Bar Bending Schedule Excel Form4(2)

download Bar Bending Schedule Excel Form4(2)

of 133

Transcript of Bar Bending Schedule Excel Form4(2)

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    1/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    CONTENTS PAGE

    ontents Page!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- 1 -

    "ist o# $a%les!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- 4 -

    $a%le o# &igures!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- ' -

    ()nopsis!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- * -

    1!+ Introduction!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- , -

    !+ Project development!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- . -

    !1 Introduction!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- . -

    ! Researc/!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- . -

    !3 onceptual Design!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- 10 -

    !4 (c/eme c/oice at conceptual design stage!!!!!!!!!!!!!!!!!!!!!!!!- ' -

    !' &eed%ac #rom onceptual Design Intervie2!!!!!!!!!!!!!!!!!!!!!- 31 -

    !* Detailed Design!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- 31 -

    !, &eed%ac #rom Detailed Design Intervie2!!!!!!!!!!!!!!!!!!!!!!!!!!- 3' -

    !0 &inal design!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- 3* -

    !. &eed%ac #rom Design (eminar!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- 3, -

    3!+ Met/od (tatements!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- 30 -

    3!1 Description o# or and "ocation!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- 30 -

    3! Piling met/od statement!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- 30 -

    3!3 Rein#orcement Met/od statement!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- 4 -

    3!4 al2a) Met/od statement!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- 44 -

    emis 5um%er 44,4 1 (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    2/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    4!+ Material (peci6cation !!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- 4' -

    4!1 (teel Elements omprising t/e Piling #oundations!!!!!!!!!!!!- 4' -

    4! (teel connections to Piling #oundations!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- 4* -

    4!3 (teel Rein#orcement!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- 4, -

    4!4 al2a) components!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- 40 -

    '!+ onstruction Processes!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- 4. -

    *!+ $esting Procedures!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- '1 -

    *!1 D)namic Pile $esting 7DP$8!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- '1 -

    *! "oading test!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- ' -

    *!3 Metallic coating to %eams #or al2a)!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- ' -

    ,!+ Per#ormanceriteria!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- '4 -

    ,!1 orrosion Protection!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- '4 -

    0!+ Maintenance!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- ', -

    0!1 Maintenance o# Piling 2ors!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- ', -

    0! Maintenance o# cat/odic protection o# Piling 2ors!!!!!!!!!!- '0 -

    .!+ "i#e c)cle 9na)lsis!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- * -

    .!1 "i#e )cle 9nal)sis o# t/e Piling &oundations!!!!!!!!!!!!!!!!!!!!!- * -

    .! Inventor) 9nal)sis!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- *4 -

    1+!+ Ris 9ssessment!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- *, -

    1+!1 Piling Ris 9ssessment!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- *0 -

    1+! (teel 6:ing Ris 9ssessment!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- *. -

    1+!3 al2a) Ris 9ssessment!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!! - ,+ -

    11!+ dm Regulations!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- ,1 -

    emis 5um%er 44,4 (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    3/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    11!1 Introduction!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- ,1 -

    11! Riss assessed %) DM Regulations #or Piling!!!!!!!!!!!!!!!!!!!- , -

    11!3 DM Regulations #or oring in ostal conditions;over 2ater!-

    ,3 -

    11!4 9pplication o# DM regulations during onstruction!!!!!!! !- ,' -

    1!+

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    4/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    emis 5um%er 44,4 4 (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    5/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    LIST OF TABLES

    $a%le 1 @ Matri: c/oice o# Pile s)stem to %e used!!!!!!!!!!!!!!!!!!!!!!!!!!!- 1. -

    $a%le @ omparison o# >rie# 2it/ solutions!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- ' -

    $a%le 3 @ omparison o# prices 2it/ solutions!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- * -

    $a%le 4 @ Decision matri:!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- 3+ -

    $a%le ' @ &reBuenc) o# #unctional c/ecs 7>(IC ++18!!!!!!!!!!!!!!!!!!!!- *+ -

    $a%le * @ Em%odied energ) in materials!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- *4 -

    $a%le , @ Energ) consumption during construction!!!!!!!!!!!!!!!!!!!!!!!!- *' -

    $a%le 0 @ Energ) consumption during Maintenance!!!!!!!!!!!!!!!!!!!!!!!!- ** -

    $a%le . @ Piling Ris 9ssessment!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- *0 -

    $a%le 1+ @ (teel 6:ing Ris 9ssessment!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- *. -

    $a%le 11 al2a) Ris 9ssessment!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- ,+ -

    $a%le 1 @ 5oise made due to piling 2it/ steel Piles 7>(1C 1..8! - 01

    -

    $a%le 13 @ Environmental assessment "eopold matri:!!!!!!!!!!!!!!!!!!!!- .4 -

    $a%le 14 @ >ill o# ?uantities!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- 1++ -

    emis 5um%er 44,4 ' (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    6/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    emis 5um%er 44,4 * (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    7/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    TABLE OF FIGURES

    &igure i @ Map o# 9rea during 10'4 1.+1!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- 1+ -

    &igure ii @ Map o# 9rea during 1.+* 1.3.!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- 1+ -

    &igure iii @ Map o# 9rea during 1.4 1.4.!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- 11 -

    &igure iv @ Map o# 9rea during 1.43 1..'!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- 11 -

    &igure v @ 9erial vie2 o# e:isting li#e%oat station!!!!!!!!!!!!!!!!!!!!!!!!!!!!- 13 -

    &igure vi @ Detailed map o# site location!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- 14 -

    &igure vii Geolog) o# 9rea!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- 1' -

    &igure viii @ -Pile ()stem!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- + -

    &igure i: @ Image illustrating a jac up >arge!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- '+ -

    &igure : @ >at/ing aters!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- 1+ -

    &igure :i @ 5ature Reserves!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- 1+ -

    &igure :iii @ (ites o# special scienti6c interest !!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- 1+ -

    &igure :iii @ Marine sensitive areas!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!- 1+ -

    emis 5um%er 44,4 , (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    8/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    SYNOPSIS

    $/e o%jective o# t/is report is t/e design and planning o# t/e piling

    #oundations o# a proposed R!5!"!I slip2a) li#e%oat station at (else)!

    $/e li#e%oat station is part o# t/e redevelopment o# old li#e%oat

    stations %) t/e R!5!"!I!

    $/is report s/o2s t/e project developmentC #rom concept to detailed

    6nal design! $/e 6nal design c/osen 2as to use 3'* : 3*0 : 1,4 steel

    pilesC to support t/e steel #rameC to t/e sla% and t/e portal #rame

    superstructure! 9ll piles to %e protected #rom corrosion %) a

    tec/niBue no2n as cat/odic protection! $/e design /as %een

    undertaen %) com%ined computer so#t2are anal)sis and /and

    calculationsC construction dra2ings /ave %een included!

    $/is report also loos at construction resources #or t/e piling

    #oundations including a cost appraisal in t/e #orm o# a >ill o#

    ?uantities giving a construction cost o# 3+C+*'!4'C ris assessments

    and mitigations giving a 6nancial contingenc) o# '.C'++C 2/ole li#e

    costing giving a total li#e cost o# '31C40.C'.C a Gantt c/art s/o2ing

    t/e piling #oundation activities and construction duration o# 3.da)sC

    detailed met/od statement #or t/e main area o# 2orC DM appraisal

    emis 5um%er 44,4 0 (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    9/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    and material speci6cations including per#ormance criteriaC

    construction processes and environmental assessment!

    emis 5um%er 44,4 . (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    10/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    1 .0 INTRODUCTION

    $/is report contains t/e design o# t/e &oundations and 2al2a)

    connecting t/e s/oreline to a proposed #ull) operating R!5!"!I slip2a)

    li#e%oat station at (else)!

    $/e report includes t/e development o# t/e designC recommendations

    #or t/e 6nal designC calculationsC dra2ingsC met/od statementC ris

    assessmentsC DM appraisalC Gantt c/art 2it/ resource aggregationC

    >ill o# ?uantities and material speci6cationsC including an

    environmental assessment #or t/e construction o# t/e #oundations and

    2al2a)!

    $/is is Volume 1 o# t/e report and s/ould %e read in conjunction 2it/

    Volumes C and 3 along 2it/ t/e Preliminar) Engineering Report!

    Volume 1 o# t/e report covers t/e design o# t/e &oundations and

    2al2a) connecting t/e s/oreline to a proposed #ull) operating

    R!5!"!I slip2a) li#e%oat station at (else)!

    emis 5um%er 44,4 1+ (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    11/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    Volume o# t/e report covers t/e design o# t/e slip2a) and t/e sla%

    arrangement to a proposed #ull) operating R!5!"!I slip2a) li#e%oat

    station at (else)!

    Volume 3 o# t/e report covers t/e design o# t/e superstructure to a

    proposed #ull) operating R!5!"!I slip2a) li#e%oat station at (else)!

    $/e Preliminar) Engineering Report covers t/e group conceptual

    researc/ and design solutions #or t/e R!5!"!I "i#e%oat station!

    emis 5um%er 44,4 11 (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    12/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    2 .0 PROJ ECT DEVE LOPM ENT

    2.1 Introdut!on

    $/is c/apter illustrates t/e development o# t/e #oundation design #or

    t/e li#e%oat station #rom t/e conceptual design stage up to t/e 6nal

    design! It s/o2s t/e development o# t/is particular aspect o# t/e

    sc/eme! It #ollo2s t/e general researc/ 2/ic/ is detailed in t/e

    Preliminar) Engineering ReportC and demonstrates t/e individual

    researc/ done a%out t/e #oundationsC construction pro%lemsC loadingC

    design development and c/oice o# construction met/od!

    2.2 R"#"$r%

    Muc/ o# t/e researc/ 2as made at t/e conceptual stageC and is

    contained in t/e preliminar) report! >elo2 is researc/ t/at is

    applica%le to t/e design o# t/e #oundationC t/us producing

    considerations #or an) #uture design!

    emis 5um%er 44,4 1 (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    13/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    2.2.1 S!t" %!#tor&.

    &igure i @ Map o# 9rea during 10'4 1.+1C 7Digimap istoricC ++*8!

    &igure ii @ Map o# 9rea during 1.+* 1.3.C 7Digimap istoricC ++*8!

    emis 5um%er 44,4 13 (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    14/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    &igure iii @ Map o# 9rea during 1.4 1.4.C ourtes) o# 7Digimap istoricC ++*8!

    &igure iv @ Map o# 9rea during 1.43 1..'C ourtes) o# 7Digimap istoricC ++*8!

    9s t/e maps a%ove s/o2C #or t/e last 1'+ )ears t/is area /as %een ver)

    sparsel) populatedC 2it/ no #orm o# industr) development! $/e area

    /as %een dedicated as a li#e%oat station #or t/e last 1'+ )ears!

    $/ere#ore contamination o# t/e area s/ould %e ver) little! Potential

    emis 5um%er 44,4 14 (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    15/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    contamination could come #rom #uel storage #or t/e li#e%oats t/is 2ill

    %e investigated in an) #uture environmental assessment!

    2.2.2 G"n"r$' !n(or)$t!on

    Pro*'" '"+"' ,

    E:isting (tation

    "ong sloping %eac/

    Deep 2ater access

    -$t"r '"+"' ,

    ig/ tide@ F '!' m

    "o2 tide@ F +!1 m

    $idal Range@ F '!+4 m

    A"## ,

    Eas) access #rom 2ater since t/e station is at t/e

    end o# a Pier 7good dept/8

    5ot eas) access and paring #or t/e cre2 and t/e

    emergenc) services!

    &urt/ermore t/e materials /ave to %e %roug/t %)

    sea!

    T%" #"$ r"##ur"/ t%" r"##ur" o( t%" $+"#

    Ma:imum tidal stream 7not8 @ !4 not

    emis 5um%er 44,4 1' (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    16/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    Ma:imum tidal stream 7m;s8 @ 1!3 m;s

    emis 5um%er 44,4 1* (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    17/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    E'"tr!!t& #u'&

    $/ere 2ould %e no pro%lems to t/e po2er suppl) i# t/e e:isting

    li#e%oat station 2as to %e replaced! $/e ne2er li#e%oat station 2ould

    %e a%le to use a similar electricit) suppl) as t/e older station!

    -$t"r #u'&

    5o pro%lem to suppl) 2aterC along a roadC on t/e %eac/!

    2.2. E!#t!n3 '!("4o$t #t$t!on.

    &igure v @ 9erial vie2 o# e:isting li#e%oat stationC 7"ive "ocalC ++,8!

    &igure illustrates t/e e:isting location o# t/e li#e%oat station! $/is

    s/o2s t/e 2al2a) 2/ic/ connects t/e station to t/e land and a car

    emis 5um%er 44,4 1, (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    18/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    paring space to accommodate t/e cre2 and emergenc) services! $/e

    possi%le location o# t/e proposed li#eguard station is s/o2n in t/e

    /atc/ed area s/o2n adjacent to t/e station! $/is 2ill tae #ull o#

    advantage o# t/e e:isting #acilities planning issues s/ould not %e a

    pro%lem due to demolition o# an old station and replacing it 2it/ a

    ne2 one!

    $/ere /as %een a station located in t/is area since t/e 10++s

    t/ere#ore site conditions s/ould not %e a pro%lem #or an) #uture

    development!

    &igure vi @ Detailed map o# site location 7DigimapC ++,a8!

    emis 5um%er 44,4 10 (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    19/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    &igure vii Geolog) o# 9reaC ourtes) o# 7(HP9C 1...a8

    &igure 3 illustrates t/e location o# /ig/ and lo2 2ater levels! $/is

    s/o2s t/at t/e li#e%oat station location is more t/an adeBuate

    concerning 2ater levels! $/e tidal range at mean spring tides is

    around 4!, m at (else)! In t/e central part o# t/e /annelC t/e

    ma:imum speed o# tidal currents on mean spring tides is %et2een

    +!,' and 1!+ m;s! and can increase to 1!' m;s! 7Englis/ 5atureC

    ++*8!

    emis 5um%er 44,4 1. (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    20/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    $/is 6gure also e:plains t/at t/e main topsoil is sand and s/ingle!

    &igure 4 demonstrates t/at (else) is located 2it/in t/e "ondon la)

    #ormationC 2/ic/ is made up o# cla)! $/ere#ore t/e structural soil

    properties o# la) 2ill %e used #or t/e #oundation design!

    2.2.5 D"#!3n on#!d"r$t!on# 4$#"d on r"#"$r%

    E:isting (tation /as piled #oundations t/ere#ore it 2ould %e sa#e to

    assume #rom t/e researc/ t/at using piled #oundations #or t/e

    proposed li#e%oat station 2ould %e t/e most suita%le option!

    "ong sloping %eac/ signi6es t/at t/e location o# t/e li#e%oat station

    can moved! it/ c/ange o# locationC t/e #oundation design 2ill

    c/angeC due to c/ange in tide levels! $/is could increase or decrease

    t/e sies o# t/e mem%ers!

    Deep 2ater access t/ere#ore indicates t/e #oundation 2ill /ave to %e

    used as a column #or t/e li#e%oat station!

    9 tidal range o# over ' m means t/at t/e #oundation 2ill /ave to %e

    constructed 2/ile su%merged in t/e 2ater!

    9ccess on site is di=icult t/ere#ore most o# t/e materials 2ill /ave to

    come to site %) seaC 2it/ construction over 2ater!

    emis 5um%er 44,4 + (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    21/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    $/ere 2ould %e no pro%lems to t/e po2er suppl) i# t/e e:isting

    li#e%oat station 2as to %e replaced! $/e ne2er li#e%oat station 2ould

    %e a%le to use a similar electricit) suppl) as t/e older station! $/is

    could /elp 2it/ possi%le protection met/ods!

    Ground conditions! 7"ondon cla)8

    - *m o# sand

    - 3+m o# cla)

    Properties o# (and!

    - Moderatel) /ig/ compressi%ilit) reBuiring lo2 %earing

    pressures in order to avoid e:cessive settlement o#

    #oundations!

    Properties o# la)! 7(ti=8!

    - Relativel) /ig/ %earing capacit)!

    - Moderate to lo2 compressi%ilit)!

    emis 5um%er 44,4 1 (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    22/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    - eav) structures #ounded on t/em s/o2 slo2 settlement

    over a ver) long

    period o# time 7$omlinsonC ++18!

    - &oundation s/ould %e taen do2n to a dept/ 2/ere t/ere

    2ill %e little or no

    movement #rom s2elling or s/rinage!

    - (/ear strengt/ varies due to 6ssures in cla)sC 2it/ 6ssures

    %eing /ard to

    - predict 7$omlinsonC ++18!

    emis 5um%er 44,4 (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    23/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    2. Con"tu$' D"#!3n

    $/e e:isting structure o# t/e li#e%oat station at (else) /as %een in

    operation since t/e 10++s! $/e implementation o# a ne2 generation

    li#e%oat station is applica%le to t/is location! "i#e%oats are %ecoming

    larger and man) o# t/e old li#e%oat stations suc/ as (else) simpl)

    cant 6t t/em!

    $/e R5"I design %rie# states t/at li#e%oat stations s/ould /ave a '+

    )ear design li#e! 9s (else) is onl) + )ears oldC it /as not come to t/e

    end o# its design li#e! >ut due to t/e sie o# t/e e:isting stationC lac o#

    #acilities doesnt meet modern da) standardsC so renovation o# t/e

    e:isting structure is inappropriate!

    >elo2 are t/e e) pro%lem areas associated 2it/ t/e (else) site and

    potential solutions!

    2..1 Found$t!on #t")

    $/e major pro%lem 2it/ t/e #oundation design 2as t/at an) #orm o#

    construction 2ould /ave to %e 2it/in t/e medium o# 2ater! ater

    poses pro%lems suc/ as corrosionC construction processesC and /ealt/

    A sa#et) riss!

    emis 5um%er 44,4 3 (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    24/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    $/e 6rst decision made 2as to use piled #oundationsC piled

    #oundations /ave %een used in marine construction #or /undreds o#

    )ears 7$omlinsonC ++18C and t/ere#ore it 2as t/e o%vious s)stem to go

    #or! Jsing traditional #oundations suc/ as pad #oundations 2ould /ave

    meant t/e use o# temporar) 2ors suc/ as a co=erdamC 2/ic/ 2ould

    /ave %een potentiall) ver) e:pensive #or a relativel) small project!

    $/e ne:t pro%lem encountered 2as 2/ic/ piling s)stem to useC eit/er

    driven or %ored piling! Due to t/e ground conditions o# sand and cla)C

    it 2as decided t/at driven piles 2ould %e most suita%le! $/e) can %e

    readil) carried a%ove ground level especiall) in marine structures

    7$omlinsonC ++18 2/ic/ 6ts t/e speci6c needs o# t/is project 2it/ an

    added %onus o# no spoil %eing created #rom t/e drivingC t/us not

    altering t/e 2ater environment!

    $o de6ne 2/at t)pe o# pile 2ill %e usedC a comparison 2it/ a decision

    matri: is use#ul!

    Hn t/e le#t is t/e magnitude o# impact@ #rom + to '

    Hn t/e rig/t is t/e importance o# t/e impact@ #rom + to 1+

    9ugured concrete pile Displacement (teel pile

    Di=icult) o# design ;, 3;,ost o# plant ;* 3;'(peed o# construction ;' 4;4(a#et) ';. ';.

    emis 5um%er 44,4 4 (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    25/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    5oise impact *;4 ;0Tot$' 106 11

    $a%le 1 @ Matri: c/oice o# Pile s)stem to %e used!

    Driven Displacement piles are more adapted to t/is particular project!

    emis 5um%er 44,4 ' (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    26/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    T&"# o( Dr!+"n P!'"#

    (teel piles 2it/ Rein#orced concrete!

    Precast Piles!

    (teel piles!

    $/e decision 2as to use a steel tu%ular pile 2it/ concrete encased

    2it/in and rein#orced 2it/ a steel pile as t/e structural element!

    -Pile

    oncrete

    $u%ular (teel Pile

    &igure viii @ -Pile ()stem!

    Properties o# -piles include 7see 6gure viii8@

    ig/ arr)ing capacit)

    ard driving 2it/out s/attering

    an %e lengt/ened %) 2elding

    Good resistance to lateral #orces and %ucling

    9dvantageous in marine structures 2/ere t/eir resilience and

    column strengt/ in

    emis 5um%er 44,4 * (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    27/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    resisting impact #orces #rom s/ips 7$omlinsonC ++18!

    ig/ tensile allo) steel piles 2ill %e used as t/e) are suita%le #or

    /ig/ impact #orces #rom s/ips or 2aves in lo2 temperature

    conditions 7$omlinsonC ++18!

    (teel piles corrodes at a speed o# +! +!. mm;)ear!

    9ll concrete to %e /ig/ sulp/ate resisting grade '+C 2it/ a

    cement content o# 33' g;mKC 2it/ t/e 2ater cement ratio not

    e:ceeding +!4!

    $/e ne2 station needs to provide an aest/eticall) pleasing and /ig/l)

    #unctional %uildingC )et at t/e same time t/e #orm and materials used

    need to 6t in 2it/ t/e e:isting area!

    $/e relativel) small cross-sectional area o# steel piles com%ined 2it/

    t/eir /ig/ strengt/ maes penetration easier in 6rm soil 79%e%e A

    (mit/C 1...8. $/e) can %e easil) cut o= or joined %) 2elding! 9s t/e

    pile 2ill %e surrounded %) 2aterC t/ere 2ill %e a ris o# corrosionC %ut

    ris o# corrosion is not as great as one mig/t t/in!

    It is common to allo2 #or an amount o# corrosion in design %) simpl)

    over dimensioning t/e cross-sectional area o# t/e steel pile! In t/is

    2a) t/e corrosion process can %e prolonged up to '+ )ears! 5ormall)

    t/e speed o# corrosion is +!-+!' mm;)ear andC in designC t/is value

    emis 5um%er 44,4 , (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    28/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    can %e taen as 1mm;)ear 79%e%e A (mit/C 1...8! $/ere#ore as added

    protectionC concrete 2ill %e pumped into t/e centre o# t/e pileC so in

    a=ect t/ere 2ill %e a concrete pile surrounded %) a steel casingC so

    2/en t/e steel eventuall) corrodes t/e concrete 2ill support t/e

    structure!

    $/ese piles 2ill %e connected to rein#orced concrete %eams acting as

    pile caps! $/e %eams 2ill t/en %e connected to a rein#orced concrete

    Loor designed to >( 011+- Part 1C >( 011+- Part C >( 011+- Part 3! 9

    ig/ grade concrete 2ill need to %e used so to avoid erosion #rom t/e

    elements and t/e steel 2ill /ave a minimum o# '+mm concrete cover

    t/is is to /ave protection to prevent corrosion!

    2..2 In!t!$' d"#!3n.

    orst loading@

    >oat +

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    29/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    2.. Pro4'"), Cont$)!n$t!on

    9s mentioned in section !!1 t/e maps s/o2C #or t/e last 1'+ )ears

    t/is area /as %een ver) sparsel) populatedC 2it/ no #orm o# industr)

    development! $/e area /as %een dedicated solel) #or use as a li#e%oat

    station #or t/e last 1'+ )ears!

    It is unliel) t/at contamination 2ill /ave to %e dealt 2it/! Potential

    #or contamination 2ill %e #rom construction or operation processes!

    &or e:ampleC a small possi%ilit) o# contamination t/roug/ oil or petrol

    spillage at sites 2/ere an older li#e%oat station is %eing replaced %) a

    ne2er one!

    $o avoid t/e ris o# contaminating t/e marine environment a detailed

    sc/eme;met/od statement #or 2ors on site s/ould %e created to

    prevent pollution!

    2..5 Pro4'"), S!t" A"## $nd Tr$:! M$n$3")"nt.

    $/ere is one road in and out o# t/e to2n - 2/ic/ %rieL) %ecomes a

    %ridge at a point no2n as Nt/e #err)NC crossing t/e 2ater inlet at

    Pag/am ar%our 7a part o# >ognor8! $/e term #err) is used %ecause at

    t/e %ridge point t/ere 2as at one time a #err)man 2/o too people

    across to t/e island 72iipediaC ++,8!

    emis 5um%er 44,4 . (else) "i#e%oat (tation

    http://en.wikipedia.org/wiki/Bognorhttp://en.wikipedia.org/wiki/Bognor
  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    30/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    $/is is a %us) area as it is a local costal route connecting to t/e main

    to2n o# (else)! $/e construction 2ors s/ould not adversel) a=ect

    congestion on t/e in and out o# t/e to2nC as t/e project is not a large

    scale civil engineering project!

    9#ter construction o# t/e siteC t/ere 2ill %e a no increase in t/e volume

    o# t/e population using t/e "i#e%oat station as it is replacing t/e

    e:isting station!

    $o ensure tra=ic is not a pro%lemC deliveries s/ould not correspond

    2it/ rus/ /our periods and minimal distur%ance 2it/ local routes

    s/ould %e ascertained! Jsing suppl) %arges as a means o#

    ascertaining t/e materials is also advantageous!

    2..6 Pro4'"), Cr$n" $nd !'!n3 $"##.

    9s t/e li#e%oat station is surrounded %) 2aterC t/ere 2ill %e an issue

    2it/ getting t/e materials to siteC and li#ting /eav) materials around

    site 2ill not %e eas)! Piling also 2ill %e di=icult as t/ere is 2ater

    constantl) surrounding t/e location!

    &irstl) a 2al2a) 2ill %e constructed #rom t/e land to t/e site 2/ere

    materials can %e delivered straig/t to site! 9ll materials 2ill %e stored

    on land under /ig/ securit)! 9 mini crane plat#orm 2ill %e constructed

    emis 5um%er 44,4 3+ (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    31/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    adjacent to t/e site t/ere#ore li#ting /eav) materials around t/e site

    2it/ ease! oncerning t/e piling a spud leg piling rig s)stem is to %e

    used to install t/e piles! $/is maes access relativel) eas) as t/e

    pilling rig Loats to its destination!

    2..8 Pro4'"), ;"$'t% $nd S$("t& !n U#"

    Due to t/e #undamental nature o# li#e%oat station constructionC

    2oring over 2ater is going to cause major /ealt/ and sa#et) issues!

    it/ t/e potential o# immersion and even #atalit) %eing /ig/ during

    t/e construction process! $/e onl) logical 2a) to mitigate against

    suc/ riss is to create a Ris assessmentC and met/od statement

    detailing t/e ris and conseBuences 2it/ control measures e=ectivel)

    reducing t/e ris o# injur)

    emis 5um%er 44,4 31 (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    32/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    2.5 S%")" %o!" $t on"tu$' d"#!3n #t$3"

    It 2as decided to do a c/eclist o# t/e R5"I room reBuirementsC and

    t/en compare t/eses to t/e preliminar) conceptual dra2ings! $/us

    providing t/e %est solution #or t/e %rie#!

    ROOM Ot!on 1 Ot!on 2 Ot!on Bo$t roo) Designed to (I %rie#

    >rie#

    (tatus(ie

    >rie#(tatus

    (ie>rie#

    (tatus(ie

    Cr" roo) ,mO 9rea

    3*mO 1 34 mO 1 3

    m

    O 1 3'

    m

    O

    Including a galle) 1 0 mO 1 *mO 1 *

    mO

    C%$n3!n3 roo)

    9rea 3+mO 1 3* mO 1 31mO 1 31

    mO

    "ocated atground level +

    &irst&loor 1 +

    &irst&loor

    M$n$3"r

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    33/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    O O

    9rea Q 1++mO 1+ mO 1

    1.4

    mO 1

    1.4

    mO

    TOTAL 13 16 .

    1 it passes>rie#

    + it doesntpass >rie#

    $a%le @ omparison o# >rie# 2it/ solutions!

    Jsing t/e >rie# as a c/eclistC solution is s/o2n as t/e most

    #avoura%le solution #or t/e li#e%oat station!

    2.5.1 Co#t

    $/ere are man) issues 2/ic/ need to %e reLected upon 2/en deciding

    2/ic/ sc/eme 2ill %e c/osen as t/e pre#erred oneC one o# t/ese

    implications is cost! 9s t/is is a preliminar) report and t/e designs are

    at a conceptual stageC t/e Loor area 2ill %e used to calculate t/e

    overall cost roug/l)!

    (pons 9rc/itects and >uilders Price >oo reveals t/e cost to %uild an

    am%ulance station is %et2een ,3+ and 1C+0+ per sBuare metre

    7"angdonC D! ++*8! $/e use o# an am%ulance station is onl) a guide as

    t/e %oo did not /ave li#e%oat stations as an option!

    ost o# t/e

    Hption

    Hption 1 734*

    m8

    Hption 73+

    m8

    Hption 3 73+

    m8&rom 'C '0+ 33C*++ 33C*++Jp to 3,3C *0+ 34'C*++ 34'C*++

    emis 5um%er 44,4 33 (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    34/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    $a%le 3 @ omparison o# prices 2it/ solutions!

    9t t/is preliminar) stageC t/is doesnt tae into account t/e slip2a) or

    #oundation and sla% designC %ut just t/e structure o# t/e actual

    li#e%oat station! >ut at t/is stage it gives some #orm o# indication on

    costing #or eac/ sc/eme even t/oug/ t/e) seem ver) lo2!

    emis 5um%er 44,4 34 (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    35/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    2.5.2 D"!#!on M$tr!.

    Hption 1

    e decided to mae a Loor station! $/e c/anging room and t/e cre2

    room are upstairs and a pat/2a) 2ill %e created to lin t/em toget/er!

    $/e ground Loor is more %asic 2it/ t/e souvenir s/opC and t/e o=ice

    on a side and t/e mec/anical storage rooms on t/e ot/er!

    Hption

    $/is solution /as #e2 di=erences@ its a single store) station! $/e

    o=ice /as a vie2 on t/e sea 2/ic/ can %e an advantage! $/e station is

    compact all rooms are close to t/e ot/ers! 9 disadvantage o# t/is

    solution is t/at it could reBuire a /ig/er sur#ace o# pilling t/is means

    a /ig/er cost!

    Hption 3

    e decided to mae a Loor station! In t/is solution 2e /ave t/e

    cre2 room and t/e souvenir s/op is upstairs! $/e ground Loor is

    occupied %) t/e o=iceC t/e c/anging room and t/e mec/anical

    storage! In t/is solutionC most o# t/e rooms are orientated to t/e sea!

    emis 5um%er 44,4 3' (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    36/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    2.5. Cr!t"r!$=# $nd t%"!r )$3n!tud"

    During Construction

    >uild a%ilit) is an important criterion in ever) construction

    project!

    9s t/e %rie# doesnt state an) time constraintsC t/e time o#

    construction isnt an important criteria!

    ost is al2a)s an important criteria especiall) in t/is case as

    t/e R5"I is a c/arit) organisationC t/ere#ore mone) comes #rom

    donations! $/is 2ill %e a ver) important consideration at t/e

    design stage!

    During operation

    Practica%ilit) #or users is t/e most important criteriaC %ecause

    t/e) need to %e as e=icient as possi%le! $/e di=erence %et2een

    good and %ad practica%ilit) could lead to t/e increase o# lives

    saved!

    Deliver) #acilities are also important #or t/e good operation o#

    t/e station!

    om#ort #or users is Buite important %ecause it is t/eir 2or

    place and t/e) spend most o# t/eir time in it!

    emis 5um%er 44,4 3* (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    37/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    General

    "ocation (uita%ilit) o# t/e project is important! It /as to %e

    integrated in t/e site and pleasant #or people living around!

    9ccess concerns t/e needs o# t/e li#eguardsC and i# it is possi%le

    #or t/em to get to t/e li#e%oat station as Buic as possi%le! Ht/er

    access comes in t/e #orm o# people 2/o visit and tour t/e

    station!

    "ocal Interest depends o# t/e vie2 2alers could get #rom and

    in t/e station! It is use#ul #or increasing donations!

    emis 5um%er 44,4 3, (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    38/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    2.5.5 L"oo'd M$tr!.

    riteria is de6ned a%oveC t/eir magnitude 7#rom 1 to 'C ' %eing t/e

    most important8 depend o# t/eir importance #or t/e project! $/e t/ree

    solutions are mared on t/ese criteria 2it/ mars #rom 1 to 1+C 1+

    %eing t/e %est!

    Cr!t"r!$# > M$3n!tud"?1>6@S%")"#

    So'ut!on

    1

    So'ut!on

    2

    So'ut!on

    Dur!n3 Con#trut!on

    >uilda%ilit) 4

    * 7:48

    4

    , 7:48

    0

    ' 7:48

    +

    $ime

    * 7:8

    1

    , 7:8

    14

    * 7:8

    1

    ost 4

    ' 7:48

    +

    , 7:48

    0

    , 7:48

    0

    Dur!n3 ut!'!#$t!on

    practica%ilit) #or people '

    * 7:'8

    3+

    . 7:'8

    4'

    ' 7:'8

    '

    Deliveries #acilities 4

    0 7:48

    3

    * 7:48

    4

    ' 7:48

    +

    om#ort 3

    , 7:38

    1

    * 7:38

    10

    , 7:38

    1

    G"n"r$' "ocation

    suita%ilit);integration to site 3

    0 7:38

    4

    * 7:38

    10

    , 7:38

    1

    9ccess

    * 7:8

    1

    0 7:8

    1*

    4 7:8

    0

    "ocal Interest

    * 7:8

    1

    4 7:8

    0

    0 7:8

    1*

    TOTAL 10, 1 1,1

    $a%le 4 @ Decision matri:

    &inall)C solution is adopted! It ma) c/ange t/e general ideas and

    design o# t/e li#e%oat station 2ill t/ere#ore 2ill #ollo2 t/e initial ideas

    emis 5um%er 44,4 30 (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    39/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    o# solution ! 9s t/is is a preliminar) solution not all ideas 2ill %e used

    and t/e design ma) even c/ange due to certain reasons suc/ as

    structural c/anges and;or c/anges in t/e design %rie#!

    emis 5um%er 44,4 3. (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    40/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    2.6 F""d4$ (ro) Con"tu$' D"#!3n Int"r+!"

    $/e conceptual design intervie2 #eed%ac #rom t/e * t/Marc/ ++,

    states t/at t/ere 2as good interpretation and understanding o# t/e

    %rie#!

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    41/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    cannot support ordinar) padC stripC or ra#t #oundations! Piled

    #oundations are a convenient met/od o# supporting structures %uilt

    over 2ater or 2/ere upli#ting loads must %e resisted 7$omlinsonC

    ++18!

    Due to t/e comments received at t/e concept intervie2 stating t/at

    t/e #oundation design 2as too comple: and t/at t/ere 2ere too man)

    pilesC a major ret/in at t/e detailed design stage 2as needed!

    2.8.1 P!'" S$!n3

    >e#ore altering t/e design o# t/e pileC t/e la)out o# t/e piles 2as

    e:amined! $/e major pro%lem 2as t/at t/e piles 2ere ver) closel)

    located %ecause t/e portal #rame and t/e step in t/e sla% level needed

    to %e supported! 9s t/ese t2o locations 2ere di=erent %ut )et ver)

    close eac/ structural element needed to %e supported %) a pile! $o

    eradicate t/is pro%lemC a group decision 2as made t/at t/e portal

    #rame and t/e c/ange in level o# t/e sla% 2ould %e modi6ed so eac/

    element 2ould line upC t/us needing one pile instead o# t2o! $/is

    reduced t/e amount o# piles needed to support t/e li#e%oat station %)

    /al#!

    emis 5um%er 44,4 41 (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    42/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    2.8.2 P!'" #t")

    $/e ot/er major pro%lem 2as t/e actual maeup o# t/e pileC t/e pile

    needed to %e simpli6ed %ut )et tae t/e loads applied upon t/e pile

    and also %e protected against an) potential corrosion! $/e decision

    2as made to eep t/e -pile as previousl) t/oug/tC %ut purge t/e

    steel tu%ular pile and concrete 6ll #rom t/e design! it/ t/is in mind

    t/e -pile 2as t/e main structural elementC %ut no2 t/e corrosion

    protection /ad %een lostC t/ere#ore it 2as decided t/at cat/ode

    protection o# t/e pile 2ould produce e:cellent protection against

    corrosion especiall) in marine conditions!

    it/ t/is no2 more simpli6ed pile designC construction o# t/e pile 2as

    also made easier! $/us potentiall) needing less people and riss to

    construct t/e pile #oundation maing it easier to ad/ere to an) #uture

    DM regulations!

    2.8. S!" o( P!'"

    Hnce t/e loads /ad %een no2n #rom t/e structural mem%ers a%ove

    t/e #oundationC calculation %egan on t/e piled #oundations!

    onsiderations made 2ere t/e vertical loadsC lateral loadsC and upli#t

    resistance!

    emis 5um%er 44,4 4 (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    43/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    $o mae t/e design process easierC a spreads/eet in Microso#t e:cel

    2as created #or vertical loading onl)! $/is gave a roug/ idea o# t/e

    sie o# pile needed!

    $/e spreads/eet /as di=erent parameters suc/ as dept/ o# pileC sin

    #riction and End %earing properties! $/e logic o# a design is t/at i#

    c/anges occurred during t/e design processC eas) modi6cation o# pile

    dept/ 2ould tell t/e user i# t/e pile could support a speci6ed load!

    Jsing t/is spreads/eetC c/anges on t/e load /ad a small e=ect on t/e

    design o# t/e #oundation! I# a load increase and t/ere is a need #or a

    %igger pileC t/e engineer /as to just alter t/e lengt/ or c/oose t/e

    ne:t pile #rom t/e spreads/eet output! (ee appendi: >!

    onstruction o# t/e #oundations is to %e over 2aterC it 2as decided to

    use t/e same pile sie %ut alter t/e lengt/s! $/is decision 2as made

    %ecause o# t/e cost o# c/anging pile /eads over 2ater! $/is is 2/ere

    t/e spreads/eet 2as most use#ul it s/o2ed 2/ic/ piles passed t/e

    load test upon t/emC /o2 long t/e pile 2ould %eC and /o2 muc/ t/e

    pile 2eig/s per metre! $/is is ver) important as t/e price o# steel is

    ver) /ig/ per tonneC so just adding a couple o# /undred ilos to eac/

    metre run 2ould /ave cost t/e client : amount in costC 2/ic/ 2as not

    accepta%le!

    emis 5um%er 44,4 43 (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    44/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    "ateral loading on t/e piles 2as a ver) di=icult specialist design! $o

    calculate i# t/e pile 2ould %e a%le to resist t/e lateral loads! (taad pro

    2as incorporated into t/e design processC t/e pile 2as anal)sed as a

    column! 9 point o# 6:it) m into t/e cla) 2as assumedC 2it/ partial

    restraint at t/e top #rom t/e structure! $/is 2as anal)sed in (taad pro

    and passed all c/ecs! $/ere#ore #rom t/e vertical and lateral loadingC

    a 3'* : 3*0 : 1,4 pile 2as to %e used!

    $/e piles 2ould %e attac/ed to t/e underside o# t/e superstructure

    2it/ nominal M4 %olts and a steel plate! 9ll %olts 2ere (&G %olts!

    2.8.5 D"t$!'"d d"#!3n.

    orst loading@

    (uperstructure 1+++ 5

    "ateral loads 4' 5

    PILE, 7 68 5 15 ; !'".

    (ee appendi: > #or calculations!

    9ll dra2ings 2ere detailed to /ave t/ese design criteria and can %e

    seen in appendi: !

    emis 5um%er 44,4 44 (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    45/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    2. F""d4$ (ro) D"t$!'"d D"#!3n Int"r+!"

    $/e detailed design intervie2 #eed%ac #rom t/e 3 rdo# Marc/ ++,

    states t/at t/e dra2ings 2ere o# a good standard %ut a detailed cross

    section o# t/e pile 2as reBuired illustrating t/e dimensions o# t/e

    section! alculations 2ere stated as %eing t/oroug/ %ut t/ere 2as

    some an:iet) a%out t/e sta%ilit) o# t/e Le:i%ilit) o# t/e piles! 9s t/e

    2orst case 2as taen #or t/e slip2a)C %oat /ouse and 2al2a)C t/e

    pile lengt/s didnt c/ange in t/ere respective areas! It 2as said t/at

    t/is needed to %e c/anged as loads e=ectivel) c/anged in di=erent

    areas! $/e consideration o# t/e construction limitations 2ere also

    considered 2it/ noise %eing t/e major issue t/at needs more t/oug/t!

    emis 5um%er 44,4 4' (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    46/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    2. F!n$' d"#!3n

    it/ t/e e:cel document it 2as possi%le to alter t/e di=erent loadings

    on t/e piles ver) easil)C t/ere#ore t/e lengt/s o# t/e piles altered

    t/roug/out t/e structure saving t/e client economicall)!

    Hn t/e su%ject o# t/e sta%ilit) o# t/e Le:i%ilit) o# t/e piles I looed at

    t/e code >(0++4 ,!3!3!3! and ,!3!3!4 and it stated to design t/e pile

    as a column!

    (ection (ies

    5o! 1'!1m long 3'* : 3*0 : 1,4 -Piles

    5o! 1'!..m long 3'* : 3*0 : 1,4 -Piles

    5o! 1*!0,'m long 3'* : 3*0 : 1,4 -Piles

    5o! 1,!,*+m long 3'* : 3*0 : 1,4 -Piles

    5o! 10!*4'm long 3'* : 3*0 : 1,4 -Piles

    5o! 1.!'3+m long 3'* : 3*0 : 1,4 -Piles

    5o! 4!.4m long 3'* : 3*0 : 1,4 -Piles

    5o! 4!,+m long 3'* : 3*0 : 1,4 -Piles

    5o! 4!4*'m long 3'* : 3*0 : 1,4 -Piles

    5o! 4!+'m long 3'* : 3*0 : 1,4 -Piles

    5o! 3*!.+'m long 3'* : 3*0 : 1,4 -Piles

    emis 5um%er 44,4 4* (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    47/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    5o! 3*!*0+m long 3'* : 3*0 : 1,4 -Piles

    5o! 3*!44'm long 3'* : 3*0 : 1,4 -Piles

    5o! 3*!+'m long 3'* : 3*0 : 1,4 -Piles

    5o! 3'!.,+m long 3'* : 3*0 : 1,4 -Piles

    5o! 3'!,1+m long 3'* : 3*0 : 1,4 -Piles

    5o! 3!..'m long 3'* : 3*0 : 1,4 -Piles

    5o! 14!0''m long 3'* : 3*0 : 1,4 -Piles

    5o! 1!,''m long 3'* : 3*0 : 1,4 -Piles

    45o! 11!44'm long 3'* : 3*0 : 1,4 -Piles

    9ll o# t/ese elements /ave %een dra2n on t/e 3+ A 3+3 dra2ing and

    /ave %een presented at t/e design seminar #or assessment and

    industrial advices!

    2. F""d4$ (ro) D"#!3n S")!n$r

    omments included considering DM regulations during t/e design

    p/aseC t/us designing out riss! $/is is s/o2n %) t/e alteration o# pile

    design %et2een conceptual and detailed design stage! ompare

    designC costs and durations 2it/ recentl) completed stations! $/is is

    s/o2n in section !4!1!

    emis 5um%er 44,4 4, (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    48/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    $/e Industrial 9dvisor) ommittee 7I98 didnt e:press an) concerns

    and commented on t/e detail t/at 2as placed in t/is project!

    emis 5um%er 44,4 40 (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    49/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    . 0 M ET ;OD S TAT EMEN TS

    .1 D"#r!t!on o( -or $nd Lo$t!on.

    9 slip2a) "i#e%oat station and uncovered access 2al2a) are

    reBuired to ena%le t/e R5"I to emplo) t/e most up to date li#e%oats in

    t/e Leet! It is proposed to use a steel pile grid design #or t/e

    #oundations!

    .2 P!'!n3 )"t%od #t$t")"nt.

    .2.1 P'$nt,

    1 : Piling rig;ac up %arge 7including operators8

    1 : rane 7including operators8

    1 : (uppl) >arge

    1 Rescue >oat

    .2.2 L$4our,

    1 Ganger

    "a%ourers 7IEC 1...8!

    emis 5um%er 44,4 4. (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    50/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    .2. M"t%odo'o3&,

    .2.5 Pr"'!)!n$r& Pro"dur"#,

    9n investigation o# t/e ground s/ould %e carried out %) competent

    and e:perienced persons in accordance 2it/ >( '.3+! >orings s/ould

    reac/ dept/s adeBuate to e:plore t/e nature o# t/e soil %ot/ around

    and %eneat/ t/e proposed piles in accordance to >( 0++4 and >(

    *34. 7?ualit) Ris8!

    $/e preliminar) investigation s/ould include a care#ul appraisal o#

    near%) structures and su%structuresC including t/e t)pes and la)out o#

    all services near and t/roug/ t/e site! $/e c/oice o# pile ma) %e

    inLuenced %) t/e e=ects 2/ic/ its installation 2ould produce on t/ese

    structures and services piles in accordance to >( 0++4 and >( *34.

    7?ualit) Ris8!

    Preliminar) test piles s/ould %e installed as part o# t/e preliminar)

    investigations in all cases e:cept 2/ere in t/e judgement o# t/e

    Engineer t/e) are unnecessar) %ecause o# e:tensive local e:perience

    or %ecause /ig/ #actors o# sa#et) are to %e emplo)ed piles in

    accordance to >( 0++4 and >( *34. 7?ualit) Ris8!

    emis 5um%er 44,4 '+ (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    51/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    .2.6 In#t$''$t!on Pro"dur"#

    (et out t/e steel pile location correctl) on siteC Ris o# accurac)

    o# dra2ingsC 7?ualit) Ris8!

    Hrder steel piles as per sc/edule! Ris o# accurac) o# dra2ings

    and setting outC 7?ualit) Ris8

    Jnload ; c/ec ; sort ; store steel Piles on land! 7?ualit) ris8

    Pile /eads to %e inspected %e#ore commencement o# 2ors! Ris

    o# Bualit) o# materialC 7?ualit) Ris8!

    Position crane and c/ec permit to li#t steel piles to %arge!

    7(ecurit) Ris8

    >ring (pud leg %arge 2it/ a diesel /ammer;drop /ammer to

    site! 9ll sa#et) guidelines to %e made %) specialist su%

    contractor! Ris o# contaminationC 7Environmental Ris8!

    9ll mem%ers o# piling cre2 to 2ear li#e jacets at all times!

    7(a#et) Ris8

    (et up t/e diesel /ammer;drop /ammer in com%ination 2it/ a

    pile driver 7?ualit) Ris8!

    Erect and install t/e %ottom section o# steel pile reBuired sie

    into t/e ground %) driving 2it/ t/e diesel /ammer;drop /ammer

    7Environmental Ris8!

    "engt/en t/e pile %) 2elding on additional section during

    driving 7?ualit) A environmental Ris8!

    emis 5um%er 44,4 '1 (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    52/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    Erection o# t/e pile section 2ill %e monitored %) means o# spirit

    level #rom time to time 7?ualit) Ris8!

    Resume t/e a%ove process until t/e pile /as %een driven to 6nal

    level according to t/e levels s/o2n in t/e piling plans 7?ualit)

    Ris8!

    (ecurit) measures to %e placed around site to prevent mem%ers

    o# t/e pu%lic in6ltrating t/e site 7securit) Ris8!

    Remove all e:cess steel #rom siteC removing an) potential

    contamination!

    $olerance #or piles to %e no more t/an '+mm and all levels

    s/o2n on dra2ing 3+!

    .2.8 Mon!tor!n3 Proo#$'

    In order to mae certain no /arm#ul e=ects imposed on t/e

    adjacent structures during constructionC t/e #ollo2ing

    preventative measures s/ould tae place and monitor t/e

    #oundations t/roug/out t/e construction period@

    (ettlement c/ecpoints and ot/er monitoring devices are to %e

    installed prior to t/e commencement o# construction 2ors!

    Initial monitoring results s/ould %e su%mitted to t/e local

    >uilding ontrol o=ice prior to t/e commencement o# 2ors!

    emis 5um%er 44,4 ' (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    53/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    $/e c/ecpoints and standpipe pieometers s/all %e monitored

    regularl) during t/e construction period and duplicate copies o#

    t/e monitoring results s/ould %e su%mitted to t/e local >uilding

    ontrol Department on a regular %asis and %e ept availa%le on

    site #or inspection at all times!

    (/ould t/e settlement at t/ose c/ecpoints %e #ound e:cessive

    during t/e course o# 2orsC t/e 2ors s/ould %e suspendedC and

    t/e Engineers and local >uilding ontrol Department s/ould %e

    noti6ed immediatel)! Remedial proposal to sa#eguard t/e

    a=ected structure s/all %e su%mitted to t/e Engineer #or

    approval!

    9ll Monitoring devices s/ould %e maintained in good order

    during t/e 2ors!

    emis 5um%er 44,4 '3 (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    54/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    . R"!n(or")"nt M"t%od #t$t")"nt

    ..1 P'$nt,

    1 : jacup %arge 7including operators8

    1 : rane 7including operators8

    1 : (uppl) >arge

    1 Rescue >oat

    ..2 L$4our G$n3,

    1 #oreman steel 6:er 7cra#tsman8C

    4 (teel 6:ers 7cra#tsman8C

    1 unsilled operativeC

    1 plant operator 'S o# time 7(pons ++,C 1...8!

    .. M"t%odo'o3&,

    General planning on siteC to c/ec #or adeBuate accessC lig/ting

    and #orm2or!

    "ocate adeBuate space #or rein#orcement storage on site! $/is is

    to prevent t/e#t o# steel #rom site!

    >ring steel to site unload into stoc piles using a 't craneC

    la%ourers! /ec #or Buali6ed crane driverC c/ec crane load

    capacit) certi6cate and communication to t/e crane driver must

    %e maintained at all times!

    emis 5um%er 44,4 '4 (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    55/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    9ll steel rein#orcement must %e inspected to t/e >ritis/

    (tandards >(444. #or Bualit) assurance measures - 7?ualit)

    RisC ?ualit) assurance o# rein#orcement8 7>(IC ++'8!

    9ll materials in use must %e certi6edC and pass all necessar)

    standards! or on t/e steel 6:ing can t/ere#ore commenceC

    6rstl) sort and place t/e steel manuall) %) a gang o# steel 6:ers

    and assisted %) t/e 't crane to place large amounts o# steel!

    ommunication must %e ept at all times 2it/ radio devices! In

    t/is process t/e placing and storage o# steel must %e done

    care#ull)! 9s /ig/ 2inds can easil) a=ect t/e craneC it s/ould not

    %e operated in /ig/ 2inds! $/e prevention o# t/is can come in

    t/e #orm o# /ecing 2ind speeds and t/e 2eat/er report

    %e#ore commencing t/e steel 6:ing - 7(a#et) RisC ig/ inds8

    7>(IC 1..,8!

    /ile 6:ing t/e steelC all personnel must 2ear li#ejacets and a

    rescue %oat must %e in operation at all times!

    $/e 6:ing o# t/e pile to t/e steel structure toget/er must %e

    accompanied 2it/ suita%le tools to cut and 6: t/e steelC t/ese

    tools must %e c/eced so t/at t/e) are not #ault) 7>(IC 1..,8!

    9ll concrete coversC must %e maintained %) spacers to prevent

    t/e steel #rom protruding t/roug/ t/e concrete to %e e:posed to

    t/e outside environmentC causing a #ailure in t/e steel 7>(IC

    1..,8!

    emis 5um%er 44,4 '' (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    56/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    /en all steel 6:ing /as %een completed disposal o# t/e

    un2anted steel s/ould %e made! Rec)cling t/e unused steel on

    ot/er sites can minimise t/is e:cess! 9n) small o= cuts s/ould

    %e taen to a scrap )ard #or disposal - 7Environmental RisC

    Disposal o# 2aste steel8!

    emis 5um%er 44,4 '* (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    57/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    .5 -$'$& M"t%od #t$t")"nt

    .5.1 M"t%odo'o3&,

    &or t/e piling please re#er to 3! t/e piling met/od statement 2/ic/

    states t/e correct procedures to #ollo2!

    &or t/e steel erection please re#er to Volume 3 #or t/e (tructural steel

    erection procedures!

    emis 5um%er 44,4 ', (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    58/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    5 .0 M AT ER IA L SP EC IF IC AT ION

    5.1 St""' E'")"nt# Co)r!#!n3 t%" P!'!n3 (ound$t!on#.

    9ll steel is to %e (3'' grade 43 2it/ a unit 2eig/t o# ,0'+g;mK! 9ll

    piles designed to >( [email protected]* code o# practice #or #oundations A >(

    *34. code o# practice #or marine structures! (teel sectionsC plain or

    #a%ricatedC and pipe piles s/ould compl) 2it/ grades 439 and '+> o#

    >( 43*+ or ot/er grades #rom t/at standard to t/e approval o# t/e

    engineer!

    5.1.1 S'!$& !'"#.

    5o! 1'!1m long 3'* : 3*0 : 1,4 -Piles

    5o! 1'!..m long 3'* : 3*0 : 1,4 -Piles

    5o! 1*!0,'m long 3'* : 3*0 : 1,4 -Piles

    5o! 1,!,*+m long 3'* : 3*0 : 1,4 -Piles

    5o! 10!*4'm long 3'* : 3*0 : 1,4 -Piles

    5o! 1.!'3+m long 3'* : 3*0 : 1,4 -Piles

    5.1.2 L!("4o$t !'"#.

    5o! 4!.4m long 3'* : 3*0 : 1,4 -Piles

    5o! 4!,+m long 3'* : 3*0 : 1,4 -Piles

    emis 5um%er 44,4 '0 (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    59/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    5o! 4!4*'m long 3'* : 3*0 : 1,4 -Piles

    5o! 4!+'m long 3'* : 3*0 : 1,4 -Piles

    5o! 3*!.+'m long 3'* : 3*0 : 1,4 -Piles

    5o! 3*!*0+m long 3'* : 3*0 : 1,4 -Piles

    5o! 3*!44'm long 3'* : 3*0 : 1,4 -Piles

    5o! 3*!+'m long 3'* : 3*0 : 1,4 -Piles

    5o! 3'!.,+m long 3'* : 3*0 : 1,4 -Piles

    5o! 3'!,1+m long 3'* : 3*0 : 1,4 -Piles

    5o! 3!..'m long 3'* : 3*0 : 1,4 -Piles

    5.1. -$'$& P!'"#.

    5o! 14!0''m long 3'* : 3*0 : 1,4 -Piles

    5o! 1!,''m long 3'* : 3*0 : 1,4 -Piles

    45o! 11!44'm long 3'* : 3*0 : 1,4 -Piles

    5.2 St""' onn"t!on# to P!'!n3 (ound$t!on#.

    '5o! M4- 1++mm long %olts!

    45o! '++ : 3++ : ' $/ic %ase Plates

    emis 5um%er 44,4 '. (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    60/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    5. St""' R"!n(or")"nt.

    Mem%er

    >armar

    $)p

    eandsie

    5o!

    o#m%rs

    5o!o#

    %ar

    s ineac/

    $otalno!

    "engt

    / o#eac/%ar

    (/a

    pecode

    9Tmm

    >Tmm

    Tmm

    DTmm

    E;RTmm

    Revletter

    $)pe

    & mm

    1 $1+

    40 *+++ ++*+++

    $1

    413 *+++ ++*+++

    3 $1

    *44 34' ++34'

    4 $1+

    * 10,' ++10,'

    ' $ 1

    ,0 10,' ++ 10,'

    * $1

    1. 1++ '1 3,+ *+

    , $1

    1 ''++ ++''++

    0 $1

    * +++ +++++

    . $3

    4 1.' ++1.'

    1+ $1+

    **+ 1,' 11+++

    +

    11 $1

    44 ''++ ++

    ''+

    +

    1 $1

    1+ +'+ +++'+

    13 $1

    1* 3+'+ ++3+'+

    14 $1

    11 1*++ ++1*++

    1' $1

    33 ''+ ++''+

    1* $1

    134 +' +++'

    1, $1

    '* ',' ++','

    10 $ 1

    110 4.,' ++ 4.,'

    1. $1

    4+ ,'+ ++,'+

    + $1

    40 30++ 41 *++ ++1,'

    ++

    1 $1

    4 1,' ++1,'

    emis 5um%er 44,4 *+ (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    61/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    $1+

    14 *'+ '1 ''+ ,+

    3 $3

    0 +++ 11 *'+

    $/e %ar %ending sc/edule a%ove s/o2s t/at t/e rein#orcement %ars

    are ig/ tensile %ars and are indicated %) t/e U$! $/e total num%er o#

    eac/ %ar are also s/o2n and t/e lengt/s! oncrete cover to all %ars is

    to %e 4+mmC to prevent corrosion attac o# t/e re%ar! 9ll

    rein#orcement to compl) 2it/ >( 0***@++'!

    5.5 -$'$& o)on"nt#.

    * 5o! 1+m long ,*:*,:1.,J> steel %eams!

    4 5o! 1!'m long ,*:*,:1.,J> steel %eams!

    3 5o! M4 /old do2n %olts!

    9ll steel is to %e (3'' grade 43 2it/ a unit 2eig/t o# ,0'+g;mK!

    *'mO marine tim%er dec 7treated8!

    4*m o# steel /andrails!

    emis 5um%er 44,4 *1 (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    62/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    6. 0 C ON ST RU CT IO N P RO CE SS ES

    $/is section covers t/e detailed construction process #or t/e pile

    #oundations o# t/e li#e%oat station structures! Prior to an) piling

    2orsC t/e site must 6rst %e set out %) GP( surve)ing tec/nolog) to

    pinpoint t/e e:act positions o# t/e piles!

    9ll structural mem%ers are to %e pre-#a%ricated in t/e #a%rication )ard

    prior to %eing delivered to site! Hnce positions /ave %een located a

    3+m : 11!m : !'m spud leg crane %arge containing a cra2ler crane

    2it/ a 0+#t >oom and a piling /ammer 2it/ a 10 #t sa#et) %oat 7aven

    PortsC ++,8 moves into position #or driving t/e piles!

    Ver) good operating conditions can %e o%tained #or pile driving in

    uns/eltered 2aters %) mounting t/e eBuipment on a %arge provided

    2it/ tu%ular legs 2/ic/ can %e lo2ered on to t/e sea %ed 7spud leg

    %arge8! $/e /ull o# t/e %arge is t/en jaced up t/e legs until it is clear

    o# t/e 2ater to #orm a sta%le plat#orm una=ected %) 2ave action

    7$omlinsonC ++48!

    emis 5um%er 44,4 * (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    63/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    9 transport %arge /auls t/e piles to siteC at t/is time t/e piles are

    transported onto t/e spud leg! $/e piles are t/en to %e driven to t/e

    speci6ed dept/s reBuired and cut at t/e correct level! $/e (pud leg

    t/en raises and moves to t/e ne:t pile position and operates to t/e

    same process as mention previousl)! 5oise 2ill %e ept to a minimum

    2it/ t/e use o# a muerC t/us reducing t/e noise levels o# t/e impact

    %et2een t/e /ammer and t/e pile!

    W# piles /ave to %e lengt/ened t/e normall) recommended practice is

    to mae a joint %) %utt-2elding in suc/ a manner t/at t/e #ull strengt/

    o# t/e original section is developed! Details o# 2elded joints and t/eir

    e:ecution s/ould %e in accordance 2it/ >( '13'C taen in conjunction

    2it/ >( 44.! $/e 2elds s/ould %e su%ject to normal visual inspection!

    $/e joints s/ould %e designed and constructed to maintain t/e true

    alignment and position o# t/e pile sections!

    Pile s/oes are generall) not reBuired #or -piles and ot/er plain rolled

    steel sections! o2everC i# t/e piles are to %e su%jected to

    e:ceptionall) /ard drivingC t/e) ma) %e strengt/ened at t/e %ottom

    end %) cast steel platesC or %) 2elding plates or anglesC to increase

    t/e t/icness o# t/e steel 7>(IC 1.0*8!

    emis 5um%er 44,4 *3 (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    64/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    (teel plates are t/en 2elded onto t/e top o# t/e pile and %olted to t/e

    Loor #rame a%ove! Hnce constructed cat/odic protection is t/en

    applied to t/e steel -piles t/us providing corrosion resistance! (ee

    (ection 1+!1 #or in dept/ detail on corrosion resistance! /ile all

    t/ese operations occurC a rescue %oat is constantl) in attendanceC and

    t/e application o# t/e DM regulations are in use!

    &igure i: @ Image illustrating a jac up >arge 7aven PortsC ++,8!

    emis 5um%er 44,4 *4 (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    65/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    8 .0 TES TING PROC ED URES

    8.1 D&n$)! P!'" T"#t!n3 ?DPT@.

    $/e ultimate %earing capacit) o# a pile ma) %e calculated

    appro:imatel) %) means o# a d)namic pile #ormula using data

    o%tained during driving t/e pile or %) a static #ormula on t/e %asis o#

    soil testsC or it ma) %e determined %) test loading! >) using a d)namic

    #ormula an estimate o# t/e ultimate %earing capacit) ma) %e o%tained

    #rom t/e driving c/aracteristics o# eac/ individual pileC t/e accurac)

    %eing dependent on t/e relia%ilit) o# t/e #ormulaC t/e conditions o# use

    and t/e data used! >) using a static #ormula an estimated value o# t/e

    ultimate %earing capacit) o# a t)pical pile is o%tainedC t/e accurac)

    %eing dependent on t/e relia%ilit) o# t/e #ormula and t/e soil strengt/

    data to 2/ic/ it is applied 7>(IC 1.0*8!

    D)namic load testing is a cost e=ective alternative to conventional

    static load testing #or a 2ide variet) o# pile t)pes and sites! Instead o#

    costl) proo#-loading 2it/ entledge or anc/or pilesC t/e tec/niBue

    uses a /eav) #alling 2eig/t suc/ as a piling /ammer to impart a s/ort

    duration impact to t/e pile /eadC 2/ilst monitoring t/e pile response

    using temporaril) attac/ed transducers! $/e pile response to d)namic

    emis 5um%er 44,4 *' (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    66/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    loading ma) %e used to provide t/e #oundation designer 2it/ an

    interpreted pile capacit)C and can usuall) provide additional

    in#ormation t/at is di=icult to o%tain via static load testing 7asanC

    ++,8!

    $/e #ollo2ing procedure is anot/er traditional met/od o# testing pilesC

    %ut due to t/e nature o# t/e projectC 2oring over 2ater could mae

    t/is test impractica%le! (pecialist contractors are used to test t/e

    piles at a potentiall) /ig/ costC to t/e load test speci6cation!

    8.2 Lo$d!n3 t"#t.

    9 loading test carried to #ailure gives t/e ultimate %earing capacit) o#

    t/e particular pile t/at /as %een tested! $o in#er t/e ultimate %earing

    capacities o# ot/er piles on t/e same site #rom loading tests alone

    reBuires eit/er t/e prior testing o# an adeBuate num%er o# piles and

    t/e use o# a statistical approac/C or a site investigation t/at is

    su=icientl) detailed to s/o2 t/e uni#ormit) or ot/er2ise o# t/e soilC

    t/us ena%ling t/e ultimate %earing capacities o# ot/er piles to %e

    estimated 7>(IC 1.0*8!

    /en driving pilesC valua%le in#ormation a%out site conditions can %e

    o%tained! $/us a judicious com%ination o# load testing 2it/ driving

    and soil records can ensure reasona%l) satis#actor) results on most

    emis 5um%er 44,4 ** (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    67/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    sites! $/e attention o# t/e Engineer s/ould %e dra2n to an) signi6cant

    variation #rom t/e e:pected ground conditions and;or %e/aviour o# t/e

    pile during drivingC so t/at /e ma) tae appropriate action! 7>(IC

    1.0*8!

    8. M"t$''! o$t!n3 to 4"$)# (or -$'$&.

    $esting t/e t/icness o# t/e metallic coating on t/e steel2or s/ould

    %e undertaen %) a suita%l) Buali6ed inspector 2it/ t/e use o# an

    ultrasonic t/icness gauge! 7oatings #or t/e Protection o# (tructural

    (teel2orC +++8

    $/e ultrasonic t/icness gauge must 6rst %e cali%rated %) placing t/e

    pro%e on an un-treated steel section! $/e pro%e is t/en placed on t/e

    area to %e inspected t/e instrument 2ill displa) an accurate reading

    #or t/e coating t/icness and steel t/icness at t/e same time!

    7Jltrasonic t/icnessC n!d!8

    $/is met/od s/ould %e used regularl) to c/ec t/at t/e t/icness o#

    t/e inc coating is at least 1++ Xm!

    &or tests on actual steel sections please re#er to testing procedures

    s/o2n in volume A 3!

    emis 5um%er 44,4 *, (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    68/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    .0 PERFOR MAN CE C RIT ERIA

    .1 Corro#!on Prot"t!on.

    .1.1 C$t%od! Prot"t!on Introdut!on.

    9ll steel -Piles to %e protected against corrosion in accordance 2it/

    >( E5 131,3@++1 cat/odic protection #or steel o=s/ore Loating

    structures!

    at/odic protection is usuall) applied to protect t/e e:ternal sur#aces

    o# steel o=s/ore Loating structures and appurtenances #rom corrosion

    due to sea 2ater or saline mud!

    at/odic protection 2ors %) suppl)ing su=icient direct current to t/e

    immersed sur#ace o# t/e structure in order to c/ange t/e steel to

    electrol)te potential to values 2/ere corrosion is insigni6cant! $/e

    general principles o# cat/odic protection are detailed in E5 14,3!

    .1.2 Pr!n!'"# o( C$t%od! Prot"t!on.

    orrosion is an electro-c/emical process t/at involves t/e passage o#

    electrical currents on a micro or macro scale! $/e c/ange #rom t/e

    metallic to t/e com%ined #orm occurs %) an

    YanodicZ reaction@

    emis 5um%er 44,4 *0 (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    69/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    M [ MF F e-

    7metal8 7solu%le salt8 7electron8

    9 common e:ample is@

    &e [ &eFF F e-

    $/is reaction produces #ree electronsC 2/ic/ pass 2it/in t/e metal to

    anot/er site on t/e metal sur#ace 7t/e cat/ode8C 2/ere it is consumed

    %) t/e cat/odic reaction! In acid solutions t/e cat/odic reaction is@

    F F e- [

    7)drogen ions 7gas8 in solution8

    In neutral solutions t/e cat/odic reaction involves t/e consumption o#

    o:)gen dissolved in t/e solution@

    H F H F 4e- [ 4H-

    7alali8

    orrosion t/us occurs at t/e anode %ut not at t/e cat/ode 7unless t/e

    metal o# t/e cat/ode is attaced %) alali8 7DaviesC ++*8!

    $/e t2o t)pes o# cat/odic s)stems are@

    9 galvanic s)stem!

    Impressed-current s)stem!

    $/e decision /as %een made to use t/e impressed-current s)stem!

    emis 5um%er 44,4 *. (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    70/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    .1. R"u!r")"nt# o( C$t%od! Prot"t!on.

    9n impressed-current s)stem reBuires@

    i8 Inert anodes 7clusters o# 2/ic/C connected toget/er o#ten in a

    %ac6llC are called t/e Yground%edZ8!

    ii8 9 D po2er source!

    iii8 Electricall) 2ell insulatedC minimum resistance and secure

    conductors %et2een anodes and po2er source!

    iv8 (ecure and minimum resistance connections %et2een po2er

    source and piles 7DaviesC ++*8!

    .1.5 P"r(or)$n"

    9 D! po2er source 2it/ automatic potential control 2ill %e used

    2/en t/e environment conditions and t/e structure con6guration and

    service conditions induce large and #reBuent variations o# t/e current

    demand necessar) to maintain polariation 7>(IC ++18!

    9 dielectric s/ield is usuall) used around t/e anodes to prevent local

    over-protection and improve t/e current distri%ution to t/e cat/ode!

    it/out an) in#ormation on t/e average resistivit) o# t/e environmentC

    t/e #ollo2ing range o# values can %e used 7>( ++18!

    cold sea 2ater @ +C3+ \ m to +C3' \ m

    2arm sea 2ater@ +C1' \ m to +C' \ m

    emis 5um%er 44,4 ,+ (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    71/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    saline mud@ +C,+ \ m to 1C,+ \ m!

    $/ere#ore it /as %een decided t/at a anodic resistance o# %et2een

    +!3+ \ to +!3' \ m s/all %e used #or t/e protection o# t/e steel

    PilesC and must /ave a design o# li#e o# '+ )ears minimum!

    emis 5um%er 44,4 ,1 (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    72/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    .0 MAINTENANCE

    .1 M$!nt"n$n" o( P!'!n3 or#.

    Jnder2ater pile Inspection is one o# t/e maintenance services t/at

    need to %e provided! (pecialist contractors 2it/ diving and

    engineering sta= s/ould /ave )ears o# e:perience dealing 2it/ piling

    inspections! 9ll inspectors s/ould %e certi6ed #or under2ater

    Inspection!

    Inspecting piling under2ater and in t/e splas/ one can drasticall)

    reduce major replacements in t/e #uture!

    Jnder2ater Inspections come in t/ree %asic pacages 7Pileap IncC

    ++,8!

    L"+"' I > General visual inspection to con6rm as %uilt condition and

    detect an) severe damage! 7$/is s/ould occur annuall)8!

    L"+"' II > lose-up visual inspection to detect sur#ace de#ects

    normall) o%scured %) marine gro2t/! 9t least 1+S o# t/e

    emis 5um%er 44,4 , (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    73/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    pile 2ill %e cleaned at designated locations t/en

    inspected! 7$/is s/ould occur once ever) ' )ears8!

    L"+"' III > ig/l) detailed inspection to detect an) /idden and

    %eginning damage! 5on-destructive tests suc/ as

    increment %oring and ultrasonic can %e used! 7$/is s/ould

    occur once ever) 1+ )ears8!

    Reports s/ould include@

    ig/l) detailed reports 2/ic/ include all 6ndings!

    Jnder2ater p/otograp/s and videos!

    9uto9D sc/ematics and dra2ings!

    Hverall site la)out and surve)s!

    .2 M$!nt"n$n" o( $t%od! rot"t!on o( P!'!n3 or#.

    $/e aim o# inspection and maintenance is to ensure t/e e=ectiveness

    o# cat/odic protection t/roug/out t/e li#e o# a structure! &or t/is to %e

    ac/ievedC t/e reBuired structure to electrol)te potential s/all %e

    maintainedC 2/ic/ generall) reBuires continuous operation o# t/e

    cat/odic protection s)stem 7>(IC ++18!

    emis 5um%er 44,4 ,3 (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    74/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    (u%seBuent to commissioningC regular inspection is necessar) to

    approved proceduresC appropriate to t/e t)pe o# structure and its

    cat/odic protection s)stem! $/e procedures s/ould %e su%ject to

    revie2 to reLect operating e:perience and ne2 tec/nolog) 7>(IC

    ++18!

    Record s)stems #or %ot/ operation and maintenance are essential!

    Manual s)stems ma) %e accepta%le #or some dataC %ut #or large

    volumes o# dataC computer %ased s)stems are pre#erred! Procedures

    #or maintaining t/e accurac) and sa#et) o# measuring eBuipment and

    instrumentation are also necessar) 7>(IC ++18!

    .2.1 F$tor# !nu"n!n3 !n#"t!on (r"u"n&

    $/e #ollo2ing #actors inLuence inspection #reBuenc) 7>(IC ++18!

    corrosive nature o# t/e electrol)te 7soil or 2ater8

    suscepti%ilit) o# structure to mec/anical damage

    D! or 9! inter#erence currents

    suscepti%ilit) o# cat/odic protection installations to damage %)

    lig/tning or mec/anical means

    riss associated 2it/ t/e contents o# a containing structure

    e:tent and comple:it) o# structure

    constructional #eatures critical to maintaining e=ective cat/odic

    protection

    emis 5um%er 44,4 ,4 (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    75/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    ?ualit) and t)pe o# applied protective coating!

    $/e inspection o# t/e e=ectiveness o# an applied cat/odic protection

    s)stem can %e convenientl) divided into t2o areas@ eBuipment c/ecs

    and structure measurements!

    $/e procedures used and t/e results o%tained s/all %e revie2ed and

    approved %) cat/odic protection personnel 2it/ adeBuate t/eoretical

    and practical no2ledge!

    $a%le ' @ &reBuenc) o# #unctional c/ecs 7>(IC ++18!

    .2.2 C$t%od! Prot"t!on "u!)"nt

    Maintenance on impressed current and drainage stations is

    recommended to %e carried out annuall)! /en #unctional or visual

    c/ecs indicate t/at it is necessar)C maintenance on test stations s/all

    %e carried out! Electrical sa#et) /as to %e c/eced in accordance 2it/

    national regulations 7>(IC ++18!

    emis 5um%er 44,4 ,' (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    76/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    .2. In#tru)"nt$t!on

    Instrumentation used #or measurements s/all %e ept in good 2oring

    order and s/all %e su%jected to periodical cali%ration and sa#et)

    c/ecs 7>(IC ++18!

    .2.5 R"#u't# o( !n#"t!on

    $/e results o# inspection 2or s/all %e recorded and evaluated! $/ese

    records s/ould %e ept #or t/e li#etime o# t/e structureC %ut al2a)s #or

    a su=icient period to provide detailed in#ormation on t/e cat/odic

    protection e=ectiveness and to allo2 comparative c/ecs to %e carried

    out! In additionC it is recommended t/at a cat/odic protection /istor)

    s/ould %e maintained #or re#erence purposes 7>(IC ++18!

    $/ere#ore #rom t/is ta%le it 2ould %e adeBuate to assume t/at

    inspections o# t/e cat/odic protection s/ould %e made annuall)!

    $/ere#ore 1 inspection annuall) 2ould %e appropriate 7>(IC ++18!

    &or maintenance inspection o# structural steel2or please see volume

    3C and #or t/e concrete sla% please see volume !

    emis 5um%er 44,4 ,* (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    77/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    .0 LIF E CYC LE ANAYLS IS

    .1 L!(" C&'" An$'!# o( t%" P!'!n3 Found$t!on#.

    .1.1 Go$' o( t%" #tud&

    $/e o%jective o# t/e "i#e )cle 9nal)sis 7"98 is to consider t/e

    environmental impact o# t/e Piling &oundations over t/e %uildings

    design li#e o# '+ )ears!

    .1.2 So" o( t%" #tud&

    $/is "9 2ill compare t/e #ollo2ing stages t/roug/out t/e %uildings

    li#e 7Elling/am ++*8!

    Procurement o# materials!

    onstruction o# piles on site!

    Maintenance t/roug/out li#e!

    Demolition at t/e end o# its design li#e!

    .1. St") 4ound$r!"#

    $/e limitations o# t/is "9 are de6ned as t/e #ollo2ing@

    $/e main structural elements o# t/e piling s)stemC steel -piles!

    emis 5um%er 44,4 ,, (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    78/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    Impacts o# t/e material e:traction at sourceC e:cluding transport

    to site!

    Jse o# t/e materials and plant on-site during construction o# t/e

    #oundations!

    Jse o# materials #or maintenance o# t/e piling #oundation!

    Jse o# plant and mac/iner) during demolition o# t/e piles!

    aste arising #rom demolitionC including transport to

    destination!

    E:clusions #rom t/e "9 are as #ollo2s@

    (lip2a) #rameC sla%C sla% #rameC internal #rame and cladding!

    Jse o# %uilding t/roug/out its '+ )ear li#e

    uman energ)!

    Production o# electricit)C gas and 2ater reBuired #or

    procurement o# materialsC constructionC maintenance and

    demolition 7Elling/am ++*8!

    aste arising #rom procurementC construction and maintenance

    stages 7Elling/am ++*8!

    $ransport o# plant and mac/iner) to site 7Elling/am ++*8!

    Manu#acture and maintenance o# plant and mac/iner)

    7Elling/am ++*8!

    emis 5um%er 44,4 ,0 (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    79/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    $ransport o# 2or#orce to site 7Elling/am ++*8!

    &a%rication o# components o# %uilding o=-site 7Elling/am ++*8!

    $ransport o# ra2 materials and assem%led components to site

    7Elling/am ++*8!

    .1.5 D$t$ $t"3or!"#

    $/is "9 report categorises t/e #ollo2ing #or comparison over t/e li#e

    c)cle o# t/e %uilding@

    Energ) in giga-joules includes em%odied energ) in materialsC

    plant useC production o# electricit)C gas and 2aterC and

    transportation o# 2aste!

    9ir emissions in tonnes HeBuivalent includes procurement o#

    cementC plant useC production o# electricit)C gas and 2aterC

    transportation o# 2aste and 2aste disposal!

    .2 In+"ntor& An$'!#

    .2.1 Prour")"nt > En"r3&

    Co)on"

    ntM$t"r!$'

    M$##?3@

    E)4od!"dEn"r3&?MJH3@

    Tot$'E)4od!"d

    En"r3& ?GJ@

    piles (teel 104C3'+ 3 '0..

    emis 5um%er 44,4 ,. (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    80/133

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    81/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    TOTAL, 51.1 GJ

    $a%le , @ Energ) consumption during construction!

    .2.5 Con#trut!on > A!r E)!##!on#

    9ir emissions #rom plant use assumed to %e negligi%leC t/ere#ore not

    used in t/is assessment!

    emis 5um%er 44,4 01 (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    82/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    .2.6 M$!nt"n$n"

    &or t/e maintenanceC t/e continuous po2er usage over a '+ )ear

    design period /as %een used!

    It 2as assumed t/at t/e cat/odic protection s)stem 2ould need '+

    2atts o# energ) #or t/e protection o# t/e piles!

    M$%!n"Po"r

    ?-@

    Dur$t!on o( U#"

    ?%our#@

    En"r3&

    Con#u)t!on

    ?GJ@

    at/odic Protection +!+'+ 430+++ ,0!04

    TOTAL, .5 GJ

    $a%le 0 @ Energ) consumption during Maintenance!

    $/e ta%le illustrates t/at ,0!04 gigajoules o# energ) 2ill %e used #or

    t/e protection 7maintenance8 o# t/e piles!

    &or t/e demolitionC I re#erred to >( 0++4 and >( *10, code o#

    practice #or #oundations and demolition respectivel)C %ut no re#erence

    is made a%out demolition o# piles in a marine environment! Researc/

    on t/e internet and %oos /as led to no %acground in#ormationC t/us

    it 2ould %e inappropriate to assume energ) consumption #or a su%ject

    2it/ so muc/ unidenti6a%le in#ormation!

    emis 5um%er 44,4 0 (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    83/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    1 0 .0 R I S A S SE SS M E NT

    $/e nature o# t/is project suggests t/at t/e overall project is /ig/ in

    risC t/is partl) due to 2oring over 2ater! $/ere#ore Riss need to

    assessedC identi6edC and mitigated to /elp prevent injur) or #atalit)

    over t/e course o# t/e contract!

    $/e #ollo2ing t/ree pages lists t/e most common riss relevant to

    pilingC steel 6:ing and erection o# t/e 2al2a)C and preventative

    control measures!

    &or eac/ ris a contingenc) ris /as %een calculated 2it/ t/e 6nancial

    contingencies #or eac/ area s/o2n %elo2@

    Piling@ '.C'++

    (teel 6:ing@ '.C'++

    Erection o# al2a)@ 3'C+++

    $otal@

    This is added to the total cost for all piling activities.

    emis 5um%er 44,4 03 (else) "i#e%oat (tation

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    84/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    10.1 P!'!n3 R!# A##"##)"nt

    R!#Pou'$t!on $t

    R!#T&!$'

    Con#"u"n"#Pro4$4!'!t&HI)$t Contro' M"$#ur"#

    T&!$'Con#"u"n"#$(t"r Contro'

    M"$#ur"#

    Pro4$4!'!t&HI)$t

    T$#, ;"$'t% $nd S$("t& R!#

    Personnel#alling in ater

    (ite &atalit) 3;'

    Implement rigorouscdm training and sa#et)

    procedures AeBuipment!

    "ess Pro%a%ilit) o##atalit) reduced

    1;'

    &inancial ost@ K16/000

    T$#, ;"$'t% $nd S$("t& R!#

    Plant insta%ilit)over 2ater

    (ite &atalit) ;'

    (ta%ilit) o#unconsolidated sea%ed

    material must %ec/eced #reBuentl)!

    "ess Pro%a%ilit) o##atalit) reduced

    1;'

    &inancial ost@ K16/000

    T$#, En+!ron)"nt$' R!#

    5oise Pu%lic Environmental &ine ';3

    Jse a muer on pile

    /ammer to reduce levelo# noise produced!

    "ess Pro%a%ilit) o#

    environmental6ne! ;3

    &inancial ost@ K/60

    T$#, En+!ron)"nt$' R!#

    Disposal o#2aste Pilearisings!

    Pu%lic Environmental &ine ';1Rec)cle (teel 2/ere

    possi%leC or dispose atscrap metal plant!

    "ess Pro%a%ilit) o#environmental

    6ne!1;1

    &inancial ost@ K60

    T$#, u$'!t& R!#

    ?ualit)assurance o##a%rication

    )ard

    (ite ?ualit) #ailure 3;

    Ensure regularc/ecing o# materials

    received and use areputa%le #a%rication

    )ard 2it/ Bualit)approvals

    /ances o# Bualit)#ailure reduced

    ;

    &inancial ost@ K12/600

    T$#, u$'!t& R!#

    "oad $esting (ite ?ualit) #ailure 3;'

    Ensure t/at all pilesare tested %) load

    testing eBuipment andt/at piles pass all

    relevant standards!

    "ess pro%a%ilit) o#Bualit) #ailure!

    1;'

    &inancial ost@ K2/600

    1+!

    emis 5um%er 44,4 04 (else) "i#e%oat (tation$a%le . @ Piling Ris 9ssessment

    1.1

  • 8/10/2019 Bar Bending Schedule Excel Form4(2)

    85/133

    MEng 4 Integrated Design Project Individual Report -Volume 1 Group 3

    10. St""' *!n3 R!# A##"##)"nt

    R!#

    Pou'$t!on $t

    R!#

    T&!$'

    Con#"u"n"# Pro4$4!'!t&HI)$t Contro' M"$#ur"#

    T&!$'Con#"u"n"#

    $(t"r Contro'M"$#ur"#

    Pro4$4!'!t&HI)$

    t

    T$#, ;"$'t% $nd S$("t& R!#

    oring Hverater

    (ite &atalit) 3;'

    Implement rigorouscdm training and sa#et)

    procedures AeBuipment!

    "ess Pro%a%ilit) o##atalit) reduced

    1;'

    &inancial ost@ K16/000

    T$#, ;"$'t% $nd S$("t& R!#

    ig/ inds (ite &atalit) 4;'

    Implement 2ind speedc/ec %e#ore 6:ing o#steel rein#orcement A

    postponeduring /ig/ 2ind

    speeds

    "ess Pro%a%ilit) o##atalit) reduced

    1;'

    &inancial ost@ K16/000

    T$#, En+!ron)"nt$' R!#

    Disposal o#2aste steel

    Pu%lic Environmental &ine ';1 Rec)cle unused steel!"ess Pro%a%ilit) o#

    environmental6ne!

    ;1

    &inancial ost@ K/60

    T$#, En+!ron)"nt$' R!#

    "ac o# (teel(torage (pace

    (ite Environmental &ine 4;1

    Mae sure all unusedsteel is stored in apurpose %uilt area

    2/ere nocontamination can

    occur

    "ess pro%a%ilit) o#environmental

    damage1;1

    &inancial ost@ K60

    T$#, u$'!t& R!#

    9ccurac) o#dra2ings

    (ite ?ualit) &ailure 3;

    Ensure t/e use o# t/elatest dra2ings and

    approved #orconstruction %)

    Buali6ed engineer

    "ess pro%a%ilit) o#Bualit) #ailure!

    ;

    &inancial ost@ K12/600

    T$#, u$'!t& R!#

    ?ualit)assurance o#

    Rein#orcement(ite ?ualit) #ailure 3;

    (tee