Arch 211 Fieldtrip Notes

download Arch 211 Fieldtrip Notes

of 20

Transcript of Arch 211 Fieldtrip Notes

  • 8/16/2019 Arch 211 Fieldtrip Notes

    1/20

    Steel rebar is tested 98000psi in tension for failure

    Concrete is 12000 psi in compression

    99.9% curtain wall failed for water-proofing test

    Freeman house

    - Concrete textile block- Double walled system

    - Rebar system

    - 16” x 16” x 3.5”

    - Distance of cavity wall is 18”

    - On-site cast

    - Bad sand on site, not pure enough, causes cracks

    Cathedral

    - Casting done at night because of chemical reactions and curing time was influenced by

    temperature- Wall thickness is 1’ - 5’ at different spots, 12’ pours

    - Lots of base isolators built on mote so that base can move in midst of earthquake

    - Mix with spanish tile to get the colour of orange, Match Limestone and Red Oxide

    - Alabaster stone has to be airconditioned if not it’ll be bleached in the sunlight

    - Bronze doors

    Frank Gehry / Ting House

    - Light wood framing

    - Wood was cheaper than steel

    - Wooden floors above ground to prevent water from coming into contact with uppermaterial

    - Slab on grade exposes aggregate

    - Encourages cracks to go along control points

    - Incremental blocking to prevent

    - Window creates king studs

    ORCO

    - EC question from midterm

    Art Center College of Design

    - Steel beam

    - Vertical and diagonal trusses get wider as they approach the ends

    Gamble house

    - Scarf joints

    - Heavy timber

  • 8/16/2019 Arch 211 Fieldtrip Notes

    2/20

    Watt Hall

    - Prefabricated waffle slabs

    - Waffle slab connection concrete is cast on site

    - Columns

    - Rebars in columns- Exposed concrete with rough structure and plywood boards create different texture

    - Corners are smooth to accentuate edge

    Manhattan Beach Library

    - Spider joint and web joints

    - Double wall

    - 18” Cavity Wall

    - Mullion tied to web joints tied to superstructure

    - Angled glass to allow for tolerances

    ARTIC

    - ETFE

    - Little acoustic isolation

    - Bad with thermal stuff

    - Spacers to separate ETFE and structure

    - Fins to reduce span

    - At every 4 glass walls horizontal structure to prevent buckling (provide lateral support)

    - Frit pattern

    - 3’ rolls to be stitched across

    - Pipes to maintain air pressure- Symmetrical Diagrid arches

    - 27’ single layer

    - 2 layers of membrane

    - Fins to Reduce Span

    - 8 Inches to support ETFE

    - Frit printed on inside of OUTER ETFE layer

    - 200’ Width

    - Curtain wall is 120’ tall

    - Louvre system

    Museum

    - Aluminum panels linked with a locking system

    - Waterproof wall behind

    - Glass screen

    - Metal cladding over aluminium exterior? (vincent)

    - Beam structure is offset by 5’

  • 8/16/2019 Arch 211 Fieldtrip Notes

    3/20

     

    Sheats Goldstein

    - Plywood formed walls

    - Playing of textures in concrete

    - Smooth metal formwork for coffer

    1.  The temperature and duration of the brick kiln firing process will affect the final brick’s

    ● Color, size, weight, and hardness

    2.  The nominal size of CMU common block is 8’ x 8’ x 16’, the height of the brick corresponds

    to the height of _____ brick courses

    ● One

    ● Two 

    3.  The texture of this masonry material in the image below is caused by

    ● Quarrying process

    4.  Concrete is a hydraulically activated composite material which means _______?● When exposed to water the cement will go through a chemical process called hydration,

    which produces heat as a byproduct of the process

    5.  What is the cross sectional dimension of #8 rebar

    ● 1 inch in diameter

    6.  If a project’s concrete has a retarded in it, the _____?

    ● The concrete will have an admixture mixed into it that slows down the chemical process

    of hydration, which is often used in hot weather conditions

    7.  The technological development and sudden availability of which product allowed for the

    rapid expansion of light wood frame construction?

    ● Steel nails8.  Light wood framing is different from “old growth” heavy timber in that it can be harvested as

    a renewable resource

    ● True

    9.   A light gauge steel frame is different from light wood frame in that it does not require shear

    panels due to the additional strength of steel compared to wood

    ● False

    10.  Which element from the periodic table determines the hardness or malleability of ferrous

    metal alloys?

    ● Carbon

    11.  The primary “ingredient” (material) in the hot-dip galvanizing process, a method of

    protecting steel and other metals from corrosion is zinc

    12.  Standard “I-beams” are formed into shape by rollers

    13.  Which common species of wood have naturally decay-and-insect-resistant heartwood?

    ● Redwood and Eastern Red Cedar

    14.  Which of the following terms would you use to identify a piece of wood with 1 ½” x 11 ¼” x

    10’ as its actual dressed dimensions?

    ● Board

  • 8/16/2019 Arch 211 Fieldtrip Notes

    4/20

    ● Dimension Lumber

    ● Timber

    ● Stud

    15.  What are the advantages of using structural composite lumber in comparison to solid

    wood?

    ● Glue-laminated and composite lumber beams can be produced in sizes and of a qualityexceeding those available in solid timbers, structural composite lumber products make

    productive use of wood materials that are rapidly renewable or that might otherwise be

    treated as waste, structural composite lumber products offer benefits of dimensional

    stability, structural strength up to three times that of conventional solid material

    16.  Which of the following are standard precast slab elements

    ● Solid flat slab, hollow core slab, double tee, single tee

    17.  Stem curing of precast elements develops the full strength of the concrete many times

    faster than curing at ambient temperature

    ● True

    18.  Hollow core slabs may be produced by direct extrusion, by casting the concrete in twolayers with dry aggregate introduced as a filler to create the voids, or by using inflatable tubes to

    form the void

    ● True

    19.  A brick _______ course bonds two wythes together into structural unit

    ● Header

    20.  Although mortar joints can vary in thickness, mortar joints (brick or CMU) are usually

    standardized at inch, this thickness allows for distortion and unevenness in the masonry units

    ● 3/8

    21.  In CMU wall construction with common block, why is ½ running bond more common than

    1/3 running bond?●   The unit’s cavity cores won’t align in a 1/3 running bond

    22.  Where/when is grout used in a masonry wall?

    ● In wall cavities between wythes (i.e. composite wall with or without rebar), in a unit’s

    cores (with or without rebar)

    23.  What are the round holes on the surface of concrete in the image below and what are they

    for?

    ● They are form tie holes, indicating ties were used to temporarily hold concrete formwork

    together, they have no structural impact on the concrete for better or worse

    24.  What is being installed in the image below?

    ●   Form-liner for concrete formwork

    25.  Why was concrete being poured in the dark at the Los Angeles Cathedral?

    ● To control the heat generated from the chemical reaction due to hydration, the concrete

    was poured in early morning hours buy ended its pours at 9am

    26.  How did architect Tadao Ando achieve this concrete finish in the image below?

    ● It is a board formed concrete finish – this is the typical finish for board formed formwork

    ● By using pozzolana form-liners

    ● By using plywood that is thinner than normal formwork

  • 8/16/2019 Arch 211 Fieldtrip Notes

    5/20

    ● Concrete being very labor intensive achieved this finish by hand after the formwork was

    removed

    27.  Which member in light wood framing distributes vertical load forces from the header to the

    sole plate?

    ● King stud

    28.  Which member in light wood framing distributes lateral forces throughout the bearing wallsystem?

    ● Sheathing

    29.  In light wood construction, how is the frame attached to the foundation?

    ● ‘Hold down’ anchors bolted to the foundation

    30.  What is the standard spacing between studs in Type V wall construction?

    ● 16”

    31.  A rigid steel frame is considerably more expensive than a simple steel frame due to the cost

    of on-site welding

    ● True

    32.  A steel beam is labeled W12x50. What does the number 50 signify?● The weight in pounds per foot of length

    33.  Steel is often used in conjunction with other building materials, such as reinforcement in

    cast concrete. What type is structural force is steel added to counteract?

    ● Tensile

    34.  Steel is a better choice than heavy timber for high-rise construction because of its natural

    fire resistance

    ● False

    35.  How is a typical platform frame building braced against wind and earthquake forces?

    ●   With exterior sheathing of OSB or plywood

    36.  Glue-laminated elements are superior to one-piece heavy timber elements (of the samesize) in regards to all of the following except _____

    ● Energy required to manufacture

    37.  What type of construction is depicted in the image below?

    ● Heavy timber frame construction

    38.  Rigid structural joints are easy to achieve in all of the following materials except ______

    ● Reinforced concrete

    39.  We may use deep foundations in situations where competent soil lies too far beneath the

    surface to be reached by shallow foundations

    ● True

    40.  The most common type of failure in foundations is differential settlement

    ● True

    41.  The “stirrups” usually left projecting from the top of precast concrete beams are standard for

    cast into the concrete topping at the jobsite to create composite structural action

    ● True

    42.  Which of the following are NOT used in connection precast elements?

    ● Grouting

    43.  At Frank Lloyd Wright’s Freeman House, the masonry units were _____

  • 8/16/2019 Arch 211 Fieldtrip Notes

    6/20

    ● Precast at a factory in Chicago and shipped to Los Angeles

    ● Precast at ORCO to regulate quality control and then shipped to the jobsite

    ● Precast onsite with special aggregate imported from Chicago

    ● Precast onsite with aggregate extracted from the jobsite

    44.  At Frank Lloyd Wright’s Freeman House, the masonry wall rebar is_______

    ● Placed between the two wall wythes45.  At Frank Lloyd Wright’s Freeman House, the masonry units were

    ● 16” x 16” nominal size and laid in traditional bed of mortar

    ● 16” x 16” actual size and laid in traditional bed of mortar

    ● 16” x 16” nominal size and dry stacked

    ● 16” x 16” actual size and dry stacked

    46.  At Rafael Moneo’s LA Cathedral, why are there slotted holes on the exterior wall of the

    structure?

    ● The holes are the remainder of form ties that were used when temporarily holding the

    formwork in place

    47.  At Rafael Moneo’s LA Cathedral, why is the concrete a tan color?● The project focused on sustainability and when using the local silica in the concrete mix,

    it colored the concrete a more natural color than the typical grey

    ● The color is a concrete additive, chosen to match the interior limestone

    ● The complex concrete formwork required a chemical releasing agent that left the residue

    that colored the concrete

    ● The project used crushed Italian marble aggregate to generate this coloring effect

    48.  At Rafael Moneo’s LA Cathedral, approximately how thick is the base of this wall?

    ● It is up to 5 feet thick, having to hold all the cumulative weight of the structure above it

    49.  At the Selwyn Ting house in Mar Vista, open web steel joists were employed for what

    purpose?● To decrease the weight of the roof

    ● No wood products could achieve the span

    ● To create the visual appearance of lightness in the ceiling

    ● None of the above

    50.  At his home in Santa Monica, Frank Gehry exposed the wood members of conventionall

    residential construction for what purpose?

    ● To reduce costs

    ● To finish the project on time

    ● As a shortcut around building codes

    ● For aesthetic purposes

    51.  Building codes require Type V structures to be clad in either stucco or wood siding

    ● FALSE

    52.  In Craig Ellwood’s “Bridge Building” on the Art Center campus, which structural steel

    members diminish in the size of their cross-section towards the center of the bridge structure’s

    span

    ● All of the above

  • 8/16/2019 Arch 211 Fieldtrip Notes

    7/20

    53.  Ellwood’s treatment of the steel construction details at Art Center is a direct influence of the

    work of which architect?

    ● Mies Van der Rohe

    54.  The primary benefit of a steel frame with rigid (moment) connections over a steel frame of

    simple connections is the elimination of diagonal bracing members

    ● True55.  At the Gamble House, the connection of heavy timber wood frame members is modeled

    after traditional British (Victorian era) construction techniques

    ● False

    56.  Unlike modern construction techniques, the Gamble House was built in a manner so that

    parts (structural membrane) could easily be removed and replaced

    ● True

    57.  At the Gamble House, the building’s material (wood) was harvested from oak trees on the

    property to provide aesthetic consistency throughout the house, also a pre-modern example of

    sustainable construction

    ● False58.  At Watt Hall, the proportions of the waffle slab for coffered ceilings suggest that there are

    steel I beams embedded in the concrete

    ● False

    59.  At Watt Hall, the column spacing tells us the slab is working as a one-way system

    ● False

    60.  At Watt Hall, as a cost saving exercise during construction the waffle slab units around the

    perimeter of each column were eliminated and substituted with a (cheaper) flat slab

    ● False

  • 8/16/2019 Arch 211 Fieldtrip Notes

    8/20

     And books issued by building material manufacturers, construction trade associations, and

    organizations concerned with fire protection of buildings.)

    6. Define ASTM, CSA, CSI. (Answer: American Society for Testing and Materials, Canadian

    Standards Association, Construction Specifications Institute.)

    True-False Questions

    1. A building code contains off-street parking requirements. (F)2. There is no limit in the building code on the height to which a Type 1A building can be built.

    (T)

    3. First cost and life-cycle cost are the same thing. (F)

    4. A single-family dwelling may be built of unprotected wood. (T)

    5. In general it costs more to make a building more resistant to fire. (T)

    Multiple Choice Questions

    1. A zoning ordinance typically governs which of the following:

    a. Types of activities that may take place on a piece of land

    b. How much of the land may be covered by a building

    c. How far a building must be seReview Question

    Arch. 106 - Lecture Syllabus

    Materials and Methods of Construction (3)Professor Howard Weisenthal

    0ffice: 21-214........Phone/Voice Mail: 756 2491........email: [email protected]

    CHAPTER 1: MAKING BUILDINGS

    Answers to Questions in the Text

    1. The members of a typical building design team are: a. The architect: Determines the form of

    the building, coordinates the design team, and takes the major responsibility for specifying and

    detailing the exterior and interior finishes. b. The structural engineer: Develops with the architect

    the design of the structural system of the building, and takes the major responsibility for

    calculating, specifying, and detailing the loadbearing structure, including cladding attachments.

    c. The mechanical engineer: Develops with the architect the design of the heating, ventilating,

    and cooling systems of the building (and often the plumbing system), and takes the major

    responsibility for calculating, detailing, and specifying these systems. d. The electrical engineer:

    Develops with the architect a design for artificial illumination of the building, and takes the major

    responsibility for calculating, detailing, and specifying this system, as well as systems of electric

    power distribution and communications wiring. e. The geotechnical and/or foundation engineer:

    Develops with the architect a design for the foundations and substructure of the building, and

    takes the major responsibility for calculating, detailing, and specifying this system. All theseprofessionals are also involved in inspecting the construction work as it progresses, to be sure

    the specifications and details are followed, and to deal with questions that arise during

    construction. On many projects, a Construction Manager (CM) is also hired by the Owner of the

    building. The CM acts to coordinate the entire process of design and construction, and is often

    responsible for hiring the architect and engineers as well as the contractor and subcontractors.

  • 8/16/2019 Arch 211 Fieldtrip Notes

    9/20

    2. The designers of a building must work under the existing physical constraints of a building

    site (size, shape, soil conditions, subsurface water conditions, vegetation, etc.), as well as legal

    constraints that include zoning ordinances, building codes, access standards, OSHA

    regulations, and energy efficiency standards. Additional constraints come from building

    insurance companies, building contractors, labor unions, and the client's program, taste, and

    budget.3. Zoning ordinances control the type of use to which a piece of land may be put, how much of

    the land may be covered by buildings, how far the buildings must be set back from the property

    lines, how tall the building may be, how large a total floor area may be constructed on a given

    piece of land, how many parking spaces must be provided, and other such matters that have to

    do with the relationship of a building to its site and the community in which it is built. Building

    codes deal with questions of safety and health by controlling the quality of construction,

    especially with regard to structural stability and fire resistance, but also including space and light

    requirements, ventilation, emergency egress, and energy efficiency.

    4. Fire resistance of building assemblies is measured in hours of fire endurance. Fire resistance

    is determined by subjecting a building assembly to a fire endurance test as specified by ASTME-119.

    5. If this building is not sprinklered, Types 1A, 1B, 2A, 2B or 4 construction are permitted; Types

    2B and 4 are probably the most economical. If sprinklers are installed, Type 3A construction is

    also permitted.

    Additional Questions

    1. Name several organizations or types of organizations that publish construction information

    that is widely used by building professionals, and give an example of each. (Answer: ASTM,

    CSA, and ANSI publish standards for construction materials. Construction trade and

    professional associations publish technical information and technical standards. CSI and CSC

    publish Masterformat. Building materials manufacturers publish material concerning theirproducts.)

    2. What is Masterformat? Give titles of several of its primary divisions. (Answer: Masterformat is

    a standard outline for organizing information about construction materials and components. Its

    primary divisions cover such topics as Sitework, Concrete, Masonry, Metals, Wood and Plastics,

    etc.)

    3. List several performance concerns, and several construction concerns, that are typically

    taken into consideration by a building professional. (Answer: Performance concerns include

    such things as fire, building movement, water vapor condensation, water leakage, acoustical

    privacy, deterioration, cleanliness, and building maintenance. Construction concerns include

    such matters as safety, schedule, budget, quality of work, division of work between the shop

    and the field, optimum use of trades, sequencing of operations, inclement weather, fitting of

    components, and quality assurance.)

    4. What does a municipal building inspector have to do with new buildings? How does the

    inspector's work relate to zoning ordinances and building codes? (Answer: The building

    inspector receives applications for building permits, checks plans for conformance with building

    codes and zoning ordinances, issues building permits, and inspects construction to make sure it

    conforms to these standards.)

  • 8/16/2019 Arch 211 Fieldtrip Notes

    10/20

    5. What types of publications would you consult to determine fire resistance ratings of various

    building components? Who publishes them? (Answer: Fire resistance ratings are tabulated in a

    variety of catalogs and ht back from property lines

    d. The maximum distance between exits in a building

    e. Total floor area of a building on a given site

    (Answer: a,b,c,e)2. Fire resistance ratings for building components are given in units of:

    a. Degrees Fahrenheit b. Degrees Celsius c. Hours d. Foot-pounds (Answer: c)

    3. Access standards for buildings relate to:

    a. Access from the street to the building for automobiles

    b. Availability of an architect's drawings to the building inspector

    c. Accessibility of all the electrical wiring and plumbing for inspection and repair the lifetime of

    the building

    d. Access to a building by all members of the population, including the physically handicapped

     Answer: d)

    CHAPTER 2: FOUNDATIONS

    Answers to Questions in the Text

    1. The most common type of failure in foundations is differential settlement, in which overall

    settlement of the building is not excessive, but differences in the amount of settlement between

    different areas of the building cause failure of structural, cladding, or finish components of the

    building.

    2. Fine sand consists of equidimensional particles that are large enough to behave as a

    particulate soil. Silt particles are also equidimensional but are much smaller, and silts are

    classified as fine-grained soils. Clay particles are even smaller than silt particles and areplatelike rather than equidimensional. Unlike fine sand and silt, clay soils are governed in their

    properties by surface effects, and are therefore much more strongly affected by water content

    and the particular arrangement of particles in a given soil.

    3. Sheeting may be by means of soldier beams and lagging, sheet piling, or slurry wall.

    4. A watertight barrier is desirable in situations where lowering of the water table would have

    serious detrimental effects on neighboring buildings, and is possible in situations where the

    bottom edge of the barrier lies in an impermeable stratum of soil below the water table.

    5. We use deep foundations in situations where competent soil lies too far beneath the surface

    to be reached by shallow foundations.

    6. Belled caissons are practical only where the bell can be excavated from a cohesive soil, and

    where the bearing stratum beneath the bottom of the caisson is impervious to the passage of

    water.

    7. Precast concrete friction piles have the largest potential loadcarrying capacity, followed by

    steel pipe piles, steel Hpiles, and sitecast concrete piles.

    8. (The answer to this question is found in detail near the end of Chapter 2 of the text, under the

    heading "Designing Foundations").

    Additional Questions

  • 8/16/2019 Arch 211 Fieldtrip Notes

    11/20

    1. How do we know how much foundation load a soil can carry? (Answer: Building code tables

    such as Figure 2.5 give approximate bearing values for soils. For a more accurate

    determination, various laboratory tests and on-site tests may be conducted.)

    2. What is the purpose of the slurry used in the process of constructing a slurry wall? (Answer:

    The pressure of the slurry against the walls of the trench prevents the walls from collapsing.)

    3. When sheeting an excavation, which type of bracing is least obstructive to excavationoperations? (Answer: Tiebacks.)

    4. Why is it necessary to carry shallow foundations below the frost line? (Answer: If the soil

    beneath a foundation freezes, the foundation may be lifted by soil expansion or ice lenses.)

    5. How does a driven pile transmit the load of a building into the soil? (Answer: By friction

    between the sides of the pile and the soil, by end bearing of the bottom of the pile against firm

    soil, or by both these means.)

    True-False Questions

    1. Wood piles may be used without a decay-preventive treatment if they lie totally beneath the

    water table. (T)

    2. A waterstop is used to lower the water table in the vicinity of a building. (F)3. Bentonite clay makes an excellent waterproof membrane around a basement. (T)

    4. A slurry wall is a type of sheeting. (T)

    5. A tieback must always be anchored in rock. (F)

    6. The soil around an excavation can sometimes be stabilized by reinforcing it. (T)

    7. Combined footings are used to save money in cases where concrete prices are high. (F)

    8. Shallow footings may only be placed on undisturbed, natural soil. (F)

    9. The foundation engineer need not be consulted by the architect and structural engineer until

    the size and position of the building on the land have been determined. (F)

    Multiple Choice Questions

    1. Which of the following are deep foundations: a. Caisson b. Strip footing c. Rock anchor d.End-bearing pile e. Mat foundation f. Friction pile (Answer: a,d,f)

    2. Underpinning may include which of the following foundation types: a. Wall and column

    footings b. Piles c. Mini-piles d. Caissons (Answer: All of the above)

    3. Which of the following are design thresholds that represent a major difference in the cost of a

    foundation? a. Building below the water table b. Building a slab on grade versus a crawlspace c.

    Using steel sheet piling versus concrete sheet piling d. Building close to an existing building e.

    Going from shallow to deep foundations (Answer: a,d,e)

    4. Which of the following are cohesive soils: a. Cobbles b. Sand c. Clay d. Silt e. Peat f. Gravel

    (Answer: c)

    5. Piles may be made from a. Timber b. Precast concrete c. Sitecast concrete d. Stone e. Steel

    f. Brick (Answer: a,b,c,e)

    CHAPTER 3: WOOD

    Answers to Questions in the Text

    1. At the time a tree is cut, depending on the species of tree, the season of the year, and the

    amount of water present in the ground around the roots of the tree, its cells will contain a weight

    of water that is 30% to 300% of the dry weight of the cellulose and lignin. Assuming that the tree

  • 8/16/2019 Arch 211 Fieldtrip Notes

    12/20

    is immediately sawed into green lumber, each piece of lumber will then be seasoned by air

    drying or kiln drying. During this seasoning process, the free water contained in the hollow

    spaces of the cells is evaporated first, bringing the moisture in the lumber into the range of 26%

    to 32%. After the free water has evaporated, the bound water in the cell walls starts to

    evaporate, and the piece of lumber begins to shrink. Because radial shrinkage is not as

    pronounced as tangential shrinkage, each piece of lumber will also distort somewhat, the natureand degree of distortion depending largely on the portion of the log from which the piece was

    sawed and the orientation of the piece in the log. At a moisture content somewhere between

    13% and 19% the piece is considered seasoned and can be installed in a building. After it is in

    place in the building, it will continue to lose water under very dry atmospheric conditions, and

    reabsorb water when the air is humid. This is usually best observed on a seasonal basis, with

    wood members of a building shrinking noticeably during a prolonged heating season, and

    swelling during a humid summer.

    2. 3/4" X 3 1/2"; 1 1/2" X 3 1/2"; 1 1/2" X 5 1/2"; 1 1/2" X 7 1/4"; 3 1/2" X 3 1/2"; 3 1/2" X 11 1/4"

    if surfaced dry.

    3. Wood is laminated to achieve a size, shape, or quality of piece that would otherwise beimpossible.

    4. Wood panel products are span rated; the first number in the rating (32) is the allowable span

    in inches between centers of rafters when used as roof sheathing, and the second number (16)

    is the allowable span when used as subflooring.

    5. Pressure-treated wood might be specified for applications required increased resistance to

    fire, decay, or insects.

    6. Redwood, Cypress, and various Cedars are the resistant species most common in North

     America.

    Additional Questions

    1. What are the advantages of quartersawn lumber? For what kinds of end uses would youspecify it? (Answer: Quartersawn lumber is less prone to seasoning distortions, has a tighter

    grain figure, and has improved surface wearing qualities over plainsawed lumber. It is especially

    useful for flooring, interior trim pieces, and furniture stock.)

    2. What grade of plywood veneer would you specify for a surface to be painted? For the

    backside of a sheathing panel? (Answers: A, D)

    3. A variety of questions can be posed that require a knowledge of lumber dimensioning to

    solve. For example, you might show a detail of a foundation wall with a nominal 2" sill, 2X12

    floor joists, and 5/8" plywood subflooring, and ask the student to figure the total actual distance

    from the top of the foundation to the top of the subfloor.

    4. What will be the cost of 27 2X8s, each 14' long, if the price of the lumber is $240.00 per

    thousand board feet? (Answer: $120.96)

    True-False Questions

    1. The heartwood of a living tree is dead wood. (T)

    2. Summerwood is stronger and stiffer than springwood. (T)

    3. Box nails and common nails are Interchangeable in construction practice. (F)

    4. Wood treated with pentachlorphenol can be painted. (F)

  • 8/16/2019 Arch 211 Fieldtrip Notes

    13/20

    5. Sheet metal joist hangers are used to make a strong connection wherever wood joists bear

    on one another at right angles. (T)

    Multiple Choice Questions

    1. Which type of wood shrinkage is greatest? a. Longitudinal b. Radial c. Tangential

    (Answer: c)2. Which of the following are growth characteristics: a. Twisting b. Knot c. Check d. Decay

    e.Wane f. Cupping (Answer: b,d)

    3 Lag screws are inserted with: a. A hammer b. A screwdriver c. A wrench d. A pneumatic gun

    (Answer: c)

    4. Adhesives are widely used on the construction job site for: a. Laminating beams b.

    Connecting framing members c. Bonding the frame to the foundation d. Attaching subflooring

    and wall panels (Answer: d)

    CHAPTER 4: HEAVY TIMBER FRAME CONSTRUCTIONAnswers to Questions in the Test

    1. Heavy timber framing receives relatively favorable fire ratings because large timbers catch

    fire and burn relatively slowly, and do not lose strength as quickly as unprotected steel members

    during a fire.

    2. Where a wood beam joins a masonry wall, it must be protected against decay from moisture

    that may be present in the masonry, it must be anchored to the masonry so it cannot pull away,

    and it must be fastened in such a way that it can rotate out of the wall without damaging the wall

    if the beam should burn through during a fire.

    Additional Questions

    1. How is floor tilting due to wood shrinkage prevented in a building of Mill construction?(Answer: Columns are detailed so they do not bear on cross-grain wood at the floor lines. This

    is done either by using a single long column from foundation to roof, butting column sections to

    one another at floor lines with only steel plates between, or using iron pintle caps to transmit

    column loads through the floor structures.)

    2. Explain why long laminated wood beams are often spliced between columns rather than at

    columns. (Answer: By splicing beams with hinge connections at points of zero moment, the

    bending action of each beam can be made fully continuous, which results in maximum structural

    economy by minimizing the size of the beam.)

    True-False Questions

    1. Two-inch framing members are permitted in the roofs of Heavy Timber buildings. (F)

    2. Floor constructions in Heavy Timber buildings may not have any internal cavities. (T)

    3. Finish flooring over the structural deck of a building of Mill construction is optional. (F)

    4. All Heavy Timber buildings must have exterior masonry or concrete walls. (Fe-such walls are

    not required if there is sufficient space between buildings.)

    Multiple Choice Questions

    1. Wind uplift of the roof of a building of tradition Mill construction is counteracted by: a. Tying

    the roof beams together with iron dogs b. Using scuppers around the perimeter of the roof c.

  • 8/16/2019 Arch 211 Fieldtrip Notes

    14/20

    Using only heavy timber roof decking d. Running a steel anchor strap down the masonry wall

    from the end of each roof framing member (Answer: d)

    2. Which of the following heavy timber frames must be buttressed or tied at the base to resist

    horizontal thrusts: a. Arch b. Continuous beam c. Rigid frame or portal frame d. Dome e. Truss

    (Answer: a,c,d)

    CHAPTER 5: WOOD LIGHT FRAME CONSTRUCTION

    Answers to Questions in the Text

    3. In balloon framing the studs run in one piece from the sill to the rafter plate, while in platform

    framing the studs are interrupted by the floor platforms. Balloon framing has less vertical

    shrinkage from drying out of the wood, while platform framing is easier and safer to erect and is

    automatically firestopped, for which reasons it has become the method of choice.

    4. Platform framing is automatically firestopped at each floor by the double top plate.

    5. A wood beam under the ground floor of a platform frame will probably dry and shrink, allowing

    the floor to tilt, while a steel beam will not. A glue laminated wood beam is an acceptable

    substitute for a steel beam because it is made of thoroughly seasoned wood and will be fairlystable dimensionally.

    6. A platform frame building is braced laterally either by let-in diagonal bracing at the corners, or

    by rigid sheathing such as plywood panels or diagonal boards.

    7. A building code deals with the combustibility of platform framing in several ways. Most

    importantly, it restricts the height and size of such buildings, to keep occupant loads low and

    escape routes short. Escape of occupants is also facilitated by smoke and heat alarms, and

    bedroom windows of a size sufficient to permit the passage of occupants and firefighters.

    Building codes also encourage (and in many specific instances require) the protection of the

    wood frame with fire-resistant materials such as gypsum board or plaster, and sometimes with

    sprinklers.Additional Questions

    1. How is a platform frame anchored to a concrete or masonry foundation? (Answer: By means

    of anchor bolts embedded in the foundation, to which the sills are attached.)

    2. Diagram in simplified fashion how a carpenter uses a framing square to lay out a common

    rafter and a hip rafter. (The answers can be extracted from Figures 5.47 and 5.51.)

    3. What are the advantages and disadvantages of roof trusses as compared to conventional

    roof framing? (Answer: In many cases trusses are quicker to erect and use less material than

    the rafters and ceiling joists they replace. They can also span much farther than most

    conventional roof framing. In most cases, however, roof trusses are difficult to adapt to

    nonstandard or highly complex roof shapes, and they destroy most of the usefulness of the attic

    space.)

    4. Sketch a floor framing layout for the plan shown, using joists spaced 16" o.c. [Furnish a plan

    that is not too extensive, but that does include a stair opening, cantilevered floor bays on two

    adjacent sides, and interior partitions in both directions.]

    True-False Questions

    1. A platform frame can be made entirely of nominal 2-inch lumber, plus suitable sheathing and

    subflooring materials. (T)

  • 8/16/2019 Arch 211 Fieldtrip Notes

    15/20

    2. Foundations can be built entirely of wood. (T)

    3. A foundation can be insulated either on the exterior or the interior. (T)

    4. Wall frames are built in a horizontal position. (T)

    5. The size of floor joists is independent of the species of wood used. (F)

    6. Joist bridging is required by most codes. (F)

    7. Subflooring runs under the sole plate in a platform frame. (T)8. A rake is the same as an eave. (F)=

    E. Multiple Choice Questions

    1. Interior nonbearing partitions that run parallel to the floor joists can be supported by: a. Joist

    hangers b. Supporting studs c. Double joists d. Transverse blocking between joists c. Headers

    (Answer: c,d)

    2. Studs that support two floors and a roof may be: a. 2 x 4, 24" o.c. b. 2 x 4, 16" o.c. c. 2 x 6,

    24" o.c. d. 2 x 6, 16" o.c. (Answer: d)

    3. A gable roof requires:, a. A ridge beam supported at intervals by columns or walls b. Ceiling

     joists to tie it against lateral thrust c. Either of the above d. Neither of the above (Answer: c)

    CHAPTER 8: MASONRY

    Answers to Questions in the Text

    1. There are 3 syllables in "masonry." It should never be pronounced "masonerry."

    2. The most common types of masonry units are bricks, concrete masonry units, and stone

    .3. Mortar serves as an adhesive, holding masonry units together; as a cushion to create full

    bearing between units; as a sealant to keep weather from penetrating between units; and as a

    part of the finished surface of the wall.4. Bricks and blocks are laid by processes that are very similar, but a brick is placed with one

    hand, while a block requires two.

    5. Mortar joints are tooled to give a neat appearance of the desired type, and to compress the

    face of the mortar and make it more weathertight

    .6. A structural bond ties two or more wythes of masonry into a single wall.

    7. A cavity wall prevents penetration of water through a masonry wall by putting a continuous

    vertical airspace between the outer and inner wythes of masonry. When water reaches the

    cavity, it has no place to go but down. At the bottom of the cavity, the water is caught by a

    flashing and drained out through weep holes. (For cavity wall details see the illustrations in

    Chapter 8.)

    8. Stone is laid differently than brick in that it is sometimes irregular and each piece must

    chosen and trimmed to fit; stones are often too heavy to lift by hand and must be lifted with

    lewises and hoists; mortar joints in fine stonework are raked out and later pointed with

    nonstaining mortar; and acids are not usedto clean many types of stonework.

    9. External flashings should be installed at intersections of masonry walls with roofs or decks, to

    prevent penetration of water. Internal flashings should be installed wherever water might

  • 8/16/2019 Arch 211 Fieldtrip Notes

    16/20

    penetrate or accumulate inside a wall, such as over lintels and shelf angles, under copings and

    sills, at intermediate floors that bear on the wall, and at the base of the wall.

    10. Weep holes should be provided just above each internal flashing, in the outside wythe of the

    wall. Their function is to drain water that accumulates over the flashing. They may be

    constructed by leaving out the mortar in head joints, laying short pieces of rope in mortar joints

    and then pulling them out, or by inserting plastic or metal tubes in the mortar.11. Ordinary construction uses floors, roof, and interior walls of balloon frame construction, while

    Mill construction uses heavy timber framing for internal construction. The heavy timbers and

    decking used in Mill construction are slow to catch fire. Ordinary construction is usually

    protected with plaster or gypsum board over the wood components, and by firestopping

    between floors. Wood members bearing on the masonry walls in either system are firecut to

    prevent them from toppling the wall should they burn through in a fire.

    Solutions to Exercises in Text

    1. A restaurant is classified in Figure 1.1 as Type A-3, Assembly. In Type 4 construction, the

    building would be limited to 3 stories or 40' of height, with a maximum of 12,600 square feet perfloor--but because the building is more than 2 stories high, Figure 1.2 tells us that we must

    reduce the allowable floor area by 20%, which comes out to 10,080 square feet per floor. In

    Type 3B construction, these figures drop to 2 stories, 30', and 8,400 square feet, respectively. If

    unprotected steel joists are substituted for the wood joists, the construction type becomes 2C,

    but the figures remain the same as for unprotected Ordinary construction. If precast concrete

    plank floors with a fireresistance rating of 2 hours are used, the building becomes

    incombustibles By looking in the chart in Figure 1.3, line 11, we see that incombustible buildings

    with 2 hour floor construction are classified as Type 1B construction. Returning to the chart in

    Figure 1.1, we find that our masonry restaurant building with precast concrete plank floors would

    have no limitations on height or area.2. This wall will consist of 17 blocks and 16 mortar joints. Its length will therefore be 16 times

    16", plus the last block at 15 5/8". This adds up to 271 5/8", or 22'-7 5/8".

    3. This opening is equivalent to 4.5 blocks at 16" of length each, plus one mortar joint of 3/8".

    This works out to 72 3/8", or 6'-0 3/8".

    4. 44 courses times 8/3 inches per course equals 117 1/3", or approximately 9'-9 3/8".

    Additional Questions

    1. What are the components of modern masonry mortar? (Answer: Portland cement, lime, fine

    aggregate (sand), and water.)

    2. What are the major molding processes for clay bricks? (Answer: water-struck and sand-mold,

    which are hand molding processes, and dry-press and stiff mud, which are machine molding

    processes)

    .3. Sketch an elevation view of a portion of a brick wall laid in running (or common, English,

    Flemish) bond. t answer: see Figure 8.17).

    4. What are the three major types of building stone? (Answer: sedimentary, metamorphic,

    igneous) Give an example of each. (Answers: Sedimentary--sandstone, limestone, travertine;

    Metamorphic--marble, slate; Igneous--granite.)

  • 8/16/2019 Arch 211 Fieldtrip Notes

    17/20

    5. What is the usual way of adding vertical and horizontal steel reinforcing to a concrete

    masonry wall? (Answer: vertical reinforcing bars are grouted into the hollow cores of the

    masonry units at the desired intervals, and horizontal joint reinforcing made of very thin steel

    bars is laid into the bed joints of mortar at the desired intervals.)

    6. What is the chief reason to build a masonry cavity wall? (Answer: A cavity wall is much more

    resistant to the passage of water than a solid wall. Additionally, a cavity wall may be thermallyinsulated by adding slabs of plastic foam insulation within the cavity.)

    7. Sketch a detail section of the base of a cavity wall with a brick facing and an 8" concrete

    block backup. Label all the parts.

    True-False Questions

    1. Quicklime is mixed with Portland cement, sand, and water to make mortar. (F)

    2. Masonry units should always be wetted before laying. (F. under most conditions units should

    be laid without wetting).

    3. Bricks shrink considerably during firing. (T)

    4. There is no truly standard brick size. (T)

    5. Mortar color is of little consequence to the finished appearance of a brick wall. (F)6. Flemish bond is purely decorative. (F)

    7. It is possible to build a brick dome without using formwork. (T)

    8. It is almost impossible to build brick walls that contain steel reinforcing bars. (F)

    9. Limestone is easily cut just after it is quarried, but becomes harder with age. (T)

    10. Ashlar stone is very irregular. (F)

    11. Marble work should be cleaned with muriatic acid after the mortar has hardened sufficiently.

    (F)

    12. There is no truly standard size of concrete block. (F)

    Multiple Choice Questions

    1. Portland cement mortar that is growing hard before use may be retempered with water andused: a. within 30 minutes of its mixing b. within one hour of its mixing c. within 90 minutes of its

    mixing d. within a half day of its mixing e. within a day of its mixing (Answer:c)

    2. The most standard mortar joint thickness is:

    a. 1/8" (3.2 mm) b. 1/4"(6.4 mm) c. 3/8" (9.5`mm) d. 1/2"(12.7 mm)

    e. 5/8"(15.9 mm) (Answer: c)

    3. Which of the following mortar joint profiles are appropriate use outdoors in a severe climate:

    a. weathered b. concave c. vee d. flush

    e. raked f. stripped g. struck (Answer: b,c)

    4. Type I (moisture-controlled) concrete masonry units should be specified:

    a. Where appearance is important

    b. In damp weather

    c. For underground work

    d. In severe climates

    e. Where shrinkage of a wall must be controlled

    (Answer: e)

    5. Movement joints should be located in masonry walls:

  • 8/16/2019 Arch 211 Fieldtrip Notes

    18/20

    a. at discontinuities where cracks would tend to form

    b. every fourth course

    c. every sixth course

    d. every seventh course

    e. at a change of brick bond

    (Answer: a)

    6. Internal flashings should be located in masonry walls: a. below copings and sills b. above

    lintels and shelf angles c. below lintels and shelf angles d. at the base of the wall e. every sixth

    course (Answer: a,b,d)

    CHAPTER 9: STEEL FRAME CONSTRUCTION

    Answers to Questions in the Text

    1. Steel is any of a range of iron alloys that contain less than 2% carbon, while iron may contain

    a larger proportion of carbon.

    2. Steel structural shapes are produced by passing steel between rollers while it is still hotenough to be formed easily. The different weights and thicknesses of a shape are produced by

    varying the spacing between the rollers.

    3. The fabricator receives steel shapes from the mill and prepares them for specific building

    frame by cutting them to length, punching or drilling connector holes as required, adding

    connecting angles and plates, and cambering and priming the components as required. The

    erector receives these prepared building parts from the fabricator and assembles them on the

    building site.

    4. A W21 X 68 is a wide-flange steel section nominally 21" in depth and weighing 68 pounds per

    linear foot.

    5. In a moment connection, the flanges or a beam or girder are attached to the adjoiningmember with welds (or, rarely, with bolts) that are as strong as the flanges themselves. One

    member cannot rotate without rotating the other member. In a shear connection, the welds or

    bolts are designed to transmit only the vertical load from the beam or girder to the adjoining

    member, and small rotations are possible between the two members. Moment connections are

    used for joints that must be made rigid to contribute to the overall rigidity of the building, or to

    create structural continuity between members. Shear connections are less expensive than

    moment connections and are used for all other connections.

    6. The top flange of a beam is often coped so its top surface can lie in the same plane as the

    top of a girder to which it is connected. The bottom flange is coped in a knife connection to allow

    the beam to be inserted between the connecting angles by sliding it in from above.

    7. Composite construction allows a steel beam or deck and the concrete fill above to act

    together as a single structural unit, which allows the use of a lighter steel member than would

    otherwise be the case.

    8. Steel is advantageous in a fire because it is incombustible and does not contribute fuel to the

    fire as a wood beam does. Steel does, however, lose much of its strength at elevated

    temperatures, so must be protected by incombustible materials that will insulate it from the high

    temperatures of a fire.

  • 8/16/2019 Arch 211 Fieldtrip Notes

    19/20

    9. Trusses, dome, arches, cable net structure, space truss

    .Answers to Exercises

    3. A department store is classified as Use Group M, Mercantile. Assuming it has no automatic

    fire suppression system, we see from the table in Figure 1.1 that the lowest type of construction

    that might permit a four-story building with 17,500 square feet per floor is Type 2A, but we must

    correct the allowable area per floor (22,800) with a 10% adjustment for a four-story building asspecified by Figure 1.2. This gives 20,520 square feet per floor, which is greater than the 17,500

    we wish to build, so Type 2A construction will suffice. Moving to Figure 1.3, we can now

    determine on line 9 that lower-floor columns must have 2-hour protection, on line 11 that floor

    beams must be 1 1/2 hours, roof beams (line 12) must be 1 hour, and walls around shafts and

    stairways (lines 5 and 6) must be of 2-hour construction.

    Additional Questions

    1. Why are the edges of steel members beveled in some cases before welding? (Answer: A

    beveled edge allows access for the welding electrode so multiple passes can be made to fill the

     joint with weld metal to the same thickness as the member being connected).

    2. What is the difference between an AISC Type 1 connection and an AISC Type 2 connection?(Answer: The Type 1 is a moment connection, and the Type 2 is a shear connection.)

    3. Where is a seated connection likely to be used, and why? (Answer: A seated connection is

    used to connect a beam or girder to a column web, because it allows better access for

    pneumatic wrenches in this restricted location than does a framed connection.)

    4. In what circumstance is a butt plate used in a column-to- column connection? (Answer:

    Where the column changes from one nominal size of section to another.)

    5. Why are columns spliced at waist level above the floor? (Answer: This avoids conflict with

    beam-column connections, and is convenient for the ironworkers to reach.)

    True-False Questions

    1. Most steel beams are I-beam shapes. (F)2. Open-web steel joists are made by cutting the web of a wide-flange section along a zig-zag

    path, then rejoining the two halves in a greater depth by welding. (F)

    3. Riveting of steel building frames is obsolete. (T)

    4. In slip-critical connections, the bolts grip the two steel components so tightly together that the

    load is transferred between them by friction. (T)

    5. Plumbing-up refers to the process of raising sections of steel from the ground to their position

    in the building. (F)

    6. Column baseplates for smaller columns are usually attached to the columns in the fabricator's

    shop. (T)

    7. Plate girders are available from stock in a variety of sizes and spans. (F)

    8. Rigid frames are economical for low-cost manufactured steel buildings. (T)

    9. Tensile structures made of steel cables can be made rigid against wind uplift. (T)

    F. Multiple Choice Questions

    1. Steel structural`: shapes are produced by: a. casting b. forging c. die- forming d. rolling e.

    milling (Answer: d)

    2. The width of the flange of a W12 X 14: a. is 12" b. is 14"

  • 8/16/2019 Arch 211 Fieldtrip Notes

    20/20

    c. is the standard 6" dimension used for all W sections d. is up to the mill that produces it e.

    must be looked up in a handbook (Answer: e)

    3. Mild structural steel is designated by the ASTM number of:

    a. A36 b. A242 c. A441 d. A572 e. A588

    (Answer: a)

    4. The following materials are good for fireproofing steel columns:a. Concrete b. Brickwork c. Metal lath and plaster d. Gypsum board e. Spray-on fireproofing

    f. Mineral fiber slabs g. Intumescent coatings

    (Answer: all of the above)