Baucau Cement Project - La'o Hamutuk

309
TL CEMENT, LDA Baucau Cement Project Cement Plant, Jetty and Other Associated Infrastructure Environmental Management Plan Document No. 301012-02135-EMP-003 02 February 17 Venture Hotel - Rua Filomena De Camara Bidau Lecidere PO Box 7 Dili Timor Leste Telephone: +670 331 3238 & 331 3238 Facsimile: +670 772 8144 www.worleyparsons.com LPA 22548/MTCI/V/2011 © Copyright 2016 WorleyParsons (TL) LDA

Transcript of Baucau Cement Project - La'o Hamutuk

Page 1: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA

Baucau Cement Project Cement Plant, Jetty and Other Associated Infrastructure Environmental Management Plan

Document No. 301012-02135-EMP-003

02 February 17

Venture Hotel - Rua Filomena De Camara Bidau Lecidere PO Box 7 Dili Timor Leste Telephone: +670 331 3238 & 331 3238 Facsimile: +670 772 8144 www.worleyparsons.com LPA 22548/MTCI/V/2011 © Copyright 2016 WorleyParsons (TL) LDA

Page 2: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Disclaimer

This report has been prepared on behalf of and for the exclusive use of TL Cement, LDA, and is subject to and issued in accordance with the agreement between TL Cement, LDA and WorleyParsons. WorleyParsons accepts no liability or responsibility whatsoever for it in respect of any use of or reliance upon this report by any third party.

Copying this report without the permission of TL Cement, LDA and WorleyParsons is not permitted.

PROJECT 301012-02135 - BAUCAU CEMENT PROJECT

REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVAL

DATE CLIENT APPROVAL

DATE

1 Final Rev 1

A Jacobs A Mratovich D Hunter

2 Feb 2017

J Rhee

2 Feb 2017

Document No : 301012-02135-EMP-003 Page ii

Page 3: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

CONTENTS A EXECUTIVE SUMMARY ................................................................................................. 10

1.1 Summary of key impact, responsibility and mitigation cost ............................................. 13

B INTRODUCTION .............................................................................................................. 19

1.2 Environmental Management Framework ......................................................................... 19

1.3 Environmental Management Plan .................................................................................... 19

1 PROJECT DESCRIPTION ............................................................................................... 20

1.1 Project Identification ......................................................................................................... 20

2 DETAILS OF PROJECT PROPONENT .......................................................................... 21

2.1 Project Environmental Impact Statement ......................................................................... 21

3 DETAILS OF EMP CONSULTANTS ............................................................................... 23

3.1.1 Local presence .................................................................................................... 23

4 DESCRIPTION OF THE PROJECT ................................................................................ 30

4.1.1 Project component equipment and technology ................................................... 30

4.1.2 Pre Construction .................................................................................................. 32

4.1.3 Construction ........................................................................................................ 34

4.1.4 Operation ............................................................................................................. 37

4.1.5 Decommissioning ................................................................................................ 41

4.2 Project Location ............................................................................................................... 43

4.2.1 Nature of the project location .............................................................................. 43

4.2.2 EMP Endorsement .............................................................................................. 44

5 LEGAL REQUIREMENTS................................................................................................ 47

5.1 Legislation and legal framework ...................................................................................... 47

5.1.1 Environmental Legislation ................................................................................... 47

5.1.2 Biodiversity and protected areas legislation ........................................................ 48

5.1.3 Land legislation ................................................................................................... 49

5.1.4 Agriculture and Fishing legislation ...................................................................... 49

Page iii 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 4: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

5.1.5 Ports Legislation .................................................................................................. 50

5.1.6 Labor legislation .................................................................................................. 50

5.2 Obligations ....................................................................................................................... 51

5.3 Summary of Project Approvals ........................................................................................ 51

5.4 Summary of Environmental Standards ............................................................................ 52

6 INSTITUTIONAL ROLES AND RESPONSIBILITIES ...................................................... 53

7 SUMMARY OF IMPACTS ................................................................................................ 58

8 DESCRIPTION OF PROPOSED MITIGATION MEASURES.......................................... 70

8.1 Climate ............................................................................................................................. 70

8.2 Topography, Geology and Soils ....................................................................................... 71

8.3 Air Quality (including dust) ............................................................................................... 72

8.4 Noise and vibration .......................................................................................................... 73

8.5 Surface Water .................................................................................................................. 73

8.6 Groundwater .................................................................................................................... 74

8.7 Coastal and Marine .......................................................................................................... 75

8.8 Flora ................................................................................................................................. 76

8.9 Fauna ............................................................................................................................... 77

8.10 Marine Fauna incl. Fisheries ....................................................................................... 78

8.11 Marine habitats (including Coral) ................................................................................. 79

8.12 Traffic ........................................................................................................................... 80

8.13 Infrastructure ................................................................................................................ 80

8.14 Employment ................................................................................................................. 81

8.15 Economic Use of Forestry and other Natural Resources ............................................ 82

8.16 Fishing ......................................................................................................................... 83

8.17 Socio Economic Agriculture ......................................................................................... 84

8.18 Population and Community ......................................................................................... 84

8.19 Community Health ....................................................................................................... 85

8.20 Institutions, Schools and Health Facilities ................................................................... 86

Page iv 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 5: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

8.21 Community and Family Structure ................................................................................ 86

8.22 Land Ownership and Land Rights ............................................................................... 87

8.23 Natural Resources Rights ............................................................................................ 87

8.24 Cultural Heritage, Archaeological and Sacred Sites ................................................... 88

8.25 Summary of Impacts and Mitigation Measures ........................................................... 88

9 GOVERNING PARAMETERS ....................................................................................... 199

9.1 Environmental Quality Standards .................................................................................. 199

9.2 International Best Practice ............................................................................................. 199

9.3 Governing parameters ................................................................................................... 199

9.3.1 Emissions .......................................................................................................... 199

9.3.2 Ambient Water Quality Standards ..................................................................... 199

9.3.3 Ambient Air Quality Standards .......................................................................... 201

9.3.4 Soil..................................................................................................................... 201

9.3.5 Occupational Health and Safety Standards ...................................................... 203

9.4 Modelling or Engineering Calculations ........................................................................... 205

10 MONITORING PROGRAM ............................................................................................ 206

10.1 Climate ....................................................................................................................... 206

10.2 Topography and Soil ................................................................................................. 207

10.3 Air Quality .................................................................................................................. 207

10.4 Noise and vibration .................................................................................................... 208

10.5 Surface water ............................................................................................................. 208

10.6 Groundwater .............................................................................................................. 209

10.7 Coastal and Marine ................................................................................................... 209

10.8 Flora ........................................................................................................................... 210

10.9 Fauna ......................................................................................................................... 210

10.10 Marine Fauna and Fisheries ...................................................................................... 210

10.11 Marine habitats and corals ........................................................................................ 211

10.12 Traffic ......................................................................................................................... 211

Page v 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 6: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

10.13 Infrastructure .............................................................................................................. 212

10.14 Employment ............................................................................................................... 212

10.15 Economic Use of Forestry and other Natural Resources .......................................... 212

10.16 Fishing ....................................................................................................................... 213

10.17 Socio-Economic Agriculture ...................................................................................... 213

10.18 Population and community ........................................................................................ 213

10.19 Community Health ..................................................................................................... 213

10.20 Institutions schools and health facilities .................................................................... 215

10.21 Community and Family Structure .............................................................................. 215

10.22 Land Ownership and Land Rights ............................................................................. 215

10.23 Natural Resources Rights .......................................................................................... 215

10.24 Cultural Heritage Archeological and Sacred Sites .................................................... 216

10.25 Summary of monitoring program ............................................................................... 217

11 REPORTING REQUIREMENTS .................................................................................... 222

12 RESPONSIBILITIES FOR MITIGATION AND MONITORING ...................................... 230

13 EMERGENCY PLAN ...................................................................................................... 236

13.1 Purpose ..................................................................................................................... 236

13.2 Objective .................................................................................................................... 236

13.3 Responsibilities .......................................................................................................... 236

13.4 Standards .................................................................................................................. 237

13.5 Incident Classification ................................................................................................ 237

13.6 Prevention .................................................................................................................. 238

13.7 Safety Data Sheets (SDS) ......................................................................................... 239

13.8 Spill Response ........................................................................................................... 240

13.8.1 Control ............................................................................................................... 240

13.8.2 Contain .............................................................................................................. 240

13.8.3 Clean Up ........................................................................................................... 240

13.9 Equipment .................................................................................................................. 241

Page vi 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 7: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

13.9.1 Spill Response .................................................................................................. 241

13.9.2 Marine Spill Response ...................................................................................... 241

13.9.3 First Aid Facilities and Personal Protective Equipment (PPE) .......................... 242

13.9.4 Fire Fighting Equipment .................................................................................... 242

13.10 Training ...................................................................................................................... 242

14 DECOMMISSIONING PLAN .......................................................................................... 243

14.1 Objectives .................................................................................................................. 243

14.2 Preliminary Decommissioning Plan ........................................................................... 243

15 CAPACITY DEVELOPMENT AND TRAINING .............................................................. 250

16 PUBLIC CONSULTATION AND INFORMATION DISCLOSURE ................................. 251

16.1 Purpose of the consultation during the preparation of the EMP ................................ 251

16.2 Methodology and Approach ....................................................................................... 251

16.2.1 Identified Stakeholders ...................................................................................... 251

16.2.2 Mechanism for Public Consultation ................................................................... 254

16.3 Summary of consultation activities carried out .......................................................... 254

16.4 Summary of main comments received from the public, community leaders, NGOs, local officials, other stakeholders ........................................................................................................... 258

16.5 Identify how those comments were taken into account ............................................. 262

16.6 Details of public participation activities ...................................................................... 262

16.7 Summarize the public acceptance or opinions on the proposed Project .................. 262

16.8 Related materials or activities .................................................................................... 263

16.9 Recommendations for future consultations ............................................................... 264

17 COMPLAINTS AND GRIEVANCES MECHANISM ....................................................... 265

18 WORK PLAN AND IMPLEMENTATION SCHEDULE ................................................... 268

19 COST ESTIMATES ........................................................................................................ 274

20 REVIEW OF THE EMP .................................................................................................. 283

21 NON-TECHNICAL SUMMARY ...................................................................................... 285

21.1 Introduction ................................................................................................................ 285

Page vii 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 8: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

21.2 Purpose of this document .......................................................................................... 285

21.3 Benefits of the project ................................................................................................ 285

21.4 Key Project Characteristics ....................................................................................... 287

21.5 Operations ................................................................................................................. 288

21.6 Project Phases........................................................................................................... 290

21.7 Key Potential Impacts and Mitigation Measures ....................................................... 294

21.8 Stakeholder Engagement Process ............................................................................ 300

22 REFERENCES ............................................................................................................... 303

23 ACRONYMS / ABBREVIATIONS .................................................................................. 307

Table of Figures

Figure 4-1 Cement Plant, Conveyor and Jetty for export – Flow diagram ........................................... 31

Figure 4-2 Conceptual view of the cement plant with components ...................................................... 32

Figure 4-3 Example of excavator to be used to clear vegetation during pre-construction ................... 33

Figure 4-4 Example of construction camp accommodation for workers .............................................. 34

Figure 4-5 Example of excavator loading a dump truck ....................................................................... 35

Figure 4-6 Example of jetty during construction (photo: marineandcivil.com) ..................................... 36

Figure 4-7 Example of a Material Offloading Facility (MOF) during construction (Photo: Inpex) ......... 37

Figure 4-8 Example of Cement Plant showing bituminsed surface for mitigation of dust .................... 38

Figure 4-9 Example of Conveyor showing covered conveyor for mitigation of dust ............................ 38

Figure 4-10 Example of power infrastructure showing housing for mitigation of noise ........................ 39

Figure 4-11 Example of crusher in the plant with mitigation (cover for dust) ....................................... 39

Figure 4-12 Example of crusher in plant (inside) – mitigation measure cover for dust ........................ 40

Figure 4-13 Example of raw mill grinding (Cement plant) – mitigation measure safety barriers ......... 40

Figure 4-14 Example of kiln area and heater tower ............................................................................. 41

Figure 4-15 Examples of Jetty infrastructure ........................................................................................ 41

Figure 4-16 Example of decommissioning process (implosion of a power station) (Photo: sandiegouniontribune.com) .................................................................................................................. 42

Page viii 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 9: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Figure 4-17 Example of revegetation process (Image : Google Images) ............................................ 42

Figure 18: Location of Cement Plant, Jetty and Conveyor Belt ........................................................... 43

Figure 19: Grievance resolution framework ....................................................................................... 267

Figure 20: Location of Baucau Cement Project components ............................................................. 286

Figure 21: Portland cement clinker ..................................................................................................... 287

Figure 22: Ordinary Portland cement ................................................................................................. 287

Figure 23: The Baucau Cement Plant Project once in operation ....................................................... 289

Figure 24: Stakeholder Engagement and Consultation ..................................................................... 300

Page ix 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 10: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

A EXECUTIVE SUMMARY

An Environmental Management Framework (EMF) sets the structure for managing environmental risks and impacts during the Project life cycle. The EMF for the TL Cement Project includes the following key approaches:

a. Select the Project option which has the lowest possible environmental footprint; b. Reduce the environmental impact, as far as possible, through engineering and design approaches; c. Mitigate environmental impact, as far as possible, through engineering and design approaches; d. Manage the direct impacts and the risk of ongoing impact through management measures and monitoring; and e. Continuously improve the environmental management and monitoring measures through the Project life cycle.

Two Environmental Management Plans (EMPs) were created for the TL Cement Project. One EMP addresses impacts associated with the limestone mine site and the other addresses impacts associated with the cement plant, jetty and other associated infrastructure. EMPs for the TL Cement Project address:

1. Environmental impacts which are identified as ‘Medium’ or greater in EIS document; 2. Mitigation measures for all aspects which are required in accordance with industry best practice; 3. Monitoring measures and standards to be followed; 4. Trigger values or target values of measurement criteria; 5. Reporting requirements; and 6. Continuous improvement process.

Key impacts

Of all the aspects associated with the Project, key aspects are those with impacts identified in the EIS as being ‘Medium’ or ‘High’ risk. These risks have been addressed through the Environmental Management Plans (EMPs).

1. Displacement / Resettlement: Local people will be displaced and will require relocation in order for this Project land to be acquired. This can cause a ‘High’ level of impact on local people. Mitigation measures including resettlement and ongoing stakeholder consultation to be undertaken by the Government of Timor-Leste will most likely result in a residual impact of ‘Medium’.

2. Cultural Heritage: Impacts of the mine on Cultural Heritage for the local area is significant with a number of sacred heritage sites directly impacted by clearing and activities within the Project footprint. Local area sites will be permanently impacted causing a ‘High’ impact, however with the implementation of controlled relocation and removal of unavoidable impacted sites, the residual impacts are ‘Medium’.

3. Traffic: An increase in heavy vehicle numbers and movements is likely to cause damage to the condition of the local road network and also poses a ‘Medium’ safety risk for the local road users and

Page 10 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 11: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

pedestrians. Mitigation measures including speed limits and road improvements reduces this risk to 'Low' which is an acceptable level.

4. Noise: In accordance with the equations provided in AS 2436-2010 (AS 2436, 2010) the predicted noise levels from a single 85dB at 1m emission source, is 45dB 100m away from the source. This falls below the noise standard of 55 dB (A) (UNTAET, 2001). This represents a ‘Medium’ level of impact. The residual impact from noise and vibration is ‘Medium’.

Monitoring

The monitoring requirements for the project have been developed to consider all the project phases, Pre-construction, construction, operation and decommissioning. Key monitoring requirements are as follows :

1. Air quality monitoring at key receptors in the neighbouring settlements 2. Noise and vibration monitoring at the Plant and Mine site and sensitive receptors at the neighbouring settlements 3. Water quality and quantity monitoring at rivers and groundwater sources including springs adjacent to the mine and plant site 4. Recording of flora and fauna information during land clearing activities and ongoing throughout the project life 5. Ongoing stakeholder and community consultation throughout the project life

Emergency Response Plan

The Emergency Plan (EP) outlines the approach for managing the handling, storage and leak / spillage of dangerous chemicals and hazardous wastes associated with the development and operation of the Baucau Cement Plant Project.

The following will be adopted by the Project to prevent spillages and leaks from occurring:

• No tanks are to be filled prior to checking available tank volume; • Tank filling and dispensing procedures shall be carried out only by appropriately trained personnel and within designated and bunded area; • The main outlet valve on tanks will be locked shut when unattended; • Each tank/storage facility will be gauged and monitored daily; • All chemical and hazardous materials are contained in bunded areas with an appropriate holding capacity; • Bunded compound shall be lined with low permeability (less than 10 - 9 m/s) material that is not adversely affected by contact with the stored chemicals. It should be constructed in such a way that permits full recovery of contents spilt from tanks and ensures that the lining material is not damaged. The bund itself should be constructed of waterproof membrane, reinforced concrete or an approved equivalent; • The bunded compound shall have a minimum capacity of 110% of the capacity of the largest tank. The compound shall also have sufficient capacity to retain spilt chemicals and not be affected during extreme rainfall events; and

Page 11 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 12: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

• All marine-based spills and emergencies are to be managed in accordance with Regulation 37 Annex 1 of the International Convention for the Prevention of Pollution from Ships 1973. This regulation deals with the management of accidental discharge and discharge of ballast to sea.

Training

Training is essential for ensuring that the provisions of the EMPs are implemented efficiently and effectively. Training needs will be identified based on the existing and available capacity of the site and Project personnel (including the proponent, contractors and subcontractors) to undertake the required management actions and monitoring activities.

EMP review

The EMP will be reviewed at the following key project milestones:

• Completion of the pre-construction phase and additional specialist studies; • Completion of the construction phase; • Award of the Operations contract to incorporate operator-specific information; • Every 5 years at minimum during Operations phase.; and • On finalization of the Closure Plan.

Page 12 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 13: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

1.1 Summary of key impact, responsibility and mitigation cost

Stage Activity Potential Key Impact

Mitigation Measure Responsibility Monitoring Measure Frequency of monitoring

Cost of Mitigation Measure USD

Pre Construction

Vehicles movement

Equipment operating

Clearing of vegetation

Limit area to be cleared TL Cement Construction contractor

Check that clearing is within the boundary

Weekly reconciliation

Compensation per the Resettlement Plan : $15,000 estimate

Monitoring and weed eradication costs: $5.6M

Fauna relocation and monitoring, re-introduction and elimination of pests: $670k

Rehabilitation costs (Labour and materials): $?

Vehicles movement

Equipment operating

Air quality and dust

Dust suppression techniques include water spraying and enclosing equipment

TL Cement Construction contractor

PM10 and PM2.5

3 monitoring stations

Measurements every 6 months

Compensation per the Resettlement Plan : $15,000 estimate

Dust suppression sprayer and labour: $? 2000/month

Cost of illness and loss of productivity: $?

Page 13 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 14: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Stage Activity Potential Key Impact

Mitigation Measure Responsibility Monitoring Measure Frequency of monitoring

Cost of Mitigation Measure USD

Vehicles movement

Equipment operating

Generating electricity

Noise Noise limitation techniques include aprons and enclosing equipment

TL Cement Construction contractor

Noise Levels

3 monitoring stations

Measurements every 6 months

Compensation per the Resettlement Plan : $15,000 estimate

Monitoring costs: $580k

Cost of illness and loss of productivity: $?

Vehicles movement

Equipment operating

Water quality and quantity

Rehabilitation in the event of a spill or contamination event

Spill and contamination mitigation measures

TL Cement Construction contractor

Every 6 months

Flow meters / stream gauges at the Bucoli River (1.6km west) and at Uaimatabai, Uaisa and Waino springs.

Monthly water quality and quantity measurements at monitoring boreholes, key spring receptors at Waiono, Uaimatabai and Uaisa.

Water Quality Monitoring costs: $1,4M

Water Quantity Monitoring costs : $970k

Rehabilitation costs in the event of a spill: $?

Construction

Vehicles movement

Equipment

Air quality and dust

Dust suppression techniques include water spraying and enclosing

TL Cement Construction contractor

PM10 and PM2.5

3 monitoring stations

Measurements every 6 months

Dust suppression sprayer and labour: $? 2000/month

Cost of illness and loss of productivity: $?

Page 14 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 15: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Stage Activity Potential Key Impact

Mitigation Measure Responsibility Monitoring Measure Frequency of monitoring

Cost of Mitigation Measure USD

operating

Generating electricity

equipment

Vehicles movement

Equipment operating

Generating electricity

Noise Noise limitation techniques include aprons and enclosing equipment

TL Cement Construction contractor

Noise Levels

3 monitoring stations

Measurements every 6 months

Monitoring costs: $580k

Cost of illness and loss of productivity: $?

Vehicles movement

Equipment operating

Water quality and quantity

Rehabilitation in the event of a spill or contamination event

Spill and contamination mitigation measures

TL Cement Construction contractor

Every 6 months

Flow meters / stream gauges at the Bucoli River (1.6km west) and at Uaimatabai, Uaisa and Waino springs.

Monthly water quality and quantity measurements at monitoring boreholes, key spring receptors at Waiono, Uaimatabai and Uaisa.

Water Quality Monitoring costs: $1,4M

Water Quantity Monitoring costs : $970k

Rehabilitation costs in the event of a spill: $?

Page 15 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 16: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Stage Activity Potential Key Impact

Mitigation Measure Responsibility Monitoring Measure Frequency of monitoring

Cost of Mitigation Measure USD

Operation

Vehicles movement

Equipment operating

Air quality and dust

Dust suppression techniques include water spraying and enclosing equipment

TL Cement Operator

PM10 and PM2.5

3 monitoring stations

Measurements every 12 months

Dust suppression sprayer and labour: $? 2000/month

Cost of illness and loss of productivity: $?

Vehicles movement

Equipment operating

Removal of buildings

Generating electricity

Cement Plant operating

Noise Noise limitation techniques include aprons and enclosing equipment

TL Cement Operator

Noise Levels

3 monitoring stations

Measurements every 6 months

Monitoring costs: $580k

Cost of illness and loss of productivity: $?

Vehicles movement

Equipment

Water quality and quantity

Rehabilitation in the event of a spill or contamination event

TL Cement Operator

Flow meters / stream gauges at the Bucoli River (1.6km west) and at Uaimatabai, Uaisa and

Every 6 months

Water Quality Monitoring costs: $1,4M

Water Quantity Monitoring costs : $970k

Page 16 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 17: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Stage Activity Potential Key Impact

Mitigation Measure Responsibility Monitoring Measure Frequency of monitoring

Cost of Mitigation Measure USD

operating Spill and contamination mitigation measures

Waino springs.

Monthly water quality and quantity measurements at monitoring boreholes, key spring receptors at Waiono, Uaimatabai and Uaisa.

Rehabilitation costs in the event of a spill: $?

Decommissioning

Vehicles movement

Equipment operating

Air quality and dust

Dust suppression techniques include water spraying and enclosing equipment

TL Cement Operator

PM10 and PM2.5

3 monitoring stations

Measurements every 6 months

Dust suppression sprayer and labour: $? 2000/month

Vehicles movement

Equipment operating

Removal of buildings

Generating electricity

Noise Noise limitation techniques include aprons and enclosing equipment

TL Cement Operator

Noise Levels

3 monitoring stations

Measurements every 6 months

Compensation per the Resettlement Plan : $15,000 estimate

Monitoring costs: $580k

Cost of illness and loss of productivity: $?

Page 17 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 18: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Stage Activity Potential Key Impact

Mitigation Measure Responsibility Monitoring Measure Frequency of monitoring

Cost of Mitigation Measure USD

Vehicles movement

Equipment operating

Revegetation activity

Water quality and quantity

Rehabilitation in the event of a spill or contamination event

Spill and contamination mitigation measures

TL Cement Operator

Flow meters / stream gauges at the Bucoli River (1.6km west) and at Uaimatabai, Uaisa and Waino springs.

Monthly water quality and quantity measurements at monitoring boreholes, key spring receptors at Waiono, Uaimatabai and Uaisa.

Every 6 months

Water Quality Monitoring costs: $1,4M

Water Quantity Monitoring costs : $970k

Rehabilitation costs in the event of a spill: $?

Page 18 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 19: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

B INTRODUCTION

The TL Cement Project will be managed through the implementation of two Environmental Management Plans. These plans are for the Cement Plant, Jetty and Other Supporting Infrastructure and the Limestone Mine. This EMP relates to the Cement Plant, Jetty and Other Supporting Infrastructure.

1.2 Environmental Management Framework

An Environmental Management Framework (EMF) sets the structure for managing environmental risks and impacts during the Project life cycle. The EMF for the TL Cement Project includes the following key approaches:

a. Select the Project option which has the lowest possible environmental footprint; b. Reduce the environmental impact, as far as possible, through engineering and design approaches; c. Mitigate environmental impact, as far as possible, through engineering and design approaches; d. Manage the direct impacts and the risk of ongoing impact through management measures and monitoring; and e. Continuously improve the environmental management and monitoring measures through the Project life cycle.

1.3 Environmental Management Plan

As required by the Environmental Licensing Law the Environmental Management Plan (EMP) is a separate stand-alone document from the Environmental Impact Statement (EIS).

The EMP is an essential tool for ensuring that mitigation of the negative impacts and enhancement of the positive impacts is carried out effectively throughout the life of the Project. An EMP should be systematically improved on a regular basis to ensure that best available technologies (BAT) and best environmental management practices are implemented in a manner that is pragmatic, efficient and cost-effective.

The EMP for the TL Cement Project Cement Plant, Jetty and Other Associated Infrastructure addresses:

1. Environmental impacts which are identified as ‘Medium’ or greater in EIS document; 2. Mitigation measures for all aspects which are required in accordance with industry best practice; 3. Monitoring measures and standards to be followed; 4. Trigger values or target values of measurement criteria; 5. Reporting requirements; and 6. Continuous improvement process.

It should be noted that the any resettlement or compensation matters are the responsibility of the Government of Timor-Leste and as such are not part of the EMP.

Page 19 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 20: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

1 PROJECT DESCRIPTION

1.1 Project Identification

TL Cement LDA, a privately-owned company, proposes to construct a greenfield cement manufacturing project in Baucau Municipality, Timor-Leste. The project will produce approximately 1.65 million tons per annum (mtpa) of Portland cement clinker. For the purposes of this EMP, the components of the Baucau Cement Plant Project that relate to the construction and operation of the cement plant, jetty and other associated infrastructure shall be referred to as the Project.

Page 20 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 21: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

2 DETAILS OF PROJECT PROPONENT

TL Cement LDA was registered in Timor-Leste as a new company to develop the Baucau Cement Clinker Plant project. The contact details of the Project Proponent are given below:

Name: TL Cement LDA

Dili Office

Address: Rua Complexo Hotel Ramelau Aimutin Comoro, Dom Aleixo Dili Timor Leste Phone: +670 331 1206

Perth Office

Address: Level 5, 22 Mount Street Perth, Western Australia 6000 Phone: +61 8 9261 1965

Contact Person Mr. James Rhee Managing Director Mob: +61 400 317 811

Email: [email protected]

Contact Person Mr. James Rhee Managing Director Mob : +61 400 317 811

Email: [email protected]

2.1 Project Environmental Impact Statement

The Environmental Authority for this Project is the National Directorate for Pollution Control and Environmental Impact (NDPCEI). WorleyParsons on behalf of the Project Proponent has consulted with the NDPCEI with regards to obtaining the Environmental Licensing Certificate for the Project. The Application for Environmental License and the Project Document were submitted to NDPCEI in June 2015. The Project Document was approved on 20 July 2015 and pursuant to Decree Law 5/2011, the NDPCEI categorized the Baucau Cement Project as Category A.

Page 21 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 22: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

TL Cement LDA and their EIA consultant, WorleyParsons TL have developed and delivered this EIS and the EMP under the guidance and instruction of the National Directorate for Pollution Control and Environmental Impact (NDPCEI). This document has been extensively reviewed by; and aligns with the expectations and direction of the advisors in the NDPCEI. WorleyParsons has compiled this document in good faith that the content will assist the NDPCEI in assessing the environmental and social impacts of the project in line with the requirements of Decreee Law 5/2011.

Page 22 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 23: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

3 DETAILS OF EMP CONSULTANTS

WorleyParsons is responsible for leading the environmental assessment process, conducting the environmental and social baseline studies, and preparing the Environmental Impact Statement (EIS) and Environmental Management Plans (EMPs).

Globally, WorleyParsons is a leading provider of professional services to the infrastructure and resource industries. WorleyParsons has been involved in environmental management for decades and has a proven track record of delivering innovative solutions for our customers. WorleyParsons offers a full suite of environmental services, which cover all aspects from planning to detailed design and implementation. Services include engineering and environmental services to assist in site selection, site analysis, site layout, and design. One of the key differentiators to WorleyParsons’ environmental assessment approach is our ability assemble multi-disciplinary, in-house teams, including but not limited to engineers, urban planners, GIS and mapping specialists, geotechnical engineers, environmental scientists, social impact specialists, and hydrological engineers. These teams are led by experienced environmental assessment professionals who are capable of integrating the technical aspects of all disciplines into a tailored solution. Our ability to draw upon all of these resources internally streamlines the project delivery process and ensures reliable quality for the customer.

3.1.1 Local presence

WorleyParsons established an office in Timor-Leste in 2010 to provide our customers with the advantages of local content and an ‘on-the-ground’ understanding of local conditions. WorleyParsons Timor-Leste has delivered several major projects nationwide for the Government of Timor-Leste, TIMOR GAP, and international development agencies, including engineering feasibility, engineering design, and environmental assessment projects.

As a local company employing local staff, WorleyParsons is intimately familiar with the Timorese environment and culture. Our local staff are fluent in Portuguese, Tetun, and other local languages and are experienced in community engagement. Our multi-disciplinary team has extensive experience in the delivery of environmental studies in Timor-Leste.

WorleyParsons is supported by the following specilst consultants, who have extensive experience in Timor-Leste, including:

• Bita Bina Semesta (BBS): BBS is based in Bandung, Indonesia and maintains a locally-registered project office in Dili, Timor-Leste. BBS specializes in 'front end' type works, including planning and environmental studies for transport, resources, urban development, infrastructure and industrial development. BBS has become a regional leader in the preparation of environmental impact assessments that meets international standards. BBS recently worked with WorleyParsons to deliver environmental studies in support of the Dili Drainage EIA for the Ministry of Public Works.

Page 23 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 24: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

• InSight Consulting: Insight is a Timorese-owned organization based in Dili conducting research into public attitudes in the country. Their work is intended to advance the mutual interest of stakeholders, civil society and the people of Timor-Leste. They have a proven record as a credible research agency, based on sound principles of investigation and an intimate knowledge of the country. Their greatest emphasis is on compiling accurate information in a fully accountable way. Insight recently worked with WorleyParsons and BBS on the Dili Drainage EIA environmental studies.

• Nuno Oliviera: Dr. Nuno Oliveira is currently the Cultural Heritage Adviser for the Timor-Leste Secretary of State for Arts and Culture where he has led development of cultural heritage management programs and policies including the National Cultural Policy, Cultural Strategic Plan, Resolution on Protection of Cultural Heritage and ratification of UNESCO’s main conventions on cultural heritage. Prior to this role, Dr. Oliveira conducted extensive research in Timor-Leste for the Australia National University (ANU), completing his dissertation on early subsistence practices and agriculture in Timor-Leste. His research included extensive fieldwork and excavations near the proposed project location.

• Dr Colin Trainor: During 1997-2002, Colin worked internationally as an ecologist with BirdLife International, leading biodiversity assessments, particularly of forest birds, in Indonesia and East Timor (Timor Leste) (Timor Leste) (Timor-Leste). In Timor-Leste (2002-2014), work included a PhD thesis involving systematic survey of birds, mammals, reptiles, ants and trees across a 2,000 km2 district, and consulting projects on transmission and proposed hydropower works at Baucau and Iralalaro in Timor-Leste; shorebird and waterbird assessments; bird species rediscoveries. In Timor-Leste has worked on establishment of a protected area, wrote and published a field guide to the birds of East Timor (Timor Leste) and a site priority guide.

The environmental assessment has been undertaken by a team of specialists with world-class expertise and extensive experience in Timor-Leste.

Page 24 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 25: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

The development of the EIS and EMP has been led by Mr Daniel Hunter.

Key Personnel Qualifications and Experience

Daniel Hunter EIA Specialist

B App Sci (Natural Resources Management), University of Melbourne Dan is a Project Manager and Scientist with over 20 years’ experience predominantly in the area of environmental assessment and management. He has extensive experience in managing multidisciplinary projects, including the assessment and management of cumulative environmental issues associated with large infrastructure projects such as mine and port developments, roads, rail corridors, land developments, pipelines and has worked pro-actively with environmental planning teams, project design teams, government regulators, construction personnel, consultants and the community to achieve environmental / sustainability objectives and the development of mitigation strategies and consents in accordance with regulatory requirements. One of Dan’s major roles on projects is to integrate environmental considerations into all aspects of decision making, planning, design, construction and operational processes and drive for sustainable outcomes. Dan has previously managed and led a study of the Timor-Leste local industry capability for ConocoPhillips.

The environmental assessment has been undertaken by a team of specialists with world-class expertise and extensive experience in Timor-Leste.

Key Personnel Qualifications and Experience

Chris Serjak Study Manager

MSc, Sustainable Development, University of London Chris is the Country Manager for WorleyParsons’ Timor-Leste operations. He has 18 years of experience in environmental management, infrastructure development, and sustainable international development. He has five years of experience in Timor-Leste working on environmental projects, community-driven development, local content, and offshore petroleum projects. Chris recently completed a year-long study of the environmental licensing process in Timor-Leste and is an expert on the local regulatory framework. He has led the Dili Airport Environmental and Social Scoping Study and provided consulting services on the environmental licensing process for the Suai Supply Base project. As a certified project-manager, Chris understands how to manage interdisciplinary teams to deliver projects that meet client expectations.

Page 25 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 26: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Key Personnel Qualifications and Experience

Annette Jacobs Lead Author

BSc (Hon) Earth Science, Dip Project Management, Rhodes University Annette is trained as an environmental scientist with 15 years’ experience in environment and social impact assessment (ESHIA), management plan development, geology and hydrogeology. Her technical experience includes numerical modelling, environmental hydrogeology and advanced spatial analysis using geographic information systems (GIS). Annette currently project manages all the large marine science projects at WorleyParsons and understands the complexities and issues often encountered. She has 10 years’ project management experience in all stages of the project life cycle. Her project specific experience includes marine environmental hydrology, environmental and groundwater management for the mining industry and infrastructure projects, contaminated sites groundwater quality investigations, ESHIA project development and implementation, and mitigation and management plans.

Alison Mratovich Community Consultation

BA Geography and Environment Management, University of Johannesburg Alison has over 10 years experience in stakeholder management providing consultancy and advisory services to government agencies and private companies on environmental and social impact assessments, community engagement and socio-economic baseline assessments. Her focus is on social and environmental impact assessments, stakeholder engagement programs and social investment strategies. Delivering assessments in accordance with WA, International Finance Corporation (IFC) and World Bank Standards.

Lindsay Furness Water Resources

MA, Hydrogeology and Engineering Geology Mr Lindsay Furness has over 38 years’ experience in groundwater and water resource management in 14 countries for ADB, WB, UNESCO, WHO, AusAID, NZAID. He is a Fellow of the Australian Institute of Geosciences (Registered Professional Geoscientist), a member of the International Association of Hydrogeologist and the National Association of Ground Water Scientists and Engineers (US). Lindsay Furness made a preliminary study of the caves and springs of the Baucau Aquifer in 2004 under an ADB water resources assessment for Timor-Leste in relation to Agricultural irrigation. In 2010 he was appointed as the Timor-Leste Water Resources and Climate Adaptation Specialist in the National Department of Water Resources (DNGRA), where he was responsible for carrying out several surveys of the Baucau geohydrology.

Page 26 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 27: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Key Personnel Qualifications and Experience

Stuart Atkinson Water Resources

MEngSc, BEng (Hons), MIEAust He has over 15 years’ experience in hydrology, hydrogeology and contaminated site assessment gained in Australia, Africa, the Middle East, UK and New Zealand. Stuart’s Master’s degree research included water balance modelling in wet and arid environments. He has worked as part of large multidisciplinary teams addressing all water resource issues on major projects, and also managing smaller projects requiring specialist technical expertise to resolve complex water resource problems. This has included working through all project phases using a variety of project delivery. Stuart’s technical experience includes numerous hydrological investigations aimed at designing flood protection measures for new mine sites, residential and commercial developments, mine water management, flood mapping, water balance modelling, environmental hydrology, dam design, drainage system design and the preparation of bridge and culvert schedules for railway, roads and pipelines with lengths in excess of 1,000km. Stuart’s experience solving complex surface and groundwater issues on mining projects allows him to identify and address project risks associated with surface and groundwater while also considering associated geotechnical and civil engineering issues.

Lekha Siraz Water Resources

PhD Hydrogeology, BSc Geology, MSc. Geology (Hydrogeology) Lekha’s fields of experience include groundwater assessments, environmental hydrogeology, hydrogeological and contaminated site assessments and groundwater modelling. She has worked on a number of hydrogeological reviews, feasibility / impact assessments and compliance monitoring for mining and industrial customers in Australia. Lekha’s expertise also includes hydrogeological Interpretation and conceptualisation leading towards flow and contaminant transport Modelling. She has project managed and reviewed hydrogeological and groundwater modelling projects for the Victorian and New South Wales Government agencies, mining clients and waste management facilities. Besides these, her other projects have included landfill liner and cover design using industry standards such as the US EPA HELP model and alternate cover conceptualisation and design for landfills using vadose zone modelling. She also assisted a WA based contaminated sites auditor in audits of several sites, reviewing assessments, reports and preparing contaminated sites audit reports.

Page 27 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 28: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Key Personnel Qualifications and Experience

Grant Hickson Air Quality

BSc (Hons) Physics and Computer Science

Grant Hickson has more than five years of air quality consulting and professional experience in environmental impact assessments. He is an Environmental Scientist specialising in pollutant and particulate matter dispersion modelling from major industrial works, emissions estimation / calculation, data analysis and management as well as data validation and quality control for reporting purposes. Grant has undertaken numerous air quality impact assessments in Australia and internationally. He has recently been the primary author for the air quality, meteorology and noise assessments for the Tasi Mane Environmental Impact Assessment project. In this assessment he was responsible for: the on-site collection of air quality samples; meteorological and noise measurements; location surveying; data management and interpretation; and reporting. All work was conducted to International Standards across multiple sites and allowed the client to assess any adverse environmental impacts from the proposed development.

Dr. Kania Dewi Air Quality

PhD, Environmental Engineering Dr. Kania has 10 years’ experience as an Air Quality Expert conducting monitoring and modelling of air quality impacts for EIAs and EMPs. She has extensive experience with mining and hydrocarbons projects throughout Indonesia. Dr Kania has conducted multiple pollutant and GHG emissions inventories and completed climate change assessments. She has also completed modelling and assessment of impacts from cement plants. Dr. Kania recently completed a baseline air quality assessment for the Dili Drainage EIA environmental studies in association with WorleyParsons.

Dr. IB Ardhana Putra Noise

PhD, Engineering Dr. Ardhana has 16 years of experience in noise impact assessment, modelling, and management. He has published nearly 40 papers on noise over the past 27 years and is a former Head of Academic Development Program at Bandung Institute of Technology and a current advisor to the Indonesian Ministry of Environment. He has extensive experience with measurement, analysis and mapping of noise condition at oil and gas facilities and power plants, as well as airports and roads.

Titi Liliani Soedirdjo Traffic

MSc, Highway and Traffic Engineering Ir Titi has 34 years of experience in traffic engineering, traffic surveys, and traffic impact assessments. He has been a lecturer at Bandung Institute of Technology since 1981 and a consultant on traffic and railways. He has been involved in several studies in Timor-Leste, including modelling the traffic signalization and signage for Dili in 2002 and a traffic impact assessment for the Dili Drainage EIA.

Page 28 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 29: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Key Personnel Qualifications and Experience

Dr. Hisyam Achmad Social Impact & Resettlement

PhD, Anthropology Dr. Hisyam has over 40 years’ experience in social sciences and anthropology. In the past 10 years, Dr. Hisyam has worked for BBS completing several socio-economic and resettlement impact studies for projects throughout Indonesia, including public consultation, field surveys, and resettlement planning. He has extensive experience with IFC Guidelines and Indonesian AMDAL. He recently completed a socio-economic and resettlement impact assessment for the Dili Drainage EIA project.

Joana Belo Public Consultation field officer

BSc, Environmental Science (Management) Joana is an HSE Professional with experience in Australia, Malaysia and Timor-Leste. She has 7 years of experience health, safety and environment (HSE) including conducting risk assessment, developing emergency procedures in hydrocarbon and infrastructure industry. She also is participating in many environmental impacts and social assessments including, Field Officer for Worley Parsons Timor-Leste working on Dili Airport Environmental and Social Scoping Study, and Field officer for Tasi Mane EIA Study.

These specialists are supported by a team of local Timorese staff including environmental specialists, social specialists, and field surveyors. Field assistants have also been hired from the local area to ensure access to local knowledge and to promote public consultation.

In addition, wherever possible, the environmental assessment process has involved participation from local communities and mentoring of Timor-Leste university students, especially during field survey activities.

Page 29 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 30: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

4 DESCRIPTION OF THE PROJECT

For the purposes of the Environmental Licensing process, the NDPCEI has divided the Baucau Cement Project into several major components, as follows:

1. Cement Plant, Conveyor Belt, Power Plant, Marine Jetty, and Associated Infrastructure; 2. Limestone Mine; 3. Clay Extraction; and 4. Road Improvements and New Roads.

All of the items included are critical to the success of the Baucau Cement Project. The Limestone Mine will supply the product to be processed and exported. The cement plant will process the raw materials to produce cement clinker for domestic use and international sale. The jetty will be used to import raw materials not available locally including coal, iron ore, and gypsum and to export the clinker product. The conveyor belt will be used to transport materials to and from the marine jetty. The cement plant also includes a 30MW CFB power plant to provide electrical power to the plant.

The area of a Future Industrial Precinct has been proposed, however is not included in this EIS assessment. The Future Industrial Precinct is pending further investigation and assessment and will be subject of a separate environmental approval.

4.1.1 Project component equipment and technology

A picture which shows the Cement Plant and export via the Jetty is included below.

Page 30 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 31: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Figure 1 Cement Plant, Conveyor and Jetty for export – Flow diagram

Page 31 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 32: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Figure 2 Conceptual view of the cement plant with components

4.1.2 Pre Construction

During pre construction, excavators and graders will be used to clear vegetation and level the ground for the construction phase.

Pre-construction also requires the establishment of a camp for workers.

Page 32 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 33: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Figure 3 Example of excavator to be used to clear vegetation during pre-construction

Page 33 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 34: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Figure 4 Example of construction camp accommodation for workers

4.1.3 Construction

During construction, heavy plant and equipment will be used to construct the Cement Plant, Jetty and Conveyor. Examples of this equipment is included below.

Page 34 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 35: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Figure 5 Example of excavator loading a dump truck

Page 35 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 36: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Figure 6 Example of jetty during construction (photo: marineandcivil.com)

Page 36 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 37: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Figure 7 Example of a Material Offloading Facility (MOF) during construction (Photo: Inpex)

4.1.4 Operation

During operation, the plant will be operational and the jetty will load ships for export. Trucks and other vehicles will be used around the site to transport material and people to and from the workplace.

Page 37 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 38: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Figure 8 Example of Cement Plant showing bituminsed surface for mitigation of dust

Figure 9 Example of Conveyor showing covered conveyor for mitigation of dust

Page 38 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 39: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Figure 10 Example of power infrastructure showing housing for mitigation of noise

Figure 11 Example of crusher in the plant with mitigation (cover for dust)

Page 39 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 40: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Figure 12 Example of crusher in plant (inside) – mitigation measure cover for dust

Figure 13 Example of raw mill grinding (Cement plant) – mitigation measure safety barriers

Page 40 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 41: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Figure 14 Example of kiln area and heater tower

Figure 15 Examples of Jetty infrastructure

4.1.5 Decommissioning

During decommissioning, equipment and buildings will be dismantled following consultation with the community and GoTL.

The area will be revegetated with native species.

Page 41 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 42: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Figure 16 Example of decommissioning process (implosion of a power station) (Photo: sandiegouniontribune.com)

Figure 17 Example of revegetation process (Image : Google Images)

Page 42 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 43: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

4.2 Project Location

The proposed Baucau Cement Project is located in Suco Tirilolo, Aldeia Osso-ua, in the Baucau administrative post of Baucau Municipality, Timor-Leste. The location is about 120 km east of Dili and approximately 16 km west of Baucau.

Figure 18: Location of Cement Plant, Jetty and Conveyor Belt

4.2.1 Nature of the project location

The Jetty and Conveyor Belt area is located at the nearby beach and is flat and already highly modified by temporary dwellings, grazing and some agriculture. The general environment is characterised by sandy soils and established breadfruit Artocarpus altilis and Corypha sp. palm groves. The area is also severely infested with weeds. The Jetty area starts at the beach which slopes gently towards the ocean with a slightly steep beach before projecting into the ocean. The overall site is dominated by a relatively uniform coastal Closed Tropical Forest (70%) which is most likely a combination of existing forest and mature plantation trees. The remaining area (30%) is cleared grazing land and residential farms. Overall, the site is a heavily modified plantation environment with a severe infestation of Lantana camara throughout. The

Page 43 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 44: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

biological diversity at these sites was very low and overall the site was not representative of a pristine coastal/beach forest (Trainor & Easton, 2015).

The Cement Plant site is located on NNE facing slopes and plains relatively close to the beach, road and proposed Jetty area. The site is characterized as hilly and slopes up away from the coast, with shallow limestone soils and scattered limestone rock outcrops, minor ridges and gullies sloping towards the beach. The site consists predominantly of very open savannah woodland (95%) which has been extensively modified for agriculture and grazing in places. The remaining areas were isolated patches of Closed Tropical Forest systems (5%), occurring in depressions and drainage floors and often surrounded by introduced Lantana camara (Trainor & Easton, 2015).

No permanent rivers exist within the Project site. Some small ephemeral watercourses flow through the area, mainly during the wet season. These tend to stop flowing in the dry season and are not considered suitable as full time water sources. The closest ephemeral stream is the Manulede River located approximately 9 km from the proposed Cement Plant site (WorleyParsons, 2015c).

The Project is located near the Caisido community of the Aldeias Parlemento, Caisido, Lialaileso, and Osso-Ua. The total population of the Caisido area (the Project Site) is 2,387 or 38% of the Suco Tirilolo population. There are 532 households in Caisido and the average size of a household is 5 people. Economic employment is mainly focused on agricultural sector. Most of the local populations in the areas surrounding Baucau Cement Project site are farmers. A small number of these farmers are also teachers, drivers and owners of small kiosks (vendors) within their villages/hamlets (BBS, 2015c).

4.2.2 EMP Endorsement

The Baucau Cement Project proponent, TL Cement, has endorsed this EIS in writing. A copy of their written endorsement is included below.

Page 44 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 45: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Page 45 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 46: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

The geographical coordinates of the Bacau Cement Project components are detailed in Table 4-1 below.

Table 4-1: Coordinates of Project components

Component Latitude Longitude

Cement Plant -8.4520 126.3424

Marine Jetty -8.4438 126.3433

Conveyor belt -8.4520 to -8.4438 126.3424 to 126.3433

Construction camp and Residential area

Adjacent to cement plant Adjacent to cement plant

Page 46 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 47: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

5 LEGAL REQUIREMENTS

5.1 Legislation and legal framework

This section identifies the legislation and guidelines governing the conduct of the Environmental Impact Assessment studies and preparation of the EIS and EMP. This section also identifies other applicable laws, regulations, guidelines, and standards governing environmental quality, health and safety, protection of protected areas and sensitive areas, protection of vulnerable and endangered species, land use control, and other environmental and social issues.

5.1.1 Environmental Legislation

Decree Law 26/2012 Environment Basic Law (EBL)

The EBL (also sometimes called the Environmental Framework Law) sets the overall framework for environmental protection in Timor-Leste. Articles 14, 15 and 16 of the Decree define the instruments for environmental standards, environmental assessment and licensing and environmental monitoring respectively for Environmental Assessment (EA).

Decree Law 5/2011 Environmental Licensing Law (ELL)

The object of the Decree Law is to create a system of environmental licensing for public and private projects likely to produce environmental and social impacts. This system of licensing is based on assessing the size of the potential impacts of projects taking account of their nature, size, technical characteristics and location. Decree-Law No. 5/2011 elaborates the licensing requirement and the EIA procedure in Timor-Leste. Article 4 of the Decree defines the categories of projects and the Type of EA procedure required. The classification of projects is made in accordance with Annex I and II of the Decree. The proposed project has been classified by the NDE as a ‘Category A’ project “that may potentially cause significant environmental impacts, and [is] subject to the procedure of Environmental Impact Assessment (EIA) and Environmental Management Plan (EMP).”

Draft Ministerial Diploma for General Regulations for Environmental Assessment

The Asian Development Bank (ADB) has prepared detailed requirements for Screening, Scoping and the Terms of Reference, Environmental Impact Statements and Environmental Management Plans for Environmental Assessment. Although these guidelines have not been formally adopted, they are in practical use by NDPCEI.

Draft Ministerial Diploma Regulation on the Public Consultation Procedures

The ADB has prepared detailed requirements for Public Consultation Procedures and Requirements during the Environmental Assessment Process. Although these guidelines have not been formally adopted,

Page 47 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 48: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

they are in practical use by NDPCEI.

5.1.2 Biodiversity and protected areas legislation

UNTAET Regulation 2000/19 on Protected Places

UNTAET Regulation 2000/19 is still in force and used by the Forestry Department, although it is intended to be replaced by a draft Decree Law on Protected Areas, a draft Decree Law on Forestry, and the draft Decree Law on Biodiversity. Section 3 provides for the protection of endangered species and their habitats. The killing, injuring, harming, taking or disturbing of any endangered species is prohibited. The destruction in any way of the habitat of an endangered species is also prohibited.

UNTAET Regulation 2000/17 on the Prohibition of Logging Operations and the Export of Wood from East Timor

UNTAET Regulation 2000/17 also remains in force at present. Section 2 prohibits the cutting, removal, and logging of wood from land in East Timor. It also prohibits the burning or any other destruction of forests. These prohibitions are subject to Section 3 which allow for exemption to be authorised for certain logging activities.

Draft Decree Law on Forest Management, draft 7, received August 2013

The cutting of “forest trees” and harvesting of other forest products in any zone is prohibited unless specifically authorized by the National Director of Forestry (Article 61). The Director may give authorization for such cutting and harvesting if it would be in accordance with this law and other legislation, any community guideline agreements or with the forest management plan. The Director must take into consideration the forest management plan, conservation of the soil and water of the area, ecology and biodiversity of the area, and any other technical specifications determined by the National Director. Article 61.2 allows for community cutting of trees and harvesting other forest products without authorization, when used for traditional purposes.

Article 67 provides for measures to prevent deforestation. No-one is allowed to cut, damage, destroy, remove, transport, purchase, sell, donate or otherwise acquire or dispose of any tree, unless that tree is private property or the person has a Community Forestry Management Agreement or a permit/authorization from the National Director.

It is an offence under Article 86 for any person to pollute or contaminate land in any Protected Area with chemicals, industrial waste or organic or other polluting substances.

Draft Decree Law on Biodiversity, dated March 2012

When preparing an SEA, EIS, EMP or any other environmental assessment, the proponent must include an assessment of the potential impacts of the proposal on biodiversity and biological resources. This

Page 48 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 49: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

assessment must include: (a) Impacts on any natural ecosystems and habitats located within or near the proposed site, in particular the habitat of any protected species and critical habitat; (b) Impacts on any legally protected areas, as well as any areas the subject of cultural or traditional protection mechanisms such as Tara Bandu; (c) Impacts associated with invasive alien species on or near the proposed site; (d) The sustainability of any proposed use of biological resources; and (e) Proposed measures to avoid, minimize, or mitigate identified impacts, and measures to offset or compensate for any affected biological resources and impacts on biodiversity.

In analyzing any environmental assessment and before deciding to grant an environmental license, the decision-maker must take into account whether granting approval for the proposed activity would be consistent with the purpose and principles of the draft Biodiversity Decree Law. In particular, the Decision-maker must be satisfied that: (a) Any adverse impacts and risks identified in the assessment are deemed satisfactory; (b) Adequate measures to avoid, minimize, or mitigate identified adverse impacts have been identified and will be implemented; (c) As a last resort, adequate compensatory measures, which are designed to achieve no net loss of biodiversity, have been identified and will be implemented by the proponent to offset or compensate for any impacts on biodiversity and affected biological resources; (d) The proponent has prepared, in close consultation with affected local communities, a comprehensive plan that includes details about all necessary remedial and restoration efforts, and is satisfied that the plan will be implemented at the proponent’s expense.

5.1.3 Land legislation

Draft Expropriation Law Property may only be expropriated for the public interest and upon timely payment of fair compensation (Article 1). Only the State can order expropriation (Article 5).

There must be public consultation on any project requiring expropriation of private or community property (Article 13), and the documents made available to the public for consultation and public hearings must include any environmental, social or economic impact assessment studies (Article 15.4).

5.1.4 Agriculture and Fishing legislation

Decree Law 6/2004 On General The Decree-Law responds to the need of regulating fishing activities so

Page 49 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 50: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Bases of the Legal Regime for Fisheries and Aquaculture Management and Regulation (amended by Decree Law 4/2005)

as to contribute to the attainment of objectives on the economic and social development policies of the country while simultaneously ensuring the protection and conservation of species, as well as their continuous and sustainable exploitation. It also establishes the legal regime for aquaculture. Prohibits the introduction into national maritime waters and hydrographical basis of Timor-Leste of any substances or toxic objects likely to cause infection, and which poisons or destroys fishing resources, algae or any aquatic flora species. Any person, entity, factory or company is prohibited from discharging wastewaters originating from industrial or commercial activities into national waters if such wastewaters are likely to stun, poison or lead to the destruction of fishing resources or any other aquatic species. Any facility which intends to discharge wastewaters into maritime waters or hydrographical basins requires the prior opinion from the Minister responsible for fishing and aquaculture. The prior opinion from the Minister responsible for fishing and aquaculture is required for any intended works or installation in national maritime waters, on the seafront up to 100m from the coastline or in hydrographical basins where there are fishing or aquaculture activities.

5.1.5 Ports Legislation

Decree Law 3/2003

Port Authority establishment

The Decree Law 3/2003 on the establishment of the Port Authority and on the approval of the bylaws thereof details the structure, nature and responsibilities of the Administração dos Portos de Timor-Leste or Port Authority of Timor-Leste (APORTIL). The annex to this law requires APORTIL to grant licences for works carried out within their jurisdiction. The marine facilities associated with the project will require the issuing of a port licence from APORTIL prior to commencement of construction.

5.1.6 Labor legislation

Law 4/2012 Labor Code The duties of the employer include providing workers with good working conditions, prevention of risks from diseases and occupational accidents, providing workers with information and equipment necessary to prevent such risks.

The employer is under a general obligation to provide appropriate health and safety conditions, to prevent accidents and dangers, and to reduce risks.

Page 50 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 51: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Employers must ensure that workers are not exposed to risks that are harmful to their health, and must promote awareness programs. Where necessary, employers must provide safety equipment to workers.

5.2 Obligations

TL Cement is committed to developing this project in the region and complying with the regulations of Timor Leste. Negotiations and discussions with stakeholders and regulators are ongoing.

5.3 Summary of Project Approvals

Project Activities Statutory

Requirement Relevant Legislation

Cement Plant, Conveyor and Jetty Jetty, Plant and Conveyor

Marine facilities Environment licence Decree law 5/2011 on environment licensing law

Port licence from APORTIL

Decree law 3/2003 on the establishment of the Port Authority and on the approval of the bylaws thereof

Prior opinion from the Minister (APORTIL)

Decree Law 6/2004 On General Bases of the Legal Regime for Fisheries and Aquaculture Management and Regulation (amended by Decree Law 4/2005)

Land facilities Environment licence from DNSMA

Decree law 5/2011 on environment licensing law

Cement Plant Mining License Ministerial Diploma 01/2008 on Licensing of Mining Activities

Borehole Water Supply Water Supply for Public use

Decree Law 4/2004 Water Supply for public consumption

Internal roads Decree law 2/2003 on basic law on the road transport system

Water Decree law 4/2004 on water supply for public consumption

Telecommunications

Decree law 11/2003 on establishing the bases for the telecommunications sector

Electricity Decree law 13/2003 on establishing the bases for the national electricity system

Page 51 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 52: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

5.4 Summary of Environmental Standards

Phase Aspect Standard Pre Construction Air Quality World Health Organization (WHO), 2006: Air

Quality Guidelines (AQGs) for PM10 Noise UNTAET Guideline on Ambient Noise (2002) Water Quality WHO Drinking Water Standards (2000)

Construction Air Quality World Health Organization (WHO), 2006: Air Quality Guidelines (AQGs) for PM10

Noise UNTAET Guideline on Ambient Noise (2002) Water Quality WHO Drinking Water Standards (2000)

Operation Air Quality World Health Organization (WHO), 2006: Air Quality Guidelines (AQGs) for PM10

Noise UNTAET Guideline on Ambient Noise (2002) Water Quality WHO Drinking Water Standards (2000) Vibration Regulation 11

Environmental Protection (Noise) Regulations 1997

Decommissioning Air Quality World Health Organization (WHO), 2006: Air Quality Guidelines (AQGs) for PM10

Noise UNTAET Guideline on Ambient Noise (2002) Water Quality WHO Drinking Water Standards (2000) Vibration Regulation 11

Environmental Protection (Noise) Regulations 1997

Page 52 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 53: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

6 INSTITUTIONAL ROLES AND RESPONSIBILITIES

Phase Item Develop/Author Implement

Detailed Engineering Design

Environmental Management Plans

Lead Engineer from the Engineering provider with approval by Project Manager – TL Cement LDA

Lead Engineer from the Engineering provider

Mitigation Measures Lead Engineer from the Engineering provider with approval by Project Manager – TL Cement LDA

Lead Engineer from the Engineering provider

Monitoring Plans Lead Engineer from the Engineering provider with approval by Project Manager – TL Cement LDA

Lead Engineer from the Engineering provider

Construction Tender Phase

Develop construction specific Environmental Management Plans

Civil works contractor with approval by Project Manager – TL Cement LDA

Civil works contractor

Develop construction specific

Mitigation Measures

Civil works contractor with approval by Project Manager – TL Cement LDA

Civil works contractor

Develop construction specific

Monitoring Plans

Civil works contractor with approval by Project Manager – TL Cement LDA

Civil works contractor

Page 53 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 54: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Phase Item Develop/Author Implement External Review

Pre-Construction Environmental Management Plans

Civil works contractor with approval by Project Manager – TL Cement LDA

TL Cement nominated EPC management firm Health, Safety Quality Manager/Officer

Mitigation Measures

Civil works contractor with approval by Project Manager – TL Cement LDA

TL Cement nominated EPC management firm Health, Safety Quality Manager/Officer

Monitoring activities

Civil works contractor with approval by Project Manager – TL Cement LDA

TL Cement nominated EPC management firm Health, Safety Quality Manager/Officer

Compliance monitoring

Project Manager – TL Cement LDA

TL Cement nominated EPC management firm Health, Safety Quality Manager/Officer

Compliance reporting

Civil works contractor with approval by Project Manager – TL Cement LDA

TL Cement nominated EPC management firm Health, Safety Quality Manager/Officer

Autoridade Nacional do Petróleo e Minerais (ANPM)

Minister of Commerce and Environment

NDPCEI

Construction Environmental Management Plans

Civil works contractor with approval by Project Manager – TL Cement LDA

TL Cement nominated EPC management firm Health, Safety Quality Manager/Officer

Page 54 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 55: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Mitigation Measures

Civil works contractor with approval by Project Manager – TL Cement LDA

TL Cement nominated EPC management firm Health, Safety Quality Manager/Officer

Monitoring activities

Civil works contractor with approval by Project Manager – TL Cement LDA

TL Cement nominated EPC management firm Health, Safety Quality Manager/Officer

Compliance monitoring

Site Supervisor from TL Cement LDA

TL Cement nominated EPC management firm Health, Safety Quality Manager/Officer

Compliance reporting

Civil works contractor with approval by Project Manager – TL Cement LDA

TL Cement nominated EPC management firm (Cement-Holtec, Jetty Royal Haskoning) Health, Safety Quality Manager/Officer

Autoridade Nacional do Petróleo e Minerais (ANPM)

Minister of Commerce and Environment

NDPCEI

Operations Year 1 to 5

Environmental Management Plans

Environmental Engineer supervised by the Plant Manager – TL Cement LDA

TL Cement nominated EPC firm Health, Safety Quality Manager/Officer

Year 6-end: TL Cement Health, Safety Quality Manager/Officer

Mitigation Measures

Environmental Engineer supervised by the Plant Manager – TL Cement LDA

TL Cement nominated EPC firm Health, Safety Quality Manager/Officer

Year 6-end: TL Cement Health, Safety Quality

Page 55 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 56: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Manager/Officer

Monitoring activities

Environmental Engineer supervised by the Plant Manager – TL Cement LDA

TL Cement nominated EPC firm Health, Safety Quality Manager/Officer

Year 6-end: TL Cement Health, Safety Quality Manager/Officer

Compliance monitoring

Environmental Engineer supervised by the Plant Manager – TL Cement LDA

TL Cement nominated EPC firm Health, Safety Quality Manager/Officer

Year 6-end: TL Cement Health, Safety Quality Manager/Officer

Compliance Reporting

Environmental Engineer supervised by the Project Manager – TL Cement LDA

TL Cement nominated EPC firm Health, Safety Quality Manager/Officer

Year 6-end: TL Cement Health, Safety Quality Manager/Officer

Autoridade Nacional do Petróleo e Minerais (ANPM)

Minister of Commerce and Environment

NDPCEI

Decommissioning#1 Environmental Management Plans

Environmental Engineer supervised by the Project Manager – TL Cement LDA

TL Cement Health, Safety Quality Manager/Officer

Mitigation Measures

Environmental Engineer supervised by the

TL Cement Health Engineering Manager

1 Assuming that TL Cement LDA undertake all the Decommissioning works and do not contract the bulk earthworks or civil works to a sub contractor

Page 56 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 57: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Project Manager – TL Cement LDA

Monitoring activities

Environmental Engineer supervised by the Project Manager – TL Cement LDA

TL Cement Health, Safety Quality Manager/Officer

Compliance monitoring

Site Supervisor from TL Cement LDA

TL Cement Health, Safety Quality Manager/Officer supervising the Civil works contractor

Compliance Reporting

Environmental Engineer supervised by the Project Manager – TL Cement LDA

TL Cement Health, Safety Quality Manager/Officer

Autoridade Nacional do Petróleo e Minerais (ANPM)

Minister of Commerce and Environment

NDPCEI

Page 57 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 58: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

7 SUMMARY OF IMPACTS

There are a number of aspects to the Project that have the potential to cause environmental and social impacts during different phases of the Project. The Impacts have been outlined in the table below.

Page 58 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 59: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Table 7-1: Activity and Potential Impacts

Activity Impact Pre construction

Construction Operations Decommissioning

Vehicles movement

Operating heavy machinery

Power generation from Power Plant

Climate Limited impact on climate change from greenhouse gases.

Limited impact on climate change from greenhouse gases.

Some impact from operation of a power plant for operations.

Reduction in impact with decommissioning of plant

Vehicles movement

Digging and excavating

Clearing of vegetation using equipment

Construction of roads and buildings

Vehicles travelling on site

Topography Geology and Soil

Reshaping and excavation of landforms in order to prepare for construction will impact the current topography

Vegetation clearing resulting in increased erosion and run-off

Plant and equipment may leak oils and hydrocarbons which pollute the soil

Increased erosion and run-off from a bituminised Cement Plant area will likely change the water quality of the ocean, springs and rivers

Plant and equipment may leak oils and hydrocarbons which pollute the soil

Increased erosion and run-off from a bituminised Cement Plant area will likely change the water quality of the ocean, springs and rivers

Plant and equipment may leak oils and hydrocarbons which pollute the soil

Decommissioning will involve the rehabilitation of the

This is expected to have a positive impact on the soil resources at the site.

Vehicles Air Quality Dust from Dust from earth Direct Direct emissions

Page 59 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 60: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Activity Impact Pre construction

Construction Operations Decommissioning

movement

Digging and excavating

Clearing of vegetation using equipment

Construction of roads and buildings

Vehicles travelling on site

earth moving and vegetation clearing activities;

Direct emissions from vehicles and plant in the form of fuel combustion (i.e. exhaust fumes) and brake wear.

moving and vegetation clearing activities;

Direct emissions from vehicles and plant in the form of fuel combustion (i.e. exhaust fumes) and brake wear.

emissions from vehicles and plant in the form of fuel combustion (i.e. exhaust fumes)

from vehicles and plant in the form of fuel combustion (i.e. exhaust fumes)

Vehicles movement

Digging and excavating

Construction of roads and buildings

Vehicles travelling on site

Plant processing

Operating conveyor belt

Vessels loading at the jetty

Noise and Vibration

Impact from Vehicle movements and earthworks

Impact from Vehicle movements and earthworks

Noise Impact from processing plant activities

Impact from Vehicle movements and earthworks

Page 60 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 61: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Activity Impact Pre construction

Construction Operations Decommissioning

Vehicles movement

Digging and excavating

Operating a borehole for water supply

Surface Water

Changes to drainage behavior and quality from earthworks

Changes to drainage behavior and quality from earthworks

Changes to drainage behavior and quality from earthworks

Changes to drainage behavior and quality from earthworks

Vehicles movement

Digging and excavating

Operating a borehole for water supply

Groundwater

Changes to spring flow and quality from earthworks

Changes to spring flow and quality from earthworks

Changes to spring flow and quality from earthworks

Long term changes to spring flow and quality after decommissioning

Vehicles movement

Digging and excavating

Construction of roads and buildings

Vehicles travelling on site

Vessels loading at the jetty

Coastal and Marine

Development of the MOF resulting in changes to coastal processes

Development of the Jetty resulting in changes to coastal processes

Shipping impacts to water quality

Decommissioning returning the beach to pre-development condition

Vehicles Flora Direct loss of Positive impact Indirect loss Positive impact

Page 61 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 62: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Activity Impact Pre construction

Construction Operations Decommissioning

movement

Digging and excavating

Construction of roads and buildings

Vehicles travelling on site

vegetation due to clearing

due to revegetation activity

of vegetation cover due to depletion of water sources

due to revegetation activity

Vehicles movement

Digging and excavating

Construction of roads and buildings

Vehicles travelling on site

Plant processing

Operating conveyor belt

Vessels loading at the jetty

Fauna Direct loss of habitat through vegetation clearing;

Harm/death/displacement of individual IUCN listed species;

.

Direct loss of habitat through vegetation clearing;

Harm/death/displacement of individual IUCN listed species

Increased susceptibility of native fauna to predation

Soil disturbance and potential refuge destruction for ground dwelling animals

Changes to natural drainage affecting fauna and their habitat;

Disturbance fauna activities due to noise, vibration and lightning

Direct loss of habitat through vegetation clearing;

Harm/death/displacement of individual IUCN listed species

Increased susceptibility of native fauna to predation

Soil disturbance and potential refuge destruction for ground dwelling animals

Changes to natural drainage

Positive impact with rehabilitation

Page 62 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 63: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Activity Impact Pre construction

Construction Operations Decommissioning

impacts. affecting fauna and their habitat;

Disturbance fauna activities due to noise, vibration and lightning impacts.

Use of MOF and road infrastructure

Vessels travelling to/from jetty

Operating conveyor belt

Vessels loading at the jetty

Marine Fauna inc. Fisheries

Construction and operation of the MOF is likely to have an impact on local fish populations and invertebrates

The Jetty and shipping operations has the potential to affect marine life and marine habitats, including fish and marine fauna

The Jetty and shipping operations has the potential to affect marine life and marine habitats, including fish and marine fauna

Positive impact due to decommissioning rehabilitation

Use of MOF and road infrastructure

Vessels travelling to/from jetty

Operating conveyor belt

Vessels loading at the jetty

Marine Habitat

The movement of ships and machinery within the project footprint has the potential to introduce marine pests and disease which impacts coral health

The movement of ships and machinery within the project footprint has the potential to introduce marine pests and disease which impacts coral health

The movement of ships and machinery within the project footprint has the potential to introduce marine pests and disease which impacts coral health

Positive impact due to decommissioning rehabilitation

Page 63 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 64: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Activity Impact Pre construction

Construction Operations Decommissioning

Vehicles movement

Digging and excavating

Construction of roads and buildings

Vehicles travelling on site

Plant processing

Operating conveyor belt

Vessels loading at the jetty

Traffic Increase in traffic to the area due to pre-construction

Increase in traffic due to construction

Limited traffic increase during operations, mainly on the project site

Increase in traffic due to decommissioning

Development of the project resulting in economic participation

Employment Some short term employment and training opportunities

Longer term employment and training opportunities

Long term employment and training opportunities

Reduction in employment opportunities as the project decommissions

Development of the project resulting in infrastructure development

Development of a training centre

Infrastructure

Increasing pressure on existing infrastructure e.g. roads and water

Reduced impact on existing infrastructure as project infrastructure construction has commenced

Positive impact on local infrastructure

Long term positive impact on local infrastructure

Development of the project resulting in

Economic Use of Forestry

Loss of access to land by community

No further impact during construction

No further impact during

Positive impact on community who get access to the

Page 64 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 65: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Activity Impact Pre construction

Construction Operations Decommissioning

infrastructure development

operations revegetated and rehabilitated forests

Vessels loading at the jetty

Access restrictions due to site fencing

Fishing Access control excludes a portion of the ocean from access by local fishermen

Ongoing access control to sections of the beach and ocean

Ongoing access control to sections of the beach and ocean

Positive impact as access controls are lifted and the jetty becomes available for community use

Access restrictions due to site fencing

People and vehicles movement

Digging and excavating

Relocation of people

Socio Economic Agriculture

Access controls and reduction in available agricultural land

Access controls and reduction in available agricultural land

Access controls and reduction in available agricultural land

Positive impact with removal of access controls and increase available agricultural land

Access restrictions due to site fencing

People movement

Digging and excavating

Relocation of people

Population and Community

Resettlement of affected families

Influx of workers to the pre-construction site

Influx of workers to the construction site

Daily movement of some employee during operations

Changes to the income source of people in the community due to project decommissioning

Vehicles movement

Community Health

Increase in respiratory

Increase in respiratory

Increase in respiratory

Positive reduction in prevalence of

Page 65 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 66: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Activity Impact Pre construction

Construction Operations Decommissioning

Digging and excavating

Construction of roads and buildings

Vehicles travelling on site

Plant processing

Operating conveyor belt

ailments due to an influx of people

Increase in the level of respiratory ailments due to increased dust

Increase in vector-related ailments such as malaria due to increase in population density;

Increase in sexually transmitted infections such as the human immunodeficiency virus due to population influx

ailments due to an influx of people

Increase in the level of respiratory ailments due to increased dust

Increase in vector-related ailments such as malaria due to increase in population density;

Increase in sexually transmitted infections such as the human immunodeficiency virus due to population influx

ailments due to an influx of people

Increase in the level of respiratory ailments due to increased dust

Increase in vector-related ailments such as malaria due to increase in population density;

Increase in sexually transmitted infections such as the human immunodeficiency virus due to population influx

diseases and dust-related ailments.

Vehicles movement

Digging and excavating

Construction of roads and buildings

Institutions Schools and Health Facilities

Increased pressure on health services infrastructure

Increase in the level of

Increased pressure on health services infrastructure due to population influx

Increased pressure on health services infrastructure due to population influx

Positive impact on community health with legacy investments

Page 66 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 67: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Activity Impact Pre construction

Construction Operations Decommissioning

Vehicles travelling on site

Plant processing

Operating conveyor belt

respiratory ailments due to increased dust

Increase in the level of respiratory ailments due to increased dust

Vehicles movement

Digging and excavating

Construction of roads and buildings

Vehicles travelling on site

Plant processing

Operating conveyor belt

Community and Family Structure

The acquisition of land for the Cement Plant and Jetty and the construction of internal roads may cause impacts on the community and family structure

Impacts to household subsistence and ability to generate income

Impacts to household subsistence and ability to generate income

Change of employment status may affect the households income

Access restrictions due to site fencing

People and vehicles movement

Digging and excavating

Land Ownership and Land Rights

The acquisition of land for the Cement Plant and Jetty and the construction of internal roads may cause conflict around

Limited ongoing impact on land rights during construction

Limited ongoing impact on land rights during construction

The change in land use and decommissioning of the Cement Plant and Jetty and the may potentially cause conflict around land owners and communities.

Page 67 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 68: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Activity Impact Pre construction

Construction Operations Decommissioning

Relocation of people

land owners and communities.

Access restrictions due to site fencing

People and vehicles movement

Clearing, Digging and excavating

Relocation of people

Natural Resources Rights

Limited impact due to limited use of the vegetation area of the Plant and Jetty.

The acquisition of land for the Cement Plant and Jetty and the construction of internal roads may potentially cause conflict around land use and harvesting of wood before clearing.

No additional impact once construction commences and resettlement has occurred.

No additional impact once operations commences and resettlement has occurred.

The change in land use and decommissioning of the Cement Plant and Jetty and the may potentially cause conflict around land owners and communities.

Access restrictions due to site fencing

People and vehicles movement

Relocation of people

Cultural Heritage and Archeology

No sites destroyed as a result of the Cement Plant, Jetty and Conveyor

Access to sites may be restricted for safety reasons

No sites destroyed as a result of the Cement Plant, Jetty and Conveyor

Access to sites may be restricted for safety reasons

No sites destroyed as a result of the Cement Plant, Jetty and Conveyor

Access to sites may be restricted for safety

Positive impact, Sites with restricted access for safety reasons will be lifted

Page 68 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 69: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Activity Impact Pre construction

Construction Operations Decommissioning

reasons

Page 69 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 70: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

8 DESCRIPTION OF PROPOSED MITIGATION MEASURES

The following section outlines the proposed mitigation measures for each of the aspect identified in the EIS. The proposed mitigation measures are considered for each of the different Project phases; i.e.:

• Pre-construction; • Construction; • Operation; and • Decommissioning.

8.1 Climate

Objective To ensure the atmospheric emissions (i.e. carbon monoxide) are minimised as much as practicable;

To ensure design of Project components accommodate climate change, including sea level rise and severe weather events

Impacts Carbon dioxide emissions

Sea level rise impacts on infrastructure

Pre-construction Construction Operations Decommissioning

Design reviews to consider

equipment selection

Design reviews to implement

Alternative Fuels in

consideration of climate

change impacts

Adoption and

implementation of clean

technology

Ensure vehicles and

equipment are regular

serviced and maintained

Limit vehicle idling and keep

vehicles well maintained

Adoption and

implementation of clean

technology

Use of substitute Alternative

fuels (Biomass, RDF, used

tyres and solvents instead of

fossil based fuels in both

cement and power plant

Ensure vehicles and

equipment are regular

serviced and maintained

Limit vehicle idling and keep

vehicles well maintained

Limit vehicle idling and keep

vehicles well maintained

Page 70 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 71: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

8.2 Topography, Geology and Soils

Objective Maintain the integrity, ecological functions and environmental values of landforms, geology and soil

Minimise permanent landform alterations

Ensure that the modifications to landforms are physically and environmentally stable and sustainable

Impacts Soil contamination

Erosion and loss of value

Landform shape change

Pre-construction Construction Operations

Soil contamination should be

monitored through

maintaining records of spill

events

Contouring and establishing

drainage systems during

pre-construction phase

Off-site contamination

should be monitored as part

of the Water Quality

Monitoring Programme

Minimizing of excavation

during construction

Soil contamination should be

monitored through

maintaining records of spill

events

Management measures to

control run off and erosion at

the Topsoil Stockpile

Soil contamination should be

monitored through

maintaining records of spill

events

Off-site contamination

should be monitored as part

of the Water Quality

Monitoring Programme

Page 71 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 72: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

8.3 Air Quality (including dust)

Objective To ensure that atmospheric emissions do not impact on the health, welfare and amenity of the population and land uses and the environment.

To use all reasonable and practicable measures to minimise airborne dust

Impacts Dust impacts on human health

Combustion emissions impacts on human health

Emissions from vehicles

Pre-construction Construction Operations Decommissioning

All raw materials storage will be in enclosed structures

All materials transport will be by fully covered conveyor belts

All areas with vehicle traffic shall be watered or have dust palliative applied as necessary for

regular stabilization of dust emissions.

All on-site vehicle traffic shall be limited to a speed of 15 mph on unpaved roads.

All material transported off-site shall be either sufficiently watered or securely covered to

prevent public nuisance, and there must be a minimum of six (6) inches of freeboard in the

bed of the transport vehicle.

No vehicles or plant will be left idling unnecessarily.

Reduce the number of vehicle movements through better planning.

Set an appropriate speed limit on haul routes.

All heavy duty vehicles should meet certain emission regulation from local Environmental

Protection Agency.

Use a good quality of fuel (e.g. with low sulphur content).

Engines and exhaust systems should be regularly serviced according to manufacturer’s

recommendations and maintained to meet statutory limits/opacity tests.

All workers onsite will undertake environmental awareness training to highlight potential

issues specific to air quality impacts associated with the project.

The contractor will provide appropriate personal protective equipment (PPE) to the workers

based on the nature of the work.

Ensure correct working methods are employed for the Project.

Page 72 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 73: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

8.4 Noise and vibration

Objective To ensure that noise emissions do not impact on the health, welfare and amenity of the population, land uses and environmental values.

To ensure that noise emissions, both individually and cumulatively, comply with the appropriate statutory requirements

Impacts Amenity

Human Health

Fauna

Pre-construction Construction Operations Decommissioning

Storage areas should be located away from sensitive receptors.

Haulage of goods and movement of vehicles/people and equipment can be scheduled.

Where required, noise barriers can be constructed to abate the noise impacts.

Alternative construction methods and selection of less noisy equipment to do the tasks.

8.5 Surface Water

Objective Maintain the integrity, ecological functions and environmental values of surface water.

Impacts Flooding behaviour.

Spring flows.

Water quality changes

Uncontrolled discharge of waste water

Pre-construction Construction Operations Decommissioning

Drains down-gradient from the site to capture potentially contaminated surface water run-off.

Storm water design will be incorporated to manage extreme weather events

Monitoring of surface water features for water quality impacts.

Page 73 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 74: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Spills management and pollution control through the Emergency Plan.

8.6 Groundwater

Objective Maintain the integrity, ecological functions and environmental values of groundwater

Minimise the impact on the flow and quality of springs

Impacts Spring flows

Vegetation impacts

Water quality

Pre-construction Construction Operations Decommissioning

Detailed hydrological study

to establish baseline

groundwater monitoring

network including boreholes,

spring flow gauging and

water quality analysis

Groundwater modelling of

Water Supply borehole to

quantify drawdown impacts

Design for handling and

storage of potential

contaminants (including

fuels and chemicals) to

eliminate risk

Emergency Plan to deal with

spills and contaminants

Substitute ground water use

with make- up sea water

systems

Emergency Plan to deal with

spills and contaminants

Page 74 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 75: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

8.7 Coastal and Marine

Objective Maintain the integrity, ecological functions and environmental values of the marine environment;

Minimise the impact on bathymetry and sediment transport from the jetty and Materials Offloading Facility (MOF); and

Minimise the impact on coastal zone including beaches.

Impacts Sedimentation

Shore erosion

Marine Pests from Ballast water (Vessels)

Pre-construction Construction Operations Decommissioning

Control of spills and discharge of material or fuels to the

beach or marine environment;

Contouring and movement of vehicles on the beach to

minimize scour and erosion;

Vessel approach to minimize discharge of ballast and spread

of marine pests; and

Storage of construction materials to minimize disturbance of

beach processes.

Control of spills and

discharge of material or

fuels to the beach or marine

environment;

Vessel approach to the Jetty

to minimize discharge of

ballast and spread of marine

pests.

Control of spills and

discharge of material or

fuels to the beach or marine

environment;

Vessel approach to the Jetty

to minimize discharge of

ballast and spread of marine

pests

Page 75 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 76: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

8.8 Flora

Objective Maintain the abundance, diversity, geographic distribution and productivity of flora at the species and ecosystem levels through the avoidance or management of adverse

impacts.

Impacts Clearing

Soil erosion

Weeds

Pre-construction Construction Operations Decommissioning

Optimize design to prevent

un-necessary excavation

Undertake stripping and

stockpiling of topsoil

Dust suppression measures

(e.g. water sprinkling) at all

dust generating sites

Weed management

activities including spraying

Minimize site excavation as

much as possible

Dust suppression measures

(e.g. water sprinkling) at all

dust generating sites

Weed management

activities including spraying

Planting Green aprons

around developed areas

where possible

Dust suppression measures

(e.g. water sprinkling) at all

dust generating sites

Weed management

activities including spraying

Sequential rehabilitation

Afforestation and plantation

of local species in areas

degraded during the pre-

construction, construction

and operation phases of the

Project

Revegetation using native

vegetation types typical of

the Project area pre-

construction.

Page 76 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 77: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

8.9 Fauna

Objective Maintain the abundance, diversity, geographic distribution and productivity of native fauna at the species and ecosystem levels through the avoidance or management of

adverse impacts

Impacts Clearing

Displacement of fauna

Pre-construction Construction Operations Decommissioning

Site clearing to be

conducted sequentially and

from one corner of the site to

the other, enabling highly

mobile fauna species to

leave the construction area

Monthly recording of fauna

impacts and mortality as a

result of project construction.

6-monthly reporting of fauna

impact data and

interpretation

Control of feral and pest

animals including frogs

Monthly recording of fauna

impacts and mortality as a

result of project operation.

6-monthly reporting of fauna

impact data and

interpretation

Control of feral and pest

animals including frogs

Sequential rehabilitation

Afforestation and plantation

of local species in areas

degraded during the pre-

construction, construction

and operation phases of the

project

Page 77 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 78: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

8.10 Marine Fauna incl. Fisheries

Objective Minimise the impact on marine fauna, fisheries and habitats from the jetty and MOF

Impacts Habitat loss due to construction of MOF and Jetty

Displacement of marine fauna

Noise, vibration and light

Spills and ballast water

Introduced marine pests

Pre-construction Construction Operations Decommissioning

Collection of additional

baseline environmental data

including large marine

mammal, turtle nesting,

seagrass and crocodile

habitat.

Collection of baseline

environmental data

pertaining to sea water

quality to provide

background data.

Identification of water quality

reference and impact sites

to be sited within and

adjacent to the project

impact area.

Implementation of Emergency Plan (EP) including Spills and

ballast

Project scheduling to limit shipping movements during the

key mammal migration period typically June, August and

November annually, particularly in November of each year.

Implementation of EP including Spills and ballast

Project scheduling to limit shipping movements during the

key mammal migration period typically June, August and

November annually, particularly in November of each year

EP including Spills and

ballast

Page 78 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 79: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

8.11 Marine habitats (including Coral)

Objective Maintain the integrity, ecological functions and environmental values of the marine environment

Minimise the impact on marine habitats including corals from the jetty and MOF

Impacts Direct impact on hard and soft coral coverage from infrastructure footprint

Indirect impacts on hard and soft coral from marine pests, disease, shipping, spills

Pre-construction Construction Operations Decommissioning

Ballast water management

and Introduced Marine Pests

monitoring and controls;

Identification of coral

locations on engineering

drawings and construction

plans;

Identification of impact zone

sites, nearby sites and

reference (background) sites

for the coral health

monitoring program.

Ballast water management and Introduced Marine Pests

monitoring and controls;

Identification of coral locations on engineering drawings and

construction plans;

Management of waste

materials during

decommissioning.

Post decommissioning

marine habitat survey within

5 years post-closure

Page 79 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 80: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

8.12 Traffic

Objective To protect the amenity and safety of nearby residents

Minimise disturbance to local traffic

Impacts Traffic volumes

Traffic types increased trucks and heavy machinery

Pre-construction Construction Operations Decommissioning

Planning to minimize vehicle movements (e.g. use of buses to transport workers and house in camps)

Limit reversing requirements

Traffic signage implementation

Speed limits and enforcement

Road widening

8.13 Infrastructure

Objective Prospective employees are provided with the necessary and appropriate skills training

The expectation of employment clearly outlined minimising any potential conflicts

Existing employment sectors/source of livelihood are not adversely impacted.

Impacts Long term beneficial impact on local communities

Pre-construction Construction Operations Decommissioning

Identify and prioritize the upgrades and construction of new infrastructure required for the

construction and operation of the Project (e.g. water treatment and wastewater facilities;

roads and accommodation facilities).

Ongoing inspection, monitoring and maintenance programmes will be developed and

implemented for the relevant infrastructure during the operational phase of the Project to

ensure optimal operation.

Prior to decommissioning

and closure, consultation

with all stakeholders

(relevant authorities,

government and local

community)

Page 80 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 81: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

8.14 Employment

Objective Upgrades to existing or construction of new infrastructure for the project are designed and built fit for purpose

Existing infrastructure are not adversely impacted by the development and operation of the Project

Impacts Short term to long term finite increase in income

Training and development

Conflict as a result of employment practices

Pre-construction Construction Operations Decommissioning

Selection and management of employee applications by a specialist employee management

institution formed through a consultative process with sub-district and suco leadership

Prior to decommissioning

and closure, consultation

with all stakeholders

(relevant authorities,

government and local

community)

Page 81 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 82: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

8.15 Economic Use of Forestry and other Natural Resources

Objective Ensure the local communities access to forest and other natural resources for economic usage are not adversely affected with the development of the Project; and

Maintain the abundance, diversity, geographic distribution and productivity of flora and fauna at the species and ecosystem levels through the avoidance or management

of adverse impacts

Impacts Loss of firewood sources

Loss of income

Pre-construction Construction Operations Decommissioning

Minimise the disturbance footprint as far as practicable.

Undertake stripping and stockpiling of vegetation and topsoil

for reuse in the decommissioning and rehabilitation phase.

Preserve topsoil for rehabilitation by stripping soil during

construction.

Site clearing to be conducted sequentially.

Topsoil to be stock piled separately from

overburden/interburden for rehabilitation purposes and

protected against loss of run-off.

Control of alien invasive plants i.e. weed control

Control of alien invasive

plants

Sequential rehabilitation to

be conducted as soon as

possible at the completion of

operation.

Afforestation and plantation

of local species in areas

degraded during the pre-

construction, construction

and operation phases of the

Project.

Page 82 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 83: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

8.16 Fishing

Objective Ensure the local communities’ access to fishing grounds for economic and subsistence use are not adversely affected by the development of the Project;

Ensure that the communities near the Project are able to contribute to the protection and maintenance of fishing resources

Impacts Access

Fish stocks

Pre-construction Construction Operations Decommissioning

Providing alternative access locations,

Providing safe passage zones across the conveyor corridor crossing the beach between the

Jetty and the Plant sites; and

Ensuring that the timeline for implementation of access controls is communicated to the

families who are directly impacted by the access restrictions.

Good construction measures that will reduce impact on fish stock such as piling which does

not interfere with the marine ecology

Implement measures to ensure coral growth (artificial reefs etc)

Providing alternative access

locations,

Providing safe passage

zones across the conveyor

corridor crossing the beach

between the Jetty and the

Plant sites; and

Ensuring that the timeline for

removal of access controls

is communicated to the

families who are directly

impacted by the access

restrictions.

Page 83 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 84: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

8.17 Socio Economic Agriculture

Objective Ensure the local communities access to agricultural land economic usage are not adversely affected with the development of the Project

Impacts Loss of agricultural land

Pre-construction Construction Operations Decommissioning

The impact on community access to farmland during the

project will be addressed by resettlement and compensation

to be undertaken by the GoTL.

Sequential rehabilitation to

be conducted as soon as

possible at the completion of

operation.

The areas degraded during

the pre-construction and

construction phases shall be

restored to their natural, pre-

construction condition.

Afforestation and plantation

of local species in areas

degraded during the pre-

construction, construction

and operation phases of the

Project.

8.18 Population and Community

Objective Maintain communities and limit secondary impacts of population increase due to the Project

Impacts Increase in population locally

Fragmentation of communities

Pre-construction Construction Operations Decommissioning

The impact on community during the project will be addressed by resettlement and compensation to be undertaken by the

GoTL.

Page 84 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 85: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

8.19 Community Health

Objective No adverse impacts to community health from the project

Impacts Illness and disease

Lifestyle diseases

Health services infrastructure

Pre-construction Construction Operations Decommissioning

Facilitate education and awareness programs throughout the lifespan of the Project;

Design roads and implement driver training to improve traffic safety.

Internal Project roads will be designed and constructed for all-weather, 24 hr capability.

Establish a secure buffer zone from activities posing safety risks to villages or scattered dwellings.

Develop an employee wellness programme

Page 85 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 86: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

8.20 Institutions, Schools and Health Facilities

Objective No adverse effects on community institutions, schools, and health facilities

Impacts 1 Air quality and noise impacts on local primary school, aldeia hall, and church.

2 Influx of jobseekers impacts on capacity of institutions, schools, and health facilities

Pre-construction Construction Operations Decommissioning

1 Refer to Section 0 [Air Quality] and Section 8.4 [Noise and vibration] for relevant mitigation measures

2 The impact on community access to institutions during the project will be addressed by

resettlement and compensation to be undertaken by the GoTL.

Decommissioning will

reduce demand for services

and should be coordinated

with the relevant line

Ministries in advance of

closure to address any

reduction in resources.

8.21 Community and Family Structure

Objective Avoid adverse effects on community and family structure

Impacts Conflicts over the status of land, conflicts over compensation values and systems, conflicts over the dismantling of graves and customary / traditional houses,

population resettlement, and potential damage to local landowners’ subsistence

resources

Pre-construction Construction Operations Decommissioning

Implementation of the Complaints and Grievance mechanism Implementation of the

Complaints and Grievance

mechanism

Advance coordination with

stakeholders with respect to

land transfer

Advance coordination with

potential land users to

maximize productive use of

rehabilitated land

Page 86 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 87: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

8.22 Land Ownership and Land Rights

Objective Limit the long term impact of the project on Land Ownership / Land Rights

Impacts People financially and physically excluded from traditional lands

Pre-construction Construction Operations Decommissioning

TL Cement is currently working with the Directorate of Land, Property and Cadastral Services (DLPCS) to map affected

households, farmland, and other property. Once TL Cement has secured the mining license and environmental licenses

required for the Project, the GoTL will enter into discussions with those affected households and property owners.

8.23 Natural Resources Rights

Objective Maintain and protect natural resource rights near the Project site and/or within new site as a part of resettlement plan.

Minimize potential impacts on surrounding environment

Impacts Reduced availability or quality of natural resources

Pre-construction Construction Operations Decommissioning

Implementation of the Complaints and Grievance

mechanism

An environmental education

programme to be developed

and implemented for all

employees

Implementation of the

Complaints and Grievance

mechanism

Implementation of the

Complaints and Grievance

mechanism

Page 87 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 88: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

8.24 Cultural Heritage, Archaeological and Sacred Sites

Objective Minimise the number of recorded heritage sites which are directly impacted by the project

Ensure that the management of the relocation of known sites is undertaken in accordance with best practice standards

Ensure transparency and consultation occurs in relation to the unavoidable impacts on known heritage sites in the project area

Impacts Permanent loss of sites

Temporary loss of access to sites for safety reasons

Pre-construction Construction Operations Decommissioning

First to minimize encroachment on such sites identified by field surveys by revising boundary parameters- If site cannot be

avoided then initiate relocation.

Where safe access cannot be guaranteed, those sites which are located adjacent to the project should be fenced off, access

restricted for the project life or relocated.

All archaeological excavations within or adjacent to the study area should be authorised by the State Secretariat of Tourism,

Art and Culture and undertaken by a team of professional archaeologists

Ceremonial platforms or altars should be properly documented and eventually relocated to a different location;

Burial sites should be properly documented, excavated and relocated to an agreed upon site; and

Archaeological sites should be test excavated.

8.25 Summary of Impacts and Mitigation Measures

Page 88 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 89: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Table 8-1 Description of proposed mitigation measures

Pre-Construction Stage –

Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp

Impact Mitigation Performance and Impact Monitoring

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Climate Atmospheric

emissions (i.e.

carbon monoxide)

increase from use

of vehicles

Design reviews to

consider

equipment

selection

Design reviews to

implement

Alternative Fuels in

consideration of

climate change

impacts

Design

Contractor

Prior to

construction

Throughout

project site

Incl. in

construction

contract cost

Automated Weather

Station (AWS)

recording

measurements of:

Station identification

number;

Date and time of

record/observation;

Air, wet bulb and wet

dew point

temperatures.

Precipitation and

Daily

measurements

TL Cement

Annual

reporting for all

project phases

of Greenhouse

Gas emissions in

accordance with

National

Greenhouse and

Energy

Reporting Act

2007.

$500,000 for

Automated

Weather

station

Monitoring

Costs $580k

Page 89 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 90: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Pre-Construction Stage –

Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp

Impact Mitigation Performance and Impact Monitoring

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

evaporation;

Relative humidity;

Wind speed and

direction;

Solar radiation;

Barometric pressure ;

Visibility;

Cloud cover; and

Cloud ceiling height, if

practicable.

Topography,

Geology and

Changes to

topography and

Soil contamination

should be

TL Cement /

Design

Prior to

construction

Throughout

project site and

Incl. in

construction

Weed growth and

drainage behaviour on

As required Construction

Contractor

Incl. in

construction

Page 90 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 91: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Pre-Construction Stage –

Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp

Impact Mitigation Performance and Impact Monitoring

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Soils increase in soil

erosion

monitored through

maintaining

records of spill

events

Contouring and

establishing

drainage systems

during pre-

construction phase

Consultant where spills

occur

contract cost the topsoil stockpile contract cost

Air Quality Increase in levels

of dust

All raw materials

storage will be in

enclosed

structures

All materials

transport will be

TL Cement /

Design

Consultant

Prior to

construction

Throughout

project site and

outside of site

where materials

are being

transported

Incl. in

construction

contract cost

At sensitive receptors:

AQ3 – At the Jetty

AQ4 – Settlement area

at Aldeia Osso-Ua

AQ5 - representing the

Every 6 months

measurements

at sensitive

receptors i.e.

Results

interpretation

TL Cement

Contractor

$500,000

Page 91 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 92: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Pre-Construction Stage –

Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp

Impact Mitigation Performance and Impact Monitoring

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

by fully covered

conveyor belts

Dust and bag

filters will be

installed at all

critical emissions

hoppers

All areas with

vehicle traffic shall

be watered or

have dust

palliative applied

as necessary for

regular

stabilization of

construction area.

and review of

the EMP as

required.

Collation of

results into

semi-annual

Environmental

Report to

NDCPEI

Page 92 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 93: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Pre-Construction Stage –

Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp

Impact Mitigation Performance and Impact Monitoring

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

dust emissions.

All on-site vehicle

traffic shall be

limited to a speed

of 15 mph on

unpaved roads.

No vehicles or

plant will be left

idling

unnecessarily.

Reduce the

number of vehicle

movements

through better

planning.

Page 93 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 94: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Pre-Construction Stage –

Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp

Impact Mitigation Performance and Impact Monitoring

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Set an appropriate

speed limit on haul

routes.

All heavy duty

vehicles should

meet certain

emission

regulation from

local

Environmental

Protection Agency.

Use a good quality

of fuel (e.g. with

low sulphur

content).

Page 94 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 95: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Pre-Construction Stage –

Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp

Impact Mitigation Performance and Impact Monitoring

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Engines and

exhaust systems

should be regularly

serviced according

to manufacturer’s

recommendations

and maintained to

meet statutory

limits/opacity

tests.

Ensure correct

working methods

are employed for

the Project.

Noise and Increase in levels Storage areas

TL Cement / Design Phase Throughout Incl. in At sensitive receptors: Every 6 months TL Cement $500,000

Page 95 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 96: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Pre-Construction Stage –

Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp

Impact Mitigation Performance and Impact Monitoring

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Vibration of noise should be located

away from

sensitive

receptors.

Haulage of goods

and movement of

vehicles/people

and equipment

can be scheduled.

Where required,

noise barriers can

be constructed to

abate the noise

impacts.

Design

Consultant

project site and

in particular in

the vicinity of

sensitive

receptors.

Local road

networks.

construction

contract cost NO3 – At the Jetty

NO4 – Settlement area

at Aldeia Osso-Ua

NO5 - representing

the construction area.

measurements

at sensitive

receptors i.e.

Results

interpretation

and review of

the EMP as

required.

Collation of

results into

semi-annual

Environmental

Report to

NDCPEI

Contractor

Page 96 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 97: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Pre-Construction Stage –

Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp

Impact Mitigation Performance and Impact Monitoring

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Alternative

construction

methods and

selection of less

noisy equipment

to do the tasks.

Surface

Water

Decrease in flows

in streams

Changes in water

quality of

streamflow

Drains down-

gradient from the

site to capture

potentially

contaminated

surface water run-

off.

TL Cement /

Design

Consultant

Design Phase /

Prior to

construction

Throughout

project site

Incl. in

construction

contract cost

Flow meters / stream

gauges at the Bucoli

River (1.6km west)

and at Uaimatabai,

Uaisa and Waino

springs

Monthly water

quality and

quantity

measurements

at monitoring

boreholes, key

spring receptors

at Waiono,

TL Cement -

Collation of

results into

Annual

Environmental

Report to

NDCPEI

$970,000

Page 97 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 98: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Pre-Construction Stage –

Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp

Impact Mitigation Performance and Impact Monitoring

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Storm water

design will be

incorporated to

manage extreme

weather events

Monitoring of

surface water

features for water

quality impacts.

Spills management

and pollution

control through

the Emergency

Plan.

Uaimatabai and

Uaisa.

Interpretation of

data every 6

months.

Groundwater Decrease in flows Detailed TL Cement / Design Phase / Monitoring at Incl. in Quality and quantity Monthly water TL Cement - Inc. Above

Page 98 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 99: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Pre-Construction Stage –

Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp

Impact Mitigation Performance and Impact Monitoring

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

in springs

Changes in water

quality of springs

hydrological study

to establish

baseline

groundwater

monitoring

network including

boreholes, spring

flow gauging and

water quality

analysis

Groundwater

modelling of

Water Supply

borehole to

quantify

drawdown impacts

Design

Consultant

Prior to

construction

water supply

boreholes,

design for

handling and

storage to be

implemented

across site.

construction

contract cost

measurements at key

spring receptors at

Uaimatabai, Uaisa and

Uaino.

quality and

quantity

measurements

Reporting and

interpretation of

data quarterly

Collation of

results into

Annual

Environmental

Report to

NDCPEI

Page 99 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 100: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Pre-Construction Stage –

Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp

Impact Mitigation Performance and Impact Monitoring

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Design for

handling and

storage of

potential

contaminants

(including fuels

and chemicals) to

eliminate risk

Coastal and

Marine

Pollution of sea

water

Increase in

turbidity of sea

water

Spread of marine

Control of spills

and discharge of

material or fuels to

the beach or

marine

environment;

Contouring and

TL Cement /

Design

Consultant

Design Phase /

Prior to

construction

Across beach

and marine

environment

within and in

the vicinity of

project site.

Incl. in

construction

contract cost

A sediment transport

model should be

developed in order to

qualify the volume,

duration and

distribution of

sediment and

NA TL Cement -

Collation of

results into

semi-annual

Environmental

Report to

NDCPEI

$500,000

Page 100 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 101: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Pre-Construction Stage –

Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp

Impact Mitigation Performance and Impact Monitoring

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

pests from ships movement of

vehicles on the

beach to minimize

scour and erosion;

Vessel approach to

minimize discharge

of ballast and

spread of marine

pests; and

Storage of

construction

materials to

minimize

disturbance of

beach processes.

erosion/scour

associated with the

MOF and Jetty.

Page 101 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 102: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Pre-Construction Stage –

Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp

Impact Mitigation Performance and Impact Monitoring

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Flora Removal of

threatened plants

Optimize design to

prevent un-

necessary

excavation

Undertake

stripping and

stockpiling of

topsoil

Dust suppression

measures (e.g.

water sprinkling)

at all dust

generating sites

Weed

TL Cement /

Design

Consultant

Design phase /

prior to

construction

Throughout

project site

Incl. in

construction

contract cost

The total area of

vegetation cleared

(habitat destruction)

at the end of phase

TL Cement -

Collation of

results into

Annual

Environmental

Report to

NDCPEI

Construction

contractor

$5.6M

Page 102 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 103: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Pre-Construction Stage –

Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp

Impact Mitigation Performance and Impact Monitoring

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

management

activities including

spraying

Fauna Removal of

threatened

animals

Site clearing to be

conducted

sequentially and

from one corner of

the site to the

other, enabling

highly mobile

fauna species to

leave the

construction area

TL Cement /

Construction

Contractor

Clearing Throughout

project site

Incl. in

construction

contract cost

Any incidents of fauna

injury and death

should be recorded.

TL Cement -

Collation of

results into

semi-annual

Environmental

Report to

NDCPEI

TL Cement $670k

Marine

Fauna

Loss of fishing

habitat and coral

Collection of

additional baseline

TL Cement /

Contractor

Prior to

construction

Throughout and

surrounding

Incl. in

construction

Regular community

engagement surveys

Annual review

and reporting of

TL Cement Inc. above

Page 103 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 104: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Pre-Construction Stage –

Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp

Impact Mitigation Performance and Impact Monitoring

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

including

fisheries

reefs environmental

data including

large marine

mammal, turtle

nesting, seagrass

and crocodile

habitat.

Collection of

baseline

environmental

data pertaining to

sea water quality

to provide

background data.

Identification of

project site contract cost around fisheries

Survey of coral health,

sedimentation and

fisheries.

Collection of water

quality measurements

at reference and

impact sites to be

sited within and

adjacent to the project

impact area.

coral habitats

around Jetty and

MOR.

Water Quality

measurements

are to be taken

at least twice

per calendar

year, outside of

and during the

monsoon

season.

Page 104 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 105: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Pre-Construction Stage –

Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp

Impact Mitigation Performance and Impact Monitoring

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

water quality

reference and

impact sites to be

sited within and

adjacent to the

project impact

area.

Marine

habitats

including

coral

Loss of fishing

habitat and coral

reefs

Ballast water

management and

Introduced Marine

Pests monitoring

and controls;

Identification of

coral locations on

engineering

TL Cement /

Contractor

Design phase Throughout

project site and

surrounding

local area

Incl. in

construction

contract cost

Undertake a pre-

construction survey of

the identified sites to

develop the reference

imagery and GPS

database.

Reporting and

recording of baseline

Pre construction

survey

TL Cement -

Collation of

results into

semi-annual

Environmental

Report to

NDCPEI

Inc. above

Page 105 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 106: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Pre-Construction Stage –

Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp

Impact Mitigation Performance and Impact Monitoring

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

drawings and

construction plans;

Identification of

impact zone sites,

nearby sites and

reference

(background) sites

for the coral health

monitoring

program.

coral health

monitoring data.

Traffic Increase in amount

of traffic on the

roads

Planning to

minimize vehicle

movements (e.g.

use of buses to

transport workers

and house in

Construction

Contractor /

Mine Operator

During planning

prior to

construction

Throughout

project site and

on local road

networks

Incl. in

construction

contract cost

Traffic incidents and

mitigation measures

implemented

Update Safety

Management

System to

record and

document traffic

Construction

Contractor

$2000/mont

h

Page 106 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 107: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Pre-Construction Stage –

Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp

Impact Mitigation Performance and Impact Monitoring

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

camps)

Limit reversing

requirements

Traffic signage

implementation

Speed limits and

enforcement

Road widening

incidents and

mitigation

measures

implemented as

and when they

occur.

Infrastructur

e

Increased pressure

on existing

infrastructure

Identify and

prioritize the

upgrades and

construction of

new infrastructure

TL Cement /

Design

Consultant

Design phase,

ongoing

throughout

construction and

operation

Throughout

project site

Incl. in

construction

contract cost

Complaints and

Grievance records

review

Stakeholder

Regular review

of Complaints

and Grievance

record

TL Cement N/A

Page 107 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 108: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Pre-Construction Stage –

Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp

Impact Mitigation Performance and Impact Monitoring

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

required for the

construction and

operation of the

Project (e.g. water

treatment and

wastewater

facilities; roads

and

accommodation

facilities).

Ongoing

inspection,

monitoring and

maintenance

programmes will

be developed and

consultation to check

progress Regular

stakeholder

consultation

Page 108 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 109: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Pre-Construction Stage –

Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp

Impact Mitigation Performance and Impact Monitoring

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

implemented for

the relevant

infrastructure

during the

operational phase

of the Project to

ensure optimal

operation.

Employment Training and

development of

local people

Selection and

management of

employee

applications by a

specialist

employee

TL Cement Prior to

construction

Selected

employment

management

institution

offices

Incl. in

construction

contract cost

Complaints and

Grievance records

review

Stakeholder

consultation to check

progress

Regular review

of Complaints

and Grievance

record

Regular

stakeholder

TL Cement N/A

Page 109 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 110: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Pre-Construction Stage –

Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp

Impact Mitigation Performance and Impact Monitoring

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

management

institution formed

through a

consultative

process with sub-

district and suco

leadership

consultation

Economic

Use of

Forestry and

other Natural

Resources

Training and

development of

local people

Minimise the

disturbance

footprint as far as

practicable.

Site clearing to be

conducted

sequentially.

TL Cement /

Construction

Contractor

Design phase,

planning phase

for site clearing

sequencing

Throughout

project site.

Incl. in

construction

contract cost

Complaints and

Grievance records

review

Stakeholder

consultation to check

progress

Regular review

of Complaints

and Grievance

record

Regular

stakeholder

consultation

TL Cement N/A

Page 110 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 111: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Pre-Construction Stage –

Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp

Impact Mitigation Performance and Impact Monitoring

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Fishing Decrease in people

who fish

Providing

alternative access

locations,

Providing safe

passage zones

across the

conveyor corridor

crossing the beach

between the Jetty

and the Plant sites;

and

Ensuring that the

timeline for

TL Cement/

Design

Consultant

Design phase,

prior to

construction

Throughout

project site and

surrounding

area

Incl. in

construction

contract cost

Fisheries assessment

is a component of the

Marine Habitats and

Coral monitoring

Per the

Grievance

mechanism

TL Cement

Manager

N/A

Page 111 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 112: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Pre-Construction Stage –

Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp

Impact Mitigation Performance and Impact Monitoring

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

implementation of

access controls is

communicated to

the families who

are directly

impacted by the

access restrictions.

Good construction

measures that will

reduce impact on

fish stock such as

piling which does

not interfere with

the marine ecology

Implement

Page 112 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 113: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Pre-Construction Stage –

Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp

Impact Mitigation Performance and Impact Monitoring

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

measures to

ensure coral

growth (artificial

reefs etc)

Socio

Economic

Agriculture

Relocation to an

area where people

can farm

The impact on

community access

to farmland during

the project will be

addressed by

resettlement and

compensation to

be undertaken by

the GoTL.

GoTL Design phase,

prior to

construction

Throughout

project site and

surrounding

area

Incl. in

construction

contract cost

Complaints and

Grievance records

review

Per the

Grievance

mechanism

TL Cement

Manager

N/A

Population

and

Influx of new

people to the area

The impact on

community during

GoTL Prior to

construction

As determined

by resettlement

Incl. in

construction

Maintain communities

and limit secondary

Per the

Grievance

TL Cement

Manager

N/A

Page 113 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 114: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Pre-Construction Stage –

Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp

Impact Mitigation Performance and Impact Monitoring

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Community from outside

Baucau

the project will be

addressed by

resettlement and

compensation to

be undertaken by

the GoTL.

facilitated by

GoTL

contract cost impacts of population

increase due to the

Project

mechanism

Community

Health

Increase in injury,

disease and

infections due to

more people in the

area

Facilitate

education and

awareness

programs

throughout the

lifespan of the

Project;

Design roads and

implement driver

TL Cement Prior to

construction and

ongoing

Throughout

project site

Incl. in

construction

contract cost

Complaints and

Grievance records

Per the

Grievance

mechanism

TL Cement

Manager

N/A

Page 114 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 115: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Pre-Construction Stage –

Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp

Impact Mitigation Performance and Impact Monitoring

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

training to improve

traffic safety.

Internal Project

roads will be

designed and

constructed for all-

weather, 24 hr

capability.

Establish a secure

buffer zone from

activities posing

safety risks to

villages or

scattered

dwellings.

Page 115 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 116: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Pre-Construction Stage –

Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp

Impact Mitigation Performance and Impact Monitoring

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Develop an

employee wellness

programme

Institutions,

Schools and

Health

Facilities

No impact

anticipated

The impact on

community access

to institutions

during the project

will be addressed

by resettlement

and compensation

to be undertaken

by the GoTL. Refer

to Air Quality and

Noise and

vibration for

GoTL / TL

Cement

Prior to

construction and

ongoing noise

and air

monitoring

during

construction,

operation and

decommissionin

g stage

Throughout

local region

Incl. in

construction

contract cost

Complaints and

Grievance records

Per the

Grievance

mechanism

TL Cement

Manager

N/A

Page 116 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 117: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Pre-Construction Stage –

Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp

Impact Mitigation Performance and Impact Monitoring

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

relevant mitigation

measures

Community

and Family

Structure

Relocation of

families may

impact structure

Implementation of

the Complaints

and Grievance

mechanism

TL Cement Prior to design

phase, during

design and prior

to construction

Throughout

wider area

Incl. in

construction

contract cost

Complaints and

Grievance records

Per the

Grievance

mechanism

TL Cement

Manager

N/A

Land

ownership

and Land

Rights

Relocation of land

users will not

impact land rights

TL Cement is

currently working

with the

Directorate of

Land, Property and

Cadastral Services

(DLPCS) to map

affected

households,

GoTL / TL

Cement

Prior to

construction

Throughout

project area

and in

surrounding

vicinity

Incl. in

construction

contract cost

Complaints and

Grievance records

Regular review

of records

To be addressed

by resettlement

and

compensation

to be addressed

by GoTL

Page 117 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 118: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Pre-Construction Stage –

Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp

Impact Mitigation Performance and Impact Monitoring

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

farmland, and

other property.

Once TL Cement

has secured the

mining license and

environmental

licenses required

for the Project, the

GoTL will enter

into discussions

with those

affected

households and

property owners.

Natural

Resources

Relocation of land

users will not

Implementation of

the Complaints

TL Cement /

GoTL

Prior to design

phase and

Throughout

project site and

Incl. in

construction

Complaints and

Grievance records

Regular review

of records

To be addressed

by resettlement

Page 118 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 119: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Pre-Construction Stage –

Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp

Impact Mitigation Performance and Impact Monitoring

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Rights impact resources

rights

and Grievance

mechanism

ongoing surrounding

environment, in

particular at

identified

natural

resources

within and near

the project site

contract cost

and

compensation

to be addressed

by GoTL

Cultural

Heritage,

Archaelogical

and Sacred

Sites

Relocation of land

users will not

cultural heritage

sites

First to minimize

encroachment on

such sites

identified by field

surveys by revising

boundary

parameters- If site

cannot be avoided

Construction

Contractor

(during

construction

stage), Mine

Operator

Prior to

construction and

ongoing

throughout

construction,

operation and

decommissionin

g

Heritage sites

identified

through the EIA

as well as any

additional sites

discovered

during

construction,

Incl. in

construction

contract cost

Any and all

occurrences of

damage sites is to be

recorded.

Records to be

reviewed every

6 months.

TL Cement.

Process

improvements

are to be

implemented

where there has

been

unauthorised

Page 119 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 120: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Pre-Construction Stage –

Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp

Impact Mitigation Performance and Impact Monitoring

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

then initiate

relocation.

Where safe access

cannot be

guaranteed, those

sites which are

located adjacent to

the project should

be fenced off,

access restricted

for the project life

or relocated.

All archaeological

excavations within

or adjacent to the

operation or

decommissionin

g phase

impact on

cultural heritage

sites.

Page 120 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 121: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Pre-Construction Stage –

Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp

Impact Mitigation Performance and Impact Monitoring

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

study area should

be authorised by

the State

Secretariat of

Tourism, Art and

Culture and

undertaken by a

team of

professional

archaeologists

Ceremonial

platforms or altars

should be properly

documented and

eventually

relocated to a

Page 121 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 122: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Pre-Construction Stage –

Activity : Clearing the land and levelling, Vehicle movement, drilling the water supply borehole, excavating trenches and preparing the construction accommodation camp

Impact Mitigation Performance and Impact Monitoring

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

different location;

Burial sites should

be properly

documented,

excavated and

relocated to an

agreed upon site;

and

Archaeological

sites should be test

excavated.

Page 122 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 123: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Construction Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Climate Atmospheric

emissions (i.e.

carbon monoxide)

increase from use

of vehicles

Design reviews to

consider

equipment

selection

Design reviews to

implement

Alternative Fuels in

consideration of

climate change

impacts

Construction

Contractor

During

construction

Throughout

project site and

on road

networks

Incl. in

construction

contract cost

Automated Weather

Station (AWS)

recording

measurements of:

Station identification

number;

Date and time of

record/observation;

Air, wet bulb and wet

dew point

temperatures.

Precipitation and

evaporation;

Relative humidity;

Daily

measurements

TL Cement

Annual

reporting for all

project phases

of Greenhouse

Gas emissions in

accordance with

National

Greenhouse and

Energy

Reporting Act

2007.

$500,000 for

Automated

Weather

station

Monitoring

Costs $580k

Page 123 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 124: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Construction Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Wind speed and

direction;

Solar radiation;

Barometric pressure ;

Visibility;

Cloud cover; and

Cloud ceiling height, if

practicable.

Topography,

Geology and

Soils

Changes to

topography and

increase in soil

erosion

Soil contamination

should be

monitored through

maintaining

records of spill

events

Construction

Contractor

During

construction

Throughout

project site and

in surrounding

area

Incl. in

construction

contract cost

Weed growth and

drainage behaviour on

the topsoil stockpile

As required Construction

Contractor

Incl. in

construction

contract cost

Page 124 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 125: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Construction Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Contouring and

establishing

drainage systems

during pre-

construction phase

Air Quality Increase in levels

of dust

All raw materials

storage will be in

enclosed

structures

All materials

transport will be

by fully covered

conveyor belts

Dust and bag

filters will be

installed at all

Construction

Contractor

During

construction

Throughout

project site and

on local road

networks when

materials are

being

transported

Incl. in

construction

contract cost

A monitoring and

reporting program

implemented to

monitor the air quality

in the following

sensitive receptors:

• AQ4 -

settlement area in

Aldeia Osso-ua.

• AQ5 -

representing the

Once every six

months during

construction and

operation

Construction

Contractor: The

monitoring

stations are

derived from

the BBS

Baseline Air

Quality

monitoring

survey (BBS,

2015b).

Page 125 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 126: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Construction Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

critical emissions

hoppers

All areas with

vehicle traffic shall

be watered or

have dust

palliative applied

as necessary for

regular

stabilization of

dust emissions.

All on-site vehicle

traffic shall be

limited to a speed

of 15 mph on

unpaved roads.

construction area.

The monitoring

program should assess

and report on the

following air quality

parameters:

• PM10; and

PM2.5

• CO

• NO2

• SO2; and

• Ozone.

Page 126 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 127: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Construction Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

No vehicles or

plant will be left

idling

unnecessarily.

Reduce the

number of vehicle

movements

through better

planning.

Set an appropriate

speed limit on haul

routes.

All heavy duty

vehicles should

meet certain

emission

Page 127 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 128: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Construction Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

regulation from

local

Environmental

Protection Agency.

Use a good quality

of fuel (e.g. with

low sulphur

content).

Engines and

exhaust systems

should be regularly

serviced according

to manufacturer’s

recommendations

and maintained to

meet statutory

limits/opacity

Page 128 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 129: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Construction Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

tests.

Ensure correct

working methods

are employed for

the Project.

Noise and

Vibration

Increase in levels

of noise

Storage areas

should be located

away from

sensitive

receptors.

Haulage of goods

and movement of

vehicles/people

and equipment

can be scheduled.

Construction

Contractor

During

construction and

pre construction

(scheduling)

Throughout

project site and

in particular in

the vicinity of

sensitive

receptors.

Local road

networks

Incl. in

construction

contract cost

At sensitive receptors:

AQ4 – Settlement area

at Aldeia Osso-Ua

AQ5 - representing the

construction area.

Every 6 months

measurements

at sensitive

receptors i.e.

Results

interpretation

and review of

the EMP as

required.

Collation of

results into

Construction

Contractor

Incl. in

construction

contract cost

Page 129 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 130: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Construction Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Where required,

noise barriers can

be constructed to

abate the noise

impacts.

Alternative

construction

methods and

selection of less

noisy equipment

to do the tasks.

semi-annual

Environmental

Report to

NDCPEI

Surface

Water

Decrease in flows

in streams

Changes in water

quality of

Drains down-

gradient from the

site to capture

potentially

Construction

Contractor

During

construction

Throughout

project site and

down gradient

of project site

Incl. in

construction

contract cost

Flow meters / stream

gauges at the Bucoli

River (1.6km west)

and at Uaimatabai,

Monthly water

quality and

quantity

measurements

TL Cement -

Collation of

results into

Annual

Page 130 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 131: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Construction Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

streamflow contaminated

surface water run-

off.

Monitoring of

surface water

features for water

quality impacts.

Spills management

and pollution

control through

the Emergency

Plan.

to capture

contaminated

surface run off

Uaisa and Waino

springs

at monitoring

boreholes, key

spring receptors

at Waiono,

Uaimatabai and

Uaisa.

Interpretation of

data every 6

months.

Environmental

Report to

NDCPEI

Groundwater Decrease in flows

in springs

Changes in water

quality of springs

Detailed

hydrological study

to establish

baseline

groundwater

Construction

Contractor

During

construction

Throughout

project site

Incl. in

construction

contract cost

Water quality and

quantity

measurements at key

spring receptors at

Uaimatabai, Uaisa and

Monthly water

quality and

quantity

measurements

TL Cement -

Collation of

results into

Annual

Environmental

Page 131 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 132: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Construction Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

monitoring

network including

boreholes, spring

flow gauging and

water quality

analysis

Groundwater

modelling of

Water Supply

borehole to

quantify

drawdown impacts

Uaino.

Reporting and

interpretation of

data quarterly

Report to

NDCPEI

Coastal and

Marine

Pollution of sea

water

Increase in

turbidity of sea

Control of spills

and discharge of

material or fuels to

the beach or

marine

Construction

Contractor

During

construction

Throughout

project site and

in local marine

environment

Incl. in

construction

contract cost

Sedimentation effects. Monitoring

should be

undertaken at a

frequency to be

determined

TL Cement -

Collation of

results into

Annual

Environmental

Page 132 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 133: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Construction Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

water

Spread of marine

pests from ships

environment;

Contouring and

movement of

vehicles on the

beach to minimize

scour and erosion;

Vessel approach to

minimize discharge

of ballast and

spread of marine

pests; and

Storage of

construction

materials to

minimize

disturbance of

once the

sediment

transport

associated with

the MOF has

been quantified;

and Jetty

construction has

been completed.

Report to

NDCPEI

Page 133 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 134: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Construction Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

beach processes.

Flora Removal of

threatened plants

Dust suppression

measures (e.g.

water sprinkling)

at all dust

generating sites

Weed

management

activities including

spraying

Construction

Contractor

During

excavation and

construction

Throughout

project site

Incl. in

construction

contract cost

The total area of

vegetation cleared

(habitat destruction)

at the end of phase

End of phase TL Cement -

Collation of

results into

Annual

Environmental

Report to

NDCPEI

Fauna Removal of

threatened

animals

Site clearing to be

conducted

sequentially and

from one corner of

the site to the

other, enabling

Construction

Contractor

During

construction

Throughout

project site

Incl. in

construction

contract cost

All fauna injury and

death records.

Reporting and

interpretation

every six months

TL Cement -

Collation of

results into

Annual

Environmental

Report to

Page 134 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 135: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Construction Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

highly mobile

fauna species to

leave the

construction area

NDCPEI

Marine fauna

(including

fisheries)

Loss of fishing

habitat and coral

reefs

Collection of

additional baseline

environmental

data including

large marine

mammal, turtle

nesting, seagrass

and crocodile

habitat.

Construction

Contractor

During

construction and

planning

(scheduling).

Limit shipping

movements

during mammal

migration.

Throughout

project site ,in

particular at the

jetty and MOF

and in wider

area as required

in case of spills

Incl. in

construction

contract cost

Regular community

engagement surveys

around fisheries

Survey of coral health,

sedimentation and

fisheries.

Collection of water

quality measurements

at reference and

impact sites to be

sited within and

adjacent to the project

Annual review

and reporting of

coral habitats

around Jetty and

MOR.

Water Quality

measurements

are to be taken

at least twice

per calendar

year, outside of

and during the

monsoon season

TL Cement -

Collation of

results into

Annual

Environmental

Report to

NDCPEI

Page 135 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 136: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Construction Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

impact area.

Marine

Habitats

(including

Coral)

Loss of fishing

habitat and coral

reefs

Ballast water

management and

Introduced Marine

Pests monitoring

and controls;

Identification of

coral locations on

engineering

drawings and

construction plans;

Identification of

impact zone sites,

nearby sites and

reference

Construction

Contractor

Pre-construction

planning and

during

construction

In marine

environment

bordering

project site and

within project

area

Incl. in

construction

contract cost

Undertake a post-

construction survey of

the identified sites to

compare the coral

health to the

reference imagery and

GPS database.

Reporting and

recording of post-

construction coral

health monitoring

data.

Make

recommendations on

One post

construction

survey.

Frequency of

monitoring

based on results

TL Cement -

Collation of

results into

Annual

Environmental

Report to

NDCPEI

Page 136 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 137: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Construction Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

(background) sites

for the coral health

monitoring

program.

the frequency of

operations coral

health surveys.

Traffic Increase in amount

of traffic on the

roads

Planning to

minimize vehicle

movements (e.g.

use of buses to

transport workers

and house in

camps)

Limit reversing

requirements

Traffic signage

implementation

Construction

Contractor /

Mine Operator

During planning

prior to

construction and

during

construction

Throughout

project site and

on local road

networks

Incl. in

construction

contract cost

Traffic incidents and

mitigation measures

implemented

Update Safety

Management

System to

record and

document traffic

incidents and

mitigation

measures

implemented as

and when they

occur

Construction

Contractor /

Mine Operator

Costs to

Construction

Contractor /

Mine

Operator

Page 137 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 138: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Construction Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Speed limits and

enforcement

Road widening

Infrastructur

e

Increased pressure

on existing

infrastructure

Identify and

prioritize the

upgrades and

construction of

new infrastructure

required for the

construction and

operation of the

Project (e.g. water

treatment and

wastewater

facilities; roads

and

TL Cement Update

priorities for

upgrade if

required

Throughout

project site

Incl. in

construction

contract cost

Complaints and

Grievance records

review

Stakeholder

consultation to check

progress

Regular review

of Complaints

and Grievance

record

Regular

stakeholder

consultation

TL Cement

Page 138 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 139: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Construction Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

accommodation

facilities).

Ongoing

inspection,

monitoring and

maintenance

programmes will

be developed and

implemented for

the relevant

infrastructure

during the

operational phase

of the Project to

ensure optimal

operation.

Page 139 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 140: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Construction Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Employment Training and

development of

local people

Selection and

management of

employee

applications by a

specialist

employee

management

institution formed

through a

consultative

process with sub-

district and suco

leadership

Construction

Contractor

During

construction

At Employee

Management

Institution

Offices

Incl. in

construction

contract cost

Complaints and

Grievance records

review

Stakeholder

consultation to check

progress

Regular review

of Complaints

and Grievance

record

Regular

stakeholder

consultation

TL Cement

Economic

Use of

Training and

development of

Minimise the

disturbance

TL Cement /

Construction

Stripping soil

and site

Throughout

project site

Incl. in

construction

Control of weed and

pathogen hygiene

NA TL Cement /

Construction

Page 140 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 141: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Construction Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Forestry and

other Natural

Resources

local people footprint as far as

practicable.

Site clearing to be

conducted

sequentially.

Contractor clearing.

Stockpile topsoil

immediately

following

clearing.

Ongoing weed

control during

construction

contract cost practices Contractor

Fishing Decrease in people

who fish

Providing

alternative access

locations,

Providing safe

passage zones

across the

conveyor corridor

crossing the beach

between the Jetty

TL Cement /

Construction

Contractor

During

construction

Throughout

project site and

in wider area

(alternative

access

locations, safe

passage zones,

artificial reef

placement)

Incl. in

construction

contract cost

Fisheries assessment

is a component of the

Marine Habitats and

Coral monitoring

Per the

Grievance

mechanism

TL Cement

Manager

N/A

Page 141 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 142: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Construction Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

and the Plant sites;

and

Ensuring that the

timeline for

implementation of

access controls is

communicated to

the families who

are directly

impacted by the

access restrictions.

Good construction

measures that will

reduce impact on

fish stock such as

piling which does

not interfere with

Page 142 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 143: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Construction Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

the marine ecology

Implement

measures to

ensure coral

growth (artificial

reefs etc)

Socio

Economic

Agriculture

Relocation to an

area where people

can farm

The impact on

community access

to farmland during

the project will be

addressed by

resettlement and

compensation to

be undertaken by

the GoTL.

GoTL Access

established prior

to construction

and managed /

mantained as

required

As determined

by resettlement

facilitated by

GoTL

Incl. in

construction

contract cost

Control of weed and

pathogen hygiene

practices

Per the

Grievance

mechanism

TL Cement

Manager

N/A

Population Influx of new The impact on GoTL Prior to As determined Incl. in Complaints and Per the TL Cement N/A

Page 143 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 144: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Construction Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

and

Community

people to the area

from outside

Baucau

community during

the project will be

addressed by

resettlement and

compensation to

be undertaken by

the GoTL.

construction and

managed /

maintained as

required

by resettlement

facilitated by

GoTL

construction

contract cost

Grievance records

Grievance

mechanism

Manager

Community

Health

Increase in injury,

disease and

infections due to

more people in the

area

Facilitate

education and

awareness

programs

throughout the

lifespan of the

Project;

Design roads and

implement driver

training to improve

TL Cement Ongoing Throughout

project site and

in surrounding

area (secure

buffer zones)

Incl. in

construction

contract cost

Complaints and

Grievance records

Per the

Grievance

mechanism

TL Cement

Manager

N/A

Page 144 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 145: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Construction Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

traffic safety.

Internal Project

roads will be

designed and

constructed for all-

weather, 24 hr

capability.

Establish a secure

buffer zone from

activities posing

safety risks to

villages or

scattered

dwellings.

Develop an

employee wellness

Page 145 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 146: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Construction Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

programme

Institutions,

Schools and

Health

Facilities

No impact

anticipated

The impact on

community access

to institutions

during the project

will be addressed

by resettlement

and compensation

to be undertaken

by the GoTL. Refer

to Air Quality and

Noise and

vibration for

relevant mitigation

measures

GoTL / TL

Cement /

Construction

Contractor

Impact on

community

access

addressed prior

to construction.

Noise and

vibration

monitoring

ongoing

throughout

construction,

operation and

decommissionin

g phases

As determined

by resettlement

facilitated by

GoTL. Air and

Noise

monitoring at

selected

appropriate

locations and

near sensitive

receptors

Incl. in

construction

contract cost

Complaints and

Grievance records

Per the

Grievance

mechanism

TL Cement

Manager

N/A

Community

and Family

Relocation of

families may

Implementation of

the Complaints

TL Cement /

Mine Operator

Impact on

community

Throughout

project site and

Incl. in

construction

Complaints and

Grievance records

Per the

Grievance

TL Cement

Manager

N/A

Page 146 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 147: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Construction Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Structure impact structure and Grievance

mechanism

addressed

construction but

complaints and

grievance

records to be

maintained

throughout

project

wider area as

required

contract cost

mechanism

Land

ownership

and Land

Rights

Relocation of land

users will not

impact land rights

TL Cement is

currently working

with the

Directorate of

Land, Property and

Cadastral Services

(DLPCS) to map

affected

households,

GoTL / TL

Cement

Ongoing Affected

households and

property

owners

Incl. in

construction

contract cost

Complaints and

Grievance records

Regular review

of records

To be addressed

by resettlement

and

compensation

to be addressed

by GoTL

Page 147 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 148: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Construction Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

farmland, and

other property.

Once TL Cement

has secured the

mining license and

environmental

licenses required

for the Project, the

GoTL will enter

into discussions

with those

affected

households and

property owners.

Natural

Resources

Rights

Relocation of land

users will not

impact resources

Implementation of

the Complaints

and Grievance

TL Cement /

GoTL

Ongoing Throughout

project site and

surrounding

Incl. in

construction

contract cost

Complaints and

Grievance records

Regular review

of records

To be addressed

by resettlement

and

Page 148 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 149: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Construction Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

rights mechanism

environment, in

particular at

identified

natural

resources

within and near

the project site

compensation

to be addressed

by GoTL

Cultural

Heritage,

Archaelogical

and Sacred

Sites

Relocation of land

users will not

cultural heritage

sites

Where safe access

cannot be

guaranteed, those

sites which are

located adjacent to

the project should

be fenced off,

access restricted

for the project life

or relocated.

Construction

Contractor

Prior to

construction for

planning and

design of

project, sites to

be fenced and

protected

throughout life

of project

Heritage sites

identified

through the EIA

as well as any

additional sites

discovered

during

construction,

operation or

decommissionin

Incl. in

construction

contract cost

Any and all

occurrences of

damage sites is to be

recorded.

Records to be

reviewed every

6 months.

TL Cement.

Process

improvements

are to be

implemented

where there has

been

unauthorised

impact on

cultural heritage

Page 149 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 150: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Construction Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

g phase sites

Page 150 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 151: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Operations

Activity : Vehicle movement, operating the jetty, conveyor belt and cement plant, operating the power plant, people moving and working on site, ships moving to/from the jetty, cement transport to/from Baucau

Environmental

Concern

Potential

Impact

Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Climate Atmospheric

emissions (i.e.

carbon

monoxide)

increase from

use of vehicles

TL Cement During operation Throughout

project site and

on local road

networks

Incl. in

Operations

contract cost

Automated Weather

Station (AWS)

recording

measurements of:

Station identification

number;

Date and time of

record/observation;

Air, wet bulb and wet

dew point

temperatures.

Precipitation and

evaporation;

Relative humidity;

Daily

measurements

TL Cement

Annual

reporting for all

project phases

of Greenhouse

Gas emissions in

accordance with

National

Greenhouse and

Energy

Reporting Act

2007.

$500,000 for

Automated

Weather

station

Monitoring

Costs $580k

Page 151 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 152: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Operations

Activity : Vehicle movement, operating the jetty, conveyor belt and cement plant, operating the power plant, people moving and working on site, ships moving to/from the jetty, cement transport to/from Baucau

Environmental

Concern

Potential

Impact

Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Wind speed and

direction;

Solar radiation;

Barometric pressure ;

Visibility;

Cloud cover; and

Cloud ceiling height, if

practicable.

Topography,

Geology and Soils

Changes to

topography

and increase

in soil erosion

Soil

contamination

should be

monitored

through

maintaining

TL Cement During operation Throughout

project site and

surrounding

area

Incl. in

Operations

contract cost

Water quality and

quantity

measurements at key

spring receptors,

Uaino, and in the

Water Reserve area.

Monthly

measurements.

Reporting and

interpretation of

data every 6

months.

Page 152 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 153: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Operations

Activity : Vehicle movement, operating the jetty, conveyor belt and cement plant, operating the power plant, people moving and working on site, ships moving to/from the jetty, cement transport to/from Baucau

Environmental

Concern

Potential

Impact

Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

records of spill

events

Contouring and

establishing

drainage

systems during

pre-construction

phase

Air Quality Increase in

levels of dust

All raw materials

storage will be

in enclosed

structures

All materials

transport will be

by fully covered

conveyor belts

TL Cement During operation Throughout

project site

Incl. in

Operations

contract cost

A monitoring and

reporting program

implemented to

monitor the air quality

in the following

sensitive receptors:

• AQ4 -

settlement area in

Once every six

months during

construction and

operation

TL Cement: The

monitoring

stations are

derived from

the BBS

Baseline Air

Quality

monitoring

survey (BBS,

Page 153 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 154: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Operations

Activity : Vehicle movement, operating the jetty, conveyor belt and cement plant, operating the power plant, people moving and working on site, ships moving to/from the jetty, cement transport to/from Baucau

Environmental

Concern

Potential

Impact

Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Dust and bag

filters will be

installed at all

critical

emissions

hoppers

All areas with

vehicle traffic

shall be watered

or have dust

palliative

applied as

necessary for

regular

stabilization of

dust emissions.

Aldeia Osso-ua.

• AQ5 -

representing the

construction area.

The monitoring

program should assess

and report on the

following air quality

parameters:

• PM10; and

PM2.5

• CO

• NO2

• SO2; and

2015b).

Page 154 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 155: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Operations

Activity : Vehicle movement, operating the jetty, conveyor belt and cement plant, operating the power plant, people moving and working on site, ships moving to/from the jetty, cement transport to/from Baucau

Environmental

Concern

Potential

Impact

Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

All on-site

vehicle traffic

shall be limited

to a speed of 15

mph on unpaved

roads.

No vehicles or

plant will be left

idling

unnecessarily.

Reduce the

number of

vehicle

movements

through better

planning.

• Ozone.

Page 155 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 156: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Operations

Activity : Vehicle movement, operating the jetty, conveyor belt and cement plant, operating the power plant, people moving and working on site, ships moving to/from the jetty, cement transport to/from Baucau

Environmental

Concern

Potential

Impact

Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Set an

appropriate

speed limit on

haul routes.

All heavy duty

vehicles should

meet certain

emission

regulation from

local

Environmental

Protection

Agency.

Use a good

quality of fuel

(e.g. with low

Page 156 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 157: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Operations

Activity : Vehicle movement, operating the jetty, conveyor belt and cement plant, operating the power plant, people moving and working on site, ships moving to/from the jetty, cement transport to/from Baucau

Environmental

Concern

Potential

Impact

Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

sulphur

content).

Engines and

exhaust systems

should be

regularly

serviced

according to

manufacturer’s

recommendatio

ns and

maintained to

meet statutory

limits/opacity

tests.

Ensure correct

working

Page 157 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 158: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Operations

Activity : Vehicle movement, operating the jetty, conveyor belt and cement plant, operating the power plant, people moving and working on site, ships moving to/from the jetty, cement transport to/from Baucau

Environmental

Concern

Potential

Impact

Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

methods are

employed for

the Project.

Noise and

Vibration

Increase in

levels of noise

Haulage of

goods and

movement of

vehicles/people

and equipment

can be

scheduled.

Where required,

noise barriers

can be

constructed to

abate the noise

impacts.

TL Cement During operation Throughout

project site and

in particular in

the vicinity of

sensitive

receptors.

Local road

networks

Incl. in

Operations

contract cost

At sensitive receptors

(as per construction)

Once per year

measurements

Results

interpretation

and review of

the EMP as

required.

Collation of

results into

Annual

Environmental

Report to

NDCPEI

Page 158 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 159: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Operations

Activity : Vehicle movement, operating the jetty, conveyor belt and cement plant, operating the power plant, people moving and working on site, ships moving to/from the jetty, cement transport to/from Baucau

Environmental

Concern

Potential

Impact

Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Alternative

construction

methods and

selection of less

noisy equipment

to do the tasks.

Surface Water Decrease in

flows in

streams

Changes in

water quality

of streamflow

Drains down-

gradient from

the site to

capture

potentially

contaminated

surface water

run-off.

Storm water

design will be

TL Cement During operation Throughout

project site and

drains down

gradient of site

Incl. in

Operations

contract cost

Flow meters / stream

gauges at the Bucoli

River (1.6km west)

and at Uaimatabai,

Uaisa and Waino

springs

Monthly water

quality and

quantity

measurements

at monitoring

boreholes, key

spring receptors

at Waiono,

Uaimatabai and

Uaisa.

TL Cement -

Collation of

results into

Annual

Environmental

Report to

NDCPEI

$1.4M

Page 159 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 160: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Operations

Activity : Vehicle movement, operating the jetty, conveyor belt and cement plant, operating the power plant, people moving and working on site, ships moving to/from the jetty, cement transport to/from Baucau

Environmental

Concern

Potential

Impact

Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

incorporated to

manage extreme

weather events

Monitoring of

surface water

features for

water quality

impacts.

Spills

management

and pollution

control through

the Emergency

Plan.

Interpretation of

data every 6

months.

Groundwater Decrease in

flows in

springs

Detailed

hydrological

study to

TL Cement During operation Throughout

project site

Incl. in

Operations

contract cost

Flow meters / stream

gauges at the Bucoli

River (1.6km west)

Monthly water

quality and

quantity

TL Cement -

Collation of

results into

$1.4M

Page 160 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 161: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Operations

Activity : Vehicle movement, operating the jetty, conveyor belt and cement plant, operating the power plant, people moving and working on site, ships moving to/from the jetty, cement transport to/from Baucau

Environmental

Concern

Potential

Impact

Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Changes in

water quality

of springs

establish

baseline

groundwater

monitoring

network

including

boreholes,

spring flow

gauging and

water quality

analysis

Groundwater

modelling of

Water Supply

borehole to

quantify

drawdown

and at Uaimatabai,

Uaisa and Waino

springs

measurements

at monitoring

boreholes, key

spring receptors

at Waiono,

Uaimatabai and

Uaisa.

Interpretation of

data every 6

months.

Annual

Environmental

Report to

NDCPEI

Page 161 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 162: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Operations

Activity : Vehicle movement, operating the jetty, conveyor belt and cement plant, operating the power plant, people moving and working on site, ships moving to/from the jetty, cement transport to/from Baucau

Environmental

Concern

Potential

Impact

Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

impacts

Design for

handling and

storage of

potential

contaminants

(including fuels

and chemicals)

to eliminate risk

Coastal and

Marine

Pollution of

sea water

Increase in

turbidity of

sea water

Spread of

marine pests

Control of spills

and discharge of

material or fuels

to the beach or

marine

environment;

Vessel approach

TL Cement During operation Throughout

project site and

in local marine

environment

Incl. in

Operations

contract cost

Sedimentation effects Should be

monitored at a

frequency to be

determined

once the

sediment

transport

associated with

TL Cement -

Collation of

results into

Annual

Environmental

Report to

NDCPEI

$1.4M

Page 162 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 163: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Operations

Activity : Vehicle movement, operating the jetty, conveyor belt and cement plant, operating the power plant, people moving and working on site, ships moving to/from the jetty, cement transport to/from Baucau

Environmental

Concern

Potential

Impact

Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

from ships to minimize

discharge of

ballast and

spread of

marine pests

the MOF has

been quantified;

and Jetty

construction has

been completed.

Flora Removal of

threatened

plants

Dust

suppression

measures (e.g.

water sprinkling)

at all dust

generating sites

Weed

management

activities

including

TL Cement Ongoing Throughout

project site

Incl. in

Operations

contract cost

The total area of

vegetation cleared

(habitat destruction)

at the end of phase

End of phase TL Cement -

Collation of

results into

Annual

Environmental

Report to

NDCPEI

Page 163 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 164: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Operations

Activity : Vehicle movement, operating the jetty, conveyor belt and cement plant, operating the power plant, people moving and working on site, ships moving to/from the jetty, cement transport to/from Baucau

Environmental

Concern

Potential

Impact

Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

spraying

Fauna Removal of

threatened

animals

Vehicles obey

speed limits.

TL Cement Ongoing Throughout and

surrounding

project site

Incl. in

Operations

contract cost

All fauna injury and

death records.

Reporting and

interpretation

every six months

TL Cement -

Collation of

results into

Annual

Environmental

Report to

NDCPEI

Marine Fauna

(including

fisheries)

Loss of fishing

habitat and

coral reefs

Identification of

water quality

reference and

impact sites to

be sited within

and adjacent to

the project

impact area.

TL Cement During operation.

Limit shipping

during mammal

migration

Throughout

project site ,in

particular at the

jetty and MOF

and in wider

area as required

in case of spills

Incl. in

Operations

contract cost

Regular community

engagement surveys

around fisheries

Survey of coral health,

sedimentation and

fisheries.

Collection of water

quality measurements

Annual review

and reporting of

coral habitats

around Jetty and

MOR.

Water Quality

measurements

are to be taken

TL Cement -

Collation of

results into

Annual

Environmental

Report to

NDCPEI

Page 164 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 165: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Operations

Activity : Vehicle movement, operating the jetty, conveyor belt and cement plant, operating the power plant, people moving and working on site, ships moving to/from the jetty, cement transport to/from Baucau

Environmental

Concern

Potential

Impact

Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

at reference and

impact sites to be

sited within and

adjacent to the project

impact area.

at least twice

per calendar

year, outside of

and during the

monsoon

season.

Marine habitats

(including coral)

Loss of fishing

habitat and

coral reefs

Ballast water

management

and Introduced

Marine Pests

monitoring and

controls;

Identification of

impact zone

sites, nearby

TL Cement During operation In marine

environment

bordering

project site and

within project

area

Incl. in

Operations

contract cost

Compare the coral

health to the

reference imagery and

GPS database

Undertake

regular,

scheduled

surveys of the

identified sites.

The frequency

(e.g. 1x per year)

should be

confirmed

during the

TL Cement -

Collation of

results into

Annual

Environmental

Report to

NDCPEI

Page 165 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 166: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Operations

Activity : Vehicle movement, operating the jetty, conveyor belt and cement plant, operating the power plant, people moving and working on site, ships moving to/from the jetty, cement transport to/from Baucau

Environmental

Concern

Potential

Impact

Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

sites and

reference

(background)

sites for the

coral health

monitoring

program.

Construction

phase.

Traffic Increase in

amount of

traffic on the

roads

Planning to

minimize vehicle

movements (e.g.

use of buses to

transport

workers and

house in camps)

Limit reversing

requirements

Traffic signage

TL Cement Throughout life of

project

Throughout

project site and

on local road

networks

Incl. in

Operations

contract cost

Traffic incidents and

mitigation measures

implemented

Update Safety

Management

System to

record and

document traffic

incidents and

mitigation

measures

implemented as

and when they

Construction

Contractor /

Mine Operator

Costs to

Construction

Contractor /

Mine

Operator

Page 166 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 167: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Operations

Activity : Vehicle movement, operating the jetty, conveyor belt and cement plant, operating the power plant, people moving and working on site, ships moving to/from the jetty, cement transport to/from Baucau

Environmental

Concern

Potential

Impact

Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

implementation

Speed limits and

enforcement

Road widening

occur.

Infrastructure Increased

pressure on

existing

infrastructure

Ongoing

inspection,

monitoring and

maintenance

programmes will

be developed

and

implemented for

the relevant

infrastructure

during the

TL Cement Ongoing Throughout

project site

Incl. in

Operations

contract cost

Complaints and

Grievance records

review

Stakeholder

consultation to check

progress

Regular review

of Complaints

and Grievance

record

Regular

stakeholder

consultation

TL Cement

Page 167 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 168: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Operations

Activity : Vehicle movement, operating the jetty, conveyor belt and cement plant, operating the power plant, people moving and working on site, ships moving to/from the jetty, cement transport to/from Baucau

Environmental

Concern

Potential

Impact

Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

operational

phase of the

Project to

ensure optimal

operation.

Employment Training and

development

of local

people

Selection and

management of

employee

applications by a

specialist

employee

management

institution

formed through

a consultative

process with

TL Cement Ongoing as

required

Selected

Employment

Management

Institution

Offices

Incl. in

Operations

contract cost

Complaints and

Grievance records

review

Stakeholder

consultation to check

progress

Regular review

of Complaints

and Grievance

record

Regular

stakeholder

consultation

TL Cement

Page 168 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 169: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Operations

Activity : Vehicle movement, operating the jetty, conveyor belt and cement plant, operating the power plant, people moving and working on site, ships moving to/from the jetty, cement transport to/from Baucau

Environmental

Concern

Potential

Impact

Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

sub-district and

suco leadership

Economic Use of

Forestry and

other Natural

Resources

Training and

development

of local

people

Minimise the

disturbance

footprint as far

as practicable.

Site clearing to

be conducted

sequentially.

TL Cement Ongoing Throughout

project site and

surrounding

area

Incl. in

Operations

contract cost

Control of weed and

pathogen hygiene

practices

NA TL Cement

Fishing Decrease in

people who

fish

Providing

alternative

access locations,

Providing safe

TL Cement Ongoing Throughout

wider region

Incl. in

Operations

contract cost

Fisheries assessment

is a component of the

Marine Habitats and

Coral monitoring

NA NA

Page 169 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 170: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Operations

Activity : Vehicle movement, operating the jetty, conveyor belt and cement plant, operating the power plant, people moving and working on site, ships moving to/from the jetty, cement transport to/from Baucau

Environmental

Concern

Potential

Impact

Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

passage zones

across the

conveyor

corridor crossing

the beach

between the

Jetty and the

Plant sites; and

Ensuring that

the timeline for

implementation

of access

controls is

communicated

to the families

who are directly

impacted by the

Page 170 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 171: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Operations

Activity : Vehicle movement, operating the jetty, conveyor belt and cement plant, operating the power plant, people moving and working on site, ships moving to/from the jetty, cement transport to/from Baucau

Environmental

Concern

Potential

Impact

Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

access

restrictions.

Good

construction

measures that

will reduce

impact on fish

stock such as

piling which

does not

interfere with

the marine

ecology

Implement

measures to

ensure coral

growth (artificial

Page 171 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 172: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Operations

Activity : Vehicle movement, operating the jetty, conveyor belt and cement plant, operating the power plant, people moving and working on site, ships moving to/from the jetty, cement transport to/from Baucau

Environmental

Concern

Potential

Impact

Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

reefs etc)

Socio Economic

Agriculture

Relocation to

an area where

people can

farm

The impact on

community

access to

farmland during

the project will

be addressed by

resettlement

and

compensation to

be undertaken

by the GoTL.

TL Cement At completion of

operation

Throughout

wider region

Incl. in

Operations

contract cost

Control of weed and

pathogen hygiene

practices

Population and

Community

Influx of new

people to the

area from

outside

Baucau

The impact on

community

during the

project will be

addressed by

GoTL Impact on

community

addressed

construction but

complaints and

Incl. in

Operations

contract cost

Complaints and

Grievance records

Regular review

of records

Page 172 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 173: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Operations

Activity : Vehicle movement, operating the jetty, conveyor belt and cement plant, operating the power plant, people moving and working on site, ships moving to/from the jetty, cement transport to/from Baucau

Environmental

Concern

Potential

Impact

Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

resettlement

and

compensation to

be undertaken

by the GoTL.

grievance records

to be maintained

throughout

project

Community

Health

Increase in

injury, disease

and infections

due to more

people in the

area

Facilitate

education and

awareness

programs

throughout the

lifespan of the

Project;

Design roads

and implement

driver training to

improve traffic

safety.

TL Cement Impact on

community

addressed

construction but

complaints and

grievance records

to be maintained

throughout

project

Incl. in

Operations

contract cost

Complaints and

Grievance records

Regular review

of records

Page 173 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 174: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Operations

Activity : Vehicle movement, operating the jetty, conveyor belt and cement plant, operating the power plant, people moving and working on site, ships moving to/from the jetty, cement transport to/from Baucau

Environmental

Concern

Potential

Impact

Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Internal Project

roads will be

designed and

constructed for

all-weather, 24

hr capability.

Establish a

secure buffer

zone from

activities posing

safety risks to

villages or

scattered

dwellings.

Develop an

employee

Page 174 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 175: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Operations

Activity : Vehicle movement, operating the jetty, conveyor belt and cement plant, operating the power plant, people moving and working on site, ships moving to/from the jetty, cement transport to/from Baucau

Environmental

Concern

Potential

Impact

Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

wellness

programme

Institutions,

Schools and

Health Facilities

No impact

anticipated

The impact on

community

access to

institutions

during the

project will be

addressed by

resettlement

and

compensation to

be undertaken

by the GoTL.

Refer to Air

Quality and

Noise and

GoTL Impact on

community

addressed

construction but

complaints and

grievance records

to be maintained

throughout

project

Throughout

local region

Incl. in

Operations

contract cost

Complaints and

Grievance records

Regular review

of records

Page 175 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 176: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Operations

Activity : Vehicle movement, operating the jetty, conveyor belt and cement plant, operating the power plant, people moving and working on site, ships moving to/from the jetty, cement transport to/from Baucau

Environmental

Concern

Potential

Impact

Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

vibration for

relevant

mitigation

measures

Community and

Family Structure

Transient

workers

families may

impact family

structures

Implementation

of the

Complaints and

Grievance

mechanism

TL Cement Impact on

community

addressed

construction but

complaints and

grievance records

to be maintained

throughout

project

Throughout

local region

Incl. in

Operations

contract cost

Complaints and

Grievance records

Regular review

of records

Land ownership

and Land Rights

No impact

during

operations

Complaints and

Grievance records

Regular review

of records

Page 176 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 177: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Operations

Activity : Vehicle movement, operating the jetty, conveyor belt and cement plant, operating the power plant, people moving and working on site, ships moving to/from the jetty, cement transport to/from Baucau

Environmental

Concern

Potential

Impact

Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Natural Resources

Rights

No impact

during

operations

Cultural Heritage,

Archaeological

and Sacred Sites

No impact

during

operations

Page 177 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 178: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Decommissioning Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Climate Atmospheric

emissions (i.e.

carbon monoxide)

increase from use

of vehicles

Select equipment

with lowest

practical

emissions.

TL Cement /

Decommissionin

g Contractor

During

decommissionin

g

Throughout

project site and

on local road

networks

Incl. in

Decommissionin

g contract cost

Maintain Automated

Weather Station

(AWS) per Operations

Phase

Daily

measurements.

TL Cement -

Annual

reporting for all

project phases

of Greenhouse

Gas emissions in

accordance with

National

Greenhouse and

Energy

Reporting Act

2007.

Page 178 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 179: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Decommissioning Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Topography,

Geology and

Soils

Changes to

topography and

increase in soil

erosion

Soil contamination

should be

monitored through

maintaining

records of spill

events

Contouring and

establishing

drainage systems

during

decommissioning

phase

TL Cement /

Decommissionin

g Contractor

During

decommissionin

g

Throughout

project site

Incl. in

Decommissionin

g contract cost

Post closure

assessment of

rehabilitation success

and soil health

5 years after

closure

Page 179 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 180: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Decommissioning Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Air Quality Increase in levels

of dust

All raw materials

storage will be in

enclosed

structures

All materials

transport will be

by fully covered

conveyor belts

Dust and bag

filters will be

installed at all

critical emissions

hoppers

All areas with

vehicle traffic shall

be watered or

have dust

palliative applied

as necessary for

regular

stabilization of

TL Cement /

Decommissionin

g Contractor

During

decommissionin

g, in particular

during

excavation,

stockpiling and

grading of

materials.

Throughout

project site

Incl. in

Decommissionin

g contract cost

Install Automated

Weather Station

(AWS) recording daily

measurements of:

Station identification

number;

Date and time of

record/observation;

Air, wet bulb and wet

dew point

temperatures.

Precipitation and

evaporation;

Relative humidity;

Wind speed and

direction;

Solar radiation;

Barometric pressure ;

Daily

measurements

TL Cement -

Annual

reporting for all

project phases

of Greenhouse

Gas emissions in

accordance with

National

Greenhouse and

Energy

Reporting Act

2007.

Page 180 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 181: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Decommissioning Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Noise and

Vibration

Increase in levels

of noise

Storage areas

should be located

away from

sensitive

receptors.

Haulage of goods

and movement of

vehicles/people

and equipment

can be scheduled.

Where required,

noise barriers can

be constructed to

abate the noise

impacts.

Alternative

construction

methods and

selection of less

noisy equipment

TL Cement /

Decommissionin

g Contractor

During

decommissionin

g

Throughout

project site and

in particular in

the vicinity of

sensitive

receptors.

Local road

networks

Incl. in

Decommissionin

g contract cost

At sensitive receptors

(as per construction)

Once per year

measurements

Results

interpretation

and review of

the EMP as

required.

Collation of

results into

semi-annual

Environmental

Report to

NDCPEI

Page 181 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 182: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Decommissioning Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Surface

Water

Decrease in flows

in streams

Changes in water

quality of

streamflow

Drains down-

gradient from the

site to capture

potentially

contaminated

surface water run-

off.

Storm water

design will be

incorporated to

manage extreme

weather events

Monitoring of

surface water

features for water

quality impacts.

Spills management

and pollution

control through

the Emergency

Plan.

TL Cement /

Decommissionin

g Contractor

During

decommissionin

g

Drains down

gradient of site.

Other measures

throughout

project site

Incl. in

Decommissionin

g contract cost

Flow meters / stream

gauges at the Bucoli

River (1.6km west)

and at Uaimatabai,

Uaisa and Waino

springs

Monthly water

quality and

quantity

measurements

at monitoring

boreholes, key

spring receptors

at Waiono,

Uaimatabai and

Uaisa.

Interpretation of

data every 6

months.

TL Cement -

Collation of

results into

Annual

Environmental

Report to

NDCPEI

Page 182 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 183: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Decommissioning Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Groundwater Decrease in flows

in springs

Changes in water

quality of springs

Design for

handling and

storage of

potential

contaminants

(including fuels

and chemicals) to

eliminate risk

TL Cement /

Decommissionin

g Contractor

During

decommissionin

g

Throughout

project site

Incl. in

Decommissionin

g contract cost

NA NA NA NA

Page 183 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 184: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Decommissioning Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Coastal and

Marine

Pollution of sea

water

Increase in

turbidity of sea

water

Spread of marine

pests from ships

Control of spills

and discharge of

material or fuels to

the beach or

marine

environment;

Contouring and

movement of

vehicles on the

beach to minimize

scour and erosion;

Vessel approach to

minimize discharge

of ballast and

spread of marine

pests; and

Storage of

decommissioning

materials to

minimize

disturbance of

TL Cement /

Decommissionin

g Contractor

During

decommissionin

g

Throughout

project site and

in local marine

environment

Incl. in

Decommissionin

g contract cost

Monitoring during the

decommissioning

period shall be limited

to surveying and

reporting on the final

post-decommissioning

beach and coastal

processes.

Where any structure

or deviation from the

pre-construction

landform is proposed

as the final footprint

post-

decommissioning, this

shall be modelled (not

costed)

NA TL Cement -

Collation of

results into

semi-annual

Environmental

Report to

NDCPEI

Page 184 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 185: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Decommissioning Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Flora Growth and

spread of weeds

Dust suppression

measures (e.g.

water sprinkling)

at all dust

generating sites

Weed

management

activities including

spraying

TL Cement /

Decommissionin

g Contractor

During

decommissionin

g

Areas degraded

during the life

of the project.

Incl. in

Decommissionin

g contract cost

Monitoring and

reporting of flora

species abundance

and coverage

5 years after

mine closure

TL Cement -

Collation of

results into

semi-annual

Environmental

Report to

NDCPEI

Fauna Removal of

threatened

animals

Planting of habitat

mimicking natural

environment.

TL Cement /

Decommissionin

g Contractor

During

decommissionin

g

Areas degraded

during the life

of the project

Incl. in

Decommissionin

g contract cost

Monitoring and

reporting of fauna

species abundance

5 years after

mine closure

TL Cement -

Collation of

results into

semi-annual

Environmental

Report to

NDCPEI

Page 185 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 186: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Decommissioning Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Marine

Fauna

(including

fisheries)

Loss of fishing

habitat and coral

reefs

Rehabilitation of

coral areas where

practical through

artificial reefs

TL Cement /

Decommissionin

g Contractor

During

decommissionin

g

Throughout

project site, in

particular in the

vicinity of the

jetty and MOF

Incl. in

Decommissionin

g contract cost

Post decommissioning

marine habitat survey

Within 5 years

post-closure

TL Cement -

Collation of

results into

semi-annual

Environmental

Report to

NDCPEI

Page 186 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 187: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Decommissioning Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Marine

habitats

(including

coral)

Loss of fishing

habitat and coral

reefs

Ballast water

management and

Introduced Marine

Pests monitoring

and controls

TL Cement /

Decommissionin

g Contractor

During

decommissionin

g and post

decommissionin

g for habitat

survey

Throughout

project site, in

particular in the

vicinity of the

jetty and MOF.

Survey to be

undertaken at

identified sites.

Incl. in

Decommissionin

g contract cost

Undertake post-

decommissioning

survey of the

identified sites to

compare the coral

health to the

reference imagery and

GPS database.

Reporting and

recording of post-

decommissioning

coral health

monitoring data.

Single post

decommissionin

g survey unless

findings suggest

otherwise.

TL Cement -

Collation of

results into

semi-annual

Environmental

Report to

NDCPEI

Page 187 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 188: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Decommissioning Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Traffic Increase in amount

of traffic on the

roads

Planning to

minimize vehicle

movements (e.g.

use of buses to

transport workers

and house in

camps)

Limit reversing

requirements

Traffic signage

implementation

Speed limits and

enforcement

TL Cement /

Decommissionin

g Contractor

During

decommissionin

g

Througout

project site and

on local road

networks

Incl. in

Decommissionin

g contract cost

Traffic incidents and

mitigation measures

implemented

Update Safety

Management

System to

record and

document traffic

incidents and

mitigation

measures

implemented as

and when they

occur.

Construction

Contractor /

Mine Operator

Costs to

Construction

Contractor /

Mine

Operator

Page 188 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 189: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Decommissioning Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Infrastructur

e

Increased pressure

on existing

infrastructure

Ongoing

inspection,

monitoring and

maintenance

programmes will

be developed and

implemented for

the relevant

infrastructure

during the

decommissioning

phase

TL Cement Prior to

decommissionin

g

Throughout

project site and

wider area

Incl. in

Decommissionin

g contract cost

Complaints and

Grievance records

reviewed regularly

Regular Stakeholder

consultation to check

progress

Regular review

of Complaints

and Grievance

record

Regular

stakeholder

consultation

TL Cement N/A

Page 189 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 190: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Decommissioning Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Employment Training and

development of

local people

Redeployment and

training

opportunities to

offset loss of

employment on

closure

TL Cement Prior to

decommissionin

g

Throughout

project site and

wider area

Incl. in

Decommissionin

g contract cost

Complaints and

Grievance records

review

Stakeholder

consultation to check

progress

Regular review

of Complaints

and Grievance

record

Regular

stakeholder

consultation

TL Cement

Economic

Use of

Forestry and

other Natural

Resources

Training and

development of

local people

Rehabilitation with

native species

TL Cement /

Decommissionin

g Contractor

Immediately

following

completion of

operation

Areas degraded

during life of

project

Incl. in

Decommissionin

g contract cost

The total area of re-

vegetation and the

species used for

rehabilitation should

be recorded and

monitored

For a period of 5

years following

decommissionin

g.

TL Cement /

Decommissionin

g Contractor

Page 190 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 191: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Decommissioning Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Fishing Increase in people

who fish

Rehabilitation of

beach accesses

TL Cement /

Decommissionin

g Contractor

During

decommissionin

g

At all locations

impacted by

access

restrictions

Incl. in

Decommissionin

g contract cost

Fisheries assessment

is a component of the

Marine Habitats and

Coral monitoring

Regular review

of Complaints

and Grievance

record

Regular

stakeholder

consultation

TL Cement N/A

Page 191 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 192: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Decommissioning Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Socio

Economic

Agriculture

Returning to the

area

The impact on

community access

to farmland during

the project will be

addressed by

resettlement and

compensation to

be undertaken by

the GoTL.

TL Cement /

Decommissionin

g Contractor

During

decommissionin

g

Areas degraded

during life of

project

Incl. in

Decommissionin

g contract cost

The total area of re-

vegetation and the

species used for

rehabilitation should

be recorded and

monitored

For a period of 5

years following

decommissionin

g.

Page 192 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 193: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Decommissioning Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Population

and

Community

Influx of new

people to the area

from outside

Baucau

The impact on

community during

the project will be

addressed by

resettlement and

compensation to

be undertaken by

the GoTL.

GoTL Impact on

community

addressed

construction but

complaints and

grievance

records to be

maintained

throughout

project

As determined

by resettlement

facilitated by

GoTL

Incl. in

Decommissionin

g contract cost

Complaints and

Grievance records

Regular review

of records

Page 193 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 194: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Decommissioning Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Community

Health

Increase in injury,

disease and

infections due to

more people in the

area

Facilitate

education and

awareness

programs

throughout the

lifespan of the

Project;

TL Cement Impact on

community

addressed

construction but

complaints and

grievance

records to be

maintained

throughout

project

Throughout

local region

Incl. in

Decommissionin

g contract cost

Complaints and

Grievance records

Regular review

of Complaints

and Grievance

record

Regular

stakeholder

consultation

TL Cement N/A

Page 194 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 195: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Decommissioning Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Institutions,

Schools and

Health

Facilities

No impact

anticipated

The impact on

community access

to institutions

during the project

will be addressed

by resettlement

and compensation

to be undertaken

by the GoTL.

TL Cement /

Decommissionin

g Contractor

Prior to

decommissionin

g . Air quality

and noise

monitoring

during

decommissionin

g.

Throughout

local region

Incl. in

Decommissionin

g contract cost

Complaints and

Grievance records

Regular review

of Complaints

and Grievance

record

Regular

stakeholder

consultation

TL Cement N/A

Page 195 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 196: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Decommissioning Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Community

and Family

Structure

Relocation of

families may

impact structure

Implementation of

the Complaints

and Grievance

mechanism

TL Cement Impact on

community

addressed

construction but

complaints and

grievance

records to be

maintained

throughout

project

Throughout

local region

Incl. in

Decommissionin

g contract cost

Complaints and

Grievance records

Regular review

of Complaints

and Grievance

record

Regular

stakeholder

consultation

TL Cement N/A

Land

ownership

and Land

Rights

Relocation of land

users will not

impact land rights

Implementation of

the Complaints

and Grievance

mechanism

TL Cement /

GoTL

Ongoing Affected

households and

property

owners

Incl. in

Decommissionin

g contract cost

Complaints and

Grievance records

Regular review

of records

To be addressed

by resettlement

and

compensation

to be addressed

by GoTL

Page 196 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 197: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Decommissioning Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Natural

Resources

Rights

Relocation of land

users will not

impact resources

rights

Implementation of

the Complaints

and Grievance

mechanism

TL Cement /

GoTL

Ongoing Throughout

project site and

surrounding

environment, in

particular at

identified

natural

resources

within and near

the project site

Incl. in

Decommissionin

g contract cost

Complaints and

Grievance records

Regular review

of records

To be addressed

by resettlement

and

compensation

to be addressed

by GoTL

Page 197 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 198: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Decommissioning Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the jetty and MOF

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to Monitor Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Cultural

Heritage,

Archaeologic

al and Sacred

Sites

Relocation of land

users will not

cultural heritage

sites

TL Cement Prior to

construction and

ongoing

throughout

construction,

operation and

decommissionin

g

Heritage sites

identified

through the EIA

as well as any

additional sites

discovered

during

construction,

operation or

decommissionin

g phase

Incl. in

Decommissionin

g contract cost

Any and all

occurrences of

damage sites is to be

recorded.

Records to be

reviewed every

6 months.

TL Cement.

Process

improvements

are to be

implemented

where there has

been

unauthorised

impact on

cultural heritage

sites.

Page 198 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 199: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

9 GOVERNING PARAMETERS

9.1 Environmental Quality Standards

The monitoring plan has been developed taking into account the best available measurement standard for the relevant criteria. The standard is detailed in Section 9.3 (Governing Parameters) below, alongside the applicable parameter.

9.2 International Best Practice

Where possible, the monitoring plan has been developed utilizing internationally-recognized standards and emissions criteria. Standards used by the World Health Organization and the International Finance Corporation have been used as first priority, followed by standards used in Australia and elsewhere.

9.3 Governing parameters

9.3.1 Emissions

Emissions standards are determined based on the medium of transmission i.e. water or air and are detailed further under Sections 9.3.2 and 9.3.3.

9.3.2 Ambient Water Quality Standards

Parameter International best practice standard

Proposed limit value Comments

Fresh Water (Springs and streams)

e.Coli or Thermotolerant coliform bacteria

WHO Drinking Water Standards (2000)

0 mg/L in 100ml sample All water directly intended for drinking

Nitrate WHO Drinking Water Standards (2000)

50 mg/L All water directly intended for drinking

Nitrite WHO Drinking Water Standards (2000)

3 mg/L All water directly intended for drinking

Chlorine WHO Drinking Water Standards (2000)

5 mg/L All water directly intended for drinking

Page 199 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 200: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Parameter International best practice standard

Proposed limit value Comments

Copper WHO Drinking Water Standards (2000)

2 mg/L All water directly intended for drinking

Lead WHO Drinking Water Standards (2000)

0.01 mg/L All water directly intended for drinking

Nickel WHO Drinking Water Standards (2000)

0.07 mg/L All water directly intended for drinking

Manganese WHO Drinking Water Standards (2000)

0.4 mg/L All water directly intended for drinking

Marine Water

Salinity Australian Water Quality Guidelines for Fresh and Marine Waters (ANZECC, 1992)

<5% variation from background

Copper Australian Water Quality Guidelines for Fresh and Marine Waters (ANZECC, 1992)

4 µg/L Table 2.7 Guidelines for the protection of human consumers of fish and other aquatic organisms

Lead Australian Water Quality Guidelines for Fresh and Marine Waters (ANZECC, 1992)

1.3 µg/L Table 2.7 Guidelines for the protection of human consumers of fish and other aquatic organisms

Page 200 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 201: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

9.3.3 Ambient Air Quality Standards

Parameter International best practice standard Proposed interim target limit (µg/m3)

Carbon monoxide

International Ambient Air Quality Standards (IAAQS)

http://www3.epa.gov/ttn/naaqs/criteria.html

1 hour = 40,000 µg/m3

Not to be exceeded more than once per year

Nitrogen dioxide

International Ambient Air Quality Standards (IAAQS)

http://whqlibdoc.who.int/hq/2006/WHO_SDE_PHE_OEH_06.02_eng.pdf

1 hour = 200 µg/m3

Annual = 40 µg/m3

Photochemical oxidants (as ozone)

International Ambient Air Quality Standards (IAAQS)

1 hour = 235 µg/m3

Sulfur dioxide International Ambient Air Quality Standards (IAAQS)

1 hour = 350 µg/m3

24 hour = 125 µg/m3

Particles as PM2.5

International Ambient Air Quality Standards (IAAQS)

24 hour = 75 µg/m3

Annual = 70 µg/m3

9.3.4 Soil

All the parameters below are obtained from the National Environment Protection Measure (Assessment of Contamination) 1999 for the Groundwater Investigation Levels in Fresh Waters “Table 1C”. The measurement of soil contamination is typically taken from groundwater monitoring boreholes located down-gradient from the suspected contamination.

Parameter Proposed discharge limit value

µg/L

Aluminium 55 µgL

Chromium IV 1 µgL

Page 201 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 202: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Parameter Proposed discharge limit value

µg/L

Nickel 11 µgL

Benzene 950 µgL

Phenol 320 µgL

Lead 3.4 µgL

Manganese 1900 µgL

Mercury (total) 0.06 µgL

Zinc 8 µgL

Ammonia (NH3-N) 900 µgL

Ethanol 1400 µgL

Page 202 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 203: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

9.3.5 Occupational Health and Safety Standards

9.3.5.1 WORKPLACE NOISE AND VIBRATION

Parameter International best practice standard

Proposed discharge limit value

Comments

Blasting

(Airblast level)

Regulation 11

Environmental Protection (Noise) Regulations 1997

120 dBLz peak at sensitive receptor

125 dBLz peak at non sensitive receptor

Blasting carried out between 7am and 6pm on any day of the week

Noise and Vibration UNTAET, 2001

Residential, Institutional and Educational Receptors

50 – 55 dB(A)

9.3.5.2 DRINKING WATER

These standards are applicable for fresh water springs and streams.

Parameter International best practice standard

Proposed limit value

E.Coli or Thermotolerant coliform bacteria

WHO Drinking Water Standards (2000)

0 mg/L in 100ml sample

Nitrate WHO Drinking Water Standards (2000)

50 mg/L

Nitrite WHO Drinking Water Standards (2000)

3 mg/L

Chlorine WHO Drinking Water Standards (2000)

5 mg/L

Copper WHO Drinking Water Standards (2000)

2 mg/L

Page 203 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 204: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Parameter International best practice standard

Proposed limit value

Lead WHO Drinking Water Standards (2000)

0.01 mg/L

Nickel WHO Drinking Water Standards (2000)

0.07 mg/L

Manganese WHO Drinking Water Standards (2000)

0.4 mg/L

9.3.5.3 SAFETY MANAGEMENT

Safety Management shall be undertaken in accordance with local labour laws and regulations.

9.3.5.4 COMMUNICATIVE DISEASES

Data and statistics on Communicative diseases will be confidentially collected through surveying of the health providers to determine if adjustments to the Workplace Health and Safety Standard are required. Communicative diseases include:

Infection control in the workplace aims to prevent pathogens from coming into contact with a person in the first place. The basis of good infection control in the workplace is to assume that everyone is potentially infectious. Proper procedures have to be followed at all times.

Good marketing of personal hygiene is the first line of defense. Infection control procedures relating to good personal hygiene include:

• Hand washing; • Covering cuts or abrasions with a waterproof dressing; and • Gloves.

Many infections are food-borne. When preparing food, it is important to:

• Wash hands before and after handling food; • Keep hot food hot and cold food cold; • Use separate storage, utensils and preparation surfaces for cooked and uncooked foods; and • Wash all utensils and preparation surfaces thoroughly with hot water and detergent after use.

Frequently, workplace illnesses are spread by droplet infection. Colds and flu are transmitted in this way, and sharing telephones is an infection risk. If at all possible, users should have personal headsets, and telephones should be regularly cleaned and sterilized.

Page 204 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 205: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

9.4 Modelling or Engineering Calculations

Trigger values and monitoring upper limit guideline values have been based on published standard and guideline values and no modelling was undertaken to derive them.

Page 205 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 206: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

10 MONITORING PROGRAM

In designing the monitoring programme for each aspect identified in the EIS, this section details:

• the specific parameters; • monitoring protocols; • sampling locations and frequencies of monitoring; and • how compliance with implementation of the EMP and sub-EMPs will be checked and reported.

The above information has been presented in table format for each phase of the Project; i.e. Pre-construction; Construction; Operation; and Decommissioning.

10.1 Climate

Monitoring Programme : Climate

Pre-construction Construction Operations Decommissioning

Install Automated Weather Station (AWS) recording daily measurements of:

• Station identification number;

• State and time of record/observation;

• Air, wet bulb and wet dew point temperatures.

• Precipitation and evaporation;

• Relative humidity;

• Wind speed and direction;

• Solar radiation;

• Barometric pressure ;

• Visibility;

• Cloud cover; and

• Cloud ceiling height, if practicable.

Annual reporting for all project phases of Greenhouse Gas emissions in accordance with National Greenhouse and Energy Reporting Act 2007.

Page 206 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 207: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

10.2 Topography and Soil

Monitoring Programme : Topography, Geology and Soil

Pre-construction Construction Operations Decommissioning

Weed growth and drainage behaviour on the topsoil stockpile

Monthly water quality and quantity measurements at key spring receptors, Uaino, and in the Water Reserve area.

Reporting and interpretation of data every 6 months.

5 years post closure assessment of rehabilitation success and soil health

10.3 Air Quality

Monitoring Programme : Air Quality

Pre-construction Construction Operations Decommissioning

A monitoring and reporting program (once every six months during construction and operation) should be implemented to monitor the air quality in the following sensitive receptors:

• AQ4 - settlement area in Aldeia Osso-ua.

• AQ5 - representing the construction area.

The monitoring stations are derived from the BBS Baseline Air Quality monitoring survey (BBS, 2015b).

The monitoring program should assess and report on the following air quality parameters:

• PM10; and PM2.5

• CO

• NO2

• SO2; and

• Ozone.

Page 207 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 208: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

10.4 Noise and vibration

Monitoring Programme : Noise and Vibration

Pre-construction Construction Operations Decommissioning

Every 6 months measurements at sensitive receptors i.e.

1. AQ4 – Settlement area at Aldeia Osso-Ua 2. AQ5 - representing the construction area.

Results interpretation and review of the EMP as required.

Collation of results into semi-annual Environmental Report to NDCPEI

Once per year measurements at sensitive receptors (as per Construction)

Results interpretation and review of the EMP as required.

Collation of results into Annual Environmental Report to NDCPEI

Once per year measurements at sensitive receptors (as per Operations)

Results interpretation and review of the EMP as required.

Collation of results into semi-annual Environmental Report to NDCPEI

10.5 Surface water

Monitoring Programme : Surface Water

Pre-construction Construction Operations Decommissioning

Flow meters / stream gauges at the Bucoli River (1.6km west) and at Uaimatabai, Uaisa and Waino springs.

Monthly water quality and quantity measurements at monitoring boreholes, key spring receptors at Waiono, Uaimatabai and Uaisa.

Interpretation of data every 6 months.

Collation of results into Annual Environmental Report to NDCPEI

Page 208 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 209: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

10.6 Groundwater

Monitoring Programme : Surface Water

Pre-construction Construction Operations Decommissioning

Monthly water quality and quantity measurements at key spring receptors at Uaimatabai, Uaisa and Uaino.

Reporting and interpretation of data quarterly

Monthly water quality and quantity measurements at key spring receptors at Uaimatabai, Uaisa and Uaino.

Reporting and interpretation of data quarterly

Collation of results into Annual Environmental Report to NDCPEI

10.7 Coastal and Marine

Monitoring Programme : Coastal and Marine

Pre-construction Construction Operations Decommissioning

A sediment transport model should be developed in order to qualify the volume, duration and distribution of sediment and erosion/scour associated with the MOF and Jetty.

Collation of results into semi-annual Environmental Report to NDCPEI

Monitoring of sedimentation effects should be undertaken at a frequency to be determined once the sediment transport associated with the MOF has been quantified; and Jetty construction has been completed.

Collation of results into Annual Environmental Report to NDCPEI

Monitoring during the decommissioning period shall be limited to surveying and reporting on the final post-decommissioning beach and coastal processes.

Where any structure or deviation from the pre-construction landform is proposed as the final footprint post-decommissioning, this shall be modelled (not costed)

Collation of results into semi-annual Environmental Report to NDCPEI

Page 209 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 210: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

10.8 Flora

Monitoring Programme : Flora

Pre-construction Construction Operations Decommissioning

The total area of vegetation cleared (habitat destruction) at the end of phase

Collation of results into Annual Environmental Report to NDCPEI

Monitoring and reporting of flora species abundance and coverage 5 years after mine closure

Collation of results into semi-annual Environmental Report to NDCPEI

10.9 Fauna

Monitoring Programme : Fauna

Pre-construction Construction Operations Decommissioning

Any incidents of fauna injury and death should be recorded.

Collation of results into semi-annual Environmental Report to NDCPEI

Reporting and interpretation of fauna injury and death records every 6 months.

Collation of results into Annual Environmental Report to NDCPEI

Monitoring and reporting of fauna species abundance 5 years after mine closure

Collation of results into semi-annual Environmental Report to NDCPEI

10.10 Marine Fauna and Fisheries

Monitoring Programme : Marine Fauna incl. Fisheries

Pre-construction Construction Operations Decommissioning

Page 210 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 211: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Regular community engagement surveys around fisheries

Annual review and reporting of coral habitats around the Jetty and MOF with a survey of coral health, sedimentation and fisheries.

Collection of water quality measurements at reference and impact sites to be sited within and adjacent to the project impact area.

Measurements are to be taken at least twice per calendar year, outside of and during the monsoon season.

Collation of results into Annual Environmental Report to NDCPEI

Post decommissioning marine habitat survey within 5 years post-closure

Collation of results into semi-annual Environmental Report to NDCPEI

10.11 Marine habitats and corals

Monitoring Programme : Marine habitat and corals

Pre-construction Construction Operations Decommissioning

Undertake a pre-construction survey of the identified sites to develop the reference imagery and GPS database.

Reporting and recording of baseline coral health monitoring data.

Collation of results into semi-annual Environmental Report to NDCPEI

Undertake a post-construction survey of the identified sites to compare the coral health to the reference imagery and GPS database.

Reporting and recording of post-construction coral health monitoring data.

Make recommendations on the frequency of operations coral health surveys.

Collation of results into Annual Environmental Report to NDCPEI

Undertake regular, scheduled surveys of the identified sites to compare the coral health to the reference imagery and GPS database. The frequency (e.g. 1x per year) should be confirmed during the Construction phase.

Collation of results into Annual Environmental Report to NDCPEI

Undertake post-decommissioning survey of the identified sites to compare the coral health to the reference imagery and GPS database.

Reporting and recording of post-decommissioning coral health monitoring data.

Collation of results into semi-annual Environmental Report to NDCPEI

10.12 Traffic

Page 211 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 212: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Monitoring Programme : Traffic

Pre-construction Construction Operations Decommissioning

Safety Management System to record and document traffic incidents and mitigation measures implemented

10.13 Infrastructure

Monitoring Programme : Infrastructure

Pre-construction Construction Operations Decommissioning

Complaints and Grievance records reviewed regularly

Regular Stakeholder consultation to check progress

10.14 Employment

Monitoring Programme : Employment

Pre-construction Construction Operations Decommissioning

Complaints and Grievance records reviewed regularly

Regular Stakeholder consultation to check progress

10.15 Economic Use of Forestry and other Natural Resources

Monitoring Programme : Economic Use of Forestry and other Natural Resources

Pre-construction Construction Operations Decommissioning

The total area of vegetation cleared during the pre-construction and construction phase should be recorded.

Control of weed and pathogen hygiene practices The total area of re-vegetation and the species used for rehabilitation should be recorded and monitored for a period of 5 years following decommissioning.

Page 212 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 213: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

10.16 Fishing

Monitoring Programme : Fishing

Pre-construction Construction Operations Decommissioning

Fisheries assessment is a component of the Marine Habitats and Coral monitoring

10.17 Socio-Economic Agriculture

Monitoring Programme : Socio Economic Agriculture

Pre-construction Construction Operations Decommissioning

Complaints and Grievance records reviewed regularly

Control of weed and pathogen hygiene practices The total area of re-vegetation and the species used for rehabilitation should be recorded and monitored for a period of 5 years following decommissioning.

10.18 Population and community

Monitoring Programme : Population and Community

Pre-construction Construction Operations Decommissioning

Maintain communities and limit secondary impacts of population increase due to the Project

Complaints and Grievance records reviewed regularly

10.19 Community Health

Page 213 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 214: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Monitoring Programme : Community Health

Pre-construction Construction Operations Decommissioning

Complaints and Grievance records reviewed regularly

Page 214 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 215: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

10.20 Institutions schools and health facil ities

Monitoring Programme : Institutions, Schools and Health Facilities

Pre-construction Construction Operations Decommissioning

Complaints and Grievance records reviewed regularly

10.21 Community and Family Structure

Monitoring Programme : Community and Family Structure

Pre-construction Construction Operations Decommissioning

Complaints and Grievance records reviewed regularly

10.22 Land Ownership and Land Rights

Monitoring Programme : Land Ownership and Land Rights

Pre-construction Construction Operations Decommissioning

Complaints and Grievance records reviewed regularly

To be addressed by resettlement and compensation to be addressed by GoTL

10.23 Natural Resources Rights

Monitoring Programme : Natural Resources Rights

Pre-construction Construction Operations Decommissioning

Complaints and Grievance records reviewed regularly

To be addressed by resettlement and compensation to be addressed by GoTL

Page 215 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 216: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

10.24 Cultural Heritage Archeological and Sacred Sites

Monitoring Programme : Cultural Heritage, Archaeological and Sacred Sites

Pre-construction Construction Operations Decommissioning

Any and all occurrences of damage sites is to be recorded and the records to be reviewed every 6 months. Process improvements are to be implemented where there has been unauthorised impact on cultural heritage sites.

Page 216 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 217: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

10.25 Summary of monitoring program

Pre - Construction Environmental Concern Parameter to Monitor Frequency and Variation Climate Automated Weather Station (AWS) recording measurements of:

Station identification number; Date and time of record/observation; Air, wet bulb and wet dew point temperatures. Precipitation and evaporation; Relative humidity; Wind speed and direction; Solar radiation; Barometric pressure ; Visibility; Cloud cover; and Cloud ceiling height, if practicable.

Daily measurements for project life

Topography, Geology and Soils

Weed growth and drainage behaviour on the topsoil stockpile As required

Air Quality At sensitive receptors: AQ3 – At the Jetty AQ4 – Settlement area at Aldeia Osso-Ua AQ5 - representing the construction area.

Every 6 months measurements at sensitive receptors i.e. Results interpretation and review of the EMP as required. Collation of results into semi-annual Environmental Report to NDCPEI

Noise and Vibration At sensitive receptors: NO3 – At the Jetty NO4 – Settlement area at Aldeia Osso-Ua NO5 - representing the construction area.

Every 6 months measurements at sensitive receptors i.e. Results interpretation and review of the EMP as required. Collation of results into semi-annual Environmental Report to NDCPEI

Water Flow meters / stream gauges at the Bucoli River (1.6km west) and at Uaimatabai, Uaisa and Waino springs

Monthly water quality and quantity measurements at monitoring boreholes, key spring receptors at Waiono, Uaimatabai and Uaisa. Interpretation of data every 6 months.

Coastal and Marine A sediment transport model should be developed in order to qualify the volume, duration and distribution of sediment and erosion/scour associated with the MOF and Jetty.

Before construction commences

Flora The total area of vegetation cleared (habitat destruction) at the end of phase

TL Cement - Collation of results into Annual Environmental Report to NDCPEI

Fauna Any incidents of fauna injury and death should be recorded.

TL Cement - Collation of results into semi-annual Environmental Report to NDCPEI

Marine Fauna including fisheries

Regular community engagement surveys around fisheries Survey of coral health, sedimentation and fisheries. Collection of water quality measurements at reference and impact sites to be sited within and adjacent to the project impact area.

Annual review and reporting of coral habitats around Jetty and MOR. Water Quality measurements are to be taken at least twice per calendar year, outside of and during the monsoon season.

Marine habitats including coral

Undertake a pre-construction survey of the identified sites to develop the reference imagery and GPS database. Reporting and recording of baseline coral health monitoring data.

Pre construction survey

Page 217 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 218: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Traffic Traffic incidents and mitigation measures implemented Update Safety Management System to record and document traffic incidents and mitigation measures implemented as and when they occur.

Social Complaints and Grievance records review Stakeholder consultation to check progress

Regular review of Complaints and Grievance record Regular stakeholder consultation

Cultural Heritage, Archaelogical and Sacred Sites

Any and all occurrences of damage sites is to be recorded. Records to be reviewed every 6 months.

Construction Environmental Concern Parameter to Monitor Frequency and Variation Climate Automated Weather Station (AWS) recording measurements of:

Station identification number; Date and time of record/observation; Air, wet bulb and wet dew point temperatures. Precipitation and evaporation; Relative humidity; Wind speed and direction; Solar radiation; Barometric pressure ; Visibility; Cloud cover; and Cloud ceiling height, if practicable.

Daily measurements for project life

Air Quality A monitoring and reporting program implemented to monitor the air quality in the following sensitive receptors: • AQ4 - settlement area in Aldeia Osso-ua. • AQ5 - representing the construction area. The monitoring program should assess and report on the following air quality parameters: • PM10; and PM2.5 • CO • NO2 • SO2; and • Ozone.

Once every six months during construction

Noise and Vibration At sensitive receptors: AQ4 – Settlement area at Aldeia Osso-Ua AQ5 - representing the construction area.

Every 6 months measurements at sensitive receptors i.e. Results interpretation and review of the EMP as required. Collation of results into semi-annual Environmental Report to NDCPEI

Surface Water Flow meters / stream gauges at the Bucoli River (1.6km west) and at Uaimatabai, Uaisa and Waino springs

Monthly water quality and quantity measurements at monitoring boreholes, key spring receptors at Waiono, Uaimatabai and Uaisa. Interpretation of data every 6 months.

Groundwater Water quality and quantity measurements at key spring receptors at Uaimatabai, Uaisa and Uaino.

Monthly water quality and quantity measurements Reporting and interpretation of data quarterly

Coastal and Marine Sedimentation effects Monitoring should be undertaken at a frequency to be determined once the sediment transport associated with the MOF has been quantified; and Jetty construction has been completed.

Page 218 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 219: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Flora The total area of vegetation cleared (habitat destruction) at the end of phase

End of phase

Fauna All fauna injury and death records. Reporting and interpretation every six months Marine fauna (including fisheries)

Regular community engagement surveys around fisheries Survey of coral health, sedimentation and fisheries. Collection of water quality measurements at reference and impact sites to be sited within and adjacent to the project impact area.

Annual review and reporting of coral habitats around Jetty and MOR. Water Quality measurements are to be taken at least twice per calendar year, outside of and during the monsoon season

Marine Habitats (including Coral)

Undertake a post-construction survey of the identified sites to compare the coral health to the reference imagery and GPS database. Reporting and recording of post-construction coral health monitoring data. Make recommendations on the frequency of operations coral health surveys.

One post construction survey. Frequency of monitoring based on results

Traffic Traffic incidents and mitigation measures implemented Update Safety Management System to record and document traffic incidents and mitigation measures implemented as and when they occur

Social Complaints and Grievance records review Stakeholder consultation to check progress

Regular review of Complaints and Grievance record Regular stakeholder consultation

Cultural Heritage, Archaelogical and Sacred Sites

Any and all occurrences of damage sites is to be recorded. Records to be reviewed every 6 months.

Operations Climate Air Quality A monitoring and reporting program implemented to monitor the

air quality in the following sensitive receptors: • AQ4 - settlement area in Aldeia Osso-ua. • AQ5 - representing the construction area. The monitoring program should assess and report on the following air quality parameters: • PM10; and PM2.5 • CO • NO2 • SO2; and • Ozone.

Once every six months during construction and operation

Noise and Vibration At sensitive receptors (as per construction) Once per year measurements Results interpretation and review of the EMP as required. Collation of results into Annual Environmental Report to NDCPEI

Water Flow meters / stream gauges at the Bucoli River (1.6km west) and at Uaimatabai, Uaisa and Waino springs

Monthly water quality and quantity measurements at monitoring boreholes, key spring receptors at Waiono, Uaimatabai and Uaisa. Interpretation of data every 6 months.

Coastal and Marine Sedimentation effects Should be monitored at a frequency to be determined once the sediment transport associated with the MOF has been quantified; and Jetty construction has been completed.

Page 219 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 220: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Marine Fauna (including fisheries)

Regular community engagement surveys around fisheries Survey of coral health, sedimentation and fisheries. Collection of water quality measurements at reference and impact sites to be sited within and adjacent to the project impact area.

Annual review and reporting of coral habitats around Jetty and MOR. Water Quality measurements are to be taken at least twice per calendar year, outside of and during the monsoon season.

Marine habitats (including coral)

Compare the coral health to the reference imagery and GPS database

Undertake regular, scheduled surveys of the identified sites. The frequency (e.g. 1x per year) should be confirmed during the Construction phase.

Traffic Traffic incidents and mitigation measures implemented Update Safety Management System to record and document traffic incidents and mitigation measures implemented as and when they occur.

Social Complaints and Grievance records review Stakeholder consultation to check progress

Regular review of Complaints and Grievance record Regular stakeholder consultation

Cultural Heritage, Archaeological and Sacred Sites

Any and all occurrences of damage sites is to be recorded. Records to be reviewed every 6 months.

Decommissioning Topography, Geology and Soils

Post closure assessment of rehabilitation success and soil health 5 years after closure

Air Quality A monitoring and reporting program implemented to monitor the air quality in the following sensitive receptors: • AQ4 - settlement area in Aldeia Osso-ua. • AQ5 - representing the construction area. The monitoring program should assess and report on the following air quality parameters: • PM10; and PM2.5 • CO • NO2 • SO2; and • Ozone.

Once every six months

Noise and Vibration At sensitive receptors (as per construction) Once per year measurements Results interpretation and review of the EMP as required. Collation of results into semi-annual Environmental Report to NDCPEI

Water Flow meters / stream gauges at the Bucoli River (1.6km west) and at Uaimatabai, Uaisa and Waino springs

Monthly water quality and quantity measurements at monitoring boreholes, key spring receptors at Waiono, Uaimatabai and Uaisa. Interpretation of data every 6 months.

Coastal and Marine Monitoring during the decommissioning period shall be limited to surveying and reporting on the final post-decommissioning beach and coastal processes. Where any structure or deviation from the pre-construction landform is proposed as the final footprint post-decommissioning, this shall be modelled (not costed)

NA

Flora Monitoring and reporting of flora species abundance and coverage

5 years after mine closure

Fauna Monitoring and reporting of fauna species abundance 5 years after mine closure

Page 220 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 221: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Marine Fauna (including fisheries)

Post decommissioning marine habitat survey Within 5 years post-closure

Marine habitats (including coral)

Undertake post-decommissioning survey of the identified sites to compare the coral health to the reference imagery and GPS database. Reporting and recording of post-decommissioning coral health monitoring data.

Single post decommissioning survey unless findings suggest otherwise.

Traffic Traffic incidents and mitigation measures implemented Update Safety Management System to record and document traffic incidents and mitigation measures implemented as and when they occur.

Social Complaints and Grievance records review Stakeholder consultation to check progress

Regular review of Complaints and Grievance record Regular stakeholder consultation

Cultural Heritage, Archaelogical and Sacred Sites

Any and all occurrences of damage sites is to be recorded. On completion of closure

Page 221 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 222: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

11 REPORTING REQUIREMENTS

Based on the monitoring programs outlined in Section 10 (Monitoring Program), this section (Table 11-1) outlines the reporting frequencies and types of reports to be prepared for each aspect identified in the EIS. Details of the reporting requirements include:

1. Monitoring limit or trigger which would dictate the need for reporting; 2. Frequency of reporting for internal and/or external purposes; 3. Incident, accident and emergency reporting; 4. Identification of the appropriate authorities/regulator to which the report is to be provided; 5. Measuring performance indicators and interpreting and acting on the indicators; and 6. Training programs required for employees/contractors.

Page 222 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 223: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Table 11-1 Monitoring reporting requirements

Aspect Frequency of monitoring

Limit / Trigger Method/Standard for monitoring

Method of monitoring Frequency of Internal Reporting

External reporting

(Authority/Regulator)

Climate Daily N/A Automated Weather Station

National Meteorological Service

NDPCEI

Minister of Commerce and Environment

Soil Monthly, in the event of leak / spillage of dangerous chemicals and hazardous wastes

Various AS/NZS 5667:1:1998 Water Quality Sampling

Water samples

Laboratory Analysis

6-monthly NDPCEI

Minister of Commerce and Environment

Page 223 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 224: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Aspect Frequency of monitoring

Limit / Trigger Method/Standard for monitoring

Method of monitoring Frequency of Internal Reporting

External reporting

(Authority/Regulator)

Air Quality (including Dust)

6-monthly 25 µg/m3 (Maximum concentration in 24 hours, 1 day averaging period)

AS/NZS 3580.1.1:2007 Methods for the sampling and analysis of ambient air – Guide to siting air monitoring equipment.

Air monitoring equipment and dust fall out containers

Annually Local suco chief

NDPCEI

Minister of Commerce and Environment

Noise and Vibration

6-monthly 50dB Exceedance greater than 10% of the time not permitted (LA10)

AS/NZS 1269.1

Occupational noise management

Noise and vibration monitors

Annually Local suco chief

NDPCEI

Minister of Commerce and Environment

Page 224 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 225: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Aspect Frequency of monitoring

Limit / Trigger Method/Standard for monitoring

Method of monitoring Frequency of Internal Reporting

External reporting

(Authority/Regulator)

Groundwater – springs

Monthly during pre-construction, construction and operations.

Flows <10% variance pre-development

Quality – below limits

AS/NZS 5667:1:1998 Water Quality Sampling

Water samples

Laboratory Analysis

Every 3 months, subject to stabilizing, then potentially every 6 months.

DWRQC

NDPCEI

Minister of Commerce and Environment

Groundwater – monitoring boreholes

Monthly Levels <10% variance pre-development

Quality – below limits

AS/NZS 5667:1:1998 Water Quality Sampling

Water samples

Laboratory Analysis

Every 3 months, subject to stabilising

Results collation every 6 months, reporting annually to NDPCEI

DWRQC

NDPCEI

Minister of Commerce and Environment

Page 225 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 226: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Aspect Frequency of monitoring

Limit / Trigger Method/Standard for monitoring

Method of monitoring Frequency of Internal Reporting

External reporting

(Authority/Regulator)

Groundwater – supply boreholes

Monthly Levels <10% variance pre-development

Quality – below limits

AS/NZS 5667:1:1998 Water Quality Sampling

Water samples

Laboratory Analysis

Every 3 months, subject to stabilizing

Results collation every 6 months, reporting annually to NDPCEI

DWRQC

NDPCEI

Minister of Commerce and Environment

Coastal and Marine

One off Sediment transport model

NDPCEI

Minister of Commerce and Environment

Page 226 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 227: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Aspect Frequency of monitoring

Limit / Trigger Method/Standard for monitoring

Method of monitoring Frequency of Internal Reporting

External reporting

(Authority/Regulator)

Flora Monthly during pre-construction, construction

<55ha Surveyor standard Accurate survey of cleared lands

Monthly reconciliation against planned clearing, clearing below approved limit

NDPCEI

Directorate of Mines

Minister of Commerce and Environment

Fauna Monthly during pre-construction and construction

Annually during operations

Fauna Fatalities < 1 per month

Data capture in the EMS Monthly reconciliation and adjustment of clearing approach if exceeded

NDPCEI

Directorate of Mines

Minister of Commerce and Environment

Minister of Commerce and Environment

Page 227 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 228: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Aspect Frequency of monitoring

Limit / Trigger Method/Standard for monitoring

Method of monitoring Frequency of Internal Reporting

External reporting

(Authority/Regulator)

Fisheries Annually N/A N/A Fisheries assessment survey and consultation

Annually Ministry of Agriculture and Fisheries

Minister of Commerce and Environment

Coral Every 2 years Coral mortality < 40%

TBC Tow camera and vessel Every 2 years and 5 years post-closure

NDPCEI

Ministry of Agriculture and Fisheries

Minister of Commerce and Environment

Traffic 4 weeks at the start of each phase

N/A Traffic enumerators At conclusion of survey, continuous improvement

MOPW DBRFC

Minister of Commerce and Environment

Page 228 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 229: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Aspect Frequency of monitoring

Limit / Trigger Method/Standard for monitoring

Method of monitoring Frequency of Internal Reporting

External reporting

(Authority/Regulator)

Health Annually Stakeholder survey

Grievances mechanism

Year on year variance

Continuous improvement process

Ministry of Health

Minister of Commerce and Environment

Cultural Heritage Monthly during pre-construction and construction

Zero incidents of non-agreed disturbance

Escalation and reporting of every instance of unknown sites encountered

N/A Cultural Heritage Monitors / Supervisors

Grievances mechanism

Monthly pre-construction and construction

Secretariat of Arts and Culture

Minister of Commerce and Environment

Page 229 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 230: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

12 RESPONSIBILITIES FOR MITIGATION AND MONITORING

This section clearly identifies the responsibilities of the various parties involved in the implementation of mitigation and monitoring requirements as outlined in Sections 8 and 10, respectively, of this EMP.

The following are the key managerial roles applicable to the Project during the following phases:

• Pre-Construction and Construction: o Project Manager – TL Cement LDA; o Project Engineer – Detailed Design and Planning; • Operation: o Plant Manager; o Engineering Manager

The Plant manager may delegate to his personnel for various functions, including the Health, Safety Quality Manager/Officer function.

The responsibility for the development, implementation and monitoring of the success of ; and review and update of mitigation measures is illustrated in the table below.

Table 12-1 Responsibility for implementation of this EMP

Phase Item Develop/Author Implement Monitoring

Detailed Engineering Design

Environmental Management Plans

Lead Engineer from the Engineering provider with approval by Project Manager – TL Cement LDA

Lead Engineer from the Engineering provider

Mitigation Measures Lead Engineer from the Engineering provider with approval by Project Manager – TL Cement LDA

Lead Engineer from the Engineering provider

Monitoring Plans Lead Engineer from the Engineering provider with approval by Project Manager – TL Cement LDA

Lead Engineer from the Engineering provider

Construction Tender Phase

Develop construction specific Environmental Management Plans

Civil works contractor with approval by Project Manager – TL Cement

Civil works contractor

Page 230 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 231: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

LDA

Develop construction specific

Mitigation Measures

Civil works contractor with approval by Project Manager – TL Cement LDA

Civil works contractor

Develop construction specific

Monitoring Plans

Civil works contractor with approval by Project Manager – TL Cement LDA

Civil works contractor

Phase Item Develop/Author Implement External review

Pre-Construction Civil works contractor with approval by Project Manager – TL Cement LDA

TL Cement nominated EPC management firm Health, Safety Quality Manager/Officer

Civil works contractor with approval by Project Manager – TL Cement LDA

TL Cement nominated EPC management firm Health, Safety Quality Manager/Officer

Monitoring activities

Civil works contractor with approval by Project Manager – TL Cement LDA

TL Cement nominated EPC management firm Health, Safety Quality Manager/Officer

Compliance monitoring

Project Manager – TL Cement LDA

TL Cement nominated EPC management firm Health, Safety Quality Manager/Officer

Compliance reporting

Civil works contractor with approval by

TL Cement nominated EPC management firm Health, Safety Quality

Minister of Commerce and Environment

NDPCEI

Page 231 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 232: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Project Manager – TL Cement LDA

Manager/Officer

Construction Environmental Management Plans

Civil works contractor with approval by Project Manager – TL Cement LDA

TL Cement nominated EPC management firm Health, Safety Quality Manager/Officer

Mitigation Measures

Civil works contractor with approval by Project Manager – TL Cement LDA

TL Cement nominated EPC management firm Health, Safety Quality Manager/Officer

Monitoring activities

Civil works contractor with approval by Project Manager – TL Cement LDA

TL Cement nominated EPC management firm Health, Safety Quality Manager/Officer

Compliance monitoring

Site Supervisor from TL Cement LDA

TL Cement nominated EPC management firm Health, Safety Quality Manager/Officer

Compliance reporting

Civil works contractor with approval by Project Manager – TL Cement LDA

TL Cement nominated EPC management firm Health, Safety Quality Manager/Officer

Minister of Commerce and Environment

NDPCEI

Operations (Year 1 to 5, Year 6 to end)

Environmental Management Plans

Environmental Engineer supervised by the Plant Manager – TL Cement LDA

TL Cement nominated EPC management firm Health, Safety Quality Manager/Officer

Page 232 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 233: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Year 6-end: TL Cement Health, Safety Quality Manager/Officer

Mitigation Measures

Environmental Engineer supervised by the Plant Manager – TL Cement LDA

TL Cement nominated EPC management firm Health, Safety Quality Manager/Officer

Year 6-end: TL Cement Health, Safety Quality Manager/Officer

Monitoring activities

Environmental Engineer supervised by the Plant Manager – TL Cement LDA

TL Cement nominated EPC management firm Health, Safety Quality Manager/Officer

Year 6-end: TL Cement Health, Safety Quality Manager/Officer

Compliance monitoring

Environmental Engineer supervised by the Plant Manager – TL Cement LDA

TL Cement nominated EPC management firm Health, Safety Quality Manager/Officer

Year 6-end: TL Cement Health, Safety Quality Manager/Officer

Compliance Reporting

Environmental Engineer supervised by the Project Manager – TL Cement LDA

TL Cement nominated EPC management firm Health, Safety Quality Manager/Officer

Year 6-end: TL Cement Health, Safety Quality Manager/Officer

Minister of Commerce and Environment

NDPCEI

Decommissioning Environmental Management Plans

Environmental Engineer supervised by the

TL Cement Health, Safety Quality Manager/Officer

Page 233 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 234: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Project Manager – TL Cement LDA

Mitigation Measures

Environmental Engineer supervised by the Project Manager – TL Cement LDA

TL Cement Health Engineering Manager

Monitoring activities

Environmental Engineer supervised by the Project Manager – TL Cement LDA

TL Cement Health, Safety Quality Manager/Officer

Compliance monitoring

Site Supervisor from TL Cement LDA

TL Cement Health, Safety Quality Manager/Officer supervising the Civil works contractor

Compliance Reporting

Environmental Engineer supervised by the Project Manager – TL Cement LDA

TL Cement Health, Safety Quality Manager/Officer

Minister of Commerce and Environment

NDPCEI

Page 234 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 235: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

This page has been intentionally left blank.

Page 235 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 236: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

13 EMERGENCY PLAN

13.1 Purpose

The Emergency Plan (EP) outlines the approach for managing the handling, storage and leak / spillage of dangerous chemicals and hazardous wastes associated with the development and operation of the Cement Plant, Jetty and Other Associated Infrastructure associated with the Baucau Cement Plant Project.

The purpose of the EP is to identify appropriate management strategies, procedures and processes to ensure that in the event of a spill / leak it is dealt with quickly and efficiently to ensure it is:

• Stopped at the source; • Contained and collected; and • If necessary, the site is remediated.

13.2 Objective

The objective of the EP is to:

• Reduce the risk of contamination and pollution to water and land from any dangerous chemicals or hazardous wastes; • Respond effectively and quickly to all spills and leaks, regardless of the size / volume; and • Minimise the risk exposure of any dangerous chemicals or hazardous wastes to all employees and contractors and subsequent health impacts.

13.3 Responsibilities

TL Cement Safety and Quality Officer/Manager:

• Regular review and updating of the EP; • Ensure the EP is effective and drills are conducted; • Notify the regulatory authority of any major spills within the required timeframes; • Ensure all employees are provided with the necessary training, PPE and equipment to deal with spills; • Notify and coordinate emergency services, if required; • Oversee incident reporting and investigation process and ensure an adequate investigation is undertaken, if required; • Ensure the Safety Data Sheets (SDS) is maintained and current for all of the chemicals and hazardous materials used and stored on the Project site; and • Ensure spill kit materials are adequately stored and restocked following any spill or leak.

All employees and contractors are responsible for:

Page 236 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 237: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

• Cleanup and removal of spills, if it is safe to do so; • Reporting all spills to the TL Cement Plant Manager using the appropriate procedure; • Participate in emergency drills; and • Ensure appropriate PPE is used when dealing with the cleanup and removal of spills.

13.4 Standards

The storage, management of and handling of all dangerous chemicals or hazardous wastes will be undertaken in accordance with the requirements of the following standards and legislation:

• Australian National Standard for the Storage and Handling of Workplace Dangerous Goods [NOHSC: 1015 (2001)]; and • Australian Standards AS 1940-2004: The storage and handling of flammable and combustible liquids. • Regulation 37 Annex 1 of the International Convention for the Prevention of Pollution from Ships 1973 • Guidelines for development of Shipboard Oil Pollution Emergency Plan (MEPC, 86:44)

13.5 Incident Classification

All spills, leaks and or uncontrolled release of materials, regardless of the size / volume are classified as an event, which needs to be reported to the TL Cement Environment Manager/Officer.

An incident includes a spill, leak or uncontrolled release of any of the following substances to water sources, ground; bitumen; bunded areas (concrete or plastic lined); concrete pads; and spill trays:

• Hydrocarbons; • Chemicals; • Saline water; • Powdered chemicals; • Oily waste water; • Sewage; • Ships ballast water; • Concrete washout; and • Bitumen.

The following table outlines the potential ‘Incident Types’ which may be applicable to the Project.

Page 237 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 238: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Table 13-1: Incident Classifications

Level 1

Minor

Level 2

Moderate

Level 3

Medium

Level 4

Major

Minor uncontrolled spill or release of materials within a bunded or contained area* including on board a ship that may:

• Impact disturbed land but not vegetation; • Does not impact water (surface or groundwater); • Does not reach the water in the case of spills on a vessel; • Does not harm fauna; and • Can be easily cleaned up.

Moderate uncontrolled spill or release of materials contained within bunded or contained area that may:

• Reaches the water as a result of washdown or spill overboard; • Has minor impacts on soil, fauna and flora but not priority flora/fauna or significant species; and • Minor impacts to surface or groundwater.

Uncontained spill or release of materials that may:

• Has impact on sea water, fauna and flora and is uncontrolled and extensive in its release; • Impacts on native vegetation including priority / rare flora; • Moderate impacts on soil requiring soil treatment or replacement • Has moderate impacts on low value surface / groundwater sources; and • Has reasonable probability of being detrimental to fauna.

Major uncontained spill or release of materials that may:

• Has impact on sea water, fauna and flora and is major, uncontrolled and time extensive in its release; • Impact soil, requiring significant treatment and soil replacement; • Major impacts on surface and/or groundwater sources; • Impacts on vegetation over an extensive area that causes loss of priority / rare flora; • Results in fauna deaths of rare / priority species; and • Has a reasonable probability of being detrimental to public health.

* Contained area can include: surface of the vessel; concrete bunds; plastic lined bunds; concrete pads; and spill trays.

13.6 Prevention

The following are some simple techniques that shall be adopt and implemented on the Project to prevent spillages and leaks from occurring:

• No tanks are to be filled prior to checking available tank volume; • Tank filling and dispensing procedures shall be carried out only by appropriately trained personnel and within designated and bunded area;

Page 238 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 239: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

• The main outlet valve on tanks will be locked shut when unattended; • Each tank/storage facility will be gauged and monitored daily; • All chemical and hazardous materials are contained in bunded areas with an appropriate holding capacity; • Bunded compound shall be lined with low permeability (less than 10 - 9 m/s) material that is not adversely affected by contact with the stored chemicals. It should be constructed in such a way that permits full recovery of contents spilt from tanks and ensures that the lining material is not damaged. The bund itself should be constructed of waterproof membrane, reinforced concrete or an approved equivalent; • The bunded compound shall have a minimum capacity of 110% of the capacity of the largest tank. The compound shall also have sufficient capacity to retain spilt chemicals and not be affected during extreme rainfall events; • After a rainfall event, pumping should be used to empty the compound, provided the water is not contaminated. The water should be checked by a suitably qualified and experienced person; • Under no circumstances shall contaminated water be allowed to discharge to the environment, but shall be pumped into a tanker for appropriate disposal; • Emptying of the compound should not be achieved through a valved (i.e. gravity flow) outlet as this may be inadvertently be left open; • Vehicle refueling and maintenance will only be conducted in the designated Vehicle Maintenance and Refueling areas; • Tanks; vehicles and equipment will be regularly inspected and maintained as per the required specifications; • The network of storm water drains, diversion ditches and drains will be regularly inspected to ensure there are no blockages; • All spills and leaks will be cleaned up immediately and reported to the TL Cement Plant Manager; • All vessels and vessel activities are to operate in accordance with Regulation 37 Annex 1 of the International Convention for the Prevention of Pollution from Ships 1973 and Guidelines for development of Shipboard Oil Pollution Emergency Plan (MEPC, 86:44) • Shovels, drip pans and absorbent materials will be strategically located throughout the Project site; and • Ensure that all chemical and hazardous materials are stored appropriately. Substances may escape from storage facilities through various means, including, but not limited to:

o Absence of containment facilities;

o Poor construction or deterioration of containment facilities;

o Inappropriate equipment maintenance operations; and

o Poor ‘house-keeping’ practices.

13.7 Safety Data Sheets (SDS) Before a contractor can bring a chemical onto site, they must inform and receive approval from the TL Cement HSE Department / Environmental Manager.

Page 239 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 240: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

All chemicals which have been approved for use on site by the TL Cement HSE Department/ Environment Manager will be stored in accordance with the SDS and in a designated bunded / contained area.

13.8 Spill Response

In the event of a spill and/or leak TL Cement shall adopted the following ‘3C Response Policy’:

• Control; • Contain; and • Clean-up.

The following sections provide an outline of the ‘3C Response Policy’.

13.8.1 Control

The ‘Control’ aspect of the response policy includes, but is not limited to; the following steps for all spills / leaks (i.e. Minor to Major):

• Identification of the source and material involved of the spill / leak. • If required, get help / advice from the TL Cement Safety and Quality Officer. • Ensure the appropriate personal protective equipment (PPE) is used. • If it is safe to do so, control the spill / leak at the source by: o Shut off valves; o Stop the pump process; o Upright the container. • Clear the area of people and equipment not directly involved in the clean-up process. • Complete the appropriate Form estimating the quantity spilled and submit to the TL Cement Safety and Quality Officer.

13.8.2 Contain

The ‘Contain’ aspect of the response policy includes, but is not limited to; the following steps for all spills / leaks (i.e. Minor to Major):

• Ensuring that the appropriate PPE is in place, it is essential for spills on or over water for the edge of the spill to be contained with booms. For land spills, sand, rags or other like materials should be used. • Block or divert the flow of the spill / leak from entering any stormwater drain. • Place appropriate spill kit material over the body of the spill to ensure it does not disperse further.

13.8.3 Clean Up

The ‘Clean Up’ aspect of the response policy includes, but is not limited to; the following steps:

Page 240 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 241: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

• Ensuring that the appropriate PPE is in place; spills / leaks should be cleaned up using appropriate absorbent materials which should then be disposed of to a suitably labelled “Contaminated Material Bin” for storage and eventual transportation via a licenced contractor to a licenced disposal facility. • Any equipment used from spill kits must be recorded and the TL Cement Environment Manager / Environment Officer is to ensure the spill kit is restocked. • For spills on soil, they may be either remediated in-situ or the contaminated soil may need to be removed for appropriate disposal.

13.9 Equipment

13.9.1 Spill Response The following spill response equipment will be stored in the fuel and other chemical storage areas:

• 55 gallon drum of absorbent granules;

• 100 absorbent pads;

• 30 metres of absorbent pigs;

• Shovels;

• Two (2) empty 55-gallon drums (steel) for collecting used absorbent;

• A hand pump and 10 metres of plastic hose;

• All PPE to safely handle spills (e.g. gloves and eye protection).

In the case of soil contaminated by a fuel or chemical spill, the soil should be excavated and taken to the volatilisation pad, before being disposed of in the approved solid waste landfill. This also applies to any sorbent material used to clean up spills.

13.9.2 Marine Spill Response

The following spill prevention measures are to be carried out for general ship operations:

Before bunker handling commences, all deck scuppers and open drains must be effectively plugged to prevent spilled oil from escaping from the vessel.

All water accumulation on deck should be periodically drained and scupper plugs replaced

All collected water is to be transferred to a slop tank or other suitable receptacle ready for proper disposal;

When not in use, sea and overboard discharge valves connected to the bunker and ballast system must be securely closed;

All emergencies at sea which have the potential to cause pollution are to be managed in accordance with Regulation 37 Annex 1 of the International Convention for the Prevention of Pollution from Ships 1973.

Page 241 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 242: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

13.9.3 First Aid Facilit ies and Personal Protective Equipment (PPE)

First aid facilities will be located in every site office and work vehicle. The location of first aid kits in the site offices will be clearly displayed. The first aid kits will be kept clean and restocked on a three monthly basis.

TL Cement will provide all employees with the necessary PPE, including but not limited to:

• Ear plugs; • Eye protection; and • Gloves.

13.9.4 Fire Fighting Equipment

Firefighting equipment (i.e. extinguishers) will be located in every site office and work vehicle. The extinguishers will be easily accessible and clearly displayed. All employees will be provided with the necessary training on the appropriate usage of extinguishers.

The firefighting equipment will be tested and tagged by a competent person every six months. Used or expired extinguishers will be removed from site and will be immediately replaced.

A complete firefighting hydrant system will be built for the plant.

13.10 Training

All personnel will receive environmental training as part of a mandatory induction for the Project. The environmental induction will include as a minimum the requirements of this EP.

All personnel will be trained in the use of the spill response kit and fire fighting equipment required for the implementation of this EP.

Environmental notices will be developed and placed on the Project site notice boards on a regular basis and in response to non-compliance and environmental incidents.

The training register will be kept onsite in an easily accessible location for inspection and auditing.

Page 242 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 243: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

14 DECOMMISSIONING PLAN

Sections 8 and 10 of this EMP contains details of the mitigation and monitoring requirements for the Decommissioning Phase of the Project.

TL Cement’s vision for closure is to:

- To ensure a self-sustaining vegetative cover on areas disturbed by mining activities where this is appropriate; - Provide sustainable end land uses in keeping with the needs of local communities; and - Ensure economic sustainability for affected communities.

14.1 Objectives The primary objective of the reclamation plan will be to return, where practical, all areas disturbed by mining operations to acceptable land use and capability.

The closure objectives for the cement plant operations are:

- Adhere to all statutory and other legal requirements; - Ensure safety & health of all stakeholders during closure and post closure and that communities using the site after closure are not exposed to unacceptable risks; - Ensure that closure supports productive uses considering pre-operational conditions and are in agreement with commitments to and requirements of stakeholders - Physically and chemically stabilize remaining structures, if required, to minimize residual risks; - Promote bio-diversity and biological sustainability; and - Utilize closure strategies that promote a self-sustaining condition with little or no need for on-going care and maintenance.

14.2 Preliminary Decommissioning Plan

In order to meet the vision for closure, a preliminary decommissioning plan has been outlined below, including impacts of the project and mitigation and monitoring measures to be undertaken during the decommissioning phase of the project (Holtec 2015).

Sections 8 and 10 of this EMP also contain details of the mitigation and monitoring requirements for the Decommissioning Phase of the Project.

Page 243 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 244: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Ecology and Biodiversity

Aspect / Impact Mitigation Measures

Re-establishment of habitats or creation of new habitats via rehabilitation

Sequential reclamation and rehabilitation is proposed; Afforestation by plantation is proposed to be carried out;

The top soil stored separately during the operation phase shall be used for afforestation and plantation only. Local species shall be planted in the area; The buildings shall be dismantled. The machinery shall be sold to other industries for use or to authorized scrap dealers. The area shall be brought to its original state.

Introduction of alien invasive flora and fauna Invasive alien species control programme implemented as a component of the EMP, including adaptive management measures; EMP should be reviewed every five years with emphasis on control of alien invasive flora and fauna;

All invasive alien species control measures specified in the EMP must be implemented.

Loss or disturbance of fauna species of special concern due to collisions and noise disturbance

Sequential rehabilitation to be conducted as soon as possible at the completion of operation; Reclamation and rehabilitation of the area to restore the area in natural, pre- construction condition; Environmental education training program, including refresher sessions, for all employees, contractors and their families;

EMP should be reviewed every five years.

Increased hunting/ poaching of wildlife and loss of habitats for crop production

No fauna are to be hunted or destroyed by any project personnel;

Effective penalties (e.g. fines) must be imposed for the hunting or harm to fauna by any

Page 244 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 245: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Ecology and Biodiversity

Aspect / Impact Mitigation Measures employee of TL Cement; The locals should be encouraged to utilize the cash income, during employment for investments that will assist with increasing productivity of the local agricultural sector; An environmental education programme to be developed and implemented for all TLC employees, their families and villages within the concession.

Water Resources

Aspect / Impact Mitigation Measures

Chemical contamination of surface water resulting from accidental spills during transportation and handling and seepage from waste

Emergency contaminant and mitigation measures must be developed to minimize impacts should accidental spillages occur along the transport routes;

Equip all trucks and equipment carrying fuels or oil with spill response materials and train personnel in the use of such materials; Store all potential sources of contamination in secure facilities with appropriate Storm Water management systems in place to ensure that contaminants are not released to the water resource through Storm Water runoff.

Sedimentation of surface water resulting from erosion and runoff from exposed surfaces and roads

Minimize disturbance of soil and vegetation; Implement rehabilitation and re-vegetation as soon as possible;

Refer to dust and erosion suppression measures listed above.

Contamination of groundwater resulting from seepage from hazardous materials and waste

Manage waste in accordance with Waste Management Plan;

Waste Management

Page 245 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 246: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Aspect / Impact Mitigation Measures

Generation of debris from p r o j e c t infrastructure

The buildings shall be dismantled. The machinery shall be sold to other industries for use or to authorized scrap dealers; The office equipment like table, chairs, computers etc. can be donated or auctioned for its use; The debris generated from dismantling of building shall be used in backfilling of exploited pits.

Socio-economic Impacts

Aspect / Impact Mitigation Measures

Direct impacts on project employees and their families

Communication with internal stakeholders i.e. employees to discuss the implications of closure;

Phased programme of retrenchments and retirements to ensure that the full impact of reduction in employment is spread over several years to ensure that the impact is absorbed as far as possible; Career counseling and capacity building;

Development of a skills register and dissemination of the register to alternative employers, government etc.

Loss of economic benefits to the project supply chain

Early communication with stakeholders i.e. service providers including local service providers, bulk service providers and the business community to discuss the implications of closure; Liaison with other industries to discuss opportunities for service providers within their supply chain.

Loss of support to the local government and other government levels with respect to taxes and royalty incomes

Timely engagement of local, regional and national government to advise of closure and the implications this will have on the government revenue from taxes and royalties; Gradual transfer/return of responsibilities to local government with respect to service

Page 246 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 247: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Socio-economic Impacts

Aspect / Impact Mitigation Measures provision where the project has played an active role in service provision.

Loss of community benefits in the form of project funded community development programme

Early engagement of stakeholders to discuss and scenario plan the transfer of usable assets to the community, local government and other stakeholders;

Provision of information on the maintenance and management costs of assets and typical maintenance programme; Capacity building for asset management.

Loss of Employment and Income due to retrenchment

Develop the TLC grievance procedure to capture and address grievances arising due to retrenchments and downscaling for the employees; If practical, shift the employees to other businesses of the group company; Compliance with IFC’s Performance Standard 2 “Labour and Working Conditions”; Actively promoting the development of different economic sectors from an early stage e.g. through incentivizing other industries to locate in the area, and promoting an increase and diversity of skills in the local population; Develop a decommissioning and closure plan which is updated every five years increasing in detail as closure approaches, and actively engaging with a range of stakeholders throughout the life-of-project to discuss potential consequences of decommissioning and possible mitigation.

Eco-system Services

Aspect / Impact Mitigation Measures

Page 247 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 248: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Reduced quality of natural resources and ecosystem services to local communities due to emissions to air, water or soil

To minimize impacts, the project must comply with best pract ice for air emissions, water (storm water and effluent) discharge quality and solid waste disposal.

Soils, land capacity and land use

Aspect / Impact Mitigation Measures

Remediation of contaminated soils and demolition of project infrastructure, resulting in re- establishment of baseline soil characteristics and land capability

The contaminated soils during de-commissioning and closure should be excavated and disposed of; Infrastructure like buildings, access roads etc. having potential post mining benefit, if desired shall be handed over to stakeholders; The areas not required by stakeholders shall be decommissioned and the area will be rehabilitated by replacing soils and adding nutrients, if necessary;

Air Quality

Aspect / Impact Mitigation Measures

Increase in PM10 and PM2.5 emissions resulting from land clearing, earthworks and vehicular movement

Continuous water spraying on roads used routinely by vehicles; Set speed limits to minimize the creation of fugitive dust within the project boundary; Continue with the routine air quality monitoring program; Minimize the disturbed footprint as far as practically possible; Revegetate and landscape disturbed areas as soon as possible.

Visual Impacts

Aspect / Impact Mitigation Measures

Page 248 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 249: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Dust generation and site disturbance due to earth moving and removal of infrastructure, affecting the visual character for communities

Minimize the disturbed footprint as far as practically possible; Revegetate and landscape disturbed areas as soon as possible to reflect the surrounding topography and vegetation as much as possible;

Re-establishment of baseline visual character due to rehabilitation of the site and removal of project infrastructure

Landscaping and re-vegetation in accordance with the surrounding vegetation and topography

Page 249 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 250: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

15 CAPACITY DEVELOPMENT AND TRAINING

Training is essential for ensuring that the provisions of the EMP are implemented efficiently and effectively. Training needs will be identified based on the existing and available capacity of the site and Project personnel (including the proponent, contractors and subcontractors) to undertake the required management actions and monitoring activities. A training program will be presented in this section of the EMP. The training program will be developed and delivered by suitably qualified personnel, in a language and medium understood by workers and/or employees.

A training needs analysis will be conducted by TL Cement as part of the resource planning for the Project implementation. The training needs analysis will consider:

• Practical training via instruction; • Formal vocational training; • Success and completion criteria; • Delivery method; • Certification and recognition system; and • Training refreshers and frequency.

During the life of the Project, the following EMP training will be provided to relevant personnel:

• Field sampling and sample handling techniques; • Data collection and collation; • Emergency response procedures (e.g. spills); • Management of exceedances (e.g. dust levels); and • Roles and responsibilities for EMP implementation.

Page 250 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 251: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

16 PUBLIC CONSULTATION AND INFORMATION DISCLOSURE

WorleyParsons and TL Cement have undertaken a process of consultation with the people who may be affected by the Project and the Project stakeholders. WorleyParsons and TL Cement have made efforts to ensure that the public, including affected people, women and vulnerable groups, have the opportunity to participate fully in the consultation process. Consultations have taken place on a continuous basis, starting as early as possible in the EIA process. This section describes the public consultation conducted to date.

Consultation was undertaken during the development of the EIS. During this consultation, aspects pertaining to the management and mitigation measures for the Project were raised. These details are included in this component to illustrate that both TL Cement and WorleyParsons have undertaken consultation around the EMP.

16.1 Purpose of the consultation during the preparation of the EMP

The public consultation process for the environmental assessment is carried out in accordance with the Draft Ministerial Diploma for the “Regulation on the Public Consultation Procedures and Requirements during the Environmental Assessment Process” dated 22 April 2014.

The EMP was referenced in the final consultation session undertaken on 11 December 2015.

16.2 Methodology and Approach

16.2.1 Identified Stakeholders

The following table lists the identified stakeholders consulted during the environmental assessment process.

Table 16-1: Identified stakeholders consulted during the EIS process

Governments

President of Republic Democratic of Timor-Leste

• President of RDTL

Prime Minister of Republic Democratic of Timor-Leste

• Prime Minister of RDTL

Ministry of Commerce, Industry, and Environment

• Minister of CIE

• National Directorate for Pollution Control and Environmental Impact

Page 251 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 252: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

• General Director for Environment

• Nacional Director for Industries and Manufacturing

Ministry of Petroleum and Mineral Resources

• Minister of PMR

• National Directorate of Minerals

• Institute of Petroleum and Geology (IPG)

Ministry of Justice

• Secretary of State for Land and Property

Ministry of Finance

• Minister of Finance

Ministry of Planning and Strategic Investment

• Minister of PSI

Ministry of Public Works, Transport and Communications

• Minister of PWTC

• Directorate of Ports/APORTIL

• National Directorate for Water Quality and Control

Ministry of Tourism, Arts and Culture

• Secretary of State for Arts and Culture

Secretary of State for Employment Policy and Vocational Training

• Secretary of State for EPVT

Municipality (District) Government

Baucau Municipality (formerly Baucau District Administration)

Baucau Administrative Post (formerly Baucau Sub-District Administration)

PNTL Baucau Municipality

PNTL Baucau Administrative Post

BOP Baucau Municipality

F-FDTL Baucau Municipality

Page 252 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 253: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Baucau Municipality Directorate of Land, Property and Cadastral Services

Baucau Municipality Directorate of Pollution Control and Environmental Impact

Baucau Municipality Health Directorate

Baucau Municipality SEPFOPE

Baucau Municipality Public Works

Baucau Municipality Social Directorate

Baucau Municipality Agriculture Directorate

Baucau Municipality Water and Sanitation Directorate

Baucau Municipality Electricity Directorate

Local Government

Suco Council Tirilolo

Suco Council Triloca

Suco Council Caibada

Suco Council Bahu,

Suco Council Bucoli

Local Community

Chefes de Aldeia

Lia’nain

Local Youth Organizations

Local Women’s Organizations

Local Fishermen’s Organization

Baucau Parish – Old Town

Baucau Parish – New Town

Baucau Bishop

Civil Society/Local NGOs

La’o Hamutuk

Page 253 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 254: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Luta Hamutuk

Haburas

Rede ba Rai

Belun

Kapeliwa (Local NGO)

Other Organizations

International Finance Corporation (IFC)

Conservation International

BESIK (Bee, Saneamentu no Ijiene iha Komunidade) Rural Water Program

Presidente CCI Baucau

16.2.2 Mechanism for Public Consultation

The public consultation conducted for the EIS and EMP engaged affected communities, general public, non-governmental organizations, government agencies, and others.

The consultation took different forms, depending on the purpose; including, but not limited to:

• One on one meetings; • Public information meetings and presentations; • Site visits; • Development and distribution of a Non-Technical Summary document; and • Questionnaire completion with stakeholders and community members.

All public consultation sessions were advertised 7 days in advance by local TV transmissions and by notices placed strategic locations; and were also advertised though local radio stations such Radio Popular Coulelemai Bucoli and Radio Komunidade Lian Matebian in Baucau. A copy of the public notice was also posted on TL Cement’s website.

Additionally, the notices were displayed at local government offices including Baucau Municipality, Baucau Administrative Post, Chief of Village, and PNTL Baucau Municipality. Lastly, a copy of all notices was provided to the NDPCEI.

16.3 Summary of consultation activities carried out

The formal consultation activities undertaken between February 2015 and December 2015 are detailed below. Ongoing consultation with key stakeholders has taken place in addition to the formal sessions.

Page 254 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 255: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Table 16-2: Summary of consultation session completed during the EIS process

Date Type of Consultation Key components

June 2014 TL Cement conducted consultation with the Tirilolo community and Youth group

The meeting was used to discuss the land use and crop types in the area, in relation to the location of the proposed project.

July 2014 TL Cement met with members of the Casido Traditional Council, Suco Council and Government of Timor Leste to coordinate activities for a cultural ceremony.

Prior to TL Cement construction and production activities it is important to hold a cultural ceremony.

October 2014 TL Cement met with the Lia-Nain of Suco Ostico The meeting was used to discuss the proposed project and the land use in the area.

November 2014 TL Cement met the communities from Suco’s Bucoli Adeia Macadai, Lulihen and Land owners Mr Virgillio G Antonio, Mr Oscar Da Silva and Mr Jose’ Da Silva

The meeting was used to discuss the proposed project and the land use in the area. The community was supportive of industry being established in Bacau.

February 2015 TL Cement and WorleyParsons conducted consultation in the local community during a site visit with the Lian Nian (Traditional Leaders)

The locals in general were enthusiastic about the project and had queries about the development activities for the locals that TL Cement would initiate as well as the employment opportunities the project would generate for the locals.

May 2015 TL cement and WorleyParsons with the community representatives :

• Chefe Suco Trololo: Ricardo Ernesto Belo (RB)

• Chief of Community Police in Suco Trilolo: Norberta Belo (NB)

• Chefe Aldeia Lia Lailesu: Cipriano Belo (CB)

• Chefe Aldeia Parlamentu: Manuel Belo (MB)

• Chief of Traditional Practice (Lia Nain): Duarte Belo (DUB)

These meetings were set up to discuss the field work surveys that would be undertaken for the EIS

Page 255 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 256: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

• Secretary of Suco Trilolo: Zeca Belo (ZB)

August 2015 Community Questionnaire

WP Timor Leste office staff visited four (4) most affected aldeias in Suco Tirilolo; aldeia lia lailesu, Parlamentu, Caisido-Kotalali and Osso-wa.

The objective was to meet the community who are unable to attend the previous meeting and hear their opinions and suggestions as well as improve their awareness of the project.

Most of them were well aware of the project and showed their enthusiasm for the project; however, they are worried about the impact of the project on their cultural heritage, land and lifestyle.

3 September 2015 Public Consultation on the draft TOR was conducted in Caisido, Baucau Municipality.

WorleyParsons presented some preliminary findings as described in the TOR and Project Documents.

11 December 2015 TL Cement and WPTL organized a public meeting in Caisido, Baucau Municipality, to discuss the proposed project and the draft EIS and EMP. The date, venue, and time of this public meeting were coordinated with the relevant Administrator, Chefes do Suco and Chefes da Aldeia.

WorleyParsons presented a description of the project, explained the EIS process, and provided a brief summary of the study findings to date. Following the presentation, two information tables were set up with maps, diagrams and pictures of a similar cement plant in Indonesia. The tables were staffed by representatives of WorleyParsons and TL Cement who provided more detailed explanations of project details and answer questions. The community members were invited to observe, ask questions and/or provide recommendations to the Project team.

07 January 2016 TL Cement and Worley Parsons met with the NGO group Lao Hamutuk to update them on preliminary EIS findings

WorleyParsons description of the project, explained the EIS process, and provided a brief summary of the study findings to date. Lao Hamutuk stated that resettlement and compensation need to be carefully addressed. Lessons learnt from the Suai Supply base should also be taken into consideration.

07 January 2016 TL Cement and Worley Parsons met with Foundação Haburas to update them on

WorleyParsons description of the project, explained the EIS process, and provided a

Page 256 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 257: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

preliminary EIS findings brief summary of the study findings to date. Foundação Haburas stated that a Resettlement/relocation and Groundwater Management Plans should be developed.

13 January 2016 TL Cement and Worley Parsons met with Direcção Nacional Controla Qualidade Agua (DNCQA)to update them on preliminary EIS findings

WorleyParsons description of the project, explained the EIS process, and provided a brief summary of the study findings to date. DNCQA stated that that resettlement and compensation need to be carefully addressed. Groundwater, Dust and Noise management plans should be developed.

13 January 2016 TL Cement and Worley Parsons met with NGO group Luta Hamutuk (LH) to update them on preliminary EIS findings

WorleyParsons description of the project, explained the EIS process, and provided a brief summary of the study findings to date. LH stated that that resettlement and compensation need to be carefully addressed. Government strategies to maintain and enhance subsistence farming strategies need to be implemented. They recommended contributions towards the health and education sectors.

Page 257 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 258: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

16.4 Summary of main comments received from the public, community leaders, NGOs, local officials, other stakeholders

The EMP has been developed to take into account the concerns raised in the Community Consultation sessions. In order to ensure that they are included in the EMP, the key aspect is identified below in relation to the question or comment and the management measure or mitigation measure is detailed below the key aspect.

# (Unique number Retained from Questions database)

Aspect &

Environmental Management and Mitigation Measure

Questions from Public Consultation

Proponent’s Response

3 Air quality

Air Quality and Dust mitigation measures

Noise

Jaime (school teacher), Suco Parlamento; Claudio (student); Agustinho da Costa Belo, Aldeia Osso-ua; Joao Freitas, Suco Caisido

What are the impacts from the cement plant and limestone mine to the surrounding environment? What are the measures taken to mitigate these impacts?

What is the level of air pollution emitted from the plant and mine (including when transporting from mine to plant)?

What will be the mitigation towards noise pollution (from machinery, heavy equipment, blasting)?

James Rhee:

Air pollution mainly will come from power generation and dust. Dust will mainly be released during transportation of material from mine to plant and from/to jetty using conveyor belt. The amount of air pollution can be mitigated by using solar and wind power to generate electricity whereas dust from the conveyor belt will be well contained using a closed system. In addition, company will build new road from mine to plant as a mitigation measure to reduce dust.

Regarding noise pollution, since it is low

Page 258 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 259: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

risk, hence no mitigation measure required.

4 Cultural Heritage

Cultural Heritage Management Plan

Jaime (school teacher), Suco Parlamento; Joao Freitas, Suco Caisido; Tomas Freitas, Administrative Post of Vemasse

What is the position of TL Cement regarding any sacred site and/or cemetery found within the project site?

TL Cement respects all cultural heritages including evidence of ancient human habitation found within the project site. In fact, a Cultural Heritage Management Plan will be prepared in coordination with the community and the Secretariat of Arts and Culture to conduct procedures and/or traditional rituals required relocating sacred site and/or tombs including the management and protection of new and known sites during the project life.

During a field study on the project site and its vicinity, some antique materials from ancient civilization (spanning the last ca 30,000 years) were found and documented.

5 Groundwater

Water Management Plan

Francisco Hero (PNTL)

Where is the location to drill borewells for water supply? Will the amount withdraw from the well affect the spring located in Osso-ua?

Water requirement for mining and plant operation is to be abstracted from groundwater through the drilling of borewells at the Uaidei River.

Page 259 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 260: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

A feasibility study will be conducted prior to finalize the decision on drilling. The location of the proposed drilling site and the Osso-Ua Spring are quite far separated and thus there will be no impact to Ossu-Ua Spring.

6 Land Use and Tenure

Relocation and Compensation Plan

Manuel Azevedo Has the company identified properties that may be found within the project site? What will be the negotiation regarding these properties?

TL Cement is currently working with the Directorate of Land, Property and Cadastral Services (DLPCS) to map affected households, farmland, and other property. Once TL Cement has secured the mining and environmental licenses required for the project, we will enter into discussions with those affected households and property owners. Based on the mapping and negotiations, TL Cement will prepare a Resettlement Plan. This Resettlement Plan will provide greater detail on the monitoring and reporting requirements in relation to the potential social and economic impacts associated with the development of the project

Page 260 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 261: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

7 Agustinho da Costa Belo, Aldeia Osso-ua

If the properties (Farm land, house etc) are taken by the company, will there be compensation to the owners?

Yes.

10 Groundwater

Water Quality Management Plan

Duarte Xavier Recommendation: Management plan for local reservoir/spring so to avoid waste water contamination from the plant.

Noted

11 Air Quality

Air Quality Management Plan

Duarte Xavier It is mentioned that traffic will increase from 3 to 71 passenger cars in a day during construction and operation. What will be the mitigation measure towards dust caused by this high traffic?

Dust suppression using water.

13 Waste

Waste Management Plan

Herminio Belo Where will the waste water from the plant be discharged? Is there any treatment plan for waste water?

The volume of waste water from plant to be discharged is very low and thus will have negligible detrimental impact to the environment. In addition, all chemicals used on site are to be stored, handled and disposed of in accordance with a Waste Management Plan.

14 Economic

Resettlement Plan

Felipe Belmiro Belo Recommendation: There should be compensation for community whose properties are directly affected by the project.

Yes

Page 261 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 262: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

21 Tenure and Land Use

Cultural Heritage

Resettlement Plan

Cultural Heritage Management Plan

Eusebio Assis (Youth Representative), Suco Tirilolo

When will the affected community be gathered to discuss property lost and cultural heritage- related issues before proceeding with construction of the plant and/or limestone extraction?

TL Cement will proceed with compensation negotiations following receipt of project approvals.

22 Economic

Training needs analysis

Training Plan

Eusebio Assis (Youth Representative), Suco Tirilolo

When will the training for local workers begin?

Once the company has obtained the Environmental License and other project approvals.

16.5 Identify how those comments were taken into account

These comments were taken into account by ensuring that any recommended mitigation measures were populated in the EMP. Key items which were raised by the community which have been incorporated are:

• Water quality impacts from the Limestone Mine have been addressed through mitigation measures and a monitoring programme; • Cultural Heritage impacts through clearing have been addressed by incorporating mitigation measures; • Abstraction impact from water supply on the springs at Osso-ua and Caisido requiring regular monitoring; and • Dust and Air Quality impacts requiring air quality monitoring and reporting.

16.6 Details of public participation activities

The public consultation and community engagement process has been detailed extensively in the EIS and the reader is referred to this document which includes the minutes and photographs.

A summary of the consultation sessions is contained in Table 16-2 in Section 16.3.

16.7 Summarize the public acceptance or opinions on the proposed Project

Key comments from community members are extracted below:

Page 262 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 263: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Lian Nian (Traditional Leaders) said “The locals in general were enthusiastic about the project and had queries about the development activities for the locals that TL Cement would initiate as well as the employment opportunities the project would generate for the locals”

Casido Community leaders “are 100% willing to accept the cement plant project in their area”

Chief of Suco “Time of development has come. Community to ignore any rumours [that project will destroy livelihood]”

Director of Environmental Department, GoTL said that many community concerns around air quality will be addressed by “technology used in Australia which does not produce smog to a level harmful to the nearby community”.

Overall the response to the project is positive and the majority (more than 90%) of the local community supports the project.

16.8 Related materials or activities

Newspaper readership is low in Baucau and thus other advertising methods are better suited to encourage broad public consultation. Therefore, all notices associated with the EIS public consultation were advertised on national television (TVTL) in Dili on the 4th to 10th of December 2015. Notices were also advertised though local radio stations such Radio Popular Coulelemai Bucoli and Radio Komunidade Lian Matebian in Baucau commencing on the 27th of November to 4th of December, 2015. A copy of the public notice was also posted on TL Cement’s website. Additionally, the notices were displayed at local government offices including Baucau Municipality, Baucau Administrative Post, Chief of Village, and PNTL Baucau Municipality. Lastly, a copy of all notices was provided to the NDPCEI.

Prior to the consultation in December 2015 a Non-Technical Summary document was prepared and translated into Tetun and made available at the following locations:

• TL Cement Office;

• Baucau Municipality Office;

• The NDPCEI Dili Office;

• The NDPCEI Baucau municipality office;

• Baucau church;

• PNTL Vemasse HQ;

• Vemasse Administrative Post;

• Baucau Municipality SEPFOPE Directorate; and

• Tirilolo Suco Hall.

Page 263 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 264: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

The document was made available for viewing during normal business hours and made available free of charge.

A copy of the document was made available at a local school, church, or other public facility (Figure 5) near the proposed project and available outside of normal work hours.

The document was also posted on TL Cement’s public website at http://www.tlcement.net/.

16.9 Recommendations for future consultations

TL Cement is committed to ensuring continued, open and transparent consultation with all Project stakeholders and interested and affected parties. Consultation will continue through the life cycle of the Project.

Page 264 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 265: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

17 COMPLAINTS AND GRIEVANCES MECHANISM

The Project Proponent will establish a Complaints and Grievances Mechanism (CGM) related to environmental and social issues arising during the pre-construction, construction, operation and decommissioning, and post-closure phases of the Project.

The Complaints and Grievance Mechanism shall be developed to ensure that concerns and potential conflicts arising during the various phases of the Project can be satisfactorily addressed. WorleyParsons has developed this grievance mechanism framework for discussion with stakeholders (including government) to refine the procedure to meet stakeholder needs through consultation. .

Once refined, project staff (comprising a representative who will receive grievances at each Project site’s grievance office, and a Dili office representative) should be provided with training. These staff will accept and log incoming grievances and, if the grievance is directly related to the Project’s actions, follow a prioritisation process to identify the required remedial action.

Figure 19 illustrates a suggested procedure for managing and resolving complaints during the feasibility stage. The procedure is equally relevant during the development stage of the Project with responsibility for resolution defined between the Project Proponent and the construction contractor. It is important to ensure the following values are upheld throughout the grievance process:

• Awareness; • Accessibility; • Transparency; and • Expediency.

Stakeholder awareness of the existence of the CGM will mean that when an issue arises, community members will know where to go to address and resolve the issue. This will encourage the issue to be dealt with through the appropriate mechanism and will improve expediency of resolution and good will with the community. Therefore, when engaging with the villages and other stakeholders they should be made aware of the grievance mechanism and where or whom they should contact to access the mechanism.

Accessibility to the CGM will also enable stakeholders to air their complaints directly thereby avoiding other forums such as the media. Typically, the earlier the Proponent becomes aware of potential issues, the more efficiently these can be mitigated and contained. Furthermore early detection of potential issues can prevent problems arising later in the Project lifecycle. It will be essential to break down barriers to accessibility which, based on baseline investigations, include, geographic location, literacy levels, language and cultural appropriateness, and distrust in government or corporate structures. Recommended strategies to overcome these barriers include:

• Establishing a grievance office at Dili, surrounding sucos and the Cement Plant site where grievances might be heard, namely Caisido and Baucau. • Upon request, remote locations and vulnerable individuals (e.g. elderly and disabled) should be visited by a representative of the project on a regular basis who will disseminate information regarding the

Page 265 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 266: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Project and receive complaints from stakeholders at their village or residence. This will promote accessibility of the grievance procedure and help build a relationship with communities and encourage dialogue. • Complaints should be able to be registered via a toll-free mobile telephone number to be established by the Proponent in cooperation with local telecom provider to allow direct access to each individual to the grievance mechanism. Another option is to provide a pre-paid mobile phone to each village chief to be exclusively used for lodging grievances. The mobile phone would allow the chief to send a message to the nearest grievance office requesting the grievance officer to visit the village and record the grievance. The pre-paid mobile option needs to be further investigated in consultation with village chiefs. • Representatives should be instructed to note down complaints where the individual is unable or unwilling to write the complaint themselves. • Local people fluent in the relevant languages should be engaged as representatives. • Locals should be consulted regarding the cultural appropriateness of the complaints process. • Complainants should be given the option of maintaining anonymity throughout the complaints process.

Transparency of process cultivates trust and ensures expectations among the stakeholders are set at an appropriate level. Elements of the grievance procedure which will encourage transparency include explaining the process and timescales associated with processing a complaint, providing the complainant with a copy of the complaint when it has been submitted and ensuring the complainant is kept informed of developments in processing their complaint. Written complaints should be held at the respective grievance offices where the complainant (or a designated advocate) should be allowed access.

Expediency will enable efficient processing of complaints. In order to encourage expediency the project should set deadlines for processing complaints and a case management approach should be established among the relevant staff, with oversight from a senior individual who should be assigned responsibility for management of the grievance mechanism.

As well as committing to the values mentioned here, the project will work to International Finance Corporation (IFC) guidelines (IFC, 2011) regarding grievance mechanisms.

Page 266 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 267: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Figure 19: Grievance resolution framework

Page 267 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 268: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

18 WORK PLAN AND IMPLEMENTATION SCHEDULE

The following sections details the work plan and implementation schedule for the various phases of the Project.

Page 268 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 269: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Figure 20 Overall work plan and implementation schedule

Post project approval 2016 - 2017 *1 2018 2019 - 2055 2055 - 2060

Tasks to implement EMP Tender and Detailed Design Phase Preconstruction Construction Operations Decommissioning

Surface Water Quality Baseline Studies ●

Project Approvals ●

Stream gauges installed ●

Monitoring boreholes installed ●

Sediment transport model ●

Relocation of people and heritage sites (w here required) ●

Groundw ater Study ●

Flora and Fauna Pre-Clearance Validation ●

Relocation of affected landholders ●

Heritage pre-clearance activities ●

Complaints and grievances mechanism ●

Baseline studies for Coral, f isheries, w ater quality ●

Fauna counts and tracking ●

Water monitoring ● ● ● ●

Fisheries assessment ● ● ●

Weed management and control of invasive species ● ● ● ●

Fauna counts and tracking ●

Traff ic assessment (4 w eeks monitoring at start of phase) ● ● ● ●

Install Automated Weather Station and commence climate recording ●

Annual air quality monitoring ● ● ● ●

6-monthly groundw ater monitoring ●

Annual groundw ater monitoring ● ● ●

Accident Emergency Response Review ● ● ● ●

Review Biodiversity Action Plan ● ●

Annual Environmental Reporting to the GoTL ● ● ●

Finalise Closure Plan ●

Monitoring and reporting of f lora species abundance and coverage 5 years after mine closure ●

Record and monitor total area of re-vegetation and the species used for rehabilitation ●

5 years post closure assessment of rehabilitation success and soil health ●

Page 269 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 270: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Table 3 Detailed work plan and implementation schedule

Activity Tender and Detailed Design Phase

Preconstruction Construction Operations Decommissioning

Post project approval 2016 - 2017 2018 2019 - 2055 2055 - 2060

Clearing and earthworks movement of heavy machinery

Surface Water Quality Baseline

Studies

Project Approvals

Stream gauges installed

Monitoring boreholes installed

Sediment transport model

Relocation of people and

heritage sites (where required)

Flora and Fauna Pre-Clearance

Validation

Relocation of affected

landholders

Heritage pre-clearance activities

Complaints and grievances

mechanism

N/A N/A Accident Emergency Response

Review

Review Biodiversity Action Plan

Water monitoring

Complaints and grievances

mechanism

Weed management and control

of invasive species

Annual Environmental Reporting

to the GoTL

Construction of infrastructure (Plant, jetty, internal roads, accommodation, power plant, MOF)

Baseline studies for Coral,

fisheries, water quality

Fauna counts and tracking

Water monitoring

Fisheries assessment

Complaints and grievances

mechanism

N/A N/A

Page 270 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 271: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Weed management and

control of invasive species

Fauna counts and tracking

Movement of vehicles and people causing dust and noise

Generate electricity through Power Station or diesel generators

N/A Traffic assessment (4 weeks

monitoring at start of phase)

Install Automated Weather

Station and commence climate

recording

Annual air quality monitoring

Traffic assessment (4 weeks

monitoring at start of phase)

Undertake daily climate

measurements

Annual air quality monitoring

Traffic assessment (4

weeks at start of phase)

Undertake daily climate

measurements

Annual air quality monitoring

Traffic assessment (4 weeks at

start of phase)

Undertake daily climate

measurements

Annual air quality monitoring

Water Supply source Groundwater Study 6-monthly groundwater

monitoring

Annual groundwater

monitoring

Annual groundwater

monitoring

Annual groundwater monitoring

Operation of infrastructure (Plant, jetty, internal roads, accommodation, power plant, MOF)

N/A N/A N/A Accident Emergency

Response Review

Review Biodiversity Action

Plan

Water monitoring

Complaints and grievances

mechanism

N/A

Page 271 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 272: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Weed management and

control of invasive species

Fauna counts and tracking

Annual Environmental

Reporting to the GoTL

Shipping and movement of ships

N/A N/A Fisheries assessment

Complaints and grievances

mechanism

Fauna counts and tracking

Review Biodiversity Action

Plan

Control of invasive species

(and Ballast)

Fauna counts and tracking

N/A

Decommissioning of infrastructure and revegetation of habitat

Biodiversity Action Plan

Closure Plan

Water monitoring

Annual air quality monitoring

Traffic assessment (4 weeks at start of phase)

Monitoring and reporting of flora species abundance and coverage 5 years after mine

Page 272 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 273: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

closure

Complaints and grievances mechanism

Record and monitor total area of re-vegetation and the species used for rehabilitation for a period of 5 years following decommissioning.

5 years post closure assessment of rehabilitation success and soil health

Undertake daily climate measurements

Notes:

1. This start date is only possible if TL Cement receives the necessary project approval permits on time and based on type of financing structure in place for the project.

Page 273 301012-02135-EMP-003 Rev 1 : 02 February 17

Page 274: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

19 COST ESTIMATES

For the purpose of the cost estimate, the following assumptions are key:

• This estimate covers both the EMP for the Cement Plant, Jetty and Other Associated Infrastructure and the EMP for the Limestone Mine • The duration of the Project phases are: o Pre-construction = 6 months; o Construction = 2 years and 6 months; and o Operations and Decommissioning = 55 years. • Replacement and maintenance costs for monitoring equipment are excluded. • All reporting and data interpretation for Construction, Operations and Decommissioning phases are undertaken by Company technical specialists. External consultant costs have not been allowed. • The responsibility for the costs are aligned with the Company responsibility matrix in Section 8 • CPIX Inflation has not been accounted for. • Costs associated with infrastructure development recommended as a mitigation measure have been excluded. • Estimate costs only.

Page 274 301012-02135-EMP-003 Rev 2 : 02 February 17

Page 275: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Table 19-1 EMP Implementation cost estimate

Aspect Activity Project Phase Mitigation and monitoring measures

Cost Estimate (USD)

Air Quality Earthworks Heavy machinery movement Vehicles, buses and cars movement

Pre-construction Automated Weather Station setup and installation Monthly data download and interpretation

$150,000

Earthworks Heavy machinery movement Vehicles, buses and cars movement

Construction Monthly data download and interpretation

$24,000

Operating cement plant Operating power plant

Operation Monthly data download, 6-monthly interpretation

$550,000

Earthworks Heavy machinery movement Vehicles, buses and cars movement

Decommissioning Monthly data download, 6-monthly interpretation

$24,000

Noise Earthworks Heavy machinery movement Vehicles, buses and cars movement

Pre-construction Twice per year measurements at receptors

$10,000

Earthworks Heavy machinery movement Vehicles, buses and cars movement

Construction Twice per year measurements at receptors

$20,000

Operating cement plant Operating power plant

Operation Annual measurements at receptors $550,000

Earthworks Heavy machinery movement Vehicles, buses and cars movement

Decommissioning Twice per year measurements at receptors

$20,000

Page 275 301012-02135-EMP-003 Rev 2 : 02 February 17

Page 276: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Aspect Activity Project Phase Mitigation and monitoring measures

Cost Estimate (USD)

Water Quality Earthworks Heavy machinery movement Vehicles, buses and cars movement Drilling of water supply borehole

Pre-construction Baseline Marine Water Quality survey (coral health, risk from ballast) Monthly sampling at 5 locations, interpretation 4x per year

$124,000

Earthworks Heavy machinery movement Vehicles, buses and cars movement Abstraction of water from the water supply borehole

Construction Monthly sampling at 5 locations, interpretation 4x per year

$48,000

Operating cement plant Operating power plant Abstraction of water from the water supply borehole

Operation Monthly sampling at 5 locations, interpretation 4x per year

$1,300,000

Earthworks Heavy machinery movement Vehicles, buses and cars movement Abstraction of water from the water supply borehole

Decommissioning Monthly sampling at 5 locations, interpretation 4x per year

$48,000

Water Quantity (flows instreams, springs)

Earthworks Heavy machinery movement Vehicles, buses and cars movement Drilling of water supply borehole

Pre-construction Detailed hydrological model and 2x monitoring boreholes in the Limestone (Mine area) Flow meters and stream gauging units x4 Measurement and interpretation monthly and interpretation 4x per year

$400,000

Page 276 301012-02135-EMP-003 Rev 2 : 02 February 17

Page 277: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Aspect Activity Project Phase Mitigation and monitoring measures

Cost Estimate (USD)

Earthworks Heavy machinery movement Vehicles, buses and cars movement Abstraction of water from the water supply borehole

Construction Measurement and interpretation monthly and interpretation 4x per year

$20,000

Operating cement plant Operating power plant Abstraction of water from the water supply borehole

Operation Measurement and interpretation monthly and interpretation 4x per year

$550,000

Earthworks Heavy machinery movement Vehicles, buses and cars movement Abstraction of water from the water supply borehole

Decommissioning Measurement and interpretation monthly and interpretation 4x per year

$20,000

Coastal processes

Earthworks Heavy machinery movement Vehicles, buses and cars movement Construction of MOF Drilling of sea floor Removal of corals

Pre-construction Sediment transport model Setup monitoring reference stations (imagery)

$250,000

Earthworks Heavy machinery movement Vehicles, buses and cars movement Abstraction of water from the water supply borehole

Construction Every 6 months image capture and interpretation

$40,000

Page 277 301012-02135-EMP-003 Rev 2 : 02 February 17

Page 278: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Aspect Activity Project Phase Mitigation and monitoring measures

Cost Estimate (USD)

Operating conveyor belt Operating jetty and MOF Abstraction of water from the water supply borehole

Operation Every 6 months image capture and interpretation

$550,000

Earthworks Heavy machinery movement Vehicles, buses and cars movement

Decommissioning Every 6 months image capture and interpretation

$40,000

Flora Earthworks Heavy machinery movement Vehicles, buses and cars movement Drilling of water supply borehole

Pre-construction Pre-clearance vegetation distribution mapping Post clearance area survey

$80,000

Earthworks Heavy machinery movement Vehicles, buses and cars movement Abstraction of water from the water supply borehole

Construction Post clearance area survey Ongoing capture of clearing area information

$20,000

Operating cement plant Operating power plant Abstraction of water from the water supply borehole

Operation Progressive rehabilitation costs (material and equipment) Post operations vegetation survey Rehabilitation success survey (post closure)

$5,500,000

Earthworks Heavy machinery movement Vehicles, buses and cars movement Abstraction of water from the water supply borehole

Decommissioning Post rehabilitation area survey Ongoing capture of rehabilitation area information

$20,000

Page 278 301012-02135-EMP-003 Rev 2 : 02 February 17

Page 279: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Aspect Activity Project Phase Mitigation and monitoring measures

Cost Estimate (USD)

Fauna Earthworks Heavy machinery movement Vehicles, buses and cars movement Drilling of water supply borehole

Pre-construction Fauna relocation expert – standby for pre- construction duration

$100,000

Earthworks Heavy machinery movement Vehicles, buses and cars movement Abstraction of water from the water supply borehole

Construction Fauna management records as required Annual environmental reporting

$20,000

Operating cement plant Operating power plant Abstraction of water from the water supply borehole

Operation Fauna management records as required Annual environmental reporting

$550,000

Earthworks Heavy machinery movement Vehicles, buses and cars movement Abstraction of water from the water supply borehole

Decommissioning Fauna management records as required Annual environmental reporting

$20,000

Marine Fauna Earthworks Heavy machinery movement Vehicles, buses and cars movement Construction of MOF Drilling of sea floor Removal of corals

Pre-construction Pre-construction baseline Marine Fauna survey (crocodiles, turtles, megafauna) Ongoing capture of fauna records

$150,000

Page 279 301012-02135-EMP-003 Rev 2 : 02 February 17

Page 280: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Aspect Activity Project Phase Mitigation and monitoring measures

Cost Estimate (USD)

Earthworks Heavy machinery movement Vehicles, buses and cars movement Abstraction of water from the water supply borehole

Construction Ongoing capture of fauna records Relocation of fauna encountered during construction

$40,000

Operating conveyor belt Operating jetty and MOF Abstraction of water from the water supply borehole

Operation Ongoing capture of fauna records $550,000

Earthworks Heavy machinery movement Vehicles, buses and cars movement

Decommissioning Ongoing capture of fauna records Relocation of fauna encountered during decommissioning

$40,000

Marine Habitats

Earthworks Heavy machinery movement Vehicles, buses and cars movement Construction of MOF Drilling of sea floor Removal of corals

Pre-construction Pre-construction marine habitat reference site establishment (corals) and reporting

$120,000

Earthworks Heavy machinery movement Vehicles, buses and cars movement Abstraction of water from the water supply borehole

Construction Post-construction marine habitat survey

$120,000

Operating conveyor belt Operating jetty and MOF Abstraction of water from the water supply borehole

Operation 5-yearly survey of marine habitat incl. final survey on completion (11 occurrences)

$1,300,000

Page 280 301012-02135-EMP-003 Rev 2 : 02 February 17

Page 281: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Aspect Activity Project Phase Mitigation and monitoring measures

Cost Estimate (USD)

Earthworks Heavy machinery movement Vehicles, buses and cars movement

Decommissioning Post-decommissioning marine habitat survey

$120,000

Traffic Earthworks Heavy machinery movement Vehicles, buses and cars movement Drilling of water supply borehole

Pre-construction Traffic monitoring equipment (1 unit) Traffic census (1 instance)

$20,000

Earthworks Heavy machinery movement Vehicles, buses and cars movement Abstraction of water from the water supply borehole

Construction Traffic census (1 instance) $10,000

Operating cement plant Operating power plant Abstraction of water from the water supply borehole

Operation Traffic census (5 instance) $50,000

Earthworks Heavy machinery movement Vehicles, buses and cars movement Abstraction of water from the water supply borehole

Decommissioning Traffic census (1 instance) $10,000

Community Clearing of land Relocation and resettlement Earthworks Heavy machinery movement Vehicles, buses and cars movement

Pre-construction Monthly community engagement events Monthly grievances committee review and reporting Community engagement survey (1 instance) Corporate social responsibility support and implementation

$120,000

$250,000

Page 281 301012-02135-EMP-003 Rev 2 : 02 February 17

Page 282: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Aspect Activity Project Phase Mitigation and monitoring measures

Cost Estimate (USD)

Earthworks Heavy machinery movement Vehicles, buses and cars movement

Construction Monthly community engagement events Monthly grievances committee review and reporting Community engagement survey (1 instance) Community awareness programmes Training of local people # development costs in Section 19.1 below

$480,000

Operating cement plant Operating power plant

Operation Annual community engagement events Quarterly grievances committee review and reporting Community engagement survey (1 instance) Community awareness programmes Corporate social responsibility support and implementation Training of local people (over the life of operations – 58 years)# development costs in Section 19.1 below

$1,100,000

Earthworks Heavy machinery movement Vehicles, buses and cars movement

Decommissioning Monthly community engagement events Monthly grievances committee review and reporting Community engagement survey (1 instance) Community awareness programmes Corporate social responsibility support and implementation

$480,000

Total cost mitigation and monitoring implementation # $15,758,000

Page 282 301012-02135-EMP-003 Rev 2 : 02 February 17

Page 283: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

19.1 Infrastructure costs

Item Cost (USD) Waste water treatment plant $ 340,000 Training centre (20 years) $22,000,000 Drainage system (bunds and drains) $ 900,000 PPE $ 20,000 Fire response system $ 840,000 Raised Conveyor system $ 5,000,000 Instrumentation $ 150,000 Water supply borehole and infrastructure $ 120,000 Total – All infrastructure for mitigation $29,370,000

Page 283 301012-02135-EMP-003 Rev 2 : 02 February 17

Page 284: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

20 REVIEW OF THE EMP

The Cement Plant, Jetty and Other Associated Infrastructure EMP will be reviewed at the following key project milestones:

• Completion of the pre-construction phase and additional specialist studies; • Completion of the construction phase; • Award of the Operations contract to incorporate operator-specific information; and • Every 5 years at minimum during Operations phase;

The Cement Plant, Jetty and Other Associated Infrastructure EMP will be reviewed following the events where:

• Equipment or procedural changes result in a positive or negative change to the project environmental and social risks; • Monitoring results indicate that a change to the mitigation and monitoring regime is required to manage the project impacts; • Legislative changes in country require update to the EMP; and • There is a change to the responsibility matrix for EMP implementation.

The review will follow standard QA/QC document management and review processes with the Approver being technically responsible for the content.

The EMP will be reviewed where the changes in the EMP have influenced the following key factors (Section 3):

• Displacement / Resettlement; • Cultural Heritage; • Traffic; • Water; and • Legally responsible person.

Page 284 301012-02135-EMP-003 Rev 2 : 02 February 17

Page 285: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

21 NON-TECHNICAL SUMMARY

21.1 Introduction

TL Cement LDA, a privately-owned company, proposes to construct a new cement manufacturing plant in Baucau Municipality, Timor-Leste. In accordance with Decree Law 05/2011, Environmental Licensing Law (ELL), the TL Cement LDA has submitted an Application for Environmental License for this project to the National Directorate of the Environment (NDE). The Baucau Cement Project will consist of:

1. Cement Plant, Marine Jetty, Conveyor Belt, and associated infrastructure

2. Limestone Mine

The NDE has classified the project as a “Category A” project, and must go through the environmental assessment process, including preparation of an Environmental Impact Statement (EIS).

21.2 Purpose of this document

This document is a Non-Technical Summary (NTS) of the EIS for the Cement Plant, Marine Jetty, Conveyor Belt and associated infrastructure. This NTS presents the assessment of the potential environmental and social impacts, proposed control measures to mitigate and manage the impacts, and remaining impacts of the project.

21.3 Benefits of the project

The benefits of the project include direct employment with 1000 permanent jobs expected during operations. The project aims to develop local capacity and will develop a training centre. Other benefits include indirect employment to local community members, through the multiplier effect due to downstream socio-economic benefits and consequent improvement in the living conditions of local population in the project area. It is estimated that at least 2000 more jobs can be created through indirect activities during operations with local business opportunity creation in supplying goods and services to TL Cement and its employees.

The location of the Baucau Cement Project and its components can be seen in Figure 21.

Page 285 301012-02135-EMP-003 Rev 2 : 02 February 17

Page 286: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Figure 21: Location of Baucau Cement Project components

Page 286 301012-02135-EMP-003 Rev 2 : 02 February 17

Page 287: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

21.4 Key Project Characteristics

The key project characteristics are listed in Table 2.

Table 2: Summary of Baucau Cement Project Characteristics

Element Description

Project life 50 years at full production capacity

Investment $400 million USD

Largest industrial project undertaken in Timor-Leste to date

Annual production

1.65 million tons per annum (mtpa) of Portland cement clinker (main component of cement (Figure 22)):

• 0.5 mtpa will be combined with the other required components to make Ordinary Portland Cement (a complete cement mixture (Figure 23)) to be sold locally in Timor Leste and Australia (~70 % in Timor-Leste and ~30% to Australia)

• 1.15 mtpa will be packaged as Portland cement clinker and exported by ships to Australia

Cement types produced

Figure 22: Portland cement clinker

Figure 23: Ordinary Portland cement

List of major project components

Cement processing plant (650 m x 400 m)

• Including a construction camp and worker residential area (35 containers of 40 feet in length. 1 office unit, one cafeteria unit, 5 accommodation units each with 24 rooms (120 rooms in total).

Fully Enclosed Pipe Conveyor Belt (1.5 km long)

Marine Jetty (500 m long)

Page 287 301012-02135-EMP-003 Rev 2 : 02 February 17

Page 288: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Area of disturbance

Cement Processing Plant + Captive Power Plant + Camp – 80 ha- Note all in one compound

Marine Jetty + pipe conveyor - 1.5 ha

Power Supply 30 Mega Watt Biomes and Recycle Power Generation (clean coal) plant

Water Supply Groundwater from borewells at the Uaidei River

• 0.35 ML/day for construction

• 3.15 ML/day for operation

Number of jobs 3000 jobs during peak of construction

1000 permanent jobs during operations

21.5 Operations

When in operation, limestone will be taken to the Cement Plant for processing. Some other cement components will be shipped to the Marine Jetty and put on a fully enclosed Pipe Conveyor Belt and taken to the Cement Plant to be processed along with the limestone and turned into Portland cement clinker.

Portland cement clinker is small lumps that are the basic ingredient of cement (Figure 22). The Portland cement clinker will then be taken by the same full enclosed Pipe Conveyor Belt from the cement plant to the Port where it will be loaded onto ships from a Marine Jetty.

A similar example of a conveyor and marine jetty can be seen in Figure 24: The Baucau Cement Plant Project once in operation

.

Page 288 301012-02135-EMP-003 Rev 2 : 02 February 17

Page 289: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Figure 24: The Baucau Cement Plant Project once in operation

Page 289 301012-02135-EMP-003 Rev 2 : 02 February 17

Page 290: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

21.6 Project Phases

The project will have four phases: Pre-construction (18 months), Construction (2 years), Operations (over 35 - 50 years) and Decommissioning (5 years). A summary of the activities to be undertaken during each phase and potential impacts are presented in Table 3. In addition, the potential impacts that could occur as a result of the activities during each phase have been outlined below. Of these, key impacts have been identified as either a ‘Medium’ or ‘High’ risk, and have been discussed further in Section 21.7, along with identified mitigation measures to manage and reduce the impacts.

Page 290 301012-02135-EMP-003 Rev 2 : 02 February 17

Page 291: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Table 3: Summary of Baucau Cement Project phase characteristics and potential impacts

Phase Activities Potential Impacts (risk)

Pre-construction

(Duration of approximately 18 months)

• Clearing of fence lines & Installing fences

• Clearing of access roads internal to the project area

• Establishment of Laydown areas and preliminary office infrastructure such as portable toilets and shipping containers for storage

• Relocation of people and animals within the project area

• Exploratory water source drilling and installation of water supply wells.

• Installation of power supply infrastructure corridors via clearing, excavation and pegging

• Geological studies including bore drilling and pit surveys

• Weir installation in streams

• Establishment of exclusion zones around fishing areas, boreholes and springs (known impact, appropriation of natural asset)

• Construction of material offloading facility (construction jetty)

• Clearing of natural vegetation (Low)

• Displacement of people (Medium to High)

• Exclusion of people from fishing grounds, boreholes and springs (Low)

• Increased traffic and transport (Low)

• Increased noise and increase in air pollution (Low)

• Disturbance of heritage sites (Low)

• Increased groundwater usage (Low)

• Clearing of coral (Low)

• Disturbance of cultural heritage at the mine site (Medium to High)

Construction

(Duration of approximately 2 years)

• Clearing of the Cement site/area - Excavation, Piling, Pouring of concrete foundations and permanent establishment of accommodation, offices and workshops

• Clearing of natural vegetation (Low)

• Displacement of people (High)

• Visual impact (High)

Page 291 301012-02135-EMP-003 Rev 2 : 02 February 17

Page 292: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

• Building structures in concrete and steel for cement equipment

• Developing internal cement plant roads and drainage

• Establishment of bunds, hauling roads, drainage areas and mine stope markers ahead of mining commencing

• Installation of cement plant equipment

• Construction of power plant

• Installation of conveyor system

• Piling and construction of jetty

• Construction of internal access roads and haul roads

• Discharge into landfill – solid and liquid waste

• Increased noise, increased air pollution (Low)

• Increased traffic and transport (Low)

• Increased light and heavy vehicle interaction with pedestrians and motorbikes (Medium)

• Increased groundwater usage (Low)

• Increase in waste (Low)

• Clearing of coral (Low)

Operation

Duration of approximately 35-50 years)

• Operating conveyor transporting material to/from Jetty

• Operational cement plant

• Operational power plant operational

• Operational jetty and MOF

• Maintenance clearing within the plant site boundary (e.g. tree lopping for power lines)

• Discharge to landfill – solid waste

• Increased traffic and transport (Medium)

• Increased noise, increased air pollution (Low)

• Disturbance to community from blasting (Medium)

• Increased light and heavy vehicle interaction with pedestrians and motorbikes (Medium)

Page 292 301012-02135-EMP-003 Rev 2 : 02 February 17

Page 293: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

• Increased groundwater usage (Medium)

• Increased pollution (waste water outfall) (Low)

De-Commissioning

(Duration of approximately 5 year)

• Rehabilitation • Reduction in employment levels

• Continued employment during rehabilitation and closure of the mine

• Negative impact on local economy

• Rehabilitated landscape-It is possible to create tourism venue during rehabilitation based on local community needs

Page 293 301012-02135-EMP-003 Rev 2 : 02 February 17

Page 294: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

21.7 Key Potential Impacts and Mitigation Measures

There are a number of aspects to the project that have the potential to cause 'environmental and social impacts during different phases of the project. Of these, key aspects and their impacts have been identified to be a ‘Medium’ or ‘High’ risk. These key aspects, along with mitigation measures identified to manage and reduce the impacts, and monitoring and reporting to ensure compliance, have been outlined in below.

Page 294 301012-02135-EMP-003 Rev 2 : 02 February 17

Page 295: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Stage Potential Key Impact Mitigation Measure Responsibility Parameter to be measured Frequency Cost of Mitigation Measure USD

Pre Construction

Clearing of vegetation

Limit area to be cleared TL Cement Construction contractor

Check that clearing is within the boundary

Daily during clearing activities Compensation per the Resettlement Plan : $15,000 estimate

Monitoring and weed eradication costs: $5.6M

Fauna relocation and monitoring, re-introduction and elimination of pests: $670k

Rehabilitation costs (Labour and materials): $?

Air quality and dust Dust suppression techniques include water spraying and enclosing equipment

TL Cement Construction contractor

PM10 and PM2.5 at 3 monitoring stations

Measurements every 6 months Compensation per the Resettlement Plan : $15,000 estimate

Dust suppression sprayer and labour: $? 2000/month

Cost of illness and loss of productivity: $?

Noise Noise limitation techniques include aprons and enclosing

TL Cement Construction

Noise Levels at 3 monitoring stations

Measurements every 6 months Compensation per the Resettlement Plan : $15,000

Page 295 301012-02135-EMP-003 Rev 2 : 02 February 17

Page 296: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Stage Potential Key Impact Mitigation Measure Responsibility Parameter to be measured Frequency Cost of Mitigation Measure USD

equipment

contractor estimate

Monitoring costs: $580k

Cost of illness and loss of productivity: $?

Water quality and quantity

Rehabilitation in the event of a spill or contamination event

Spill and contamination mitigation measures

TL Cement Construction contractor

Flow meters / stream gauges at the Bucoli River (1.6km west) and at Uaimatabai, Uaisa and Waino springs.

Water quality and quantity measurements at monitoring boreholes, key spring receptors at Waiono, Uaimatabai and Uaisa.

Every 6 months

Monthly water quality and quantity measurements

Water Quality Monitoring costs: $1,4M

Water Quantity Monitoring costs : $970k

Rehabilitation costs in the event of a spill: $?

Construction

Air quality and dust Dust suppression techniques include water spraying and enclosing equipment

TL Cement Construction contractor

PM10 and PM2.5 at 3 monitoring stations

Measurements every 6 months Dust suppression sprayer and labour: $? 2000/month

Cost of illness and loss of productivity: $?

Noise Noise limitation techniques include aprons and enclosing equipment

TL Cement Construction contractor

Noise Levels at 3 monitoring stations

Measurements every 6 months Monitoring costs: $580k

Cost of illness and loss of productivity: $?

Page 296 301012-02135-EMP-003 Rev 2 : 02 February 17

Page 297: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Stage Potential Key Impact Mitigation Measure Responsibility Parameter to be measured Frequency Cost of Mitigation Measure USD

Water quality and quantity

Rehabilitation in the event of a spill or contamination event

Spill and contamination mitigation measures

TL Cement Construction contractor

Flow meters / stream gauges at the Bucoli River (1.6km west) and at Uaimatabai, Uaisa and Waino springs.

Measurements at monitoring boreholes, key spring receptors at Waiono, Uaimatabai and Uaisa.

Every 6 months

Monthly water quality and quantity measurements

Water Quality Monitoring costs: $1,4M

Water Quantity Monitoring costs : $970k

Rehabilitation costs in the event of a spill: $?

Operation

Air quality and dust Dust suppression techniques include water spraying and enclosing equipment

TL Cement Operator PM10 and PM2.5 at 3 monitoring stations

Measurements every 12 months

Dust suppression sprayer and labour: $? 2000/month

Cost of illness and loss of productivity: $?

Noise Noise limitation techniques include aprons and enclosing equipment

TL Cement Operator Noise Levels at 3 monitoring stations

Measurements every 6 months Monitoring costs: $580k

Cost of illness and loss of productivity: $?

Water quality and quantity

Rehabilitation in the event of a spill or contamination event

Spill and contamination

TL Cement Operator Flow meters / stream gauges at the Bucoli River (1.6km west) and at Uaimatabai, Uaisa and Waino

Every 6 months

Water Quality Monitoring costs: $1,4M

Water Quantity Monitoring Page 297 301012-02135-EMP-003 Rev 2 : 02 February 17

Page 298: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Stage Potential Key Impact Mitigation Measure Responsibility Parameter to be measured Frequency Cost of Mitigation Measure USD

mitigation measures springs.

Measurements at monitoring boreholes, key spring receptors at Waiono, Uaimatabai and Uaisa.

Monthly water quality and quantity measurements

costs : $970k

Rehabilitation costs in the event of a spill: $?

Decommissioning

Air quality and dust Dust suppression techniques include water spraying and enclosing equipment

TL Cement Operator PM10 and PM2.5 at 3 monitoring stations

Measurements every 6 months Dust suppression sprayer and labour: $? 2000/month

Noise Noise limitation techniques include aprons and enclosing equipment

TL Cement Operator Noise Levels at 3 monitoring stations

Measurements every 6 months Compensation per the Resettlement Plan : $15,000 estimate

Monitoring costs: $580k

Cost of illness and loss of productivity: $?

Water quality and quantity

Rehabilitation in the event of a spill or contamination event

Spill and contamination mitigation measures

TL Cement Operator Flow meters / stream gauges at the Bucoli River (1.6km west) and at Uaimatabai, Uaisa and Waino springs.

Monthly water quality and quantity

Every 6 months

Monthly water quality and

Water Quality Monitoring costs: $1,4M

Water Quantity Monitoring costs : $970k

Rehabilitation costs in the Page 298 301012-02135-EMP-003 Rev 2 : 02 February 17

Page 299: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Stage Potential Key Impact Mitigation Measure Responsibility Parameter to be measured Frequency Cost of Mitigation Measure USD

measurements at monitoring boreholes, key spring receptors at Waiono, Uaimatabai and Uaisa.

quantity measurements event of a spill: $?

Table 4: Key Potential Impacts, Mitigation Measures and Monitoring and Reporting

Page 299 301012-02135-EMP-003 Rev 2 : 02 February 17

Page 300: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

21.8 Stakeholder Engagement Process

This project has involved consultation with people who may be affected by the project and other project stakeholders. This includes the public, such as those who will be directly affected, women and vulnerable groups. As can be seen by Figure 25, public engagement consultation is a continuous process throughout the EIA process and has already been initiated.

The public consultation process for the environmental assessment is being carried out in accordance with the Draft Ministerial Diploma for the “Regulation on the Public Consultation Procedures and Requirements during the Environmental Assessment Process” dated 22 April 2014.

Figure 25: Stakeholder Engagement and Consultation

The stakeholder consultation list to date is shown in Table 5.

Table 5: Consultation Summary

Stakeholder

Government Ministries

Ministry of Commerce, Industry, and Environment

• National Directorate for Environment

Ministry of Petroleum and Mineral Resources

• National Directorate of Mines and Minerals

• Institute of Petroleum and Geology

Ministry of Justice

• National Directorate of Land, Property and Cadastral Services

Ministry of Finance

Page 300 301012-02135-EMP-003Rev 1 : 02 February 17

Page 301: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Ministry of Planning and Strategic Investment

Ministry of Public Works, Transport and Communications

• Directorate of Roads, Bridges, and Flood Control

• Directorate of Ports/APORTIL

Ministry of Tourism, Arts and Culture

State Secretariat of Arts and Culture

Municipality (District) Government

Baucau Municipality (formerly Baucau District Administration)

Baucau Administrative Post (formerly Baucau Sub-District Administration)

Baucau Municipality Police District

Baucau Municipality Directorate of Land, Property and Cadastral Services

Baucau Municipality Directorate of Environment

Vemasse Administrative Post

Local Government

Suco Council Tirilolo

Suco Council Triloca

Suco Council Vemasse-Vila

Suco Council Caibada

Suco Council Bahu

Suco Council Wailili

Suco Council Bucoli

Suco Council Fatumaca

TL Cement and Worley Parsons conducted follow up consultation in the local community during site visits in February 2015 and May 2015.

These meetings were attended by the following community members:

• Chefe Suco Tirilolo: Ricardo Ernesto Belo (RB)

• Chief of Community Police in Suco Tirilolo: Norberta Belo (NB)

• Chefe Aldeia Lialailesu: Cipriano Belo (CB)

• Chefe Aldeia Parlamentu: Manuel Belo (MB)

• Chief of Traditional Practice (Lia-Nain): Duarte Belo (DUB)

• Secretary of Suco Tirilolo: Zeca Belo (ZB)

Representative of youth of Suco Tirilolo: Damião Belo (DB)

Local Communities

Chefes de Aldeia

Lia-Nain

Page 301 301012-02135-EMP-003Rev 1 : 02 February 17

Page 302: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Local Youth Organizations

Local Women’s Organizations

Local Fishermen’s Organization

Baucau Parish

Civil Society/Local NGOs

Lao Hamutuk

Luta Hamutuk

Haburas

Rede ba Rai

Belun

Kapeliwa

Other Organizations

International Finance Corporation

Conservation International

BESIK (Bee, Saneamentu no Ijiene iha Komunidade) Rural Water Program

End of Non Technical Summary

Page 302 301012-02135-EMP-003Rev 1 : 02 February 17

Page 303: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

22 REFERENCES

Advisian (2016). Baucau Cement Project: Surface Water Impact Assessment Report. Unpublished report for WorleyParsons, Feb 2016.

BBS (2015a). Air Quality Impact Assessment study of Clinker Cement Project Baucau – Timor-Leste. Final Draft Report No: 15.3380-DR-002 Rev B, Oct 2015.

BBS (2015b) Noise Impact Assessment study of Clinker Cement Project Baucau – Timor-Leste. Final Draft Report No: 15.3380-FDR-002 Rev B, Oct 2015.

BBS (2015c). Traffic Impact Assessment Study of Clinker Cement Project Baucau-Timor-Leste. Final Draft Report No:15.3380-FD-002, Rev B, Oct 2015.

BBS (2015d). Social Impact Assessment Study of Clinker Cement Project Baucau – Timor-Leste. Final Draft Report No: 15.3380-DR-002, Rev. C, Oct 2015.

BOM (2015). What are El Niño and La Niña events? Online publication of the Australian Bureau of Meteorology (BOM) [Accessed 3 Dec 2015] http://www.bom.gov.au/climate/enso/history/ln-2010-12/ENSO-what.shtml

CDU (2009) The Timor-Leste Coastal / Marine Habitat Mapping for Tourism and Fisheries Development Project. A joint research project by Charles Darwin University, Northern Territory Government, Republica Democratica de Timor-Leste, Australian National University, the Australian Government and the Australian Institute of Marine Science. http://www.cdu.edu.au/sites/default/files/research/docs/36091-executive-summary-secured-final.pdf

Conservation International (2013). A Marine Rapid Assessment (MRAP) of Timor-Leste, 14-23 August 2012. Report prepared by Conservation International, Edited by MV Erdmann and C Mohan.

Cowie, I. 2006. Assessment of floristic values of the proposed Jaco-Tutuala-Lore National Park, TimorLeste (East Timor). . Northern Territory Herbarium, Darwin.

CSIRO (2010). Climate change in Timor-Leste. A brief overview on future climate projections. Prepared by the CSIRO.

CSIRO (2011). Current and future climate of Timor-Leste, International Climate Change Adaption Initiative. A report for the Pacific Climate Change Science Program partners [Accessed online 3 December 2015] http://www.pacificclimatechangescience.org/wp-content/uploads/2013/06/5_PCCSP_East_Timor_8pp.pdf

Dethmers K, Chatto R, Meekan M, Amaral A, de Cunha C, de Carvalho N, Edyvane K (2012) Marine Megafauna Surveys in Timor Leste Coastal-Marine Habitat Mapping, Tourism and Fisheries Development Project. Ministry of Agriculture & Fisheries, Government of Timor Leste.

DotE (2015) Lead. Online database for the Australian Department of the Environment. [Accessed 10 December 2015] https://www.environment.gov.au/protection/chemicals-management/lead

Page 303 301012-02135-EMP-003Rev 1 : 02 February 17

Page 304: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Edyvane K, McWilliam A, Quintas J, Turner A, Penny S, Teixeira I, Pereira C, Tibirica Y, Birtles A. (2009) Coastal and Marine Ecotourism Values, Issues & Opportunities on the North Coast of Timor Leste – Final Report. Ministry of Agriculture and Fisheries, National Directorate of Tourism, Government of Timor Leste.

EPA (2015a). National Ambient Air Quality Standards (NAAQS). Online database for the US Environmental Protection Authority. [Accessed 9 December 2015, last updated 10 July 2015] http://www3.epa.gov/ttn/naaqs/criteria.html

EPA (2015b) Particulate Matter. Online database for the US Environmental Protection Agency. [Accessed 9 December 2015. Last updated 9 November 2015] http://www3.epa.gov/pm/

EPA (2015c) Nitrogen Oxides (NOx) Control Regulations. Online database for the US Enironmental Protection Authority [Accessed 9 December 2015, last updated 12 September 2015] http://www3.epa.gov/region1/airquality/nox.html

EMEP-MSC-W (1995) Status of the development of the multilayer Eulerian model: a) Model description; b) A new method of calculating mixing heights; c) Model results for sulphur transport and deposition in Europe for 1992 in the 50 km grid. http://www.atmos-chem-phys.net/12/7825/2012/acp-12-7825-2012.pdf

European Commission (2015) Air Quality Standards. Website on Environmental Air Quality Standards. Available at: http://ec.europa.eu/environment/air/quality/standards.htm. Accessed 13 October 2015

Fabricius KE & Alderslade P (2001) Soft Corals and Sea Fans: A comprehensive guide to the tropical shallow water genera of the central-west Pacific, the Indian Ocean and the Red Sea. Australian Institute of Marine Science, Townsville. 264 pp. ISBN: 0 642 322104.

FAO (2015) Food and Agriculture Organisation (FAO) of the United Nations. Fishery and Aquaculture Country Profiles (The Democratic Republic of Timor-Leste). Available online at: http://www.fao.org/fishery/facp/TLS/en#CountrySector-PostHarvest . Accessed 13 October 2015

Goines, L and Hagler, L (2007). Noise Pollution: A Modern Plague. Southern Medical Journal, vol. 100, issue 3, pgs 287-294 [http://www.medscape.com/viewarticle/554566_3]

Grantham HS, Watson JEM, Mendes M, Santana F, Fernandez G, Pinto P, Ribeiro LM and da Cunha Barreto C (2010) National Ecological Gap Assessment for Timor-Leste 2010. CNRM Solutions report for the Department of Protected Areas and National Parks of Timor-Leste, National Directorate of Forestry, Ministry of Agriculture and Fisheries. [file:///C:/Users/katherine.swain/Downloads/tl_nega_final%20(2).pdf]

Holtec. 2015a. Mine Closure Plan for Bucoli Limestone Deposit – Block I-1, Baucau District, Timor-Leste. September 2015.

Jocson, J. M. U., Jenson, J. W. & Contractor, D. N. (2002) Recharge and aquifer response: northern Guam lens aquifer, Guam, Mariana Islands. J. Hydrol. 260, 231–254.

MAFF (2004) Ministry of Agriculture, Forestry and Fisheries website. [Accessed 11 December 2015, last updated 2004] http://gov.east-timor.org/MAFF/index.htm

Page 304 301012-02135-EMP-003Rev 1 : 02 February 17

Page 305: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Monk KA, Y De Fretes, and G Reksodinharjo-Lilley (1997). The Ecology of Nusa Tenggara and Maluku. Periplus Editions, Singapore.

Oliveira NV (2015). Baucau Cement Plant, Assessing the Impact on Archaelogical and Cultural Heritage Sites. Unpublished report for WorleyParsons, August 2015

Rong Y, Park J, Duggan D, Mahdyiar M and Bazzuro P (2012). Probabilistic Seismic Hazard Assessment for the Pacific Island Counties. 15 WCEE, Lisboa 2012 [http://www.iitk.ac.in/nicee/wcee/article/WCEE2012_2521.pdf]

Royal Hakoning DHV (2015). Report on TL Cement Jetty Facilities, for TL Cement LDA, Ref. No. M&WSA1071R001F01, August 2015.

The World Bank (2015). Reducing the Risk of Disasters and Climate Variability in the Pacific Islands: Timor-Leste Country Assessment. A Report by the Global Facility for Disaster Reduction and Recovery, The World Bank and SOPAC. Washington DC [Accessed 4 December 2015] http://siteresources.worldbank.org/INTPACIFICISLANDS/Resources/TIMOR_LESTE_ASSESSMENT.pdf

Trainor, C. R. 2010. Timor’s fauna: the influence of scale, history and land-use on faunal patterning. . Faculty of Education, Health and Science. Charles Darwin University, Darwin.

Trainor, C. & Easton, B. (2015). Baucau Cement Clinker Plant Vegetation and Fauna Survey Report. Prepared for WorleyParsons, August 2015.

Trainor, C. (2015) Baucau Cement Clinker Plant, Mine I-2 and II-1 Desktop study of vegetation and fauna. Report to WorleyParsons, September 2015.

UNDP (2010). Disaster Risk and Hazard Map Analysis for Timor-Leste: An overview of existing risk maps. Disaster Risk Management Institutional and Operations Systems Development in Timor-Leste Project, UNDP. United Nations Disaster Planning, published on the Global Risk Information Platform, January 2010 [http://www.gripweb.org/gripweb/sites/default/files/Hazard_and_Risk_Map_Analysis_for_Timor_Jan'10_Ver_4_(3).pdf]

US DOT (2014). Lane Width. Mitigation Strategies for Design Exceptions. Website for the US Department of Transport, Federal Highway Administration. [Accessed 21 December 2015, last updated 15 October 2014] http://safety.fhwa.dot.gov/geometric/pubs/mitigationstrategies/chapter3/3_lanewidth.cfm

Valdivieso L M (2001). East Timor: Macroeconomic Management on the Road to Independence but cant work it out. See here http://www.highbeam.com/doc/1G1-73849042.html.

WHO (1999) Guidelines on Community Noise. A publication of the World Health Organization [http://www.who.int/docstore/peh/noise/guidelines2.html]

WHO (2005) WHO Air Quality Guidelines for Particulate Matter, Ozone, Nitrogen Dioxide and Sulphur Dioxide, Global update for the World Health Organization, 2005

Wikramanayake E, E Dinerstein, C J Loucks, D Olson, J Morrison, J Lamoreux, M McKnight and P Hedao. (2002a). Terrestrial Ecoregions of the Indo-Pacific: A Conservation Assessment. Island Press.

Page 305 301012-02135-EMP-003Rev 1 : 02 February 17

Page 306: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

Wikramanayake E, E Dinerstein, G. Loucks, D. Olson, J. Morrison, J. Lamoreux, M. McKnight, and P.

Hedao. 2002b. Ecoregions in ascendance: reply to Jepson and Whittaker. Conservation Biology

16:238-243.

WorleyParsons (2015a) Coastal Processes Desktop Study - Marine Facilities, Unpublished report 301012-02135 – CS-REP-0001) for TL Cement LDA, 23 September 2015

WorleyParsons (2015b), Baucau Cement Plant Marine Jetty, Benthic Habitat Survey and Fisheries Assessment Report. Unpublished report for WorleyParsons, October 2015.

WorleyParsons (2015c) Timor-Leste Cement Project : Preliminary Groundwater Environmental Impact Assessment.

Page 306 301012-02135-EMP-003Rev 1 : 02 February 17

Page 307: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

23 ACRONYMS / ABBREVIATIONS

$ United States dollar

% Percentage

< Less than

µg/L Microgram per litre

µg/m3 Micrograms per cubic meter

µg/m3 Micrograms per cubic meter

ADB Asian Development Bank

AWS Automated Weather Station

BAP Biodiversity Action Plan

BAT Best Available Technologies

CEMP Construction Environmental Management Plan

CFB Circulating Fluidized Bed

CGM Complaints and Grievances Mechanism

CHMP Cultural Heritage Management Plan

CO Carbon monoxide

CPIX Consumer Price Index

dB Decibels

DBRFC Directorate of Bridges, Roads, and Flood Control

DLPCS Directorate of Land, Property and Cadastral Services

DWRQC Directorate of Water Resources and Quality Control

EA Environmental Assessment

EBL Environment Basic Law

EIS Environmental Impact Statement

ELL Environmental Licensing Law

EMF Environmental Management Framework

Page 307 301012-02135-EMP-003Rev 1 : 02 February 17

Page 308: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

EMP Environmental Management Plan

EMS Environmental Management System

ERP Emergency Response Plan

EP Emergency Plan

GPS Global positioning satellite

ha Hectares

hr hour

HSE Health, Safety and Environment

IFC International Finance Corporation

IAAQS International Ambient Air Quality Standards

IPG Institute of Petroleum and Geology

km Kilometre

m/s Metres per seconds

mg/L Milligram per litre

ML Mega liters

ml Millilitres

MOF Materials Offloading Facility

MOPW Ministry of Public Works

MOU Memorandum of Understanding

Mtpa Million tonnes per annum

MW Megawatt

N/A Not Applicable

NDPCEI National Directorate for Pollution Control and Environmental Impact

NGOs Non-Government Organisations

NO2 Nitrogen dioxide

OEMP Operational Environmental Management Plan

PM10 and Particulate matter

Page 308 301012-02135-EMP-003Rev 1 : 02 February 17

Page 309: Baucau Cement Project - La'o Hamutuk

TL CEMENT, LDA BAUCAU CEMENT PROJECT CEMENT PLANT, JETTY AND OTHER ASSOCIATED INFRASTRUCTURE ENVIRONMENTAL MANAGEMENT PLAN

PM2.5

PPE Personal Protective Equipment

ppm Part per million

RDTL Republic Democratic of Timor-Leste

SDS Safety Data Sheet

SEP Stakeholder Engagement Plan

SO2 Sulphur dioxide

UNTAET United Nations Transitional Administration in East Timor

USD United States Dollar

WHO World Health Organisation

Page 309 301012-02135-EMP-003Rev 1 : 02 February 17