Stage 5 - ConstructionPrintable version of Stage 55.01 OverviewOBJECTIVE - Functional facility delivered within cost, time and
quality parameters.
RATIONALE - Successfully discharge building contract
KEY OUTPUT - Completed building
^ Back to top
5.02 TimescalesThe construction timescales will vary according to the size, complexity
and location of the project. The following table indicates approximate
construction periods for a range of costs, based on a traditionally procuredproject.
Contract Value (000s) Construction Period (months)
150 3.5
200 4.5
250 5.5
300 6.5
400 7
500 7.5
750 9
http://onsurestart.portal.echarris.com/apps/ProjManToolkit/pdf_s/Section_55.pdfhttp://onsurestart.portal.echarris.com/apps/ProjManToolkit/construction.htm#top%23tophttp://onsurestart.portal.echarris.com/apps/ProjManToolkit/pdf_s/Section_55.pdfhttp://onsurestart.portal.echarris.com/apps/ProjManToolkit/construction.htm#top%23top -
8/3/2019 Basic Construction Breakdown
2/9
1000 11
1250 12.5
1500 15
2000 20
^ Back to top
5.03 Sure Start client and design guidesThis Stage should be read in conjunction with Building for Sure Start: a
client guide, Sections 6.2, 6.3, 6.6.^ Back to top
5.04 QualityThe Design Team will specify goods, materials and standards of
construction to be incorporated into the project using relevant British
Standards, Codes of Practice, Agrment Board criteria and other
appropriate standards.
The achievement of these standards rests with the appointed Contractor.
The Project Manager/Lead Consultant, through the design team will
monitor quality of output on site to ensure compliance with design details
and specifications.^ Back to top
5.05 Contractor's programmme
http://onsurestart.portal.echarris.com/apps/ProjManToolkit/construction.htm#top%23tophttp://onsurestart.portal.echarris.com/apps/ProjManToolkit/construction.htm#top%23tophttp://onsurestart.portal.echarris.com/apps/ProjManToolkit/construction.htm#top%23tophttp://onsurestart.portal.echarris.com/apps/ProjManToolkit/construction.htm#top%23tophttp://onsurestart.portal.echarris.com/apps/ProjManToolkit/construction.htm#top%23tophttp://onsurestart.portal.echarris.com/apps/ProjManToolkit/construction.htm#top%23top -
8/3/2019 Basic Construction Breakdown
3/9
A master programme will have been established during brief development
at Stage 1 (1.08), including the time that the design team assesses asreasonable for the construction process. This time period will be stated
within the Construction Contract documentation, and it is the contractors
responsibility to arrange the progress and sequence of works, to achieve
completion within this period. It is a normal contractual requirement for
the contractor to develop a detailed construction programme, setting out
the sequence and duration of all the different construction activities, and
highlighting critical path elements associated with the construction process
to ensure and demonstrate that expected delivery timescales are met (see
also 5.09 below).
In defining the construction period within the master programme, the
client may also have identified whether there are any circumstances
(relating say to financial or operational issues) whereby access to certain
parts of the project will be necessary prior to formal completion and
handover of the project as a whole. Any such requirements will need to be
discussed and agreed with the appointed contractor (if not identified
within the tender documents), as they may impact on intended progress
and sequence of working.
Additionally, if the client has elected to organise provision of IT and
telecoms systems, ordering and payment for services can be pre-planned,working back from the projected contract completion date. A typical
construction programme may look like:
http://onsurestart.portal.echarris.com/apps/ProjManToolkit/construction.htm#top%23top -
8/3/2019 Basic Construction Breakdown
4/9
5.06 Cost managementOn a day-to-day basis, cost management during the construction stage will
be undertaken by the Quantity Surveyor/cost consultant by:
Highlighting changes in the anticipated costs as early as
possible, to enable any corrective action (i.e. modifications to
the design or specification) to be considered.
Continuous proactive liaison between all members of the Project
Team.
Prompt evaluation of design variations in conjunction with a
strict regime for Client authorisation (see 5.08 below).
Adopting a continuous attitude of value engineering to the scope
and the cost of the works.
Continuous review of risk assessment on the project.
Preparing detailed valuations (usually monthly) of work
satisfactorily completed.
The Project Manager/Contract Administrator should constantly review theoperation and effectiveness of the change monitoring and authorisation
system in relation to cost control.^ Back to top
5.07 Cost reportingIt is clearly important to keep the Client advised on a regular basis of the
anticipated final out-turn cost of the project, usually by way of a specific
Cost Report prepared by the Quantity Surveyor. This would primarily
address Construction costs, but may also include professional fees,
statutory charges, surveys, furniture and loose fittings, Client direct orders
and VAT.
Cost reports will reconcile the latest forecast for the anticipated final
account for each element within the agreed budget. Construction cost
reports will also incorporate costed schedules of Client and Design Team
variations and instructions. A cashflow forecast (month by month
prediction of future construction spend) would also normally be provided,
taking into account any changes in construction progress from that
originally planned to that achieved.^ Back to top
5.08 Change controlSometimes variations to the scope, content or specification of the construction
works are unavoidable, and will be due to either:
a) circumstances on site dictating change of design e.g. soft spots in the ground,
necessitating stronger foundations,
b) changes or variations initiated by the client (for whatever reason), or
c) as the result of the value engineering process.
The deliberate introduction of late changes to incorporate new ideas or demands
http://onsurestart.portal.echarris.com/apps/ProjManToolkit/construction.htm#top%23tophttp://onsurestart.portal.echarris.com/apps/ProjManToolkit/construction.htm#top%23tophttp://onsurestart.portal.echarris.com/apps/ProjManToolkit/construction.htm#top%23tophttp://onsurestart.portal.echarris.com/apps/ProjManToolkit/construction.htm#top%23top -
8/3/2019 Basic Construction Breakdown
5/9
for the building should be avoided during the construction phase. Design choices
should have been thoroughly worked through during the outline and detail
design stages. Introduction of even small changes at this stage risk delaying the
project and increasing costs by a disproportionate amount. In this respect,
changes should only be instigated when absolutely necessary, when any
available options have been evaluated, and when impacts on cost andprogramme are fully understood and accepted by all concerned.
All changes (or Variations) are required to be formally notified to the contractor
by the Contract Administrator ONLY (only the Contract Administrator has the
contractual authority to instruct the contractor to vary the contract works).
^ Back to top
5.09 Supply chainIn order to construct any facility, the main contractor will have to establish
and co-ordinate a supply chain of sub-contractors, suppliers and
specialists.
Establishment of this chain will closely relate to the critical path element
in the contractors programme, ensuring timely availability and delivery of
main construction elements such as steelwork, bricks, windows and doors,
identifying goods and materials that require long lead times, and
availability of sub-contract labour at the appropriate stage in the contract.^ Back to top
5.10 CDM(Construction Design and Management )activity
http://onsurestart.portal.echarris.com/apps/ProjManToolkit/construction.htm#top%23tophttp://onsurestart.portal.echarris.com/apps/ProjManToolkit/construction.htm#top%23tophttp://onsurestart.portal.echarris.com/apps/ProjManToolkit/construction.htm#top%23tophttp://onsurestart.portal.echarris.com/apps/ProjManToolkit/construction.htm#top%23top -
8/3/2019 Basic Construction Breakdown
6/9
In compliance with CDM legislation, the contractor will have developed
the Health & Safety plan before commencing work on site, during Stage 4,
Mobilisation (4.05). This will include full response to designers risk
assessments as appropriate, and identification and mitigation of
construction risks, and will also co-ordinate with any client procedures or
requirements that remain in force during the construction period.
Health and Safety should be an agenda item at all progress meetings
throughout the lifetime of the project, and should cover such issues as:
Continued risk identification/mitigation
Site facilities WCs, catering, etc
First Aid procedures
Working at heights Manual Handling
COSHH(Control Of Substances Hazardous to Health)
Hazardous substances
Electrical safety
Confined spaces
During the construction period the contractor will be assembling
information for inclusion in the buildings Health and Safety file to be
submitted to the client/building user at Handover.
^ Back to top
5.11 Handover proceduresWhen building works are complete to the satisfaction of the Contract
Administrator, the Contract Administrator will issue a Certificate of
Practical Completion. This formally signifies that the construction activity
associated with the site as complete and the building fit and safe to occupy
and use. The ownership and responsibility for the building (in terms of
security, insurance, safety, energy costs, etc) then passes to the client. It
also marks the commencement of the Defects Liability Period (DLP -
normally 12 months), during which the Contractor remains responsible for
remedying defects that occur within the building and its systems. In somecases a partial handover may be carried out. On larger projects with
phased completion, part of the building may be declared fit for occupation
and thus handed to the client, whilst other areas remain in the contractors
possession as building work continues.
If the construction works run to programme, the handover date will be
either at or before the Date for Completion stated in the contract
documents (if there have been legitimate delays, this date will of course be
later) and in anticipation of this the Contract Administrator, accompanied
by the Contractor, will compile a list of outstanding or unsatisfactory
works (snagging list). Such works should be completed prior to the
formal handover, although certain specific items may be addressed later,
http://onsurestart.portal.echarris.com/apps/ProjManToolkit/construction.htm#top%23tophttp://onsurestart.portal.echarris.com/apps/ProjManToolkit/construction.htm#top%23top -
8/3/2019 Basic Construction Breakdown
7/9
by agreement.
In addition to dealing with any outstanding or unsatisfactory works, the
Contractor will also be required to demonstrate that all the buildings
mechanical and electrical installations are safe and functioning as required
(these include heating/ventilation systems, electrical (power and lighting)installations, gas and water installations and specialist items such as fire
alarms, emergency lighting and security systems). This is normally
undertaken by the relevant specialist subcontractors, together with the
appropriate services engineers, and is dealt with in two phases:
Testing
Testing is important, to ensure the newly installed equipment is in a safe
condition and functioning correctly. Testing should thus be undertaken as
a formal exercise, accurately recording:
Plant, section and installation under test.
Manufacturers reference number where applicable.
Date, time, duration of test (and weather conditions if
appropriate).
Test results with itemised readings including records of all other
checks and tests.
Commissioning
Follow satisfactory completion of testing, systems should be run so that
they can be regulating and adjusting to meet the design requirements.
Commissioning is particularly important in modern heating systems where
sophisticated controls are likely to exist to manage the operation of
heating plant to meet not only room temperature and comfortrequirements, but also environmental criteria associated with energy
consumption. Lifts, fire and security alarms and cameras are other systems
that will need proper commissioning.
There may also be requirements to train the client or building user in the
operation of the buildings systems.
As well as satisfactorily dealing with the building and its systems, the
Contractor would normally be required to provide specific building-related
documentation at handover. This would include:
Operating and Maintenance manuals
Operating and maintenance (O&M) manuals should be produced for the
building and all equipment within it. A typical O&M manual should
include:
Description of Design Intent & Operational Policy
Commissioning Documents and Reports
Manufacturers Operation/Service & Maintenance Manuals
Manufacturers Spares List & Ordering Procedure
Operational & Maintenance Routines
Line Diagrams of Plant Control Systems Schematic Layouts locating Valves, Switches etc.
-
8/3/2019 Basic Construction Breakdown
8/9
Schedule of Installed Equipment
Description Working Drawings for each main item of
plant/equipment, showing safety features etc.
Emergency call-out service - personnel & telephone contacts
Copies of all charts posted elsewhere in building
List of tools, keys and any special requirements
Guarantees, Test Certificates & Reports
Insurance & Inspecting Authority Certificates & Reports
List of Record Drawings (drawings separately available)
Record drawings
Upon completion, the design team should produce sets of record drawings
showing the building and its installations as actually built, incorporating
all design/construction changes that have occurred during the projects
lifetime.
Safety FileThe operating and maintenance (O&M) manual will also form the basis of
the buildings Safety File. Provision of a Safety File is a requirement
under the CDM Regulations. The file will be assembled taking relevant
parts of the O&M manual, together with details of risk assessments carried
out over the lifetime of the project and mitigating actions taken. It will
also include details of special measures needed to manage risk in the
operation, maintenance and occupancy of the building.
This file will subsequently evolve as future alteration/refurbishment work
takes
place. In this respect the file will represent a works history for the building
and allow hazardous situations to be identified immediately at the start of
future work programmes.
As the completion and handover date approaches, this should trigger client
arrangements in respect of future building operation and service delivery,
staff appointments and training, working arrangements with other
stakeholders/service providers, Planning for this should have been
incorporated in the early stages of development, at Brief Development
stage (see Section1.8 Programme above).^ Back to top
5.12 Trouble shooting
WHAT CAN
GO WRONG
RISKS WHAT CAN BE DONE
ABOUT IT
Slippage to
Contractors
Programme
Delay to project
completion
Quality/value for money
risks
Potential for costs
Contractors best endeavours
Reconsider master programme
Revisit/Re-engineer
designs/specifications
http://onsurestart.portal.echarris.com/apps/ProjManToolkit/construction.htm#top%23tophttp://onsurestart.portal.echarris.com/apps/ProjManToolkit/construction.htm#top%23top -
8/3/2019 Basic Construction Breakdown
9/9
arising from extension
of time
Issue of major/
untimely/
numerous
variations/
changes
Potential for costs
arising from extension
of time
Delays to project
completion
Minimise changes at this stage
Implement rigid change control
policy
Failure in Supply
Chain operation
Delays to project
completion. Costs or
quality compromised
Ensure contractor has robust
supply chains in place for
material/labour taking account
of programme critical path
issues.
Health & Safety
compromised
Health and Safety
related incidents-major
incidents may suspendworks
HSE involvement
Ensure Health and Safety plan
is in place, implemented and
regularly reviewed
Ensure Health and Safety
aspects of pre-start procedures
are fully considered.
Required quality
not achieved
Early establishment of required
standards
Appropriate checking during
construction
Testing andcommissioning
failed/
incomplete Non-
availability of
statutory services
Critical path element tohandover. Requirements should
be co-ordinated well in advance
with all documentation
certificates, O&M manuals etc
available.
Early placement of orders.
Liaison with services providers