Basic Project Management on PMI Framework 2nd Rel

65
 Basic Project Management Training on PMI® Framework Organized by Internal Support, Project Management Office Compliance, Technology Division Robi Axiata Bangladesh Trainer Mufakharul Islam, PMP®, MCITP

description

Project Management Guideline

Transcript of Basic Project Management on PMI Framework 2nd Rel

  • Basic Project Management

    Training on PMI Framework

    Organized by Internal Support, Project Management Office

    Compliance, Technology Division

    Robi Axiata Bangladesh

    Trainer

    Mufakharul Islam, PMP, MCITP

  • Basic Project Management Training on PMI Framework

    2 Monday, July 16, 2012 Security Company Internal

    Table of Contents

    Module 01: Introduction to Project Management ......................................................................... 8

    1.1 Introduction ............................................................................................................................ 9

    1.2 Do and Dons for this training ................................................................................................. 9

    1.3 Global Standard of Project Management ............................................................................... 9

    1.4 What is Project? .................................................................................................................... 10

    1.5 What are Project Management, Program and Portfolio? ..................................................... 10

    1.6 Project Management Office (PMO) ...................................................................................... 13

    1.7 Projects and Strategic Planning ............................................................................................ 14

    1.8 Operational Activity Vs Project Management ...................................................................... 14

    1.9 Enterprise Environmental Factors (EEF) ............................................................................... 14

    1.10 Organizational Process Asset (OPA) ...................................................................................... 14

    1.11 Stakeholders ......................................................................................................................... 15

    1.12 Organizational Structure ....................................................................................................... 15

    1.13 PMI Standard Project Management ..................................................................................... 17

    Module 02: Project Initiation ...................................................................................................... 20

    2.1 Introduction .......................................................................................................................... 21

    2.2 Project Management Roles and Responsibility .................................................................... 21

    2.3 How a project initiate ........................................................................................................... 22

    2.4 Feasibility Study .................................................................................................................... 22

    2.5 Project Charter ...................................................................................................................... 22

    2.6 Project Kick off ...................................................................................................................... 23

    2.7 Planning Project .................................................................................................................... 23

    2.8 Team Activity for Project Initiation ....................................................................................... 24

    Module 03: Project Scope Management ..................................................................................... 25

    2.1 Introduction .......................................................................................................................... 26

    2.2 Collect Requirements ............................................................................................................ 26

    2.2.1 Source of Requirements: .............................................................................................. 26

    2.2.2 Tools and Techniques for collect Requirements: .......................................................... 26

    2.2.3 Output from collect Requirements: .............................................................................. 27

    2.3 Identify Scope ....................................................................................................................... 28

    2.3.1 Source of Scope ............................................................................................................. 28

    2.3.2 Tools and Techniques for identify scope ...................................................................... 28

    2.3.3 Output from collect Requirements: .............................................................................. 29

  • Basic Project Management Training on PMI Framework

    3 Monday, July 16, 2012 Security Company Internal

    2.4 Defining Assignment from Scope .......................................................................................... 29

    2.4.1 Source of Defining Assignment ..................................................................................... 29

    2.4.2 Tools and Techniques for identify scope ...................................................................... 29

    2.4.3 Output from Defining Assignment ................................................................................ 30

    2.5 Verify and Validate Scope ..................................................................................................... 30

    2.5.1 Source of verification and Validation ............................................................................ 30

    2.5.2 Tools and Techniques for verify and validate scope ..................................................... 30

    2.5.3 Output from Verify and Validate Scope: ....................................................................... 30

    2.6 Control Scope ........................................................................................................................ 30

    2.6.1 Source of Control Scope ................................................................................................ 30

    2.6.2 Tools and Techniques for identify scope ...................................................................... 30

    2.6.3 Output from collect Requirements: .............................................................................. 30

    2.7 Team Activity for Project Management ................................................................................ 31

    Module 04: Project Time Management ....................................................................................... 32

    4.1 Introduction .......................................................................................................................... 33

    4.2 Define Activities .................................................................................................................... 34

    4.2.1 Source of Define Activities: ........................................................................................... 35

    4.2.2 Tools and Techniques for Define Activities: .................................................................. 35

    4.2.3 Output from collect Requirements: .............................................................................. 35

    4.3 Sequencing and Grouping Activities ..................................................................................... 36

    4.3.1 Source of Sequencing and Grouping Activities ............................................................. 36

    4.3.2 Tools and Techniques for Sequencing and Grouping Activities .................................... 36

    4.3.3 Output from Sequencing and Grouping Activities: ....................................................... 38

    4.4 Estimate Duration and Cost .................................................................................................. 38

    4.4.1 Source of Estimate duration and Cost .......................................................................... 38

    4.4.2 Tools and Techniques for Estimate duration and Cost ................................................. 38

    4.4.3 Output from Estimate duration and Cost ..................................................................... 39

    4.5 Develop Schedule .................................................................................................................. 39

    4.5.1 Consideration for a Complete Schedule ....................................................................... 39

    4.6 Control Schedule ................................................................................................................... 39

    4.6.1 Source of Control Schedule ........................................................................................... 39

    4.6.2 Tools and Techniques for Control Schedule: ................................................................ 40

    4.6.3 Output from Control Schedule:..................................................................................... 40

    4.7 Team Activity for Project Time Management ....................................................................... 40

    Module 05: Project Quality Management ................................................................................... 41

  • Basic Project Management Training on PMI Framework

    4 Monday, July 16, 2012 Security Company Internal

    5.1 Introduction .......................................................................................................................... 42

    5.1.1 Project Quality Issues .................................................................................................... 42

    5.2 Plan Quality ........................................................................................................................... 42

    5.2.1 Source of Plan Quality: .................................................................................................. 43

    5.2.2 Tools and Techniques for Plan Quality: ........................................................................ 43

    5.2.3 Output from Plan Quality: ............................................................................................. 44

    5.3 Perform Quality Assurance ................................................................................................... 44

    5.3.1 Source of Perform Quality Assurance ........................................................................... 44

    5.3.2 Tools and Techniques for Perform Quality Assurance .................................................. 44

    5.3.3 Output from Perform Quality Assurance ...................................................................... 44

    5.4 Perform Quality Control ........................................................................................................ 45

    5.4.1 Source of Perform Quality Control ............................................................................... 45

    5.4.2 Tools and Techniques for Perform Quality Control ...................................................... 45

    5.4.3 Output from Perform Quality Control .......................................................................... 46

    Module 06: Resource and Cost Management .............................................................................. 47

    6.1 Introduction Human Resource Management .................................................................... 48

    6.2 Develop Human Resource Plan ............................................................................................. 48

    6.2.1 Source of Human Resource Plan: .................................................................................. 48

    6.2.2 Tools and Techniques for Human Resource Plan: ........................................................ 48

    6.2.3 Output from Human Resource Plan: ............................................................................. 49

    6.3 Acquire Project Team ............................................................................................................ 49

    6.3.1 Source of Acquire Project Team.................................................................................... 49

    6.3.2 Tools and Techniques for Acquire Project Team .......................................................... 49

    6.3.3 Output from Acquire Project Team .............................................................................. 50

    6.4 Develop Project Team ........................................................................................................... 50

    6.4.1 Source of Develop Project Team ................................................................................... 50

    6.4.2 Tools and Techniques for Develop Project Team ......................................................... 50

    6.4.3 Output from Develop Project Team .............................................................................. 51

    6.5 Manage Project Team ........................................................................................................... 51

    6.5.1 Source of Manage Project Team ................................................................................... 51

    6.5.2 Tools and Techniques for Manage Project Team.......................................................... 51

    6.5.3 Output from Manage Project Team .............................................................................. 51

    6.6 Collect and Utilization of Non-Human Resources ................................................................. 51

    6.7 Cost Management Estimate Cost ....................................................................................... 52

    6.7.1 Source of Estimate Cost ................................................................................................ 52

  • Basic Project Management Training on PMI Framework

    5 Monday, July 16, 2012 Security Company Internal

    6.7.2 Tools and Techniques for Estimate Cost ....................................................................... 52

    6.7.3 Output from Estimate Cost ........................................................................................... 52

    6.8 Cost Management Determine Budget ............................................................................... 52

    6.8.1 Source of Determine Budget ......................................................................................... 52

    6.8.2 Tools and Techniques for Determine Budget ............................................................... 53

    6.8.3 Output from Determine Budget ................................................................................... 53

    6.9 Cost Management Cost Control ......................................................................................... 53

    6.9.1 Source of Cost Control .................................................................................................. 53

    6.9.2 Tools and Techniques for Cost Control ......................................................................... 53

    6.9.3 Output from Cost Control ............................................................................................. 54

    Module 07: Communication Management .................................................................................. 55

    7.1 Introduction .......................................................................................................................... 56

    7.2 Identify Stakeholder .............................................................................................................. 56

    7.2.1 Source of Identify Stakeholder: .................................................................................... 56

    7.2.2 Tools and Techniques for Identify Stakeholder: ........................................................... 56

    7.2.3 Output from Identify Stakeholder: ............................................................................... 57

    7.3 Plan Communication ............................................................................................................. 57

    7.3.1 Source of Plan Communication ..................................................................................... 57

    7.3.2 Tools and Techniques for Plan Communication ........................................................... 57

    7.3.3 Output from Plan Communication ................................................................................ 58

    7.4 Distribute Information .......................................................................................................... 58

    7.4.1 Source of Distribute Information .................................................................................. 58

    7.4.2 Tools and Techniques for Distribute Information ......................................................... 58

    7.4.3 Output from Distribute Information ............................................................................. 58

    7.5 Manage Stakeholders Expectations ...................................................................................... 58

    7.5.1 Source of Manage Stakeholders Expectations .............................................................. 58

    7.5.2 Tools and Techniques for Manage Stakeholders Expectations .................................... 58

    7.5.3 Output from Manage Stakeholders Expectations ......................................................... 59

    7.6 Report Performance.............................................................................................................. 59

    7.6.1 Source of Report Performance ..................................................................................... 59

    7.6.2 Tools and Techniques for Report Performance ............................................................ 59

    7.6.3 Output from Report Performance ................................................................................ 59

    Module 08: Risk Management .................................................................................................... 60

    8.1 Introduction .......................................................................................................................... 61

    8.2 Plan Risk Management and Identify Risk .............................................................................. 61

  • Basic Project Management Training on PMI Framework

    6 Monday, July 16, 2012 Security Company Internal

    8.2.1 Source of Plan Risk Management and Identify Risk ...................................................... 61

    8.2.2 Tools and Techniques for Plan Risk Management and Identify Risk ............................ 61

    8.2.3 Output from Plan Risk Management and Identify Risk ................................................. 62

    8.3 Perform Qualitative Risk Analysis ......................................................................................... 62

    8.3.1 Source of Perform Qualitative Risk Analysis ................................................................. 62

    8.3.2 Tools and Techniques for Perform Qualitative Risk Analysis ........................................ 62

    8.3.3 Output from Perform Qualitative Risk Analysis ............................................................ 62

    8.4 Perform Quantitative Risk Analysis ....................................................................................... 62

    8.4.1 Source of Perform Quantitative Risk Analysis .............................................................. 62

    8.4.2 Tools and Techniques for Perform Quantitative Risk Analysis ..................................... 62

    8.4.3 Output from Perform Quantitative Risk Analysis ......................................................... 62

    8.5 Plan Risk Response ................................................................................................................ 63

    8.5.1 Source of Plan Risk Response ........................................................................................ 63

    8.5.2 Tools and Techniques for Plan Risk Response .............................................................. 63

    8.5.3 Output from Plan Risk Response .................................................................................. 63

    8.6 Monitor and Control Risk ...................................................................................................... 63

    8.6.1 Source of Monitor and Control Risk .............................................................................. 63

    8.6.2 Tools and Techniques for Monitor and Control Risk .................................................... 63

    8.6.3 Output from Monitor and Control Risk ......................................................................... 64

    Module 09: Closing a Project ...................................................................................................... 64

    9.1 Introduction .......................................................................................................................... 65

    9.2 Project Closing What need to ensure ................................................................................ 65

  • Basic Project Management Training on PMI Framework

    7 Monday, July 16, 2012 Security Company Internal

    Copyright Robi Axiata Bangladesh Limited

    July 2012

    All Right Reserved

    No part of this publication may be reproduced, stored in retrieval system, or transmitted, in

    any form or by any means, electronic, mechanical, photocopying, recording, or otherwise,

    without the prior written permission of Robi Axiata, Technology PMO

    The names of all companies and characters used in these materials are purely fictional. Any

    resemblance to any existing or no longer existing company or living or dead person is not intended,

    and is purely coincidental.

    PMI is a service and trademark of the Project Management Institute, Inc., which is registered in the

    United States and other nations.

    PMBOK is a trademark of the Project Management Institute, Inc., which is registered in the United

    States and other nations.

    All materials used in this training guide, solely used for Robi Axiata Bangladesh Limited internal

    training. This material delivered as a part of non-financial internal competency development session.

    Project Management Office

    Technology PMO, Compliance,

    Technology

    Robi Axiata Bangladesh Limited

  • Basic Project Management Training on PMI Framework

    8 Monday, July 16, 2012 Security Company Internal

    Module 01: Introduction to Project Management

  • Basic Project Management Training on PMI Framework

    9 Monday, July 16, 2012 Security Company Internal

    1.1 Introduction

    The course is designed based on practical experience on Telecommunication / ICT project

    management best practices for Project Manager, Project Associate, Project Coordinator and Project

    Team Member to add the best value for the project and organization. This interactive training will

    deliver project management standards based on PMI USA, Global and Local best practices.

    Todays fast growing technology driven industry demand adequate knowledge on project

    management not only for project managers but also for all stakeholders. Faster time to market,

    efficient costing and quality product delivery are main challenges for todays competitive market.

    Having good project management skills does not mean we have no problems, but good project

    management discipline is the way to overcome these shortcomings.

    1.2 Do and Dons for this training

    Donts

    a. We dont need laptops for this training; please do not open your laptop

    b. Please do not use your mobile phone on Training Premises

    c. Please do not panicked in case of Fire or Earthquakes, follow the safety instructions

    Dos

    a. You can leave any time; based on your interest or urgency

    b. Please put your name and phone number clearly on Signature Sheet.

    c. You are allowed to ask any question regarding Project Management

    d. Participate and being active!!

    1.3 Global Standard of Project Management

    There are many standards for Project management based on industry, region and organizations, but

    few are accepted by all industry leaders. The following standards are not conflicting but

    complementary.

    a. Project Management Institute (PMI), USA affiliated standard

    I. CAPM (Certified Associate in Project Management)

    II. PMP (Project Management Professional)

    III. PgMP (Program Management Professional)

    IV. PMI-ACP (Agile Certified Practitioner)

    V. PMI-RMP (Risk Management Professional)

    VI. PMI-SP (Scheduling Professional)

    b. PRojects IN Controlled Environments (PRINCE2) [Used extensively by the UK Government]

    c. MPMM (Project Management Methodology Manager)

    d. UPMM (Unified Project Management methodology)

  • Basic Project Management Training on PMI Framework

    10 Monday, July 16, 2012 Security Company Internal

    e. MITP Managing Information Technology Projects

    1.4 What is Project?

    As per PMBOK guide 4th edition A project is a temporary endeavor undertaking to create a

    unique product, service or result.

    Temporary means the project has a definite beginning and ending (finite duration).

    Temporary does not necessary indicate a project of short duration.

    Unique means the product or service is different in some distinguishing way from all similar

    products or services.

    The purpose of a project is to attain its objective and then terminate.

    Numerous project management guru agree on two additional characteristics for describing

    project

    Requires coordination of interrelated activities (Complex enough to require a team)

    Is Progressively Elaborated i.e. proceeds in steps or increments. The words progressively

    detailing and rolling wave planning is also used to describe the same phenomenon.

    As per PMBOK guide 4th edition, A project can create:

    A product that can be either a component of another item or an item itself

    A capability to perform a service (e.g. a business function that supports production

    or distribution)

    A result such as an outcome or document (e.g. a research project that develops

    knowledge that can be used to determine whether a trend is present or a new

    process will benefit society)

    PMBOK = Project Management Body of Knowledge, a PMI authorised body for project management

    standardization.

    1.5 What are Project Management, Program and Portfolio?

    Project Management is the application of knowledge, skills, tools and techniques to project

    activities to meet project requirements. Managing projects typically includes:

    a. Identify Requirements

    b. Addressing various needs, concerns and expectations of the stakeholders as the project

    is planned and carried out.

    c. Balancing the competing project constraints includes, but not limited to

    Scope

    Quality

    Schedule

    Budget

  • Basic Project Management Training on PMI Framework

    11 Monday, July 16, 2012 Security Company Internal

    Resource and

    Risk

    A globally recognize Jargon for Project Management is Triple Constraints, is as follows.

    It means a project manager / project team will satisfy stakeholders scope (requirement) within

    committed budget (cost) and in given timeline maintaining agreed quality.

    Program and Program Management

    As per PMI A Program is a group of projects managed in a coordinated way to obtain

    benefits not available from managing them individually.

    Program Management is centralized, coordinated management to achieve a programs

    strategic objectives and benefits.

    Portfolio

    A Portfolio is a collection of projects, programs or other work that is grouped together to

    facilitated effective management and to meet strategic business objectives.

  • Basic Project Management Training on PMI Framework

    12 Monday, July 16, 2012 Security Company Internal

    Relationship among Project, Program and Portfolio

  • Basic Project Management Training on PMI Framework

    13 Monday, July 16, 2012 Security Company Internal

    1.6 Project Management Office (PMO) Project Management Office (PMO) is an organizational body or entity assigned various responsibility

    related to the centralized and coordinated management of those projects under its domain. The

    responsibilities of a PMO can range from providing project management support functions actually

    being responsible for the direct management of a project.

    A primary function of a PMO is to support Project Manager in a variety of ways which may include,

    but not limited to:

    a. Managing shared resources across all projects administrated by PMO

    b. Identifying and developing project management methodology, best practice, and standard

    c. Coaching, Mentoring, Training, and Oversight

    d. Monitoring Compliance with project management standards, policies, procedures, and

    templates via project audits

    e. Developing and managing project policies, procedures, templates, and other shared

    documentations

    f. Coordinating communication across projects

  • Basic Project Management Training on PMI Framework

    14 Monday, July 16, 2012 Security Company Internal

    1.7 Projects and Strategic Planning Projects are often utilized as a means of achieving an organizations strategic plan. Projects are

    typically authorized as a result of one or more of the following strategic considerations:

    a. Market Demand

    b. Strategic Opportunity / Business Need

    c. Customer Request

    d. Technology Advance

    e. Legal Requirements

    1.8 Operational Activity Vs Project Management

    Operations are an organizational function performs the ongoing execution of activities that

    produced the same product or provide a repetitive service. For Robi:

    - Billing System

    - Call Center Operation

    - WIC operation

    Though temporary in nature, projects can help achieve the organizational goals when they are

    aligned with the organizational strategy. Projects required Project Management while Operation

    required business process management. Project can intersect with operation at various points

    during the product lifecycles. For Robi Projects are:

    - OCS migration

    - Regionalization

    1.9 Enterprise Environmental Factors (EEF)

    All projects occur within an environment that influences the potential for success. The factors in this

    environment may help or hinder project outcomes and may include, but are not limited to, the

    followings:

    - Organizational Culture, Structure and Processes

    - Government or industry standards (BTRC, BOI, Bangladesh Bank etc)

    - Infrastructure

    - Existing infrastructure and existing human resource

    - Personal administration

    - Company work authorization system

    - Market place conditions

    - Stakeholder risk tolerance

    - Political climate

    - Organizations established communication channels

    - Commercial database

    - Project Management Information Systems

    1.10 Organizational Process Asset (OPA)

    Any or all process related to assets, from any or all of the organizations involved in the project that

    are or can be used to influence the projects success. This process asset includes formal and informal

  • Basic Project Management Training on PMI Framework

    15 Monday, July 16, 2012 Security Company Internal

    plans, policies, procedures and guidelines. Process assets also include the organizations knowledge

    bases such as lesson learned and historical information. Following are example but not limited to:

    - All past projects historical data

    - Formally recorded Lesson Learned

    - Any formal or informal experiences

    1.11 Stakeholders

    A project Stakeholder is anyone (Individual or organization) that is involved in a project, may be

    affected by the results of the project or may exert influences over the project.

    PMI emphasizes the importance of identifying and managing stakeholders. Key stakeholders are:

    a. Project Manager

    b. Customer / User

    c. Sponsor (Provides funding and other critical resources)

    d. Project team

    e. PMO

    f. Performing Organization

    1.12 Organizational Structure

    Functional Organization

    Classic functional organization shown below is a hierarchy where each employee has one clear

    superior. Stuff members are grouped by specialty, such as Technology, Market Operation, Finance,

    and Human Resource at the Top. Each department in a functional organization will do its project

    work independent of other departments.

    Fig Functional Organization

    Matrix Organization

    Matrix organizations are blend of functional and projectized characteristics. Weak matrices maintain

    many of the characteristics of a functional organization and the project manager role is more of a

    coordinator or expediter than that of a true project manager.

  • Basic Project Management Training on PMI Framework

    16 Monday, July 16, 2012 Security Company Internal

    Strong matrices have many of the characteristics of the projectized organization, and can have full

    time project manager with considerable authority and full time project administrative staffs.

    Balance Matrices organization recognizes the need for a project manager; it does not provide the

    project manager with full authority over the project and project funding.

    Fig Weak Matrices Organization

    Fig Balance Matrices Organization

    Fig Strong Matrices Organization

    Projectized Organization

  • Basic Project Management Training on PMI Framework

    17 Monday, July 16, 2012 Security Company Internal

    In the projectized organization, team members are often co-located, most of the organizations

    resources are involved in project work, and project managers have a great deal of independence and

    authority. Projectized organizations often have organization units called departments, but these

    groups either report directly to the project manager or provide support services to the various

    projects.

    Fig Projectized Organization

    Organizational Influence on Projects

    1.13 PMI Standard Project Management

    PMI defines project management in 5 Process Groups

    Initiating

    Planning

    Execution

    Monitoring and Controlling

    Closing

  • Basic Project Management Training on PMI Framework

    18 Monday, July 16, 2012 Security Company Internal

    Fig : Interaction with in Project Management Process Groups.

    There are 9 knowledge areas in PMI standard Project Management

    Integration

    Scope

    Time

    Cost

    Quality

    Human Resource

    Communication

    Risk

    Procurement

    This 9 knowledge area and 5 process group distributed among 42 processes.

  • Basic Project Management Training on PMI Framework

    19 Monday, July 16, 2012 Security Company Internal

  • Basic Project Management Training on PMI Framework

    20 Monday, July 16, 2012 Security Company Internal

    Module 02: Project Initiation

  • Basic Project Management Training on PMI Framework

    21 Monday, July 16, 2012 Security Company Internal

    2.1 Introduction

    The purpose of Project Initiation is to begin to define the overall parameters of a project and

    establish the appropriate project management and quality environment required to complete the

    project.

    Development of the Project Charter is a pivotal starting point for the project, establishing the project

    definition that will serve as the foundation for all future efforts. The completion of this process is

    marked by the Project Kick-off Meeting, in which the Project Manager presents the Project Charter.

    Also during Project Initiation, a high-level Project Schedule is developed as the roadmap to more

    detailed Project Planning and Project Execution and Control. This high-level schedule will be refined

    over time, and will serve as the primary source of information regarding project status and progress.

    An accurate, realistic, and complete schedule, rigorously maintained, is essential to the success of a

    project.

    Sponsorship of the project must be confirmed or gained during Project Initiation. Having a Project

    Sponsor, and securing approval early in the project management lifecycle, helps to ensure a

    commitment to the project.

    2.2 Project Management Roles and Responsibility

    Executive Sponsor / Sponsor: is a manager with demonstrable interest in the outcome of the project

    who is responsible for securing spending authority and resources for the project

    Steering Committee / Management Committee: generally includes management representatives

    from the key organizations involved in the project oversight and control, and any other key

    stakeholder groups that have special interest in the outcome of the project

    Customer: comprise the business units that identified the need for the product or service the project

    will develop

    Stakeholder: are all those groups, units, individuals, or organizations, internal or external to our

    organization, which are impacted by, or can impact, the outcomes of the project.

    Project Team Member: are responsible for executing tasks and producing deliverables as outlined in

    the Project Plan and directed by the Project Manager, at whatever level of effort or participation has

    been defined for them

    Corporate/Enterprise PMO/PMO: A Project Management office is an organizational body or entity

    assigned various responsibilities related to the centralized and coordinated management of those

    projects under its domain. The responsibilities of a PMO can range from providing project

    management support functions to actually being responsible for direct management of Project.

  • Basic Project Management Training on PMI Framework

    22 Monday, July 16, 2012 Security Company Internal

    The projects supported or administered by the PMO may not be related, other than by being

    managed together. The specific form, function, and structure of PMO is dependent upon the needs

    of the organization that it supports.

    2.3 How a project initiate

    It depends, how a project will be initiate. Based on organizational culture and overall control on

    business environment, followings are some key areas from where the Project Initiate.

    a. Organizational Strategy: Is the most common way to initiate a planned project in corporate

    world. Depending on various criteria, organization prepares them for next year and decides

    on its investment areas. Business units support the organization with their proposal and

    Business control units identifies the best area to invest depending on organizations

    capability.

    b. Regulatory Directives: This is common for all organizations, some initiative from regulatory

    directives. Most of the cases these initiatives are mandatory to implement on a given period

    of time.

    c. Market Competitiveness: Competition is now everywhere and to accept the competitor

    challenges, organizations initiate projects. It could be price war, value proposition, product

    range or brad value.

    d. Risk Minimization: To reduce the business risk and for long sustainability, organizations

    initiates projects. It may be to secure the investment, reduce or minimize the regulatory

    penalty or legal issues.

    e. Any adhoc enhancement on the business

    2.4 Feasibility Study

    As per Wikipedia Feasibility studies aim to objectively and rationally uncover the strengths and

    weaknesses of the existing business or proposed venture, opportunities and threats as presented by

    the environment, the resources required to carry through, and ultimately the prospects for success.

    In its simplest terms, the two criteria to judge feasibility are cost required and value to be attained.

    As such, a well-designed feasibility study should provide a historical background of the business or

    project, description of the product or service, accounting statements, details of the operations and

    management, marketing research and policies, financial data, legal requirements and tax

    obligations. Generally, feasibility studies precede technical development and project

    implementation.

    2.5 Project Charter

    Project charter is a written document that formally recognizes and authorizes the existence of ne a

  • Basic Project Management Training on PMI Framework

    23 Monday, July 16, 2012 Security Company Internal

    project. It establishes a partnership between the performing organization and the requesting

    organization (or customer, in the case of external projects). The approved project charter formally

    initiates the project. A project manager is defined and assigned as early in the project as is feasible,

    preferably while the project charter is being developed and always prior to the start of planning. It is

    recommended that project manager participate in the development of project charter, as the

    project charter provides the project manager with the authority to apply resource to project

    activities.

    A Project Charter may have:

    Projects high level scope / Project statement

    Mention out of scope

    Identify Project Manager

    Identify key stakeholders

    Project Key information like ROI, TCO etc.

    2.6 Project Kick off The objective of a project kick off is to produce a plan which defines how to perform the Project

    Initiation Stage itself, in a way that ensures the involvement and commitment of the key people who

    see the need for the project and also of those who will fund it, takes account of the background to

    the project and of previous and related initiatives, establishes a team to carry out the Project

    Initiation Stage, so that a clear and explicit plan is available for setting up the project.

    Activities of project kick off:

    Introduce Project Manager and Project Team

    Briefing key resources regarding the project

    Share High Level Scope and Out of scope

    Identify high level stakeholders

    2.7 Planning Project Project Management Plan defines how the project will be executed, monitored, controlled and

    closed. It is a key integrative document that is usually developed by the entire team.

    Subsidiary Plans

    Scope Management

    Schedule Management

    Cost Management

    Quality Management

    Staffing / Human Resource / Resource Management

    Communication Management

    Risk Management

    Procurement

  • Basic Project Management Training on PMI Framework

    24 Monday, July 16, 2012 Security Company Internal

    2.8 Team Activity for Project Initiation

    Robi Axiata decided to launch 3G Services for its valued customer, design a simple project charter

    for this project. Only the information heads (No detail informations)

    It will be a :

    a. Team Work

    b. Expected time 10 min

    c. Discussion 10 min

  • Basic Project Management Training on PMI Framework

    25 Monday, July 16, 2012 Security Company Internal

    Module 03: Project Scope Management

  • Basic Project Management Training on PMI Framework

    26 Monday, July 16, 2012 Security Company Internal

    2.1 Introduction Project scope management ensures that a project includes all the work required but only the work

    required to complete the project successfully. In other words, proper scope management carefully

    identifies what is and what is not included in the project.

    In the project context, the term Scope can refer to:

    Product Scope: The future and functions that characterize a product, service, or result

    Project Scope: The work that needs to be accomplished to deliver a product, service, or result with

    the specified features and functions.

    2.2 Collect Requirements Collect requirements involves defining and managing customers, sponsors and other stakeholders

    expectations. These requirements must be captured in sufficient detail to be measured during

    project execution. Requirements become the foundation for many other vital project management

    activities.

    2.2.1 Source of Requirements:

    a. Project Charter: The charter provides the high level project and product requirements. As

    such , it forms a starting point for the development if detail requirements

    b. Stakeholder Register: Stakeholder register identifies stakeholders who can provide

    information needed to develop detailed requirements.

    2.2.2 Tools and Techniques for collect Requirements:

    a. Interviews: An interview is a formal or informal approach to discover information from

    stakeholder by taking to them directly. It is typically performed by asking prepared and

    spontaneous questions and recording the response. Interviews are often conducted One-

    to-One, but may involve multiple interviews and/or multiple interviewers.

    b. Focus Group Discussion (FGD): Interactive conversational discussions guided by trained

    moderators with pre-selected stakeholders and subject matter experts.

    Functional Scope

    Non Functional Scope

    Bubble Scope

    Product Scope SCOPE

    Scope Creep

    Project Scope

    Out of Scope Requirem

    ent

  • Basic Project Management Training on PMI Framework

    27 Monday, July 16, 2012 Security Company Internal

    c. Facilitated Workshop: Requirements workshops are focused sessions that bring key cross

    functional stakeholders together to define product requirements. Workshops are considered

    a primary technique for quickly defining cross-functional requirements and reconciling

    stakeholder differences. Because of their interactive group nature, well-facilitated sessions

    can build trust, foster relationships, and improve communication among the participants

    which can lead to increase stakeholder consensus. Another benefit of this technique is that

    issues can be discovered and resolved more quickly than in individual sessions.

    d. Group Creativity Technique

    I. Brainstorming

    II. Nominal group discussion

    III. Delphi Technique: Experts answer questions anonymously and the summarized

    results are provided to the group

    IV. Idea/Mind mapping

    V. Affinity Diagram: A technique for sorting a large number of detailed, specific ideas

    into logical groups.

    e. Group Decision Making Techniques

    I. Unanimity

    II. Majority

    III. Plurality

    IV. Dictatorship

    f. Questionnaires and surveys: Questionnaires and surveys are written sets of questions

    designed to quickly accumulate information for a wide number of respondents. Questioners

    and/or surveys are most appropriate with broad audiences, when quick turnaround is

    needed, and where statistical is appropriate.

    g. Observation: Observations provide a direct way of viewing individuals in their

    environmental and how they perform their jobs or tasks and carry out processes. It is

    practically helpful for detailed processes when the people that use the product have difficult

    or are reluctant to articulate there requirements.

    h. Prototypes: Prototyping is a method of obtaining early feedback on requirements by

    providing a working model of the expected product before actually building it. Since

    prototypes are tangible, it allows stakeholders to experiment with a model of their final

    product rather than only discussing abstract relationship of their requirements.

    2.2.3 Output from collect Requirements:

    a. Requirement Documentation: Requirement documentation describes how individual

    requirement meet the business need for the project. Requirements may start out at a high

    level and become progressively more detailed as more is known. Before being baselines,

    requirements must be unambiguous (measurable and testable), traceable, complete,

    consistent, and acceptable to key stakeholders.

  • Basic Project Management Training on PMI Framework

    28 Monday, July 16, 2012 Security Company Internal

    b. Requirement Management Plan: Requirement management plan documents how

    requirements will be analyzed, documented, and managed throughout the project.

    Components of the requirements management plan can be in include, but not limited to:

    - How requirements activities will be planned, tracked, and reported

    - Configuration management activities such as how changes to the product, service,

    or result requirements will be initiated, how impacts will be analyzed, how they will

    be tracked, traced and reported, as well as the authorization level required to

    approve these changes.

    - Requirement Prioritization Process

    - Product Matrices that will be used and rationale for using them

    - Traceability structure

    c. Requirement Traceability Matrix: Requirement traceability matrices are a table that links

    requirements to their origin and traces them throughout the project life cycle.

    2.3 Identify Scope Scope identification produces a written, detailed scope statement that is crucial to project success.

    This statement represents an agreement between the project team and the customer. The project

    team and appropriate stakeholders conduct a needs assessment and use it as the basis to develop

    written project requirements. Assumptions, constraints and risks are identified and validated as

    necessary.

    2.3.1 Source of Scope

    a. Project Charter

    b. Requirements Documentation

    c. Organizational Process Assets

    2.3.2 Tools and Techniques for identify scope

    a. Expert Judgment: Expert judgment is often used to analyze the information needed to

    develop the project scope statement. Such judgment and expertise is applied to any

    technical details. Such expertise is provided by any group or individual with specialized

    knowledge, training, and is available from many sources, includes:

    - Other units within organization

    - Consultants

    - Stakeholders, including customer or sponsors

    - Professional or Technical associates

    - Industry groups

    - Subject matter experts

    b. Product Analysis: Translating project objectives into measurable deliverables and

    requirements using techniques such as product breakdown, system engineering, value

    engineering, functional analysis and quality functions deployment.

    c. Alternative Identification: Techniques such as brainstorming, lateral thinking (Think outside

    the Box), pairwise comparisons are used to identify different possible approaches to the

    project.

    d. Facilitated Workshops

  • Basic Project Management Training on PMI Framework

    29 Monday, July 16, 2012 Security Company Internal

    2.3.3 Output from collect Requirements:

    a. Project Scope Statement: The Project scope statement typically includes:

    i. Product Scope Description

    ii. Product Acceptance Criteria

    iii. Project Deliverables

    iv. Project Out of Scope

    v. Project Constraints

    vi. Project Assumptions

    2.4 Defining Assignment from Scope Assignment of scope is a deliverables-oriented decomposition of the work to be accomplished

    commonly known as WBS. Various software used for create assignment of WBS, such as MS project

    or Primavera.

    2.4.1 Source of Defining Assignment

    a. Project Scope Statement

    b. Requirements Documentation

    c. Organizational Process Assets

    2.4.2 Tools and Techniques for identify scope

    Decomposition: Is the process of breaking project deliverables into smaller and smaller pieces, in

    other words, finding the level of details at which tasks can be adequately planned and managed.

  • Basic Project Management Training on PMI Framework

    30 Monday, July 16, 2012 Security Company Internal

    2.4.3 Output from Defining Assignment

    a. Accepted Deliveries

    b. Change Request

    2.5 Verify and Validate Scope Scope verification is the process of obtaining formal acceptance of the project scope by the

    stakeholder.

    Scope validation is the process of obtaining formal acceptance of product delivery confirmation from

    stakeholder.

    2.5.1 Source of verification and Validation

    a. Project Management plan

    b. Requirement Documentation

    c. Requirement Traceability Matrix

    d. Validated deliveries

    2.5.2 Tools and Techniques for verify and validate scope

    Inspection: Activities such as measuring, examining and testing undertaken to determine whether

    work results confirm to requirements. Alternative names for inspection includes review, product

    review, audits and walk through.

    2.5.3 Output from Verify and Validate Scope:

    a. Work Breakdown Structure

    b. Work Breakdown Structure Dictionary

    c. Scope Baseline

    2.6 Control Scope This process monitors the status of the project and product scope and also manages any changes to

    the scope baseline.

    2.6.1 Source of Control Scope

    a. Project Management plan

    b. Work Performance Information

    c. Requirement Documentation

    d. Requirement Traceability Matrix

    e. Organizational Process Assets

    2.6.2 Tools and Techniques for identify scope

    Variance Analysis: Project Performance measurements are used to assess the magnitude of

    variation from the original scope baseline. Important aspects of project scope control include

    determining the cause and degree of variance relative to scope baseline and deciding whether

    corrective or preventive action is required.

    2.6.3 Output from collect Requirements:

    a. Work Performance Measurement

  • Basic Project Management Training on PMI Framework

    31 Monday, July 16, 2012 Security Company Internal

    b. Change request

    c. Organizational Process Assets Updates

    2.7 Team Activity for Project Management Robi Axiata decided to launch 3G Services for its valued customer, Please identify 5 Project Scope

    and 5 Product Scope

    It will be a:

    d. Team Work

    e. Expected time 10 min

    f. Discussion 10 min

  • Basic Project Management Training on PMI Framework

    32 Monday, July 16, 2012 Security Company Internal

    Module 04: Project Time Management

  • Basic Project Management Training on PMI Framework

    33 Monday, July 16, 2012 Security Company Internal

    4.1 Introduction Time management is the act or process of planning and exercising conscious control over the

    amount of time spent on specific activities, especially to increase effectiveness, efficiency or

    productivity. Time management may be aided by a range of skills, tools, and techniques used to

    manage time when accomplishing specific tasks, projects and goals complying with a due date. This

    set encompasses a wide scope of activities, and these include planning, allocating, setting goals,

    delegation, analysis of time spent, monitoring, organizing, scheduling, and prioritizing. Initially, time

    management referred to just business or work activities, but eventually the term broadened to

    include personal activities as well. A time management system is a designed combination of

    processes, tools, techniques, and methods. Usually time management is a necessity in any project

    development as it determines the project completion time and scope.

  • Basic Project Management Training on PMI Framework

    34 Monday, July 16, 2012 Security Company Internal

    Overview of Scheduling is as follows:

    4.2 Define Activities Define activity is the process of identifying the specific actions to be performed to produce the

    project deliverables. The process decomposed lowest level of work package (WBS) to activity or

    schedule activities. Define activity involves identifying and documenting the specific activities that

    must be performed.

  • Basic Project Management Training on PMI Framework

    35 Monday, July 16, 2012 Security Company Internal

    4.2.1 Source of Define Activities:

    c. Scope Baseline: The information explicitly used at this step includes project deliverables,

    constraints and assumptions.

    d. Enterprise Environmental Factors

    e. Organizational Process Assets

    4.2.2 Tools and Techniques for Define Activities:

    i. Decomposition: Subdividing project activities into smaller components. The lowest level

    shown in the Work Breakdown Structure (WBS) in the work package; however work

    packages can be further decomposed into schedule activities, which are the steps required

    to produce the work package deliveries.

    j. Rolling Wave Planning: A form of progressive elaboration where work to be performed in

    the near term is planned at a low level of the WBS, i.e. a highly detailed plan. Work farther in

    the future is planned with much less detail.

    k. Templates

    l. Expert Judgment

    4.2.3 Output from collect Requirements:

    b. Activity List: A comprehensive list of all activities that must be performed. The list should be

    include all activities, an activity identifier and a sufficient description of the work

    c. Activity Attributes: Normally an activity attributes includes following information:

    a. Activity ID, WBS ID and Activity Name

    b. Activity Description

    c. Predecessor and Successor activity

    d. Logical Relationship

    e. Leads and Lags

    f. Resource Required

    g. Imposed Dates and Constraints

  • Basic Project Management Training on PMI Framework

    36 Monday, July 16, 2012 Security Company Internal

    h. Assumptions

    i. Responsible resource

    j. Geographical Area (If work done in multiple locations)

    d. Milestone List: Milestones are important points in time and have zero duration (normally).

    Milestone may be requested or demanded by the customer, management, the team or may

    be required by the contract.

    4.3 Sequencing and Grouping Activities Activity sequencing and grouping involves identifying and documenting interactive dependencies (So

    called logical relationship). The process can be done manually, with software or with a combination

    of both.

    4.3.1 Source of Sequencing and Grouping Activities

    a. Activity List

    b. Activity Attributes

    c. Milestone List

    d. Project Scope Statement

    e. Organizational Process Assets

    4.3.2 Tools and Techniques for Sequencing and Grouping Activities

    a. Precedence Diagramming Method (PDM): This is one way to display a schedule in network

    fashion; it is also called activity-on-node. It was developed in early 1960s at Stanford

    University and the method that project management software uses today.

    The PDM approach uses the following four types of dependencies:

    Finish to Start (FS): Initiation of the successor activity depends on completing of the

    predecessor activity.

    Finish to Finish (FF): Completion of the successor activity depends on completion of

    the predecessor activity.

    Start to Start (SS): Initiation of the successor activity depends on initiation of the

    predecessor activity.

  • Basic Project Management Training on PMI Framework

    37 Monday, July 16, 2012 Security Company Internal

    Start to Finish (SF): Completion of the successor activity depends on initiation of the

    predecessor activity.

    Precedence Diagramming Method All together

    b. Dependency Determination: The followings three types of dependencies are used during

    activity sequencing:

    I. Mandatory Dependencies: Also referred as a hard logic, mandatory dependencies

    are inherent in the nature of the work and often involve physical or technical

    limitations of some kind. For example you cannot shingle the roof of a building until

    the roof has been built.

    II. Discretionary Dependencies: Known as Soft Logic or preferential logic, these

    optional dependencies are usually chosen because they represent best practices

    or there is a preferred approach even though other approaches would also be

    accepted.

    III. External Dependencies: These dependencies usually involve interfaces outside the

    project.

    c. Appling Leads and Legs: The project management team determinates the dependencies that

    may require a lead or a lag to accurately define the logical relationship. The use of lead and

    lags should not replace scheduling logic. Activities and their related assumptions should be

    documented.

    A lead allows an acceleration of the successor activity. For example, on a project to

    construct a new office building, the landscaping could be scheduled to start 2 weeks prior to

  • Basic Project Management Training on PMI Framework

    38 Monday, July 16, 2012 Security Company Internal

    the scheduled punch list completion. This would be show as a finish-to-start with a 2 week

    lead.

    A lag directs a delay in the successor activity. For example, a technical writing team can

    begin editing the draft of a large document 15 days after they begin writing it. The could be

    shown as a start-to-start relationship with a 15-days lag.

    d. Scheduling Network templates

    4.3.3 Output from Sequencing and Grouping Activities:

    a. Project Schedule Network Diagram

    b. Project Document Updates

    4.4 Estimate Duration and Cost Estimate duration and cost depends resource require and duration of a task. Every single task

    required to be executed by some resources (Work, Material or Cost type), and depending of the

    duration or number of uses, cost is calculated.

    4.4.1 Source of Estimate duration and Cost

    a. Activity List

    b. Activity Attributes

    c. Resource Calendar

    d. Project Scope Statement

    e. Activity Resource Requirement

    f. Enterprise Environmental Factors

    g. Organizational Process Assets

    4.4.2 Tools and Techniques for Estimate duration and Cost

    a. Expert Judgment: For estimation PMI recommends expert judgment based on historical

    information whenever the combination is possible.

    b. Analogous Estimation: A form of top-down estimating, this approaches uses the actual

    durations of previous, similar activities to estimate the duration if future activities. These

    estimates are usually adjusted by experts for differences in complexity, size and risk. Key

    Points:

    c. Parametric Estimation: For some tasks, duration estimates can be derived from the quantity

    needed multiply by the appropriate productivity rate.

    d. Three Point Estimation: Such estimates can improve accuracy by considering risk. This

    technique calculates an expected average duration from the following:

    Optimistic

    Pessimistic

    Most Likely

    In similar fashion, a well-known technique for doing the same thing is PERT [Program

    Evolution and Review Technique].

    e. Reserve Analysis: Contingency reserves (Sometimes referred as Time Reserve or Buffers) are

    sometimes added to duration estimates to account for risk or uncertainty.

  • Basic Project Management Training on PMI Framework

    39 Monday, July 16, 2012 Security Company Internal

    4.4.3 Output from Estimate duration and Cost

    a. Activity Resource Requirement

    b. Activity Duration Estimate

    4.5 Develop Schedule Put all previous time management data into a single scheduling tool (MS Project, Primavera or

    others) will establish planned schedule for each task. The approved schedule becomes the baseline

    for tracking progress.

    4.5.1 Consideration for a Complete Schedule

    a. Schedule Network Analysis: Techniques that generate the project schedule using a schedule

    model and various analytical techniques such as Critical Path Method, What if Analysis etc.

    b. Critical Path Method: Calculates theoretical start and finish dates for all schedule activities

    without regard to resource limitations. The technique:

    a. Uses a forward and backward pass to determine early and late times

    b. Calculate available float or slack

    c. Determines the critical path (the longest path and has either zero float or the least

    float available.

    c. Resource Leveling

    d. What if Scenario Analysis

    e. Applying Leads and Legs

    f. Schedule Compression: Seeking ways to shorten the schedule without changing the scope.

    There are two primary techniques:

    a. Crashing: The technique essentially involves adding resources to critical path

    activities but will almost always increase project cost.

    b. Fast Tracking: Doing more activities in parallel. Note that fast tracking usually

    increase risk because it requires increased coordination of resource and may result

    in rework.

    4.6 Control Schedule Control schedule is the process of monitoring the status of the project to update project progress

    and manage changes to the schedule baseline. Schedule Control is the most critical task for Project

    Manager and concerned with:

    Determining the current status of the project schedule

    Influencing the factors that create schedule change

    Determine that the project schedule has changed

    Manage the actual changes as the occur

    4.6.1 Source of Control Schedule

    a. Project Management plan

    b. Project Schedule

    c. Work Performance Information

    d. Organizational Process Asset

  • Basic Project Management Training on PMI Framework

    40 Monday, July 16, 2012 Security Company Internal

    4.6.2 Tools and Techniques for Control Schedule:

    Performance review

    Variance Analysis: Used to assess the magnitude of schedule variations against the

    planned baseline. Variance is defined as plan minus actual. Negative variances indicate

    that work took longer than expected.

    Resource Leveling

    What if Scenario Analysis

    Adjusting leads and legs

    Scheduling Compression

    4.6.3 Output from Control Schedule:

    a. Work Performance Measurement (Schedule Variance, Cost Variance)

    b. Change request

    c. Organizational Process Assets Updates

    4.7 Team Activity for Project Time Management Create a network diagram based on following information and identify Critical Path

    Activity Duration Predecessor

    A 5 Days NA

    B 3 Days A

    C 2 Days B

    D 6 Days C

    E 1 Day A

    F 3 Days E

    G 2 Days D, F

    It will be a:

    a. Team Work

    b. Expected time 15 min

    c. Discussion 15 min

  • Basic Project Management Training on PMI Framework

    41 Monday, July 16, 2012 Security Company Internal

    Module 05: Project Quality Management

  • Basic Project Management Training on PMI Framework

    42 Monday, July 16, 2012 Security Company Internal

    5.1 Introduction PMI defines quality as the degree to which a set of inherent characteristics fulfill requirements. A

    critical part of this is to identify stakeholders need clearly. Project quality management addresses

    the management of the project and the product of the project. It applies to all projects, regardless of

    the nature of the project. Product quality measures and techniques are specific to the types of

    product produced by the project. While quality management of software products uses different

    approaches and measure than building a nuclear power plant, project quality management

    approaches apply to both.

    5.1.1 Project Quality Issues

    Quality and Grades: Grade is a category assigned to products or services having the same

    functional use but different technical characteristics. While a quality level that fails to meet

    quality requirements is always a problem, low grade may not be.

    Gold Plating: Gold plating is providing a solution that exceeds the original requirement and

    is bad to the extent that it may causes the project to cost more and take longer time. If the

    requirements are accurate, there is no reason to exceed them.

    Customer Satisfaction: Which is requires attention to conformance to specifications and

    fitness for use.

    Prevention over inspection: One of the fundamental tenets of modern quality management

    states that quality is planned, designed, and built in; not inspected in. The cost of preventing

    mistakes is generally much less than the cost of correcting them when they are found by

    inspection.

    Management Responsibility: Which is recognizes that participation of the entire

    organization is needed for success, but it is the responsibility of management to provide

    adequate resources and sound processes.

    5.2 Plan Quality Quality planning involves identifying quality requirements and standards for the project and the

    product and documenting how to demonstrate compliance. PMI emphasizes that quality should be

    planned in, not inspected in.

  • Basic Project Management Training on PMI Framework

    43 Monday, July 16, 2012 Security Company Internal

    5.2.1 Source of Plan Quality:

    a. Scope Baseline: The information explicitly used at this step includes project deliverables,

    constraints and assumptions.

    b. Stakeholder Register

    c. Cost performance Index

    d. Schedule Baseline

    e. Risk Register

    f. Enterprise Environmental Factors

    g. Organizational Process Assets

    5.2.2 Tools and Techniques for Plan Quality:

    a. Cost Benefit Analysis: For quality planning purpose, benefit/cost tradeoffs refer to the cost

    engaging in quality management activities against the resulting benefit to the project. The

    potential benefits of meeting quality requirements include:

    I. Less rework

    II. Higher Productivity

    III. Lower Costs

    IV. Increased stakeholder Satisfaction

    b. Cost of Quality: Cost of quality includes all costs incurred by over the life of the product by

    investment in preventing nonconformance to requirements, appraising the product or

    service for conformance to requirements, and failing to requirement (rework). Failure costs

    are often categorized into internal and external. Failure costs are also called cost of poor

    quality.

    c. Control Charts: Control charts are used to determine whether a process is stable (under

    control) and is therefore producing predictable results. Upper and lower control limit, Rule

    of Seven or Six Sigma rules are some example of Control chart application in project

    management.

  • Basic Project Management Training on PMI Framework

    44 Monday, July 16, 2012 Security Company Internal

    d. Benchmarking

    e. Design of Experiments

    f. Statistical Sampling

    g. Flowcharting

    h. Proprietary Quality Management Methodology

    5.2.3 Output from Plan Quality:

    a. Quality Management Plan

    b. Quality Matrix

    c. Quality Checklist

    d. Process Improvement Plan

    5.3 Perform Quality Assurance Quality assurance involves auditing requirements and results from quality control measurements to

    ensure the project will use appropriate quality standards and processes.

    5.3.1 Source of Perform Quality Assurance

    a. Project Management Plan

    b. Quality Metrics

    c. Work Performance Information: Actual performance outcomes collected at reporting

    intervals as the project progresses and includes:

    a. Technical Performance Measures

    b. Status of Project Deliverables

    c. Schedule Progress

    d. Costs Incurred

    d. Quality Control Measurements

    5.3.2 Tools and Techniques for Perform Quality Assurance

    a. Quality Audit: Structured, independent reviews to identify inefficient processes reduce the

    cost of quality and increase the percentage of accepted products. The specific objectives of a

    quality audit may include:

    I. Identify and share best practice

    II. Identify Shortcomings

    III. Share the good practices from similar project

    IV. Proactive offer assistance to improve processes and raise productivity

    V. Document the lessons learned from each audit

    b. Process Analysis

    5.3.3 Output from Perform Quality Assurance

    a. Project Management Plan Update

    b. Change Request

    c. Project Document Updates

  • Basic Project Management Training on PMI Framework

    45 Monday, July 16, 2012 Security Company Internal

    5.4 Perform Quality Control Quality control involves monitoring and recording specific project results to assess performance and

    recommends necessary changes.

    5.4.1 Source of Perform Quality Control

    a. Project Management Plan

    b. Quality Metrics

    c. Quality Checklist

    d. Work Performance Measurement: Work performance measurements are used to produce

    project activity metrics evaluate progress as compared to planned progress. This metrics

    include, but not limited to:

    a. Planned vs Technical Performance

    b. Planned vs Actual Schedule Performance

    c. Planned vs Actual Cost Performance

    e. Approved Change Requests

    f. Deliverables

    g. Organizational Process Assets

    5.4.2 Tools and Techniques for Perform Quality Control

    a. Cause and Effect Diagram: Cause and effect diagrams, also called Ishikawa diagram or

    fishbone diagram, illustrate how various factors might be lined to potential problem or

    effects. A possible root cause can be uncovered by continuing to ask why or how along

    one of lines.

    b. Control Charts

    c. Flowcharting

    d. Histogram: A histogram is a vertical bar chart showing how often a particular variable state

    occurred. Each column represents an attribute or characteristics of a problem/situation. The

    height of each column represents the relative frequency of the characteristics.

  • Basic Project Management Training on PMI Framework

    46 Monday, July 16, 2012 Security Company Internal

    e. Pareto Chart

    f. Run Chart

    g. Scatter Diagram

    h. Statistical Sampling

    i. Inspection

    j. Approved Change Request review

    5.4.3 Output from Perform Quality Control

    a. Quality Control Measurements

    b. Validated Changes

    c. Validated Deliverables

    d. Organizational Process Assets Update

    e. Change Requests

    f. Project Management Plan Update

  • Basic Project Management Training on PMI Framework

    47 Monday, July 16, 2012 Security Company Internal

    Module 06: Resource and Cost Management

  • Basic Project Management Training on PMI Framework

    48 Monday, July 16, 2012 Security Company Internal

    6.1 Introduction Human Resource Management Human resource management involves organizing, managing and leading the project team. The

    processes are aimed at making the most effective use of the people associated with the project,

    including all stakeholders (Sponsor, Customers, Team Members, Management and others).

    Managing and Leading includes:

    a. Influence the project team

    b. Professional and ethical behavior

    6.2 Develop Human Resource Plan Human resource planning involves identifying, documenting and assigning project roles and

    responsibilities and reporting relationships. These roles may be assigned to individuals or to group. It

    also creates the staffing management plan that addresses how team members will be acquired and

    released, training needs, reward system and safety issues.

    6.2.1 Source of Human Resource Plan:

    a. Activities resource requirements

    b. Enterprise environmental factors: Factors that may influence human resource planning

    include:

    a. Organizational Culture

    b. Existing Human resource

    c. Personal Administration Policies

    d. Marketplace Condition

    c. Organizational Process Assets

    6.2.2 Tools and Techniques for Human Resource Plan:

    a. Organizational Charts and Position Description

  • Basic Project Management Training on PMI Framework

    49 Monday, July 16, 2012 Security Company Internal

    b. Networking: Informal interactions for the purpose of understanding potential political and

    interpersonal influences on the project. An example includes informal conversations, lunch

    meetings, attendance at conferences and recreational activities.

    c. Organizational Theory

    6.2.3 Output from Human Resource Plan:

    Human Resource Plan: Following information should be addressed:

    a. Roles and Responsibility

    b. Project Organizational Chart

    c. Staffing Management Plan

    6.3 Acquire Project Team Staffing acquisition is getting the right people assigned to the project. Failure to do so in a timely

    manner may affect schedules, costs, risks, quality and ultimately customer satisfaction.

    6.3.1 Source of Acquire Project Team

    a. Project Management Plan

    b. Enterprise Environmental Factors : when recruiting team members, the following factors

    should be considered:

    a. Human Resource Information

    b. Personal Administration Policies

    c. Organizational Structures

    d. Location

    c. Organizational Process Assets

    6.3.2 Tools and Techniques for Acquire Project Team

    a. Pre-assessment

    b. Negotiation

    c. Acquisition

    d. Virtual Teams: Virtual teams spend little or no time working face to face. Given modern

    technology, virtual teaming makes the following approaches possible:

    I. Teams with members from different geographic areas

    II. Use people who work from home or work different shifts

    III. Add special expertise even though they are not in the same location

    IV. Pursue projects that would have been rejected due to travel costs.

    When using virtual teams, communication and conflicts management become more

    important than ever.

  • Basic Project Management Training on PMI Framework

    50 Monday, July 16, 2012 Security Company Internal

    6.3.3 Output from Acquire Project Team

    a. Project Staff assignments

    b. Resource Calendars

    c. Project Management Plan Update

    6.4 Develop Project Team This process is aimed at improving the competencies, interactions among team members and the

    overall team environment to, in turn, improve project performance. Include the following:

    Team development involves

    o Improve the ability to team members to contributes as individuals

    o Improving the ability of the team to function effectively

    o Improving trust and cohesiveness among team members.

    PMI also recommends that team development occurs through the entire project life cycle.

    6.4.1 Source of Develop Project Team

    a. Project Staff Assignment

    b. Project Management Plan

    c. Resource Calendar

    6.4.2 Tools and Techniques for Develop Project Team

    a. Interpersonal Skills

    I. Problem Solving

    II. Leadership

    III. Influencing

    IV. Negotiation and Conflict Management

    V. Communication

    VI. Motivation

    VII. Empathy

    VIII. Creativity

    IX. Group Facilitation Skills

    X. Team Building

    XI. Decision Making