measures provision where the project has played an active role in service provision.
Loss of community benefits in the form of project funded community development programme
Early engagement of stakeholders to discuss and scenario plan the transfer of usable assets to the community, local government and other stakeholders;
Provision of information on the maintenance and management costs of assets and typical maintenance programme; Capacity building for asset management.
Loss of Employment and Income due to retrenchment
Develop the TLC grievance procedure to capture and address grievances arising due to retrenchments and downscaling for the employees; If practical, shift the employees to other businesses of the group company; Compliance with IFC’s Performance Standard 2 “Labour and Working Conditions”; Actively promoting the development of different economic sectors from an early stage e.g. through incentivizing other industries to locate in the area, and promoting an increase and diversity of skills in the local population; Develop a decommissioning and closure plan which is updated every five years increasing in detail as closure approaches, and actively engaging with a range of stakeholders throughout the life-of-project to discuss potential consequences of decommissioning and possible mitigation.
Eco-system Services
Aspect / Impact Mitigation Measures
Page 247 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Reduced quality of natural resources and ecosystem services to local communities due to emissions to air, water or soil
To minimize impacts, the project must comply with best pract ice for air emissions, water (storm water and effluent) discharge quality and solid waste disposal.
Soils, land capacity and land use
Aspect / Impact Mitigation Measures
Remediation of contaminated soils and demolition of project infrastructure, resulting in re- establishment of baseline soil characteristics and land capability
The contaminated soils during de-commissioning and closure should be excavated and disposed of; Infrastructure like buildings, access roads etc. having potential post mining benefit, if desired shall be handed over to stakeholders; The areas not required by stakeholders shall be decommissioned and the area will be rehabilitated by replacing soils and adding nutrients, if necessary;
Air Quality
Aspect / Impact Mitigation Measures
Increase in PM10 and PM2.5 emissions resulting from land clearing, earthworks and vehicular movement
Continuous water spraying on roads used routinely by vehicles; Set speed limits to minimize the creation of fugitive dust within the project boundary; Continue with the routine air quality monitoring program; Minimize the disturbed footprint as far as practically possible; Revegetate and landscape disturbed areas as soon as possible.
Visual Impacts
Aspect / Impact Mitigation Measures
Page 248 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Dust generation and site disturbance due to earth moving and removal of infrastructure, affecting the visual character for communities
Minimize the disturbed footprint as far as practically possible; Revegetate and landscape disturbed areas as soon as possible to reflect the surrounding topography and vegetation as much as possible;
Re-establishment of baseline visual character due to rehabilitation of the site and removal of project infrastructure
Landscaping and re-vegetation in accordance with the surrounding vegetation and topography
Page 249 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
15 CAPACITY DEVELOPMENT AND TRAINING
Training is essential for ensuring that the provisions of the EMP are implemented efficiently and effectively. Training needs will be identified based on the existing and available capacity of the site and Project personnel (including the proponent, contractors and subcontractors) to undertake the required management actions and monitoring activities. A training program will be presented in this section of the EMP. The training program will be developed and delivered by suitably qualified personnel, in a language and medium understood by workers and/or employees.
A training needs analysis will be conducted by TL Cement as part of the resource planning for the Project implementation. The training needs analysis will consider:
• Practical training via instruction; • Formal vocational training; • Success and completion criteria; • Delivery method; • Certification and recognition system; and • Training refreshers and frequency.
During the life of the Project, the following EMP training will be provided to relevant personnel:
• Field sampling and sample handling techniques; • Data collection and collation; • Emergency response procedures (e.g. spills); • Management of exceedances (e.g. dust levels); and • Roles and responsibilities for EMP implementation.
Page 250 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
16 PUBLIC CONSULTATION AND INFORMATION DISCLOSURE
WorleyParsons and TL Cement have undertaken a process of consultation with the people who may be affected by the Project and the Project stakeholders. WorleyParsons and TL Cement have made efforts to ensure that the public, including affected people, women and vulnerable groups, have the opportunity to participate fully in the consultation process. Consultations have taken place on a continuous basis, starting as early as possible in the EIA process. This section describes the public consultation conducted to date.
Consultation was undertaken during the development of the EIS. During this consultation, aspects pertaining to the management and mitigation measures for the Project were raised. These details are included in this component to illustrate that both TL Cement and WorleyParsons have undertaken consultation around the EMP.
16.1 Purpose of the consultation during the preparation of the EMP
The public consultation process for the environmental assessment is carried out in accordance with the Draft Ministerial Diploma for the “Regulation on the Public Consultation Procedures and Requirements during the Environmental Assessment Process” dated 22 April 2014.
The EMP was referenced in the final consultation session undertaken on 11 December 2015.
16.2 Methodology and Approach
16.2.1 Identified Stakeholders
The following table lists the identified stakeholders consulted during the environmental assessment process.
Table 16-1: Identified stakeholders consulted during the EIS process
Governments
President of Republic Democratic of Timor-Leste
• President of RDTL
Prime Minister of Republic Democratic of Timor-Leste
• Prime Minister of RDTL
Ministry of Commerce, Industry, and Environment
• Minister of CIE
• National Directorate for Pollution Control and Environmental Impact
Page 251 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
• General Director for Environment
• Nacional Director for Industries and Manufacturing
Ministry of Petroleum and Mineral Resources
• Minister of PMR
• National Directorate of Minerals
• Institute of Petroleum and Geology (IPG)
Ministry of Justice
• Secretary of State for Land and Property
Ministry of Finance
• Minister of Finance
Ministry of Planning and Strategic Investment
• Minister of PSI
Ministry of Public Works, Transport and Communications
• Minister of PWTC
• Directorate of Ports/APORTIL
• National Directorate for Water Quality and Control
Ministry of Tourism, Arts and Culture
• Secretary of State for Arts and Culture
Secretary of State for Employment Policy and Vocational Training
• Secretary of State for EPVT
Municipality (District) Government
Baucau Municipality (formerly Baucau District Administration)
Baucau Administrative Post (formerly Baucau Sub-District Administration)
PNTL Baucau Municipality
PNTL Baucau Administrative Post
BOP Baucau Municipality
F-FDTL Baucau Municipality
Page 252 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Baucau Municipality Directorate of Land, Property and Cadastral Services
Baucau Municipality Directorate of Pollution Control and Environmental Impact
Baucau Municipality Health Directorate
Baucau Municipality SEPFOPE
Baucau Municipality Public Works
Baucau Municipality Social Directorate
Baucau Municipality Agriculture Directorate
Baucau Municipality Water and Sanitation Directorate
Baucau Municipality Electricity Directorate
Local Government
Suco Council Tirilolo
Suco Council Triloca
Suco Council Caibada
Suco Council Bahu,
Suco Council Bucoli
Local Community
Chefes de Aldeia
Lia’nain
Local Youth Organizations
Local Women’s Organizations
Local Fishermen’s Organization
Baucau Parish – Old Town
Baucau Parish – New Town
Baucau Bishop
Civil Society/Local NGOs
La’o Hamutuk
Page 253 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Luta Hamutuk
Haburas
Rede ba Rai
Belun
Kapeliwa (Local NGO)
Other Organizations
International Finance Corporation (IFC)
Conservation International
BESIK (Bee, Saneamentu no Ijiene iha Komunidade) Rural Water Program
Presidente CCI Baucau
16.2.2 Mechanism for Public Consultation
The public consultation conducted for the EIS and EMP engaged affected communities, general public, non-governmental organizations, government agencies, and others.
The consultation took different forms, depending on the purpose; including, but not limited to:
• One on one meetings; • Public information meetings and presentations; • Site visits; • Development and distribution of a Non-Technical Summary document; and • Questionnaire completion with stakeholders and community members.
All public consultation sessions were advertised 7 days in advance by local TV transmissions and by notices placed strategic locations; and were also advertised though local radio stations such Radio Popular Coulelemai Bucoli and Radio Komunidade Lian Matebian in Baucau. A copy of the public notice was also posted on TL Cement’s website.
Additionally, the notices were displayed at local government offices including Baucau Municipality, Baucau Administrative Post, Chief of Village, and PNTL Baucau Municipality. Lastly, a copy of all notices was provided to the NDPCEI.
16.3 Summary of consultation activities carried out
The formal consultation activities undertaken between February 2015 and December 2015 are detailed below. Ongoing consultation with key stakeholders has taken place in addition to the formal sessions.
Page 254 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Table 16-2: Summary of consultation session completed during the EIS process
Date Type of Consultation Key components
June 2014 TL Cement conducted consultation with the Tirilolo community and Youth group
The meeting was used to discuss the land use and crop types in the area, in relation to the location of the proposed project.
July 2014 TL Cement met with members of the Casido Traditional Council, Suco Council and Government of Timor Leste to coordinate activities for a cultural ceremony.
Prior to TL Cement construction and production activities it is important to hold a cultural ceremony.
October 2014 TL Cement met with the Lia-Nain of Suco Ostico The meeting was used to discuss the proposed project and the land use in the area.
November 2014 TL Cement met the communities from Suco’s Bucoli Adeia Macadai, Lulihen and Land owners Mr Virgillio G Antonio, Mr Oscar Da Silva and Mr Jose’ Da Silva
The meeting was used to discuss the proposed project and the land use in the area. The community was supportive of industry being established in Bacau.
February 2015 TL Cement and WorleyParsons conducted consultation in the local community during a site visit with the Lian Nian (Traditional Leaders)
The locals in general were enthusiastic about the project and had queries about the development activities for the locals that TL Cement would initiate as well as the employment opportunities the project would generate for the locals.
May 2015 TL cement and WorleyParsons with the community representatives :
• Chefe Suco Trololo: Ricardo Ernesto Belo (RB)
• Chief of Community Police in Suco Trilolo: Norberta Belo (NB)
• Chefe Aldeia Lia Lailesu: Cipriano Belo (CB)
• Chefe Aldeia Parlamentu: Manuel Belo (MB)
• Chief of Traditional Practice (Lia Nain): Duarte Belo (DUB)
These meetings were set up to discuss the field work surveys that would be undertaken for the EIS
Page 255 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
• Secretary of Suco Trilolo: Zeca Belo (ZB)
August 2015 Community Questionnaire
WP Timor Leste office staff visited four (4) most affected aldeias in Suco Tirilolo; aldeia lia lailesu, Parlamentu, Caisido-Kotalali and Osso-wa.
The objective was to meet the community who are unable to attend the previous meeting and hear their opinions and suggestions as well as improve their awareness of the project.
Most of them were well aware of the project and showed their enthusiasm for the project; however, they are worried about the impact of the project on their cultural heritage, land and lifestyle.
3 September 2015 Public Consultation on the draft TOR was conducted in Caisido, Baucau Municipality.
WorleyParsons presented some preliminary findings as described in the TOR and Project Documents.
11 December 2015 TL Cement and WPTL organized a public meeting in Caisido, Baucau Municipality, to discuss the proposed project and the draft EIS and EMP. The date, venue, and time of this public meeting were coordinated with the relevant Administrator, Chefes do Suco and Chefes da Aldeia.
WorleyParsons presented a description of the project, explained the EIS process, and provided a brief summary of the study findings to date. Following the presentation, two information tables were set up with maps, diagrams and pictures of a similar cement plant in Indonesia. The tables were staffed by representatives of WorleyParsons and TL Cement who provided more detailed explanations of project details and answer questions. The community members were invited to observe, ask questions and/or provide recommendations to the Project team.
07 January 2016 TL Cement and Worley Parsons met with the NGO group Lao Hamutuk to update them on preliminary EIS findings
WorleyParsons description of the project, explained the EIS process, and provided a brief summary of the study findings to date. Lao Hamutuk stated that resettlement and compensation need to be carefully addressed. Lessons learnt from the Suai Supply base should also be taken into consideration.
07 January 2016 TL Cement and Worley Parsons met with Foundação Haburas to update them on
WorleyParsons description of the project, explained the EIS process, and provided a
Page 256 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
preliminary EIS findings brief summary of the study findings to date. Foundação Haburas stated that a Resettlement/relocation and Groundwater Management Plans should be developed.
13 January 2016 TL Cement and Worley Parsons met with Direcção Nacional Controla Qualidade Agua (DNCQA)to update them on preliminary EIS findings
WorleyParsons description of the project, explained the EIS process, and provided a brief summary of the study findings to date. DNCQA stated that that resettlement and compensation need to be carefully addressed. Groundwater, Dust and Noise management plans should be developed.
13 January 2016 TL Cement and Worley Parsons met with NGO group Luta Hamutuk (LH) to update them on preliminary EIS findings
WorleyParsons description of the project, explained the EIS process, and provided a brief summary of the study findings to date. LH stated that that resettlement and compensation need to be carefully addressed. Government strategies to maintain and enhance subsistence farming strategies need to be implemented. They recommended contributions towards the health and education sectors.
Page 257 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
16.4 Summary of main comments received from the public, community leaders, NGOs, local officials, other stakeholders
The EMP has been developed to take into account the concerns raised in the Community Consultation sessions. In order to ensure that they are included in the EMP, the key aspect is identified below in relation to the question or comment and the management measure or mitigation measure is detailed below the key aspect.
# (Unique number Retained from Questions database)
Aspect &
Environmental Management and Mitigation Measure
Questions from Public Consultation
Proponent’s Response
3 Air quality
Air Quality and Dust mitigation measures
Noise
Jaime (school teacher), Suco Parlamento; Claudio (student); Agustinho da Costa Belo, Aldeia Osso-ua; Joao Freitas, Suco Caisido
What are the impacts from the cement plant and limestone mine to the surrounding environment? What are the measures taken to mitigate these impacts?
What is the level of air pollution emitted from the plant and mine (including when transporting from mine to plant)?
What will be the mitigation towards noise pollution (from machinery, heavy equipment, blasting)?
James Rhee:
Air pollution mainly will come from power generation and dust. Dust will mainly be released during transportation of material from mine to plant and from/to jetty using conveyor belt. The amount of air pollution can be mitigated by using solar and wind power to generate electricity whereas dust from the conveyor belt will be well contained using a closed system. In addition, company will build new road from mine to plant as a mitigation measure to reduce dust.
Regarding noise pollution, since it is low
Page 258 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
risk, hence no mitigation measure required.
4 Cultural Heritage
Cultural Heritage Management Plan
Jaime (school teacher), Suco Parlamento; Joao Freitas, Suco Caisido; Tomas Freitas, Administrative Post of Vemasse
What is the position of TL Cement regarding any sacred site and/or cemetery found within the project site?
TL Cement respects all cultural heritages including evidence of ancient human habitation found within the project site. In fact, a Cultural Heritage Management Plan will be prepared in coordination with the community and the Secretariat of Arts and Culture to conduct procedures and/or traditional rituals required relocating sacred site and/or tombs including the management and protection of new and known sites during the project life.
During a field study on the project site and its vicinity, some antique materials from ancient civilization (spanning the last ca 30,000 years) were found and documented.
5 Groundwater
Water Management Plan
Francisco Hero (PNTL)
Where is the location to drill borewells for water supply? Will the amount withdraw from the well affect the spring located in Osso-ua?
Water requirement for mining and plant operation is to be abstracted from groundwater through the drilling of borewells at the Uaidei River.
Page 259 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
A feasibility study will be conducted prior to finalize the decision on drilling. The location of the proposed drilling site and the Osso-Ua Spring are quite far separated and thus there will be no impact to Ossu-Ua Spring.
6 Land Use and Tenure
Relocation and Compensation Plan
Manuel Azevedo Has the company identified properties that may be found within the project site? What will be the negotiation regarding these properties?
TL Cement is currently working with the Directorate of Land, Property and Cadastral Services (DLPCS) to map affected households, farmland, and other property. Once TL Cement has secured the mining and environmental licenses required for the project, we will enter into discussions with those affected households and property owners. Based on the mapping and negotiations, TL Cement will prepare a Resettlement Plan. This Resettlement Plan will provide greater detail on the monitoring and reporting requirements in relation to the potential social and economic impacts associated with the development of the project
Page 260 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
7 Agustinho da Costa Belo, Aldeia Osso-ua
If the properties (Farm land, house etc) are taken by the company, will there be compensation to the owners?
Yes.
10 Groundwater
Water Quality Management Plan
Duarte Xavier Recommendation: Management plan for local reservoir/spring so to avoid waste water contamination from the plant.
Noted
11 Air Quality
Air Quality Management Plan
Duarte Xavier It is mentioned that traffic will increase from 3 to 71 passenger cars in a day during construction and operation. What will be the mitigation measure towards dust caused by this high traffic?
Dust suppression using water.
13 Waste
Waste Management Plan
Herminio Belo Where will the waste water from the plant be discharged? Is there any treatment plan for waste water?
The volume of waste water from plant to be discharged is very low and thus will have negligible detrimental impact to the environment. In addition, all chemicals used on site are to be stored, handled and disposed of in accordance with a Waste Management Plan.
14 Economic
Resettlement Plan
Felipe Belmiro Belo Recommendation: There should be compensation for community whose properties are directly affected by the project.
Yes
Page 261 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
21 Tenure and Land Use
Cultural Heritage
Resettlement Plan
Cultural Heritage Management Plan
Eusebio Assis (Youth Representative), Suco Tirilolo
When will the affected community be gathered to discuss property lost and cultural heritage- related issues before proceeding with construction of the plant and/or limestone extraction?
TL Cement will proceed with compensation negotiations following receipt of project approvals.
22 Economic
Training needs analysis
Training Plan
Eusebio Assis (Youth Representative), Suco Tirilolo
When will the training for local workers begin?
Once the company has obtained the Environmental License and other project approvals.
16.5 Identify how those comments were taken into account
These comments were taken into account by ensuring that any recommended mitigation measures were populated in the EMP. Key items which were raised by the community which have been incorporated are:
• Water quality impacts from the Limestone Mine have been addressed through mitigation measures and a monitoring programme; • Cultural Heritage impacts through clearing have been addressed by incorporating mitigation measures; • Abstraction impact from water supply on the springs at Osso-ua and Caisido requiring regular monitoring; and • Dust and Air Quality impacts requiring air quality monitoring and reporting.
16.6 Details of public participation activities
The public consultation and community engagement process has been detailed extensively in the EIS and the reader is referred to this document which includes the minutes and photographs.
A summary of the consultation sessions is contained in Table 16-2 in Section 16.3.
16.7 Summarize the public acceptance or opinions on the proposed Project
Key comments from community members are extracted below:
Page 262 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Lian Nian (Traditional Leaders) said “The locals in general were enthusiastic about the project and had queries about the development activities for the locals that TL Cement would initiate as well as the employment opportunities the project would generate for the locals”
Casido Community leaders “are 100% willing to accept the cement plant project in their area”
Chief of Suco “Time of development has come. Community to ignore any rumours [that project will destroy livelihood]”
Director of Environmental Department, GoTL said that many community concerns around air quality will be addressed by “technology used in Australia which does not produce smog to a level harmful to the nearby community”.
Overall the response to the project is positive and the majority (more than 90%) of the local community supports the project.
16.8 Related materials or activities
Newspaper readership is low in Baucau and thus other advertising methods are better suited to encourage broad public consultation. Therefore, all notices associated with the EIS public consultation were advertised on national television (TVTL) in Dili on the 4th to 10th of December 2015. Notices were also advertised though local radio stations such Radio Popular Coulelemai Bucoli and Radio Komunidade Lian Matebian in Baucau commencing on the 27th of November to 4th of December, 2015. A copy of the public notice was also posted on TL Cement’s website. Additionally, the notices were displayed at local government offices including Baucau Municipality, Baucau Administrative Post, Chief of Village, and PNTL Baucau Municipality. Lastly, a copy of all notices was provided to the NDPCEI.
Prior to the consultation in December 2015 a Non-Technical Summary document was prepared and translated into Tetun and made available at the following locations:
• TL Cement Office;
• Baucau Municipality Office;
• The NDPCEI Dili Office;
• The NDPCEI Baucau municipality office;
• Baucau church;
• PNTL Vemasse HQ;
• Vemasse Administrative Post;
• Baucau Municipality SEPFOPE Directorate; and
• Tirilolo Suco Hall.
Page 263 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
The document was made available for viewing during normal business hours and made available free of charge.
A copy of the document was made available at a local school, church, or other public facility (Figure 5) near the proposed project and available outside of normal work hours.
The document was also posted on TL Cement’s public website at http://www.tlcement.net/.
16.9 Recommendations for future consultations
TL Cement is committed to ensuring continued, open and transparent consultation with all Project stakeholders and interested and affected parties. Consultation will continue through the life cycle of the Project.
Page 264 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
17 COMPLAINTS AND GRIEVANCES MECHANISM
The Project Proponent will establish a Complaints and Grievances Mechanism (CGM) related to environmental and social issues arising during the pre-construction, construction, operation and decommissioning, and post-closure phases of the Project.
The Complaints and Grievance Mechanism shall be developed to ensure that concerns and potential conflicts arising during the various phases of the Project can be satisfactorily addressed. WorleyParsons has developed this grievance mechanism framework for discussion with stakeholders (including government) to refine the procedure to meet stakeholder needs through consultation. .
Once refined, project staff (comprising a representative who will receive grievances at each Project site’s grievance office, and a Dili office representative) should be provided with training. These staff will accept and log incoming grievances and, if the grievance is directly related to the Project’s actions, follow a prioritisation process to identify the required remedial action.
Figure 19 illustrates a suggested procedure for managing and resolving complaints during the feasibility stage. The procedure is equally relevant during the development stage of the Project with responsibility for resolution defined between the Project Proponent and the construction contractor. It is important to ensure the following values are upheld throughout the grievance process:
• Awareness; • Accessibility; • Transparency; and • Expediency.
Stakeholder awareness of the existence of the CGM will mean that when an issue arises, community members will know where to go to address and resolve the issue. This will encourage the issue to be dealt with through the appropriate mechanism and will improve expediency of resolution and good will with the community. Therefore, when engaging with the villages and other stakeholders they should be made aware of the grievance mechanism and where or whom they should contact to access the mechanism.
Accessibility to the CGM will also enable stakeholders to air their complaints directly thereby avoiding other forums such as the media. Typically, the earlier the Proponent becomes aware of potential issues, the more efficiently these can be mitigated and contained. Furthermore early detection of potential issues can prevent problems arising later in the Project lifecycle. It will be essential to break down barriers to accessibility which, based on baseline investigations, include, geographic location, literacy levels, language and cultural appropriateness, and distrust in government or corporate structures. Recommended strategies to overcome these barriers include:
• Establishing a grievance office at Dili, surrounding sucos and the Cement Plant site where grievances might be heard, namely Caisido and Baucau. • Upon request, remote locations and vulnerable individuals (e.g. elderly and disabled) should be visited by a representative of the project on a regular basis who will disseminate information regarding the
Page 265 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Project and receive complaints from stakeholders at their village or residence. This will promote accessibility of the grievance procedure and help build a relationship with communities and encourage dialogue. • Complaints should be able to be registered via a toll-free mobile telephone number to be established by the Proponent in cooperation with local telecom provider to allow direct access to each individual to the grievance mechanism. Another option is to provide a pre-paid mobile phone to each village chief to be exclusively used for lodging grievances. The mobile phone would allow the chief to send a message to the nearest grievance office requesting the grievance officer to visit the village and record the grievance. The pre-paid mobile option needs to be further investigated in consultation with village chiefs. • Representatives should be instructed to note down complaints where the individual is unable or unwilling to write the complaint themselves. • Local people fluent in the relevant languages should be engaged as representatives. • Locals should be consulted regarding the cultural appropriateness of the complaints process. • Complainants should be given the option of maintaining anonymity throughout the complaints process.
Transparency of process cultivates trust and ensures expectations among the stakeholders are set at an appropriate level. Elements of the grievance procedure which will encourage transparency include explaining the process and timescales associated with processing a complaint, providing the complainant with a copy of the complaint when it has been submitted and ensuring the complainant is kept informed of developments in processing their complaint. Written complaints should be held at the respective grievance offices where the complainant (or a designated advocate) should be allowed access.
Expediency will enable efficient processing of complaints. In order to encourage expediency the project should set deadlines for processing complaints and a case management approach should be established among the relevant staff, with oversight from a senior individual who should be assigned responsibility for management of the grievance mechanism.
As well as committing to the values mentioned here, the project will work to International Finance Corporation (IFC) guidelines (IFC, 2011) regarding grievance mechanisms.
Page 266 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Figure 19: Grievance resolution framework
Page 267 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
18 WORK PLAN AND IMPLEMENTATION SCHEDULE
The following sections details the work plan and implementation schedule for the various phases of the Project.
Page 268 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Figure 20 Overall work plan and implementation schedule
Post project approval 2016 - 2017 *1 2018 2019 - 2055 2055 - 2060
Tasks to implement EMP Tender and Detailed Design Phase Preconstruction Construction Operations Decommissioning
Surface Water Quality Baseline Studies ●
Project Approvals ●
Stream gauges installed ●
Monitoring boreholes installed ●
Sediment transport model ●
Relocation of people and heritage sites (w here required) ●
Groundw ater Study ●
Flora and Fauna Pre-Clearance Validation ●
Relocation of affected landholders ●
Heritage pre-clearance activities ●
Complaints and grievances mechanism ●
Baseline studies for Coral, f isheries, w ater quality ●
Fauna counts and tracking ●
Water monitoring ● ● ● ●
Fisheries assessment ● ● ●
Weed management and control of invasive species ● ● ● ●
Fauna counts and tracking ●
Traff ic assessment (4 w eeks monitoring at start of phase) ● ● ● ●
Install Automated Weather Station and commence climate recording ●
Annual air quality monitoring ● ● ● ●
6-monthly groundw ater monitoring ●
Annual groundw ater monitoring ● ● ●
Accident Emergency Response Review ● ● ● ●
Review Biodiversity Action Plan ● ●
Annual Environmental Reporting to the GoTL ● ● ●
Finalise Closure Plan ●
Monitoring and reporting of f lora species abundance and coverage 5 years after mine closure ●
Record and monitor total area of re-vegetation and the species used for rehabilitation ●
5 years post closure assessment of rehabilitation success and soil health ●
Page 269 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Table 3 Detailed work plan and implementation schedule
Activity Tender and Detailed Design Phase
Preconstruction Construction Operations Decommissioning
Post project approval 2016 - 2017 2018 2019 - 2055 2055 - 2060
Clearing and earthworks movement of heavy machinery
Surface Water Quality Baseline
Studies
Project Approvals
Stream gauges installed
Monitoring boreholes installed
Sediment transport model
Relocation of people and
heritage sites (where required)
Flora and Fauna Pre-Clearance
Validation
Relocation of affected
landholders
Heritage pre-clearance activities
Complaints and grievances
mechanism
N/A N/A Accident Emergency Response
Review
Review Biodiversity Action Plan
Water monitoring
Complaints and grievances
mechanism
Weed management and control
of invasive species
Annual Environmental Reporting
to the GoTL
Construction of infrastructure (Plant, jetty, internal roads, accommodation, power plant, MOF)
Baseline studies for Coral,
fisheries, water quality
Fauna counts and tracking
Water monitoring
Fisheries assessment
Complaints and grievances
mechanism
N/A N/A
Page 270 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Weed management and
control of invasive species
Fauna counts and tracking
Movement of vehicles and people causing dust and noise
Generate electricity through Power Station or diesel generators
N/A Traffic assessment (4 weeks
monitoring at start of phase)
Install Automated Weather
Station and commence climate
recording
Annual air quality monitoring
Traffic assessment (4 weeks
monitoring at start of phase)
Undertake daily climate
measurements
Annual air quality monitoring
Traffic assessment (4
weeks at start of phase)
Undertake daily climate
measurements
Annual air quality monitoring
Traffic assessment (4 weeks at
start of phase)
Undertake daily climate
measurements
Annual air quality monitoring
Water Supply source Groundwater Study 6-monthly groundwater
monitoring
Annual groundwater
monitoring
Annual groundwater
monitoring
Annual groundwater monitoring
Operation of infrastructure (Plant, jetty, internal roads, accommodation, power plant, MOF)
N/A N/A N/A Accident Emergency
Response Review
Review Biodiversity Action
Plan
Water monitoring
Complaints and grievances
mechanism
N/A
Page 271 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Weed management and
control of invasive species
Fauna counts and tracking
Annual Environmental
Reporting to the GoTL
Shipping and movement of ships
N/A N/A Fisheries assessment
Complaints and grievances
mechanism
Fauna counts and tracking
Review Biodiversity Action
Plan
Control of invasive species
(and Ballast)
Fauna counts and tracking
N/A
Decommissioning of infrastructure and revegetation of habitat
Biodiversity Action Plan
Closure Plan
Water monitoring
Annual air quality monitoring
Traffic assessment (4 weeks at start of phase)
Monitoring and reporting of flora species abundance and coverage 5 years after mine
Page 272 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
closure
Complaints and grievances mechanism
Record and monitor total area of re-vegetation and the species used for rehabilitation for a period of 5 years following decommissioning.
5 years post closure assessment of rehabilitation success and soil health
Undertake daily climate measurements
Notes:
1. This start date is only possible if TL Cement receives the necessary project approval permits on time and based on type of financing structure in place for the project.
Page 273 301012-02135-EMP-003 Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
19 COST ESTIMATES
For the purpose of the cost estimate, the following assumptions are key:
• This estimate covers both the EMP for the Cement Plant, Jetty and Other Associated Infrastructure and the EMP for the Limestone Mine • The duration of the Project phases are: o Pre-construction = 6 months; o Construction = 2 years and 6 months; and o Operations and Decommissioning = 55 years. • Replacement and maintenance costs for monitoring equipment are excluded. • All reporting and data interpretation for Construction, Operations and Decommissioning phases are undertaken by Company technical specialists. External consultant costs have not been allowed. • The responsibility for the costs are aligned with the Company responsibility matrix in Section 8 • CPIX Inflation has not been accounted for. • Costs associated with infrastructure development recommended as a mitigation measure have been excluded. • Estimate costs only.
Page 274 301012-02135-EMP-003 Rev 2 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Table 19-1 EMP Implementation cost estimate
Aspect Activity Project Phase Mitigation and monitoring measures
Cost Estimate (USD)
Air Quality Earthworks Heavy machinery movement Vehicles, buses and cars movement
Pre-construction Automated Weather Station setup and installation Monthly data download and interpretation
$150,000
Earthworks Heavy machinery movement Vehicles, buses and cars movement
Construction Monthly data download and interpretation
$24,000
Operating cement plant Operating power plant
Operation Monthly data download, 6-monthly interpretation
$550,000
Earthworks Heavy machinery movement Vehicles, buses and cars movement
Decommissioning Monthly data download, 6-monthly interpretation
$24,000
Noise Earthworks Heavy machinery movement Vehicles, buses and cars movement
Pre-construction Twice per year measurements at receptors
$10,000
Earthworks Heavy machinery movement Vehicles, buses and cars movement
Construction Twice per year measurements at receptors
$20,000
Operating cement plant Operating power plant
Operation Annual measurements at receptors $550,000
Earthworks Heavy machinery movement Vehicles, buses and cars movement
Decommissioning Twice per year measurements at receptors
$20,000
Page 275 301012-02135-EMP-003 Rev 2 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Aspect Activity Project Phase Mitigation and monitoring measures
Cost Estimate (USD)
Water Quality Earthworks Heavy machinery movement Vehicles, buses and cars movement Drilling of water supply borehole
Pre-construction Baseline Marine Water Quality survey (coral health, risk from ballast) Monthly sampling at 5 locations, interpretation 4x per year
$124,000
Earthworks Heavy machinery movement Vehicles, buses and cars movement Abstraction of water from the water supply borehole
Construction Monthly sampling at 5 locations, interpretation 4x per year
$48,000
Operating cement plant Operating power plant Abstraction of water from the water supply borehole
Operation Monthly sampling at 5 locations, interpretation 4x per year
$1,300,000
Earthworks Heavy machinery movement Vehicles, buses and cars movement Abstraction of water from the water supply borehole
Decommissioning Monthly sampling at 5 locations, interpretation 4x per year
$48,000
Water Quantity (flows instreams, springs)
Earthworks Heavy machinery movement Vehicles, buses and cars movement Drilling of water supply borehole
Pre-construction Detailed hydrological model and 2x monitoring boreholes in the Limestone (Mine area) Flow meters and stream gauging units x4 Measurement and interpretation monthly and interpretation 4x per year
$400,000
Page 276 301012-02135-EMP-003 Rev 2 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Aspect Activity Project Phase Mitigation and monitoring measures
Cost Estimate (USD)
Earthworks Heavy machinery movement Vehicles, buses and cars movement Abstraction of water from the water supply borehole
Construction Measurement and interpretation monthly and interpretation 4x per year
$20,000
Operating cement plant Operating power plant Abstraction of water from the water supply borehole
Operation Measurement and interpretation monthly and interpretation 4x per year
$550,000
Earthworks Heavy machinery movement Vehicles, buses and cars movement Abstraction of water from the water supply borehole
Decommissioning Measurement and interpretation monthly and interpretation 4x per year
$20,000
Coastal processes
Earthworks Heavy machinery movement Vehicles, buses and cars movement Construction of MOF Drilling of sea floor Removal of corals
Pre-construction Sediment transport model Setup monitoring reference stations (imagery)
$250,000
Earthworks Heavy machinery movement Vehicles, buses and cars movement Abstraction of water from the water supply borehole
Construction Every 6 months image capture and interpretation
$40,000
Page 277 301012-02135-EMP-003 Rev 2 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Aspect Activity Project Phase Mitigation and monitoring measures
Cost Estimate (USD)
Operating conveyor belt Operating jetty and MOF Abstraction of water from the water supply borehole
Operation Every 6 months image capture and interpretation
$550,000
Earthworks Heavy machinery movement Vehicles, buses and cars movement
Decommissioning Every 6 months image capture and interpretation
$40,000
Flora Earthworks Heavy machinery movement Vehicles, buses and cars movement Drilling of water supply borehole
Pre-construction Pre-clearance vegetation distribution mapping Post clearance area survey
$80,000
Earthworks Heavy machinery movement Vehicles, buses and cars movement Abstraction of water from the water supply borehole
Construction Post clearance area survey Ongoing capture of clearing area information
$20,000
Operating cement plant Operating power plant Abstraction of water from the water supply borehole
Operation Progressive rehabilitation costs (material and equipment) Post operations vegetation survey Rehabilitation success survey (post closure)
$5,500,000
Earthworks Heavy machinery movement Vehicles, buses and cars movement Abstraction of water from the water supply borehole
Decommissioning Post rehabilitation area survey Ongoing capture of rehabilitation area information
$20,000
Page 278 301012-02135-EMP-003 Rev 2 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Aspect Activity Project Phase Mitigation and monitoring measures
Cost Estimate (USD)
Fauna Earthworks Heavy machinery movement Vehicles, buses and cars movement Drilling of water supply borehole
Pre-construction Fauna relocation expert – standby for pre- construction duration
$100,000
Earthworks Heavy machinery movement Vehicles, buses and cars movement Abstraction of water from the water supply borehole
Construction Fauna management records as required Annual environmental reporting
$20,000
Operating cement plant Operating power plant Abstraction of water from the water supply borehole
Operation Fauna management records as required Annual environmental reporting
$550,000
Earthworks Heavy machinery movement Vehicles, buses and cars movement Abstraction of water from the water supply borehole
Decommissioning Fauna management records as required Annual environmental reporting
$20,000
Marine Fauna Earthworks Heavy machinery movement Vehicles, buses and cars movement Construction of MOF Drilling of sea floor Removal of corals
Pre-construction Pre-construction baseline Marine Fauna survey (crocodiles, turtles, megafauna) Ongoing capture of fauna records
$150,000
Page 279 301012-02135-EMP-003 Rev 2 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Aspect Activity Project Phase Mitigation and monitoring measures
Cost Estimate (USD)
Earthworks Heavy machinery movement Vehicles, buses and cars movement Abstraction of water from the water supply borehole
Construction Ongoing capture of fauna records Relocation of fauna encountered during construction
$40,000
Operating conveyor belt Operating jetty and MOF Abstraction of water from the water supply borehole
Operation Ongoing capture of fauna records $550,000
Earthworks Heavy machinery movement Vehicles, buses and cars movement
Decommissioning Ongoing capture of fauna records Relocation of fauna encountered during decommissioning
$40,000
Marine Habitats
Earthworks Heavy machinery movement Vehicles, buses and cars movement Construction of MOF Drilling of sea floor Removal of corals
Pre-construction Pre-construction marine habitat reference site establishment (corals) and reporting
$120,000
Earthworks Heavy machinery movement Vehicles, buses and cars movement Abstraction of water from the water supply borehole
Construction Post-construction marine habitat survey
$120,000
Operating conveyor belt Operating jetty and MOF Abstraction of water from the water supply borehole
Operation 5-yearly survey of marine habitat incl. final survey on completion (11 occurrences)
$1,300,000
Page 280 301012-02135-EMP-003 Rev 2 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Aspect Activity Project Phase Mitigation and monitoring measures
Cost Estimate (USD)
Earthworks Heavy machinery movement Vehicles, buses and cars movement
Decommissioning Post-decommissioning marine habitat survey
$120,000
Traffic Earthworks Heavy machinery movement Vehicles, buses and cars movement Drilling of water supply borehole
Pre-construction Traffic monitoring equipment (1 unit) Traffic census (1 instance)
$20,000
Earthworks Heavy machinery movement Vehicles, buses and cars movement Abstraction of water from the water supply borehole
Construction Traffic census (1 instance) $10,000
Operating cement plant Operating power plant Abstraction of water from the water supply borehole
Operation Traffic census (5 instance) $50,000
Earthworks Heavy machinery movement Vehicles, buses and cars movement Abstraction of water from the water supply borehole
Decommissioning Traffic census (1 instance) $10,000
Community Clearing of land Relocation and resettlement Earthworks Heavy machinery movement Vehicles, buses and cars movement
Pre-construction Monthly community engagement events Monthly grievances committee review and reporting Community engagement survey (1 instance) Corporate social responsibility support and implementation
$120,000
$250,000
Page 281 301012-02135-EMP-003 Rev 2 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Aspect Activity Project Phase Mitigation and monitoring measures
Cost Estimate (USD)
Earthworks Heavy machinery movement Vehicles, buses and cars movement
Construction Monthly community engagement events Monthly grievances committee review and reporting Community engagement survey (1 instance) Community awareness programmes Training of local people # development costs in Section 19.1 below
$480,000
Operating cement plant Operating power plant
Operation Annual community engagement events Quarterly grievances committee review and reporting Community engagement survey (1 instance) Community awareness programmes Corporate social responsibility support and implementation Training of local people (over the life of operations – 58 years)# development costs in Section 19.1 below
$1,100,000
Earthworks Heavy machinery movement Vehicles, buses and cars movement
Decommissioning Monthly community engagement events Monthly grievances committee review and reporting Community engagement survey (1 instance) Community awareness programmes Corporate social responsibility support and implementation
$480,000
Total cost mitigation and monitoring implementation # $15,758,000
Page 282 301012-02135-EMP-003 Rev 2 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
19.1 Infrastructure costs
Item Cost (USD) Waste water treatment plant $ 340,000 Training centre (20 years) $22,000,000 Drainage system (bunds and drains) $ 900,000 PPE $ 20,000 Fire response system $ 840,000 Raised Conveyor system $ 5,000,000 Instrumentation $ 150,000 Water supply borehole and infrastructure $ 120,000 Total – All infrastructure for mitigation $29,370,000
Page 283 301012-02135-EMP-003 Rev 2 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
20 REVIEW OF THE EMP
The Cement Plant, Jetty and Other Associated Infrastructure EMP will be reviewed at the following key project milestones:
• Completion of the pre-construction phase and additional specialist studies; • Completion of the construction phase; • Award of the Operations contract to incorporate operator-specific information; and • Every 5 years at minimum during Operations phase;
The Cement Plant, Jetty and Other Associated Infrastructure EMP will be reviewed following the events where:
• Equipment or procedural changes result in a positive or negative change to the project environmental and social risks; • Monitoring results indicate that a change to the mitigation and monitoring regime is required to manage the project impacts; • Legislative changes in country require update to the EMP; and • There is a change to the responsibility matrix for EMP implementation.
The review will follow standard QA/QC document management and review processes with the Approver being technically responsible for the content.
The EMP will be reviewed where the changes in the EMP have influenced the following key factors (Section 3):
• Displacement / Resettlement; • Cultural Heritage; • Traffic; • Water; and • Legally responsible person.
Page 284 301012-02135-EMP-003 Rev 2 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
21 NON-TECHNICAL SUMMARY
21.1 Introduction
TL Cement LDA, a privately-owned company, proposes to construct a new cement manufacturing plant in Baucau Municipality, Timor-Leste. In accordance with Decree Law 05/2011, Environmental Licensing Law (ELL), the TL Cement LDA has submitted an Application for Environmental License for this project to the National Directorate of the Environment (NDE). The Baucau Cement Project will consist of:
1. Cement Plant, Marine Jetty, Conveyor Belt, and associated infrastructure
2. Limestone Mine
The NDE has classified the project as a “Category A” project, and must go through the environmental assessment process, including preparation of an Environmental Impact Statement (EIS).
21.2 Purpose of this document
This document is a Non-Technical Summary (NTS) of the EIS for the Cement Plant, Marine Jetty, Conveyor Belt and associated infrastructure. This NTS presents the assessment of the potential environmental and social impacts, proposed control measures to mitigate and manage the impacts, and remaining impacts of the project.
21.3 Benefits of the project
The benefits of the project include direct employment with 1000 permanent jobs expected during operations. The project aims to develop local capacity and will develop a training centre. Other benefits include indirect employment to local community members, through the multiplier effect due to downstream socio-economic benefits and consequent improvement in the living conditions of local population in the project area. It is estimated that at least 2000 more jobs can be created through indirect activities during operations with local business opportunity creation in supplying goods and services to TL Cement and its employees.
The location of the Baucau Cement Project and its components can be seen in Figure 21.
Page 285 301012-02135-EMP-003 Rev 2 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Figure 21: Location of Baucau Cement Project components
Page 286 301012-02135-EMP-003 Rev 2 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
21.4 Key Project Characteristics
The key project characteristics are listed in Table 2.
Table 2: Summary of Baucau Cement Project Characteristics
Element Description
Project life 50 years at full production capacity
Investment $400 million USD
Largest industrial project undertaken in Timor-Leste to date
Annual production
1.65 million tons per annum (mtpa) of Portland cement clinker (main component of cement (Figure 22)):
• 0.5 mtpa will be combined with the other required components to make Ordinary Portland Cement (a complete cement mixture (Figure 23)) to be sold locally in Timor Leste and Australia (~70 % in Timor-Leste and ~30% to Australia)
• 1.15 mtpa will be packaged as Portland cement clinker and exported by ships to Australia
Cement types produced
Figure 22: Portland cement clinker
Figure 23: Ordinary Portland cement
List of major project components
Cement processing plant (650 m x 400 m)
• Including a construction camp and worker residential area (35 containers of 40 feet in length. 1 office unit, one cafeteria unit, 5 accommodation units each with 24 rooms (120 rooms in total).
Fully Enclosed Pipe Conveyor Belt (1.5 km long)
Marine Jetty (500 m long)
Page 287 301012-02135-EMP-003 Rev 2 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Area of disturbance
Cement Processing Plant + Captive Power Plant + Camp – 80 ha- Note all in one compound
Marine Jetty + pipe conveyor - 1.5 ha
Power Supply 30 Mega Watt Biomes and Recycle Power Generation (clean coal) plant
Water Supply Groundwater from borewells at the Uaidei River
• 0.35 ML/day for construction
• 3.15 ML/day for operation
Number of jobs 3000 jobs during peak of construction
1000 permanent jobs during operations
21.5 Operations
When in operation, limestone will be taken to the Cement Plant for processing. Some other cement components will be shipped to the Marine Jetty and put on a fully enclosed Pipe Conveyor Belt and taken to the Cement Plant to be processed along with the limestone and turned into Portland cement clinker.
Portland cement clinker is small lumps that are the basic ingredient of cement (Figure 22). The Portland cement clinker will then be taken by the same full enclosed Pipe Conveyor Belt from the cement plant to the Port where it will be loaded onto ships from a Marine Jetty.
A similar example of a conveyor and marine jetty can be seen in Figure 24: The Baucau Cement Plant Project once in operation
.
Page 288 301012-02135-EMP-003 Rev 2 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Figure 24: The Baucau Cement Plant Project once in operation
Page 289 301012-02135-EMP-003 Rev 2 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
21.6 Project Phases
The project will have four phases: Pre-construction (18 months), Construction (2 years), Operations (over 35 - 50 years) and Decommissioning (5 years). A summary of the activities to be undertaken during each phase and potential impacts are presented in Table 3. In addition, the potential impacts that could occur as a result of the activities during each phase have been outlined below. Of these, key impacts have been identified as either a ‘Medium’ or ‘High’ risk, and have been discussed further in Section 21.7, along with identified mitigation measures to manage and reduce the impacts.
Page 290 301012-02135-EMP-003 Rev 2 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Table 3: Summary of Baucau Cement Project phase characteristics and potential impacts
Phase Activities Potential Impacts (risk)
Pre-construction
(Duration of approximately 18 months)
• Clearing of fence lines & Installing fences
• Clearing of access roads internal to the project area
• Establishment of Laydown areas and preliminary office infrastructure such as portable toilets and shipping containers for storage
• Relocation of people and animals within the project area
• Exploratory water source drilling and installation of water supply wells.
• Installation of power supply infrastructure corridors via clearing, excavation and pegging
• Geological studies including bore drilling and pit surveys
• Weir installation in streams
• Establishment of exclusion zones around fishing areas, boreholes and springs (known impact, appropriation of natural asset)
• Construction of material offloading facility (construction jetty)
• Clearing of natural vegetation (Low)
• Displacement of people (Medium to High)
• Exclusion of people from fishing grounds, boreholes and springs (Low)
• Increased traffic and transport (Low)
• Increased noise and increase in air pollution (Low)
• Disturbance of heritage sites (Low)
• Increased groundwater usage (Low)
• Clearing of coral (Low)
• Disturbance of cultural heritage at the mine site (Medium to High)
Construction
(Duration of approximately 2 years)
• Clearing of the Cement site/area - Excavation, Piling, Pouring of concrete foundations and permanent establishment of accommodation, offices and workshops
• Clearing of natural vegetation (Low)
• Displacement of people (High)
• Visual impact (High)
Page 291 301012-02135-EMP-003 Rev 2 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
• Building structures in concrete and steel for cement equipment
• Developing internal cement plant roads and drainage
• Establishment of bunds, hauling roads, drainage areas and mine stope markers ahead of mining commencing
• Installation of cement plant equipment
• Construction of power plant
• Installation of conveyor system
• Piling and construction of jetty
• Construction of internal access roads and haul roads
• Discharge into landfill – solid and liquid waste
• Increased noise, increased air pollution (Low)
• Increased traffic and transport (Low)
• Increased light and heavy vehicle interaction with pedestrians and motorbikes (Medium)
• Increased groundwater usage (Low)
• Increase in waste (Low)
• Clearing of coral (Low)
Operation
Duration of approximately 35-50 years)
• Operating conveyor transporting material to/from Jetty
• Operational cement plant
• Operational power plant operational
• Operational jetty and MOF
• Maintenance clearing within the plant site boundary (e.g. tree lopping for power lines)
• Discharge to landfill – solid waste
• Increased traffic and transport (Medium)
• Increased noise, increased air pollution (Low)
• Disturbance to community from blasting (Medium)
• Increased light and heavy vehicle interaction with pedestrians and motorbikes (Medium)
Page 292 301012-02135-EMP-003 Rev 2 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
• Increased groundwater usage (Medium)
• Increased pollution (waste water outfall) (Low)
De-Commissioning
(Duration of approximately 5 year)
• Rehabilitation • Reduction in employment levels
• Continued employment during rehabilitation and closure of the mine
• Negative impact on local economy
• Rehabilitated landscape-It is possible to create tourism venue during rehabilitation based on local community needs
Page 293 301012-02135-EMP-003 Rev 2 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
21.7 Key Potential Impacts and Mitigation Measures
There are a number of aspects to the project that have the potential to cause 'environmental and social impacts during different phases of the project. Of these, key aspects and their impacts have been identified to be a ‘Medium’ or ‘High’ risk. These key aspects, along with mitigation measures identified to manage and reduce the impacts, and monitoring and reporting to ensure compliance, have been outlined in below.
Page 294 301012-02135-EMP-003 Rev 2 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Stage Potential Key Impact Mitigation Measure Responsibility Parameter to be measured Frequency Cost of Mitigation Measure USD
Pre Construction
Clearing of vegetation
Limit area to be cleared TL Cement Construction contractor
Check that clearing is within the boundary
Daily during clearing activities Compensation per the Resettlement Plan : $15,000 estimate
Monitoring and weed eradication costs: $5.6M
Fauna relocation and monitoring, re-introduction and elimination of pests: $670k
Rehabilitation costs (Labour and materials): $?
Air quality and dust Dust suppression techniques include water spraying and enclosing equipment
TL Cement Construction contractor
PM10 and PM2.5 at 3 monitoring stations
Measurements every 6 months Compensation per the Resettlement Plan : $15,000 estimate
Dust suppression sprayer and labour: $? 2000/month
Cost of illness and loss of productivity: $?
Noise Noise limitation techniques include aprons and enclosing
TL Cement Construction
Noise Levels at 3 monitoring stations
Measurements every 6 months Compensation per the Resettlement Plan : $15,000
Page 295 301012-02135-EMP-003 Rev 2 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Stage Potential Key Impact Mitigation Measure Responsibility Parameter to be measured Frequency Cost of Mitigation Measure USD
equipment
contractor estimate
Monitoring costs: $580k
Cost of illness and loss of productivity: $?
Water quality and quantity
Rehabilitation in the event of a spill or contamination event
Spill and contamination mitigation measures
TL Cement Construction contractor
Flow meters / stream gauges at the Bucoli River (1.6km west) and at Uaimatabai, Uaisa and Waino springs.
Water quality and quantity measurements at monitoring boreholes, key spring receptors at Waiono, Uaimatabai and Uaisa.
Every 6 months
Monthly water quality and quantity measurements
Water Quality Monitoring costs: $1,4M
Water Quantity Monitoring costs : $970k
Rehabilitation costs in the event of a spill: $?
Construction
Air quality and dust Dust suppression techniques include water spraying and enclosing equipment
TL Cement Construction contractor
PM10 and PM2.5 at 3 monitoring stations
Measurements every 6 months Dust suppression sprayer and labour: $? 2000/month
Cost of illness and loss of productivity: $?
Noise Noise limitation techniques include aprons and enclosing equipment
TL Cement Construction contractor
Noise Levels at 3 monitoring stations
Measurements every 6 months Monitoring costs: $580k
Cost of illness and loss of productivity: $?
Page 296 301012-02135-EMP-003 Rev 2 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Stage Potential Key Impact Mitigation Measure Responsibility Parameter to be measured Frequency Cost of Mitigation Measure USD
Water quality and quantity
Rehabilitation in the event of a spill or contamination event
Spill and contamination mitigation measures
TL Cement Construction contractor
Flow meters / stream gauges at the Bucoli River (1.6km west) and at Uaimatabai, Uaisa and Waino springs.
Measurements at monitoring boreholes, key spring receptors at Waiono, Uaimatabai and Uaisa.
Every 6 months
Monthly water quality and quantity measurements
Water Quality Monitoring costs: $1,4M
Water Quantity Monitoring costs : $970k
Rehabilitation costs in the event of a spill: $?
Operation
Air quality and dust Dust suppression techniques include water spraying and enclosing equipment
TL Cement Operator PM10 and PM2.5 at 3 monitoring stations
Measurements every 12 months
Dust suppression sprayer and labour: $? 2000/month
Cost of illness and loss of productivity: $?
Noise Noise limitation techniques include aprons and enclosing equipment
TL Cement Operator Noise Levels at 3 monitoring stations
Measurements every 6 months Monitoring costs: $580k
Cost of illness and loss of productivity: $?
Water quality and quantity
Rehabilitation in the event of a spill or contamination event
Spill and contamination
TL Cement Operator Flow meters / stream gauges at the Bucoli River (1.6km west) and at Uaimatabai, Uaisa and Waino
Every 6 months
Water Quality Monitoring costs: $1,4M
Water Quantity Monitoring Page 297 301012-02135-EMP-003 Rev 2 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Stage Potential Key Impact Mitigation Measure Responsibility Parameter to be measured Frequency Cost of Mitigation Measure USD
mitigation measures springs.
Measurements at monitoring boreholes, key spring receptors at Waiono, Uaimatabai and Uaisa.
Monthly water quality and quantity measurements
costs : $970k
Rehabilitation costs in the event of a spill: $?
Decommissioning
Air quality and dust Dust suppression techniques include water spraying and enclosing equipment
TL Cement Operator PM10 and PM2.5 at 3 monitoring stations
Measurements every 6 months Dust suppression sprayer and labour: $? 2000/month
Noise Noise limitation techniques include aprons and enclosing equipment
TL Cement Operator Noise Levels at 3 monitoring stations
Measurements every 6 months Compensation per the Resettlement Plan : $15,000 estimate
Monitoring costs: $580k
Cost of illness and loss of productivity: $?
Water quality and quantity
Rehabilitation in the event of a spill or contamination event
Spill and contamination mitigation measures
TL Cement Operator Flow meters / stream gauges at the Bucoli River (1.6km west) and at Uaimatabai, Uaisa and Waino springs.
Monthly water quality and quantity
Every 6 months
Monthly water quality and
Water Quality Monitoring costs: $1,4M
Water Quantity Monitoring costs : $970k
Rehabilitation costs in the Page 298 301012-02135-EMP-003 Rev 2 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Stage Potential Key Impact Mitigation Measure Responsibility Parameter to be measured Frequency Cost of Mitigation Measure USD
measurements at monitoring boreholes, key spring receptors at Waiono, Uaimatabai and Uaisa.
quantity measurements event of a spill: $?
Table 4: Key Potential Impacts, Mitigation Measures and Monitoring and Reporting
Page 299 301012-02135-EMP-003 Rev 2 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
21.8 Stakeholder Engagement Process
This project has involved consultation with people who may be affected by the project and other project stakeholders. This includes the public, such as those who will be directly affected, women and vulnerable groups. As can be seen by Figure 25, public engagement consultation is a continuous process throughout the EIA process and has already been initiated.
The public consultation process for the environmental assessment is being carried out in accordance with the Draft Ministerial Diploma for the “Regulation on the Public Consultation Procedures and Requirements during the Environmental Assessment Process” dated 22 April 2014.
Figure 25: Stakeholder Engagement and Consultation
The stakeholder consultation list to date is shown in Table 5.
Table 5: Consultation Summary
Stakeholder
Government Ministries
Ministry of Commerce, Industry, and Environment
• National Directorate for Environment
Ministry of Petroleum and Mineral Resources
• National Directorate of Mines and Minerals
• Institute of Petroleum and Geology
Ministry of Justice
• National Directorate of Land, Property and Cadastral Services
Ministry of Finance
Page 300 301012-02135-EMP-003Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Ministry of Planning and Strategic Investment
Ministry of Public Works, Transport and Communications
• Directorate of Roads, Bridges, and Flood Control
• Directorate of Ports/APORTIL
Ministry of Tourism, Arts and Culture
State Secretariat of Arts and Culture
Municipality (District) Government
Baucau Municipality (formerly Baucau District Administration)
Baucau Administrative Post (formerly Baucau Sub-District Administration)
Baucau Municipality Police District
Baucau Municipality Directorate of Land, Property and Cadastral Services
Baucau Municipality Directorate of Environment
Vemasse Administrative Post
Local Government
Suco Council Tirilolo
Suco Council Triloca
Suco Council Vemasse-Vila
Suco Council Caibada
Suco Council Bahu
Suco Council Wailili
Suco Council Bucoli
Suco Council Fatumaca
TL Cement and Worley Parsons conducted follow up consultation in the local community during site visits in February 2015 and May 2015.
These meetings were attended by the following community members:
• Chefe Suco Tirilolo: Ricardo Ernesto Belo (RB)
• Chief of Community Police in Suco Tirilolo: Norberta Belo (NB)
• Chefe Aldeia Lialailesu: Cipriano Belo (CB)
• Chefe Aldeia Parlamentu: Manuel Belo (MB)
• Chief of Traditional Practice (Lia-Nain): Duarte Belo (DUB)
• Secretary of Suco Tirilolo: Zeca Belo (ZB)
Representative of youth of Suco Tirilolo: Damião Belo (DB)
Local Communities
Chefes de Aldeia
Lia-Nain
Page 301 301012-02135-EMP-003Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Local Youth Organizations
Local Women’s Organizations
Local Fishermen’s Organization
Baucau Parish
Civil Society/Local NGOs
Lao Hamutuk
Luta Hamutuk
Haburas
Rede ba Rai
Belun
Kapeliwa
Other Organizations
International Finance Corporation
Conservation International
BESIK (Bee, Saneamentu no Ijiene iha Komunidade) Rural Water Program
End of Non Technical Summary
Page 302 301012-02135-EMP-003Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
22 REFERENCES
Advisian (2016). Baucau Cement Project: Surface Water Impact Assessment Report. Unpublished report for WorleyParsons, Feb 2016.
BBS (2015a). Air Quality Impact Assessment study of Clinker Cement Project Baucau – Timor-Leste. Final Draft Report No: 15.3380-DR-002 Rev B, Oct 2015.
BBS (2015b) Noise Impact Assessment study of Clinker Cement Project Baucau – Timor-Leste. Final Draft Report No: 15.3380-FDR-002 Rev B, Oct 2015.
BBS (2015c). Traffic Impact Assessment Study of Clinker Cement Project Baucau-Timor-Leste. Final Draft Report No:15.3380-FD-002, Rev B, Oct 2015.
BBS (2015d). Social Impact Assessment Study of Clinker Cement Project Baucau – Timor-Leste. Final Draft Report No: 15.3380-DR-002, Rev. C, Oct 2015.
BOM (2015). What are El Niño and La Niña events? Online publication of the Australian Bureau of Meteorology (BOM) [Accessed 3 Dec 2015] http://www.bom.gov.au/climate/enso/history/ln-2010-12/ENSO-what.shtml
CDU (2009) The Timor-Leste Coastal / Marine Habitat Mapping for Tourism and Fisheries Development Project. A joint research project by Charles Darwin University, Northern Territory Government, Republica Democratica de Timor-Leste, Australian National University, the Australian Government and the Australian Institute of Marine Science. http://www.cdu.edu.au/sites/default/files/research/docs/36091-executive-summary-secured-final.pdf
Conservation International (2013). A Marine Rapid Assessment (MRAP) of Timor-Leste, 14-23 August 2012. Report prepared by Conservation International, Edited by MV Erdmann and C Mohan.
Cowie, I. 2006. Assessment of floristic values of the proposed Jaco-Tutuala-Lore National Park, TimorLeste (East Timor). . Northern Territory Herbarium, Darwin.
CSIRO (2010). Climate change in Timor-Leste. A brief overview on future climate projections. Prepared by the CSIRO.
CSIRO (2011). Current and future climate of Timor-Leste, International Climate Change Adaption Initiative. A report for the Pacific Climate Change Science Program partners [Accessed online 3 December 2015] http://www.pacificclimatechangescience.org/wp-content/uploads/2013/06/5_PCCSP_East_Timor_8pp.pdf
Dethmers K, Chatto R, Meekan M, Amaral A, de Cunha C, de Carvalho N, Edyvane K (2012) Marine Megafauna Surveys in Timor Leste Coastal-Marine Habitat Mapping, Tourism and Fisheries Development Project. Ministry of Agriculture & Fisheries, Government of Timor Leste.
DotE (2015) Lead. Online database for the Australian Department of the Environment. [Accessed 10 December 2015] https://www.environment.gov.au/protection/chemicals-management/lead
Page 303 301012-02135-EMP-003Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Edyvane K, McWilliam A, Quintas J, Turner A, Penny S, Teixeira I, Pereira C, Tibirica Y, Birtles A. (2009) Coastal and Marine Ecotourism Values, Issues & Opportunities on the North Coast of Timor Leste – Final Report. Ministry of Agriculture and Fisheries, National Directorate of Tourism, Government of Timor Leste.
EPA (2015a). National Ambient Air Quality Standards (NAAQS). Online database for the US Environmental Protection Authority. [Accessed 9 December 2015, last updated 10 July 2015] http://www3.epa.gov/ttn/naaqs/criteria.html
EPA (2015b) Particulate Matter. Online database for the US Environmental Protection Agency. [Accessed 9 December 2015. Last updated 9 November 2015] http://www3.epa.gov/pm/
EPA (2015c) Nitrogen Oxides (NOx) Control Regulations. Online database for the US Enironmental Protection Authority [Accessed 9 December 2015, last updated 12 September 2015] http://www3.epa.gov/region1/airquality/nox.html
EMEP-MSC-W (1995) Status of the development of the multilayer Eulerian model: a) Model description; b) A new method of calculating mixing heights; c) Model results for sulphur transport and deposition in Europe for 1992 in the 50 km grid. http://www.atmos-chem-phys.net/12/7825/2012/acp-12-7825-2012.pdf
European Commission (2015) Air Quality Standards. Website on Environmental Air Quality Standards. Available at: http://ec.europa.eu/environment/air/quality/standards.htm. Accessed 13 October 2015
Fabricius KE & Alderslade P (2001) Soft Corals and Sea Fans: A comprehensive guide to the tropical shallow water genera of the central-west Pacific, the Indian Ocean and the Red Sea. Australian Institute of Marine Science, Townsville. 264 pp. ISBN: 0 642 322104.
FAO (2015) Food and Agriculture Organisation (FAO) of the United Nations. Fishery and Aquaculture Country Profiles (The Democratic Republic of Timor-Leste). Available online at: http://www.fao.org/fishery/facp/TLS/en#CountrySector-PostHarvest . Accessed 13 October 2015
Goines, L and Hagler, L (2007). Noise Pollution: A Modern Plague. Southern Medical Journal, vol. 100, issue 3, pgs 287-294 [http://www.medscape.com/viewarticle/554566_3]
Grantham HS, Watson JEM, Mendes M, Santana F, Fernandez G, Pinto P, Ribeiro LM and da Cunha Barreto C (2010) National Ecological Gap Assessment for Timor-Leste 2010. CNRM Solutions report for the Department of Protected Areas and National Parks of Timor-Leste, National Directorate of Forestry, Ministry of Agriculture and Fisheries. [file:///C:/Users/katherine.swain/Downloads/tl_nega_final%20(2).pdf]
Holtec. 2015a. Mine Closure Plan for Bucoli Limestone Deposit – Block I-1, Baucau District, Timor-Leste. September 2015.
Jocson, J. M. U., Jenson, J. W. & Contractor, D. N. (2002) Recharge and aquifer response: northern Guam lens aquifer, Guam, Mariana Islands. J. Hydrol. 260, 231–254.
MAFF (2004) Ministry of Agriculture, Forestry and Fisheries website. [Accessed 11 December 2015, last updated 2004] http://gov.east-timor.org/MAFF/index.htm
Page 304 301012-02135-EMP-003Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Monk KA, Y De Fretes, and G Reksodinharjo-Lilley (1997). The Ecology of Nusa Tenggara and Maluku. Periplus Editions, Singapore.
Oliveira NV (2015). Baucau Cement Plant, Assessing the Impact on Archaelogical and Cultural Heritage Sites. Unpublished report for WorleyParsons, August 2015
Rong Y, Park J, Duggan D, Mahdyiar M and Bazzuro P (2012). Probabilistic Seismic Hazard Assessment for the Pacific Island Counties. 15 WCEE, Lisboa 2012 [http://www.iitk.ac.in/nicee/wcee/article/WCEE2012_2521.pdf]
Royal Hakoning DHV (2015). Report on TL Cement Jetty Facilities, for TL Cement LDA, Ref. No. M&WSA1071R001F01, August 2015.
The World Bank (2015). Reducing the Risk of Disasters and Climate Variability in the Pacific Islands: Timor-Leste Country Assessment. A Report by the Global Facility for Disaster Reduction and Recovery, The World Bank and SOPAC. Washington DC [Accessed 4 December 2015] http://siteresources.worldbank.org/INTPACIFICISLANDS/Resources/TIMOR_LESTE_ASSESSMENT.pdf
Trainor, C. R. 2010. Timor’s fauna: the influence of scale, history and land-use on faunal patterning. . Faculty of Education, Health and Science. Charles Darwin University, Darwin.
Trainor, C. & Easton, B. (2015). Baucau Cement Clinker Plant Vegetation and Fauna Survey Report. Prepared for WorleyParsons, August 2015.
Trainor, C. (2015) Baucau Cement Clinker Plant, Mine I-2 and II-1 Desktop study of vegetation and fauna. Report to WorleyParsons, September 2015.
UNDP (2010). Disaster Risk and Hazard Map Analysis for Timor-Leste: An overview of existing risk maps. Disaster Risk Management Institutional and Operations Systems Development in Timor-Leste Project, UNDP. United Nations Disaster Planning, published on the Global Risk Information Platform, January 2010 [http://www.gripweb.org/gripweb/sites/default/files/Hazard_and_Risk_Map_Analysis_for_Timor_Jan'10_Ver_4_(3).pdf]
US DOT (2014). Lane Width. Mitigation Strategies for Design Exceptions. Website for the US Department of Transport, Federal Highway Administration. [Accessed 21 December 2015, last updated 15 October 2014] http://safety.fhwa.dot.gov/geometric/pubs/mitigationstrategies/chapter3/3_lanewidth.cfm
Valdivieso L M (2001). East Timor: Macroeconomic Management on the Road to Independence but cant work it out. See here http://www.highbeam.com/doc/1G1-73849042.html.
WHO (1999) Guidelines on Community Noise. A publication of the World Health Organization [http://www.who.int/docstore/peh/noise/guidelines2.html]
WHO (2005) WHO Air Quality Guidelines for Particulate Matter, Ozone, Nitrogen Dioxide and Sulphur Dioxide, Global update for the World Health Organization, 2005
Wikramanayake E, E Dinerstein, C J Loucks, D Olson, J Morrison, J Lamoreux, M McKnight and P Hedao. (2002a). Terrestrial Ecoregions of the Indo-Pacific: A Conservation Assessment. Island Press.
Page 305 301012-02135-EMP-003Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
Wikramanayake E, E Dinerstein, G. Loucks, D. Olson, J. Morrison, J. Lamoreux, M. McKnight, and P.
Hedao. 2002b. Ecoregions in ascendance: reply to Jepson and Whittaker. Conservation Biology
16:238-243.
WorleyParsons (2015a) Coastal Processes Desktop Study - Marine Facilities, Unpublished report 301012-02135 – CS-REP-0001) for TL Cement LDA, 23 September 2015
WorleyParsons (2015b), Baucau Cement Plant Marine Jetty, Benthic Habitat Survey and Fisheries Assessment Report. Unpublished report for WorleyParsons, October 2015.
WorleyParsons (2015c) Timor-Leste Cement Project : Preliminary Groundwater Environmental Impact Assessment.
Page 306 301012-02135-EMP-003Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
23 ACRONYMS / ABBREVIATIONS
$ United States dollar
% Percentage
< Less than
µg/L Microgram per litre
µg/m3 Micrograms per cubic meter
µg/m3 Micrograms per cubic meter
ADB Asian Development Bank
AWS Automated Weather Station
BAP Biodiversity Action Plan
BAT Best Available Technologies
CEMP Construction Environmental Management Plan
CFB Circulating Fluidized Bed
CGM Complaints and Grievances Mechanism
CHMP Cultural Heritage Management Plan
CO Carbon monoxide
CPIX Consumer Price Index
dB Decibels
DBRFC Directorate of Bridges, Roads, and Flood Control
DLPCS Directorate of Land, Property and Cadastral Services
DWRQC Directorate of Water Resources and Quality Control
EA Environmental Assessment
EBL Environment Basic Law
EIS Environmental Impact Statement
ELL Environmental Licensing Law
EMF Environmental Management Framework
Page 307 301012-02135-EMP-003Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
EMP Environmental Management Plan
EMS Environmental Management System
ERP Emergency Response Plan
EP Emergency Plan
GPS Global positioning satellite
ha Hectares
hr hour
HSE Health, Safety and Environment
IFC International Finance Corporation
IAAQS International Ambient Air Quality Standards
IPG Institute of Petroleum and Geology
km Kilometre
m/s Metres per seconds
mg/L Milligram per litre
ML Mega liters
ml Millilitres
MOF Materials Offloading Facility
MOPW Ministry of Public Works
MOU Memorandum of Understanding
Mtpa Million tonnes per annum
MW Megawatt
N/A Not Applicable
NDPCEI National Directorate for Pollution Control and Environmental Impact
NGOs Non-Government Organisations
NO2 Nitrogen dioxide
OEMP Operational Environmental Management Plan
PM10 and Particulate matter
Page 308 301012-02135-EMP-003Rev 1 : 02 February 17
TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN
PM2.5
PPE Personal Protective Equipment
ppm Part per million
RDTL Republic Democratic of Timor-Leste
SDS Safety Data Sheet
SEP Stakeholder Engagement Plan
SO2 Sulphur dioxide
UNTAET United Nations Transitional Administration in East Timor
USD United States Dollar
WHO World Health Organisation
Page 309 301012-02135-EMP-003Rev 1 : 02 February 17