Batesville High School Batesville Middle School Master Plan January 21, 2019

Transcript of Batesville High School Batesville Middle School Master Plan · 1/21/2019  · 2011 ARTS 2011 ITE...

Page 1: Batesville High School Batesville Middle School Master Plan · 1/21/2019  · 2011 ARTS 2011 ITE 1998 Academic Wing 2011 LABS BHS Master Plan Age of Construction Non-Colored Areas

Batesville High SchoolBatesville Middle School

Master PlanJanuary 21, 2019

Page 2: Batesville High School Batesville Middle School Master Plan · 1/21/2019  · 2011 ARTS 2011 ITE 1998 Academic Wing 2011 LABS BHS Master Plan Age of Construction Non-Colored Areas

2012 Admin/Guidance.

1998 Academic Wing

1998 Music

Non-Colored Areas are Original 1967 Construction

BHS Master PlanAge of Construction

2

2013 Finishes

``

2017 SAC (not shown)

N

2013 FINISHES

Page 3: Batesville High School Batesville Middle School Master Plan · 1/21/2019  · 2011 ARTS 2011 ITE 1998 Academic Wing 2011 LABS BHS Master Plan Age of Construction Non-Colored Areas

2011ARTS

2011ITE

1998 Academic Wing

2011LABS

BHS Master PlanAge of Construction

Non-Colored Areas are Orig. 1967 Construction

3

2017 SAC (not shown)

N

2013 FINISHES

Page 4: Batesville High School Batesville Middle School Master Plan · 1/21/2019  · 2011 ARTS 2011 ITE 1998 Academic Wing 2011 LABS BHS Master Plan Age of Construction Non-Colored Areas

First Floor

BHS Master Plan

4

Must Priority Scope: Tier 1

Door Monitoring/Security New Mechanical Controls throughoutSelective HVAC Equipment Replacement

N

Page 5: Batesville High School Batesville Middle School Master Plan · 1/21/2019  · 2011 ARTS 2011 ITE 1998 Academic Wing 2011 LABS BHS Master Plan Age of Construction Non-Colored Areas

Must Priority Scope: Tier 1

Second Floor

BHS Master Plan

5

N

Page 6: Batesville High School Batesville Middle School Master Plan · 1/21/2019  · 2011 ARTS 2011 ITE 1998 Academic Wing 2011 LABS BHS Master Plan Age of Construction Non-Colored Areas

Re-Roof

Auditorium & Student CommonsRoof is 30+ yrs. of Age

Original Academic Area Roof is 30+ yrs. of Age

BHS Master Plan

6

Must Priority Scope: Tier 1

N

Page 7: Batesville High School Batesville Middle School Master Plan · 1/21/2019  · 2011 ARTS 2011 ITE 1998 Academic Wing 2011 LABS BHS Master Plan Age of Construction Non-Colored Areas

BHS Master Plan

Remodel 1998 Finishes and open up for flexible use and connection to Student Commons

Cafeteria

7

Must Priority Scope: Tier 1

N

Page 8: Batesville High School Batesville Middle School Master Plan · 1/21/2019  · 2011 ARTS 2011 ITE 1998 Academic Wing 2011 LABS BHS Master Plan Age of Construction Non-Colored Areas

BHS Master Plan

8

Must Priority Scope: Tier 1

Expand & reconfigure South Parking Area to 110 Cars, aNet increase of 44 Cars

N

Page 9: Batesville High School Batesville Middle School Master Plan · 1/21/2019  · 2011 ARTS 2011 ITE 1998 Academic Wing 2011 LABS BHS Master Plan Age of Construction Non-Colored Areas

BHS Master Plan

Remodel 1967 Restrooms by Cafeteria

Cafeteria

9

Must Priority Scope: Tier 2

Restrooms

N

Page 10: Batesville High School Batesville Middle School Master Plan · 1/21/2019  · 2011 ARTS 2011 ITE 1998 Academic Wing 2011 LABS BHS Master Plan Age of Construction Non-Colored Areas

1998 Music

CARPET TILE IN CLASSROOMS (9)

BHS Master Plan

10

Must Priority Scope: Tier 2

N

Page 11: Batesville High School Batesville Middle School Master Plan · 1/21/2019  · 2011 ARTS 2011 ITE 1998 Academic Wing 2011 LABS BHS Master Plan Age of Construction Non-Colored Areas

CARPET TILE IN CLASSROOMS (18)

BHS Master Plan

11

Must Priority Scope: Tier 2

N

Page 12: Batesville High School Batesville Middle School Master Plan · 1/21/2019  · 2011 ARTS 2011 ITE 1998 Academic Wing 2011 LABS BHS Master Plan Age of Construction Non-Colored Areas

First Floor

Locker Room

BHS Master Plan

12

Must Priority Scope: Tier 2Complete Shelled out

Locker from last Project

N

Page 13: Batesville High School Batesville Middle School Master Plan · 1/21/2019  · 2011 ARTS 2011 ITE 1998 Academic Wing 2011 LABS BHS Master Plan Age of Construction Non-Colored Areas

Batesville Middle School

13

Page 14: Batesville High School Batesville Middle School Master Plan · 1/21/2019  · 2011 ARTS 2011 ITE 1998 Academic Wing 2011 LABS BHS Master Plan Age of Construction Non-Colored Areas

First Floor

Old Gym

BMS Master Plan

14

Cafeteria

Gymnasium

Main Entry

N

Age of Construction1998 Gym

Non-Colored Areas are Original 1974 Construction

1998 Academic Wing

Page 15: Batesville High School Batesville Middle School Master Plan · 1/21/2019  · 2011 ARTS 2011 ITE 1998 Academic Wing 2011 LABS BHS Master Plan Age of Construction Non-Colored Areas

First Floor

BMS Master Plan

15

Must Priority Scope: Tier 1

Door Monitoring/Security New Mechanical Controls throughoutSelective HVAC Equipment Replacement

Cafeteria

Gymnasium

Main Entry

N

Media Center

Page 16: Batesville High School Batesville Middle School Master Plan · 1/21/2019  · 2011 ARTS 2011 ITE 1998 Academic Wing 2011 LABS BHS Master Plan Age of Construction Non-Colored Areas

Must Priority Scope: Tier 2

BMS Master PlanSite Plan

16

Re-Roof Old GymRoof is 30+ yrs. of Age

N

Page 17: Batesville High School Batesville Middle School Master Plan · 1/21/2019  · 2011 ARTS 2011 ITE 1998 Academic Wing 2011 LABS BHS Master Plan Age of Construction Non-Colored Areas

First Floor

New Construction

Band

Music Admin

Choir

Corridor

Old Gym

BMS Master Plan

17

Must Priority Scope: Tier 1

N

Music and Administration Expansion with Link to Old Gymnasium (Security)

Media Center

Cafeteria

Gymnasium

Main Entry

Page 18: Batesville High School Batesville Middle School Master Plan · 1/21/2019  · 2011 ARTS 2011 ITE 1998 Academic Wing 2011 LABS BHS Master Plan Age of Construction Non-Colored Areas

BMS Master PlanSite Plan

Locker Room

Support

Music and Admin Addition

18

Page 19: Batesville High School Batesville Middle School Master Plan · 1/21/2019  · 2011 ARTS 2011 ITE 1998 Academic Wing 2011 LABS BHS Master Plan Age of Construction Non-Colored Areas

New Construction

Cafeteria/Serving Expansion

Renovation/Right size Choir

First Floor

Band

Music Admin

ExpandCafeteria

Choir

Corridor

Old Gym

New Corridor

Expand Food Service

BMS Master Plan

19

High Priority Scope: Tiers 3 & 4

N

Future

Media Center

Gymnasium

Main Entry

Page 20: Batesville High School Batesville Middle School Master Plan · 1/21/2019  · 2011 ARTS 2011 ITE 1998 Academic Wing 2011 LABS BHS Master Plan Age of Construction Non-Colored Areas

First Floor

Carpet Tile in Classrooms (19)

C̀arpet Tile in Corridors

`

BMS Master Plan

20

Must Priority Scope: Tier 2

Cafeteria

Gymnasium

Main Entry

N

Media Center

Page 21: Batesville High School Batesville Middle School Master Plan · 1/21/2019  · 2011 ARTS 2011 ITE 1998 Academic Wing 2011 LABS BHS Master Plan Age of Construction Non-Colored Areas

Second Floor

Carpet Tile in Corridors

Carpet Tile in Academics (10)

BMS Master Plan

21

Must Priority Scope: Tier 2

N

Page 22: Batesville High School Batesville Middle School Master Plan · 1/21/2019  · 2011 ARTS 2011 ITE 1998 Academic Wing 2011 LABS BHS Master Plan Age of Construction Non-Colored Areas

First Floor

Secured Media Center

Old Gym

Media Center

New Wall/Doors

BMS Master Plan

22

Cafeteria

Gymnasium

Main Entry

N

Must Priority Scope: Tier 1

Page 23: Batesville High School Batesville Middle School Master Plan · 1/21/2019  · 2011 ARTS 2011 ITE 1998 Academic Wing 2011 LABS BHS Master Plan Age of Construction Non-Colored Areas

First Floor

Window Wall

Renovate to Student Commons

Remodel

Old Gym

Media Center

Open Student Collaboration

New Connecting Corridor

Comm.Room

STEMLab

BMS Master Plan

23

High Priority Scope: Tier 2

Cafeteria

Gymnasium

Main Entry

N

Future

Page 24: Batesville High School Batesville Middle School Master Plan · 1/21/2019  · 2011 ARTS 2011 ITE 1998 Academic Wing 2011 LABS BHS Master Plan Age of Construction Non-Colored Areas

Batesville High SchoolBatesville Middle School

Master Plan

24