Basics of Government Subcontracting webinar2016 · oPolicy and Procedure ... complies with...
Transcript of Basics of Government Subcontracting webinar2016 · oPolicy and Procedure ... complies with...
10/18/2016
1
ESSENTIALS OF COMPLIANTSUBCONTRACTING
Reducing Risk & MeetingRequirements as a PrimeContractor
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
AGENDA
oIntroduction
oThe Process
oThe Solicitation
oThe Agreement
oConsent
oPolicy and Procedure
oDocumentation and Accountability
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
COMMON ACRONYMS
ACO – Administrative Contracting Officer
CO – Contracting Officer
FAR – Federal Acquisition Regulation
PoP – Period of Performance
SOW – Statement of Work
Subk – Subcontract
CAS – Cost Accounting Standards
DCAA CAM – Defense Contract Audit Agency Contract Audit Manual
Ts and Cs – Terms and Conditions
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
10/18/2016
2
INTRODUCTION
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
WHAT IS “SUBCONTRACTING”?Procurement = the purchase of goods, services, and materials from vendors,subcontractors and consultants in support of a government contract
May be referred to as “purchasing”, “buying”, “acquisition”or “subcontracting” “Subcontractor” may also mean “vendor” or “consultant”
FAR 2.101
“Acquisition” means the acquiring by contract with appropriatedfunds of supplies or services (including construction) by and for theuse of the Federal Government through purchase or lease, whetherthe supplies or services are already in existence or must be created,developed, demonstrated, and evaluated. Acquisition begins atthe point when agency needs are established and includes thedescription of requirements to satisfy agency needs, solicitationand selection of sources, award of contracts, contract financing,contract performance, contract administration, and thosetechnical and management functions directly related to theprocess of fulfilling agency needs by contract
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
DEFINITION OF SUBCONTRACTFAR 52.244-2 “Subcontract” means any contract, as defined in FAR Subpart 2.1, entered into by a
subcontractor to furnish supplies or services for performance of the prime contract ora subcontract. It includes, but is not limited to, purchase orders, and changes andmodifications to purchase orders
FAR Part 44 “Subcontractor” means any supplier, distributor, vendor, or firm that furnishes supplies
or services to or for a prime contractor or another subcontractor
FAR Part 19 “Subcontract” means any agreement (other than one involving an employer-employee
relationship) entered into by a Government prime contractor or subcontractor callingfor supplies and/or services required for performance of the contract, contractmodification, or subcontract.
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
10/18/2016
3
WHY IS GOVERNMENT PROCUREMENTDIFFERENT?
Commercial Preferred vendors
Discounts, deals and handshakes
Simple competition
Documentation IAW companypolicy (sometimes)
Government Competition unless justified solesource Market research and duediligence Approvals Adequate solicitation Adequate evaluation Determination of adequatepricing Documentation IAW compliantProcurement Policy
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
WHY COMMERCIAL PRACTICES DON’TALWAYS APPLYContractors are entrusted to use tax payer money to completecontracts Therefore, you must follow the same procurement rules as a government contracting
activity
Government has the right to review and approve/disapprovepurchasing system
Government has the right to review Procurement Policy to ensureproper accounting of subcontractors
Government may require approval of purchases
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
GOVERNING REGS
FAR Part – 6 Competition Requirements
FAR Part 19 – Small Business Programs (for large businesses)
FAR Part 44 – Subcontracting Policies and Procedures
DCAA Contract Audit Manual Chapter 5 5-600 Audit of Purchasing System Internal Controls
5-607 Purchasing System -- Contract Clause Flow Down
5-608 Purchasing Management and Administration (Make or Buy)
5-609 Purchasing Source Selections
5-610 Pricing/Cost Analysis and Negotiated Purchases
5-611 Subcontract Award and Administration
5-612 Purchasing System - Information Technology System Internal
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
10/18/2016
4
FAR 52.244-2 SUBCONTRACTS
(1) The contracting officer shall insert the clause at 52.244-2,Subcontracts in solicitations and contracts when contemplating--
(i) A cost-reimbursement contract;
(ii) A letter contract that exceeds the simplified acquisitionthreshold;
(iii) A fixed-price contract that exceeds the simplifiedacquisition threshold under which unpriced contract actions(including unpriced modifications or unpriced delivery orders)are anticipated;
(iv) A time-and-materials contract that exceeds the simplifiedacquisition threshold; or
(v) A labor-hour contract that exceeds the simplifiedacquisition threshold
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
PRIVITYDefinition - The relation which subsists between two contractingparties.
Exceptions Payment
Small Business Subcontracting Plan
Flowdowns
Contract Disputes Act claims sponsored by Prime
New labor reporting requirements
The Government does not have privity of contract with subcontractors Therefore, prime contractors are responsible for subcontractors and to fulfill all
contracting responsibilities.
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
IMPORTANCE OF PROPERSUBCONTRACTING
Contractor Purchasing System Reviews (CPSR)
DCAA Pre –Award Systems Survey Questions
DFARS Business Systems Rules
Reduces Risk Transfer of liability
Avoid breach of contract
Eases reporting burdens
Perception of responsible government contractor
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
10/18/2016
5
CONTRACTOR PURCHASING SYSTEMREVIEW
44.301 -- Objective. The objective of a contractor purchasing system review (CPSR) is to evaluate the
efficiency and effectiveness with which the contractor spends Government funds andcomplies with Government policy when subcontracting.
The review provides the ACO a basis for granting, withholding, or withdrawingapproval of the contractor’s purchasing system.
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
CPSR THRESHOLD
44.302 -- Requirements.
(a) The ACO shall determine the need for a CPSR based on, but not limitedto,
1) the past performance of the contractor, and the volume,complexity and dollar value of the subcontracts.
2) If a contractor’s sales to the Government (excludingcompetitively awarded firm-fixed-price and competitivelyawarded fixed-price with economic price adjustment contracts andsales of commercial items pursuant to Part 12) are expected toexceed $25 million during the next 12 months
Sales include those represented by prime contracts, subcontracts under Governmentprime contracts, and modifications.
(b) Once an initial determination has been made , at least every threeyears, the ACO shall determine whether a purchasing system review isnecessary.
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
THE PROCESS
10/18/2016
6
THE ACQUISITION TEAM
Contracts Manager
Purchasing/Subcontracts Manager
Business Development
Accounting
Technical
Management (as needed)
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
PROCUREMENT PLANNINGRESPONSIBILITIES
•Identify Need
•NDA’s and TA’s
•Make or Buy decisions
•Purchase Requisitions and approvals
•Solicitation preparation
•Market research and due diligence
•Determination of qualification and non-exclusion
•Promoting competition
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
ORGANIZATION FOR EFFECTIVE SUBKMGMT
The purchasing department should have an organizational plan whichestablishes clear lines of authority and responsibility. Items to considerinclude:
(1) The purchasing department is independent of otherdepartments and is responsible for procuring all materials, supplies,services, and equipment.
(2) The receiving function is performed by personnel independentof the buying function.
(3) All purchasing department personnel should understand theirassigned responsibilities, authority, and limitations.
(4) There should be procedures delegating who has the authorityto make commitments and to question quality and quantity of materialrequisitioned or received
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
10/18/2016
7
CRADLE TO GRAVE
Plan
Solicit
Evaluate
Award
Admin
Close
Consent?
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
IDENTIFY NEEDProposal Review SOW Company's responsibilities (Make or Buy)?
What aspects will required subcontracted services?
What supplies/items/products will need to be bought to support the SOW?
May be directed by government to work with a particular company– managed the same
Post – AwardWhy was the need not identified during the proposal?
What is required and why?
How will the process of subcontracting delay schedule?
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
NDAS AND TAS
Non-Disclosure Agreements (NDAs) First document to be executed with key subs who may participate in proposal
Ensure purpose is specific to the proposal
If subs need to coordinate with them, make it multi-party
Teaming Agreements (TAs) Once decided who are key service or product suppliers
Ensure high level SOW or item list included
Commits so that not left hanging without a sub at award
Ensure purpose is for proposal and NDA is incorporated
Exclusivity (or not)
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
10/18/2016
8
MAKE OR BUY
Apply a consistent make-or-buy policy that is in the best interest of theGovernment (from the DFARS)
FAR 2.101 “Make-or-buy program” means that part of a contractor's written plan for a contract
identifying those major items to be produced or work efforts to be performed in theprime contractor's facilities and those to be subcontracted.
Pertains mainly to manufacturing, but can pertain to services.
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
MAKE OR BUY PROGRAM
FAR 15.407-2 - “Make item,” means an item or work effort to beproduced or performed by the prime contractor or its affiliates,subsidiaries, or divisions. Part of contractor’s written plan for a contract identifying those major items to be
produced or work efforts to be performed by the prime and those to besubcontracted.
Contracting officers may require prospective contractors to submit make-or-buyprogram plans for negotiated acquisitions requiring certified cost or pricing datawhose estimated value is $12.5 million or more, except when the proposed contract isfor research or development and, if prototypes or hardware are involved, nosignificant follow-on production is anticipated.
The requirement will be called out in a solicitation – and program willbe included in proposal
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
MARKET RESEARCH
Identify capable and qualified subcontractors
For recurring needs – build and maintain abidders list of potential vendors. Maintain on a current basis to ensure maximum usefulness.
For rare or project-specific situations Utilize a method similar to govt with industry days, draft SOWs, andpublication of notices (sources sought)
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
10/18/2016
9
QUALIFICATIONTechnical Validate technical capabilities with past performance assessment Either during build of bidders list or as a solicitation evaluation requirement.
Debar (non-exclusion) Ensure company (nor individual) is excluded Check debarred and suspended parties on www.epls.gov
Financial Bonding capabilities
D&B
DCAA Assist Audit (rate)
Refer to FAR Part 9
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
PROMOTING COMPETITION
52.244-5 -- Competition in Subcontracting.
As prescribed in 44.204(c), insert the following clause: Competition in Subcontracting (Dec 1996)
(a) The Contractor shall select subcontractors (includingsuppliers) on a competitive basis to the maximumpractical extent consistent with the objectives andrequirements of the contract.
(b) If the Contractor is an approved mentor under theDepartment of Defense Pilot Mentor-Protégé Program(Pub. L. 101-510, section 831 as amended), theContractor may award subcontracts under this contracton a noncompetitive basis to its protégés.
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
SOLE SOURCE JUSTIFICATION
Exception to competition documentation See FAR 6.302
Must prepare a document similar to a Justification and Approval(J&A) Includes “story” of reason and rationale for sole source and how it will benefit the
government and project
And how it fits within the FAR rules
Keep in file in case it must be provided to government
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
10/18/2016
10
PURCHASE REQUISITIONS ANDAPPROVALS
Purchase Requisition (PR) - Used to ensure nothing is bought outside company practice,that there is funding available, and to fulfill regulations
Per DCAA CAM 5.608.2 - purchases must be based on authorized requisitions
PR should be the evidence of “need”
Even if requirement included in proposal, the PR is the tool to get the acquisition started
PR should be pre-numbered and have
Contract for which it supports, description, quantity, independent estimate or ROM, potential suppliers, PoP
Approval signature
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
PR PROCESS
PR Built
PRReviewed
PRApproved
Solicitation
Technical
Contracts
Accounting
Entire Team
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
THE SOLICITATION
10/18/2016
11
PRE-AWARD VS. POST-AWARDPre-Award Identify need to procure
Solicit Don’t promise
LOI’s (if necessary)
Evaluate and decide
Incorporate into proposal
Release orders upon win
Post-Award Identify need to procure
Identify ability to procure Allowed?
Budget?
Solicit Don’t Promise
Evaluate and decide
Request consent
Release orders upon consent
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
SOLICITATION RESPONSIBILITIES
Plan the solicitation with key players
Provide clear SOW, SOO, specs, etc. Date the SOW!
Build appropriate proposal/quote prep instructions and evaluationfactors
Ensure prime contract clauses are flowed down From prime solicitation
From prime contract
If competitive – ensure adequate competition Go for 3+
Best to follow methods of appropriate FAR sections depending on dollarvalue
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
FORMULATE SPECS
Identify what will be needed for a sub to provide a good quote.
Take into consideration how narrow the SOW or specs should be.
For services: Scope, Background, Objective, Tasks, Period of Performance, Deliverables, and misc
areas (Access, Travel, Milestones, etc)
For supplies Part number or detailed description (can use brand name), unit of issue, # units,
delivery date, etc.
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
10/18/2016
12
CHOOSING SUBCONTRACT TYPE
Need to identify up front in solicitation what type of solicitation iscontemplated
If the potential sub does NOT have an approved accounting system,do not award a cost type subcontract.
Determine type based upon risk, scope of work, and ability toprovide adequate pricing.
Reference FAR Part 16
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
THE SOLICITATION PACKAGE
Required As Needed
Instructions Solicitation Letter
Basic subcontractor info form Templates
Representations and Certifications Subcontractor qualification forms
SOW, SOO, or specs document Draft subcontract
Evaluation methodology
Prime contract flow downs
Company terms and conditions
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
COST & PRICE ANALYSIS
CAM 5-610.1 Cost/Price Analysis and Technical Evaluation
a. The contractor should perform cost/price analysis and technicalevaluation of its subcontractor's and supplier'sproposals/quotations.
The scope and conclusions of the analysis should be documented and included in thepurchase order file. The contractor should obtain a certificate of current cost andpricing data when applicable.
b. Buyers should document the purchase order file to explain priceincreases (over previous buys or over bill of material estimates) andlack of decreases in price when circumstances indicate that the priceshould be lower (when quantity is increased over a previous buy orvendor quote, or when learning or other factors indicate lesser coststhan in a previous buy).
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
10/18/2016
13
SELECT
Build “Apparent Successful Offeror” letter
Build “No Award” letter
Be prepared for debrief request
If company that was not on a bidder’s list made a good showing,remember to add them to bidder’s list
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
THE AGREEMENT
WHAT TYPE OF DOCUMENT?
Subcontract
Purchase Order
Blanket Purchase Agreement
Letter Contract
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
10/18/2016
14
FLOWDOWNSDCAA CAM 5-606.3 All applicable purchase orders and subcontracts contain all flowdown
clauses, including terms and conditions
DFARS Ensure that all applicable purchase orders and subcontracts contain all
flowdown clauses, including terms and conditions and any other clausesneeded to carry out the requirements of the prime contract
Utilize the prime contract, FAR (and supplements), FARMatrix
Mandatory and Non-Mandatory Mandatory – labor, CAS, Audit and Intellectual Property
Non-Mandatory – termination, changes, risk mitigation
Also can utilize clauses to pass other areas of risk down to the sub
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
FLOWDOWN CONSIDERATIONS
Ensure preface includes language replacing terms such as “Government” with“Contractor” and similar replacements
Understand the difference between general or standard provisions/clauses andthose which are special (use only when warranted)
Mandatory, Optional and Desired?
Reference or full text?
Custom or modified?
Type of Prime Contract?
Type of Subcontract?
Method of Award
Subject Matter
Dollar Value
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
RISKY FLOWDOWNS
Disputes
Payment
Intellectual Property
Government Property
Labor Laws
Termination
Purchasing
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
10/18/2016
15
MODIFICATION52.249-10 -- Default (Fixed-Price Construction). (Apr 1984)
(a) If the SubContractor refuses or fails to prosecute the work or anyseparable part, with the diligence that will insure its completion within thetime specified in this contract including any extension, or fails to complete thework within this time, the Government Prime may, by written notice to theSubContractor, terminate the right to proceed with the work…
(b) The SubContractor’s right to proceed shall not be terminated nor theSubContractor charged with damages under this clause, if --…..
(2) The SubContractor, within 10 days from the beginning of any delay(unless extended by the SubContracting Officer Manager), notifies theSubContracting Officer Manager in writing of the causes of delay. TheSubContracting Officer Manager shall ascertain the facts and the extent ofdelay. If, in the judgment of the SubContracting Officer Manager, thefindings of fact warrant such action, the time for completing the work shallmay be extended. The findings of the Contracting Officer shall be final andconclusive on the parties, but subject to appeal under the Disputes clause.
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
EXAMPLE - FLOWDOWNS
A prime contractor’s contract includes the following clauses: 52.222-41 Service Contract Act
52.227-14 Rights in Data – General
52.232-25 Prompt Payment
52.223-6 Drug-Free Workplace
52.243-1 Changes – Fixed Price
52.203-13 Contractor Code of Business Ethics and Conduct
Which are mandatory flowdowns and which are not?
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
SUBCONTRACTOR INFORMATION
Company information Address, website, CAGE, DUNS, Tax ID, etc.
Business size and designation
POCs
Remit info
NAICS
Past Performance info (if not part of the proposal package)
D&B Report (if necessary)
Other info as necessary to determine capabilities
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
10/18/2016
16
SOLICIT
Pull the entire solicitation package together
Publicize and/or send out to bidders list
Allow adequate time for response
Issue amendments as needed Make sure publicized the same way as original solicitation
Allow Q&A Publicize Q&A the same way as solicitation
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
DISCUSSIONS & CLARIFICATIONS
Discussions Occur with all bidders
Bring in each potential subcontractor and ask same set of questions to each
Beneficial to get a personal impression
Allows you to hear explanation of their proposal
Clarifications Use with a potential sub as needed
Only to clarify a part of a proposal.
Not meant to be a opportunity to materially change proposal or promote.
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
NEGOTIATION OF TS AND CS
Essential Terms/Conditions That Will Likely Needto be Negotiated Changes
Payment
Intellectual property and patents
Inspection and acceptance
Terminations
Warranties
Disputes
Indemnification and Limitations of Liability
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
10/18/2016
17
HIERARCHY OF TERMS
Precedence General Terms and Conditions
Prime Contract FAR Supplement Flowdowns
Prime Contract FAR Flowdowns
Special Contract Terms
Special Program Terms
Special Company Terms
Include an order of precedence clause in Ts andCs
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
EVALUATION AND NEGOTIATIONRESPONSIBILITIES
Competitive Evaluate responses in accordance with solicitation
Determine if there is a competitive range and/or clarifications need to be conducted
Document process and decision
Identify successful subcontractor
Sole Source Review offer
Build negotiation position
Negotiate (if necessary)
Document decision
Provide notice of completion of negotiations
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
EVALUATE
Evaluate price, quality, delivery, technical capabilities, and financialcapabilities of competing vendors to ensure fair and reasonableprices. Conduct cost or price analysis to further determine reasonableness
Include PR originator and accounting in review at minimum
Record evaluation Price Negotiation Memorandum
Price Competition Memorandum
Establish and maintain adequate documentation to provide acomplete and accurate history of purchase transactions to supportvendors selected and prices paid.
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
10/18/2016
18
COMMERCIAL SUBCONTRACTS52.244-6 -- Subcontracts for Commercial Items.
To the maximum extent practicable, the Contractor shall incorporate, and require its subcontractors at all tiers toincorporate, commercial items or nondevelopmental items as components of items to be supplied under this contract.
The Contractor shall insert the following clauses in subcontracts for commercial items: 52.203-13, Contractor Code of Business Ethics and Conduct (Apr 2010) (Pub. L. 110-252, Title VI, Chapter 1 (41
U.S.C. 251 note)), if the subcontract exceeds $5,000,000 and has a performance period of more than 120 days. Inaltering this clause to identify the appropriate parties, all disclosures of violation of the civil False Claims Act or ofFederal criminal law shall be directed to the agency Office of the Inspector General, with a copy to the ContractingOfficer.
52.203-15, Whistleblower Protections Under the American Recovery and Reinvestment Act of 2009 (Jun 2010)(Section 1553 of Pub. L. 111-5), if the subcontract is funded under the Recovery Act.
52.219-8, Utilization of Small Business Concerns (Dec 2010) (15 U.S.C. 637(d)(2) and (3)), if the subcontract offersfurther subcontracting opportunities. If the subcontract (except subcontracts to small business concerns) exceeds$650,000 ($1.5 million for construction of any public facility), the subcontractor must include 52.219-8 in lower tiersubcontracts that offer subcontracting opportunities.
52.222-26, Equal Opportunity (Mar 2007) (E.O. 11246).
52.222-35, Equal Opportunity for Veterans (Sep 2010) (38 U.S.C. 4212(a));
52.222-36, Affirmative Action for Workers with Disabilities (Oct 2010) (29 U.S.C. 793).
52.222-40, Notification of Employee Rights Under the National Labor Relations Act (Dec 2010) (E.O. 13496), if flowdown is required in accordance with paragraph (f) of FAR clause 52.222-40.
52.222-50, Combating Trafficking in Persons (Feb 2009) (22 U.S.C. 7104(g)).
52.247-64, Preference for Privately Owned U.S.-Flag Commercial Vessels (Feb 2006) (46 U.S.C. App. 1241 and 10U.S.C. 2631), if flow down is required in accordance with paragraph (d) of FAR clause 52.247-64.
(2) While not required, the Contractor may flow down to subcontracts for commercial items a minimal number ofadditional clauses necessary to satisfy its contractual obligations.
(d) The Contractor shall include the terms of this clause, including this paragraph (d), in subcontracts awardedunder this contract.
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
CONSENT
CONSENTLook for FAR 52.244-2 Subcontracts – By obtaining consent to subcontract, theGovernment is afforded the opportunity to verify that the purchase is IAW withthe contract and regulations, as well as the application of sound businessjudgment.
(b) If the contractor does not have an approved purchasing system, consent to subcontractis required for cost-reimbursement, time-and-materials, labor-hour, or letter contracts, andalso for unpriced actions (including unpriced modifications and unpriced delivery orders)under fixed-price contracts that exceed the simplified acquisition threshold, for--
(1) Cost-reimbursement, time-and-materials, or labor-hour subcontracts; and
(2) Fixed-price subcontracts that exceed—
(i) For the Department of Defense, the Coast Guard, and theNational Aeronautics and Space Administration, the greater of the simplified acquisitionthreshold or 5 percent of the total estimated cost of the contract; or
(ii) For civilian agencies other than the Coast Guard and theNational Aeronautics and space Administration, either the simplified acquisition threshold or5 percent of the total estimated cost of the contract.
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
10/18/2016
19
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
WHAT IS CONSENT MADE OF?
(i) A description of the supplies or services to besubcontracted.
(ii) Identification of the type of subcontract to be used.
(iii) Identification of the proposed subcontractor.
(iv) The proposed subcontract price.
(v) The subcontractor’s current, complete, and accuratecertified cost or pricing data and Certificate of CurrentCost or Pricing Data If over $750,000
(vi) The subcontractor’s Disclosure Statement orCertificate relating to CAS If sub is subject to CAS
(vii) A Negotiation Memorandum per the FAR© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
MEMO FOR CONSENT(vii) A negotiation memorandum reflecting -
(A) The principal elements of price negotiations;(B) The most significant considerations controlling establishment of initial orrevised prices;(C) The reason certified cost or pricing data were or were not required;(D) The extent, if any, to which the Contractor did not rely on thesubcontractor’s certified cost or pricing data in determining the price objectiveand in negotiating the final price;(E) The extent to which it was recognized in the negotiation that thesubcontractor’s certified cost or pricing data were not accurate, complete, orcurrent; the action taken by the Contractor and the subcontractor; and theeffect of any such defective data on the total price negotiated;(F) The reasons for any significant difference between the Contractor’s priceobjective and the price negotiated; and(G) A complete explanation of the incentive fee or profit plan when incentives areused.
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
10/18/2016
20
NO CONSENT
Contracting officers shall not consent to --
(1) Cost-reimbursement subcontracts if the fee exceeds the fee limitationsof 15.404-4(c)(4)(i);
(2) Subcontracts providing for payment on a cost-plus-a-percentage-of-cost basis;
(3) Subcontracts obligating the contracting officer to deal directly with thesubcontractor;
(4) Subcontracts that make the results of arbitration, judicialdetermination, or voluntary settlement between the prime contractor andsubcontractor binding on the Government; or
(5) Repetitive or unduly protracted use of cost-reimbursement, time-and-materials, or labor-hour subcontracts (contracting officers should followthe principles of 16.103(c)).
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
CONSENT OF PROPOSED SUBS
The designation of a specific subcontractor duringcontract negotiations does not in itself satisfy therequirement of consent. However, if in the opinion of the CO, the consent requirement wassatisfied for certain subcontracts, the CO will have identified thosesubcontractors in the Subcontracts clause of the contract.
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
EXAMPLE
A prime contractor holds a Time & Materials contract for warehousingthat is valued at $750,000. The prime does not have an approvedpurchasing system. The prime realized during the proposal phase thatthey would need to subcontract the logistics services and purchasingshelving. The prime competed both needs before the proposal wassubmitted and selected a company for each need to include in theprime contract proposal. The CO accepted the proposal. FAR52.244-2 is included in the prime contract, unedited. The logisticsservices will be a T&M subcontract valued at $70,000. The shelvingwill be an FFP order valued at $152,000.
Does either purchase require consent? Why?
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
10/18/2016
21
POLICY AND PROCEDURE
POLICY
Policy is the high level instruction for government subcontracting
Dictates who has authority to make commitments
Approved by an appropriate level of management to signify thedelegation of authority to effectively convey management’scommitment to adhere to the policy and procedure, FAR, DFARS, etc.
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
PROCEDURE
Use the FAR and DCAA CAM
Modify (within reason) to fit Company's business
Actual practices should be consistent withestablished procedures
Ensure Consistency
Based on authorized requirements
Communication and training
All major duties and responsibilities are addressed
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
10/18/2016
22
DETERMINING INTERNAL THRESHOLDS
Advisable to utilize the Government thresholds Less than $3,000 is micropurchase
Can use credit cards
Greater than or equal to $3,000 but under $150,000
Use Purchase Orders
Greater than $150,000
Use Subcontracts
For long term, broad scope of various dollars amounts
Use BPA or IDIQ with orders under
Task or purchase
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
DFARS CLAUSE252.244-7001 Contractor Purchasing System Administration (May 2011)
a) Definitions. As used in this clause—
“Acceptable purchasing system” means a purchasing system that complies with the systemcriteria in paragraph (c) of this clause.“Purchasing system” means the Contractor’s system or systems for purchasing andsubcontracting, including make-or-buy decisions, the selection of vendors, analysis ofquoted prices, negotiation of prices with vendors, placing and administering of orders,and expediting delivery of materials.“Significant deficiency” means a shortcoming in the system that materially affects theability of officials of the Department of Defense to rely upon information produced bythe system that is needed for management purposes.
(b) General. The Contractor shall establish and maintain an acceptable purchasingsystem. Failure to maintain an acceptable purchasing system, as defined in this clause,may result in disapproval of the system by the Contracting Officer and/or withholdingof payments.
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
DCAA CAM
http://www.dcaa.mil/cam.htm
5-600 Audit of Purchasing System and Internal Controls
5-608.2 Administrative Controls
5-608.3 Purchasing File Data (see worksheet)
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
10/18/2016
23
DOCUMENTATION &ACCOUNTABILITY
“Administration”
DOCUMENTATION
Subcontract FilesSubcontract File Checklist
Subcontract Summaries – similar to contract briefs
Subcontract Database
Internal numbering system Tie all purchasing to a prime contract IN ADDITION to anything tied in
QuickBooks
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
ADMINISTRATION•Some form of register or control is maintained to "flag" delivery due dates
•Procedures are in effect to expedite delivery of subcontract material.
•Corrective action is taken when the supplier is delinquent in delivery schedules
•Evaluate the delivery schedules when engineering changes have been introduced.
•Timely notification from to subcontractors when modifications are introduced.
•Adequate action taken when change orders or modification notices affect cost.
•Emphasis on production and financial controls, which ensure that physical progress ofproduction is commensurate with reimbursement;
•Timeliness and adequacy of the repricing actions
•Propriety of the costs generated by the subcontractor
•Audit of progress payments (refer to 5-1107.7 billing system audit of subcontractorprogress payments).
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
10/18/2016
24
REPS AND CERTS
Section K of a prime contract built for a sub
FAR Part 4.1200
SAM.gov includes a company’s reps and certs
Best practice to build a company version of reps and certs, but canuse SAM.gov instead
This Company's evidence of the sub certifying to critical items such as: Not being debarred
Paying taxes
Socioeconomic certification
Etc.
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
REPORTING
Ensure that any reporting required under the prime contract, butsubject to subcontract input, is delivered with enough time to review anincorporate
Identify in prime contract any reporting requirements for subs Ex) DD882/Reporting of Patentable Inventions
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
REPORTING OF SUBS
First Tier subcontract awards - 52.204-10 – Reporting Executive Compensation andFirst-Tier Subcontract Awards.
If clause is in contract, then unless otherwise directed by the contracting officer, by the end of the monthfollowing the month of award of a first-tier subcontract with a value of $30,000 or more, (and anymodifications to these subcontracts that change previously reported data), the Contractor shall report thefollowing information at http://www.fsrs.gov for each first-tier subcontract.
10/18/2016
25
AUDITING
•Property
•Costs/Accounting
•Quality
•Records
TYING PURCHASING TO PRIMECONTRACTS
All subcontracts or purchase orders must reference the prime contractnumber
Ensure subcontractor invoices reference the subcontract number -accounting should have an internal numbering system that allows asubcontract # to tie to a prime contract number
Ensure subcontract payment terms are no less restrictive than primecontract payment terms
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
COMMERCIAL DEFENSE SUBCONTRACTS
SUBPART 244.4--SUBCONTRACTS FOR COMMERCIAL ITEMS ANDCOMMERCIAL COMPONENTS
244.402 Policy requirements. (a) Contractors shall determine whether a particular subcontract item meets the
definition of a commercial item.
Contractors are expected to exercise reasonable business judgment in making suchdeterminations, consistent with the guidelines for conducting market research in FARPart 10.
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
10/18/2016
26
CLOSEOUT RESPONSIBILITIES
Ensure all items delivered and services completed
All invoices have been submitted and paid
Vendor is no longer needed to support the prime contract
Obtain written authorization to close the subcontract by technicalPOCs
Submit liability and release of claims form to vendor for signature
Submit signed closeout letter to vendor
Identify files as closed and archive May not be able to officially close for years under Cost Type prime contracts
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
RELATED ADMINISTRATION
Property Management
Standards of Business Conduct
Intellectual Property Rights
Accounting System Compliance
Export Compliance
Small Business Subcontracting Goals
Contract Administration It all ties back to the government contract
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
BEST PRACTICES
Written, compliant policy and procedure (P&P) FOLLOW the P&P
Training
Testing System against P&P
Look to the FAR and CAM
Tie procurements to contracts Via contract briefs and internal coding
Watch costs
Document, Document, Document Purchasing files, checklists, memos, etc.
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
10/18/2016
27
SPECIAL TOPICS
QUALITY/ACCEPTANCE
Quality and acceptance requirements, surveillance and proceduresshould have been in solicitation
Ensure the subcontract is clear on Quality and Acceptance
General Terms and Conditions would dictate warranty and paymentupon acceptance UNLESS – the prime contract dictates something specific
Or
Subcontract acceptance is tied to prime contract acceptance
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
CHANGES
If proper flowdowns are included, then sub will handle changes(hopefully) IAW the subcontract and FAR
Follow FAR principles in issuing and managing modifications tosubcontracts/orders
Maintain modification templates
Review mods to prime contract to ensure no changes trigger a mod tothe subcontract/order
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
10/18/2016
28
WARRANTIES
Warranty terms should mirror the prime contract.
Watch commencement of coverage Ensure coverage will cover through prime contract
Avoid implied warranties
Be clear in the solicitation what warranty terms are expected
Avoid collision of requirements in prime contract
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
TERMINATION/BREACH
Remember to keep the Govt CO in the loop on any subcontractorissues Although privity of contract is between Company and subcontractor, actions of sub
reflect on Company.
Understand your rights to terminate
Understand how it will impact the prime contract Avoid terminations by
Picking the right subs
Managing and monitoring constantly and consistently
Keeping lines of communication open
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
QUESTIONS?
10/18/2016
29
THANK YOU!
Stephanie Amend
Arrowhead Solutions, LLC
720-515-0527
www.arrowheadsolutionsllc.com
THE UCC
The Federal Common Law , as embodied in the FAR, controls thecreation, administration and interpretation of federal prime contracts
Commercial contracts (prime/sub) are governed by the laws ofvarious states embodied in the UCC as adopted by the state. The body of law governing the prime contract is different than that governs a
subcontract
Some of this difference can be addressed through flowdowns
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.
THE UCC CONT.
Under the UCC, parties can agree to do most anything they choose. If they are silent on certain matters, then the UCC will fill in the blanks.
Mandatory flow down clauses protect the government Some key clauses that protect the prime are not mandatory, but should be flowed
down and modified
Ex) Terminations
© ARROWHEAD SOLUTIONS 2016 NO CLAIM TO ORIGINAL U.S. GOVERNMENT WORKS.