Assets Delivery Group Engineering APPLICATION …...CIA Concrete Institute of Australia CIP Coating...
Transcript of Assets Delivery Group Engineering APPLICATION …...CIA Concrete Institute of Australia CIP Coating...
Assets Delivery Group
Engineering
APPLICATION OF CHEMICAL RESISTANT PROTECTIVE COATING ON
CONCRETE BUNDS IN WATER AND WASTEWATER TREATMENT PLANTS
SPECIFICATION: CR5 ISSUE: 2 DATE: AUGUST 2018
Page 1 of 12
1.0 SCOPE
This document summarises the procedure for the application of a 2 pack chemical resistant
Novolac Epoxy coating on concrete chemical bunds.
2.0 PURPOSE
The purpose of this coating specification is to prepare a concrete substrate for the application of a
chemical resistance coating.
3.0 DEFINITIONS
ACA Australian Corrosion Association
APAS Australian Paint Approval Scheme
CIA Concrete Institute of Australia
CIP Coating Inspector Program
Contractor The service provider or its sub-contractor who will undertake the works
Corporation The Water Corporation and the Principal for the purposes of externally
contracted asset delivery
ITP Detailed Inspection and Test Plan(s) for the Works
ITR Detailed Inspection and Test Record(s) for the Works
NACE National Association of Corrosion Engineers
PCCP Painting Contractors Certification Program
SSPC Society for Protective Coatings
Superintendent Superintendent for the contract, as defined in the conditions of contract,
who is appointed by the Water Corporation to manage/oversee the work
under the contract on behalf of the Water Corporation
Works The surface preparation, coating application and inspection to be
undertaken by the contractor to which this coating specification applies
Assets Delivery Group
Engineering
APPLICATION OF CHEMICAL RESISTANT PROTECTIVE COATING ON
CONCRETE BUNDS IN WATER AND WASTEWATER TREATMENT PLANTS
SPECIFICATION: CR5 ISSUE: 2 DATE: AUGUST 2018
Page 2 of 12
4.0 GENERAL
4.1 Work shall only be carried out by competent personnel.
4.2 The work shall be undertaken by a coating contractor accredited by the PCCP to a class
appropriate for the work to be undertaken.
4.3 The Applicator’s Coating Supervisor shall possess as a minimum one of the following
certifications:
ACA - Coating Inspector; or
NACE - CIP Level II Coating Inspector.
4.4 The coating contractor shall nominate a Coating Inspector as their Quality Control
Officer to carry out inspections, submit the ITP, undertake the required testing and
maintain appropriate records for all work performed.
The Applicator’s Coating Inspector shall possess as a minimum one of the following
certifications:
ACA - Coating Inspector; or
NACE - CIP Level II Coating Inspector.
5.0 SURFACE PREPARATION
5.1 The substrate shall be sound, dry, free from dust/dirt and any surface defects and
contaminants (e.g. oil, grease, salts, chemicals, paint, formwork release and curing
membranes) that may be detrimental to the coating adhesion to the substrate.
5.2 Reference shall be made to SSPC-SP13/NACE 6 “Standard on Surface Preparation of
Concrete Structures” and the coating manufacturer’s standard requirements for the
coating to be applied.
5.3 Principal Representative along with the contractor shall identify and document areas that
contain cracks (> 0.3mm), spalling, rebar corrosion and drumminess and record in the
ITR. Contractor shall repair the defective surfaces in accordance with the construction
supplier’s technical data sheet prior to the application of coating.
5.4 Floor to wall joints, sharp corners etc. shall be “coved” prior to the coating application.
[Refer: Figure 1].
5.5 If needed, spray apply moisture tolerant penetrating surface binding epoxy coat to
strengthen and seal concrete surfaces and allow to harden.
Assets Delivery Group
Engineering
APPLICATION OF CHEMICAL RESISTANT PROTECTIVE COATING ON
CONCRETE BUNDS IN WATER AND WASTEWATER TREATMENT PLANTS
SPECIFICATION: CR5 ISSUE: 2 DATE: AUGUST 2018
Page 3 of 12
5.6 Where expansion joints are noted, remove joint material and terminate coating into the
joint prior to reinstating a chemical resistant sealant. Sides of joint to be re-abraded and
primed prior to injecting the new sealant.
Figure 1 – Coving on the floor to wall joint.
6.0 ATMOSPHERIC CONDITIONS
6.1 Prior to and during coating application, the contractor shall record details pertaining to
environmental conditions including ambient and surface temperature, relative humidity
and dew point.
7.0 COATING MATERIALS 7.1 Where a suitable Australian Paint Approval Scheme (APAS) approved product is
available it shall be used. If a suitable APAS approved product is not available, then an
equivalent non-APAS approved product may be used subject to approval by the
Corporation.
7.2 The coating components shall be thoroughly mixed in the specified proportions. Material
so prepared shall be used within the “pot-life” period claimed by the manufacturer for the
relevant site conditions.
7.3 Coating specifications inclusive of datasheets, coating application, method statements and
ITP’s shall be submitted to the Principal for approval at least 10 working days prior to
commencement of the work.
7.4 Recommended drying times between coats for on-site conditions shall not be exceeded.
Coving
Assets Delivery Group
Engineering
APPLICATION OF CHEMICAL RESISTANT PROTECTIVE COATING ON
CONCRETE BUNDS IN WATER AND WASTEWATER TREATMENT PLANTS
SPECIFICATION: CR5 ISSUE: 2 DATE: AUGUST 2018
Page 4 of 12
7.5 Applied coatings shall be protected from rain or moisture until cured.
8.0 COATING TYPE & THICKNESS
8.1 Brush apply two or more coats of chemical resistant Novolac Epoxy to produce 500
microns minimum dry film thickness [Refer: Figures 2 & 3].
8.2 For areas requiring a trafficable non-skid surface, broadcast silica/calcined Alumina of
100 mesh directly onto the trowel coat.
Note: Ensure the broadcasted particle do not pierce through the coating.
8.3 Refer Section 15.0 commonly used chemical resistant coatings for concrete bunds in
water & wastewater treatment plants. Select relevant coating system based on the type of
chemical stored in the concrete bund.
9.0 INSPECTION AND TESTING OF COATING
9.1 Visual Testing - Coatings shall be visually examined for surface defects and any
discontinuity arising after curing shall be recorded.
9.2 Spark Testing - The finished coating shall be holiday tested in accordance with NACE
Standard SP0188 – Discontinuity (Holiday) Testing of New Protective Coatings on
Conductive Substrates.
9.3 Adhesion Testing - This test shall be conducted in accordance with AS/NZS 1580
Method 408.5 to determine the adhesion strength of the coating to the substrate.
Reference shall also be made to ASTM Standard D4541, ASTM D7234 and ASTM
C1583/C1583M [Refer: Figure 4].
9.3.1 The minimum acceptable adhesion value for elastomeric coatings on concrete shall be in
accordance with the Section X1.1.1.4 of ASTM D7234 standard.
9.3.2 The location of test sites shall be identified and agreed upon by both the Contractor and
the Principal prior to the start of attaching the dollies to the substrate.
9.4 Coating Thickness Testing – Coating DFT shall be tested using concrete coating
thickness gauge [Refer: Figure 5].
9.5 The results of all testing shall be submitted to the Superintendent at the completion of
work.
Assets Delivery Group
Engineering
APPLICATION OF CHEMICAL RESISTANT PROTECTIVE COATING ON
CONCRETE BUNDS IN WATER AND WASTEWATER TREATMENT PLANTS
SPECIFICATION: CR5 ISSUE: 2 DATE: AUGUST 2018
Page 5 of 12
Figure 2 – Full coating on the internals of
the concrete wall.
Figure 3 – Termination of coating on the
outside of the concrete wall.
Figure 4 – Pull-off test on the test panel
[outside of the bund].
Figure 5 – DFT inspection using Positector®
200 gauge.
10.0 REPAIR OF A DEFECTIVE COATING AND RETESTING
10.1 Coatings with defective areas equal to 20% or more of the total coated surface will be
rejected outright.
10.2 Defects such as pinholes, cracks, blisters, voids, foreign inclusions and irregular profile
peaks shall be marked for repair and retested upon full cure of the repaired coating.
Assets Delivery Group
Engineering
APPLICATION OF CHEMICAL RESISTANT PROTECTIVE COATING ON
CONCRETE BUNDS IN WATER AND WASTEWATER TREATMENT PLANTS
SPECIFICATION: CR5 ISSUE: 2 DATE: AUGUST 2018
Page 6 of 12
11.0 RECORDING AND REPORTING
11.1 Following testing a report shall be submitted by the Contractor. The Contractor shall
keep detailed records and reports including the following:
Environmental conditions (relative humidity, dew point etc.);
Surface preparation;
Surface profile;
Coating application;
Coating testing; and
General failure.
12.0 COATING FINISH
12.1 The finished coating shall be of uniform thickness, colour, appearance and gloss. It shall
be fully cured, adherent, coherent and free from holidays, laps, sags, blistering, checking,
wrinkling, overspray, patchiness and any other defects that may impair the performance
and/or appearance of the coating.
13.0 INSPECTION
13.1 The Contractor shall maintain records and evidence of the original surface, blast surface
and blast profile. These shall be made available to the Superintendent and/or delegate at
the completion of the project. Evidence of these parameters shall be provided by means
of photographic evidence.
13.2 The Contractor shall provide the Superintendent (or nominated delegate) adequate prior
notice as to when and where the surface preparation and coating operations will be
conducted to facilitate all specified inspections.
13.3 If recognised as a hold point in the ITP, the coating application shall not be carried out
until the Superintendent has accepted the surface preparation.
14.0 CONTRACTOR'S RESPONSIBILITY
14.1 The Contractor shall supply all necessary plant, equipment, materials and labour, prepare
the surface and apply and maintain the protective coating in accordance with this
specification and the coating manufacturer’s requirements.
14.2 The preceding inspection clauses shall not relieve the Contractor of their responsibility to
supply materials and perform work in accordance with the requirements of any overriding
contract documentation.
Assets Delivery Group
Engineering
Page 7 of 12
15.0 Commonly Used Chemical Resistant Coatings for Concrete Bunds in Water & Wastewater Treatment Plants
Chemical Name Epigen Sika Parchem BASF Epimax SIM Chesterton
Alum. Sulphate - Alum [25%] Chemproof 4029 Sikagard 63N Nitocote EP410 + Durafloor N Ucrete 333AR
Chemclad SC
Chemclad XC
CS4
NVE
Aluminium Chloride
Hydroxide [23-30%]
Chemproof 4029 Sikagard 62 Nitocote EP410 + Durafloor N Ucrete 333AR
Chemclad SC
Chemclad XC
CS4
NVE
Anhydrous Ammonia Chemproof 4029 Sikagard 62 Nitocote EP410 + Durafloor N Ucrete ---
Chemclad SC
Chemclad XC
CS4
NVE
Citric Acid [90%] Chemproof 4029 Sikagard 63N Nitocote EP410 + Durafloor N Ucrete 333AR Chemclad XC NVE
Chlorine Chemproof 4029 Sikagard 62 Nitocote EP410 + Durafloor N Ucrete ---
Chemclad SC
Chemclad XC NVE
Ferric Sulphate [45%] Chemproof 4029 Sikagard 63N Nitocote EP410 + Durafloor N Ucrete 333AR Chemclad XC
CS4
NVE
Fluorosilicic Acid Chemproof 4029 Sikagard 63N Durafloor N short term contact Ucrete --- Chemclad XC NVE
Hydrochloric Acid [26%] Chemproof 4029 Sikagard 63N Nitocote EP410 + Durafloor N Ucrete 421HAR Chemclad XC
988
NVE
Magnesium Hydroxide Liquid Chemproof 4029 Sikagard 62
Sikagard 63N Nitocote EP410 + Durafloor N Ucrete ---
Chemclad SC
Chemclad XC NVE
Magnesium Hydroxide Chemproof 4029 Sikagard 62
Sikagard 63N Nitocote EP410 + Durafloor N Ucrete ---
Chemclad SC
Chemclad XC NVE
Potassium Permanganate Chemproof 4029 Sikagard 62
Sikagard 63N Nitocote EP410 + Durafloor N Ucrete 421HAR
Chemclad SC
Chemclad XC
CS4
NVE
Sodium Hydroxide
[Caustic Soda 50%]
Chemproof 4029 Sikagard 62
Sikagard 63N Nitocote EP410 + Durafloor N Ucrete 333AR
Chemclad SC
Chemclad XC
CS4
NVE
Sulphuric Acid [98%] Chemproof 4029 Sikagard 63N Durafloor N short term contact Ucrete 421HAR Chemclad XC
CS4
988
Sodium Bisulphite [35-40%] Chemproof 4029 Sikagard 63N Nitocote EP410 + Durafloor N Ucrete 333AR
Chemclad SC
Chemclad XC
CS4
NVE
Sodium Hypochlorite [12.5%] Chemproof 4029 Sikagard 62
Sikagard 63N Nitocote EP410 + Durafloor N Ucrete 333AR Chemclad XC NVE
Sod.Metabisulphite [35 - 40%] Chemproof 4029 Sikagard 62
Sikagard 63N Nitocote EP410 + Durafloor N Ucrete ---
Chemclad SC
Chemclad XC
CS4
NVE
Note:
If there is an acid spill in the coated bund area, the spillage shall be cleaned within 48 hours.
Where a coating system requires more than one product to be used (e.g. Primer and top coat) both product shall be from the same supplier unless approved otherwise by the Senior Engineer, Corrosion Control
Section.
The Water Corporation cannot be held responsible for the claims or performance guarantees offered by construction product suppliers.
Due to continuous product development, coating contractors shall check with product suppliers to confirm that the product names and numbers are current at the time of ordering.
Assets Delivery Group
Engineering
Page 8 of 12
16.0 INSPECTION AND TEST PLAN [SAMPLE]
CLIENT WATER CORP LOCATION Chlorine Building ACTIVITY CC5 – EPIGEN EPOXY APPLICATION
ITEM ACTIVITY DESCRIPTION TEST TYPE FREQ. OF TEST INSPECTED BY APPROVED BY ACCEPTANCE CRITERIA
CODE / SPEC
1 Cut delineations to all horizontal and
vertical terminations
Measurement and
visual
On completion PCS / Client SS WC Cut to be 5 x 5mm around all cast in items and floor
joints
2 Surface preparation – 5000 psi
pressure water cleaning
Visual inspection
of cleaned surface
Ongoing and on
completion
PCS / Client SS WC All surface contamination and dusting removed,
Section 5.1, 10.3 & 10.4
2
Surface patching – Epigen 4040 Visual inspection
of repaired
surfaces
On completion PCS / Client SS WC Large surface imperfections removed, Section 5.1 and
Manufacturers specification
3
Coating application – Epigen 4040 &
4029 Topcoat as per Method
Statement Supplied
Visual inspection
of coating
application
100% of surface after
each coat
PCS / Client SS HC Section 10.3 and Manufacturers specification
5
Film thickness Non-Destructive
DFT testing
On completion,
minimum 6 test per
building
PCS / Client SS HC Thickness Appendix 2 CC5, Manufacturers
specification
6
Coating Discontinuity (Holiday)
Testing
Spark Testing 100% of surface on
completion
PCS / Client SS HC Section 10.8
LEGEND DESCRIPTION Form No. Rev No. Amendment Date Approved
SS Initial by PCS Site Supervisor QC Prepared By S Power 01 7/11/2011
WC Witness. Initial by Client QA - QC Manager Client Approval P Dumitra 01 8/11/2011
HC Hold. Initial by Client QA - QC Manager Client Approval
PLEASE NOTE: If any items has not been initialed or signed off by either party it will be classed as a non-conformance and the consequences are to be met or the item will remain as a non-conforming item.
Any non-conforming items may void the application warranty
COMMENTS:
--End of Document---
Assets Delivery Group
Engineering
CONCRETE CONDITION ASSESSMENT SURVEY FORM
CONCRETE SURVEY FORM: SF ISSUE: 2 DATE: AUGUST 2018
Page 9 of 12
Surface Condition
Honeycombing
Yes
No
If yes, Approximate % area ______________
Bleeding
Yes
No
If yes, Is it mild? or severe?
Pop-outs
Yes
No
If yes, big lumps? Or small?
Voids
Yes
No
If yes, diameter? ______________mm
Early Cracking
Voids
Yes
No
Comments:
_________________________________________
Date: Asset Deficiency
Report [ADR] No.
Inspected
By:
Asset
Location:
SWR NWR GPS Co-Ordinates
GSR MWR Easting:
GAR PM Northing:
Functional Location:
Years in Service:
Asset Type:
Assets Delivery Group
Engineering
CONCRETE CONDITION ASSESSMENT SURVEY FORM
CONCRETE SURVEY FORM: SF ISSUE: 2 DATE: AUGUST 2018
Page 10 of 12
Concrete Quality
Surface
hardness/Strength
Min Value _________________________________________ MPa
Max Value _________________________________________ MPa
Compliance to AS/NZS 3735: Waste Water Potable Water
Rebar Cover
Concrete Cover
Min Cover _________________________________________mm
Max Cover _________________________________________mm
Compliance to AS/NZS 3735: Waste Water Potable Water
Mechanical
breakout
Yes
No
Structural effects
Overloading
Yes
No
Dynamic Effects
Yes
No
Structural
Cracking
Yes
No
Surface damage
Chemical attack
Yes
No
Comments:
_________________________________________
Abrasion
Yes
No
Comments:
_________________________________________
Leaching
Yes
No
Comments:
_________________________________________
Assets Delivery Group
Engineering
CONCRETE CONDITION ASSESSMENT SURVEY FORM
CONCRETE SURVEY FORM: SF ISSUE: 2 DATE: AUGUST 2018
Page 11 of 12
Spalling
Yes
No
Comments:
_________________________________________
Staining
Rebar corrosion
Yes
No
Comments:
_________________________________________
Efflorescence
Yes
No
Comments:
_________________________________________
Salts
Yes
No
Comments:
_________________________________________
Cracking
Width Yes No
Less than 0.2 mm
Comments:
_________________________________________
0.2 mm to 1.0 mm
Comments:
_________________________________________
Greater than 1.0
mm
Comments:
_________________________________________
Assets Delivery Group
Engineering
CONCRETE CONDITION ASSESSMENT SURVEY FORM
CONCRETE SURVEY FORM: SF ISSUE: 2 DATE: AUGUST 2018
Page 12 of 12
Rebar condition
Visual examination of
bar
Yes
No
Comments:
____________________________________
Rust
Yes
No
Comments:
____________________________________
Pitting damage
Yes
No
Comments:
____________________________________
Carbonation
Indicator test on cores
Yes
No
Comments:
___________________________________
Mechanical breakouts
Yes
No
Comments:_________________________
Delamination
Size
Yes
No
Comments: ___________________________
Frequency
Yes
No
Comments:
____________________________________
Severity of delamination
Yes
No
Comments:___________________________
Previous Repairs
Integrity of repairs
Yes
No
Comments: __________________________
Signs of damage near
repair locations
Yes
No
Comments: __________________________
--- End of Document ---