Ashley Lyon CGSIC May 7th 2006 European Satellite Services Provider “EGNOS Operations Status”

19
Ashley Lyon CGSIC May 7th 2006 European Satellite Services Provider “EGNOS Operations Status”

Transcript of Ashley Lyon CGSIC May 7th 2006 European Satellite Services Provider “EGNOS Operations Status”

Page 1: Ashley Lyon CGSIC May 7th 2006 European Satellite Services Provider “EGNOS Operations Status”

Ashley Lyon CGSIC

May 7th 2006

European Satellite Services Provider “EGNOS Operations Status”

Page 2: Ashley Lyon CGSIC May 7th 2006 European Satellite Services Provider “EGNOS Operations Status”

May 8th 2006EGNOS Operations StatusPage 2

ESSP in EGNOS

• A centralized management entity for EGNOS: ESSP

• ESSP has been created from a subset of the EOIG (EGNOS Operators and Infrastructure Group)

• ESSP has been founded to become theEGNOS OperatorEGNOS Safety of Life Service Provider, for example for Civil Aviation

Page 3: Ashley Lyon CGSIC May 7th 2006 European Satellite Services Provider “EGNOS Operations Status”

May 8th 2006EGNOS Operations StatusPage 3

EGNOS Operations Consortium

MCC Operations

EGNOSOperations

Management

RIMS Operations

PACF Operations Training Services

Other OperationsServices

Support FacilityOperations

NLES Operations

Torrejon MCC

Langen MCC

Ciampino MCC

Swanwick MCC

AENA RIMSCanary Is., Malaga,

Palma, Santiago

CNESParis,

Hartebeeshoek,Kourou

DFSBerlin

ENAVCatania, Ciampino

TelespazioFucinoNLES

TelespazioScanzano

NLES

AENATorrejonNLES

ASQF Operations

SkyguideZurich

NATSSwanwick and

Glasgow

Logistics ServicesDFS

Page 4: Ashley Lyon CGSIC May 7th 2006 European Satellite Services Provider “EGNOS Operations Status”

May 8th 2006EGNOS Operations StatusPage 4

Jan 2005 Jan 2007 Jan 2006

System Evolutions

System Development

System Operations System Initial Operations

EGNOS Timeline

Page 5: Ashley Lyon CGSIC May 7th 2006 European Satellite Services Provider “EGNOS Operations Status”

May 8th 2006EGNOS Operations StatusPage 5

Jan 2005 Jan 2007

Open Service

Commercial Services

SoL Service

Jan 2006

System Evolutions

System Development

System Operations

System and Application Certification ( Safety Case)

System Initial Operations

EGNOS Services

Page 6: Ashley Lyon CGSIC May 7th 2006 European Satellite Services Provider “EGNOS Operations Status”

May 8th 2006EGNOS Operations StatusPage 6

Jan 2005 Jan 2007 Jan 2006

System Initial Operations

Initial Operations

ORR ODR

Operationsperformance

OQR

Ramp- upStabilization

Op. QualificationESA Reqt

Δ ESA Reqt

Δ ESA Reqt

Page 7: Ashley Lyon CGSIC May 7th 2006 European Satellite Services Provider “EGNOS Operations Status”

May 8th 2006EGNOS Operations StatusPage 7

Start of EGNOS operationsby the ESSP Operation Consortium

•Increase of staff and resources to fully support EGNOS operations

•Facilitate the transfer of knowledge and experience from ESA / Industry to Operator

•Test the operations processes and procedures

•Deliver remaining training packages to build up team capabilities

Initial Operations Ramp-up

Page 8: Ashley Lyon CGSIC May 7th 2006 European Satellite Services Provider “EGNOS Operations Status”

May 8th 2006EGNOS Operations StatusPage 8

Reach nominal EGNOS operations performance (started on April 3rd

2006)

•Stabilise team resource profiles, to support EGNOS operations according to the operations performance requirements

•Run nominal maintenance procedures across the EGNOS system

•Complete operations processes and procedure testing

Initial Operations Stabilization

Page 9: Ashley Lyon CGSIC May 7th 2006 European Satellite Services Provider “EGNOS Operations Status”

May 8th 2006EGNOS Operations StatusPage 9

Operational qualification of EGNOS system operations

•Demonstrate that EGNOS operations staff, plus procedures and documentation, can support EGNOS operations performances

•Provide evidence towards the EGNOS System Safety Case with nominal operations

•Concludes with the Operations Qualification Review (OQR) in early 2007

•Safety of Life service provision planned to follow this milestone

Initial Operations Qualification

Page 10: Ashley Lyon CGSIC May 7th 2006 European Satellite Services Provider “EGNOS Operations Status”

May 8th 2006EGNOS Operations StatusPage 10

6 NLESNavigation Land Earth

Stations

EGNOS SitesGPS &

GLONASS

34 RIMSRanging &Integrity

Monitoring Stations

User Segment

4 MCCMission Control Centers

3 Satellites EGNOS

EWAN EGNOS Wide Area Network

2 Support Facilities

Page 11: Ashley Lyon CGSIC May 7th 2006 European Satellite Services Provider “EGNOS Operations Status”

May 8th 2006EGNOS Operations StatusPage 11

EGNOS system handover

•Full handover of the EGNOS system did not take place at ORR

A subset of the EGNOS system was provided to EGNOS industry

1 CPF, 1 CCF, 3 RIMS (Paris, Toulouse, Lappeenranta), 2 NLES

EGNOS industry retained IOR-W (PRN 126)ESTB was continued using AOR-E (PRN 120)EGNOS was broadcasting on ARTEMIS (PRN 124) only

1 NLES only due to technical problem with other NLES Remaining subset of RIMS 3 CPFs with numerous stability problems

Page 12: Ashley Lyon CGSIC May 7th 2006 European Satellite Services Provider “EGNOS Operations Status”

May 8th 2006EGNOS Operations StatusPage 12

Recent changes

•PRN 120 - AOR-EESTB operating continuously since 09/06/05Will be used for EGNOS SIS operations as from early July

2006

•PRN 124 – ARTEMISOperated by ESSP consortium since 26/07/2005Software version 0.4.9 currently being broadcast since

December 2005Swap with PRN 126 mid June 2006 for operations mid July

2006

•PRN 126 – IND-W Swap with PRN 126 mid June 2006 for industrial testing

mid July 2006 Limited transmissions over recent months with long

periods of inactivity

Page 13: Ashley Lyon CGSIC May 7th 2006 European Satellite Services Provider “EGNOS Operations Status”

May 8th 2006EGNOS Operations StatusPage 13

System Releases

New release 2.0.2 as from mid June 2006

Another planned at the end of the year to solve CPF common mode failures

Page 14: Ashley Lyon CGSIC May 7th 2006 European Satellite Services Provider “EGNOS Operations Status”

May 8th 2006EGNOS Operations StatusPage 14

SIS Availability

Page 15: Ashley Lyon CGSIC May 7th 2006 European Satellite Services Provider “EGNOS Operations Status”

May 8th 2006EGNOS Operations StatusPage 15

Operational EGNOS

Page 16: Ashley Lyon CGSIC May 7th 2006 European Satellite Services Provider “EGNOS Operations Status”

May 8th 2006EGNOS Operations StatusPage 16

EGNOS System Test Bed

Page 17: Ashley Lyon CGSIC May 7th 2006 European Satellite Services Provider “EGNOS Operations Status”

May 8th 2006EGNOS Operations StatusPage 17

Operations User Support Website

•New ESSP website (www.essp.be) planned in a few weeks providing additional information to the users per market domain

•Link to the Operations User Support Web Site (already existing on current ESSP website):

General information on EGNOS operations. Projection of performances on a weekly basis (registered users).

Performance information at RIMS sites (registered users).

EGNOS Subsystem status (restricted). SIS-down alerts by e-mail (registered users)…

•Existence of a Helpdesk (already existing on current ESSP website)

Page 18: Ashley Lyon CGSIC May 7th 2006 European Satellite Services Provider “EGNOS Operations Status”

May 8th 2006EGNOS Operations StatusPage 18

EGNOS Operations Website Services

Page 19: Ashley Lyon CGSIC May 7th 2006 European Satellite Services Provider “EGNOS Operations Status”

May 8th 2006EGNOS Operations StatusPage 19

ESSPAvenue Louise 2401050 BrusselsBELGIUMTelephone: +32 (0)2 641 17 50Fax: +32 (0)2 641 17 59

[email protected] More about EGNOS:www.essp.be

www.esa.int/navigation

Information