ASIC Test Oriented Simulation Manual - ww1.microchip.com

31
ASIC Test Oriented Simulation Manual Introduction A challenge of testing application-specific ICs is creating test patterns by IC-design engineers who do not have deep knowledge of the test-equipment and the related requirements and restrictions. This manual bridges the gap by providing explanations, examples, and the necessary information to successfully set up and perform simulations, which must be usable for testprogram-generation. It also explains the Microchip-internal transformation-flow and the tools involved. Terminology The following terms are used frequently to identify specific test features and constraints: Terminology Description ATE Automatic Test Equipment (ATE). A tester is an ATE. DUT Device Under Test (DUT) A hardware product verified on the tester. It can either be a die on a wafer or a packaged part. Wafer Probe Testing operation for die on wafers. It uses an additional ATE named Prober and a DUT interface named Probe Card. Final Test Testing operation for packaged parts after assembly. It uses a DUT interface named Load Board. Test Cycle The interval of time (also called period) in which a test vector is presented to the DUT. The beginning of a Test Cycle is the reference time for relative timings. Test Vector A Test Vector consists of one signal state line in a test pattern. It contains: A period that delimits the beginning and end of the test vector, also called Test Cycle. Signal states. Each signal state is represented by a symbol, which reflects its level and direction (input or output mode for bidirectional). See Waveform File Format for more information about symbols. Timing data. Each signal has its own timing data. Inputs are stimulated at predefined times (driven by the hardware of the tester), and outputs are sampled at predefined Strobe times. Test Pattern This is a set of test vectors, usually composed of one or two files: one for the signal states and one for the timing information. They are the results from the conversion of a simulation. The very first test vector starts at time 0, which is the absolute time (reference) for the pattern. © 2021 Microchip Technology Inc. and its subsidiaries Manual DS50003170A-page 1

Transcript of ASIC Test Oriented Simulation Manual - ww1.microchip.com

ASIC Test Oriented Simulation ManualIntroduction
A challenge of testing application-specific ICs is creating test patterns by IC-design engineers who do not have deep knowledge of the test-equipment and the related requirements and restrictions.
This manual bridges the gap by providing explanations, examples, and the necessary information to successfully set up and perform simulations, which must be usable for testprogram-generation. It also explains the Microchip-internal transformation-flow and the tools involved.
Terminology The following terms are used frequently to identify specific test features and constraints:
Terminology Description
ATE Automatic Test Equipment (ATE). A tester is an ATE.
DUT Device Under Test (DUT)
A hardware product verified on the tester. It can either be a die on a wafer or a packaged part.
Wafer Probe Testing operation for die on wafers.
It uses an additional ATE named Prober and a DUT interface named Probe Card.
Final Test Testing operation for packaged parts after assembly.
It uses a DUT interface named Load Board.
Test Cycle The interval of time (also called period) in which a test vector is presented to the DUT.
The beginning of a Test Cycle is the reference time for relative timings.
Test Vector A Test Vector consists of one signal state line in a test pattern.
It contains:
A period that delimits the beginning and end of the test vector, also called Test Cycle.
Signal states. Each signal state is represented by a symbol, which reflects its level and direction (input or output mode for bidirectional). See Waveform File Format for more information about symbols.
Timing data. Each signal has its own timing data. Inputs are stimulated at predefined times (driven by the hardware of the tester), and outputs are sampled at predefined Strobe times.
Test Pattern This is a set of test vectors, usually composed of one or two files: one for the signal states and one for the timing information. They are the results from the conversion of a simulation. The very first test vector starts at time 0, which is the absolute time (reference) for the pattern.
© 2021 Microchip Technology Inc. and its subsidiaries
Manual DS50003170A-page 1
...........continued Terminology Description
Tset Tset or Timing Set
It is the (named) identification of all timing data for a given test vector. Testers have a hardware limitation for the maximum number of Tsets in general.
Fset Fset or Format Set
It is the combination of formats of all signals (that is, input mode, output mode or undriven mode) at a given test vector. The Fsets can change from one test vector to the next one. However, testers have a hardware limitation for the maximum number of Fsets. In order to avoid violating the maximum number of Fsets, it is recommended to carefully check the direction of bidirectional ports in the simulations.
TOS Test Oriented Simulation (TOS)
A specific simulation performed by the designer to build the corresponding test pattern, which is intended to run on the ATE.
NRZ Non-Return to Zero (NRZ)
Format of a signal which has only a single event transition (at a given time) in a test vector.
RTZ Return To Zero (RTZ)
Format of a signal, which may have two event transitions, the first to go to HIGH state, and the second to return to LOW (Zero) state.
RTO Return To One (RTO)
Format of a signal, which may have two event transitions, the first to go to LOW state, and the second to return to HIGH (One) state.
Advice Copyright 2021 by Microchip Nantes S.A., printed in France
All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted in any form or by any means without prior written permission from Microchip Nantes S.A.
DISCLAIMER
The information in this document is subject to change without notice and should not be construed as a commitment of Microchip Nantes S.A. The reader should, in all cases, consult Microchip Nantes to determine whether any changes have been made.
NOTICE
This documentation for Microchip Nantes software proprietary product (programs, libraries) is subject to the conditions of a Software License Agreement, and may be used only by licensees and their employees. Access to Microchip Nantes documents by other persons is prohibited.
As provided in the Software License Agreement, no copies of the software and documentation may be made, in whole or part, without express written permission of Microchip Nantes S.A. The license is attached to a "Design Development", it starts at the "Project Order Entry" date and expires at the "Design Approval" date.
To prevent confusion because of multiple versions and to control unauthorized access and use, all copies of previous versions of the documentation should be destroyed by the licensee of the product, upon receipt of the latest version.
MICROCHIP NANTES SOFTWARE SUPPORT
Contact the ASIC Field Application Engineer in your local Microchip Technical Center office.
© 2021 Microchip Technology Inc. and its subsidiaries
Manual DS50003170A-page 2
To ensure accurate and expedient assistance with your questions or problems, please use the hotline call electronic form.
TRADEMARKS
CADENCE, MENTOR GRAPHICS, SUN, SYNOPSYS are registered trademarks.
© 2021 Microchip Technology Inc. and its subsidiaries
Manual DS50003170A-page 3
Table of Contents
Manual DS50003170A-page 4
Manual DS50003170A-page 5
1. Product Testing
1.1 Design Cycle The design cycle of a product consists of several operations, one of them being the functional simulation. Several kinds of functional simulations can be performed, some of them to check the product functionality (digital, analog or mixed signal) in its application environment, and some of them are dedicated to build a test program for chip verification after fabrication (TOS).
TOS consist of several parts—Scan test, at-speed test, functional test, BIST, and so on. Each of them is either outputs from a golden simulator (such as VHDL or Verilog™) or from an automatic test pattern generator (ATPG) such as FastScan™ or TetraMax™.
1.1.1 TVT Overview The waveforms are generated in .vcd files or .stil files. The .vcd file format must be translated with Test Vector Translator (TVT) (part of Microchip Design Kit) into a proprietary Microchip format as a set of two files—VECT and TIMSET. Besides, the .stil format generated by most ATPG commercial tools can be directly transferred to Microchip if it is restricted to the IEEE® 1450.99 specification.
1.1.1.1 Sub-Nanosecond Times in TVT TVT and VECT-TIMSET files can support times less than a nanosecond. The minimal time unit in TVT is 1 ps. All times expressed with a fraction smaller than 1 ps are rounded.
Using the minimal test resolution of 10 ps for simulations is a good compromise between simulation-time, precision, and file size.
For the test-oriented simulations, this might cause differences between the minimum and maximum-simulations. It is recommended to first simulate with a precision of 1 ps to check, if the mismatch disappears before investigating in other directions.
1.1.2 TECT Overview Test Entities Configuration Tools (TECT) is used (also part of Microchip Design Kit) to manage and transfer product files to Microchip Technical Center. It includes a series of verifiers to check simulation results and other special DC and AC test requirements. You will find some TECT information in this document, and more details in the TECT User Manual.
After file transfer to Microchip, they are combined into a test program that runs onto a tester. The tester provides a method to certify that the hardware product is functional after fabrication in the given environment (temperature, voltage, radiation, life test, and so on). These tests are run first at wafer level (wafer probe), then after assembly at device level (final test).
1.2 TOS Guidelines To stimulate a device off its final application board, a series of logical vectors must be applied to the device inputs. These are called test vectors that are used to stimulate the design inputs and check the outputs against the expected values. In other words, on a tester the test vectors replace the HDL test bench (used by designers) to verify the design functionality.
Microchip sets some rules and formats for customers to generate test vectors. A standardized format helps customers and Microchip to:
• Improve simulation by reducing errors • Simplify design verification on ATE • Reduce project cycle times • Reduce debugging costs
This document provides guidelines for test vector sets. These are recommended for functional verification of ASIC designs made with Microchip and cover several aspects of design verification including:
Product Testing
Manual DS50003170A-page 6
• Waveform file format • Tester constraints • Mandatory tools to use—TVT and TECT • Simultaneously switching outputs (in Appendix)
1.2.1 Waveform File Format The vector file (VECT) is a text file that contains binary values of all signals of the device. Each line of the file forms a test vector, which indicates the state of all ports at a given test cycle.
Individual signal entries in each line must use the following characters:
• Inputs—0, 1, D or U • Outputs—L, H, Z or X (tested states) • Bidirectional—either 0, 1, D or U (input mode) or L, H, Z or X (output mode)
1.2.2 Tester Constraints The vector files are applied to the device using the tester (ATE) as described in Microchip Test Equipment. The tester limitations along with general hardware considerations imply constraints, which must be considered during the test vector generation.
The tester activities such as applying input signals and reading back the outputs of the design are synchronous to a reference clock, which is extracted from the vector file. Therefore, synchronous vector files are always required.
As the vector files must always be synchronous, care must be taken in generating vectors for signals, which are asynchronous in the application. The asynchronous inputs must be applied in the test vectors synchronously to the tester cycle and outputs will be sampled synchronously to the tester cycle.
As with asynchronous inputs, you must check if multiple clock inputs to the design are asynchronous with respect to each other. Due to the synchronous nature of the vector files, the asynchronous clocks may be affected by missing edges with respect to the reference clock. As a result, clocks must be synchronized to avoid errors.
1.2.3 Analog IPs The test of the analog IPs must be considered during the code-development phase. For more information on integration and test strategy, see the IP’s datasheet. Support and additional information can be provided at the Microchip local design center.
1.3 MICROCHIP Test Equipment For testing the high complexity circuits such as those using MICROCHIP ASIC families, the following tester will be used: Cohu D10 (100 MHz, up to 200 Mbits/sec, 672 digital pins, accurate DC measurements with VIS16 option).
A tester specification datasheet can be provided on request.
Product Testing
Manual DS50003170A-page 7
Product Testing
Manual DS50003170A-page 8
2. TOS Rules Most testers have hardware and software restrictions and limitations that designers must take into consideration. These restrictions and rules must be checked as early as possible in the TOS design cycle with Microchip’s TVT and TECT tools.
2.1 What is TECT? Since 2014, Test Entities Configuration Tools (TECT) is a utility tool between design and test environments.
TECT collects design data files such as simulation results, and several other product description files, to build a package to be transferred to Microchip Technical Center then to Test Engineering to generate test programs.
TECT includes built-in interactive verifiers that check data consistencies and various causes of error, and it creates error reports.
2.2 Design to Test Flow The following figure shows where TECT is in the test program generation flow:
TECT is designed to use in an interactive way. It is delivered as part of Microchip Design Kits (DK). See the TECT User Manual for more information about installation and usage.
Usually, at the beginning of a project for a new product, the Microchip Technical Center receives a pin list from the customer. The Microchip Technical Center analyses the pin list and starts working with TECT. TECT supports several processes (from 0.15 µm to 65 nm) and the technology choice is the starting point.
Microchip’s TECT archive, by Microchip’s DC, is transferred back to the customer to finish the remaining tasks.
2.3 TECT Startup The graphical user interface of TECT consists of a series of primary tabs (Product, SignalGroups, Patterns, and so on) and a series of secondary tabs (Supply nets, Signals, Bondings, and so on). Each of these tabs must be opened and filled to satisfy TOS rules, before navigating to the next tab.
TOS Rules
Manual DS50003170A-page 9
The different tabs show an attached symbol:
• Indicates, if there is a missing information (for example, CellInst is missing).
• Indicates, if an error was detected that must be fixed (for example, an AC Check for which the signal transitions are not present in the corresponding test pattern).
2.4 TECT Tabs The TECT tabs are named as:
• Product: Definition of the product and the following sub-tabs: – Supply nets: Set voltages (Typ, Min, and Max) for all supply ports (Note 1). – Signals: External I/Os and all associated information, including internal control ports (Note 1). – Bondings: Package pin lists (Note 2). – Toolings: Tester hardware interfaces. Wafer Probe Cards, Device Load Boards, and Burn-In Boards are
Microchip’s responsibility (See TECT Manual). • SignalGroups (optional): To help designer to group signals together. • Patterns: Definition of the TOS patterns to be used in the test program.
– Defines the format and the use of each pattern. • IPs: Definition of additional IP information such as LVDS pairs and reference voltages (Note 3). • Tests: Access to three sub-tasks: DC Tests, AC Tests, and Idd Tests.
– DC Tests: Allow selection of dedicated patterns for DC tests. – AC Tests: Manage all AC tests to be performed. – Idd Tests: Manage Idd StandBy, (Dyn) Operating Idd, and Iddq measurements.
• Checks: Click the Check All button to perform all possible checks. • Archive: Builds a TECT database for transfer to Microchip Technical Center (See Test Prep Flow).
See the TECT User Manual for more information.
Note 1: This information can be uploaded automatically from the .P0 file (output from PIMTOOL). When the .P0 file is not filled correctly (for example, internal control ports are often missing), you can import the Verilog description (.v file), which contains the top module of the product.
TOS Rules
Manual DS50003170A-page 10
Note 2: The bonding information (connections between die signals to package pins) can be entered automatically from the .bdf file (output from PIMTOOL).
Note 3: For all LVDS I/O ports, it is mandatory to identify the external voltage reference pins, except if the given reference voltage is internally generated.
For each pair during simulation, the N and P pins must be stimulated, one at the inverse state than the other. Ensure that the external reference voltage pins must be present in the netlist and driven to logical 1.
2.5 TECT Flow The TECT flow consists of the following steps:
• An initial .vdf file for TVT is generated by TECT. • TVT generates patterns in VECT-TIMSET file format, from designer’s simulation provided in .vcd or .evcd file
formats. • The .stil files are only verified by TECT for their IEEE® 1450.99 compliance, then transferred to the TTZ
database. • The TTZ database is a zipped tarball of all necessary files to transfer to the Microchip Technical Center. This
database is encrypted by default for transfer security. However, the encryption may be disabled. • The Modular Test Program Generator (MTPG) requires DDF file, BDF file, and patterns in VECT-TIMSET and/or
STIL formats. The TPC file gives an additional information about the test program to be generated. All these files are packaged and compressed in the TTZ database file.
• After place and route operation, the pad locations (X-Y coordinates of the wire bonding areas) are known and written in the .ddf file. They are required in TECT, prior to transfer the TTZ database to your Microchip Technical Center. They are used to build the Probe Card documents. Instead of the .ddf file, you may also receive a .coord file that provides the required X-Y coordinates of the wire bonding areas.
TOS Rules
Manual DS50003170A-page 11
2.6 TECT Files (Bonded Packages)
Note: This flow with PimTool applies for standard bonded packages (For Flipchip-Packages, see here below).
TOS Rules
Manual DS50003170A-page 12
2.7 TECT Files (Flipchip Packages)
2.8 Test Prep Flow At the end of the TECT flow, the TTZ archive database must be transferred through FTP to the Microchip Technical Center.
The following figure shows what happens with the TTZ archive after transfer:
• The files in the TTZ archive are backed up on a secured Microchip server and recorded in Microchip’s Test Prep database.
• A Microchip Graphical User Interface shows the status of files. • The Microchip MTPG is used to build the appropriate test program for the target ATE. • A Microchip Test Engineer checks the test program with actual parts on the target tester.
TOS Rules
Manual DS50003170A-page 13
2.9 Burn-in Board and Patterns Definition Microchip provides multiple kinds of ovens with different testing capabilities (burn-in with test, individual temperature control).
For now, TECT only provides an interface for the Criteria and MCC ovens, for all other kinds of hardware, burn-in board, and dedicated patterns must be done outside TECT control.
See the Microchip DSGE 003 specification, Burn-in Board Definition for more information.
TOS Rules
Manual DS50003170A-page 14
3. Test Patterns Each test pattern consists of a set of test vectors. A test vector is a combination of inputs/outputs within a test cycle named period. In this test cycle, the inputs are FORCED (driven) by the tester, while the outputs are STROBED (sampled) and compared to the expected states.
The test vectors must be checked by comparing the simulations in worst case against the best case, and must take into account the delay back annotation (.sdf file) after chip place and route.
All patterns used for DC tests must use static vectors. There must be enough time to ensure stable outputs after changing the inputs.
The outputs are usually sampled (at Strobe time) at the end of the test vector (90% of the period).
The following two file formats are supported:
• STIL format (Only IEEE 1450.99 version) for scan test vectors (Stuck-At fault model or Transition Delay fault model), generated by an ATPG after scan insertion. The STIL file format also supports the specific keyword IddqTestPoint, generated by the appropriate IDDQ tool, to generate the corresponding Iddq measurements in the test program.
• VECT-TIMSET format (VCD or EVCD file format translated by TVT into two files .vect and .timset) for functional test vectors or BIST. This is a Microchip proprietary file format, which consists of two files. Both VECT and TIMSET files must be identified in TECT to make one test pattern.
Useful TECT buttons for the Patterns tab:
• Scan Dir: Scans for all patterns (simulation results) present in a given directory. • Browse: Opens directories to find and select pattern files. • Preserve STIL scan chains: (only for STIL patterns), can be used if the target tester supports the scan chain
feature.
The customer is responsible for the global product test coverage. When the test coverage of a pattern is known, you must provide it in the Coverage field of the pattern.
Some other possibilities are supported, see the TECT User Manual.
3.1 VCD Rules Most testers have limitations in terms of Tsets and Fsets. The product designer must follow the recommendations (Best practices) to avoid the excessive use of Tsets and Fsets:
Best Practice 1:
Input signals: Ensure that all input events (transitions driven by the ATE) change state at the same relative time with respect to the beginning of the test cycles, which must be periodic over all your simulation.
Note: TDF (for Transition Delay Fault detection) patterns (usually in .stil format, not .vcd) do not follow this rule.
Best Practice 2:
Clock signals: Avoid setting active clock edges at the very beginning (time 0) or very end of test cycles. The chronologic scheme must always be:
1. Initializing the data signals first (ideally at the very beginning of the cycle). 2. Then the active clock-edge. However, try to keep it in the first half of the cycle to limit the best case/worst case
differences due to timing delay increases.
Test Patterns
Manual DS50003170A-page 15
Best Practice 3:
Bidir signals: Always make a bidir pin tristate (drive Z) mode (at the same time as inputs) when switching direction from input to output. For instance, drive a Z state at 5.0 ns, if the other input pins are changing at 5.0 ns. There is not such restriction on the strobe time.
Best Practice 4:
Bidir signals: Always make a bidirectional bus to switch direction all together (all bits of the bus at the same time) from input to output, or vice-versa. This is to reduce the number of format sets reserved by the tester.
Best Practice 5:
Never simulate with pull-up/pull-down models. On-chip pulls are too weak and test board is not equipped with any resistor. This leads to errors during test.
TVT checks the rules so that testing your product is possible on every available tester.
Input timings and output strobes are controlled by customer simulation testbench. The customer generates waveforms that are suitable to meet the required functionality and fault coverage.
3.2 Patterns Order Even if TECT tracks the patterns order, ensure that the test program does not execute them in a totally different order depending on the test flow. For example, patterns used by AC tests are executed multiple times at different moments of the test flow.
To avoid side effects due to pattern order execution, each pattern must begin by a reset sequence, which guarantees that DUT is in a stable state before the test execution.
There is no constraint on pattern length (vector count). But for any reason, a pattern has to be split into multiple sub-patterns, the reset sequence is mandatory only on the first part.
Execution order of different patterns must be specified in TECT in the comment field attached to the pattern. As a result, DC and AC tests cannot be done on sub-patterns due to the lack of the reset sequence.
Test Patterns
Manual DS50003170A-page 16
4. Tests Tab TECT contains three different categories under the Tests tab: DC Tests, AC Tests, and Idd.
4.1 DC Tests The aim of DC tests is to perform all possible static DC measurements to confirm that the DC specifications are addressed. The goal is 100% coverage in all possible configurations. A recommended practice is to build only one dedicated DC Tests functional simulation to perform all DC tests.
SCAN or TDF simulations in STIL format, are not suitable for DC test measurements. Simulations requiring 4x mode usage are also not suitable for DC test.
DC tests must be performed on all external pins of the product, in all possible configurations. DC tests of SCAN in and SCAN out pins can be performed by a serial shift test of the sequence 00110011 (usually provided as the first scan chain sanity check). This validation must be provided as part of a DC tests dedicated functional simulation.
DC tests pattern(s) requires a specific simulation built where all internal control ports must be traced in the .vcd file. The TVT setup must be setup (using a specific flag) accordingly to translate the state of these internal nodes into the output VECT-TIMSET files. It is also recommended to unset this flag for the remaining patterns (those that are not used for DC tests).
In some cases, the configuration requirement may be difficult to satisfy, but it is the designer’s responsibility to achieve the best DC Tests coverage (ideally 100%). The report file dctReport.txt is provided to help finding the missing states or conditions for each signal. A detailed explanation is required for all signals that do not fulfill this DC test requirement.
The difficulty occurs especially with configurable I/O cells (see the next chapter 4.1.2), which have multiple control ports. To meet the 100% coverage requirement for DC test, all possible combinations of the control ports must be exercised during the simulation. The waveforms of these internal signals must be translated by TVT into Microchip VECT format, so the Test Program Generator can find the required conditions for DC tests.
4.1.1 Bidirectional Ports The drive direction of the bidirectional ports is defined by their bidirectional I/O buffer control signal, usually an internal signal. As mentioned, the tester is unable to both drive and sample within a given cycle. Therefore, control signals must be monitored during the test vector generation whether they are internal signals or external inputs to the design. When none of the external ports can indicate the status of the bidirectional I/O control signals at each time, the control signals must be brought out to the testbench level through creating virtual output ports in the top-level of the design and connect the control signals to the ports. The control signal can then be read and monitored in the testbench level for test vector generation.
4.1.2 Configurable Cells The configurable I/O cells (also called programmable buffers) include amongst other:
• A switchable pull-up resistor • A switchable pull-down resistor • Selectable drive strengths for output
in addition to a direction control for bidirectional port and a tri-state control, and possibly more. Consequently, the number of control ports may be quite high. All configuration modes must be exercised for each specific buffer.
All internal control signals must be present in the simulation results (monitored in Verilog VCD files), except those that are permanently tied to logical level high or low. In addition, all these internal ports must be switched to their different states in the DC test simulation, because DC tests require these setups to perform the corresponding measurements.
4.2 AC Tests – Dynamic Timing Measurements It is possible to generate a test program with automatic inclusion of AC test measurements, such as propagation delay time, setup time, and hold time. These measurements are detailed in the P file format specification. Read this specification to see the requirements for these measurements.
Tests Tab
Manual DS50003170A-page 17
TECT provides a simple method to define these AC tests with all the required data. See the TECT User Manual for more information about the fields of the user interface.
4.2.1 ATE Limitations As not all testers are equipped with a specific timing measurement unit, the generic test method is to get an indirect measure by moving edges placement (search method). This method may consume a lot of tester timing resources. As these resources are limited, the number of AC tests must be reduced to a minimal set. A good practice is to limit the number of timing measurements to less than 10 or 15.
4.2.2 AC Tests Range AC tests can be performed on three different modes:
• Single: AC test is performed only once at a given time. • Range: AC test is performed several times between the start and the stop time. The worst case is reported. • All: AC test is performed along the whole selected pattern (from time 0 to the end of pattern).
Note: The Event Position parameter must be specified in absolute time values (relative to time 0 of the simulation) for the Test Range Single, but specified in relative values (relative to the beginning of current test cycle) for other Test Range modes.
If the AC tests have already been defined in the .P0 file, the button Import P0 must be used to load them into TECT. Also, you can create the AC tests by clicking the Add button
Depending on the type of AC test, there are three possible signals:
• R (Reference signal—always an input), always used as base for measurements • D (Data signal—always an input) • O (Output signal—strobe time)
A propagation delay measurements (TP) uses only R and O. The tester is moving O strobe (search feature) towards R as long as O satisfies the expected state. The measured timing is recorded when O fails.
A setup time (TS) or a hold time (TH) measurement is performed by moving the transition event of D (driven input) towards R as long as O satisfies the expected state. The measured setup or hold time is recorded when O fails.
The differential propagation delay allows to compute the difference between two AC tests results. Obviously, the two corresponding AC tests must be defined first.
Click Check all to verify that the AC Tests are correctly defined and check for the appropriate signal transitions in the given pattern.
If a range (measurement between specified start and stop time) is selected, ensure that for the same set of signals, there cannot be overlaps of two different AC tests ranges in the same pattern.
4.3 Idd Tests – StandBy, Dynamic, or Iddq Current Measurements The Idd Tests can be:
• StandBy Idd for standby mode current measurements. • Dynamic Idd operating current measurement in application mode (≥ 100 samples). • Iddq measurement mode for predefined quiescent current measurement points.
TECT provides the appropriate setup for all Idd test types under the Idd tab. Idd measurements can be setup in TECT for automatic test generation with the MTPG.
4.3.1 StandBy Current StandBy Idd must be measured at a given time, at which the product is put in quiescent (or sleep) mode. It requires to indicate the pattern to use and the appropriate time for this measurement.
If the StandBy current test is to be performed, a simulation must exist that includes a vector suitable for this test. Such a simulation can be any simulation intended for a functional test. Ensure that the goal is to measure as less current as possible. So, the presence of a pull-up or a pull-down resistor must be considered in the measurement
Tests Tab
Manual DS50003170A-page 18
current estimation. It is recommended that ports with pull-down resistor are set low and ports with pull-up resistor are set high on the chosen test vector. In addition, all static current sources must be disabled.
4.3.2 Dynamic Current The operating Idd current measurement must be performed by specifying a functional pattern (typical product usage in an application) and a time interval (from time – to time) during which the tester samples a series of measurements. To obtain a good accuracy, the tester tries to perform at least 100 measurements in the given time interval. TECT displays an error, if this requirement is not met.
4.3.3 Iddq Current The Iddq measurements can automatically be generated if a .stil file is provided with the appropriate statements in it. The required statement is IddqTestPoint, and there must be at least one of them in the STIL file. In addition, you must specify the STIL pattern for Iddq usage in TECT in the Patterns tab, by selecting IDDQ.
Note: This feature communicates to the test program generator (MTPG) to include Iddq measurements, but there is no corresponding consequences like binning. As a result, only values of the current measurement is reported. If necessary, the limits and consequences must be added manually in the program later on.
If several Idd measurements must be done, it is required to setup as many Idd Tests as necessary. Each Idd Test has a unique user configurable name.
Tests Tab
Manual DS50003170A-page 19
5. TECT Completion
5.1 Checks TECT provides a powerful built-in verifier that checks many possible issues. The various checks that are performed are given on the following pages in the section TECT Rules.
5.1.1 Complete Check It is mandatory to perform a complete check by selecting the Check All button in this tab. After verification, save the error log file by clicking the Report button.
The online checker looks for errors interactively. A red minus sign is shown on the tab button until all errors are fixed. It is mandatory to fill in all the highlighted empty fields. Click on the light red area, then update the field by selecting an item in the list presented on the right pane, or by typing the name of the internal signal.
5.2 Save The Save or Save As buttons are used to save the changes made during the TECT session. It generates files with the .tect and .tpc extensions, which can be read to retrieve the saved TECT session.
5.3 Archive The Archive tab can be used to build a database file to be transferred. A zip compression option is used to reduce the size of the archive file.
5.3.1 Pack The Pack command on the left pane is used to build a package of the required files to transfer to the Microchip Technical Center. This command is available only when all reported errors have been fixed. The revision number of the package is automatically incremented at each time it is called.
• A window is presented in which it is required to select the appropriate patterns to add to the package (for transfer).
• Optionally, a Comment field is provided to additional details of the package. • The database is a compressed tarball with the .ttz extension. This file must be sent to Microchip Technical
Center.
TECT provides a built-in FTP client, which may be used to send the TTZ file. For security purposes, this FTP client can optionally encrypt the file during transfer.
TECT Completion
Manual DS50003170A-page 20
6. TECT Rules This list is non-exhaustive and can be updated as required. It is a list of rules that derive both from tester constraints and limitations and from Microchip’s recommendations.
Product Description:
• Supply nets, Signals, and Bonding tabs must be free of errors (existence, consistency). • X and Y coordinates may be omitted at first (Warning), but it is turned into an error at the final verification stage.
Signal Groups:
Test Patterns:
• VECT-TIMSET file format is allowed (Verilog simulations processed by TVT). • STIL file format is allowed, when the IEEE 1450.99 standards are followed. • All signals must be declared in patterns, including LVDS voltage reference. • For a Cohu D10 tester, the minimum test cycle period is 10 ns. The test cycle period may violate these values,
then TECT is able to check if the special 4x Mode may be used. Indeed, this 4x Mode has a number of additional constraints (indicated below) as it consists of building one test vector with two existing test vectors.
4x Mode Algorithm:
• This mode is available for VECT-TIMSET patterns (from TVT) only, as it is completely dependent on TVT generated waveforms.
• The pattern period is multiplied by 2. • The vectors are grouped by 2, therefore, it increases the number of transition edges in the waveforms of the
resulting vector (up to four transitions instead of two in the same test vector). For outputs, this may lead to strobe twice in the same test vector.
Additional constraints related to this 4x mode:
• The number of vectors in each TIMSET must be an even number. If necessary, an extra vector must be added to match this requirement.
• A limited number of waveform combinations is supported: – NRZ: 0/0, 1/1, 1/0, 0/1 – RTZ: 0/0, U/0, 0/U, U/U – RTO: 1/1, D/1, 1/D, D/D – Strobe: L/L, H/H, H/L, L/H, X/X, X/L, L/X, X/H, H/X
Bidirectional signals support the following additional combinations:
X/0, 0/X, X/1, 1/X, X/U, U/X, X/D, D/X
Any other combination is not allowed.
• The bidirectional switching is only allowed on odd vectors, except if there is an X in the switch sequence (0/L disallowed, 0/X/L allowed)
LVDS checks:
• Input and output pairs must be identified • Voltage Reference (VREF) inputs must be identified • DC coverage on output pairs must reach 100%. These tests include VOL_p/VOH_p and VOH_n/VOL_n on each
output pair. If 100% is not accomplished, a good reason with arguments must be provided.
DC Tests:
• DC Tests cannot be performed on STIL patterns. • The patterns selected for DC tests must be made of static vectors. • A single dedicated pattern for DC tests is recommended. • If DC Tests coverage does not reach 100%, a good reason with arguments must be provided.
TECT Rules
Manual DS50003170A-page 21
AC Tests:
In AC Tests measurements, the tester loops over a given pattern and performs a series of measurements on the same test cycle as long as it is necessary to find the worst case delay.
It is recommended using the AC builder button for creating AC tests. This ensures that all rules and constraints are met. It analyses your simulations and checks for the required conditions for the given AC Test to be performed, alerts, if the AC test can be performed or not, and fills the appropriate information.
In the following rules, the used terminology is listed:
• TG – Timing Generator: A tester hardware element, which accurately controls event transitions of input signals (stimuli) and output strobe time (sampling).
• R – Reference: The reference event for the measurement. It must be an input signal. • D – Data: is an input data, always an input signal. • O – Output: An output data, a strobe to an output signal. • R, D and O: A single or a group of signals (usually a bus). In this case, all signals of the same group must share
the same TG. • Range or Test Range: Time interval in which the measurement will be done. By default, the measurement is
performed in a single test cycle (Single mode). • TP or Propagation Delay: Indicates the type of measurement. • TS or Setup Time: Indicates a Setup Time Measurement. • TH or Hold Time: Indicates a Hold Time Measurement.
Rules for AC Tests:
• AC tests can only be performed on VECT - TIMSET patterns, not on STIL patterns. • Rules (per test):
– For each signal (R, D, or O), the defined events must exist (the transition edge direction and the exact timing information).
– For propagation delay measurement, the O signal must only depend on the R signal within the whole Range.
– For hold and setup time measurements, the O signal must only depend on D signal within the whole Range.
– If the Test range button is set to Single: • Do not select Group for the R signal as all signals must share the same TG. • Do not select Any edge type for the R signal as the edge type of a single signal on a single vector is
known (to be specified). • Do not select Group for the D signal as all signals must share the same TG. • Do not select Any edge type for the D signal as the edge type of a single signal on a single vector is
known (to be specified). • If the O signal is a group signal, all signal states of the given group must switch in the test cycle. If
some signals do not switch, consider removing them from the group. • If the O signal is a group signal and all signals have the same edge type, do not use Any as edge
type, but indicate the actual edge type. • R/O events for TP must occur within the same test cycle • R/D events for TS or TH must occur within the same cycle.
– If the Test range button is set to Range or All, • The relative edge position (within the cycle) must remain the same within the whole range.
• Rules and constraints when multiple tests are declared: – Two tests cannot be done on the same vector, if the same data or output signals are involved.
Dynamic Idd Tests:
• Dynamic Idd Tests cannot be done on STIL patterns. • Time range for dynamic Idd tests must be wide enough to allow at least 100 samples. • The tester minimal sampling rate is 4 µs (on D10) or 20 µs (on Sapphire).
TECT Rules
Manual DS50003170A-page 22
Additional checks:
• Number of available I/Os and powers on tester must match the product definition. • Number of scan chains must not exceed tester capability. • Pattern Memory consumption must not exceed tester capability.
TECT Rules
Manual DS50003170A-page 23
7. Appendix
7.1 Simultaneous Switching Outputs Noise voltages in test equipment can sometimes be increased by many simultaneously switching outputs (SSO). To avoid triggering unintended device state changes, the number of SSOs in vector files must be minimized. Customers can reduce the number of SSOs during the test by avoiding unnecessary output switching. This can be done by controlling the enable signals to disable the unnecessary sections of the design. Note: The test vectors are usually generated to stimulate specific nodes or specific areas of the design.
7.2 Vref Pins Vref external pins must be present in the netlist, so that TVT uses them to generate the vectors and they are checked against opens, shorts, and ESD.
It is recommended to maintain a logic 1 on these pins during simulation. The appropriate level is manually set by the test engineer. For MH1 library, the Vref pin must be declared as Tristate-Output (O/Z), and an X state must be applied during simulation. For other libraries, it must be declared as Input (I) and a level 1 must be applied during simulation.
7.3 DFT and Coverage The customer must demonstrate a design style and a design-for-test (DFT) methodology that, along with CAD for test tools, can provide 99% or greater fault coverage on a design of reasonable complexity. To achieve this, all available techniques can be used (Functional tests, At-Speed tests, ATPG = DFT scan, TDF = Transition Delay Fault tests, and so on).
Objectives are to reach at least a test coverage of 80% for Transition Delay Fault (TDF) and 98% for stuck-at SCAN. As these values maybe unreachable due to design complexity or ATE limitations, these objectives may be lowered during the Design Review (DR).
DFT tests and full scan ATPG tests implementation may induce physical phenomena such as voltage drop and high power consumption, and it may lead to discrepancies in test results. To address this possible problem, it is recommended to apply the appropriate specific techniques to minimize the simultaneous internal switching during scan tests.
Appendix
Manual DS50003170A-page 24
8. Conclusion The test strategy of the future circuits must be defined very early during the design phase. It is recommended to contact the Technical Center to introduce the test constraints in the design, as soon as possible.
Conclusion
Manual DS50003170A-page 25
9. Revision History Revision Date Description
A 06/2021 The following sections are updated: • Replaced Atmel references by Microchip. • Remove reference to Sapphire tester. • Added reference to MCC oven. • Corrected some typos.
4.4 03/2017 Corrected an erroneous note about how to drive Lvds inputs in simulations and some typos.
4.3 01/2017 The following sections were updated: • Add patterns order and reset recommendations. • Restrict 4X simulations usage for DC tests.
4.2 01/2016 The following sections were updated: • Precision on 4X mode. • Add references on external specifications (Burn-In)
4.1 01/2016 Precision on scan test coverage.
4.0.0 06/2015 The following sections were updated: • Revision of the ASIC Test Manual • Apply now to all Atmel Aerospace libraries • Added new TECT features (Burn-In, Iddq)
3.0.0 01/2015 The following sections were updated: • Introduce TECT as mandatory tool • Table of contents has strongly changed
2.9.1 01/2014 Precision on test coverage responsibilities
2.9 02/2012 Tester support, Dynamic tests updates and limitations
2.8 04/2011 ADBI not authorized
2.7 04/2011 Changed ref. to ATD-DE-GR-R0324.
2.6 04/2011 Added AC Test Description
2.5 03/2011 Recommendation added for customer responsibilities.
2.4 11/2010 Test Guide is now separated from the design guide. It is updated for TVT support, TPG and tester limitations
2.3 02/2010 Add SET mitigation in chapter 4 Design Rules
2.2 04/2008 LVDS buffer enable
2.1 03/2008 The following sections were updated: • ATPG sim • Remove 1% failing patterns
2.0 07/2007 Remove 1.8v Buffers and Add 2.5v Buffers
1.2 06/2006 SRAM/DPRAM/TPRegister read write cycles
Revision History
Manual DS50003170A-page 26
1.1 04/2006 The following sections were updated: • ESD protection considerations • Double pad ring considerations • Spare cells percentage StarRCXT • Replaces HypeExtract & Fire&Ice ADBI paragraph removed
1.0 03/2005 The following sections were updated: • Updated the timing specification • Updated the genesys input desc.
0.3 Pre-production 12/2004 The following sections are updated: • Design Management • Power Rules • TOS Rules
0.2 Beta 05/2004 Hardware considerations
0.1 Beta 03/2004 Initial Version
Revision History
Manual DS50003170A-page 27
The Microchip Website
Microchip provides online support via our website at www.microchip.com/. This website is used to make files and information easily available to customers. Some of the content available includes:
• Product Support – Data sheets and errata, application notes and sample programs, design resources, user’s guides and hardware support documents, latest software releases and archived software
• General Technical Support – Frequently Asked Questions (FAQs), technical support requests, online discussion groups, Microchip design partner program member listing
• Business of Microchip – Product selector and ordering guides, latest Microchip press releases, listing of seminars and events, listings of Microchip sales offices, distributors and factory representatives
Product Change Notification Service
Microchip’s product change notification service helps keep customers current on Microchip products. Subscribers will receive email notification whenever there are changes, updates, revisions or errata related to a specified product family or development tool of interest.
To register, go to www.microchip.com/pcn and follow the registration instructions.
Customer Support
Users of Microchip products can receive assistance through several channels:
• Distributor or Representative • Local Sales Office • Embedded Solutions Engineer (ESE) • Technical Support
Customers should contact their distributor, representative or ESE for support. Local sales offices are also available to help customers. A listing of sales offices and locations is included in this document.
Technical support is available through the website at: www.microchip.com/support
Microchip Devices Code Protection Feature
Note the following details of the code protection feature on Microchip devices:
• Microchip products meet the specifications contained in their particular Microchip Data Sheet. • Microchip believes that its family of products is secure when used in the intended manner and under normal
conditions. • There are dishonest and possibly illegal methods being used in attempts to breach the code protection features
of the Microchip devices. We believe that these methods require using the Microchip products in a manner outside the operating specifications contained in Microchip’s Data Sheets. Attempts to breach these code protection features, most likely, cannot be accomplished without violating Microchip’s intellectual property rights.
• Microchip is willing to work with any customer who is concerned about the integrity of its code. • Neither Microchip nor any other semiconductor manufacturer can guarantee the security of its code. Code
protection does not mean that we are guaranteeing the product is “unbreakable.” Code protection is constantly evolving. We at Microchip are committed to continuously improving the code protection features of our products. Attempts to break Microchip’s code protection feature may be a violation of the Digital Millennium Copyright Act. If such acts allow unauthorized access to your software or other copyrighted work, you may have a right to sue for relief under that Act.
© 2021 Microchip Technology Inc. and its subsidiaries
Manual DS50003170A-page 28
Legal Notice
Information contained in this publication is provided for the sole purpose of designing with and using Microchip products. Information regarding device applications and the like is provided only for your convenience and may be superseded by updates. It is your responsibility to ensure that your application meets with your specifications.
THIS INFORMATION IS PROVIDED BY MICROCHIP “AS IS”. MICROCHIP MAKES NO REPRESENTATIONS OR WARRANTIES OF ANY KIND WHETHER EXPRESS OR IMPLIED, WRITTEN OR ORAL, STATUTORY OR OTHERWISE, RELATED TO THE INFORMATION INCLUDING BUT NOT LIMITED TO ANY IMPLIED WARRANTIES OF NON-INFRINGEMENT, MERCHANTABILITY, AND FITNESS FOR A PARTICULAR PURPOSE OR WARRANTIES RELATED TO ITS CONDITION, QUALITY, OR PERFORMANCE.
IN NO EVENT WILL MICROCHIP BE LIABLE FOR ANY INDIRECT, SPECIAL, PUNITIVE, INCIDENTAL OR CONSEQUENTIAL LOSS, DAMAGE, COST OR EXPENSE OF ANY KIND WHATSOEVER RELATED TO THE INFORMATION OR ITS USE, HOWEVER CAUSED, EVEN IF MICROCHIP HAS BEEN ADVISED OF THE POSSIBILITY OR THE DAMAGES ARE FORESEEABLE. TO THE FULLEST EXTENT ALLOWED BY LAW, MICROCHIP'S TOTAL LIABILITY ON ALL CLAIMS IN ANY WAY RELATED TO THE INFORMATION OR ITS USE WILL NOT EXCEED THE AMOUNT OF FEES, IF ANY, THAT YOU HAVE PAID DIRECTLY TO MICROCHIP FOR THE INFORMATION. Use of Microchip devices in life support and/or safety applications is entirely at the buyer’s risk, and the buyer agrees to defend, indemnify and hold harmless Microchip from any and all damages, claims, suits, or expenses resulting from such use. No licenses are conveyed, implicitly or otherwise, under any Microchip intellectual property rights unless otherwise stated.
Trademarks
The Microchip name and logo, the Microchip logo, Adaptec, AnyRate, AVR, AVR logo, AVR Freaks, BesTime, BitCloud, chipKIT, chipKIT logo, CryptoMemory, CryptoRF, dsPIC, FlashFlex, flexPWR, HELDO, IGLOO, JukeBlox, KeeLoq, Kleer, LANCheck, LinkMD, maXStylus, maXTouch, MediaLB, megaAVR, Microsemi, Microsemi logo, MOST, MOST logo, MPLAB, OptoLyzer, PackeTime, PIC, picoPower, PICSTART, PIC32 logo, PolarFire, Prochip Designer, QTouch, SAM-BA, SenGenuity, SpyNIC, SST, SST Logo, SuperFlash, Symmetricom, SyncServer, Tachyon, TimeSource, tinyAVR, UNI/O, Vectron, and XMEGA are registered trademarks of Microchip Technology Incorporated in the U.S.A. and other countries.
AgileSwitch, APT, ClockWorks, The Embedded Control Solutions Company, EtherSynch, FlashTec, Hyper Speed Control, HyperLight Load, IntelliMOS, Libero, motorBench, mTouch, Powermite 3, Precision Edge, ProASIC, ProASIC Plus, ProASIC Plus logo, Quiet-Wire, SmartFusion, SyncWorld, Temux, TimeCesium, TimeHub, TimePictra, TimeProvider, WinPath, and ZL are registered trademarks of Microchip Technology Incorporated in the U.S.A.
Adjacent Key Suppression, AKS, Analog-for-the-Digital Age, Any Capacitor, AnyIn, AnyOut, Augmented Switching, BlueSky, BodyCom, CodeGuard, CryptoAuthentication, CryptoAutomotive, CryptoCompanion, CryptoController, dsPICDEM, dsPICDEM.net, Dynamic Average Matching, DAM, ECAN, Espresso T1S, EtherGREEN, IdealBridge, In-Circuit Serial Programming, ICSP, INICnet, Intelligent Paralleling, Inter-Chip Connectivity, JitterBlocker, maxCrypto, maxView, memBrain, Mindi, MiWi, MPASM, MPF, MPLAB Certified logo, MPLIB, MPLINK, MultiTRAK, NetDetach, Omniscient Code Generation, PICDEM, PICDEM.net, PICkit, PICtail, PowerSmart, PureSilicon, QMatrix, REAL ICE, Ripple Blocker, RTAX, RTG4, SAM-ICE, Serial Quad I/O, simpleMAP, SimpliPHY, SmartBuffer, SMART-I.S., storClad, SQI, SuperSwitcher, SuperSwitcher II, Switchtec, SynchroPHY, Total Endurance, TSHARC, USBCheck, VariSense, VectorBlox, VeriPHY, ViewSpan, WiperLock, XpressConnect, and ZENA are trademarks of Microchip Technology Incorporated in the U.S.A. and other countries.
SQTP is a service mark of Microchip Technology Incorporated in the U.S.A.
The Adaptec logo, Frequency on Demand, Silicon Storage Technology, and Symmcom are registered trademarks of Microchip Technology Inc. in other countries.
GestIC is a registered trademark of Microchip Technology Germany II GmbH & Co. KG, a subsidiary of Microchip Technology Inc., in other countries.
All other trademarks mentioned herein are property of their respective companies. © 2021, Microchip Technology Incorporated, Printed in the U.S.A., All Rights Reserved.
ISBN: 978-1-5224-8503-2
Manual DS50003170A-page 29
© 2021 Microchip Technology Inc. and its subsidiaries
Manual DS50003170A-page 30
Australia - Sydney Tel: 61-2-9868-6733 China - Beijing Tel: 86-10-8569-7000 China - Chengdu Tel: 86-28-8665-5511 China - Chongqing Tel: 86-23-8980-9588 China - Dongguan Tel: 86-769-8702-9880 China - Guangzhou Tel: 86-20-8755-8029 China - Hangzhou Tel: 86-571-8792-8115 China - Hong Kong SAR Tel: 852-2943-5100 China - Nanjing Tel: 86-25-8473-2460 China - Qingdao Tel: 86-532-8502-7355 China - Shanghai Tel: 86-21-3326-8000 China - Shenyang Tel: 86-24-2334-2829 China - Shenzhen Tel: 86-755-8864-2200 China - Suzhou Tel: 86-186-6233-1526 China - Wuhan Tel: 86-27-5980-5300 China - Xian Tel: 86-29-8833-7252 China - Xiamen Tel: 86-592-2388138 China - Zhuhai Tel: 86-756-3210040
India - Bangalore Tel: 91-80-3090-4444 India - New Delhi Tel: 91-11-4160-8631 India - Pune Tel: 91-20-4121-0141 Japan - Osaka Tel: 81-6-6152-7160 Japan - Tokyo Tel: 81-3-6880- 3770 Korea - Daegu Tel: 82-53-744-4301 Korea - Seoul Tel: 82-2-554-7200 Malaysia - Kuala Lumpur Tel: 60-3-7651-7906 Malaysia - Penang Tel: 60-4-227-8870 Philippines - Manila Tel: 63-2-634-9065 Singapore Tel: 65-6334-8870 Taiwan - Hsin Chu Tel: 886-3-577-8366 Taiwan - Kaohsiung Tel: 886-7-213-7830 Taiwan - Taipei Tel: 886-2-2508-8600 Thailand - Bangkok Tel: 66-2-694-1351 Vietnam - Ho Chi Minh Tel: 84-28-5448-2100
Austria - Wels Tel: 43-7242-2244-39 Fax: 43-7242-2244-393 Denmark - Copenhagen Tel: 45-4485-5910 Fax: 45-4485-2829 Finland - Espoo Tel: 358-9-4520-820 France - Paris Tel: 33-1-69-53-63-20 Fax: 33-1-69-30-90-79 Germany - Garching Tel: 49-8931-9700 Germany - Haan Tel: 49-2129-3766400 Germany - Heilbronn Tel: 49-7131-72400 Germany - Karlsruhe Tel: 49-721-625370 Germany - Munich Tel: 49-89-627-144-0 Fax: 49-89-627-144-44 Germany - Rosenheim Tel: 49-8031-354-560 Israel - Ra’anana Tel: 972-9-744-7705 Italy - Milan Tel: 39-0331-742611 Fax: 39-0331-466781 Italy - Padova Tel: 39-049-7625286 Netherlands - Drunen Tel: 31-416-690399 Fax: 31-416-690340 Norway - Trondheim Tel: 47-72884388 Poland - Warsaw Tel: 48-22-3325737 Romania - Bucharest Tel: 40-21-407-87-50 Spain - Madrid Tel: 34-91-708-08-90 Fax: 34-91-708-08-91 Sweden - Gothenberg Tel: 46-31-704-60-40 Sweden - Stockholm Tel: 46-8-5090-4654 UK - Wokingham Tel: 44-118-921-5800 Fax: 44-118-921-5820
Worldwide Sales and Service
Manual DS50003170A-page 31
1.1.2. TECT Overview
1.2. TOS Guidelines
2.3. TECT Startup
2.4. TECT Tabs
2.5. TECT Flow
2.8. Test Prep Flow
3. Test Patterns
3.1. VCD Rules
3.2. Patterns Order
4. Tests Tab
4.1. DC Tests
4.1.1. Bidirectional Ports
4.1.2. Configurable Cells
4.2.1. ATE Limitations
4.3.1. StandBy Current
4.3.2. Dynamic Current
4.3.3. Iddq Current
5. TECT Completion
Legal Notice