Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset...

166
CTW – Water Asset Management Plan April 2014 WATER SUPPLY ASSET MANAGEMENT PLAN Version: 1.0 April 2014

Transcript of Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset...

Page 1: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

CTW – Water Asset Management Plan April 2014

WATER SUPPLY

ASSET MANAGEMENT PLAN

Version: 1.0

April 2014

Page 2: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

CTW – Water Asset Management Plan April 2014

Table of Contents

EXECUTIVE SUMMARY i 1.0 INTRODUCTION 1

1.1 OBJECTIVES OF THIS PLAN 1 1.2 SCOPE OF THIS PLAN 1 1.3 THE ASSET MANAGEMENT PLAN 7 1.4 PLAN FORMAT 7 1.5 KEY STAKEHOLDERS 8 1.6 LEGISLATIVE REQUIREMENTS 8 1.7 RELATIONSHIPS WITH OTHER PLANS AND DOCUMENTS 9 1.8 RATIONALE FOR ASSET OWNERSHIP 9

2.0 LEVELS OF SERVICE 10 2.1 INTRODUCTION 10 2.2 LEVELS OF SERVICE REQUIREMENTS 11 2.3 COMMUNITY RESEARCH AND EXPECTATIONS 12

2.3.1 Community Satisfaction Survey 12 2.4 STRATEGIC AND CORPORATE GOALS 12

2.4.1 Best Practice 13 2.5 LEGISLATIVE REQUIREMENTS, STANDARDS AND CODES OF PRACTICE 13 2.6 CURRENT/TARGET LEVELS OF SERVICE 14 2.7 LEVELS OF SERVICE TABLES 16

2.7.1 Community Levels of Service 16 3.0 DEMAND FORECAST 19

3.1 INTRODUCTION 19 3.2 GROWTH TRENDS 19

3.2.1 Population 19 3.3 RESIDENTIAL IMPACTS 20 3.4 COMMERCIAL/INDUSTRIAL IMPACTS 20 3.5 CURRENT DEVELOPMENTS AND IMPACTS 21 3.6 IMPACT OF TRENDS ON INFRASTRUCTURE 21

3.6.1 Existing Infrastructure 21 3.6.2 New Infrastructure 21

4.0 LIFECYCLE MANAGEMENT PLANS 22 4.1 INTRODUCTION 22

4.1.1 Section Contents 22 4.1.2 Work Category Definitions 22 4.1.3 Asset Hierarchy 26 4.1.4 Maintenance Contract 27 4.1.5 Inspections 27 4.1.6 Intervention Levels 28 4.1.7 Performance Monitoring 28 4.1.8 Consultation Process 29 4.1.9 Boundary Issues 29 4.1.10 Council Ownership Functions 29

4.2 ASSET GROUP 1 – FILTRATION PLANT 30 4.2.1 Objective 30 4.2.2 Background Data 30 4.2.3 New Works Strategies 31

4.3 ASSET GROUP 2 – PUMP STATIONS 32 4.3.1 Objective 32 4.3.2 Background Data 32

Page 3: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

CTW – Water Asset Management Plan April 2014

4.3.4 Maintenance 33 4.3.5 Renewal 34 4.3.6 New Works Strategies 34 4.3.7 Disposal 34

4.4 ASSET GROUP 3 – RESERVOIRS 34 4.4.1 Objective 34 4.4.2 Background Data 35 4.4.3 Operations 35 4.4.4 Maintenance 36 4.4.5 New Works Strategies 36

4.5 ASSET GROUP 4 – RETICULATION 37 4.5.1 Objective 37 4.5.2 Background Data 37 4.5.3 Operations 38 4.5.4 Maintenance 38 4.5.5 Renewal 38 4.5.6 New Works Strategies 39 4.5.7 Disposal 39

APPENDIX A – OPERATIONS MANAGEMENT PLAN 40 APPENDIX B – 30 YEAR FINANCIAL & CAPITAL WORKS PLAN 41

Page 4: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

CTW – Water Asset Management Plan April 2014 Page i

Executive Summary

Central Tablelands Water County Council (CTW) is the local water utility responsible for the provision of potable

water to the local government areas of Blayney, Cabonne & Weddin to service the following towns and villages:

Blayney Shire: Blayney, Millthorpe, Carcoar, Mandurama, Lyndhurst and Somers.

Cabonne Shire: Canowindra, Morebel, Cargo, Cudal, Manildra, and Eugowra.

Weddin Shire: Grenfell and Quandialla.

CTW also supplies bulk potable water to Cowra Shire to service the villages of Woodstock and Gooloogong.

Potable water is also supplied to approximately 670 rural consumers on council’s trunk mains.

With the exception of Quandialla, all towns and villages across the supply network receive treated water from

Lake Rowlands. Quandialla receives chlorinated water from a groundwater source located 17 kilometres from

the village on the West Wyalong Road. This Asset Management Plan provides a means for CTW, as the

responsible authority for the water supply infrastructure in these three local government areas, to manage the

water supply assets in an efficient and timely manner.

In this plan levels of service will be set, below which it will be unacceptable for the condition of the specified

assets to fall. Intervention will be expected to occur before these minimum levels of service are breached. A

community consultation process will become part of future Asset Management plans and it will be during this

process that adjustments to these levels of service can be negotiated.

CTW Supply Network

Page 5: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

CTW – Water Asset Management Plan April 2014 Page 1

1.0 Introduction

1.1 Objectives of this Plan

Asset Management Overall objective

Council’s water supply infrastructure represents a significant investment by the community and is vital to its

health and future growth. The overall objective of asset management (AM) is:

• Demonstrate responsible management

• To communicate and justify funding requirements

• To comply with statutory/regulatory requirements

• To provide operate and maintain physical assets over their whole life cycle to achieve the required

levels of service at the least life cycle cost while still satisfying corporate goals.

Specific purpose

The specific purpose of this plan is to:

• Demonstrate responsible stewardship;

• Define and articulate how the infrastructure is and will be managed to achieve Council’s

objectives;

• Provide a basis for customer consultation to determine the appropriate levels of service;

• Manage risk of asset failure;

• Achieve savings by optimising whole of life costs; and

• Support long term financial planning.

1.2 Scope of This Plan

Central Tablelands Water is the trading name adopted by Central Tablelands County Council, a water supply

authority constituted under NSW Local Government legislation. The Council is located in the central west of

New South Wales and services a geographically large, but sparsely populated area. This area ranges from

Blayney in the east, to Grenfell in the west.

We currently have approximately 5,620 connections and provide potable water to around 11,500 consumers in

14 towns and villages. Our main water source is Lake Rowlands. Water from this source is supplemented by

various groundwater bores during summer.

Lake Rowlands Dam, formerly known as Coombing Dam, is situated on the Coombing Rivulet, a tributary of the

Belubula River. The Dam was designed in 1939 by Gutteridge, Haskins and Davey as a reinforced concrete

slab and buttress type dam with a top water level (TWL) at RL 882.70m. Construction was carried out in the

period 1949 to 1954. The dam has a gross storage volume of 4,500 megalitres and the TWL was constructed to

RL 877.82m, 5 metres below the original design height.

Page 6: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

CTW – Water Asset Management Plan April 2014 Page 2

The storage catchment area is approximately 197 square kilometres and the surface area of the dam, when full,

is approx. 0.8 square kilometres (80 hectares).

Lake Rowlands

Scope and value of the assets

The scope and value of the assets covered by this plan are identified in the following table:

Asset Type Unit Quantity Replacement Value

Lake Rowlands Supply Area Water Filtration Plants ea 3 $ 10,980,439.52

Pump Stations ea 32 $ 3,434,205.00

Bores ea 6 $ 276,400.00

Reservoirs ea 40 $ 12,039,840.00

Dams - Lake Rowlands ea 1 $ 18,459,420.00

Dams - Bogolong ea 1 $ 1,348,864.00

Telemetry ea 28 $ 316,289.52

Trunk Main 25mm m 360 $ 21,000.00

Trunk Main 50mm m 8 $ 446.00

Trunk Main 100mm m

21,327 $ 2,079,768.25

Trunk Main 150mm m

80,160 $ 11,810,702.16

Trunk Main 200mm m

89,205 $ 11,819,633.36

Trunk Main 225mm m

43,187 $ 5,722,295.19

Trunk Main 250mm m

17,836 $ 3,119,435.62

Trunk Main 300mm m

17,681 $ 3,767,194.82

Trunk Main 324mm m

713 $ 151,871.95

Trunk Main 375mm m

9,258 $ 2,953,981.65

Reticulation Main 25mm m

804 $ 46,846.85

Reticulation Main 32mm m

43 $ 2,523.84

Reticulation Main 38mm m

2,759 $ 160,826.38

Reticulation Main 40mm m

309 $ 18,011.34

Reticulation Main 50mm m

6,367 $ 371,171.03

Reticulation Main 56mm m

146 $ 8,524.20

Page 7: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

CTW – Water Asset Management Plan April 2014 Page 3

Reticulation Main 58mm m

2,214 $ 129,057.58

Reticulation Main 63mm m

1,706 $ 99,488.54

Reticulation Main 65mm m

26 $ 1,524.94

Reticulation Main 75mm m

12,388 $ 722,220.65

Reticulation Main 80mm m

15,315 $ 1,185,057.73

Reticulation Main 100mm m 178,801 $ 17,435,703.09

Reticulation Main 110mm m

101 $ 9,805.05

Reticulation Main 125mm m

922 $ 89,930.18

Reticulation Main 150mm m

30,619 $ 4,511,416.45

Reticulation Main 180mm m

268 $ 26,106.91

Reticulation Main 200mm m

5,643 $ 747,655.96

Reticulation Main 250mm m

235 $ 41,085.59

Reticulation Main 300mm m

1,964 $ 418,504.31

Total $ 114,327,247.67

Quandialla Pump Stations ea 3 $ 162,463.00

Bores ea 2 $ 106,560.00

Reservoirs ea 6 $ 125,000.00

Telemetry ea 1 $ 10,192.48

Trunk Main 100mm m

16,320 $ 1,591,543.81

Reticulation Main 100mm m

2,308 $ 225,066.52

Reticulation Main 150mm m

312 $ 45,942.48

Total $ 2,266,768.29

Condition assessment of the infrastructure assets as at 30/06/2009

Asset Capacity Year of Construction

Design Life

Condition 1 - Poor 10 -Perfect

Storages - Lake Rowlands 4,500 ML 1950 100 yrs 6 - Bogolong 295 ML 1930 100 yrs 3

Reservoirs

Blayney - Hill Street 1.14 ML 1930 100 yrs 6

- Filtration Plant 4.55 ML 1966 100 yrs 6

- Patricks Subdvn 0.45 ML 1974 100 yrs 6

- Plumb Street 0.91 ML 1958 100 yrs 6

Millthorpe 1.36 ML 1954 100 yrs 6

Trunk Main 'D' - Browns Creek

0.23 ML 1954 100 yrs 6

Page 8: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

CTW – Water Asset Management Plan April 2014 Page 4

Asset Capacity Year of Construction

Design Life

Condition 1 - Poor 10 -Perfect

Carcoar - Village 0.68 ML 1954 100 yrs 6

- Filtration Plant 2.16 ML 1954 100 yrs 4

Mandurama 0.91 ML 1954 100 yrs 6

Lyndhurst 0.68 ML 1954 100 yrs 6

Garland 0.09 ML 1954 100 yrs 6

Bangaroo No.1 0.18 ML 1968 100 yrs 6

Bangaroo No.2 0.18 ML 1968 100 yrs 6

Bangaroo No.3 0.18 ML 1968 100 yrs 6

Gooloogong Bore 0.18 ML 1977 100 yrs 6

Grenfell -West 1.36 ML 1930 100 yrs 6

- South 0.09 ML 1970 100 yrs 6

- East No 1 0.18 ML 1965 100 yrs 7

- East No 2 0.45 ML 1990 100 yrs 9

- North 4.55 ML 1959 100 yrs 6

Eugowra -Main 1.36 ML 1955 100 yrs 6

- Hill Street No. 1 0.09 ML 1971 100 yrs 6

- Hill Street No. 2 0.40 ML 2003 100 yrs 9

- Bore 0.09 ML 1977 100 yrs 6

Trajere 0.14 ML 1965 100 yrs 6

Pyes Gap 0.14 ML 1965 100 yrs 6

Canowindra 0.91 ML 1933 100 yrs 6

South Canowindra No. 1

0.18 ML 1986 100 yrs 6

South Canowindra No. 2

0.27 ML 1990 100 yrs 6

North Canowindra No.1

0.09 ML 1967 100 yrs 6

North Canowindra No.2

0.09 ML 1967 100 yrs 6

Morebel 1.14 ML 1955 100 yrs 6

Nyrang Creek No 1 0.14 ML 1969 100 yrs 6

Nyrang Creek No 2 0.09 ML 1969 100 yrs 6

Nyrang Creek No 3 0.05 ML 1969 100 yrs 6

McDonalds Lane 0.14 ML 1981 100 yrs 6

Cargo 0.68 ML 1957 100 yrs 6

Cudal 0.23 ML 1957 100 yrs 6

Manildra 0.45 ML 1957 100 yrs 6

Greys Hill 2.27 ML 1962 100 yrs 6

Quandialla x 7 0.18 ML 2002 100 yrs 9

Page 9: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

CTW – Water Asset Management Plan April 2014 Page 5

Asset Capacity Year of Construction

Design Life

Condition 1 - Poor 10 -Perfect

Bores

Bangaroo 1999 30 yrs 5 Bangaroo -Standby 1987 30 yrs 5 Cudal 1994 30 yrs 8 Gooloogong No. 1 1993 30 yrs 6 Gooloogong No. 2 1987 30 yrs 2 Quandialla 2002 30 yrs 7 Filtration Plants

Blayney Water Filtration Plant 6 ML/day 1966 50 yrs 4

Carcoar Water Filtration Plant

9 ML/d ML/day 2002 50 yrs 8

Pumping Stations Blayney Shire - 8 Pumping Stations 50 7

housing 18 pumps of varying sizes 25 7 Cabonne Shire - 13 Pumping Stations 50 7

housing 24 pumps of varying sizes 25 7 Weddin Shire - 7 Pumping Stations 50 7

housing 17 pumps of varying sizes 25 7 Trunk Mains

Trunk Main 'A' - Lake Rowlands to Carcoar WFP 375mm x 4.81 kms 1955 70 yrs 4

Trunk Main 'B' -Carcoar WFP to Mandurama 250mm x 5.47 kms 1955 70 yrs 4

Trunk Main 'C' - Mandurama to Gooloogong 200mm x 16.33 kms 1946-1955 70 yrs 3 225mm x 47.50 kms 1946-1955 70 yrs 3 250mm x 8.68 kms 1946-1955 70 yrs 3

Trunk Main 'D' - Carcoar WFP to Browns Creek P/Stn 200mm x 19.88 kms 1955 70 yrs 5

Trunk Main 'E' - Browns Creek P/Stn to Blayney - 150mm x 3.15 kms 1954 70 yrs 5 Trunk Main 'F' -Browns Creek P/Stn to Millthorpe - 150mm x 8.38 kms 1954 70 yrs 5 Trunk Main 'G' - Trunk Main 'C' to Lyndhurst - 100mm x 2.13 kms 2007 70 yrs 9 Trunk Main 'K' -Gooloogong to Grenfell

200mm x 34.12 kms 1946 70 yrs 1 Trunk Main 'L' - Gooloogong to Eugowra

150mm x 20.00 kms 1980 70 yrs 6 Trunk Main 'P' - Trunk Main 'C' to Somers

100mm x 1.72 kms 1955 70 yrs 2 100mm x 1.50 kms 1990 70 yrs 8

Page 10: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

CTW – Water Asset Management Plan April 2014 Page 6

Asset Capacity Year of Construction

Design Life

Condition 1 - Poor 10 -Perfect

Trunk Main 'Q' - West Wyalong Road to Quandialla

100mm x 17.50 kms 2003 70 yrs 8

Trunk Main 'U' - Trunk Main 'C' to Manildra

150mm x 34.39 kms 1957 70 yrs 4

150mm x 12.10 kms 2004 70 yrs 9

100mm x 12.21 kms 1957 70 yrs 5

Trunk Main 'V' - Trunk Main 'C' to Morebel

200mm x 4.20 kms 1990 70 yrs 7

Trunk Main 'X' -Lake Rowlands to Blayney

375mm x 1.61 kms 1966 70 yrs 5

300mm x 13.33 kms 1966 70 yrs 5

Reticulation Mains

Blayney Shire - 100mm x 51.20 kms 1930-2005 70 yrs 4

- 150mm x 15.68 kms 1930-1970 70 yrs 4

- 200mm x 1.15 kms 1930 70 yrs 4

- 300mm x 3.94 kms 1965-1973 70 yrs 4

Cabonne Shire - 58mm x 1.13 kms 1957 70 yrs 6

- 100mm x 71.35 kms 1930-2005 70 yrs 6

- 150mm x 10.23 kms 1950-2005 70 yrs 6

Weddin Shire - 100mm x 39.41 kms 2002-2003 70 yrs 9

- 150mm x 2.05 kms 2002-2003 70 yrs 9

- 250mm x 2.84 kms 2003 70 yrs 9

Buildings

Blayney Bulk Store 1972 70 yrs 5

Chemical Shed 1972 70 yrs 5

Workshop 1972 70 yrs 5

Canowindra Office 1973 50 yrs 4

Workshop/Store 1994 70 yrs 7

Grenfell Workshop and Office

1997 70 yrs 8

Administration Office - Blayney

1930 100 yrs 5

Page 11: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

CTW – Water Asset Management Plan April 2014 Page 7

1.3 The Asset Management Plan

The AM plan is a tool combining management, financial, engineering and technical practices to ensure the level

of service required by customers is provided in the most efficient and economical manner possible to the

community. The plan is also intended to protect the environmental and cultural values of the assets providing

the service.

This AM plan is a written representation of intended AM programmes for the water infrastructure network based

on CTW’s understanding of customer requirements, existing and projected network and the asset conditions

and performance.

The plan is the medium by which Council articulates its management of its water supply infrastructure to

achieve the desired outcomes.

Asset Management

Plan

Commercial TacticsOrganisational Issues

People Issues

Processes &Methodologies

Information Systems

Knowledgeand Data

Management Practices

Implementation Practices

Planning Practices

Figure 1-1: Asset Management Plan

The scope of the AM Plan relates to the four broad AM plan inputs and outputs.

Processes: The processes, analysis and evaluation techniques needed to support effective lifecycle AM.

Information Systems: The information systems to support AM processes and manipulate data.

Data: Appropriate, accessible and reliable data for manipulation by information systems to produce the outputs

required.

Implementation Tactics: Including organisation, contractual and people issues.

1.4 Plan Format The figure below follows the logic of the AM planning process and illustrates the relevant AMP section

references in this plan.

Page 12: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

CTW – Water Asset Management Plan April 2014 Page 8

DEFINE LEVEL O F SERVICE

Section 2

L.O .S INPUTS• S tra teg ic • Environm enta l • Legisla tive • Custom er • F inancia l • Politica l PREDICT DEM AND

Section 3

DECIS IO N TO O LS

AM system s • Data • Processes • Analys is techniques

Section 7

PREPARE ASSET LIFE CYCLE PLANS

Evaluate asset condition/ perform ance

• Identify m anagem ent tactics

Identify, eva luate & se lect options •

Develop work program m es Section 5

PREPARE FINANCIAL FO RECASTS Section 6

M O NITO R PERFO RM ANCE & AM PLAN IM PRO VEM ENTS

Section 7

XX

CO NSIDER RISKS Section 4

1.5 Key Stakeholders

This plan is intended to demonstrate to stakeholders that Council is managing the assets responsibly. The key

stakeholders include:

• State and Federal Government;

• Councillors;

• Community;

• Visitors;

• Utilities/Developers;

• Employees/Volunteers;

• Contractors/Suppliers;

• Insurers;

• Auditors – internal/external;

• Grant Providers;

• Constituent Councils;

• Central West Utilities Alliance (CWUA)

• Regulators;

1.6 Legislative Requirements

There are a number of Acts that affect the management of water supply assets. These Acts mainly affect

environmental protection and performance criteria. The principal ones are:

• Local Government Act 1993

• Australian Drinking Water Guidelines 2011

• The Pollution Control Act 1994

• The Clean Water Act 1970

Page 13: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

CTW – Water Asset Management Plan April 2014 Page 9

• Protection of the Environment Operations Act 1997

• The Environmentally Hazardous Chemical Act 2008

• Environment Protection Act 1994

• Environmental Planning and Assessment Act 1979

• Catchment Management Act 1989

• Soil Conservation Act

• Work Cover

• Protection of Threatened Species Act

• Fisheries Act

• Work Health & Safety Act 2012

• Government Pricing Tribunal Act 1992

1.7 Relationships with Other Plans and Documents

AM Plans are a key component of the Council planning process linking with the following plans and documents:

• CTW Strategic Management Plan - The Plan incorporates Council’s budget for the next 12

months with projections for the following ten years, and also a thirty year Capital Works

Financial Plan. The plan also reflects Council’s priorities and the direction being taken in

the short term, the next ten years and long term thirty year period.

• Operating Management Plan.

• CTW Section 64 Developer Servicing Plan.

1.8 Rationale for Asset Ownership

Local Authorities exist principally to supply core services that meet the needs of their communities. What

services are provided, and how they are provided, depends on the level of service required by the community.

Membership in the CWUA will provide assistance with the development of best practice strategies, obtaining

funding and skill and resource sharing between member councils.

As the water supply asset owner CTW will continue to provide a water supply system of superior environmental

sensitivity that is reliable and efficient and meets current and future community needs at an affordable cost.

Page 14: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

CTW - Water Asset Management Plan 22.04.14 Page 10

2.0 Levels of Service

2.1 Introduction

Levels of Service provide the basis for the life cycle management strategies and works programme identified within the AM Plan. They support the CTW’s strategic goals and are based on the expectations of CTW’s customers, and statutory requirements. Levels of service are there so that the community knows what to expect and are based to a certain extent upon what the community wants. CTW’s objective when planning for asset management is to match the level of service provided by the asset with the expectations of the consumer and visitors to the shire. The expectations of the consumer will be continually monitored so that the levels of service of the asset can be maintained appropriately. CTW will endeavour, through the levels of service, to provide the most cost efficient and value for money service to its consumers. The levels of service in this Section will be used:

• to inform the consumers of CTW of the proposed type and level of service to be offered; • develop asset management strategies to deliver the required level of service; • to identify the costs and benefits to the consumer of the services offered; • to enable the consumers of CTW to asses suitability and value for money of the services

offered; • as a measure of the performance of the AM Plan, and;

The levels of service outlined in this Section are based on:

• Community Research and Expectations • Information gathered from customers on expected quality and cost of services; • CTW’s mission and strategic objectives as detailed in Councils Strategic/Management

Plan - 2010/2015; • Availability of resources, particularly financial constraints; • Legislation, Regulations, Environmental Standards and Council by-laws that impact on the

way assets are managed; • Council policies and procedures; • Design Standards and Codes of Practice; • Australian Design Standards also provide the minimum design parameters for

infrastructure delivery by the Professional Engineer • Research conducted to predict future trends.

Page 15: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

CTW – Water Asset Management Plan April 2014 Page 11

The relationship between ‘levels of service’ with key Council plans is outlined in the figure below:

2.2 Levels of Service Requirements

This section identifies the necessary criteria to develop appropriate levels of service by considering legislative, customer and strategic needs. Councill will continue to provide services to the current high level and in addition will endeavour to improve on the following requirements as shown below.

LEGISLATIVE Key Service / Performance Criteria Reference: 1. Need to be more accountable and need for better use of management plans, and comply with State Government Best Practice requirements. 2. Need for continual upgrading of system 3. Maintain user pays pricing system

Local Government Act 1993 NSW Office of Water Best Practice Requirements Environmental Offences and Penalties Act 1989 & Environmental Planning and Assessment Act 1979. Public Health Act Work Health & Safety Act 2012 Government Pricing Tribunal Act 1992

CUSTOMER Key Service / Performance Criteria Reference: 1. Reliability 2. Value/Affordability 3.Maintenance

CTW Strategic Business Plan for Water Supply Services CTW Social and Community Plan Locality Meetings

CTW Strategic Management Plan 2010-2040

(Long term Objectives)

Council Management Plan 2011-2021 (Goals to achieve objectives)

Best Value Consultation (Affordable Target Setting)

Service Delivery Service Level Definition

Asset Management Plan (Funding Program)

Page 16: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

CTW – Water Asset Management Plan April 2014 Page 12

STRATEGIC / CORPORATE GOALS Key Service / Performance Criteria Reference: 1. Reliability 2. Value/Affordability 3. Maintenance 4. Compliance with Legislation 5. Customer satisfaction

As above CTW Management Plan 2010 – 2021

2.3 Community Research and Expectations

This Section outlines Council’s knowledge and research of customer expectations. It describes the methods of collecting data and outlines how this information is used. Customer Research and Expectations

Council’s customer research into water supply infrastructure needs and satisfaction has included: • Locality meetings • Receipt of complaints

2.3.1 Community Satisfaction Survey

From time to time CTW will undertake Community Satisfaction Surveys to gain extra feedback and gauge the consumer’s level of satisfaction with the current service. The first of these surveys is planned for early 2012/2013. Interpretation of results

Council will use the community satisfaction surveys as a performance measure of customer satisfaction.

2.4 Strategic and Corporate Goals

This Section outlines the specific levels of service, which CTW wishes to achieve, as defined in its Strategic/Management Plan 2008/2013 and Asset Management Policy. It also outlines details of Best Practice. Council’s strategic goals and mission statement for water supply are also detailed in this section. Council’s Vision and Mission

The Council Mission:

“Central Tablelands Water will develop a commercial focus as it operates in partnership with the communities it serves, fostering their development and growth, while maintaining both its level of service and its prices at an acceptable level.”

The Council’s Vision:

Central Tablelands Water sees its future as a Regional Water Authority, independent of other agencies. It sees itself as a responsible member of the communities it serves, aiding the development of the region. It will continue to develop further sources of water and continue to supply an economical and acceptable water supply to its customers, and it will do so in an ecologically sustainable manner. Central Tablelands Water will continue to evolve its method of operations to incorporate a sound commercial focus. It will do so without compromising on the services it provides, becoming more efficient and maintaining process at a reasonable level.

Page 17: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

CTW – Water Asset Management Plan April 2014 Page 13

AM Policy

CTW is currently developing an AM policy with consideration of points as detailed below, identified as needed through AM plan development. The Council’s Vision in its Asset Management Policy will be: To develop, implement and continually review an Asset Management Plan that will:

• Apply to all the asset groups under the care and control of CTW; • Include a total life cycle approach to asset needs identification to asset disposal; • Will be subject to a disciplined continuous improvement program

Asset Management goals identified for inclusion in the Asset Management Policy are:

• To work closely with consumers to meet their needs, taking into account an appropriate balance between service delivery, risk, reliability and costs;

• To act in a manner which is consistent with the preservation of the natural environment and the sustainable management of resources;

• To achieve a position of leadership in the water utility industry.

2.4.1 Best Practice

Best Practice management is fundamental to the effective and efficient delivery of water supply services. The NSW Government is required to demonstrate compliance with National Competition Policy. From 1 July 2004, compliance with the six best-practice criteria is mandatory for future assistance under the Country Towns Water Supply & Sewerage Program. With increasing demands on the limited water resources of NSW, it is vital that these resources are managed in an efficient and sustainable manner. Best-practice management is essential for efficient and sustainable management of water resources and the environment. It enables Council to achieve sustainable water supply business and comply with National Competition Policy. Best–practice management involves a triple bottom line focus that provides a balanced view of the long-term sustainability of NSW water utilities. Triple bottom line accounting (social, environmental and economic) involves consideration of Council’s business plan together with its social and environmental management practices. Best-practice management of water supply and sewerage involves the following six criteria:

• Strategic Business Planning • Pricing and Developer Charges • Demand Management • Drought Management • Performance Reporting • Integrated Water Cycle Management

2.5 Legislative Requirements, Standards and Codes of Practice

This Section details CTWs legal obligations relating to the management of its water supply infrastructure assets. It outlines the relevant legislative requirements, standards and codes of practice that Council must adhere to in order to provide an appropriate water treatment and reticulation service.

Page 18: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

CTW – Water Asset Management Plan April 2014 Page 14

Legislative Requirements, Standards and Codes of Practice.

The following legislative requirements, Standards and Codes of Practice, with respect to levels of service, are to be taken into account:

REFERENCE DETAILS Local Government Act 1993 Provide a legal framework for an effective, efficient,

environmentally responsible, and open system of Local Government in NSW.

Australian Drinking Water Guidelines –NHMRC 2011 & NRMMC 2011

Outlines minimum quality standards for potable water.

Pollution Control Act 1994 Clear Air ACT 1961 The Clean Water Act 1970 Protection of the Environment Operations Act 1997 The Environmentally Hazardous Chemical Acts 2008

These acts give Environment Protection Authority the power to control pollution and the disposable of wastes, to protect the environment, and to avoid chemical contamination from both Government and private developments or works.

Environmental Planning and Assessment Act 1979

Specifies the environmental considerations required in all development activities.

Catchment Management Act 1989 To Co-ordinate policies, programs and activities as they relate to total catchment management.

Soil Conservation Act The object of this Act is the conservation of soil resources and farm water resources and the mitigation of erosion and land degradation.

Public Health Act 2010 Consolidates Acts relating to Public Health and provides for the prevention of the spread of disease.

Work Health & Safety Act 2012 This Act details Council’s responsibilities to ensure health, safety and welfare of employees and others at places of work.

Government Pricing Tribunal Act 1992 The Government Pricing Tribunal Act establishes the Government Pricing Tribunal and enables the Tribunal to determine and advise on prices and pricing policy for Government monopoly services.

2.6 Current/Target Levels of Service This section details the current levels of service provided by Council, dividing them into customer and technically related groups, and the assets covered by those levels of service. This section also details where/how the levels of service have been derived. Types of levels of service

The service levels are divided into two types: • Customer related • Technically related

Customer related levels of service relate to the function of the service provided and how the customer receives the service in terms of:

Level of Service How the level of service was derived Appearance Customer feedback – letters, phone calls etc Reliability Customer expectations, quality of materials Maintenance Customer feedback and expectations Responsiveness Customer expectations, availability of resources Availability Customer expectation, assumption based on local knowledge Safety Legislative requirements, customer expectation Affordability Customer expectation, budgetary constraints Empathy (understanding, individual attention)

Customer feedback , assumption based on local knowledge

Assurance/customer/community satisfaction

Customer expectations and feedback

Page 19: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

CTW – Water Asset Management Plan April 2014 Page 15

Customer feedback is recorded using “Customer Service Request” forms and action is taken according to the severity of the fault, this is determined by an Intervention Level ranking as explained in Section 4.1.6. Technically related levels of service relate to the technical measures and the outputs the customer receives in terms of: Level of Service How the level of service was derived Quality Legislation, customer expectation Maintainability Availability/quality of resources Capacity Size of asset, design constraints Legislative requirements Relevant Authorities Cost Efficiency Available resources, management of asset Assets covered by Levels of Service

The following tables identify the current service levels adopted and the targets set by council for: • Filtration Plants; • Pump Stations, • Reservoirs and • Mains.

Page 20: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

CTW – Water Asset Management Plan April 2014 Page 16

2.7 Levels of Service Tables

2.7.1 Community Levels of Service

Levels of Service   

DESCRIPTION UNIT LEVEL OF SERVICE

Current Target

AVAILABILITY OF SERVICE

Normal Quantity Available:

Domestic Peak day

Domestic Annual

Total Annual Average Consumption

Total Peak Daily Consumption (Potable)

Peak/Average consumption

L/tenement/day

kL/tenement/yr

ML/yr

ML/day

%

3,000

254

2,110

16

211

3,000

254

2,000

16

211

Fire Fighting:

Compliance with the Water Supply Investigation Manual* (AS 2419.1 classifications 2,3,4 & 9 with floor area less than 1000 m2)

% urban area served 100 100

Pressure:

Min. pressure when delivering 15 L/min

Max. static pressure

Metres head

Metres head

20

60

20

60

Flow Rates:

Domestic (non-rural consumers) 15 L/min

Rural

litres/minute

litres/minute

25

6.3

25

6.3

Consumption Restrictions in Droughts:

Level of restriction applied through a repeat of the worst drought on record

− Average duration of restrictions

− Average frequency of restrictions

% Normal usage

No./ 10yr period

0

1

0

0

Supply Interruptions to Consumers

Planned (95% of time):

Notice given to domestic customers

Notice given to commercial customers

Notice given to major industrial and institutional customers

Unplanned:

Maximum duration

Frequency

Hours

Hours

Days

Hours No./yr/customer

48

48

7

12 2

48

48

7

12

<2

Page 21: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

CTW – Water Asset Management Plan April 2014 Page 17

DESCRIPTION UNIT LEVEL OF SERVICE

Current Target

Supply Failure: Priority 1 (Defined as failure to maintain continuity or quality of supply to a large number of customers or to a critical use at a critical time)

During working hours Out of working hours

Hours Hours

1 2

1 2

Priority 2 (Defined as failure to maintain continuity or quality of supply to a small number of customers or to a critical use at a non-critical time)

During working hours

Out of working hours

Hours

Hours

3

4

3

4

Priority 3 (Defined as failure to maintain continuity or quality of supply to a single customers)

Working Days 1 1

Priority 4 (Defined as a minor problem or complaint, which can be dealt with at a time convenient to the customer and the Council)

Weeks 1 1

Customer Complaints: − Personal/ Oral − Written

Note: Times apply for 95% of occasions

Working Days Working Days

5 5

5 5

Service Provision: Time to provide a domestic individual connection to water supply in serviced area (95% of times) Working days 10 10

WATER QUALITY (Should meet Drinking Water Quality Guidelines of Australia, NHMRC & NRMMC 2011)

Microbiological Parameters: Total coliforms Thermo-tolerant coliforms Sampling frequency

CFU/100ml CFU/100ml Samples/week

98

100 52

98 100 52

Physico-chemical Parameters:

pH

Turbidity

Fluoride

Free available chlorine (WFP)

Free available chlorine (Reticulation)

Sampling frequency

Unit

NTU

mg/L

mg/L

mg/L

Samples/year

7.5

<0.2

1

-

0.6

365

7.5

<0.2

1

-

0.6

365

Page 22: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

CTW – Water Asset Management Plan April 2014 Page 18

DESCRIPTION UNIT LEVEL OF SERVICE

Current Target Percentage Compliance with 2011 NHMRC / NRMMC Australian Drinking Water Quality Guidelines:

Physical parameters % 100 100 Chemical parameters % 100 100

Total coliforms % 98 98

Thermo-tolerant coliforms % 100 100 Note:  the  Levels of  Service  are  the  targets, which Council  aims  to meet;  they  are not  intended  as  a  formal  customer contract. 

Page 23: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

CTW – Water Asset Management Plan April 2014 Page 19

3.0 Demand Forecast

3.1 Introduction

This Section of the plan analyses factors affecting demand including population growth, social and technological changes. Impacts of the growth trends including social, cultural, residential, commercial and industrial are examined and in particular the impacts on new and existing infrastructure. Demand management strategies are place as a technique to modify demand without compromising customer expectations. A period of twenty years is considered.

3.2 Growth Trends

The key drivers of demand for CTW water infrastructure are: • Population growth; • Industrial growth; • Residential Development; • Demand for increased services; and • Extensions to the network

3.2.1 Population

Current and future population demographics of the three constituent council’s local government areas have an impact on demand on CTW’s infrastructure. Following is an analysis of future trends with regard to population indicators such as age profile and population distribution within each of the LGA’s. Population Growth by LGA

Local Government Area

Population Annual Growth (%) 1996 Census 2001 Census 2006 Census

Blayney 6,025 6,141 6,364 0.56 % Cabonne 12,105 11,813 12,395 0.24 % Weddin 3,831 3,660 3,641 -0.50 % Totals 21,961 21,614 22,400 0.20%

Source: Australian Bureau of Statistics. From the above data, it would appear that population growth within the LGA’s overall is largely static, or in a steady small (less than 1.0%) incline. Future population projections make assumption that the past population trends will continue, namely static or steady incline in the overall populations, unless there was a specific event such as a large development that drew new consumers to a particular centre.

Age Profile across Overall LGA’s

Age 1996 Census 2001 Census 2006 Census Population % Population % Population % NSW Av.

0 - 4 1,574 7.2 1,483 6.9 1,466 6.7 6.3% 5 - 14 3,643 16.8 3,543 16.4 3,456 15.6 13.5% 15 - 24 2,377 11.0 2,267 10.5 2,216 10.0 13.6% 25 - 54 8,733 40.2 8,459 39.1 8,414 38.0 42.2% 55 - 64 2,366 10.9 2,602 12.0 2,920 13.2 11.0 65 plus 3,012 13.9 3,276 15.1 3,652 16.5 13.3 Totals 21,705 100% 21,630 100% 22,124 100% 100%

Source: Australian Bureau of Statistics

Page 24: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

CTW – Water Asset Management Plan April 2014 Page 20

Age Profile across Overall LGA’s (Graph Form)

The following trends can be noted from the Age Profile data above and as graphed above:

• Population proportions in the under 24 age groups have remained largely static over the 1996 – 2006 period.

• There has been a steady increase in population proportion in the over 55 age groups over the 1996 – 2006 period, such that the 2006 CTW LGA percentage is 6.4% higher than the 2006 NSW average.

• The “working age” population proportion (25 – 54 age groups) has been in steady decline over the 1996 – 2006 period, to an extent that the 2006 CTW LGA percentage for this age group is 8% below the NSW state average.

The above data suggests that the CTW LGA, overall, has an ageing population trend.

The 1996 – 2006 period has seen a decrease in working age population with a corresponding increase in population in the over 55 year of age groups.

3.3 Residential Impacts

With the exception of perhaps Blayney and Millthorpe, generally within the CTW supply area, in both urban and rural areas, there is not predicted to be significant change to existing residential trends, with existing population remaining static or with very slow increase or decline. The village of Millthorpe has been identified as a potential growth centre, mainly due to its proximity to the regional centre of Orange. Growth in the town of Blayney appears to be benefitting from the increased gold mine development in the Shire. Neither of these should impact the water supply system substantially as growth is expected to be small and there is enough unused capacity available in the system for the foreseeable future.

3.4 Commercial/Industrial Impacts

Future commercial and industrial development within the 20 year forecast period is likely to be sporadic and difficult to predict. Isolated developments will have both initial and sustained impacts on the supply area in the form of:

- Spikes in population for high intensity phases such as construction with an ongoing employment demand dependant on development type.

- Increased demands on water services in regional centres as a result of population increase.

The current water supply infrastructure has enough capacity to service any increased load due any new developments in the foreseeable future.

Page 25: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

CTW – Water Asset Management Plan April 2014 Page 21

3.5 Current Developments and Impacts

Due to the minor nature of future growth in the LGA, the primary goal of current asset planning is management of current infrastructure and continued upgrade of existing infrastructure to meet modern community expectations and best practice.

3.6 Impact of Trends on Infrastructure

3.6.1 Existing Infrastructure

Given the lack of any significant growth forecast over the next 20 year period, the overwhelming focus of this Asset Management Plan is management of Council’s existing infrastructure base. Aging of existing assets is an issue, in particular the trunk main system across the supply area, this has no bearing on its capacity to service future demand and is addressed in a later section of this plan.

3.6.2 New Infrastructure

New infrastructure will be provided to Council’s water supply network generally through either development contribution or upgrade of existing infrastructure by Council. Additional assets due to new developments are relatively minor and will not impact greatly on the capacity of the existing infrastructure Council provided new asset infrastructure will generally be the replacement or upgrading of existing assets.

Page 26: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

CTW - Water Asset Management Plan 22.04.14 Page 22

4.0 Lifecycle Management Plans

4.1 Introduction This Section of the plan outlines exactly what is planned in order to manage and operate CTW’s water supply assets at the agreed level of service (defined earlier in this plan) while optimising the lifecycle costs.

4.1.1 Section Contents

This section describes the lifecycle management plans for the following key asset groups:

1. Filtration Plants 2. Pump stations 3. Reservoirs 4. Reticulation 5. Trunk Mains

The lifecycle management plans outline for each asset:

• The objectives for the asset group. • Supporting data for each asset group including:

- Key life-cycle management issues - Physical parameters and value - Asset capacity/performance - Asset condition - Historical expenditure

• The management tactics to achieve the levels of service defined in Section 2, identified in

the following work categories: - Operations and maintenance - Renewals - New works - Disposal

4.1.2 Work Category Definitions

Operations Operations activities keep the asset utilised but have no effect on asset condition. Asset operation has no effect on asset condition but is necessary to keep the asset appropriately utilised. Typical operational activities for each asset group include: Filtration Plants

• Power Costs • Water Charges • Rates • Chemical costs for the treatment of the water • Licensing fees • Water testing • Data collection and cataloguing • Depreciation

Page 27: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

CTW – Water Asset Management Plan April 2014 Page 23

Pump Stations • Power Cost • Rates • Data collection and cataloguing • Depreciation

Reservoirs

• Rates • Data collection and cataloguing • Depreciation

Reticulation & Trunk Mains

• Data collection and cataloguing • Depreciation

For each of the operational activities an outline of how they are managed is detailed below. Data collection and cataloguing Captured and recorded via telemetry system. Power costs

Pump and Filtration Plant running times are monitored via telemetry system and adjusted as necessary in order to achieve minimum operation time with maximum efficiency.

Water Charges Purchase of raw water pumped from Lake Rowlands.

Rates Charged to the asset on an annual basis for the services provided to the land the asset occupies

Chemical Costs

Regular testing of potable water to ensure water quality and optimum chemical usage. Subsequent adjustment of chemical usage and cost comparison if required.

Licensing fees

Payment of fees as per legislative requirements set by State Water. Council has no control of licensing fee structure. Review of license necessity annually.

Depreciation

Depreciation is charged to the asset as per legislative requirements. It is determined based on the expected life of the asset.

For Council budgetary reporting purposes (as defined in Council’s Strategic Management Plan) Operations is classed as Operating Expenditure. Routine Maintenance Maintenance work is the day-to-day work required to maintain the asset’s ability to provide the required service levels It is the day to day work required to keep assets operating at required service levels, and falls into two broad categories:

• Planned or programmed (preventative) Maintenance: Proactive inspection and maintenance works planned to prevent asset failure.

• Unplanned (responsive) Maintenance: Response action to correct asset malfunctions and failures on an as required basis (i.e. emergency repairs).

Planned maintenance is carried out to optimise the life of the asset, monitoring by telemetry system and regular inspections but limited due to budgetary constraints. By collating the data from the above parameters and constraints, programs are formulated to prioritise and efficiently carry out the required maintenance.

Page 28: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

CTW – Water Asset Management Plan April 2014 Page 24

Unplanned maintenance is generated by complaints and emergencies. Complaints are assessed and dealt with on a case by case basis, whilst emergencies are dealt with immediately. The following table provides examples of planned and unplanned maintenance for each asset group.

Asset Group Planned Maintenance Unplanned Maintenance

Filtration Plant Inspections & checks Breakages

Servicing of mechanical components Breakdown

Property maintenance Electrical fault

Telemetry fault

Pump Stations Inspections & checks Pump breakdown

Servicing of pumps Electrical fault

Property Maintenance Telemetry fault

Reservoirs Inspections & checks Valve replacement

Valve exercising Telemetry fault

Desilting

Property maintenance

Reticulation & Trunk Mains

Inspections & checks Leak repairs

Mains flushing Mains flushing (dirty water)

Valve exercising Mains break repairs

Hydrant maintenance Valve repairs

Hydrant repairs

Meter replacement

Maintenance is defined in each section of the lifecycle plan, and includes:

• All repairs/maintenance which are not classified as renewals

• All inspections planned and unplanned A key element of advanced AM planning is determining the most cost-effective mix of planned and unplanned maintenance. Renewals Renewal work is the substantial replacement of the asset or a significant asset component to its original size and capacity

Page 29: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

CTW – Water Asset Management Plan April 2014 Page 25

These works are defined as being: • The renewal and rehabilitation of existing assets to their original size and capacity, or, • The replacement of the entire component of the asset with the equivalent size or capacity,

or, • The replacement component of the capital works which does not increase the capacity of

the assets (that portion of the work which restores the assets to their original size and capacity).

Renewals expenditure includes the following:

• Replacement of existing mains - With the same capacity along existing alignment

- Upgrading along existing alignment • Replacement of valves and hydrants • Rehabilitation of pump stations

- Replacement/upgrading of components - Upgrading of switchboard - Upgrade capacity of pump station

• Replacement of existing pump stations • Rehabilitation of Filtration Plant/s

- With the same capacity - Upgrade of components

- Replacement of existing surfacing – concrete, asphalt, brick and other pavers • Replacement of Filtration Plant/s

For Council budgetary reporting purposes (as defined in Council’s Strategic Management Plan) Renewals are classed as Non-Operating Expenditure (or Capital Works). Planned renewals are identified in Councils Thirty Year Financial Plan. New Works New works create an asset that did not exist, or extend an asset beyond its original size or capacity. Projects (including land purchase) for the extension or upgrading of assets required to cater for growth or additional levels of service, including:

• Works which create an asset that did not exist in any shape or form, or • Works which improves the Filtration Plants, pump stations, reservoirs or reticulation

beyond their original size or capacity, or • Upgrade works which increase the capacity of the Filtration Plant, pump stations,

reservoirs or reticulation, or • Works designed to produce an improvement in the standard and operation of the Filtration

Plant, pump stations, reservoirs or reticulation beyond their current capacity.

For Council budgetary reporting purposes (as defined in Council’s Strategic Management Plan) New Works are classed as Non-Operating Expenditure (or Capital Works).

The CTW Forward Financial Plan reports on Water Supply Services as shown below. Operating Expenditure

• Management Expenses • Pumping Stations • Reservoirs • Water Filtration Plants • Mains • Miscellaneous (incl. Interest, Depreciation, Plant etc.)

Non-Operating Expenditure

• Loan Principal Repayments • Transfer to Reserve • Capital Works

Page 30: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

CTW – Water Asset Management Plan April 2014 Page 26

Asset Disposal Asset disposal is defined as the decommissioning and/or removal of the asset. In the past Council has disposed of Filtration Plants and pump stations by decommissioning, removing useable equipment and isolating from the reticulation system. In some cases the land and remaining infrastructure has been disposed of otherwise the infrastructure has been left in place unused, unless there is a beneficial reason, site reestablishment is not undertaken. Reticulation and trunk mains that have been replaced or rerouted are disconnected from the active mains and left in-situ. Council currently has no policy in place for the disposal of water assets. There are no future plans for the disposal of any part of the water supply asset.

4.1.3 Asset Hierarchy

The asset hierarchy adopted by CTW is defined in this section together with an explanation of the purpose of the hierarchy. The objective of developing an asset hierarchy is to provide a suitable framework for assets, which segments the asset base into appropriate classifications. The hierarchy can be based on asset function, asset type or a combination of the two. The hierarchy must however meet short and long term asset management requirements. The intent of the asset hierarchy is to provide the framework in which data is collected, information is reported and decisions are made. In most cases organisations work with an informal asset hierarchy, however, this often leads to data being collected to inappropriate levels, thereby either creating situations where costs escalate with minimal increases in benefit or insufficient information is available to make informed decisions. The asset hierarchy is used to structure the framework, to formalise the understanding of the levels at which decisions take place and to understand the levels at which actions such as data collection takes place and outputs are generated. The adopted asset hierarchy is defined in the following table.

Water Supply Assets Asset Group Asset Category Asset Component

Filtration Plant Carcoar WFP Blayney WFP Gooloogong & Cudal Chlorination Plants

Civil Mechanical Electrical

Pump Stations Various locations (32)

Civil Mechanical Electrical

Reservoirs Various locations (46)

Civil Electrical (telemetry)

Reticulation & Trunk Mains Trunk Mains (295km) Reticulation Mains (278km)

Pipe sections (incl. valves and hydrants)

Dams Lake Rowlands Dam Bogolong Dam

Civil Mechanical Electrical

Groundwater Bores Various locations (5) Civil Mechanical Electrical

Page 31: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

CTW – Water Asset Management Plan April 2014 Page 27

4.1.4 Maintenance Contract

Council has no formal maintenance contract associated with any part of its water supply infrastructure.

4.1.5 Inspections

Inspections are designed to identify defects that have the potential to create a risk of damage or inconvenience to the public. The inspections are aligned with the hierarchy and recommend outcomes that may require maintenance or changes to processes. The inspections are designed to highlight and prioritise maintenance works and assist in the planning of future renewals. Personnel undertaking the inspections have been trained to comply with relevant OH&S legislation to undertake the activities and are conversant with the Council’s inspection procedures and safety requirements. The following types of inspection are carried out:-

Maintenance Inspections/ Visual inspections

Inspections are currently carried out on a daily basis for Carcoar and Blayney WFP’s. Checks include

visual inspections of mechanical components (to see that they are running/operating O.K.), electrical

components (Alarms and switches are operating to settings) and water testing for quality. The pump

stations and reservoirs are inspected similarly on a weekly basis. The WFP’s, pump stations and

reservoirs are continuously monitored via telemetry.

Safety Inspections

A hazard analysis and risk assessment is carried out before commencing any job.

The following table details the inspection and inspection frequencies undertaken for each asset group.

Asset Group Inspection Type Frequency Outcome

Filtration Plant - Visual Daily Operating as expected – normally

Carcoar Safety Daily Safe working environment

Water Testing Daily Water Quality

Telemetry Continuously Alarms – abnormal operation

Filtration Plant - Visual Daily Operating as expected – normally

Blayney Safety Daily Safe working environment

Water Testing Daily Water Quality

Telemetry Continuously Alarms – abnormal operation

Pump Stations Visual Weekly Operating as expected – normally

Safety Weekly Safe working environment

Telemetry Continuously Alarms – abnormal operation

Reservoirs Visual Weekly Operating as expected – no leaks

Safety Weekly Safe working environment

Telemetry Continuously Alarms – abnormal operation

Reticulation Visual As necessary Repair fault

Page 32: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

CTW – Water Asset Management Plan April 2014 Page 28

4.1.6 Intervention Levels

The intervention levels support the service levels provided to the community as they define the trigger points in determining the type of works to be carried out. They are also very useful in the development of ongoing maintenance programs. Having defined intervention levels also assists council in being able to organise maintenance works on a risk priority basis, rather than be susceptible to carrying out works on a chronological basis, or as a result of pressure from individuals within the community i.e. complaints. Refer also to Section 2.6.

Defect Measurement

Criteria Intervention

Level Response Time Action

Pump Failure Low level at Raw Water intake Chemical Dosing System fault Low/High Reservoir level Plant Shutdown Chlorine leak

Yes/No Yes 2 hr Correct Fault

System Failure Priority 1

Yes/No Yes 1 hr 2 hr (AH)

Correct Fault

System Failure Priority 2

Yes/No Yes 3 hr 4 hr (AH)

Correct Fault

System Failure Priority 3

Yes/No Yes 1 Working Day Correct Fault

System Failure Priority 4

Yes/No Yes 1 Week Correct Fault

Personal Complaints Yes/No Yes 5 Working Days Investigate & correct fault

Written Complaints Yes/No Yes 5 Working Days Investigate & correct fault

System Failure Priority level is used to determine the response time to particular faults and is defined as; Priority 1 - a failure to maintain continuity or quality of supply to a large number of customers or to a critical user at a critical time. Priority 2 - a failure to maintain continuity or quality of supply to a small number of customers or to a critical user at a non critical time. Priority 3 - a failure to maintain continuity or quality of supply to a single customer. Priority 4 - a minor problem or complaint, which is dealt with at a time convenient to the customer and the Council. Response time is defined as the time to have staff on site, to commence rectification of the problem after notification by public or own staff.

4.1.7 Performance Monitoring

The following table describes the way in which each asset group is monitored: Asset Group Performance Monitoring Activities Filtration Plants Telemetry, Inspections, Complaints, Legislative Compliance Pump Stations Telemetry, Inspections, Complaints, Legislative Compliance Reservoirs Telemetry, Inspections, Complaints, Legislative Compliance Reticulation Inspections, Complaints, Legislative Compliance

Page 33: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

CTW – Water Asset Management Plan April 2014 Page 29

Telemetry The object of the telemetry system is to provide a continuous flow of data including flow rates, pumping times (cut in/cut out), faults etc so that Council can better assess the adequacy, capacity and efficiency of its water supply network. Inspections Inspections are designed to identify defects that have the potential to create a risk of damage or inconvenience to the public. The inspections are aligned with the hierarchy and recommend outcomes that may require maintenance or changes to processes. The inspections are designed to highlight and prioritise maintenance works and assist in the planning of future renewals. Complaints Complaints are received from users of the asset (consumers) and are used to identify inadequacies and/or inefficiencies in the system. All complaints and resulting actions are recorded, using “Customer Service Request” forms, for future reference and used to aid in the prioritisation of future maintenance works. Legislative Compliance There are certain conditions relating to the operation of the water supply asset that Council must comply with by law. Compliance with these conditions ensures that the system is operating to a minimum required standard. These activities identify inadequacies within the water supply infrastructure and are used to identify and prioritise maintenance and future works requirements.

4.1.8 Consultation Process

This section indicates the level of consultation undertaken by CTW in an effort to gain feedback about the water supply assets.

Public consultation is/will be undertaken through the following processes: • Best Practice • Special interest groups/stakeholders (regulatory bodies) • Consumer surveys • Public forums at bi-monthly Council meetings • Complaints

The outcomes of these forms of consultation are used to identify and prioritise future works. They also serve as a conduit for information transfer between CTW and the community at large. They give the council and the public the opportunity to discuss issues regarding the asset. Generally the bulk of the consultation comes through complaints and via public display of policy documents. Public meetings are held to discuss major changes to the asset.

4.1.9 Boundary Issues

CTW’s water supply network does not extend beyond the three constituent council boundaries, except for a few

rural consumers in Bland and Forbes Council areas. It presently covers the townships and villages of Blayney,

Millthorpe, Carcoar, Mandurama, Lyndhurst, Somers, Canowindra, Morebel, Cargo, Cudal, Manildra, Eugowra

Grenfell and Quandialla.

Bulk water is also supplied to Cowra Shire for the villages of Gooloogong and Woodstock and Pierce’s rural scheme.

4.1.10 Council Ownership Functions

This section refers to the use of contractors and contractual arrangements undertaken by Council. Currently there are no contractual arrangements between Council and a contractor aside from minor day-to-day works as required.

Page 34: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

CTW – Water Asset Management Plan April 2014 Page 30

4.2 Asset Group 1 – Filtration Plant The purpose of this section is to outline how Council manages the Water Filtration Plants.

4.2.1 Objective

Council’s objective in owning and providing Water Filtration Plants is to provide a potable water supply to the community. The Water Filtration Plants treat raw water pumped from Lake Rowlands on the Coombing Creek and supply potable water to the town and villages, via trunk mains, through pump stations, reservoirs and reticulation pipelines.

4.2.2 Background Data

CTW operates two Water Filtration Plants at Carcoar and Blayney. The Carcoar Water Filtration Plant, located on Fell Timber Road., is Dissolved Air Flotation Filter (DAFF) plant commissioned in 2002 with design capacity 9 ML/day. The Blayney Water Filtration Plant located on Hills Lane, is conventional sand filter plant constructed in 1966 with design capacity of 6 ML/day. The Gooloogong groundwater supply system, which supplements water from Lake Rowlands in extreme peak demand periods ,a chlorine disinfection system, There are two bores at Gooloogong, No.1 was constructed in 1993 and No. 2 was constructed in 1987. The Carcoar WFP consists of the following main facilities.

o Filtered water pumping station o Chemical dosing pit o Six settling lagoons o Settled water pumping station o Two rapid gravity sand filters and associated pumps and air scour blower for filter backwashing o Clear water tank and pumping station o Chemical dosing facilities to meter alum, polyelectrolyte, chlorine, fluoride and powder activated

carbon o Compressed air facilities

Raw water gravitates from Lake Rowlands and treated water gravitates via trunk mains to reservoirs and the reticulation system. The Blayney WFP consists of the following main facilities.

o Chemical dosing pit o Three settling lagoons o Four gravity sand filters and associated pumps and air scour blower for filter backwashing o Clear water tank and pumping station o Chemical dosing facilities to meter alum, polyelectrolyte, chlorine, fluoride and powder activated

carbon o Compressed air facilities

Raw water is pumped from Lake Rowlands and treated water gravitates via trunk mains to reservoirs and the reticulation system.

The Gooloogong groundwater system consists of the following facilities. o Chlorination unit, pump station building and reservoir.

The chlorination unit and pump station building are adjacent to the reservoir and treats the raw water as it is pumped into the reservoir.

Page 35: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

CTW – Water Asset Management Plan April 2014 Page 31

Overview Some of the key life-cycle issues that affect the Water Filtration Plants are:

o Condition of system o Scheduled maintenance o Condition based maintenance and monitoring including regular maintenance o Works needed to meet Level Of Service o Community concerns o The age of the Asset o System Operating Rules o Operating Procedures per facility o Operational efficiency – Energy

Hierarchy The Water Filtration Plants are classified using the following hierarchy: Buildings Raw water supply Chemical pre-dosing Clarification and settled water pumping Filtration Clear water storage and pumping Air scour/backwash facilities Backwash recovery and residuals disposal Chemical handling, metering and dosing equipment Compressed air system Building services water system Sampling arrangements Plant control and instrumentation Asset Performance The Water Filtration Plants are monitored using the following techniques:-

• Telemetry • Inspections • Complaints • Legislative Compliance

Council’s Integrated Water Cycle Management Plan (IWCM) has identified that the two Water Filtration Plants and Gooloogong groundwater system have adequate capacity to supply the future demands of CTW for at least the next twenty years.

Maintenance Expenditure Forecasts Considerations include:

• Water Filtration Plant maintenance costs will increase if the water supply network grows in size and flow volumes increase.

• Historical costs have been between $173,000 and $187,000 over the last five years.

The 30-year financial plan allows for a relatively constant operation and maintenance costs of $570,000 per

annum, over the whole water supply system. Any increase in costs due to the ageing of the system will be

offset by staged replacement of deteriorating and therefore high maintenance components.

Page 36: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

CTW – Water Asset Management Plan April 2014 Page 32

4.2.3 New Works Strategies

Subdivision and capacity driven development All the Filtration Plants have ample capacity to accommodate any increased load due to new subdivisions, or other developments for the foreseeable future. New Works Expenditure Forecasts The 30 Year Financial Plan indicates that $0.7 million will be spent on an upgrade to the Blayney Water Filtration Plant in 2014/2015 and $1.4 million on an upgrade to Carcoar Water Filtration Plant in 2020/2021. No new capital works are planned.

4.3 Asset Group 2 – Pump Stations The purpose of this section is outline how Council manages the Pump Stations associated with the water supply reticulation system.

4.3.1 Objective

Council’s objective in owning and providing Pumping Stations is to provide a water supply system/service to the community. The water reticulation system supplies potable water to households, commercial and public premises through a network of pipelines that include storage reservoirs and pump stations.

4.3.2 Background Data

CTW operates two independent water supply systems, Lake Rowlands and Quandialla and operates 32 pump stations across the two systems with a total capacity of 26ML/day.

Overview Some of the key life-cycle issues that affect the Pump Stations are:

o Condition of Pump Station o Scheduled maintenance o Condition based maintenance and monitoring including regular maintenance o Works needed to meet Level Of Service o Community concerns o The age of the Asset o System Operating Rules o Operating Procedures per facility o Operational efficiency – Energy

Hierarchy The pumping stations group is classified using the following hierarchy: Civil Structure, including wells and bores Mechanical Components, including pumps, valves and pipe work Electrical Components, including switch gear, safety equipment and telemetry

Page 37: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

CTW – Water Asset Management Plan April 2014 Page 33

Asset Performance The Pumping Station is monitored using the following techniques:-

• Telemetry • Inspections • Complaints • Legislative Compliance

All the pump stations have adequate capacity to supply present and future forecast demand.

4.3.3 Operations

Operational activities should be explained incorporating the impacts of the operations on the assets. Operational activities for Pump Station relate to the following:

• Sequence to perform particular tasks • Priming and starting procedures • In-service operational checks • Routine test/operational procedures • Procedure for engaging stand-by pump • Resetting procedure • Procedure for using temporary equipment

All water pump stations are automatic in operation and generally unattended. To ensure reliable and cost-effective operation of these pump stations, an on-going program of systematic inspections, preventative maintenance and equipment overhaul is necessary.

Hierarchy Pump Station Inspection frequency (weeks)

Work area free from rubbish and obstructions

Weekly

Surface areas safe and suitable

Weekly

Cut/mow grass As necessary Operate ‘off duty’ pump As per operation manual

4.3.4 Maintenance

Maintenance work is the day-to-day work required to maintain the asset’s ability to provide the required service levels Work Definition In the case of pump station assets, maintenance affects mechanical, electrical and civil aspects and includes:

• Leaks at pump seat, pipe work • Excessive amp draw, vibration, irregular noise, overheating • Valve malfunction

General maintenance strategies include:

• Carry out systematic inspection of plant/equipment to detect and correct problems before they develop into costly major repairs, or replacements.

• Ensuring the pumping station is maintained to deliver the desired levels of service.

Page 38: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

CTW – Water Asset Management Plan April 2014 Page 34

Maintenance work is carried out by Council’s own employees. Maintenance Expenditure Forecasts Considerations include:

• Pump station maintenance costs will increase if the water supply network grows in size and flow volumes increase.

• Historical costs have been between $56,000 and $66,000 over the last five years.

The 30-year financial plan allows for a relatively constant pump station operation and maintenance costs of $134,000 per annum, over the whole water supply system. Any increase in costs due to the ageing of the system will be offset by staged replacement of deteriorating and therefore high maintenance components.

4.3.5 Renewal

Council’s 30 year financial plan has an annual provision of $41,000 for pump replacement if necessary.

4.3.6 New Works Strategies

Subdivision development Any new water pump station infrastructure required due to subdivisions is to be provided by the developer at their cost, not council’s. Capacity driven development Current population projections for the CTW LGA indicate that the current water supply network has adequate capacity for the foreseeable future. New Works Expenditure Forecasts There are no further pump stations being planned in the near future. Refurbishment of Gooloogong Bore is planned for 2021/2022 at an estimated cost of $780,000.

4.3.7 Disposal

There is currently no policy to dispose of water supply assets within CTW’s boundaries and it is not expected that any water pump stations will need to be disposed of in the foreseeable future.

4.4 Asset Group 3 – Reservoirs The purpose of this section is outline how Council manages the reservoirs associated with the water supply reticulation system.

4.4.1 Objective

Council’s objective in owning and providing reservoirs is to provide a water supply system/service to the community. The water reticulation system supplies potable water to households, commercial and public premises through a network of pipelines that include storage reservoirs and pump stations. The reservoirs store treated water to

Page 39: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

CTW – Water Asset Management Plan April 2014 Page 35

provide relatively constant water pressure to the reticulation system and also provides a reserve supply in case of Filtration Plant or pump station failure.

4.4.2 Background Data

CTW operates two independent water supply systems, Lake Rowlands and Quandialla and has 46 service reservoirs across the two systems with a total capacity of 29.6ML.

Overview Some of the key life-cycle issues that affect the reservoirs are:

o Condition of Reservoirs o Scheduled maintenance o Condition based maintenance and monitoring including regular maintenance o Works needed to meet Level Of Service o Community concerns o The age of the Asset o System Operating Rules

Hierarchy The reservoir group is classified using the following hierarchy: Civil Structure Mechanical Components, including valves and pipe work Electrical Components, including telemetry Asset Performance The Reservoirs are monitored using the following techniques:-

• Telemetry • Inspections • Complaints • Legislative Compliance

All the reservoirs have adequate capacity to supply present and future forecast demand.

4.4.3 Operations

Operational activities should be explained incorporating the impacts of the operations on the assets. There are minimal operational activities required for the efficient operation of reservoirs as most are performed automatically via the telemetry system. The operational activities that are carried out relate to the following:

• Sequence to perform particular tasks • In-service operational checks • Routine test/operational procedures • Procedure for using temporary equipment

All water reservoirs are automatic in operation and unattended. To ensure reliable and cost-effective operation of these reservoirs, an on-going program of systematic inspections, preventative maintenance and equipment overhaul is necessary.

Page 40: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

CTW – Water Asset Management Plan April 2014 Page 36

4.4.4 Maintenance

Maintenance work is the day-to-day work required to maintain the asset’s ability to provide the required service levels Work Definition In the case of reservoir assets, maintenance affects mechanical, electrical and civil aspects and includes:

• Leaks from reservoirs • Telemetry malfunction • Valve malfunction

General maintenance strategies include:

• Carry out systematic inspections to detect and correct problems before they develop into costly major repairs, or replacements.

• Exercise valves to ensure free movement. Maintenance work is carried out by Council’s own employees. Maintenance Expenditure Forecasts

Considerations include:

• Reservoir maintenance costs are not influenced by flow volumes but are influenced more by the age of the asset as frequency of leaks increase.

• Historical costs have been between $25,000 and $41,000 over the last five years.

The 30-year financial plan allows for a relatively constant operation and maintenance costs of $25,000 per annum, over the whole water supply system. Any increase in costs due to the ageing of the system will be offset by staged replacement of deteriorating and therefore high maintenance components. Reservoir Expenditure Forecasts The selection of the reservoirs to be refurbished or replaced is based on condition as outlined above.

The 30-year Financial Plan has provided $4.9 million reservoir upgrades or replacement in 2036/2037.

4.4.5 New Works Strategies

Subdivision development Any new reservoirs infrastructure required due to subdivisions is to be provided by the developer at their cost, not council’s. Capacity driven development Current population projections for the CTW LGA indicate that the current water supply network has adequate capacity for the foreseeable future.

Page 41: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

CTW – Water Asset Management Plan April 2014 Page 37

4.5 Asset Group 4 – Trunk & Reticulation Mains The purpose of this section is to outline how Council manages the water supply trunk and reticulation mains system.

4.5.1 Objective

Council’s objective in owning and providing a water supply trunk and reticulation mains system is to provide potable water to households and commercial users. The water is supplied from reservoirs, pump stations or directly from the water Filtration Plant.

4.5.2 Background Data

CTW has two independent water supply systems, Lake Rowlands and Quandialla. The system is comprised of a network of trunk and reticulation mains including cast iron, asbestos cement, DICL, PVC and Polythene pipes. The majority of the unlined cast iron mains have been replaced with UPVC and the remaining unlined cast iron pipes in line with CTW’s annual renewal programme.

Overview Some of the key life-cycle issues that affect the Water Supply Reticulation system are:

o Condition of system o Scheduled maintenance o Condition based maintenance and monitoring including regular maintenance o Works needed to meet Level Of Service o Community concerns o The age of the Asset o System Operating Rules

Hierarchy The reticulation group is classified using the following hierarchy: Reticulation Mains Reticulates water through the town or village. They include isolation valves and

hydrants, Customer services are connected to these mains. Flow direction can change and is dependent on demand.

Trunk Mains Carries water from reservoirs, pump stations or Filtration Plant to the reticulation

mains. The pipes are generally larger than those for reticulation and the flow is normally in the one direction. Hydrants are not usually connected to these mains.

Asset Performance The reticulation system is monitored using the following techniques:-

• Telemetry • Inspections • Complaints • Legislative Compliance

The current trunk and reticulation systems are adequate to supply current peak demand and the location of reservoirs reduces the likelihood of pressure fluctuations.

Data has been collected to assess the future requirements/demand that will be placed on the reticulation system and this indicates that it is adequate for the foreseeable future.

Page 42: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

CTW – Water Asset Management Plan April 2014 Page 38

4.5.3 Operations

Operational activities should be explained incorporating the impacts of the operations on the assets. Operational activities for trunk and reticulation relate to the following:

• The location of assets, in particular major/important trunk or reticulation mains, • Relevant details of catchment areas and/or potentially sensitive areas that may cause problem, • The number of customers affected in each of the areas, including major contributors to the area, • Level of response and procedures for attending to emergencies.

Inspections are undertaken as leaks or breaks in the line occur.

4.5.4 Maintenance

Maintenance work is the day-to-day work required to maintain the asset’s ability to provide the required service levels Work Definition In the case of reticulation assets, maintenance affects both mains and customer services, and includes:

• Breaks • Leaks • Hydrant and valve leaks • Illegal connections

General maintenance strategies include:

• Deferring minor maintenance work if mains are due for upgrading or replacement. • Ensuring the network is maintained to deliver the desired levels of service. • Attending to after-hour call-outs.

Maintenance works are carried out by Council’s own employees. Maintenance Expenditure Forecasts Considerations include:

• Trunk and reticulation maintenance costs will increase if the water supply network grows in size and flow volumes increase.

• Historical costs which have been $292,000 to $300,000 over the last five years.

The 30-year financial plan allows for a relatively constant operation and maintenance costs of $371,000 per annum, over the whole water supply system. Any increase in costs due to the ageing of the system will be offset by staged replacement of deteriorating and therefore high maintenance components.

4.5.5 Renewal

Reticulation Renewal Expenditure Forecasts The 30-year Financial Plan has provided $14.5 million for reticulation renewals in various locations across the network.

Page 43: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

CTW – Water Asset Management Plan April 2014 Page 39

4.5.6 New Works Strategies

Subdivision development Any new water reticulation infrastructure required due to subdivisions is to be provided by the developer at their cost, not council’s. Capacity driven development Current population projections for the CTW LGA indicate that the current reticulation network has adequate capacity for the foreseeable future. New Works Expenditure Forecasts The 30 year financial plan provides for the renewal and upgrade of Council’s trunk main system, outlined as follows:

• Renewal of Trunk Main ‘K’ Gooloogong to Grenfell, 35.325 kilometres, $5.97M – commencing 2013. Current condition poor. To be upsized from 200mm to 250mm.

• Renewal of Trunk Main ‘U’ from Trunk Main ‘C’ to Cudal, 33.8 kilometres, $3.38M – commencing 2016. Current condition poor. To be upsized from 150mm to 200mm.

• Renewal of Trunk Main ‘C’ Mandurama to Gooloogong, 72.92 kilometres, $12.20M – commencing 2021 to 2025. Current condition poor. To be upsized from 225/250mm to 300mm.

• Renewal of Trunk Main ‘B’ Carcoar Filtration Plant to Mandurama, 6.575 kilometres, $1.12M – commencing in 2022. Current condition fair. To be upsized from 250mm to 300mm.

• Renewal of Trunk Main ‘D’ Carcoar Filtration Plant to Browns Creek, 19.7 kilometres, $2.81M – commencing in 2026. Current condition fair. To be upsized from 200mm to 250mm.

• Renewal of Trunk Main ‘A’ Lake Rowlands to Carcoar Filtration Plant, 4.5 kilometres, $1.46M – commencing in 2028. Current condition fair. To remain at 375mm.

• Renewal of Trunk Main ‘F’ Browns Creek to Millthorpe, 8.325 kilometres, $0.84m – commencing in 2026. Current condition fair. To be upsized from 150mm to 200mm.

• Renewal of Trunk Main ‘P’ from Trunk Main ‘C’ to Somers, 3.387 kilometres, $0.17M – commencing in 2026. Current condition fair.

• Renewal of Trunk Main ‘X’ Lake Rowlands to Blayney, 14.94 kilometres, $3.49M – commencing in 2034. Current condition fair. To remain at 375/300mm.

4.5.7 Disposal

There is currently no policy to dispose of trunk or reticulation mains within CTW’s boundaries. The water mains that are being replaced are being decommissioned by isolating from the network and left in place.

Page 44: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

CTW – Water Asset Management Plan April 2014 Page 40

Appendix A – Operations Management Plan

Page 45: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

 

OPERATION MANAGEMENT PLAN Central Tablelands Water

September 2013

Page 46: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan
Page 47: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan September 2013

OPERATIONS MANAGEMENT PLAN

Table of Contents 1. INTRODUCTION .............................................................................................................. 1

2. SYSTEM DESCRIPTION ................................................................................................. 2

3. OPERATIONS MANAGEMENT AND LEVELS OF SERVICE ........................................ 4

3.1 WATER QUALITY ......................................................................................................... 4 3.2 PROCEDURE FOR COLLECTING WATER SAMPLES FOR ANALYSIS AT THE LABORATORY . 5 3.2 WATER QUANTITY ...................................................................................................... 7 3.3 RELIABILITY OF SUPPLY .............................................................................................. 8 3.4 WATER RESOURCE CONSERVATION ............................................................................ 9 3.5 ENVIRONMENTAL AND ENERGY MANAGEMENT ........................................................... 10

4. OPERATIONAL OVERVIEW ......................................................................................... 11

THE CTW SYSTEM .............................................................................................................. 13 4.1 SUB-SYSTEM 1 ......................................................................................................... 14

4.1.1 Lake Rowlands .................................................................................................... 15 4.1.2 Lake Rowlands Pump Station ............................................................................. 16 4.1.3 Trunk Main ‘X’ ..................................................................................................... 17 4.1.4 Blayney Water Filtration Plant ............................................................................. 18 4.1.5 Polona Street Pump Station ................................................................................ 19 4.1.6 Patrick’s Reservoir .............................................................................................. 19 4.1.7 Plumb Street Reservoir ....................................................................................... 20 4.1.8 Plumb Street Pump Station ................................................................................. 21 4.1.9 Hill Street, Blayney Reservoir .............................................................................. 22 4.1.10 Blayney Well .................................................................................................... 22 4.1.11 Trunk Main ‘A’ .................................................................................................. 23 4.1.12 Carcoar Water Filtration Plant ......................................................................... 24 4.1.13 Booster #1 Pump Station ................................................................................. 25 4.1.14 Trunk Main ‘D’.................................................................................................. 26 4.1.15 Carcoar Reservoir ............................................................................................ 26 4.1.16 Browns Creek Reservoir .................................................................................. 27 4.1.17 Browns Creek Pump Station ............................................................................ 28 4.1.18 Trunk Main ‘E’ .................................................................................................. 28 4.1.19 Trunk Main ‘F’ .................................................................................................. 29 4.1.20 Millthorpe Reservoir ......................................................................................... 30

4.2 SUB-SYSTEM 2 ......................................................................................................... 30 4.2.1 Trunk Main ‘B’ ..................................................................................................... 32 4.2.2 Trunk Main ‘P’ ..................................................................................................... 32 4.2.3 Mandurama Reservoir ......................................................................................... 33 4.2.4 Mandurama Pump Station .................................................................................. 34 4.2.5 Trunk Main ‘C’ ..................................................................................................... 34 4.2.6 Trunk Main ‘G’ ..................................................................................................... 35 4.2.7 Lyndhurst Reservoir ............................................................................................ 36 4.2.8 Garland Pump Station ......................................................................................... 37

Page 48: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan September 2013

4.2.9 Garland Reservoir ............................................................................................... 37 4.2.10 Newry Downs Pump Station ............................................................................ 38 4.2.11 Sugarloaf Road Pump Station ......................................................................... 39

4.3 SUB-SYSTEM 3 ......................................................................................................... 39 4.3.1 Trunk Main ‘U’ ..................................................................................................... 40 4.3.2 Canomodine Pump Station ................................................................................. 41 4.3.3 Cargo Pump Station ............................................................................................ 42 4.3.4 Cargo Reservoir .................................................................................................. 43 4.3.5 Cudal Reservoir................................................................................................... 43 4.3.6 Cudal Bore .......................................................................................................... 44 4.3.7 Cudal Booster Pump Station ............................................................................... 45 4.3.8 Greys Hill Reservoir ............................................................................................ 46 4.3.9 Manildra Reservoir .............................................................................................. 46

4.4 SUB-SYSTEM 4 ......................................................................................................... 47 4.4.1 Trunk Main ‘V’ ..................................................................................................... 48 4.4.2 Moorbel Reservoir ............................................................................................... 49 4.4.3 Canowindra Reservoir ......................................................................................... 50 4.4.4 Canowindra Pump Station ................................................................................... 50 4.4.5 South Canowindra Reservoirs ............................................................................. 51 4.4.6 North Canowindra Pump Station ......................................................................... 52 4.4.7 North Canowindra Rural Scheme ........................................................................ 53 4.4.8 Nyrang Creek Pump Station ................................................................................ 53 4.4.9 Nyrang Creek Rural Scheme .............................................................................. 54

4.5 SUB-SYSTEM 5 ......................................................................................................... 55 4.5.1 Bangaroo Bore Pump Station .............................................................................. 56 4.5.2 Bangaroo Bore Service Reservoirs ..................................................................... 57 4.5.3 Bangaroo Bores .................................................................................................. 58

4.6 SUB-SYSTEM 6 ......................................................................................................... 59 4.6.1 Gooloogong Bore Pump Station .......................................................................... 60 4.6.2 Gooloogong Bore Service Reservoir ................................................................... 61 4.6.3 Chlorinator ........................................................................................................... 62 4.6.4 Gooloogong Bores .............................................................................................. 63

4.7 SUB-SYSTEM 7 ......................................................................................................... 64 4.7.1 Trunk Main ‘L’ ...................................................................................................... 65 4.7.2 Trunk Main ‘L’ Booster Pump ............................................................................. 66 4.7.3 Trajere Pump Station .......................................................................................... 67 4.7.4 Trajere Reservoir................................................................................................. 67 4.7.5 Pyes Gap Reservoir ............................................................................................ 68 4.7.6 Eugowra Reservoir .............................................................................................. 69 4.7.7 Broad Street Pump Station .................................................................................. 69 4.7.8 Hill Street Reservoirs........................................................................................... 70

4.8 SUB-SYSTEM 8 ......................................................................................................... 71 4.8.1 Trunk Main ‘K’ ..................................................................................................... 72 4.8.2 McDonalds Lane Pump Station ........................................................................... 73 4.8.3 Grenfell North Reservoir ...................................................................................... 74 4.8.4 Grenfell North Transfer Booster .......................................................................... 74 4.8.5 North Street Pump Station .................................................................................. 75 4.8.6 Grenfell East Reservoirs ..................................................................................... 76 4.8.7 Quondong Road Pump Station ........................................................................... 76

Page 49: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan September 2013

4.8.8 Grenfell South Reservoir ..................................................................................... 77 4.8.9 Grenfell West Reservoir ...................................................................................... 78

4.9 SUB-SYSTEM 9 ......................................................................................................... 78 4.9.1 Quandialla Bores ................................................................................................. 79 4.9.2 Quandialla Bore Reservoir .................................................................................. 80 4.9.3 Quandialla Bore Chlorinator ................................................................................ 81 4.9.4 Quandialla Bore Surface Pumps ......................................................................... 81 4.9.5 Trunk Main ‘Q’ ..................................................................................................... 82 4.9.6 Quandialla On-Ground Storage ........................................................................... 83 4.9.7 Quandialla Booster Pump ................................................................................... 83 4.9.8 Quandialla Elevated Storage............................................................................... 84

5. OPERATING RULES ..................................................................................................... 85

GENERAL RULES ................................................................................................................. 86 NORMAL CONDITIONS .......................................................................................................... 86

5.2.1 Sub-System 1 ...................................................................................................... 86 5.2.2 Sub-System 2 ...................................................................................................... 86 5.2.3 Sub-System 3 ...................................................................................................... 86 5.2.4 Sub-System 4 ...................................................................................................... 87 5.2.5 Sub-System 5 ...................................................................................................... 87 5.2.6 Sub-System 6 ...................................................................................................... 87 5.2.7 Sub-System 7 ...................................................................................................... 87 5.2.8 Sub-System 8 ...................................................................................................... 87 5.2.9 Sub-System 9 ...................................................................................................... 87

5.3 PEAK DEMAND CONDITIONS ...................................................................................... 87 5.3.1 Sub-System 1 ...................................................................................................... 88 5.3.2 Sub-System 2 .................................................................................................... 101 5.3.3 Sub-System 3 .................................................................................................... 101 5.3.4 Sub-System 4 .................................................................................................... 101 5.3.5 Sub-System 5 .................................................................................................... 101 5.3.6 Sub-System 6 .................................................................................................... 101 5.3.7 Sub-System 7 .................................................................................................... 101 5.3.8 Sub-System 8 .................................................................................................... 101 5.3.9 Sub-System 9 .................................................................................................... 102

5.4 ABNORMAL CONDITIONS ......................................................................................... 102 5.4.1 Drought ............................................................................................................. 102 5.4.2 Water Filtration Plants ....................................................................................... 102 5.4.3 Pump Stations ................................................................................................... 102 5.4.4 Trunk Mains ...................................................................................................... 102 5.4.5 Reservoirs ......................................................................................................... 103

5.5 DISASTER CONDITIONS ........................................................................................... 103 5.5.1 Lake Rowlands Dam Failure ............................................................................. 103 5.5.2 Chemical Accidents ........................................................................................... 103 5.5.3 Severe Drought ................................................................................................. 104

Page 50: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 1 September 2013

1. INTRODUCTION This Operations Management Plan for Central Tablelands Water outlines the operation of CTW assets in a manner which economical provides acceptable levels of service to our customers through the: • Setting of operational objectives and monitoring procedures, • Preparation of proper operating procedures and their utilisation at CTW facilities, • Identification of system deficiencies and constraints and thus determining Operating

Rules, • Efficient use of water resources, and • Ensuring that the scheme’s operating methods minimise adverse environmental impacts. The Plan includes: • A description and history of the CTW system, • The objectives of Operations Management and target Levels of Service, • An overview of system operation, • Operating parameters of facilities within each Sub-Systems, • System operating rules in general and for Normal, Peak Demand, Abnormal (breakdown)

and Disaster operating conditions. This document also forms part of CTW’s Asset Management Plan, developed as part of the Total Asset Management approach to the provision of water supply services. This plan will enable CTW to meet service standards, to increase the system’s operating efficiency and to more effectively invest capital in assets to provide services that will meet future needs.

Page 51: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 2 September 2013

2. SYSTEM DESCRIPTION The overall scheme (known as the A/D system) is an interconnected network of sub-systems, which are primarily fed from Lake Rowlands. In peak periods, supply is supplemented from additional sources such as Gooloogong Bore, Bangaroo Bore and Cudal Bore. The scheme supplies water to a significant area of central New South Wales, including towns and villages in the shires of Blayney, Cabonne, Cowra and Weddin. The scheme is a long, linear system that is now under stress due to its limited transfer capacity and aging components, rendering it vulnerable to breakdown problems and complex operation. For the purposes of this document, the system is divided into the following sub-systems: Blayney - Carcoar - Millthorpe system: Sub-System 1 Blayney Shire villages: Sub-System 2 D-Section (from Trunk Main ‘C’ to Manildra): Sub-System 3 Canowindra System: Sub-System 4 Bangaroo Bore: Sub-System 5 Gooloogong Bore: Sub-System 6 Eugowra System: Sub-System 7 Grenfell System: Sub-System 8 Quandialla System: Sub-System 9 The main source of supply is Lake Rowlands, which was constructed in the late 1940’s. There are two trunk mains drawing water from Lake Rowlands. One of these is a 375mm gravity main to Carcoar Water Filtration Plant, which originally serviced the whole system. The other pipeline is a 300/375mm rising main to Blayney Water Filtration Plant. This section was constructed in 1966 to provide an increased supply to Blayney and to allow the output from the Carcoar Water Filtration Plant to feed the rest of the system. The A/D section, completed in the 1950’s, was a gravity system fed from the Carcoar Water Filtration Plant. In 1961, booster stations were installed at Gooloogong and Canomodine to maintain supplies at the extremities of the system. In 2003, booster stations were installed on Trunk Main ‘C’ at Newry Downs and Sugarloaf Road to increase flows to the western end of the system. Bogolong Dam, built in 1930, was maintained as a backupemergency supply. It was taken out of operation in 2000. In 1968 a bore field at Bangaroo was commissioned to feed the Western end of the system, further reducing the demand on Carcoar Water Filtration Plant. Further development of ground water resources took place in 1977 when the Gooloogong Bore was commissioned. It was proposed that Bangaroo Bore could supplement supply to Canowindra, and indirectly to D-Section, while Gooloogong Bore could supplement supply to Grenfell or Eugowra. A standby bore was installed at Gooloogong in 1987 to provide security for that system. The bores at Cudal and Blayney Well have also been added to the system. They are maintained as stand-by facilities, used only during peak demand periods. The Quandialla

Page 52: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 3 September 2013

section, built in 2002, is a stand-alone system, which supplies the Quandialla Township and rural customers from a bore via a 100mm rising main. This development of additional water resources throughout the system has allowed supply to be increased generally in line with demand, without being completely restricted by the limited transfer capacity of the original system.

Page 53: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 4 September 2013

3. OPERATIONS MANAGEMENT AND LEVELS OF SERVICE Central Tablelands Water’s Operations Management objectives relate to the use of component assets to deliver bulk water to customers in an economical manner. CTW however must operate with environmental responsibility and meet consumer needs for service and reliability.

3.1 WATER QUALITY

Objective: • Meet or exceed guidelines for water quality at point of sale set by National Health and

Medical Research Council (NHMRC) and Australia Water Resources Council (AWRC). Levels of Service: For microbiological quality;

Faecal Coliforms 100% or routine samples to have zero e-coli per 100ml of water.

Coliforms 98% of routine samples to have zero coliforms per 100ml of water; no sample to have more than 10 coliforms per 100ml of water.

For physical and chemical quality the guidelines specify a series of recommended values. The guidelines also state: “In general, the physical characteristics of water are not of direct public health concern, but they do affect the aesthetic quality of the water. The guideline for each…. chemical is the concentration that…. does not result in any significant risk to the health of the consumer. The health related guideline values are very conservative…. The physical guideline values should not be regarded as absolute, but as value judgments. Consequently small, short-term excursions beyond a guideline value do not necessarily mean that the water will be unacceptable.” 100% compliance with the guideline values is unrealistic and is not achievable without complete treatment of all water sources. 90% compliance is considered to be more realistic and generally acceptable to consumers. With this in mind, the following levels of service have been adopted.

Colour 100% of samples to be 10 HU or less 90% of all samples to be 3 HU or less

Turbidity 100% of samples to be 1 NTU or less 90% of all samples to be 0.2 NTU or less

Iron 100% of samples to have 0.2 mg/L or less Manganese 100% of samples to have 0.1 mg/L or less

Note: It must be recognised that the ability to control chemical and physical parameters such as iron and water colour is limited.

The current water quality monitoring program is detailed in Table 1.

Page 54: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 5 September 2013

Table 1: Water Quality Monitoring Schedule. Type of Analysis Frequency Sampling Points

Pesticide Annually All sources of raw water Comprehensive chemical Annually All reticulation networks

Routine chemical Six-monthly All reticulation networks

Residual Fluoride Weekly Blayney, Lyndhurst, Mandurama and

Manildra reticulations

Residual Chlorine Weekly

Blayney, Lyndhurst, Mandurama, Grenfell, Eugowra and Manildra reticulations

Microbiological

Populations > 2000 - Weekly Populations > 1000 - Fortnightly Populations < 1000 - Monthly

All reticulation networks

Fluoride Daily Blayney and Carcoar WFP’s Chlorine Daily Blayney and Carcoar WFP’s pH Daily Blayney and Carcoar WFP’s Turbidity Daily Blayney and Carcoar WFP’s Iron Weekly Blayney and Carcoar WFP’s Manganese Weekly Blayney and Carcoar WFP’s

3.2 PROCEDURE FOR COLLECTING WATER SAMPLES FOR ANALYSIS AT THE LABORATORY

The collection and submission of water samples will be undertaken in accordance with the Forensic and Analytical Science Service (FASS) 2010, Guide for Submitting Water Samples to the Division of Analytical Laboratories for Analysis 2nd Edition. NSW Health and the companion document, Guide for Submitting Water Samples to the Division of Analytical Laboratories for Analysis – Quick Reference Guide which can be found at www.health.nsw.gov.au/environment/water/Documents/dal analysis.pdf The Quick Reference Guide provides a summary of the more detailed information set out in the Guide for Submitting Water Samples to the Division of Analytical Laboratories for Analysis. A copy outlining the procedure for collecting and submitting water samples to the Division of Analytical Laboratories is attached at Appendix 1. The following monitoring and testing programs are recommended for the water supply systems of CTW: Daily

Page 55: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 6 September 2013

Samples of the raw and final water at CTW Filtration Plant, testing by operators for the following:

• pH • Apparent colour • Free Chlorine • Fluoride • Temperature

Weekly CTW operators collect samples from around reticulation systems of Blayney, Millthorpe, Carcoar, Mandurama, Lyndhurst and Trunk Main ‘H’, and is tested by CTW operators for the following:

• pH • Apparent colour • Turbidity • Free Chlorine • Fluoride • Iron • Manganese • Aluminium Residuals

Lake Rowlands

• Iron • Manganese

Fortnightly CTW operators collect samples from Lake Rowlands inflow streams, and is tested by CTW operators for the following:

• Ammonia • Chloride • Nitrate • pH • Apparent Colour • Alkalinity

Weekly/Monthly CTW operator collects samples from CTW systems and sends to Division of Analytical Laboratories Testing for MIB & Geosmin (summer months only) Samples of raw and filtered water and backwash water from sludge lagoons at Water Filtration Plants may be collected by the WTP Operator to be tested for methylisoborneol (MIB) and geosmin. AWT at the Australian Water Quality Centre in Adelaide can test for MIB & Geosmin

Page 56: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 7 September 2013

3.2 WATER QUANTITY

Objectives: • Ensure availability of supply to meet peak daily demand levels for individual towns and

villages. • Ensure availability of supply to meet Council's obligations to Cowra Shire under the

agreement to supply water. • Ensure availability of supply to meet peak daily demand levels for industry. Levels of Service: • The peak daily demand requirements of each town and village are as set out in Table 2. • The peak daily demand of each major industrial consumer is as set out in Table 3. Table 2: Peak Daily Demands for Towns and Villages.

Town or Village Peak Demand (ML/day)

Blayney 1.7

Canowindra - Moorbel 2.2

Carcoar 0.2

Cargo 0.3

Cudal 0.4

Eugowra 1.3

Gooloogong (Cowra Shire) 0.1

Grenfell 2.3

Lyndhurst 0.2

Mandurama 0.1

Manildra 0.6

Millthorpe 0.5

Pierces Scheme (Cowra Shire) 0.1

Rurals 4.3

Somers 0.1

Trajere 0.1

Woodstock (Cowra Shire) 0.6

Page 57: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 8 September 2013

Table 3: Peak Daily Demands for Major Industrial Consumers.

Industry Peak Demand (ML/day) Friskies Pet Care 0.3

Western White Linen 0.1

Manildra Flour Mills 0.2

Baiada Poultry 0.3

3.3 RELIABILITY OF SUPPLY

Objectives: • Ensure agreed targets for planned and unplanned interruptions to consumers are not

exceeded. • Meet target levels of service for water restrictions. Levels of Service: • Formal water restrictions not to exceed 10 days during the summer season.

• Table 4 sets out the maximum duration of unplanned interruptions to supply.

• Table 5 shows the service priorities and response times for water supply interruptions. Table 4: Target maximum duration of interruptions in supply to consumers.

Consumer Circumstance Target duration of supply interruption

Major Industrial Planned 8 hours: each 7 days

Unplanned 6 hours: each 7 days

Towns and Villages

Planned 12 hours: each 7 days

Unplanned 1 - 4 hours: each 3 months 4 - 8 hours: each 6 months 8 + hours: never

Minor and On-Line Planned 10 hours: daily

Unplanned 12 hours: daily

Note: Interruptions are defined as cessation of supply for more than one hour. Table 5: Priorities and Response Time to Water Supply Interruption.

Page 58: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 9 September 2013

Priority Definition Causes Effects Response Time

1 Failure to maintain continuity or quality of supply to one or more major consumers, a large number of consumers; or any major failure

• Main break • Pump station or

valve failure

• Major Property damage • Large volume of water

wasted • Significant depletion of

service reservoir • Major environmental

impact • Personal injury or risk

to public health

2 hours (Bh) 3 hours (Ah)

2 Failure to maintain continuity or quality of supply to a number of consumers

• Minor main break

• Partial valve failure

• Leaking connection

• Minor property damage • Minor environmental

impact

4 hours (Bh) 5 hours (Ah)

3 Failure to maintain continuity or quality of supply to a single minor consumer

• Leaks from main• Inadequate

maintenance of pipes

• Partial failure of connections

• Poor pressure or reduced flow

• Reduction in aesthetic quality of water (no health risk)

• Minimal or no impact on environment

One working day

4

Minor problem or complaint which can be dealt with at a time convenient to the customer and to CTW

• Minor faults at service

• Aesthetics of CTW equipment

• No significant effect Within 2 weeks

3.4 WATER RESOURCE CONSERVATION

Objectives: • Carefully manage the region’s valuable water supply. Levels of Service: • Limit the quantity of unaccounted for water to 8% or less per annum of the delivered.

Page 59: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 10 September 2013

3.5 ENVIRONMENTAL AND ENERGY MANAGEMENT

Objective: • Ensure that the Scheme’s operating methods do not have any detrimental impact on the

surrounding environment. • Ensure operating methods comply with the requirements of the appropriate Acts. • To minimise the energy used for pumping. • To use fuel efficient methods in the operation and maintenance of motor vehicles, plant

and equipment. Levels of Service: • Zero incidence of non-compliance with Environmental Acts and Licenses.

Page 60: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 11 September 2013

4. OPERATIONAL OVERVIEW To facilitate operational analysis and management, the CTW System has been divided into nine Sub-Systems, as shown on the following diagrams.

WTP

WTP WTP

Grenfell

Bogalong

Eugowra

Trajere Rura l Scheme Canowindra

Bangaroo Bore

Gooloogong Bor e

McDonalds Lane

Nyrang Creek Rura l Scheme Canomodine

Cargo

Greys Hill

Manildra

C udal

Cargo North Canowindra

Moorbel

Lake Rowlands Booster #1

Garland Garland

Lyndhurst Mandurama

Lake Rowlands

Carcoar Blayney

Millt horpe

So mers

Carcoar Blayney

Browns Creek

Consumer Consumer

Town Reticulation Reservoir Pump Station Dam Bore

Lege nd

Sub - System 7

Sub - System 8 Sub - System 6

Sub - System 5

Sub - System 4

Sub - System 3

Sub - Sy stem 2

Sub - System 1

Blayney We ll L

K

C V

U

BORE

Sub-System 9

Figure 4.1: The CTW System and its Sub-Systems. Each Sub-System can conveniently be considered as an operating entity with its own specific performance requirements and operating rules. The Sub-Systems are: Blayney - Carcoar - Millthorpe system: Sub-System 1 Blayney Shire Villages: Sub-System 2 D-Section (from Trunk Main ‘C’ to Manildra): Sub-System 3 Canowindra System: Sub-System 4 Bangaroo Bore: Sub-System 5 Gooloogong Bore: Sub-System 6 Eugowra System: Sub-System 7 Grenfell System: Sub-System 8 Quandialla System: Sub-System 9 Operating parameters in terms of objectives, performance requirements, operating rules, existing capacity, criticality, deficiencies and constraints are described for each of the Sub-Systems. Criticality for each component of a Sub-System is rated and given a numerical value. This value corresponds with planned maintenance priorities, response times for unplanned

Page 61: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 12 September 2013

maintenance and the component’s importance to the correct operation of the Sub-System and the CTW system as a whole. Table 6, below, displays the meaning of the each criticality rating. Table 6: Explanation of Criticality Ratings. Criticality Meaning

1 • Major (or total) loss of a service or severe impact on a large number of customers.

• Failure would cause severe damage to system and/or surrounding property. • Major loss of income or major repairs. • Major impact on levels of service. • Severe public relations or political repercussions.

2 • Significant disruption to a service or impact on a large number of customers (may involve a lengthy period of loss of supply).

• Failure would cause moderate damage to system and/or surrounding property.

• Potential for significant loss of income or expensive repairs. • Significant public relations or political repercussions.

3 • Significant inconvenience to a large number of customers involving severe restrictions on services and/or periods of total loss of service.

• Failure could cause moderate local impact to both the asset or surrounding area.

• Levels of service severely affected. • Moderate public relations or political repercussions.

4 • Some inconvenience to a larger group of customers involving restricted or short loss of service and/or moderate impact to surrounding area.

• Levels of service moderately affected. • Mild public relations repercussions possible.

5 • Minor inconvenience to a small number of customers, minor impact on surrounding area or to levels of service.

6 • Lowest importance - negligible impact on surrounding area, levels of service or public relations.

Note: Some facilities are only operated during peak demand periods, which may only be

for a few weeks every year. During these periods, the facility may be vital for supply, and so it is given a high criticality rating. During normal demand periods, which are usually around 90% of the year, these facilities are not needed and so are given a low criticality during these periods. These stand-by facilities are maintained all year round, ready to operate when needed, due to breakdowns in other parts of the system, for example.

Page 62: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 13 September 2013

THE CTW SYSTEM

Objective: To economically deliver water to customers that meets consumer needs for service, quality and reliability and to do so in an environmentally responsible manner. Performance Requirements: As stated in ‘Levels of Service’, Chapter 3. Existing Facilities: Raw Water Sources: Lake Rowlands, Gooloogong Bore, Bangaroo Bore, Cudal Bore,

Blayney Well and Quandialla Bore. Water Filtration Plants: Blayney and Carcoar. Services: 5395 (5795 including Cowra Shire bulk supply) Reservoirs: 45 Pump Stations: 32 Trunk Mains: 295 kilometres. Reticulation Mains: 264 kilometres Depots: Blayney, Canowindra, Cudal and Grenfell. Capacity: CTW delivers, on average, a total of 1600 ML/year to its customers. Criticality: A reliable supply of clean, healthy water is a fundamental component of sustaining any human population. CTW is, to nearly all the people living around the system, their sole supply of water. Correct functioning of the CTW system is vital for supplying the various communities and other consumers connected to the system. Deficiencies and Constraints: • Age and condition of some mains reduce the transfer capacity of the system. • During peak demand periods, co-ordination and operation of the various stand-by

facilities throughout the system becomes increasingly difficult and complex. • When the system is stressed to its limit, the safety margins for main breaks decrease with

the result that the system becomes less reliable when it is needed most. • During peak demand periods, several water sources are utilised. This creates varied

water quality throughout the system, which, especially in the case of some groundwater supplies, results in complaints from customers due to poor aesthetic quality.

Page 63: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 14 September 2013

4.1 SUB-SYSTEM 1

Sub-System 1 is the Blayney - Carcoar - Millthorpe system as shown on the diagram below.

Dam

Res

Res

ResRes

WTP

Res

WTP

Res

ResRes

Res

Res

Res

Millthorpe retic.

Millthorpe

Browns Creek

Tannery

Hill St

Browns Creek

CarcoarCarcoar retic.

Blayney WellFriskiesAbattoir

Plumb St

Palona St

Patricks

Booster #1

Carcoar Clean Water Tank

CarcaorLake Rowlands

Lake Rowlands

Blayney

Blayney Clean Water Tank

Blayney retic.

Blayney retic.

Blayney retic.

Blayney retic.

P.S.

P.S.

P.S.

P.S.

TM 'B'

TM 'X'

TM 'D'

TM 'E'

TM 'F'

TM 'A'

Figure 4.2: Sub-System 1

Page 64: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 15 September 2013

All the water for Blayney, Carcoar and Millthorpe is supplied from Lake Rowlands. The major part of the water for Blayney is pumped from Lake Rowlands, via Trunk Main ‘X’, to the Blayney Water Filtration Plant. Treated water is stored in a clear water tank adjacent to the WTP. This reservoir supplies water to the: • Friskies Pet Care Reservoir; • Patrick’s Reservoir via Polona Street Pump Station; • Plumb Street Reservoir; • Hill Street, Blayney Reservoir; • Browns Creek Reservoir; • Millthorpe Reservoir via Browns Creek Reservoir. The remainder of supply for Blayney and all of Carcoar comes from the Carcoar Water Filtration Plant. Water flows, under gravity, from Lake Rowlands to Carcoar WFT, via Trunk Main ‘A’. Following treatment, water is stored in the Plant’s adjacent clear water tank. From this tank, water is pumped by Booster #1 Pump Station, along Trunk Main ‘D’. Carcoar Reservoir is fed off Trunk Main ‘D’.

4.1.1 LAKE ROWLANDS

Objective: To collect, store and supply water. Performance Requirements: Safety: As appropriate for a significant hazard dam. Average Annual Yield: 1400 ML Peak Daily Demand: 12 ML Unplanned Interruptions: Not more than twice per year. Water Quality: As specified in Levels of Service, Section 3 of this document. Environmental Safeguards: Maintain a riparian flow of 1.22 - 2.44 ML/day (depending on

weather conditions).

Existing Facilities: The dam is the System’s main source of water. The catchment area is rural, the main land use being sheep farming. The dam structure is a combination of an earth and rock fill embankment and concrete slab and buttress wall. Main spillway is over the dam wall with an emergency spillway located north of the wall to prevent the embankment over-topping. A destratification system prevents dam turnover from causing water quality problems. The outlet works consist of a valve tower and main. The outlet tower can draw off water from two different levels.

Page 65: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 16 September 2013

Capacity:

Dam: Volume of 4500 ML Catchment Area of 197 km2 Assessed Safe Yield of 1900 ML/year Riparian Release: 1.2 - 2.4 ML/day

Outlet Works: Maximum of 12 ML/day

Criticality: Rating: 1 As the dam is the System’s primary source of raw water, the maintaining of Lake Rowlands as a reliable, clean source of supply is of the highest priority. Although the dam has proved a reliable source, an increase in its capacity is proposed so as meet future demands levels and raise security against severe drought. Deficiencies and Constraints: • Prone to algal blooms when at low levels.

4.1.2 LAKE ROWLANDS PUMP STATION

Objective: To boost water from Lake Rowlands to Blayney Water Filtration Plant. Performance Requirements: Peak Daily Demand: 6.0 ML/day Unplanned Interruptions: Not more than 24 hours duration, 4 times in one month. Existing Facilities: The Pump Station contains two pumps: • 2 x Southern Cross ‘Sovereign’ 125 x 100 x 315 with a 132 kW motor. The pumps are run individually - never together. Capacity: Southern Cross Pump Operation: 6.0 ML/day Criticality: Rating: 1

Page 66: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 17 September 2013

• Lake Rowlands Pump Station is the only means of getting water to Blayney WTP. With two pumps, a complete failure of the Pump Station is unlikely, but would cause major disruption of supply in Blayney.

• If Carcoar was not supplied and the maximum pumping output at Booster #1 was gained, a maximum of 1.4 ML/day could be supplied to Blayney from Carcoar WTP via Trunk Mains ‘D’ and ‘E’.

• Blayney Well, in theory, is capable of delivery 0.6 ML/day. Water quality concerns restrict the operation of Blayney Well to extreme cases of supply deficiency.

• With maximum supply to Blayney and Millthorpe from Carcoar WFP and Blayney Well, 90% of the Peak Daily Demand of 2.7 ML/day could be supplied.

Deficiencies and Constraints: • None

4.1.3 TRUNK MAIN ‘X’

Objective: To deliver water from Lake Rowlands Pump Station to Blayney WFP. Performance Requirements: Peak Daily Transfer: 6.0 ML Unplanned Interruptions: Not more than four every month. Not more than 24 hours duration. Existing Facilities: • 375mm Cast Iron pipe from 0 km to 1.61 km. • 300mm AC pipe from 1.61 km to Blayney WTP. • Total length of 14.94 km. Capacity: • Transfer capacity limited by pumping capacity at Lake Rowlands Pump Station and

capacity of Blayney WTP to 6.0 ML/day. • Provisions have been made in the Trunk Main for a possible rise to 9.0 ML/day (with

installation of two extra pump stations). Criticality: Rating: 1 As for Lake Rowlands Pump Station. Deficiencies and Constraints: The Trunk Main is still in good condition, very few breaks occur, but if the main is ever operated at its theoretical maximum transfer capacity of 9.0 ML/day, the margin for failure

Page 67: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 18 September 2013

due to pressure peaks, for example, will increase. This combined with the loss of strength and reliability due to aging could prove to be a problem in the future.

4.1.4 BLAYNEY WATER FILTRATION PLANT

Objective: To supply water which meets or exceeds water quality guidelines. Performance Requirements: Peak Daily Output: 6.0 ML/day Unplanned Interruptions: Not more than twice per year. Not more than two days duration. Water Quality: As specified in Levels of Service, Section 3. Environmental Safeguards: As specified in Levels of Service, Section 3. Existing Facilities: Water is supplied from Trunk Main ‘X’ to the mixing chamber. Coagulant and polyelectrolyte are added, it then gravitates to a sedimentation tank, water is decantered off to four rapid sand filters. Filtered water is chlorinated and fluoridated before it is stored in a clear water tank. Capacity: 6.0 ML/day (possible increase to 9.0 ML/day with extensive modification). Criticality: Rating: 1 Reliable supply to Blayney depends on the contribution from Blayney WFP. If Blayney WFP was inoperative, then virtually all treated water for entire system would need to be supplied from Carcoar WFP. During high demand periods, this would prove unfeasible. With groundwater back-up facilities contributing to other parts of the system, a maximum of 1.4 ML/day (of treated water) can be supplied to Blayney from Carcoar WFP. This represents only 84% of Blayney’s Peak Daily Demand. Deficiencies and Constraints: • The Plant is reliant on signals via the telemetry system, which can be affected by weather

conditions. • The throughput of Blayney WTP is automatically controlled by the telemetry system.

Normal operations are predetermined times. There is, however, an emergency override level. If storage reaches this level the pump will start automatically overriding any predetermined times.

• The plant’s throughput rate of 6.0 ML/day is limited by the filter media. An increased throughput rate of 9.0 ML/day (in line with upgrades at Lake Rowlands Pump Station and Trunk Main ‘X’) could be attained by changing the filter material.

Page 68: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 19 September 2013

4.1.5 POLONA STREET PUMP STATION

Objective: To deliver water to Patrick’s Reservoir. Performance Requirements: Peak Daily Demand: 0.22 ML/day Unplanned Interruptions: Not more than 24 hours duration, twice every month. Existing Facilities: Polona Street Pump Station pumps water from the Blayney reticulation system to a reservoir that feeds back into the reticulation. Pump #1 Kelly and Lewis, Model 70 (reduced impeller diameter) with 18 kW, 31 amp

motor. Pump #2 Kelly and Lewis, Model 70 with 18 kW, 31 amp motor. Only one pump is run at any one time. Pump #2 is rarely used as a backup. Capacity: Pump #1 0.22 ML/day Pump #2 0.22 ML/day Criticality: Rating: 4 Polona Street Pump Station only operates a few hours per day to maintain ample water in Patrick’s Reservoir. A breakdown of the pump station would only cause minor disruption to consumers in way of reduced pressure. Deficiencies and Constraints: • Stand-by pump requires careful operation.

4.1.6 PATRICK’S RESERVOIR

Objective: To accept water from Polona Street Pump Station, store it and supply it to the reticulation system in the Southwest area of Blayney. Performance Requirements: Peak Daily Input: 0.22 ML/day Peak Daily Output: 0.22 ML/day

Page 69: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 20 September 2013

Unplanned Interruptions: Not more than twice every month. Not more than 24 hours duration. Existing Facilities: • 0.45 ML Reservoir (reinforced concrete). • 100mm inlet - two 50mm overhead feeds. • 150mm outlet - underneath. Capacity: 0.45 ML Criticality: Rating: 4 The reticulation that the Reservoir feeds to can be supplied from other sources. Deficiencies and Constraints: • Only bypass is 25mm. • No underneath feed capability.

4.1.7 PLUMB STREET RESERVOIR

Objective: To accept water from Blayney WFP, store it and supply it to the reticulation system in Blayney. Performance Requirements: Peak Daily Input: 0.23 ML/day Peak Daily Output: 0.23 ML/day Unplanned Interruptions: Not more than twice every month. Not more than 24 hours duration. Existing Facilities: • 0.91 ML Reservoir (reinforced concrete). • 75mm inlet - overhead feed. • 150mm outlet - underneath. • 150mm bypass. Capacity: 0.91 ML Criticality:

Page 70: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 21 September 2013

Rating: 4 The reservoir is easily bypassed so water from Blayney WTP flows directly into the reticulation. Deficiencies and Constraints: • None

4.1.8 PLUMB STREET PUMP STATION

Objective: To accept water from Plumb Street reservoir, pressurise the system bound by Plumb Street/Carcoar Street, Palmer Street, Johnsons Crescent and Trunk Main ‘E’ to Browns Creek reservoir Performance Requirements: Peak Daily Demand: 1.0 ML/day Unplanned Interruptions: Not more than once in seven days. Not more than 24 hours duration. Existing Facilities: The pump station comprises two pumps. Pump #1 Southern Cross Starline 125x100x315, 18.5 kw motor Pump #2 Southern Cross Starline 125x100x315, 18.5 kw motor Pumps are always run individually – never together. Capacity: Operations: Pump #1 1.0 ML/day Pump #2 1.0 ML/day Criticality: Rating: 5 Plumb Street Pump Station pressurises the north western section of Blayney and supplies water to Browns Creek reservoir. A breakdown of the pump station would only cause a minor interruption, as water would automatically bypass the pump station and Browns Creek reservoir can be supplied from Booster 1 Pump Station. Deficiencies and Constraints:

Page 71: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 22 September 2013

• None.

4.1.9 HILL STREET, BLAYNEY RESERVOIR

Objective: To accept water from Blayney WFP, Browns Creek Reservoir and Blayney Well, store it and supply it to the reticulation system in Blayney. Performance Requirements: Peak Daily Input: 1.4 ML/day Peak Daily Output: 1.4 ML/day Unplanned Interruptions: Not more than twice every month. Not more than 24 hours duration. Existing Facilities: • 1.14 ML Reservoir (reinforced concrete). • Two 50mm inlets - overhead feed. • 200mm outlet - underneath. • 300mm bypass. Capacity: 1.14 ML Criticality: Rating: 3 The reservoir is easily bypassed so water from Blayney WFP or Browns Creek Reservoir flows directly into the reticulation. Deficiencies and Constraints: • None.

4.1.10 BLAYNEY WELL

Objective: To act as an emergency water source to supplement supply to Blayney during extreme conditions. Performance Requirements: Peak Daily Output: 0.6 ML/day Unplanned Interruptions: Must be ready to operate when needed.

Page 72: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 23 September 2013

Existing Facilities: • Well structure. • Surface Pump (Grundfos SP60-6, 11kW, 415 V, 2900 rpm @ 50 Hz) • Chlorinator (Wallace and Tiernan EA741 ‘V’ Notch) • Chlorinator Booster Pump (Grundfos 0.55 kW, 4 amp, 240 V, 2750 rpm @ 50 Hz) Capacity: Well: 0.6ML/day Surface Pump: 1.0 ML/day Chlorinator: Relative to flow (dose at 5 mg/L, at max. well output, is 3 kg/day of chlorine). Criticality: Rating: 6 Blayney Well is a stand-by structure that is not normally used but must still be maintained in operating condition. Deficiencies and Constraints: • Poor water quality. • Uncontrolled catchment area. • Unpredictable water table level. • High chlorine dosing rate to cope with unknown and varying microbiological content of the

water. • Consumers served off main from Blayney Well to Hill Street, Blayney Reservoir get

undiluted water.

4.1.11 TRUNK MAIN ‘A’

Objective: To deliver water from Lake Rowlands to Carcoar Water Filtration Plant. Performance Requirements: Peak Daily Transfer: 8 ML Unplanned Interruptions: Not more than once every month. Not more than 24 hours duration. Existing Facilities: 375mm Cast Iron, gravity main from Lake Rowlands to Carcoar WFP is 4.81 km long. Capacity:

Page 73: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 24 September 2013

9 ML/day. Criticality: Rating: 1 Trunk Main ‘A’ is the only means of transferring raw water to Carcoar WFP. Therefore, any lengthy break would cause major disruption to the operation of Carcoar WFP, which in turn, affects supply to the towns of Carcoar, Millthorpe, Mandurama, Lyndhurst and all other consumers served by Trunk Mains ‘C’ and ‘U’ to as far as Canowindra and Manildra. Deficiencies and Constraints: • No booster facilities. • Transfer capacity is reliant upon available need.

4.1.12 CARCOAR WATER FILTRATION PLANT

Objective: To supply water which meets or exceeds water quality guidelines. Performance Requirements: Peak Daily Output: 9.0 ML/day Unplanned Interruptions: Not more than twice per year. Not more than two days duration. Water Quality: As specified in Levels of Service, Section 3. Environmental Safeguards: As specified in Levels of Service, Section 3. Existing Facilities: Water is supplied from Trunk Main ‘A’ to a mixing chamber, where a coagulant is added. It then enters a DAF chamber where organic material and alum floc are floated off. Water is filtered to remove any excess, and then pumped to the clear water storage. The treated water is chlorinated and fluoridated prior to entering Trunk Main ‘B’ and Trunk Main ‘D’. Clear Water Tank: 2.16 ML Capacity: 9ML/day Criticality: Rating: 1 Reliable supply of fully treated water to consumers west and north of Carcoar WFP depends on the contribution from Carcoar WFP. Under normal conditions, water from Carcoar WFP supplies almost all of the CTW system. If Carcoar WFP was inoperative, then all towns and consumers along Trunk Mains ‘B’, ‘C’, ‘U’,

Page 74: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 25 September 2013

’D’ ,’F’, ‘K’ and ‘L’ which includes the larger centres of Canowindra, Eugowra, Grenfell and Manildra would all be significantly affected. Groundwater and back-up facilities would need to contribute to western parts of the system. Gooloogong Bore and Bangaroo Bore could supply the Grenfell and Eugowra to Canowindra area. Cudal, Cargo, Manildra and Carcoar would be seriously affected. Deficiencies and Constraints: • The throughput of Carcoar WFP is proportional to water levels in Lake Rowlands due to

the fact that the main feeding the WFP is a gravity main. A decrease in hydraulic gradient between Lake Rowlands and Carcoar WFP caused by falling water level in Lake Rowlands results in a reduced flow entering Carcoar WFP.

4.1.13 BOOSTER #1 PUMP STATION

Objective: To deliver water from Carcoar WFP to Trunk Main ‘D’. Performance Requirements: Peak Daily Demand: 1.6 ML/day Unplanned Interruptions: Not more than 24 hours duration, 4 times every month. Existing Facilities: The Pump Station has two pumps: Pump #1 Southern Cross IS0 80x50x250, 30kw, 50A motors Pump #2 Southern Cross IS0 80x50x250, 30kw, 50A motors The pumps are always run individually - never together. Capacity: Pump #1 Operation: 1.6 ML/day Pump #2 Operation: 1.6 ML/day Criticality: Rating: 1 Booster station operation is not critical to the supply of Carcoar but Millthorpe depends on the proper functioning of Booster #1 Pump Station as a backup supply. Millthorpe is supplied from Browns Creek Reservoir and Pump Station, which is in turn supplied from Plumb Street Pump Station. Booster #1 Pump Station is the alternate supply to Browns Creek reservoir. Deficiencies and Constraints:

Page 75: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 26 September 2013

• When Pumps are run, the pump’s discharge pressure must not exceed 1000 kpa to supply Trunk Main ‘D’ or 1200 kpa to supply Browns Creek reservoir.

4.1.14 TRUNK MAIN ‘D’

Objective: To transfer water from Booster #1 Pump Station to Carcoar Reservoir and Browns Creek Reservoir. Performance Requirements: Peak Daily Transfer: 1.6 ML/day Unplanned Interruptions: Not more than 4 times every month. Not more than 24 hours duration. Existing Facilities: 200mm Cast Iron main, 19.88 km long. Capacity: 1.6 ML/day Criticality: Rating: 1 Trunk Main ‘D’ is the only means of moving water to Carcoar. Extended breakdown of the main would cause major problems for rural customers beyond Carcoar. Deficiencies and Constraints: • The main is susceptible breaks under the effects of water hammer when Browns Creek

Reservoir is being fed overhead.

4.1.15 CARCOAR RESERVOIR

Objective: To accept water from Trunk Main ‘D’, store it and supply it to the reticulation system of Carcoar. Performance Requirements: Peak Daily Input: 0.3 ML/day Peak Daily Output: 0.3 ML/day Unplanned Interruptions: Not more than once per month. Not more than 8 hours duration.

Page 76: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 27 September 2013

Existing Facilities: • 0.68 ML Reservoir (elevated, reinforced concrete). • 100mm inlet - single 50mm overhead feed. • 100mm outlet - underneath. Capacity: 0.68 ML Criticality: Rating: 1 Reservoir can be bypassed - supply from Trunk Main ‘D’ directly to Carcoar reticulation. Deficiencies and Constraints: • None

4.1.16 BROWNS CREEK RESERVOIR

Objective: To accept water from Plumb Street Pump Station or Trunk Main ‘D’, store it and supply it to Browns Creek Pump Station. Performance Requirements: Peak Daily Input: 1.3 ML/day Peak Daily Output: 1.3 ML/day Unplanned Interruptions: Not more than 4 times every month. Not more than 24 hours duration. Existing Facilities: • 0.23 ML Reservoir (reinforced concrete). • Inlet - single 100mm overhead feed or 150mm underneath feed. • Outlet - 150mm underneath.

Capacity: 0.23 ML Criticality: Rating: 3 Water to Browns Creek Pump Station, and then to Millthorpe, must come from Browns Creek Reservoir. Browns Creek Reservoir can be bypassed to supply Hill Street, Blayney Reservoir.

Page 77: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 28 September 2013

Deficiencies and Constraints: • When being fed from Plumb Street Pump Station, the telemetry system will detect when

the reservoir is full, and signal the pumps at Plumb Street Pump Station to stop. The telemetry system relies on electricity.

4.1.17 BROWNS CREEK PUMP STATION

Objective: To deliver water from Browns Creek Reservoir to Millthorpe Reservoir. Performance Requirements: Peak Daily Demand: 0.8 ML/day Unplanned Interruptions: Not more than 24 hours duration, every week. Existing Facilities: The Pump Station is comprised of two pumps. Pump #1 Southern Cross 80x50x315 with 30 kW, 52 amp motor. Pump #2 Southern Cross 80 x 50 x 315 with 30 kW, 52 amp motor. Pumps are always run individually - never together. Capacity: Pump #1 Operation: 0.8 ML/day Pump #2 Operation: 0.8 ML/day Criticality: Rating: 1 Supply in Millthorpe depends on the proper functioning of Browns Creek Pump Station as there is no alternative supply for Millthorpe. Deficiencies and Constraints: • None

4.1.18 TRUNK MAIN ‘E’

Objective:

Page 78: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 29 September 2013

To transfer water from Plumb Street Pump Station to Browns Creek Reservoir, or to transfer water from Browns Creek Reservoir to Hill Street, Blayney Reservoir. Performance Requirements: Peak Daily Transfer: 1.4 ML/day Unplanned Interruptions: Not more than 4 times every month. Not more than 24 hours duration. Existing Facilities: • 150mm Cast Iron main, 3.15 km long. Capacity: 1.4 ML/day Criticality: Rating: 4 Supply to Hill Street, Blayney Reservoir can be easily obtained from other sources. Deficiencies and Constraints: • None

4.1.19 TRUNK MAIN ‘F’

Objective: To transfer water from Browns Creek Pump Station to Millthorpe Reservoir. Performance Requirements: Peak Daily Transfer: 0.8 ML/day Unplanned Interruptions: Not more than once every week. Not more than 24 hours duration. Existing Facilities: • 150mm Cast Iron main, 8.38 km long. Capacity: 0.8 ML/day Criticality: Rating: 1

Page 79: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 30 September 2013

Trunk Main ‘F’ is the only means of supplying water to Millthorpe. There is no alternative supply route for Millthorpe. Deficiencies and Constraints: • If Millthorpe Reservoir is being fed overhead, the ball/float valve closing when the

reservoir is full will cause man failure due to water hammer.

4.1.20 MILLTHORPE RESERVOIR

Objective: To accept water from Trunk Main ‘F’, store it and supply it to the reticulation system of Millthorpe. Performance Requirements: Peak Daily Input: 0.8 ML/day Peak Daily Output: 0.8 ML/day Unplanned Interruptions: Not more than once in seven days. Not more than 24 hours

duration. Existing Facilities: • 1.36 ML Reservoir (reinforced concrete). • Inlet - single 50mm overhead feed or 150mm underneath feed. • Outlet - 150mm underneath. Capacity: 1.36 ML Criticality: Rating: 3 If supply to Millthorpe was interrupted completely and Millthorpe reservoir was full, it would supply Millthorpe’s Peak Daily Demand for 48 hours. Deficiencies and Constraints: • Nearby customers experience low pressure when reservoir is less than 50% of capacity.

4.2 SUB-SYSTEM 2

Sub-System 2 is the Blayney Shire Villages and Trunk Main ‘C’ system as shown on the diagram below.

Page 80: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 31 September 2013

Res

Res

TM 'B '

Mandurama retic. Mandurama

Somers

Lyndhurst Lyndhurst retic.

to Woodstock

Trunk Main 'U' to Manildra

Off-take to Canowindra

Trunk Main 'V' to Moorbel

TM 'C'

TM 'C'

P.S. Res

Garland retic.

Garland

Garland

TM 'G'

TM 'P'

PS

PS

PS

PS

TM 'P '

Figure 4.3: Sub-System 2. Trunk Main ‘B’ from Carcoar WFP joins Trunk Main ‘C’ at the Mandurama off-take. Trunk Main ‘B’ supplies the village of Somers (via Trunk Main ‘P’). Trunk Main ‘C’ then supplies: Mandurama, Lyndhurst and Garland via Trunk Main ‘G’. The off-takes of Trunk Main ‘U’, Trunk Main ‘V’, Woodstock and Canowindra are also supplied via Trunk Main ‘C’.

Page 81: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 32 September 2013

Under normal conditions all water to Sub-System 2 is supplied from Lake Rowlands via Carcoar WFP and Trunk Main ‘B’.

4.2.1 TRUNK MAIN ‘B’

Objective: To transfer water from Carcoar WTP to Trunk Main ‘P’, Trunk Main ‘C’ and Mandurama Reservoir. Performance Requirements: Peak Daily Transfer: 7.3 ML/day Unplanned Interruptions: Not more than once every month. Not more than 24 hours duration. Existing Facilities: • 250mm Cast Iron main, 5.45 km long. Capacity: 7.3 ML/day Criticality: Rating: 1 Trunk Main ‘B’ is the only means of transferring supply from Carcoar WFP to the rest of the system. Lengthy breakdown of this main would therefore cause major disruption in the rest of the system. Deficiencies and Constraints: • None

4.2.2 TRUNK MAIN ‘P’

Objective: To transfer water from Trunk Main ‘B’ to the village of Somers. Performance Requirements: Peak Daily Transfer: 0.1 ML/day Unplanned Interruptions: Not more than 4 times every month. Not more than 24 hours duration. Existing Facilities:

Page 82: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 33 September 2013

• 1.72 km of 100mm AC pipe. • 1.50 km of 100mm uPVC pipe. Capacity: 0.1 ML/day Criticality: Rating: 5 This main serves only a small number of rural consumers, all of whom have on-site storage. Deficiencies and Constraints: • 1.72km of main is ‘Italia’ AC pipe which has deteriorated and is in quite bad condition.

Pressure is regulated via a PRV. A pressure setting of 600kpa is sufficient to maintain the service.

4.2.3 MANDURAMA RESERVOIR

Objective: To accept water from Trunk Main ‘B’, store it and supply it to the reticulation system of Mandurama via the Mandurama Pump Station. Performance Requirements: Peak Daily Input: 0.1 ML/day Peak Daily Output: 0.1 ML/day Unplanned Interruptions: Not more than once in seven days. Not more than 24 hours duration. Existing Facilities: • 0.91 ML Reservoir (reinforced concrete). • Inlet - single 50mm overhead feed or 100mm underneath feed. • Outlet - 100mm underneath. Capacity: 0.91 ML Criticality: Rating: 3 Reservoir can be bypassed allowing water to flow directly from Trunk Main ‘B’ into the Mandurama reticulation system. Deficiencies and Constraints: • None

Page 83: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 34 September 2013

4.2.4 MANDURAMA PUMP STATION

Objective: To accept water from Mandurama reservoir, deliver it to Mandurama reticulation. Performance Requirements: Peak Daily Demand: 0.1ML/day Unplanned Interruptions: Not more than 24 hours duration, each week Existing Facilities: The pump station is comprised of three pumps. Pump #1 Grundfos SV8-03T, 1.5kw motor Pump #2 Grundfos SV8-03T, 1.5kw motor Pump #3 Grundfos SV8-03T, 1.5kw motor The pumps can be operated individually or run together in series. Capacity: Pump #1 0.1ML/day Pump #2 0.1ML/day Pump #3 0.1ML/day Criticality: Rating 3 The pump station is easily bypassed so water from Mandurama Reservoir flows directly into the reticulation. Deficiencies and Constraints: • None

4.2.5 TRUNK MAIN ‘C’

Objective: To transfer water from Carcoar WFP to all CTW consumers west of Mandurama. Performance Requirements: Peak Daily Transfer: 7.3 ML/day Unplanned Interruptions: Not more than once every month. Not more than 24 hours duration.

Page 84: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 35 September 2013

Existing Facilities: 225mm Cast Iron main, 0 km to 19.48 km 225mm Steel main, 19.48 km to 35.41 km – 15.93 km 200mm Steel main, 35.41 km to 60.98 km – 25.57 km 250mm Steel main, 60.98 km to 69.64 km – 8.66 km Capacity: 7.3 ML/day Criticality: Rating: 1 Mandurama, Lyndhurst, Garland, Canowindra, Moorbel, Woodstock and all consumers supplied from Trunk Main ‘U’ rely on water from Trunk Main ‘C’. These consumers would all be affected by lengthy breaks on Trunk Main ‘C’, the magnitude of the disruption depending on the location of the break. Under normal conditions, Trunk Main ‘C’ also supplies water to Grenfell, Gooloogong and Eugowra. If supply from Trunk Main ‘C’ was interrupted, Grenfell, Canowindra and Eugowra could readily be supplied from Gooloogong Bore. Cudal has the emergency backup supply of Cudal Bore. Mandurama, Lyndhurst, Garland, Cargo and Manildra have no alternative supply. Deficiencies and Constraints: • There is a theoretical shortfall in the pipeline capacity. However, in practice, inability to

supply has only been a problem during very high demand periods or in event of main failure.

• Some sections of the main are unreliable and incur relatively frequent breakages.

4.2.6 TRUNK MAIN ‘G’

Objective: To transfer water from Trunk Main ‘C’ to Lyndhurst Reservoir. Performance Requirements: Peak Daily Transfer: 0.4 ML/day Unplanned Interruptions: Not more than 4 times every month. Not more than 24 hours duration. Existing Facilities: • 100mm uPVC pipe, 2.13 km long.

Page 85: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 36 September 2013

Capacity: 0.2 ML/day Criticality: Rating: 2 Trunk Main ‘G’ is the only means of supply for Lyndhurst and Garland. A full Lyndhurst Reservoir could supply Lyndhurst and Garland for over 48 hours at peak daily demand. Therefore interruption due to failure of Trunk Main ‘G’ would only be minor. Deficiencies and Constraints: • None

4.2.7 LYNDHURST RESERVOIR

Objective: To accept water from Trunk Main ‘G’, store it and supply it to the reticulation system of Lyndhurst and Garland. Performance Requirements: Peak Daily Input: 0.4 ML/day Peak Daily Output: 0.4 ML/day Unplanned Interruptions: Not more than once in seven days. Not more than 24 hours duration. Existing Facilities: • 0.68 ML Reservoir (reinforced concrete). • Inlet - single 50mm overhead feed or 100mm underneath feed. • Outlet - 150mm underneath. Capacity: 0.68 ML Criticality: Rating: 3 Reservoir can be bypassed allowing water to flow directly from Trunk Main ‘G’ into the Lyndhurst reticulation system and hence through to Garland. Deficiencies and Constraints: • None

Page 86: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 37 September 2013

4.2.8 GARLAND PUMP STATION

Objective: To deliver water to the Garland Reservoir. Performance Requirements: Peak Daily Demand: 0.01 ML/day Unplanned Interruptions: Not more than 3 days duration, every month. Existing Facilities: Garland Pump Station pumps water from the Lyndhurst reticulation system to Garland Reservoir. Pump: Southern Cross IS0 50x32x160, 3kw, 5.7 amp motor. Capacity: Pump Operation: 0.1 ML/day Criticality: Rating: 6 Pump only operates for several hours per week. Only extended pump outages would affect supply to Garland. Deficiencies and Constraints: • No timer or telemetry control.

4.2.9 GARLAND RESERVOIR

Objective: To accept water from Garland Pump Station, store it and supply it to the consumers of Garland. Performance Requirements: Peak Daily Input: 0.01 ML/day Peak Daily Output: 0.01 ML/day Unplanned Interruptions: Not more than once in seven days. Not more than 24 hours duration. Existing Facilities: • 0.045 ML Reservoir (reinforced concrete). • Inlet - single 50mm overhead feed or 100mm underneath feed.

Page 87: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 38 September 2013

• Outlet - 100mm underneath. Capacity: 0.045 ML Criticality: Rating: 6 Garland only small consumers. Deficiencies and Constraints: • No telemetry monitoring equipment.

4.2.10 NEWRY DOWNS PUMP STATION

Objective: To accept water from Trunk Main ‘C’ boost to Sugarloaf Road pump station or boost into Trunk Main ‘C’. Performance Requirements: Peak Daily Demand: 7.10ML/day Unplanned Interruptions: No more than 24 hours, four times in one month. Existing Facilities: The pump station contains two pumps. Pump #1: Vogel MP 125. 2/3 with a 250 kW motor Pump #2: Vogel MP 125. 2/3 with a 250 kW motor The pumps are run individually – never together. Capacity: 7.10ML/day Criticality: Rating: 3 Newry Downs Pump Station is only operated during summer periods, to boost water to the western end of the system. A breakdown of the pump station would only cause a minor interruption, as water would automatically bypass the pump station. Deficiencies and Constraints: • None

Page 88: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 39 September 2013

4.2.11 SUGARLOAF ROAD PUMP STATION

Objective: To accept water from Trunk Main ‘C’ boost to the western end of the system. Performance Requirements: Peak Daily Demand: 6.0ML/day Unplanned Interruptions: No more than 24 hours, four times in one month. Existing Facilities: The pump station contains two pumps. Pump #1: Southern Cross 25x100x315 ISO with a 132kW motor Pump #2: Southern Cross 25x100x315 ISO with a 132kW motor The pumps are run individually – never together. Capacity: 6.0ML/day Criticality: Rating: 3 Sugarloaf Road Pump Station is only operated during summer periods to boost water to the western end of the system. A breakdown of the pump station would only cause a minor interruption, as water would automatically bypass the pump station. Deficiencies and Constraints: • None

4.3 SUB-SYSTEM 3

Sub-System 3 is otherwise known as the ‘D - Section’. It is a 46.1 km branch off Trunk Main ‘C’ that supplies the towns of Cargo, Cudal and Manildra as well as other consumers fed directly from the Trunk Main.

Page 89: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 40 September 2013

Figure 4.4: Sub-System 3.

4.3.1 TRUNK MAIN ‘U’

Objective: To transfer water from Trunk Main ‘C’ to Cargo, Cudal and Manildra. Performance Requirements:

Res

Res

Manildra retic

Manildra

Greys Hill

Res

ResP.S

P.S

Trunk Main 'C'

Canomodine

Cargo Cargo Cargo retic

Cudal retic

Cudal

Cudal Bore

TM 'U'

P.S

Page 90: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 41 September 2013

Peak Daily Transfer: 1.8 ML/day Unplanned Interruptions: Not more than once every month. Not more than 24 hours duration. Existing Facilities: 150mm Steel from TM’C’ to Belubula River 5.611 km 150mm Cast Iron main from Belubula River to Cudal 28.275 km 150mm UPVC from Cudal to Gray’s Hill 3.409 km 100mm CI main from Grays Hill to Manildra 8.800 km 150mm UPVC main from Grays Hill to Manildra 8.800 km Capacity: 1.8 ML/day Criticality: Rating: 1 Cargo, Cudal, Manildra and all consumers supplied from Trunk Main ‘U’ rely almost entirely on water from Trunk Main ‘U’. These consumers would all be affected by lengthy breaks on Trunk Main ‘U’, the magnitude of the disruption depending on the location of the break. Cudal has the emergency backupsupply of Cudal Bore. Cargo and Manildra have no alternative supply. Deficiencies and Constraints: • Three stand-pipes along the length of main immediately downstream from Canomodine

Pump Station may cause enough water hammer to rupture the main when they are closed.

• Sections of the main are unreliable and incur relatively frequent breaks.

4.3.2 CANOMODINE PUMP STATION

Objective: To boost supply through Trunk Main ‘U’. Performance Requirements: Peak Daily Demand: 1.8 ML/day Unplanned Interruptions: Not more than 24 hours duration, every month, when run. Existing Facilities: Pump #1 Ritz 4 Multistage with 55 kW motor driven via a Hitachi J300 VSD.

Page 91: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 42 September 2013

Pump #2 Ritz 4 Multistage with 55 kW motor driven via a Eaton Cutter Hammer VSD Capacity: Pump #1 Operation: 1.8 ML/day (running at 50hz) to Cudal Pump #2 Operation: 1.8 ML/day Criticality: Rating: 1 (in peak demand periods).

6 (in normal conditions).

During peak demand periods, supply for the entire Trunk Main ‘U’ depends on the proper functioning of Canomodine Pump Station. As there is a duty and a stand-by pump, complete disruption of operation is highly unlikely. Deficiencies and Constraints: • None

4.3.3 CARGO PUMP STATION

Objective: To boost supply from Trunk Main ‘U’ to Cargo Reservoir. Performance Requirements: Peak Daily Demand: 0.3 ML/day Unplanned Interruptions: Not more than 24 hours duration, every week. Existing Facilities: The pumps can be operated individually or run together in series. Pump #1 Southern Cross ISO 50x32x200, 5.5kW motor Pump #2 Southern Cross ISO 50x32x200, 5.5kW motor Capacity: Pump #1 Operation: 0.16 ML/day Pump #2 Operation: 0.16 ML/day Pumps #1 and #2 Operation: 0.32 ML/day Criticality: Rating: 1 Supply to Cargo relies on the correct functioning of Cargo Pump Station. As there is a duty and a stand-by pump, complete disruption of operation is highly unlikely.

Page 92: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 43 September 2013

During high demand periods, when both pumps are operating, failure of one of the pumps will reduce supply to Cargo. Deficiencies and Constraints: • If inlet pressure from Trunk Main ‘U’ is low (below 400 kpa) then both pumps must be run

in order to generate enough delivery head.

4.3.4 CARGO RESERVOIR

Objective: To accept water from Cargo Pump Station, store it and supply it to the reticulation system of Cargo. Performance Requirements: Peak Daily Input: 0.32 ML/day Peak Daily Output: 0.32 ML/day Unplanned Interruptions: Not more than once in seven days. Not more than 24 hours duration. Existing Facilities: • 0.68 ML Reservoir (reinforced concrete). • Inlet - single 50mm overhead feed. • Outlet - 150mm underneath. Capacity: 0.68 ML Criticality: Rating: 3 Reservoir can be bypassed allowing water to flow directly from Cargo Pump Station into the Cargo reticulation system. Deficiencies and Constraints: • None

4.3.5 CUDAL RESERVOIR

Objective: To accept water from Trunk Main ‘U’, store it and supply to Cudal Booster Pump Station and deliver to Grays Hill Reservoir and Cudal Reticulation. Performance Requirements:

Page 93: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 44 September 2013

Peak Daily Input: 2.1 ML/day Peak Daily Output: 2.1 ML/day Unplanned Interruptions: Not more than once in seven days. Not more than 24 hours duration. Existing Facilities: • 0.23 ML Reservoir (reinforced concrete). • Inlet - single 100mm underneath. • Outlet - 150mm underneath. Capacity: 0.23 ML Criticality: Rating: 3 Deficiencies and Constraints: • None.

4.3.6 CUDAL BORE

Objective: To act as an emergency water source to supplement supply to Grays Hill during extreme conditions. Performance Requirements: Peak Daily Output: 0.45 ML/day Unplanned Interruptions: Must be ready to operate when needed. Existing Facilities: • Well structure. • Submersible Pump • Chlorinator (Wallace and Tiernan EA741 ‘V’ Notch) • Chlorinator Booster Pump (Grunfus 0.55 kW, 4 amp, 240 V, 2750 rpm @ 50 Hz) Capacity: Well: 4 L/S Bore Pump: 0.35 ML/day Chlorinator: Relative to flow (dose at 5 mg/L, at max. well output, is 2.25 kg/day of

chlorine).

Page 94: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 45 September 2013

Criticality: Rating: 6 Cudal Bore is a stand-by structure that is not normally used but must still be maintained in operating condition. Deficiencies and Constraints: • Poor water quality. • Uncontrolled catchment area. • Unpredictable water table level. • High chlorine dosing rate to cope with unknown and varying microbiological content of the

water. • Ability to cope with sustained operation is unknown.

4.3.7 CUDAL BOOSTER PUMP STATION

Objective: To accept water from Cudal Reservoir or Trunk Main ‘U’and deliver it to Grays Hill Reservoir or Cudal reticulation. Performance Requirements: Peak Daily Demand: 1.94ML/day Unplanned Interruptions: No more than 24 hours duration, four times in one month. Existing Facilities: The pump station contains two pumps, one to supply Greys Hill Reservoir, the other to supply the Cudal township. Pump #1 Southern Cross Starline 80x50x250 37kW Pump #2 Southern Cross Starline 80x50x250 37kW Capacity: Pump #1 (town) 2.1ML/day running at 50Hz via the reticulation to Grays Hill Pump #2 (Grays Hill) 2.1ML/day running at 50Hz via Trunk Main ‘V’ Criticality: Rating: 3 Both pumps can be used to service either Cudal township or Grays Hill Reservoir via the 100mm CI or 150mm PVC mains. Deficiencies and Constraints:

Page 95: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 46 September 2013

• None

4.3.8 GREYS HILL RESERVOIR

Objective: To act as a balance tank for Trunk Main ‘U’ and storage for Cudal. Performance Requirements: Peak Daily Input: 2.1 ML/day Peak Daily Output: 1.0 ML/day Unplanned Interruptions: Not more than once in seven days. Not more than 24 hours duration. Existing Facilities: • 2.27 ML Reservoir (reinforced concrete). • Single inlet / outlet - 100mm underneath to Cudal. • Single overhead 150mm – 150mm outlet to Manildra Capacity: 2.27 ML Criticality: Rating: 1 (in peak demand periods). 4 (in normal conditions). Deficiencies and Constraints: • None

4.3.9 MANILDRA RESERVOIR

Objective: To accept water from Trunk Main ‘U’, store it and supply it to the reticulation system of Manildra. Performance Requirements: Peak Daily Input: 1.6 ML/day Peak Daily Output: 0.8 ML/day Unplanned Interruptions: Not more than once in seven days. Not more than 24 hours duration. Existing Facilities:

Page 96: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 47 September 2013

• 0.45 ML Reservoir (reinforced concrete). • Inlet - single 75mm overhead feed or 150mm underneath feed. • Outlet - 150mm underneath. Capacity: 0.45 ML Criticality: Rating: 3 Reservoir can be bypassed allowing water to flow directly from Trunk Main ‘U’ into the Manildra reticulation system. Deficiencies and Constraints: • Consumers in the higher areas experience low pressure in high demand periods.

4.4 SUB-SYSTEM 4

Sub-System 4 is the Canowindra and Moorbel system as shown on the diagram below.

Page 97: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 48 September 2013

Figure 4.5: Sub-System 4. Water for the Canowindra system comes from Lake Rowlands via Trunk Main ‘C’ but can be supplemented in peak demand periods by flow from Bangaroo Bore or Gooloogong Bore. Under normal conditions, all water for Canowindra, Moorbel, South Canowindra, North Canowindra Rural Scheme and Nyrang Creek Rural Scheme is taken in via Trunk Main ‘V’ and Moorbel Reservoir. Moorbel Reservoir feeds to Canowindra Reservoir, South Canowindra Reservoir and Moorbel reticulation. Canowindra Reservoir then feeds to Canowindra reticulation. Canowindra Pump Station, can be used to boost supply from Canowindra Reservoir to Canowindra reticulation, Moorbel reticulation and Moorbel Reservoir. Nyrang Creek Pump Station and North Canowindra Pump Station boost water from Canowindra’s reticulation to reservoirs in satellite rural schemes.

4.4.1 TRUNK MAIN ‘V’

Objective: To transfer water from Trunk Main ‘C’ to Moorbel Reservoir.

Res

Res

P.S.

P.S.

P.S.

Res

Res Res

Res

Res

Res

Res

Off-take to Pierces

Rural Scheme

TM 'C'

SouthCanowindra

retic.

SouthCanowindra

Canowindra

Canowindraretic.

Canowindra

Moorbel

Moorbelretic.

North Canowindra North CanowindraRural Scheme

Nyrang Creek Rural Scheme

Nyrang Creek

TM 'C'

TM 'V'

Page 98: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 49 September 2013

Performance Requirements: Peak Daily Transfer: 2.3 ML/day Unplanned Interruptions: Not more than 4 times every month. Not more than 24 hours duration. Existing Facilities: 4.20 km of 200mm uPVC. Capacity: 4.0 ML/day Criticality: Rating: 4 Under normal conditions, all water for Sub-System 4 is supplied via Trunk Main ‘V’. As the main is in good condition and an alternative supply main is available, the criticality of Trunk Main ‘V’ is relatively low. Deficiencies and Constraints: • None.

4.4.2 MOORBEL RESERVOIR

Objective: To accept water from Trunk Main ‘V’, store it and supply it to Canowindra Reservoir and the reticulation system of Moorbel. Performance Requirements: Peak Daily Input: 2.3 ML/day Peak Daily Output: 2.3 ML/day Unplanned Interruptions: Not more than once in seven days. Not more than 24 hours duration. Existing Facilities: • 1.14 ML Reservoir (reinforced concrete). • Inlet - dual 100mm overhead feeds. • Outlet - dual 150mm underneath. Capacity: 1.14 ML Criticality:

Page 99: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 50 September 2013

Rating: 1 Moorbel Reservoir cannot be completely bypassed. The overhead feeds may be closed allowing a partial bypass operation. Moorbel Reservoir is the largest of the Canowindra area reservoirs and so its correct operation is important to the areas reliability of supply. Deficiencies and Constraints: • No bypass operation.

4.4.3 CANOWINDRA RESERVOIR

Objective: To accept water from either Moorbel Reservoir or main from Trunk Main ‘C’, store it and supply it to the reticulation systems of Canowindra. Performance Requirements: Peak Daily Input: 0.8 ML/day Peak Daily Output: 0.8 ML/day Unplanned Interruptions: Not more than once in seven days. Not more than 24 hours duration. Existing Facilities: • 0.91 ML Elevated Reservoir (reinforced concrete). • Inlet / Outlet 150mm underneath, from Moorbel Reservoir. • Inlet / Outlet 150mm underneath, from Trunk Main ‘C’. Capacity: 0.91 ML Criticality: Rating: 3 Reservoir can be bypassed in the event of problems occurring with any valves or other hardware. Deficiencies and Constraints: • Some consumers experience low pressure, as elevation difference between reservoir and

reticulation is small.

4.4.4 CANOWINDRA PUMP STATION

Objective:

Page 100: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 51 September 2013

To pump water from Canowindra Reservoir to Moorbel Reservoir and/or boost supply to Canowindra and South Canowindra reticulations. Performance Requirements: Peak Daily Demand: 1.0 ML/day Unplanned Interruptions: Not more than 24 hours duration, 4 times every month. Existing Facilities: Pumps are only run individually - never together. Pump #1: Southern Cross 80x50x315 with 30 kW, 50 amp motor. Pump #2: Kelly and Lewis, Model 70 with 22 kW, 38 amp motor. Capacity: Pump #1 Operation: 1.0 ML/day Pump #2 Operation: 1.0 ML/day Criticality: Rating: 4 As there is a duty and stand-by pump arrangement, combined with the fact that Canowindra Pump Station is very rarely used, this facility is considered as having low criticality. Deficiencies and Constraints: • None.

4.4.5 SOUTH CANOWINDRA RESERVOIRS

Objective: To accept water from either Moorbel Reservoir or main from Trunk Main ‘C’, store it and supply it to the reticulation system of South Canowindra. Performance Requirements: Peak Daily Input: 0.1 ML/day Peak Daily Output: 0.1 ML/day Unplanned Interruptions: Not more than once in seven days. Not more than 24 hours duration. Existing Facilities: • Two 0.18 ML Reservoir (reinforced concrete). • Inlet / Outlet 150mm underneath, from Moorbel Reservoir. • Inlet / Outlet 150mm underneath, from Trunk Main ‘C’.

Page 101: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 52 September 2013

Capacity: 0.36 ML (two 0.18 ML connected reservoirs) Criticality: Rating: 3 South Canowindra Reservoirs provide storage to help meet peak consumption rates in South Canowindra. The reservoirs can be bypassed allowing water from Canowindra Reservoir or main from trunk Main ‘C’ to flow directly into the South Canowindra reticulation. Deficiencies and Constraints: • None

4.4.6 NORTH CANOWINDRA PUMP STATION

Objective: To pump water from Canowindra reticulation to the North Canowindra Rural Scheme. Performance Requirements: Peak Daily Demand: 0.1 ML/day Unplanned Interruptions: Not more than 24 hours duration, 4 times every month. Existing Facilities: The pumps can only be operated individually - they are never run together. Pump #1 Southern Cross, Model MFAO 8A-F with 5.5 kW, 10.2 amp motor. Pump #2 Southern Cross, Model MFAO 8A-F with 5.5 kW, 10.2 amp motor. Capacity: Pump #1 Operation: 0.43 ML/day Pump #2 Operation: 0.43 ML/day Criticality: Rating: 1 Supply to the North Canowindra Rural Scheme relies on the correct functioning of North Canowindra Pump Station. As there is a duty and a stand-by pump, complete disruption of operation is highly unlikely. Deficiencies and Constraints: • No telemetry control.

Page 102: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 53 September 2013

• A pump is usually run continuously during summer increasing operating and maintenance costs.

4.4.7 NORTH CANOWINDRA RURAL SCHEME

Objective: To supply water to the consumers of North Canowindra for domestic and rural applications. Performance Requirements: Peak Daily Demand: 0.1 ML/day Unplanned Interruptions: Not more than once in seven days. Not more than 24 hours duration. Existing Facilities: • Two 0.09 ML Reservoir (reinforced concrete) each with 50mm overhead feeds and 75mm

underneath outlets. • Approximately 9.82 km of 75mm A.C. main. Capacity: Reservoir #1: 0.09 ML Reservoir #2: 0.09 ML Main: 0.1 ML/day Criticality: Rating: 1 The small number of consumers supplied by the North Canowindra Rural Scheme rely on this supply, which is therefore given a high criticality. Deficiencies and Constraints: • During high demand periods, consumers at the extremities of the scheme are starved of

supply due to the large demands of downstream consumers. • Consumers served off the rising main experience fluctuations in pressure caused by

starting and stopping of the duty pump. • CTW has responsibility for several long service connections made of inferior grade pipe

that give continuous maintenance problems.

4.4.8 NYRANG CREEK PUMP STATION

Objective: To pump water from Canowindra reticulation to the Nyrang Creek Rural Scheme.

Page 103: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 54 September 2013

Performance Requirements: Peak Daily Demand: 0.1 ML/day Unplanned Interruptions: Not more than 24 hours duration, 4 times every month. Existing Facilities: This is a single pump: Southern Cross, Model MFAO 8A-F with 5.5kW, 10.2 amp motor. Capacity: 0.1 ML/day Criticality: Rating: 3 During peak demand periods, usually in summer, supply to the Nyrang Creek Rural Scheme relies on the correct functioning of Nyrang Creek Pump Station. If the pump fails, the scheme is still supplied but a reduced rate. Deficiencies and Constraints: • No telemetry control. • No automatic or timer control - the pump must be started and stopped by the operator. • Only a single pump - no stand-by. Failure during peak demand periods would significantly

reduce supply to Nyrang Creek consumers, especially at the scheme’s extremities.

4.4.9 NYRANG CREEK RURAL SCHEME

Objective: To supply water to the consumers of the Nyrang Creek area for domestic and rural applications. Performance Requirements: Peak Daily Demand: 0.1 ML/day Unplanned Interruptions: Not more than once in seven days. Not more than 24 hours duration. Existing Facilities: Northern Reservoir: 0.045 ML (reinforced concrete) with a 50mm overhead feed and a

50mm underneath outlet. Southern Reservoir: 0.091 ML (reinforced concrete) with a 75mm overhead feed, two

75mm underneath outlets and a 50mm bypass.

Page 104: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 55 September 2013

Eastern Reservoir: 0.136 ML (reinforced concrete) with a 50mm overhead feed and two 75mm underneath outlets.

Main: Various lengths of 100mm, 75mm and 50mm PVC mains. Capacity: Northern Reservoir: 0.045 ML Southern Reservoir: 0.091 ML Eastern Reservoir: 0.136 ML Main: 0.1 ML/day Criticality: Rating: 1 The small number of minor consumers supplied by the Nyrang Creek Rural Scheme rely on this supply, which is therefore given a high criticality. Deficiencies and Constraints: • During high demand periods, consumers at the extremities of the scheme are starved of

supply due to the large demands of downstream consumers. • Consumers served off the rising main experience fluctuations in pressure caused by

starting and stopping of the duty pump.

4.5 SUB-SYSTEM 5

Sub-System 5 is Bangaroo Bore and Pump Station, as shown on the diagram below.

Page 105: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 56 September 2013

Res

Res

Res

P.S.

North Bore

Bangaroo

West Bore

TM 'C'

Figure 4.6: Sub-System 5. Bangaroo Bore and Pump Station consists of two bores with surface pumps, three service reservoirs and two pumps. The Western Bore is the duty bore while the Northern Bore is the stand-by. The reservoirs are all connected underneath. Water can be pumped in either direction along Trunk Main ‘C’. Under normal conditions Bangaroo Bore and Pump Station is not used but is maintained as a back-up supply. In emergency conditions, Bangaroo Bore usually supplements supply to Canowindra but can also be used to supply Grenfell and Eugowra-Gooloogong systems.

4.5.1 BANGAROO BORE PUMP STATION

Objective:

Page 106: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 57 September 2013

To pump water from Bangaroo Bore to either Canowindra or to Grenfell and Eugowra-Gooloogong during extreme operating conditions. Performance Requirements: Peak Daily Demand: 1.3 ML/day Unplanned Interruptions: Must be ready to operate when needed. Existing Facilities: Pumps #1 and #2 run individually, never together. Pump #1: Southern Cross 80x50x250 pump with 55 kW motor. Pump #2 Ornel 150 mm Bore, 23 stage pump with 22 kW, 93 amp motor. Capacity: Pump #1 Operation: 1.3 ML/day Pump #2 Operation: 0.6 ML/day Criticality: Rating: 4 As there are several pumping arrangements available when supplying Canowindra (the primary function) the likelihood of complete breakdown is highly unlikely. As Bangaroo Bore and Pump Station is a stand-by facility that is rarely operated its criticality is considered as being low. Deficiencies and Constraints: • No automatic or telemetrical control over the pump station. Pumps must be started and

stopped manually by the operator. • No protection against the service reservoirs running dry during pump operation. • As the pumps are rarely used it is necessary for the pumps to manually turned,

periodically, to prevent seizing and clogging.

4.5.2 BANGAROO BORE SERVICE RESERVOIRS

Objective: To accept water from the Bangaroo Bores, store it and supply it to Bangaroo Bore Pump Station. Performance Requirements: Peak Daily Input: 3.5 ML/day Peak Daily Output: 1.3 ML/day

Page 107: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 58 September 2013

Unplanned Interruptions: Not more than once in seven days. Not more than 24 hours duration. Existing Facilities: • Three 0.18 ML Reservoirs (reinforced concrete). • Inlets: 150mm overhead feeds from each bore. • Outlets: 200mm underneath, connecting reservoirs and to Pump Station. Capacity: 0.54 ML (three 0.18 ML reservoirs). Criticality: Rating: 4 In the context of Sub-System 5, the service reservoirs are important as they cannot be bypassed and are needed to store bore water. In the context of the whole CTW system the Bangaroo Bore service reservoirs have a low criticality. Deficiencies and Constraints: • No telemetry level indication. • No level sensing equipment for automatic control of bore pumps or pump station.

4.5.3 BANGAROO BORES

Objective: To pump groundwater into the Bangaroo Bore Service Reservoirs. Performance Requirements: Peak Daily Output: 0.6 ML/day (North Bore) 3.0 ML/day (West Bore) Unplanned Interruptions: Must be ready to operate when needed. Existing Facilities: Northern Bore: Southern Cross LAJ, 150mm, 6 stage with 9 kW, 31 amp motor. Western Bore: Ornel Bore Pump, 150mm, 13 stage with 18.5 kW, 61 amp motor. Capacity: 3.0 ML/day (rated bore field capacity). 0.6 ML/day (Northern Bore pump capacity).

Page 108: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 59 September 2013

3.0 ML/day (Western Bore pump capacity). Criticality: Rating: 4 In the context of Sub-System 5, the bores are important, as they are needed to supply bore water. As there is a duty and a stand-by bore, complete failure is very unlikely. In the context of the whole CTW system the Bangaroo Bores have a low criticality. Deficiencies and Constraints: • No automatic control of the bore pumps. • No control over quality of bore water. • Unknown and varying water table may not sustain bore pump maximum output for

lengthy, continuous operation.

4.6 SUB-SYSTEM 6

Sub-System 6 is the Gooloogong Bore and Pump Station, as shown on the diagram below.

Page 109: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 60 September 2013

Res

P.S.

Bore Bore

Gooloogong

TM 'C'

Figure 4.7: Sub-System 6. Gooloogong Bore and Pump Station consists of two bores , a service reservoir and two surface pumps. There is one duty bore and one stand-by bore, delivering water to the reservoir. Water can be pumped in either direction along Trunk Main ‘C’. Under normal conditions Gooloogong Bore and Pump Station is not used but is maintained as a back-up supply. In emergency conditions, Gooloogong Bore usually supplements supply to Grenfell but can also be used to supply the Eugowra-Gooloogong and Canowindra systems.

4.6.1 GOOLOOGONG BORE PUMP STATION

Objective:

Page 110: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 61 September 2013

To pump water from Gooloogong Bore to either Grenfell or to Grenfell, Eugowra-Gooloogong and Canowindra during extreme operating conditions. Performance Requirements: Peak Daily Demand: 3.0 ML/day Unplanned Interruptions: Must be ready to operate when needed. Existing Facilities: The pumps are run individually. The surface pumps are run individually – never together. Pump #1 KSB Multitec C100/4 – 7.1.11.62 4 stage, 132kW motor Pump #2 KSB Multitec C100/4 – 7.1.11.62 4 stage, 132kW motor Capacity: Pump #1 Operation: 1.8 ML/day (direct to Grenfell). 3.0 ML/day (to Grenfell via McDonalds Lane Pump Station). Pump #2 Operation: 1.8 ML/day (direct to Grenfell). 3.0 ML/day (to Grenfell via McDonalds Lane Pump Station). Pumps #1 and #2 Operation: 3.0 ML/day (to Grenfell, Eugowra/Gooloogong and

Canowindra). Pumps #1 and #2 Operation: 3.0 ML/day (to Grenfell via McDonald’s Lane &

Eugowra/Gooloogong). Criticality: Rating: 1 (during peak demand periods). 4 (during normal conditions). As there are several pumping arrangements available the likelihood of complete breakdown is highly unlikely. As Gooloogong Bore and Pump Station is a stand-by facility that is not normally operated its criticality is considered as being low. Deficiencies and Constraints: • Poor electrical infrastructure lead to power outages during peak summer periods.

4.6.2 GOOLOOGONG BORE SERVICE RESERVOIR

Objective:

Page 111: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 62 September 2013

To accept water from the Gooloogong Bores, store it and supply it to Gooloogong Bore Pump Station. Performance Requirements: Peak Daily Input: 3.0 ML/day Peak Daily Output: 3.0 ML/day Unplanned Interruptions: Not more than once in seven days. Not more than 24 hours duration. Existing Facilities: • 0.18 ML Reservoir (reinforced concrete). • Inlets: 150mm overhead feeds from each bore. • Outlets: One 200mm underneath and one 150mm underneath. Capacity: 0.18 ML Criticality: Rating: 1 (during peak demand periods). 4 (during normal conditions). In the context of Sub-System 6, the service reservoir is important as it cannot be bypassed and is needed to store bore water. In the context of the whole CTW system the Gooloogong Bore service reservoir has a low criticality. Deficiencies and Constraints: • None.

4.6.3 CHLORINATOR

Objective: To disinfect the bore water before it is contributed to supply. Performance Requirements: Peak Daily Flow: 2.6 ML/day Chlorine Dose: 5 mg/L Unplanned Interruptions: Must be ready to operate when needed. Existing Facilities: • Chlorinator (Wallace and Tiernan, V100, V-Notch) • Two Chlorine Cylinders:

Page 112: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 63 September 2013

The chlorinator consists of a chlorine gas supply gauge, a manually adjusted V-notch orifice to regulate gas flow rate and a chlorine injector. Capacity: Dose at 5 mg/L Disinfection of 2.6 ML/day 13.5 kg of chlorine per day Criticality: Rating: 1 (during peak demand periods). 4 (during normal conditions). Correct operation of the chlorinator is important if consumers are to be supplied with bore water for periods of time greater than 24 hours. If water from Gooloogong Bore is diluted with water supplied from Carcoar WTP or Grenfell WTP, then the criticality of Gooloogong chlorinator is slightly lessened. As the Gooloogong Bore only operates as a stand-by facility, its criticality as part of the whole CTW system is considered to be low. Deficiencies and Constraints: • Must be prepared, started and stopped manually by the operator. • As this facility is only operated for a few weeks every year, time consuming set-up and

removal-from-operation procedures must be carried out every year.

4.6.4 GOOLOOGONG BORES

Objective: To pump groundwater into the Gooloogong Bore Service Reservoir. Performance Requirements: Peak Daily Output: 3.8 ML/day Unplanned Interruptions: Must be ready to operate when needed. Existing Facilities: Bore #1: Gould 3 stage 8RJHC turbine submersible 30kW Bore #2: Southern Cross, 150mm, LAJ, 2-stage with 18.5 kW, 31 amp motor. Capacity: Bore Pump Capacity: 3.8 ML/day (each bore). Bore Field Rated Capacity: 5.0 ML/day.

Page 113: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 64 September 2013

Criticality: Rating: 1 (during peak demand periods). 4 (during normal conditions). In the context of Sub-System 6, the bores are important, as they are needed to supply bore water. As there is a duty and a stand-by bore, complete failure is very unlikely. In the context of the whole CTW system the Gooloogong Bores have a low criticality. Deficiencies and Constraints: • No control over quality of bore water. • Sustained supply of bore water to consumers may result in high number of complaints of

poor aesthetic quality. • Poor electrical infrastructure leads to power outages during peak summer periods.

4.7 SUB-SYSTEM 7

Sub-System 7 is the Eugowra area, as shown on the diagram below.

Page 114: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 65 September 2013

Res P.S

Res

P.S Res

Res

Hill Street

Broad Street

Eugowra retic.

Trajere

Trajere

Pyes Gap

TM 'L'

Eugowra

Trajere Rural

Scheme P.S

Figure 4.8: Sub-System 7. Under normal conditions, water from Carcoar WFP, transferred via Trunk Main ‘C’, is fed to Eugowra via Trunk Main ‘L’. Water for Eugowra is stored in Eugowra Reservoir and Hill Street Reservoirs. Trajere Pump Station delivers water to Trajere and Pyes Gap Reservoirs and on to Trajere Rural Scheme. Under extreme conditions, supply to Eugowra can be supplemented from Gooloogong Bore or Bangaroo Bore.

4.7.1 TRUNK MAIN ‘L’

Objective:

Page 115: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 66 September 2013

To transfer water from Trunk Main ‘C’ to Eugowra Reservoir. Performance Requirements: Peak Daily Transfer: 1.3 ML/day Unplanned Interruptions: Not more than once every month. Not more than 24 hours duration. Existing Facilities: 150mm AC main, 20.0 km long. Capacity: 0.8 ML/day. Criticality: Rating: 1 Eugowra and Trajere Rural Scheme rely on supply from Trunk Main ‘L’. Lengthy breaks on the main would affect consumers in these centers. Deficiencies and Constraints: • Use of standpipes along main during peak demand periods starves Eugowra of supply.

4.7.2 TRUNK MAIN ‘L’ BOOSTER PUMP

Objective: To accept water from Trunk Main ‘L’ boost to Eugowra. Performance Requirements: Peak Daily Demand: 1.3 ML/Day Unplanned Interruptions: No more than 24 hours, four times in one month. Existing Facilities: The pump station contains two pumps. Pump #1 Southern Cross 80x50x250 with a 22kW motor Pump #2 Southern Cross 80x50x250 with a 22kW motor The pumps are run individually – never together. Capacity: 2.1 ML/day

Page 116: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 67 September 2013

Criticality: Rating: 3 The Trunk Main ‘L’ Booster pump only operates during peak summer periods to boost water to Eugowra. A breakdown of the pump station would only cause a minor interruption, as water would automatically bypass the pump station.

4.7.3 TRAJERE PUMP STATION

Objective: To pump water from Trunk Main ‘L’ to Trajere Reservoir. Performance Requirements: Peak Daily Demand: 0.1 ML/day Unplanned Interruptions: Not more than 24 hours duration, every month. Existing Facilities: Both pumps operate directly in series. Pump #1 Southern Cross Model MFAO 8A-F with 5.5kW motor. Pump #2 Southern Cross Model MFAO 8A-F with 5.5kW motor. Capacity: 0.1 ML/day Criticality: Rating: 2 Supply to Trajere Rural Scheme depends upon the correct functioning of Trajere Pump Station. Deficiencies and Constraints: • None.

4.7.4 TRAJERE RESERVOIR

Objective: To accept water from Trajere Pump Station, store it and supply it to Trajere Rural Scheme and supply Pyes Gap reservoir.

Page 117: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 68 September 2013

Performance Requirements: Peak Daily Input: 0.1 ML/day Peak Daily Output: 0.1 ML/day Unplanned Interruptions: Not more than once in seven days. Not more than 24 hours duration. Existing Facilities: • 0.14 ML Reservoir (reinforced concrete). • Inlet - single 75mm overhead feed. • Outlet - single 75mm underneath. Capacity: 0.14 ML Criticality: Rating: 2 Supply to Trajere Rural Scheme depends upon the correct functioning of Trajere Reservoir. Deficiencies and Constraints: • Reservoir cannot be bypassed.

4.7.5 PYES GAP RESERVOIR

Objective: To accept water from Trajere Reservoir, store it and supply it to Pyes Gap Rural Scheme. Performance Requirements: Peak Daily Input: 0.1 ML/day Peak Daily Output: 0.1 ML/day Unplanned Interruptions: Not more than once in seven days. Not more than 24 hours duration. Existing Facilities: • 0.14 ML Reservoir (reinforced concrete). • Inlet - single 50mm overhead feed. • Outlet - single 100mm underneath. Capacity: 0.14 ML

Page 118: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 69 September 2013

Criticality: Rating: 2 Supply to Pyes Gap Rural Scheme depends upon the correct functioning of Pyes Gap Reservoir. Deficiencies and Constraints: • No telemetry monitoring equipment. • Reservoir cannot be bypassed.

4.7.6 EUGOWRA RESERVOIR

Objective: To accept water from Trunk Main ‘L’, store it and supply it to the reticulation system of Eugowra. Performance Requirements: Peak Daily Input: 1.3 ML/day Peak Daily Output: 1.3 ML/day Unplanned Interruptions: Not more than once in seven days. Not more than 24 hours duration. Existing Facilities: • 1.36 ML Reservoir (reinforced concrete). • Inlet - single 150mm overhead feed or 150mm underneath feed. • Outlet - single 150mm underneath. Capacity: 1.36 ML Criticality: Rating: 3 Reservoir is the main storage source for Eugowra but can be bypassed if required. Deficiencies and Constraints: • None

4.7.7 BROAD STREET PUMP STATION

Objective:

Page 119: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 70 September 2013

To pump water from Eugowra reticulation to Hill Street Reservoir, boost the pressure in the reticulation on the western side of the bridge. Performance Requirements: Peak Daily Demand: 0.8 ML/day Unplanned Interruptions: Not more than 24 hours duration, every week. Existing Facilities: • Pump/Motor Starline 80x50x200 with 11kW motor. • Pump/Motor Starline 80x50x200 with 11kW motor. Capacity: 0.8 ML/day Criticality: Rating: 4 Broad Street Pump Station only operates during peak periods and to fill the Hill Street Reservoir. A breakdown of the pump station would only cause minor disruption to consumers in way of reduced pressure. Deficiencies and Constraints: • Consumers served off the rising main and the section of reticulation that the pump draws

from will experience changes in pressure during pump start-up and shutdown.

4.7.8 HILL STREET RESERVOIRS

Objective: To accept water from Broad Street Pump Station, store it and supply it the Eugowra reticulation system. Performance Requirements: Peak Daily Input: 0.8 ML/day Peak Daily Output: 0.8 ML/day Unplanned Interruptions: Not more than once in seven days. Not more than 24 hours duration. Existing Facilities: • 0.05 ML Reservoir (reinforced concrete). • 0.45 ML Reservoir (reinforced concrete).

Page 120: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 71 September 2013

• Inlet - single 100mm overhead feed. • Outlet - single 150mm underneath. Capacity: 0.50 ML Criticality: Rating: 4 Hill Street Reservoirs are used to supply the higher areas of Eugowra. Therefore, if Hill Street Reservoir were off-line, only a small number of consumers would be affected. Deficiencies and Constraints: • No telemetry monitoring equipment.

4.8 SUB-SYSTEM 8

Sub-System 8 is the Grenfell area, as shown on the diagram below.

Page 121: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 72 September 2013

Res

Res

P.S .

Res

P.S. Res Res

Res P.S .

Quandong Rd ret iculation

East Grenfel l reticulat ion

Grenfell East North St, Grenfell

Gr enfell South

Grenfel l North

McDonalds Lane

McDonal ds Lane

Quandong Road, Grenfell

TM 'K '

Grenfell retic P.S .

Res

Grenfell West

Figure 4.9: Sub-System 8. Under normal conditions, water from Carcoar WFP is supplied to Grenfell via Trunk Main ‘C’ and Trunk Main ‘K’. This water is stored in reservoirs around the town. During peak demand periods, water from Gooloogong Bore and in emergency conditions, water from Bangaroo Bore is used to supplement supply to Grenfell.

4.8.1 TRUNK MAIN ‘K’

Objective: To transfer supply from Trunk Main ‘C’ to Grenfell North Reservoir. Performance Requirements: Peak Daily Transfer: 1.4 ML/day (straight through). 2.6 ML/day (with McDonalds Lane Pump Station). Unplanned Interruptions: Not more than once every month. Not more than 24 hours duration. Existing Facilities: 200mm Steel main, 34.12 km long. Capacity: 2.6 ML/day

Page 122: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 73 September 2013

Criticality: Rating: 1 Trunk Main ‘K’ is the only means of supplying water to Grenfell. Deficiencies and Constraints: • None.

4.8.2 MCDONALDS LANE PUMP STATION

Objective: To boost supply to Grenfell via Trunk Main ‘K’ during peak demand periods. Performance Requirements: Peak Daily Demand: 2.6 ML/day Unplanned Interruptions: Must be ready to operate when needed. Existing Facilities: Pump #1 Ritz 4910A 4 stage with 110kW motor. Pump #2 KSB WFK 80.6.6.1 BG4-53.4 with 110kW motor. Service Reservoir: 0.14 ML (reinforced concrete). Inlet: 150mm overhead feed and 150mm underneath feed. Outlet: 150mm underneath. Capacity: Booster Pump: 2.6 ML/day Service Reservoir: 0.14 ML Criticality: Rating: 2 McDonalds Lane Pump Station is stand-by facility, only used when supply to Grenfell via Trunk Main ‘K’ is needed at an increased rate. As Grenfell can be supplied via Trunk Main ‘K’, without McDonalds Lane, a breakdown of the pump station would only cause a minor interruption to the supply. Deficiencies and Constraints: • Trunk Main ‘K’ beyond McDonalds Lane pump station fails at pressures above 2000 kpa.

Page 123: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 74 September 2013

4.8.3 GRENFELL NORTH RESERVOIR

Objective: To act as a balance tank for Trunk Main ‘K’ and store water for supply to Grenfell. Performance Requirements: Peak Daily Input: 2.6 ML/day Peak Daily Output: 2.6 ML/day Unplanned Interruptions: Not more than once in seven days. Not more than 24 hours duration. Existing Facilities: • 4.55 ML Reservoir (reinforced concrete). • Inlet - single 200mm underneath feed. • Outlet - single 200mm underneath. Capacity: 4.55 ML Criticality: Rating: 3 As the Grenfell North Reservoir is the largest water storage for Grenfell, it does have a higher level of criticality than other reservoirs around Grenfell. This reservoir can be bypassed and water to Grenfell easily supplied from other sources. Deficiencies and Constraints: • None

4.8.4 GRENFELL NORTH TRANSFER BOOSTER

Objective: To accept water from the Grenfell north Reservoir and boost the pressure through the Grenfell reticulation. Performance Requirements: Peak Daily Demand: 2.6ML/day Unplanned Interruptions: No more than 24 hours, four times in one month. Existing Facilities: The pump station contains two pumps.

Page 124: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 75 September 2013

Pump #1 Southern Cross Starline 125x100x315 with 18.5kW motors Pump#2 Southern Cross Starline 125x100x315 with 18.5kW motors These pumps are run individually, never together. Capacity: 2.6ML/day Criticality: Rating: 3 The Grenfell north Transfer Booster operates during peak summer periods. A breakdown on the pump station would only cause a minor interruption, as water would automatically bypass the pump station.

4.8.5 NORTH STREET PUMP STATION

Objective: To pump water from Grenfell reticulation to Grenfell East Reservoirs. Performance Requirements: Peak Daily Demand: 0.1 ML/day Unplanned Interruptions: Not more than 24 hours duration, every week. Existing Facilities: Southern Cross Starline 50x32x200 with a 7.5kW motor. Capacity: 0.1 ML/day Criticality: Rating: 1 If the pump station broke down, the reticulation fed by the Grenfell East Reservoirs cannot be supplied by an alternative source. Deficiencies and Constraints: • Pump located in pit. • Consumers served off the rising main and the section of reticulation that the pump draws

from will experience changes in pressure during pump start-up and shutdown.

Page 125: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 76 September 2013

4.8.6 GRENFELL EAST RESERVOIRS

Objective: To accept water from North Street Pump Station, store it and supply it to Grenfell East reticulation. Performance Requirements: Peak Daily Input: 0.1 ML/day Peak Daily Output: 0.1 ML/day Unplanned Interruptions: Not more than once in seven days. Not more than 24 hours duration. Existing Facilities: Reservoir #1: Material: Reinforced concrete. Inlet: Single 100mm overhead feed. Outlet: Three 100mm underneath. Reservoir #2: Material: Reinforced concrete. Inlet: Single 100mm overhead feed. Outlet: Single 100mm underneath. Capacity: Reservoir #1: 0.181 ML Reservoir #2: 0.272 ML Criticality: Rating: 3 Under normal conditions, both reservoirs are used, though if desired, only one reservoir can be used or both can be bypassed. The reticulation fed by the Grenfell East Reservoirs cannot be supplied by an alternative source. Deficiencies and Constraints: • None

4.8.7 QUONDONG ROAD PUMP STATION

Objective: To provide a static pressure to the Quondong Road reticulation system. Performance Requirements:

Page 126: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 77 September 2013

Peak Daily Demand: 0.1 ML/day Unplanned Interruptions: Not more than 24 hours duration, every month. Existing Facilities: Southern Cross Sovereign, 155mm impeller with 4 kW, 7 amp motor. Capacity: 0.1 ML/day Criticality: Rating: 2 Supply to the small number of consumers along Quondong Road, Grenfell, depends on the correct operation of Quondong Road Pump Station. Deficiencies and Constraints: • Pump operates continuously, 24 hours per day, increasing running costs and the need for

maintenance and shortening expected operating life. • No telemetry control. • Pump located in pit.

4.8.8 GRENFELL SOUTH RESERVOIR

Objective: To accept water from Grenfell reticulation, store it and supply it to Grenfell South reticulation. Performance Requirements: Peak Daily Input: 0.1 ML/day Peak Daily Output: 0.1 ML/day Unplanned Interruptions: Not more than once in seven days. Not more than 24 hours duration. Existing Facilities: • 0.09 ML Reservoir (reinforced concrete). • Inlet - single 50mm underneath feed. • Outlet - single 50mm underneath. Capacity: 0.09 ML Criticality:

Page 127: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 78 September 2013

Rating: 4 As the reservoir feeds a small number of consumers, its criticality is considered low. Deficiencies and Constraints: • No telemetry monitoring system.

4.8.9 GRENFELL WEST RESERVOIR

Objectives: Under normal conditions, to accept water from Grenfell North Reservoir, store it and supply it to Grenfell reticulation. Performance Requirements: Peak Daily Input: 1.5 ML/day Peak Daily Output: 1.5 ML/day Unplanned Interruptions: Not more than once in seven days. Not more than 24 hours duration. Existing Facilities: • 1.36 ML Reservoir (reinforced concrete). • Inlet - single 150mm overhead feed (from WTP). • Inlet / Outlet - single 100 underneath. • Outlet - single 150mm overhead (to booster). Capacity: 1.36 ML Criticality: Rating: 1 The reservoir is a large storage component for Grenfell. Deficiencies and Constraints: • None

4.9 SUB-SYSTEM 9

Sub-System 9 is the Quandialla Bore, Pump Station and reservoirs as shown on the diagram below.

Page 128: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 79 September 2013

Res

Res

Quandialla Bore

Chlorinator

Reticulation

Elevated Storage

P.S.

TM’Q’

P.S.

Figure 4.10: Sub-System 9. Quandialla system consists of two bore with a reservoir and two surface pumps, Trunk Main ‘Q’ which delivers water from the surface pumps to on-ground storage at Quandialla village. One duty pump which takes water from the on-ground storage lifts it to the elevated storage, and then gravitates to the reticulation of Quandialla.

4.9.1 QUANDIALLA BORES

Objectives: To pump water from the Quandialla Bore to the Bore reservoir. Performance Requirements:

Page 129: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 80 September 2013

Peak Daily Demand: 1.3 ML/day Unplanned Interruptions: Must be ready to operate when needed. Existing Facilities: Bore #1 Pump Grundfos SP60-6, 11kw Bore #2 Pump Grundfos SP60-6, 11kw Capacity: 1.3 ML/day Criticality: Rating: 1 With two bores a complete failure of the system is unlikely. Deficiencies and Constraints: • None

4.9.2 QUANDIALLA BORE RESERVOIR

Objectives: To accept water from the Quandialla bore, store it and supply it to the Quandialla Pump Station. Performance Requirements: Peak Daily Input: 1.3 ML/day Peak Daily Output: 1.3 ML/day Unplanned Interruptions: Not more than once in seven days. Not more than 24 hours duration. Existing Facilities: • 0.02 ML Reservoir (Polyethylene). • Inlet 100mm underneath feed from bore. • Outlet 100mm underneath to surface pumps. Capacity: 0.02 ML Criticality: Rating: 1

Page 130: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 81 September 2013

Deficiencies and Constraints: • Unable to direct feed surface pumps.

4.9.3 QUANDIALLA BORE CHLORINATOR

Objectives: To disinfect the bore water before it contributes to supply. Performance Requirements: Peak Daily Flow: 1.3 ML/day Chlorine Dose: 2 mg/l Unplanned Interruptions: Must be ready to operate when needed. Existing Facilities: • Chlorinator (Prominent V-100 gas chlorine). • One chlorine cylinder. • One water supply pump. The chlorinator consists of a chlorine gas supply gauge, a manually adjusted V-notch orifice to regulate gas flow rate, a chlorine injector and a water supply pump to supply sufficient pressure for the injector. Capacity: • Dose at 2 mg/l • Disinfection of 1.3 ML/day • 2.6 kg of chlorine per day Criticality: Rating: 1 Deficiencies and Constraints: • Remote site

4.9.4 QUANDIALLA BORE SURFACE PUMPS

Objectives: To pump water from the Quandialla Bore reservoir to the on-ground storages at the Quandialla village, via Trunk Main ‘Q’. Performance Requirements:

Page 131: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 82 September 2013

Peak Daily Demand: 0.8 ML/day Unplanned Interruptions: Must be ready to operate when needed. Existing Facilities: The pumps are run individually, never together. Pump #1 Southern Cross Starline 60x40x315, 18.5 kw, 2pole Pump #1 Southern Cross Starline 60x40x315, 18.5 kw, 2pole Capacity: 0.8 ML/day Criticality: Rating: 1 Quandialla Bore Surface Pumps are the only means of getting water to Quandialla village. With two pumps a complete failure of the Pump Station is unlikely. Deficiencies and Constraints: • None

4.9.5 TRUNK MAIN ‘Q’

Objectives: To deliver water from the Quandialla Surface Pumps to the on-ground storage at Quandialla. Performance Requirements Peak Daily Demand: 0.8 ML/day Unplanned Interruptions: Must be ready to operate when needed. Existing Facilities: • 100mm OPVC main, 16.5 km length. Capacity: 0.8 ML/day Criticality: Rating: 1 Trunk Main ‘Q’ is the only means of supplying water to the village of Quandialla.

Page 132: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 83 September 2013

Deficiencies and Constraints: • None

4.9.6 QUANDIALLA ON-GROUND STORAGE

Objectives: To accept water from Trunk Main ‘Q’, store it and supply to the booster pump when required. Performance Requirements: Peak Daily Input: 0.8 ML/day Peak Daily Output: 0.8 ML/day Unplanned Interruptions: Not more than once in seven days. Not more than 48 hours duration. Existing Facilities: • 4 x 45,000 litre Polyethylene Reservoirs Capacity: 0.18 ML Criticality: Rating: 3 As all four reservoirs are independent of each other, any three can be off line at any given time. Deficiencies and Constraints: • None

4.9.7 QUANDIALLA BOOSTER PUMP

Objectives: To accept water from the on-ground storage and pump to the elevated storage reservoirs. Performance Requirements: Peak Daily Input: 0.8 ML Peak Daily Output: 0.8 ML

Page 133: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 84 September 2013

Unplanned Interruptions: Must be ready to operate when needed. Existing Facilities: Pump: Southern Cross Starline 100x65x250, 5.5 kw, 4 pole Capacity: 1.7 ML/day Criticality: Rating: 2 Quandialla Booster Pump supplies water to the elevated storage, which in turn supplies 15 metre head to the Quandialla village.

A pump failure would cause minor interruption a water can be bypassed direct into the reticulation. Deficiencies and Constraints: • None

4.9.8 QUANDIALLA ELEVATED STORAGE

Objectives: To accept water from the Quandialla Booster pump and supply it to Quandialla village. Performance Requirements: Peak Daily Input: 1.7 ML Peak Daily Output: 1.7 ML Unplanned Interruptions: Must be ready to operate when needed. Existing Facilities:

• 0.02 ML Polyethylene Reservoir • Inlet: 100mm underneath • Outlet: 150mm underneath

Capacity: 0.02 ML Criticality: Rating: 2 Reservoir supplies pressure to the Quandialla village, but can be bypassed if required.

Page 134: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 85 September 2013

Deficiencies and Constraints: • None

5. OPERATING RULES Operating rules are guidelines that help the system achieve its primary objective of “economically delivering water to customers that meets consumer needs for service, quality and reliability, doing so in an environmentally responsible manner” under varying conditions. Specific operating rules and procedures are detailed in each facility’s Operation and Maintenance Manual.

Page 135: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 86 September 2013

GENERAL RULES

General operating rules govern all procedures for operating CTW facilities. Detailed below, in order of priority, they summarise the approach taken for developing more detailed operation rules. 1. Operate facilities and components in the safest possible manner to protect CTW

operators and members of the public from personal risk and prevent damage to CTW, public and private property.

2. Meet NHMRC guidelines for water quality. 3. Minimise delivery costs. 4. Ensure system is 98% reliable. 5. Operate the CTW system with due diligence to ensure adverse environmental impact is

minimised.

NORMAL CONDITIONS

Normal conditions are defined as the entire CTW system being satisfactorily supplied with water from Lake Rowlands. Normal conditions are usually present for most of the year, between March and December. When operating pump stations under normal conditions, minimising pumping costs takes precedence over reservoir levels. The system is juggled to only operate pumps during low tariff periods whilst balancing supply and reservoir levels.

5.2.1 SUB-SYSTEM 1

• Monitor raw water quality in Lake Rowlands, quality at WFP’s and in reticulation systems in accordance with schedule.

• Keep level of Lake Rowlands at maximum. Only open scour valve to prevent over-topping and meet the requirements of NOW Licence.

• Operate destratification system only during spring/summer • Maintain Millthorpe, Carcoar and Blayney area Reservoirs at adequate levels. • At Browns Creek Pump Station, use Pump #1 as duty pump. • At Booster #1 Pump Station, use either Pump #1 or #2 as duty pump. • Adhere to routine and preventative maintenance schedules.

5.2.2 SUB-SYSTEM 2

• Maintain Lyndhurst, Mandurama and Garland Reservoirs at adequate levels. • Ensure sufficient flow through Trunk Mains ‘U’, ‘V’ and ‘C’. • Adhere to routine and preventative maintenance schedules.

5.2.3 SUB-SYSTEM 3

• Maintain Cargo, Cudal, Greys Hill and Manildra Reservoirs at adequate levels. • Single pump operation of Cargo Pump Station. • Adhere to routine and preventative maintenance schedules.

Page 136: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 87 September 2013

5.2.4 SUB-SYSTEM 4

• Maintain Moorbel Reservoir full. • Feed supply for whole sub-system via Trunk Main ‘V’ and Moorbel Reservoir. • Maintain all other Reservoirs at an adequate level. • Adhere to routine and preventative maintenance schedules.

5.2.5 SUB-SYSTEM 5

• Adhere to routine and preventative maintenance schedules.

5.2.6 SUB-SYSTEM 6

• Adhere to routine and preventative maintenance schedules.

5.2.7 SUB-SYSTEM 7

• Keep operation of Broad Street and Trajere Pump Stations to a minimum. • Maintain Eugowra, Hill Street, Trajere and Pyes Gap Reservoirs at an adequate level. • Adhere to routine and preventative maintenance schedules.

5.2.8 SUB-SYSTEM 8

• Maintain all Grenfell Reservoirs at an adequate level. • Adhere to routine and preventative maintenance schedules.

5.2.9 SUB-SYSTEM 9

• Monitor water quality from bores. • Monitor SWL in bores. • Maintain Quandialla reservoirs at an adequate level. • Adhere to routine and preventative maintenance schedules.

5.3 PEAK DEMAND CONDITIONS

Peak demand conditions are defined as when demand is such that the entire CTW system is unable to be solely supplied with water from Lake Rowlands. Stand-by sources and facilities are utilised to supplement supply from Lake Rowlands. These conditions usually occur for several weeks during the summer months. When operating pump stations under peak demand conditions, maintaining supply is more important than minimising pumping costs. The larger pumps are selected as the duty pumps to keep pumping times to a minimum whilst maintaining reservoir levels.

Page 137: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 88 September 2013

5.3.1 SUB-SYSTEM 1

The Council of Central Tablelands Water, at its meeting on 14th August 2013, adopted the following water restriction policy for the Lake Rowlands supply area:

Page 138: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 89 September 2013

Page 139: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 90 September 2013

Page 140: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 91 September 2013

Page 141: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 92 September 2013

Page 142: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 93 September 2013

Page 143: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 94 September 2013

Page 144: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 95 September 2013

Page 145: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 96 September 2013

Page 146: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 97 September 2013

Page 147: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 98 September 2013

Page 148: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 99 September 2013

Page 149: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 100 September 2013

Page 150: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 101 September 2013

5.3.2 SUB-SYSTEM 2

• Monitor all reservoir levels and adjust feed set-ups where necessary.

5.3.3 SUB-SYSTEM 3

• Operate Pumps at Canomodine Pump Station if level of Greys Hill Reservoir is below 50%.

• Operate both pumps at Cargo Pump Station. • If demand in Cudal is very high then operate Cudal Pump Station. • Monitor all reservoir levels and adjust feed set-ups where necessary. • Monitor chlorine residuals maintain at or near 1.0 mg/l

5.3.4 SUB-SYSTEM 4

• Take in water through Trunk Main ‘V’ and Canowindra off-take if Bangaroo Bore/Gooloogong Bore is being used to supplement supply to Canowindra.

• Adjust PRV 9 to allow sufficient flow into Trunk Main ‘U’. • Monitor all reservoir levels and adjust feed set-ups where necessary.

5.3.5 SUB-SYSTEM 5

• Boost supply to Canowindra AND Eugowra, use Pump #1 OR #2. • Boost supply to Canowindra ONLY - if demand in Canowindra is very high, use Pumps #1

AND #2. • Boost supply to Grenfell ONLY - use Pumps #1 AND #2. • See Operation and Maintenance Manual for full procedure.

5.3.6 SUB-SYSTEM 6

• Boost supply to Grenfell ONLY - use Pump #1 OR Pump #2. • Boost supply to Eugowra ONLY - use Pump #1 or Pump #2. • Boost supply to Grenfell AND Eugowra - use Pump #1 OR #2 • See Operation and Maintenance Manual for full procedure.

5.3.7 SUB-SYSTEM 7

• Adjust flow into Trunk Main ‘L’ at Old River Pump House. • Operate Trunk Main ‘L’ booster as required. • Monitor all reservoir levels and adjust feed set-ups where necessary. • Operate Broad Street Booster as required. • Monitor Chlorine residuals maintain at or near 1.0 mg/l

5.3.8 SUB-SYSTEM 8

• Boost supply via Trunk Main ‘K’ by operating McDonalds Lane Pump Station.

Page 151: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 102 September 2013

• Monitor all reservoir levels and adjust feed set-ups where necessary. • Monitor Chlorine residuals maintain at or near 1.0 mg/l

5.3.9 SUB-SYSTEM 9

• Supply and boost water to Quandialla via TM ‘Q’. • Monitor all reservoir levels and adjust feed set-ups where necessary. • Monitor Chlorine residuals maintain at or near 0.5 mg/l

5.4 ABNORMAL CONDITIONS

Abnormal conditions are caused by major main breaks, mechanical failures, prolonged drought conditions, planned maintenance and other interruptions that require the operation of the system to be altered.

5.4.1 DROUGHT

• Apply consumption restrictions. • Increase monitoring of water quality at Lake Rowlands. • Maximise use of stand-by, groundwater resources. • Prevent use of standpipes.

5.4.2 WATER FILTRATION PLANTS

• Notify consumers of possible quality problems. • Treat repair work of major WFP components as high priority. • Increase monitoring of water quality to help prevent infringements of the water quality

guidelines. • Repair of chlorinator is high priority - restore operation within 2 hours.

5.4.3 PUMP STATIONS

If Pump Station has duty / stand-by facilities; • Duty failure - switch to stand-by. • Repair duty pump within three working days. If Pump Station has no duty / stand-by facilities; • Attempt to maximise existing supply or obtain alternative supply. • Repair pump within two working days. Planned maintenance should not affect consumers for more than 8 hours duration, twice every month.

5.4.4 TRUNK MAINS

• Repair breaks in accordance with criticality and priority response times.

Page 152: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 103 September 2013

• Attempt to obtain alternative supply. Planned maintenance should not affect consumers for more than 8 hours duration, twice every month. Note: An exception to the planned maintenance interruption rule is the annual flushing of

Trunk Mains. During the flushing program, in which all Trunk Mains are flushed in sequence from Lake Rowlands to Grenfell, supply is not guaranteed for a maximum of 5 days. Industrial consumers are given 7 days notice and domestic consumers are given 48 hours notice.

5.4.5 RESERVOIRS

• Bypass reservoir where possible. • Repair failure with high priority if preventing supply from reaching reticulation system. • Attempt to obtain alternative supply. Planned maintenance should not affect consumers for more than 8 hours duration, twice every month.

5.5 DISASTER CONDITIONS

Disaster conditions are defined as life threatening failures of CTW facilities.

5.5.1 LAKE ROWLANDS DAM FAILURE

Complete, partial or even potential failure of Lake Rowlands Dam is a disaster. Failure of the dam wall at Lake Rowlands would endanger many lives and cause extensive property damage. Grenfell, Eugowra, Canowindra and Cudal can all be supplied by using stand-by groundwater facilities. Blayney’s domestic consumers could be supplied, with heavy consumption restrictions, with water from Blayney Well. All other towns and consumers would be without water supply. A disaster plan has been developed for Blayney Shire and is described in the ‘Blayney Shire DISPLAN’ document.

5.5.2 CHEMICAL ACCIDENTS

Chlorine is the most dangerous of the chemicals handled by CTW personnel. Transport, storage and handling of chlorine (and other chemicals) are done in accordance with ‘Dangerous Goods’ and/or ‘Hazardous Substances’ regulations by trained and licenced personnel. Information on first aid, containment of leaks and other emergency procedures is also given in the ‘Chemical Safety Data Sheets’ that are kept at storage facilities, transport trucks and by personnel.

Page 153: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

Central Tablelands Water

Operations Management Plan 104 September 2013

5.5.3 SEVERE DROUGHT

If the water level of Lake Rowlands falls to a level below that of the middle-level draw-off point of the outlet tower, then it is considered an emergency. The lower level draw-off point is too close to the floor of the dam to be used. A portable, barge-mounted pump is used to move water from the dam to the outlet works.

Page 154: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

CTW – Water Asset Management Plan April 2014 Page 41

Appendix B – 30 Year Financial & Capital Works Plan

Page 155: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

OPERATING STATEMENT 13/14 14/15 15/16 16/17 17/18 18/19 19/20 20/21 21/22 22/23 23/24 24/25 25/26 26/27 27/28 28/29 29/30 30/31 31/32 32/33 33/34 34/35 35/36 36/37 37/38 38/39 39/40 40/41 41/42 42/43

Operating Revenue

Availability Charges (1,235,673) (1,207,290) (1,215,675) (1,224,121) (1,232,626) (1,241,192) (1,249,819) (1,258,508) (1,267,258) (1,276,071) (1,284,946) (1,293,884) (1,302,887) (1,311,953) (1,321,083) (1,330,279) (1,339,540) (1,348,867) (1,358,261) (1,367,721) (1,377,249) (1,386,844) (1,396,508) (1,406,240) (1,416,042) (1,425,913) (1,435,855) (1,445,867) (1,455,951) (1,466,106)

Water Sales (3,661,242) (3,560,318) (3,762,787) (3,976,800) (4,203,014) (4,442,126) (4,694,873) (4,962,034) (5,244,432) (5,542,937) (5,858,471) (6,192,005) (6,544,568) (6,917,247) (7,311,192) (7,727,618) (8,167,810) (8,633,126) (9,125,002) (9,644,956) (10,194,593) (10,775,610) (11,389,800) (12,039,061) (12,725,397) (13,450,929) (14,217,896) (15,028,669) (15,885,752) (16,791,794)

User Charges (117,000) (103,799) (106,913) (110,120) (113,424) (116,827) (120,331) (123,941) (127,660) (131,489) (135,434) (139,497) (143,682) (147,993) (152,432) (157,005) (161,715) (166,567) (171,564) (176,711) (182,012) (187,473) (193,097) (198,890) (204,856) (211,002) (217,332) (223,852) (230,568) (237,485)

Interest (168,000) (213,000) (286,406) (365,266) (300,962) (226,458) (310,451) (304,853) (238,208) (198,460) (633,033) (388,706) (356,402) (331,033) (473,342) (273,381) (82,307) (123,994) (309,638) (516,352) (758,793) (1,036,211) (1,331,732) (909,730) (1,265,538) (1,660,720) (2,115,275) (2,623,633) (3,194,487) (3,829,484)

Other Revenues (330,510) (328,997) (338,867) (348,834) (359,101) (369,675) (380,567) (391,984) (392,410) (403,906) (415,746) (427,942) (440,504) (453,442) (466,769) (480,495) (494,633) (509,196) (524,195) (539,644) (555,557) (571,947) (588,829) (606,217) (624,127) (642,574) (661,575) (681,145) (701,303) (722,066)

Grants - Aquisition of Assets (158,415) (142,135) (146,399) (150,791) (155,315) (159,974) (164,773) (169,717) (174,808) (180,052) (185,454) (191,018) (196,748) (202,651) (208,730) (214,992) (221,442) (228,085) (234,927) (241,975) (249,235) (256,712) (264,413) (272,345) (280,516) (288,931) (297,599) (306,527) (315,723) (325,195)

Grants - Other (53,707) (55,392) (55,669) (55,947) (56,227) (56,508) (56,791) (57,075) (57,360) (57,647) (57,935) (58,225) (58,516) (58,808) (59,102) (59,398) (59,695) (59,993) (60,293) (60,595) (60,898) (61,202) (61,508) (61,816) (62,125) (62,435) (62,748) (63,061) (63,377) (63,694)

Contributions (22,893) (38,653) (39,812) (41,007) (42,237) (43,504) (44,809) (46,153) (47,538) (48,964) (50,433) (51,946) (53,504) (55,110) (56,763) (58,466) (60,220) (62,026) (63,887) (65,804) (67,778) (69,811) (71,905) (74,063) (76,284) (78,573) (80,930) (83,358) (85,859) (88,435)

Gains on Disposal of Assets (64,699) (51,700) (53,251) (54,849) (56,494) (58,189) (59,934) (61,733) (63,584) (65,492) (67,457) (69,480) (71,565) (73,712) (75,923) (78,201) (80,547) (82,963) (85,452) (88,016) (90,656) (93,376) (96,177) (99,063) (102,034) (105,095) (108,248) (111,496) (114,841) (118,286)

Total Operating Revenue (5,812,139) (5,701,283) (6,005,779) (6,327,734) (6,519,398) (6,714,452) (7,082,348) (7,375,997) (7,613,258) (7,905,018) (8,688,908) (8,812,703) (9,168,375) (9,551,948) (10,125,337) (10,379,835) (10,667,909) (11,214,818) (11,933,219) (12,701,774) (13,536,770) (14,439,185) (15,393,969) (15,667,425) (16,756,920) (17,926,173) (19,197,458) (20,567,609) (22,047,860) (23,642,543)

Operating Expenses

Management Expenses 1,013,334 1,175,616 1,057,710 1,077,395 1,109,717 1,143,008 1,177,299 1,207,840 1,237,471 1,274,595 1,312,835 1,352,218 1,392,784 1,434,568 1,477,605 1,521,933 1,567,591 1,614,619 1,663,057 1,712,949 1,764,337 1,817,267 1,871,785 1,927,939 1,985,777 2,045,351 2,106,711 2,169,912 2,235,010 2,302,060

Supervision & Technical Expenses 213,534 218,195 224,741 397,644 228,222 219,546 226,132 232,916 239,904 264,572 254,515 262,149 270,014 278,114 286,458 295,051 303,903 313,020 322,411 332,083 342,045 352,307 362,876 373,762 384,975 396,524 408,420 420,673 433,293 446,292

Operational Expenses 2,189,583 2,242,346 2,244,877 2,310,528 2,458,127 2,413,931 2,572,093 2,630,152 2,728,380 2,816,715 2,871,841 2,979,492 3,046,730 3,162,940 3,265,345 3,329,244 3,454,048 3,531,995 3,666,714 3,785,429 3,859,506 4,004,188 4,094,550 4,250,727 4,388,350 4,474,225 4,641,952 4,746,706 4,927,757 5,087,300

Interest 244,365 221,653 197,948 171,560 143,932 114,437 83,170 49,352 13,612 - 795,791 778,273 759,325 738,832 716,666 692,692 666,761 638,715 608,380 575,569 540,081 501,697 460,181 415,278 366,710 314,179 257,362 195,908 129,440 57,548

Depreciation - System Assets 1,656,336 1,622,048 1,670,710 1,720,831 1,772,456 1,825,630 1,880,398 1,936,810 1,994,915 2,054,762 2,116,402 2,179,897 2,245,294 2,312,653 2,382,032 2,453,493 2,527,098 2,602,911 2,680,999 2,761,428 2,844,271 2,929,599 3,017,487 3,108,012 3,201,252 3,297,290 3,396,209 3,498,095 3,603,038 3,711,129

Depreciation - Plant & Equipment 192,825 212,223 218,590 225,147 231,902 238,859 246,025 253,405 261,008 268,838 276,903 285,210 293,766 302,579 311,657 321,006 330,637 340,556 350,772 361,295 372,134 383,298 394,797 406,641 418,840 431,406 444,348 457,678 471,409 485,551

Amortisation - Intangible Assets - 46,873 46,873 39,059 - - - - - - - - - - - - - - - - - - - - - - - - - -

Total Operating Expenses 5,509,977 5,738,953 5,661,448 5,942,165 5,944,355 5,955,411 6,185,118 6,310,476 6,475,289 6,679,482 7,628,287 7,837,239 8,007,913 8,229,686 8,439,762 8,613,420 8,850,038 9,041,815 9,292,332 9,528,754 9,722,376 9,988,357 10,201,677 10,482,359 10,745,905 10,958,975 11,255,002 11,488,972 11,799,946 12,089,880

Estimated Operating Result for Period

(Surplus)/Deficit (302,162) 37,670 (344,331) (385,569) (575,043) (759,041) (897,231) (1,065,520) (1,137,969) (1,225,536) (1,060,622) (975,463) (1,160,461) (1,322,262) (1,685,575) (1,766,415) (1,817,871) (2,173,002) (2,640,887) (3,173,019) (3,814,394) (4,450,828) (5,192,292) (5,185,066) (6,011,015) (6,967,198) (7,942,456) (9,078,637) (10,247,914) (11,552,663)

Add Expenses not Involving Flow of Funds

Depreciation (1,849,161) (1,881,144) (1,936,172) (1,985,037) (2,004,358) (2,064,488) (2,126,423) (2,190,216) (2,255,922) (2,323,600) (2,393,305) (2,465,107) (2,539,060) (2,615,232) (2,693,689) (2,774,500) (2,857,735) (2,943,467) (3,031,771) (3,122,724) (3,216,406) (3,312,898) (3,412,285) (3,514,653) (3,620,093) (3,728,696) (3,840,557) (3,955,773) (4,074,446) (4,196,680)

Add Non-operating Funds Employed

Carrying amount of Assets Sold (266,301) (273,300) (281,499) (289,944) (298,642) (307,602) (316,830) (326,334) (336,125) (346,208) (356,595) (367,292) (378,311) (389,660) (401,350) (413,391) (425,792) (438,566) (451,723) (465,275) (479,233) (493,610) (508,419) (523,671) (539,381) (555,563) (572,230) (589,396) (607,078) (625,291)

Loan Funds Utilised - - - - - - - - - (10,000,000) - - - - - - - - - - - - - - - - - - - -

Less Funds Deployed for Non-operating

Purposes

Aquisition of Assets 701,811 2,132,046 746,761 3,603,873 3,867,514 1,139,089 2,946,108 4,263,849 4,040,826 5,995,397 8,039,541 4,164,420 4,289,352 1,469,520 8,123,908 8,112,073 4,001,217 1,809,431 1,965,359 1,919,625 1,997,214 2,377,018 16,237,022 2,160,555 2,343,207 2,292,133 2,360,897 2,431,724 2,504,675 1,269,958

Repayment of Loans 336,292 359,004 382,708 409,096 436,725 466,219 497,487 531,304 413,245 - 214,679 232,197 251,145 271,638 293,804 317,778 343,709 371,755 402,090 434,901 470,389 508,773 550,289 595,192 643,760 696,291 753,108 814,562 881,030 952,912

Less Internal Transactions

Transfer to Reserves 982,581 918,194 964,103 1,011,670 1,060,973 1,112,091 1,165,109 1,220,115 1,172,266 1,222,357 1,273,937 1,327,052 1,381,748 1,438,071 1,496,072 1,555,799 1,617,306 1,680,643 1,745,867 1,813,034 1,882,203 1,953,433 2,026,785 2,102,324 2,180,115 2,260,224 2,326,550 2,394,851 2,465,186 2,537,616

Transfer from Reserves (370,811) (1,913,032) (412,011) (3,441,034) (3,582,647) (773,299) (2,569,344) (3,875,782) (3,641,117) (5,583,697) (7,615,490) (3,727,647) (3,839,476) (1,006,148) (7,646,634) (7,620,481) (3,494,878) (1,287,901) (1,428,183) (1,366,334) (1,427,324) (1,790,032) (15,632,427) (1,537,821) (1,701,791) (1,631,475) (1,680,419) (1,730,832) (1,782,757) (526,381)

Estimated Budget Result (Surplus)/Deficit (767,751) (620,562) (880,441) (1,076,946) (1,095,477) (1,187,030) (1,301,123) (1,442,584) (1,744,795) (12,261,287) (1,897,854) (1,811,841) (1,995,064) (2,154,073) (2,513,465) (2,589,137) (2,634,044) (2,981,108) (3,439,249) (3,959,792) (4,587,551) (5,208,144) (5,931,325) (5,903,140) (6,705,198) (7,634,283) (8,595,107) (9,713,501) (10,861,304) (12,140,530)

CENTRAL TABLELANDS Water - 30 Year Financial Plan

Page 156: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

SCHEDULES 13/14 14/15 15/16 16/17 17/18 18/19 19/20 20/21 21/22 22/23 23/24 24/25 25/26 26/27 27/28 28/29 29/30 30/31 31/32 32/33 33/34 34/35 35/36 36/37 37/38 38/39 39/40 40/41 41/42 42/43

Management Expenses 1,013,334 1,175,617 1,057,710 1,077,395 1,109,717 1,143,008 1,177,299 1,207,840 1,237,471 1,274,595 1,312,833 1,352,218 1,392,784 1,434,568 1,477,605 1,521,933 1,567,591 1,614,619 1,663,057 1,712,949 1,764,337 1,817,267 1,871,785 1,927,939 1,985,777 2,045,351 2,106,711 2,169,912 2,235,010 2,302,060

Salaries 403,768 422,137 434,801 447,845 461,281 475,119 489,373 504,054 519,175 534,751 550,793 567,317 584,337 601,867 619,923 638,520 657,676 677,406 697,728 718,660 740,220 762,427 785,299 808,858 833,124 858,118 883,861 910,377 937,689 965,819

Employees Leave Entitlements 61,806 160,493 64,150 66,074 68,056 70,098 72,201 74,367 76,598 78,896 81,263 83,701 86,212 88,798 91,462 94,206 97,032 99,943 102,941 106,029 109,210 112,487 115,861 119,337 122,917 126,605 130,403 134,315 138,344 142,495

Employee Overhead Expenses 45,778 48,652 50,111 39,272 40,450 41,664 42,913 44,201 45,527 46,893 48,300 49,749 51,241 52,778 54,362 55,992 57,672 59,402 61,184 63,020 64,911 66,858 68,864 70,929 73,057 75,249 77,507 79,832 82,227 84,694

Management Travelling Expenses 33,600 36,750 37,853 38,988 40,158 41,362 42,603 43,881 45,198 46,554 47,950 49,389 50,871 52,397 53,969 55,588 57,255 58,973 60,742 62,564 64,441 66,375 68,366 70,417 72,529 74,705 76,946 79,255 81,632 84,081

Office Building Expenses 28,761 34,296 35,325 36,385 37,476 38,600 39,758 40,951 42,180 43,445 44,748 46,091 47,474 48,898 50,365 51,876 53,432 55,035 56,686 58,386 60,138 61,942 63,800 65,715 67,686 69,717 71,808 73,962 76,181 78,467

Office Equipment Expenses 62,875 61,887 63,743 65,656 67,625 69,654 71,744 73,896 76,113 78,396 80,748 83,171 85,666 88,236 90,883 93,609 96,418 99,310 102,289 105,358 108,519 111,774 115,128 118,582 122,139 125,803 129,577 133,465 137,468 141,593

Sundry Administration Expenses 269,675 304,785 262,429 270,301 278,410 286,763 295,366 299,450 308,434 317,687 327,218 337,034 347,145 357,559 368,286 379,335 390,715 402,436 414,509 426,945 439,753 452,946 466,534 480,530 494,946 509,794 525,088 540,841 557,066 573,778

Chairman's Allowance 14,420 14,781 15,224 15,681 16,151 16,636 17,135 17,649 18,178 18,723 19,285 19,864 20,460 21,073 21,706 22,357 23,028 23,718 24,430 25,163 25,918 26,695 27,496 28,321 29,171 30,046 30,947 31,875 32,832 33,817

Members Fees 52,713 54,013 55,634 57,303 59,022 60,792 62,616 64,495 66,429 68,422 70,475 72,589 74,767 77,010 79,320 81,700 84,151 86,675 89,276 91,954 94,712 97,554 100,480 103,495 106,600 109,798 113,092 116,484 119,979 123,578

Members Travelling & Subsistence 4,400 4,400 4,532 4,668 4,808 4,952 5,101 5,254 5,411 5,574 5,741 5,913 6,091 6,273 6,462 6,655 6,855 7,061 7,273 7,491 7,715 7,947 8,185 8,431 8,684 8,944 9,213 9,489 9,774 10,067

Members Sundry Expenses 2,628 2,628 2,706 2,788 2,871 2,957 3,046 3,136 3,136 3,230 3,327 3,427 3,530 3,636 3,745 3,857 3,973 4,092 4,215 4,341 4,472 4,606 4,744 4,886 5,033 5,184 5,339 5,500 5,665 5,835

Delegates Expenses 9,236 7,570 7,797 8,031 8,272 8,520 8,776 9,039 9,310 9,589 9,877 10,173 10,479 10,793 11,117 11,450 11,794 12,148 12,512 12,887 13,274 13,672 14,082 14,505 14,940 15,388 15,850 16,325 16,815 17,320

Subscriptions 23,674 23,226 23,406 24,404 25,136 25,890 26,667 27,467 21,781 22,434 23,107 23,800 24,514 25,250 26,007 26,787 27,591 28,419 29,271 30,149 31,054 31,985 32,945 33,933 34,951 36,000 37,080 38,192 39,338 40,518

Technical & Supervision Expenses 213,534 218,195 224,741 397,644 228,222 219,546 226,132 232,916 239,904 264,572 254,514 262,149 270,014 278,114 286,458 295,051 303,903 313,020 322,411 332,083 342,045 352,307 362,876 373,762 384,975 396,524 408,420 420,673 433,293 446,292

Salaries 105,969 109,119 112,393 115,764 119,237 122,814 126,499 130,294 134,203 138,229 142,376 146,647 151,046 155,578 160,245 165,052 170,004 175,104 180,357 185,768 191,341 197,081 202,994 209,083 215,356 221,817 228,471 235,325 242,385 249,656

Employees Leave Entitlements 22,977 23,108 23,801 206,470 20,743 21,366 22,007 22,667 23,347 24,047 24,769 25,512 26,277 27,065 27,877 28,714 29,575 30,462 31,376 32,318 33,287 34,286 35,314 36,374 37,465 38,589 39,747 40,939 42,167 43,432

Employee Overhead Expenses 9,788 9,244 9,521 (5,986) (6,166) (6,351) (6,541) (6,738) (6,940) (7,148) (7,362) (7,583) (7,811) (8,045) (8,286) (8,535) (8,791) (9,055) (9,326) (9,606) (9,894) (10,191) (10,497) (10,812) (11,136) (11,470) (11,814) (12,169) (12,534) (12,910)

Travelling Expenses 19,800 18,000 18,540 19,096 19,669 20,259 20,867 21,493 22,138 22,802 23,486 24,190 24,916 25,664 26,434 27,227 28,043 28,885 29,751 30,644 31,563 32,510 33,485 34,490 35,525 36,590 37,688 38,819 39,983 41,183

Sundry Technical Expenses 55,000 58,724 60,486 62,300 74,738 61,457 63,301 65,200 67,156 86,642 71,246 73,383 75,585 77,852 80,188 82,594 85,071 87,624 90,252 92,960 95,749 98,621 101,580 104,627 107,766 110,999 114,329 117,759 121,292 124,930

Operational Expenses 2,189,583 2,242,346 2,244,877 2,310,528 2,458,127 2,413,931 2,572,093 2,630,152 2,728,380 2,816,715 2,871,835 2,979,492 3,046,730 3,162,940 3,265,345 3,329,244 3,454,048 3,531,995 3,666,714 3,785,429 3,859,506 4,004,188 4,094,550 4,250,727 4,388,350 4,474,225 4,641,952 4,746,706 4,927,757 5,087,300

Operations Staff Leave Entitlements 132,662 131,906 135,863 139,939 216,827 130,780 134,704 138,745 142,907 147,194 151,610 156,159 160,843 165,669 170,639 175,758 181,031 186,461 192,055 197,817 203,751 209,864 216,160 222,645 229,324 236,204 243,290 250,589 258,106 265,849

Operations Staff Overheads 68,758- 80,528- 82,944- 105,628- 108,797- 112,061- 115,422- 118,885- 122,452- 126,125- 129,909- 133,806- 137,820- 141,955- 146,214- 150,600- 155,118- 159,772- 164,565- 169,502- 174,587- 179,824- 185,219- 190,776- 196,499- 202,394- 208,466- 214,720- 221,161- 227,796-

Meter Reading 75,356 74,205 76,431 78,724 81,085 83,518 86,023 88,604 91,262 94,000 96,820 99,725 102,716 105,798 108,972 112,241 115,608 119,077 122,649 126,328 130,118 134,022 138,042 142,184 146,449 150,843 155,368 160,029 164,830 169,775

Depot Expenses 68,368 71,909 74,066 76,288 78,577 80,934 83,362 85,863 88,439 91,092 93,824 96,639 99,538 102,525 105,600 108,768 112,031 115,392 118,854 122,420 126,092 129,875 133,771 137,784 141,918 146,176 150,561 155,078 159,730 164,522

Work Health & Safety (WHS) 5,346 17,598 5,671 5,841 6,016 6,197 6,383 6,574 6,771 6,974 7,184 7,399 7,621 7,850 8,085 8,328 8,578 8,835 9,100 9,373 9,654 9,944 10,242 10,549 10,866 11,192 11,528 11,873 12,230 12,597

Dams & Weirs 96,139 109,982 112,497 115,872 119,348 122,929 126,617 130,415 134,328 138,358 142,508 146,783 151,187 155,723 160,394 165,206 170,162 175,267 180,525 185,941 191,519 197,265 203,183 209,278 215,557 222,023 228,684 235,544 242,611 249,889

Mains Maintenance 450,784 472,784 486,967 501,576 516,624 532,122 548,086 564,528 581,464 598,908 616,876 635,382 654,443 674,077 694,299 715,128 736,582 758,679 781,439 804,883 829,029 853,900 879,517 905,902 933,080 961,072 989,904 1,019,601 1,050,189 1,081,695

Reservoirs - Operation Expenses - - - - - - - - - - - - - - - - - - - - - - - - - -

- Maintenance Expenses 38,394 39,192 40,368 41,579 42,826 44,111 45,434 46,797 48,201 49,647 51,137 52,671 54,251 55,879 57,555 59,282 61,060 62,892 64,779 66,722 68,724 70,785 72,909 75,096 77,349 79,669 82,059 84,521 87,057 89,669

Pumping Station - Operation Expenses - - - - - - - - - - - - - - - - - - - - - - - - - -

- Maintenance Expenses 78,612 80,472 82,886 85,373 87,934 90,572 93,289 96,088 98,970 101,939 104,998 108,148 111,392 114,734 118,176 121,721 125,373 129,134 133,008 136,998 141,108 145,341 149,701 154,193 158,818 163,583 168,490 173,545 178,751 184,114

- Energy Costs 218,489 251,465 259,009 266,780 274,783 283,026 291,517 300,263 309,271 318,549 328,105 337,948 348,087 358,529 369,285 380,364 391,775 403,528 415,634 428,103 440,946 454,174 467,800 481,834 496,289 511,177 526,513 542,308 558,577 575,335

Water Treatment - Operation Expenses 157,363 183,093 188,586 194,243 200,071 206,073 279,451 287,834 294,393 303,225 312,322 321,691 331,342 341,282 351,521 362,066 372,928 384,116 395,640 407,509 419,734 432,326 445,296 458,655 472,414 486,587 501,185 516,220 531,707 547,658

- Maintenance Expenses 284,829 261,832 269,686 277,777 286,110 294,694 303,535 312,641 322,020 331,680 341,631 351,880 362,436 373,309 384,508 396,044 407,925 420,163 432,768 445,751 459,123 472,897 487,084 501,696 516,747 532,250 548,217 564,664 581,604 599,052

- Chemical Costs 207,851 169,533 174,619 179,857 185,253 190,811 196,535 202,431 208,504 214,759 221,202 227,838 234,673 241,713 248,965 256,434 264,127 272,051 280,212 288,618 297,277 306,195 315,381 324,843 334,588 344,625 354,964 365,613 376,582 387,879

- Energy Costs 125,459 127,472 131,296 135,235 139,292 143,471 147,775 152,209 156,775 161,478 166,322 171,312 176,452 181,745 187,197 192,813 198,598 204,556 210,692 217,013 223,523 230,229 237,136 244,250 251,578 259,125 266,899 274,906 283,153 291,647

Other Costs 287,062 297,472 254,897 281,043 295,068 278,532 305,436 295,495 325,760 342,017 322,895 354,084 342,560 377,644 396,490 374,324 410,481 397,120 437,793 459,641 433,944 475,860 460,371 507,523 532,850 503,060 551,652 533,697 588,358 617,719

Quandialla Water Supply 31,627 33,960 34,979 36,028 37,109 38,222 39,369 40,550 41,766 43,019 44,310 45,639 47,008 48,419 49,871 51,367 52,908 54,496 56,130 57,814 59,549 61,335 63,175 65,071 67,023 69,033 71,104 73,237 75,435 77,698

Interest Expenses 244,365 221,653 197,948 171,560 143,932 114,437 83,170 49,352 13,612 - 795,791 778,273 759,325 738,832 716,666 692,692 666,761 638,715 608,380 575,569 540,081 501,697 460,181 415,278 366,710 314,179 257,362 195,908 129,440 57,548

Interest on Loans 244,365 221,653 197,948 171,560 143,932 114,437 83,170 49,352 13,612 - 795,791 778,273 759,325 738,832 716,666 692,692 666,761 638,715 608,380 575,569 540,081 501,697 460,181 415,278 366,710 314,179 257,362 195,908 129,440 57,548

CENTRAL TABLELANDS Water - 30 Year Financial Plan

Page 157: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

OPERATING INCOME 13/14 14/15 15/16 16/17 17/18 18/19 19/20 20/21 21/22 22/23 23/24 24/25 25/26 26/27 27/28 28/29 29/30 30/31 31/32 32/33 33/34 34/35 35/36 36/37 37/38 38/39 39/40 40/41 41/42 42/43

Availability Charges 1,235,673 1,207,290 1,215,675 1,224,121 1,232,626 1,241,192 1,249,819 1,258,508 1,267,258 1,276,071 1,284,946 1,293,884 1,302,887 1,311,953 1,321,083 1,330,279 1,339,540 1,348,867 1,358,261 1,367,721 1,377,249 1,386,844 1,396,508 1,406,240 1,416,042 1,425,913 1,435,855 1,445,867 1,455,951 1,466,106

Residential, Rural & Commercial 1,266,379 1,269,890 1,278,779 1,287,731 1,296,745 1,305,822 1,314,963 1,324,168 1,333,437 1,342,771 1,352,170 1,361,635 1,371,167 1,380,765 1,390,430 1,400,163 1,409,964 1,419,834 1,429,773 1,439,781 1,449,860 1,460,009 1,470,229 1,480,521 1,490,884 1,501,320 1,511,830 1,522,412 1,533,069 1,543,801

Industrial 14,512 15,312 15,312 15,312 15,312 15,312 15,312 15,312 15,312 15,312 15,312 15,312 15,312 15,312 15,312 15,312 15,312 15,312 15,312 15,312 15,312 15,312 15,312 15,312 15,312 15,312 15,312 15,312 15,312 15,312

Quandialla Service Charges 52,432 22,800 22,800 22,800 22,800 22,800 22,800 22,800 22,800 22,800 22,800 22,800 22,800 22,800 22,800 22,800 22,800 22,800 22,800 22,800 22,800 22,800 22,800 22,800 22,800 22,800 22,800 22,800 22,800 22,800

Less: Pensioner Rebates (97,650) (100,713) (101,216) (101,722) (102,231) (102,742) (103,256) (103,772) (104,291) (104,812) (105,336) (105,863) (106,392) (106,924) (107,459) (107,996) (108,536) (109,079) (109,624) (110,172) (110,723) (111,277) (111,833) (112,392) (112,954) (113,519) (114,087) (114,657) (115,230) (115,807)

Water Sales 3,661,242 3,560,318 3,762,787 3,976,800 4,203,014 4,442,126 4,694,873 4,962,034 5,244,432 5,542,937 5,858,471 6,192,005 6,544,568 6,917,247 7,311,192 7,727,618 8,167,810 8,633,126 9,125,002 9,644,956 10,194,593 10,775,610 11,389,800 12,039,061 12,725,397 13,450,929 14,217,896 15,028,669 15,885,752 16,791,794

Price per Kilolitre 2.15 2.25 2.36 2.48 2.60 2.73 2.87 3.02 3.17 3.32 3.49 3.67 3.85 4.04 4.24 4.45 4.68 4.91 5.16 5.41 5.69 5.97 6.27 6.58 6.91 7.26 7.62 8.00 8.40 8.82

Average Annual Consumer Account 611 630 651 674 697 722 748 776 805 835 867 900 935 972 1,010 1,051 1,093 1,138 1,185 1,234 1,286 1,340 1,397 1,457 1,520 1,586 1,655 1,728 1,804 1,885

Water Sales - Residential etc 3,030,000 2,880,000 3,045,168 3,219,808 3,404,464 3,599,710 3,806,154 4,024,437 4,255,238 4,499,276 4,757,310 5,030,141 5,318,620 5,623,643 5,946,159 6,287,171 6,647,740 7,028,988 7,432,100 7,858,331 8,309,007 8,785,528 9,289,378 9,822,124 10,385,423 10,981,027 11,610,789 12,276,668 12,980,735 13,725,180

Water Sales - Industrial 333,207 400,163 423,112 447,377 473,034 500,163 528,847 559,177 591,245 625,153 661,006 698,915 738,997 781,379 826,191 873,573 923,672 976,645 1,032,656 1,091,878 1,154,498 1,220,708 1,290,716 1,364,738 1,443,006 1,525,762 1,613,265 1,705,785 1,803,612 1,907,049

Water Sales - Cowra 167,700 175,500 185,565 196,207 207,460 219,357 231,937 245,239 259,304 274,175 289,899 306,524 324,103 342,691 362,344 383,124 405,097 428,329 452,894 478,867 506,330 535,368 566,071 598,536 632,862 669,156 707,532 748,109 791,014 836,378

Water Sales - Other 13,385 10,155 10,663 11,196 11,756 12,343 12,961 13,609 14,289 15,004 15,754 16,541 17,368 18,237 19,149 20,106 21,112 22,167 23,275 24,439 25,661 26,944 28,291 29,706 31,191 32,751 34,388 36,108 37,913 39,809

Water Sales - Quandialla 63,200 94,500 98,280 102,211 106,300 110,552 114,974 119,573 124,356 129,330 134,503 139,883 145,478 151,298 157,349 163,643 170,189 176,997 184,077 191,440 199,097 207,061 215,344 223,957 232,916 242,232 251,922 261,998 272,478 283,377

Excess Water Sales Price per kilolitre 3.23

Water Sales Above 450kl 53,750 - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

User Charges 117,000 103,799 106,913 110,120 113,424 116,827 120,331 123,941 127,660 131,489 135,434 139,497 143,682 147,993 152,432 157,005 161,715 166,567 171,564 176,711 182,012 187,473 193,097 198,890 204,856 211,002 217,332 223,852 230,568 237,485

Installations & Private Works Income 75,000 58,699 60,460 62,274 64,142 66,066 68,048 70,090 72,192 74,358 76,589 78,887 81,253 83,691 86,201 88,788 91,451 94,195 97,021 99,931 102,929 106,017 109,197 112,473 115,848 119,323 122,903 126,590 130,387 134,299

Attendance & Reconnection Charges 30,000 32,500 33,475 34,479 35,514 36,579 37,676 38,807 39,971 41,170 42,405 43,677 44,988 46,337 47,727 49,159 50,634 52,153 53,718 55,329 56,989 58,699 60,460 62,273 64,142 66,066 68,048 70,089 72,192 74,358

Meter Test & Special Reading Fees - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

Section 603 Certificates 12,000 12,600 12,978 13,367 13,768 14,181 14,607 15,045 15,496 15,961 16,440 16,933 17,441 17,965 18,504 19,059 19,630 20,219 20,826 21,451 22,094 22,757 23,440 24,143 24,867 25,613 26,382 27,173 27,988 28,828

Interest 168,000 213,000 286,406 365,266 300,962 226,458 310,451 304,853 238,208 198,460 633,033 388,706 356,402 331,033 473,342 273,381 82,307 123,994 309,638 516,352 758,793 1,036,211 1,331,732 909,730 1,265,538 1,660,720 2,115,275 2,623,633 3,194,487 3,829,484

Investments 160,000 206,000 279,336 358,125 293,749 219,174 303,094 297,423 230,703 190,880 625,377 380,974 348,592 323,146 465,376 265,335 74,180 115,786 301,348 507,979 750,336 1,027,670 1,323,105 901,017 1,256,738 1,651,831 2,106,298 2,614,566 3,185,330 3,820,235

Overdue Accounts 8,000 7,000 7,070 7,141 7,212 7,284 7,357 7,431 7,505 7,580 7,656 7,732 7,810 7,888 7,967 8,046 8,127 8,208 8,290 8,373 8,457 8,541 8,627 8,713 8,800 8,888 8,977 9,067 9,157 9,249

Other Revenues 330,510 328,997 338,867 348,834 359,101 369,675 380,567 391,984 392,410 403,906 415,746 427,942 440,504 453,442 466,769 480,495 494,633 509,196 524,195 539,644 555,557 571,947 588,829 606,217 624,127 642,574 661,575 681,145 701,303 722,066

Catchment Area Rents 6,429 6,429 6,622 6,622 6,622 6,622 6,622 6,821 6,821 6,821 6,821 6,821 6,821 6,821 6,821 6,821 6,821 6,821 6,821 6,821 6,821 6,821 6,821 6,821 6,821 6,821 6,821 6,821 6,821 6,821

Lease Income NBN & Police Dept 6,571 11,000 11,330 11,670 12,020 12,381 12,752 13,135 2,400 2,400 2,400 2,400 2,400 2,400 2,400 2,400 2,400 2,400 2,400 2,400 2,400 2,400 2,400 2,400 2,400 2,400 2,400 2,400 2,400 2,400

Sundry Income 1,500 1,000 1,030 1,061 1,093 1,126 1,159 1,194 1,230 1,267 1,305 1,344 1,384 1,426 1,469 1,513 1,558 1,605 1,653 1,702 1,754 1,806 1,860 1,916 1,974 2,033 2,094 2,157 2,221 2,288

Plant Running Income 302,510 297,268 306,186 315,372 324,833 334,578 344,615 354,954 365,602 376,570 387,867 399,503 411,488 423,833 436,548 449,645 463,134 477,028 491,339 506,079 521,261 536,899 553,006 569,596 586,684 604,285 622,413 641,086 660,318 680,128

Insurance Experience Discount & Rebates 13,500 13,300 13,699 14,110 14,533 14,969 15,418 15,881 16,357 16,848 17,353 17,874 18,410 18,963 19,531 20,117 20,721 21,343 21,983 22,642 23,322 24,021 24,742 25,484 26,249 27,036 27,847 28,683 29,543 30,429

Grants 53,707 55,392 55,669 55,947 56,227 56,508 56,791 57,075 57,360 57,647 57,935 58,225 58,516 58,808 59,102 59,398 59,695 59,993 60,293 60,595 60,898 61,202 61,508 61,816 62,125 62,435 62,748 63,061 63,377 63,694

Acquisition of Assets - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

Pensioner Rebates 53,707 55,392 55,669 55,947 56,227 56,508 56,791 57,075 57,360 57,647 57,935 58,225 58,516 58,808 59,102 59,398 59,695 59,993 60,293 60,595 60,898 61,202 61,508 61,816 62,125 62,435 62,748 63,061 63,377 63,694

Sundry Grants & Subsidies - IWCM & Drought - - - - - - -

Contributions 22,893 38,653 39,812 41,007 42,237 43,504 44,809 46,153 47,538 48,964 50,433 51,946 53,504 55,110 56,763 58,466 60,220 62,026 63,887 65,804 67,778 69,811 71,905 74,063 76,284 78,573 80,930 83,358 85,859 88,435

Staff contributions - vehicles & superannuation 22,893 38,653 39,812 41,007 42,237 43,504 44,809 46,153 47,538 48,964 50,433 51,946 53,504 55,110 56,763 58,466 60,220 62,026 63,887 65,804 67,778 69,811 71,905 74,063 76,284 78,573 80,930 83,358 85,859 88,435

Gain or Loss on Sale of Assets 64,699 51,700 53,251 54,849 56,494 58,189 59,934 61,733 63,584 65,492 67,457 69,480 71,565 73,712 75,923 78,201 80,547 82,963 85,452 88,016 90,656 93,376 96,177 99,063 102,034 105,095 108,248 111,496 114,841 118,286

Profit on Sale Plant & Equipment 64,699 51,700 53,251 54,849 56,494 58,189 59,934 61,733 63,584 65,492 67,457 69,480 71,565 73,712 75,923 78,201 80,547 82,963 85,452 88,016 90,656 93,376 96,177 99,063 102,034 105,095 108,248 111,496 114,841 118,286

320,827 304,730 390,682 320,454 239,098 330,648 324,461 251,676 208,233 682,230 415,608 380,282 352,523 507,682 289,457 80,924 126,312 328,743 554,159 818,549 1,121,094 1,443,387 982,928 1,370,987 1,801,998 2,297,780 2,852,254 3,474,905 4,167,529 5,016,635

CENTRAL TABLELANDS Water - 30 Year Financial Plan

Page 158: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

OPERATING STATEMENT 13/14 14/15 15/16 16/17 17/18 18/19 19/20 20/21 21/22 22/23 23/24 24/25 25/26 26/27 27/28 28/29 29/30 30/31 31/32 32/33 33/34 34/35 35/36 36/37 37/38 38/39 39/40 40/41 41/42 42/43

Administration Salaries 403,768 422,137 434,801 447,845 461,281 475,119 489,373 504,054 519,175 534,751 550,793 567,317 584,337 601,867 619,923 638,520 657,676 677,406 697,728 718,660 740,220 762,427 785,299 808,858 833,124 858,118 883,861 910,377 937,689 965,819

General Manager 141,848 146,090 150,473 154,987 159,637 164,426 169,358 174,439 179,672 185,063 190,614 196,333 202,223 208,289 214,538 220,974 227,604 234,432 241,465 248,709 256,170 263,855 271,771 279,924 288,321 296,971 305,880 315,057 324,508 334,243

Administration Staff 261,920 276,047 284,329 292,858 301,644 310,693 320,014 329,615 339,503 349,688 360,179 370,984 382,114 393,577 405,384 417,546 430,072 442,975 456,264 469,952 484,050 498,572 513,529 528,935 544,803 561,147 577,981 595,321 613,180 631,576

Administration Leave Entitlements 61,806 160,493 64,150 66,074 68,056 70,098 72,201 74,367 76,598 78,896 81,263 83,701 86,212 88,798 91,462 94,206 97,032 99,943 102,941 106,029 109,210 112,487 115,861 119,337 122,917 126,605 130,403 134,315 138,344 142,495

Annual Leave 34,703 35,178 36,233 37,320 38,440 39,593 40,781 42,004 43,265 44,563 45,899 47,276 48,695 50,156 51,660 53,210 54,806 56,451 58,144 59,888 61,685 63,536 65,442 67,405 69,427 71,510 73,655 75,865 78,141 80,485

Long Service Leave 27,103 125,315 27,916 28,754 29,616 30,505 31,420 32,362 33,333 34,333 35,363 36,424 37,517 38,642 39,802 40,996 42,226 43,492 44,797 46,141 47,525 48,951 50,420 51,932 53,490 55,095 56,748 58,450 60,204 62,010

Administration - Overhead 45,778 48,652 50,111 39,272 40,450 41,664 42,913 44,201 45,527 46,893 48,300 49,749 51,241 52,778 54,362 55,992 57,672 59,402 61,184 63,020 64,911 66,858 68,864 70,929 73,057 75,249 77,507 79,832 82,227 84,694

Payroll Tax 12,936 14,131 14,555 14,992 15,441 15,905 16,382 16,873 17,379 17,901 18,438 18,991 19,561 20,147 20,752 21,374 22,016 22,676 23,356 24,057 24,779 25,522 26,288 27,076 27,889 28,725 29,587 30,475 31,389 32,331

Fringe Benefits Tax 6,000 8,000 8,240 8,487 8,742 9,004 9,274 9,552 9,839 10,134 10,438 10,751 11,074 11,406 11,748 12,101 12,464 12,838 13,223 13,619 14,028 14,449 14,882 15,329 15,789 16,262 16,750 17,253 17,770 18,303

Training Expenses 6,000 7,985 8,225 8,471 8,725 8,987 9,257 9,535 9,821 10,115 10,419 10,731 11,053 11,385 11,726 12,078 12,440 12,814 13,198 13,594 14,002 14,422 14,854 15,300 15,759 16,232 16,719 17,220 17,737 18,269

Workers Compensation Insurance 12,147 12,670 13,050 13,442 13,845 14,260 14,688 15,129 15,583 16,050 16,531 17,027 17,538 18,064 18,606 19,165 19,739 20,332 20,942 21,570 22,217 22,883 23,570 24,277 25,005 25,756 26,528 27,324 28,144 28,988

Superannuation 46,434 49,400 50,882 40,066 41,268 42,506 43,781 45,095 46,447 47,841 49,276 50,754 52,277 53,845 55,461 57,125 58,838 60,603 62,422 64,294 66,223 68,210 70,256 72,364 74,535 76,771 79,074 81,446 83,889 86,406

Sick Leave Insurance 3,071 1,146 1,180 1,216 1,252 1,290 1,329 1,368 1,409 1,452 1,495 1,540 1,586 1,634 1,683 1,733 1,785 1,839 1,894 1,951 2,010 2,070 2,132 2,196 2,262 2,330 2,399 2,471 2,546 2,622

less Contributions to Admin.Overheads (40,810) (44,680) (46,021) (47,402) (48,824) (50,288) (51,797) (53,351) (54,951) (56,600) (58,298) (60,047) (61,848) (63,704) (65,615) (67,583) (69,611) (71,699) (73,850) (76,066) (78,348) (80,698) (83,119) (85,612) (88,181) (90,826) (93,551) (96,358) (99,248) (102,226)

Administration Travelling 33,600 36,750 37,853 38,988 40,158 41,362 42,603 43,881 45,198 46,554 47,950 49,389 50,871 52,397 53,969 55,588 57,255 58,973 60,742 62,564 64,441 66,375 68,366 70,417 72,529 74,705 76,946 79,255 81,632 84,081

General Manager 17,100 17,550 18,077 18,619 19,177 19,753 20,345 20,956 21,584 22,232 22,899 23,586 24,293 25,022 25,773 26,546 27,342 28,163 29,007 29,878 30,774 31,697 32,648 33,628 34,636 35,676 36,746 37,848 38,984 40,153

Administration Staff 16,500 19,200 19,776 20,369 20,980 21,610 22,258 22,926 23,614 24,322 25,052 25,803 26,577 27,375 28,196 29,042 29,913 30,810 31,735 32,687 33,667 34,677 35,718 36,789 37,893 39,030 40,201 41,407 42,649 43,928

CENTRAL TABLELANDS Water - 30 Year Financial Plan

Page 159: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

OPERATING STATEMENT 13/14 14/15 15/16 16/17 17/18 18/19 19/20 20/21 21/22 22/23 23/24 24/25 25/26 26/27 27/28 28/29 29/30 30/31 31/32 32/33 33/34 34/35 35/36 36/37 37/38 38/39 39/40 40/41 41/42 42/43

Administration Building 28,761 34,296 35,325 36,385 37,476 38,600 39,758 40,951 42,180 43,445 44,748 46,091 47,474 48,898 50,365 51,876 53,432 55,035 56,686 58,386 60,138 61,942 63,800 65,715 67,686 69,717 71,808 73,962 76,181 78,467

Building M & R 4,506 4,683 4,823 4,968 5,117 5,271 5,429 5,592 5,759 5,932 6,110 6,293 6,482 6,677 6,877 7,083 7,296 7,515 7,740 7,972 8,211 8,458 8,711 8,973 9,242 9,519 9,805 10,099 10,402 10,714

Office Cleaning 15,055 16,057 16,539 17,035 17,546 18,072 18,614 19,173 19,748 20,341 20,951 21,579 22,227 22,893 23,580 24,288 25,016 25,767 26,540 27,336 28,156 29,001 29,871 30,767 31,690 32,641 33,620 34,628 35,667 36,737

Electricity & Gas 7,000 11,192 11,528 11,874 12,230 12,597 12,975 13,364 13,765 14,178 14,603 15,041 15,492 15,957 16,436 16,929 17,437 17,960 18,499 19,054 19,625 20,214 20,821 21,445 22,089 22,751 23,434 24,137 24,861 25,607

Council Rates 1,720 1,884 1,941 1,999 2,059 2,120 2,184 2,250 2,317 2,387 2,458 2,532 2,608 2,686 2,767 2,850 2,935 3,023 3,114 3,207 3,304 3,403 3,505 3,610 3,718 3,830 3,945 4,063 4,185 4,310

Sundry Building Expenses 480 480 494 509 525 540 556 573 590 608 626 645 664 684 705 726 748 770 793 817 842 867 893 920 947 976 1,005 1,035 1,066 1,098

Office Equipment 62,875 61,887 63,743 65,656 67,625 69,654 71,744 73,896 76,113 78,396 80,748 83,171 85,666 88,236 90,883 93,609 96,418 99,310 102,289 105,358 108,519 111,774 115,128 118,582 122,139 125,803 129,577 133,465 137,468 141,593

Equipment M & R 12,680 13,302 13,701 14,112 14,536 14,972 15,421 15,884 16,360 16,851 17,356 17,877 18,413 18,966 19,535 20,121 20,724 21,346 21,987 22,646 23,325 24,025 24,746 25,488 26,253 27,041 27,852 28,687 29,548 30,434

Computer Hardware & Software Support 42,445 43,435 44,738 46,080 47,462 48,886 50,353 51,863 53,419 55,022 56,672 58,372 60,124 61,927 63,785 65,699 67,670 69,700 71,791 73,945 76,163 78,448 80,801 83,225 85,722 88,294 90,942 93,671 96,481 99,375

Computer & Copier Lease Payments - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

Computer Sundry Expenses 7,750 5,150 5,305 5,464 5,628 5,796 5,970 6,149 6,334 6,524 6,720 6,921 7,129 7,343 7,563 7,790 8,024 8,264 8,512 8,768 9,031 9,301 9,581 9,868 10,164 10,469 10,783 11,106 11,440 11,783

Other Administration Expenses 269,675 304,785 262,429 270,301 278,410 286,763 295,366 299,450 308,434 317,687 327,218 337,034 347,145 357,559 368,286 379,335 390,715 402,436 414,509 426,945 439,753 452,946 466,534 480,530 494,946 509,794 525,088 540,841 557,066 573,778

Advertising 6,000 6,000 6,180 6,365 6,556 6,753 6,956 7,164 7,379 7,601 7,829 8,063 8,305 8,555 8,811 9,076 9,348 9,628 9,917 10,215 10,521 10,837 11,162 11,497 11,842 12,197 12,563 12,940 13,328 13,728

Printing & Stationery 23,187 23,414 24,116 24,840 25,585 26,353 27,143 27,958 28,796 29,660 30,550 31,466 32,410 33,383 34,384 35,416 36,478 37,573 38,700 39,861 41,057 42,288 43,557 44,864 46,210 47,596 49,024 50,494 52,009 53,570

Postage & Courier Charges 14,000 15,400 15,862 16,338 16,828 17,333 17,853 18,388 18,940 19,508 20,094 20,696 21,317 21,957 22,615 23,294 23,993 24,712 25,454 26,217 27,004 27,814 28,649 29,508 30,393 31,305 32,244 33,212 34,208 35,234

Telephone & Fax Charges - Office 7,295 7,192 7,408 7,630 7,859 8,095 8,337 8,588 8,845 9,111 9,384 9,665 9,955 10,254 10,562 10,879 11,205 11,541 11,887 12,244 12,611 12,990 13,379 13,781 14,194 14,620 15,058 15,510 15,976 16,455

Bank & Merchant Charges 25,200 25,725 26,497 27,292 28,110 28,954 29,822 30,717 31,638 32,588 33,565 34,572 35,609 36,678 37,778 38,911 40,079 41,281 42,519 43,795 45,109 46,462 47,856 49,292 50,771 52,294 53,862 55,478 57,143 58,857

Consultancy Fees Consumer Survey - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

Audit Fees 16,427 16,986 17,496 18,020 18,561 19,118 19,691 20,282 20,891 21,517 22,163 22,828 23,513 24,218 24,945 25,693 26,464 27,258 28,075 28,918 29,785 30,679 31,599 32,547 33,523 34,529 35,565 36,632 37,731 38,863

Internal Audit 10,000 15,000 15,450 15,914 16,391 16,883 17,389 17,911 18,448 19,002 19,572 20,159 20,764 21,386 22,028 22,689 23,370 24,071 24,793 25,536 26,303 27,092 27,904 28,742 29,604 30,492 31,407 32,349 33,319 34,319

Legal Expenses 8,000 8,000 8,240 8,487 8,742 9,004 9,274 9,552 9,839 10,134 10,438 10,751 11,074 11,406 11,748 12,101 12,464 12,838 13,223 13,619 14,028 14,449 14,882 15,329 15,789 16,262 16,750 17,253 17,770 18,303

Integrated Planning & Reporting (IP&R) 1,500 2,500 2,575 2,652 2,732 2,814 2,898 2,985 3,075 3,167 3,262 3,360 3,461 3,564 3,671 3,781 3,895 4,012 4,132 4,256 4,384 4,515 4,651 4,790 4,934 5,082 5,234 5,391 5,553 5,720

Insurance - Public Liability/Prof. Indemnity 23,585 24,387 25,119 25,872 26,648 27,448 28,271 29,119 29,993 30,893 31,820 32,774 33,757 34,770 35,813 36,888 37,994 39,134 40,308 41,517 42,763 44,046 45,367 46,728 48,130 49,574 51,061 52,593 54,171 55,796

- Industrial Special Risk (Property) 56,975 61,658 63,508 65,413 67,375 69,397 71,479 73,623 75,832 78,107 80,450 82,863 85,349 87,910 90,547 93,263 96,061 98,943 101,911 104,969 108,118 111,361 114,702 118,143 121,687 125,338 129,098 132,971 136,960 141,069

- Fidelity Guarantee 1,000 1,030 1,061 1,093 1,126 1,159 1,194 1,230 1,267 1,305 1,344 1,384 1,426 1,469 1,513 1,558 1,605 1,653 1,702 1,754 1,806 1,860 1,916 1,974 2,033 2,094 2,157 2,221 2,288 2,357

Sundry Administration Expenses:

- Sundry Expenses 9,219 7,700 7,931 8,169 8,414 8,666 8,926 9,194 9,470 9,754 10,047 10,348 10,659 10,978 11,308 11,647 11,996 12,356 12,727 13,109 13,502 13,907 14,324 14,754 15,197 15,653 16,122 16,606 17,104 17,617

- Rounding of Cents - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

- Collection Agency Charges - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

- Commission on Water Sales 1,284 - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

Blayney Shire - Shared HR Support 4,000 4,000 4,120 4,244 4,371 4,502 4,637 - - - - - - - - - - - - - - - - - - - - - - -

WBC Alliance 19,143 22,883 23,569 24,277 25,005 25,755 26,528 27,323 28,143 28,987 29,857 30,753 31,675 32,626 33,604 34,613 35,651 36,720 37,822 38,957 40,125 41,329 42,569 43,846 45,162 46,516 47,912 49,349 50,830 52,355

WBC Alliance Projects 30,000 50,000

Contributions & Donations 12,860 12,910 13,297 13,696 14,107 14,530 14,966 15,415 15,878 16,354 16,845 17,350 17,870 18,407 18,959 19,528 20,113 20,717 21,338 21,978 22,638 23,317 24,016 24,737 25,479 26,243 27,031 27,842 28,677 29,537

Chairman's Allowance 14,420 14,781 15,224 15,681 16,151 16,636 17,135 17,649 18,178 18,723 19,285 19,864 20,460 21,073 21,706 22,357 23,028 23,718 24,430 25,163 25,918 26,695 27,496 28,321 29,171 30,046 30,947 31,875 32,832 33,817

Chairman's Allowance 14,420 14,781 15,224 15,681 16,151 16,636 17,135 17,649 18,178 18,723 19,285 19,864 20,460 21,073 21,706 22,357 23,028 23,718 24,430 25,163 25,918 26,695 27,496 28,321 29,171 30,046 30,947 31,875 32,832 33,817

Members' Fees - Section 248 52,713 54,013 55,634 57,303 59,022 60,792 62,616 64,495 66,429 68,422 70,475 72,589 74,767 77,010 79,320 81,700 84,151 86,675 89,276 91,954 94,712 97,554 100,480 103,495 106,600 109,798 113,092 116,484 119,979 123,578

Annual Fee 52,713 54,013 55,634 57,303 59,022 60,792 62,616 64,495 66,429 68,422 70,475 72,589 74,767 77,010 79,320 81,700 84,151 86,675 89,276 91,954 94,712 97,554 100,480 103,495 106,600 109,798 113,092 116,484 119,979 123,578

CENTRAL TABLELANDS Water - 30 Year Financial Plan

Page 160: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

OPERATING STATEMENT 13/14 14/15 15/16 16/17 17/18 18/19 19/20 20/21 21/22 22/23 23/24 24/25 25/26 26/27 27/28 28/29 29/30 30/31 31/32 32/33 33/34 34/35 35/36 36/37 37/38 38/39 39/40 40/41 41/42 42/43

Members' Travelling & Subsistence 4,400 4,400 4,532 4,668 4,808 4,952 5,101 5,254 5,411 5,574 5,741 5,913 6,091 6,273 6,462 6,655 6,855 7,061 7,273 7,491 7,715 7,947 8,185 8,431 8,684 8,944 9,213 9,489 9,774 10,067

Travelling & Subsistence 4,400 4,400 4,532 4,668 4,808 4,952 5,101 5,254 5,411 5,574 5,741 5,913 6,091 6,273 6,462 6,655 6,855 7,061 7,273 7,491 7,715 7,947 8,185 8,431 8,684 8,944 9,213 9,489 9,774 10,067

Members' Sundry Expenses 2,628 2,628 2,706 2,788 2,871 2,957 3,046 3,136 3,136 3,230 3,327 3,427 3,530 3,636 3,745 3,857 3,973 4,092 4,215 4,341 4,472 4,606 4,744 4,886 5,033 5,184 5,339 5,500 5,665 5,835

Insurance 2,628 2,628 2,706 2,788 2,871 2,957 3,046 3,136 3,136 3,230 3,327 3,427 3,530 3,636 3,745 3,857 3,973 4,092 4,215 4,341 4,472 4,606 4,744 4,886 5,033 5,184 5,339 5,500 5,665 5,835

Delegates Expenses 9,236 7,570 7,797 8,031 8,272 8,520 8,776 9,039 9,310 9,589 9,877 10,173 10,479 10,793 11,117 11,450 11,794 12,148 12,512 12,887 13,274 13,672 14,082 14,505 14,940 15,388 15,850 16,325 16,815 17,320

LG One Association & LGMA Conferences 6,438 4,920 5,068 5,220 5,376 5,538 5,704 5,875 6,051 6,233 6,419 6,612 6,810 7,015 7,225 7,442 7,665 7,895 8,132 8,376 8,627 8,886 9,153 9,427 9,710 10,001 10,301 10,610 10,929 11,257

Water Resources Conference 2,798 2,650 2,730 2,811 2,896 2,983 3,072 3,164 3,259 3,357 3,458 3,561 3,668 3,778 3,892 4,008 4,129 4,252 4,380 4,511 4,647 4,786 4,930 5,078 5,230 5,387 5,549 5,715 5,886 6,063

Subscriptions 23,674 23,226 23,406 24,404 25,136 25,890 26,667 27,467 21,781 22,434 23,107 23,800 24,514 25,250 26,007 26,787 27,591 28,419 29,271 30,149 31,054 31,985 32,945 33,933 34,951 36,000 37,080 38,192 39,338 40,518

LGNSW Subscription 2,358 2,475 2,549 2,626 2,704 2,786 2,869 2,955 3,044 3,135 3,229 3,326 3,426 3,529 3,635 3,744 3,856 3,972 4,091 4,214 4,340 4,470 4,604 4,742 4,885 5,031 5,182 5,338 5,498 5,663

Water Directorate 3,416 3,455 3,559 3,665 3,775 3,889 4,005 4,125 4,249 4,377 4,508 4,643 4,783 4,926 5,074 5,226 5,383 5,544 5,711 5,882 6,058 6,240 6,427 6,620 6,819 7,023 7,234 7,451 7,675 7,905

Australian Water Association 618 655 675 695 716 737 759 782 806 830 855 880 907 934 962 991 1,020 1,051 1,083 1,115 1,149 1,183 1,218 1,255 1,293 1,331 1,371 1,413 1,455 1,499

CENTROC 6,000 5,645 5,814 5,989 6,168 6,353 6,544 6,740 432 445 458 472 486 501 516 531 547 564 581 598 616 634 653 673 693 714 735 758 780 804

CENTROC Water Utilities Alliance 8,197 8,740 8,485 9,036 9,307 9,586 9,874 10,170 10,475 10,789 11,113 11,447 11,790 12,144 12,508 12,883 13,270 13,668 14,078 14,500 14,935 15,383 15,845 16,320 16,810 17,314 17,833 18,368 18,919 19,487

CENTROC Savewater Alliance Membership 2,595 2,256 2,324 2,393 2,465 2,539 2,615 2,694 2,775 2,858 2,944 3,032 3,123 3,217 3,313 3,412 3,515 3,620 3,729 3,841 3,956 4,075 4,197 4,323 4,452 4,586 4,724 4,865 5,011 5,162

Lachlan Valley Water Inc 490 - - - - - - - -

Technical/Supervision Salaries 105,969 109,119 112,393 115,764 119,237 122,814 126,499 130,294 134,203 138,229 142,376 146,647 151,046 155,578 160,245 165,052 170,004 175,104 180,357 185,768 191,341 197,081 202,994 209,083 215,356 221,817 228,471 235,325 242,385 249,656

Operations Manager 105,969 109,119 112,393 115,764 119,237 122,814 126,499 130,294 134,203 138,229 142,376 146,647 151,046 155,578 160,245 165,052 170,004 175,104 180,357 185,768 191,341 197,081 202,994 209,083 215,356 221,817 228,471 235,325 242,385 249,656

Technical Assistance - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

Technical/Super. Staff Leave Entitlements 22,977 23,108 23,801 206,470 20,743 21,366 22,007 22,667 23,347 24,047 24,769 25,512 26,277 27,065 27,877 28,714 29,575 30,462 31,376 32,318 33,287 34,286 35,314 36,374 37,465 38,589 39,747 40,939 42,167 43,432

Annual Leave 8,831 9,093 9,366 9,647 9,936 10,235 10,542 10,858 11,184 11,519 11,865 12,221 12,587 12,965 13,354 13,754 14,167 14,592 15,030 15,481 15,945 16,423 16,916 17,424 17,946 18,485 19,039 19,610 20,199 20,805

Long Service Leave 14,146 14,015 14,435 196,823 10,807 11,131 11,465 11,809 12,163 12,528 12,904 13,291 13,690 14,101 14,524 14,959 15,408 15,870 16,347 16,837 17,342 17,862 18,398 18,950 19,519 20,104 20,707 21,329 21,968 22,627

Technical/Supervision Staff Overheads 9,788 9,244 9,521 5,986- 6,166- 6,351- 6,541- 6,738- 6,940- 7,148- 7,362- 7,583- 7,811- 8,045- 8,286- 8,535- 8,791- 9,055- 9,326- 9,606- 9,894- 10,191- 10,497- 10,812- 11,136- 11,470- 11,814- 12,169- 12,534- 12,910-

Payroll Tax 4,107 3,742 3,855 3,970 4,090 4,212 4,339 4,469 4,603 4,741 4,883 5,030 5,180 5,336 5,496 5,661 5,831 6,006 6,186 6,371 6,562 6,759 6,962 7,171 7,386 7,608 7,836 8,071 8,313 8,563

Fringe Benefits Tax 2,000 4,000 4,120 4,244 4,371 4,502 4,637 4,776 4,919 5,067 5,219 5,376 5,537 5,703 5,874 6,050 6,232 6,419 6,611 6,810 7,014 7,224 7,441 7,664 7,894 8,131 8,375 8,626 8,885 9,152

Training Expenses 1,240 1,200 1,236 1,273 1,311 1,351 1,391 1,433 1,476 1,520 1,566 1,613 1,661 1,711 1,762 1,815 1,870 1,926 1,983 2,043 2,104 2,167 2,232 2,299 2,368 2,439 2,513 2,588 2,666 2,746

Workers Compensation Insurance 3,533 3,675 3,785 3,898 4,015 4,136 4,260 4,388 4,519 4,655 4,794 4,938 5,086 5,239 5,396 5,558 5,725 5,897 6,073 6,256 6,443 6,637 6,836 7,041 7,252 7,470 7,694 7,924 8,162 8,407

Superannuation 23,067 23,370 24,071 9,000 9,270 9,548 9,835 10,130 10,433 10,746 11,069 11,401 11,743 12,095 12,458 12,832 13,217 13,613 14,022 14,442 14,876 15,322 15,782 16,255 16,743 17,245 17,762 18,295 18,844 19,409

Sick Leave Insurance 3,461 3,044 3,135 3,229 3,326 3,426 3,529 3,635 3,744 3,856 3,972 4,091 4,214 4,340 4,470 4,604 4,742 4,885 5,031 5,182 5,338 5,498 5,663 5,833 6,008 6,188 6,373 6,565 6,762 6,964

less Supervision O/heads charged to jobs (27,620) (29,787) (30,681) (31,601) (32,549) (33,526) (34,531) (35,567) (36,634) (37,733) (38,865) (40,031) (41,232) (42,469) (43,743) (45,055) (46,407) (47,799) (49,233) (50,710) (52,232) (53,799) (55,413) (57,075) (58,787) (60,551) (62,367) (64,238) (66,166) (68,150)

Technical/Supervision Travelling 19,800 18,000 18,540 19,096 19,669 20,259 20,867 21,493 22,138 22,802 23,486 24,190 24,916 25,664 26,434 27,227 28,043 28,885 29,751 30,644 31,563 32,510 33,485 34,490 35,525 36,590 37,688 38,819 39,983 41,183

Operations Manager 19,800 18,000 18,540 19,096 19,669 20,259 20,867 21,493 22,138 22,802 23,486 24,190 24,916 25,664 26,434 27,227 28,043 28,885 29,751 30,644 31,563 32,510 33,485 34,490 35,525 36,590 37,688 38,819 39,983 41,183

CENTRAL TABLELANDS Water - 30 Year Financial Plan

Page 161: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

OPERATING STATEMENT 13/14 14/15 15/16 16/17 17/18 18/19 19/20 20/21 21/22 22/23 23/24 24/25 25/26 26/27 27/28 28/29 29/30 30/31 31/32 32/33 33/34 34/35 35/36 36/37 37/38 38/39 39/40 40/41 41/42 42/43

Sundry Engineering Expenses 55,000 58,724 60,486 62,300 74,738 61,457 63,301 65,200 67,156 86,642 71,246 73,383 75,585 77,852 80,188 82,594 85,071 87,624 90,252 92,960 95,749 98,621 101,580 104,627 107,766 110,999 114,329 117,759 121,292 124,930

Engineers Office/Mapping Expenses 3,082 3,030 3,121 3,215 3,311 3,410 3,513 3,618 3,727 3,838 3,953 4,072 4,194 4,320 4,450 4,583 4,721 4,862 5,008 5,158 5,313 5,473 5,637 5,806 5,980 6,159 6,344 6,534 6,731 6,932

Telemetry Expenses 45,618 44,194 45,520 46,886 48,292 49,741 51,233 52,770 54,353 55,984 57,663 59,393 61,175 63,010 64,901 66,848 68,853 70,919 73,046 75,237 77,495 79,819 82,214 84,680 87,221 89,838 92,533 95,309 98,168 101,113

Asset/Mapping Management System 1,500 7,000 7,210 7,426 7,649 7,879 8,115 8,358 8,609 8,867 9,133 9,407 9,690 9,980 10,280 10,588 10,906 11,233 11,570 11,917 12,275 12,643 13,022 13,413 13,815 14,230 14,656 15,096 15,549 16,015

Asset Revaluation - - - - 15,071 - - - - 17,471

Waterwise/Demand Management 4,800 4,500 4,635 4,774 415 428 441 454 467 481 496 511 526 542 558 575 592 610 628 647 666 686 707 728 750 773 796 820 844 869

Operations Staff Leave Entitlements 132,662 131,906 135,863 139,939 216,827 130,780 134,704 138,745 142,907 147,194 151,610 156,159 160,843 165,669 170,639 175,758 181,031 186,461 192,055 197,817 203,751 209,864 216,160 222,645 229,324 236,204 243,290 250,589 258,106 265,849

Annual Leave 57,902 58,323 60,072 61,874 63,731 65,643 67,612 69,640 71,729 73,881 76,098 78,381 80,732 83,154 85,649 88,218 90,865 93,591 96,398 99,290 102,269 105,337 108,497 111,752 115,105 118,558 122,115 125,778 129,551 133,438

Sick Leave - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

Long Service Leave 46,718 45,287 46,646 48,045 122,176 33,290 34,289 35,317 36,377 37,468 38,592 39,750 40,943 42,171 43,436 44,739 46,081 47,464 48,887 50,354 51,865 53,421 55,023 56,674 58,374 60,125 61,929 63,787 65,701 67,672

Public Holidays 28,042 28,296 29,145 30,020 30,920 31,848 32,803 33,787 34,801 35,845 36,920 38,028 39,169 40,344 41,554 42,801 44,085 45,407 46,769 48,173 49,618 51,106 52,639 54,219 55,845 57,521 59,246 61,024 62,854 64,740

Operations Staff Overheads 68,758- 80,528- 82,944- 105,628- 108,797- 112,061- 115,422- 118,885- 122,452- 126,125- 129,909- 133,806- 137,820- 141,955- 146,214- 150,600- 155,118- 159,772- 164,565- 169,502- 174,587- 179,824- 185,219- 190,776- 196,499- 202,394- 208,466- 214,720- 221,161- 227,796-

Payroll Tax 25,797 23,347 24,048 24,769 25,512 26,277 27,066 27,878 28,714 29,575 30,463 31,377 32,318 33,287 34,286 35,315 36,374 37,465 38,589 39,747 40,939 42,167 43,432 44,735 46,078 47,460 48,884 50,350 51,861 53,416

Fringe Benefits Tax - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

Training Expenses 19,235 19,499 20,084 20,687 21,307 21,947 22,605 23,283 23,982 24,701 25,442 26,205 26,992 27,801 28,635 29,494 30,379 31,291 32,229 33,196 34,192 35,218 36,274 37,363 38,484 39,638 40,827 42,052 43,314 44,613

Workers Compensation Insurance 20,810 20,874 21,500 22,145 22,810 23,494 24,199 24,925 25,673 26,443 27,236 28,053 28,895 29,762 30,654 31,574 32,521 33,497 34,502 35,537 36,603 37,701 38,832 39,997 41,197 42,433 43,706 45,017 46,368 47,759

Superannuation 79,637 75,143 77,397 59,524 61,310 63,149 65,043 66,995 69,005 71,075 73,207 75,403 77,665 79,995 82,395 84,867 87,413 90,035 92,736 95,519 98,384 101,336 104,376 107,507 110,732 114,054 117,476 121,000 124,630 128,369

Sick Leave Insurance 5,059 4,390 4,521 4,657 4,797 4,941 5,089 5,242 5,399 5,561 5,728 5,899 6,076 6,259 6,446 6,640 6,839 7,044 7,256 7,473 7,697 7,928 8,166 8,411 8,664 8,923 9,191 9,467 9,751 10,043

less: Charged to New Installations - - - - - - - - - - - - - - - - - - - - - - - - - - - -

less: Quandialla Overheads & Supervision - - - - - - - - - - - - - - - - - - - - - - - - - - - -

less: Contributions to Overheads (219,296) (223,782) (230,495) (237,410) (244,532) (251,868) (259,424) (267,207) (275,223) (283,480) (291,984) (300,744) (309,766) (319,059) (328,631) (338,490) (348,645) (359,104) (369,877) (380,973) (392,403) (404,175) (416,300) (428,789) (441,653) (454,902) (468,549) (482,606) (497,084) (511,996)

Meter Reading 75,356 74,205 76,431 78,724 81,085 83,518 86,023 88,604 91,262 94,000 96,820 99,725 102,716 105,798 108,972 112,241 115,608 119,077 122,649 126,328 130,118 134,022 138,042 142,184 146,449 150,843 155,368 160,029 164,830 169,775

Meter Reading 75,356 74,205 76,431 78,724 81,085 83,518 86,023 88,604 91,262 94,000 96,820 99,725 102,716 105,798 108,972 112,241 115,608 119,077 122,649 126,328 130,118 134,022 138,042 142,184 146,449 150,843 155,368 160,029 164,830 169,775

Depot Expenses 68,368 71,909 74,066 76,288 78,577 80,934 83,362 85,863 88,439 91,092 93,824 96,639 99,538 102,525 105,600 108,768 112,031 115,392 118,854 122,420 126,092 129,875 133,771 137,784 141,918 146,176 150,561 155,078 159,730 164,522

Depot Expenses 68,368 71,909 74,066 76,288 78,577 80,934 83,362 85,863 88,439 91,092 93,824 96,639 99,538 102,525 105,600 108,768 112,031 115,392 118,854 122,420 126,092 129,875 133,771 137,784 141,918 146,176 150,561 155,078 159,730 164,522

Work Health & Safety (WHS) 5,346 17,598 5,671 5,841 6,016 6,197 6,383 6,574 6,771 6,974 7,184 7,399 7,621 7,850 8,085 8,328 8,578 8,835 9,100 9,373 9,654 9,944 10,242 10,549 10,866 11,192 11,528 11,873 12,230 12,597

Work Health & Safety (WHS) 5,346 17,598 5,671 5,841 6,016 6,197 6,383 6,574 6,771 6,974 7,184 7,399 7,621 7,850 8,085 8,328 8,578 8,835 9,100 9,373 9,654 9,944 10,242 10,549 10,866 11,192 11,528 11,873 12,230 12,597

Dams & Weirs 96,139 109,982 112,497 115,872 119,348 122,929 126,617 130,415 134,328 138,358 142,508 146,783 151,187 155,723 160,394 165,206 170,162 175,267 180,525 185,941 191,519 197,265 203,183 209,278 215,557 222,023 228,684 235,544 242,611 249,889

Lake Rowlands - Foreshore Management 13,033 12,510 12,885 13,272 13,670 14,080 14,502 14,937 15,385 15,847 16,322 16,812 17,316 17,836 18,371 18,922 19,490 20,075 20,677 21,297 21,936 22,594 23,272 23,970 24,689 25,430 26,193 26,979 27,788 28,621

- Algal Control 3,844 3,589 3,697 3,807 3,922 4,039 4,161 4,285 4,414 4,546 4,683 4,823 4,968 5,117 5,270 5,429 5,591 5,759 5,932 6,110 6,293 6,482 6,676 6,877 7,083 7,296 7,514 7,740 7,972 8,211

- Council Rates - - - - - - - - - - - - - - - - - - - - - - - - - - - -

- Maintenance 55,071 53,343 54,943 56,591 58,289 60,037 61,839 63,694 65,605 67,573 69,600 71,688 73,839 76,054 78,335 80,685 83,106 85,599 88,167 90,812 93,536 96,343 99,233 102,210 105,276 108,434 111,687 115,038 118,489 122,044

- Check Levels & Destratif'n - - - - - - - - - - - - - - - - - - - - - - - - - - - -

- Other 18,619 39,779 40,973 42,202 43,468 44,772 46,115 47,499 48,924 50,391 51,903 53,460 55,064 56,716 58,417 60,170 61,975 63,834 65,749 67,722 69,754 71,846 74,002 76,222 78,508 80,863 83,289 85,788 88,362 91,013

Lake Rowlands - Safety Review - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

Bogolong Dam - Foreshore Management 5,421 761

- Other 151 - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

Mains Maintenance 450,784 472,784 486,967 501,576 516,624 532,122 548,086 564,528 581,464 598,908 616,876 635,382 654,443 674,077 694,299 715,128 736,582 758,679 781,439 804,883 829,029 853,900 879,517 905,902 933,080 961,072 989,904 1,019,601 1,050,189 1,081,695

Reticulation - Hydrants & Stop Valves 98,420 121,330 124,970 128,719 132,580 136,558 140,654 144,874 149,220 153,697 158,308 163,057 167,949 172,987 178,177 183,522 189,028 194,699 200,540 206,556 212,752 219,135 225,709 232,480 239,455 246,638 254,037 261,659 269,508 277,594

- Flushing 12,284 12,634 13,013 13,404 13,806 14,220 14,647 15,086 15,538 16,005 16,485 16,979 17,489 18,013 18,554 19,110 19,684 20,274 20,882 21,509 22,154 22,819 23,503 24,208 24,935 25,683 26,453 27,247 28,064 28,906

- Breakages & Leaks 75,372 76,391 78,682 81,043 83,474 85,978 88,558 91,214 93,951 96,769 99,672 102,663 105,743 108,915 112,182 115,548 119,014 122,585 126,262 130,050 133,951 137,970 142,109 146,372 150,764 155,286 159,945 164,743 169,686 174,776

- Locations 3,110 3,188 3,284 3,382 3,484 3,588 3,696 3,807 3,921 4,039 4,160 4,285 4,413 4,546 4,682 4,823 4,967 5,116 5,270 5,428 5,591 5,758 5,931 6,109 6,292 6,481 6,676 6,876 7,082 7,295

- Services 51,133 52,160 53,725 55,337 56,997 58,707 60,468 62,282 64,151 66,075 68,057 70,099 72,202 74,368 76,599 78,897 81,264 83,702 86,213 88,799 91,463 94,207 97,034 99,945 102,943 106,031 109,212 112,488 115,863 119,339

- System Checks 37,969 39,060 40,232 41,439 42,682 43,962 45,281 46,640 48,039 49,480 50,964 52,493 54,068 55,690 57,361 59,082 60,854 62,680 64,560 66,497 68,492 70,547 72,663 74,843 77,088 79,401 81,783 84,236 86,763 89,366

- Restorations 2,392 2,465 2,539 2,615 2,693 2,774 2,857 2,943 3,031 3,122 3,216 3,312 3,412 3,514 3,620 3,728 3,840 3,955 4,074 4,196 4,322 4,452 4,585 4,723 4,864 5,010 5,161 5,316 5,475 5,639

- Other 40,567 44,024 45,345 46,705 48,106 49,550 51,036 52,567 54,144 55,768 57,442 59,165 60,940 62,768 64,651 66,590 68,588 70,646 72,765 74,948 77,197 79,512 81,898 84,355 86,885 89,492 92,177 94,942 97,790 100,724

Trunk Mains - Air & Scour Valves 48,819 39,789 40,983 42,212 43,478 44,783 46,126 47,510 48,935 50,403 51,916 53,473 55,077 56,730 58,431 60,184 61,990 63,850 65,765 67,738 69,770 71,863 74,019 76,240 78,527 80,883 83,309 85,809 88,383 91,034

- Flushing 4,628 4,768 4,911 5,058 5,210 5,366 5,527 5,693 5,864 6,040 6,221 6,407 6,600 6,798 7,002 7,212 7,428 7,651 7,880 8,117 8,360 8,611 8,869 9,135 9,409 9,692 9,982 10,282 10,590 10,908

- Breakages & Leaks 28,879 28,730 29,592 30,480 31,394 32,336 33,306 34,305 35,334 36,394 37,486 38,611 39,769 40,962 42,191 43,457 44,761 46,103 47,486 48,911 50,378 51,890 53,446 55,050 56,701 58,402 60,154 61,959 63,818 65,732

- System Checks 31,553 32,280 33,248 34,246 35,273 36,331 37,421 38,544 39,700 40,891 42,118 43,382 44,683 46,023 47,404 48,826 50,291 51,800 53,354 54,954 56,603 58,301 60,050 61,852 63,707 65,618 67,587 69,615 71,703 73,854

- Services 11,855 12,073 12,436 12,809 13,193 13,589 13,996 14,416 14,849 15,294 15,753 16,226 16,712 17,214 17,730 18,262 18,810 19,374 19,955 20,554 21,171 21,806 22,460 23,134 23,828 24,543 25,279 26,037 26,818 27,623

- Locations 3,803 3,892 4,008 4,129 4,252 4,380 4,511 4,647 4,786 4,930 5,078 5,230 5,387 5,548 5,715 5,886 6,063 6,245 6,432 6,625 6,824 7,029 7,240 7,457 7,680 7,911 8,148 8,393 8,644 8,904

CENTRAL TABLELANDS Water - 30 Year Financial Plan

Page 162: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

OPERATING STATEMENT 13/14 14/15 15/16 16/17 17/18 18/19 19/20 20/21 21/22 22/23 23/24 24/25 25/26 26/27 27/28 28/29 29/30 30/31 31/32 32/33 33/34 34/35 35/36 36/37 37/38 38/39 39/40 40/41 41/42 42/43

Reservoirs - Operations Expenses - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

Blayney Area Reservoir Operations to be split up from Reservoir Maintenance

Canowindra Area - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

Grenfell Area - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

D-Section Area - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

Reservoirs - Maintenance 38,394 39,192 40,368 41,579 42,826 44,111 45,434 46,797 48,201 49,647 51,137 52,671 54,251 55,879 57,555 59,282 61,060 62,892 64,779 66,722 68,724 70,785 72,909 75,096 77,349 79,669 82,059 84,521 87,057 89,669

Blayney Area 10,603 10,663 10,983 11,313 11,652 12,002 12,362 12,733 13,115 13,508 13,913 14,331 14,760 15,203 15,659 16,129 16,613 17,111 17,625 18,154 18,698 19,259 19,837 20,432 21,045 21,676 22,327 22,996 23,686 24,397

Canowindra Area 14,216 14,664 15,104 15,557 16,024 16,505 17,000 17,510 18,035 18,576 19,133 19,707 20,299 20,908 21,535 22,181 22,846 23,532 24,238 24,965 25,714 26,485 27,280 28,098 28,941 29,809 30,703 31,625 32,573 33,550

Grenfell Area 3,135 3,185 3,281 3,379 3,481 3,585 3,692 3,803 3,917 4,035 4,156 4,281 4,409 4,541 4,678 4,818 4,962 5,111 5,265 5,423 5,585 5,753 5,925 6,103 6,286 6,475 6,669 6,869 7,075 7,287

Other - Mowing 7,631 7,827 8,062 8,303 8,553 8,809 9,073 9,346 9,626 9,915 10,212 10,519 10,834 11,159 11,494 11,839 12,194 12,560 12,936 13,325 13,724 14,136 14,560 14,997 15,447 15,910 16,387 16,879 17,385 17,907

D-Section Area 2,809 2,853 2,938 3,026 3,117 3,211 3,307 3,406 3,509 3,614 3,722 3,834 3,949 4,067 4,189 4,315 4,444 4,578 4,715 4,857 5,002 5,152 5,307 5,466 5,630 5,799 5,973 6,152 6,337 6,527

Pumping Station - Operation Expenses - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

Blayney Area Pumping Station Operations to be split from Pumping Station Maintenance - - - - - - - - - - - - - - - - - - - - - - - - -

Canowindra Area - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

Grenfell Area - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

D-Section Area - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

Pumping Station - Maintenance & Repair 78,612 80,472 82,886 85,373 87,934 90,572 93,289 96,088 98,970 101,939 104,998 108,148 111,392 114,734 118,176 121,721 125,373 129,134 133,008 136,998 141,108 145,341 149,701 154,193 158,818 163,583 168,490 173,545 178,751 184,114

Blayney Area 24,980 25,740 26,512 27,307 28,126 28,970 29,839 30,735 31,657 32,606 33,585 34,592 35,630 36,699 37,800 38,934 40,102 41,305 42,544 43,820 45,135 46,489 47,883 49,320 50,800 52,324 53,893 55,510 57,175 58,891

Canowindra Area 29,111 28,530 29,386 30,267 31,175 32,110 33,074 34,066 35,088 36,141 37,225 38,342 39,492 40,677 41,897 43,154 44,448 45,782 47,155 48,570 50,027 51,528 53,074 54,666 56,306 57,995 59,735 61,527 63,373 65,274

Grenfell Area 14,362 15,170 15,625 16,094 16,576 17,074 17,586 18,114 18,657 19,217 19,793 20,387 20,999 21,629 22,277 22,946 23,634 24,343 25,073 25,826 26,600 27,398 28,220 29,067 29,939 30,837 31,762 32,715 33,697 34,707

D-Section Area 10,159 11,033 11,364 11,705 12,056 12,417 12,790 13,174 13,569 13,976 14,395 14,827 15,272 15,730 16,202 16,688 17,188 17,704 18,235 18,782 19,346 19,926 20,524 21,140 21,774 22,427 23,100 23,793 24,507 25,242

Pumping Station - Energy Costs 218,489 251,465 259,009 266,780 274,783 283,026 291,517 300,263 309,271 318,549 328,105 337,948 348,087 358,529 369,285 380,364 391,775 403,528 415,634 428,103 440,946 454,174 467,800 481,834 496,289 511,177 526,513 542,308 558,577 575,335

Blayney Area 122,409 91,322 94,062 96,883 99,790 102,784 105,867 109,043 112,314 115,684 119,154 122,729 126,411 130,203 134,109 138,133 142,277 146,545 150,941 155,469 160,134 164,938 169,886 174,982 180,232 185,639 191,208 196,944 202,852 208,938

Canowindra Area 70,530 87,423 90,045 92,747 95,529 98,395 101,347 104,387 107,519 110,745 114,067 117,489 121,014 124,644 128,383 132,235 136,202 140,288 144,497 148,831 153,296 157,895 162,632 167,511 172,536 177,713 183,044 188,535 194,191 200,017

Grenfell Area 19,600 63,830 65,745 67,717 69,749 71,841 73,996 76,216 78,503 80,858 83,283 85,782 88,355 91,006 93,736 96,548 99,445 102,428 105,501 108,666 111,926 115,284 118,742 122,304 125,974 129,753 133,645 137,655 141,784 146,038

D-Section Area 5,950 8,891 9,158 9,432 9,715 10,007 10,307 10,616 10,935 11,263 11,601 11,949 12,307 12,676 13,057 13,448 13,852 14,267 14,695 15,136 15,590 16,058 16,540 17,036 17,547 18,073 18,616 19,174 19,749 20,342

CENTRAL TABLELANDS Water - 30 Year Financial Plan

Page 163: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

OPERATING STATEMENT 13/14 14/15 15/16 16/17 17/18 18/19 19/20 20/21 21/22 22/23 23/24 24/25 25/26 26/27 27/28 28/29 29/30 30/31 31/32 32/33 33/34 34/35 35/36 36/37 37/38 38/39 39/40 40/41 41/42 42/43

Water Filtration - Operating Expenses 157,363 183,093 188,586 194,243 200,071 206,073 279,451 287,834 294,393 303,225 312,322 321,691 331,342 341,282 351,521 362,066 372,928 384,116 395,640 407,509 419,734 432,326 445,296 458,655 472,414 486,587 501,185 516,220 531,707 547,658

Blayney WFP 53,831 57,114 58,828 60,593 62,410 64,283 66,211 68,198 70,244 72,351 74,521 76,757 79,060 81,432 83,874 86,391 88,982 91,652 94,401 97,233 100,150 103,155 106,250 109,437 112,720 116,102 119,585 123,172 126,868 130,674

Carcoar WFP 53,831 57,114 58,828 60,593 62,410 64,283 66,211 68,198 70,244 72,351 74,521 76,757 79,060 81,432 83,874 86,391 88,982 91,652 94,401 97,233 100,150 103,155 106,250 109,437 112,720 116,102 119,585 123,172 126,868 130,674

Grenfell WFP Permanently out of operation - - - - - - - - - - - - - - - - - - - - - - - -

Off-site Sludge Disposal - - - - - - 67,196 69,212 69,212 71,288 73,427 75,630 77,899 80,236 82,643 85,122 87,676 90,306 93,015 95,805 98,680 101,640 104,689 107,830 111,065 114,397 117,829 121,363 125,004 128,754

Staff Training 5,079 6,194 6,380 6,572 6,769 6,972 7,181 7,396 7,618 7,847 8,082 8,325 8,575 8,832 9,097 9,370 9,651 9,940 10,238 10,546 10,862 11,188 11,523 11,869 12,225 12,592 12,970 13,359 13,760 14,172

Water Analysis - Reticulation 16,922 21,090 21,722 22,374 23,045 23,737 24,449 25,182 25,938 26,716 27,517 28,343 29,193 30,069 30,971 31,900 32,857 33,843 34,858 35,904 36,981 38,090 39,233 40,410 41,622 42,871 44,157 45,482 46,846 48,252

- Trunk Mains 16,723 16,152 16,637 17,136 17,650 18,180 18,725 19,287 19,865 20,461 21,075 21,708 22,359 23,030 23,720 24,432 25,165 25,920 26,698 27,498 28,323 29,173 30,048 30,950 31,878 32,835 33,820 34,834 35,879 36,956

- Lake Rowlands 9,306 8,903 9,170 9,445 9,728 10,020 10,321 10,631 10,949 11,278 11,616 11,965 12,324 12,693 13,074 13,466 13,870 14,287 14,715 15,157 15,611 16,080 16,562 17,059 17,571 18,098 18,641 19,200 19,776 20,369

- Other 1,671 16,525 17,020 17,531 18,057 18,599 19,156 19,731 20,323 20,933 21,561 22,208 22,874 23,560 24,267 24,995 25,745 26,517 27,313 28,132 28,976 29,845 30,741 31,663 32,613 33,591 34,599 35,637 36,706 37,807

Water Filtration - Maintenance & Repair 284,829 261,832 269,686 277,777 286,110 294,694 303,535 312,641 322,020 331,680 341,631 351,880 362,436 373,309 384,508 396,044 407,925 420,163 432,768 445,751 459,123 472,897 487,084 501,696 516,747 532,250 548,217 564,664 581,604 599,052

Blayney WFP 113,162 111,066 114,397 117,829 121,364 125,005 128,755 132,618 136,597 140,694 144,915 149,263 153,741 158,353 163,103 167,997 173,036 178,228 183,574 189,082 194,754 200,597 206,615 212,813 219,197 225,773 232,547 239,523 246,709 254,110

Carcoar WFP 171,667 150,766 155,289 159,948 164,746 169,689 174,779 180,023 185,423 190,986 196,715 202,617 208,695 214,956 221,405 228,047 234,889 241,935 249,193 256,669 264,369 272,300 280,469 288,883 297,550 306,476 315,671 325,141 334,895 344,942

Grenfell WFP Permanently out of operation - - - - - - - - - - - - - - - - - - - - - - - - - - -

Water Filtration - Chemical Costs 207,851 169,533 174,619 179,857 185,253 190,811 196,535 202,431 208,504 214,759 221,202 227,838 234,673 241,713 248,965 256,434 264,127 272,051 280,212 288,618 297,277 306,195 315,381 324,843 334,588 344,625 354,964 365,613 376,582 387,879

Blayney WFP 68,088 48,760 50,223 51,729 53,281 54,880 56,526 58,222 59,969 61,768 63,621 65,529 67,495 69,520 71,606 73,754 75,966 78,245 80,593 83,011 85,501 88,066 90,708 93,429 96,232 99,119 102,093 105,155 108,310 111,559

Carcoar WFP 135,983 116,993 120,503 124,118 127,841 131,677 135,627 139,696 143,887 148,203 152,649 157,229 161,946 166,804 171,808 176,962 182,271 187,739 193,371 199,173 205,148 211,302 217,641 224,171 230,896 237,822 244,957 252,306 259,875 267,671

Grenfell WFP 3,780 3,780 3,893 4,010 4,131 4,254 4,382 4,514 4,649 4,788 4,932 5,080 5,232 5,389 5,551 5,718 5,889 6,066 6,248 6,435 6,628 6,827 7,032 7,243 7,460 7,684 7,914 8,152 8,396 8,648

Water Filtration - Energy Costs 125,459 127,472 131,296 135,235 139,292 143,471 147,775 152,209 156,775 161,478 166,322 171,312 176,452 181,745 187,197 192,813 198,598 204,556 210,692 217,013 223,523 230,229 237,136 244,250 251,578 259,125 266,899 274,906 283,153 291,647

Blayney WFP 18,891 20,161 20,765 21,388 22,030 22,691 23,372 24,073 24,795 25,539 26,305 27,094 27,907 28,744 29,606 30,495 31,409 32,352 33,322 34,322 35,352 36,412 37,505 38,630 39,789 40,982 42,212 43,478 44,782 46,126

Carcoar WFP 104,927 105,095 108,248 111,495 114,840 118,285 121,834 125,489 129,254 133,131 137,125 141,239 145,476 149,840 154,336 158,966 163,735 168,647 173,706 178,917 184,285 189,813 195,508 201,373 207,414 213,637 220,046 226,647 233,446 240,450

Grenfell WFP 1,641 2,217 2,283 2,352 2,422 2,495 2,570 2,647 2,726 2,808 2,892 2,979 3,069 3,161 3,255 3,353 3,454 3,557 3,664 3,774 3,887 4,004 4,124 4,248 4,375 4,506 4,641 4,781 4,924 5,072

Other Costs 287,062 297,472 254,897 281,043 295,068 278,532 305,436 295,495 325,760 342,017 322,895 354,084 342,560 377,644 396,490 374,324 410,481 397,120 437,793 459,641 433,944 475,860 460,371 507,523 532,850 503,060 551,652 533,697 588,358 617,719

Safety Equipment & Clothing 6,978 7,187 7,403 7,625 7,853 8,089 8,332 8,582 8,839 9,104 9,377 9,659 9,948 10,247 10,554 10,871 11,197 11,533 11,879 12,235 12,602 12,981 13,370 13,771 14,184 14,610 15,048 15,499 15,964 16,443

Installations & Private Works 54,126 36,532 37,628 38,757 39,920 41,117 42,351 43,622 44,930 46,278 47,666 49,096 50,569 52,086 53,649 55,258 56,916 58,624 60,382 62,194 64,060 65,981 67,961 70,000 72,100 74,263 76,491 78,785 81,149 83,583

Plant Running Expenses 204,958 203,753 209,866 216,162 222,646 229,326 236,206 243,292 250,590 258,108 265,851 273,827 282,042 290,503 299,218 308,195 317,441 326,964 336,773 346,876 357,282 368,001 379,041 390,412 402,124 414,188 426,614 439,412 452,594 466,172

IWCM - - - - - - - - - - - - - - - - - - - - - -

Demand Management Plan - - - 18,500 - - - - 21,400 24,808 28,759 33,340 38,650

Drought Management Plan - - - - 11,600 - - - - 13,400 15,534 18,008 20,876 24,201

Drinking Water Management Plan 5,000 -

Lake Rowlands Dam Surveillance Review 16,000 - 18,548 21,502 24,927 28,897 33,500

Consultancy - Asset Management Plan - 25,000

Consultancy - Quality Assurance Plan - 25,000 - - - - - - - - - - - - - - - - - - - - - - - - - - - -

Update Developer Servicing Plan 0 0 - 13,048 - 15,126 17,535 20,328 23,566 27,319

Quandialla Water Supply 31,627 33,960 34,979 36,028 37,109 38,222 39,369 40,550 41,766 43,019 44,310 45,639 47,008 48,419 49,871 51,367 52,908 54,496 56,130 57,814 59,549 61,335 63,175 65,071 67,023 69,033 71,104 73,237 75,435 77,698

Electricity 7,291 9,392 9,674 9,964 10,263 10,571 10,888 11,214 11,551 11,897 12,254 12,622 13,001 13,391 13,792 14,206 14,632 15,071 15,523 15,989 16,469 16,963 17,472 17,996 18,536 19,092 19,664 20,254 20,862 21,488

Maintenance 19,110 19,397 19,979 20,578 21,195 21,831 22,486 23,161 23,855 24,571 25,308 26,068 26,850 27,655 28,485 29,339 30,219 31,126 32,060 33,022 34,012 35,033 36,084 37,166 38,281 39,429 40,612 41,831 43,086 44,378

Chemicals 550 550 567 583 601 619 638 657 676 697 718 739 761 784 808 832 857 883 909 936 964 993 1,023 1,054 1,085 1,118 1,152 1,186 1,222 1,258

Overheads 4,676 4,621 4,760 4,903 5,050 5,201 5,357 5,518 5,684 5,854 6,030 6,211 6,397 6,589 6,787 6,990 7,200 7,416 7,638 7,867 8,103 8,347 8,597 8,855 9,121 9,394 9,676 9,966 10,265 10,573

CENTRAL TABLELANDS Water - 30 Year Financial Plan

Page 164: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

OPERATING STATEMENT 13/14 14/15 15/16 16/17 17/18 18/19 19/20 20/21 21/22 22/23 23/24 24/25 25/26 26/27 27/28 28/29 29/30 30/31 31/32 32/33 33/34 34/35 35/36 36/37 37/38 38/39 39/40 40/41 41/42 42/43

Interest 244,365 221,653 197,948 171,560 143,932 114,437 83,170 49,352 13,612 - 795,791 778,273 759,325 738,832 716,666 692,692 666,761 638,715 608,380 575,569 540,081 501,697 460,181 415,278 366,710 314,179 257,362 195,908 129,440 57,548

Interest on Loans - Quandialla 17,496 15,869 14,172 12,283 10,305 8,193 5,955 3,533 975 795,791 778,273 759,325 738,832 716,666 692,692 666,761 638,715 608,380 575,569 540,081 501,697 460,181 415,278 366,710 314,179 257,362

195,908 129,440 57,548

Interest on Loans - Capital Works 226,869 205,783 183,776 159,278 133,627 106,244 77,216 45,819 12,638

Depreciation - System Assets 1,656,336 1,622,048 1,670,710 1,720,831 1,772,456 1,825,630 1,880,398 1,936,810 1,994,915 2,054,762 2,116,405 2,179,897 2,245,294 2,312,653 2,382,032 2,453,493 2,527,098 2,602,911 2,680,999 2,761,428 2,844,271 2,929,599 3,017,487 3,108,012 3,201,252 3,297,290 3,396,209 3,498,095 3,603,038 3,711,129

Trunk Mains 562,012 538,969 555,138 571,792 588,946 606,614 624,813 643,557 662,864 682,750 703,232 724,329 746,059 768,441 791,494 815,239 839,696 864,887 890,834 917,559 945,085 973,438 1,002,641 1,032,720 1,063,702 1,095,613 1,128,481 1,162,336 1,197,206 1,233,122

Reticulation Mains 328,417 244,401 251,733 259,285 267,063 275,075 283,327 291,827 300,582 309,599 318,887 328,454 338,308 348,457 358,911 369,678 380,768 392,191 403,957 416,076 428,558 441,415 454,657 468,297 482,346 496,816 511,721 527,072 542,884 559,171

Reservoirs 160,386 159,668 164,458 169,391 174,473 179,707 185,098 190,651 196,371 202,262 208,330 214,580 221,017 227,648 234,477 241,512 248,757 256,220 263,906 271,823 279,978 288,377 297,029 305,940 315,118 324,571 334,308 344,338 354,668 365,308

Pump Stations 128,060 148,156 152,600 157,178 161,894 166,751 171,753 176,906 182,213 187,679 193,310 199,109 205,082 211,235 217,572 224,099 230,822 237,746 244,879 252,225 259,792 267,586 275,613 283,882 292,398 301,170 310,205 319,511 329,097 338,970

Bores 12,600 11,387 11,728 12,080 12,442 12,816 13,200 13,596 14,004 14,424 14,857 15,303 15,762 16,235 16,722 17,223 17,740 18,272 18,820 19,385 19,967 20,566 21,183 21,818 22,473 23,147 23,841 24,556 25,293 26,052

Filtration Plants 220,077 265,831 273,806 282,020 290,480 299,195 308,171 317,416 326,938 336,746 346,849 357,254 367,972 379,011 390,381 402,093 414,156 426,580 439,378 452,559 466,136 480,120 494,524 509,359 524,640 540,379 556,591 573,288 590,487 608,202

Telemetry 34,636 38,283 39,431 40,614 41,832 43,087 44,380 45,711 47,083 48,495 49,950 51,449 52,992 54,582 56,219 57,906 59,643 61,432 63,275 65,174 67,129 69,143 71,217 73,353 75,554 77,821 80,155 82,560 85,037 87,588

Dams 210,148 215,355 221,816 228,470 235,325 242,384 249,656 257,145 264,860 272,806 280,990 289,419 298,102 307,045 316,256 325,744 335,516 345,582 355,949 366,628 377,627 388,956 400,624 412,643 425,022 437,773 450,906 464,433 478,366 492,717

Depreciation - Plant & Equipment 192,825 212,223 218,590 225,147 231,902 238,859 246,025 253,405 261,008 268,838 276,903 285,210 293,766 302,579 311,657 321,006 330,637 340,556 350,772 361,295 372,134 383,298 394,797 406,641 418,840 431,406 444,348 457,678 471,409 485,551

Motor Vehicles 127,662 145,904 150,281 154,789 159,433 164,216 169,143 174,217 179,443 184,827 190,372 196,083 201,965 208,024 214,265 220,693 227,314 234,133 241,157 248,392 255,843 263,519 271,424 279,567 287,954 296,593 305,490 314,655 324,095 333,818

Other Plant 22,250 20,767 21,390 22,031 22,692 23,373 24,074 24,796 25,540 26,307 27,096 27,909 28,746 29,608 30,496 31,411 32,354 33,324 34,324 35,354 36,414 37,507 38,632 39,791 40,985 42,214 43,481 44,785 46,129 47,513

Buildings 38,870 38,870 40,036 41,237 42,474 43,749 45,061 46,413 47,805 49,239 50,717 52,238 53,805 55,419 57,082 58,794 60,558 62,375 64,246 66,174 68,159 70,204 72,310 74,479 76,713 79,015 81,385 83,827 86,342 88,932

Office Equipment - Engineers Instruments 1,325 1,199 1,235 1,272 1,310 1,349 1,390 1,432 1,475 1,519 1,564 1,611 1,660 1,709 1,761 1,814 1,868 1,924 1,982 2,041 2,102 2,166 2,230 2,297 2,366 2,437 2,510 2,586 2,663 2,743

- Computer 2,330 5,216 5,373 5,534 5,700 5,871 6,047 6,229 6,416 6,608 6,806 7,010 7,221 7,437 7,661 7,890 8,127 8,371 8,622 8,881 9,147 9,421 9,704 9,995 10,295 10,604 10,922 11,250 11,587 11,935

Furniture & Fittings 388 267 275 283 292 301 310 319 328 338 348 359 370 381 392 404 416 428 441 455 468 482 497 512 527 543 559 576 593 611

Amortisation - Intangible Assets - 46,873 46,873 39,059 - - - - - - - - - - - - - - - - - - - - - - - - - -

IT Corporate System - 46,873 46,873 39,059

CENTRAL TABLELANDS Water - 30 Year Financial Plan

Page 165: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

NON OPERATING EXPENSES 13/14 14/15 15/16 16/17 17/18 18/19 19/20 20/21 21/22 22/23 23/24 24/25 25/26 26/27 27/28 28/29 29/30 30/31 31/32 32/33 33/34 34/35 35/36 36/37 37/38 38/39 39/40 40/41 41/42 42/43

Acquisition of Assets 701,811 2,132,046 746,761 3,603,873 3,867,514 1,139,089 2,946,108 4,263,849 4,040,826 5,995,397 8,039,541 4,164,420 4,289,352 1,469,520 8,123,908 8,112,073 4,001,217 1,809,431 1,965,359 1,919,625 1,997,214 2,377,018 16,237,022 2,160,555 2,343,207 2,292,133 2,360,897 2,431,724 2,504,675 1,269,958

Funding

Vehicle Replacements 416,000 407,000 419,210 431,786 444,740 458,082 471,825 485,979 500,559 515,575 531,043 546,974 563,383 580,285 597,693 615,624 634,093 653,116 672,709 692,890 713,677 735,087 757,140 779,854 803,250 827,347 852,168 877,733 904,065 931,187

Office Furniture & Equipment - - 1,150 - - - - 1,350 - - - - - - - - - - - - - - - - - - - - - -

Meter Replacement Programme 131,266 102,189 105,255 108,412 111,665 115,015 118,465 122,019 125,680 129,450 133,333 137,333 141,454 145,697 150,068 154,570 159,207 163,983 168,903 173,970 179,189 184,565 190,102 195,805 201,679 207,729 213,961 220,380 226,991 233,801

Provision for Pump Replacements 44,545 45,880 47,256 48,674 50,134 51,638 53,187 54,783 56,427 58,119 59,863 61,659 63,509 65,414 67,376 69,398 71,480 73,624 75,833 78,108 80,451 82,864 85,350 87,911 90,548 93,265 96,063 98,944 101,913 104,970

Telemetry - - - - 261,000 - - - - - - - - - - - - - - - - - - - - - - - -

Reticulation Mains Renewals

- As determined 245,975 253,354 260,955 268,784 276,847 285,152 293,707 302,518 311,594 320,942 840,748 865,970 891,950 918,708 946,269 974,657 1,003,897 1,034,014 1,065,034 1,096,985 1,129,895 1,163,792 1,198,706 1,234,667 1,271,707

- Millthorpe - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

- South Canowindra - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

- Cudal AC Pipe - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

- Carcoar - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

Reticulation Mains Extensions - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

CWFP & BWFP - Mech & Elec refurb

CWFP - Mech & Elec refurb - - - - 1,384,234 2,356,566

CWFP - Low Level Storage - 445,000 -

CWFP - Repair Plenum Floor - 200,000 -

Blayney WFP - Upgrade - 700,000 - - - - - - - - - 876,753 6,321,389 - - - - - - - - - - - -

Blayney Water Filtration Plant - - - - - - - 75,630 87,680 101,645 117,835

Trunk Main Renewals

Trunk Main 'K' Renewal - - 173,890 3,015,000 3,015,000 - - - - - - - - - - - - - - - - - - - - - - -

Trunk Main 'U' - 'C' to Cudal - - - - 130,810 1,946,700 1,946,700

Trunk Main 'C' - Mand to 'U' - - - - - - - 280,000 4,780,000 4,780,000

Trunk Main 'B' - CWFP to Mand. - - - - - - - - - 71,300 1,395,000

Trunk Main 'C' - 'U' to G'gong - - - - - - - - 226,888 3,115,935 3,209,413 - - - - - - - - - - - - - - - -

Trunk Main'D' - CWFP to B/Ck - - - - - - - - - - - - - 165,284 4,085,839 - - - - - - - - - - - - - -

Trunk Main 'A' - L/R to CWFP - - - - - - - - - 85,122 2,244,488 - - - - - - - - - - - -

Trunk Main 'F' B/Ck to M'Thorp - - - - - - - - - - - - - 68,097 1,244,989 - - - - - - - - - - - - - -

Trunk Main 'P' - 'C' to Somers - - - - - - - - - - - - - 36,122 260,441 - - - - - - - - - - - - - -

Trunk Main 'X' - L/R to Blayney - - - - - - - - - - - - - - - - - - - - - 170,244 7,069,698 - - - - - -

Flood Restoration - - - - - -

Gooloogong Bridge Trunk Main relocation 60,000 204,977 - - - - -

Lake Rowlands Remediation 1,910,866 - - - - - - - - - - - - - - - - - - - - - -

- - - - -

Service Reservoirs - - - - - - - - - - - - - - - - - - - - - 170,244 4,713,132 - - - - - -

Administration Building

Admin Building Refurbishment (Indoor) 25,000 22,000 - - - - - - - - 15,000 - - - - - - - - 20,000 - - - - - - - -

Admin Building Refurbishment (Outdoor) 15,000 5,000 - - - - - - - - 604,707 - - - - - - - - - - - - - - - - - -

Admin Building Replacement - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

IT Link Upgrade (BSC & CTW) 10,000 -

Gooloogong Bore

New Bore Gooloogong - - - - - - - - - 155,800

Refurbish Gooloogong Bore - - - - - - - - 778,984

Caragabal Investigation - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

Repayment of Loans 336,292 359,004 382,708 409,096 436,725 466,219 497,487 531,304 413,245 - 214,679 232,197 251,145 271,638 293,804 317,778 343,709 371,755 402,090 434,901 470,389 508,773 550,289 595,192 643,760 696,291 753,108 814,562 881,030 952,912

Principal on Loans - Quandialla 24,077 25,703 27,400 29,289 31,267 33,379 35,618 38,039 29,586

- Capital Works 312,215 333,301 355,308 379,807 405,457 432,840 461,869 493,265 383,659 214,679 232,197 251,145 271,638 293,804 317,778 343,709 371,755 402,090 434,901 470,389 508,773 550,289 595,192 643,760 696,291 753,108 814,562 881,030 952,912

Transfers to Reserves 982,581 918,194 964,103 1,011,670 1,060,973 1,112,091 1,165,109 1,220,115 1,172,266 1,222,357 1,273,937 1,327,052 1,381,748 1,438,071 1,496,072 1,555,799 1,617,306 1,680,643 1,745,867 1,813,034 1,882,203 1,953,433 2,026,785 2,102,324 2,180,115 2,260,224 2,326,550 2,394,851 2,465,186 2,537,616

Renewals Reserve 536,916 565,916 599,066 633,210 668,379 704,603 741,914 780,343 819,926 860,697 902,690 945,943 990,494 1,036,381 1,083,645 1,132,327 1,182,470 1,234,116 1,287,312 1,342,104 1,398,540 1,456,669 1,516,541 1,578,210 1,641,729 1,707,153 1,758,368 1,811,119 1,865,452 1,921,416

Renewals Reserve - Dev Charges 158,415 142,135 146,399 150,791 155,315 159,974 164,773 169,717 174,808 180,052 185,454 191,018 196,748 202,651 208,730 214,992 221,442 228,085 234,927 241,975 249,235 256,712 264,413 272,345 280,516 288,931 297,599 306,527 315,723 325,195

Renewals Reserve - 5% increase 135,498 58,314 63,420 68,973 75,012 81,580 88,724 96,492 - - - - - - - - - - - - - - - - - - - - - -

Plant & Equipment Reserve 97,553 93,515 96,320 99,210 102,186 105,252 108,410 111,662 115,012 118,462 122,016 125,676 129,447 133,330 137,330 141,450 145,693 150,064 154,566 159,203 163,979 168,898 173,965 179,184 184,560 190,097 195,800 201,674 207,724 213,956

Employees Leave Reserve - - - - - - - -

Development Assistance Reserve 54,199 58,314 58,897 59,486 60,081 60,682 61,289 61,901 62,521 63,146 63,777 64,415 65,059 65,710 66,367 67,030 67,701 68,378 69,062 69,752 70,450 71,154 71,866 72,584 73,310 74,043 74,784 75,532 76,287 77,050

Funding Summary

Plant 416,000 407,000 419,210 431,786 444,740 458,082 471,825 485,979 500,559 515,575 531,043 546,974 563,383 580,285 597,693 615,624 634,093 653,116 672,709 692,890 713,677 735,087 757,140 779,854 803,250 827,347 852,168 877,733 904,065 931,187

Reserves 285,811 1,725,046 327,551 3,172,086 3,422,774 681,007 2,474,283 3,777,870 3,540,267 5,479,822 7,508,498 3,617,446 3,725,969 889,236 7,526,214 7,496,449 3,367,124 1,156,315 1,292,650 1,226,735 1,283,537 1,641,931 15,479,882 1,380,701 1,539,957 1,464,786 1,508,729 1,553,991 1,600,611 338,771

Contributions - - - - - -

701,811 2,132,046 746,761 3,603,873 3,867,514 1,139,089 2,946,108 4,263,849 4,040,826 5,995,397 8,039,541 4,164,420 4,289,352 1,469,520 8,123,908 8,112,073 4,001,217 1,809,431 1,965,359 1,919,625 1,997,214 2,377,018 16,237,022 2,160,555 2,343,207 2,292,133 2,360,897 2,431,724 2,504,675 1,269,958

CENTRAL TABLELANDS Water - 30 Year Financial Plan

Page 166: Asset Management Plan Training - Central Tablelands Water Supply Asset ma… · CTW – Water Asset Management Plan April 2014 Page 1 1.0 Introduction 1.1 Objectives of this Plan

NON OPERATING INCOME 13/14 14/15 15/16 16/17 17/18 18/19 19/20 20/21 21/22 22/23 23/24 24/25 25/26 26/27 27/28 28/29 29/30 30/31 31/32 32/33 33/34 34/35 35/36 36/37 37/38 38/39 39/40 40/41 41/42 42/43

Carrying Amount of Assets Sold 266,301 273,300 281,499 289,944 298,642 307,602 316,830 326,334 336,125 346,208 356,595 367,292 378,311 389,660 401,350 413,391 425,792 438,566 451,723 465,275 479,233 493,610 508,419 523,671 539,381 555,563 572,230 589,396 607,078 625,291

Motor Vehicles 266,301 273,300 281,499 289,944 298,642 307,602 316,830 326,334 336,125 346,208 356,595 367,292 378,311 389,660 401,350 413,391 425,792 438,566 451,723 465,275 479,233 493,610 508,419 523,671 539,381 555,563 572,230 589,396 607,078 625,291

Other Plant & Equipment - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

Office Furniture & Equipment - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

Loan Funds Utilised - - - - - - - - - 10,000,000 - - - - - - - - - - - - - - - - - - -

Capital Works - - - - - - - - - 10,000,000 - - - - - - - - - - - - - - - - - -

Transfer from Reserves 370,811 1,913,032 412,011 3,441,034 3,582,647 773,299 2,569,344 3,875,782 3,641,117 5,583,697 7,615,490 3,727,647 3,839,476 1,006,148 7,646,634 7,620,481 3,494,878 1,287,901 1,428,183 1,366,334 1,427,324 1,790,032 15,632,427 1,537,821 1,701,791 1,631,475 1,680,419 1,730,832 1,782,757 526,381

Plant Reserve 85,000 82,000 84,460 86,994 89,604 92,292 95,060 97,912 100,850 103,875 106,991 110,201 113,507 116,912 120,420 124,032 127,753 131,586 135,534 139,600 143,787 148,101 152,544 157,120 161,834 166,689 171,690 176,840 182,146 187,610

Employees Leave Reserve 105,986 181,954 70,269 - - - - - - - - - - - - - - - - - - - - - - - - -

Development Assistance Reserve - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

Capital Works 285,811 1,725,046 327,551 3,172,086 3,422,774 681,007 2,474,283 3,777,870 3,540,267 5,479,822 7,508,498 3,617,446 3,725,969 889,236 7,526,214 7,496,449 3,367,124 1,156,315 1,292,650 1,226,735 1,283,537 1,641,931 15,479,882 1,380,701 1,539,957 1,464,786 1,508,729 1,553,991 1,600,611 338,771

Transfer to/from Reserve re Surplus/Deficit

Capital Works Reserve

Balance at beginning of year 3,708,732 5,021,501 4,683,381 6,045,157 4,802,990 3,374,399 4,826,580 4,648,831 3,360,097 2,559,360 10,381,574 5,859,074 5,190,430 4,646,767 7,150,636 3,430,261 (129,732) 541,100 3,828,093 7,496,932 11,814,068 16,765,857 22,045,450 14,277,847 20,650,842 27,738,327 35,903,909 45,046,253 55,323,409 66,765,277

Transfer from Reserve for Capital Works (285,811) (1,725,046) (327,551) (3,172,086) (3,422,774) (681,007) (2,474,283) (3,777,870) (3,540,267) (5,479,822) (7,508,498) (3,617,446) (3,725,969) (889,236) (7,526,214) (7,496,449) (3,367,124) (1,156,315) (1,292,650) (1,226,735) (1,283,537) (1,641,931) (15,479,882) (1,380,701) (1,539,957) (1,464,786) (1,508,729) (1,553,991) (1,600,611) (338,771)

3,422,921 3,296,454 4,355,830 2,873,070 1,380,216 2,693,392 2,352,296 870,961 180,170- 2,920,462- 2,873,076 2,241,628 1,464,461 3,757,531 375,578- 4,066,188- 3,496,856- 615,216- 2,535,444 6,270,197 10,530,531 15,123,926 6,565,568 12,897,146 19,110,885 26,273,542 34,395,180 43,492,262 53,722,798 66,426,506

Transfer to Reserve 830,829 766,365 808,885 852,974 898,706 946,158 995,411 1,046,552 994,734 1,040,749 1,088,144 1,136,961 1,187,242 1,239,032 1,292,375 1,347,319 1,403,912 1,462,201 1,522,239 1,584,079 1,647,775 1,713,381 1,780,954 1,850,555 1,922,245 1,996,084 2,055,967 2,117,646 2,181,175 2,246,610

4,253,750 4,062,819 5,164,715 3,726,044 2,278,922 3,639,550 3,347,707 1,917,513 814,564 1,879,713- 3,961,219 3,378,588 2,651,703 4,996,563 916,797 2,718,869- 2,092,944- 846,985 4,057,683 7,854,276 12,178,306 16,837,307 8,346,522 14,747,701 21,033,129 28,269,626 36,451,146 45,609,907 55,903,973 68,673,116

Transfer to/from Reserve re Surplus/(Deficit) 767,751 620,562 880,441 1,076,946 1,095,477 1,187,030 1,301,123 1,442,584 1,744,795 12,261,287 1,897,854 1,811,841 1,995,064 2,154,073 2,513,465 2,589,137 2,634,044 2,981,108 3,439,249 3,959,792 4,587,551 5,208,144 5,931,325 5,903,140 6,705,198 7,634,283 8,595,107 9,713,501 10,861,304 12,140,530

Balance at end of year 5,021,501 4,683,381 6,045,157 4,802,990 3,374,399 4,826,580 4,648,831 3,360,097 2,559,360 10,381,574 5,859,074 5,190,430 4,646,767 7,150,636 3,430,261 (129,732) 541,100 3,828,093 7,496,932 11,814,068 16,765,857 22,045,450 14,277,847 20,650,842 27,738,327 35,903,909 45,046,253 55,323,409 66,765,277 80,813,646

Development Assistance Reserve

Balance at beginning of year 196,520 250,719 309,033 367,930 427,416 487,497 548,179 609,468 671,369 733,890 797,035 860,812 925,227 990,286 1,055,996 1,122,363 1,189,393 1,257,094 1,325,472 1,394,533 1,464,286 1,534,735 1,605,889 1,677,755 1,750,339 1,823,650 1,897,693 1,972,477 2,048,008 2,124,295

Transfer from Reserve - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

196,520 250,719 309,033 367,930 427,416 487,497 548,179 609,468 671,369 733,890 797,035 860,812 925,227 990,286 1,055,996 1,122,363 1,189,393 1,257,094 1,325,472 1,394,533 1,464,286 1,534,735 1,605,889 1,677,755 1,750,339 1,823,650 1,897,693 1,972,477 2,048,008 2,124,295

Transfer to Reserve 54,199 58,314 58,897 59,486 60,081 60,682 61,289 61,901 62,521 63,146 63,777 64,415 65,059 65,710 66,367 67,030 67,701 68,378 69,062 69,752 70,450 71,154 71,866 72,584 73,310 74,043 74,784 75,532 76,287 77,050

250,719 309,033 367,930 427,416 487,497 548,179 609,468 671,369 733,890 797,035 860,812 925,227 990,286 1,055,996 1,122,363 1,189,393 1,257,094 1,325,472 1,394,533 1,464,286 1,534,735 1,605,889 1,677,755 1,750,339 1,823,650 1,897,693 1,972,477 2,048,008 2,124,295 2,201,345

Renewals Reserve + Dev.Assistance Reserve 5,272,220 4,992,414 6,413,087 5,230,406 3,861,897 5,374,759 5,258,298 4,031,466 3,293,249 11,178,609 6,719,886 6,115,657 5,637,053 8,206,632 4,552,624 1,059,661 1,798,194 5,153,565 8,891,465 13,278,354 18,300,592 23,651,340 15,955,602 22,401,181 29,561,977 37,801,602 47,018,729 57,371,417 68,889,572 83,014,990

Plant & Equipment Reserve

Balance at beginning of year 62,349 74,902 86,417 98,277 110,494 123,076 136,037 149,386 163,135 177,297 191,884 206,909 222,384 238,323 254,741 271,651 289,068 307,008 325,487 344,519 364,123 384,314 405,112 426,533 448,597 471,323 494,730 518,840 543,673 569,252

Transfer from Reserve - Deficit on Sales (85,000) (82,000) (84,460) (86,994) (89,604) (92,292) (95,060) (97,912) (100,850) (103,875) (106,991) (110,201) (113,507) (116,912) (120,420) (124,032) (127,753) (131,586) (135,534) (139,600) (143,787) (148,101) (152,544) (157,120) (161,834) (166,689) (171,690) (176,840) (182,146) (187,610)

(22,651) (7,098) 1,957 11,284 20,890 30,785 40,976 51,473 62,286 73,422 84,893 96,707 108,877 121,411 134,321 147,619 161,315 175,423 189,953 204,920 220,335 236,213 252,568 269,413 286,763 304,634 323,041 342,000 361,528 381,642

Transfer to Reserve - Surplus on Sales - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

Transfer to Reserve 97,553 93,515 96,320 99,210 102,186 105,252 108,410 111,662 115,012 118,462 122,016 125,676 129,447 133,330 137,330 141,450 145,693 150,064 154,566 159,203 163,979 168,898 173,965 179,184 184,560 190,097 195,800 201,674 207,724 213,956

74,902 86,417 98,277 110,494 123,076 136,037 149,386 163,135 177,297 191,884 206,909 222,384 238,323 254,741 271,651 289,068 307,008 325,487 344,519 364,123 384,314 405,112 426,533 448,597 471,323 494,730 518,840 543,673 569,252 595,597

ELE Reserve

Balance at beginning of year 350,000 437,967 410,612 499,609 409,322 426,542 501,468 578,641 658,130 740,004 824,333 911,193 1,000,658 1,092,808 1,187,722 1,285,483 1,386,177 1,489,892 1,596,718 1,706,750 1,820,082 1,936,814 2,057,048 2,180,889 2,308,445 2,439,828 2,575,153 2,714,537 2,858,102 3,005,975

Transfer from Reserve (105,986) (181,954) (72,690)

350,000 331,981 410,612 317,655 336,632 426,542 501,468 578,641 658,130 740,004 824,333 911,193 1,000,658 1,092,808 1,187,722 1,285,483 1,386,177 1,489,892 1,596,718 1,706,750 1,820,082 1,936,814 2,057,048 2,180,889 2,308,445 2,439,828 2,575,153 2,714,537 2,858,102 3,005,975

Transfer to Reserve 87,967 78,631 88,997 91,667 89,910 74,926 77,174 79,489 81,874 84,330 86,860 89,465 92,149 94,914 97,761 100,694 103,715 106,826 110,031 113,332 116,732 120,234 123,841 127,556 131,383 135,324 139,384 143,566 147,873 152,309

437,967 410,612 499,609 409,322 426,542 501,468 578,641 658,130 740,004 824,333 911,193 1,000,658 1,092,808 1,187,722 1,285,483 1,386,177 1,489,892 1,596,718 1,706,750 1,820,082 1,936,814 2,057,048 2,180,889 2,308,445 2,439,828 2,575,153 2,714,537 2,858,102 3,005,975 3,158,284

Total Reserves (excluding ELE) 5,347,122 5,078,831 6,511,364 5,340,900 3,984,973 5,510,795 5,407,684 4,194,601 3,470,546 11,370,493 6,926,795 6,338,041 5,875,377 8,461,373 4,824,275 1,348,730 2,105,202 5,479,052 9,235,984 13,642,476 18,684,907 24,056,451 16,382,135 22,849,778 30,033,300 38,296,332 47,537,570 57,915,090 69,458,824 83,610,587

Grants, Subsidies & Contributions - Capital

Contributions - Mains Extension

IWCM - Blayney, Weddin & Cabonne

Section 64 Developer Charges 158,415 142,135 146,399 150,791 155,315 159,974 164,773 169,717 174,808 180,052 185,454 191,018 196,748 202,651 208,730 214,992 221,442 228,085 234,927 241,975 249,235 256,712 264,413 272,345 280,516 288,931 297,599 306,527 315,723 325,195

158,415 142,135 146,399 150,791 155,315 159,974 164,773 169,717 174,808 180,052 185,454 191,018 196,748 202,651 208,730 214,992 221,442 228,085 234,927 241,975 249,235 256,712 264,413 272,345 280,516 288,931 297,599 306,527 315,723 325,195

Cash at Bank 400,000 412,000 424,360 437,091 450,204 463,710 477,621 491,950 506,708 521,909 537,567 553,694 570,304 587,413 605,036 623,187 641,883 661,139 680,973 701,402 722,444 744,118 766,441 789,435 813,118 837,511 862,637 888,516 915,171

Total Reserves 5,078,831 6,174,582 4,848,606 6,462,466 6,450,035 5,330,352 4,702,500 12,701,535 8,359,897 7,876,266 7,521,878 10,219,399 6,697,172 3,339,943 4,218,281 7,717,653 11,603,873 16,143,531 21,323,123 26,835,943 19,307,142 25,924,664 33,262,563 41,684,602 51,089,618 61,635,829 73,353,314 87,684,043

Interest at 4% 304,730 - 370,475 290,916 387,748 387,002 319,821 282,150 762,092 501,594 472,576 451,313 613,164 401,830 200,397 253,097 463,059 696,232 968,612 1,279,387 1,610,157 1,158,428 1,555,480 1,995,754 2,501,076 3,065,377 3,698,150 4,401,199 5,261,043

Interest on investments 279336 358125 293749 219174 303094 297423 230703 190880 625377 380974 348592 323146 465376 265335 74180 115786 301348 507979 750336 1027670 1323105 901017 1256738 1651831 2106298 2614566 3185330 3820235

CENTRAL TABLELANDS Water - 30 Year Financial Plan