AY1516 Cuthbert's Reflections on LTA C923

download AY1516 Cuthbert's Reflections on LTA C923

of 14

Transcript of AY1516 Cuthbert's Reflections on LTA C923

  • 8/18/2019 AY1516 Cuthbert's Reflections on LTA C923

    1/14

    Name: Cuthbert Yeo, Year 4

    Organisation: Land Transport Authority

    Area of Specialisation: Geotechnical/Project Management

    VIP period: 18 May 15 – 6 Aug 15

    Designation: Site Intern @ C923 Upper Changi Station

    Personally, I really felt the need to see for myself what I have actually learnt so far from school that is

    applied in reality, so I have requested from HR to place me on site nearest to my house. I was posted to

    C923 Upper Changi Station of Downtown Line 3 Package C which would complete by 2017. Only

    Entrance A was Top-Down (with secant bored piling) and the rest of the station box was constructed

    Bottom-Up (with Dwall). This is a Design-Bid-Build project.

    C923 site surrounded by various stakeholders; sheltered walkway to be provided within 400m radius ofstation to provide better connectivity for commuters to ride.

  • 8/18/2019 AY1516 Cuthbert's Reflections on LTA C923

    2/14

    The beginning weeks were rather daunting. I was inundated with meetings (project

    safety/risk/design/instrumentation audit/concrete casting plans/CD Door inspections@Yongnam

    factory/PDM/QPs audit/weekly and bi-weekly progress meetings from main contractor Samsung C&T) as

    well as policies that you have to pick up and be aware of in 1 to 2 weeks’ time (mainly your TR26, CP65

    Concrete bible, CP4 Foundation, LTA Construction Safety Handbook, LTA Materials and Workmanship

    (M&W) Specifications bible and Civil Design Criteria RevA1 as well as some BCA Advisory) so that you

    understand what is exchanged on the meeting tables. They can be found here:

    https://www.lta.gov.sg/content/dam/ltaweb/corp/Industry/files/Construction_Safety_Handbook.pdf  

    and this VIP: https://www.corenet.gov.sg/general/e-info/codes-and-regulations.aspx 

    After you’re done, quickly move on to method statements (so that deviations can be spotted during PGI),

    design change reports and GIBR for borelogs and preliminary damage assessment reports by consultants.

    In my case, these were done by MEINHARDT, Amberg and instrumentation readings by TRITECH.

    It is important to get the hang of how the drawings are to be read based on sections or gridlines (in my

    case 1xGL ~ 11.6m) as well as understand their shorthand acronyms. You also have to make the personal

    effort to break the ice and establish good relationships with not only your colleagues from your site

    office, but also those from the main contractor and QPs teams. What I did was to went round the

    Samsung C&T office and Parsons Brinckerhoff office and introduced myself personally and for staffs who

    aren’t around at their tables, you could leave a POST-IT note leaving your name and school email (or HP

    number if you really need to) so that you can get the required information you need later in your report.

    It is good to do all of this early so it wouldn’t be so awkward later.

    I will now briefly elaborate as much as I can remember in these 13 weeks based on topics:

    Diaphragm Wall (Dwall) similar to CE3115

    I was guided by HENO Hafiz on construction of Dwall.

    The general sequence is to survey, mark, then hoard the areaperform trial trench whenever utilities

    or SPPG or Singtel cables are thereconstruct guide wall(control alignment of box cutter)setup

    bentonite plant (foundation has to be PE calc; pipes embedded must be properly connected; concreting

    slurry to be fresh and not reused; working slurry can be reused)mobilise excavator then grab cutter

    then box cutter(increasing depth for different reach of machine; bite sequence shown below

    pic)KODEN machine to test vertical profile of trenchStop ends with water stops placed at corners of

    panels to be castedRebar cage inConcreting through surging( where concreting bentonite slurry

    floats up as concrete is tremie in; with pipe at least 3m embedded to prevent re-entry of slurry; RFI first

    then cast!)Stop ends are removed when concrete still green leaving behind the water stop

    (hydrophilic water strips)

    https://www.lta.gov.sg/content/dam/ltaweb/corp/Industry/files/Construction_Safety_Handbook.pdfhttps://www.lta.gov.sg/content/dam/ltaweb/corp/Industry/files/Construction_Safety_Handbook.pdfhttps://www.corenet.gov.sg/general/e-info/codes-and-regulations.aspxhttps://www.corenet.gov.sg/general/e-info/codes-and-regulations.aspxhttps://www.corenet.gov.sg/general/e-info/codes-and-regulations.aspxhttps://www.corenet.gov.sg/general/e-info/codes-and-regulations.aspxhttps://www.lta.gov.sg/content/dam/ltaweb/corp/Industry/files/Construction_Safety_Handbook.pdf

  • 8/18/2019 AY1516 Cuthbert's Reflections on LTA C923

    3/14

     

    Any bulge would then be hacked. Major cracks or water seepages would then be Polyurethane grouted

    depending on the severity of the finishes. If honeycombs were found in panels, they would be hacked,

    BRC and casted. 

  • 8/18/2019 AY1516 Cuthbert's Reflections on LTA C923

    4/14

    Key problems faced and solutions implemented are summarized in mindmap below:

  • 8/18/2019 AY1516 Cuthbert's Reflections on LTA C923

    5/14

    Utilities Gap and Diversion

    I was guided by

    ENO Vasu on

    utility gaps. (See

    Instrumentation

     for settlement

    limits of utilities

    as an example)

    The utilities were

    either supported

    by I-beams or

    concrete

    haunching.

    Most of the utilities were not diverted despite being in the way of the designated construction area due to

    the high cost of fines imposed for damages. The presence of the utilities would impede the use of grab

    cutters or BAUER box cutters in the construction of diaphragm wall. Hence, the construction of diaphragm

    wall beneath these utilities was constructed in stages as excavation progress. Based on the soil condition,

    the utility gap excavation may vary with different depth and with or without the use of BRC. Exposed soil

    surface at utility gap must be monitored for water seepage or soil collapse. Lean concrete was used as soilprotection wall to protect the soil face from collapse. At every section of the utility gap, hydrophilic strips

    and re-groutable tubes would be installed along the perimeter of the opening to manage the water

    seepage through the construction joint. After the main reinforcement is installed, formwork installation

    follows and gaps will be casted with C40 concrete between existing Dwalls.

    PUB, SP telecom and SPPG utilities

    clearly surveyed and marked.

  • 8/18/2019 AY1516 Cuthbert's Reflections on LTA C923

    6/14

    Strutting with Bottom-Up Approach similar to CE5108/CE5112

    I was guided by SPE Karthigesh on strutting systems used. It was unusual to use 3xUB as struts for deep

    excavations (usually 2xUB) until after 2005. This also meant greater emphasis of settlement or

    deflection readings by TRITECH and contractors. The lack of openings requires the Sub contractor

    YONGNAM to lower all the struts in pieces. These pieces of struts would then be preloaded with

    hydraulic jacks, before assembling them on site and installing them at required levels. For diagonal

    struttings, shear ankles has to be placed between the waler and concrete packing; this would also mean

    longer time for hacking and removal as compared to 20.2m long horizontal struts. LTA requires

    reinforced concrete strutting system for certain area in this project.

    Hydraulic Jacks used to preload

    the horizontal struts

  • 8/18/2019 AY1516 Cuthbert's Reflections on LTA C923

    7/14

    Minimum of 2 Strain gauges attached on web of struts

    Omission of S7 @Section F-F and G-GThis deep excavation requires 7 struts initially, which contractors themselves later found the last

    unnecessary and the final strut (S7) was omitted at Section F-F and Section G-G. I made the attempt to

    do a similar soil modelling with the help of FEM analysis tool PLAXIS. The estimated excavation depth

    during construction is approximately 28m below existing ground level. The following results were found:

  • 8/18/2019 AY1516 Cuthbert's Reflections on LTA C923

    8/14

     

  • 8/18/2019 AY1516 Cuthbert's Reflections on LTA C923

    9/14

     

  • 8/18/2019 AY1516 Cuthbert's Reflections on LTA C923

    10/14

     

  • 8/18/2019 AY1516 Cuthbert's Reflections on LTA C923

    11/14

     

  • 8/18/2019 AY1516 Cuthbert's Reflections on LTA C923

    12/14

     

    BCA Advisory Note on ERSS: https://www.corenet.gov.sg/einfo/Uploads/Circulars/CBCA090402.pdf  

    Comparisons of design results from FEM programme, actual strain gauge readings from TRITECH and

    ultimate deflection limits imposed by BCA would then be compared to see if they meet serviceability

    state requirements. BCA also requires the analysis in the event of a one strut failure. When all

    requirements are satisfied would then validate the omission of S7 strut from initial design.

    Instrumentation similar to CE4216C923 tunnel and station box is mainly situated in Old Alluvium (OA). Hence, most report took only

    drained analysis. EC7 requires both drained and undrained analysis. Also, with the presence of

    important services and live utilities, settlement is closely monitored with settlement markers and optical

    prisms to ensure they do not reach alert level or work suspension level. For example, for C923 project,

    Singtel Submarine cable can only settle no more than 5mm; 15mm or more settlement would cause a

    SWO. Monitoring frequency is arranged prior to and during excavation as well as during and after

    backfilling. It is important for instruments to be placed in sets (in the event one spoils; the next closest

    reading would provide an equally realistic result) as well as to monitor the drawdown of groundwater

    table for excavations.

    https://www.corenet.gov.sg/einfo/Uploads/Circulars/CBCA090402.pdfhttps://www.corenet.gov.sg/einfo/Uploads/Circulars/CBCA090402.pdfhttps://www.corenet.gov.sg/einfo/Uploads/Circulars/CBCA090402.pdfhttps://www.corenet.gov.sg/einfo/Uploads/Circulars/CBCA090402.pdf

  • 8/18/2019 AY1516 Cuthbert's Reflections on LTA C923

    13/14

     

    TR26 –  Technical Reference for Deep Excavations 

    Site Language and Work Culture

    Relationships between supervisors and workers must be good to ensure good exchange of information.

    Whatsapp messenger is pretty much abused when reporting on site conditions haha, so it’s important

    that you are in the group chat. It is also important to learn the Chinese, Blangadashi and Korean

    language (in my case of Korean engineers) when communicating with the worker on progress of works.

    The following are some important phrase you should learn to effectively communicate with workers:

    Blangadashi Meaning in English

    Shobu Shakal Good Morning

    Shobu Dopul Good Afternoon

    Shobu Aso Good EveningTara Teri Faster

    Astei Astei Slowly

    Aseh Yes

    Nei No

    Ak 1

    Dul 2

    Tin 3

  • 8/18/2019 AY1516 Cuthbert's Reflections on LTA C923

    14/14

    Cha 4

    Pass 5

    Dono Butt Thank You

    I must say the work culture and perks given by LTA can be pretty good! There is travel credit provided to

    full time personals and welfare events like yoga, dragonboat and even floorball for you to interact withthe people from other departments like the project, contracts or design teams even!

    Floorball welfare organized monthly around months end by Racheal