Barrier Warrant Process - Illinois Tollway

88
Tracy Borchardt April 2013 Barrier Warrant Process 1

Transcript of Barrier Warrant Process - Illinois Tollway

Page 1: Barrier Warrant Process - Illinois Tollway

Tracy Borchardt April 2013

Barrier Warrant Process

1

Page 2: Barrier Warrant Process - Illinois Tollway

Traffic Barrier Warrants Each roadside barrier and safety appurtenance

installed on the Tollway System needs to be justified and the analysis documented.

2

Page 3: Barrier Warrant Process - Illinois Tollway

Traffic Barrier Guidelines

3

• BWA Process

• Usage Guide

March 2013

Page 4: Barrier Warrant Process - Illinois Tollway

References

AASHTO Roadside Design Guide, 4th Edition-2011

Clear Zone, Chapter 3

Location of Barriers, Chapter 5

Barrier Length & End Treatment, Chapter 5

Benefit/Cost Analysis

4

Page 5: Barrier Warrant Process - Illinois Tollway

POTENTIAL ROADSIDE OBSTACLES

TBG – SECTION 3.0

5

Page 6: Barrier Warrant Process - Illinois Tollway

Potential Roadside Obstacles

Design Options:

1. Remove obstacle

2. Relocate obstacle

3. Reduce impact severity.

4. Shield obstacle.

5. Delineate obstacle.

6

Page 7: Barrier Warrant Process - Illinois Tollway

Potential Roadside Obstacles

Gutters and Curbs

Embankments

Sign Supports

Bridge Piers, Parapets, Abutments & Bridge Cones

Noise Abatement Wall

Drainage Structures

Ditches

Riprap

Roadway Lighting

ITS Systems

Utility Poles

Trees

Bodies of Water

Rock Cuts

7

Page 8: Barrier Warrant Process - Illinois Tollway

Gutters and Curbs

Type C Curb

Type G-3 Modified Gutter

Type G-3 Gutter

8

Page 9: Barrier Warrant Process - Illinois Tollway

Type G-3 Gutters

9

Page 10: Barrier Warrant Process - Illinois Tollway

Type G-2 Gutters

10

Page 11: Barrier Warrant Process - Illinois Tollway

Gutter and Guardrail

G-3 Modified Gutter G-3 Gutter

11

Gutter may be constructed in conjunction with guardrail, but is not required

solely because of the presence of guardrail and vice versa.

Guardrail shall not be constructed to shield improperly placed gutter or curb.

Guardrail

Page 12: Barrier Warrant Process - Illinois Tollway

Embankments

Roadside Geometry and Terrain Features ,

Section 5.2.1 of the AASHTO Guide.

12

Page 13: Barrier Warrant Process - Illinois Tollway

Comparative Risk Warrants for Embankments (RDG Fig. 5-1b)

13

Page 14: Barrier Warrant Process - Illinois Tollway

Sign Supports

Overhead Sign Truss – Cantilever Type

Overhead Sign Truss – Span Type

14

Page 15: Barrier Warrant Process - Illinois Tollway

Bridges

Pier

Abutment Cone

Economical bridge designs usually result in the location of bridge piers, abutments, and parapets within mainline or ramp clear zones.

Parapets

15

Page 16: Barrier Warrant Process - Illinois Tollway

Noise Abatement Wall

Non-Crashworthy Noise Wall

Crashworthy Noise Wall

16

Page 17: Barrier Warrant Process - Illinois Tollway

Drainage Structures

Issues:

•Headwall not flush with embankment

•Pipe too short

•Headwall too close to roadway

•Steep slope just above headwall

•Skew

17

Page 18: Barrier Warrant Process - Illinois Tollway

Drainage Structures- Corrected

18

Page 19: Barrier Warrant Process - Illinois Tollway

Safety End Treatment

19

Page 20: Barrier Warrant Process - Illinois Tollway

Ditches

Drainage Channels, Section 3.2.4 of the AASHTO Guide.

20

Page 21: Barrier Warrant Process - Illinois Tollway

Roadway Lighting

21

Page 22: Barrier Warrant Process - Illinois Tollway

Roadway Lighting (cont.)

Controllers and Transformers

22

Page 23: Barrier Warrant Process - Illinois Tollway

Communication Systems and ITS Devices

NID RWIS CCTV Camera

Non-Breakaway 23

Page 24: Barrier Warrant Process - Illinois Tollway

Bodies of Water

Bodies of water greater than 2’ in depth must be shielded.

Locate detention basins well outside the clear zone.

24

Page 25: Barrier Warrant Process - Illinois Tollway

BARRIER WARRANT ANALYSIS PROCEDURE

TBG – SECTION 4.0

25

Page 26: Barrier Warrant Process - Illinois Tollway

Barrier Warrant Analysis Procedure

1. Identify Potential Obstacles

2. Name Obstacles

3. Prepare/Present Exhibit (Concept Meeting)

26

Page 27: Barrier Warrant Process - Illinois Tollway

Barrier Warrant Analysis Procedure

1. Identify Potential Obstacles.

2. Name Obstacles.

3. Prepare/Present Exhibit.

4. Each AOC shall be analyzed separately.

a. Establish EOTW

27

Page 28: Barrier Warrant Process - Illinois Tollway

a. Establish Edge of Traveled Way

EOP 1’ outside of the EOTW

EOTW = EOP

28

Page 29: Barrier Warrant Process - Illinois Tollway

Barrier Warrant Analysis Procedure

1. Identify Potential Obstacles.

2. Name Obstacles.

3. Prepare/Present Exhibit.

4. Each AOC shall be analyzed separately.

a. Establish EOTW

b. Design Speed (Speed Profile for ramps, etc.)

29

Page 30: Barrier Warrant Process - Illinois Tollway

Barrier Warrant Analysis Procedure

1. Identify Potential Obstacles.

2. Name Obstacles.

3. Prepare/Present Exhibit.

4. Each AOC shall be analyzed separately.

a. Establish EOTW

b. Design Speed

c. Design ADT

30

Page 31: Barrier Warrant Process - Illinois Tollway

Barrier Warrant Analysis Procedure

1. Identify Potential Obstacles.

2. Name Obstacles.

3. Prepare/Present Exhibit.

4. Each AOC shall be analyzed separately.

a. Establish EOTW

b. Design Speed

c. Design ADT

d. Length of Runout

31

Page 32: Barrier Warrant Process - Illinois Tollway

c. Length of Runout

L2

Figure 5-39. Approach Barrier Layout Variables

LR

32

Page 33: Barrier Warrant Process - Illinois Tollway

Barrier Warrant Analysis Procedure

1. Identify Potential Obstacles.

2. Name Obstacles.

3. Prepare/Present Exhibit.

4. Each AOC shall be analyzed separately.

a. Establish EOTW

b. Design Speed

c. Design ADT

d. Length of Runout

e. Shy Line Offset

33

Page 34: Barrier Warrant Process - Illinois Tollway

d. Shy Line Offset

34

Page 35: Barrier Warrant Process - Illinois Tollway

Barrier Warrant Analysis Procedure

1. Identify Potential Obstacles.

2. Name Obstacles.

3. Prepare/Present Exhibit.

4. Each AOC shall be analyzed separately.

a. Establish EOTW

b. Design Speed

c. Design ADT

d. Length of Runout

e. Shy Line Offset

f. Foreslope/Backslope

35

Page 36: Barrier Warrant Process - Illinois Tollway

f. Foreslope/Backslope

Foreslope

Backslope

Foreslopes

Within clear zone Elsewhere

1:6 (desirable) 1:4 (desirable)

1:4 (maximum) 1:2.5 (maximum)

Backslopes

1:4 or flatter (desirable)

1:2.5 (maximum)

V1:H1

V2:H2

36

Page 37: Barrier Warrant Process - Illinois Tollway

Barrier Warrant Analysis Procedure (cont.)

g. Clear Zone

37

Page 38: Barrier Warrant Process - Illinois Tollway

Clear Zone

The unobstructed, traversable area provided beyond the edge of through traveled way for the recovery of errant vehicles.

38

Page 39: Barrier Warrant Process - Illinois Tollway

Clear Zone Distances (Feet) From Edge of Traveled Way (Table 3-1)

Use highest value in range 39

Page 40: Barrier Warrant Process - Illinois Tollway

Barrier Warrant Analysis Procedure (cont.)

g. Clear Zone

h. Clear Zone Adjustment

40

Page 41: Barrier Warrant Process - Illinois Tollway

h. Clear Zone Adjustment

41

Page 42: Barrier Warrant Process - Illinois Tollway

Barrier Warrant Analysis Procedure (cont.)

g. Clear Zone

h. Clear Zone Adjustment

i. Lateral Extent of the Area of Concern (LA)

42

Page 43: Barrier Warrant Process - Illinois Tollway

i. Lateral Extent of the Area of Concern

L2

Figure 5-39. Approach Barrier Layout Variables

LA

L3

43

Page 44: Barrier Warrant Process - Illinois Tollway

Barrier Warrant Analysis Procedure (cont.)

g. Clear Zone

h. Clear Zone Adjustment

i. Lateral Extent of the Area of Concern

j. Warrant Analysis Level

44

Page 45: Barrier Warrant Process - Illinois Tollway

j. Warrant Analysis Level

Decide Warrant Analysis Level

Level 1

Level 2

Level 3

Level 0

Use

Flowchart For Existing

Obstacles

or

Flowchart for Proposed

Obstacles

45

Page 46: Barrier Warrant Process - Illinois Tollway

Warrant Analysis Level (Article 5.5)

46

Page 47: Barrier Warrant Process - Illinois Tollway

Flowchart for Analysis of Existing Obstacles

47

Page 48: Barrier Warrant Process - Illinois Tollway

Flowchart for Analysis of Proposed Obstacles

48

Page 49: Barrier Warrant Process - Illinois Tollway

Level 1 Analysis

Level 1 – Existing AOC’s that are traversable elements or can easily be made traversable elements such as:

Existing ground mounted signs, and existing drainage items

Existing ground mounted light poles and electrical handholes

49

Page 50: Barrier Warrant Process - Illinois Tollway

Level 1 Analysis

Level 1 – Proposed AOC’s that are traversable elements:

Proposed Ground-Mounted Signs

Proposed light poles

Proposed Drainage Items (culvert and pipe ends 84” or less in vertical opening)

50

Page 51: Barrier Warrant Process - Illinois Tollway

Traversable Element

RDG-Figure 4-1. Breakaway Support

Stub Height Measurements

51

4 in.

Page 52: Barrier Warrant Process - Illinois Tollway

Traversable Element

4’

1:6

(V:H)

52

Page 53: Barrier Warrant Process - Illinois Tollway

Breakaway Sign Supports

An important feature of this breakaway sign system is the ability of its post support to swing up and out of the way when it is struck by an errant vehicle.

53

Page 54: Barrier Warrant Process - Illinois Tollway

Safety End Treatment-Steel Grate

Headwall and storm sewer outlets shall be provided with appropriate safety end treatment per Standard Drawings – Section B.

54

Page 55: Barrier Warrant Process - Illinois Tollway

Roadway Lighting

Steel Helix Foundation

Needs to be a Traversable

Element

55

Page 56: Barrier Warrant Process - Illinois Tollway

Level 2 Analysis

When shielding is required and barrier length of need must be determined.

Cantilever sign post

56

Page 57: Barrier Warrant Process - Illinois Tollway

Level 2 Analysis

This analysis is performed for:

EXISTING/PROPOSED OBSTACLES when there are no feasible alternatives for eliminating, or reducing the impact severity of the obstacle.

PROPOSED OBSTACLES for an Alternative in a Level 3 Analysis. The length of barrier and type of terminals has to be determined for each Alternative that involves shielding of the obstacle.

57

Page 58: Barrier Warrant Process - Illinois Tollway

Level 3 Analysis

The evaluation of 2 or more possible alternatives for eliminating or reducing the obstacle.

Only consider alternatives that are feasible.

Cannot analyze an alternative that leaves an obstacle unshielded in the clear zone.

This is part of the design process

58

Page 59: Barrier Warrant Process - Illinois Tollway

Roadside Safety Analysis Program (RSAP)

http://rsap.roadsafellc.com/

59

Page 60: Barrier Warrant Process - Illinois Tollway

Level 3 Analysis

Overhead sign to span roadway with barrier

Overhead sign to span beyond clear zone with no barrier

60

This is most

common Level 3

obstacle

Page 61: Barrier Warrant Process - Illinois Tollway

Barrier Warrant Analysis Procedure (cont.)

g. Clear Zone

h. Clear Zone Adjustment

i. Lateral Extent of the Area of Concern

j. Warrant Analysis Level

k. Lateral Offset of Barrier (L2)

61

Page 62: Barrier Warrant Process - Illinois Tollway

k. Lateral Offset of Barrier

L2

Figure 5-39. Approach Barrier Layout Variables

L2

62

Page 63: Barrier Warrant Process - Illinois Tollway

k. Lateral Offset of Barrier

2’- 2 ¾” With Type G-3 Gutter

63

Page 64: Barrier Warrant Process - Illinois Tollway

k. Lateral Offset of Barrier 1’-0” Without Gutter

Page 65: Barrier Warrant Process - Illinois Tollway

Barrier Warrant Analysis Procedure (cont.)

g. Foreslope/Backslope

h. Clear Zone

i. Clear Zone Adjustment

j. Warrant Analysis Level

k. Lateral Offset of Barrier

l. Upstream End of Guardrail

65

Page 66: Barrier Warrant Process - Illinois Tollway

l. Upstream End of Guardrail

L2

Figure 5-39. Approach Barrier Layout Variables

Point of Need

66

Page 67: Barrier Warrant Process - Illinois Tollway

Barrier Warrant Analysis Procedure (cont.)

g. Clear Zone

h. Clear Zone Adjustment

i. Lateral Extent of the Area of Concern

j. Warrant Analysis Level

k. Lateral Offset of Barrier

l. Upstream End of Guardrail

m. Upstream End of Barrier Wall

67

Page 68: Barrier Warrant Process - Illinois Tollway

m. Upstream End of Barrier Wall

A = Suggested maximum flare rate for rigid barrier system.

B = Suggested maximum flare rate for semi-rigid barrier system.

68

Page 69: Barrier Warrant Process - Illinois Tollway

Barrier Warrant Analysis Procedure (cont.)

g. Clear Zone

h. Clear Zone Adjustment

i. Lateral Extent of the Area of Concern

j. Warrant Analysis Level

k. Lateral Offset of Barrier

l. Upstream End of Guardrail

m. Upstream End of Barrier Wall

n. Downstream Terminal

69

Page 70: Barrier Warrant Process - Illinois Tollway

n. Downstream Terminal

Traffic Barrier Terminal Type T2

Traffic Barrier Terminal Type T6

70

Page 71: Barrier Warrant Process - Illinois Tollway

Barrier Warrant Analysis Procedure (cont.)

g. Clear Zone

h. Clear Zone Adjustment

i. Lateral Extent of the Area of Concern

j. Warrant Analysis Level

k. Lateral Offset of Barrier

l. Upstream End of Guardrail

m. Upstream End of Barrier Wall

n. Downstream Terminal

o. Barrier Obstacle

71

Page 72: Barrier Warrant Process - Illinois Tollway

Barrier Warrant Analysis Procedure (cont.)

g. Clear Zone

h. Clear Zone Adjustment

i. Lateral Extent of the Area of Concern

j. Warrant Analysis Level

k. Lateral Offset of Barrier

l. Upstream End of Guardrail

m. Upstream End of Barrier Wall

n. Downstream Terminal

o. Barrier Obstacle

p. Compare existing length to proposed

72

Page 73: Barrier Warrant Process - Illinois Tollway

Barrier Warrant Analysis Procedure (cont.)

g. Clear Zone

h. Clear Zone Adjustment

i. Lateral Extent of the Area of Concern

j. Warrant Analysis Level

k. Lateral Offset of Barrier

l. Upstream End of Guardrail

m. Upstream End of Barrier Wall

n. Downstream Terminal

o. Barrier Obstacle

p. Compare existing length to proposed

q. Prepare warrant text and exhibits

73

Page 74: Barrier Warrant Process - Illinois Tollway

PRESENTATION OF BARRIER WARRANT

ANALYSIS TBG – SECTION 6.0

74

Page 75: Barrier Warrant Process - Illinois Tollway

Presentation of Barrier Warrant Analyses

Samples

Speed Profile

Location Plan

Level 1 Table

Data Sheet

Calculation sheet

Site Plan

RSAP Feature Sketch

Level 0 Table

75

Page 76: Barrier Warrant Process - Illinois Tollway

Presentation of Barrier Warrant Analysis

Checklists

Cover Sheet

Table of Contents

Disposition

Location Plan

Data Sheet

Calculation Sheet

Site Plan

Summary Site Plan

Cross Sections

Level 0 Table

Level 1 Analysis

Level 2 Analysis

Level 3 Analysis

76

Page 77: Barrier Warrant Process - Illinois Tollway

BARRIER WARRANT SUBMITTAL SCHEDULE

TBG – SECTION 7.0

77

Page 78: Barrier Warrant Process - Illinois Tollway

Submittal Schedule

Barrier Warrant Analysis is part of the Design Process.

Barrier Warrants are not considered final until there are no further review comments on the final submittal.

78

Page 79: Barrier Warrant Process - Illinois Tollway

Concept Meeting

The general goals of the meeting are to:

Provide an overview of the project limits, scope of work, and any omissions

Summarize the overall project schedule

Discuss potential AOC’s and barrier warrant analysis methodology

Present unique project issues

Identify locations that are good candidates to be included in the preliminary submittal.

79

Page 80: Barrier Warrant Process - Illinois Tollway

Preliminary Submittal Barrier Warrant Analysis shall be submitted with

the Preliminary Plans.

Submit a minimum of five sample locations

At least two Level 2

At least two Level 3 with RSAP output and feature sketch

It is recommended that Designer choose locations that may require more review cycles, are more complex or require extra coordination.

Submit one page of the Level 1 Table (at least 4 AOC’s)

Submit Completed Checklist.

80

Page 81: Barrier Warrant Process - Illinois Tollway

Pre-Final Submittal Barrier Warrant Analysis shall be submitted with

the Pre-Final Plans.

Similar to Pre-Final Plans, the Pre-Final Barrier Warrant shall be considered 100% complete.

All comments on preliminary submittal addressed and a disposition provided.

Submit completed checklist.

All above materials shall be submitted through the Tollway’s web-based project management system and in hard copy format.

81

Page 82: Barrier Warrant Process - Illinois Tollway

Final Submittal

DSE Final Barrier Warrant shall match the DSE plans submitted for advertisement.

Final Barrier Warrant Analysis should be complete at the Final Plan Check.

All previous review comments addressed and a disposition provided.

Submit completed checklist.

82

Page 83: Barrier Warrant Process - Illinois Tollway

Barrier Warrant Amendment Process

83

What

initiated

change to

design?

Who

initiated

change?

Who

completes

Amendment

to BWA?

In addition to

GEC, who

reviews BWA

Amendment?

Field

change

CM or

Contractor DSE CM

Field Change

Page 84: Barrier Warrant Process - Illinois Tollway

Barrier Warrant Amendment Process

84

What

initiated

change to

design?

Who

initiated

change?

Who

completes

Amendment

to BWA?

In addition to

GEC, who

reviews BWA

Amendment?

Value

Engineering

Proposal

Contractor Contractor’s

Designer DSE & CM

Value Engineering Proposal

Page 85: Barrier Warrant Process - Illinois Tollway

Barrier Warrant Amendment Process

85

What

initiated

change to

design?

Who

initiated

change?

Who

completes

Amendment

to BWA?

In addition to

GEC, who

reviews BWA

Amendment?

Performance

Based

Design

Contractor Contractor’s

Designer DSE & CM

Performance Based Design

Page 86: Barrier Warrant Process - Illinois Tollway

Record

Drawings

Field

Conditions

Final Amended

Barrier Warrant

3 Components must be equal

=

=

86

Page 87: Barrier Warrant Process - Illinois Tollway

Questions ?

E-Mail: [email protected]

87

Page 88: Barrier Warrant Process - Illinois Tollway

Closing Remarks

Fill out the comment sheet

Take PDH forms

Contact any of the presenters with questions

PowerPoint presentations will be posted to the Tollway website after the 3rd session