ANALYSIS OF RATES Page - 1 ITEM DESCRIPTION : QUANTITY ANALYSED : 1 NUMBER Sr. No. Particulars Quantity Rate Unit Amount 1 Preliminaries 1.00 95,000.00 ITEM 95,000.00 2 Excavation 50.02 30.00 CUM 1,500.72 3 Backfilling 25.96 25.00 CUM 649.10 4 Cartaway 24.06 25.00 CUM 601.50 5 Road Base 250mm thk 6.76 150.00 CUM 1,014.00 6 Plain Cement Concrete 2.70 550.00 CUM 1,485.00 7 Polythene sheet 27.04 5.00 SQM 135.20 8 Anti termite 66.00 5.00 SQM 330.00 9 Sub structure water proofing 127.40 150.00 SQM 19,110.00 10 Raft 12.50 550.00 CUM 6,875.00 11 RCC walls 4.00 550.00 CUM 2,200.00 12 Grade Slab 2.40 550.00 CUM 1,320.00 13 Columns 10.80 500.00 CUM 5,400.00 14 Beam 2.88 500.00 CUM 1,440.00 15 Slab Roof 4.00 500.00 CUM 2,000.00 16 Parapet 2.40 500.00 CUM 1,200.00 17 Formworks 217.60 85.00 SQM 18,496.00 18 Steel Reinforcement bars 5.85 4,500.00 TONNE 26,311.50 19 Roof Waterproofing 16.00 250.00 SQM 4,000.00 20 250 mm Thermal Block 62.00 200.00 SQM 12,400.00 21 Internal Plastering 64.00 35.00 SQM 2,240.00 22 External Plastering 62.00 45.00 SQM 2,790.00 23 Wall Tiles 64.00 200.00 SQM 12,800.00 24 Flooring alkali resistant tile 16.00 200.00 SQM 3,200.00 25 Ceiling chemical resistant paint 16.00 100.00 SQM 1,600.00 26 External Paint 110.00 90.00 SQM 9,900.00 27 Door Aluminium Louvered 1.00 9,000.00 NOS 9,000.00 28 Exhaust Fan 2.00 7,000.00 NOS 14,000.00 29 Light 6.00 1,000.00 NOS 6,000.00 30 Power 4.00 750.00 NOS 3,000.00 31 Wash Basin 1.00 3,500.00 NOS 3,500.00 32 Eyewash 1.00 6,000.00 NOS 6,000.00 33 DB 1.00 15,000.00 NOS 15,000.00 34 Neutralisation Pit 1.00 20,000.00 NOS 20,000.00 35 Fire fighting ( Clean Agent) 1.00 100,000.00 ITEM 100,000.00 - 410,498.02 TOTAL 410,498.02 Therefore the rate works out to Dirhams 410,498.02 PER NOS Therefore for 6 NOS 2,462,988.12 DHS Construction of Battery Room 4x4 m .

description

Estimate for Battery Room in Substation

Transcript of Battery Room Estimate

ANALYSIS OF RATES

Page - 1

ITEM DESCRIPTION :

QUANTITY ANALYSED : 1 NUMBER

Sr. No. Particulars Quantity Rate Unit Amount

1 Preliminaries 1.00 95,000.00 ITEM 95,000.00 2 Excavation 50.02 30.00 CUM 1,500.72 3 Backfilling 25.96 25.00 CUM 649.10 4 Cartaway 24.06 25.00 CUM 601.50 5 Road Base 250mm thk 6.76 150.00 CUM 1,014.00 6 Plain Cement Concrete 2.70 550.00 CUM 1,485.00 7 Polythene sheet 27.04 5.00 SQM 135.20 8 Anti termite 66.00 5.00 SQM 330.00 9 Sub structure water proofing 127.40 150.00 SQM 19,110.00

10 Raft 12.50 550.00 CUM 6,875.00 11 RCC walls 4.00 550.00 CUM 2,200.00 12 Grade Slab 2.40 550.00 CUM 1,320.00 13 Columns 10.80 500.00 CUM 5,400.00 14 Beam 2.88 500.00 CUM 1,440.00 15 Slab Roof 4.00 500.00 CUM 2,000.00 16 Parapet 2.40 500.00 CUM 1,200.00 17 Formworks 217.60 85.00 SQM 18,496.00 18 Steel Reinforcement bars 5.85 4,500.00 TONNE 26,311.50 19 Roof Waterproofing 16.00 250.00 SQM 4,000.00 20 250 mm Thermal Block 62.00 200.00 SQM 12,400.00 21 Internal Plastering 64.00 35.00 SQM 2,240.00 22 External Plastering 62.00 45.00 SQM 2,790.00 23 Wall Tiles 64.00 200.00 SQM 12,800.00 24 Flooring alkali resistant tile 16.00 200.00 SQM 3,200.00 25 Ceiling chemical resistant paint 16.00 100.00 SQM 1,600.00 26 External Paint 110.00 90.00 SQM 9,900.00 27 Door Aluminium Louvered 1.00 9,000.00 NOS 9,000.00 28 Exhaust Fan 2.00 7,000.00 NOS 14,000.00 29 Light 6.00 1,000.00 NOS 6,000.00 30 Power 4.00 750.00 NOS 3,000.00 31 Wash Basin 1.00 3,500.00 NOS 3,500.00 32 Eyewash 1.00 6,000.00 NOS 6,000.00 33 DB 1.00 15,000.00 NOS 15,000.00 34 Neutralisation Pit 1.00 20,000.00 NOS 20,000.00 35 Fire fighting ( Clean Agent) 1.00 100,000.00 ITEM 100,000.00

-

410,498.02

TOTAL 410,498.02

Therefore the rate works out to Dirhams 410,498.02 PER NOS

Therefore for 6 NOS 2,462,988.12 DHS

Construction of Battery Room 4x4 m .