B0405

3
 Part B - Information Systems and Information Technology Solutions B .4.5. S electing a n A cquis ition A lternat ive  An objective comparison of options for the acquisitio n of software application s is rarely possible. A completely objective analysis can be done only if one assumes that absolutely equivalent systems would be acquired and only the manner of acquisition would differ. Table 1  compares the four software acquisition alternatives.

description

B0405

Transcript of B0405

  • Part B - Information Systems and Information Technology Solutions

    B.4.5. Selecting an Acquisition Alternative

    An objective comparison of options for the acquisition of software applications is rarely possible. Acompletely objective analysis can be done only if one assumes that absolutely equivalent systemswould be acquired and only the manner of acquisition would differ. Table 1 compares the foursoftware acquisition alternatives.

  • Part B - Information Systems and Information Technology Solutions

    Table 1. Summary of Project Requirements and Application Software Acquisition Alternatives

    Acquisition AlternativeProject

    Requirement In-houseDevelopment

    ContractDevelopment

    PurchasedPackage

    (Turn-key)

    TransportedSystem

    Contract Not applicable Tight control of costAnd schedules;recourse againstcontractor possible;may includewarranty andsupport

    Predefined costand schedule; easeof specificperformancestatement;recourse againstvendor welldefined; shouldinclude warrantyand supportprovisions

    Not normallyavailable

    Development orAcquisition Cost

    High High Moderate Low

    Implementation Cost High to moderate High to moderate Moderate to low High to lowSystems' Reliability Moderate Moderate to high High Moderate to lowFlexibility inMeeting User'sRequirements

    Excellent Excellent Moderate Minimal

    Maintenance andEase of Modification

    High with permanentin-house staff,difficult otherwise

    High with supportcontract, low without

    High if performedby vendor,probably extremelydifficult otherwise

    Limited to supportavailable fromoriginal developerand quality ofdocumentation

    Confidence in FinalProduct's Operation(1-4) where 1 = low

    2. (assumingcompetent staff)

    3. (assumingcompetentcontractor)

    4. (assumingproven package)

    1. (assuming nopreviouswidespreaddistribution)

    Planning andAnalysisRequirement

    Full conceptual planRequired; generalAnalysis completed;minimal detaildesign required

    Full conceptual planrequired; generalanalysis completed;full detail designdefined; milestonesdefined; projectmanagement plancompleted

    Conceptual plannecessary forpackage selection;general analysiscompleted foradaptation; nodetail designrequired

    Conceptual plannecessary forpackage selection;general analysiscompleted foradaptation; nodetail designrequired

    ImplementationTime/complexity(1-4) where 1 = best

    3. 2. 1. 4. (generality anddocumentationproblems)

    Staffing Needed Projectmanagement,administrativefunctions,systems analysis,systems design,programming

    Projectmanagement,administrativefunctions,systems analysis

    Administrativefunctions,minimal projectmanagementrequired

    Projectmanagement,administrativefunctions,programming (ifoutside support isunavailable)

    Major PotentialProblems

    Technical staffing,personnelmanagement,project management,cost control, controlof system scope

    RFP preparation,contracting, projectadministration,contractor reliability,staff acceptance ofsystem, long-termsupport

    Packagecapabilities andadaptability, staffacceptance ofsystem,maintenance,modifications,upgrading, long-term support

    System capabilitiesand adaptability,reliability,implementationsupport and cost,documentation,long-term support,maintenance,upgrading,modification,staffacceptance

  • Part B - Information Systems and Information Technology Solutions

    Although theoretically possible, this assumption is unlikely to be the case except possibly in acomparison of in-house development and contract development. The following assumptions aboutacquisition alternatives could reflect a more realistic set of circumstances:

    The in-house staff is competent, but not as experienced or technically strong overall as thestaff a good contractor could provide, and there will be turnover in the in-house staff.

    The contractor has worked in the same or a closely related application area, will not be proneto miss schedules, and will not fully comprehend all aspects of the hospital's managementrequirements.

    The packaged system comes close to the actual requirement but will require modification,and the package has been successfully installed beyond its original development point.

    The transported system was originally developed to meet a very specific set of requirementsfor another facility and it is not well documented.

    Each of the four alternatives offers inherent advantages and disadvantages. However, all the optionsshare several basic requirements:

    Determination of minimum system requirements must precede any move to acquire aninformation system.

    Planning for the implementation process must be carefully developed and documented well inadvance.

    Policies and procedures to support the systems must be established before implementation iscomplete.

    Management commitment to and support of the system must be very strong and evident.

    In many situations, the best approach may well be a combination of the four options. For example, areliable system might be available from another health organization or an independent softwarevendor that appears to meet the majority of the organization's needs. In this case, a contractor couldbe employed to make modifications to the software and assist in implementation planning andconversion. In-house staff could be hired to assist in the modification process, conduct staff training,provide conversion support, and provide long-range system maintenance.