Bangladesh: Southwest Transmission Grid Expansion Project
Transcript of Bangladesh: Southwest Transmission Grid Expansion Project
Semi-annual Environmental Monitoring Report
Project No. 51137-001 June 2020
Bangladesh: Southwest Transmission Grid Expansion Project
This semi-annual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.
In preparing any country program or strategy, financing any project, or by making any
designation of or reference to a particular territory or geographic area in this document, the
Asian Development Bank does not intend to make any judgments as to the legal or other status
of any territory or area.
Southwest Transmission Grid Expansion Project
Loan 3683-BAN | Grant No. 0589 | Component BAN & 0590-BAN
Semi-Annual Environmental Monitoring Report
Reporting Period
January to June 2020
Implementing Agency
Power Grid Company of Bangladesh Limited (PGCB)
Ministry of Power, Energy and Mineral Resources
(Power Division)
June 2020
Environmental Monitoring Report
Southwest Transmission Grid Expansion Project
Semi-Annual Environmental Monitoring Report
January to June 2020
June 2020
The environmental impact assessment report is a document of the borrower. The views expressed herein
do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be
preliminary in nature.
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
i
Table of Contents
Executive Summary
I. Introduction 1 A. Background 1 B. The project 1
1. Brief project information 1 2. Impact and Outcome 4 3. Outputs 4
C. ADB and GoB categorization 4 D. Purpose of the Environmental Safeguards 5 E. PGCB safeguards policy 1
II. Status of Ongoing Contract Packages 3 A. Project status 3
1. Package No. 1Bangladesh: Southwest Transmission Grid Expansion Project 3 2. Package No. 2 3 3. Package No. 3 3 4. Package No. 4 4 5. Package No. 5 4
B. Contract requirements (Environment) 4 C. Financing Agreement 4
III. Environmental Status 5 A. Status of Environmental Safeguards Documents 5 B. Environmental safeguards monitoring 5
1. Gopalganj substation 5 2. Transmission line 6
C. Construction period environmental quality monitoring 8 1. Gopalganj substation 8 2. Transmission line subproject: Bogura-Rahanpur 400kV 8 3. Transmission line subproject: Chapainawabganj-Rahanpur 132kV 10
D. Training, awareness and workshop 13 E. Environmental issues of the current project 14 F. Performance of EMP implementation 14 G. Grievance Redress Mechanism 29
IV. Environmental Compliance (agreements) 30 A. Compliance with environmental related project covenants 30
1. National Covenant 30 2. The ADB Safeguards Policy Statement (2009) 33 3. ADB Safeguards Policy Statement (2009) compliance status 34 4. Compliance with loan Covenants 35
V. Performance Indicators 37 A. Overall performances 37 B. Health and Safety performance 41 C. COVID – 19 response performance 43
VI. Concluding Observations 45 VII. Appendix - I 47
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
ii
List of Tables
Table I-1 Brief project information 1 Table III-1 Summary Status of environmental safeguards documents prepared for the project 5 Table III-2 Noise testing results at TL sites 8 Table III-3 Water quality test results at the TL sites 9 Table III-4 Air quality test results at TL sites 9 Table III-5 Soil test results at TL sites (400kV TL Naogaon site) 10 Table III-6 Noise test results at TL sites (132kV) 10 Table III-7 Water quality test results at TL sites (132kV) 11 Table III-8 Air quality test results at TL sites (132kV) 12 Table III-9 Performance status of the EMP implementation processes in the project 15 Table IV-1 Summary of Environmental Legislations Applicable to the Proposed Project 30 Table IV-2 ADB Safeguards Policy environmental compliance Status for the STGEP subprojects (ADB
SPS 2009 Appendix 1 Safeguards Requirement: Environment) 34 Table IV-3 Compliance with Environmental Considerations of Loan Agreements 35 Table V-1 Overall performance in relation to environmental compliance (Gopalganj substation) 37 Table V-2 Overall performance in relation to environmental compliance (TL) 39 Table V-3 H&S Performance indicators of all subprojects 42 Table V-4 COVID-19 Performance indicators of all subprojects 43
List of Figures
Figure I-1 Project area of the southern part 3 Figure I-2 Project area of the northern part 3 Figure IV-1 Overall environmental monitoring checklist reported by Energypac (Sample June 2020) 6 Figure IV-2 Monitoring checklists used by KPTL (Sample June 2020) 7 Figure IV-3 Onsite water quality and air quality test at TL site 12 Figure IV-4 Onsite training and awareness materials at the project sites 13
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
iii
ABBREVIATIONS
ADB Asian Development Bank
APs affected persons
BDT Bangladesh Taka (Currency)
CAP Corrective Action Plan
CSMMP Construction Site Management and Monitoring Plan
DOE Department of Environment
DC Deputy Commissioner
EA Executing Agency
EIA Environmental Impact Assessment
EPC Engineering, Procurement and Construction
ESIA Environmental and Social Impact Assessment (ESIA)
ESMP Environmental and Social Management Plan
ECC Environmental Clearance Certificated
EMP Environmental Management Plan
ECR Environmental Conservation Rule
GoB Government of Bangladesh
GRC Grievance Redress Committee
GRM Grievance Redress Mechanism
HIV Human Immunodeficiency Virus
HSE Health Safety and Environment
IEE Initial Environmental Examination
KPTL Kalpataru Power Transmission Limited
PAP Project Affected Person
PMU Project Management Unit
PIU Project Implemented Unit
PPE Personal Protective Equipment
RAP Resettlement Action Plan
RP Resettlement Plan
ROW Right of Way
SMP Social Management Plan
SPS Safeguard Policy Statement
TL Transmission line
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
iv
Executive Summary
1 This report is the Semi-annual Environmental Monitoring Report (hereinafter refereed as EMR) of
the Asian Development Bank (ADB) financed Southwest Transmission Grid Expansion Project (STGEP) in
Bangladesh, which covers the period of January – June 2020.
2 The project will improve the operational performance of the power sector and contribute to the
Government of Bangladesh’s target to achieve electricity for all by 2021 through (i) constructing (a) a
400/132-kilovolt (kV) substation at Gopalganj; (b) a 230 kV transmission line in the southern zone, from
Barisal to Faridpur; and (c) a 400 kV transmission line in the western zone, from Bogra to Rohanpur; and
(ii) implementing a capacity development program in the electric utility industry to promote socially and
gender inclusive growth. The project will use state-of-the-art conductors with higher power transmission
capacity and lower energy loss in both the 230 kV and 400 kV transmission lines.
3 The Department of Environment is responsible for environmental issues while forest issues are
looked after by Department of Forests. Over the years, the MoEFCC has adopted number of legal
instruments in the form of Acts for the protection and conservation of the environment. Table IV-1
summarizes the Environmental Legislation applicable to the sub-projects. Refer to Table IV-2 for the status
of the respective component sub-projects with regard to environmental compliance status to ADB’s policy
statement (SPS 2009). Schedule 4 of the Agreements for Grant 0582-BAN includes covenants for
environmental issues. The Project’s compliance with the contractual environmental safeguards’ covenants
are shown in the Table IV-3
4 A GRC has been formed for mitigating any unavoidable circumstances during implementing the
compensation process. The committee consists of representatives from PGCB, EPC Contractor,
Consultant (IISPL), and local people. Any dispute regarding determination of compensation against the
losses, usage of land for tower construction and approach road, and other relevant issues during
construction will be solved through the GRC. No grievances have arisen during the reporting period January
2020 to June 2020 at the Transmission Line and Substation project.
5 At Gopalganj substation site Enegrypac is working as contractor and they have their HSE team at
site. The HSE team is lead my Mr. Moniruzzaman. The entire team with their phone number and
designation is listed at site and in their report. The HSE team is monitoring the site continuously and report
back to the contractor who shares with PGCB. To date Monthly environmental inspection report is the
lowest tier of environmental reporting. The latest report is available for June 2020.
6 Kalpataru Power Transmission Limited is the contractor for the transmission line project
(132kV/230kV). The HSE team of the contractor is led by Md. Nur E Alam Siddique, Environmental
Specialist. Environmental monitoring in the field is carried out by the Engineers and the task of actual
monitoring is undertaken by environmental specialists. The environmental specialist is mobilized on an
intermittent basis to undertake field audits and compilation of necessary periodic environmental report for
the PGCB and Financier (Asian Development Bank).
7 The IEE prepared for the project has estimated around 8900 plants to be affected during
construction of Transmission Line (TL). Records of compensation for trees are not well kept. During Midterm
Review Mission with ADB, the Project Director mentioned that the compensation has been paid and the
records will be provided to ADB in due course. The tree plantation plan has not been formulated yet.
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
v
However, the contractor of the Subproject, KPTL mentioned that they have already distributed 2000
saplings to local schools and Madrasas. This record is also not well kept.
8 At both sites, toolbox meetings were found as commonly adopted instead of formal training for EMP
implementation. Both sites are equipped with a trained HSE team lead by specialist. It has been found that,
at Gopalganj substation site, the HSE team works at site with every activity are monitored by a specialist
who is staff of the company. The activities include toolbox meeting, monitoring and reporting, register
maintenance and check upon environmental checklists. On the other hand, at the TL worksite, the
contractor has hired an external environmental specialist to lead the HSE team. The team does regular
HSE meetings and report as monitoring checklists.
9 At TL worksite some awareness materials were also found to be displayed nearby, although the
awareness materials are not found to be adequate, especially in the time of COVID-19 Pandemic. In the
Gopalganj substation site, the site is closed and awareness poster or signboards were found. It is
recommended that, regarding the COVID-19 situation, signboards and posters suggested by ADB and
Health Department of GoB should be showing at the worksite.
10 Until date no significant environmental issue has been identified and reported. However, during
discussion at the Mid Term Review Mission of ADB, it was known that during construction of the substation
low land was sand filled and prepared for construction. No record for local waterlogging, drainage
congestion and grievance has been kept. It was advised that such record needed to be kept all the time
and should be shared with ADB. Since the worksites were in pause during the high outbreak of COVID-19,
not many environmental issues were identified and reported.
11 The concluding observations are as follows:
The Environmental Safeguards compliance performance of the EAs are in good shape except
a few things. The onsite training workshop and regular monitoring of PGCB and contractors
HSE team to sensitize the workers need to be continued for greater benefit.
Due to accessibility issues attributed to restrictions associated with COVID-19, implementation
of environmental safeguards is hindered. In addition, inadequate safety measures, especially
social distancing and frequent disinfection of equipment are still visible at work site.
Environmental quality data from periodic monitoring indicated that in reference to the
Bangladesh standard, the quality of ambient air and groundwater in the project area is within
the standard limit. The noise level is within the safe limit for mixed areas with intermittent spikes
due to proximity of the sites to the roads and human interference.
The labour shed and labour hygiene appear to be ignored by the contractors. This needs
immediate attention and frequent monitoring to improve the condition of labour sheds and
associated hygiene facilities.
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
1
I. Introduction
A. Background
12 This report is the Semi-annual Environmental Monitoring Report (hereinafter refereed as EMR) of
the Asian Development Bank (ADB) financed Southwest Transmission Grid Expansion Project (STGEP) in
Bangladesh, which covers the period of January – June 2020. The report is produced to comply with the
environmental scope stipulated in the sub-projects’ Environmental Management Plans (EMPs)
implemented by Power Grid Company of Bangladesh Limited (PGCB), Ministry of power, Energy and
mineral resources, under the project. The report serves the mandatory monitoring report in the form of six-
monthly environmental safeguards monitoring as per the loan agreement between ADB and Bangladesh
Government and belongs to PGCB.
B. The project
13 The project will improve the operational performance of the power sector and contribute to the
Government of Bangladesh’s target to achieve electricity for all by 2021 through (i) constructing (a) a
400/132-kilovolt (kV) substation at Gopalganj; (b) a 230 kV transmission line in the southern zone, from
Barisal to Faridpur; and (c) a 400 kV transmission line in the western zone, from Bogra to Rohanpur; and
(ii) implementing a capacity development program in the electric utility industry to promote socially and
gender inclusive growth. The project will use state-of-the-art conductors with higher power transmission
capacity and lower energy loss in both the 230 kV and 400 kV transmission lines.
1. Brief project information
14 Power Grid Company of Bangladesh Limited (PGCB) is the implementing agency for Southwest of
Transmission Grid Expansion Project. The details project title, objectives, location, execution funding
provisions and signing of agreements etc is given in Table-1. The site map of southern part and northern
part of the project is given in Figure I-2 and Figure I-1.
Table I-1 Brief project information
Item Description
Project Title Southwest Transmission Grid Expansion Project
Ministry/Division Ministry of power, Energy and mineral resources/Power Division
Executing Agency Power Grid Company of Bangladesh Limited (PGCB)
Location of the project
Division District City corporation/Pouroshova/Upazila
Dhaka Faridpur Faridpur sadar, Nagarkanda, Bhanga
Gopalganj Maksudpur
Madaripur Madaripur Sadar, Rajoir, Kalkini
Barishal Barishal Gournadi, Babuganj,Wazirpur, Barishal Sadar
Rajshahi Chapainawabganj Gomastapur, Nachole, Nawabganj Sadar
Naogaon Naogaon Sadar, Manda, Niamatpur
Rajshahi Tanore
Bogura Kahaloo, Bagura Sadar, Nandigram, Adamdighi
Objectives of the project (Main)
To ensure adequate and reliable power supply for the upcoming Economic Zones in Barisal area as well as in Rajshahi area which is known as the largest agricultural production zone of Bangladesh and meet the rapidly growing demands of residential and commercial consumers in the southwest region of Bangladesh.
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
2
Item Description
Specific Objectives
i. To construct 104 km Bagura(West) - Rahanpur (Chapainababganj) 400 kV Double Circuit transmission Line.
ii. To Construct 11 km LILO of Bagura- Barapukuria 230 kV Transmission Line to Bagura(West) 400/230 kV GIS Substation
iii. To Construct 126 km Barishal(N)-Gopalganj(N)-Faridpur 230 kV Double Circuit Transmission Line
iv. To Construct 26 km Chapainawabganj (old)-Rahanpur (Chapainawabganj) 132 kV Transmission Line
v. To Construct 400/230 kV Outdoor GIS at Bagura (West), 400/132 kV at Rahanpur (Chapainawabganj) & Upgradation of 400/132 kV Gopalganj Substation
vi. To Construct 230/132 kV GIS Substation at Faridpur & Extension of Barishal 230 kV SS vii. Two nos. 132 kV GIS bay extension at Chapainawabganj (Old)
Financing of Foreign component
Being financed by ADB under Loan Agreement No. 3683-BAN, Grant No. 0589-Component BAN & 0590-BAN signed between ADB & GOB
Financing of Local component
Being financed by ADB under Loan Agreement No. 3683-BAN, Grant No. 0589-Component BAN & 0590-BAN signed between ADB & GOB
Financing for Land Acquisition, Land Development, CD VAT & Right of Way
Being Financed from GoB
Financing for AIT & other official Expense
Being Financed from PGCB
Signing of Loan/Grant
Between GoB & ADB Loan No.: 3683-BAN = 350.00 mUSD, Date of signing: 10/09/2018 Grant No.: 0589-BAN = 7.00 mUSD. Date of signing: 10/09/2018 Grant No.: 0590-BAN = 0.50 mUSD. Date of signing: 10/09/2018
Signing of SLA/SGA
Between GoB & PGCB Loan on 07/05/2019 Grant on 06/08/2019
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
3
Figure I-1 Project area of the southern part
Figure I-2 Project area of the northern part
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
4
2. Impact and Outcome
15 The project is aligned with the following impacts: (i) national target of electricity for all achieved by
20211, and (ii) combined transmission and distribution losses reduced from 13% to 9% of generation, and
uninterrupted power supply provided to industries by 20202. The project will have the following outcome:
capacity of electricity supply in Bangladesh increased.
3. Outputs
16 Output 1: New substation at Gopalganj installed. The project will construct and commission the
Gopalganj (North) 400/132 kV substation comprising three 325 megavolt-ampere (MVA) transformers.
17 Output 2: Transmission network in southern Bangladesh expanded. The project will expand the
network by (i) constructing and commissioning a 126-kilometer (km) Barisal (North)– Gopalganj (North)–
Faridpur 230 kV double-circuit line, (ii) constructing and commissioning two 230 kV bay extensions at the
existing Barisal (North) substation and augmenting the existing Faridpur 132/33 kV substation with four 132
kV bays; five 230 kV bays; and 230/132 kV, 2x250 MVA transformers; and (iii) augmenting the Gopalganj
(North) substation with 400/230 kV, 2x750 MVA transformers.
18 Output 3: Transmission network in western Bangladesh expanded. The project will expand the
network by constructing and commissioning (i) a new 104 km Bogra (West)–Rohanpur 400 kV double-
circuit line; (ii) a new 400/230 kV, 2x750 MVA Bogra (West) substation; (iii) a new 400/132 kV, 2x325 MVA
Rohanpur substation; (iv) a new 26 km Chapainawabganj–Rohanpur 132 kV double-circuit transmission
line; (v) two 132 kV bay extensions at the existing Chapainawabganj substation; and (vi) an 11 km line-in,
line-out connection from the Barapukuria-Bogra (South) 230 kV transmission line to the Bogra (West)
substation, and a 1 km line-in, line-out connection from the Chowdala–Niamatpur 132 kV transmission line
to the Rohanpur substation.
19 Output 4: Socially inclusive capacity in the electric utility industry enhanced. The project will
enhance capacity, particularly emphasizing inclusive development and gender equality, through a university
program relevant to the energy sector, supporting (i) 50 university students, of which at least 40% are
women; and (ii) 30 staff from Power Grid Company of Bangladesh Limited (PGCB), of which at least 30%
are women.
C. ADB and GoB categorization
20 ADB categorization: In compliance with ADB’s Safeguard Policy Statement (2009), the project’s
safeguard category for environment is ‘B’. The project will not pass through any ecologically sensitive areas
and will not bring significant adverse environmental impacts. An initial environmental examination (IEE) has
been prepared in accordance with the Safeguard Policy Statement. The IEE and environmental
management plan propose mitigation measures to minimize effluent, noise, and waste from the project that
may impact the environment, health, and safety. PGCB will disclose any updates to the IEE resulting from
some changes in project scope. The project will utilize aluminum conductor composite core cable in the
transmission lines under outputs 2 and 3 as an advanced technology to reduce greenhouse gas emissions
1 Government of Bangladesh, Ministry of Planning, Planning Commission. 2012. Perspective Plan of Bangladesh, 2010– 2021:
Making Vision 2021 a Reality. Dhaka. 2 Government of Bangladesh; Ministry of Power, Energy and Mineral Resources. 2016. Power System Master Plan 2016. Dhaka.
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
5
by 174,595 tons of carbon dioxide-equivalent per year. The project has been assessed for its risk and
vulnerability to climate change impacts, and design measures have been integrated to minimize these risks.
The draft IEE report was prepared from the technical due diligence and fact-finding mission. PGCB has
implemented several ADB projects and has adequate institutional capacity and experience to manage the
environmental risks through its project management unit. PGCB is committed to implementing the
environmental management plan and submitting environmental monitoring reports on a regular basis to
ADB.
21 GoB categorization: The Environment Conservation Act of 1995 establishes the requirement for an
environmental assessment in Bangladesh. Any proposed "industrial unit or project" must obtain prior
approval from the Department of Environment (DoE). The act has classified projects to be assessed by the
DoE in four categories (Green, Amber A, Amber B, and Red). Power development projects are allocated to
the Red category, which triggers an automatic requirement for an IEE followed by a full EIA.
D. Purpose of the Environmental Safeguards
22 According to the loan agreement, PGCB has to submit semi-annual safeguards monitoring report
to ADB and disclose relevant information from such reports to the project affected persons promptly upon
submission. The safeguards issues are guided by the ADB Safeguards Policy Statement (SPS) 2009. The
objectives of these ADB environmental safeguards are: (i) to ensure the environmental soundness and
sustainability of projects and (ii) to support the integration of environmental considerations into the project
decision-making process. ADB environmental safeguards are triggered if a project is likely to have potential
environmental risks and impacts.
23 The purpose of the Environmental Safeguards for a project are defined as:
Assist in determining adequacy of cost for EMP implementation;
Assist in addressing any concern related to IEEs and EMPs;
Assist in summarizing IEEs, translating to language understood by local people and disclosure
in public locations;
Oversee implementation of EMP including environmental monitoring of contractors;
Assist in implementing corrective actions when necessary to ensure no environmental impacts;
Review quarterly reports by contractors, assist PMU to submit environmental monitoring
reports on regular basis;
Assist in establishing the grievance mechanism for safeguards and addressing any grievances
brought about through the GRM in a timely manner as per IEE;
Submit semi-annual environmental safeguards monitoring report to ADB via PMU;
Be responsible for training the PMU/contactor safeguards officers on environmental awareness
and management in accordance with both ADB and government requirements and implement
the capacity building program for PMU and all staff involved in project implementation on (a)
ADB SPS, (b) Government of Bangladesh national and local environmental laws and
regulations, (c) core labor standards, (d) occupational health and safety monitoring given in the
environmental safeguards monitoring report and (e) EMP implementation especially spoil
management, working in congested areas, public relations and ongoing consultations,
grievance redress, etc.; and
Provide induction course for the training of contractors preparing them on EMP implementation.
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
1
E. PGCB safeguards policy
24 The PGCB has its own policy and requirements for compliance relating to environment, health and
safety issues for its operations. The company is committed to managing its operations in a safe, efficient
and environmentally responsible manner. The PGCB's Health Environment and Safety (HES) manuals,
guidelines, procedures, and plans are important tools indicating their commitment. HES manuals include:
• Environmental Impact Assessment Module;
• Guideline on Integrated Impact Assessment;
• Health Impact Assessment Module; and
• Social Impact Assessment Module.
25 In addition, the requirement for impact assessment is affirmed in the PGCB's Statement of General
Business Principles. The PGCB is committed to:
• Pursuing the goal of no harm to people;
• Protecting the environment; and,
• Managing HES as any other critical business activity.
26 The mandatory company Operations Management System, Environmental Care Element/
Standards, issued in March 1997, refers to Environmental Assessment indicating that "EIA (including a
consideration of social impacts) shall be conducted prior to all new activities and facility developments, or
significant modifications of existing ones.”
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
2
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
3
II. Status of Ongoing Contract Packages
A. Project status
28 The following paragraphs detail the package progress status:
1. Package No. 1
Project Title: Design, Supply, Installation, Testing & Commissioning of Barisal (N)-Gopalganj (N)-Faridpur
230 kV Double Circuit Transmission Line on Turnkey basis.
Contract was signed on 22/05/2019; Contract Effective date: 22.10.2019
Financial Progress from the contract effective date:
a. Foreign & Local portion against 10% Mobilization advance Paid to consultant.
b. Progress payment USD: 11,050721.66 BDT: 341099585.95
Physical Progress:
a. Route/Check Survey and route map are completed for Barishal Gopalganj Section and Gopalganj-
Faridpur portion
b. Piling of the line has been started on 05.09.2019.
c. Total Piling completed 213 towers out of 345
d. Total Pile cap completed 80 out of 345
e. Total Tower erection completed 47 out of 345
2. Package No. 2
Project title: Design, Supply, Installation, Testing & Commissioning of 230 kV Indoor GIS Substation with
132 kV AIS Substation at Faridpur and GIS Bay Extension in the existing 230/132 kV Barisal (North) AIS
Substation on turnkey basis
Contract was signed on 08/05/2019; Contract Effective date on 12.11.2019
Financial Progress from the contract effective date: Foreign & Local portion against 10% mobilization
advance Paid to consultant.
Physical progress:
a. Sub-station Layout has been finalized.
b. Piling of GIS Building at faridpur has been started.
c. Ansar barak building work is going on.
d. Design Drawing approval is going on.
3. Package No. 3
Project Title: Design, Supply, Installation, Testing & Commissioning of Bogura-Rahanpur 400kV Double
Circuit and Associated 230kV & 132kV Transmission Lines on Turnkey Basis.
Contract was signed on 20/11/2019; Contract Effective date: 10.02.2020
Financial Progress from the contract effective date:
a) Foreign & Local portion against 10% mobilization advance Paid to consultant.
b) Progress payment USD
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
4
Physical progress:
132 kV Transmission Line
a) Route/Check Survey and route map have been completed 23 km out of 26 km
b) Piling of the line has been started on 10.01.2020.
c) Total Piling completed 55 towers out of 86
400 kV Transmission line
a) Route/Check Survey and route map has been completed 98 km out of 104 km.
b) Piling of the line has been started on 29.02.2019.
c) Total Piling completed 37 towers out of 278
4. Package No. 4
Project title: Design, Supply, Installation, Testing & Commissioning of 400kv Outdoor GIS Substation at
Bogura (West) & Rahanpur up gradation /Extension of Gopalganj and Chapainababganj (Old) Substation
on Turnkey Basis
Status: Financial evaluation has been completed & Report sent to ADB for their concurrence.
5. Package No. 5
Consultancy Services for the EMTP study, bid documentation preparation & clarification, design checking,
supervision for 400 kV substations of the project
Status: NOA Issued to consultant (WAPCOS) on 27.09.2020 & accepted it unconditionally on the same
day. Draft contract document sent to ministry for vetting on 05.08.2020.
B. Contract requirements (Environment)
29 The following documents, relating to the identified environmental safeguards, form part of the
Contract Package and are part of the monitoring requirements in ascertaining the degree of compliance:
a) Initial Environmental Examination (IEE)
b) Environmental Management Plan (EMP); and In addition to the foregoing, the Contractor is to
provide the Project Director with a written notice of any unanticipated environmental risks or
impacts that arise during construction, implementation or operation of the Plant or Works, which
were not considered in the IEE’s and the EMP’s.
30 The general anticipated impacts for all subprojects and their mitigation measures are summarized
in Error! Reference source not found. for reference of the later chapters which discuss the environmental
safeguard compliance in relation to the requirements set by subproject specific EMPs.
C. Financing Agreement
31 Financial cost provision for the Contractor to complete all the required Environmental mitigation
and monitoring requirements is given in the EMP cost stipulated with the subproject specific EMPs, along
with the stipulated frequency and extent of sample monitoring, in accordance with the respective
Environmental Management and Monitoring Plan, of the particular contract package.
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
5
III. Environmental Status
A. Status of Environmental Safeguards Documents
32 The following safeguards documents have been prepared by PGCB and contractors for the project
(Table III-1):
Table III-1 Summary Status of environmental safeguards documents prepared for the project
Type of safeguards document Agency Package Latest version
Coverage
Semi Annual Environmental Monitoring Report PGCB All August 2019
April – June 2019
Semestral Environmental Monitoring report PGCB All June 2019 April – June 2019
COVID-19 Exposure Prevention, Preparedness & Response Plan Contractor (Energypac Engineering Ltd)
Gopalganj Substation
August 2020
Rest of the contract
Site specific Environmental Management Plan (SEMP) Contractor (Energypac Engineering Ltd)
Gopalganj Substation
August 2020
Rest of the contract
Monthly environmental inspection report Contractor (Energypac Engineering Ltd)
Gopalganj Substation
June 2020 June 2020
Complain and sick register report Contractor (Energypac Engineering Ltd)
Gopalganj Substation
August 2020
From beginning of construction
OHS Plan Contractor (Energypac Engineering Ltd)
Gopalganj Substation
August 2020
Rest of the contract
Monthly HSE meeting reports Contractor (Energypac Engineering Ltd)
Gopalganj Substation
June 2020 June 2020
Overall monitoring checklist Contractor (Energypac Engineering Ltd)
Gopalganj Substation
June 2020 June 2020
Environment test report (132kV): included environmental monitoring, checklist, HSE monitoring
Contractor (Kalpataru Power Transmission Limited (KPTL)
Transmission line
June 2020 January – June 2020
Environment test report (230kV): included environmental monitoring, checklist, HSE monitoring
Contractor (Kalpataru Power Transmission Limited (KPTL)
Transmission line
June 2020 January – June 2020
B. Environmental safeguards monitoring
1. Gopalganj substation
33 HSE Team: At Gopalganj substation site Enegrypac is working as contractor and they have their
HSE team at site. The HSE team is lead my Mr. Moniruzzaman. The entire team with their phone number
and designation is listed at site and in their report. The HSE team is monitoring the site continuously and
report back to the contractor who shares with PGCB. To date Monthly environmental inspection report is
the lowest tier of environmental reporting. The latest report is available for June 2020. Besides that, the
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
6
team generates overall environmental monitoring checklist. The latest is available for June 2020 (Figure
IV-1).
34 Environmental testing: To date environmental testing was not done. At present only civil
construction is in progress without use of chemicals and without burning any fossil fuel. Therefore, gasses
detrimental to the environment are not generated and emitted to the environment. Contamination of surface
water and ground water due to construction work is also not expected. Only source of noise during
construction was piling work. In this project, piles of maximum 500 mm diameter and 12 m length have
been constructed. As the drilling was done by using earth auger without using any hammer, generated
noise was minimum, which did not affect the environment outside the substation boundary. Therefore, no
environmental monitoring has been carried out by the Contractor and therefore no monitoring data /
documents are available for review and comments.
2. Transmission line
35 HSE team: Kalpataru Power Transmission Limited is the contractor for the transmission line project
(132kV/230kV). The HSE team of the contractor is led by Md. Nur E Alam Siddique, Environmental
Specialist. The Executing Agency (EA) of PGCB, Kalpataru Power Transmission Limited (KPTL) has
established a Project Implementation Unit (PIU) including its regional specialists to manage day-to-day
coordination, implementation and environmental monitoring and administration activities of the 400kV and
Figure III-1 Overall environmental monitoring checklist reported by Energypac (Sample June 2020)
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
7
230 kV transmission line project. The PIU of Kalpataru Power Transmission Limited (KPTL) is assisted by
PGCB. The Kalpataru Power Transmission Limited (KPTL) also has an Environmental Specialist dedicated
to the project, as mentioned earlier. Environmental monitoring in the field is carried out by the Engineers
and the task of actual monitoring is undertaken by environmental specialists. The environmental specialist
is mobilized on an intermittent basis to undertake field audits and compilation of necessary periodic
environmental report for the PGCB and Financier (Asian Development Bank). Likewise, the national
environmental and social safeguard specialist is engaged on a regular basis to support acquisition and
ensure validation of monitoring data. The HSE team of KPTL also do internal monitoring using checklist
and reporting and reflected in the quarterly progress report and environmental report that are submitted to
PGCB (Figure IV-2).
36 Environmental testing: Recent Environmental testing was done in July 2020. The contractor hired
an external monitoring company for water, soil, noise and air quality testing. The results are reported in the
later section of this report. All the parameters tested were found to be within the DoE limits set in ECR 1997
and its amendments.
Figure III-2 Monitoring checklists used by KPTL (Sample June 2020)
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
8
C. Construction period environmental quality monitoring
37 In order to ensure proper implementation of the environmental safeguard requirements during the
construction period, Contractors have appointed third party organizations for testing of required
environmental parameters (air quality, noise quality, surface water quality and groundwater quality). All
instruments used by the organization are maintained following International Standards and calibrated
regularly in accordance with the manufacturer’s instructions.
1. Gopalganj substation
38 No environmental testing was done at Gopalganj substation as discussed in the earlier sections.
2. Transmission line subproject: Bogura-Rahanpur 400kV
39 Noise quality: Noise samples were collected at pilling workplace and apart from 300-meter
distance (North & South) at Bil-palsha, Raninagor, Naogoan. According to the Environment Conservation
Rules (ECR, “SRO no 212-law/2006”), noise levels were within limits. The results are reported in the
Environmental report prepared by the contractor for PGCB for the period of January to July 2020.
40 Surface water: The surface water sample has been collected from adjacent area near the Bil-
palsha, Raninagor, Naogoan, Bogura-Rahanpur 400kV Double Circuit and associated 230kV Transmission
Lines. The parameters were determined by appropriate approved analytical method. However, the
concentration of above parameters was within the acceptable limit of DoE Standards for inland surface
water [Schedule-10 (Rule 13) & Standards for inland surface water Schedule-3 (Rule12)]. The results are
reported in the Environmental report prepared by the contractor for PGCB for the period of January to June
2020.
Table III-2 Noise testing results at TL sites
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
9
41 Air quality: As part of environmental management & monitoring guidelines, periodical
environmental air quality monitoring has been carried out by the high-volume sampler with gaseous
attachment which has been using for collecting air for a certain period of time from Bil-palsha, Raninagor,
Naogoan of Bogura-Rahanpur 400kV Double Circuit and associated 230kV Transmission Lines. The origin
of ambient air quality standard for Bangladesh has set at Environmental Conservation Rules, 1997, later
on, the standard limit ambient air quality has been revised since 2005 as National Ambient Air Quality
Standard for Bangladesh. The values of ambient air quality parameters are showed in the table below. It
has been observed that the concentrations of ambient air quality parameters are within the allowable
ambient limit as per DoE, Bangladesh Standard for air quality.
Table III-3 Water quality test results at the TL sites
Table III-4 Air quality test results at TL sites
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
10
42 Soil quality: The soil samples have been collected from Bil-palsha, Raninagor, Naogoan of
Rahanpur - Bogura- Barapukura 400 kV duble circuit TL and Polsha of Chapainawabganj Sadar from 132kV
double circuit TL. The test result of the parameters (Organic matter, Total CaCO3, soil pH and nitrogen
content) suggest that the parameters tested are within the recommended levels for crop land.
43 Comparative results: Since the results presented in the above section are the first batch of
environmental testing results, comparison with previous results cannot be made. Therefore, these results
should be used as the baseline results and should be compared with future results to investigate any
change in the environmental quality from the project.
3. Transmission line subproject: Chapainawabganj-Rahanpur 132kV
44 Noise quality: Noise samples are collected at pilling workplace and from 300-meter distance
(North & South) at Polsa, Chapainababgonj Sador of the 132kV Double Circuit TL from Chapainawabganj
(Old) substation to Rahanpur (Chapainawabganj) substation. Except at worksite, all the sites were
measured as noise being allowable limit set by ECR 1997 and its amendments.
Table III-6 Noise test results at TL sites (132kV)
Table III-5 Soil test results at TL sites (400kV TL Naogaon site)
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
11
45 Surface water quality: The surface water sample has been collected from adjacent area near the
Polsa, Chapainababgonj Sador 132kV Double Circuit TL from Chapainawabganj (Old) substation to
Rahanpur (Chapainawabganj) substation. The parameters were determined by appropriate approved
analytical method. However, the concentration of above parameters was within the acceptable limit of
Department of Environment Standards for inland surface water [Schedule-10 (Rule 13) & Standards for
inland surface water Schedule-3 (Rule 12)]
46 Air quality: As part of environmental management & monitoring guidelines, periodical
environmental air quality monitoring has been carried out by the high-volume sampler with gaseous
attachment which has been using for collecting air for a certain period of time from Polsa, Chapainababgonj
Sador (N 24039’ 2 E 88018’ 15) of 132kV Double Circuit TL from Chapainawabganj (Old) substation to
Rahanpur (Chapainawabganj) substation. Results suggest all the parameters are within the allowable limit
set by DoE.
Table III-7 Water quality test results at TL sites (132kV)
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
12
47 Tree Plantation Programme: The IEE prepared for the project has estimated around 8900 plants
to be affected during construction of Transmission Line (TL). Records of compensation for trees are not
well kept. During Midterm Review Mission with ADB, the Project Director mentioned that the compensation
has been paid and the records will be provided to ADD in due course. The tree plantation plan has not been
formulated yet. However, the contractor of the Subproject, KPTL mentioned that they have already
distributed 2000 saplings to local schools and Madrasas. This record is also not well kept. KPTL
representative mentioned that they will come up with the full tree plantation plan/distribution plan and will
keep hardcopy and visual records of plant distribution which will be shared with PGCB and ADB.
Table III-8 Air quality test results at TL sites (132kV)
Figure III-3 Onsite water quality and air quality test at TL site
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
13
D. Training, awareness and workshop
48 Training: At both sites, toolbox meetings were found as commonly adopted instead of formal
training for EMP implementation. Both sites are equipped with a trained HSE team lead by specialist. It has
been found that, at Gopalganj substation site, the HSE team works at site with every activity are monitored
by a specialist who is staff of the company. The activities include toolbox meeting, monitoring and reporting,
register maintenance and check upon environmental checklists. On the other hand, at the TL worksite, the
contractor has hired an external environmental specialist to lead the HSE team. The team does regular
HSE meetings and report as monitoring checklists.
49 Awareness: At TL worksite some awareness materials were also found to be displayed nearby,
although the awareness materials are not found to be adequate, especially in the time of COVI-19
Pandemic. In the Gopalganj substation site, the site is closed and awareness poster or signboards were
found. It is recommended that, regarding the COVID-19 situation, signboards and posters suggested by
ADB and Health Department of GoB should be showing at the worksite.
Figure III-4 Onsite training and awareness materials at the project sites
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
14
E. Environmental issues of the current project
50 Until date no significant environmental issue has been identified and reported. However, during
discussion at the Mid Term Review Mission of ADB, it was known that during construction of the substation
low land was sand filled and prepared for construction. Not record for local waterlogging, drainage
congestion and grievance has been kept. It was advised that such record needed to be kept all the time
and should be shared with ADB. Since the worksites were in pause during the high outbreak of COVID-19,
not many environmental issues were identified and reported.
F. Performance of EMP implementation
51 Performance of the EMP implementation for the project has been presented in the following table:
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
15
Table III-9 Performance status of the EMP implementation processes in the project
Environmental issue
Mitigation measures suggested in EMP Observation during monitoring period Recommendation /comments
Gopalganj substation: Construction phase Topsoil Prior to start of filling of the site, collect and store top soils
(minimum 0.5 m thick) for using on the surface of the site boundary and access road side slopes for protection from side slope erosion. The topsoil, excavated from the proposed construction sites, should be re-spread in areas to be landscaped.
Land filling of Access Road and Substation Area has been completed in October 2019. More than 3 m land filling have been done in entire area by dredged sand directly transported from the reverbed to the site through pipeline. Therefore, the filled-up area is well compacted. Proper slope has been provided at the top of compacted filled up soil. Proper slopes have provided at the sides of the access road and covered with concrete slabs to protect from erosion.
Photo evidences needs to be kept
Vegetation clearing Prior to the start of clearing of vegetation, provide adequate compensation to the owners in good time.
Compensation has been given to the affected people. However, proper records are not kept.
PGCB has been advised to keep proper records and share with ADB
Fauna Prepare construction management plan (CMP, by the contractor) and follow it properly. Follow GoB rules and regulations on noise. Project workers should not disturb or kill any wildlife.
The Contractor for the Gopalganj sub-station project has prepared an Environmental and Social Management Plan for implementation during construction of the sub-station. The document is titled as ESMP. The ESMP document was submitted by Contractor on 8th May 2020 and awaiting PGCB approval.
The ESMP, however, needs to be aligned with the EMP contained in the IEE report as well as with the other conditions stipulated in the Contract documents with respect to management of environmental, health, safety and social aspects on the project. However, contractor confirmed that the revised ESMP has been sent to PGCB on 25 September 2020.
Construction waste Use of durable, long-lasting materials that will not need to be replaced as often, thereby reducing the amount of construction waste generated over time. Provision of facilities for proper handling and storage of construction materials to reduce the amount of waste caused by damage or exposure to the elements. Purchase of perishable construction materials such as paints incrementally to ensure reduced spoilage of unused materials. Use of building materials that have minimal packaging to avoid the generation of excessive packaging waste. Use of construction materials containing recycled content when possible and in accordance with accepted standards. Adequate collection, separation, and storage of waste on site and safe transportation to the disposal sites and disposal methods at designated area shall be provided.
As part of waste management system at site, garbage collection bins are located in numerous locations. Garbage collected in these bins are disposed of on daily basis.
In the situation of COVID-19 pandemic, waste need to regularly disinfected. Set waste bins dedicated to COVID-19 on site. Monitor for COVID-19 related waste being dumped and disposed in healthy manner and keep record in a register. Used mask, gloves are to be disposed in the COVID-19 designated waste bins. Assign the HSE officer on field to
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
16
Environmental issue
Mitigation measures suggested in EMP Observation during monitoring period Recommendation /comments
There is designated space with sign board at site to be used as scrapyard. Scrap material accumulated in this scrapyard are disposed of at regular intervals.
monitor such activities and record in a separate register.
Drainage construction and flooding
Provide culverts in the access road of the substation. Ensure adequate monitoring, especially if construction works are carried out during the monsoon period. Provision for pumping of congested water, if needed. Consideration of the HFL during design of substations, to avoid inundation.
Currently no drainage congestion has been found at site.
Noise Use of noise reducers in heavy construction equipment. It is recommended that no construction should be allowed during night time (9 PM to 6 AM). Avoid prolonged exposure to noise (produced by equipment) by workers. Use of noise reducers in heavy construction equipment. It is recommended that no construction should be allowed during night time (9 PM to 6 AM). Avoid prolonged exposure to noise (produced by equipment) by workers.
Only civil works are ongoing in the site. Noise level is slightly higher than accepted limit (~71dB) for industrial areas. However, this is common in worksite.
Site work should be limited with the stipulated time (9AM – 6PM). However, the construction site is away from residential area and noise pollution therefore is negligible.
Air quality and dust All vehicles (e.g., trucks, equipment, and other vehicles that support construction works) shall be well maintained and not emit dark or smoky emissions in excess of the limits described in the EQS. Specific training will be focused on minimizing dust and
Dust suppression measures are taken and the site was observed as dust free (photos later). Dust suppression activities are taken twice a day and more if required.
The entire site is filled with sand. Therefore, the dust suppression activities need to be frequent so that
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
17
Environmental issue
Mitigation measures suggested in EMP Observation during monitoring period Recommendation /comments
exhaust gas emissions from heavy construction vehicles. Drivers of vehicles used during construction will be under strict instructions to minimize unnecessary trips and minimize idling of engines. Dust suppression facilities (water sprayer) shall be available where earth and cement works are required. Spray water on dry and loose surfaces of the construction sites regularly. Maintain adequate moisture content of soil during transportation, compaction and handling. Construction materials (sand, gravel, and rocks) and spoil materials will be transported in trucks covered with tarpaulins. Sprinkle and cover stockpiles of loose construction materials (e.g., fine aggregates, sand). Avoid use of equipment such as stone crushers at the sites, which produce significant amount of particulate matter. Dust masks should be provided to all personnel in areas prone to dust emissions throughout the period of construction.
At the moment, civil construction is going on without using chemicals. Stockpiles were found covered and within designated places.
communities and workers are not affected.
Soil Laboratory analysis of the river bed materials to be confirmed prior to starting collection from the river. Prevention of spillage and leakage of hazardous liquids at construction sites and camp. Ensure no use of transformers containing PCB to avoid soil and air pollution.
Soil was collected from a local supplier certified by the local DC office. Soil was taken form nearby river. However, laboratory analysis of the riverbed material for PCBs has not been performed.
Soil/sand used for construction needs to be immediately tested for PCBs and report to PGCB.
Traffic congestion Follow Bangladesh Road Traffic Authority (BRTA) traffic rules and regulations. Schedule deliveries of materials/ equipment during off-peak hours. Engage flagmen especially at the entry of the substation sites and construction camps for traffic control. Engage experienced drivers to drive project vehicles. Arrange for signal lights at night. Prepare and follow proper traffic management. Avoid stockpiling of materials, especially at the road sides, that could disturb traffic movement.
Traffic congestion at the worksite is very low due its distance from the road ways. Traffic congestion, therefore was not observed at site.
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
18
Environmental issue
Mitigation measures suggested in EMP Observation during monitoring period Recommendation /comments
Community Health and Safety (H&S)
Safety barriers and warning signs surrounding the construction site. Generators should be placed in closed rooms. Formulate and implement an emergency risk management plan (by the contractor).
The Contractor have posted one HSE Engineer at site, who is responsible for implementation and monitoring of environmental, health, safety and social aspects of the project. Records relating to monitoring of HSE aspects at site are being maintained at site by the Contractor. A register for Grievance has been kept at site.
Occupational Health and Safety
An experienced Health & Safety (H&S) Manager must be engaged by the contractor prior to start of construction. Only permit trained and certified workers to work with any electrical equipment. Safety induction by the H&S Manager should be provided for the workers. Prior to starting work, a tool box meeting should be arranged by the H&S Manager for the workers. First Aid Box and personal protective equipment, PPE (such as safety helmets, safety shoes, eye protection glasses, ear plugs/muffs, waist belts, masks, hand gloves, body protective aprons and insulating boots) must be provided to the workers and ensure their use by the workers. Safety signs, health signs, prohibition signs, warning signs, mandatory signs, emergency escape signs, first-aid signs, information signs, signboards, supplementary signboards, safety collar, symbol, pictogram, illuminated signs, acoustic signals, verbal communication and hand signals must be fitted at the designated.
The Contractor have posted one HSE Engineer at site, who is responsible for implementation and monitoring of environmental, health, safety and social aspects of the project.
Records relating to monitoring of HSE aspects at site are being maintained at site by the Contractor. A register for Grievance has been kept at site. There is designated space with sign board at site to be used as scrapyard. Scrap material accumulated in this scrapyard are disposed of at regular intervals.
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
19
Environmental issue
Mitigation measures suggested in EMP Observation during monitoring period Recommendation /comments
Safety fencing was observed.
Regular toolbox meeting on site safety and COVID-19 situation are conducted
Workers were observed to be using PPEs.
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
20
Environmental issue
Mitigation measures suggested in EMP Observation during monitoring period Recommendation /comments
Proper housekeeping was observed in the store room forming a part of the site office complex. In the store room, materials of various kinds were observed to be stored in satisfactory way.
First Aid boxes are available and kept in the store room.
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
21
Environmental issue
Mitigation measures suggested in EMP Observation during monitoring period Recommendation /comments
The Vehicle is available at site for handling any emergency and for reaching the nearby hospital in case of an emergency. Emergency Contact numbers are displayed in the office area. Safety signage have been placed at numerous locations at site.
Fire extinguishers are kept inside store & generator room. As part of grievance redress mechanism, a complaint register is maintained at site. To maintain records of accidents and injuries a sick register maintained at site. Safe drinking water supply was found for workers.
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
22
Environmental issue
Mitigation measures suggested in EMP Observation during monitoring period Recommendation /comments
Extra precautions for COVID-19 situation has been observed.
Transmission line
Contractor’s CEMP/SEMP The contractor should develop a site-specific CEMP and approved by PCGB. The CEMP should be shared with ADB.
Environmental monitoring is overseen by PGCB. The responsible engineer of PGCB reviews the CESMMP and environmental report relating to the project and performs monitoring of compliance of Kalpataru Power Transmission Limited (KPTL)’s performance with the approved CESMMP, environmental standards and other environmental commitments of the Kalpataru Power Transmission Limited (KPTL). Environmental monitoring in the field is carried out by the Engineers and the task of
Once PGCB approves the SEMP/CEMP, in this CESMMP, the document should be shared with ADB for observation.
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
23
Environmental issue
Mitigation measures suggested in EMP Observation during monitoring period Recommendation /comments
actual monitoring is undertaken by environmental specialists. The environmental specialist is mobilized on an intermittent basis to undertake field audits and compilation of necessary periodic environmental report for the PGCB and Financier (Asian Development Bank). Likewise, the national environmental and social safeguard specialist is engaged on a regular basis to support acquisition and ensure validation of monitoring data.
Fauna Preparation of construction management plan by the contractor and follow it. Follow GoB rules and regulations on noise. Project workers should not disturb or kill birds or other animals.
The contractor has developed site specific CEMPs which prohibits the disturbances on the local fauna. To avoid wetlands which have potential fauna, tower footing has been changed.
However, the changes in tower footings and changes reflected in the CEMP has not been shared with PGCB and ADB. These changes should be recorded well and shared with PGCB and ADB to verify whether any changes in the IEE/EMP is required or not.
Construction waste and water pollution
Use of durable, long-lasting materials that will not need to be replaced as often, thereby reducing the amount of construction waste generated over time. Provision of facilities for proper handling and storage of construction materials to reduce the amount of waste caused by damage or exposure to the elements Purchase of perishable construction materials such as paints incrementally to ensure reduced spoilage of unused materials Use of building materials that have minimal packaging to avoid the generation of excessive packaging waste. Use of construction materials containing recycled content when possible and in accordance with accepted standards. Adequate collection and storage of waste on site and safe transportation to the disposal sites and disposal methods at designated area shall be provided.
Effluent from worksite are controlled and brough to a detention basin for settling. Once settled the soil is carried away to a designated place by city corporation/municipality.
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
24
Environmental issue
Mitigation measures suggested in EMP Observation during monitoring period Recommendation /comments
Effluent drainage is maintained and monitored at worksite all the time.
Noise It is recommended that no construction should be allowed during night
time (9 PM to 6 AM). Avoid using of construction equipment producing excessive noise at any time. Avoid prolonged exposure to noise (produced by equipment) by workers. Regulate use of horns and avoid use of hydraulic horns in project vehicles.
Measured noise at various site was high only at workplaces while the transmission line area was found to be within limits (see noise test results in the previous sections).
Construction works should be strictly limited to (9AM to 6PM) to avoid complains from surroundings. Spraying of water should be more frequent in the upcoming dry season.
Air quality and dust All vehicles (e.g., trucks, equipment, and other vehicles that support construction works) shall be well maintained and not emit dark or smoky emissions in excess of the limits described in the Environment Quality Standards (EQS). Specific training will be focused on minimizing dust and exhaust gas emissions from heavy construction vehicles. Drivers of vehicles used during construction will be under strict instructions to minimize unnecessary trips and minimize idling of engines. Dust suppression facilities (back pack water sprayer) shall be available where earth and cement works are required. Spray water on dry and loose surfaces of the construction sites regularly. Maintain adequate moisture content of soil during transportation, compaction and handling. Construction materials (sand, gravel, and rocks) and spoil materials will be transported in trucks covered with tarpaulins. Sprinkle and cover stockpiles of loose construction materials (e.g., fine aggregates, sand). Dust masks should be provided to all personnel in areas prone to dust emissions throughout the period of construction.
Water is spayed regularly to avoid dust concentration in air. It was found from the onsite EHS specialist that, water is sprayed twice a day.
Vehicle movements are also restricted with the site to avoid smoke and dust.
Traffic congestion Follow Bangladesh Road Transport Authority (BRTA) traffic rules and regulations. Schedule deliveries of material/ equipment during off-peak hours. Engage flagman where needed. Engage experienced drivers to drive project vehicles. Arrange for signal lights at night, for
Kalpataru has devised a traffic management plan to implement on worksites.
The traffic plan needs to be updated and align with the TL and submitted to PGCB and BRTA for approval.
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
25
Environmental issue
Mitigation measures suggested in EMP Observation during monitoring period Recommendation /comments
proper traffic management. Avoiding stockpiling of materials, especially at the road sides, that could hamper traffic movement.
Additionally, the following measures have been taken by the contractor: a) All deliveries of stocks have been carefully planned and suppliers should be advised as to the time and location at which these will have to be delivered to the Gopalgonj to Mongla. b) The frequent presence of trucks is added to increase traffic, sound (excessive noise) and smoke pollution through exhaust emission. c) Avoided as far as possible the peak traffic hours such as school hours in order to reduce the risk of any children/traffic accident/incidents. d) Ensured that allowable axel weight is not exceeded when the deliveries are brought by the suppliers using the Fort portal main highway.
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
26
Environmental issue
Mitigation measures suggested in EMP Observation during monitoring period Recommendation /comments
Community health and safety
Safety barriers and warning signs surrounding the tower construction site. Formulate and implement an emergency risk management plan (by the contractor).
Worksite safety fencing were found.
compliance register was found at site.
Proper signboards and posters on community safety should be posted along the TL and worksites. Before posting them, PGCB needs to approve the posters.
Occupational health and safety
An experienced H&S Manager must be engaged by the contractor prior to the start of construction of the towers. Only permitting trained and certified workers to work with any electrical equipment. First aid box and personal protective equipment, PPE (such as helmet, safety shoes, eye protection glass, ear plugs, waist belt, mask, hand gloves, body protective apron, ear muff and insulating boots, as needed) must be provided to the workers, and ensure their use by workers. Safety signs as needed at the tower sites.
Labors specially who will be climbing up and work at height are trained on safety matters including accident prevention, safe lifting practices, and proper control of all site machineries at TL project; and maintenance of equipment and facilities. Training is also included emergency response, including the location and proper use of emergency equipment, emergency contacts, PPE, health and hygiene procedures for raising the notifying emergency response teams and proper response actions for each foreseeable emergency situation for all labors and stakeholders of this TL project. Fire extinguisher was found at the project site.
Register or records of each training given and their outcomes should be kept at site for tracking progress and lacking. These records should be shared with PGCB and ADB via quarterly and semi-annual monitoring reports. Additionally, to tackle COVID-19 situation the contractor should develop its own guideline using the combined GoB and ADB guidelines and should use awareness posters around the works site. The contractor needs to pay immediate attention to the worker hygiene, toilet and labor shed. They are in pretty bad shape and unhygienic. A checklist is needed to be prepared by the contractor after taking care of the labour shed to ensure that the living condition of the labour shed
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
27
Environmental issue
Mitigation measures suggested in EMP Observation during monitoring period Recommendation /comments
Kalpataru Power Transmission Limited (KPTL) has given the basic training on environmental, social, safety, incident, PPE of all the workers who are newly engaged with TL tower installation project. Kalpataru Power Transmission Limited (KPTL) has been progressing work at the moment of COVID-19 Pandemic. At this moment workers and labors have been following all of the health and safety condition of COVID-19 pandemic. Regular site safety briefing is done.
In the situation of COVID-19, the contractor is using the GoB guideline to combat contamination.
meet the Bangladesh Government’s labour law compliance as well as ADB guideline. Contractor also must ensure that no effluent is discharged from labour shed to nearby wetland, cropland or any sensitive ecosystem.
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
28
Environmental issue
Mitigation measures suggested in EMP Observation during monitoring period Recommendation /comments
However, toilets and shelters provided for the workers were found in pretty bad shape.
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
29
G. Grievance Redress Mechanism
52 The objective of the grievance redress mechanism (GRM) is to resolve complaints as quickly as
possible and at the local level through a process of conciliation; and, if that is not possible, to provide clear
and transparent procedures for appeal. A well-defined grievance redress and resolution mechanism will be
established to resolve grievances and complaints in a timely and satisfactory manner. All affected persons
will be made fully aware of their rights, and the detailed grievance redress procedures will be publicized
through an effective public information campaign.
53 A GRC has been formed for mitigating any unavoidable circumstances during implementing the
compensation process. The committee consists of representatives from PGCB, EPC Contractor,
Consultant (IISPL), and local people. Any dispute regarding determination of compensation against the
losses, usage of land for tower construction and approach road, and other relevant issues during
construction will be solved through the GRC. According to GRM, affected people and communities would
place their claims/counterclaims to the GRC. The affected people may appeal to the GRC against any
disagreeable decision, practice, or activity arising from construction related activities especially in terms of
compensation against affected land and assets. The feature of GRM of the proposed project are mostly
similar to the features of another similar donor funded project in Bangladesh include:
a) An assigned focal person or grievance redress officer managed the grievance redress mechanism,
to whom people can appeal if they are unhappy with the decision made by the implementing
authority;
b) The provision and process of the grievance redress mechanism is well publicized;
c) Information about the complaint and its resolution is documented in registered book and
photography with others relevant soft copies are in DVDs as well as in electronic devices. This
information is generally supposed to be managed in safe and secured hand for using in this project
and sharing experience in other upcoming projects;
d) If the aggrieved person is female, they have been assisted in hearings by any favorable female
participants from her/proponent end, and if from a tribal community, by a tribal representative;
e) Complaints have been dealt with within a specific timeframe, generally around two weeks to four
weeks; The GRM does not interfere in a person’s right to seek redress in the courts of law.
54 No grievances have arisen during the reporting period January 2020 to June 2020 at the
Transmission Line and Substation project.
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
30
IV. Environmental Compliance (agreements)
A. Compliance with environmental related project covenants
1. National Covenant
55 The National Environmental Policy (NEP) was adopted in 1992 and is now under revision. It
embraces different sectors related to agriculture, forest, power, health, transport, housing etc. The central
theme of policy is to ensure protection and improvement in environment. The policy supports sustainable
development and long-term use of natural resources. The National Environment Policy contains policy
statements and strategic options with regard to population and land-use management, management and
utilization of natural resources and other socio-economic sectors, as well as the necessary arrangements
for the implementation of the policy.
56 The main Ministry, Department, Institutions and Boards responsible for development of policy,
framing regulation, developing projects, monitoring and approval of issues related to environment protection
and conservation are presented in this section. The Department of Environment (DoE) was established in
1977 under the Environment Pollution Control Ordinance, 1977. During 1987-89, Forestry was a Division
of Agriculture Ministry with a Secretary to Government in charge of the Forestry Division. With the formation
of the new Ministry of Environment and Forests, in 1989, both the departments were transferred to this new
Ministry.
57 The DoE has been placed under the MoEFCC as its technical wing and is statutorily responsible
for the implementation of the Environment Conservation Act, 1995. Besides these two departments,
MoEFCC controls the Bangladesh Forest Industries Development Corporation (BFIDC), Bangladesh Forest
Research Institute (BFRI) and Bangladesh National Herbarium (BNH).
58 The Ministry of Environment and Forests and Climate Change (MoEFCC) prepare the
environmental policies. MoEFCC has also formulated regulation toward clearance of projects from
environmental angles based on environmental impact assessment report.
59 The Department of Environment is responsible for environmental issues while forest issues are
looked after by Department of Forests. Over the years, the MoEFCC has adopted number of legal
instruments in the form of Acts for the protection and conservation of the environment. Table IV-1
summarizes the Environmental Legislation applicable to the sub-projects.
Table IV-1 Summary of Environmental Legislations Applicable to the Proposed Project
No. Environmental Legislation / Act
Objective Relevance to the Project Responsible Institution
Compliance status
1 National Environmental Policy, 1992
Ensure that development components do not pollute the environment or degrade resources. It sets out the basic framework for environmental action together with a set of broad sectoral action guidelines.
Restriction on operations which cannot be initiated in ecological critical areas
Regulation on vehicles emitting smoke which is harmful to the environment
Follow standards on quality of air, water, noise and soil
Sets limits for discharging and emitting waste
Ministry of Environment and Forests, and Climate Change
The final design of the transmission alignment has been selected avoiding ECAs and PAs. The substations are also located avoided any ECA/PA nearby.
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
31
No. Environmental Legislation / Act
Objective Relevance to the Project Responsible Institution
Compliance status
2 National Environmental Management Action Plan (NEMAP), 1995
An action plan to identify key environmental issues affecting Bangladesh, identifies actions for reducing the rate of environmental degradation and improve quality of life.
Sectoral agencies to coordinate with MoEFCC in preparing environmental guidelines
Ministry of Environment and Forests, and Climate Change
EC has been obtained from DoE for the transmission line (active unstill September 2020) project and has been applied for renewal. Additionally, EMP has been formulated in IEE indicating potential impacts and their remedies. Moreover, SEMPs have been formulated by the contractors and send to PGCB for approval
3 Environment Court Act, 2000 and subsequent amendments in 2003
Establishment of Environment Court for trial of an offence or for compensation under environmental law, such as environment pollution.
Option to affected persons for grievances related to environment safeguards.
Ministry of Environment and Forests, and Climate Change
GRC has been formulated to address the affected persons for grievance.
4 The Forest Act (1927) and Forest (Amendment) Act (2000)
An act to control trespassing, illegal resource extraction and provide a framework for the forestry revenue collection system;
Requires clearances for any project within forest areas and clearances for any felling, extraction, and transport of forest produce.
Department of Forests
The transmission line avoids forested areas.
5 National Forest Policy (1994)
To conserve existing forests and bring about 20% of the country’s land area under the Forestation Programme and increase reserved forests by 10% per year until 2015
Incorporate tree planting in the subproject
Clearance for any felling, extraction, and transport of forest produce
Department of Forests
The transmission line avoids forested areas.
6 The Bangladesh Wildlife (Conservation & Security) Act, 2012
To conserve and protect wildlife in Bangladesh including designation of protected areas. Protection of wildlife is provided with lists of species with four schedules: first, second, third and fourth schedule. The fourth schedule species have the highest level of protection.
Consultation and necessary permits required if the project will pass through the wildlife sanctuaries and other protected areas.
Department of Forests
The transmission line does not cross any wildlife sanctuaries.
7 Wetland Protection Act 2000
Advocates protection against degradation and resuscitation of natural water-bodies such as lakes, ponds, beels3, khals, tanks, etc. affected by man-made
There are some ponds and small wetlands on the way of transmission line that might affect the natural flow and size of the wetlands
Ministry of Water Resources
Site specific designs have been formulated by the contractor who have made some minor changes in the tower footings to
3 A beel is a billabong or a lake-like wetland with static water (as opposed to moving water in rivers and canals - typically called
khaals), in the Ganges - Brahmaputra flood plains of the Eastern Indian states of West Bengal, and Assam and in the country of Bangladesh.
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
32
No. Environmental Legislation / Act
Objective Relevance to the Project Responsible Institution
Compliance status
interventions or other causes. Prevents the filling of publicly-owned water bodies and depressions in urban areas for preservation of the natural aquifers and environment. Prevents unplanned construction on riverbanks and indiscriminate clearance of vegetation on newly accreted land.
avoid wetlands on the way.
8 Bangladesh Labor Law, 2006
It is a comprehensive law covering labour issues such as: conditions of service and employment, youth employment, benefits including maternal benefits, compensation for injuries, trade unions and industrial relations, disputes, participation of workers in company’s profits, regulation of safety of dock workers, penalty procedures, administration and inspection.
This Act pertains to the occupational rights and safety of factory workers and the provision of a comfortable environment for working. It also includes rules on registration of labourers, misconduct rules, income and benefits, health and fire safety, factory plan
Compliance to provisions on employment standards, occupational health and safety, welfare and social protection, labor relations and social dialogue, and enforcement.
Prohibition of employment of children and adolescents.
Ministry of Labor and Employment
OHS and COVID-19 guidelines have been formulated for the project by PGCB and Contractors.
9 Bangladesh Labor Rules, 2015
Includes rules on registration of laborers, misconduct rules, income and benefits, health and fire safety, factory plan
Contractors to implement occupational health and safety measures
Contractor will be liable for compensation for work-related injuries
Department of Labor
OHS and COVID-19 guidelines have been formulated for the project by PGCB and Contractors.
10 Bangladesh Climate Change Strategy and Action Plan of 2009
Enhances the capacity of government ministries, civil society and private sector to meet the challenges of climate change
Integrate adaptation measures for buildings in consideration of extreme climatic events
Ministry of Environment, Forests and Climate Change
The design includes climate enhancement. Climate mitigation is estimated to cost estimated as $93 million.
11 Building Construction (Amendment) Act and Building Construction Rules, Bangladesh
Regulates technical details of building construction and to maintain standards of building construction
Follow specifications to ensure structural integrity of buildings
Ministry of Housing and Public Works
The design of the building construction (Gopalganj substation) followed all the specifications required.
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
33
No. Environmental Legislation / Act
Objective Relevance to the Project Responsible Institution
Compliance status
National Building Code
12 Electricity Act, 1910 and Electricity Rules 1937
Requires compensation for any damage, detriment or inconvenience caused by the project; Requires precautionary measures in laying down electricity supply lines near or where any metallic substance or line crosses to avoid electrocution
Secure permission to supply energy and lay down or place electricity supply lines for the conveyance and transmission of electricity from respective authorities prior to any works
Give full compensation for any damage, detriment or inconvenience caused by him or by anyone employed by him
Take precautions in laying down electricity supply lines near or where any metallic
substance or line crosses in order to avoid electrocution
Ministry of Power, Energy and Mineral Resources
GRC has been formed and compensation lists is with the GRC.
13 The National Energy Policy (1996 and Updated 2004)
Ensures environmentally sound sustainable energy development programs causing minimum damage to the environment, to encourage public and private sector participation in the development and management of the energy sector and to bring the entire country under electrification.
Public and private sector participation in the development and management of the energy subprojects.
Provides guidelines for renewable energy subprojects
Ministry of Power, Energy and Mineral Resources
This project does not consider renewable energy; however, the climate mitigation measures have been included in the project design.
14 National Disaster Management Act of 2012
Establishes a framework for managing disasters in a comprehensive way.
Setting-up emergency response procedures
Ministry of Disaster and Relief
Site specific measures have been developed by the contractors in the form of SEMP.
2. The ADB Safeguards Policy Statement (2009)
60 The ADB SPS (2009) provides the guiding principles of the environmental safeguards monitoring
of a project. The ADB Safeguard Policy Statement (SPS), 2009 (ADB, 2009) defines, generally, the actions
that should be undertaken to avoid, minimise, or mitigate adverse environmental and social impacts,
including protecting the rights of those likely to be affected or marginalised by the development process.
The three operational components of the safeguard policy are: protection of the environment, protection of
vulnerable (indigenous) people, and preventing/minimizing involuntary resettlement. These three safeguard
policies involve a structured process of impact assessment, planning, and mitigation to address the adverse
effects of projects throughout the project cycle. The safeguard policies require (i) identifying and assessing
impacts early in the Project cycle; (ii) developing and implementing plans to avoid, minimise, mitigate, or
compensate for the potential adverse impacts; and (iii) informing and consulting affected people during the
Project preparation and implementation.
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
34
61 ADB’s safeguard policies have provisions for compliance monitoring throughout the Project cycle
and an accountability mechanism whereby people adversely affected by ADB-financed projects can
express their grievances and seek solutions. The procedure referred to as the Grievance Redress
Mechanism (GRM) must be defined in every IEE and EIA.
62 SPS 2009 has also provisions for identify measures to avoid, minimize, or mitigate potentially
adverse impacts on and risks to biodiversity, natural resources, safety of both workers and affected
community and physical cultural resources during the design, construction, operation, and
decommissioning of the project.
3. ADB Safeguards Policy Statement (2009) compliance status
63 Refer to Table IV-2 for the status of the respective component sub-projects with regard to
environmental compliance status to ADB’s policy statement (SPS 2009).
Table IV-2 ADB Safeguards Policy environmental compliance Status for the STGEP subprojects (ADB SPS 2009 Appendix 1 Safeguards Requirement: Environment)
ADB Safeguard Policy Statement Contract Package Status
Package 1 Package 2 Package 3 Package 4 Package 5
(i) Environmental Assessment
(Category B: Requires IEE) done
and disclosed
Complied Complied Complied Complied Complied
IEE done for all packages, available at: https://www.adb.org/projects/documents/ban-51137-
001-iee
(ii) Environmental Management Plan
drafted
Complied Complied Complied Partially
complied
Partially
complied
EMP drafted along with IEE, sperate site specific CEMPs for each site has been developed by
contractors, Package 4 and 5 are still under processing. No CEMP has been done since no
contractor is engaged.
(iii) Information disclosed
Complied Complied Complied Complied Complied
IEE done for all packages, available at: https://www.adb.org/projects/documents/ban-51137-
001-iee
(iv) Consultation and participation have
been done and public opinion has
been used in project design phase.
Complied Complied Complied Complied Complied
Consultations were done during IEE development. GRC has been establish to consult public
grievance during project implementation.
(v) Establishment of GRC and notes of
grievances
Complied Complied Complied Yet to start Yet to start
GRCs have been establish for each package and are active. No grievance has been noted till
date.
(vi) Monitoring and reporting: client will
document regular monitoring
results, in case of adverse
significant affects external NGO will
be involved as third party monitoring
Complied Complied Complied Yet to start Yet to start
Biannual environmental monitoring report submitted by PGCB. External NGO will be engaged
in October 2020.
(vii) Unanticipated environmental
impacts
Complied Complied Complied Yet to start Yet to start
Site specific CEMPs have been prepared by the contractors and have been approved by
PGCB. Due to the unanticipated COVID-19 pandemic, the project activities were stopped to
avoid contamination. Sites were reopened in June 2020 with contractors forming their own
COVID-19 guidelines for workspace reopening based on ADB COVID-19 guidelines and GoB
COVID-19 guidelines. The guidelines have been approved by PGCB.
(viii) Biodiversity Conservation and
Sustainable Natural Resource
Management: The borrower/client
will assess the significance of
project impacts and risks on
Complied Complied Complied Complied Complied
The assessment was done during the development of IEE and has been disclosed on ADB’s
website. The project does not impact any critical habitat. The tree plantation programme does
not include any invasive alien species. Contractors have distributed 2000 native tree saplings to
local schools and Madrasas.
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
35
ADB Safeguard Policy Statement Contract Package Status
Package 1 Package 2 Package 3 Package 4 Package 5
biodiversity and natural resources
as an integral part of the
environmental assessment process
(ix) Pollution presentation: During the
design, construction, and operation
of the project the borrower/client will
apply pollution prevention and
control technologies and practices
consistent with international good
practice, as reflected in
internationally recognized standards
such as the World Bank Group’s
Environment, Health and Safety
Guidelines.
Complied Complied Complied Yet to start Yet to start
Both contractors drafted their own site-specific CEMPs and that has been approved by PGCB.
No hazardous materials of toxic properties have been found at site. All nonhazardous wastes
are being dumped to the municipalities’ designated area. The project itself has invested for
climate mitigation. Therefore, GHG emissions is expected to be marginalized. Environmental
tests were done for 400kV and 132kV transmission lines and no parameter exceeded DoE
recommended guidelines.
(x) Health and safety: The
borrower/client will provide workers
with a safe and healthy working
environment, taking into account
risks inherent to the particular
sector and specific classes of
hazards in the borrower’s/client’s
work areas, including physical,
chemical, biological, and
radiological hazards.
Complied Complied Complied Yet to start Yet to start
Both contractors have their own OHS rules which are effective in field. Additionally, PGCB has
its own rules regarding OHS. During the COVID-19 pandemic spread in March – June, the
project activities were stopped to avoid contamination. Upon reopening the contractors drafted
their COVID-19 response plan that are approved by PGCB. ADB has also provided its COVID-
19 guidelines for contractors following which contractors prepared, updated and implemented
the plan at site
(xi) Physical and cultural resources:
The borrower/client is responsible
for siting and designing the project
to avoid significant damage to
physical cultural resources
Complied Complied Complied Complied Complied
The project design considered the important cultural and physical resources in the project sites
4. Compliance with loan Covenants
64 Schedule 4 of the Agreements for Grant 0582-BAN includes covenants for environmental issues.
The Project’s compliance with the contractual environmental safeguards’ covenants are shown in the Table
IV-3
Table IV-3 Compliance with Environmental Considerations of Loan Agreements
Covenant Reference in the Grant Agreement
Compliance Status
Environment
PGCB shall ensure that the preparation, design, construction, implementation, operation and decommissioning of each Subproject comply with: (i) all applicable laws and regulations of the Recipient relating to environment, health, and safety; (ii) the Environmental Safeguards; the EARF; and (iii) all measures and requirements set forth in the respective IEE and EMP, and any corrective or preventative actions set forth in a Safeguards Monitoring Report.
Schedule 4, Para. 5 Complied. All requirements addressed in preparation and design stages including contract documentation.
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
36
Covenant Reference in the Grant Agreement
Compliance Status
Safeguards – Related Provisions in Bidding Documents and Works Contracts
The Recipient shall ensure, or cause the EAs to ensure, that all bidding documents and contracts for Works contain provisions that require contractors to:
Schedule 4, Para. 9 Complied.
(a) comply with the measures and requirements relevant to the contractor set forth in the relevant IEE, EMP and RP (to the extent they concern impacts on affected people during construction), and any corrective or preventative actions set out in a Safeguards Monitoring Report;
Complied. All Bidding Documents and Contracts contain the required provisions
(b) make available a budget for all such environmental and social measures; Complied.
(c) provide the Recipient with a written notice of any unanticipated environmental, resettlement or indigenous peoples risks or impacts that arise during construction, implementation or operation of the Subproject that were not considered in the relevant IEE, EMP and RP;
Complied.
(d) adequately record the condition of roads, agricultural land and other infrastructure prior to starting to transport materials and construction.
Complied.
(e) reinstate pathways, other local infrastructure, and agricultural land to at least to their pre project condition upon completion of construction
Yet to comply
Safeguards Monitoring and Reporting
The Recipient shall do the following, or shall cause the EAs to do the following: (a) submit semi-annual Safeguards Monitoring Reports to ADB and disclose relevant information from such reports to affected persons promptly upon submission.
Schedule 4, Para. 10 Complied.
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
37
V. Performance Indicators
A. Overall performances
65 Overall performances of the project in the perspective of environmental compliance has been
analysed based on monitoring reports and site visit impressions are presented in Table V-1 and Table V-2.
Table V-1 Overall performance in relation to environmental compliance (Gopalganj substation)
No. Aspects of
Environmental issues
Compliance Status
Remarks
FC PC NC
A. General
1. Legal working hours approval
The workers work 10 hours a day at site including 1.5-hour lunch break. Sometimes worker taking rest if they feel bored due to work which is maximum 30 min.
2. Employment Record keeping arrangement
The employment records are kept in a register book manually every day in the field.
3. Payment Record keeping arrangement
The payment records are kept in a register book manually every day in the field.
4. Environment, Health and Safety Officer designated
Appointed from the beginning. The contractor has inhouse HSE team
5. Provision for monthly meeting for inspection of site activities
Meetings are held on working progress, environmental compliance and future planning periodically during mission. However, it is strongly advised that the meeting minutes need to be reported to PGCB and compilation of the monthly meeting reports needed to be included in the Semi-annual report prepared by PGCB which is disclosed at ADB website.
B. Health and Sanitation
Occupational Health
1. First-Aid Box availability at work sites
A well-equipped first aid box is available at the site.
2. Provision of personal protection equipment’s (PPEs)
Site Engineers, supervisors and workers are provided with PPEs including vests, helmets, safety boots etc. However, it was found that not all workers are wearing the appropriate PPEs, neither they are aware of the COVID-19 situation. During monthly meeting and COVID-19 awareness programmes arranged by the contractor, it found that both the workers and communities receiving training are not maintaining social distancing and not wearing mask. It is strongly advised that COVID-19 measures as drafted by the contractor and ADB guidelines should be strictly followed at site and awareness trainings should be arranged on monthly basis which needs to be reported back to PGCB. Additionally, toolbox meetings everyday should feature PPE and COVID-19 awareness and should be recorded as meeting memos at site.
3. Handling of cement and other hazardous materials by workers
Hazardous and Non-Hazardous materials were collected by a separate waste bin. Fuel drums are stored in the designated area. However, no chemical handling plan was not found at site. It is recommended that, contractor should draft a chemical handling plan for the site.
4. Workers’ complains taken care of by the supervisor
Planning to appoint a supervisor for the workers is appointed to take care of the worker’s problems and receiving complaints from the workers and solving those problems accordingly.
5. Children below 18 employment
There are no below 18 children working in the site
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
38
No. Aspects of
Environmental issues
Compliance Status
Remarks
FC PC NC
C. Environmental Pollution Dust and emission control
1.
Construction vehicles and machineries maintained properly to reduce emissions
Try to maintain the vehicles and machineries with least pollution.
2. Proper storage of materials and regular watering.
The materials are stored in proper manner and watering is done when required to mitigate air pollution. Removal of dust fully is quite difficult but the project team is trying to remove by water spraying in an environmentally friendly manner. As suggested earlier, a chemical handling plan should be drafted and followed by the contractor. The plan needs to be approved by PGCB.
Noise Pollution
1. Movement of vehicles at desired hours
Heavy vehicles movements are done mostly from morning to afternoon.
2. Noise control measures at sites
Noise created due to construction and heavy machineries affects less on the surrounding household because the construction site is away from the residential area.
Water Pollution
1. Land filling During land filling no proper record were kept to observe waterlogging and drainage congestion.
2. Wastes, cement, effluents and junks not disposed in water
Settling ponds were dug for effluent discharge. The dried sand/soil is excavated and carried away to a municipality designated area.
Flora and Fauna
1.
Trees and bushes outside the construction area preserved from damages
Trees and bushes in the construction area is cleared during pre-construction phase. Vegetation outside of the working area is not affected. However, plantation programme will be commenced during site reinstatement as part of environmental enhancement.
2. Disturbance to terrestrial fauna minimized
The camp site has no significant terrestrial fauna; few birds, mouse, snake etc. are identified there which are not affected by the project works. Workers are instructed not to hurt any wildlife if they encountered in the construction site.
Waste Management
1. Construction wastes are removed off site regularly
The wastes are kept in a specific place and they are removed off site regularly in and environmentally friendly manner. The contractor needs to draft a waste management plan and follow the plan accordingly with reports to PGCB.
2. Chemical wastes, if any, collected and disposed of properly
Chemical used for water purification is stored offsite in the chemical storage safely. During the monitoring period, no incident of chemical spills is seen. As advised earlier, the contractor needs to devise a chemical handling plan approved by PGCB.
D. Environmental documents at Field Office and Project sites
1.
Field Office possesses copies of EMP, contract document and Technical Specifications
All the documents are kept in the field office.
2. Heavy equipment maintenance records
In the mini pipe packages, no heavy equipment is required except mechanical drilling rig which is checked regularly. The maintenance records are yet to kept at site.
TOTAL 18 3 1
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
39
Table V-2 Overall performance in relation to environmental compliance (TL)
No. Aspects of
Environmental issues
Compliance Status
Remarks
FC PC NC
A. General
1. Legal working hours approval
The workers work 10 hours a day at site including 1.5-hour lunch break. Sometimes worker taking rest if they feel bored due to work. This break is maximum 30 min which is known to the workers as tea break.
2. Employment Record keeping arrangement
The employment records are kept in a register book manually every day in the field.
3. Payment Record keeping arrangement
The payment records are kept in a register book manually every day in the field.
4. Environment, Health and Safety Officer designated
Appointed from the beginning. The contractor has inhouse HSE team
5. Provision for monthly meeting for inspection of site activities
Meetings are held on working progress, environmental compliance and future planning periodically during mission. The meeting memos are kept by contractor, but they should be submitted to PGCB to report back to ADB.
B. Health and Sanitation
Occupational Health
1. First-Aid Box availability at work sites
A well-equipped first aid box is available at the site
2. Provision of personal protection equipment’s (PPEs)
Site Engineers, supervisors and workers are provided with PPEs including vests, helmets, safety boots etc. However, it was found that not all workers are wearing the appropriate PPEs, neither they are aware of the COVID-19 situation. During monthly meeting and COVID-19 awareness programmes arranged by the contractor, it found that both the workers and communities receiving training are not maintaining social distancing and not wearing mask. It is strongly advised that COVID-19 measures as drafted by the contractor and ADB guidelines should be strictly followed at site and awareness trainings should be arranged on monthly basis which needs to be reported back to PGCB. Additionally, toolbox meetings everyday should feature PPE and COVID-19 awareness and should be recorded as meeting memos at site.
3. Handling of cement and other hazardous materials by workers
Hazardous and Non-Hazardous materials were collected by a separate waste bin. Fuel drums are stored in the designated area.
4. Workers health and sanitation
Worker labour shed and toilets were found unhygienic. The contractors need to immediately improve the labour shed condition and report back to PGCB. The contractor also should prepare a compliance sheet stating the current condition and conditions being provided for the workers. PGCB will check the compliance sheet and inspect site to observe the condition. The contractor also shall report to the PGCB team on worker conditions including labour shed and hygiene facilities.
5. Children below 18 employment
There are no below 18 children working in the site
C. Environmental Pollution Dust and emission control
1.
Construction vehicles and machineries maintained properly to reduce emissions
Try to maintain the vehicles and machineries with least pollution.
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
40
No. Aspects of
Environmental issues
Compliance Status
Remarks
FC PC NC
2. Proper storage of materials and regular watering.
The materials are stored in proper manner and watering is done when required to mitigate air pollution. Removal of dust fully is quite difficult but the project team is trying to remove by water spraying in an environmentally friendly manner. However, it was found the water spray needs to be more frequent. Therefore, records of water spray and complains should be registered.
Noise Pollution
1. Movement of vehicles at desired hours
Heavy vehicles movements are done mostly from morning to afternoon.
2. Noise control measures at sites
Noise created due to construction and heavy machineries affects less on the surrounding household because the construction site is away from the residential area.
Water Pollution
1. Wastes, cement, effluents and junks not disposed in water
Settling ponds were dug for effluent discharge. The dried sand/soil is excavated and carried away to a municipality designated area. This needs to be under strict monitoring. Therefore, the contractor needs to develop a waste management plan in the light of waste management guidelines provided in the IEE and submit to PGCB for approval. The compliance of the waste management plan should be recorded in a register.
Flora and Fauna
1. Compensatory tree plantation
2000 Tree saplings were distributed to local schools and madrasas. No proper record kept.
2.
Trees and bushes outside the construction area preserved from damages
Trees and bushes in the construction area is cleared during pre-construction phase. Vegetation outside of the working area is not affected. However, plantation programme will be commenced during site reinstatement as part of environmental enhancement.
3. Disturbance to terrestrial fauna minimized
The camp site has no significant terrestrial fauna; few birds, mouse, snake etc. are identified there which are not affected by the project works. Workers are instructed not to hurt any wildlife if they encountered in the construction site.
Waste Management
1. Construction wastes are removed off site regularly
The wastes are kept in a specific place and they are removed off site regularly in and environmentally friendly manner. The contractor needs to develop a waste management plan in the light of waste management guidelines provided in the IEE and submit to PGCB for approval. The compliance of the waste management plan should be recorded in a register.
2. Chemical wastes, if any, collected and disposed of properly
Chemical used for water purification is stored offsite in the chemical storage safely. During the monitoring period, no incident of chemical spills is seen. The contractor needs to develop a waste management plan in the light of waste management guidelines provided in the IEE and submit to PGCB for approval. The compliance of the waste management plan should be recorded in a register.
D. Environmental documents at Field Office and Project sites
1.
Field Office possesses copies of EMP, contract document and Technical Specifications
All the documents are kept in the field office.
2. Heavy equipment maintenance records
In the mini pipe packages, no heavy equipment is required except mechanical drilling rig which is checked regularly. The maintenance records are yet to kept at site.
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
41
No. Aspects of
Environmental issues
Compliance Status
Remarks
FC PC NC
TOTAL 14 6 1
B. Health and Safety performance
66 This section presents some site-based H&S performance indicators for all running subprojects at
a glance. The performance indicators are based on field observations from each subproject. The
performance indicators are presented in Table V-3.
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
42
Table V-3 H&S Performance indicators of all subprojects
Environmental Safeguards Questions Package 1 Package 2 Package 3 Package 4 Package 5
1. Sensitive receptors adjacent to the site? (i.e. residential, schools/learning center, health care center, daycare...)
N Y Y - -
2. Are the workers aware of the EMP? Y Y Y - -
3. Occupational Health and Safety: 3.1 Is there a designated person responsible for ensuring safe working practices? Are the workers aware?
Y Y Y - -
3.2 Have the workers received appropriate OHS training to perform their jobs? How often are they briefed on OHS requirements? *
Y Y Y - -
3.3 Do the workers use personal protective equipment (PPE - hats, glasses, boots etc.)? ** Y Y Y - -
3.4 Are working areas clear of slipping and tripping hazards? Y PC PC - -
3.5 Are health and safety warning and information signs visible and understandable to workers? PC PC PC - -
3.6 Are there any hazardous materials? Are they stored and handled appropriately? Y Y Y - -
3.7 Are workers exposed to risks from working at height? If yes, are the workers using harnesses (fall protection equipment)?
N Y Y - -
3.8 Are workers exposed to risk from confined spaces? (i.e. storage areas for hazardous materials) N N N - -
3.9 Is there a record of occupational injuries and diseases? N N N - -
3.10 Do workers receive health checks? Y Y Y - -
3.11 What medical facilities are made available for the workers? First aid First aid First aid - -
Labor Camps: 3.12 What toilet and washing facilities are provided?
Y PC PC - -
3.13 Do workers have access to clean drinking water? Y Y Y - -
3.14 Is the workers accommodation provided by the contractor? Y Y Y - -
Emergency Procedures: 3.15 Are any procedures in place in case of an injury on site?
N N N - -
3.16 Is there a first aid kit available on site? Y Y Y - -
3.17 Are any procedures in place for chlorine leak, oil spills? Y N N - -
3.18 Is firefighting equipment available on site? Is servicing up to date? Y Y Y - -
4. Grievance Redress Mechanism {GRM): 4.1 Are the names and contact information posted for possible complaints?
Y Y Y - -
4.2 Is there a log book available on site? Y Y Y - -
5. House Keeping: 5.1 Did you observe examples of poor housekeeping? (i.e. empty containers scattered, stagnation of water from improper disposal of solid waste?)
N N N - -
Y = Yes; N = No: PC = partially complied
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
43
C. COVID – 19 response performance
67 This section presents some site-based performance indicators COVID-19 for all running
subprojects at a glance. The performance indicators are based on field observations from each subproject
and compared with ADB and Bangladesh Government guideline. The performances indicators are
presented in Table V-3.
Table V-4 COVID-19 Performance indicators of all subprojects
COVID-19 Response questions
Pac
kag
e 1
Pac
kag
e 2
Pac
kag
e 3
Pac
kag
e 4
Pac
kag
e 5
Comments
Site re-opening and entry protocol Locate the closest medical establishment equipped with COVID -19 response facilities.
C C C - -
Engage a full time EHS professional at site C C C - - Purchase thermometer gun, soap, hand sanitizer, disinfectants and PPEs (mask, hand gloves, hard shoes etc.) and keep it at worksite office.
PC PC PC - - Workers are not always using the safety cautions. Need frequent awareness training
Establish site entrance protocol. Redesign the site safety notices/signboards/protocol according to the ADB guidelines NC NC NC - -
Entry protocol has been established, but not satisfactory. Site signboards are not visible.
Arrange washbasin, soap and clean water at the entrance of every worksite/campsite. Also keep either a disinfectant tub for shoes or keep disinfectant spray that must be sprayed under the boots/hard shoes of the persons entering worksite.
PC PC PC - -
Wash basin, soap, clean water etc. has been arranged. However, enforcement of the entry protocol is poor
Provide every personnel working in the site with mask, hand gloves and hard shoes for their personal use.
C C C - -
Everyone entering the worksite must wear a mask, gloves and hard shoes
PC PC PC - - Enforcement of entry protocol is poor
Daily worksite protocol A designated EHS and medical person should stay all time during work. The EHS/Medical person should also monitor campsite. He/she will be in charge of ensuring physical distances (minimum 1m) among workers, disinfecting surfaces that are commonly used and investigate workers/site personnel health and safety.
PC PC PC - -
Fulltime ESH officer is present at site. However, enforcement of physical distancing and frequent disinfection is poor.
At the start and end of the day disinfect the total worksite.
NC NC NC - -
No prove of disinfection at start and end of work. Need to start immediately and monitoring from EHS officer and PGCBB needs to improve.
Encourage site personnel/camp dwellers to not touch their eyes, mouth or nose if not washed thoroughly with soap recently. Also discourage hand shaking or hugs.
PC PC PC - -
Daily toolbox meetings are done and records are kept. But implementation has not been up to the mark.
Arrange a mandatory site brief on COVID awareness in the morning. The session must be conducted by the EHS/medical professional.
PC PC PC - - Same as above.
While worksites are commonly well ventilated (if not make sure the work sites are well ventilated), ensure that the camp sites including the rooms designated for the camp dwellers are well ventilated and spacious.
NC NC NC - -
Labor shed has been found as in pretty bad shape with lack of hygiene facilities. Mitigation measures are reported elsewhere in this report (EMP performance section).
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
44
COVID-19 Response questions
Pac
kag
e 1
Pac
kag
e 2
Pac
kag
e 3
Pac
kag
e 4
Pac
kag
e 5
Comments
Before sharing common tools/machines at worksite, ensure to disinfect.
NC NC NC - - Need to start immediately and monitoring from EHS officer and PGCBB needs to improve.
Discourage site personnel to gather and gossip at any time, rather encourage physical distance while chatting/discussing.
PC PC PC - -
Workers are not enough sensitized on COVID issues. Also, enforcement of site rules appeared to be weak. The ESH officer needs to be much strict on this issue.
Restrict worksite personnel to go outside unnecessarily. Also restrict campsite personnel to go outside without any valid cause.
C C C - -
If any person related at worksite/campsite fall victim to COVID-19 or being kept isolated for pre-caution, consider paid leave with no exception allowed.
- - - - -
No incident has recorded to date.
Every day training Train workers on how to properly put on, use/wear, and take off protective clothing and equipment. The on-site EHS/Medical person should be in-charge of these trainings. These trainings must maintain the WHO’s social distancing protocol. Make these trainings mandatory at worksites. Provide 10-15 minutes of a workday for such ‘training and encouragement’ activities.
PC PC PC - -
Toolbox meetings are done. But the workers seem not enough sensitized. Therefore, effective training and enforcement of site rules is needed.
*C = Complied, NC = Non complied; PC = Partially complied.
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
45
VI. Concluding Observations
68 Current environmental conditions of 3 ongoing subprojects are presented through some site
photographs in Appendix I of this report.
69 The concluding observations are as follows:
The Environmental Safeguards compliance performance of the EAs are in good shape except
a few things. The onsite training workshop and regular monitoring of PGCB and contractors
HSE team to sensitize the workers need to be continued for greater benefit. However, it was
found that despite of the trainings and awareness programmes, onsite photos (Appendix I)
suggest the workers and community people are not maintaining proper PPEs and COVID-19
guidelines. This needs to be strictly monitored and HSE guidelines including COVID-19
guidelines needs to be enforced at site. The reports need to be submitted to PGCB. PGCB
also shall increase the number of monitoring visits and enforce the guidelines.
Due to accessibility issues attributed to restrictions associated with Covid-19, implementation
of environmental safeguards is hindered. In addition, inadequate safety measures, especially
social distancing and frequent disinfection of equipment are still visible at work site.
Environmental quality data from periodic monitoring indicated that in reference to the
Bangladesh standard, the quality of ambient air and groundwater in the project area is within
the standard limit. The noise level is within the safe limit for mixed areas with intermittent spikes
due to proximity of the sites to the roads and human interference.
The labour shed and labour hygiene appear to be ignored by the contractors. This needs
immediate attention and frequent monitoring to improve the condition of labour sheds and
associated hygiene facilities.
70 Recommended actions: The following actions with timeframe is recommended:
Sl. no Recommended action Time frame to
achieve
1 Immediate improvement of the labour shed conditions. The contractor will prepare a
compliance checklist of the labour shed’s present condition and submit to PGCB for
approval. The PGCB team will visit site for checking and approve the compliance checklist.
Then the contractor will take immediate action to improve the prevailing condition using the
checklist and submit to PGCB. The PGCB team will again visit site and inspect using the
checklist whether the situation has improved or not. Then PGCB will make a report on the
improvement and share with ADB
November 30, 2020
2 Contractor must devise On-site waste management plan and submit to PGCB for approval.
The contractor should also develop a onsite checklist for monthly reporting and should report
back to PGCB on monthly basis.
November 30, 2020
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
46
Sl. no Recommended action Time frame to
achieve
3 The PPE and COVID-19 guidelines are not in full compliance. Contractor needs to strictly
monitor the PPE and COVID-19 compliance on site and report back to PGCB. Contractor
shall arrange a general PPE awareness and COVID-19 awareness training workshop at site
with all workers and report to PGCB as compliance reporting. Monthly reports on PPE and
COVID compliance should be submitted to PGCB.
General workshop
by November 15,
2020
4 Tree plantation plan shall be submitted by the contractor to PGCB immediately. Proper
records of tree plantation need to be kept and submitted to PGCB
November 15, 2020
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
47
VII. Appendix - I
Community awareness programme at TL site: People are without mask and not maintaining social
distancing as per COVID-19 awareness guideline. Recommended actions are stipulated in the text.
Posters shown in worksite on COVID-19 awareness:
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
48
Health awareness campaign near the TL area on COVID-19. Participants are not wearing mask and not
maintaining social distancing, which is not acceptable. Recommended measures are stipulated in the report
Tree plantation activities around the TL area:
Southwest Transmission Grid Expansion Project Semi-annual Environmental Monitoring Report (January – June 2020)
49
Traffic safety management at the TL area:
Hand washing facilities at site: as seen in photo, workers are not maintaining proper OHS guideline.
Recommended measures are stipulated in the report.