Improving the Quality of your Microsoft Project 2010 Schedule

Page 2: B leach

Why Have Scheduling Software?

Page 3: B leach

The Key to a High Quality Schedule

Page 4: B leach

The Key to a High Quality Schedule

Page 5: B leach

In the World of the Biggest Projects . . .

Page 6: B leach

The Need for A Good Critical Path

“In most cases, 99.9% of the time, we can't produce a valid critical path.”

- Mike Beattie, Defense Contract Management Agency (DCMA), May 2007

Page 7: B leach

Schedule Quality Is . . .• Trust – Is it the truth? Are the Tasks, Resources, Assignments, Costs, Actuals,

etc. accurate?• Fidelity – Is the critical path really the critical path? • Detail – Does it contain the right level of detail?

Trust

DetailFidelity

Page 8: B leach

Schedule Quality Is Not . . .• Performance Problems• Defects in the Deliverables• Scheduler Quality

Trust

DetailFidelity

Page 9: B leach

Ten Common and Serious Problems

Page 10: B leach

1. Missing Predecessors

Task A

Page 11: B leach

2. Missing Successors

Task B

Page 12: B leach

3. Use of Constraints

Must Start OnMust Finish OnStart No Later ThanFinish No Later Than

A slip here . . . . . . won‘t cause a slip here.

As Late As PossibleStart No Earlier ThanFinish No Earlier Than

Hard Constraints Soft Constraints

Page 13: B leach

3. Use of Constraints

Will your schedule pass the push test?

Page 14: B leach

4. Lags

Lag

Page 15: B leach

5. Leads

Lead

Page 16: B leach

6. Planned Start in the Past

Task A

Status Date(or today if no Status

Date)

Hasn’t Started Yet

Task A has a planned Start Date in the past but hasn’t started. The existing Planned Start Date cannot be trusted!

Page 17: B leach

7. Actual Date in the Future

Status Date (or today if no status date)

Task C

Page 18: B leach

8. Summaries With Resources

Summary Task B

Task B1Task A Task B2

Page 19: B leach

9. Summary Tasks With Links

Summary Task B

Task B1Task A Task B2

No!

Yes!

Page 20: B leach

10. Manual Scheduling

Task A

Page 21: B leach

The Impact of Poor Schedule Quality• Don’t Know True Project Finish Date• Rework• Schedule Slippage• Budget Overruns• Lack of trust

Page 22: B leach

A “Spell Checker” for Microsoft Project

Page 23: B leach

5 Second Commercial

Page 24: B leach

Improving the Quality of your Microsoft Project 2010 Schedule