BAF3 Civil engineering Status -25 April 2014 • EDMS approval procedure for « Execution drawings » launched on 29/07/2013. Drawings approved on 28/08/2013 – https://edms.cern.ch/nav/P:GS-DEP:V0/P:CERN-0000093812:V0/TAB3 In case of « obsolete Drawings » - last version in CDD • CERN preparatory works : – Week 3 Tree Felling – Week 5 to 11 -Work for primary water connection (CV) • Contractor’s main works started on 17/03/2014: Done : – Worksite installation – Trench excavation for survey of existing networks – Trench excavation for connection of drainage of the access road to the CERN’s clean water – Execution of the access road – Relocation of water hydrant – Earthworks – Lean concrete shaft under separate foundations Ongoing: – Openings in the existing wall of Service Tunnel GT9 – Openings in the upper slab of service tunnel GT10 GS / SE

description

BAF3 Civil engineering Status -25 April 2014. EDMS approval procedure for «  Execution drawings  » launched on 29/07/2013. Drawings approved on 28/08/2013 https://edms.cern.ch/nav/P:GS-DEP:V0/P:CERN-0000093812:V0/TAB3  In case of «  obsolete Drawings  » - last version in CDD - PowerPoint PPT Presentation

Transcript of BAF3 Civil engineering Status -25 April 2014

Page 1: BAF3 Civil engineering Status  -25 April 2014

BAF3 Civil engineeringStatus -25 April 2014

• EDMS approval procedure for « Execution drawings » launched on 29/07/2013. Drawings approved on 28/08/2013– https://edms.cern.ch/nav/P:GS-DEP:V0/P:CERN-0000093812:V0/TAB3 In case of « obsolete Drawings » - last version in CDD

• CERN preparatory works :– Week 3 Tree Felling – Week 5 to 11 -Work for primary water connection (CV)

• Contractor’s main works started on 17/03/2014:

Done:– Worksite installation– Trench excavation for survey of existing networks– Trench excavation for connection of drainage of the access road to the CERN’s clean water– Execution of the access road– Relocation of water hydrant– Earthworks– Lean concrete shaft under separate foundations

Ongoing:– Openings in the existing wall of Service Tunnel GT9– Openings in the upper slab of service tunnel GT10

GS / SE

Page 2: BAF3 Civil engineering Status  -25 April 2014

Mise en place clôtures de chantier

Sondages au droit des réseaux

Passage canalisation EC sous réseaux existants

Page 3: BAF3 Civil engineering Status  -25 April 2014

Canalisation EC jusqu’au regard existant Regard de connexion Drainage / EC

Drainage le long de l’accèsTraversée de la voie d’accès

Page 4: BAF3 Civil engineering Status  -25 April 2014

Drainage le long du chemin d’accès

Canalisation Eaux claires

Page 5: BAF3 Civil engineering Status  -25 April 2014

Protections des transformateurs

Page 6: BAF3 Civil engineering Status  -25 April 2014

Essais de plaques sur chemin d’accès

Mise en place, réglage et compactage matériaux pour chemin d’accès

Page 7: BAF3 Civil engineering Status  -25 April 2014

Décaissement pour chemin d’accès provisoire

Réalisation du chemin d’accès

Page 8: BAF3 Civil engineering Status  -25 April 2014

Déviation de l’hydrante

Page 9: BAF3 Civil engineering Status  -25 April 2014

Excavations pour puits en Béton Maigre

Contrôle du sol en place

Page 10: BAF3 Civil engineering Status  -25 April 2014

Bétonnage des puits en Béton Maigre

Page 11: BAF3 Civil engineering Status  -25 April 2014

Ouvertures dans galerie GT9 sous le niveau du Faux-plancher

Page 12: BAF3 Civil engineering Status  -25 April 2014

Planning Prévisionnel

Date limite avant fabrication Mezzanine

Page 13: BAF3 Civil engineering Status  -25 April 2014

Next steps

• Concreting of the building foundation - May 2014• Concreting of the Slab → July 2014• Steel structure of the hall July– August 2014• Steel structure of the intermediate platform Sept

14• Façades, roofing and partitions Oct – Nov 2014• Resin-based floor covering - Landscaping → Nov -

Dec 2014