COURSE : BFC 32703 – SUSTAINABLE CONSTRUCTION MANAGEMENT
SECTION : 2 TASK : ASSINGMENT NO. 2
TOPIC : PLANNING AND SCHEDULING
QUESTION:
You are required to develop a network diagram based on the information provided to you in the
Table 1. Your diagram should develop in manually and no computer software is allowed.
The project start date is on Sunday, 1st Mac 2016. There are only six (6) working days in a week and
Friday is the non-working day. Therefore the other public holiday that falls in the project planning
schedule must take into consideration.
The Gantt Chart view must show the relevant column with the following title:
TASK; DURATION; ES; EF; LF; TF; PREDECESSOR
The task bar must display the critical path.
This task required you to form a group which consists of four to five persons.
This assignment must be submitted not later than 1st Jun 2016 (Wednesday)
UNIVERSITI TUN HUSSEIN ONN MALAYSIA FACULTY OF CIVIL AND ENVIRONMENTAL ENGINEERING
FAKULTI KEJURUTERAAN AWAM DAN ALAM SEKITAR
Table 1
Activity Duration (Days)
Predecessor
Start 0 - A 8 START
C 15 START
D 10 START B 20 A
G 16 C,D F 9 B
E 14 B
K 7 G
P 9 K
O 7 K I 20 E
H 10 E
V 6 P
Q 5 L(FF-2)
L 4 H Z 3 V
J 8 F(FS+5), G, I
M 25 I
N 16 J
T 10 N R 15 M
U 30 O(FS-5), N(FS+3)
X 3 T(FS+4)
S 18 Q,R
W 5 U, V(SS) Y 8 W, X
FINISH 0 Y, Z, S