Arch 2005 project week 4 1(phillip) - sheet - a-7-1 - wall sections
Click here to load reader
-
Upload
phillip-morris -
Category
Design
-
view
15 -
download
1
Transcript of Arch 2005 project week 4 1(phillip) - sheet - a-7-1 - wall sections
![Page 1: Arch 2005 project week 4 1(phillip) - sheet - a-7-1 - wall sections](https://reader038.fdocuments.in/reader038/viewer/2022100723/58f2bafa1a28ab8f438b45a5/html5/thumbnails/1.jpg)
J
123 m²
DRIVE IN TRUCK BAY
CASSON FOUNDATION1200mm DIA
150 mm CONCRETE SLAB
TORCH DOWN ROOFING16mm ROOF SHEATHING
3A.8.1
W4
150 mm CONCRETE SLAB
T/O PARAPET
T/O OWSJ
T/O SECOND FLOOR
4.72
4 m
3.50
5 m
3.76
2 m
0.20
0 m
T/O MAIN FLOOR
B/O CASSON
STEEL BEAM SIZE TO BESPECIFIED BY ENGINEER
CASSON FOOTING 1200mm DIA2360mm DIA BOTTOM
150mm GRAVEL
W1
12K1 @ 1830 O/C
1.98
1 m
STEEL BEAM SIZE TO BESPECIFIED BY ENEGINEER
G
1A.8.1
150 mm CONCRETE SLAB
150 mm CONCRETE SLAB
TORCH DOWN ROOFING16mm ROOF SHEATHING
CASSON FOUNDATION1200mm DIA
W1
4627 m²
RECEIVING AREA
W4
0.20
0 m
3.76
2 m
3.50
5 m
4.72
4 m
T/O PARAPET
T/O OWSJ
T/O SECOND FLOOR
T/O MAIN FLOOR
B/O CASSON
CASSON FOOTING 1200mm DIA2360mm DIA BOTTOM
150mm GRAVEL
12K1 @ 1830 O/C
STEEL BEAM SIZE TO BESPECIFIED BY ENGINEER
STEEL BEAM SIZE TO BESPECIFIED BY ENGINEER
1.98
1 m
1.20
0 m
Scale
Project number
Date
Drawn by
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
ConsultantAddressAddressPhoneFaxe-mail
1 : 30
A.7.1
WALL SECTIONS
0001
FINAL DRAWINGS
FEBRUARY 25TH, 2014PHILLIP MORRIS, 1004447251 : 30
WALL SECTION 31 1 : 30
WALL SECTION 42
No. Description Date