Architectural Technology 3.1 Case Study
description
Transcript of Architectural Technology 3.1 Case Study
![Page 1: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/1.jpg)
John Hope GatewayRoyal Botanical Gardens, Edinburgh
Architectural Technology 3.1
![Page 2: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/2.jpg)
Sam Hayes33241624
Aaron Morris33250666
Yuen Chak Ngai33242502
Daniel Whelan33245349
Brad McArdle33255523
Jan Harmens33254426
Christopher Pepper33250999
Stewart Craven33259578
![Page 3: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/3.jpg)
intr
od
uct
ion
Building: John Hope Gateway.Client: Royal Botanical Gardens.
Location: Edinburgh, Scotland.Architect: Edward Cullinan Architects.
Contractor: Xircon.Completion: 2009.
Value: £10,700,000.
![Page 4: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/4.jpg)
intr
od
uct
ion
The John Hope Gateway is home to Edinburgh’s botanical gardens. Building was designed by Edward Cullinan Architects and was
completed in 2009. The building is situated to the north of Edinburgh city centre. The building beautifully fits into its surrounding
environment making for a stunning link between nature and architecture.
A sustainable, low-energy, minimum-waste approach to the building's design became part of the message the Garden wished to convey to its
visitors. The Gateway has many demonstrable environmental solutions, including a biomass boiler, a green roof, rainwater
harvesting, a wind turbine, natural ventilation and passive night-time cooling.
![Page 5: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/5.jpg)
KLH by the nature of its product, is a specialistin sustainable construction.
The cross laminated timber is produced from spruce and fir trees. They do not release co2 in production and can be recycled and reused to make other forms of timber panels.
Much of the by-product is used to manufacture our own biomass pellets which generate heat / power in the KLH factory, with the excess being sold to local CHP plants.
KLH
cro
ss-l
amin
ated
tim
be
r p
anel
s
![Page 6: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/6.jpg)
Using KLH timber panels do not just create environmental benefits, but it can also save the cost of the building.
-Lighter structure, more economic design of the substructure and foundations (less concrete)
- Reduction on the the thickness of the transfer slab(less concrete)
- Prelims can be reduced due to the shortened construction programme
- Programming can be enhanced. E.g. pre-ordering windows, will be delivered to site.
KLH
cro
ss-l
amin
ated
tim
be
r p
anel
s
![Page 7: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/7.jpg)
Cross-laminated timber (KLH) is produced from spruce strips that are stacked crosswise on top of each other and glued to each other. Depending on the purpose and static requirement, the plates are available in 3, 5, 7 or more board layers
Exp
lora
tio
n o
f th
e cr
oss
-lam
inat
ed t
imb
er
pan
els
![Page 8: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/8.jpg)
Compared to conventional timber construction products, cross-laminated timber offers entirely new possibilities when it comes to load transfer. Not only can loads be transferred in one direction but on all sides.
Exp
lora
tio
n o
f th
e cr
oss
-lam
inat
ed t
imb
er
pan
els
![Page 9: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/9.jpg)
The crossways arrangement of the longitudinal and crosswise lamellas reduces the swelling and shrinkage in the board plane to an insignificant minimum - static strength and shape retention increase considerably.
Exp
lora
tio
n o
f th
e cr
oss
-lam
inat
ed t
imb
er
pan
els
![Page 10: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/10.jpg)
The KLH Massivholz GmbH factories in Austria, cutting and beaming of KLH solid cross laminated timber boards takes place using state-of-the-art CNC technology.
Exp
lora
tio
n o
f th
e cr
oss
-lam
inat
ed t
imb
er
pan
els
![Page 11: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/11.jpg)
Because of the cross-lamination timber , the KLH panels are stronger than conventional wood products.
Exp
lora
tio
n o
f th
e cr
oss
-lam
inat
ed t
imb
er
pan
els
![Page 12: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/12.jpg)
The CO2 is absorbed by the trees, and the carbon is stored and oxygen been released.
With 1m³ of KLH panels will have approx 240-250kg of "locked-in" carbon.
The John Hope Gateway Biodiversity Centre has used 674m³ of KLH timber, which has locked 161760-168500kg of carbon.
KLH
cro
ss-l
amin
ated
tim
be
r p
anel
s
![Page 13: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/13.jpg)
Stru
ctu
re in
pla
n Ground floor plan
Single height columns
![Page 14: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/14.jpg)
Stru
ctu
re in
pla
n Ground floor plan
Double height columns
![Page 15: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/15.jpg)
Stru
ctu
re in
pla
n Ground floor plan
Load bearing masonry
![Page 16: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/16.jpg)
Stru
ctu
re in
pla
n First floor plan
Double storey columns
![Page 17: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/17.jpg)
Stru
ctu
re in
pla
n First floor plan
Load bearing masonry
![Page 18: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/18.jpg)
Stru
ctu
ral S
yste
m –
Pri
mar
y &
sec
on
dar
y
Longitudinal section A-A
Cross section B-B
1. Concrete pad foundations2. Concrete/Dolomite Floor3. Cold rolled mild steel columns4. First floor KLH beams5. Diagonal roof bracing
A
A
B
B
![Page 19: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/19.jpg)
Longitudinal section
Cross section
Stru
ctu
ral S
yste
m –
Pri
mar
y &
sec
on
dar
y
1. Concrete pad foundations2. Concrete/Dolomite Floor3. Cold rolled mild steel columns4. First floor KLH beams5. Diagonal roof bracing
![Page 20: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/20.jpg)
Longitudinal section
Cross section
Stru
ctu
ral S
yste
m –
Pri
mar
y &
sec
on
dar
y
1. Concrete pad foundations2. Concrete/Dolomite Floor3. Cold rolled mild steel columns4. First floor KLH beams5. Diagonal roof bracing
![Page 21: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/21.jpg)
Longitudinal section
Cross section
Stru
ctu
ral S
yste
m –
Pri
mar
y &
sec
on
dar
y
1. Concrete pad foundations2. Concrete/Dolomite Floor3. Cold rolled mild steel columns4. First floor KLH beams5. Diagonal roof bracing
![Page 22: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/22.jpg)
Longitudinal section
Cross section
Stru
ctu
ral S
yste
m –
Pri
mar
y &
sec
on
dar
y
1. Concrete pad foundations2. Concrete/Dolomite Floor3. Cold rolled mild steel columns4. First floor KLH beams5. Diagonal roof bracing
![Page 23: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/23.jpg)
Longitudinal section
Cross section
Stru
ctu
ral S
yste
m –
Pri
mar
y &
sec
on
dar
y
1. Concrete pad foundations2. Concrete/Dolomite Floor3. Cold rolled mild steel columns4. First floor KLH beams5. Diagonal roof bracing
![Page 24: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/24.jpg)
Stru
ctu
ral S
yste
m –
Fou
nd
atio
n p
late
Steel base plate- The steel base plate is set into the concrete pad- Hessian sacks allow for tolerances needed when the column is introduced later on
![Page 25: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/25.jpg)
Stru
ctu
ral S
yste
m –
Fou
nd
atio
n p
late
Shuttering- Ply shuttering is put up around the base plate so the next layers of concrete do not come in contact with steel
![Page 26: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/26.jpg)
Stru
ctu
ral S
yste
m –
Fou
nd
atio
n p
late
Floor construction -The floor is built up around the shuttering-The column is not put in place until the top layer of concrete has dried through
![Page 27: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/27.jpg)
Stru
ctu
ral S
yste
m –
Fou
nd
atio
n p
late
Column connection -The main column slots over the base plate- The hessian sacks under the base plate allow for slight movement of the column
![Page 28: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/28.jpg)
Stru
ctu
ral S
yste
m –
Fou
nd
atio
n p
late
Grout- Grout is applied around the base plate to create a solid connection
![Page 29: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/29.jpg)
Stru
ctu
ral S
yste
m –
Fou
nd
atio
n p
late
Concrete back fill- The remaining gap is backfilled with concrete once the column is in the correct position
![Page 30: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/30.jpg)
Stru
ctu
ral S
yste
m –
Co
lum
n b
uild
up
1. Inner supports2. Main column3. Top column connection4. Base connection5. First floor connection6. Flitch plate
![Page 31: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/31.jpg)
1. Inner supports2. Main column3. Top column connection4. Base connection5. First floor connection6. Flitch plate
Stru
ctu
ral S
yste
m –
Co
lum
n b
uild
up
-The inner supports prevent the column from warping- There are a total of 4 cross sections- The gap in the middle is for the later first floor connection plate
![Page 32: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/32.jpg)
Stru
ctu
ral S
yste
m –
Co
lum
n b
uild
up
1. Inner supports2. Main column3. Top column connection4. Base connection5. First floor connection6. Flitch plate
- The outer L plates are welded onto the inner supports- These will be done to a high tolerance to ensure that when they arrive on site they can be put in place quickly
![Page 33: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/33.jpg)
Stru
ctu
ral S
yste
m –
Co
lum
n b
uild
up
1. Inner supports2. Main column3. Top column connection4. Base connection5. First floor connection6. Flitch plate
![Page 34: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/34.jpg)
Stru
ctu
ral S
yste
m –
Co
lum
n b
uild
up
1. Inner supports2. Main column3. Top column connection4. Base connection5. First floor connection6. Flitch plate
-The top connection plate welds into the column
![Page 35: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/35.jpg)
Stru
ctu
ral S
yste
m –
Co
lum
n b
uild
up
1. Inner supports2. Main column3. Top column connection4. Base connection5. First floor connection6. Flitch plate
![Page 36: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/36.jpg)
Stru
ctu
ral S
yste
m –
Co
lum
n b
uild
up
1. Inner supports2. Main column3. Top column connection4. Base connection5. First floor connection6. Flitch plate
-The bottom connection is welded onto the column
![Page 37: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/37.jpg)
Stru
ctu
ral S
yste
m –
Co
lum
n b
uild
up
1. Inner supports2. Main column3. Top column connection4. Base connection5. First floor connection6. Flitch plate
![Page 38: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/38.jpg)
Stru
ctu
ral S
yste
m –
Co
lum
n b
uild
up
1. Inner supports2. Main column3. Top column connection4. Base connection5. First floor connection6. Flitch plate
-The first floor connection plate should just slot through the column and be welded to the existing structure
![Page 39: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/39.jpg)
Stru
ctu
ral S
yste
m –
Co
lum
n b
uild
up
1. Inner supports2. Main column3. Top column connection4. Base connection5. First floor connection6. Flitch plate
![Page 40: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/40.jpg)
Stru
ctu
ral S
yste
m –
Co
lum
n b
uild
up
1. Inner supports2. Main column3. Top column connection4. Base connection5. First floor connection6. Flitch plate
-The flitch plate slots though the top welded connection -This is again welded to the existing column
![Page 41: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/41.jpg)
Stru
ctu
ral S
yste
m –
Co
lum
n b
uild
up
1. Inner supports2. Main column3. Top column connection4. Base connection5. First floor connection6. Flitch plate
![Page 42: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/42.jpg)
Stru
ctu
ral S
yste
m
Pad foundation-The pad foundation is cast with the connection plate inside it- Any required movement in the base plate is accommodated by the hessian sacks
![Page 43: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/43.jpg)
Stru
ctu
ral S
yste
m
Shuttering- Ply shuttering is put up around the base plate so the next layers of concrete do not come in contact with steel
![Page 44: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/44.jpg)
Stru
ctu
ral S
yste
m
Dolomite layer-Dolomite is the first layer to be poured on site- 200mm thick
![Page 45: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/45.jpg)
Stru
ctu
ral S
yste
m
Blinding layer-A thin blinding layer is cast to seal the lower levels
![Page 46: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/46.jpg)
Stru
ctu
ral S
yste
m
Concrete layer- A concrete base is poured for the main floor structure- 150mm thick
![Page 47: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/47.jpg)
Stru
ctu
ral S
yste
m
DPM-The damp proof membrane is laid over the concrete
![Page 48: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/48.jpg)
Stru
ctu
ral S
yste
m
Insulation-Rigid insulation is placed over the DPM layer- 100mm thick
![Page 49: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/49.jpg)
Stru
ctu
ral S
yste
m
Final concrete layer-The top layer of concrete is polished to make it aesthetically pleasing - 100mm thick
![Page 50: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/50.jpg)
Stru
ctu
ral S
yste
m
Main column-The main columns are now introduced on site once the floor build up is complete- These columns can be slightly altered due to hessian sacks in the foundations
![Page 51: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/51.jpg)
Stru
ctu
ral S
yste
m
Concrete backfill-Once the column has been welded in place, concrete is poured to secure the column
![Page 52: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/52.jpg)
Stru
ctu
ral S
yste
m
First floor beams- Paired 210mm x 815mm gluelam beams are lifted between the columns- There are two different sizes in columns
![Page 53: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/53.jpg)
Stru
ctu
ral S
yste
m
First floor beams- Steel bolts are then put through both beams and the central connection plate- Total of 18 bolts hold both beams in place
![Page 54: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/54.jpg)
Stru
ctu
ral S
yste
m
KLH floor panels- The KLH floor panels are now lifted and dropped in place individually- Each panel is 2m x 6m- 226mm thick
![Page 55: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/55.jpg)
Stru
ctu
ral S
yste
m
KLH floor panels- The KLH floor panels are now lifted and dropped in place individually-Each panel is 2m x 6m- 226mm thick
![Page 56: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/56.jpg)
Stru
ctu
ral S
yste
m
KLH floor panels- The KLH floor panels are now lifted and dropped in place individually-Each panel is 2m x 6m- 226mm thick
![Page 57: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/57.jpg)
Stru
ctu
ral S
yste
m
KLH floor panels- The KLH floor panels are now lifted and dropped in place individually-Each panel is 2m x 6m- 226mm thick
![Page 58: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/58.jpg)
Stru
ctu
ral S
yste
m
Top flitch plate- Now that the first floor is in, the top flitch plate can be prepped to receive the roof beams
![Page 59: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/59.jpg)
Stru
ctu
ral S
yste
m
Roof beams - Each beam is exactly the same as tapers from 1035mm to 500mm- A slot is cut from the larger end to receive the flitch plate
![Page 60: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/60.jpg)
Stru
ctu
ral S
yste
m
Roof beams - M24 bolts go through the beams and the connection plate to secure the beams in place- There are 24 bolts in total holding each beam
![Page 61: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/61.jpg)
Stru
ctu
ral S
yste
m
Roof beams - M24 bolts go through the beams and the connection plate to secure the beams in place- There are 24 bolts in total holding each beam
![Page 62: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/62.jpg)
Stru
ctu
ral S
yste
m
Connection plates- Each connection plate, connects four different beams together
![Page 63: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/63.jpg)
Stru
ctu
ral S
yste
m
Connection plates- Each connection plate, connects four different beams together
![Page 64: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/64.jpg)
Stru
ctu
ral S
yste
m
Connection plates- The arrangement of the bolts helps visitors understand the structure; a circular arrangement indicates a rotational force or movement while a vertical arrangement indicates a vertical force or shear.
![Page 65: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/65.jpg)
Stru
ctu
ral S
yste
m
KLH roof panels- The roof panels are also made of KLH panels- 2m x 6m- 226mm thick
![Page 66: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/66.jpg)
Stru
ctu
ral S
yste
m
KLH roof panels- The roof panels are also made of KLH panels- 2m x 6m- 226mm thick
![Page 67: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/67.jpg)
Stru
ctu
ral S
yste
m
KLH roof panels- The roof panels are also made of KLH panels- 2m x 6m- 226mm thick
![Page 68: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/68.jpg)
Stru
ctu
ral S
yste
m
KLH roof panels- The roof panels are also made of KLH panels- 2m x 6m- 226mm thick
![Page 69: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/69.jpg)
Load Paths: A Live Load in the Office Space. The Occupier
Live
Lo
ads
![Page 70: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/70.jpg)
Gravity Exerts a Vertical Load on the First Floor
Live
Lo
ads
![Page 71: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/71.jpg)
Gravity Exerts a Vertical Load on the First FloorWhere the Seven Laminations of 42mm Thick KLH Panels form a stable platform
Live
Lo
ads
![Page 72: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/72.jpg)
Gravity Exerts a Vertical Load on the First FloorWhere the Seven Laminations of 42mm Thick KLH Panels form a stable platformAnd Distributes the Load Evenly Across the Panels
Live
Lo
ads
![Page 73: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/73.jpg)
Gravity Exerts a Vertical Load on the First FloorWhere the Seven Laminations of 42mm Thick KLH Panels form a stable platformAnd Distributes the Load Evenly Across the Panels To 855mm Thick Beams
Live
Lo
ads
![Page 74: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/74.jpg)
Gravity Exerts a Vertical Load on the First FloorWhere the Seven Laminations of 42mm Thick KLH Panels form a stable platformAnd Distributes the Load Evenly Across the Panels To 855mm Thick BeamsWhich Connect to and Transfer the Load to Columns Laid on a 6m by 8m GridLi
ve L
oad
s
![Page 75: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/75.jpg)
Gravity Exerts a Vertical Load on the First FloorWhere the Seven Laminations of 42mm Thick KLH Panels form a stable platformAnd Distributes the Load Evenly Across the Panels To 855mm Thick BeamsWhich Connect to and Transfer the Load to Columns Laid on a 6m by 8m GridAnd then Delivers the Load to a Composite Pad and Raft Foundation
Live
Lo
ads
![Page 76: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/76.jpg)
Gravity Exerts a Vertical Load on the First FloorWhere the Seven Laminations of 42mm Thick KLH Panels form a stable platformAnd Distributes the Load Evenly Across the Panels To 855mm Thick BeamsWhich Connect to and Transfer the Load to Columns Laid on a 6m by 8m GridAnd then Delivers the Load to a Composite Pad and Raft FoundationWhere the Ground Resists With an Equal and Opposite Force
Live
Lo
ads
![Page 77: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/77.jpg)
Load Paths: A Dead Load on the Roof. The Skylight
De
ad L
oad
s
![Page 78: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/78.jpg)
The Mass of the Skylight Exerts a Force
De
ad L
oad
s
![Page 79: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/79.jpg)
The Mass of the Skylight Exerts a ForceOnto the Diagonal Grid Roof Beams,
De
ad L
oad
s
![Page 80: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/80.jpg)
The Mass of the Skylight Exerts a ForceOnto the Diagonal Grid Roof BeamsWhich Transfer the Load onto the Flitch Plate of the Columns
De
ad L
oad
s
![Page 81: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/81.jpg)
The Mass of the Skylight Exerts a ForceOnto the Diagonal Grid Roof BeamsWhich Transfer the Load onto the Flitch Plate of the ColumnsAnd Turns the Horizontal force into a Vertical Force
De
ad L
oad
s
![Page 82: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/82.jpg)
The Mass of the Skylight Exerts a ForceOnto the Diagonal Grid Roof BeamsWhich Transfers the Load onto the Flitch Plate of the ColumnsAnd Turns the Horizontal force into a Vertical ForceThat Then Travels Down the Columns
De
ad L
oad
s
![Page 83: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/83.jpg)
The Mass of the Skylight Exerts a ForceOnto the Diagonal Grid Roof BeamsWhich Transfer the Load onto the Flitch Plate of the ColumnsAnd Turns the Horizontal force into a Vertical ForceThat Then Travels Down the ColumnsAnd Into the Pad and Raft Composite FoundationD
ead
Lo
ads
![Page 84: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/84.jpg)
The Mass of the Skylight Exerts a ForceOnto the Diagonal Grid Roof BeamsWhich Transfer the Load onto the Flitch Plate of the ColumnsAnd Turns the Horizontal force into a Vertical ForceThat Then Travels Down the ColumnsAnd Into the Pad and Raft Composite FoundationWhere the Ground Exerts an Equal and Opposite ForceD
ead
Lo
ads
![Page 85: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/85.jpg)
Co
nst
ruct
ion
bu
ild-u
p
Basement floor-In-situ concrete is cast for the basement floor- 250mm thick
![Page 86: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/86.jpg)
Co
nst
ruct
ion
bu
ild-u
p
Basement floor-In-situ concrete is cast for the basement floor- 250mm thick
![Page 87: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/87.jpg)
Co
nst
ruct
ion
bu
ild-u
p
Basement walls-In-situ concrete walls are cast using plyboard shuttering- 250mm thick
![Page 88: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/88.jpg)
Co
nst
ruct
ion
bu
ild-u
p
Basement ceiling construction - Acroprops are put in place the support the shuttering for the ceiling poor
![Page 89: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/89.jpg)
Co
nst
ruct
ion
bu
ild-u
p
Concrete roof shuttering- Plyboard is layered to create the shuttering
![Page 90: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/90.jpg)
Co
nst
ruct
ion
bu
ild-u
p
Basement roof- 250mm thick pre-cast concrete slabs
![Page 91: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/91.jpg)
Co
nst
ruct
ion
bu
ild-u
p
Site backfill- Once the basement concrete panels have been positioned , the basement excavation is backfilled
![Page 92: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/92.jpg)
Co
nst
ruct
ion
bu
ild-u
p
Pad foundations- As a result of good load bearing underlying strata, pad foundations were the most suitable choice of main foundation - The pad foundations are positioned on a 6m x 8m grid which is shared by the primary structural system-There are two sizes of pad foundations. The larger 1500mm x 1500mm x 800mm pads support the primary structural steel columnswhereas the smaller 1200mm x 1200mm x 800mm pads support the wooden cladding facade and atrium area
![Page 93: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/93.jpg)
Co
nst
ruct
ion
bu
ild-u
p
Alternative foundations-Raft foundations were used in areas of load bearing capacity such as the entrance and structural cores- Strip foundations were used for elongated load bearing retaining walls at the rear of the building
![Page 94: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/94.jpg)
Co
nst
ruct
ion
bu
ild-u
p
Shuttering - The foundation perimeter is encased with ply board shuttering
![Page 95: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/95.jpg)
Co
nst
ruct
ion
bu
ild-u
p
Dolomite/hardcore layer-A 200mm thick compacted dolomite is poured around the plyboard shuttering
![Page 96: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/96.jpg)
Co
nst
ruct
ion
bu
ild-u
p
Blinding/screed layer- A 6mm blinding layer is poured to fill and cracks and gaps within the dolomite to prevent water causing a freeze thaw effect which ultimately prevents cracking within the dolomite and concrete foundations
![Page 97: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/97.jpg)
Co
nst
ruct
ion
bu
ild-u
p
Concrete- A concrete layer is poured over reinforced steel re-bar which together act as a composite layer to help distribute uneven loads- The concrete is 150mm thick and completes the structural foundations
![Page 98: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/98.jpg)
Co
nst
ruct
ion
bu
ild-u
p
DPC- The damp proof course is laid over the entire length of the concrete for waterproofing purposes
![Page 99: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/99.jpg)
Co
nst
ruct
ion
bu
ild-u
p
Insulation- 100mm thick Kingspan rockwool insulation is laid
![Page 100: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/100.jpg)
Co
nst
ruct
ion
bu
ild-u
p
Under floor heating- Polybutylene piping is laid out over the insulation in isolation zones to allow different areas of the building to be heated individually
![Page 101: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/101.jpg)
Co
nst
ruct
ion
bu
ild-u
p
Polished concrete-A 100mm thick layer of concrete with marble veneer finish to complete the finished floor level of 600mm
![Page 102: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/102.jpg)
Co
nst
ruct
ion
bu
ild-u
p
Remove shuttering- Now that the floor build up is complete the shuttering can be removed
![Page 103: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/103.jpg)
Co
nst
ruct
ion
bu
ild-u
p
Single storey columns- 12 columns are welded into position, attached to the pad foundations . The steel work will start in one corner and progress across site to add strength during the construction sequence
![Page 104: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/104.jpg)
Co
nst
ruct
ion
bu
ild-u
p
Entrance columns- Full height cold rolled mild steel including flitch plates are erected in the atrium area due to full height uninterrupted nature
![Page 105: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/105.jpg)
Co
nst
ruct
ion
bu
ild-u
p
Load bearing masonry- Along steel work a group of brick layers
will start laying load bearing masonry
![Page 106: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/106.jpg)
Co
nst
ruct
ion
bu
ild-u
p
First floor beams- First floor beams are introduced while steel beams are still being erected to provide lateral strength during the build process to withstand wind loading
![Page 107: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/107.jpg)
Co
nst
ruct
ion
bu
ild-u
p
Continuation of columns and beams- Steel and load bearing masonry progress
![Page 108: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/108.jpg)
Co
nst
ruct
ion
bu
ild-u
p
Continuation of columns, beams and advanced brickwork
![Page 109: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/109.jpg)
Co
nst
ruct
ion
bu
ild-u
p
Continuation of columns and beams- Steel and load bearing masonry progress
![Page 110: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/110.jpg)
Co
nst
ruct
ion
bu
ild-u
p
Completion of columns and beams- Steel and load bearing masonry progress
![Page 111: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/111.jpg)
Co
nst
ruct
ion
bu
ild-u
p
Advanced ramp brickwork and pond concrete- The load bearings areas are completed with cavity and window and door openings- Wet tradesman will then start laying the in-situ concrete retaining walls for the water feature
![Page 112: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/112.jpg)
Co
nst
ruct
ion
bu
ild-u
p
KLH floor panels- 2m x 6m KLH panels are added to provide horizontal support during construction
![Page 113: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/113.jpg)
Co
nst
ruct
ion
bu
ild-u
p
Diagonal roof bracing- The diaconal roof bracing is erected in a similar fashion to the columns by building from a corner and progressing across the building
![Page 114: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/114.jpg)
Co
nst
ruct
ion
bu
ild-u
p
Continuation of diagonal roof bracing- Diagonal roof bracing progress
![Page 115: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/115.jpg)
Co
nst
ruct
ion
bu
ild-u
p
Continuation of diagonal roof bracing- Diagonal roof bracing progress
![Page 116: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/116.jpg)
Co
nst
ruct
ion
bu
ild-u
p
Continuation of diagonal roof bracing- Diagonal roof bracing progress
![Page 117: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/117.jpg)
Co
nst
ruct
ion
bu
ild-u
p
Continuation of diagonal roof bracing- Diagonal roof bracing progress
![Page 118: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/118.jpg)
Co
nst
ruct
ion
bu
ild-u
p
KLH roof panels-Each KLH panel has seven laminate layers totalling 226mm thick and are 2m x 6m- The KLH panels span a total of 100m x 50m
![Page 119: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/119.jpg)
Co
nst
ruct
ion
bu
ild-u
p
Entrance columns- Atrium glazing framework connected to steel base plates which connect to concrete raft foundations
![Page 120: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/120.jpg)
Co
nst
ruct
ion
bu
ild-u
p
Lower cladding- Lower cladding is constructed of 3000mm x 250mm x 50mm stained Scots Pine
![Page 121: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/121.jpg)
Co
nst
ruct
ion
bu
ild-u
p
Intermediate cladding-Intermediate cladding is constructed of 3000mm x 250mm x 50mm dark stained Scots Pine-- Complete with internal window glazing and 1100mm tall vertical louvre system
![Page 122: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/122.jpg)
Co
nst
ruct
ion
bu
ild-u
p
Final cladding-Final cladding is constructed of 3000mm x 250mm x 50mm stained Scots Pine and forms the structural basis of the roof parapett
![Page 123: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/123.jpg)
Co
nst
ruct
ion
bu
ild-u
p
Zinc roof-Zinc flashing completes the wooden cladding by providing a waterproof layer for the parapettroof- A zinc roof is added to toilets complete with aluminium grey water storage sistern
![Page 124: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/124.jpg)
Co
nst
ruct
ion
bu
ild-u
p
DPC
![Page 125: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/125.jpg)
Co
nst
ruct
ion
bu
ild-u
p
Insulation- 100mm thick rigid insulation
![Page 126: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/126.jpg)
Co
nst
ruct
ion
bu
ild-u
p
Concrete tray- A corrugated 12mm thick 100mm riveted concrete in-filled tray is constructed
![Page 127: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/127.jpg)
Co
nst
ruct
ion
bu
ild-u
p
Sedum bedding tray- Several containment trays are formed as part of the Sedum roof
![Page 128: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/128.jpg)
Co
nst
ruct
ion
bu
ild-u
p
Soil- Compacted aerated soil is filled to accommodate Sedum layer
![Page 129: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/129.jpg)
Co
nst
ruct
ion
bu
ild-u
p
Pebbles- A layer of medium to fine course pebbles surround the soil filled containment rays to provide increased drainage
![Page 130: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/130.jpg)
Co
nst
ruct
ion
bu
ild-u
p
Soffit- A finishing layer of wood encases and
waterproofs the roof build up
![Page 131: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/131.jpg)
Co
nst
ruct
ion
bu
ild-u
p
ETFE roof skylights-Steel framework, timber batons, plastic window frames, glazing and ETFE skylight roofing are added along with remaining windows to weather proof the building
![Page 132: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/132.jpg)
Co
nst
ruct
ion
bu
ild-u
p
Glazing- By starting the construction in January the building was weatherproof by the start of next winter, allowing for internal walls and first fix progression while construction is not viable due to weather
![Page 133: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/133.jpg)
Co
nst
ruct
ion
bu
ild-u
p
Sedum roof- The Sedum roof is used as a dual purpose facility, it is a lightweight, cheap and efficient insulation layer. It also collects a larger volume of water for the grey water system
![Page 134: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/134.jpg)
Caf
é ar
ea s
ecti
on 1) Pad foundations and columns
![Page 135: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/135.jpg)
Caf
é ar
ea s
ecti
on 1) Pad foundations and columns
2) Insulation bracket
![Page 136: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/136.jpg)
Caf
é ar
ea s
ecti
on 1) Pad foundations and columns
2) Insulation bracket 3) Below slab insulation
![Page 137: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/137.jpg)
Caf
é ar
ea s
ecti
on 1) Pad foundations and columns
2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab
![Page 138: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/138.jpg)
Caf
é ar
ea s
ecti
on 1) Pad foundations and columns
2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane
![Page 139: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/139.jpg)
Caf
é ar
ea s
ecti
on 1) Pad foundations and columns
2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping
![Page 140: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/140.jpg)
Caf
é ar
ea s
ecti
on 1) Pad foundations and columns
2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP
![Page 141: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/141.jpg)
Caf
é ar
ea s
ecti
on
![Page 142: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/142.jpg)
Caf
é ar
ea s
ecti
on 1) Pad foundations and columns
2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete
![Page 143: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/143.jpg)
Caf
é ar
ea s
ecti
on 1) Pad foundations and columns
2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation
![Page 144: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/144.jpg)
Caf
é ar
ea s
ecti
on 1) Pad foundations and columns
2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane
![Page 145: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/145.jpg)
Caf
é ar
ea s
ecti
on 1) Pad foundations and columns
2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks
![Page 146: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/146.jpg)
Caf
é ar
ea s
ecti
on 1) Pad foundations and columns
2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall
![Page 147: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/147.jpg)
Caf
é ar
ea s
ecti
on 1) Pad foundations and columns
2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall13) Floor beams
![Page 148: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/148.jpg)
Caf
é ar
ea s
ecti
on 1) Pad foundations and columns
2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall13) Floor beams14) Cross laminated timber panel
![Page 149: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/149.jpg)
Caf
é ar
ea s
ecti
on 1) Pad foundations and columns
2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall13) Floor beams14) Cross laminated timber panel15) Single poly membrane
![Page 150: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/150.jpg)
Caf
é ar
ea s
ecti
on 1) Pad foundations and columns
2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall13) Floor beams14) Cross laminated timber panel15) Single poly membrane 16) Beam
![Page 151: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/151.jpg)
Caf
é ar
ea s
ecti
on 1) Pad foundations and columns
2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall13) Floor beams14) Cross laminated timber panel15) Single poly membrane 16) Beam17) Beam fixing
![Page 152: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/152.jpg)
Caf
é ar
ea s
ecti
on 1) Pad foundations and columns
2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall13) Floor beams14) Cross laminated timber panel15) Single poly membrane 16) Beam17) Beam fixing18) Beam
![Page 153: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/153.jpg)
Caf
é ar
ea s
ecti
on 1) Pad foundations and columns
2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall13) Floor beams14) Cross laminated timber panel15) Single poly membrane 16) Beam17) Beam fixing18) Beam19) Under floor heating
![Page 154: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/154.jpg)
Caf
é ar
ea s
ecti
on 1) Pad foundations and columns
2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall13) Floor beams14) Cross laminated timber panel15) Single poly membrane 16) Beam17) Beam fixing18) Beam19) Under floor heating
![Page 155: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/155.jpg)
Caf
é ar
ea s
ecti
on 1) Pad foundations and columns
2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall13) Floor beams14) Cross laminated timber panel15) Single poly membrane 16) Beam17) Beam fixing18) Beam19) Under floor heating20) Raised timber floor
![Page 156: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/156.jpg)
Caf
é ar
ea s
ecti
on 1) Pad foundations and columns
2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall13) Floor beams14) Cross laminated timber panel15) Single poly membrane 16) Beam17) Beam fixing18) Beam19) Under floor heating20) Raised timber floor
![Page 157: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/157.jpg)
Caf
é ar
ea s
ecti
on 1) Pad foundations and columns
2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall13) Floor beams14) Cross laminated timber panel15) Single poly membrane 16) Beam17) Beam fixing18) Beam19) Under floor heating20) Raised timber floor21) Column
![Page 158: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/158.jpg)
Caf
é ar
ea s
ecti
on 1) Pad foundations and columns
2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall13) Floor beams14) Cross laminated timber panel15) Single poly membrane 16) Beam17) Beam fixing18) Beam19) Under floor heating20) Raised timber floor21) Column22) Timber decking
![Page 159: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/159.jpg)
Caf
é ar
ea s
ecti
on 1) Pad foundations and columns
2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall13) Floor beams14) Cross laminated timber panel15) Single poly membrane 16) Beam17) Beam fixing18) Beam19) Under floor heating20) Raised timber floor21) Column22) Timber decking23) Pressed metal insulated panel
![Page 160: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/160.jpg)
Caf
é ar
ea s
ecti
on 1) Pad foundations and columns
2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall13) Floor beams14) Cross laminated timber panel15) Single poly membrane 16) Beam17) Beam fixing18) Beam19) Under floor heating20) Raised timber floor21) Column22) Timber decking23) Pressed metal insulated panel
![Page 161: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/161.jpg)
Caf
é ar
ea s
ecti
on 1) Pad foundations and columns
2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall13) Floor beams14) Cross laminated timber panel15) Single poly membrane 16) Beam17) Beam fixing18) Beam19) Under floor heating20) Raised timber floor21) Column22) Timber decking23) Pressed metal insulated panel
![Page 162: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/162.jpg)
Caf
é ar
ea s
ecti
on 1) Pad foundations and columns
2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall13) Floor beams14) Cross laminated timber panel15) Single poly membrane 16) Beam17) Beam fixing18) Beam19) Under floor heating20) Raised timber floor21) Column22) Timber decking23) Pressed metal insulated panel
![Page 163: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/163.jpg)
Caf
é ar
ea s
ecti
on 1) Pad foundations and columns
2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall13) Floor beams14) Cross laminated timber panel15) Single poly membrane 16) Beam17) Beam fixing18) Beam19) Under floor heating20) Raised timber floor21) Column22) Timber decking23) Pressed metal insulated panel24) Glass
![Page 164: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/164.jpg)
Caf
é ar
ea s
ecti
on 1) Pad foundations and columns
2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall13) Floor beams14) Cross laminated timber panel15) Single poly membrane 16) Beam17) Beam fixing18) Beam19) Under floor heating20) Raised timber floor21) Column22) Timber decking23) Pressed metal insulated panel24) Glass25) Pressed metal insulation pad
![Page 165: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/165.jpg)
Caf
é ar
ea s
ecti
on 1) Pad foundations and columns
2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall13) Floor beams14) Cross laminated timber panel15) Single poly membrane 16) Beam17) Beam fixing18) Beam19) Under floor heating20) Raised timber floor21) Column22) Timber decking23) Pressed metal insulated panel24) Glass25) Pressed metal insulation pad26) RWP
![Page 166: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/166.jpg)
Caf
é ar
ea s
ecti
on 1) Pad foundations and columns
2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall13) Floor beams14) Cross laminated timber panel15) Single poly membrane 16) Beam17) Beam fixing18) Beam19) Under floor heating20) Raised timber floor21) Column22) Timber decking23) Pressed metal insulated panel24) Glass25) Pressed metal insulation pad26) RWP27) Stone block
![Page 167: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/167.jpg)
Caf
é ar
ea s
ecti
on 1) Pad foundations and columns
2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall13) Floor beams14) Cross laminated timber panel15) Single poly membrane 16) Beam17) Beam fixing18) Beam19) Under floor heating20) Raised timber floor21) Column22) Timber decking23) Pressed metal insulated panel24) Glass25) Pressed metal insulation pad26) RWP27) Stone block28) Dressed coping stone
![Page 168: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/168.jpg)
Caf
é ar
ea s
ecti
on 1) Pad foundations and columns
2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall13) Floor beams14) Cross laminated timber panel15) Single poly membrane 16) Beam17) Beam fixing18) Beam19) Under floor heating20) Raised timber floor21) Column22) Timber decking23) Pressed metal insulated panel24) Glass25) Pressed metal insulation pad26) RWP27) Stone block28) Dressed coping stone29) Supports to roof
![Page 169: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/169.jpg)
Caf
é ar
ea s
ecti
on 1) Pad foundations and columns
2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall13) Floor beams14) Cross laminated timber panel15) Single poly membrane 16) Beam17) Beam fixing18) Beam19) Under floor heating20) Raised timber floor21) Column22) Timber decking23) Pressed metal insulated panel24) Glass25) Pressed metal insulation pad26) RWP27) Stone block28) Dressed coping stone29) Supports to roof30) Cross laminated timber panel
![Page 170: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/170.jpg)
Caf
é ar
ea s
ecti
on
1) Pad foundations and columns2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall13) Floor beams14) Cross laminated timber panel15) Single poly membrane 16) Beam17) Beam fixing18) Beam19) Under floor heating20) Raised timber floor21) Column22) Timber decking23) Pressed metal insulated panel24) Glass25) Pressed metal insulation pad26) RWP27) Stone block28) Dressed coping stone29) Supports to roof30) Cross laminated timber panel31) Sedum roof
![Page 171: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/171.jpg)
Caf
é ar
ea s
ecti
on
1) Pad foundations and columns2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall13) Floor beams14) Cross laminated timber panel15) Single poly membrane 16) Beam17) Beam fixing18) Beam19) Under floor heating20) Raised timber floor21) Column22) Timber decking23) Pressed metal insulated panel24) Glass25) Pressed metal insulation pad26) RWP27) Stone block28) Dressed coping stone29) Supports to roof30) Cross laminated timber panel31) Sedum roof32) Timber cap
![Page 172: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/172.jpg)
Caf
é ar
ea s
ecti
on
1) Pad foundations and columns2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall13) Floor beams14) Cross laminated timber panel15) Single poly membrane 16) Beam17) Beam fixing18) Beam19) Under floor heating20) Raised timber floor21) Column22) Timber decking23) Pressed metal insulated panel24) Glass25) Pressed metal insulation pad26) RWP27) Stone block28) Dressed coping stone29) Supports to roof30) Cross laminated timber panel31) Sedum roof32) Timber cap33) Sedum roof build up
![Page 173: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/173.jpg)
Caf
é ar
ea s
ecti
on
1) Pad foundations and columns2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall13) Floor beams14) Cross laminated timber panel15) Single poly membrane 16) Beam17) Beam fixing18) Beam19) Under floor heating20) Raised timber floor21) Column22) Timber decking23) Pressed metal insulated panel24) Glass25) Pressed metal insulation pad26) RWP27) Stone block28) Dressed coping stone29) Supports to roof30) Cross laminated timber panel31) Sedum roof32) Timber cap33) Sedum roof build up
![Page 174: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/174.jpg)
Caf
é ar
ea s
ecti
on
1) Pad foundations and columns2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall13) Floor beams14) Cross laminated timber panel15) Single poly membrane 16) Beam17) Beam fixing18) Beam19) Under floor heating20) Raised timber floor21) Column22) Timber decking23) Pressed metal insulated panel24) Glass25) Pressed metal insulation pad26) RWP27) Stone block28) Dressed coping stone29) Supports to roof30) Cross laminated timber panel31) Sedum roof32) Timber cap33) Sedum roof build up34) Outer flooring
![Page 175: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/175.jpg)
Typ
ical
wal
l sec
tio
n1) Concrete base
![Page 176: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/176.jpg)
Typ
ical
wal
l se
ctio
n1) Concrete base2) Pad foundations
![Page 177: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/177.jpg)
Typ
ical
wal
l sec
tio
n1) Concrete base2) Pad foundations3) Load bearing slab
![Page 178: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/178.jpg)
Typ
ical
wal
l sec
tio
n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks
![Page 179: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/179.jpg)
Typ
ical
wal
l sec
tio
n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing
![Page 180: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/180.jpg)
Typ
ical
wal
l sec
tio
n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane
![Page 181: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/181.jpg)
Typ
ical
wal
l sec
tio
n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab
![Page 182: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/182.jpg)
Typ
ical
wal
l sec
tio
n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain
![Page 183: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/183.jpg)
Typ
ical
wal
l sec
tio
n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation
![Page 184: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/184.jpg)
Typ
ical
wal
l sec
tio
n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation10) Façade fixtures
![Page 185: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/185.jpg)
Typ
ical
wal
l sec
tio
n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation10) Façade fixtures11) Breather membrane
![Page 186: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/186.jpg)
Typ
ical
wal
l sec
tio
n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation10) Façade fixtures11) Breather membrane12) Laminated timber panel
![Page 187: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/187.jpg)
Typ
ical
wal
l sec
tio
n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation10) Façade fixtures11) Breather membrane12) Laminated timber panel13) Horizontal timber element
![Page 188: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/188.jpg)
Typ
ical
wal
l sec
tio
n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation10) Façade fixtures11) Breather membrane12) Laminated timber panel13) Horizontal timber element14) Laminated timber panel
![Page 189: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/189.jpg)
Typ
ical
wal
l sec
tio
n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation10) Façade fixtures11) Breather membrane12) Laminated timber panel13) Horizontal timber element14) Laminated timber panel15) Cross laminated timber floor
![Page 190: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/190.jpg)
Typ
ical
wal
l sec
tio
n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation10) Façade fixtures11) Breather membrane12) Laminated timber panel13) Horizontal timber element14) Laminated timber panel15) Cross laminated timber floor16) Slotted MS cleat
![Page 191: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/191.jpg)
Typ
ical
wal
l sec
tio
n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation10) Façade fixtures11) Breather membrane12) Laminated timber panel13) Horizontal timber element14) Laminated timber panel15) Cross laminated timber floor16) Slotted MS cleat
![Page 192: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/192.jpg)
Typ
ical
wal
l sec
tio
n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation10) Façade fixtures11) Breather membrane12) Laminated timber panel13) Horizontal timber element14) Laminated timber panel15) Cross laminated timber floor16) Slotted MS cleat17) Insulation
![Page 193: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/193.jpg)
Typ
ical
wal
l sec
tio
n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation10) Façade fixtures11) Breather membrane12) Laminated timber panel13) Horizontal timber element14) Laminated timber panel15) Cross laminated timber floor16) Slotted MS cleat17) Insulation18) Laminated timber panel
![Page 194: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/194.jpg)
Typ
ical
wal
l sec
tio
n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation10) Façade fixtures11) Breather membrane12) Laminated timber panel13) Horizontal timber element14) Laminated timber panel15) Cross laminated timber floor16) Slotted MS cleat17) Insulation18) Laminated timber panel19) Vertical timber stud
![Page 195: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/195.jpg)
Typ
ical
wal
l sec
tio
n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation10) Façade fixtures11) Breather membrane12) Laminated timber panel13) Horizontal timber element14) Laminated timber panel15) Cross laminated timber floor16) Slotted MS cleat17) Insulation18) Laminated timber panel19) Vertical timber stud20) Cavity
![Page 196: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/196.jpg)
Typ
ical
wal
l sec
tio
n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation10) Façade fixtures11) Breather membrane12) Laminated timber panel13) Horizontal timber element14) Laminated timber panel15) Cross laminated timber floor16) Slotted MS cleat17) Insulation18) Laminated timber panel19) Vertical timber stud20) Cavity21) Vertical sawn larch cladding
![Page 197: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/197.jpg)
Typ
ical
wal
l sec
tio
n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation10) Façade fixtures11) Breather membrane12) Laminated timber panel13) Horizontal timber element14) Laminated timber panel15) Cross laminated timber floor16) Slotted MS cleat17) Insulation18) Laminated timber panel19) Vertical timber stud20) Cavity21) Vertical sawn larch cladding22) 2x plasterboard and vapour barrier
![Page 198: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/198.jpg)
Typ
ical
wal
l sec
tio
n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation10) Façade fixtures11) Breather membrane12) Laminated timber panel13) Horizontal timber element14) Laminated timber panel15) Cross laminated timber floor16) Slotted MS cleat17) Insulation18) Laminated timber panel19) Vertical timber stud20) Cavity21) Vertical sawn larch cladding22) 2x plasterboard and vapour barrier23) Insulation and laminated timber panel
![Page 199: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/199.jpg)
Typ
ical
wal
l sec
tio
n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation10) Façade fixtures11) Breather membrane12) Laminated timber panel13) Horizontal timber element14) Laminated timber panel15) Cross laminated timber floor16) Slotted MS cleat17) Insulation18) Laminated timber panel19) Vertical timber stud20) Cavity21) Vertical sawn larch cladding22) 2x plasterboard and vapour barrier23) Insulation and laminated timber panel24) Vertical timber stud
![Page 200: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/200.jpg)
Typ
ical
wal
l sec
tio
n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation10) Façade fixtures11) Breather membrane12) Laminated timber panel13) Horizontal timber element14) Laminated timber panel15) Cross laminated timber floor16) Slotted MS cleat17) Insulation18) Laminated timber panel19) Vertical timber stud20) Cavity21) Vertical sawn larch cladding22) 2x plasterboard and vapour barrier23) Insulation and laminated timber panel24) Vertical timber stud25) Lower rail on cleats
![Page 201: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/201.jpg)
Typ
ical
wal
l sec
tio
n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation10) Façade fixtures11) Breather membrane12) Laminated timber panel13) Horizontal timber element14) Laminated timber panel15) Cross laminated timber floor16) Slotted MS cleat17) Insulation18) Laminated timber panel19) Vertical timber stud20) Cavity21) Vertical sawn larch cladding22) 2x plasterboard and vapour barrier23) Insulation and laminated timber panel24) Vertical timber stud25) Lower rail on cleats26) Slotted cleat
![Page 202: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/202.jpg)
Typ
ical
wal
l sec
tio
n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation10) Façade fixtures11) Breather membrane12) Laminated timber panel13) Horizontal timber element14) Laminated timber panel15) Cross laminated timber floor16) Slotted MS cleat17) Insulation18) Laminated timber panel19) Vertical timber stud20) Cavity21) Vertical sawn larch cladding22) 2x plasterboard and vapour barrier23) Insulation and laminated timber panel24) Vertical timber stud25) Lower rail on cleats26) Slotted cleat27) Cross laminated timber floorboard
![Page 203: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/203.jpg)
Typ
ical
wal
l sec
tio
n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation10) Façade fixtures11) Breather membrane12) Laminated timber panel13) Horizontal timber element14) Laminated timber panel15) Cross laminated timber floor16) Slotted MS cleat17) Insulation18) Laminated timber panel19) Vertical timber stud20) Cavity21) Vertical sawn larch cladding22) 2x plasterboard and vapour barrier23) Insulation and laminated timber panel24) Vertical timber stud25) Lower rail on cleats26) Slotted cleat27) Cross laminated timber floorboard28) Angles to fix vertical panel to horizontal
![Page 204: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/204.jpg)
Typ
ical
wal
l sec
tio
n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation10) Façade fixtures11) Breather membrane12) Laminated timber panel13) Horizontal timber element14) Laminated timber panel15) Cross laminated timber floor16) Slotted MS cleat17) Insulation18) Laminated timber panel19) Vertical timber stud20) Cavity21) Vertical sawn larch cladding22) 2x plasterboard and vapour barrier23) Insulation and laminated timber panel24) Vertical timber stud25) Lower rail on cleats26) Slotted cleat27) Cross laminated timber floorboard28) Angles to fix vertical panel to horizontal29) Insulation
![Page 205: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/205.jpg)
Typ
ical
wal
l sec
tio
n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation10) Façade fixtures11) Breather membrane12) Laminated timber panel13) Horizontal timber element14) Laminated timber panel15) Cross laminated timber floor16) Slotted MS cleat17) Insulation18) Laminated timber panel19) Vertical timber stud20) Cavity21) Vertical sawn larch cladding22) 2x plasterboard and vapour barrier23) Insulation and laminated timber panel24) Vertical timber stud25) Lower rail on cleats26) Slotted cleat27) Cross laminated timber floorboard28) Angles to fix vertical panel to horizontal29) Insulation30) Sedum roof
![Page 206: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/206.jpg)
Typ
ical
wal
l sec
tio
n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation10) Façade fixtures11) Breather membrane12) Laminated timber panel13) Horizontal timber element14) Laminated timber panel15) Cross laminated timber floor16) Slotted MS cleat17) Insulation18) Laminated timber panel19) Vertical timber stud20) Cavity21) Vertical sawn larch cladding22) 2x plasterboard and vapour barrier23) Insulation and laminated timber panel24) Vertical timber stud25) Lower rail on cleats26) Slotted cleat27) Cross laminated timber floorboard28) Angles to fix vertical panel to horizontal29) Insulation30) Sedum roof
![Page 207: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/207.jpg)
Typ
ical
wal
l sec
tio
n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation10) Façade fixtures11) Breather membrane12) Laminated timber panel13) Horizontal timber element14) Laminated timber panel15) Cross laminated timber floor16) Slotted MS cleat17) Insulation18) Laminated timber panel19) Vertical timber stud20) Cavity21) Vertical sawn larch cladding22) 2x plasterboard and vapour barrier23) Insulation and laminated timber panel24) Vertical timber stud25) Lower rail on cleats26) Slotted cleat27) Cross laminated timber floorboard28) Angles to fix vertical panel to horizontal29) Insulation30) Sedum roof31) Vertical timber stud
![Page 208: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/208.jpg)
Typ
ical
wal
l sec
tio
n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation10) Façade fixtures11) Breather membrane12) Laminated timber panel13) Horizontal timber element14) Laminated timber panel15) Cross laminated timber floor16) Slotted MS cleat17) Insulation18) Laminated timber panel19) Vertical timber stud20) Cavity21) Vertical sawn larch cladding22) 2x plasterboard and vapour barrier23) Insulation and laminated timber panel24) Vertical timber stud25) Lower rail on cleats26) Slotted cleat27) Cross laminated timber floorboard28) Angles to fix vertical panel to horizontal29) Insulation30) Sedum roof31) Vertical timber stud32) Timber cap
![Page 209: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/209.jpg)
Typ
ical
wal
l sec
tio
n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation10) Façade fixtures11) Breather membrane12) Laminated timber panel13) Horizontal timber element14) Laminated timber panel15) Cross laminated timber floor16) Slotted MS cleat17) Insulation18) Laminated timber panel19) Vertical timber stud20) Cavity21) Vertical sawn larch cladding22) 2x plasterboard and vapour barrier23) Insulation and laminated timber panel24) Vertical timber stud25) Lower rail on cleats26) Slotted cleat27) Cross laminated timber floorboard28) Angles to fix vertical panel to horizontal29) Insulation30) Sedum roof31) Vertical timber stud32) Timber cap
![Page 210: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/210.jpg)
Typ
ical
wal
l sec
tio
n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation10) Façade fixtures11) Breather membrane12) Laminated timber panel13) Horizontal timber element14) Laminated timber panel15) Cross laminated timber floor16) Slotted MS cleat17) Insulation18) Laminated timber panel19) Vertical timber stud20) Cavity21) Vertical sawn larch cladding22) 2x plasterboard and vapour barrier23) Insulation and laminated timber panel24) Vertical timber stud25) Lower rail on cleats26) Slotted cleat27) Cross laminated timber floorboard28) Angles to fix vertical panel to horizontal29) Insulation30) Sedum roof31) Vertical timber stud32) Timber cap33) Sawn larch cladding
![Page 211: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/211.jpg)
Typ
ical
wal
l sec
tio
n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation10) Façade fixtures11) Breather membrane12) Laminated timber panel13) Horizontal timber element14) Laminated timber panel15) Cross laminated timber floor16) Slotted MS cleat17) Insulation18) Laminated timber panel19) Vertical timber stud20) Cavity21) Vertical sawn larch cladding22) 2x plasterboard and vapour barrier23) Insulation and laminated timber panel24) Vertical timber stud25) Lower rail on cleats26) Slotted cleat27) Cross laminated timber floorboard28) Angles to fix vertical panel to horizontal29) Insulation30) Sedum roof31) Vertical timber stud32) Timber cap33) Sawn larch cladding34) Window fixture
![Page 212: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/212.jpg)
Gla
ss e
ntr
ance
sec
tio
n1) Concrete base
![Page 213: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/213.jpg)
Gla
ss e
ntr
ance
sec
tio
n1) Concrete base2) Pebble marble surface
![Page 214: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/214.jpg)
Gla
ss e
ntr
ance
sec
tio
n1) Concrete base2) Pebble marble surface3) Cold rolled mild steel column
![Page 215: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/215.jpg)
Gla
ss e
ntr
ance
sec
tio
n1) Concrete base2) Pebble marble surface3) Cold rolled mild steel column4) Marble veneered concrete
![Page 216: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/216.jpg)
Gla
ss e
ntr
ance
sec
tio
n1) Concrete base2) Pebble marble surface3) Cold rolled mild steel column4) Marble veneered concrete 5) Chanel framed single glazed window
![Page 217: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/217.jpg)
Gla
ss e
ntr
ance
sec
tio
n1) Concrete base2) Pebble marble surface3) Cold rolled mild steel column4) Marble veneered concrete 5) Chanel framed single glazed window6) Cross laminated timber panels
![Page 218: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/218.jpg)
Gla
ss e
ntr
ance
sec
tio
n1) Concrete base2) Pebble marble surface3) Cold rolled mild steel column4) Marble veneered concrete 5) Chanel framed single glazed window6) Cross laminated timber panels7) Laminated timber panel
![Page 219: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/219.jpg)
Gla
ss e
ntr
ance
sec
tio
n1) Concrete base2) Pebble marble surface3) Cold rolled mild steel column4) Marble veneered concrete 5) Chanel framed single glazed window6) Cross laminated timber panels7) Laminated timber panel8) Insulation
![Page 220: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/220.jpg)
Gla
ss e
ntr
ance
sec
tio
n1) Concrete base2) Pebble marble surface3) Cold rolled mild steel column4) Marble veneered concrete 5) Chanel framed single glazed window6) Cross laminated timber panels7) Laminated timber panel8) Insulation9) Laminated timber panel
![Page 221: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/221.jpg)
Gla
ss e
ntr
ance
sec
tio
n1) Concrete base2) Pebble marble surface3) Cold rolled mild steel column4) Marble veneered concrete 5) Chanel framed single glazed window6) Cross laminated timber panels7) Laminated timber panel8) Insulation9) Laminated timber panel
![Page 222: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/222.jpg)
Gla
ss e
ntr
ance
sec
tio
n1) Concrete base2) Pebble marble surface3) Cold rolled mild steel column4) Marble veneered concrete 5) Chanel framed single glazed window6) Cross laminated timber panels7) Laminated timber panel8) Insulation9) Laminated timber panel10) Sedum tray
![Page 223: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/223.jpg)
Gla
ss e
ntr
ance
sec
tio
n1) Concrete base2) Pebble marble surface3) Cold rolled mild steel column4) Marble veneered concrete 5) Chanel framed single glazed window6) Cross laminated timber panels7) Laminated timber panel8) Insulation9) Laminated timber panel10) Sedum tray 11) Automatic opening vent columns
![Page 224: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/224.jpg)
Gla
ss e
ntr
ance
sec
tio
n1) Concrete base2) Pebble marble surface3) Cold rolled mild steel column4) Marble veneered concrete 5) Chanel framed single glazed window6) Cross laminated timber panels7) Laminated timber panel8) Insulation9) Laminated timber panel10) Sedum tray 11) Automatic opening vent columns12) Insulation
![Page 225: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/225.jpg)
Gla
ss e
ntr
ance
sec
tio
n1) Concrete base2) Pebble marble surface3) Cold rolled mild steel column4) Marble veneered concrete 5) Chanel framed single glazed window6) Cross laminated timber panels7) Laminated timber panel8) Insulation9) Laminated timber panel10) Sedum tray 11) Automatic opening vent columns12) Insulation
![Page 226: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/226.jpg)
Gla
ss e
ntr
ance
sec
tio
n1) Concrete base2) Pebble marble surface3) Cold rolled mild steel column4) Marble veneered concrete 5) Chanel framed single glazed window6) Cross laminated timber panels7) Laminated timber panel8) Insulation9) Laminated timber panel10) Sedum tray 11) Automatic opening vent columns12) Insulation13) Pressed aluminium gutter with down pipes
![Page 227: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/227.jpg)
Gla
ss e
ntr
ance
sec
tio
n1) Concrete base2) Pebble marble surface3) Cold rolled mild steel column4) Marble veneered concrete 5) Chanel framed single glazed window6) Cross laminated timber panels7) Laminated timber panel8) Insulation9) Laminated timber panel10) Sedum tray 11) Automatic opening vent columns12) Insulation13) Pressed aluminium gutter with down pipes14) Automatic opening vents
![Page 228: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/228.jpg)
Gla
ss e
ntr
ance
sec
tio
n1) Concrete base2) Pebble marble surface3) Cold rolled mild steel column4) Marble veneered concrete 5) Chanel framed single glazed window6) Cross laminated timber panels7) Laminated timber panel8) Insulation9) Laminated timber panel10) Sedum tray 11) Automatic opening vent columns12) Insulation13) Pressed aluminium gutter with down pipes14) Automatic opening vents15) Window 4m span 120x200
![Page 229: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/229.jpg)
Gla
ss e
ntr
ance
sec
tio
n1) Concrete base2) Pebble marble surface3) Cold rolled mild steel column4) Marble veneered concrete 5) Chanel framed single glazed window6) Cross laminated timber panels7) Laminated timber panel8) Insulation9) Laminated timber panel10) Sedum tray 11) Automatic opening vent columns12) Insulation13) Pressed aluminium gutter with down pipes14) Automatic opening vents15) Window 4m span 120x20016) Pressed all internal cover by ETFE contractor
![Page 230: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/230.jpg)
Gla
ss e
ntr
ance
sec
tio
n1) Concrete base2) Pebble marble surface3) Cold rolled mild steel column4) Marble veneered concrete 5) Chanel framed single glazed window6) Cross laminated timber panels7) Laminated timber panel8) Insulation9) Laminated timber panel10) Sedum tray 11) Automatic opening vent columns12) Insulation13) Pressed aluminium gutter with down pipes14) Automatic opening vents15) Window 4m span 120x20016) Pressed all internal cover by ETFE contractor17) ETFE pillow fixture
![Page 231: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/231.jpg)
Fire
Str
ateg
y Ground Floor Plan
![Page 232: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/232.jpg)
Fire
Str
ateg
y Ground Floor Plan
Fire ExitsDoors in the fire cores are held open on electro-magnetic devices-these devices had not yet been activated when we visited.Sliding doors in the entrance and back of the building are fall safe automatic doors with a ‘break-out’ facility.
![Page 233: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/233.jpg)
Fire
Str
ateg
y Ground Floor Plan
Other Exits
![Page 234: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/234.jpg)
Fire
Str
ateg
y Ground Floor Plan
Capacity of Each Space
![Page 235: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/235.jpg)
Fire
Str
ateg
y Ground Floor Plan
Fire Cores
![Page 236: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/236.jpg)
Fire
Str
ateg
y Ground Floor Plan
Fire Travel DistancesThe maximum travelling distance should be 42.5meters as the building is public visitors centre
47m
30m
39m
17m
![Page 237: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/237.jpg)
Fire
Str
ateg
y Ground Floor Plan
Area Outside Fire Travel DistancesThe space outside the fire travel distance was allowed as a timber downstand beam was put within the ceiling which will form a smoke reservoir. Therefore occupants can escape via a smoke free reservoir.
![Page 238: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/238.jpg)
Fire
Str
ateg
y Ground Floor Plan
Exits to Assembly Points
![Page 239: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/239.jpg)
Fire
Str
ateg
y Ground Floor Plan
Assembly Points
![Page 240: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/240.jpg)
Fire
Str
ateg
y Ground Floor Plan
Fire Zone 1
![Page 241: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/241.jpg)
Fire
Str
ateg
y Ground Floor Plan
Fire Zone 2
![Page 242: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/242.jpg)
Fire
Str
ateg
y Ground Floor Plan
Fire Zone 3
![Page 243: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/243.jpg)
Fire
Str
ateg
y Ground Floor Plan
Fire Zone 4
![Page 244: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/244.jpg)
Fire
Str
ateg
y Ground Floor Plan
Fire Zone 5
![Page 245: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/245.jpg)
Fire
Str
ateg
y Ground Floor Plan
60 min Protected Zone
![Page 246: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/246.jpg)
Fire
Str
ateg
y Ground Floor Plan
60 min Protected Walls and Doors
![Page 247: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/247.jpg)
Fire
Str
ateg
y Ground Floor Plan
30 min Protected Walls and Doors
![Page 248: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/248.jpg)
Fire
Str
ateg
y Ground Floor Plan
Access For Emergency Services
![Page 249: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/249.jpg)
Fire
Str
ateg
y Ground Floor Plan
Emergency Services Turning CirclesThese must be a minimum of 14m in diameter.
![Page 250: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/250.jpg)
Fire
Str
ateg
y Ground Floor Plan
Smoke Detectors and Sprinklers
![Page 251: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/251.jpg)
Fire
Str
ateg
y First Floor Plan
![Page 252: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/252.jpg)
Fire
Str
ateg
y First Floor Plan
Fire Exits
![Page 253: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/253.jpg)
Fire
Str
ateg
y First Floor Plan
Other Exits
![Page 254: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/254.jpg)
Fire
Str
ateg
y First Floor Plan
Capacity of Each Space
![Page 255: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/255.jpg)
Fire
Str
ateg
y First Floor Plan
Fire Cores
![Page 256: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/256.jpg)
Fire
Str
ateg
y First Floor Plan
Fire Travel Distances
16m
28m
16m
37m
![Page 257: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/257.jpg)
Fire
Str
ateg
y First Floor Plan
Fire Zone 1
![Page 258: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/258.jpg)
Fire
Str
ateg
y First Floor Plan
Fire Zone 2
![Page 259: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/259.jpg)
Fire
Str
ateg
y First Floor Plan
Fire Zone 3
![Page 260: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/260.jpg)
Fire
Str
ateg
y First Floor Plan
Fire Zone 4
![Page 261: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/261.jpg)
Fire
Str
ateg
y First Floor Plan
Fire Zone 5
![Page 262: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/262.jpg)
Fire
Str
ateg
y First Floor Plan
60 min Protected Zone
![Page 263: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/263.jpg)
Fire
Str
ateg
y First Floor Plan
60 min Protected Walls and Doors
![Page 264: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/264.jpg)
Fire
Str
ateg
y First Floor Plan
30 min Protected Walls and Doors
![Page 265: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/265.jpg)
Fire
Str
ateg
y First Floor Plan
Smoke Detectors and Sprinklers
![Page 266: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/266.jpg)
Fire
Str
ateg
y First Floor Plan
Hazardous ZoneThe kitchen
![Page 267: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/267.jpg)
Fire
Str
ateg
y Ground Floor Plan
![Page 268: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/268.jpg)
Fire
Str
ateg
y Ground Floor Plan
Fire ExitsDoors in the fire cores are held open on electro-magnetic devices-these devices had not yet been activated when we visited.Sliding doors in the entrance and back of the building are fall safe automatic doors with a ‘break-out’ facility.
![Page 269: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/269.jpg)
Fire
Str
ateg
y Ground Floor Plan
Other Exits
![Page 270: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/270.jpg)
Fire
Str
ateg
y Ground Floor Plan
Capacity of Each Space
![Page 271: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/271.jpg)
Fire
Str
ateg
y Ground Floor Plan
Fire Cores
![Page 272: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/272.jpg)
Fire
Str
ateg
y Ground Floor Plan
Fire Travel DistancesThe maximum travelling distance should be 42.5meters as the building is public visitors centre
47m
30m
39m
17m
![Page 273: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/273.jpg)
Fire
Str
ateg
y Ground Floor Plan
Area Outside Fire Travel DistancesThe space outside the fire travel distance was allowed as a timber downstand beam was put within the ceiling which will form a smoke reservoir. Therefore occupants can escape via a smoke free reservoir.
![Page 274: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/274.jpg)
Fire
Str
ateg
y Ground Floor Plan
Exits to Assembly Points
![Page 275: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/275.jpg)
Fire
Str
ateg
y Ground Floor Plan
Assembly Points
![Page 276: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/276.jpg)
Fire
Str
ateg
y Ground Floor Plan
Fire Zone 1
![Page 277: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/277.jpg)
Fire
Str
ateg
y Ground Floor Plan
Fire Zone 2
![Page 278: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/278.jpg)
Fire
Str
ateg
y Ground Floor Plan
Fire Zone 3
![Page 279: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/279.jpg)
Fire
Str
ateg
y Ground Floor Plan
Fire Zone 4
![Page 280: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/280.jpg)
Fire
Str
ateg
y Ground Floor Plan
Fire Zone 5
![Page 281: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/281.jpg)
Fire
Str
ateg
y Ground Floor Plan
60 min Protected Zone
![Page 282: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/282.jpg)
Fire
Str
ateg
y Ground Floor Plan
60 min Protected Walls and Doors
![Page 283: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/283.jpg)
Fire
Str
ateg
y Ground Floor Plan
30 min Protected Walls and Doors
![Page 284: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/284.jpg)
Fire
Str
ateg
y Ground Floor Plan
Access For Emergency Services
![Page 285: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/285.jpg)
Fire
Str
ateg
y Ground Floor Plan
Emergency Services Turning CirclesThese must be a minimum of 14m in diameter.
![Page 286: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/286.jpg)
Fire
Str
ateg
y Ground Floor Plan
Smoke Detectors and Sprinklers
![Page 287: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/287.jpg)
Fire
Str
ateg
y First Floor Plan
![Page 288: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/288.jpg)
Fire
Str
ateg
y First Floor Plan
Fire Exits
![Page 289: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/289.jpg)
Fire
Str
ateg
y First Floor Plan
Other Exits
![Page 290: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/290.jpg)
Fire
Str
ateg
y First Floor Plan
Capacity of Each Space
![Page 291: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/291.jpg)
Fire
Str
ateg
y First Floor Plan
Fire Cores
![Page 292: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/292.jpg)
Fire
Str
ateg
y First Floor Plan
Fire Travel Distances
16m
28m
16m
37m
![Page 293: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/293.jpg)
Fire
Str
ateg
y First Floor Plan
Fire Zone 1
![Page 294: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/294.jpg)
Fire
Str
ateg
y First Floor Plan
Fire Zone 2
![Page 295: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/295.jpg)
Fire
Str
ateg
y First Floor Plan
Fire Zone 3
![Page 296: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/296.jpg)
Fire
Str
ateg
y First Floor Plan
Fire Zone 4
![Page 297: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/297.jpg)
Fire
Str
ateg
y First Floor Plan
Fire Zone 5
![Page 298: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/298.jpg)
Fire
Str
ateg
y First Floor Plan
60 min Protected Zone
![Page 299: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/299.jpg)
Fire
Str
ateg
y First Floor Plan
60 min Protected Walls and Doors
![Page 300: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/300.jpg)
Fire
Str
ateg
y First Floor Plan
30 min Protected Walls and Doors
![Page 301: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/301.jpg)
Fire
Str
ateg
y First Floor Plan
Smoke Detectors and Sprinklers
![Page 302: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/302.jpg)
Fire
Str
ateg
y First Floor Plan
Hazardous ZoneThe kitchen
![Page 303: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/303.jpg)
Spring:
Autumn:
Summer:
Winter:
> 480460 - 480440 - 460420 - 440400 - 420380 - 400380 - 380340 - 360< 340
> 640600 - 640560 - 600520 - 560480 - 520440 - 480400 - 440360 - 400< 360
> 170160 - 170150 - 160140 - 150130 - 140120 - 130110 - 120100 - 110< 100
> 320300 - 320280 - 300260 - 280240 - 260220 - 240200 - 220180 - 200< 180
Average Values (Hours)Average Values (Hours)
Average Values (Hours) Average Values (Hours)
Sola
r A
nal
ysis Sunshine Duration Averages:
![Page 304: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/304.jpg)
25
20
15
10
05
0
-05
-10
-15
-20
-25
Average Min and Max Temperature Degrees Celsius: Extreme Min and Max Temperature Degrees Celsius:
Jan Feb Mar Apr May Jun Jul Aug Sept Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sept Oct Nov Dec
25
20
15
10
05
0
-05
-10
-15
-20
-25
Sola
r A
nal
ysis Temperature Averages:
The general solar analysis shows that the site averages temperatures above 0 degrees Celsius throughout the yearOccasional extreme temperatures may occur and the building should factor in these extremesAdvantages: The relatively steady temperature should inform accurate predictions for building systemsDisadvantages: the occasional extreme temperature could occur and preparations for such days should be factored
![Page 305: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/305.jpg)
9.00, March
There are no man-made structure casting shadow onto the building. The shadowing of the building is only affected by itself and the foliage around it in the garden
Sola
r A
nal
ysis Shadow Study:
![Page 306: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/306.jpg)
12.00, March
There are no man-made structure casting shadow onto the building. The shadowing of the building is only affected by itself and the foliage around it in the garden
Sola
r A
nal
ysis Shadow Study:
![Page 307: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/307.jpg)
15.00, March
There are no man-made structure casting shadow onto the building. The shadowing of the building is only affected by itself and the foliage around it in the garden
Sola
r A
nal
ysis Shadow Study:
![Page 308: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/308.jpg)
18.00, March
There are no man-made structure casting shadow onto the building. The shadowing of the building is only affected by itself and the foliage around it in the garden
Sola
r A
nal
ysis Shadow Study:
![Page 309: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/309.jpg)
9.00, July
There are no man-made structure casting shadow onto the building. The shadowing of the building is only affected by itself and the foliage around it in the garden
Sola
r A
nal
ysis Shadow Study:
![Page 310: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/310.jpg)
12.00, July
There are no man-made structure casting shadow onto the building. The shadowing of the building is only affected by itself and the foliage around it in the garden
Sola
r A
nal
ysis Shadow Study:
![Page 311: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/311.jpg)
15.00, July
There are no man-made structure casting shadow onto the building. The shadowing of the building is only affected by itself and the foliage around it in the garden
Sola
r A
nal
ysis Shadow Study:
![Page 312: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/312.jpg)
18.00, July
There are no man-made structure casting shadow onto the building. The shadowing of the building is only affected by itself and the foliage around it in the garden
Sola
r A
nal
ysis Shadow Study:
![Page 313: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/313.jpg)
9.00, September
There are no man-made structure casting shadow onto the building. The shadowing of the building is only affected by itself and the foliage around it in the garden
Sola
r A
nal
ysis Shadow Study:
![Page 314: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/314.jpg)
12.00, September
There are no man-made structure casting shadow onto the building. The shadowing of the building is only affected by itself and the foliage around it in the garden
Sola
r A
nal
ysis Shadow Study:
![Page 315: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/315.jpg)
15.00, September
There are no man-made structure casting shadow onto the building. The shadowing of the building is only affected by itself and the foliage around it in the garden
Sola
r A
nal
ysis Shadow Study:
![Page 316: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/316.jpg)
18.00, September
There are no man-made structure casting shadow onto the building. The shadowing of the building is only affected by itself and the foliage around it in the garden
Sola
r A
nal
ysis Shadow Study:
![Page 317: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/317.jpg)
9.00, December
There are no man-made structure casting shadow onto the building. The shadowing of the building is only affected by itself and the foliage around it in the garden
Sola
r A
nal
ysis Shadow Study:
![Page 318: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/318.jpg)
12.00, December
There are no man-made structure casting shadow onto the building. The shadowing of the building is only affected by itself and the foliage around it in the garden
Sola
r A
nal
ysis Shadow Study:
![Page 319: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/319.jpg)
15.00, December
There are no man-made structure casting shadow onto the building. The shadowing of the building is only affected by itself and the foliage around it in the garden
Sola
r A
nal
ysis Shadow Study:
![Page 320: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/320.jpg)
18.00, December
There are no man-made structure casting shadow onto the building. The shadowing of the building is only affected by itself and the foliage around it in the garden
Sola
r A
nal
ysis Shadow Study:
![Page 321: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/321.jpg)
Summer: Winter:
> 2520 - 2515 - 2010 - 158 - 106 - 8< 6
Average Values (Knots)> 2520 - 2515 - 2010 - 158 - 106 - 8< 6
Average Values (Knots)
Win
d A
nal
ysis Mean Wind Speed Averages:
The wind analysis shows that the site may experience winds which average 10-25 knots throughout the yearAdvantages: strong winds can be used by wind turbines to generate powerDisadvantages: the shape of the building may cause adverse wind deflections
![Page 322: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/322.jpg)
Jan:
May:
Sept:
Feb:
June:
Oct:
Mar:
July:
Nov:
Apr:
Aug:
Dec:
Win
d A
nal
ysis Month By Month:
![Page 323: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/323.jpg)
N
S
EW
Win
d A
nal
ysis Year Overall:
The wind analysis shows that the site may experience strong winds, predominantly from the north-east and south-west
![Page 324: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/324.jpg)
The large trees around the site can channel the wind into narrow spaces and increase wind forces and speed
Win
d A
nal
ysis Wind Channels:
![Page 325: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/325.jpg)
Win
d A
nal
ysis South West:
Strong winds often approach the site from the south-west
![Page 326: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/326.jpg)
Win
d A
nal
ysis South West:
1. Winds approach from the south-west
![Page 327: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/327.jpg)
Win
d A
nal
ysis South West:
1. Winds approach from the south-west2. As wind is forced through channels speeds increase
![Page 328: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/328.jpg)
Win
d A
nal
ysis South West:
1. Winds approach from the south-west2. As wind is forced through channels speeds increase
![Page 329: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/329.jpg)
Win
d A
nal
ysis South West:
1. Winds approach from the south-west2. As wind is forced through channels speeds increase3. Wind disperses into more open ground
![Page 330: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/330.jpg)
Win
d A
nal
ysis South West:
As the wind passes by the large trees areas of negative pressurePositive pressureNegative pressure
![Page 331: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/331.jpg)
Win
d A
nal
ysis South West:
As the wind passes by the large trees areas of negative pressurePositive pressureNegative pressure
![Page 332: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/332.jpg)
Win
d A
nal
ysis South West:
As the wind passes by the large trees areas of negative pressurePositive pressureNegative pressure
![Page 333: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/333.jpg)
Win
d A
nal
ysis South West:
As the wind passes by the large trees areas of negative pressurePositive pressureNegative pressure
![Page 334: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/334.jpg)
Win
d A
nal
ysis North East:
Strong winds often approach the site from the north-east
![Page 335: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/335.jpg)
Win
d A
nal
ysis North East:
1. Winds approach from the north-east
![Page 336: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/336.jpg)
Win
d A
nal
ysis North East:
1. Winds approach from the north-east2. As wind is forced through channels speeds increase
![Page 337: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/337.jpg)
Win
d A
nal
ysis North East:
1. Winds approach from the north-east2. As wind is forced through channels speeds increase
![Page 338: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/338.jpg)
Win
d A
nal
ysis North East:
1. Winds approach from the north-east2. As wind is forced through channels speeds increase3. Wind disperses into more open ground
![Page 339: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/339.jpg)
Win
d A
nal
ysis North East:
As the wind passes by the large trees areas of negative pressurePositive pressureNegative pressure
![Page 340: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/340.jpg)
Win
d A
nal
ysis North East:
As the wind passes by the large trees areas of negative pressurePositive pressureNegative pressure
![Page 341: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/341.jpg)
Win
d A
nal
ysis North East:
As the wind passes by the large trees areas of negative pressurePositive pressureNegative pressure
![Page 342: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/342.jpg)
Win
d A
nal
ysis North East:
As the wind passes by the large trees areas of negative pressurePositive pressureNegative pressure
![Page 343: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/343.jpg)
Spring:
Autumn:
Summer:
Winter:
> 800600 - 800500 - 600400 - 500300 - 400250 - 300200 - 250150 - 200< 150
> 800600 - 800500 - 600400 - 500300 - 400250 - 300200 - 250150 - 200< 150
> 800600 - 800500 - 600400 - 500300 - 400250 - 300200 - 250150 - 200< 150
> 800600 - 800500 - 600400 - 500300 - 400250 - 300200 - 250150 - 200< 150
Average Values (mm)Average Values (mm)
Average Values (mm) Average Values (mm)
Wat
er A
nal
ysis Rainfall Averages:
![Page 344: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/344.jpg)
Mean Monthly Rainfall (mm):
Jan Feb Mar Apr May Jun Jul Aug Sept Oct Nov Dec
130
120
110
100
90
80
70
60
50
40
30
20
10
Wat
er A
nal
ysis Rainfall Averages:
Rainfall analysis shows that the site experiences a large amount of rainfall throughout the yearAdvantages: rainwater may be harvested for utilitiesDisadvantages: the building will need to be very weather tight and damp conditions may restrict material choice
![Page 345: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/345.jpg)
Spring:
Autumn:
Summer:
Winter:
> 4030 - 4020 - 3015 - 2010 - 155 - 10< 5
< 0.5
> 4030 - 4020 - 3015 - 2010 - 155 - 10< 5
> 4030 - 4020 - 3015 - 2010 - 155 - 10< 5
Average Values (mm)Average Values (mm)
Average Values (days) Average Values (mm)
Wat
er A
nal
ysis Lying Snow Averages:
![Page 346: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/346.jpg)
26
24
22
20
18
16
14
12
10
08
06
04
02
26
24
22
20
18
16
14
12
10
08
06
04
02
Average No. Days Ground Frost: Average No. Days Air Frost:
Jan Feb Mar Apr May Jun Jul Aug Sept Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sept Oct Nov Dec
Wat
er A
nal
ysis Frost:
Snow and frost analysis shows that the site may experience severe cold spellsAdvantages: no significant advantagesDisadvantages: lying snow will need to be accounted for in room loading, colder conditions may not be suitable for some environmental conditions
![Page 347: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/347.jpg)
Wat
er A
nal
ysis River Location:
The site is located on raised ground to the north of the Water of Leith
![Page 348: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/348.jpg)
Wat
er A
nal
ysis Flood Zone:
Flood analysis shows that the site should not experience any significant flooding should the river burst its banks.
Please note: localised flooding could occur if drains are not properly maintained and cleared due to the large volume of rainfall the site experiences.
![Page 349: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/349.jpg)
Borehole Sample Map:G
eo
logy
An
alys
is
![Page 350: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/350.jpg)
Borehole Sample 130m:
0m
5m
10m
TopsoilSoft Silt And Sandy ClayMedium Dense Brown ClayFirm Dark Gray Gravelly ClayGravel And SandSand With Broken SandstoneFire Clay
Cobble SetsMudstoneRed Clay With Burnt ShaleConcreteCompacted Brick FillBoulders / Broken RockParaffin Shale
Medium Sand Mixed With StoneWeak Weathered MudstoneTarmacBroken StoneFirm SandstoneBlack Ash FillingBlack Sand
Key:
Ge
olo
gy A
nal
ysis
![Page 351: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/351.jpg)
TopsoilSoft Silt And Sandy ClayMedium Dense Brown ClayFirm Dark Gray Gravelly ClayGravel And SandSand With Broken SandstoneFire Clay
Cobble SetsMudstoneRed Clay With Burnt ShaleConcreteCompacted Brick FillBoulders / Broken RockParaffin Shale
Medium Sand Mixed With StoneWeak Weathered MudstoneTarmacBroken StoneFirm SandstoneBlack Ash FillingBlack Sand
Key:
0m
5m
10m
15m
Ge
olo
gy A
nal
ysis Borehole Samples:
![Page 352: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/352.jpg)
TopsoilSoft Silt And Sandy ClayMedium Dense Brown ClayFirm Dark Gray Gravelly ClayGravel And SandSand With Broken SandstoneFire Clay
Cobble SetsMudstoneRed Clay With Burnt ShaleConcreteCompacted Brick FillBoulders / Broken RockParaffin Shale
Medium Sand Mixed With StoneWeak Weathered MudstoneTarmacBroken StoneFirm SandstoneBlack Ash FillingBlack Sand
Key:
0m
5m
10m
15m
Ge
olo
gy A
nal
ysis Borehole Samples:
![Page 353: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/353.jpg)
Key:1: Clay and Large Stones2:Clay3: Broken Rock and Boulders4: Coarse Gravel and Boulders5: Black Sand6: Sandstone7: Clay8: Paraffin Shale9: Sandstone10: Clay11: Sandstone12: Clay with Boulders and Gravel13: Sandstone14: Clay15: Sandstone16: Fireclay17: Sandstone and Quartz
1
234567
8
9
101112
13
14
15
1617
0 - 9.14m9.14 - 13.1m13.1 - 15.24m15.24 - 22.55m22.55 - 25.29m25.29 - 30.17m30.17 - 30.78m30.78 - 40.23m40.23 - 53.64m53.64 - 54.25m54.25 - 57.30m57.30 - 67.05m67.05 - 86.56m86.56 – 87.17m87.17 - 118.87m118.87 - 122.52m122.52 - 129.54m
Ge
olo
gy A
nal
ysis Geological Build-Up 130m:
Geological analysis shows that the site sits on approx. 25m of clay and sand. After 25m there are significant deposits of sandstone.
Around the site the smaller bore hole samples suggest that a lot of man made spoil could occur. This should not be a problem for the specific site because of the age of the gardens.
We would suggest that pad foundations would be suitable for these geological conditions.
![Page 354: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/354.jpg)
Entrance foyer- Natural lighting from the two side glass facade and ETFE roofing- Artificial lighting system is using spot light to shire from the floor up to the roof and from the roof coming down, when the outside is dark- Naturally Ventilated by passive ventilation
Ground FloorZo
nin
g –
Pri
nci
pal
Sp
ace
s
![Page 355: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/355.jpg)
Toilet- Although natural light enter the area from the small glazing on the roof, but artificial lighting is still required- Mechanical ventilated space
Ground FloorZo
nin
g –
Pri
nci
pal
Sp
ace
s
![Page 356: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/356.jpg)
Open plan space- Natural light enter the space from the glass facade and ETFE roofing- Artificial lighting is also required to increase the luminosity- Passive Ventilated from automatically controlled vents- Mechanical ventilation will be use when its needed- Under floor heating is used
Ground FloorZo
nin
g –
Pri
nci
pal
Sp
ace
s
![Page 357: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/357.jpg)
Toilet- Natural and artificial lighting are both used to light up the space- Mechanical ventilated space - Under floor heating is used
Ground FloorZo
nin
g –
Pri
nci
pal
Sp
ace
s
![Page 358: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/358.jpg)
Circulation and Storage-Glazing are installed but due to small openings artificial lighting is mostly used- Spaces are mechanical ventilated- Under floor heating is used
Ground FloorZo
nin
g –
Pri
nci
pal
Sp
ace
s
![Page 359: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/359.jpg)
Plant room- Artificial lighting is constantly needed due to lack of windows, but with the space being not having a lot of human access, the light will not required to be on for a long period of time- Mechanically ventilated through vents controlled by extractor fans
Ground FloorZo
nin
g –
Pri
nci
pal
Sp
ace
s
![Page 360: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/360.jpg)
Open plan spaces- Natural light enter the space from the glass facade and ETFE roofing- Artificial lighting is also required to increase the luminosity- Passive Ventilated from automatically controlled vents- Mechanical ventilation will be use when its needed- Under floor heating is used
First FloorZo
nin
g –
Pri
nci
pal
Sp
ace
s
![Page 361: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/361.jpg)
Office- Natural and artificial lighting are both used in this space- On the facade glazing, white light reflectors are installed to reflect all available sunlight into the space to reduce the need for artificial lighting- The top of the internal walls are also made of glass which allows light enter from the roof atrium- Mechanical ventilated space- Under floor heating is used
First FloorZo
nin
g –
Pri
nci
pal
Sp
ace
s
![Page 362: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/362.jpg)
Kitchen- Natural and artificial lighting are both used to light up the space- It is assume that it is mechanically ventilated, because of the function of the space and the lack of window- Under floor heating is used
First FloorZo
nin
g –
Pri
nci
pal
Sp
ace
s
![Page 363: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/363.jpg)
Toilet- Artificial lighting is used in the enclosed space- Mechanical ventilated space- Under floor heating is used
First FloorZo
nin
g –
Pri
nci
pal
Sp
ace
s
![Page 364: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/364.jpg)
Circulation and Storage- The space is mainly artificial lighted. Although there are glazed opening, but the opening is not big enough to have the space totally naturally lighted- Mechanical ventilated space- Under floor heating is used
First FloorZo
nin
g –
Pri
nci
pal
Sp
ace
s
![Page 365: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/365.jpg)
Education room- Natural and artificial lighting are both used to light up the space- Natural ventilation is controlled by the automatically controlled vents- Mechanical ventilation will be use when its needed- Under floor heating is used
First FloorZo
nin
g –
Pri
nci
pal
Sp
ace
s
![Page 366: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/366.jpg)
First Floor PlanPublic Spaces
Zon
ing
–P
rin
cip
al S
pac
es
![Page 367: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/367.jpg)
First Floor PlanPrivate Spaces
Zon
ing
–P
rin
cip
al S
pac
es
![Page 368: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/368.jpg)
Ground Floor PlanPublic Spaces
Zon
ing
–P
rin
cip
al S
pac
es
![Page 369: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/369.jpg)
Ground Floor PlanPrivate Spaces
Zon
ing
–P
rin
cip
al S
pac
es
![Page 370: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/370.jpg)
Due to the buildings orientation to the sun,
there is very little direct sunlight allowed into the
building one measure implemented to allow sunlight into the office
spaces are these Louvre's. They work by bouncing a
subdued sunlight into the offices
The building internal atriums are lit by roof light
which have a polymer cover on them. This is to give a more uniform and
bright light rather than direct intense sun light. As there is gallery space with
in the atriums this polymer helps to block out
UV rays.
Nat
ura
l Lig
hti
ng Lighting Systems:
![Page 371: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/371.jpg)
Nat
ura
l Lig
hti
ng Lighting Systems:
Due to the buildings orientation to the sun,
there is very little direct sunlight allowed into the
building one measure implemented to allow sunlight into the office
spaces are these Louvre's. They work by bouncing a
subdued sunlight into the offices
The building internal atriums are lit by roof light
which have a polymer cover on them. This is to give a more uniform and
bright light rather than direct intense sun light. As there is gallery space with
in the atriums this polymer helps to block out
UV rays.
![Page 372: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/372.jpg)
Nat
ura
l Lig
hti
ng Lighting Systems:
Due to the buildings orientation to the sun,
there is very little direct sunlight allowed into the
building one measure implemented to allow sunlight into the office
spaces are these Louvre's. They work by bouncing a
subdued sunlight into the offices
The building internal atriums are lit by roof light
which have a polymer cover on them. This is to give a more uniform and
bright light rather than direct intense sun light. As there is gallery space with
in the atriums this polymer helps to block out
UV rays.
![Page 373: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/373.jpg)
Nat
ura
l Lig
hti
ng Lighting Systems:
Due to the buildings orientation to the sun,
there is very little direct sunlight allowed into the
building one measure implemented to allow sunlight into the office
spaces are these Louvre's. They work by bouncing a
subdued sunlight into the offices
The building internal atriums are lit by roof light
which have a polymer cover on them. This is to give a more uniform and
bright light rather than direct intense sun light. As there is gallery space with
in the atriums this polymer helps to block out
UV rays.
![Page 374: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/374.jpg)
Nat
ura
l Lig
hti
ng Lighting Systems:
Due to the buildings orientation to the sun,
there is very little direct sunlight allowed into the
building one measure implemented to allow sunlight into the office
spaces are these Louvre's. They work by bouncing a
subdued sunlight into the offices
The building internal atriums are lit by roof light
which have a polymer cover on them. This is to give a more uniform and
bright light rather than direct intense sun light. As there is gallery space with
in the atriums this polymer helps to block out
UV rays.
![Page 375: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/375.jpg)
Despite the buildings position in relation to the sun, it has been designed to make the most of
the suns natural light throughout the day.
Maximum sun angle 73 degrees
Nat
ura
l Lig
hti
ng Summer 9am:
![Page 376: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/376.jpg)
Summer 12pm
Maximum sun angle 73 degrees
Nat
ura
l Lig
hti
ng Summer 12pm:
![Page 377: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/377.jpg)
Maximum sun angle 73 degrees
Nat
ura
l Lig
hti
ng Summer 5pm:
![Page 378: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/378.jpg)
Minimum sun angle 20 degrees
Nat
ura
l Lig
hti
ng Winter 9am:
![Page 379: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/379.jpg)
Minimum sun angle 20 degrees
Nat
ura
l Lig
hti
ng Winter 12pm:
![Page 380: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/380.jpg)
Minimum sun angle 20 degrees
Nat
ura
l Lig
hti
ng Winter 5pm:
![Page 381: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/381.jpg)
The restaurant light system consists of fluorescent tubes
suspended from the ceiling and integrated into panels that aid
acoustics' and contain heating and ventilation pipes.
Restaurant:
Exhibition Space:
In the exhibition space no lighting could be integrated into the
structural beams or walls this means all the lighting is suspended
within a neat panel system that also contains all of the heat and
ventilation ducts.The lighting in this space
comprises of spot lights that can be moved along tracks to alter the
space depending on what the exhibition requires.
Art
ific
ial L
igh
tin
g Lighting - Space By Space:
![Page 382: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/382.jpg)
The restaurant light system consists of fluorescent tubes
suspended from the ceiling and integrated into panels that aid
acoustics' and contain heating and ventilation pipes.
In the evening the space is transformed by atmospheric blue
LED lighting that is contained within the same suspended ceiling
panels.
Restaurant:
Exhibition Space:
In the exhibition space no lighting could be integrated into the
structural beams or walls this means all the lighting is suspended
within a neat panel system that also contains all of the heat and
ventilation ducts.The lighting in this space
comprises of spot lights that can be moved along tracks to alter the
space depending on what the exhibition requires.
Art
ific
ial L
igh
tin
g Lighting - Space By Space:
![Page 383: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/383.jpg)
The exterior lighting consists of LED units that illuminate up the blue slate wall. This create and
interesting effect of shadows and highlight using the natural form of
the stone work.
Exterior Lighting:
Timber Staircase:
The stairs are one of the most outstanding features within the building. The lighting engineers
worked with architects and manufacturers to integrate an LED
lighting system that would compliment the sculptural form.The LED strips are built into the
treads of the stair and illuminate both the top and bottom of the
staircase.
Art
ific
ial L
igh
tin
g Lighting - Space By Space:
![Page 384: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/384.jpg)
Section to show the use of lighting throughout the building
Art
ific
ial L
igh
tin
g Lighting - Building Overall:
![Page 385: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/385.jpg)
The buildings primary ventilation strategy is the use of windows and vents along side atriums and opening roof lights to create a chimney
stack effect to naturally cool the volume.
Nat
ura
l Ven
tila
tio
n
![Page 386: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/386.jpg)
The buildings primary ventilation strategy is the use of windows and vents along side atriums and opening roof lights to create a chimney
stack effect to naturally cool the volume.
Nat
ura
l Ven
tila
tio
n
![Page 387: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/387.jpg)
There is no air conditioning or air pumped within the building, instead the building relies
on allowing air to enter the building through air vents that are automatically controlled by comparing outside temperatures with the
temperatures inside the building
Nat
ura
l Ven
tila
tio
n
![Page 388: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/388.jpg)
This safes energy and has the additional benefit of allowing us to breathe fresh air instead of
recycled ‘second hand’ air.
Nat
ura
l Ven
tila
tio
n
![Page 389: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/389.jpg)
This safes energy and has the additional benefit of allowing us to breathe fresh air instead of
recycled ‘second hand’ air.
Nat
ura
l Ven
tila
tio
n
![Page 390: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/390.jpg)
The services come up the side of the lift shaft located next to the kitchen, above the basement where the plant room is located. In this plant room the utilities enter the building ready to be distributed
throughout the structure. The plant room also services the heating cooling and ventilation systems.
Plant Room Location:Se
rvic
e R
un
s
![Page 391: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/391.jpg)
The services come up the side of the lift shaft located next to the kitchen, above the basement where the plant room is located. In this plant room the utilities enter the building ready to be distributed
throughout the structure. The plant room also services the heating cooling and ventilation systems.
Plant Room Location:Se
rvic
e R
un
s
![Page 392: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/392.jpg)
The services come up the side of the lift shaft located next to the kitchen, above the basement where the plant room is located. In this plant room the utilities enter the building ready to be distributed
throughout the structure. The plant room also services the heating cooling and ventilation systems.
Plant Core Location:Se
rvic
e R
un
s
![Page 393: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/393.jpg)
The services come up the side of the lift shaft located next to the kitchen, above the basement where the plant room is located. In this plant room the utilities enter the building ready to be distributed
throughout the structure. The plant room also services the heating cooling and ventilation systems.
Plant Core Location:Se
rvic
e R
un
s
![Page 394: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/394.jpg)
The services come up the side of the lift shaft located next to the kitchen, above the basement where the plant room is located. In this plant room the utilities enter the building ready to be distributed
throughout the structure. The plant room also services the heating cooling and ventilation systems.
Service Run Locations:Se
rvic
e R
un
s
![Page 395: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/395.jpg)
Serv
ice
Ru
ns Service Run Locations:
The services come up the side of the lift shaft located next to the kitchen, above the basement where the plant room is located. In this plant room the utilities enter the building ready to be distributed
throughout the structure. The plant room also services the heating cooling and ventilation systems.
![Page 396: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/396.jpg)
Serv
ice
Ru
ns Service Run Locations:
The services come up the side of the lift shaft located next to the kitchen, above the basement where the plant room is located. In this plant room the utilities enter the building ready to be distributed
throughout the structure. The plant room also services the heating cooling and ventilation systems.
![Page 397: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/397.jpg)
The services come up the side of the lift shaft located next to the kitchen, above the basement where the plant room is located. In this plant room the utilities enter the building ready to be distributed
throughout the structure. The plant room also services the heating cooling and ventilation systems.
Service Run Locations:Se
rvic
e R
un
s
![Page 398: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/398.jpg)
The services come up the side of the lift shaft located next to the kitchen, above the basement where the plant room is located. In this plant room the utilities enter the building ready to be distributed
throughout the structure. The plant room also services the heating cooling and ventilation systems.
Service Run Locations:Se
rvic
e R
un
s
![Page 399: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/399.jpg)
The services come up the side of the lift shaft located next to the kitchen, above the basement where the plant room is located. In this plant room the utilities enter the building ready to be distributed
throughout the structure. The plant room also services the heating cooling and ventilation systems.
Service Run Locations:Se
rvic
e R
un
s
![Page 400: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/400.jpg)
Serv
ice
Ru
ns
The services come up the side of the lift shaft located next to the kitchen, above the basement where the plant room is located. In this plant room the utilities enter the building ready to be distributed
throughout the structure. The plant room also services the heating cooling and ventilation systems.
Service Run Locations:
![Page 401: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/401.jpg)
Serv
ice
Ru
ns Service Run Locations:
The services come up the side of the lift shaft located next to the kitchen, above the basement where the plant room is located. In this plant room the utilities enter the building ready to be distributed
throughout the structure. The plant room also services the heating cooling and ventilation systems.
![Page 402: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/402.jpg)
The services come up the side of the lift shaft located next to the kitchen, above the basement where the plant room is located. In this plant room the utilities enter the building ready to be distributed
throughout the structure. The plant room also services the heating cooling and ventilation systems.
Service Run Locations:Se
rvic
e R
un
s
![Page 403: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/403.jpg)
The services come up the side of the lift shaft located next to the kitchen, above the basement where the plant room is located. In this plant room the utilities enter the building ready to be distributed
throughout the structure. The plant room also services the heating cooling and ventilation systems.
Service Run Locations:Se
rvic
e R
un
s
![Page 404: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/404.jpg)
The services come up the side of the lift shaft located next to the kitchen, above the basement where the plant room is located. In this plant room the utilities enter the building ready to be distributed
throughout the structure. The plant room also services the heating cooling and ventilation systems.
Service Run Locations:Se
rvic
e R
un
s
![Page 405: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/405.jpg)
Serv
ice
Ru
ns Heating and Cooling System:
The heating and cooling system on the ground floor is a flat line
radiant system manufactured by Zehnder. The system is an efficient
way of maintaining an ambient temperature. It does this by using
convection to move air through the unit which dependent on
requirements can heat or cool the effected space. The system uses
hot or cold water pumped through the system to either heat or cool
the space depending on the requirement of the gallery.
![Page 406: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/406.jpg)
Serv
ice
Ru
ns Heating and Cooling System:
The heating and cooling system on the ground floor is a flat line
radiant system manufactured by Zehnder. The system is an efficient
way of maintaining an ambient temperature. It does this by using
convection to move air through the unit which dependent on
requirements can heat or cool the effected space. The system uses
hot or cold water pumped through the system to either heat or cool
the space depending on the requirement of the gallery.
![Page 407: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/407.jpg)
Serv
ice
Ru
ns Heating and Cooling System:
The heating and cooling system on the ground floor is a flat line
radiant system manufactured by Zehnder. The system is an efficient
way of maintaining an ambient temperature. It does this by using
convection to move air through the unit which dependent on
requirements can heat or cool the effected space. The system uses
hot or cold water pumped through the system to either heat or cool
the space depending on the requirement of the gallery.
![Page 408: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/408.jpg)
Heating and Cooling System:
The heating and cooling system on the ground floor is a flat line
radiant system manufactured by Zehnder. The system is an efficient
way of maintaining an ambient temperature. It does this by using
convection to move air through the unit which dependent on
requirements can heat or cool the effected space. The system uses
hot or cold water pumped through the system to either heat or cool
the space depending on the requirement of the gallery.
Serv
ice
Ru
ns
![Page 409: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/409.jpg)
Nat
ura
l Lig
hti
ng
Sect
ion
4 -
Sust
ain
abili
ty
A - Wind TurbineB - Sedum RoofC - Rainwater HarvestingD - Solar PanelsE - Bio-mass Boiler
![Page 410: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/410.jpg)
Win
d T
urb
ine Current Wind Turbine System:
Current System:
Computer control system(Uses a gust tracking algorithm to detect the behaviour of the wind. This information is then used to gain maximum power from the wind during gusts, to optimize the turbine performance.)
Compact size(Five metres high and three metres in diameter makes it compact and easy to integrate)
One moving part(Limits maintenance and inspection)
Wire safety system(Built in wire tensile system to prevent parts coming away from the turbine in the event of structural failure)
A
![Page 411: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/411.jpg)
Turbine specification:
Physical dimensions 5.5m tall, 3.1m diameterGenerator Direct drive, mechanically integrated,
weather sealed permanent magnet generatorPower control Peak power tracking constantly optimises
turbine output for all sites and wind speedsPower The projected peak power at 16m/s is:
8.5kW aerodynamic; 7.0kW DC; 6.5kWh at 7m/sAnnual energy yield 4197kWh at 5m/s to BWEA standards
Up to 12729kWh at 7m/sNo reduction in power output at up to 40%
turbulence intensityOperating wind speeds Cut in at sustained 5m/s; Cut out sustained
26m/sDesign life 25 years (annual inspections
recommended)Rotor construction Carbon fibre
Power Regulation and shutdownPower regulation above 13.5m/s wind
speed, auto shutdown in high wind speeds (above 26m/s)Roof mounting 6m mastTower mounting 18m mastRemote monitoring Event log can be accessed via PC. Remote
monitoring stores operation, average wind speeds and kW hours of electricity generatedWarranty Two years on components
Win
d T
urb
ine Current Wind Turbine System - Statistics:
A
![Page 412: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/412.jpg)
Win
d T
urb
ine
The turbine can generate around 4000 to 10000kWh per year, energy enough to supply an office which has 15-20 men.
Current Wind Turbine System:A
![Page 413: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/413.jpg)
Designed as a quiet solution of consuming wind energy. Because of its quietness, it can be installed in urban areas.
Win
d T
urb
ine Current Wind Turbine System:
A
![Page 414: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/414.jpg)
Win
d T
urb
ine Wind Turbine Does Not Work:
The wind turbine is not currently working
Possible reasons for turbine failure could be: Too strong / weak wind strengthWind blocked by trees Hardware or software failureA
![Page 415: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/415.jpg)
The Turbine will work at speeds between 5m/s and 26m/s Speeds below 5m/s are shown in Red, The grey areas show up to an optimum speed of approx 16m/s Analysis shows that the site experiences suitable wind speeds for turbine operation
Win
d T
urb
ine Wind Strength?:
Jan:
May:
Sept:
Feb:
June:
Oct:
Mar:
July:
Nov:
Apr:
Aug:
Dec:
A
![Page 416: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/416.jpg)
= Turbine Location
Win
d T
urb
ine Turbine Positioning?:
The Turbine will work with winds from any direction As shown in the wind analysis the site experiences strong channels of wind around and over the building Analysis indicates the turbine should not be blocked from the wind and have strong channels passingA
![Page 417: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/417.jpg)
Win
d T
urb
ine Computer System?:
The chosen turbine incorporates a sophisticated computer system which: Determines when to spin turbine to start Determines when to brake in high winds Decides when to shut down Production of event logs for analysis Predictive controller learns site wind analysis over time Remote monitoring
Analysis shows under the environmental conditions of the site the turbine should operate. Because conditions are adequate we would suggest that the turbine may have malfunctioned due hardware or software problems.
A
![Page 418: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/418.jpg)
Quietrevolution QR5 Windspire Gyromill Venturi Turbine Ropatec Vertical
Cut in: 5m/s 4m/s 2m/s 1.94m/s
Optimum: 16m/s 5.4m/s 5m/s 13.88m/s
Max: 26m/s 45m/s 40m/s 75m/s
kW/hr: 9600 2000 500 2300
Features: Low Noise Predictive Controller Auto Shut Down Low Vibration
Low Noise Small Scale Self Starting High Strength
Low Noise Almost continuous Low Cost Ideal for Low Speeds
Low Noise Low Maintenance Aerodynamic brakingsystem
Win
d T
urb
ine Correct Turbine Choice?:
Our Suggestion:We believe alternative vertical turbines would be suited to the site. A turbine which does not rely on computer systems wouldeliminate the chance of software failure.
A
![Page 419: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/419.jpg)
Win
d T
urb
ine Alternative Turbine Choice?:
Our Suggestion:A system using the Ropatec Vertical turbine would be more suited to the site.
Ropatec Vertical Turbine Quietrevolution QR5
Operates at lower speed Requires higher speeds
Able to operate at higher speeds Unable to operate at highest speeds
Optimum speed is higher Optimum speed is lower
Generates less power Generates more power
Aerodynamic braking system Computerised braking system
Although the Quiet revolution produces more power and it optimal at lower speeds, we believe that the Ropatec would be better suited due to its ability to work in lower and higher winds. Also by eliminating a reliance on complex computer systems will minimise failure.
More desirable traits are highlighted in red
A
![Page 420: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/420.jpg)
Win
d T
urb
ine Alternative Turbine Choice?:
Our Suggestion:Using two Ropatec Vertical turbines would give more power generation and produce approx. 2/3 of the power from the Quietrevolution QR5 system
We would suggest utilising both wind channels and putting a second turbine on the south-east corner
Although 2 Ropatec turbines only produce 4600kW/hr compared to 9600kW/hr of the Quietrevolution QR5 system we believe the ability to run at lower and higher speeds would make up for some of this loss
= Turbine Location
A
![Page 421: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/421.jpg)
Green roof is a roof that is partially or completely covered with vegetation and a growing medium.
Green roof has a longer lifespan than conventional roof, with roofs are under constant ultra-violet light.
In it’s first summer the roof was colonised by butterflies, insects and birds
Gre
en
Ro
of Current Roof System:
B
![Page 422: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/422.jpg)
Gre
en
Ro
of Green Roof Section:
Key:1. Sedum Roof2. Rock Fill3. Growing Medium4. Primary Filter Layer5. Secondary Filter LayerDrainage Layer6. Root Barrier7. Insulation8. Vapour Control Layer9. Cross Laminated Timber
1346
7
8
9
25
B
![Page 423: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/423.jpg)
Green roof provide a sustainable drainage as it reduce the immediate storm-water run off, by trapping the water within the soil and plants.
Gre
en
Ro
of Drainage:
B
![Page 424: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/424.jpg)
Green roof has a longer lifespan than conventional roof, with roofs are under constant ultra-violet light.
Gre
en
Ro
of Life Span:
B
![Page 425: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/425.jpg)
Gre
en
Ro
of
During the summer, solar energy is utilised by plants for evapotranspiration, reducing the temperature of the green roof and the surrounding microclimate.
Summer
Winter
During the winter months, a green roof can add to the insulating qualities of the roof. Water has a negative effect on thermal conductance. So in damp winter climate, such as the UK, a green roof will add little to the overall thermal performance of the roof.
Thermal Properties:B
![Page 426: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/426.jpg)
Gre
en
Ro
of
Sedums herbs Sedums herbs perennials Perennials grasses shrubs Grasses shrubs trees76 – 102 mm 127 – 178 mm 203 -279 mm 305 + mm
The roof currently has a thinner growing medium which is only suitable to plants such as sedum, we believe that the roof could benefit biodiversity by having different plant species.
Green Roof Depth Analysis:
The thickness of the growing medium will be depends on the vegetation. The taller and bigger the vegetation , the thicker the growing medium. This is because of the taller and bigger the plants, the more and longer the roots they will have to keep them stable.
B
![Page 427: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/427.jpg)
Gre
en
Ro
of Potential Biodiversity Promotion :
Our Suggestion:The botanical gardens could help bio-diversity by having a green roof incorporating plants which help endangered insect species.
However, as discussed on the previous page this would increase the loading on the roof if a thicker growing medium was needed.
We suggest a tiered system to enable more diverse planting. This would minimise growing medium thickness and maintain a reduced loading on the structure
B
![Page 428: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/428.jpg)
Large Heath Butterfly (Coenonympha tullia)
Habitat: Bog moss Hare’s-tail Cottongrass Cross-leaved Heath
Northern Brown Argus (Aricia artaxerxes)
Habitat:Drained and unimproved grasslandsRock-roseSheltered scrubPatches of bare ground
Gre
en
Ro
of Potential Biodiversity Promotion - Priority Species in UK Biodiversity Action Plan:
The roof has already been colonised by some common butterflies and insects. However the area around the site is home to the following endangered butterflies which we feel can benefit from different roof planting
B
![Page 429: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/429.jpg)
Small Pearl-bordered Fritillary (Boloria selene)
Habitat: Bracken Pteridium aquilinumDamp grassland Flushes and moorlandOpen wood-pasture
Dark Green Fritillary (Argynnis aglaja)
Habitat:Flower-rich grasslandPatches of scrubBracken Pteridium aquilinum
Gre
en
Ro
of Potential Biodiversity Promotion - Priority Species in UK Biodiversity Action Plan:
The roof has already been colonised by some common butterflies and insects. However the area around the site is home to the following endangered butterflies which we feel can benefit from different roof planting
B
![Page 430: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/430.jpg)
Current System:
2x 7000 litre tanks(5000 litre per tank dedicated to rainwater)
Simple filter system(Because the rainwater is only being use as toilet water, large and complex filter system can be avoid, Gravity treatment cyclonic filters are used to the north)
Part gravity fed(Harvesting to the north toilet drum is gravity fed)
Part pumped(Harvesting to the south end of the building is pumped with the booster set to allow all WC’s in building to be served)
Low maintenance Low running cost
Rai
nw
ater
Har
vest
ing Current Rainwater Harvesting From Roof Area:
C
![Page 431: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/431.jpg)
On this building, the rainwater is collected from the roof and used for flushing the toilets.
Rai
nw
ater
Har
vest
ing Current Rainwater Harvesting From Roof Area:
C
![Page 432: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/432.jpg)
Rai
nw
ater
Har
vest
ing Current Rainwater Harvesting From Roof Area:
Some of the rainwater being store away, the large drainage system for the rainwater will not be required, as another solution on reducing the cost on the construction of the building.
C
![Page 433: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/433.jpg)
Rai
nw
ater
Har
vest
ing Current Rainwater Harvesting From Roof Area:
This system reduces the amount of water needed to flush the toilet by at least 36% a year.
36%
C
![Page 434: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/434.jpg)
Rai
nw
ater
Har
vest
ing Potential Rainwater Harvesting From Roof Area:
Our Suggestion:We believe that the rainwater harvesting system can be more efficient than 36%
Surface area of roof =1630.099817m2
Based of the following criteria:Adequate drainage can be used to collect 100% of the waterThe green roof does not consume a large quantity of the waterC
![Page 435: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/435.jpg)
Rai
nw
ater
Har
vest
ing
Jan = 195,610Feb = 138,560Mar = 163,010Apr = 130,410May = 154,860Jun = 179,310
Jul = 187,460Aug = 171,160Sept = 203,760Oct = 220,060Nov = 187,460Dec = 203,760
Potential Rainwater Harvesting From Roof Area:
Jan Feb Mar Apr May Jun Jul Aug Sept Oct Nov Dec
22,000
20,000
18,000
16,000
14,000
12,000
10,000
8,000
6,000
4,000
2,000
Key:
= 2000 Litres Collected
We believe the surface area of the roof and average rainfall for Edinburgh can provide 100% of the water for the building
C
![Page 436: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/436.jpg)
Rai
nw
ater
Har
vest
ing
No. Visitors 2010 = 707,244 visitorsPublic Buildings require = 3-10 litres per person100% rainwater harvesting system requires = 2,121,732 litres Summer total (April to September) = 1,273,039.2 litresWinter total (October – March) = 848,692.8 litresSummer month = 212,173.2 litresWinter month = 141,448.8 litres
22,000
20,000
18,000
16,000
14,000
12,000
10,000
8,000
6,000
4,000
2,000
Jan Feb Mar Apr May Jun Jul Aug Sept Oct Nov Dec
(We will allow 3 litres per visitor because not all visitors to the park will use the facilities)
(As there are more visitors in summer 60% of the total will be required and 40% in winter)
Required Rainwater for 100% Rainwater Usage:
Key:
= Required
C
![Page 437: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/437.jpg)
Rai
nw
ater
Har
vest
ing
22,000
20,000
18,000
16,000
14,000
12,000
10,000
8,000
6,000
4,000
2,000
Key:
= Harvested = Stored = Shortage
Jan Feb Mar Apr May Jun Jul Aug Sept Oct Nov Dec
Jan = +54,161.2Feb = -2888.8Mar = +21561.2Apr = -81763.2May = -57313.2Jun = -32863.2
Jul = -24713.2Aug = -41013.2Sept = -8413.2Oct = +78611.2Nov = +46011.2Dec = +62311.2
Yearly shortage = -19,465.6
Rainwater harvesting from roofYearly capacity = 99.08%
Collected Water Vs Required Water:C
![Page 438: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/438.jpg)
The roof falls just short of providing 100% water for the building.
Our Suggestion:Harvesting water from the car park to provide any extra water Supplying the missing 0.92% Provide in times of low rain Allow extra water for the green roof
(Car park would be only suitable for flushing toilets due to potential contamination from cars)
Rai
nw
ater
Har
vest
ing How to Achieve 100% Rainwater Harvesting:
Surface area of car park area = 407.374491m2C
![Page 439: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/439.jpg)
Utilising rainwater from both the roof and car park should supply a large surplus which can be utilised in other ways
Our Suggestion:If car park water is used as first choice for toilets, the large surplus of water collected from the roof could use a UV sterilisation system to produce safe drinking water.
Advantages:No chemicals added to the water Low running costs Simple maintenance Safe and environmentally friendly
Rai
nw
ater
Har
vest
ing
Rain water harvested from roof
Secondary filtration with a minimum of 5 micron filter to remove any remaining sediment
Pre-filtration 10 micron filter to remove larger sediment
UV sterilisation systems to kill bacteria and viruses making the water suitable for drinking
Safe dinking water produced
Making Rainwater Safe to Drink:C
![Page 440: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/440.jpg)
Photovoltaic and solar hot water heating panels are installed on the south side of the roof.
Sola
r Po
wer Current Solar Power System:
D
![Page 441: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/441.jpg)
Sola
r Po
wer
Photovoltaic Panel Charge Controller
Charge Controller
Electric Meter
Battery Electrical Device
National Grid
Solar Power System:D
![Page 442: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/442.jpg)
Key:1.) N-type silicon2.) Junction3.) P-type silicon
4.) Photons5.) Electron flow6.) ‘Hole’ flow
Sola
r Po
wer Solar Power System - Panel Build-Up:
123
45
6
Photons in sunlight strike PV and may be absorbed by atom Energy of the photon transferred to the electron of the atom that receives that energy. Cell materials (semiconductors)
N-type, – charge (lot of nearly free electrons)P-type, + charge (lot of "Holes“ - when an electron has left its place)
When an electron is free to move and has a negative charge it will try to catch a positive charge Although the charges are attracted it is impossible for electrons to pass the junction The only way to find a Hole is by going out from the solar cell, through an electrical device and toward the P-Type semiconductor. Thus creating electricity.D
![Page 443: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/443.jpg)
When a visible light strike a solar cell, three things would happen:1) Pass straight through2) Be reflected3) Be absorbed
Sola
r Po
wer
1) 2) 3)
Solar Power System:D
![Page 444: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/444.jpg)
11sqm of photovoltaic panel on the roofGenerate 1400 kWh per year, which is equal saving 600kg of carbon dioxide per year
Sola
r Po
wer Solar Power System:
D
![Page 445: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/445.jpg)
Sola
r Po
wer
Evacuated tube solar thermal panels
Water pump
Hot water
Boiler
Solar Heating System:D
![Page 446: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/446.jpg)
Key:1.) Evacuated Tube2.) Copper Heat Pipe3.) Non-toxic LiquidSo
lar
He
atin
g Solar Heating System - Panel Build-Up:
Infra-red radiation from the sun is absorbed by this sealed heat pipe which contains an anti-freeze liquid. As heat rises, hot vapours from the antifreeze rise up to the top of the heat pipe where its copper tip connects with a header pipe through which more antifreeze flows This hot antifreeze is pumped through pipes inside the hot water tank with the end result that the water gets hotter and the antifreeze cooler
1
3
2
Hot vapour rises to heat pipe tip
Cold vapour liquefies and returns to bottom
D
![Page 447: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/447.jpg)
15sqm of solar hot water panels can generate 12 kV of warm water, which will provide enough hot water for 100000 hand wash or 1500 showers per year
Sola
r H
eat
ing Solar Heating System:
D
![Page 448: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/448.jpg)
The photovoltaic and the solar hot water heating panels both do not work.During us visit to the building, the panels were protected
We suggest an alternative method of heating could be more appropriate
Sola
r H
eat
ing Solar Heating System:
D
![Page 449: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/449.jpg)
He
atin
g A
lter
nat
ive Alternative Heating Method:
Ground Source Heat Pump:1.) Energy absorbed from the ground2.) Transferred to the refrigerant3.) Refrigerant turns to gaseous state4.) Refrigerant compressed, reducing its volume causes temperature rise
5.) Heat exchanger extracts heat from refrigerant to heat water6.) After loss of heat energy refrigerant turns back to liquid 7.) Cycle begins again
1
2
3
4
5
6
D
![Page 450: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/450.jpg)
Our Suggestion:Ground source heat pumps require a large space to lay pipes, to minimise damaging the site gardens we suggest the use of a bore hole heat pump.
He
atin
g A
lter
nat
ive Alternative Heating Method:
The geology study shows it is relatively easy to drill a borehole to a depth of approx. 25m. Which will be sufficient for the ground source heat pump.
25m
D
![Page 451: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/451.jpg)
He
atin
g A
lter
nat
ive Alternative Heating Method - Heat Pump Efficiency:
Standard Gas Boiler:
Ground Source Heat Pump:
The ratio of output energy compared to input energy is called co-efficiency of performance (COP). Most standard boilers have a COP of 1 (i.e. 1kW energy is turned into 1kW heat energy). Ground source heat pumps often achieve a COP of 4. At temperature of 35-45 degrees Celsius COP 5 can be achieved.
D
![Page 452: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/452.jpg)
Co
olin
g A
lter
nat
ive Alternative Heating Method – Combined Passive Cooling System
Our Suggestion:The bore hole can also be utilised in combination with the water tank to provide passive cooling
Summer Cooling:1.) Rainwater collected2.) Rainwater transferred to storage tank3.) Cold energy absorbed from the water tank4.) Cold transferred via distribution system
Winter Heating:5.) Heat energy absorbed6.) Transferred to the refrigerant7.) Refrigerant turns to gaseous state8.) Refrigerant compressed9.) Heat exchanger extracts heat from refrigerant to heat water10.) After loss of heat energy refrigerant turns back to liquid 11.) Cycle begins again
1
23
4
5
6
7
8
9
10
11
h Summer(Cold used for cooling)
Winter h(Heat used for compressor)
D
![Page 453: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/453.jpg)
Bio
mas
s B
oile
r
The Biomass Boiler is used to heat water and the building . The waste ash is then mixed into the soil and acts as fertilizer. The Botanical Garden uses a closed loop system of burning trees and waste from the garden and then replanting any trees used.
EUtilising Waste From The Biomass Boiler:
![Page 454: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/454.jpg)
Bio
mas
s B
oile
r
Advantages-Biomass is a sustainable fuel source if managed correctly, i.e. trees need to be planted to replace those used.
-It is virtually carbon neutral.
-If they are well maintained and run they will produce very little smoke.
-Biomass is a good way of using up waste wood. It is used by the Royal Botanical Gardens for a large proportion of their garden waste.
Disadvantage-The main disadvantage of using biomass boilers is the need for a regular supply of wood however this is over come by the building being a Botanical garden Centre.
Fact-12 cubic metres of wood chips can produce similar levels of heat to 1000 litres of heating oil. For your information, 4.8 cubic metres (approx 4.8 tonnes) of raw wood makes 12 cubic metres of chips.
EAdvantages and Disadvantages of Biomass Boilers:
![Page 455: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/455.jpg)
The Use of KLH Panels
Co
ncl
usi
on
Structure:
KLH panels are manufactured to specific sizes and thicknesses which means bulk producing is easy
In the event of a fire, the laminations of the panels make it difficult for the fire to spread throughout the building
The panels are easily assembled and connected on site, reducing labour costs and construction time
Compared to other structural systems, they are very small/thin which means thin load bearing walls are possible
They are manufactured from a sustainable wood source and are a storage of carbon
Structure:
During the construction of the building there were relatively few problems with the build up. This was due to the standardised KLH panelling system.
The first floor, roof and beams were all built offsite and simply delivered to be bolted onto the columns. This consequently meant that the building could be constructed extremely quickly and with relatively low skilled labourers.
This not only made it cheaper to build but it also meant that there were a limited number of human errors during construction.
Although the building is now structurally complete, the main contractor Xircon went into liquidation towards the end of the build. This has consequently meant that many small finishing bits on the building are either yet to be done or a later contractor had to finish.
![Page 456: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/456.jpg)
Wind Turbine:
The current wind turbine is not working due to a technical fault. From our analysis we believe the malfunction could be due to the complex computer system that controls the turbine.
We suggest an alternative vertical turbine would be more suited to the site because a turbine which does not rely on computer systems would eliminate the chance of software failure.
After analysing several vertical turbines we would suggest a system using the Ropatec Vertical turbine would be more suited to the site. The Ropatec would work under both lower and higher wind speeds. The wind analysis shows that the site could experience high wind due to channelling.
The downside to the Ropatec turbine is that is produces less power. To make up for this loss we suggest using two Ropatec Vertical turbines would produce approx. 2/3 of the power from the Quietrevolution QR5 system. The wind analysis shows that the site could be suited to a second turbine to the south of the building, we would suggest locating the second Ropatec turbine here.
Sustainability Conclusion:
Sedum Roof:
One of the key objectives of the botanical gardens is to promote biodiversity. We feel that the roof of this building has missed an opportunity to help struggling species of insects and birds. We suggest a green roof which incorporates plants which help endangered insect species would be more suited.
New species of plants on the roof may require deeper growing medium which would in turn increase the loading on the building. In order to have both deeper growing medium yet maintain a lower loading force we suggest a tiered system could be suitable and enable more diverse planting.
The roof has already been colonised by some common butterflies and insects. Our research showed that there are several species of endangered butterfly which are a priority for government biodiversity targets. We suggest selective planting could create a suitable habitat for these endangered butterflies.
We suggest that the following changes and additions could greatly increase the sustainability of the building:
Co
ncl
usi
on
![Page 457: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/457.jpg)
Rainwater Harvesting:
Currently the rainwater harvesting system provides 36% of the toilet water. We believe that the rainwater harvesting system can be utilised better and become more efficient than 36%. Our aim is to increase the amount of water harvested to provide 100% of the water for the building. Based on our calculations with the size of the roof, the amount of average rain on the site and the average consumption of water per visitor it is possible to harvest almost 100% of the water for the building.
Because rain amounts fluctuate we also suggest harvesting water from the car park would provide extra water to supply the 0.92% shortfall from the roof, provide in times of low rain and also provide water to feed the green roof.
If the building had a system which could utilise rainwater from both the roof and the car park our research shows that 100% of the needed water would be achieved. This can be achieved by increasing the size of the storage tanks and the area of water harvesting.
Car park water would be used as first choice for toilets.We suggest installing a UV filtration system so that the large surplus of water collected from the roof could be sterilised to produce safe drinking water. This filtration and sterilisation system would also be more suited than the current filtration system which leaves the water yellow and has resulted in complaints from the visitors.
Solar panels:
The current solar panel system is not working due to a technical fault. The specific fault is unknown, but we suggest that by using several systems together will provide a back-up to cover such times.
Based on our geological research we suggest that the site is suitable for a ground source heat pump. Commonly ground source heat pumps require a large space to lay pipes, we suggest that to minimise damaging the site gardens the use of a bore hole heat pump would be more suitable. The geological research shows that a bore hole of 25m should be easy to drill before reaching sandstone.
By combining the suggested ground source heat pump with both the bio mass boiler and the solar heating (when it becomes active) the building would be more covered for all eventualities. Ground source heat pumps are also one of the most efficient ways to heat the building and has significant environmental advantages over traditional heating systems.
The bore hole system can also be used in reverse to provide additional cooling in the summer. By using the borehole in combination with the water tank the building should be able to cool the passing liquid enough to provide passive cooling to the building
We suggest that the following changes and additions could greatly increase the sustainability of the building:
Sustainability Conclusion:C
on
clu
sio
n
![Page 458: Architectural Technology 3.1 Case Study](https://reader036.fdocuments.in/reader036/viewer/2022062521/568c38461a28ab02359e63a5/html5/thumbnails/458.jpg)
http://www.edwardcullinanarchitects.com/http://www.rbge.org.uk/http://www.journal-online.co.uk/article/7493-visitor-numbers-for-botanics-on-the-risehttp://www.metoffice.gov.uk/climate/uk/es/print.htmlhttp://www.solaruk.net/lazer2_solar_thermal_collectors.asp?gclid=CL3njZ7X7KwCFSFItAod_2CLHQhttp://www.coste53.net/downloads/Edinburgh/Edinburgh-Presentation/78.pdfhttp://www.architecture.com/SustainabilityHub/Casestudies/5-RoyalBotanicGardenEdinburgh.aspxhttp://www.petervaldivia.com/technology/energy/solar-power.phphttp://www.energ.co.uk/gshp-technologyhttp://www.britishbutterflies.co.uk/protected.asphttp://www.windfinder.com/windstats/windstatistic_edinburgh.htmhttp://www.quietrevolution.com/index.htm?gclid=CJOGmdvh76wCFdEhtAodPmZfPwhttp://peswiki.com/index.php/Directory:Vertical_Axis_Wind_Turbineshttp://www.zae-bayern.de/english/division-2/projects/archive/regenerative-cooling-system.htmlwww.speirsandmajor.comwww.zehnder.co.ukwww.edwardcullinanarchitects.co.ukwww.rbge.org.uk