B&a-Startup Export Pipeline
-
Upload
kerasaktibanget -
Category
Documents
-
view
218 -
download
0
Transcript of B&a-Startup Export Pipeline
-
7/27/2019 B&a-Startup Export Pipeline
1/2
-
7/27/2019 B&a-Startup Export Pipeline
2/2
Startup 2.2.5.1 WH7 38 Export Pipeline
Important
considerations
For startup of the pipeline whether it be the initial startup or a restart following either
a planned or unplanned shutdown, the important considerations are:
condition of the pipelineplanned flow quantity and schedule for increasing the flow quantity, andambient seawater/air temperatures.
Schedule Initial startup is scheduled to commence during the winter months.
Rationale
The pipeline will have been previously dried to a set level of dryness and filled with dry
gas from onshore. The initial flow rates are likely to be low resulting in a large liquid
hold up.
Hydrate
formation
What is it?
Hydrate formation can occur in the presence of water at low temperature/high
pressure conditions and has the capacity to block the pipeline.
How to control
Control of hydrate formation can be achieved by the presence of Kinetic Hydrate
Inhibitor (KHI) injected into the pipeline from the WH7 platform in sufficient quantity
depending upon the operating conditions, liquid hold up and concentration of
corrosion inhibitor.
Corrosion What is it?Corrosion of the carbon steel will occur in the presence of water that is exacerbated by
the startup conditions.
How to control
To ensure effective corrosion management during startup the recommended maximum
dosage of 1.2 l / hr of corrosion inhibitor should be injected into the pipeline. Greater
quantities of corrosion inhibitor are not recommended as they affect the performance
of the KHI.
Recommended
dosage of CI
during startup
Update of the recommended and maximum recommended dosage of CI during startup
should be included on completion of the ongoing Corrosion Management Review and
CI/KHI Compatibility Study.
Slugging
prevention
During startup and shutdown the rate of increase in flow should be controlled to
prevent slugging in the pipeline. This rate of increase should be in the order of 50
MMSCFD/HR.
The same document, written using Information Mapping