Avoided Cost and E3 Calculator Workshops Energy and Environmental Economics, Inc. October 3, 2005.
-
Upload
allyson-hutchinson -
Category
Documents
-
view
213 -
download
1
Transcript of Avoided Cost and E3 Calculator Workshops Energy and Environmental Economics, Inc. October 3, 2005.
Avoided Cost and E3 Calculator Workshops
Energy and Environmental Economics, Inc.
October 3, 2005
Review of E3 Avoided Costs
Background Overview of the Methodology Valuation of Peak Hours Utility-specific Data
Information on New Avoided Costs
Spreadsheets and reports can be downloaded free from the E3 website:
http://www.ethree.com/cpuc_avoidedcosts.html
Avoided Cost Objectives Goals:
Provide objectively derived estimates of avoided costs that are suitable for evaluating PUC funded programs
Develop a transparent and repeatable costing methodology that does not rely on either proprietary data or models
Deliverables: Transparent and defensible avoided cost methodology
Separate presentations with proposals for each cost component Make use of existing studies and data to the extent possible
Provide software to update estimates of avoided costs Provide a report describing methodology, results, and data to
support estimates
Summary of Project Requirements
Forecast values (2004-2023) for:
X = RFP Requirement; R = E3 Recommendation
Annual Values
Monthly Values
Hourly Values
Vary by Location
Traditional avoided costsElectric generation X RElectric T&D X R RNatural gas procurement X R RNatural gas transportation X R R
Environmental externality X RReliability adder XDemand Reduction Benefit X R
Additional avoided costs (gas and electric)
Electric Avoided Cost Dimensions
UtilitiesPG&ESCESDG&E
Voltage LevelTransmissionPrimarySecondary
Dimensions of the Electric Avoided Cost(8760 Hours from 2004 to 2023)
PG&E: 9 | 18SCE: 8 | 5SDG&E: 4 | 1
Climate Zones | Planning Areas
Avoided Cost Selection NPV InputsComponent Included in
Hourly Calculation
Utility 1 Life (Years) 20
Climate Zone Discount Rate 8.15%
Division 3 Annualization 10%
Voltage Level 3
Utility Control Panel
PG&E
Secondary
Weighted Average
4
Prior Electric and Gas Avoided Costs
Prior Electric and Gas Avoided Costs
$0.00
$0.02
$0.04
$0.06
$0.08
$0.10
$0.12
$0.14
Env.Ext.
T&D
Gen
Electric Electric ($/kWh)($/kWh)
Gas Gas ($/Therm)($/Therm)
$0.00
$0.10
$0.20
$0.30
$0.40
$0.50
$0.60
$0.70
$0.80
2002
2003
2004
2005
2006
2007
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
Env.Ext.
T&D
Commodity
Source:Energy EfficiencyPolicy Manualp 24-2511/29/01
The New Costing Framework
200?: 2.84% * $60.00/MWh = $1.70/MWh of load
Conceptual Framework
Electric Avoided Costs / BenefitsElectric Avoided Costs / Benefits
Gas Avoided Costs / BenefitsGas Avoided Costs / Benefits
Where a = area, t = time dimension (e.g., hour, TOU period), y = year.
TotalBenefita,h,t = GenMCa,t,y + Externalitya,t,y + TransMCa,t,y + DistMCa,t,y
+ Reliabilitya,t,y + DemandReductionBenefita,t,y
TotalBenefita,t,y = Commoditya,t,y + Transportationa,t,y + Externalitya,t,y
+ DistMCa,t,y + DemandReductionBenefita,t,y (if available)
Formulation of Avoided CostElectric
Period 1 (2004-2008)Platt’s / NYMEX
Period 2Transition
Period 3 (2008-2023)LRMC
1 + Ancillary Services (A/S)
Period 1 (2004-2008)NYMEXPeriod 2
TransitionPeriod 3 (2008-2023)
Long-run Forecast
1 + LUAF + Compression
Commodity
Natural GasCommodity
Market Multiplier
1 + Energy Losses
T&D Costs (1 + Peak Losses )
Environment (1+ Energy Losses)
T&D Costs
Environment
+
+
+
+
• “NYMEX” = “New York Mercantile Exchange”• “LRMC “ = “Long-run marginal cost” = all-in cost of a combined cycle gas turbine (CCGT)• “LUAF “ = “Loss and unaccounted for”
Components that Contribute to Shape
Components with Peak Shape
Energy and capacity Ancillary Services Market Elasticity Transmission and Distribution Capacity Losses Emissions
Inputs that Vary by Utility
Energy and capacity (A/S, environment)Northern and Southern California
T&DVaries by 16 climate zones in the State
LossesAverage and peak losses by IOU
Commodity Shape: Example NP15
1
5
9
13
17
21
1 2 3 4 5 6 7 8 9 10 11 12
0.00
10.00
20.00
30.00
40.00
50.00
60.00
70.00
Hours
MonthsHour
Ave
rag
e o
f H
ou
rly
Val
ues
by
Mo
nth
Price Duration Curve
0
20
40
60
80
100
120
140
160
1
484
967
1450
1933
2416
2899
3382
3865
4348
4831
5314
5797
6280
6763
7246
7729
8212
8695
Hours
NP
15 M
arke
t P
rice
Sh
ape
Average of period 4/1/1998 through 3/31/2000 – Matched by Daytype
Market Price Forecast Results Annual Average Forward Price Estimate
Market Price Forecast by Utility
0
10
20
30
40
50
60
70
80
90
2004
2006
2008
2010
2012
2014
2016
2018
2020
2022
Year
Mar
ket
Pri
ce (
No
min
al $
/MW
h)
PG&E
SDG&E
SCE
Market LRMC
Market Prices Updated as of October 15, 2003
Example of Capacity Separation Integral of the light blue area is the
capacity cost.
0.00
20.00
40.00
60.00
80.00
100.00
120.00
140.00
1
251
501
751
1001
1251
1501
1751
2001
2251
2501
2751
3001
3251
3501
3751
4001
4251
4501
4751
5001
5251
5501
5751
6001
6251
6501
6751
7001
7251
7501
7751
8001
8251
8501
8751
Hours
$/M
Wh
CT Energy Margin
CT Operating Costs
NP15 2005 Market Prices
Average CEC Variable Cost
827 Hours of CT Operation
Energy Losses by TOU PeriodPG&E LossesDescription Transmission Primary SecondarySummer On-Peak 1.024 1.058 1.109Summer Shoulder 1.010 1.042 1.073Summer Off 1.012 1.036 1.057Winter On-Peak - - -Winter Shoulder 1.012 1.039 1.090Winter Off 1.017 1.040 1.061
SDG&E LossesDescription Transmission Primary SecondarySummer On-Peak 1.009 1.036 1.081Summer Shoulder 1.009 1.034 1.077Summer Off 1.007 1.027 1.068Winter On-Peak 1.010 1.038 1.083Winter Shoulder 1.008 1.033 1.076Winter Off 1.007 1.027 1.068
SCE LossesDescription Transmission Primary SecondarySummer On-Peak 1.029 1.061 1.084Summer Shoulder 1.027 1.057 1.080Summer Off 1.025 1.050 1.073Winter On-Peak - - -Winter Shoulder 1.027 1.054 1.077Winter Off 1.024 1.047 1.070
A/S Cost Computation
Average of A/S costs as share of total energy costs, during non-crisis period (8/99-5/00, 8/01-7/03): 2.84%
Apply 2.84% to shaped hourly energy price 2004: 2.84% * $45.57/MWh = $1.29/MWh of load 2005: 2.84% * $46.65/MWh = $1.32/MWh of load
A/S Costs are the same multiplier for the entire state.
Market Elasticity Estimates
Month On-Peak Off-PeakJanuary NA 1.30February NA 1.35March NA 1.40April NA 1.32May 1.60 1.42June 1.85 1.62July 1.30 1.57August 1.47 1.44September 1.73 1.27October 1.05 1.02November NA 1.19December NA 1.30
On-Peak Off-PeakJanuary 100% 100%February 100% 100%March 100% 100%April 100% 100%May 108% 100%June 109% 100%July 107% 100%August 107% 100%September 109% 100%October 105% 100%November 100% 100%December 100% 100%
On-Peak: 8am to 6pm, Working Weekdays, May to OctoberOff-Peak: All Other Hours
Market ElasticityMarket Multiplier
(On Peak RNS = 5%)
T&D Formulation
T&D Capacity T&D Capacity
Cost ($/kW-yr)Cost ($/kW-yr)
YearYear
UtilityUtility
Planning AreaPlanning Area
PeakPeak
AllocationAllocation
HourHour
Climate ZoneClimate Zone
(1 + Losses)(1 + Losses)
UtilityUtility
Voltage levelVoltage level
T&D Capacity T&D Capacity
Cost ($/kW-hr)Cost ($/kW-hr)
YearYear
HourHour
UtilityUtility
Planning AreaPlanning Area
Climate ZoneClimate Zone
Voltage LevelVoltage Level
** ** ==
Item
Item
Dim
en
sio
Dim
en
sio
nn
T&D Capacity $/kW-year{Year}
T&D Allocation{Climate Zone,
Hour}
1 + Peak Losses{Utility, Voltage
Level}
Transmission andDistribution
{Utility, ClimateZone, Voltage
Level, Hour, Year}
* *
T&D Capacity $/kW-year{Year}
T&D Allocation{Climate Zone,
Hour}
1 + Peak Losses{Utility, Voltage
Level}
Transmission andDistribution
{Utility, ClimateZone, Voltage
Level, Hour, Year}
* *
Climate zones and planning
areas
North Valley
NorthCoast Sierra
Sacra-mento
Stockton
Kern
Yosemite
Fresno
LosPadres
CentralCoast
North Valley
Sacramento
North Coast
De Anza
Stockton
Yosemite
San JosePeninsula
EastBay
Diablo
Central Coast
San Francisco Mission
See detail map for divisions in San
Francisco Bay Area
San Francisco Bay Area detail map
PG&EServiceTerritoryDivision
Map
NorthBayNorth
Valley
NorthCoast Sierra
Sacra-mento
Stockton
Kern
Yosemite
Fresno
LosPadres
CentralCoast
North Valley
Sacramento
North Coast
De Anza
Stockton
Yosemite
San JosePeninsula
EastBay
Diablo
Central Coast
San Francisco Mission
See detail map for divisions in San
Francisco Bay Area
San Francisco Bay Area detail map
PG&EServiceTerritoryDivision
Map
NorthBay
Dominguez Hills
Foothill
Rural
Santa Ana
Ventura
CEC Title 24
Climate Zones
T&D Avoided Costs by Planning Division
SDG&E
$77.76
SCE
$36.00
$21.00
$5.00
PG&E
$70.00
$38.00
$5.00
Calculation of the PCAFs is based on Load Duration Curve of Each Area
1 125 …8,600 8,700 8,760
Hours
LOAD
KW
PCAF’s
1 Std Deviation
PCAF weights are assigned proportionally to how high the load is compared to the peak.
Load Duration Curve
Only highest load hours (top standard deviation) receive any weight.
Allocation of T&D Based on Temperature by Climate Zone
Temperature Loads T&D Capacity Cost
Drives Drives
Load Information Missing or Difficult to Obtain in Many Areas
Temperature
Use temperature as a proxy for load, and as the basis for allocating costs to
hours of the year.
T&D Capacity Cost
T&D AllocationActual Load vs. Temperature
Fresno
Yellow8am to 10pm
Similar analysis done on 33 PG&E areas as part of CEC Title 24 development
PCAF / Load Relationship Shown Chronologically
-
50
100
150
200
250
300
6/1/99 6/21/99 7/11/99 7/31/99 8/20/99
Date
Lo
ad (
MW
)
0%
2%
4%
6%
8%
10%
12%
PC
AF
Wei
gh
t
Load (MW)
PCAF
Example Results for PG&E Stockton based on TMY Weather
15
913
1721
14
710
$0
$50
$100
$150
$200
$250
Hour
Month
Levelized Avoided Cost by Month and Hour ($/MWh)
$200.00 - $250.00
$150.00 - $200.00 $100.00 - $150.00
$50.00 - $100.00
$- - $50.00
Peak Losses
Utility Avoided CostTransmission Primary Secondary
PG&E Distribution 0 1 1.0065Transmission 1 1.0318 1.0385
SDG&E Distribution 0 1 1.0140Transmission 1 1.0251 1.0395
SCE Distribution 0 1 1.0218Transmission 1 1.0364 1.0591
Customer Level
Environmental Cost Formulation
NOx $/MWh{Hour, Year}
PM10 $/MWh{Hour, Year}
CO2 $/MWh{Hour, Year}
NOx Cost $/Ton{Year}
Emission RateTon/MWh
{Hour}
PM10 Cost $/Ton{Year}
PM10Emission Rate
Ton/MWh{Hour}
CO2 Cost $/Ton{Year}
CO2 EmissionRate Ton/MWh
{Hour}
Emissions{Voltage Level,
Hour, Year}
* * *
1+Energy Losses{Voltage Level,TOU Period}
* 1+Energy Losses{Voltage Level,TOU Period}
1+Energy Losses{Voltage Level,TOU Period}
* *
$/MWh Emissions Costs & Plant Heat Rate
02000400060008000
10000120001400016000
$- $2.00 $4.00 $6.00 $8.00 $10.00
$/MWh
He
at
Ra
te
Emission Prices & Plant Heat Rates
• Includes NOx, PM-10, and CO2 emission credit prices• Lower bound of heat rate is set at a 6,240 heat rate, upper bound is set at a
14,000 heat rate
Putting the Components Together:Base Case Results
Total Avoided Cost - 8760 hours by 20 years
{Utility, Climate Zone, Voltage Level, Hour, Year}
Commodity{Utility, Voltage
Level, Hour, Year}
Transmission andDistribution
{Utility, ClimateZone, Voltage
Level, Hour, Year}
Emissions{Voltage Level,
Hour, Year}
14
710
1316
1922
14
710
$0
$50
$100
$150
$200
$250
Hour
Month
San Jose: Levelized Avoided Cost by Month and Hour ($/MWh)
$200.00 - $250.00
$150.00 - $200.00
$100.00 - $150.00
$50.00 - $100.00
$- - $50.00
T&D Costs
Total Electric Avoided Costs
Shape is Based on PG&E’s San Jose Planning Division
3 Day Snapshot of Disaggregated Electric Avoided Costs
Total Avoided Costs
$-
$50
$100
$150
$200
$250
1 8
15
22 5
12
19 2 9
16
23
Hour of Day
$/M
Wh
Distribution
Transmission
CO2
PM10
NOX
Multiplier
AS
Generation
14-Jul 15-Jul 16-Jul
2004
Avoided Cost is Based on PG&E’s San Jose Planning Division
Comparison of Efficiency Programs
• Levelized Avoided Cost ($/MWh) over 16 Year Life for All Devices• AC Load Shape Based on SEER 12 to SEER 13 Change in Fresno• New Avoided Costs are based on PG&E, Climate Zone 13, Secondary• Based on hourly simulated AC data, proxy outdoor lighting, flat refrigeration
Comparison of Avoided Costs for 3 Example Measures
$0.00
$20.00
$40.00
$60.00
$80.00
$100.00
$120.00
$140.00
New
Existin
gNew
Existin
gNew
Existin
g
We
igh
ted
Ave
rag
e
Avo
ide
d C
os
t(L
ev
eli
zed
$/M
Wh
)
$0.00
$0.02
$0.04
$0.06
$0.08
$0.10
$0.12
$0.14
Le
ve
lize
d $
/kW
h
Generation T&D Environment $/kWh
AirConditioning
OutdoorLighting
Refrigeration