End client: ONGC Client / Partner: SapuraKencana Location: Mumbai High Installation Vessel(s): Kreuz Supporter Water Depth: 60 - 110 MSW Commencement Date: March 2017 Completion Date: April 2017
Kreuz Subsea’s diving sup-port and construction barge has been engaged performing construction and installation scopes for B-127 project in Mumbai High.
Installation scope included 16” pipeline sectional replace-ments using pipe end con-nectors, stalk-on and spooled risers, SBM removal and pre-commissioning support.
Spool installation
B-127 Project Mumbai High
Project Datasheet
Going beyond limits
� 2 x 16” stalk-on risers
� 2 x 6” and 16” tie-in spools
� 1 x 16” SPRU alongwith tie-in spool installation
� 1 x 8” installation of pig launcher
� 1 x bow string installation
� Installation of riser protection frame
� 3 x hydro-testing of spools
� Installation of double elevated and single ele-
vated bow strings
1 x SBM Removal
Tie-in spool installation
SPRU with spool
Riser Stalk-on
www.kreuzsubsea.com
Construction Scope
Removal / Decomm Scope
SPM decomm and removal
Supervisors performed well.. Good
Procedures..