Arizona Dept. of Transportation Project Management
Transcript of Arizona Dept. of Transportation Project Management
![Page 1: Arizona Dept. of Transportation Project Management](https://reader031.fdocuments.in/reader031/viewer/2022020704/61fb51a02e268c58cd5cc260/html5/thumbnails/1.jpg)
Arizona Department of TransportationProject Management
October 5, 2009
![Page 2: Arizona Dept. of Transportation Project Management](https://reader031.fdocuments.in/reader031/viewer/2022020704/61fb51a02e268c58cd5cc260/html5/thumbnails/2.jpg)
History
Process in place since 1995Based on the recommendations of a Project Management Process Team -February 1993 through October 1993Project Management Implementation Team formed in November 1993
![Page 3: Arizona Dept. of Transportation Project Management](https://reader031.fdocuments.in/reader031/viewer/2022020704/61fb51a02e268c58cd5cc260/html5/thumbnails/3.jpg)
Identified Problems
Time needed to get project to bidLack of Project OwnershipPoor Project DefinitionScope CreepLack of timely decisionsCommunications breakdowns
![Page 4: Arizona Dept. of Transportation Project Management](https://reader031.fdocuments.in/reader031/viewer/2022020704/61fb51a02e268c58cd5cc260/html5/thumbnails/4.jpg)
Desired Outcomes
Clearly-stated and improved Process to better serve our customersProject Manager’s Role definedFunctional Manager’s Role definedProject Manager’s authority definedReduced time to bring project to bidScope and cost control
![Page 5: Arizona Dept. of Transportation Project Management](https://reader031.fdocuments.in/reader031/viewer/2022020704/61fb51a02e268c58cd5cc260/html5/thumbnails/5.jpg)
Questions to be Answered
Does it apply to all projectsConcept of cradle to grave project managementIssue resolution processTraining RequirementsDevelopment of a Project Management Manual
![Page 6: Arizona Dept. of Transportation Project Management](https://reader031.fdocuments.in/reader031/viewer/2022020704/61fb51a02e268c58cd5cc260/html5/thumbnails/6.jpg)
Results
Project Development Process Manual –February 1995Project Manager Team Training –August 1995Identification of a pool of Project Managers in the Valley and Statewide Project Management Groups
![Page 7: Arizona Dept. of Transportation Project Management](https://reader031.fdocuments.in/reader031/viewer/2022020704/61fb51a02e268c58cd5cc260/html5/thumbnails/7.jpg)
Organizational Structure
Centralized Organization
![Page 8: Arizona Dept. of Transportation Project Management](https://reader031.fdocuments.in/reader031/viewer/2022020704/61fb51a02e268c58cd5cc260/html5/thumbnails/8.jpg)
![Page 9: Arizona Dept. of Transportation Project Management](https://reader031.fdocuments.in/reader031/viewer/2022020704/61fb51a02e268c58cd5cc260/html5/thumbnails/9.jpg)
![Page 10: Arizona Dept. of Transportation Project Management](https://reader031.fdocuments.in/reader031/viewer/2022020704/61fb51a02e268c58cd5cc260/html5/thumbnails/10.jpg)
Project Management
Most projects managed by Valley or Statewide Project Management GroupsSub-program projects managed by the technical areaMatrix organization with project team representation from each technical area80% of design by Consultants
![Page 11: Arizona Dept. of Transportation Project Management](https://reader031.fdocuments.in/reader031/viewer/2022020704/61fb51a02e268c58cd5cc260/html5/thumbnails/11.jpg)
Valley Project Management
10/1/2009
TRANSPORTATION MANAGER
STEVE BEASLEY
PROJECT MANAGER RON McCALLY
PROJECT MANAGERDON GORMAN
SENIOR PROJECT MANAGERVACANT
PROJECT MANAGERMOHAMMAD ZAID
PROJECT MANAGER ERIC PROSNIER
PROJECT MANAGERSTEPHANIE HUANG
SENIOR PROJECT MANAGER VACANT
PROJECT MANAGER VELVET MATHEW
ASSISTANT STATE ENGINEER
LARRY LANGER
SENIOR PROJECT MANAGER
ANNETTE RILEY
ADMINISTRATIVE SERVICES OFFICER I
KAY ALBERTY
ADMINISTRATIVE ASSISTANT II
ELENA RENN
Transportation Engineering Specialist
LEANNE CAIRNS
TRANSPORTATION MANAGER
MIKE BRUDER
Transportation Engineering Specialist
MONICA BAIZA
Transportation Engineering Specialist
LYNN GRANDY
![Page 12: Arizona Dept. of Transportation Project Management](https://reader031.fdocuments.in/reader031/viewer/2022020704/61fb51a02e268c58cd5cc260/html5/thumbnails/12.jpg)
ARIZONA DEPARTMENT OF TRANSPORTATIONPROJECT DEVELOPMENT PROCESS MANUAL
TRANSPORTATION
![Page 13: Arizona Dept. of Transportation Project Management](https://reader031.fdocuments.in/reader031/viewer/2022020704/61fb51a02e268c58cd5cc260/html5/thumbnails/13.jpg)
What is a Project?
A project is defined as any temporary effort having scope, schedule and budget, and desired outcome satisfactory to the customer to address the purpose and needs for the transportation facilities.
![Page 14: Arizona Dept. of Transportation Project Management](https://reader031.fdocuments.in/reader031/viewer/2022020704/61fb51a02e268c58cd5cc260/html5/thumbnails/14.jpg)
Project Development Process
PLANNING
CONSTRUCTION
OPERATION/MAINTENANCE
SCOPING
DESIGN
![Page 15: Arizona Dept. of Transportation Project Management](https://reader031.fdocuments.in/reader031/viewer/2022020704/61fb51a02e268c58cd5cc260/html5/thumbnails/15.jpg)
Project Manager Roles and Responsibilities
Ensures all Project Development steps are followedDelegates and coordinates work effortsMonitors progress and takes corrective actionCoordination and communication with internal and external stakeholdersNegotiates project agreements
![Page 16: Arizona Dept. of Transportation Project Management](https://reader031.fdocuments.in/reader031/viewer/2022020704/61fb51a02e268c58cd5cc260/html5/thumbnails/16.jpg)
Project Manager Roles and Responsibilities con’t
Manages scope, schedule and budgetResolution of project issues not resolved by team consensusResponsible for obtaining approvals for all project changesManages consultant contractsCoordinates Public Involvement with CCP (Communication & Community Partnerships)
![Page 17: Arizona Dept. of Transportation Project Management](https://reader031.fdocuments.in/reader031/viewer/2022020704/61fb51a02e268c58cd5cc260/html5/thumbnails/17.jpg)
Project Manager Authority
Limited AuthorityEmpowered to make scope, schedule and budget decisions with team consensus Communication and consensus building skills essential
![Page 18: Arizona Dept. of Transportation Project Management](https://reader031.fdocuments.in/reader031/viewer/2022020704/61fb51a02e268c58cd5cc260/html5/thumbnails/18.jpg)
Project Manager Accountability
Ensure Process is followedProject Scope Timely escalation of issues
![Page 19: Arizona Dept. of Transportation Project Management](https://reader031.fdocuments.in/reader031/viewer/2022020704/61fb51a02e268c58cd5cc260/html5/thumbnails/19.jpg)
Project Tracking
PPMS tracks all project schedules –PrimaveraProject Work Plans are to be developed for every project (This is one area we don’t do well and need to do differently)
![Page 20: Arizona Dept. of Transportation Project Management](https://reader031.fdocuments.in/reader031/viewer/2022020704/61fb51a02e268c58cd5cc260/html5/thumbnails/20.jpg)
Performance Measures
Project Delivery – Percentage of projects and dollar value delivered each quarterConstruction – Final cost growth compared to the bid amount5.75% Incentive Pay for meeting goals
![Page 21: Arizona Dept. of Transportation Project Management](https://reader031.fdocuments.in/reader031/viewer/2022020704/61fb51a02e268c58cd5cc260/html5/thumbnails/21.jpg)
Reasons for Success
Corporate Culture of Project DeliveryDedicated Project ManagersWell defined Five-Year ProgramEarly Planning and Scoping Extensive use of Consultants
![Page 22: Arizona Dept. of Transportation Project Management](https://reader031.fdocuments.in/reader031/viewer/2022020704/61fb51a02e268c58cd5cc260/html5/thumbnails/22.jpg)
Things to Improve
TrainingProject Manager guidanceBetter maintenance feedback
![Page 23: Arizona Dept. of Transportation Project Management](https://reader031.fdocuments.in/reader031/viewer/2022020704/61fb51a02e268c58cd5cc260/html5/thumbnails/23.jpg)
Questions?