Basic Resource Adequacy Study Concepts
-
Upload
september-major -
Category
Documents
-
view
26 -
download
0
description
Transcript of Basic Resource Adequacy Study Concepts
DRAFT
Basic Resource Adequacy Study Concepts
Wayne CostePrincipal Engineer, Resource Adequacy
RC MeetingMay 14, 2009
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
Resource Adequacy Metrics/Calculations
• Resource Adequacy assessments are studies– That attempt to answer the question
– May be framed in simple or complex terms– Resource Adequacy frameworks have evolved over time
• Simple deterministic analyses• More complex deterministic analyses• Probabilistic analyses
– Local area– Local area plus neighbors– Local area plus neighbors plus their neighbors and their neighbors
• “Resource Adequacy” will be used instead of “Reliability”– “Reliability” is a concept of “will the system fail”
2
“Do I have enough resources to serve the loads under all reasonably foreseeable circumstances”
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
Resource Adequacy Metrics
• In “ancient days” when systems were small and the next resource to be added would be the largest unit on the system, some “Rules-Of-Thumbs” were developed – “Largest Unit Rule”
– “Largest Unit and a Half Rule”– Percent Reserve Margin
• As unit size began to stabilize and systems became strongly interconnected– “Largest units” became small part of the total system
– Different approaches were used to answer the question, “when do I need more resources?”
– Probabilistic approaches were developed in the 1950s
– Use of these techniques became widespread in the 1960s
3
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
Probabilistic Resource Adequacy
• Resource Adequacy now based on probabilistic analysis– Probabilistic assessments are translated into adequacy metrics
• Percent reserve margins
• Percent capacity margins
• Amount of resources needed (total MW)
• Maximum peak load that can be served
– Probabilistic assessments assume• Some factors are correlated
– All areas / regions see the same heat wave at the same time– A resource outage can be correlated to an interface rating change– Seasonal derating
• Many resource adequacy risks are random and independent– One resource outage does not affect the “state” of another resource– “Independent” is a key assumption
4
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
Risk and Probabilities
• For every hour, of every day, the probability of insufficient resources to serve load can be quantified– For most hours, this probability is (virtually) zero– For some hours, the probability is non-zero and has a contribution– Basic metric is “Loss of Load Probability” or “LOLP”
• Given a load distribution and a supply distribution – LOLP is the probability of insufficient resources to serve load– There are no “measurement units” associated with a probability– “Measurement units” are “per period,” “per event” or “per coin flip,” etc.
• Summation of LOLP over time gives an “expectation”
5
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
“Expectation” in Adequacy Studies
• Adequacy index is “Loss of Load Expectation” or “LOLE”– LOLP is calculated for each time period
• Peak load of the day, or
• Each hour (including the peak hour)
– Time period used depends on desired adequacy index• Every hour
• Every contiguous event (i.e., possibly more than one per day)
• Every daily peak (i.e., a day is limited to one Loss of Load event)
– Summation of the LOLPs over a specified period of time• 5-day-week, 7-day-week, month, season, year or ten-years
– If absolutely unreliable … maximum 260 days per year (week days) – If absolutely unreliable … maximum 365 days per year (all days)
• Gives an “expectation” of how many occurrences could be experienced over a period of time
6
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
Other Probabilistic Indices
• Loss of Load Hours (LOLH)– The expected number of hours when shortages would occur– LOLH (hours/year) is not LOLE (days/year) times 24
• 0.1 days / year * 24 hours / day = 2.4 hours per year – Would happen only if peak occurred in each of the 24 hours of the day
– New England’s LOLH would be about 0.3 to 0.5 hours per year
• Loss of Energy Expectation (LOEE)– Measure of how many MWhs would be lost in each hour times the
probability of shortage (typically used for comparing load shape changes)
– Also called Expected Un-served Energy (EUE)
• Frequency & Duration (F&D)– Indication of how frequently outages would occur and how long they
might last (typically used for comparing load shape changes)
• Loss of Reserve Expectation (LORE)– Indication of how often emergency operations would be required
7
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
Interchangeability of Indices
• Expressing adequacy with different measurement units does not provide additional information about the adequacy of the system– “Measurement units” may not describe “different aspects” of adequacy
– Indices expressed using “different terms” may highlight secondary effects
• A parallel for “measurement units” can be made to a person’s height– The height of the presenter can be stated in different ways
• 6 feet tall• 72 inches tall• 182 centimeters tall• 18 hands tall (as used in measuring horses)• 0.001136 miles tall
• Indices can reflect “different aspects” for more information– Total height
– Total height and weight
– Total height, weight and shoe size
8
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
LOLE Criterion for Resource Adequacy
• This development of the LOLE index considers– Possible levels of peak loads due to weather variations – Impact of assumed generating unit performance– Load and capacity relief obtainable (Through the use of ISO NE Operating
Procedure No. 4 - Action During a Capacity Deficiency)
• LOLE index used in New England– A day with any loss-of-load counts only once
• Does not describe how many hours load is interrupted
• Two possible events in a single day – i.e., an outage at noon, then recovery, then an evening outage– Counts as only one day with loss-of-load
– Does not quantify how many MW are interrupted– Does not quantify the number of MWhs interrupted
9
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
Resource Adequacy Tools
• Westinghouse/ABB Capacity model program– It is a “Single Area” program
• Single area refers to the assumption that there is adequate transmission to deliver energy where and when it is needed
• All loads and generators assumed to be connected to a single bus• Maintenance scheduled to minimize LOLE throughout the year
– Uses mathematical (i.e., “closed form”) technique for solution– Probabilistic calculations to capture the random nature of loads
and resource availability• Determines the probabilities of different amounts of unavailable
capacity on the system as a result of resource forced outages• Mathematics gets very complex if any transmission is included
– A two-area Westinghouse/ABB model does exist, but has not been used in nearly 20 years
10
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
Resource Adequacy Tools (cont.)
• GE Multi-Area Reliability Simulation (MARS) model– MARS is a “Multi-Area” program
• Multi-area refers to the assumption that transmission constraints may impede delivery of energy to where and when it is needed
• Loads and generators can be assumed to be connected to different parts of the system
• Provides a locational dimension for resource adequacy studies
– MARS model uses different technique to “do the math”• Uses “Monte-Carlo” sampling instead of “closed form” solutions
• Exactly the same inputs would produce exactly the same results– Load distributions– Resource distributions
• “Monte-Carlo” models can include more constraints than analytical “closed form” models
11
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
Resource Adequacy Tools (cont.)
• Other types of resource adequacy models have been developed– Attempt to be more detailed– Potentially at a bus level resolution– Uncertainty whether
• Useful input assumptions are available at a detailed level
• Whether those assumptions are meaningfully robust
• What the meaning of a failure state actually means – Add more New England wide capacity, or– Add static capacitors at a specific location
– Uncertain how this more detailed information could / should be used in resource adequacy analysis
• Models more granular than MARS will not be discussed
12
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
Resource Adequacy – Excluded Factors
• Major factors not considered in adequacy calculations– Common mode failures of resources
– Catastrophic long-term resource outages
– Delays in resource additions or retirements
– Energy / fuel limited resources• Energy / fuel supply• Fuel delivery issues
– Uncertainty in assumptions for forced outage rate statistics
– Intra-hour load excursions
– Internal transmission constraints or transmission forced outages
– Effects of ambient air temperatures above 90oF on combustion turbine technologies
– Effect of air and water environmental restrictions
– Number of loss-of-load days that will actually incur a loss of load
13
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
Resource Adequacy – Excluded Risks
• Not all risks are considered– Perfect foresight is assumed in operations
• All resources are assumed to be available if they are not “broken”
• All resources are assumed to be committed in a timely manner so that all resources are ready when needed
• All resources are committed if higher than expected loads materialize
– Non-peak seasons contribute miniscule amounts to LOLE• No transmission outages are considered
• Generation maintenance, while modeled, is not a problem – For New England which is strongly summer peaking– Because we neglect transmission outages and additional constraints
• Non-peak season LOLE risk – LOLE risk in the “non-peak season” is a non-trivial operational issue– This is a question of “outage management” and not “resource adequacy” – Not part of the question “do we have sufficient resources” for peak loads
14
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
Resource Adequacy – Included Risks
• The most significant factors to be considered are– Customer load distributions
– Random resource outages• Generating resources
• Demand Resources
• Intermittent resources
– Static transmission interface limits• Based on specific system configurations
• Actual conditions may change interface limits significantly
– Operating Procedure No. 4, “Actions During a Capacity Deficiency” (OP-4)
• Voltage reductions
• Erosion of required operating reserve
• Emergency assistance from neighboring systems
15
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
Customer Load Distributions
• Uses distributions of daily peak loads for each week, explicitly taking into account weather uncertainty– Westinghouse load model is developed for
• Non-holiday weekday peaks
• Excludes weekend peaks
– Assumes weekend peak contribution to system risk is negligible• Weekend peaks are much lower that weekday peaks
• Risk of not having enough installed capacity is “much” lower
• Weekend operational issues may reduce flexibility of the system– Resource maintenance– Transmission maintenance– More units on reserve shutdown (i.e., not needed)
• MARS load model developed to mimic Westinghouse loads (to be discussed later)
16
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
Loads Model Development
• Loads represented by distributions of weekday peak loads– Represents daily peak loads only, not all hours– 52 weekly distributions for each year– Based on historical weather distributions from the last 3 decades
• These distributions are the key inputs in adequacy studies– Projected monthly and seasonal peak loads
• Are specific points on these load distribution curves
• Specific points are useful as guideposts– 50/50 summer peak load is one point on composite distribution– 90/10 summer peak load is another point on composite distribution
– Shape of load distributions affect the adequacy calculations– Statistical parameters for the distributions are used to characterize
the load levels with the probability of their occurrence
17
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
Peak Load Distribution Development
• For each of the 52 weeks of the forecast year– A distribution of 1,000 possible peak load points are developed
• Weather uncertainty is the primary uncertainty considered• Seasonal trends in composition of load (heating / cooling / other)
– Distribution of raw peak load data– Raw peak load points approximated by a continuous distribution
• Parameters estimated for three moments of the distribution– Mean– Standard deviation– Skewness (fat / skinny tails)
• Skewness is needed to capture the frequency of highest daily peak loads accurately as shown in next few slides
• The following distributions are illustrative and not for a specific year
18
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
Distribution of Raw Data for One Week
1000 Peak Load Points For Week 30 (2001)Cumulative Probability Distribution
0.00
0.10
0.20
0.30
0.40
0.50
0.60
0.70
0.80
0.90
1.00
16000 18000 20000 22000 24000 26000 28000
Load (MW)
Pro
bab
ilit
y
1000 Points Per Week
Note: Distribution represents 5 weekdays
19
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
Normal Approximation is “Generally Good”
1000 Peak Load Points For Week 30 (2001)Cumulative Probability Distributions
0.000.100.200.300.400.500.600.700.800.901.00
16000 18000 20000 22000 24000 26000 28000
Load (MW)
Pro
bab
ilit
y
1000 Points Per Week Normal Approx
High loads dominate risk calculations
Note: Distribution represents 5 weekdays
20
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
“Generally Good” Neglects the Upper Tail
1000 Peak Load Points For Week 30 (2001)Cumulative Probability Distributions
0.900.910.920.930.940.950.960.970.980.991.00
23000 25000 27000
Load (MW)
Pro
bab
ilit
y
1000 Points Per Week Normal Approx
Normal Approximation does not represent the probability of higher peak loads. Skewness (fat / skinny tail) corrects for much of this. [Note: At the 97th percentile, the approximated load is 800 MW lower than the distribution.]
Note: Distribution represents 5 weekdays
21
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
Cumulative Daily Peak Distribution for Highest Summer Week
0.00
0.20
0.40
0.60
0.80
1.00
1.20
1500
0
1600
0
1700
0
1800
0
1900
0
2000
0
2100
0
2200
0
2300
0
2400
0
2500
0
2600
0
2700
0
2800
0
2900
0
3000
0
3100
0
3200
0
3300
0
3400
0
Pro
babi
lity
Den
sity
for
Load
Load Level (MW)
Distributions of Daily Peak LoadsCumulative Distribution of Daily Peak Loads
Summer Peak Week
Sum m er Peak Week
Note: Distribution represents 5 weekdays
22
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
Daily Peak Density Distribution for Highest Summer Week
1500
0
1600
0
1700
0
1800
0
1900
0
2000
0
2100
0
2200
0
2300
0
2400
0
2500
0
2600
0
2700
0
2800
0
2900
0
3000
0
3100
0
3200
0
3300
0
3400
0
Pro
babi
lity
Den
sity
for
Load
Load Level (MW)
Distributions of Daily Peak LoadsDensity Distribution For Highest Summer Week
Sum m er Peak Week
Note: Distribution represents 5 weekdays
23
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
Daily Peak Density Distribution for Highest Seven Summer Weeks
1500
0
1600
0
1700
0
1800
0
1900
0
2000
0
2100
0
2200
0
2300
0
2400
0
2500
0
2600
0
2700
0
2800
0
2900
0
3000
0
3100
0
3200
0
3300
0
3400
0
Pro
bab
ilit
y D
ensi
ty f
or
Lo
ad
Load Level (MW)
Distributions of Daily Peak LoadsDensity Distribution For Highest Seven Summer Weeks
Week 28 Week 29 Week 30 Week 31 Week 32 Week 33 Week 34
Note: Each distribution represents 5 weekdays
24
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
Cumulative Daily Peak Distribution for Highest Seven Summer Weeks
0.00
0.20
0.40
0.60
0.80
1.00
1.20
1500
0
1600
0
1700
0
1800
0
1900
0
2000
0
2100
0
2200
0
2300
0
2400
0
2500
0
2600
0
2700
0
2800
0
2900
0
3000
0
3100
0
3200
0
3300
0
3400
0
Pro
bab
ilit
y
Peak Load (MW)
Distribution of Weekday Peak Loads - Highest Seven WeeksIndivudual Week Distributions
Week 28 Week 29 Week 30 Week 31 Week 33 Week 34 Week 35
Note: Each distribution represents 5 weekdays
25
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
Cumulative Daily Peak Distribution for Highest Seven Summer Weeks
0.00
0.20
0.40
0.60
0.80
1.00
1.20
1500
0
1600
0
1700
0
1800
0
1900
0
2000
0
2100
0
2200
0
2300
0
2400
0
2500
0
2600
0
2700
0
2800
0
2900
0
3000
0
3100
0
3200
0
3300
0
3400
0
Pro
babi
lity
Den
sity
for
Load
Load Level (MW)
Distributions of Daily Peak LoadsCumulative Distribution of Daily Peak Loads
Summer Peak Week
Summer Peak Week
Note: This load distribution represents 35 weekdays
26
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
Effect of Including all 52 Weeks
Note: Seven week distribution represents 35 weekdays 52 week distribution represents 260 weekdays
0.00
0.20
0.40
0.60
0.80
1.00
1.20
1500
0
1600
0
1700
0
1800
0
1900
0
2000
0
2100
0
2200
0
2300
0
2400
0
2500
0
2600
0
2700
0
2800
0
2900
0
3000
0
3100
0
3200
0
3300
0
3400
0
Cum
ulat
ive
Pro
babi
lity
for L
oad
Load Level (MW)
Distributions of Daily Peak LoadsCumulatve Distribution For all 52 Weeks
and 31,000 MW of Resources
Composite 52 Week Loads Seven Week Composite
52 week composite reflects lower loads
7 week composite reflects peak loads
27
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
Illustrating LOLP
• LOLP is the cornerstone of probabilistic adequacy studies• Adequacy studies compare differences between
– Loads to be served, and – Available resources (e.g., not on forced or scheduled outages)
• If resources were perfectly available when needed– Whenever loads are less than installed resources
• Then: no “Loss Of Load” (i.e., no contribution to LOLP)
– Whenever loads are more than installed resources• Then: a “Loss of Load” occurs (i.e., contribution to LOLP)
• Following examples– Assumes 31,000 MW of perfectly reliable resources– Resource uncertainty will be incorporated in later slides
28
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
Illustrating LOLP (cont.)
• Approach shown here is applicable to both– New England-wide Installed Capacity Requirements (ICR), and– Minimum and maximum locational capacity requirements
• Loads – Total New England loads are developed as shown– Loads for sub-areas are
• Approximately a percentage of the total load
• Percentage changes by month
• Calculations are identical– Question addressed by the calculation is
• What is the MINIMUM of capacity that is required IN THE AREA UNDER STUDY to satisfy the reliability criterion, GIVEN the risks and constraints that have been modeled
29
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
0.00
0.20
0.40
0.60
0.80
1.00
1.20
1500
0
1600
0
1700
0
1800
0
1900
0
2000
0
2100
0
2200
0
2300
0
2400
0
2500
0
2600
0
2700
0
2800
0
2900
0
3000
0
3100
0
3200
0
3300
0
3400
0
Cu
mu
lati
ve P
rob
abil
ity
for
Ava
ilab
le C
apac
ity
Pro
bab
ilit
y D
ensi
ty f
or
Lo
ad
Load Level (MW)
Distributions of Daily Peak LoadsDensity Distribution For Highest Summer Week
and 31,000 MW of Resources
Summer Peak Week Available Resources
LOLP With 31,000 MW of Resources
Loss of Load Probability: when loads greater than available resources
30
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
LOLP and LOLE Calculations
• Probability of loads exceeding available capacity– Probability of loads in excess of 31,000 MW– 0.01293 probability (area under the curve above 31,000 MW)
• If the load distribution represents 1 day then– The “expectation” that load would exceed available resources
would be 0.01293 for that one day• Restating this would be 0.01293 “expected outage events per day”• Identical days have the same probability value
• If the load distribution represented five weekdays– The “expectation” would be the same for each of the five days– The “expectation” would be five times or 0.06463 expected
outage events per week– Risk in other weeks to be evaluated separately and then summed
31
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
0.00
0.20
0.40
0.60
0.80
1.00
1.2015
000
1600
0
1700
0
1800
0
1900
0
2000
0
2100
0
2200
0
2300
0
2400
0
2500
0
2600
0
2700
0
2800
0
2900
0
3000
0
3100
0
3200
0
3300
0
3400
0
Cu
mu
lati
ve P
rob
abil
ity
for
Ava
ilab
le C
apac
ity
Pro
bab
ilit
y D
ensi
ty f
or
Lo
ad
Load Level (MW)
Distributions of Daily Peak LoadsDensity Distribution For Seven Highest Summer Weeks
and 31,000 MW of Resources
Week 28 Week 29 Week 30 Week 31
Week 32 Week 33 Week 34 Available Resources
Seven Critical Weeks of Peak Loads
LOLP changes for each week’s peak load distribution
32
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
LOLE adequacy Index for Seven Weeks
• Loss of Load Probabilities vary for each week depending on the level of the loads– Each week represents five weekdays– Loss of load expectation equals LOLP times number of days
– With 31,000 MW of resources and the seven peak load weeks • We have a LOLE of 0.26831 outage events per summer• If these were the only weeks with significant LOLP, then adequacy
index would be 0.26831 expected outage events per year (or LOLE)
Loss of Load Probability (LOLP)Loss of Load Expectation (LOLE)
Expected outage events per weekWeek 28 0.00783 0.03913Week 29 0.01028 0.05139Week 30 0.01293 0.06463Week 31 0.01174 0.05870Week 32 0.00687 0.03433Week 33 0.00403 0.02014Week 34 0.00263 0.01316Total 0.26831
33
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
0.00
0.20
0.40
0.60
0.80
1.00
1.20
1500
0
1600
0
1700
0
1800
0
1900
0
2000
0
2100
0
2200
0
2300
0
2400
0
2500
0
2600
0
2700
0
2800
0
2900
0
3000
0
3100
0
3200
0
3300
0
3400
0
Cu
mu
lati
ve P
rob
abil
ity
for
Ava
ilab
le C
apac
ity
Pro
bab
ilit
y D
ensi
ty f
or
Lo
ad
Load Level (MW)
Distributions of Daily Peak LoadsComposite Density Distribution For Highest Seven Summer Weeks
and 31,000 MW of Resources
Summer Peak Week Available Resources
Single Distribution Can Represent the 35 Days
LOLP for seven week composite distribution is 0.00804Note: 0.00804 x 35 days/ period = 0.2814 days/period
Note: This distribution represents 35 weekdays
34
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
Equivalent LOLE When Adjusted for Days
0.90
0.92
0.94
0.96
0.98
1.00
1.02
1.04
2500
0
2600
0
2700
0
2800
0
2900
0
3000
0
3100
0
3200
0
3300
0
3400
0
Cum
ulat
ive
Pro
babi
lity
for L
oad
Load Level (MW)
Distributions of Daily Peak LoadsCumulatve Distribution For all 52 Weeks
and 31,000 MW of Resources
Composite 52 Week Loads Seven Week Composite Available Resources
Note: Seven week distribution represents 35 weekdays 52 week distribution represents 260 weekdays
LOLP times 260 days per distribution
LOLP times 35 days per distribution
35
0.00110 x 260 days/ year = 0.2860 days/ year
Note: 0.00804 x 35 days/ period = 0.2814 days/period
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
Effect of Resource Unavailability
• Previous examples assumed that– There were 31,000 MW available– Perfectly reliable capacity– LOLE was only the area to the right of 31,000 MW
• However, real capacity is not perfectly reliable– In a large system
• All of the resources are never 100% available
• All of the resources are never completely broken
• Amount of resources available can be described as a distribution
– The LOLP calculation becomes more complicated• No longer a vertical line
• Now a cumulative distribution
36
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
Resource Unavailability Distribution
• Following slides show how resource unavailability is represented in a probabilistic analysis– Each resource has a probability of outage– Whenever any unit is unavailable, total available resources are
reduced
• When the risk of discrete units possibly being on outage are considered, a stair-step distribution will result– This example assumes the 31,000 MW is comprised of
• Thirty one 1000 MW units• Unavailability rate is 5 percent
• Normal approximation is shown for these outages– Not a good representation for only 31 large resources – Used here for illustrative purposes only
37
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
Perfect Capacity vs. One Resource with Uncertainty (1000 MW out of 31000 MW)
38
0.0000
0.2000
0.4000
0.6000
0.8000
1.0000
1.2000
1500
0
1600
0
1700
0
1800
0
1900
0
2000
0
2100
0
2200
0
2300
0
2400
0
2500
0
2600
0
2700
0
2800
0
2900
0
3000
0
3100
0
3200
0
3300
0
3400
0Cu
mu
lati
ve P
rob
abil
ity
of
Cap
acit
y
Capacity Level (MW)
Cumulative Distribution For Discrete OutagesAssumed 31 1000 MW resources with 5% Unavailability
No Resource Uncertainty With One 1000 MW Unit Uncertain
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
Normal Approximation of Capacity Outages
0.0000
0.2000
0.4000
0.6000
0.8000
1.0000
1.2000
1500
0
1600
0
1700
0
1800
0
1900
0
2000
0
2100
0
2200
0
2300
0
2400
0
2500
0
2600
0
2700
0
2800
0
2900
0
3000
0
3100
0
3200
0
3300
0
3400
0
Cu
mu
lati
ve P
rob
abili
ty o
f Cap
acity
Capacity Level (MW)
Cumulative Distribution For Discrete OutagesAssumed 31 1000 MW Resources with 5% Unavailability
No Resource Uncertain ty With 31 1000 MW Units Uncertain Normal Approximation o f Resource Outages
39
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
Density Distribution of Capacity Outages
0.0000
0.2000
0.4000
0.6000
0.8000
1.0000
1.2000
1500
0
1600
0
1700
0
1800
0
1900
0
2000
0
2100
0
2200
0
2300
0
2400
0
2500
0
2600
0
2700
0
2800
0
2900
0
3000
0
3100
0
3200
0
3300
0
3400
0
Cu
mu
lati
ve P
rob
abil
ity
of
Cap
acit
y
Capacity Level (MW)
Cumulative and Density Distribution For Discrete OutagesAssumed 31 1000 MW Resources with 5% Unavailability
No Resource Uncertain ty With 31 1000 MW Units Uncertain
Normal Approximation o f Resource Outages
40
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
Availability Capacity Density Distribution
Distributions of Daily Peak LoadsCombined Density Distribution For
Seven Summer Weeks
0.0000
0.0000
0.0000
0.0001
0.0001
0.0001
0.0001
0.0001
0.0002
0.0002
0.0002
1500
0
1600
0
1700
0
1800
0
1900
0
2000
0
2100
0
2200
0
2300
0
2400
0
2500
0
2600
0
2700
0
2800
0
2900
0
3000
0
3100
0
3200
0
3300
0
3400
0
Load Level (MW)
Pro
bab
ilit
y D
ensi
ty f
or
Lo
ad
0.00000
0.00010
0.00020
0.00030
0.00040
0.00050
0.00060
Pro
bab
ilit
y D
ensi
ty f
or
Ava
ilab
le C
apac
ity
Summer Peak Week Available Resources
Load
With uncertainty, more resources than 31,000 MW are neededNote: This load distribution represents 35 weekdays
Available Resource Distributions
With no resource uncertainty only 31,000 MW needed
Loss of Load> 0.1 days/year
41
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
Effect of Resources with Different EFOR
• Equivalent Forced Outage Rate (EFOR) is a statistic that describes the probability of finding a resource in a state – Available or – Unavailable
• With 100 percent available resources (EFOR = 0%)– “Fewer” resources needed to meet peak loads with a given LOLE
• With 70 percent available resources (EFOR = 30%)– “More” resources needed to meet peak loads with a given LOLE
• With a variety of resources with different EFOR statistics– Each resource’s contribution to meeting peaks can be quantified
• Removing any resource will mean that the peak load that could be served, at a given LOLE, must decrease
• Can be expressed in terms of the MW effect of the reserve margin
42
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
Available Capacity Cumulative Distribution
Distributions of Daily Peak LoadsCombined Density Distribution For
Seven Summer Weeks
0.0000
0.0000
0.0000
0.0001
0.0001
0.0001
0.0001
0.0001
0.0002
0.0002
0.0002
1500
0
1600
0
1700
0
1800
0
1900
0
2000
0
2100
0
2200
0
2300
0
2400
0
2500
0
2600
0
2700
0
2800
0
2900
0
3000
0
3100
0
3200
0
3300
0
3400
0
Load Level (MW)
Pro
bab
ilit
y D
ensi
ty f
or
Lo
ad
0.00000
0.20000
0.40000
0.60000
0.80000
1.00000
1.20000
Cu
mu
lati
ve P
rob
abil
ity
fo
r A
vail
able
Cap
acit
y
Summer Peak Week Available Resources
Note: This load distribution represents 35 weekdays LOLP for seven week composite distribution and cumulative capacity
35,000 MW Minimum Installed Resources
Loss of Load = 0.1 days/year
43
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
0.00000
0.20000
0.40000
0.60000
0.80000
1.00000
1.20000
0.0000
0.0000
0.0000
0.0001
0.0001
0.0001
0.0001
0.0001
0.0002
0.0002
0.0002
1500
0
1600
0
1700
0
1800
0
1900
0
2000
0
2100
0
2200
0
2300
0
2400
0
2500
0
2600
0
2700
0
2800
0
2900
0
3000
0
3100
0
3200
0
3300
0
3400
0
Cu
mu
lati
ve P
rob
abil
ity
fo
r A
vail
able
Cap
acit
y
Pro
bab
ilit
y D
ensi
ty f
or
Lo
ad
Load Level (MW)
Distributions of Daily Peak LoadsCombined Density Distribution For
Seven Summer Weeks
Sum m er Peak Week Available Resources
Effect of Base Resources with High EFOR
LOLP for seven week composite distribution and cumulative capacityNote: This load distribution represents 35 weekdays
Installed Resources
Loss of LoadIncreases
44
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
0.00000
0.10000
0.20000
0.30000
0.40000
0.50000
0.60000
0.70000
0.80000
0.90000
0.0000
0.0000
0.0000
0.0001
0.0001
0.0001
0.0001
0.0001
0.0002
0.0002
0.0002
1500
0
1600
0
1700
0
1800
0
1900
0
2000
0
2100
0
2200
0
2300
0
2400
0
2500
0
2600
0
2700
0
2800
0
2900
0
3000
0
3100
0
3200
0
3300
0
3400
0
Cu
mu
lati
ve P
rob
abil
ity
fo
r A
vail
able
Cap
acit
y
Pro
bab
ilit
y D
ensi
ty f
or
Lo
ad
Load Level (MW)
Distributions of Daily Peak LoadsCombined Density Distribution For
Seven Summer Weeks
Sum m er Peak Week Available Resources
Adding Resources Returns Risk to TargetAdjusted Minimum Installed Resources
Loss of Loadreturned to 0.1 days/year
Note: This load distribution represents 35 weekdays
45
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
Effect of Base Resources with Low EFOR
0.00000
0.20000
0.40000
0.60000
0.80000
1.00000
1.20000
0.0000
0.0000
0.0000
0.0001
0.0001
0.0001
0.0001
0.0001
0.0002
0.0002
0.0002
1500
0
1600
0
1700
0
1800
0
1900
0
2000
0
2100
0
2200
0
2300
0
2400
0
2500
0
2600
0
2700
0
2800
0
2900
0
3000
0
3100
0
3200
0
3300
0
3400
0
Cu
mu
lati
ve P
rob
abil
ity
fo
r A
vail
able
Cap
acit
y
Pro
bab
ilit
y D
ensi
ty f
or
Lo
ad
Load Level (MW)
Distributions of Daily Peak LoadsCombined Density Distribution For
Seven Summer Weeks
Sum m er Peak Week Available Resources
Minimum Installed Resources
Note: This load distribution represents 35 weekdays
Loss of Loaddecreased
46
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
0.00000
0.20000
0.40000
0.60000
0.80000
1.00000
1.20000
0.0000
0.0000
0.0000
0.0001
0.0001
0.0001
0.0001
0.0001
0.0002
0.0002
0.0002
1500
0
1600
0
1700
0
1800
0
1900
0
2000
0
2100
0
2200
0
2300
0
2400
0
2500
0
2600
0
2700
0
2800
0
2900
0
3000
0
3100
0
3200
0
3300
0
3400
0
Cu
mu
lati
ve P
rob
abil
ity
fo
r A
vail
able
Cap
acit
y
Pro
bab
ilit
y D
ensi
ty f
or
Lo
ad
Load Level (MW)
Distributions of Daily Peak LoadsCombined Density Distribution For
Seven Summer Weeks
Sum m er Peak Week Available Resources
Removing Resources Returns Risk to TargetAdjusted Minimum Installed Resources
Note: This load distribution represents 35 weekdays
Loss of Loadreturned to 0.1 days/year
47
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
Calculation Techniques
• Preceding illustration suggests an analytical solution– Numerical solution to intersection of distributions– Adjustment to loads or resources done first then LOLP calculated
• Illustration could be done with a Monte Carlo simulation– Monte Carlo representation would require many “draws” or
“replications” to represent the distributions– Easier to reflect conditionality (explicit correlation) with a state
specific representation– Interface constraints can be easily represented
• Interface constraint modeling can quantify when an interface limit causes a loss of load that would not otherwise occur
• Subdividing an area into several sub-area now requires monitoring and understanding relationships between multiple indices
48
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
Load Model Development for MARS
• Load Models– Loads in the Westinghouse / ABB model are input as continuous
mathematical functions• Includes low probability, higher loads
• Includes all loads (i.e., 30/70 … 50/50 … 60/40 … 90/10 … 95/05 …)
– Loads in MARS are input as discrete 8760 hourly loads• When representing a future year, highest load is 50/50
• Need to reflect larger range of possible loads
• This is done using Load Forecast Multipliers (LFU)– Seven pairs of “scaling factor” and “associated probability”– These pairs are optimized to replicate the high loads in the load model– Each replication year is now seven cases with different load levels that,
probabilistically, are summed to represent one year
49
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
Discrete Load Model Before Load Forecast Uncertainty Multipliers
50
Cumulative Daily Peak Load Distribution for Month
Based on Discrete Loads
0.500.550.600.650.700.750.800.850.900.951.00
15000 16000 17000 18000 19000 20000 21000 22000 23000
Load (MW)
Pro
bab
ility
Load Distribution
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
Load Model After Load Forecast Uncertainty Multipliers
51
Peak Load Distribution for Week
Probability of Load or Higher
0.0000.1000.2000.3000.4000.5000.6000.7000.8000.9001.000
15000 17000 19000 21000 23000 25000 27000 29000
Load (MW)
Pro
bab
ility
Load Distribution
DRAFT
Sub-Area / Multi-Area LOLE Indices
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
Multi-Area LOLE Index Characteristics
• Understanding LOLE index characteristics is important– “Control area” level LOLE indices to be used
• “Control area” indices based on individual sub-area LOLE indices
• Union of LOLE events across all sub-areas of a control area
– A “high” sub-area LOLE index may, or may not be indicative of a sub-area resource adequacy problem
• Initial resource and load balance in a sub-area– Will influence where an LOLE ‘hit’ will be assigned– Could be a sub-area problem or a control-area wide shortage
• Comparison of “Control Area” LOLE and “Sub-Area” LOLE with Venn diagrams can provide insight
53
Total area LOLE of 0.1 days per year
Total area LOLE Sub-area LOLE
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
Multi-Area LOLE Index Characteristics (cont.)
• Adding capacity in one area (or sub-area) – Will improve the LOLE index of that area the most– Will improve the LOLE of other areas
• Amount of improvements will depend on number of joint shortages
• Any intervening transmission constraints
• Sharing and priority rules can affect where benefits are “steered”
54
Total area LOLE becomes less than 0.100 days per year
Capacity added to “yellow” area
Total area LOLE of 0.1 days per year
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
Sub-Area LOLE Index Characteristics
• Generation only sub-area (no load) always has zero LOLE
• For a sub-area that has only load and no generation
– LOLE ‘hit’ will occur whenever there is a control area wide shortage
– LOLE ‘hit’ will NOT occur if another part of the control area is short and this sub-area is “export” constrained to the “short” area
• For a sub-area with BOTH load and resources
– LOLE ‘hit’ will occur whenever there is a control area wide shortage and the sub-area is deficient in that shortage hour
– LOLE ‘hit’ will NOT occur if the area is initially not in shortage
• Control area to control area considerations
– If control area has sufficient resources
• It will satisfy its own loads first
• Before providing assistance to other control areas
55
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
Understanding a Sub-Area Index
• Four sub-areas with no constraints– One sub-area has only generation– One sub-area has only load– Two sub-areas have balance of both
MARS Index Example
Little GenSome Load
More GenSome Load
All GenNo Load
No GenAll Load
Sub Area Iter 1 Iter 2 Iter 3 Iter 4 Iter 5 Iter 6 AverageResource
Q 1100 1100 900 1100 700 900R 0 0 0 0 0 0S 350 450 510 450 510 490T 549 355 549 450 549 549
LoadQ 0 0 0 0 0 0R 1000 1000 1000 1000 1000 1000S 500 500 500 500 500 500T 500 500 500 500 500 500
Surplus MW -1 -95 -41 0 -241 -61Pool LOLE Yes Yes Yes No Yes Yes
Pool LOLE 'Hit' 1 1 1 0 1 1 0.83Q LOLE 'Hit' 0 0 0 0 0 0 0.00R LOLE 'Hit' 1 1 1 0 1 1 0.83S LOLE 'Hit' 1 1 0 0 0 1 0.50T LOLE 'Hit' 0 1 0 0 0 0 0.17
56
T
Q R
S
R = 0.83S = 0.50T = 0.17Q = 0.00
Venn Diagram for this example
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
Multiple Control Area LOLE Indices
• Indices for multiple control areas calculated identically– LOLE for each control areas could be brought to 0.100 days/year
• Sometimes Area ‘X’ is deficient and sometimes Area ‘Y’ is deficient
• Sometimes both are deficient simultaneously
• Union of all events for combined XY area may be 0.162 days per year– Adding more capacity to combined area XY
• Could bring the LOLE of XY area to 0.100 days per year
• Individual area LOLE would then be less than 0.10 days per year
• Capacity could be added in either area X or area Y if there is no area criterion
– An area specific criterion may require some capacity to be added in each– No transmission constraints are even considered at this stage
57
X YEach area LOLE is 0.100 days per year
X YUnion of LOLE forBoth is 0.162 days per year
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
Multiple Control Area and Tie Benefits
• Other areas, say area “Z,” can provide tie benefits to– Area “X” (preference) or – Area “Y” (preference)– Both areas “X” and “Y” (no preference)
• Transmission interface from “Y” to “X” could affect the sharing of tie benefits from “Z”– If areas “X” and “Y” are deficient at the same time,– Some of the tie benefits that would have been shared with “X” can’t get
there and “Y” get a disproportionate share of the benefits
58
X Y Z
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
Contract Modeling
• Multi-Area models can represent contracts between control areas– Define originating sub-area– Define destination sub-area– Designate a transmission interface link as the contract path
• Removal / Transfer reduction of contract path– Contract flow has priority rights on contract path link– Uses as much transmission capacity as necessary
• Contracting allows for improving reliability in one area vis-à-vis another area– Contracted capacity treated as the exporter’s native load– Contracted capacity treated as the importer’s native capacity
59
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
Monte Carlo Indices
• Monte Carlo simulations are the result of many replications– Some replications have un-resolvable shortages– Shortages require loss of customer loads– Shortages are the basis of a Loss of Load event
• With 10,000 years replicated (365 days per year at risk)– If 1,000 days result in shortages
LOLE = (1000 days with Loss of Load) / (10,000 years)
LOLE = 0.100 days per year
• Convergence criterion for a Monte Carlo– Tells the model that enough replications have been done– Resulting index is “stable” (as defined by the criterion)
60
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
Monte Carlo: Year-to-Year Variability
61
Distribution of Loss of-Load Days in 10,000 Simulated Years
(1000 Loss-of-Load-Days => Expectation of 0.100 Days/Year)
0
20
40
60
80
100
120
1 6 11 16 21 26 31 36 41 46
Number of Loss-of-Load-Days Lost in Simulated Year
Occ
ura
nce
s o
f T
his
Man
y D
ays
0.100 days per year (expected value)
Goes out to10,000 years
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
Bringing an Area to Criterion: Resources
• Add or remove generation– Specific resources would need to be added or removed– Each resource has its own characteristics
• Size
• EFOR
– Depending upon resource characteristics, the effect of one MW may not be equal to a different MW
• If future, unspecified, resource additions are needed– A proxy units is used– Characteristics are “typical” of the rest of the system– Neutral impact on an area’s reserve metric (i.e., reserve margin)
62
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
Bringing an Area to Criterion: Loads
63
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT
Deliverability
• All resources are assumed to be fully deliverable within a sub-area– Resources are assumed able to put capacity up on the grid– Deliverability between sub-areas are assumed to be limited only
by pre-specified transmission interface limits– Load within a sub-area is assumed able to receive and distribute
energy / capacity from the grid to customers
• Real world conditions may affect the validity of these assumptions depending on the actual system configuration
64
Basic Resource Adequacy Study ConceptsMay 14, 2009
© 2009 ISO New England Inc. DRAFT 65
Questions?