Asset Management Update Overview and Scrutiny Committee 14 th May 2013 Item 4 Appendix B 28.
-
Upload
suzan-hancock -
Category
Documents
-
view
215 -
download
0
Transcript of Asset Management Update Overview and Scrutiny Committee 14 th May 2013 Item 4 Appendix B 28.
Asset Management Update
Overview and Scrutiny Committee
14th May 2013
Item 4 Appendix B
1
AMP 2021 Asset Strategy
Starting from
Maintenance backlog £62m
Investment need to moderniseDiverse and
dispersed estate
Item 4 Appendix B
2
Delivery of the AMP 2021Item 4 Appendix B
3
Core Data and Review and ChallengeItem 4 Appendix B
4
Coed Parc Library
.Suite 4, Dragon House
Examples of assets: Released, Retained and Remodelled delivering:
Oldcastle Offices
Sunnyside House
Since 2009 64 assets
have been released
Accessibility improvements to over 58 facilities
Release of assets not fit for purpose
DeliveringFit for purpose assets
Releasing AssetsRemodelling Assets
Item 4 Appendix B
5
Working with services: Wellbeing
Adult Social Care
Release : former day-care centre site
Healthy Living
•HALO assets•8 sports/life centres recently leased to Halo Leisure Services Ltd •The partnership is based on an outcomes based delivery model which is designed to facilitate future investment in the facilities. •This is supplemented by individual lease agreements for each property. The main lease terms include:•Term - 15 years with effect from 1/4/12•Rent - peppercorn•Repair – Halo to undertake all repairs
Remodel and Retain: Bryn Y Cae residential re-ablement
Item 4 Appendix B
6
Working with services: Schools ModernisationRemodelNew Coleg Cymunedol Y Dderwen
• Sharing new space• dedicated community areas • sports provision, which can be used
outside the school dayFormer Ogmore comprehensive
ReleaseLand at YBCSurplus land at Coleg Cymunedol Y Dderwen
Retain and Maintainfacilities
Delivering £11m in capital receipts…Property services are now working with the Children’s directorate to deliver a programme of disposals amounting to over £11m to help support the Council’s match funding requirement for the Welsh Government’s 21st Century Schools Programme.
Item 4 Appendix B
7
£10,
600
p.a.
Unit 3, The Highwayman
Office Accommodation phase 1~ Project Summary
2009 Direction of Travel 2012
Suite 2 Tremains Business Park
£2,5
92 p
.a.
Suite 4, Dragon House
£11,000 p.a.
Unit 5 The Highwayman
£5,5
00 p
.a.
Unit 4, The Highwayman
£106,500 p.a.
£13,
500
p.a.
Brackla House
£4,5
00 p
.a.
87 Park Street
£43,
945
p.a
Item 4 Appendix B
8
Office Accommodation phase 2 and Integrated Hubs
Phase 2: Retaining and Maintaining our core offices,To have sustainable, fit for purpose office accommodation with IYS completed in all of our core offices & investment decisions leading to a more efficient estate
Management and space efficiencies Financial efficiencies and savings Reduced CO2 emissions Corporate facilities management. Successful integrated working in core
buildings and network hubs
Item 4 Appendix B
9
Sharing the accommodation cost
Sharing accommodation
Integrated Hubs: Providing integrated social care,
– Innovation Centre
– Sunnyside
– Pyle Life Centre
– Bryncethin Depot offices
– Coleg Cymunedol Y Dderwen
Depots:– Joint Fleet Services: Bryncethin
Developing protocols based around:•Service charge payment
• running costs• utility costs• maintenance costs
•Capital charge• cost of area occupied
Item 4 Appendix B
10
Depots – feasibility work
New joint fleet services Depot Bryncethin
Review and relocation of building maintenance and highway depot facilities from Waterton to Bryncethin
Parc Afon Ewenni (Waterton Master Plan)
Item 4 Appendix B
11
Non-operational property strategyPrimary Use No of
AssetsReason Held Planned
Review/ Strategy
3rd party Community Use 29 Community Support
Community use agreement completed
Allotments 25 Community Support
Allotment Strategy
CompletedGarage bases 14 Historic / Community SupportGarage compounds 2 Community Support
Commercial (inc.5 investment) 13Economic / community support / historic / Investment
Ongoing Review
Enterprise Centres 3 Community Support / EconomicIndustrial (starter units) 76 Community Support / Economic
Industrial (units & plots) (inc 9 Investment) 116
Economic / Community support/ Investment
Markets 2 Community Support Jul-2013
Surplus land 11 No longer required for service provision
Surplus building 2 No longer required for service provisionResidential Ground Leases 21 HistoricReclamation Schemes 13 Historic / Community Support
Vacant land 85 Historic
Vacant building 6 Historic / Pending redevelopment
Other leases 2 Historic420
May-2013
Disposal Strategy
Completed
Identified actions in geographical
reviews Vacant buildings
plans Unallocated land
project
Jun-2013
Item 4 Appendix B
12
Overall measures
Total Assets released
Total Rental Saved
Capital Receipts Generated
Maintenance Backlog associated with released assets
CO2 Emissions reduction from released assets
Carbon tax savings
64 £403,487 £2,566,000
£8,073,295 4,269.61 £51,235
Assets released outcomes 2009/12
Rating Savings
Total savings over 5 years from 2005 to 10 RV reductions
£1,138,128
Total savings from RV (2010 to 15) reductions to date
£387,541
RENTAL INCOME 2009-20122009-2010 £1,846,795.272010-2011 £1,917,452.842011-2012 £1,771,649.59
TOTAL £4,615,066.69
Item 4 Appendix B
13
Future Focuses
Future focuses for Property Services, as set out in the Directorate business plan include: Council’s Improvement Priority
Directorate Priority
Developing the local economy Making best use of our resources
Parc Afon Ewenni(TPC)
Making best use of our resources
Improving Your Space(TPC)
Making best use of our resources
Increasing income and Capital receipts(TPC)
Item 4 Appendix B
14
Ongoing challenges
Capital investment is often required to deliver longer term property savings and efficiencies.
The current economic climate and market changes will impact on the delivery of income and capital receipts.
The reduction in both the minor capital works budget and capital programme will have a negative impact on our efforts to reduce the maintenance back log.
Item 4 Appendix B
15