Asset Management
Making a Financial CaseILM Level 5
Mark FreemanProfessor of Finance
School of Business and Economics
Objectives
This course is divided into four parts Until 2.30 today. Capital budgeting in the University sector After 2.30 today. The Loughborough context Tomorrow morning. Writing a case Tomorrow lunchtime. Case review with the DVC
The agenda until 2.30
9.00 – 10.30 “Dragons’ Den” 10.30 – 11.00 The capital budgeting process 11.00 – 11.15Coffee 11.15 – 12.15 Analysing monetary costs and benefits 12.15 – 1.00 Analysing non-monetary costs and benefits 1.00 – 1.45 Lunch 1.45 – 2.30 Combining the monetary and non-monetary
Core sources
The UK Treasury “Green Book” “Appraisal and Evaluation in Central Government” http://www.hm-treasury.gov.uk/data_greenbook_index.htm
HEFCE “Investment Decision Making” http://webarchive.nationalarchives.gov.uk/20120118171947/http:/
www.hefce.ac.uk/pubs/hefce/2003/03_17.htm
Another University
University of Leeds
‘The University must follow both Treasury and HEFCE guidelines and is ultimately accountable to the Committee of Public Accounts on the use of public monies’
Guidelines on Investment Decision Making: Capital Equipment over £100k (excluding Research Equipment)
Academic and corporate best practice
It is important to realise that the Green Book / HEFCE guidelines conform closely to what is considered by academics to be ‘best practice’
The techniques are also very similar to those most widely used in the private sector
The Capital Budgeting ProcessQuotations liberally taken from the HEFCE guidance
Project stages
Organisational Need Strategic Context Objectives Appraisal Monitoring Evaluation Feedback
Primary focus today
Choosing between two or more options when something must be done
Deciding whether to take on a project that is optional
Organisational needs
‘At the outset, the institution will have determined that there is a problem to be solved or a need to be satisfied. This must be clearly defined, since it will form the basis of the whole analysis. As the analysis develops, it may call into question whether the problem or need does in fact exist.’
Strategic context
‘The appraisal must be placed in its strategic context. This should refer to the aims and objectives of the institution, the strategic plan, the capital and infrastructure plans, and other
relevant policies.’
Rationale
‘The statement of objectives sets out what is to be achieved and defines a firm boundary to the appraisal. It provides the criteria against which options will be judged, and against which the success of the project will be evaluated. Experience has shown that it is a crucial factor in the subsequent steps of the appraisal.’
Project appraisal
This is where we will spend most of the rest of today: Identify all the possible options Identify all the possible risks Identify all the appropriate costs and benefits Analyse the data
For others within the University Is the project affordable? How will the project be financed?
Monitoring, evaluation and feedback
‘At the time of the appraisal it is important to plan for monitoring during implementation and post-project evaluation of the decision. This provides feedback into future decisions. Evaluation should cover the extent to which the objectives were met, any cost and time overruns, the relationship between estimated and actual costs and benefits, and any implications for future decisions.’
Detailed guidance on project evaluation in the public sector is given in HM Treasury’s Magenta Bookhttp://www.hm-treasury.gov.uk/data_magentabook_index.htm
Choosing options
‘It is important, particularly for major investment decisions, to consider a wide range of options, even though many may be rejected at an early stage. Rarely will there be no realistic choice of options. Institutions must keep an open mind, and be prepared to ‘think the unthinkable’. Experience indicates that institutions gain considerable value from using a wide-ranging multi-disciplinary team, and involving the end-users in the development of the project from an early stage.’
Choosing options
‘Institutions must include a ‘do nothing’ option as a baseline, even if it falls short of the operational requirement.’
I think this is wrong for reasons I’ll explain on the next slide. The sentence below, though, is in my opinion correct
‘Where a ‘do nothing’ option is clearly unacceptable, then a ‘do minimum’ option should be considered.’
Identifying costs and benefits
The identification of costs and benefits are reasonably straightforward in principle:
Incremental cost/benefit = cost/benefit with project – cost/benefit without project
The incremental cost/benefit approach automatically compares to the ‘do nothing’ option
This is why I disagree with the first point on the previous slide This definition is surprisingly difficult to implement accurately
Over-optimism bias
Managers have a systematic tendency to be too optimistic about proposed projects
Green Book: “To redress this tendency, appraisers should make explicit adjustments for this bias. These will take the form of increasing estimates of the costs and decreasing, and delaying the receipt of, estimated benefits.”
Project Appraisal
Analysing Financial Costs and Benefits
Cash today vs. tomorrow
In financial cost / benefit analysis, capital budgeting involves comparing an investment cost today against (hopefully) greater cash flows in future
So we are comparing a money cost today with a money gain in the future
How do we do this?
The four things that matter
When looking at the monetary gains that a project will deliver, four things primarily matter The expected MAGNITUDE of the gains WHEN the gains occur The RISK that those gains will not occur The gains offered by OTHER projects
Net Present Values
The way in which we evaluate a project is to use “Net Present Value” criteria
1 22
[ ] [ ]...
1 (1 )
E C E CNPV I
r r
Expected financial gain in year 1
Initial investment
Discount rate / Cost of Capital
NPV decision rules
If the NPV is positive (negative) then the project is good (bad) When choosing between two projects, select the one with the
higher NPV
Why use the NPV criteria
There are alternatives to NPV for assessing financial costs and benefits (Payback Periods, Return on Capital Employed, Internal Rates of Return, etc.) but: Green Book: “The NPV is the primary criterion for deciding whether
government action can be justified.” HEFCE Technical Guidance: “To compare options, costs and
benefits must be discounted so that a single figure – the net present value (NPV) – can be calculated for each option.’
The NPV is also the criterion most heavily used in the private sector for capital budgeting purposes
Simple example
A proposed project requires an investment today of £1m. We expect financial benefits of £0.25m in one year, £0.6m in two years, £0.3m in three years and nothing thereafter. The discount rate is 10%
The NPV here is negative, so this is a bad project
2 3
0.25 0.6 0.31 0.0514
1.1 1.1 1.1NPV
The time of gains
In project appraisal, the sooner the benefits arrive the better Inflation erodes monetary value Investors and managers are, by nature, impatient. Even
after adjusting for inflation, investors need about 1% - 2% a year to encourage them to invest in a risk-free project
Real vs. nominal discounting
Real analysis Analysis undertaken in
current £ terms Nominal analysis Analysis undertaken in
actual £ terms at the time
The difference between real and nominal analysis is inflation Of course, it is necessary for the discount rate & the cash
flows to be consistent
Real discounting
The Green Book has an explicit preference for real analysis, “The valuation of costs or benefits should be expressed in ‘real terms’ or ‘constant prices’ (i.e. at ‘today’s’ general price level), as opposed to ‘nominal terms’ or ‘current prices’.”
“The discount rate is used to convert all costs and benefits to ‘present values’, so that they can be compared. The recommended discount rate is 3.5% (real).”
Dealing with project riskiness in the private sector
As a general rule (but not invariably) the riskier the project, the less attractive it is, all else being equal
To account for this, companies usually use higher discount rates for riskier project than less risky ones
Expected future benefits then have to be higher for risky projects to give the same NPV as safer ones
This, though, is not true in the public sector The Green Book uses 3.5% irrespective of project risk
Dealing with project riskiness in the University sector
‘It is particularly important that decision makers take account of risk and uncertainty. In many cases, their impact can be valued and factored into the decision-making process. Even when the impact cannot be defined precisely, institutions must recognise the potential for risk and uncertainty to influence their decision. The process will be clarified if the risks and uncertainties are set out in a formal risk register.’
Project Appraisal
Analysing Non-Financial Costs and Benefits
Example
Consider a situation where a project will not only have financial implications, but will also impact on: Academic quality Flexibility of provision Student experience Equal opportunities Internationalisation
How do we include these features in project analysis?
Apples and pears
The problem, of course, is that you are now comparing apples and pears
For this reason, the standard recommendation is to combine everything into a single non-monetary unit
QALYs
The best known example of combining different elements to one common unit of measurement is the “Quality Adjusted Life Year” (QALY) measure used by the National Institute for Health and Clinical Excellence
Effectively they consider all drugs, irrespective of their medical benefits, on the single QALY criterion
This measures a combination of life expectancy and life quality as a consequence of taking a certain medical remedy
Scorecards
The basic principle involves determining each type of potential benefit that you are looking to achieve and then ranking these with a weighting depending on their importance
Then, for each project, a score between 0 and 100 is allocated for each type of benefit
A weighted score can then be determined for each project The supplementary guidance to the Green Book gives further
information about these scoring techniques(http://www.communities.gov.uk/documents/corporate/pdf/1132618.pdf)
An example
Option A Option B
Weight Score Total Score Total
Quality 10 75 750 50 500
Flexibility 5 30 150 90 450
Experience 7 80 560 50 350
Equality 9 50 450 90 810
International 4 10 40 50 200
Total 1950 2220
Two tasks
There are two elements here that should not be confused:
1. The key non-financial criteria and their relative importance. This is a University-wide issue, based on the University strategic objectives, and should be largely independent of the particular options under consideration
2. The weighting of each project against the scorecard. This should be done as independently from the project stakeholder as possible
Group exercise
What are the seven most important non-financial objectives for the University?
Weight their relative importance in your own opinion What weighting structure do you think the University Senior
Management Team would give to each of these non-financial objectives?
Project Appraisal
Combining the Financial and Non-Financial
(The Controversial Bit)
An example
NPV Scorecard
Project A +£150,000 1950
Project B +£100,000 2220
• Both projects are financially viable• Project A is better than Project B on financial criteria• Project B is better than Project A on non-financial criteria• Which one do we choose?
Implicit monetisation
Project A beats Project B by £50,000 financially Project B beats Project A by 270 points on the scorecard So, the two projects are equivalent if each scorecard point is
worth 50,000/270 = £185.19 Therefore, by choosing A or B we are implicitly valuing each
scorecard point at either less or more than £185.19 So our choice implicitly reveals the way in which we monetise
non-financial benefits
Implicit monetisation
As the Green Book observes
“… weighting and scoring can be used to bring data expressed in different units into the appraisal process ... It often involves an implicit monetisation of different impacts once the performance against the various criteria is compared to the costs considered worth spending to secure or to avoid them.”
Explicit monetisation
The Green Book’s recommendations dislike this implicit monetisation
It instead recommends explicitly valuing each scorecard point
“The valuation of non-market impacts is a challenging but important element of appraisal, and should be attempted wherever feasible…It is difficult to determine whether a health programme should be funded, or how large it should be, without first allocating a monetary value to the projected health gains.”
The value of a QALY
“In the early days of NICE the cost/QALY ‘threshold’ was not particularly explicit, although frequently people applied a ‘rule of thumb’ of £30,000 … The figure quoted now tends to be £20,000 … My personal view would be that it is helpful to consider three ranges rather than one point:
£0-£20,000 intervention is cost-effective
£20,000-£30,000 a ‘grey area’ …
>£30,000 intervention is not likely to be cost-effective”
Professor Brian Ferguson, Director of YHPHO and Chair of DPHIG, 2006
A Cost-benefit analysis framework
Assign a monetary value to the scorecard points. Again, this should be a University-wide / project-independent process
The monetised scorecard values for each option can be added on to the simple financial costs / benefits of the proposed project. You are no longer adding apples and pears
From this, an NPV value can be calculated and simple NPV decision rules can be implemented (positive good, negative bad, choose the project the with the most positive NPV)
This is consistent with Green Book best practice