B2C Hosting
March 21, 2012
2
Executive Summary
Business Problem:
The primary goal of the project is to provide a world class web hosting Infrastructure and web engineering support for Sony Pictures customer facing web sites and web applications. Currently, it’s targeted to support three major line of businesses within SPE.
- Sony Pictures Interactive (Sonypictures.com)- Produces award-winning content, websites and comprehensive digital marketing of Sony
Pictures Entertainment business and Production units- Crackle (SPT Crackle.com)
- SPE's premium video website featuring high quality original content and television shows, and feature films from the studio's library
- SPTI (SPTI Production and Platform Development)- Sony Pictures Television (SPT) hosts over 70 discrete branded international websites for
AXN, Animax, and Sony Entertainment Television Worldwide
Issues with the current model are:- Satisfactory support from SNEI - High cost of hosting & support
3
Proposed Solution
The services provided by of IST will include:
- Systems Administrations/Engineering Serviceo OS Management (Primarily LAMP stacks)o Systems Monitoring
- Web Farm Management Serviceo Virtual Hosting Management (Apache Virtual Hosting and release management)o URLs / Redirect Management (New URL redirect and update)o File Management (Web content publishing management)o Scheduled Publishing Management (Web content publishing management)
- Network Management Serviceo Web Hosting Network Core Infrastructure managemento Web Network Security including Firewall and Intrusion Detection managemento Network Protocol Analysis and bandwidth management for billingo VIP and DNS update service
- Application Management Serviceo Open source application management such as Tomcat, Alfresco CMS, vBulletin,
Google search
- Database Management Serviceo Enterprise MySQL, and MS SQL management
- Storage/Backup Management Serviceo Web Hosting Shared Storage managemento Storage and backup monitoring
Host the websites within SPE’s data center and create a new group, Internet Systems Technology (IST), to support these sites.
4
Executive Summary
Project Costs• Software: $
0K• Hardware $
1,073K• Internal Labor: $
222K• External Labor: $
271K• Other/Miscellaneous $
0K
Total Year One Costs: $ 1,566K
FY 13 Project Benefits• Hard $ Benefits: $
1,094K• Soft $ Benefits (Error prevention): $
0K• Soft $ Benefits (Efficiencies): $
0K
FY13 Project Benefits: $ 1,094K
Five-year Summary and Payback• Five-year total costs:
$8,450K• Five-year total benefits:
$9,912K• Five-year net benefit:
$1,461K• Internal Rate of Return
24.7%• Net present value @ 10%: $622K• Payback: 37 months
This project is in the FY13 BudgetFunding Needed FY13 $ 0KFunding Needed FY14 $ 0KFunding Needed FY15 $ 0K
Total Project Costs $ 0K
Depreciation:On Going Costs: $ 1,403K
FY14 FY15 FY16 FY17 FY18 FY19$187,957 $250,609 $250,609 $250,609 $250,609 $62,562
5
Benefits
Cost Avoidance $1,896K 1,020K SonyPictures.Com Hosting & Support 876K Crackle.Com Hosting & Support
Risk Mitigation $0 0
6
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
Project Timeline
2012 2013
Infrastructure Build Out
Migration Of Crackle.Com
Hire & Build ITS Team
Migration of SonyPictures.Com
Migration of First SPTI Web Site
Creation of Support Process
7
Appendix
Current Operating Cost
• Sony Pictures Interactive (Sonypictures.com)– Avg. $85,000 per month to SNEI ($1.02M per year)
• Sonypictures.com - $70,000 per month (example below)
• Adam Sandler - $6,000• Games Network – $10,000
• Crackle– Avg. $73,000 per month ($876K per year)
• $63,000 per month to Level 3 Colocation datacenter in Emeryville• $10,000 per month to SNEI for Systems/Network Support
– Crackle expects to reduce their hosting budget drastically, if they can move out of Level 3 datacenter. They expect the hosting fee should be under $45,000
• Sony Pictures Television International– Avg. $15,000 per month ($180K per year) to CopperFrog Drupal Hosting
provider
DESCRIPTION RATE USAGE UNITS TOTALTotal FeesBandwidth – Backbone $9 142.8 Mbps $1,285 Managed Storage $2.00 3,560.0 GB 7,120 Production $1,565 27 Instance 42,255 Non-Production 1,155 15 Instance 17,325 TOTAL INVOICE $67,985
Function Description Qty CostNetwork Core - Cisco 6509-E Routers/Switches 2 $265,000.00ADC (Application Delivery Controllers) - A10 5520 Load Balancer 2 $260,000.00Network Aggregate (TOR) Switches - Cisco Nexus 5010 (10G and 1G) with 10G SFPs 7 $100,000.00Enterprise Network Firewall - Cisco ASA 5585-X S40 Firewall 2 $112,000.00Out of Band Serial Console - Serial / Modem Terminal Server 1 $30,000.00Two Factor Authentication - RSA/Secure Auth 2 $40,000.00
Storage Network Attached Storage - NetApp 3240 or Isilon (10TB) 2 $180,000.00Security Change Management Auditing, Configuration Control and Compliance - Solidcore or Tripwire
Total $987,000.00
Data Center Rack and Cable Plant build out - 8 Racks, 4 Ports FOP and 24 UTP back to Network $30,000.00Network ARIN (America Registry for Internet Numbers) - AS(Autonomus System) and Address Space Request $5,000.00Network Network 10G Circuit - Initial Circuit Installation $1,000.00Network Network PDU Installation $20,000.00Migration External Load Testing Service for the Migration $20,000.00
Total $76,000.00
Internal Labor Internal Labor (5 FTEs - $76.00 per hour rate) $790,400.00Network DNS Management for external DNS $50,000.00Network 2 x Redundant Carriers 10G Network Circuit $96,000.00
Tool Incident/Service Ticket Management Systems $5,000.00
Data Center8 Racks (@$25.75 per SF based on 8.5 SF per 19 inch rack - $17K per Year)Power (@$150 per 1Kwh, assumption 20Kwh - $36K per Year)
$53,000.00
Maintenance Network, Storage Hardware/Software Maintenance $250,000.00Security DDoS (Distributed Denial of Service) Attack Mitigation Service such as Prolexic, Verisign, Neustar
Total $1,244,400.00
Network
Initial Infrastructure Cost
One Time Initial/Migration Cost
Operating Expenses (Yearly)
Infrastructure Initial/Operating Cost Analysis
High Level Migration Plan
1. Build out Core Infrastructure at El Segundo Datacenter1. Order 2 x 10G IP transit cross connect and Infrastructure Hardware2. Order ARIN for AS and Portable IP space3. Setup production network, VPN to peers, server farms, and storage4. Setup Monitoring systems5. Setup/Migrate Incident/Service ticketing systems
2. Validate Infrastructure fail-over1. Validate BGP, HSRP, VRRP for network fail-over2. Validate Server Load balancing and NAS Storage controller fail-over
3. Perform Infrastructure security assessment1. Address any critical security issues
4. Critical Services Migration1. DNS Migration (Service from SNEI to UltraDNS)2. Web Farm Migration (initial Apache image migration)3. Storage Migration (data migration from SNEI to SPE)4. Database Migration (MySQL data migration from SNEI to SPE)5. CDN Updates (Content Distribution Network updates for the new Origin servers)
5. Load Testing1. Prepare environment for real load simulation from the external load test vendor2. Run simulated peak load along with DDoS simulation (Network, Server, and Storage fail-over and design
validation)3. Make necessary design and configuration changes to the environment if needed4. Run another load test for the final confirmation of the Infrastructure performance
6. Final Cut-over1. Communicate with line of businesses2. Synchronized all data from SNEI to SPE (Storage, Web/Server configuration, and Database)3. DNS Cut-over4. Validation