Assessment for Ground Improvement Work
description
Transcript of Assessment for Ground Improvement Work
-
Ground Improvement work
(Assessment for ground improvement Works at Carbon Capture and
Storage (CCS) project at ICAD-1, Abu Dhabi
(Main Contractor: Dodsal)
Client: MASDAR & ADNOC
-
Al Dhafra Pipe Line and Contracting WLL
Project: Ground Improvement works
Client: Dodsal
Rev 0, Dated 27-05-2014 Page 1
Contents
1. General ................................................................................................................................ 2
2. Site Location & Brief ............................................................................................................ 2
3. Scope of Work: .................................................................................................................... 2
3.1. Ground Improvement .......................................................................................................... 2
4. Bill of Quantities .................................................................................................................. 4
5. Soil Investigation Report ..................................................................................................... 6
6. Commercial Payment Terms ............................................................................................... 7
7. Duration of the Project ........................................................................................................ 7
8. Submission Procedure ......................................................................................................... 7
9. Responsibility Matrix for ground improvement: ................................................................. 8
-
Al Dhafra Pipe Line and Contracting WLL
Project: Ground Improvement works
Client: Dodsal
Rev 0, Dated 27-05-2014 Page 2
1. General
We have prepared an assessment for the Ground Improvement works by using Stone Columns based on
the Enquiries we have received from M/s Dodsal, Abu Dhabi.
Total Area of Ground Improvement 24,700 Sq.m
2. Site Location & Brief
The site is located in ICAD-1, Abu Dhabi.
3. Scope of Work:
3.1. Ground Improvement
Main Contractor requested to submit our offer based on two Options, Option-1 by using stone columns
and Option-2 by dynamic replacement.
Emirates Steel Factory
ESNAD
Ground
Improvement Area
-
Al Dhafra Pipe Line and Contracting WLL
Project: Ground Improvement works
Client: Dodsal
Rev 0, Dated 27-05-2014 Page 3
The total area is around 24,700 sq.m.
The allowable bearing pressure required is 200Kpa for Plot Area- 130m x 190m
190.0m
130.0m
190.0m
-
Al Dhafra Pipe Line and Contracting WLL
Project: Ground Improvement works
Client: Dodsal
Rev 0, Dated 27-05-2014 Page 4
4. Bill of Quantities
The bill of Quantities provide for the both Options are as follows:
OPTION-1- By using Stone Columns
-
Al Dhafra Pipe Line and Contracting WLL
Project: Ground Improvement works
Client: Dodsal
Rev 0, Dated 27-05-2014 Page 5
OPTION-2- By using Dynamic Replacement
-
Al Dhafra Pipe Line and Contracting WLL
Project: Ground Improvement works
Client: Dodsal
Rev 0, Dated 27-05-2014 Page 6
5. Soil Investigation Report
In this area there are 6 bores holes conducted to a maximum depth of 20m and some trial pits.
As per the soil investigation report, the following is the summary for general information, for detailed
information one has to go through the Soil report.
-
Al Dhafra Pipe Line and Contracting WLL
Project: Ground Improvement works
Client: Dodsal
Rev 0, Dated 27-05-2014 Page 7
Summary of Borehole Data:
Depth(m)
SP
T V
alu
es
BH-1 BH-2 BH-3 BH-4 BH-5 BH-6
1.0m 12 7 5 18 19 19
2.0m 1 1 4 1 10 2
3.0m 2 2 3 2 4 1
4.0m 2 1 0 20 2 1
5.0m 25 24 29 20 33 29
6.0m 25 30 26 25 32 34
7.0m 38 36 35 33 37 40
8.0m 43 40 50 50 41 42
9.0m 50 50 50 50 50 50
10.0m >50 >50 >50 >50 >50 >50
11.0m
UCS-
0.33Mpa
UCS-
0.25Mpa
UCS-
0.29Mpa
UCS-
0.36Mpa
UCS-
0.33Mpa
UCS-
0.60Mpa
13.0m
UCS-
1.1Mpa
UCS-
0.59Mpa
UCS-
1.11Mpa
UCS-
0.87Mpa
UCS-
1.49Mpa
UCS-
3.26Mpa
14.5m
UCS-
2.36Mpa UCS-1.0Mpa
UCS-
3.15Mpa
UCS-
0.72Mpa
UCS-
3.11Mpa
In general the top strata is Silty Sand with traces of clay upto 9.0m and very dense Silty sand from 9 to
11.0m and Mudstone starts from 11.0m, with UCS varies from 0.25MPa to 3.15MPa.
6. Commercial Payment Terms
1. 5% Advance Payment 2. Performance guarantee 10%, validity until Jan 31st 2019. 3. 10% Rention shall be released after receipt of completion certificate.
7. Duration of the Project
Total duration is 45days for construction of Stone Columns.
8. Submission Procedure
1. Technical Bid- 3 sets
2. Unpriced Commercial Bid- 1 set
3. Priced Commercial Bid- 1 set
-
Al Dhafra Pipe Line and Contracting WLL
Project: Ground Improvement works
Client: Dodsal
Rev 0, Dated 27-05-2014 Page 8
9. Responsibility Matrix for ground improvement:
A Copy of the same is attached for information.