Baldwin Community Schools
May 2018 BondProposal Update
Janua ry 30 , 2018
![Page 2: Baldwin Community Schools Community Schools - Update Presentation...Baldwin Community Schools Bond Program Cost Breakdown Site Work ‐ $560K Remodeling/New Construction ‐ $5.96M](https://reader033.fdocuments.in/reader033/viewer/2022042013/5e733261fcceec3ab773d43f/html5/thumbnails/2.jpg)
May 2018 Bond Program Review
Financial Considerations
Preliminary Schedule and Next Steps
![Page 3: Baldwin Community Schools Community Schools - Update Presentation...Baldwin Community Schools Bond Program Cost Breakdown Site Work ‐ $560K Remodeling/New Construction ‐ $5.96M](https://reader033.fdocuments.in/reader033/viewer/2022042013/5e733261fcceec3ab773d43f/html5/thumbnails/3.jpg)
May 2018 Bond Program Review
![Page 4: Baldwin Community Schools Community Schools - Update Presentation...Baldwin Community Schools Bond Program Cost Breakdown Site Work ‐ $560K Remodeling/New Construction ‐ $5.96M](https://reader033.fdocuments.in/reader033/viewer/2022042013/5e733261fcceec3ab773d43f/html5/thumbnails/4.jpg)
Baldwin Community SchoolsBond Program Cost Breakdown
Site Work ‐ $560K Remodeling/New Construction ‐ $5.96M
Contingency ‐ $1.16M Loose Furniture/Equipment ‐ $595K
Architect/Engineer Costs ‐ $538K Construction Manager Costs ‐ $461K
Owners' Representative ‐ $318K Election/Issuance/Interest Earnings ‐ $302K
Remodel/Construction
Contingency
May 2018 Bond Program Identified $9,910,000 worth of need
District needs to address in the next 5 years
Approximately $3.2M at Baldwin Elementary
Approximately $6.7M at Junior-Senior High
![Page 5: Baldwin Community Schools Community Schools - Update Presentation...Baldwin Community Schools Bond Program Cost Breakdown Site Work ‐ $560K Remodeling/New Construction ‐ $5.96M](https://reader033.fdocuments.in/reader033/viewer/2022042013/5e733261fcceec3ab773d43f/html5/thumbnails/5.jpg)
Bond Costs (breakdown by scope)
5
![Page 6: Baldwin Community Schools Community Schools - Update Presentation...Baldwin Community Schools Bond Program Cost Breakdown Site Work ‐ $560K Remodeling/New Construction ‐ $5.96M](https://reader033.fdocuments.in/reader033/viewer/2022042013/5e733261fcceec3ab773d43f/html5/thumbnails/6.jpg)
Bond Features: Interiors
6
• Renovate Junior High School science lab for modern learning• Renovate Senior High School science lab for modern learning• Build fitness center addition• Replace worn flooring in multiple locations• Replace worn ceiling tiles• Replace and upgrade doors for enhanced security
![Page 7: Baldwin Community Schools Community Schools - Update Presentation...Baldwin Community Schools Bond Program Cost Breakdown Site Work ‐ $560K Remodeling/New Construction ‐ $5.96M](https://reader033.fdocuments.in/reader033/viewer/2022042013/5e733261fcceec3ab773d43f/html5/thumbnails/7.jpg)
7
• Replace and upgrade lighting in parking lots and emergency and exit locations
• Add energy-efficient temperature controls• Replace boilers• Upgrade fire alarm systems• LED Lighting
Bond Features: HVAC, Plumbing, & Electrical
![Page 8: Baldwin Community Schools Community Schools - Update Presentation...Baldwin Community Schools Bond Program Cost Breakdown Site Work ‐ $560K Remodeling/New Construction ‐ $5.96M](https://reader033.fdocuments.in/reader033/viewer/2022042013/5e733261fcceec3ab773d43f/html5/thumbnails/8.jpg)
8
• Repave deteriorating parking lots and sidewalks• Replace roofing• Build covered walkway connecting band room to HS• Replace doors and hardware • Install energy-efficient windows (Jr./Sr. High School)
Bond Features: Exteriors
![Page 9: Baldwin Community Schools Community Schools - Update Presentation...Baldwin Community Schools Bond Program Cost Breakdown Site Work ‐ $560K Remodeling/New Construction ‐ $5.96M](https://reader033.fdocuments.in/reader033/viewer/2022042013/5e733261fcceec3ab773d43f/html5/thumbnails/9.jpg)
Bond Features: Furniture, Technology, & Equipment
9
• Replace worn, unusable classroom furniture• Replace cafeteria tables• Update computer lab equipment• Update weight room equipment
![Page 10: Baldwin Community Schools Community Schools - Update Presentation...Baldwin Community Schools Bond Program Cost Breakdown Site Work ‐ $560K Remodeling/New Construction ‐ $5.96M](https://reader033.fdocuments.in/reader033/viewer/2022042013/5e733261fcceec3ab773d43f/html5/thumbnails/10.jpg)
10
• Upgrade playground site and equipment• Install lighting at football field• Add bleachers and irrigation to football field
Bond Features: Playgrounds & Athletic Fields
![Page 11: Baldwin Community Schools Community Schools - Update Presentation...Baldwin Community Schools Bond Program Cost Breakdown Site Work ‐ $560K Remodeling/New Construction ‐ $5.96M](https://reader033.fdocuments.in/reader033/viewer/2022042013/5e733261fcceec3ab773d43f/html5/thumbnails/11.jpg)
Financial Considerations
![Page 12: Baldwin Community Schools Community Schools - Update Presentation...Baldwin Community Schools Bond Program Cost Breakdown Site Work ‐ $560K Remodeling/New Construction ‐ $5.96M](https://reader033.fdocuments.in/reader033/viewer/2022042013/5e733261fcceec3ab773d43f/html5/thumbnails/12.jpg)
12
![Page 13: Baldwin Community Schools Community Schools - Update Presentation...Baldwin Community Schools Bond Program Cost Breakdown Site Work ‐ $560K Remodeling/New Construction ‐ $5.96M](https://reader033.fdocuments.in/reader033/viewer/2022042013/5e733261fcceec3ab773d43f/html5/thumbnails/13.jpg)
13
![Page 14: Baldwin Community Schools Community Schools - Update Presentation...Baldwin Community Schools Bond Program Cost Breakdown Site Work ‐ $560K Remodeling/New Construction ‐ $5.96M](https://reader033.fdocuments.in/reader033/viewer/2022042013/5e733261fcceec3ab773d43f/html5/thumbnails/14.jpg)
Preliminary Schedule and Next Steps
![Page 15: Baldwin Community Schools Community Schools - Update Presentation...Baldwin Community Schools Bond Program Cost Breakdown Site Work ‐ $560K Remodeling/New Construction ‐ $5.96M](https://reader033.fdocuments.in/reader033/viewer/2022042013/5e733261fcceec3ab773d43f/html5/thumbnails/15.jpg)
Key Dates (May 2018 Election)
• Friday December 8 • Treasury application provided to Thrun Law for filing with Treasury
• Mid‐December• Treasury meeting with BCS, PMC, and Thrun Law
• Tuesday December 19• Regular school board meeting to approve Treasury Application
• January 2018• Special or rescheduled regular school board meeting to adopt the
resolution calling the election for May 2018
• Early February, 2017• Forward ballot wording and resolution to Election Coordinator
• February through May• Ballot Information Campaign – Ongoing Efforts
• May 8th, 2018 – Election Day
![Page 16: Baldwin Community Schools Community Schools - Update Presentation...Baldwin Community Schools Bond Program Cost Breakdown Site Work ‐ $560K Remodeling/New Construction ‐ $5.96M](https://reader033.fdocuments.in/reader033/viewer/2022042013/5e733261fcceec3ab773d43f/html5/thumbnails/16.jpg)
Questions / Answers