3 Level Colonial Single Family Home in Waterford VA - 9316 waterford dr, manassas, va 20110
ARTICLE 5 WATER DISTRIBUTION SYSTEM - Manassas, VA
Transcript of ARTICLE 5 WATER DISTRIBUTION SYSTEM - Manassas, VA
5-1
ARTICLE 5
WATER DISTRIBUTION SYSTEM
TABLE OF CONTENTS
Page Number
SECTION 5-100 WATER MAIN DESIGN CRITERIA 5-5
5-110 MINIMUM WATERLINE SIZE 5-5
5-120 LOCATIONS AND SEPARATIONS 5-5
5-130 FIRE SERVICE SYSTEMS 5-6
5-140 DETECTOR CHECK VALVES 5-7
5-150 GENERAL CRITERIA 5-7
5-160 EASEMENTS 5-9
5-170 SURFACE WATER CROSSINGS 5-9
SECTION 5-200 WATERLINE CONSTRUCTION 5-10
5-210 GENERAL REQUIREMENTS 5-10
5-220 EXCAVATIONS, BEDDING AND BACKFILL 5-10
5-230 CONSTRUCTION PERMITS 5-12
5-240 UNDERGROUND LOCATES 5-12
SECTION 5-300 STANDARD SPECIFICATIONS
5-12
5-310 DESCRIPTION OF WORK 5-12
5-310.1 Related Work Specified Elsewhere 5-12
5-310.2 Applicable Specifications 5-12
5-310.3 Applicable References 5-13
5-310.4 Submittals 5-13
5-310.5 Quality Assurance 5-13
5-2
5-320 MATERIALS 5-13
5-320.1 General Criteria 5-13
5-320.2 Iron Pipe 5-14
5-320.3 Tie Rods and Accessories: Restrainer Glands 5-14
5-320.4 Gate Valves 5-14
5-320.5 Butterfly Valves and Cone Valves 5-15
5-320.6 Fire Hydrants 5-15
5-320.7 Valve Boxes 5-16
5-320.8 Copper Pipe 5-16
5-320.9 Corporation Stops 5-16
5-320.10 Water Meters and Services 5-16
5-320.11 Air Release Valves and Assemblies 5-16
5-320.12 Tapping Sleeves and Valves 5-17
5-320.13 Inserting Valves 5-17
5-320.14 Service Clamps 5-17
5-320.15 Valve Vaults 5-17
5-320.16 Manhole Frames and Covers 5-18
5-320.17 Manhole Steps 5-18
5-330 EXECUTION 5-18
5-330.1 Laying Pipe 5-19
5-330.2 Connections to Existing Mains 5-21
5-330.3 Installing Valves and Fittings 5-22
5-330.4 Setting Fire Hydrants 5-22
5-330.5 Thrust Restraint 5-23
5-330.6 Water Service Connections 5-23
5-330.7 Abandoning Existing Water Mains
5-24
5-330.8 Sterilization of Water Mains 5-24
5-330.9 Hydrostatic Testing 5-28
5-330.10 Repair Guidelines 5-30
5-3
5-330.11 Certificate to Operate 5-31
5-330.12 Final Approval 5-31
SECTION 5-400 WATER DISTRIBUTION
SYSTEM DETAILS 5-32
5-4
(This page has intentionally been left blank)
5-5
ARTICLE 5
WATER DISTRIBUTION SYSTEM
SECTION 5-100 WATER MAIN DESIGN CRITERIA
Water mains and appurtenances shall be designed and installed to conform to
the latest revision or revised edition of the City of Manassas Design and Construction
Standard Manual, the Virginia Department of Health Water Works Regulations,
American Water Works Association Standards, National Fire Protection Association
Codes and Standards and the design criteria specified hereinafter. The review of all
water distribution systems will be performed by Public Works and coordinated with the
City’s Water Department with approval by the Director or his designated agent. The
authority for discretionary provisions for water main designs shall vest with the Director
of Public Works of the City of Manassas.
5-110 MINIMUM WATER LINE SIZE
The minimum size of waterline shall be as follows:
A. In residential districts, eight (8”) inch is required.
B. In other areas, eight (8”) inch and twelve (12”) inch; eight inch (8")
to be used only when it completes a good gridiron and twelve inch
(12") for long lines not interconnected.
C. Lead lines for fire hydrants shall not be less than six inches (6") in
diameter.
.
5-120 LOCATIONS AND SEPARATIONS
In general, water mains shall be installed in the street right-of-way and six
(6’) feet minimum from the centerline of the water main, to the edge of the gutter
in streets with curb and gutter, and ten (10’) feet from the centerline in streets
5-6
without curb and gutter. Water mains shall be a minimum horizontal distance of
ten (10’) feet measured edge to edge from a sanitary sewer main or manhole.
When unusual conditions prevent a ten (10’) foot horizontal separation, a
minimum horizontal separation of six (6’) feet may be allowed, provided the
sewer main has a minimum of eighteen (18”) inches of clearance below the
water main. Also, provide a minimum of at least eighteen (18”) inches between
steel gas lines and water mains, and services.
Water mains crossing sanitary sewers shall be laid to provide a separation
of at least eighteen (18”) inches between the bottom of the water main and the
top of the sewer. If this vertical separation cannot be accomplished, the water
main shall be relocated to provide the separation directed by a City of Manassas
Utilities Engineer, or the sewer shall be constructed of ductile iron pipe, pressure
tested in place, with no joint of the sewer closer than eight (8’) feet to the water
main. Concrete piers are an option when the conflict involves RCP storm sewers
when approved by the Utilities and Public Works Engineer, in accordance with
Standard Detail SS - 4.2 of this Manual.
5-130 FIRE SERVICE SYSTEMS
Fire service systems and fire hydrants shall be located in accordance with
Article 6 of this manual.
Fire hydrants shall be painted in accordance with the City of Manassas
Fire Marshal Specification. See Standard Detail FS - 1.0 of this Manual.
Fire hydrants shall be controlled by an independent six(6”) inch gate
valve, located as near to the service main as practical. Where the six (6”) inch
hydrant service line is longer than fifty-feet (50') a second six (6”) inch gate valve
shall be located not less than one (1’) foot or more than six (6’) feet from the
hydrant.
5-7
5-140 DETECTOR CHECK VALVES
Approved detector check valves shall be required on all building fire
service mains that serve a "wet pipe" sprinkler system. The detector check valve
shall be equipped with an appropriately sized gate valve on either side of the
check valve. The O.S. and Y and the post indicator valve are required to have
tamper switches in use groups A, E, I, and R.
5-150 GENERAL CRITERIA
Water systems shall be so designed as to adequately supply the normal
and peak demands of all customers, both domestic and commercial, maintaining
a pressure of not less than thirty (30) pounds per square inch at all points of
delivery, without reducing the service to existing customers. Where the
supplying system can provide sufficient water, the designed extension shall have
adequate capacity to be capable of delivering not less than the required fire flows
as specified by the Fire Marshal, with a residual pressure of not less than twenty
(20) pounds per square inch to at least one (1) point within five hundred (500’)
feet of each building proposed to be served by such extension. In those cases
where the source of supply cannot deliver fire flows at adequate pressures, the
developer shall design his water system based on achieving the required fire
flows with an assumed pressure of 30 p.s.i. at point of connection. A pressure
regulating valve will be installed by the developer or property owner in the
building plumbing system where the pressure exceeds eighty (80) psi.
Valve boxes shall be set and adjusted so that the covers shall be exposed
and flush with the street surface. If street surfaces are renewed or replaced by
the developer or owner after the water system has been approved and accepted
by the City, but while such streets are still the obligation of the developer or
owner, the valve boxes therein shall be readjusted to proper location relative to
the new street surfacing. Valve boxes located in sodded or other off-street areas
5-8
shall be set and adjusted so that the covers shall be exposed and flush with the
immediate surface.
Where a water main is terminated beyond a gate valve in that main, the
minimum length of pipeline between valve and end of the line shall be two (2)
pipe lengths or as directed otherwise.
No water main shall terminate under a concrete valley gutter. Whenever
possible to avoid, no gate valve shall be located under a concrete valley gutter.
All pipe shall be laid to a minimum depth of forty-two (42”) inches from
established grade to the top of the pipe. Water lines will not be laid at depths
greater than eight (8') feet without the permission of the Director of Public Works.
Valves shall be installed at the intersection of waterlines. Generally, a
minimum of four (4) valves will be used at crosses and three (3) valves at tees.
A valve shall be also be installed every one thousand (1000’) feet on distribution
mains.
Provide a means to blow off dead-end lines in residential developments
by installing a fire hydrant at the lines terminous.
A standard blow-off assembly shall only be provided at the end of a dead-
end line in a commercial development where fire hydrants cannot be installed
and located within the pavement. Or where it is not possible to complete a loop
within the system. Refer to Standard Detail W-5.0 of this Article.
Air release valves or hydrants shall be placed at strategic high points in
the system to provide for the release of trapped air.
All transmission mains shall be provided with blow- off valves at strategic
low points in the line.
No water pipes shall pass through or come in contact with any part of a
sanitary or storm sewer manhole.
Cross connections and backflow prevention connections shall be
inspected to insure compliance with the adopted cross-connection and backflow
ordinance. Refer to Article 13 of this Manual.
5-9
5-160 EASEMENTS
Water mains may be installed on private property if an easement of a
minimum of fifteen (15’) feet in width is duly recorded. Increased easement
widths may be required by the Engineer when determined necessary due to
large mains or excessive depths. Easement instruments denoting waterline
easements shall include a note giving the water purveyor the right- of- access to
the water service connection and the water meter for the purpose of
maintenance and operation. No permanent structure shall be constructed within
an easement.
Where deemed necessary by the Director of Public Utilities and in order to
assure maximum utilization of the public water system, it will be required that
appropriate easements be provided to adjacent properties for access to future
extensions.
5-170 SURFACE WATER CROSSINGS
Surface water crossing, both over and under water, present special
problems and should be discussed with the Engineer before final plans are
prepared.
A. Above Water Crossings - The pipe above water crossings shall be:
1) Adequately supported.
2) Insulated to protect from damage due to freezing.
3) Accessible for repair or replacement.
4) Installed so that the bottom of the pipe is a minimum of one (1’)
foot above the 100 - year flood level.
B. Under Water Crossing:
1) The pipe shall be of special construction, having flexible watertight
joints.
5-10
2) Valves shall be provided at both ends of the water crossing so that
the section can be isolated for tests or repair; the valves shall be
easily accessible and not subject to flooding.
3) Sample taps shall be available at each end of the crossing and at a
reasonable distance from each side of the crossing.
SECTION 5-200 WATERLINE CONSTRUCTION
5-210 GENERAL REQUIREMENTS
Pipe, fittings, valves, hydrants and accessories shall be loaded and
unloaded by lifting with hoists of skidding so as to avoid shock or damage.
Under no circumstances shall such material be dropped. Pipe shall be so
handled that the coating and lining shall not be damaged.
The water main shall be laid and maintained to the required lines and
grades with fittings, valves, hydrants and accessories set at the required
locations as indicated on the approved plans for the project. All valves and
hydrant stems shall be set plumb. Whenever obstructions not shown on the
plans are encountered during progress of the work and interfere to such an
extent that alteration in plans is required, the Director of Public Works and
Assistant Water and Sewer Director shall be advised and approval given by the
Director of Public Works before such alternatives are put into effect. All
development plans shall be properly noted to specify this requirement.
5-220 EXCAVATION, BEDDING AND BACKFILL
The trench shall be dug so that the pipe can be laid to the alignment and
depth required and it shall be excavated not more than five hundred (500) feet in
advance of the completed pipe laying operation. The width of the trench shall be
ample to permit the pipe to be placed, backfilled, and thoroughly compacted in
accordance with the requirements of these specifications. Trenches shall be of
5-11
such extra widths when required as will permit the convenient placing of timber
supports, sheeting and bracing and handling of special fittings or appurtenances.
The trench shall be excavated to the depth required so as to provide a
uniform and continuous bearing and support for the pipe on solid and
undisturbed ground at every point between bell holes, except that it will be
permissible to disturb and otherwise damage the finished surface over a
maximum length of eighteen (l8) inches near the middle of each length of pipe by
the withdrawal of pipe slings or other lifting tackle. Any part of the bottom of the
trench excavated below the specified grade shall be backfilled with approved
materials, thoroughly compacted. The finished subgrade shall be prepared
accurately by means of hand tools.
Where excavation is made in rock, boulders, or other unsuitable material,
the subgrade shall be made by backfilling with a minimum four (4) inches of
gravel or clean selected soil which shall be thoroughly compacted.
Bell holes shall be provided at each joint to permit the jointing to be made
properly.
Ledge rocks, boulders, and large stones shall be removed to provide a
clearance of at least six (6) inches below and on each side of all pipes, valves
and fittings. The specified minimum clearances are the minimum clear distances
which will be permitted between any part of the pipe and appurtenances being
laid and any part, projection, or joint of such rock or stone.
No pipe shall be laid in water or when, in the opinion of the Director of
Public Works and/or the Assistant Water and Sewer Director, the trench
conditions are unsuitable.
Backfill shall be placed in two (2), one (l) foot layers over the pipe and
shall be thoroughly compacted to 95% density, the remainder of the backfill shall
be placed in no greater than one layer eight (8) inches thick uncompacted, then
thoroughly tamped to 95% of the maximum dry density. Backfill material shall be
free of perishable material, frozen clods, sticky masses of clay and other
unsuitable matter. Rock pieces larger than two (2) inches shall not be used in
5-12
the backfill which is within two (2) feet of the pipe. Refer to Section 9-5100, 10-
700, and Standard Detail TS-15.0 of this Manual for backfill required within
existing/proposed roads or rights- of- way.
5-230 CONSTRUCTION PERMITS
No water main shall be constructed, added to, or altered without the
issuance of a construction permit by the Inspections Department. The
requirements and procedures outlined in Chapter 34 of the City Ordinances and
Section 2-830 of this Manual shall be followed in applying for a construction
permit.
5-240 UNDERGROUND LOCATES
The contractor/excavator who is performing the actual work must contact
"Miss Utility" prior to the commencement of work.
SECTION 5-300 STANDARD SPECIFICATIONS
5-310 DESCRIPTION OF WORK
Provide all parts, labor, materials and equipment to install all water pipe
and appurtenances to the lines and depths as called for on the approved plans
and as described herein for a complete and operable water distribution system.
5-310.1 RELATED WORK SPECIFIED ELSEWHERE
Section 10-600 Geotechnical Guidelines
Section 11-500 Tunneling
Section 11-600 Boring and Jacking
5-310.2 APPLICABLE SPECIFICATIONS
American National Standards Institute (ANSI).
American Society for Testing and Materials (ASTM and current standard).
5-13
American Water Works Association (AWWA).
National Fire Protection Association (NFPA).
5-310.3 APPLICABLE REFERENCES
Virginia Soil and Water Conservation Commission Erosion and Sediment
Control Handbook.
Erosion and Sediment Control Ordinance (Chapter 9 of the City of
Manassas Code).
For definition of terms used within this Article, Refer to Section 1-500 of
this Manual.
5-310.4 SUBMITTALS
Submit full descriptions and details of all pipe, valves, hydrants,
and other appurtenances proposed for the project to include an affidavit of
compliance that all products meet the specifications herein. Submit sworn
statements from the manufacturers that the inspections and tests
specified in the referenced standards have been made and that the
results of such inspections and tests comply with the requirements of the
applicable standard. Certificates of compliance and approval shall apply.
5-310.5 QUALITY ASSURANCE
The manufacturer shall provide facilities or a certified laboratory for
conducting load bearing and other tests required by the referenced
specifications such as the current ASTM.
The Engineer will inspect pipe, fittings and joint material upon
delivery to the site. The Contractor shall provide ample space between
rows of stockpiled pipe to facilitate adequate inspections.
5-320 MATERIALS
5-320.1 GENERAL CRITERIA
5-14
A. All water mains shall be constructed using ductile iron pipe as
specified herein.
B. All materials shall be suitable for 150 psi working pressure unless
otherwise indicated.
C. Pipe of the same size and material shall be furnished by the same
manufacturer. Each pipe length and fitting shall be clearly marked
with the manufacturer's name, trademark and class of pipe.
D. Materials shall be recently manufactured and unused. Only
previously approved manufacturers items may be furnished.
E. Materials shall be listed by an approved testing laboratory.
5-320.2 IRON PIPE
Iron pipe shall be ductile iron conforming to AWWA C151 (ANSI
A21.51), class 52 unless otherwise indicated. Pipe shall be single cement
lined conforming to AWWA C104 (ANSI A21.4) and shall have
mechanical or push-on joints utilizing rubber gasket rings, conforming to
AWWA C111 (ANSI A21.11). Polyethylene encasements shall be used in
accordance with ANSI/AWWA C105 / A21.5 American National Standard
for Polyethylene Encasement for Ductile Iron Pipe Systems.
Fittings shall be mechanical joint ductile or gray iron conforming to
AWWA C110 (ANSI A21.10), with a minimum pressure rating of 250 psi.
Fittings shall be cement lined conforming to ANSI A21.4.
5-320.3 TIE RODS AND ACCESSORIES: RESTRAINER BANDS
Tie Rods, tie bolts and accessories shall be manufactured of
corrosion resistant steel conforming to ASTM-A242. Restraining bands
shall be Megalug manufactured by Ebaa Iron or approved equal.
5-320.4 GATE VALVES
A. Gate valves four (4") inches through twelve (12") inches for buried
installation shall be iron-body, bronze mounted, resilient seat, 0-
5-15
ring sealed, inside screw, non-rising stem, fitted with a two(2")
inches operating nut opening left, with mechanical joint ends,
unless indicated otherwise on the drawings. Valves shall conform
to AWWA C509. Provide buried valves with valve boxes. Provide
extension stems extended to within two (2’) feet of finished grade if
valve depth exceeds five ( 5') feet. Valves shall be as
manufactured by Mueller - American-Darling, Kennedy or approved
equal.
B. Gates valves three ( 3") inches and larger for vault or interior
installation shall be iron-body, bronze mounted, solid wedge disc,
bolted bonnet, class 125 psi, outside screw and yoke, rising stem
with hand wheel, opening left, with flanged ends.
C. Gate valves two ( 2") and smaller shall be bronze-body, solid disc,
union bonnet, class 125 psi, non-rising stem with hand wheel,
opening left, with inside threaded ends.
5-320.5 BUTTERFLY VALVES AND CONE VALVES
Butterfly and cone valves shall be as directed by the Engineer as a
special project basis.
5-320.6 FIRE HYDRANTS
Fire hydrants shall be dry top, dry barrel compression type, with a
valve opening of 5¼ inches, double O-ring seals and safety flange, and
shall conform to AWWA C502 requirements. Hydrants shall be provided
with two--2½ inch hose nozzles and one- 4½ inch pumper nozzle with
threading conforming to NFPA No. 194 for National Standard Fire Hose
Company Screw Threads, six ( 6”)’ inch mechanical joint inlet connection,
National Standard one and one-half (1-1/2) inch pentagon operating nut
and outlet nozzle cap nuts, chains on outlet nozzle caps, and harnessed
lugs. Hydrants shall open left and counterclockwise. Protective coating
5-16
color shall be as directed by the Fire Marshal. Hydrants shall be Mueller
Centurion (Model A-423), American Darling (Model B-84-B), Kennedy
Guardian (Model K-81-A) or approved equal.
5-320.7 VALVE BOXES
Valve boxes shall be of the two-piece, sliding type five and one
fourth (5¼ inch shaft, cast iron kind. Valve box shall read "Water". Valve
boxes shall be as manufactured by Bingham and Taylor Company or
Tyler Company and conform to their standard dimensions.
5-320.8 COPPER PIPE
Copper pipe shall be seamless water tube, type K conforming to
ASTM designation B88. Fittings shall be undergound copper service,
flare type, or lead-free solder.
5-320.9 CORPORATION STOPS
Corporation stops shall be Mueller H-15008 series, Ford-F1000 or
approved equal.
5-320.10 WATER METERS AND SERVICE
Water meters including taps, pipe fittings, meter box and
accessories from the water main through the meter, will be furnished and
installed by the City after payment of the appropriate fees. Newly installed
meters shall be of the touch read type.
5-320.11 AIR RELEASE VALVES AND ASSEMBLIES
Air release valves shall be constructed of cast iron body and cover
conforming to ASTM A48, class 30. The float shall be stainless steel
conforming to ASTM A240 and the seat shall be Buna-N. Air release
5-17
valves shall be Apco or approved equal. All piping and miscellaneous
fittings shall be brass as shown on standard detail W-4.0 of this article
5-320.12 TAPPING SLEEVES AND VALVES
Tapping sleeves and valves shall conform to the applicable
requirements specified herein for fittings and gate valves. The tapping
sleeves shall be of iron body, corrosion resistant construction and shall be
the mechanical joint type. All bolts used in valve assembly shall be
stainless steel. A bituminous coating shall be applied to all exposed
surfaces of the sleeve and valve assembly prior to backfill. The tapping
sleeve and valve shall be as manufactured by Mueller Co., Clow
Company, or approved equal.
5-320.13 INSERTING VALVES
Inserting valves shall conform to the specifications for gate valves.
Inserting valves twelve (12”) inches and smaller shall be No. H-800 as
manufactured by Mueller Company. Inserting valves twelve (12”) inches
and larger shall be as manufactured by A.P. Smith, or approved equal.
Valve shall be suitable for installation on the existing pipe.
5-320.14 SERVICE CLAMPS
Generally, service clamps are required for 1 ½” and 2” service
lines and shall be double strap ductile iron with corporation stop,
neoprene gasket cemented in place, cadmium plated nuts and removable
straps (for cast iron pipe) and shall be the diameter required. Clamps
shall be manufactured by Mueller, or approved equal.
5-320.15 VALVE VAULTS
Valve vaults shall be cast-in-place concrete, as specified in Section
11-700, Cast-in-Place Concrete, or precast concrete as specified in
5-18
Section 11-800, precast Concrete. The vaults shall be constructed to the
dimensions shown on the contract drawings. All vaults shall be
waterproofed according to Section 11-1400, Waterproofing, and shall be
provided with a double-leaf door as manufactured by Bilco Co. or
approved equal.
5-320.16 MANHOLE FRAMES AND COVERS
Manhole frames and covers shall be constructed of gray or ductile
iron conforming to ASTM A-48 and A-536. Frames and covers shall have
machined bearing surfaces to prevent rocking and rattling under traffic.
Frames and covers shall be manufactured by Dewey Brothers or
approved equal.
5-320.17 MANHOLE STEPS
Manhole steps shall be a composite of a No. 3 grade 60 deformed
steel bar encased in copolymer polypropylene plastic of the "press-fit"
design or rubber. Steps shall be PSI-PF as manufactured by M. A.
Industries, Inc. or Wedge-Lok as manufactured by Delta Pipe Products,
Inc. or approved equal.
5-330 EXECUTION
Maintain a minimum ten (10’) feet horizontal distance (edge to edge)
between sanitary sewers and water mains. If this cannot be done, a minimum
horizontal distance of six (6’) feet may be allowed, provided the bottom of water
main is at least eighteen (18”) inches above the crown of sewer main. Ductile
iron pipe may be required by the City for sewer mains at this separation.
Maintain at least eighteen (18”) inches between the top of the sewer and
the bottom of the water main whenever water main must cross over sewers. If
this cannot be done, the water main shall be relocated to provide the separation
directed by the Engineer, or the sewer shall be constructed of ductile iron pipe
5-19
pressure tested in place with no joint of the sewer closer than eight (8’) feet to
the water main.
Use proper and suitable tools for the safe handling and laying of pipes
and fittings. Prevent fitting linings and coatings from being damaged. Damaged
pipe shall be replaced or repaired to the satisfaction of the Engineer.
5-330.1 LAYING PIPE
A. Unless indicated otherwise, the depth of trench shall be sufficient to
provide a minimum cover over the top of the pipe of three and one-
half (3.5’) feet from the finished grade elevation and to avoid
interfere of the pipe-line with other utilities. Install pipe on
continuous grades, as indicated on plans, to avoid sags or crests in
the line. Whenever obstructions are encountered during progress
of the work and interfere to such an extent that alteration in plans is
required, the Public Works and Water and Sewer Engineers shall
be advised and approval given before such alternatives are put into
effect.
B. The cutting of pipe for inserting valves, fittings, or closure pieces
shall be done in a neat and workmanlike manner in accordance
with the manufacturer's specifications without damage to the pipe,
so as to leave a smooth end at right angles to the axis of the pipe.
The outside edge of cut pipe shall be beveled and smoothed to
avoid damage to the gasket and avoid damage to the lining. Do
not flame cut cast iron pipe with an oxyacetylene torch.
C. Thoroughly clean pipes and fittings before they are laid.
D. Carefully lower pipe fittings into trench. Every precaution shall be
taken to prevent foreign material including nonpotable water from
entering the pipe while it is being placed in the line. If the pipe-
laying crew cannot put the pipe into the trench and in place without
getting earth into it, a heavy, tightly woven canvas bag of suitable
5-20
size shall be placed over each end and left there until the
connection is to be made to the adjacent pipe. During laying
operations, no debris, tools, clothing, or other materials shall be
placed in the pipe. Butt ends of pipe against each other in such
manner that there shall be no shoulder or unevenness on the
inside of main.
E. Pipe shall not be laid in water or when, in the opinion of the Public
Works Engineer, trench conditions are unsuitable.
F. Insure that pipe is well bedded on a solid foundation as shown in
the standard details. Correct any defects due to settlement.
Excavation bell holes sufficiently large to insure making proper
joints. Exercise precautions to include the furnishing and placing of
aggregate to prevent any pipe from resting directly on rock.
G. After placing a length of pipe in the trench, the spigot end shall be
centered in the open bell of the pipeline and the pipe pushed until
seated so that the face of the spigot is in close contact with the
shoulder of the bell. Ductile cast iron pipe shall be laid with the
bells facing the direction of the laying.
H. No stub of any water main shall terminate with a capped or plugged
valve. Where a valve is required to be installed near a stub end,
not less than two (2) standard lengths of pipe shall be installed
between the valve and the plugged stub end of the pipe for
adequate anchoring. All tees, bends, plugs, caps and fire hydrants
shall be substantially braced, blocked and/or strapped to prevent
any movements by providing adequate reaction blocking and/or
other approved restraining method. Blocking is not required if
Megalug is used at these locations.
I. Whenever it is necessary to deflect pipe from a straight line, either
in the vertical or horizontal plane, to avoid obstructions or plumb
stems, or where long-radius curves are permitted, the amount of
5-21
deflection allowed shall not exceed that required, for satisfactory
joining of the pipes, as specified by the manufacturer.
J. Iron pipe shall be jointed in full accordance with AWWA Standard
C600, the manufacturer's recommendations and the following
requirements:
1) Push-on joints shall be thoroughly cleaned. Insert the
rubber gasket in the bell socket. Supply a thin film of
approved gasket lubricant; center the spigot end of the pipe
into the socket; complete the joint by forcing the spigot end
to the bottom of the socket.
2) Mechanical joints shall be thoroughly cleaned. Lubricate the
gasket and spigot. Place the band on the spigot end,
followed by the gasket, with the pipe end seated and
centered in the socket. The gasket shall then be seated in
the sockets, gland moved into position and bolts and nuts
loosely assembled by hand. Tighten with a wrench.
K. At the close of work each day, close the end of the pipeline with an
expansion stopper so that no dirt or other foreign substance may
enter the line. Keep this stopper in place until pipe laying is
resumed.
L. Remove and replace all defective materials at no additional cost to
the City.
5-330.2 CONNECTIONS TO EXISTING MAINS
The Contractor shall notify the City two (2) working days in advance
of when the connection is to be made. The Contractor shall excavate the
trench and backfill after the connection is made. The Contractor shall
provide the tapping sleeve and valve and install it on the main for a wet
tap. For connections less than or equal to 2”, materials must be
purchased from the City. Installation of connections 2” or less may be
5-22
performed by City or contractor labor. For connections greater than 2”,
contractor will provide labor and materials for installations.
Reaction blocking at connections to existing mains shall be made
with high early strength concrete. In the event that line pressure must be
restored less than 48 hours after the placement of reaction backing at
these connections, provide temporary deadmen and/or similar devices as
required to maintain stability of the water mains.
5-330.3 INSTALLING VALVES AND FITTINGS
Install valves, fitting, and caps to pipe in the manner herein before
specified for laying pipe. Provide valve boxes for each buried gate valve.
Boxes shall not transmit shock or stress to the valve, with the box cover
flush. Valves shall be strapped to adjacent fittings unless directed
otherwise.
Inserting valves, tapping sleeves, and valves shall be installed in
accordance with the valve manufacturer's recommendations. Test pits
shall be dug by the contractor to determine type and size of existing pipe
and suitability of tapping locations on the pipe.
5-330.4 SETTING FIRE HYDRANTS
Connect hydrants to the main with a six (6”) inch ductile iron branch
controlled by an independent six (6”) inch gate valve. Hydrants shall be
set plumb and to established finished grade as follows:
The bottom of the four and one-half inch (4½") nozzle shall be
eighteen (18”) inches above the elevation of the edge of the shoulder on
streets without curb and gutter and eighteen (18”) inches above the
elevation of the curb on streets with curb and gutter.
The two and one-half (2 1/2”) inch hose connections shall have a
minimum of four feet, zero (4.0”) inches clearance on all sides.
5-23
Provide the drainage fill at the base of the hydrants as indicated in
the Standard Details.
5-330.5 THRUST RESTRAINT
Valves for connections to future lines, fire hydrants and related
valves, and other fittings or valves so indicated shall be anchored by steel
rods and concrete reaction blocking, as shown on the drawings or
Standard Details W-2.0 to W-4.0 and FS-1.1 of this Manual. Protect tie
rods, sleeves and clamps by two (2) coats of acid-resisting asphalt paint.
The use of mechanical joint restraint (such as megalug or an approved
equal) will be considered an option to steel rodding and thrust blocking.
(Refer to Standard Detail W-3.0 of this Article.)
5-330.6 WATER SERVICE CONNECTIONS
Water service connections from the water mains through the water
meters will be furnished and installed by the City at the owner’s expense.
New meters shall be of the touch read type. The Contractor shall provide
excavation, backfill and all other associated work. Connections from the
meter installation to the building shall be installed by the building owner's
plumber. Containment backflow prevention devices are required for all
commercial facilities and required for all 4 story or higher structures.
Provide backflow prevention devices on service lines after the meter and
prior to take offs (see section 6 and 13 DCSM). Meters shall be installed
behind the curbing in the utility strip. This is the area between the curbing
and sidewalk. The meter box shall be set at finished grade and any re-
adjustment after its initial placement will be performed by the contractor.
The water meter shall only be located within a sidewalk when there is no
utility strip and there is not sufficient room to place the meter behind the
sidewalk.
5-24
5-330.7 ABANDONING EXISTING WATER MAINS
A. Drain and abandon existing water mains not required in the
completed system. Abandoned mains and appurtenances that
conflict with proposed construction shall be removed as required.
Abandoned mains not removed shall be capped at all open ends.
Boxes on abandoned valves shall be removed.
B. At the locations indicated on the drawings, cut the existing water
mains, cap and provide reaction blocking. Keep the length of pipe
removed to the minimum necessary for installing the cap and
concrete blocking. A cap shall be placed over the end of the pipe
to be abandoned. The concrete thrust block shall be placed to
bear against undisturbed ground. After this work has been
completed, the capped line shall not be recharged unless so
directed by the Engineer.
C. Existing fire hydrants not required in the completed system shall be
carefully removed, cleaned and transported to the City storage
yard. The hydrant lead shall be removed from the gate valve and
provided with a mechanical plug.
D. Existing water services will be discontinued at the main.
Excavation, backfill and pavement restoration between the water
meter and the main shall be the responsibility of the Contractor.
Water meters shall be removed by the City upon notification of
abandonment. Removal of meter box castings shall be the
responsibility of the Contractor.
5-330.8 STERILIZATION OF WATER MAINS
A. When each pipe length has been placed and shut off, sterilize each
section of the water main. Provide all labor, materials and
equipment to perform the sterilization operations in compliance with
5-25
all state and local regulations. Disinfection shall conform to AWWA
C601.
B. Water for sterilization, flushing and testing will be furnished to the
Contractor from the existing water system at no charge to the
Contractor. Schedule water usage with the Engineer to result in a
minimum interference to water service throughout the existing
system. Temporary connections to the existing water system shall
be provided and removed by the Contractor and shall include
approved means to prevent backflow and possible contamination of
the existing water system. Temporary taps for removing air and
flushing the main shall be provided by the contractor as necessary.
C. Disinfection of the water main shall be accomplished in the
following manner:
1. Preliminary Flushing of Mains: All mains shall be flushed
prior to disinfection except when the tablet method of
disinfection is used. The mains shall be flushed at a
minimum velocity of 2.5 feet/second and all points in the
main shall receive a minimum of five (5) consecutive
minutes of flushing at this velocity, or until the water runs
clear.
2. Form of Chlorine to be used: Liquid chlorine, calcium
hypochlorite or sodium hypochlorite may be used for
disinfection. Liquid chlorine shall be used only when
approved by the Engineer. Calcium hypochlorite and
sodium hypochlorite shall be added to water to form a
chlorine water solution before being used.
3. Methods of Application: The chlorine shall be applied by
continuous feed method or the tablet method and performed
as follows:
5-26
a. Continuous Feed Method: The rate of water and
chlorine shall be proportioned so that the chlorine
concentration of water in the pipe is maintained at a
minimum of 50 mg/l available chlorine. To assure
that this concentration is maintained, the chlorine
residual shall be measured at regular intervals.
During the application of the chlorine, valves shall be
manipulated to prevent the treatment dosage from
flowing back into the line supplying the water.
Chlorine application shall not cease until the entire
main is filled with the chlorine solution.
b. Tablet Method: Because the preliminary flushing step
must be eliminated, this method shall be used only
when scrupulous cleanliness has been exercised.
Tablet method shall not be used if trench water or
foreign material has entered the main or if the water
is below five (5) degrees C. Forty-one (41 degrees
F). Tablets are placed in each section of pipe and
also in hydrant branches and other appurtenances.
They shall be attached by an adhesive, except for the
tablets placed in hydrants and in the joints between
the pipe sections. All the tablets are fastened before
the pipe section is placed in the trench, their positions
shall be marked on the section to assure that there
will be no rotation. In placing tablets in joints, they
are crushed and placed on the inside annular space
or if the type of assembly does not permit, they are
rubbed like chalk on the butt ends of the sections to
coat them with calcium hypochlorite. The adhesive
may be Permatex No. 1 or any alternative approved
5-27
by the Engineer. There shall be no adhesive on the
tablet except on the broad side next to the surface to
which the tablet is attached. When installation has
been completed, the main shall be filled with water at
a velocity of less than one (1) foot per second.
4. Contact Period: The chlorinated water shall be retained in
the main for at least twenty-four (24) hours during which time
all valves and hydrants, in the section treated shall be
operated in order to disinfect the appurtenances. At the end
of this twenty-four (24) hour period, the treated water shall
contain no less than twenty-five (25) mg/l chlorine
throughout the length of the main. The tests for chlorine
residual shall be made by the Engineer. The Contractor
shall install corporation cocks and copper tubing for the tests
at the locations indicated by the Engineer.
5. Final Flushing: After the applicable retention period, the
heavily chlorinated water shall be flushed from the main until
the chlorine concentration in the water leaving the main is no
higher than that generally prevailing in the system or less
than one (1) mg/l. Chlorine residual determination shall be
made by the Engineer. The heavily chlorinated water and
flushing water shall be lawfully disposed of by the
Contractor.
6. Bacteriologic Test: After chlorination and final flushing, and
before the water main is placed in service, samples shall be
collected from the main and tested for enteric bacterial
contamination and shall show the absence of coliform
organism. At least two (2) consecutive satisfactory
bacteriological samples shall be obtained from the
distribution system before the system can be placed into
5-28
services. Samples shall be collected in duplicate at the
opposite end of the line from where the pipe was filled with
water and at approximately one (1,000) thousand foot
intervals. Samples shall be taken through the use of sample
tap consisting of a corporation cock and copper tube.
Testing shall conform to AWWA Standard C651 or C652.
All bacteriological sampling and testing shall be conducted by a
state certified laboratory. If the initial disinfection fails to produce
satisfactory samples, disinfection shall be repeated until satisfactory
samples have been obtained. After each group of samples is taken, the
Contractor shall submit in writing to the Engineer a report stating the
results of the tests. The testing of the service shall be done according to
the BOCA Plumbing Code.
5-330.9 HYDROSTATIC TESTING
Pressure tests shall conform with Section 4 of AWWA Standard
C600.
A. The water mains shall be tested for leakage by the Contractor at
his own expense in the presence of the Engineer. All tests will be
conducted in a manner to minimize as much as possible any
interference with the Contractor's work or progress. A maximum of
five thousand (5,000) linear feet of water main may be tested at
one time.
B. The Contractor shall notify the Engineer when the work is ready for
hydrostatic testing and tests shall be made as soon thereafter as
practicable under the direction of the Engineer. Personnel for
reading meters, gauges or other measuring devices will be
furnished by the Engineer, but all other labor, equipment, water and
5-29
materials, including meters and gauges, shall be furnished by the
Contractor.
C. The water mains shall be tested as a whole or in sections valved or
bulkheaded at the ends. Test piping under a hydrostatic pressure
of 200 psi unless shown otherwise on the approved plans. Apply
pressure to the piping after it has been purged of air. Maintain
water pressure for a minimum of two hours. Testing procedures
shall be in accordance with AWWA C600 and the measured
amount of leakage shall not exceed the amount found in Table 6 of
AWWA Specification C600.82.
The table has been established by the following formula:
L = SD P 133200 L = Allowable leakage in gallons/hour S = Total length of pipe being tested D = Nominal diameter of the pipe P = Average test pressure during testing
ALLOWABLE LEAKAGE PER 1,000 FT OF PIPE LINE * - GPH
Normal Pipe Diameter - in. Avg. Test
Pressure psi
(Bar)
3
4
6
8
10
12
14
16
18
20
24
30
36
250 (17) 0.36 0.47 0.71 0.95 1.19 1.42 1.66 1.90 2.14 2.37 2.85 3.56 4.27
225 (16) 0.34 0.45 0.68 0.90 1.13 1.35 1.58 1.80 2.03 2.25 2.70 3.38 4.05
200 (14) 0.32 0.43 0.64 0.85 1.06 1.28 1.48 1.70 1.91 2.12 2.55 3.19 3.82
175 (12) 0.30 0.40 0.59 0.80 0.99 1.19 1.39 1.59 1.79 1.98 2.38 2.98 3.58
150 (10) 0.28 0.37 0.55 0.74 0.92 1.10 1.29 1.47 1.66 1.84 2.21 2.76 3.31
125 ( 9) 0.25 0.34 0.50 0.67 0.84 1.01 1.18 1.34 1.51 1.68 2.01 2.52 3.02
100 ( 7) 0.23 0.30 0.45 0.60 0.75 0.90 1.05 1.20 1.35 1.50 1.80 2.25 2.70
• For pipe with eighteen (18’) ft. nominal lengths. To obtain the
recommended allowable leakage for pipe with twenty (20) ft. nominal
lengths, multiply the leakage calculated from the table by 0.9. If the
pipeline under test contains sections of various diameters, the allowable
leakage will be the sum of the computed leakage for each size.
5-30
D. All joints or fittings at which leakage occurs shall be reworked to
insure tightness. Following repair, the pipeline shall be retested
until leakage is within the limit set. Methods of repair prior to
retesting shall be done with City inspection and approval. All
materials must be rated by an approved testing agency.
5-330.10 REPAIR GUIDELINES
Structural repairs to pipe (i.e., holes, crushed or slipped joints)
required as a result of a pressure test, shall be made in accordance with
the guidelines of this Manual.
Prior approval of the Director is required for repairing damaged
water mains.
A. Slipped or leaking joints may be repaired by jacking to properly
realign the pipe.
B. All other damage (i.e., displaced gasket or crushed pipe) shall be
repaired by replacement of the damaged section. To repair this
type of damage, vertical plane cuts shall be made a minimum of
one foot beyond the extremity of the damaged section. A
replacement section shall then be installed such that the joint gap
at either end shall be no more than ¾ of an inch. The replacement
section will then be installed with couplings of the same pipe
material.
C. All excavation shall be done to afford proper protection to the line
while the repair is made.
D. Location of the water main repairs will be reported to the Water and
Sewer Director to be made part of the as-built records.
E. Location of each repair will be measured from the closest valve to
the side of the repair.
F. The type of repair situation will be noted.
5-31
G. When pipe is required to be removed and replaced, the length and
number of couplings used will be noted.
H. The design engineer of record shall be responsible for obtaining
the approved repair method from the City of Manassas.
5-330.11 CERTIFICATE TO OPERATE
No occupancy permit shall be issued where a building is connected
to a new water main until an acceptable pressure test and bacteriological
sampling indicates that construction conforms to the specifications and
criteria.
5-330.12 FINAL APPROVAL
Final approval for the satisfactory completion of the water main
system shall not be given until all site work is complete, the as-built plan (if
required) is submitted to and approved by the Director of Public Works
and the performance bond is released.
5-32
SECTION 5-500 WATER DISTRIBUTION SYSTEM DETAILS
TABLE OF CONTENTS
DRAWING NO.
TRENCH DETAIL FOR DUCTILE IRON PIPE ........................................................ W-1.0
CONCRETE THRUST BLOCKS HORIZONTAL BENDS ........................................ W-2.0
CONCRETE THRUST BLOCKS TEES AND CAPS ................................................ W-2.1
CONCRETE THRUST BLOCKS LOWER VERTICAL BENDS ............................... W-2.2
CONCRETE THRUST BLOCKS UPPER VERTICAL BENDS ................................ W-2.3
CONCRETE THRUST BLOCKS INSERTING VALVES .......................................... W-2.4
MECHANICAL RESTRAINER GLAND .................................................................... W-3.0
AIR RELEASE VALVE SETTING ............................................................................ W-4.0
BLOWOFF DETAIL ................................................................................................. W-5.0
GATE VALVE SETTING.......................................................................................... W-6.0
WATER SERVICE CONNECTIONS 2" AND SMALLER ......................................... W-7.0
WATER METER INSTALLATION 3/4" AND 1" SERVICES .................................... W-7.1
WATER METER INSTALLATION 1½" SERVICES ................................................. W-7.2
WATER METER INSTALLATION 1" METER IN 2" SERVICE ................................ W-7.3
WATER METER INSTALLATION 2" SERVICE ...................................................... W-7.4
WATER SERVICE CONNECTIONS 3" AND 4" SERVICES ................................... W-8.0
WATER METER INSTALLATION 3" SERVICE ...................................................... W-8.1
WATER METER INSTALLATION 4" SERVICE ...................................................... W-8.2
WATER SERVICE CONNECTIONS 6" AND 8" SERVICES ................................... W-9.0
WATER METER INSTALLATION 6" SERVICE ...................................................... W-9.1
WATER METER INSTALLATION 8" SERVICE ...................................................... W-9.2