AT-GRADE, HINGED, & UNDERGROUND GRADE CONTROL. AT-GRADE & HINGED GRADE CONTROL STRUCTURE ON...

42
AT-GRADE, HINGED, & UNDERGROUND GRADE CONTROL

Transcript of AT-GRADE, HINGED, & UNDERGROUND GRADE CONTROL. AT-GRADE & HINGED GRADE CONTROL STRUCTURE ON...

Page 1: AT-GRADE, HINGED, & UNDERGROUND GRADE CONTROL. AT-GRADE & HINGED GRADE CONTROL STRUCTURE ON HICKAHALLA CREEK NEAR SENATOBIA, MS. Constructed in 1989 to.

AT-GRADE, HINGED, &

UNDERGROUND GRADE

CONTROL

Page 2: AT-GRADE, HINGED, & UNDERGROUND GRADE CONTROL. AT-GRADE & HINGED GRADE CONTROL STRUCTURE ON HICKAHALLA CREEK NEAR SENATOBIA, MS. Constructed in 1989 to.

AT-GRADE & HINGED GRADE CONTROL

STRUCTURE ON HICKAHALLA CREEK NEAR SENATOBIA, MS. Constructed in 1989 to arrest headward migration of

existing downstream knickpoints (headcuts)

Mini case study: 1 of 12

Page 3: AT-GRADE, HINGED, & UNDERGROUND GRADE CONTROL. AT-GRADE & HINGED GRADE CONTROL STRUCTURE ON HICKAHALLA CREEK NEAR SENATOBIA, MS. Constructed in 1989 to.

DEFINITIONS OF TERMS

Page 4: AT-GRADE, HINGED, & UNDERGROUND GRADE CONTROL. AT-GRADE & HINGED GRADE CONTROL STRUCTURE ON HICKAHALLA CREEK NEAR SENATOBIA, MS. Constructed in 1989 to.

“At-Grade Grade Control Structures” are buried stone grade control structures where the top (crest) of the AGGCS is equal to the invert (lowest elevation) of the stream channel cross-section. AGGCS are typically built of well-graded (adjustable, self-healing) launchable stone.

Definition of an At-Grade Grade Control Structure

(AGGCS)

Page 5: AT-GRADE, HINGED, & UNDERGROUND GRADE CONTROL. AT-GRADE & HINGED GRADE CONTROL STRUCTURE ON HICKAHALLA CREEK NEAR SENATOBIA, MS. Constructed in 1989 to.

“Hinged Grade Control Structures” are grade control structures designed to adjust & stabilize undercutting foundation failure (due to headcutting) at the downstream end of the structure.

Definition of a Hinged Grade Control Structure (HGCS)

Page 6: AT-GRADE, HINGED, & UNDERGROUND GRADE CONTROL. AT-GRADE & HINGED GRADE CONTROL STRUCTURE ON HICKAHALLA CREEK NEAR SENATOBIA, MS. Constructed in 1989 to.

AT-GRADE GRADE CONTROL, FLAT-SLOPED SAND BED STREAM

Crest of stone equal to bottom (invert) of stream

Headcut advancing

Stone has adjustedCover overStone has adjusted & arrested

the advancing headcut

Sheet pile

Mini case study: 2 of 12

Sheet pile

Flow

Page 7: AT-GRADE, HINGED, & UNDERGROUND GRADE CONTROL. AT-GRADE & HINGED GRADE CONTROL STRUCTURE ON HICKAHALLA CREEK NEAR SENATOBIA, MS. Constructed in 1989 to.

Headcut advancing

Stone has adjustedCover overStone has adjusted & arrested

the advancing headcut

Sheet pile cutoff wall

Mini case study: 3 of 12

AT-GRADE GRADE CONTROL, FLAT-SLOPED SAND BED STREAM

Crest of stone equal to bottom (invert) of stream

Page 8: AT-GRADE, HINGED, & UNDERGROUND GRADE CONTROL. AT-GRADE & HINGED GRADE CONTROL STRUCTURE ON HICKAHALLA CREEK NEAR SENATOBIA, MS. Constructed in 1989 to.

At-Grade structure, Hickahala Creek, MS, {rural, sand bed, slope<1%, pool-riffle-pool, straightened, incised} as-built in 1989, note concrete cap on sheet-pile cutoff wall (red line)

Mini case study: 4 of 12

Page 9: AT-GRADE, HINGED, & UNDERGROUND GRADE CONTROL. AT-GRADE & HINGED GRADE CONTROL STRUCTURE ON HICKAHALLA CREEK NEAR SENATOBIA, MS. Constructed in 1989 to.

At-Grade, Grade Control structure, Hickahala Creek, MS, as-built in 1989, note

concrete cap on sheet-pile cutoff wall

Mini case study: 5 of 12

Page 10: AT-GRADE, HINGED, & UNDERGROUND GRADE CONTROL. AT-GRADE & HINGED GRADE CONTROL STRUCTURE ON HICKAHALLA CREEK NEAR SENATOBIA, MS. Constructed in 1989 to.

At-Grade Grade Control, Hickahala Creek, MS. Functioning as designed to arrest headward migration of knickpoints, picture taken April 2004

Mini case study: 6 of 12Sheet-pile cutoff wall

Page 11: AT-GRADE, HINGED, & UNDERGROUND GRADE CONTROL. AT-GRADE & HINGED GRADE CONTROL STRUCTURE ON HICKAHALLA CREEK NEAR SENATOBIA, MS. Constructed in 1989 to.

Hickahala Cr. At-Grade GC at high flow, April 6, 2005. Well-behaved flow, but return current is eroding far bank

Mini case study: 7 of 12

Page 12: AT-GRADE, HINGED, & UNDERGROUND GRADE CONTROL. AT-GRADE & HINGED GRADE CONTROL STRUCTURE ON HICKAHALLA CREEK NEAR SENATOBIA, MS. Constructed in 1989 to.

At-Grade GC, Hickahala Creek, MS. April 2007. Compared to the 2004 pictures, some stone has been displaced on the DS side of the sheetpile cap.

Mini case study: 8 of 12Sheet-pile cutoff wall

Page 13: AT-GRADE, HINGED, & UNDERGROUND GRADE CONTROL. AT-GRADE & HINGED GRADE CONTROL STRUCTURE ON HICKAHALLA CREEK NEAR SENATOBIA, MS. Constructed in 1989 to.

At-Grade GC, Hickahala Creek, MS. April 2007. Close-up of displaced stone on the DS side of sheetpile cap. Stone upstream of sheetpile is doing

nothing.

Mini case study: 9 of 12Sheet-pile cutoff wall

Page 14: AT-GRADE, HINGED, & UNDERGROUND GRADE CONTROL. AT-GRADE & HINGED GRADE CONTROL STRUCTURE ON HICKAHALLA CREEK NEAR SENATOBIA, MS. Constructed in 1989 to.

At-Grade GC, Hickahala Creek, MS. April 2007. Stone on DS face has self-adjusted to form a pool-riffle-pool configuration. Excessive stone movement is troubling

Mini case study: 10 of 12Sheet-pile cutoff wall

Original DS edge of stone

Page 15: AT-GRADE, HINGED, & UNDERGROUND GRADE CONTROL. AT-GRADE & HINGED GRADE CONTROL STRUCTURE ON HICKAHALLA CREEK NEAR SENATOBIA, MS. Constructed in 1989 to.

At-Grade GC, Hickahala Cr.-April 2010. Stone on the DS side of the cutoff wall has moved. Taller drop @ DS end of displaced stone means another headcut has arrived

Mini case study: 11 of 12Sheet-pile cutoff wall

Page 16: AT-GRADE, HINGED, & UNDERGROUND GRADE CONTROL. AT-GRADE & HINGED GRADE CONTROL STRUCTURE ON HICKAHALLA CREEK NEAR SENATOBIA, MS. Constructed in 1989 to.

At-Grade GC, Hickahala Creek, MS. April 2010. Structure should be closely monitored. Left bank erosion has increased, right bank is stable.

Stone is undersized & structure overwhelmed by number & height of headcuts

Mini case study: 12 of 12Sheet-pile cutoff wall

Page 17: AT-GRADE, HINGED, & UNDERGROUND GRADE CONTROL. AT-GRADE & HINGED GRADE CONTROL STRUCTURE ON HICKAHALLA CREEK NEAR SENATOBIA, MS. Constructed in 1989 to.

CLEAR CREEK, BOVINA, MS.

Arresting an active headcut using an At-Grade Grade

Control (GC) Structure(Crest of the grade control

structure is equal to the bed of the stream)

Page 18: AT-GRADE, HINGED, & UNDERGROUND GRADE CONTROL. AT-GRADE & HINGED GRADE CONTROL STRUCTURE ON HICKAHALLA CREEK NEAR SENATOBIA, MS. Constructed in 1989 to.

BACKSTORY:Landowner dug a massive cutoff channel

through a big hill in 2002, shortening stream length by approximately 710 ft.

The At-Grade Grade Control structure was built to halt the expected headcut generated

by the channel cutoff activities, which it has to some degree, but is presently in danger of

failing!!

Page 19: AT-GRADE, HINGED, & UNDERGROUND GRADE CONTROL. AT-GRADE & HINGED GRADE CONTROL STRUCTURE ON HICKAHALLA CREEK NEAR SENATOBIA, MS. Constructed in 1989 to.

Cutoff channel is 590 ft in yellow, original stream length is 1,300 ft in red, shortened 710 ft!! At-Grade Grade Control is blue line.

Page 20: AT-GRADE, HINGED, & UNDERGROUND GRADE CONTROL. AT-GRADE & HINGED GRADE CONTROL STRUCTURE ON HICKAHALLA CREEK NEAR SENATOBIA, MS. Constructed in 1989 to.

Looking US & across at LPSTP (both banks) and an At-Grade, Grade Control structure on Clear Creek, Bovina, MS. As-built photos unavailable. Since installation, degradation has occurred on the DS side of the structure due to knickpoint migration caused by landowner

shortening of the stream. GC & LPSTP installed 2002, pix shot March 2003.

Page 21: AT-GRADE, HINGED, & UNDERGROUND GRADE CONTROL. AT-GRADE & HINGED GRADE CONTROL STRUCTURE ON HICKAHALLA CREEK NEAR SENATOBIA, MS. Constructed in 1989 to.

One year later, note undersized stone displaced downstream by flow. Considered a functional failure, only one section of rock moved, flow now concentrated. Grade control stone appears smaller than LPSTP stone!!

Page 22: AT-GRADE, HINGED, & UNDERGROUND GRADE CONTROL. AT-GRADE & HINGED GRADE CONTROL STRUCTURE ON HICKAHALLA CREEK NEAR SENATOBIA, MS. Constructed in 1989 to.

HINGED GRADE

CONTROL STRUCTURE

Page 23: AT-GRADE, HINGED, & UNDERGROUND GRADE CONTROL. AT-GRADE & HINGED GRADE CONTROL STRUCTURE ON HICKAHALLA CREEK NEAR SENATOBIA, MS. Constructed in 1989 to.

BACKSTORY:

Headcuts had migrated thru the reach exposing two high pressure pipelines. A

significant Submar Inc. Articulating Concrete Mattress system was installed over the

pipelines (& keyed to top of both banks) to provide direct protection & cover so that the

pipelines were again in compliance with applicable law.

Page 24: AT-GRADE, HINGED, & UNDERGROUND GRADE CONTROL. AT-GRADE & HINGED GRADE CONTROL STRUCTURE ON HICKAHALLA CREEK NEAR SENATOBIA, MS. Constructed in 1989 to.

HICKAHALLA CREEK NEAR SENATOBIA, MS. Arresting an active headcut at

the downstream end of an Articulated Concrete Mattress

(ACM) system. Located on Hickahalla Creek DS of the At-Grade GC shown previously.

Page 25: AT-GRADE, HINGED, & UNDERGROUND GRADE CONTROL. AT-GRADE & HINGED GRADE CONTROL STRUCTURE ON HICKAHALLA CREEK NEAR SENATOBIA, MS. Constructed in 1989 to.

April 2004

2004 No evidence of a headcut.

Page 26: AT-GRADE, HINGED, & UNDERGROUND GRADE CONTROL. AT-GRADE & HINGED GRADE CONTROL STRUCTURE ON HICKAHALLA CREEK NEAR SENATOBIA, MS. Constructed in 1989 to.

LOOKING US, JULY 2004

March 2007

3-years later, large headcut arrested by Submar ACM mat. Mat undercut but self-adjusted.

Page 27: AT-GRADE, HINGED, & UNDERGROUND GRADE CONTROL. AT-GRADE & HINGED GRADE CONTROL STRUCTURE ON HICKAHALLA CREEK NEAR SENATOBIA, MS. Constructed in 1989 to.

SELF-ADJUSTING, GRADE CONTROL

STRUCTURES WORK WELL !!

Page 28: AT-GRADE, HINGED, & UNDERGROUND GRADE CONTROL. AT-GRADE & HINGED GRADE CONTROL STRUCTURE ON HICKAHALLA CREEK NEAR SENATOBIA, MS. Constructed in 1989 to.

January 2008

Non-uniform undercutting of mat. Still 14 ft until headcut gets back to the pipeline.

Pix by Lloyd Falgout

Page 29: AT-GRADE, HINGED, & UNDERGROUND GRADE CONTROL. AT-GRADE & HINGED GRADE CONTROL STRUCTURE ON HICKAHALLA CREEK NEAR SENATOBIA, MS. Constructed in 1989 to.

March 18, 2009

A more uniform adjustment of the mat to approx. 3 ft of headcut, still 14 ft until the headcut gets back to the

pipeline. Closely monitor this one!!

Pix by Derrick

Page 30: AT-GRADE, HINGED, & UNDERGROUND GRADE CONTROL. AT-GRADE & HINGED GRADE CONTROL STRUCTURE ON HICKAHALLA CREEK NEAR SENATOBIA, MS. Constructed in 1989 to.

Arresting an active headcut at the

downstream end of another Articulating Concrete Mattress

project.

Page 31: AT-GRADE, HINGED, & UNDERGROUND GRADE CONTROL. AT-GRADE & HINGED GRADE CONTROL STRUCTURE ON HICKAHALLA CREEK NEAR SENATOBIA, MS. Constructed in 1989 to.

Pickens, MS. ACM “tail” was laid on flat bathymetry, headcuts migrated US, mat has adjusted & arrested the headcut

“Hinged” ACM grade control, more mats can

be added as needed

Page 32: AT-GRADE, HINGED, & UNDERGROUND GRADE CONTROL. AT-GRADE & HINGED GRADE CONTROL STRUCTURE ON HICKAHALLA CREEK NEAR SENATOBIA, MS. Constructed in 1989 to.

UNDERGROUND

GRADE CONTROL

(Headcut mitigation)

Page 33: AT-GRADE, HINGED, & UNDERGROUND GRADE CONTROL. AT-GRADE & HINGED GRADE CONTROL STRUCTURE ON HICKAHALLA CREEK NEAR SENATOBIA, MS. Constructed in 1989 to.

BUILDING A TOTALLY UNDERGROUND

ENGINEERED ROCKED RIFFLE TO STOP

DOWNSTREAM HEADCUTS FROM

MOVING PAST THE ERR!

Page 34: AT-GRADE, HINGED, & UNDERGROUND GRADE CONTROL. AT-GRADE & HINGED GRADE CONTROL STRUCTURE ON HICKAHALLA CREEK NEAR SENATOBIA, MS. Constructed in 1989 to.

Entire area excavated

Basically an underground extension of an ERR which is designed to halt headcut migration. Depth of stone in the underground

ERR would be the effective depth for headcut mitigation.

STONE UNDERGROUND ERR TO STOP HEADCUT MIGRATION

Page 35: AT-GRADE, HINGED, & UNDERGROUND GRADE CONTROL. AT-GRADE & HINGED GRADE CONTROL STRUCTURE ON HICKAHALLA CREEK NEAR SENATOBIA, MS. Constructed in 1989 to.

Place a granular filter on the bed, or use a self-filtering stone

STONE UNDERGROUND ERR TO STOP HEADCUT MIGRATION

Page 36: AT-GRADE, HINGED, & UNDERGROUND GRADE CONTROL. AT-GRADE & HINGED GRADE CONTROL STRUCTURE ON HICKAHALLA CREEK NEAR SENATOBIA, MS. Constructed in 1989 to.

Stones placed on granular filter

STONE UNDERGROUND ERR TO STOP HEADCUT MIGRATION

Page 37: AT-GRADE, HINGED, & UNDERGROUND GRADE CONTROL. AT-GRADE & HINGED GRADE CONTROL STRUCTURE ON HICKAHALLA CREEK NEAR SENATOBIA, MS. Constructed in 1989 to.

Riprap stones placed for bank protection

STONE UNDERGROUND ERR TO STOP HEADCUT MIGRATION

DONE

Page 38: AT-GRADE, HINGED, & UNDERGROUND GRADE CONTROL. AT-GRADE & HINGED GRADE CONTROL STRUCTURE ON HICKAHALLA CREEK NEAR SENATOBIA, MS. Constructed in 1989 to.

Flow

Profile view

201

10

1

STONE UNDERGROUND ERR TO STOP HEADCUT MIGRATION

Underground ERR slope could vary, might be economically driven

Page 39: AT-GRADE, HINGED, & UNDERGROUND GRADE CONTROL. AT-GRADE & HINGED GRADE CONTROL STRUCTURE ON HICKAHALLA CREEK NEAR SENATOBIA, MS. Constructed in 1989 to.

Flow

STONE UNDERGROUND ERR TO STOP HEADCUT MIGRATION

Depth of stone will be designed to halt the

upstream movement of that depth of

headcut(s)

Page 40: AT-GRADE, HINGED, & UNDERGROUND GRADE CONTROL. AT-GRADE & HINGED GRADE CONTROL STRUCTURE ON HICKAHALLA CREEK NEAR SENATOBIA, MS. Constructed in 1989 to.

AN UNDERGROUND ENGINEERED ROCKED

RIFFLE WAS BUILT ON SAN ANTONIO CREEK,

VANDENBERG AIR FORCE BASE, CA. TO MITIGATE 10

FT OF DOWNSTREAM HEADCUTS. I DESIGNED IT

BUT DO NOT HAVE ANY PIX!

Page 41: AT-GRADE, HINGED, & UNDERGROUND GRADE CONTROL. AT-GRADE & HINGED GRADE CONTROL STRUCTURE ON HICKAHALLA CREEK NEAR SENATOBIA, MS. Constructed in 1989 to.

This PowerPoint presentation was developed & built by Dave Derrick.

Any questions or comments, call my personal cell @ 601-218-7717, or email @ [email protected]

Enjoy the information!!