ASMS Project Plan

49
___________________________________ South East Gippsland University ___________________________________ Automated Student Management System (ASMS) Project Plan Date: 20/08/2012 Prepared by ITPM Group 2 University of Colombo School of Computing

description

This is a complete project plan which is prepared using a given business case. It included determining project scope, schedule, cost, budgeting, communication, risk management & human resource management and etc.

Transcript of ASMS Project Plan

Page 1: ASMS Project Plan

___________________________________

South East Gippsland University ___________________________________

Automated Student

Management System

(ASMS)

Project Plan

Date: 20/08/2012

Prepared by ITPM Group 2

University of Colombo School of Computing

Page 2: ASMS Project Plan

2 | P a g e

Table of Contents 1. Introduction and Objectives of the Project Plan ................................................................................. 4

1.1 Overview of the Organization ....................................................................................................... 4

1.2 Current Situation and Problem/ Opportunity Statement ............................................................... 4

1.3 Project Objectives ......................................................................................................................... 5

2. Project ................................................................................................................................................. 6

2.1 Project Information ....................................................................................................................... 6

2.2 Project Objectives ......................................................................................................................... 6

2.3 Project Approach .......................................................................................................................... 7

2.4 Roles and Responsibilities ............................................................................................................ 7

2.5 Project Constraints ........................................................................................................................ 8

2.6 Assumptions .................................................................................................................................. 8

2.7 Preliminary Schedule and Budget Estimates ................................................................................ 9

2.7.2 Preliminary Budget Estimate ............................................................................................... 10

2.8 Plan Modification Rules ............................................................................................................. 10

2.9 Approval Signatures .................................................................................................................... 10

3. Project Scope Management Plan....................................................................................................... 11

3.1 Product description ..................................................................................................................... 11

3.2 Project Deliverables .................................................................................................................... 11

3.3 Scope Statement .......................................................................................................................... 12

3.31 Within Scope ......................................................................................................................... 12

3.3.2 Out of Scope ........................................................................................................................ 13

3.3.3 Project Success Criteria ....................................................................................................... 13

3.4 Work Breakdown Structure Development .................................................................................. 14

3.5 Scope Change Management Process ........................................................................................... 15

3.5.1 Scope of Change Requests ................................................................................................... 15

3.5.2 Change Request Process ...................................................................................................... 16

3.5.3 Change Control Team .......................................................................................................... 16

3.6 Plan Modification Rules ............................................................................................................. 17

4. Schedule management plan ............................................................................................................... 17

4.1 Project Schedule .......................................................................................................................... 17

Assumptions .................................................................................................................................. 17

5. Cost Management Plan ..................................................................................................................... 17

5.1 Project Budget ............................................................................................................................. 19

5.2 Budget Constraints ...................................................................................................................... 19

6. Quality Management plan ................................................................................................................. 21

Page 3: ASMS Project Plan

3 | P a g e

6.1 Quality Standards ........................................................................................................................ 21

6.2 Quality Metrics ........................................................................................................................... 23

6.3 Quality Management Approach .................................................................................................. 23

6.4 Quality Assurance ....................................................................................................................... 24

6.5 Quality Control ........................................................................................................................... 25

6.5.1 Quality Control Reviews ...................................................................................................... 25

6.5.2 Quality Control Activities .................................................................................................... 25

6.5.3 Measures of Software Quality .............................................................................................. 26

7. Risk management plan ...................................................................................................................... 27

7.1 Risk Management Strategies ....................................................................................................... 27

7.2 Risk Management Tools ............................................................................................................. 28

7.3 Data Sources ............................................................................................................................... 29

7.4 Risk Categories ........................................................................................................................... 30

7.5 Risk Probability and Impact ........................................................................................................ 32

8. HR management plan ........................................................................................................................ 33

8.1 Project Organization ................................................................................................................... 33

8.1.1 Project Team ........................................................................................................................ 33

8.1.2 Organization Structure ......................................................................................................... 34

8.1.3 Stakeholders ......................................................................................................................... 35

8.2Resource Requirements ............................................................................................................... 37

8.3 Resource Assignment .................................................................................................................. 38

9. Communication plan ......................................................................................................................... 45

9.1 Stakeholder Analysis .................................................................................................................. 45

9.2 Project Reports ............................................................................................................................ 47

9.3 Project Meetings ......................................................................................................................... 48

9.4 Project Information Accessibility ............................................................................................... 48

9.5 Communications Summary ......................................................................................................... 49

List of Figures

1. WBS

2. Organizational Structure

3. Resource Histogram

Page 4: ASMS Project Plan

4 | P a g e

1. Introduction and Objectives of the Project Plan

1.1 Overview of the Organization

South East Gippsland University is a modern academic organization. The Student

Management System of the University provides support for the university’s endeavours,

teaching and research. The goal of the management of the University is to continue with the

improvement of its systems to achieve service excellence and cost advantages. The proposed

project is attempting to revolutionize the service delivery to key stakeholders and foster

excellence in teaching, research, and public service that will establish the University as a

leader among the nation's major research universities.

The University currently has an aging student management system. It currently runs on old

technology, which is difficult and expensive to maintain, and does not provide the flexibility

and services needed in a modern academic organization. Implementing an appropriate

replacement presents an opportunity to integrate new technology such as SMS

communication with students (i.e. for the delivery of results), and use of social media (such

as Facebook, You Tube and Twitter), therefore increasing the overall ability of students to

communicate with the university and to facilitate the university with better communication

and feedback with students.

1.2 Current Situation and Problem/ Opportunity Statement

Currently at South East Gippsland University there is a separate and costly infrastructure for

student enrolments, students’ updates, alumni management and results publishing services.

Some of the systems rely on out-dated and unsupported equipment. The current technology

has limited flexibility for new, expanded and integrated services. A system is required to

support all the communications, infrastructure, and services to students and staff. Therefore

they are going to implement a new Automated Student Management System (ASMS) to

avoid those limitations.

The ASMS Project will renew the student management services and infrastructure at South

East Gippsland University. The University will implement a state-of-the-art web based

system to provide a higher level of service at lower cost for University customers. The system

will integrate the use of SMS and other social media technology with the student

management system. The ASMS’s strategy is to change all of its obsolete student

management systems (student enrolment system, student reporting system (for lecturers and

administrative staff to view results), the results submission system (for lecturers to submit

results) and the results publication system that publish results to students.

The new implementation will provide one integrated system instead of an assortment of

systems, integration with other technologies (such as SMS), applications and social media,

availability of trained systems-developers and Lower operational costs for the University.

Page 5: ASMS Project Plan

5 | P a g e

The existing student management suite cannot utilize cost-effective new technology (SMS

and other social media) and cannot be effectively maintained due to a scarcity of trained

systems-developers due to the age of the system and the compartmentalised nature of

previous enhancements of the systems.

In this situation, the University will update its aging student management suite of systems.

The existing systems will be replaced with a modern, integrated system. This modernization

is expected to enhance service delivery to faculty, students and staff in ways that cannot

effectively be accomplished with the existing core technology resources in place.

1.3 Project Objectives

Objectives

Transform and advance quality in teaching, research, and public service.

Enable new voice and data applications to support the University's mission.

Provide a robust, flexible, ways of communication between students and the university

to meet the communications requirements of the instructional faculty, researchers, and

students.

Upgrade technology infrastructure and support the organization.

Potential Benefits new ASMS.

A modern, state-of-the-art student management system. Integration with other

technologies and applications.

Improved services for all staff and students

Quicker and more responsive action on new and change service requests and

troubleshooting.

Simplified billing.

Upgrade of systems will reduce maintenance overheads on current old systems

A more dependable, robust and secure network.

University staff will benefit as they will not have to use multiple systems.

New technology already used by students will be utilised for student management

processes. This will provide the university with immediate feedback about the service

quality and what students think about the degrees and units taught.

Page 6: ASMS Project Plan

6 | P a g e

2. Project

2.1 Project Information

Project Start Date: 2nd of May, 2012

Project Manager: Mr. Waruna Kodituwakku

Project Sponsor: Information Technology Services (ITS), South East Gippsland University.

2.2 Project Objectives

Objectives

Transform and advance quality in teaching, research, and public service.

Enable new voice and data applications to support the University's mission.

Provide a robust, flexible, ways of communication between students and the university

to meet the communications requirements of the instructional faculty, researchers, and

students.

Upgrade technology infrastructure and support the organization.

Potential Benefits new ASMS.

A modern, state-of-the-art student management system. Integration with other

technologies and applications.

Improved services for all staff and students

Quicker and more responsive action on new and change service requests and

troubleshooting.

Simplified billing.

Upgrade of systems will reduce maintenance overheads on current old systems

A more dependable, robust and secure network.

University staff will benefit as they will not have to use multiple systems.

New technology already used by students will be utilised for student management

processes. This will provide the university with immediate feedback about the service

quality and what students think about the degrees and units taught.

Project End Date: 30th of May, 2014

Page 7: ASMS Project Plan

7 | P a g e

2.3 Project Approach

Project Approach Phase Description

Project Initiation & Planning In this phase all initiation activities such

as resource allocation, planning and

approving project charter will be done.

Project Execution In this phase following activities will be

done.

1. Monitoring & Control

1. Requirement Analysis & Specification

2. Design

3. Implementation

4. Quality Management

5. Training

Installation Install all the software, database and

hardware components.

Maintenance Monitor and take actions to solve issues

and gather requirement for further

enhancements.

2.4 Roles and Responsibilities

Name Role Position Contact Information

Waruna Kodituwakku Project Manager Project Manager [email protected]

Charaka Hettiarachchi Accountant Accountant [email protected]

Shanika Udeshini Human

Resources

Manager

Human Resources

Manager

[email protected]

m

Aloka Weerasuriya Communications

Manager

Communications

Manager

alokaweerasooriya07@

gmail.com

Dasitha Wijesundara Business Analyst Business Analyst [email protected]

Harshani

Wickramarachchi

Quality

Assurance

Analyst

Quality Assurance

Analyst

[email protected]

Page 8: ASMS Project Plan

8 | P a g e

NimalBandara Network

Engineer

Network Engineer [email protected]

Kumudu Lokuge Assistant

Network

Engineer

Assistant Network

Engineer

[email protected]

m

Sadishani Rangika Network

Operators

Network Operators [email protected]

m

Sunil de zoysa Security

Specialist

Security Specialist [email protected]

Nirmal Perera User Interface

Designer( LMS

expertise)

User Interface

Designer( LMS

expertise)

[email protected]

2.5 Project Constraints

Resource Constraints

Some staff resources will be available only on a part-time basis.

Budgetary Constraints

Salary scheme for employees will be based on the current market situation and total

employee costs will be at around 60% of the project budget.

No additional cost for Wireless broadband hardware and software apart from $50,000.

Schedule Constraints

Project requires to be implemented within 24 months or less time frame and the

existing services have to be maintained continuously.

Project Team does not work on weekends.

Quality Constraints

Deliverables of the project plan and ASMS System should be subject to quality review

process throughout the designing and implementation process.

2.6 Assumptions

Resource Assumptions

• Project staff resources will be available when and as they are needed.

• Required hardware resources will be available when and as they are needed.

Page 9: ASMS Project Plan

9 | P a g e

• Required customer resources will be available when and as they are needed.

• A significant percentage of the project staff will be experienced with the technical

environment.

• Access to industry experts and specialized skills will occur as needed.

Delivery Assumptions

• Deliverables will be subject to no more than a specific number of review cycles.

• Software and Equipment order lead times are known and can be expected to be met.

Environmental Assumptions

• No industrial action will be taken that will affect the project.

• Issues will be resolved in a timely manner.

Budgetary Assumptions

• The statistics used in preparing the estimates are accurate within a given percent.

• Outsourced consulting will be limited to a specified number of days at a specified rate per

day.

Functionality Assumptions

• The scope of the project is limited to that described in the project scope statement.

2.7 Preliminary Schedule and Budget Estimates

2.7.1 Preliminary Schedule

Phase Estimated Duration

(Days)

Project Initiation & Planning 48 days

Monitoring & Control 130 days

Requirement Analysis &

Specification

55 days

Quality Management 10 +176 days (parallel)

Design 50 days

Implementation 100 days

Installation 25 days

Page 10: ASMS Project Plan

10 | P a g e

Testing 110 days (parallel)

Training 30 days (parallel)

Maintenance 65 days(parallel)

2.7.2 Preliminary Budget Estimate

2.8 Plan Modification Rules

Only the project manager has the authority to change this project charter. Before getting approval by

the sponsor any change will be informed to project team members via email. After getting approval

there will be any change will be not approved.

2.9 Approval Signatures

Project Manager:

As project manager on Automated Student Management Project, I have reviewed the information

contained in the Project Charter and agree to its content.

Name Position Signature Date

Cost Areas $

Total Employee cost 1,700,000.00

Total software cost 1,100,000.00

Total Hardware cost 100,000.00

Total service charges 20,000.00

Total Overhead cost 30,000.00

Total Outsourced Costs 50,000.00

Total 3,000,000.00

Page 11: ASMS Project Plan

11 | P a g e

The signatures above represent stakeholders’ agreement and acknowledgement of the information

contained in this document.

3. Project Scope Management Plan

3.1 Product description

The new Automated Student Management System (ASMS) will be a web based software

application for the administration, documentation, tracking, reporting, communication and

delivery of education courses or training programs online. The ASMS will be able to do the

following.

Centralize and automate administration

Use self-service and self-guided services

Assemble and deliver learning content rapidly

Consolidate training initiatives on a scalable web-based platform

Support portability and standards

Personalize content and enable knowledge reuse

Deliver online training and webinars

Communication through SMS and social media such as Face book and YouTube.

ASMSs range from systems for managing training and educational records, to software for

distributing and delivering of online courses, augment on-campus courses and deliver online

training, as well as automate record-keeping and student registration. Student self-service

(e.g., self-registration on instructor-led training), training workflow (e.g., user notification,

manager approval, wait-list management), the provision of on-line learning (e.g., computer-

based training, read & understand), on-line assessment, management of continuous

professional education (CPE), collaborative learning (e.g., application sharing, discussion

threads), and training resource management (e.g., instructors, facilities, equipment), are all

important dimensions of the Student Management System.

3.2 Project Deliverables

Software Documentation

o System Documentation

o User Documentation (User Manual)

Project documentation

o Software Requirements Specification (SRS)

o Software Design Specification (SDS)

Page 12: ASMS Project Plan

12 | P a g e

o Software Project Management Plan (SPMP)

o Software Test Plan (STP)

o Software Quality Assurance Plan (SQAP)

o Software Configuration Management Plan (SCMP)

o Software Verification and Validation Plan (SVVP)

3.3 Scope Statement

Project Title : Automated Student Management System (ASMS)

Prepared by : Waruna Kodituwakku, Project Manager ([email protected])

Project Justification:

The South East Gippsland University, requested this project be done to support the

management of students of university in meeting its strategic goals. This system will help to

reduce operational costs and improve profitability of the university by providing One

integrated system instead of an assortment of systems, integration with other technologies

such as SMS communication (i.e. for the delivery of results) and applications and social

media (Facebook, YouTube) and availability of trained systems-developers.

3.3.1. Within Scope

1. Requirement gathering and defining: Project team will contact university lecturers,

administrative staff and students to determine the best interface and website content. This

will be backed up by prototypes of the major parts of the software and existing system for

more feedback.

2. System capacity: The system’s capacity to hold files for the staff, student and

management will be unlimited by the software, but by the hardware capacity there’re

using.

3. Expert Database: Since ASMS will be receiving many user requests, a dedicated

database is required to record and organize requests in order for best possible response

time and the ability to quickly and easily review past complaints or suggestions.

4. Installation: Once the system is completely implemented and agreed on, System

Development team will install it on all of the necessary components.

Page 13: ASMS Project Plan

13 | P a g e

5. Testing: Testing will include the development of test plans to document how the system

will be tested, who will do the testing, and how bugs will be reported. We will provide

additional Network security for the University Network to prevent unauthorized accesses.

6. Maintenance: We will provide maintenance for the system and the website for 1 year of

the installation date. There will be a well-defined plan for rolling out the new system,

supporting users, and providing updates, enhancements, or other support, as required.

7. Security: All services must be secure with restricted access rights.

8. Training: A 40 days training period will be available of the university’s staff and system

administrative staff on how to use the system. Starting from top level staff and covering

all other relevant parties of the university staff.

9. User Manual: A user manual for the staff will be available. Also, an online user manual

on the website will be available for the users.

3.3.2 Out of Scope

1. All retraining and further maintenance will be responsible of the university

2. All data entering, registration of users, course delivery and etc will be undertaken by

university’s administrative processes as part of operations.

3. Any upgrades required to other systems to enable them to work with the new ASMS.

4. Any social media element such as User Generated Content, communities or moderated

forums.

5. The network room/space, proposed will be delivered by the university.

6. All advertising and marketing required for launch and on an ongoing basis will not be

delivered or paid for by this project

7. Any recruitment required of resources for university purposes once the new system

launches and training and testing completed.

3.3.3 Project Success Criteria

Our goal is to complete the project within 24 months. The initial budget will not be exceeded.

In order to meet this goal each team member must put in three work hours per week.

Deliverables must be completed on time and within the sponsor’s specifications. Late

completion of the project is not acceptable.

Page 14: ASMS Project Plan

14 | P a g e

3.4 Work Breakdown Structure Development

Work Breakdown Structure (WBS) is developed as a chart in which the critical work

elements, called tasks, of the project are illustrated to portray their relationships to each other

and to the project as a whole. This WBS will assist key personnel in the effective allocation

of resources, project budgeting, procurement management, scheduling, quality assurance,

quality control, risk management, product delivery and service oriented management.

The project tasks are categorized into ten phases. Each of these phases is then subdivided

further down to sub phases. Each sub phase of the main phases may be subdivided into at

most two sub phases. Here we have used top-down approach to create the WBS.

Project Manager, Software Architect, Programmer, Business Analyst, Quality Assurance

Analyst, Database Administrator, Software Designer Technical writers, Human Resources

Manager and Web Developers engaged in developing the WBS.

(For detailed WBS refer Appendix B)

Page 15: ASMS Project Plan

3.5 Scope Change Management Process

The purpose of the Scope Change Management Plan is to:

1. Manage and control scope change during the implementation of the Project.

2. Ensure that the project is implemented on time and within the approved budget and

scope.

3. Evaluate and prioritize all changes to the project implementation plan at the

institutional level.

4. Provide a process for implementing change required by the system.

3.5.1 Scope of Change Requests

The following change requests will be addressed by the Scope and Change Management

Plan:

1. Modifications to software.

2. Purchase of 3rd party software.

3. Changes to contracted professional services (e.g. additional consulting visits).

4. Scope (includes modules, data conversion and migration, interfaces, etc.).

5. Milestone dates, including interim milestones and major go-lives.

6. Additional project spending (hardware, training, conferences, etc).

7. Functionality required by policy changes at the university and/or external mandates.

The following change requests will not be addressed by the Scope and Change Management

Plan:

1. Policy / process changes. May occur as a result of a change request.

2. Requests for modifications to current systems which are not to be replaced. Changes

may occur as a result of integration, migration, and conversion decisions.

3. Re-allocation of contracted professional services hours. May occur due to a change

request, but specific requests to re-allocate service hours will not be accepted without

justification based on the change.

4. Changes to existing systems

Page 16: ASMS Project Plan

16 | P a g e

3.5.2 Change Request Process

Step1 - Person who wants to initiates Change Request by completing the Change Request

Information section on the Change Request Form and submitting to Project Manager.

Step 2- Project Manager Reviews the request identifies needed information and next steps to

complete; enters into Change Request Log. Project manager communicates and coordinates

with appropriate personnel to gather required information.

Step 3 - Project Manager prepares and submits Change Request Impact Analysis section and

submits it to the Change Control Team.

Step 4 - Development Team receives weekly updates of pending change requests and

provides input as needed / requested.

Step 5 - Change Control Team approves/denies change request, provides Final

Recommendation on the Change Request Form and advises project Manager and If

appropriate, forward for review and disposition.

Step 7 - Project Manager communicates the decision to:

a. The person who is making the request of the Change Review Team decision.

b. Development Team/ Designers/ Analysts

c. All Project members and appropriate interested parties.

d. Makes appropriate entries into the Change Management Request Log.

Step 8 - Modify Implementation plan and documentation as needed to incorporate approved

change.

Requests resulting in changes to the vendor contract require approval from the Project

Sponsor and no changes to the contract should be acted upon or conveyed as an approved

change until we have verified that we are in compliance with the original contract. Changes

to software, budget, or contracted hours will be reviewed, managed and approved by the

Project Manager. First priority will be given to change requests for mission-critical functions

and/or services. Other criteria for evaluating change requests will be approved by the Change

Review Team. Documents using in this process will be Change Request Form, Change

Request Log and Scope Change Management Plan

3.5.3 Change Control Team

Following personnel will be the members of the Change Control Team

1. Project Manager

2. Business Analyst

3. Software Developing Manager

4. Change Review Team members

Page 17: ASMS Project Plan

17 | P a g e

3.6 Plan Modification Rules

Only the project manager has the authority to change this plan. Notification of scheduled and

unscheduled updates to the plan will be communicated via e-mail to all project participants.

The plan will only receive further baselines if significant change in scope occurs.

4. Schedule management plan

4.1 Project Schedule

Milestone Completion Date

Project Charter Approved 07/08/2012

All project deliverables have been delivered 03/01/2013

All deliverables have been delivered 22/03/2013

Evaluate project quality Starting from 24th of 2013

After that once a week

Create Software Design Specification (SDS) 14/06/2013

Implementation Completed 01/11/2013

Installation Completed 06/12/2013

Director view of the system 03/01/2014

Upload current data to the system 30/04/2014

Testing Completed 09/05/2014

Training Completed 30/05/2014

(For detailed schedule plan (Gantt chart) refer Appendix A)

Assumptions

Project Team does not work on weekend days.

We outsource Security Specialist , Legal consultant, Network Engineer, Network

Operator, User Interface Designer ( LMS Expertise ) for the project

Assume following team members will work on the project to achieve the goals as mentioned

bellow.

CIO - He works First week of the May 2012 and some additional 15 hours. All

together 55 hours.

Page 18: ASMS Project Plan

18 | P a g e

IT Project Manager – He works through all stages of the project, Project Monitoring

and Control, Project Initiation and additional 22 hours.

Accountant Works for 4 hours per month for entire project. And some additional

hours regarding when its needs for the project.

Human Resource Manager - He works especially on managing human resources

and training university staff. 320 hours on whole project.

System Administration - He works specially on Installation, Resolve technical

problems, Resolve technical problems. We allocate 200 days for him

System Architect - He assign to work on Design stage from April 2013 up to June

2013 other and additional hours spend for the iterations 200 hours on whole project.

Software Development Manager – He works for additional plugins that integrate for

the student management system and the design. We allocate 200 hours for him.

Software Engineer / Developer - He works for additional plugins that integrate for

the student management system and the design. We allocate 340 hours for each.

Test Manager - He works in System testing stage we allocate 1120 hours for each of

them. Starting from December 9 2013.

Technical Writers – He works 120 days specially the areas of Requirement Analysis,

Specification ,Design and User Documentation

Help Desk level 2 - Allocate for 60 days for training the staff starting from February

2014 and ends May 2014. (2 steps)

Quality Assurance (QA) Analyst –He works on Quality Plan and Monitor product

quality .( Meet the company deliverables together with web developer, Database

Admin, Data warehouse Engineer and Business analysis) we allocate 480 hours with

Additional hours for referring the quality of the project

Business Analyst – He specially works on Requirement Analysis, Specification,

Develop Software Quality Management Plan and Manage Risk areas and with

additional hours we allocate 560 hours for him.

Network Operator - Work 2 month (June 2013 and August 2013) 160 hours per each

with additional hours apply for maintenance.

Network Engineer - Work 2 month (June 2013 and August 2013) 60 hours with

additional hours apply for maintenance.

Database Administrator - He works specially on Installation, Design and Monitor

product quality. (Meet the out project deliverables together with web developer,

Page 19: ASMS Project Plan

19 | P a g e

Database Admin, Data warehouse Engineer and Business analysis) with additional

hours we allocate 560 hours for him.

Data - warehouse Engineer - He works specially on Installation, Design and Monitor

product quality. (Meet the out project deliverables together with web developer,

Database Admin, Data warehouse Engineer and Business analysis) with additional

hours we allocate 580 hours for him.

Web Developer

o He works June 2013 October 18 2013.He works 8 hours per week. 1920 hours

per each. And he also allocate for 60 days for training the staff .He got to have

some extra hours to train the staff and other developing purposes.

5. Cost Management Plan

5.1 Project Budget

Cost Areas $

Total Employee cost 1,650,670.00

Total software cost 932,487.95

Total Hardware cost 96,910.00

Total service charges 14,670.00

Total Overhead cost 27,044.00

Total Outsourced Costs 49,204.00

Total 2,770,985.95

(For detailed budget refer Appendix D)

Page 20: ASMS Project Plan

20 | P a g e

5.2 Budget Constraints

We use Budgetary Estimate for almost all cost fields.

We use following professional tools for the ASMS project and we purchase them - Web

Studio 5.0 (15 users) , CS Adobe 6 Master Collection 2 yrs (with renewal ), Database and

DB Firewall (Oracle), MyEclips Bling Edition (2 yrs) , Security software (Kaspersky) ,

MS Project Standard 2010. They are Budget Estimates.

Web Developers may use for staff training also.

“Student management System” cost includes the all license fees and the integration

modules of it. Has no additional cost apart from what allocates from budget.

“IT work desk Implementation” has no additional cost apart from what allocates from

budget.

We never allow any amount of Money for the maintenance of the system after the June

2014

We do abide for the security of the network system for 6 months after 2014 June(as

standard procedure)

No additional cost for Wireless broadband hardware and software apart from $50,000

No additional cost for Wireless broadband maintenance e apart from $5,000/annual

5.3 Budget Assumptions

The currency use for calculations is US dollars.

Administration costs not exceed $5000

Reserves $6,806 as “Reserves” for use unexpected costs that when project is going on.

We outsource Security Specialist , Legal consultant, Network Engineer, Network

Operator, User Interface Designer ( LMS Expertise ) for the project

Security Specialist assign for security testing purposes.

We consider that there are no more additional money to spend on training the staff but as

if they need we will negotiate it with Utility and System and functional Testing Cost.

We didn’t include additional food and beverages cost the final budget as they appear on

utility cost.

We assume that current network system of the University has to be upgrade (we already

examined) so we include “Hardware maintenance & implementation” for it.

We add 10 PC maintenance cost and the software renewal cost to the budget.( developers

usages)

Page 21: ASMS Project Plan

21 | P a g e

6. Quality Management plan

6.1 Quality Standards

Project process/ Reports Quality Standards

Project Planning and Management

Project Plan

Configuration Management

Plan

Quality Assurance Plan

Project Status

Reports/ongoing Project

Management

Technology Assessment

Report

Feasibility Report

Team members will go through the case study and

understand the current situation and the project manager

will closely monitor the process of collecting of project

information for the status reports.

IEEE 1058

Requirements Analysis Process

Prototypes and other

diagrams

Flowcharts

System Requirements

Specification Document

(SRS)

Functional Specifications

Document (FS)

Requirements Traceability

Matrix

Use Cases

Once the requirement analysis process is complete in that

case team members provide comprehensive documentation

covering all requirements gathered.

IEEE 830

Design

System Design Document

System Security Consensus

Document (SSCD)

Security Plan

Data Retention Plan

Disaster Recovery Plan

Unit and Integration Test

plan (Begin)

Conversion Plan (Begin)

Transform the requirements into complete and detailed

system design specifications. Once the design is approved,

the Development Team begins the Development Phase.

IEEE 1016

Page 22: ASMS Project Plan

22 | P a g e

Implementation Plan

Operation or System

Administration Manual

(Begin)

Maintenance Manual

(Begin)

Training plan

User Manual (Begin)

Requirements Traceability

Matrix (Update)

Implementation

Finalized System

Documentation

Post-Implementation

Review Summary

Methodology Compliance

Form

System Manual

Program Manual

Data Manual

Application Operation

Manual

Application User Manual

Computer Operating

Procedures Manual

By using the architecture document from the design phase

and the requirement document from the analysis phase, the

team will build exactly what has been requested.

Testing

Unit and Integration Test

plan

Software Validation and

Verification Plan (SVVP)

Software Test

Documentation (STD)

The team will be test the system in the relevant

environment and fix the errors.

IEEE 1012

IEEE 829

Maintenance

Maintenance Manual

Maintenance and Support

Services From

Keeps the system up to date with environment changes and

changing user requirements.

IEEE1993

Page 23: ASMS Project Plan

23 | P a g e

6.2 Quality Metrics

Project Deliverables Quality Metrics

Tensile Strength The system will be used in various industrial environments

under high material stress loads.

Shear Strength The system will be subject to potentially high stress torque

loads in various applications.

Customer Satisfaction The customers should be given the customer satisfaction

form and the customer satisfaction of the system should

reach the expected level.

Material Scrap The system should ensure whether it is following the metrics

which internally established for measuring and controlling

material scrap for manufacturing efforts of it.

Product Defect Rate The system should ensure whether it is following the metrics

which internally established for measuring and controlling

product defects.

6.3 Quality Management Approach

Tool Use of Tool Person Responsible

Total Quality

Management (TQM)

Aims to produce product and service

specifications with zero defects.

TQM creates a virtuous cycle of

continuous improvement that boosts

production, customer satisfaction

and profits.

Quality Assurance Analyst

Quality Management

Framework (QMF)

The QMF standardizes processes,

allowing for increased efficiencies.

These processes strengthen supplier

management techniques in addition

to robust cost control, thereby

improving overall profit. And by

implementing the QMF we ensure

security compliance across a project

lifecycle.

Project Manger

Page 24: ASMS Project Plan

24 | P a g e

Six Sigma Improve the quality of process

outputs by identifying and removing

the causes of defects (errors) and

minimizing variability in

manufacturing

Quality Assurance Analyst

6.4 Quality Assurance

Stage Deliverable Work Product QA Activity

Planning Project Plan Project Schedule ISA Process- (review

process and audit contents )

Preparation Functional Requirements

Document

Acquisition Plan

Installation Plan

Revised Project

Plan

ISA Process- (review

process and audit contents )

Software Design Functional Design

Document

Security Plan

Training Plan

System Test Plan

Acceptance Plan

Conf. Mgmt. Plan

Conversion Plan

Traceability

Matrix

Revised Project

Plan

ISA Process- (review

process and audit contents )

Trace design components to

requirements

Trace requirements to

design components

Programming and

Integration

Site Installation Plan,

System Documentation

Revised Project

Plan

ISA Process- (review

process and audit contents )

System Testing and

Acceptance

Test results, System

Documentation

Operational System

Revised Project

Plan

ISA Process- (review

process and audit contents )

Page 25: ASMS Project Plan

25 | P a g e

6.5 Quality Control

6.5.1 Quality Control Reviews

Bendability Reviews:

These reviews are initialized by Project Management Team. These reviews can take

place as part of the Final Plans Processing.

Constructability and Right of Way Reviews:

These reviews allow input from the departments, for constructability reviews and

assist in the Right of Way Office in reducing right of way costs.

Checking procedures

Checking Reports

o Avoid redundant data.

o Support for focusing on major issues.

o Makes data & structures consistent.

Checking Drawings

o Provides the design according to the requirement of project.

o Provides complete & clear idea of project.

o Provides coordination with other aspects of the project.

o Gives compatible standards and good plans preparation practice

Checking Calculations

Checking Correspondence

6.5.2 Quality Control Activities

1. Check that assumptions and criteria for the selection of data and the different factors

related to data are documented.

2. Check for transcription errors in data input and reference.

3. Check the integrity of database files.

4. Check for consistency in data.

5. Check that the movement of inventory data among processing steps is correct.

6. Check for uncertainties in data, database files etc.

7. Undertake review of internal documentation.

8. Check methodological and data changes resulting in recalculations.

9. Undertake completeness checks.

10. Compare results to previous results.

11. Defining and classifying the severity of defects.

12. Inspecting documents.

13. Inspecting code .(either manually or via automatic static code analysis)

14. Testing executable software. For example: module, unit, integration, system and

acceptance testing.

Page 26: ASMS Project Plan

26 | P a g e

15. Recording of defects.

16. Setting quality control limits outside of which corrective action must be taken.

17. Tracking corrective action on defects.

18. Defect data analysis – tracking defect trends over time.

6.5.3 Measures of Software Quality

Where:

KLOC = Thousand Lines of Code

NDT = Number of Defects Detected in Testing

NDO = Number of Defects Detected in Operation

Assumptions

We have to ensure the quality of the data of the existing system and the data entering process

of the new system. So we are using a Data Base Administrator (DBA) and a Data

Administrator (DA). As we have to increase the communication process of the system, we

have to use some extra plug-in so we are using two Software Engineers and one Software

Manager (SM) to supervise them. Once a week we are conducting a meeting to ensure the

quality of the process. So DBA, DA, SM and the two Quality Assurance Analysts are

participating to the meeting and they are finally providing a weekly Status Report to the

Quality Manager.

Metric Formula Significance

Code defect

density

(in system test)

NDT/KLOC Indicates the quality of the code presented to the

system test group

Code defect

density

(in operation)

NDO/KLOC Indicates the quality of the code delivered to the

customer

Defect removal

efficiency

NDT/(NDT +

NDO)

Indicates the effectiveness of the test function in

removing defects from the delivered software product

Page 27: ASMS Project Plan

27 | P a g e

7. Risk management plan

7.1 Risk Management Strategies

When developing a system, an area of uncertainty that comes along with developing system.

The purpose of the risk management plan is to establish the framework in which the project

team will identify risks and develop strategies to reduce or avoid those risks.

Process Name Process Description

Risk Identification Risk identification should be done in initial step of the

project. So we going to held a project risk assessment

meeting at the beginning. There are few methods to

identify risks. Such as Brainstorming, Delphi Technique,

NGT, Crawford slip etc… here we planned to use

Crawford method. In risk assignment meeting Project

manager distribute slips among all team members and

asked to write down every possible risks which related to

the our project within 5 minutes.

Risk Qualification and

Prioritization

In order to determine the effectiveness of the risks

identified by the team, a probability and impact factor

assign to each risk. This process allows the project

manager to prioritize risks based on the effect they may

have on the project. The project manager develops a

probability impact matrix to facilitate the team in moving

each risk to the appropriate place on the chart. Once the

risks were assigned a probability and impact and placed in

the appropriate position on the chart, the recorder

captured the finished product and the project manager

moved the process on to the next step: risk

mitigation/avoidance planning.

Risk Monitoring In this step the identified greatest risks have been added to

the project plan and ensure that they are monitoring at the

appropriate time in the project schedule. During team

meetings the Risk manger discussed the status of that risk.

Here we take the risk which is relevant to that time period

according to the schedule. Risk monitoring will be a

continuous process throughout the life of this project.

According to the project schedule The Project manager

ensured that the Risk manager provide the necessary

updates about risk status, trigger conditions,

documentation about risk response etc…

Page 28: ASMS Project Plan

28 | P a g e

Risk Mitigation and Avoidance The project manager led the team to develop responses to

each identified risk. Then the project team develops

avoidance and mitigation strategies. Those risks will be

added to the Risk register and the project plan to ensure

that they are monitored at the appropriate time and

responded to the particular risk. All risks which are

relevant to this project will be managed and controlled

within the project time, scope & cost. All identified risks

will evaluated in order to determine the best way to

respond to each risk to ensure compliance with these

constraints. In extreme cases it may be necessary to allow

flexibility to one of the project’s constraints. Here time

and scope are not flexible constrains. Otherwise it will

affect the whole project schedule. Cost is the only flexible

constrain which can change.

Risk Register The risk register is a record of all identifies risks, their

probability and impact, risk categories, mitigation

strategies etc… The risk register also will create at the

initial step of the project. During risk management

meeting, team will identified and categorized each risk.

Based on identified risks and time frames in the risk

register each risk been added to the project plan. Risk

manager will assign a risk manager to ensure agreed

mitigation strategy. Risk manager will provide status

reports of assigned risks according to the planned

timeframe.

7.2 Risk Management Tools

Tool Name Tool Description

Risk Audits Risk audits examine and document the effectiveness of

risk responses in dealing with identified risks and their

root causes, as well as the effectiveness of the risk

management process.

Risk Status Report Weekly report generated by the project team to provide

stakeholders with regular updates on risks and actions

taken to mitigate risks.

Status Meetings Project risk management can be an agenda item at

periodic status meetings. That item may take no time or

Page 29: ASMS Project Plan

29 | P a g e

a long time, depending on the risks that have been

identified, their priority, and difficulty of response. Risk

management becomes easier the more often it is

practiced, and frequent discussions about risk make

talking about risks, particularly threats, easier and more

accurate.

Preparing Resource Scope

Statements

Defines all project inputs that need to be analyzed as a

part of the risk analysis procedure and this includes

defining expected performance levels.

Risk Trigger Questions Lists of situations or events in a particular area of a

municipality that can lead to risk identification. These

are situations or areas where risks have been discovered

within the organization. These trigger questions may be

grouped by areas such as performance, cost, schedule,

software etc…

Risk Lists Usually lists of risks that have been found in similar

municipalities and/or similar situations. Caution must

be used when using this type of information to ensure it

is relevant and applicable to the current situation.

Technical Performance

Measurement

Technical performance measurement compares

technical accomplishments during project execution to

the project management plan's schedule of technical

achievement. Deviation, such as demonstrating more or

less functionality than planned at a milestone, can help

to forecast the degree of success in achieving the

project's scope.

7.3 Data Sources

Data Source Name Data Source Description

Surveys Technique where lists of questions are developed to seek

out risk in a particular area. A limitation of this method

is that people inherently don't like to complete surveys

and may not provide accurate information. The value of

the surveys may be difficult to determine due to

subjectivity in the answers or because of the focus of the

questions themselves.

Lessons Learned Database Project Manager maintained database with previous risk

management documentation from earlier projects

Page 30: ASMS Project Plan

30 | P a g e

Experiential Knowledge The collection of information that a person has obtained

through their experience. Caution must be used when

using any knowledge based information to ensure it is

relevant and applicable to the current situation.

Documented Knowledge The collection of information or data that has been

documented about a particular subject. This is a source

of information that provides insight into the risks in a

particular area of concern.

Historical Information Basically the same as documented knowledge. The

difference is that historical information is usually widely

accepted as fact.

Engineering Templates A set of flow charts for various aspects of the

development process. These templates are preliminary in

nature and are intended as general guidance to

accomplish a top down assessment of activities.

7.4 Risk Categories

Categories Description

Schedule Risk Wrong time estimation

Unexpected project scope expansions

Budget Risk Wrong budget estimation

Cost overruns

Operational Risks

Insufficient resources

No proper system training

No proper resource planning

Less communication in team

Technical Risks Changing requirements

System is complex to implement

o The number of features

o The volume of content

o The levels of permissions required

o The expected volume of traffic

o The expected number of users

o The expected response times

Page 31: ASMS Project Plan

31 | P a g e

Client or target environment Risk The level of internet access

The level of interaction with the system required

The impact of the solution on the people using it

The quality of the equipment being used, SMS

gateway/plug-in required etc…

Production System Risk

The provision for support and maintenance

The experience of the production support team

members

The age of the production system and versions of

software

The level of supporting documentation and

training

Page 32: ASMS Project Plan

32 | P a g e

7.5 Risk Probability and Impact

Item Probability (P) Impact (I) Total Risk

Score(PxI)

Software & Hardware changes 0.8 8 6.4

Poor schedule estimation 0.6 7 4.2

Poor budget estimation and cost

overruns

0.6 7 4.2

High response time of the system 0.6 5 3.0

System breakdowns 0.5 10 5.0

High volume of traffic to the system 0.5 6 3.0

Insufficient resources 0.4 8 3.2

Lack of communication between team

members

0.3 6 1.8

Changing requirements & scope

expansions

0.3 7 2.1

Employee turnover 0.3 4 1.2

Lack of skills in selected team members 0.3 7 2.1

Conflict between team members and

university management

0.2 5 1.0

Conflicts between team members 0.2 5 1.0

Difficulties in training university staff

to the new system

0.2 3 0.6

Team member changes 0.1 3 0.3

University not satisfy about final

outcome

0.1 8 0.8

Unexpected sudden project closedown 0.1 9 0.9

Changes in University management 0.1 4 0.4

Page 33: ASMS Project Plan

33 | P a g e

8. HR management plan

8.1 Project Organization

8.1.1 Project Team

Name Role Phone Number Email Address

Waruna

Kodituwakku

Project Manager,

System Admin

System Architect

+94712092875 [email protected]

Harshani

Wickramaarac

hi

Quality Assurance

Analysis, Test

Manager, Database

Admin

+94717652239 [email protected]

Aloka Lakmali Communication

Specialist, Web

Developer, Help

Desk officers

+94774409754 alokaweerasooriya07@g

mail.com

Dasitha

Wijesundara

Business Analyst,

Database warehouse

Engineer

+94718774454 [email protected]

Shanika

Udeshini

HR Manager,

Software Developer,

Help Desk officers

+94776786279 [email protected]

Charaka

Hettiaarachchi

Accountant, Software

Development

Manager, Technical

Writer

+94714438974 [email protected]

NimalBandara Network Engineer +94784568454 [email protected]

Kumudu Lokuge Assistant Network

Engineer

+94778763944 [email protected]

Sadishani Rangika Network Operators +94714424587 [email protected]

Sunil de zoysa Security Specialist +94753546291 [email protected]

Nirmal Perera User Interface

Designer( LMS

expertise)

+94779752638 [email protected]

Page 34: ASMS Project Plan

34 | P a g e

8.1.2 Organization Structure

(For detailed Resource Allocation Plan refer Appendix C)

Page 35: ASMS Project Plan

35 | P a g e

8.1.3 Stakeholders

Information

Technology

Services

Priyantha

Galpaya

Waruna

Harshana

Dasitha Wijeysundara

Charaka Hettiaarachchi

Shanika Udeshinii

Aloka Lakmali

Harshani Wickramarachchi

Nimal Bandara

Kumudu Lokuge

Sadishani Rangika

Nirmal Perera

Sunil De Zoyza

Students,

Lecturers,

Administra

tive Staff

Thomas

Andrewson

ChandanaIru

galbandara

Dr. David

Gibson

Role on

Project

Project

Sponsor

Chief

Information

Officer

(CIO)

Project

Manager

Project Team Key

Stakeholde

r

Change

Control

Board

Legal

consultant

Steering

Committee

Organization South East

Gippsland

University

Exilesoft

(Pvt.) Ltd.

Exilesoft

(Pvt.) Ltd.

Exilesoft (Pvt.) Ltd. South East

Gippsland

University

Information

Technology

Services

Ruhunu

Legal

solutions pvt

ltd

South East

Gippsland

University

Contact

Information

priyantha197

[email protected]

m

vharshana

@gmail.com

[email protected] Itsdep.ymail

.com

chan24@ym

ail.co

davefast@ya

hoo.com

Page 36: ASMS Project Plan

36 | P a g e

Unique Facts Prefers use of

email for

project

documents

Responsible

for Develop,

maintain, and

facilitate

implementati

on of a sound

and

integrated IT

architecture

as such they

require more

detailed

communicati

ons

Manages day

to day

resources,

provides

project

guidance and

monitors and

reports on the

projects

metrics

Need to have a clear

understanding of the work

to be completed and the

framework in which the

project is to be executed.

reviews

technical

specificatio

ns and

authorizes

changes

within the

organization

s

infrastructur

e

Interest about

the legal

facet of the

project

Ensure that

changes

within the

organization

are effected

in such a way

that it

benefits the

organization

as a whole

Suggestions

for managing

relationships

Keep

informed of

all project

progress

Keep all

information

about the

project

progress.

He is the

primary

communicator

for the project

distributing

information

according to

this

Communicati

ons

Management

Plan

Require a detailed level of

communications which is

achieved through day to

day interactions with the

Project Manager and other

team members along with

weekly team meetings.

Keep

informed

about

current

changes

and can get

feedback to

assist the

progress

Technical

design

documents,

user impact

analysis and

implementat

ion

strategies

are used to

communicat

e with them.

Keep

informed

about the

legal facts of

the project

Steering

Committee

requires

communicati

on on matters

which will

change the

scope of the

project and

its

deliverables

Page 37: ASMS Project Plan

37 | P a g e

8.2Resource Requirements

0

5

10

15

20

25M

ay Jun

Jul

Au

g

Sep

Oct

No

v

De

c

Jan

Feb

Mar

Ap

r

May Jun

Jul

Au

g

Sep

Oct

No

v

De

c

Jan

Feb

Mar

Ap

r

May Jun

Jul

Au

g

Sep

Oct

No

v

De

c

2013 2014

No

of

Emp

loye

es

year/Month

SW developer

CIO

SW development manager

Technical Writer

Security Specialist

Test Manager

Help Desk Officers

Web Developer

Data-Warehouse Eng:

Database Admin

Network Operator

Assistant Network Engineer

Network Engineer

Business Analyst

HR manager

Accountant

QA Analyst

System Admin2012

Page 38: ASMS Project Plan

38 | P a g e

8.3 Resource Assignment

ID T

ask

Nam

e Sub Task 1 Sub Task 2

Waru

na H

ars

han

a

Hars

han

iWath

sala

Alo

kaL

ak

mali

Dasi

tha W

ijes

un

dara

Sh

an

ikaU

des

hin

i

Ch

ara

kaH

etti

ara

chi

Nim

alB

an

dara

Ku

mu

du

Lok

uge

Sad

ish

an

iRan

gik

a

Su

nil

de

zoysa

Nir

malP

erer

a

1 Project Initiation and

Planning

1.1 Start Project √

1.2 Define Project Scope √ √

1.3 Project Planning √

1.3.1 Create task list √

1.3.2 Create estimates √

1.3.3 Create network diagram (PERT) √

1.3.4 Create work breakdown structure (WBS) √

1.3.5 Create schedule (GANTT) √

1.3.6 Create milestone plan √

1.3.7 Create organization plan √

1.3.8 Allocate resources √

1.3.9 Assign Roles and responsibilities √

1.4 Establish Project Environment √

1.4.1 Identify & acquire equipment and tools for the

project √ √

1.4.2 Supporting Staff √ √

Page 39: ASMS Project Plan

39 | P a g e

1.4.3 Communication Procedure √ √

1.4.4 Documentation Procedure √

1.4.5 Workplace √

1.5 Develop Project Charter √

1.6 Project Charter Approved √

2 Project Monitoring and Control √

2.1 Manage Risk √ √

2.1.1 Monitor risks √ √

2.1.2 Specify responses √ √

2.2 Manage Human Resources √ √

2.2.1 Develop HR Plan √ √

2.2.2 Form project team √ √

2.2.3 Train project team √ √

2.2.4 Adapt team √ √

2.3 Manage scope / cost / schedule √

2.3.1 Monitor product changes √

2.3.2 Monitor project changes √

2.3.3 Renegotiate scope / cost / schedule

commitments √

2.4 Manage communications √

2.4.1 Implement communications methods and

strategies √

2.4.2 Distribute information √

2.5 Documentation √

2.5.1 Project team meetings √

2.5.2 Retain records √

2.5.3 Maintain project charter √

Page 40: ASMS Project Plan

40 | P a g e

2.5.4 document updates √

2.6 Request for proposal submitted √ √

2.7 Response from the client √

2.8 Manage integration √

2.8.1 Update project plan √ √

2.8.2 Update communications plan √ √

2.8.3 Update quality plan √

2.8.4 Update risk management plan √ √

2.8.5 Update HR plan √ √

2.9 Manage user acceptance √

2.10 Finalize the conformation

from the university

√ √

2.11 All project deliverables have been delivered √

2.11.1 project closeout √

3 Requirement Analysis and Specification

3.1 Requirement

Identification

3.1.1 Prepare research instruments √

3.1.2 Interview users √

3.1.3 Draft requirements document √

Review requirements document √

Finalize requirements document √ √

3.2 Domain Analysis √ √

3.2.1 Technical feasibility √

Operational feasibility √

Economic feasibility √

Legal feasibility √

Page 41: ASMS Project Plan

41 | P a g e

3.3 Software Requirement Specification (SRS) √

3.3.1 Identify general background of the project √

3.3.2 Requirement analysis and elicitation √ √

3.3.3 Requirement specification √

3.4 All deliverables have been delivered

4 Quality Management

4.1 Develop Software Quality Management Plan √

4.1.1 Define quality criteria √

4.1.2 Define quality assessment methods √

4.2 Monitor product quality √ √

4.2.1 Analyze defects reported √ √ √

4.2.2 Analyze change requests submitted √ √ √

4.2.3 Analyze tests failed √ √ √

4.2.4 Analyze requirements revised √ √ √

4.4 Perform audits/ Quality Improvements √

4.5 Evaluate project quality

5 Design

5.1 Architectural Design √

5.1.1 Develop use cases √ √

5.1.2 Create data architecture √

5.1.3 Create hardware architecture √

5.2 Purchase student management system √ √

5.3 Design the Database √ √

5.3.1 Design database for sub system √ √

5.3.2 design central database system √ √

5.3.3 Provide weekly updates

5.4 Interface Designing √ √

Page 42: ASMS Project Plan

42 | P a g e

5.4.1 Design user interfaces √ √

5.4.2 Design software interfaces √ √

5.4.3 Design additional plug-ins √ √

5.5 Develop System Architecture √ √ √

5.6 Create Software Design Specification (SDS)

6 Implementation

6.1 Develop Prototype with Purchased student management system √

6.2 Wireless communication √ √ √

6.2.1 Check the drawbacks of the wireless broadband √ √ √

6.2.2 Implement wireless broadband hardware &

software

√ √ √

6.2.3 Integration it to the current university network √ √ √ √

6.3 Develop System √

6.3.1 Develop UI √

6.3.2 Develop objects √

6.3.3 Develop workflow √

6.3.4 Develop rules √

6.3.5 Develop middle tier √

6.3.6 Develop database √

6.3.7 Develop connections with other systems √

6.3.8 Develop permissions √

6.3.9 Develop migration scripts √ √

6.3.10 Develop System Documentation √ √

6.4 IT service help desk establish √ √

6.5 Create User Documentation √ √

6.6 Implementation Completed √ √

Page 43: ASMS Project Plan

43 | P a g e

7 Installation √

7.1 Develop Installation Plan √

7.2 Install Software √

7.3 Database √ √ √

7.3.1 Migrate data (previous) √ √ √

7.3.2 Back up databases √ √ √

7.4 Install Hardware components √ √ √ √ √

7.5 Installation Completed

8 Testing √

8.1 Develop Tests √

8.1.1 Develop Unit Tests √

8.1.2 Develop System Tests √

8.1.3 Develop integration tests √ √

8.1.4 Develop environment tests √

8.1.5 Develop migration tests √

8.2 Configure test environment √

8.3 Select Testing tools √

8.4 Execute tests √ √

8.4.1 Execute manual tests √ √

8.4.2 Execute automated tests √ √

8.4.3 Execute beta test √ √

8.4.4 Execute user acceptance test √ √

8.5 Analyze test results √

8.6 Compile test statistics √

8.7 Version finalized √

8.8 Version approved for deployment √

8.9 Upload current data to the system

Page 44: ASMS Project Plan

44 | P a g e

8.10 Testing Completed √

9 Training

9.1 Form Staff

9.1.1 Identify project HR requirements

9.1.2 Select staff members

9.1.3 Recruit consultants

9.1.4 Hire new staff

9.2 Schedule training √ √

9.3 Train Staff

9.3.1 Develop project training materials √ √

9.3.2 Attend business orientation √ √

9.3.3 Attend technical orientation √ √

9.3.4 Attend internal class √ √

9.3.5 Attend external class √ √

9.4 Adapt team √ √

9.4.1 Attend team-building activity √ √

9.4.2 Support remote/virtual/telecommuting work √ √

9.5 Training Completed √ √

10 Maintenance

10.1 Perform impact analysis √

10.2 Monitor user acceptance √

10.3 Monitor performance √

10.4 Monitor defects √ √

10.5 Resolve training and support issues √ √

10.6 Resolve technical problems √ √

10.7 Analyze statistics

10.8 Gather requirements for enhancements √ √

Page 45: ASMS Project Plan

45 | P a g e

9. Communication plan

9.1 Stakeholder Analysis

Information

Technology

Services

Priyantha

Galpaya

Waruna

Kodituwakku

Dasitha Wijeysundara

Charaka Hettiaarachchi

Shanika Udeshinii

W.L.A.T.A.Lakmali

Harshani

Wickckramaarachchi

Nimal Bandara

Kumudu Lokuge

Sadishani Rangika

Nirmal Perera

Sunil De Zoyza

Students,

Lecturers,

Administrative

Staff

Thomas

Andrewson

ChandanaIrug

albandara

Dr. David

Gibson

Role on

Project

Project

Sponsor

Chief

Information

Officer (CIO)

Project Manager Project Team Key Stakeholder Change

Control

Board

Legal

consultant

Steering

Committee

Organization South East

Gippsland

University

Exilesoft (Pvt.)

Ltd.

Exilesoft (Pvt.)

Ltd.

Exilesoft (Pvt.) Ltd. South East

Gippsland

University

Information

Technology

Services

Ruhunu Legal

solutions (Pvt)

ltd

South East

Gippsland

University

Contact

Information

Priyantha1978

@gmail.com

vharshana

@gmail.com

itpm-group-

[email protected]

itsdep.ymail.c

om

chan24@ymai

l.co

davefast@yah

oo.com

Unique Facts Prefers use responsible for manages day to Need to have a clear reviews Interest about Ensure that

Page 46: ASMS Project Plan

46 | P a g e

of email for

project

documents

Develop,

maintain, and

facilitate

implementation

of a sound and

integrated IT

architecture as

such they

require more

detailed

communication

s

day resources,

provides project

guidance and

monitors and

reports on the

projects metrics

understanding of the

work to be completed

and the framework in

which the project is to be

executed.

technical

specifications

and

authorizes

changes

within the

organizations

infrastructure

the legal facet

of the project

changes within

the

organization

are effected in

such a way

that it benefits

the

organization

as a whole

Level of

Interest

High High High High Medium High High High

Level of

Influence

High High High High Low High High High

Suggestions

for managing

relationships

Keep

informed of

all project

progress

Keep all

information

about the

project

progress.

He is the primary

communicator for

the project

distributing

information

according to this

Communications

Management Plan

Require a detailed level

of communications

which is achieved

through day to day

interactions with the

Project Manager and

other team members

along with weekly team

meetings.

Keep informed

about current

changes and can

get feedback to

assist the progress

Technical

design

documents,

user impact

analysis and

implementati

on strategies

are used to

communicate

with them.

Keep informed

about the legal

facts of the

project

Steering

Committee

requires

communicatio

n on matters

which will

change the

scope of the

project and its

deliverables

Page 47: ASMS Project Plan

47 | P a g e

9.2 Project Reports

Data Needed Frequen

cy of

Collectio

n

Responsible Party

for Data Collection

& Analysis

Report Media

& Format

Responsible

Party for

Distributing

Report

Trend

Analysis

Past project

data,Previous Status

reports

Monthly Project Team Printed

document with

calculations

Project Manager

Variance

Analysis

Proposed

results,actual results

Bi-

weekly

Project Team Through e-

mail,

favourable and

adverse

mentioned

Project Manager

Earned

Value

Analysis

Previous

records,estimations,

proposed bugdet

Monthly Project Team Printed

copy,handed

individually

Project Manager

Schedule

Status

Tracking Gantt Chart Bi-

Weekly

Project Team Status Form Project Manager

Project

progress

Report

Work has been

completed and works

to be completed

through the meetings

that have among

project team

Bi-

Weekly

Project Team Printed

document

Project Manager

Project

Status

Report

Status of the project

including activities,

progress, costs and

issues, e-mails (sent

by team members),

Analyzing the

workload

Monthly Project Sponsor

Project Team

Stakeholders

Printed

document

Project Manager

Page 48: ASMS Project Plan

48 | P a g e

9.3 Project Meetings

Purpose Frequenc

y

Attendees Reporting

Requirements

Kickoff

Meeting

Introduce the project team and

the project. Review project

objectives and management

approach

Once Project Sponsor,

Project Manager,

Project Team,

Stakeholders, CIO

Meeting

Minutes

Status

Review

Meeting

Update on project status Weekly Project Manager,

Project Team

Meeting

Minutes,

variance and

trend analysis,

Status report

Monthly

Project Status

Meetings

Report on the status of the

project to management

Monthly Project Manager, PMO Monthly Status

Report

Project Status

Reports

Report the status of the project

including activities, progress,

costs and issues

Monthly Project Sponsor,

Project Team, Project

manager, CIO,

Stakeholders

Project Status

Report

Technical

Design

Meeting

Discuss and develop technical

design solutions for the project

As needed Project Technical staff Design

specification

documents,Req

uirement

specification

documents

9.4 Project Information Accessibility

It is important to keep project information secured from outsiders and it is critical to the

success of the project. Considering about the ASMS project of South East Gippsland

University it is very important to keep all information in a secured place and allow access

those information to relevant persons. So consider about those facts we are going to store all

the information related with the ASMS project in a web site that created for the project. Team

members and stakeholders can access that information by log in to the site to do that first they

have to register to the site and create user accounts. Administrator of the site will grant the

relevant privileges to the users according to their user level.

Page 49: ASMS Project Plan

49 | P a g e

In addition to that all the documents that related to the project will be e-mailed to the project

management group mail. For an example people who responsible to do the work allocated by

project manager, after completing the work he can send it to the group mail. So anyone

interest with it can access it according to their necessity.

9.5 Communications Summary

Stakeholder Type Communication

Medium

Frequency Responsible Party

Project Sponsor

Project Team

Key Stakeholders

Kickoff Meeting

Face to Face

Once

Project Manager

Project Team Project Team

Meetings

Face to Face

Conference Call

By Weekly Project Manager

Project Technical

Staff

Technical Design

Meetings

Face to Face As Needed Project Technical Lead

PMO(Project

Management

Office)

Monthly Project

Status Meetings

Face to Face

Conference Call

Monthly Project Manager

Project Sponsor

Project Team

Key Stakeholders

PMO

Project Status

Reports

Email Monthly Project Manager