Assessment for Ground Improvement Work

9
Ground Improvement work (Assessment for ground improvement Works at Carbon Capture and Storage (CCS) project at ICAD-1, Abu Dhabi (Main Contractor: Dodsal) Client: MASDAR & ADNOC

description

ground improvement

Transcript of Assessment for Ground Improvement Work

  • Ground Improvement work

    (Assessment for ground improvement Works at Carbon Capture and

    Storage (CCS) project at ICAD-1, Abu Dhabi

    (Main Contractor: Dodsal)

    Client: MASDAR & ADNOC

  • Al Dhafra Pipe Line and Contracting WLL

    Project: Ground Improvement works

    Client: Dodsal

    Rev 0, Dated 27-05-2014 Page 1

    Contents

    1. General ................................................................................................................................ 2

    2. Site Location & Brief ............................................................................................................ 2

    3. Scope of Work: .................................................................................................................... 2

    3.1. Ground Improvement .......................................................................................................... 2

    4. Bill of Quantities .................................................................................................................. 4

    5. Soil Investigation Report ..................................................................................................... 6

    6. Commercial Payment Terms ............................................................................................... 7

    7. Duration of the Project ........................................................................................................ 7

    8. Submission Procedure ......................................................................................................... 7

    9. Responsibility Matrix for ground improvement: ................................................................. 8

  • Al Dhafra Pipe Line and Contracting WLL

    Project: Ground Improvement works

    Client: Dodsal

    Rev 0, Dated 27-05-2014 Page 2

    1. General

    We have prepared an assessment for the Ground Improvement works by using Stone Columns based on

    the Enquiries we have received from M/s Dodsal, Abu Dhabi.

    Total Area of Ground Improvement 24,700 Sq.m

    2. Site Location & Brief

    The site is located in ICAD-1, Abu Dhabi.

    3. Scope of Work:

    3.1. Ground Improvement

    Main Contractor requested to submit our offer based on two Options, Option-1 by using stone columns

    and Option-2 by dynamic replacement.

    Emirates Steel Factory

    ESNAD

    Ground

    Improvement Area

  • Al Dhafra Pipe Line and Contracting WLL

    Project: Ground Improvement works

    Client: Dodsal

    Rev 0, Dated 27-05-2014 Page 3

    The total area is around 24,700 sq.m.

    The allowable bearing pressure required is 200Kpa for Plot Area- 130m x 190m

    190.0m

    130.0m

    190.0m

  • Al Dhafra Pipe Line and Contracting WLL

    Project: Ground Improvement works

    Client: Dodsal

    Rev 0, Dated 27-05-2014 Page 4

    4. Bill of Quantities

    The bill of Quantities provide for the both Options are as follows:

    OPTION-1- By using Stone Columns

  • Al Dhafra Pipe Line and Contracting WLL

    Project: Ground Improvement works

    Client: Dodsal

    Rev 0, Dated 27-05-2014 Page 5

    OPTION-2- By using Dynamic Replacement

  • Al Dhafra Pipe Line and Contracting WLL

    Project: Ground Improvement works

    Client: Dodsal

    Rev 0, Dated 27-05-2014 Page 6

    5. Soil Investigation Report

    In this area there are 6 bores holes conducted to a maximum depth of 20m and some trial pits.

    As per the soil investigation report, the following is the summary for general information, for detailed

    information one has to go through the Soil report.

  • Al Dhafra Pipe Line and Contracting WLL

    Project: Ground Improvement works

    Client: Dodsal

    Rev 0, Dated 27-05-2014 Page 7

    Summary of Borehole Data:

    Depth(m)

    SP

    T V

    alu

    es

    BH-1 BH-2 BH-3 BH-4 BH-5 BH-6

    1.0m 12 7 5 18 19 19

    2.0m 1 1 4 1 10 2

    3.0m 2 2 3 2 4 1

    4.0m 2 1 0 20 2 1

    5.0m 25 24 29 20 33 29

    6.0m 25 30 26 25 32 34

    7.0m 38 36 35 33 37 40

    8.0m 43 40 50 50 41 42

    9.0m 50 50 50 50 50 50

    10.0m >50 >50 >50 >50 >50 >50

    11.0m

    UCS-

    0.33Mpa

    UCS-

    0.25Mpa

    UCS-

    0.29Mpa

    UCS-

    0.36Mpa

    UCS-

    0.33Mpa

    UCS-

    0.60Mpa

    13.0m

    UCS-

    1.1Mpa

    UCS-

    0.59Mpa

    UCS-

    1.11Mpa

    UCS-

    0.87Mpa

    UCS-

    1.49Mpa

    UCS-

    3.26Mpa

    14.5m

    UCS-

    2.36Mpa UCS-1.0Mpa

    UCS-

    3.15Mpa

    UCS-

    0.72Mpa

    UCS-

    3.11Mpa

    In general the top strata is Silty Sand with traces of clay upto 9.0m and very dense Silty sand from 9 to

    11.0m and Mudstone starts from 11.0m, with UCS varies from 0.25MPa to 3.15MPa.

    6. Commercial Payment Terms

    1. 5% Advance Payment 2. Performance guarantee 10%, validity until Jan 31st 2019. 3. 10% Rention shall be released after receipt of completion certificate.

    7. Duration of the Project

    Total duration is 45days for construction of Stone Columns.

    8. Submission Procedure

    1. Technical Bid- 3 sets

    2. Unpriced Commercial Bid- 1 set

    3. Priced Commercial Bid- 1 set

  • Al Dhafra Pipe Line and Contracting WLL

    Project: Ground Improvement works

    Client: Dodsal

    Rev 0, Dated 27-05-2014 Page 8

    9. Responsibility Matrix for ground improvement:

    A Copy of the same is attached for information.