Authorities involved in the project :
-Obtain Water Approval Water related approvals are regulated by Water Services Industry Act 2006, section 45
Agency: Water Authority SYABAS
-Obtain Sewerage Approval
Agency: Sewage Services Department IWK
-Obtain Fire Safety (Arch) Comment Fire safety procedures are regulated by Fire Services Act 1988 and Uniform Building Bylaws 1984 (Chapter 8)
Agency: Fire Department
-Obtain Hoarding & Signboard Approval Agency: Municipality of Kuala Lumpur DBKL
-Obtain RORO Bin Approval Agency: Municipality of Kuala Lumpur DBKL
-Obtain Earthwork Approval Agency: Municipality of Kuala Lumpur DBKL
-Obtain Road and Drainage Approval Agency: Municipality of Kuala Lumpur DBKL
-Obtain Landscape Approval Agency: Municipality of Kuala Lumpur DBKL
-Obtain Street Lighting Approval Street lightning regulations are governed by Street, Drainage and Building Act, 1974 Agency: Municipality of Kuala Lumpur DBKL
-Obtain Car Park Approval Agency: Municipality of Kuala Lumpur DBKL
-Obtain MSMA (Manual Saliran Mesra Alam )and SPAH (Sistem Penuaian Air Hujan ) Approvals Agency: Municipality of Kuala Lumpur DBKL
-Obtain Building Plan Approval Agency: Municipality of Kuala Lumpur DBKL
-Obtain Fire Safety (M&E) Approval Agency: Fire Department BOMBA
-Obtain Permission to start work from Building Department (KMB) Agency: Municipality of Kuala Lumpur DBKL
-Notification to start Earthwork from Engineering Department (B FORM) Agency: Municipality of Kuala Lumpur DBKL
-Notification to Start Sewerage Work (PDC 6) Agency: Municipality of Kuala Lumpur DBKL
-Request sewerage inspection Agency: Sewage Services Department IWK
-Sewerage inspection Agency: Sewage Services Department IWK
-Sewerage report Agency: Sewage Services Department IWK
-Request Road & Drainage Clearance Agency: Sewage Services Department IWK
-Road and Drainage Inspection Agency: Municipality of Kuala Lumpur DBKL
-Road and Drainage Report Agency: Municipality of Kuala Lumpur DBKL
-Request Sewerage Clearance Agency: Sewage Services Department IWK
-Sewerage Inspection Agency: Sewage Services Department IWK
-Sewerage Report Agency: Sewage Services Department IWK
-Request Fire Safety Clearance Agency: Fire Department
-Fire Safety Inspection Agency: Fire Department
-Fire Safety Report Agency: Fire Department
-Request Water Clearance Agency: Water Authority SYABAS
-Water Inspection Agency: Water Authority SYABAS
-Water Report Agency: Water Authority SYABAS
-Obtain Water Connection Agency: Water Authority SYABAS
-Obtain Telco Connection Agency: Telekom Malaysia (Telco)
Authorities in Project (ICI LECTURE) :
1.)TNB
-electric power supply
2.)BOMBA
-Fire safety , door & window
-Get CF (Certifcate of Fitness)-Architect
3.)Syabas
- Related to water
4.)Indah water
- Water treatment
5.)PPSPPA(Perbadanan Pengurusan Sisa Pepejal Dan Pembersihan Awam)
-Waste handling
6.)UBBL (Uniform Building by law)
7.)MSMA ( Manual Saliran Mesra Alam)
8.)DOSH ( Department Of Occupatinal Safety & Health)
-Heath & safety
9.)GBI
-Green Building Index
10.)IKRAM
-for slope
11.)Jabatan Warisan Negara
-Culture House
12.)Internal Facility Management
13.)Bank & Finance
14.)Insurance