  • 7/27/2019 B193(R)-RQ-IN-4019

    1/6

    SHEET 1 OF 6

    B193 FIELD DEVELOPMENT PROJECTOWNER TENDER NO.: MR/OW/MM/B-193/07(R)/2007

    DOC.

    NO.:B193(R)-RQ-IN-4019

    REV.

    Q1

    MATERIAL REQUISITION FOR

    OIL METERING SYSTEM(MX-2000/ MX-2005)

    Q1 19/09/08 ISSUED FOR ENQUIRY MHN PMM PMM

    REV. DATE REASON FOR ISSUE PREPD CHKD. APPD. PM CLIENT

    FOR BIDDING PURPOSES ONLY

  • 7/27/2019 B193(R)-RQ-IN-4019

    2/6

    PAGE No.: 2

    PROJECT : B-193 FIELD DEVELOPMENT PROJECT, Owner Tender No.: MR/OW/MM/B-193/07(R)/2007

    TITLE: OIL METERING SYSTEM DOC. No.: B193(R)-RQ-IN-4019 REV. Q1

    TABLE OF CONTENT

    1.0 INTRODUCTION..........................................................3

    2.0 SUMMARY DESCRIPTION OF SCOPE OF WORK/SUPPLY...........................3

    3.0 TECHNICAL REQUIREMENTS................................................43.1 General Requirement........................................................4

    3.2 Meter Run Flow Measurement................................................43.3 Flow Computer:............................................................5

    4.0 VENDOR DOCUMENTS REQUIREMENT .........................................5

    5.0 INSPECTION AND TESTING................................................5

    6.0 INDEX TO ATTACHMENT...................................................6

  • 7/27/2019 B193(R)-RQ-IN-4019

    3/6

    PAGE No.: 3

    PROJECT : B-193 FIELD DEVELOPMENT PROJECT, Owner Tender No.: MR/OW/MM/B-193/07(R)/2007

    TITLE: OIL METERING SYSTEM DOC. No.: B193(R)-RQ-IN-4019 REV. Q1

    1.0 INTRODUCTION

    Oil & Natural Gas Corporation Ltd. (ONGC) under their tender ref MR/OW/MM/B-193/07(R)/2007intends to develop B-193 cluster fields comprising of seven oil /gas facilities viz. B-193A, B193AQ,B-172, B-178, B-179, B-180, B-28A and B-23A which are located in the Heera-Panna-Bassein blockof Bombay Offshore basin, about 60-90 km towards west of Mumbai city in water depth ranging from60 to 75m. The fields are in close proximity of giant Bassein gas field towards the south. ONGC hascarried out facilities optimization study for B-22 and B-193field development and included additionalfacilities.

    The development plan of B-193 cluster fields has been conceptualized in order to monetize theresources from the discovered fields that are located in the vicinity of main B-193 structure. Thesefields are of marginal nature and have high H2S & moderate CO2 content.

    Bassein Formation is the main oil bearing reservoir with minor oil/gas accumulations in Panna andMukta formations in B-193, B-178, B-179 and B-180 fields whereas Mukta formation is the mainreservoir in B-172 field with minor accumulations in Bombay and Alibaug formations. In B-28A field,Bassein and Panna formations are the main oil reservoirs followed by gas accumulation in Muktaformation. In B-23A field Panna formation is the main gas reservoir. These fields are in close

    proximity and all of them, except B-23A, have shown high H2S concentration in the range of 6000 to24,000 ppm except in B-28A where it is reported as 40,000 ppm. The CO2 concentration in all theabove fields is of the order of 4 to 6 % except in B-23A where it reported as 6 to 11.8%.

    The B-22 field which is at a distance of around 27 kms from B-193A process complex have 3 remoteplatforms which are gas producing where as B22 platform has gas as well as oil production. Oil

    production from B22 platform shall be transported to B-193 AP process platform for furtherprocessing to separate oil, water and gas for which additional liquid handling facilities for 42000

    BLPD at B-193 AP are provided. Additionally water treatment and pumping facilities, powergeneration, water injection at B-193AQ platform are provided which will have a 90 personsaccommodation.

    For B-193 Field Development Project, tender ref MR/OW/MM/B-193/07(R)/2007, the following

    major facilities are; B193-AP Well cum-Process platform.

    B-193-AQ 90 men living quarter cum Water injection cum power generation facilities platform

    bridge connected to B-193-AP.

    B172A, B178A, B179A.B28A-A,B23A-A Wellhead Platforms.

    Submarine pipelines of overall 116.5km of varying sizes

    Modifications at BCP-B complex and tie-in with the Heera Trunk line.

    2.0 SUMMARY DESCRIPTION OF SCOPE OF WORK/SUPPLY

    This specification with its attachments defines the technical requirements for the engineering,procurement, supply, inspection, testing, installation and commissioning of Oil metering packagesfor ONGCs B-193 Field Development Project.

  • 7/27/2019 B193(R)-RQ-IN-4019

    4/6

    PAGE No.: 4

    PROJECT : B-193 FIELD DEVELOPMENT PROJECT, Owner Tender No.: MR/OW/MM/B-193/07(R)/2007

    TITLE: OIL METERING SYSTEM DOC. No.: B193(R)-RQ-IN-4019 REV. Q1

    VENDOR shall be responsible for material supply, manufacture, co-ordination with all SUB-VENDORs, assembly, inspection, testing, surface preparation, preservation, packing, preparationfor shipment, shipment and delivery of the Oil Metering systems in accordance with this

    requisition, process data, attachments and applicable codes and standards. VENDOR is alsoresponsible for the above said items furnished by any SUB-VENDORs.

    3.0 TECHNICAL REQUIREMENTS

    3.1 General Requirement

    This specification outlines the minimum requirements for the design, manufacture, testing andsupply of ANSI 600 2 x 100% Oil Metering system. This Package shall consist of the followingcomponents:

    Oil Metering System, which shall comprise following component as a minimum:

    i) Structural skid including all structural steel, supports, lifting device for maintenance, stairs andaccess platforms where applicable.

    ii) One (1) ANSI 600 lb RF Inlet header with manifold for 2 x 100% capacity meter runs.iii) Two (2) meter runs, each comprising:

    Upstream and downstream isolation ball valves

    Basket Strainer

    Differential Pressure Indicator

    Pressure relief valve

    Coriolis flowmeter complete with field mounted transmitter

    iv) Field Junction boxv) One (1) ANSI 600 lb RF Outlet header with manifold for 2 x 100% capacity meter runs.vi) Dedicated Flow computers system; to be installed in the control room.

    Vendor shall come up with an accurate sizing for all above item listed based on attached processdata. All process wetted parts shall conform to NACE MR-01-75, latest edition. All castings &Weldings shall be 100% radiographed. All the above components shall be assembled, piped withinlet and outlet appropriately rated flanges, wired, tested and painted for offshore marine

    environment.

    For process fluid containing CO2 in excess of 2 PSI partial pressure, the instrumentation wetted partmaterials shall be as follows:

    < 71 deg C ASTM A182-F316 (316SS)

    > 71 deg C ASTM A182-F51 (2205 duplex steel)

    The vendor shall supply all the items shown within the battery limit of Oil Metering skid with

    associated instruments as per the enclosed P&ID, as a minimum. Any other item, not shown on theP&ID, but required to make the system complete and efficiently operable shall be supplied by theVendor.

    3.2 Meter Run Flow Measurement

    Coriolis Mass flowmeters shall be supplied for flow measurement and shall meet all therequirements as per the functional specification enclosed along with this requisition.

  • 7/27/2019 B193(R)-RQ-IN-4019

    5/6

    PAGE No.: 5

    PROJECT : B-193 FIELD DEVELOPMENT PROJECT, Owner Tender No.: MR/OW/MM/B-193/07(R)/2007

    TITLE: OIL METERING SYSTEM DOC. No.: B193(R)-RQ-IN-4019 REV. Q1

    The Coriolis Meter shall include the meter, transmitter and all other accessories necessary to make thesystem complete. The Vendor shall ensure that the sensor and all other wetted parts are shall conformto NACE MR-01-75 requirement.

    The following requirement shall be considered in Vendor proposal:

    The design shall be according to API MPMS 5.6

    Flanged end connections, rated for the associated piping class.

    Coriolis Flow Meters shall have an accuracy of 0.2% and repeatability of 0.05% or better.

    Material selection for the Coriolis flowmeters shall be as per the functional specification for

    Coriolis flowmeters

    Enclosure class for Coriolis flowmeter, local indicator and transmitter, shall be weather proof

    to IP 65 or better.

    3.3 Flow Computer:

    Flow Computer shall have the following features as a minimum

    Facility to calculate mass flow with pressure & temperature compensation

    Facility to calculate totalized flow value as per API requirements. It shall indicate volumetric

    flow, mass flow, totalized flow, temperature, pressure etc.

    Communicates with the DCS to provide process and totalisation data including but not limited

    to gross standard volumetric flowrate, net volumetric flow rate, mass flow rate, pressure,temperature, density, water cut, gross total daily volume, net total daily volume, daily averagedensity, daily average temperature and common alarms.

    For further technical details, refer to attached functional specification for liquid flow

    computer.

    4.0 VENDOR DOCUMENTS REQUIREMENT

    As part of the bid, vendor shall furnish the following document:

    Bill of Material

    Vendor filled in data sheets

    System Block Diagram Drawing

    P&ID

    Preliminary GA Drawing

    Weight data Technical catalogues

    5.0 INSPECTION AND TESTING

    The Vendor shall be responsible for the complete inspection and testing of the oil metering package inthe Vendors works and shall provide all equipment and personnel necessary to carry out the tests tothe satisfaction of the Company prior to Factory Acceptance Test (FAT), Flow test / SystemIntegration Test, Site Acceptance Test (SAT) and Commissioning.

  • 7/27/2019 B193(R)-RQ-IN-4019

    6/6

    PAGE No.: 6

    PROJECT : B-193 FIELD DEVELOPMENT PROJECT, Owner Tender No.: MR/OW/MM/B-193/07(R)/2007

    TITLE: OIL METERING SYSTEM DOC. No.: B193(R)-RQ-IN-4019 REV. Q1

    6.0 INDEX TO ATTACHMENT

    ITEM TITLE DOC./ DRG. NO.

    REV.

    NO.

    1.Functional Specification for Coriolisflow meter

    FS 3208 1

    2.Functional specification for Flowcomputer

    FS 3211 2

    3.Functional Specification ForInstrumentation For Equipment Package

    FS 3503

    4. Process data for Oil Metering System --- ---

    5. Corioilis Meter Datasheet

    6. Valve Specification --- ---

    7. Piping Class --- ---

    8. ONGC Specification:(to be attached by client)

    8.1 Instrument Design Criteria Section 3.6 (Vol II)

    8.2 General Specification For Definition Spec No. 1050 (Vol III)

    8.3 General Specification For Vendor DataRequirements

    Spec No. 1060 (Vol III)