Ball Mill Inspection

download Ball Mill Inspection

of 9

Transcript of Ball Mill Inspection

  • 8/12/2019 Ball Mill Inspection

    1/9

    www.thecementgrindingoffice.com

    www.thecementgrindingoffice.com Page 1

    BALL MILL INSPECTION PROCEDURE

    Introduction

    This document is intended to help the staff of the cement plants.

    On a process point of view, a mill inspection is only representative if the grinding mill circuit is in a steady working

    condition with a representative cement product.

    If this condition is fulfilled, the whole installation must be stopped in crash-stop (it means all the equipments

    must stop at the same moment).

    It is better to enter first into the first compartment in order to follow the flowpath of the material from the

    beginning of the grinding process.

    Generally, people enter in a manhole. From time to time, when the mill diameter is larger, it is possible to enter

    from the mill inlet.

    This procedure was performed for a 2 compartments mill.

    For other configurations of mills, a simple adjustment is necessary.

    For outside staff, it is also necessary to check the kind of internals and the length of the chambers.

    What we need:

    Now, let's go inside the mill (for the turkish bath...)

  • 8/12/2019 Ball Mill Inspection

    2/9

    www.thecementgrindingoffice.com

    www.thecementgrindingoffice.com Page 2

    First chamber

    Action Data-Measurement Reason

    1 Mill inlet:

    - Check if the inlet is clean and not

    blocked

    To allow a good ventilation of the mill.

    - Check the mill material feeder To allow a good progression of the feed.

    - Check if there are screws and their

    condition

    Height of screw

    Number of screws

    To avoid accumulation of material and

    balls.

    - If there is water injection system,

    check its

    Visual appreciation Water injection in chamber 1 can be

    necessary in case of very hot clinker.

    2 Feed end liners:

    - Check the condition and the wear of

    these liners

    Thickness To maintain the mill shell protected.

    - Check if there are broken liners Number

    3 Volume load or filling degree

    - The measurement must be achieved

    in 3 points on the mill-axis (inlet,

    middle of compartment and

    compartment outlet). The best

    procedure is probably to measure

    the height from the ball charge to

    the linings

    3 points

    (mesure height H)

    To maintain the production (tons/hour) of

    the mill because the volume load is directly

    linked to the mill absorbed power and the

    mill efficiency.

    - Other method: count the number of

    visible lining plates (less reliable

    At least 3 points If it is the only way to measure the volume

    load.

  • 8/12/2019 Ball Mill Inspection

    3/9

    www.thecementgrindingoffice.com

    www.thecementgrindingoffice.com Page 3

    method)

    4 Linings

    - Check the condition and the wear of

    the linings (Lining practically worn-

    out on the picture)

    Thickness

    Lifter height

    To maintain the lining efficiency (don't

    forget that the function of the 1st chamber

    is TO CRUSH).

    - Check if there are broken plates Number To maintain the mill shell protected.

    - Check if there is coating Evaluate if it is hard

    to remove, measure

    the thickness

    This phenomenon can happen, especially in

    the case of raw mills.

    Causes inefficient grinding, low throughput

    and high energy consumption.

    5 Ball charge

    - Check the ball charge: the principle

    is to evaluate visually the proportion

    of big balls (90mm) and small balls

    (60mm)

    Better with

    experienced

    persons

    To maintain the crushing efficiency of the

    1stcompartment.

    - Measure the biggest and the

    smallest ball diameter

    Minimum

    Maximum

    To determine the next ball make up

    composition or the substitution of the ball

    charge.

    - Check if there are broken balls Visual estimation To avoid blockage of the intermediate

    diaphragm.

    To analyse the balls quality with the

    supplier.

    - Check if there is coating Evaluate if it is hard

    to remove

    Causes inefficient grinding, low throughput

    and high energy consumption.

  • 8/12/2019 Ball Mill Inspection

    4/9

    www.thecementgrindingoffice.com

    www.thecementgrindingoffice.com Page 4

    6 Material level

    - Check the material level at mill inlet Not enough material may be due to high air

    velocity.

    Result is the loss of this part of chamber.

    - Check the material level (too highyou don't see the balls, good if you

    see the top of the balls, not enough

    material if you don't see it)

    Make a designVisual estimation

    Measure if too high

    Not enough material can cause breakage ofballs.

    Too much material results in a drop of

    efficiency.

    - Check specially at the intermediate

    diaphragm

    Remove the balls Not enough material may cause excessive

    wear of the grid plates of the diaphragm.

    7 Sampling of the first chamber

    - Take 3 or 4 samples (inlet, 1 or 2

    intermediate samples, at the

    diaphragm)

    2-3kg/sample In order to know the efficiency of the first

    compartment.

    - Ideally for each sample, take

    materiel in three points as shown on

    drawing here below

    Mill-axis point is the

    best if only 1 point

    This is more representative.

    - Remove the balls at the sampling

    point

    Depth of 20-30 cm To allow the sampling with the collector.

    This is more representative.

    - Don't reject the unground particles

    from the sample

    Especially at the

    diaphragm

    It is important to know the percentage of

    uncrushed particles, especially at the

    diaphragm.

    - Drop a ball on unground grains (put

    these grains on the top of a ball)near the diaphragm

    Height 30-40cm To have an idea of the hardness of these

    grains.

  • 8/12/2019 Ball Mill Inspection

    5/9

    www.thecementgrindingoffice.com

    www.thecementgrindingoffice.com Page 5

    8 Intermediate diaphragm

    - Check the general aspect of the

    diaphragm

    Visual

    - Check the condition and the wear of

    the plates and the grid plates

    Visual and thickness To insure the protection of the diaphragm

    frame.

    - Check the width of the slots and ifthere are blocked by unground

    particles or scraps

    Maximum widthMinimum width

    % of area blocked

    To insure that the slots of the intermediatediaphragm are smaller than the slots of the

    outlet diaphragm.

    - Check the condition of the central

    screen

    Visual To prevent the passage of balls from one

    compartment to the other.

    - Check other specific features like

    control systems

    To determine if these features have the

    good settings.

    Second chamber

    Action Data-Measurement Reason

    1 Intermediate diaphragm

    - Check the condition and the wear of

    the back plates

    Visual and thickness To insure the protection of the diaphragm

    frame.

  • 8/12/2019 Ball Mill Inspection

    6/9

    www.thecementgrindingoffice.com

    www.thecementgrindingoffice.com Page 6

    2 Volume load or filling degree

    - The measurement must be achieved

    in 4 points on the mill-axis (inlet, first

    third of compartment, second third

    and compartment outlet). The best

    procedure is probably to measure

    the height from the ball charge tothe linings

    4 points

    (mesure height H)

    To maintain the production (tons/hour) of

    the mill because the volume load is directly

    linked to the mill absorbed power and the

    mill efficiency.

    - Other method: count the number of

    visible lining plates (less reliable

    method)

    At least 4 points If it is the only way to measure the volume

    load.

    3 Linings

    - Check the condition and the wear of

    the linings

    To maintain the lining efficiency (don't

    forget that the function of the 2nd

    chamber is TO GRIND).

    - Check if there are broken plates Number To maintain the mill shell protected

    - Check if there is coating on the

    linings

    Evaluate the impor-

    tance of the problem

    Evaluate if it is hard

    to remove, measure

    the thickness

    This phenomenon can happen, especially in

    the case of open circuit.

    Causes inefficient grinding, low throughput

    and high energy consumption.

  • 8/12/2019 Ball Mill Inspection

    7/9

    www.thecementgrindingoffice.com

    www.thecementgrindingoffice.com Page 7

    4 Ball charge and classification

    - Check the ball charge: the principle

    is to evaluate visually the proportion

    of big balls (60mm) and small balls

    (17-15mm)

    Better with

    experienced

    persons

    To respect the initial ball charge

    recommendation.

    To maintain the efficiency of the 2nd

    compartment.

    - Measure the biggest and the

    smallest ball diameter

    Minimum

    Maximum

    To determine the next ball make up

    composition or the substitution of the ball

    charge.

    - Check if there are broken balls Visual estimation To avoid blockage of the outlet diaphragm

    slots.

    To analyse the balls quality with the

    supplier.

    - Check if there is coating on the balls Evaluate the impor-

    tance of the problem

    Evaluate if it is hard

    to remove

    Causes inefficient grinding, low throughput

    and high energy consumption.

    - In case of classifying lining, check the

    classification of the balls (perfect,

    good, poor or disturbed, mixture of

    the balls, reversed classification)

    Visual estimation

    Sampling of the

    charge but takes

    time and a lot of

    hard work

    Bad classification may be due to a bad

    lining, excessive coating or presence of

    unground particles coming from the first

    compartment.

    Causes inefficient grinding, low throughput

    and high energy consumption.

    5 Material level

    - Check the material level (too high

    you don't see the balls, good if you

    see the top of the balls, not enough

    material if you don't see it)

    Visual estimation

    Make a design

    Not enough material may be due to high air

    velocity.

    Result is a higher wear, a drop of efficiency

    and lower throughput.

    Too much material may cause overfilling, adrop of efficiency and lower throughput.

  • 8/12/2019 Ball Mill Inspection

    8/9

    www.thecementgrindingoffice.com

    www.thecementgrindingoffice.com Page 8

    6 Sampling of the second chamber

    - Take 6-8 samples (inlet, 4-6

    intermediate samples at equal

    distance, diaphragm)

    500gr to 1kg for each

    sample

    In order to know the reduction efficiency of

    the second compartment.

    - Ideally for each sample, take

    materiel in three

    Mill-axis point is the

    best if 1 point

    It is more representative.

    - Remove the balls and the material at

    the sampling point

    Depth of 20-30 cm To collect the material only in surface is not

    correct.

    - With the shovel, put balls and

    material in the sieve which is above

    a paper bag. Remove the balls from

    the sieve. Put the collected material

    in a bag

    Don't forget to put possible uncrushed

    particles with the material sample!

    - Check the presence of uncrushed

    particles, especially an accumulation

    at mill outlet

    Visual estimation Accumulation causes blockage of the outlet

    diaphragm and a drop of efficiency and

    throughput.

    7 Outlet diaphragm

    - Check the general aspect of the

    diaphragm

    Visual

    - Check the condition and the wear of

    the plates and the grid plates

    Visual and

    thickness

    To insure the protection of the diaphragm

    frame.

  • 8/12/2019 Ball Mill Inspection

    9/9

    www.thecementgrindingoffice.com

    www.thecementgrindingoffice.com Page 9

    - Check the width of the slots and if

    there are blocked by unground

    particles or scraps

    Maximum width

    Minimum width

    % of area blocked

    To insure that the slots of the outlet

    diaphragm are bigger than the slots of the

    intermediate diaphragm.

    - Check the condition of the centralscreen

    Visual estimation To prevent the passage of balls.

    - Check the condition of the water

    injection system and if it is blocked

    by material (nozzle)

    Visual inspection Maybe, it is useful to make a test in order

    to see the trajectory of the water jet.