1
Port Expansion ProjectRegional Ports Conference 28 June, 2012
PORT OF TOWNSVILLE LIMITED:
SUMMARY
Snapshot of the Port of Townsville
Growth Projections
Projects under way – Townsville Port Inner Harbour Expansion
• Berth 8 Upgrade
• Berth 10 Reconstruction
Projects Proposed – Port Expansion Project
• Berth 12
• Berths 14 – 19
Landside Infrastructure
• Townsville Port Access Road
• Eastern Access Rail
• Townsville State Development Area
Logistics Chain Coordination
18/06/2012
2
Current Berth ActivitiesBerth 11
Berth 2
Berth 3
Berth 4
Berth 7
Berth 8Berth 9Berth 10
Berth 1
18/06/2012
3
PORT OF TOWNSVILLE LIMITED:
TRADE PERFORMANCE and OUTLOOK (high growth)
-
10
20
30
40
50
60
70
Tonnes
(Mill
ions)
Low Growth Bulk Project/s Capacity - Do Nothing Capacity - Enhancements
MAJOR PROJECTS:
BERTH 8 and BERTH 10A
18/06/2012
4
MAJOR PROJECTS:
BERTH 10 Terminal Building
18/06/2012
5
MAJOR PROJECTS:
BERTH 10 B & C
Stage A
Stages B and C
18/06/2012
6
MAJOR PROJECTS:
BERTH 12
Proposed Berth 12
Current Berth 11
18/06/2012
7
MAJOR PROJECTS:
PORT EXPANSION PROJECT
18/06/2012
8
Port of Townsville - 2040
PORT OF TOWNSVILLE LIMITED:
TOWNSVILLE STATE DEVELOPMENT AREA
• The TSDA covers about 4,900 hectares and includes the
Stuart Industrial Area and the Townsville Port Access Road.
• An area with a number of potential port-related uses.
• Investigations underway into how to best utilise the asset.
• Development of the area would enable future port activity to
move away from urban environments.
18/06/2012
9