Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and...

222
ARARAT PLANNING SCHEME PERMIT APPLICATION 09/004799 AND NORTHERN GRAMPIANS PLANNING SCHEME PERMIT APPLICATION 5.2009.94.1 ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Transcript of Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and...

Page 1: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

 

 

 

ARARAT PLANNING SCHEME PERMIT APPLICATION 09/004799 AND

NORTHERN GRAMPIANS PLANNING SCHEME PERMIT APPLICATION 5.2009.94.1 ARARAT WIND ENERGY FACILITY

 

 

 

 

PANEL REPORT

 

 

 

 

 

 

 

 

 

 

 

 

SEPTEMBER 2010

Page 2: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

 

 

ARARAT PLANNING SCHEME PERMIT APPLICATION 09/004799

and NORTHERN GRAMPIANS PLANNING SCHEME

PERMIT APPLICATION 5.2009.94.1 ARARAT WIND ENERGY FACILITY

 

 

PANEL REPORT

 

 

ROBIN SAUNDERS, CHAIR 

 

 

JACK CHIODO, MEMBER 

 

 

IAN GIBSON, MEMBER 

SEPTEMBER 2010

Page 3: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 1

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

TABLE OF CONTENTS

1.  SUMMARY....................................................................................................................8 

2.  OVERVIEW ...................................................................................................................9 

2.1  THE SUBJECT SITE AND SURROUNDS.................................................................10 

2.2  NATURE OF THE PROPOSAL...............................................................................10 

3.  STRATEGIC & STATUTORY CONTEXT.............................................................12 

3.1  STRATEGIC PLANNING FRAMEWORK.................................................................12 

3.2  LEGISLATION .......................................................................................................12 

3.3  STATE PLANNING POLICY FRAMEWORK (SPPF) ................................................13 

3.4  LOCAL POLICY PLANNING FRAMEWORK (LPPF) ..............................................15 

3.4.1  Ararat Planning Scheme..............................................................................15 

3.4.2  Northern Grampians Planning Scheme ....................................................16 

3.5  ZONES ..................................................................................................................16 

3.6  OVERLAYS............................................................................................................17 

3.6.1  Ararat Planning Scheme: VPO1 and VPO2 ..............................................17 

3.6.2  Ararat Planning Scheme: WMO.................................................................17 

3.6.3  Northern Grampians Planning Scheme: ESO1.........................................18 

3.7  PARTICULAR PROVISIONS...................................................................................18 

3.7.1  Clause 52.32: Wind Energy Facility ...........................................................18 

3.7.2  Clause 52.17: Native Vegetation.................................................................20 

3.8  GUIDELINES .........................................................................................................20 

3.8.1  The Victorian Wind Energy Guidelines (VWEG) ....................................20 

3.8.2  The EPHC National Wind Farm Guidelines ............................................21 

3.8.3  Model Planning Permit Conditions for Wind Energy Facilities............21 

3.9  SUMMARY OF STRATEGIC FRAMEWORK ............................................................22 

3.10  CONCLUSIONS .....................................................................................................24 

4.  ISSUES..........................................................................................................................25 

4.1  NATURE OF SUBMISSIONS ..................................................................................25 

4.2  ISSUES FOUND TO BE NOT RELEVANT TO THE PANEL ....................................27 

4.2.1  Grid Connection ...........................................................................................27 

4.2.2  Loss of Value.................................................................................................29 

4.3  ARRANGEMENT OF ISSUES IN THE REPORT.......................................................30 

5.  FLORA AND FAUNA................................................................................................31 

5.1  WHAT ARE THE ISSUES? ....................................................................................31 

5.2  BACKGROUND .....................................................................................................32 

5.3  EVIDENCE AND SUBMISSIONS ............................................................................35 

5.3.1  Native vegetation removal..........................................................................35 

5.3.2  Disturbance of habit.....................................................................................37 

5.3.3  Potential bird strike......................................................................................38 

5.4  DISCUSSION .........................................................................................................39 

5.4.1  Native vegetation removal..........................................................................39 

5.4.2  Disturbance of habit.....................................................................................40 

Page 4: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 2

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

5.4.3  Potential bird strike......................................................................................43 

5.5  CONCLUSIONS AND RECOMMENDATIONS........................................................44 

6.  NOISE AND HEALTH ..............................................................................................45 

6.1  THE ISSUES..........................................................................................................45 

6.2  BACKGROUND .....................................................................................................45 

6.2.1  The application of NZS6808:2010...............................................................45 

6.2.2  Do the predictions meet the NZS6808:1998 criteria?...............................46 

6.2.3  Human health impact ..................................................................................50 

6.2.4  What permit conditions should be imposed? ..........................................51 

6.3  SUBMISSIONS........................................................................................................51 

6.4  DISCUSSION .........................................................................................................52 

6.4.1  The application of NZS6808:2010...............................................................52 

6.4.2  Do the predictions meet the NZS6808:1998 criteria?...............................52 

6.4.3  Human health impact ..................................................................................52 

6.4.4  What permit conditions should be imposed? ..........................................53 

6.5  CONCLUSIONS AND RECOMMENDATIONS ........................................................55 

7.  LANDSCAPE AND VISUAL IMPACTS ...............................................................56 

7.1  THE ISSUES ...........................................................................................................56 

7.2  BACKGROUND .....................................................................................................56 

7.2.1  Landscape impacts .......................................................................................57 

7.2.2  Visual impacts...............................................................................................60 

7.2.3  Cumulative impacts .....................................................................................62 

7.2.4  Night lighting impacts.................................................................................63 

7.2.5  Powerlines within the site ...........................................................................64 

7.3  SUBMISSIONS AND EVIDENCE .............................................................................64 

7.4  DISCUSSION .........................................................................................................68 

7.4.1  Landscape impacts .......................................................................................68 

7.4.2  Visual impacts...............................................................................................75 

7.4.3  Cumulative impacts .....................................................................................77 

7.4.4  Night lighting impacts.................................................................................77 

7.4.5  Powerlines within the site ...........................................................................79 

7.5  CONCLUSIONS .....................................................................................................79 

7.5.1  Landscape impacts .......................................................................................79 

7.5.2  Visual impacts...............................................................................................80 

7.5.3  Cumulative impacts .....................................................................................80 

7.5.4  Night lighting impacts.................................................................................80 

7.5.5  Powerlines within the site ...........................................................................80 

8.  ROADS AND TRAFFIC MANAGEMENT ...........................................................82 

8.1  THE ISSUES ...........................................................................................................82 

8.2  BACKGROUND......................................................................................................82 

8.3  SUBMISSION AND EVIDENCE...............................................................................84 

8.4  DISCUSSION..........................................................................................................85 

8.5  CONCLUSIONS......................................................................................................87 

Page 5: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 3

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

9.  AVIATION SAFETY AND FIRE .............................................................................88 

9.1  ISSUES...................................................................................................................88 

9.2  BACKGROUND .....................................................................................................88 

9.2.1  Interference with current operations.........................................................88 

9.2.2  Interference with Future operations ..........................................................89 

9.2.3  Aviation lighting ..........................................................................................89 

9.2.4  Fire risk from the WEF ................................................................................89 

9.3  SUBMISSIONS AND EXPERT EVIDENCE...............................................................89 

9.3.1  Interference with current operations.........................................................90 

9.3.2  Interference with Future operations ..........................................................90 

9.3.3  Aviation lighting ..........................................................................................90 

9.3.4  Fire risk from the WEF ................................................................................92 

9.4  DISCUSSION AND CONCLUSIONS.......................................................................92 

10.  SHADOW FLICKER, BLADE GLINT & ELECTROMAGNETIC 

INTERFERENCE (EMI) .............................................................................................93 

10.1  ISSUES...................................................................................................................93 

10.2  BACKGROUND .....................................................................................................93 

10.3  SUBMISSIONS AND EVIDENCE ............................................................................95 

10.3.1  Shadow Flicker .............................................................................................95 

10.3.2  Blade glint......................................................................................................96 

10.3.3  Electromagnetic Interference ......................................................................96 

10.4  CONCLUSIONS AND RECOMMENDATIONS ......................................................100 

11.  SOIL AND WATER MANAGEMENT .................................................................102 

11.1  WHAT IS THE ISSUE?..........................................................................................102 

11.2  BACKGROUND ...................................................................................................102 

11.3  EVIDENCE AND SUBMISSIONS ...........................................................................105 

11.4  DISCUSSION .......................................................................................................106 

11.4.1  Potential Erosion Hazards ........................................................................106 

11.4.2  Structural soundness of on‐site access roads .........................................106 

11.4.3  Mitigation and Management of Erosion .................................................107 

11.5  CONCLUSIONS ...................................................................................................109 

12.  SOCIAL AND ECONOMIC...................................................................................110 

12.1  WHAT IS THE ISSUE?..........................................................................................110 

12.2  BACKGROUND ...................................................................................................110 

12.2.1  The Proponent’s Approach .......................................................................110 

12.2.2  Results of Perception Studies....................................................................110 

12.2.3  The Consultation Process ..........................................................................111 

12.2.4  Minimising Social Disruption...................................................................112 

12.2.5  Impacts on Agriculture and the Tourism Industry ...............................112 

12.2.6  Maximising Local Economic Benefits......................................................113 

12.2.7  Sustainable Energy.....................................................................................114 

12.3  EVIDENCE AND SUBMISSIONS ...........................................................................114 

12.3.1  The Nature of Submissions .......................................................................114 

12.3.2  The Consultation Process ..........................................................................114 

Page 6: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 4

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

12.3.3  Impacts on Agriculture and the Tourism Industry ...............................114 

12.3.4  Maximising Local Economic Benefits......................................................115 

12.3.5  Sustainable Energy.....................................................................................116 

12.4  DISCUSSION .......................................................................................................116 

12.4.1  Results of Perception Studies.........................................................................116 

12.4.2  The Consultation Process ...............................................................................117 

12.4.3 Minimising Social Disruption........................................................................117 

12.4.4  Impacts on Agriculture and the Tourism Industry ....................................118 

12.4.5 Maximising Local Economic Benefits ...........................................................119 

12.4.6  Sustainable Energy ..........................................................................................119 

12.5  CONCLUSIONS ...................................................................................................119 

13.  ABORIGINAL CULTURAL HERITAGE.............................................................121 

13.1  THE ISSUES.........................................................................................................121 

13.2  BACKGROUND ...................................................................................................121 

13.3  DISCUSSION .......................................................................................................122 

13.4  CONCLUSIONS ...................................................................................................122 

14.  ADMINISTRATION AND ENFORCEMENT....................................................123 

14.1  ISSUES.................................................................................................................123 

14.2  BACKGROUND ...................................................................................................123 

14.3  SUBMISSIONS......................................................................................................124 

14.4  DISCUSSION .......................................................................................................126 

14.5  CONCLUSIONS ...................................................................................................127 

15.  PLANNING PERMIT AND ENVIRONMENTAL MANAGEMENT PLAN 128 

15.1  ISSUES.................................................................................................................128 

15.2  BACKGROUND ...................................................................................................129 

15.3  SUBMISSIONS......................................................................................................131 

15.4  DISCUSSION .......................................................................................................131 

15.5  CONCLUSIONS ...................................................................................................133 

16.  CONCLUSIONS AND RECOMMENDATIONS...............................................135 

16.1  CONCLUSIONS ...................................................................................................135 

16.2  RECOMMENDATIONS ........................................................................................136 

 

Page 7: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 5

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

APPENDICES

APPENDIX A  SUBMISSIONS ....................................................................................138 

APPENDIX B  HEARING DOCUMENT LIST..........................................................139 

APPENDIX C  DRAFT PLANNING PERMIT (PREPARED BY THE 

PROPONENT) ......................................................................................142 

APPENDIX D  ENVIRONMENTAL MANAGEMENT PLAN (PREPARED  

BY THE PROPONENT).......................................................................165 

APPENDIX E  RECOMMENDED PLANNING PERMIT.......................................190 

APPENDIX F  RECOMMENDED “ENVIRONMENTAL MANAGEMENT  

PLAN AT THE PRE‐CONSTRUCTION STAGE”.........................198 

 

TABLE OF FIGURES

Figure 1  Location and form of the Ararat WEF proposal .............................. 11 

Figure 2  Locations of background noise measurements................................ 48 

Figure 3  Background noise levels at House AH12, with average 

L95 noise levels superimposed ............................................................ 50 

Figure 4  Site Access Points ................................................................................. 83 

Figure 5  Lookout Hill broadcast transmitter and proposed 

Ararat Wind Farm showing areas potentially affected 

by television interference. ................................................................... 97 

Figure 6  Potential interference zones predicted by the RES 

Interference Model ............................................................................... 98 

Figure 7  Development of the EMP through its stages.................................. 133 

TABLE OF TABLES

Table 1 Summary of Strategic Framework .......................................................... 22

Table 2 Visual assessment of residential viewpoints for which photomontages were done....................................................................... 61

Table 3 Visual impact of lights trialled and installed in Victoria and South Australia........................................................................................ 63

Table 4 Summary of SNR output from the RES Interference Model .................. 99

Page 8: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 6

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

 

LIST OF ABBREVIATIONS USED

ABS  Australian Bureau of Statistics 

AH8  House 8 ‐ a location of ambient noise monitoring, shown on 

Figure 1 

ARC  Ararat Rural City 

ARCC  Ararat Rural City Council 

AusWEA  Australian Wind Energy Association 

BBMP   Bat and Bird Management Plan 

CFA  Country Fire Authority 

BL&A  Brett Lane & Associates 

CASA  Civil Aviation Safety Authority 

CHMP  Cultural Heritage Management Plan 

dBA  Measure of loudness, measured on the decibel scale, and 

adjusted for equivalence to the response of the human ear. 

DPCD  Department of Planning and Community Development 

DSE  Department of Sustainability and Environment 

EMI  Electromagnetic Interference 

EMP  Environmental Management Plan 

EPHC  Environment Protection and Heritage Council 

ESO1  Environmental Significance Overlay Schedule 1 

GHCMA  Glenelg Hopkins Catchment Management Authority 

GWMW  Grampians‐Wimmera‐Mallee Water 

LPPF  Local Planning Policy Framework 

L95  Noise level exceeded for 95% of the time 

MAV  Municipal Association of Victoria 

Page 9: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 7

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

MSS  Municipal Strategic Statement 

MW  Megawatt (a million Watts, a measure of electrical power) 

NGS  Northern Grampians Shire 

NGSC  Northern Grampians Shire Council 

NHMRC  National Health and Medical Research Council 

NZS6808:1998 New Zealand Standard NZS6808:1998 Acoustics – The Assessment and Measurement of Sound for Wind Turbine Generators

NZS6808:2010 New Zealand Standard NZS6808:2010 Acoustics – The Assessment and Measurement of Sound for Wind Turbine Generators (superseding the 1998 version in New Zealand)

OLS  Obstacle Limitation Surface 

PAD  Planning Application Documentation 

PS  Pyrenees Shire  

PSC  Pyrenees Shire Council 

RES  RES Australia Pty Ltd 

RVP01  Residential Viewing Point 01 

SPPF  State Planning Policy Framework 

VCAT  Victorian Civil and Administrative Tribunal 

VPO1  Vegetation Protection Overlay Schedule 1 

VPO2  Vegetation Protection Overlay Schedule 2 

VPP  Victorian Planning Provisions 

VWEG  Victorian Wind Energy Guidelines (Policy and Planning 

Guidelines for Development of Wind Energy Facilities in Victoria, 

September 2009) 

WCMA  Wimmera Catchment Management Authority 

WEF     Wind Energy Facility 

WTG    Wind Turbine Generators 

Page 10: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 8

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

1. SUMMARY

RES Australia Pty Ltd (the proponent), part of Renewable Energy Systems, 

which has wind energy facilities in a number of countries, has applied for 

planning permits to establish a 75 turbine wind energy facility north east of 

Ararat.  The relevant permit applications are Application 09/004799 under the 

Ararat Planning Scheme (for 70 turbines) and Application 5.2009.94.1 1 under 

the Northern Grampians Planning Scheme (five turbines). 

The application is based on the wind turbines having a hub height of up to 94 

metres, a rotor diameter of up to 104 metres, and a blade tip height of up to 

135 metres, and will have a capacity up to 3.3 Megawatts. 

The electrical connection to the State’s high voltage grid is not included as part 

of the application. 

The principal issues arising from the Ararat WEF proposal are: 

medium to high landscape and visual impacts; 

the need for native vegetation removal and the required offset works to 

achieve the Net Gain policy; 

the need for some further investigation of stability and safety issues on the 

on‐site and off‐site access routes; and 

the need to take particular care to avoid erosion of the fragile soils encountered at the site. 

These matters, and a number of more minor matters, are addressed in the 

Recommended Permit Conditions (Appendix E) and the Environmental 

Management Plan at the Pre‐Construction Stage (Appendix F). 

After considering the contribution that the WEF can make to sustainable 

energy supply, the Panel had no difficulty in concluding that the net 

community benefit was substantial, and the project should proceed. 

Other matters, with potential for wider application than just for the Ararat 

WEF are: 

the conclusion that the compilation by DSE of all Victorian data on bird and 

bat strike from Victorian WEF’s is highly desirable; 

the approach taken in this report of having not merely an outline EMP, but 

a developed EMP, which included the recommendations of the Panel, the 

recommendations from other authorities, and all the detailed commitments 

of the proponent, including the adoption by the proponent of the 

recommendations of the experts it employed. 

Page 11: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 9

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

2. OVERVIEW

The Permit Applications:

Ararat Planning Scheme Application 09/004799 Northern Grampians Planning Scheme Application 5.2009.94.1 1

The Project: The proposed Wind Energy Facility (WEF) is for 75 wind turbine generators (70 within the Rural City of Ararat, and 5 within the Northern Grampians Shire) and associated infrastructure sited 9 to 17 km northeast of Ararat on both sides of the Pyrenees Highway.

Proponent: RES Australia Pty Ltd

Responsible Authority:

Minister for Planning

Panel Members: A Panel with the following members was appointed under Sections 97E, 153 and 155 of the Planning and Environment Act 1987 to consider submissions and make recommendations to the Minister about the Ararat WEF: Robin Saunders, Chair Jack Chiodo, Member Ian Gibson, Member

Panel Hearings: The Hearings were held at Ararat on the following dates: Directions Hearing: 27 April 2010 Main Hearings: 5, 6, 7, 8, 12, 13 and 14 July 2010

Site Inspection: An accompanied inspection was conducted on the second day of the Hearings (6 July 2010). The Panel also viewed the site and surrounding Wind Energy Facilities (Waubra and Challicum Hills) from public roads on a number of occasions, and was unaccompanied on these occasions.

Appearances: Department of Planning and Community Development represented by Ms Donna Grace-Davis.

RES Australia Pty Ltd represented by Mr Tim Power, a Partner of Freehills, who called the following evidence:

Mr Chris Turnbull of Sonus Pty Ltd—Acoustics;

Mr Allan Wyatt of ERM Consultants—Landscape/visual;

Mr Sydney Herron of Ambidji Group P/L—Aviation;

Mr Brett Lane of Brett Lane & Associates—Flora and fauna;

Dr Trenton Gilbert of GL Garrad Hassan—Shadow flicker, blade glint and electromagnetic interference.

Ararat Rural City Council represented by Mr Eoghan McColl.

Northern Grampians Shire Council represented by Mr Scott Douglas.

Mrs Lorraine Stewien

Mr Ormond Randell

Submitters A list of all submissions referred to the Panel is included in Appendix A

Page 12: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 10

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

2.1 THE SUBJECT SITE AND SURROUNDS

The Planning Application Documentation (PAD), comprising Volume 1 – 

Main Report, Volume 2 – Specialist Assessments and Volume 3 – Drawings, 

describes the site, the surrounds and the proposed development.  Figure 11 

below shows the locality of the WEF. 

The WEF is entirely within the Farming Zone under both councils’ planning 

schemes.  The land is at the western end of the Great Dividing Range, within 

the Wimmera River catchment (via Mount Cole Creek) to the north and within 

the Hopkins River catchment to the south. 

2.2 NATURE OF THE PROPOSAL

The proposed WEF is for 75 wind turbine generators and associated 

infrastructure sited 9 to 17 km northeast of Ararat on both sides of the 

Pyrenees Highway.  70 of those turbines are within the Ararat Rural City 

(ARC), and 5 within the Northern Grampians Shire (NGS).  The proposal also 

includes access tracks, access points from public roads, internal collector 

network cabling (overhead and underground), permanent meteorological 

masts, on‐site electrical substation and associated buildings and works. 

The wind turbines proposed will fit within the following dimensions: 

a blade tip height of up to 135 metres; 

a rotor diameter of up to 104 metres; 

a hub height of up to 94 metres; 

and have a capacity up to 3.3 megawatts. 

Other features of the WEF are: 

road and junction upgrading / construction works to provide five site 

entries; 

provision of five site vehicular access locations; 

preparation of up to four construction compounds; 

crane hard‐standing areas; 

excavation of rock for roadbase and land filling (located within the 

infrastructure zone; 

excavation and construction of wind turbine foundations; 

relocation of excess excavated material; 

construction of crane hard‐standing areas; 

1 Source: Volume 2 of the Application Documentation, Landscape and Visual Assessment ERM

September 2009, Figure 2.1

Page 13: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 11

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

construction of approximately 55km of new permanent access tracks; 

clearing of some native vegetation on‐site and at the site entry locations; 

establishment of mobile concrete batching plants; 

underground cabling that generally follows the access track alignment and 

some additional overhead power lines; 

on‐site substation; 

site office and storage building; 

maintenance and control room including car parking area; and 

three permanent meteorological masts (lattice tower construction). 

The general location and form of the proposal is given in Figure 1 below, taken 

from Mr Wyatt’s Expert Witness report.2 

Figure 1 Location and form of the Ararat WEF proposal

 

2 Expert Witness Statement of Allan Wyatt, Landscape and Visual Assessment, June 2010, Figure 2.1

Page 14: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 12

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

3. STRATEGIC & STATUTORY CONTEXT

3.1 STRATEGIC PLANNING FRAMEWORK

This section of the Report considers the policy context for the Ararat WEF and 

focuses on the strategic and policy issues.  It assesses how the application 

meets the objectives of the Ararat and Northern Grampians Planning Schemes. 

It includes a brief appraisal of the legislation relevant to the application, State 

Planning Policy Framework (SPPF), the Local Planning Policy Framework 

(LPPF) including Municipal Strategic Statements (MSS) and Local Planning 

Policies, the appropriate zone and overlay controls, and particular provisions 

in the Victorian Planning Provisions.  Further, it outlines the status and 

content of Guidelines available to evaluate wind energy facilities. 

The submissions from the Department of Community Planning and 

Development (DPCD), ARC and NGS Councils and the evidence from Mr 

Power for the applicant set out the details of the relevant planning provisions.  

The Panel notes that other submitters did not take issue with the interpretation 

of these provisions by DPCD, Councils and the proponent. 

The Panel does not propose to set out the details of all the provisions that may 

be relevant; rather, the Panel will refer to them as appropriate.  The clauses 

referred to this discussion are contained in the Ararat and Northern 

Grampians Planning Schemes. 

3.2 LEGISLATION

The legislative framework surrounding the development of wind farms has 

been thoroughly addressed in other Planning Panel reports relating to wind 

farms.  This report will outline the legislative and strategic planning 

framework that has informed the application and the Panel’s considerations, 

but will not reproduce it in depth. 

The relevant legislation is described in the RES Australia Main Application3, 

which covers the following: 

Planning and Environment Act 1987; 

Environment Effects Act 1978; 

3 RES Australia, Ararat Wind Farm Planning Permit Application Documentation, 2009 Volume 1, pp.

101-09

Page 15: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 13

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Environment Protection Act 1970; 

Flora and Fauna Guarantee Act 1988; 

Aboriginal Heritage Act 2006; 

Heritage Act 1995; 

Catchment and Land Protection Act 1994; 

Water Act 1989; 

Victorian Renewable Energy Act 2006; and 

Environment Protection and Biodiversity Conservation Act 1999. 

3.3 STATE PLANNING POLICY FRAMEWORK (SPPF)

The SPPF clarifies the aspects of State Policy to be considered in land use 

planning decisions.  It establishes the need to integrate the range of policies to 

be considered in any issue to be determined, and “balance conflicting 

objectives in favour of net community benefit and sustainable development”. 

The Goal of the SPPF (Clause 11.02) is: 

...to ensure that the objectives of planning in Victoria (as set out in Section 

4 of the Planning and Environment Act 1987) are fostered through 

appropriate land use and development planning policies and practices 

which integrate relevant environmental, social and economic factors in the 

interests of net community benefit and sustainable development. 

A number of clauses within the SPPF are relevant to the consideration of the 

proposed Ararat WEF.  The single most significant clause is 15.14 Renewable 

Energy, which has the following Objective 15.14‐1: 

To promote the provision of renewable energy in a manner that ensures 

appropriate siting and design considerations are met. 

Clause 15.14‐2 covers General Implementation: 

Planning should facilitate renewable energy development in appropriate 

locations. 

Planning should consider the economic and environmental benefits to the 

broader community of renewable energy generation and the effects on the 

local environment. 

In planning for wind energy facilities, planning should: 

- Facilitate the consideration of wind energy development proposals; 

- Recognise that economically viable wind energy facilities are dependent on 

locations with consistently strong winds over the year and that such sites 

may be highly localised; 

Page 16: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 14

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

and must take into account the Policy and Planning Guidelines for 

Development of Wind Energy Facilities in Victoria, 2009. 

In considering proposals for renewable energy, planning and responsible 

authorities should have regard to the Renewable Energy Action Plan, July 

2006. 

The Panel noted that the terminology including “promote” and “facilitate” 

establishes support for the establishment of renewable energy facilities, 

including wind farms.  On the other hand, the SPPF does not provide 

unqualified support for wind farms, requiring consideration of appropriate 

location, design and environmental impacts.  Importantly, the clause 

references the Policy and Planning Guidelines for Development of Wind Energy 

Facilities in Victoria, revised September 2009, providing a statutory basis for the 

Wind Energy Guidelines for the proponent, submitters, Planning and 

Responsible Authorities, and the Panel. 

Several other clauses within the SPPF are of significance: 

Clause 15.01 Protection of catchments, waterways and groundwater requires 

avoidance of activities which degrade catchment soils and water sources.  

Clause 15.04 Air quality requires protection and improvement of air 

quality. 

Clause 15.06 Noise abatement states that suitable project design or distance 

separation is needed to protect sensitive land uses and development. 

Clause 15.07 Protection from wildfire requires avoidance of conditions that 

promote wildfire and installation of appropriate infrastructure and 

equipment to assist with fire fighting efforts. 

Clause 15.09 Conservation of native flora and fauna requires protection and 

conservation of biodiversity, including native vegetation and habitats for 

native plants and animals, and suitable control of pest plants and 

animals. 

Clause 15.11 Heritage requires the conservation of places that have 

natural, environmental, aesthetic, historic, cultural, scientific or social 

significance or other special values important for scientific and research 

purposes. 

Clause 17.04 Tourism encourages tourism development that maximises 

employment and assists the State to be a competitive tourist destination. 

Clause 17.05 Agriculture seeks to protect the State’s agricultural base from 

unplanned loss and encourages sustainable agriculture. 

Clause 18.04 Airfields seeks to facilitate the siting of airfields and 

extensions to airfields, restrict incompatible land use and development in 

Page 17: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 15

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

the vicinity of airfields, and recognise and strengthen the role of airfields 

as focal points within the Stateʹs economic and transport infrastructure 

Clause 18.09 Water supply, sewerage and drainage states runoff from 

development should not contaminate water supplies.  

Clause 19.03 Design and built form requires development to have regard to 

its context and achieve good quality design. 

3.4 LOCAL POLICY PLANNING FRAMEWORK (LPPF)

3.4.1 Ararat Planning Scheme

The MSS within the Ararat Planning Scheme provides the local land use 

planning framework relevant to the consideration of the proposed Ararat 

WEF.  Relevant clauses include: 

Clause 21.02 Vision – Strategic Framework outlines the Council’s vision for 

the community.  Notably, it includes the following: 

Actively pursue wind energy industry opportunities for the establishment 

of the Ararat Wind Industry Park 

Actively investigate and promote opportunities for large scale tourism 

accommodation development. 

Support and advocate for the construction of the Challicum Hills Wind 

Farm. 

Clause 21.05 Environment, covering natural resource management, water 

quality, catchment management, rural landscapes, heritage and 

sustainable development. 

Clause 21.06 Economic Development, outlining the importance of existing 

industries and promoting new ones.  This clause includes the following 

reference to the Wind Energy Industry: 

Ararat Rural City Council is committed to actively pursuing wind energy 

opportunities in the municipality including wind farm sites (such as at 

Challicum Hills) and the establishment of manufacturing facilities related 

to the wind energy industry.  Council supports the development of an 

Ararat Renewable Energy Park. 

The Ararat Renewable Energy Park will accommodate different types of 

industrial uses including manufacturing primarily relating to renewable 

energy.  The site is ideally located adjacent to the aerodrome and along the 

Western Highway providing excellent access and logistics opportunities. 

Page 18: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 16

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

3.4.2 Northern Grampians Planning Scheme

The Northern Grampians Planning Scheme includes the following clauses 

relevant to the Panel’s assessment: 

Clause 21.03 Vision Statement outlines the Council’s vision for the 

community, including agriculture, tourism, environment and heritage 

Clause 21.06 Agriculture, aiming to protect, conserve and enhance 

agricultural land for the benefit of current and future generations.  

Clause 21.10 Environment, with the following objectives: 

to achieve total catchment management 

to manage salinity 

to maintain and improve the condition of waterways and wetlands to 

achieve acceptable water quality standards 

to protect flora and fauna 

to reduce soil erosion 

to reduce the impacts of flooding and surface water run‐off 

to ensure that land use and development does not increase the level of 

fire risk and includes adequate fire protection measures. 

Clause 21.07 Tourism, aiming to foster further tourism development. 

Clause 22.11 Heritage, aiming to recognise and preserve natural, spiritual, 

cultural and built forms. 

3.5 ZONES

The site is in the Farming Zone (Clause 35.07‐1) in Ararat Rural City and the 

Northern Grampians Shire, while parts of the site in Ararat Rural City are in 

the Road Zone (Clause 36.04).  

The purposes of the Farming Zone include: 

...To provide for the use of land for agriculture. 

To encourage the retention of productive agricultural land. 

To ensure that non‐agricultural uses, particularly dwellings, do not adversely 

affect the use of land for agriculture. 

To encourage use and development of land based on comprehensive and 

sustainable land management practices and infrastructure provision. 

To protect and enhance natural resources and the biodiversity of the area. 

Page 19: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 17

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

A WEF is a Section 2 use in the Farming Zone.  Thus, the proposed Ararat 

Wind Farm requires a planning permit for: 

The use and development of the site for a wind energy facility, including 

associated infrastructure and removal of native vegetation, pursuant to the 

Farming Zone (clause 35.07); 

Construction of a building or carrying out of works within the Farming 

Zone (clause 35.07‐4); and 

Earthworks within the Farming Zone (clause 35.07‐4). 

3.6 OVERLAYS

3.6.1 Ararat Planning Scheme: VPO1 and VPO2

Parts of the site are subject to the Vegetation Protection Overlay ‐ Schedule 1 

(VPO1) and Vegetation Protection Overlay ‐ Schedule 2 (VPO2) under the 

Ararat Planning Scheme.  VPO1 aims to protect areas of significant remnant 

vegetation throughout the municipality, while VPO2 protect areas of 

significant remnant vegetation located along roadsides. 

A permit is required to remove, destroy or lop any native vegetation.  An 

application to remove native vegetation must: 

Indicate the total extent of native vegetation on the subject land and the 

extent of proposed clearing, destruction or lopping, the location of any river, 

stream, watercourse, wetland or channel on the subject land, and if relevant 

the location of areas with a slope exceeding 20%. 

Specify the purpose of the proposed clearing. 

Demonstrate that the need for removal, destruction or lopping of remnant 

native vegetation has been reduced to the minimum extent that is reasonable 

and practicable. 

Specify proposals for revegetation following disturbance or restoration of an 

alternate site, including proposed species, ground stabilisation and ongoing 

maintenance. 

If the area of proposed clearing exceeds 0.4 ha, include a report on the 

vegetation and habitat significance of the area subject to the permit, to the 

satisfaction of the responsible authority.  

3.6.2 Ararat Planning Scheme: WMO

After the lodging of the application, a Wildfire Management Overlay (WMO) 

was introduced by the Minister for Planning via Amendment C22 and 

gazetted on 11 February 2010.  The WMO covers an insignificant part of the 

WEF site. 

Page 20: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 18

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

3.6.3 Northern Grampians Planning Scheme: ESO1

The Environmental Significance Overlay Schedule 1 (ESO1) applies to the part 

of the site located within the Northern Grampians Shire. 

The Schedule to ESO1 provides the following “Statement of environmental 

significance”: 

There are significant ridges on the highest land in the municipality which 

display erosion characteristics and which are susceptible to further 

environmental degradation. 

The “Environmental objectives to be achieved” are the following: 

To protect significant ridges from development which may accentuate erosion. 

To maintain the natural beauty of the ridge system. 

To protect the remnant native vegetation and to encourage the re‐establishment 

of native communities in degraded areas. 

To prevent erosion of the ridge system. 

To maintain the landscape qualities of the ridge system especially when viewed 

from surrounding areas. 

Within this Overlay a permit is required to construct a building or construct or 

carry out works where these activities are undertaken on an area with a 

gradient of more than 10%, or where native vegetation is proposed to be 

removed. 

3.7 PARTICULAR PROVISIONS

3.7.1 Clause 52.32: Wind Energy Facility

Clause 52.32 of the Victorian Planning Provisions covers the requirements for 

a WEF, and is the clause in the Ararat and Northern Grampians Planning 

Schemes that is of primary significance to the Ararat application. 

The “Purpose” of the Clause is: 

To facilitate the establishment and expansion of wind energy facilities, in 

appropriate locations, with minimal impact on the amenity of the area. 

The Application requirements in Clause 52.32‐2 are of particular significance.  

The application must include the following information, as appropriate: 

A site and context analysis, including: 

- A site plan, photographs or other techniques to accurately describe the site 

and surrounding area. 

Page 21: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 19

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

- A location plan showing the full site area, local electricity grid and access 

roads. 

A design response, including: 

- Detailed plans of the proposed development. 

- Accurate visual simulations illustrating the development in the context of 

the surrounding area and from key public view points. 

A rehabilitation plan for the site. 

A written report(s), including: 

- An explanation of how the proposed design derives from and responds to 

the site analysis. 

- A description of the proposal. 

- A description of how the proposal responds to any significant landscape 

features for the area identified in the planning scheme. 

An assessment of: 

- the visual impact of the proposal on the landscape. 

- the visual impact on abutting land that is subject to the National Parks 

Act 1975. 

- the impact of the proposal on any species (including birds and bats) listed 

under the Flora and Fauna Guarantee Act 1988 or Environment 

Protection and Biodiversity Conservation Act 1999. 

- the noise impacts of the proposal on existing dwellings prepared in 

accordance with the New Zealand Standard NZS6808:1998, Acoustics – 

The Assessment and Measurement of Sound from Wind Turbine 

Generators. 

- the impacts upon Aboriginal or non‐Aboriginal cultural heritage. 

A statement of why the site is suitable for the wind energy facility. 

An environmental management plan including any rehabilitation and 

monitoring. 

Clause 52.32‐3 covers Decision Guidelines.  In addition to the Decision 

Guidelines under Clause 65, the following must be considered, as appropriate: 

The effect of the proposal on the surrounding area in terms of noise, blade glint, 

shadow flicker and electromagnetic interference. 

The impact of the development on significant views, including visual corridors 

and sightlines. 

The impact of the facility on the natural environment and natural systems. 

The impact of the facility on cultural heritage. 

The impact of the facility on aircraft safety. 

The Policy and Planning Guidelines for Development of Wind Energy Facilities 

in Victoria, 2009. 

Page 22: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 20

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

3.7.2 Clause 52.17: Native Vegetation

Clause 52.17 of the Victorian Planning Provisions covers the requirements for 

a Wind Energy Facility. 

The “Purposes” of the Clause are: 

To protect and conserve native vegetation to reduce the impact of land and water 

degradation and provide habitat for plants and animals. 

To achieve the following objectives: 

- To avoid the removal of native vegetation. 

- If the removal of native vegetation cannot be avoided, to minimise the 

removal of native vegetation through appropriate planning and design. 

- To appropriately offset the loss of native vegetation. 

To provide for the management and removal of native vegetation in accordance 

with a property vegetation plan. 

To manage vegetation near buildings to reduce the threat to life and property 

from wildfire. 

The Decision Guidelines in Clause 52.17‐5 reference Victoria’s Native 

Vegetation Management – A Framework for Action (Department of Natural 

Resources and Environment 2002), which has as its primary goal “…to achieve: 

A reversal, across the entire Landscape, of the long‐term decline in the extent and 

quality of native vegetation, leading to a Net Gain”.  The decision guidelines then 

set out the fundamental principles of the Framework, “to avoid, minimise and 

offset” the removal of native vegetation.  They refer to the role of native 

vegetation in protecting water quality and waterway and riparian ecosystems 

and preventing land degradation.  Further, they require assessment of the 

conservation status of the native vegetation, its quality and condition and 

“whether the native vegetation is a threatened community, or provides habitat for 

threatened fauna or flora, as listed in the Flora and Fauna Guarantee Act 1988”.

3.8 GUIDELINES

3.8.1 The Victorian Wind Energy Guidelines (VWEG)

The Policy and Planning Guidelines for Development of Wind Energy Facilities in 

Victoria, September 2009 (VWEG) represent a significant document in the 

consideration of the merits of the Ararat proposal by the Panel.  The 

Guidelines clarify State Government support for the development of the wind 

energy industry in Victoria.  It identifies the planning framework for wind 

energy facility proposals, clarifies the requirements of planning permit 

applications, establishes the criteria for assessing wind energy facilities, and 

describes planning permit administration and enforcement. 

Page 23: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 21

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

The purpose of the Wind Energy Guidelines is: 

To outline how the Victorian Government will facilitate the appropriate 

development of wind energy facilities, balancing environmental, social and 

economic outcomes. 

The Victorian Wind Energy Guidelines have statutory status, as described in 

Section 3.3 State Planning Policy Framework above.  While the Guidelines are 

often broad in scope, they provide the principles that guide the proponent in 

its application, and the Panel in its assessment.  Further, the Guidelines 

reference other more specific documents and guidelines, such as the 

Australian Wind Energy Association’s (AusWEA) Best Practice Guidelines for 

Implementation of Wind Energy Projects in Australia (2006) and the New Zealand 

Standard NZS6808:1998, Acoustics – The Assessment and Measurement of Sound 

from Wind Turbine Generators. 

3.8.2 The EPHC National Wind Farm Guidelines

The Draft Environment Protection and Heritage Council (EPHC) National 

Wind Farm Development Guidelines were developed by a Working Group 

that included Commonwealth and state representatives of the Environment 

Protection and Heritage Council (EPHC) and the Local Government and 

Planning Ministers’ Council.  The report was released in July 2010, after the 

Ararat Wind Energy Facility application, but before consideration by the 

Panel. 

Unlike the Victorian Wind Energy Guidelines, the Draft National Guidelines 

do not have statutory status.  Nevertheless, they provide a sound compilation 

of current standards relating to wind farms.  In particular, the Technical 

Appendices provide detailed consideration of methodology for assessment of 

a range of issues such as consultation, noise, landscape, birds and bats, 

shadow flicker and electromagnetic interference. 

The Panel therefore gave consideration to the methodologies in the Draft 

National Guidelines, and used them to the extent that they assisted the Panel 

in its assessment of the project according to statutory requirements. 

3.8.3 Model Planning Permit Conditions for Wind Energy Facilities

DPCD has prepared model planning permit conditions for wind energy 

facilities, aiming “to assist all parties involved in permit applications for wind 

energy facilities where the Minister for Planning is the responsible authority”4.  

4 DPCD website, Wind Energy Facilities

Page 24: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 22

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

These model conditions “are for guidance only and should be adapted 

depending on the individual circumstance of each wind energy proposal”. 

The Model Conditions formed the basis of “without prejudice” discussions 

between DPCD, Ararat Rural City Council, Northern Grampians Shire 

Council and the  proponent between formal sessions during the Panel 

hearings.  In turn, these discussions provided an important input into the 

Panel workshop session on Planning Permit Conditions and the 

Environmental Management Plan. 

3.9 SUMMARY OF STRATEGIC FRAMEWORK

Table 1 summarises the most significant elements of the strategic and statutory 

framework considered by the Panel in its assessment of the application. 

Table 1 Summary of Strategic Framework

Chapter and topic: Area Relevant elements of the strategic and statutory context

3. Strategic assessment / contribution to Government policy objectives

SPPF

LPPF

VPP

VWEG

Clause 11.03-3 Management of resources

APS Clause 21.02 Vision – Strategic Framework

APS Clause 21.05 Environment

APS Clause 21.06 Economic Development

NGPS Clause 21.03 Vision Statement

Clause 52-32 Wind Energy Facility

pp.27-28

5. Flora and fauna SPPF

LPPF

VPP

Overlays

Other Govt policy

VWEG

Clause 15.09 Conservation of native flora and fauna

APS Clause 21.05 Environment

NGPS Clause 21.10 Environment

Clause 52-17 Native Vegetation

APS VPO1 and VPO2

NGPS ESO1

Victoria’s Native Vegetation Management – A Framework for Action (DNRE 2002

Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act)

pp 13-14; 21-22; p. 33

Page 25: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 23

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Chapter and topic: Area Relevant elements of the strategic and statutory context

6. Noise SPPF

VPP

VWEG

Clause 15.05 Noise Abatement

Clause 52.32 the noise impacts of the proposal on existing dwellings prepared in accordance with the New Zealand Standard NZS6808:1998, Acoustics – The Assessment and Measurement of Sound from Wind Turbine Generators.) pp.30-31

7. Landscape and visual

LPPF

Overlays

VWEG

APS Clause 21.05 Environment

NGPS Clause 21.10 Environment

NGPS ESO1

p. 14; pp. 28-30

8. Roads and traffic management

SPPF Clause 11.03-4 Infrastructure

9. Aviation and Fire Safety

SPPF

VWEG

Clause 15.07 Protection from Wildfire

Clause 18.04 Airfields

p 32

10. Shadow Flicker, blade glint and EMI

VWEG p31

11. Soil and water management

SPPF

LPPF

Other Govt policy VWEG

Clause 15.01 Protection of Catchments, Waterways and Groundwater APS Clause 21.05 Environment

APS Clause 21.05 Environment

NGPS Clause 21.10 Environment

Glenelg Hopkins and Wimmera Regional Catchment Strategies pp.13-14

12. Social and economic impacts

SPPF

LPPF

VWEG

Clause 11.03-5 Economic well-being

Clause 11.03-6 Social needs

Clause 11.03-7 Regional co-operation

Clause 15.12 Energy efficiency

Clause 15.14 Renewable energy

Clause 17.05 Agriculture APS Clause 21.05 Environment

APS Clause 21.06 Economic Development

NGPS Clause 21.06 Agriculture

NGPS Clause 21.07 Tourism

p.12 (employment and regional development); pp. 17-18 (consultation)

Page 26: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 24

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Chapter and topic: Area Relevant elements of the strategic and statutory context

13. Aboriginal cultural heritage.

SPPF

LPPF

VWEG

Clause 15.11 Heritage

APS Clause 21.05 Environment

NGPS Clause 22.11 Heritage

pp.14

14. Administration and enforcement

VWEG Section 4.2 and pp.34

15. Environmental Management Plan

VWEG pp.26

3.10 CONCLUSIONS

As described in this report, the Panel concluded that there is strong State 

Government support for the development of wind energy facilities in Victoria, 

as long as the facilities are appropriately sited, have acceptable environmental 

impact and generate net community benefit. 

Page 27: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 25

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

4. ISSUES

4.1 NATURE OF SUBMISSIONS

20 submissions were received by DPCD and were referred to the Panel.  Of 

these, four supported the proposal, two had no objections, three had qualified 

approval providing development was in accordance with guidelines or 

specified conditions, and eleven objected to aspects of the proposal. 

The issues identified in the submissions were: 

flora and fauna, including the need for vegetation removal on access roads 

off‐site; 

noise, including low frequency sound, infrasound, and health impacts; 

landscape and visual impacts, including aviation lighting; 

roads and traffic management; 

aviation safety; 

fire; 

shadow flicker, blade glint and electromagnetic interference; 

soil and water management; 

social and economic impact, including consultation and tourism; 

rights of adjacent land owners; 

ongoing administration and enforcement of any planning permit that may 

be issued; 

Environmental Management Plan; 

grid connection; and 

loss of value. 

While the last two of these issues are outside the scope of the Panel’s task, they 

are briefly addressed to the extent that is necessary to document why the 

Panel is not reporting on them at greater length. 

DPCD Grampians Region, acting on behalf of the Minister for Planning, 

provided advice on policy matters and the statutory framework for the 

proposal, along with a brief discussion of the issues raised in submissions. 

Mr Power, a partner of Freehills, acting for the proponent, RES Australia, 

called evidence on the following matters: 

acoustics — Mr Chris Turnbull of Sonus Pty Ltd; 

Page 28: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 26

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

landscape/visual — Mr Allan Wyatt of ERM Consultants; 

aviation — Mr Sydney Herron of Ambidji Group P/L; 

flora and fauna — Mr Brett Lane of Brett Lane & Associates; and 

shadow flicker, blade glint and electromagnetic interference — Dr Trenton 

Gilbert of GL Garrad Hassan. 

No other party was represented by Counsel. 

The ARCC generally supported the proposal5.  It provided comment on a 

range of matters, including night lighting, loss of native vegetation, and 

enforcement. 

The NGS made a submission6 to the hearing in response to the Panel’s 

Directions, and addressed specifically the Environmental Significance Overlay 

that affects that part of the proposal within their municipality. 

The referral authorities nominated under the relevant Planning Schemes are: 

ESO1 – Glenelg Hopkins (GHCMA) and Wimmera Catchment (WCMA) 

Management Authorities and Grampians‐Wimmera‐Mallee Water 

(GWMW); 

ESO2 – Department of Sustainability and Environment (DSE): 

WMO – Country Fire Authority (CFA); and 

Clause 52.29 Land Adjacent to a Road Zone, Category 1, or a public Acquisition Overlay for a Category 1 Road – VicRoads. 

DSE made a written submission7 on the application, expressing concern that 

the application did not adequately address the avoid and minimise principles 

of Victoria’s Native Vegetation Management – A Framework for Action (DNRE 

2002), the affect of Turbines T32, T33, T64 and T65 on avifauna accessing the 

Ararat Regional Park, landscape and visual amenity from Langi Ghiran State 

Park and providing detailed items to be included in the environmental 

management plan.  DSE attended the Hearings (in part) but made no further 

written submission, save for marked up sections of the DPCD draft Planning 

Permit and a response to a Panel query relating to the impact of the Land and 

Biodiversity White Paper on the project. 

GWMW made a submission8 to the referred application, and offered no 

objection.  It did not attend the Hearing. 

5 Submission No 15 6 Hearing Document No 22 7 Submission No 14 8 Submission No 3

Page 29: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 27

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

The GHCMA made a written submission9 focussing on the need to manage 

impacts of batters, internal roads and drainage on erosion, and avoid the 

transport of weed species, but did not attend the Hearing.  The WCMA did 

not provide a written submission, and did not attend the Hearing. 

The CFA made a submission10 on the referred application, and offered no 

objection, and recommended that the site be developed in accordance with 

CFA’s document Emergency Management Guidelines for Windfarms. 

VicRoads made a submission11 on the referred application, and offered no 

objection, providing specified permit conditions were adopted. 

4.2 ISSUES FOUND TO BE NOT RELEVANT TO THE PANEL

4.2.1 Grid Connection

The Pyrenees Shire Council written submission12 objected to the failure by RES 

Australia to include the grid connection as an integral component of the 

proposal on which they are seeking a planning permit, and requests that the 

Minister defer the consideration of the Ararat WEF until a complete 

application is submitted.  Two submitters, Mr and Mrs Harrington and Mr 

Wilde objected to the proposed acquisition for the grid connection, while Mr 

Wilde was also concerned at the potential for the construction and operation 

of the grid connection to introduce weeds to his property, which operates 

under a bio‐security arrangement and is weed free. 

None of these submitters presented to the Hearing, though the PSC was 

scheduled to appear, but made a further written submission after the Panel 

Hearing was closed.  This written submission repeated the main concern of 

the PSC, namely the incomplete nature of the proposal, and addressed further 

issues.  These were enforcement, noise, siting of turbines in relation to 

property boundaries, aviation lighting, and secondary consent.  These further 

issues had been discussed at the Hearing, and the material before the Panel at 

the time of the Hearing has formed the basis of the Panel’s considerations. 

The Panel did arrange for the late written submission from the PSC to be sent 

to parties for information, and RES Australia made a further submission on 

the matters raised.  However, as noted above, it was the material before the 

Panel at the time of the Hearing that has formed the basis of the Panel’s 

considerations. 

9 Submission No 7 10 Submission No 1 11 Submission No 2 12 Submission No 20

Page 30: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 28

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Turning now to the issue of the completeness of the application, Mr Power in 

his opening address to the Panel drew attention to Part 4 of the VWEG that 

makes clear that the grid connection does not form part of the Minister’s 

assessment of a WEF.  Notwithstanding that, Mr Lane did undertake some 

preliminary investigation of the clearing that might be required for any grid 

connection, but this material was not put forward for considered deliberation 

at the Panel Hearing, but rather for general information. 

Mr Power also commented as follows: 

It is standard practice for separate permit applications to be made for 

electricity transmission lines.  This is primarily because connection to the 

electricity grid is a separate land use from a wind energy facility, and is 

typically subject to input from the network service provider.  In any event, 

impacts of the electricity transmission line are unlikely to be significant. 

Section 2.1.2 of the VWEG13 addresses the grid connection.  It states that “The 

transmission or distribution system of power lines necessary to connect a wind farm to 

the electricity grid is a separate land use to that of a wind energy facility.”  It also 

states: 

While the applications can run in parallel, there may be two different 

responsible authorities [ie the Minister for Planning and Council for some 

projects] and timelines for approval could differ depending on the nature of 

the application.  Where they are separate applications, details of the power 

line infrastructure are not required to be provided as part of the wind 

energy facility application, with the exception of the distribution starting 

point. 

The Panel has no power to consider the detail of the grid connection, in a 

situation where the applicant has chosen to apply separately for a permit for 

the grid connection, and where comprehensive details, impacts and 

ameliorative measures are not provided to be considered in tandem with the 

application for the WEF.  As this is the case for the Ararat WEF, the Panel will 

not further consider the merits of different grid connection alternatives. 

The Panel does, however, share the concerns of the PSC, and notes the concern 

and anxiety expressed by the two submitters who must now wait for a further 

process prior to any decision on the grid connection being made.  The normal 

definition of a project includes elements necessary to bring the project to 

fruition, and will include off‐site matters as required.  In the present Ararat 

WEF, examples include the use and maintenance of local roads, necessary 

vegetation clearance along public roads, and traffic safety measures on the 

13 Policy and planning guidelines for development of wind energy facilities in Victoria, Revised

September 2009

Page 31: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 29

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

road system for the transport of imported heavy equipment.  All these matters 

have been addressed by the proponent, and will form part of either any 

planning permit condition or the Environmental Management Plan (EMP). 

In just the same way, the VWEG contemplate the grid connection being 

considered in conjunction with the WEF application.  The proponent has not 

chosen to take that approach, no doubt in part because of the difficulty of 

getting the required input from the network service provider at this time.  The 

Panel would agree with the PSC that considering a project holistically is good 

practice, and is routinely recommended in international Environmental 

Impact Assessment practice. 

The Panel therefore recommends that: 

The Minister for Planning and the Minister for Energy and Resources 

amend the Policy and Planning Guidelines to require the grid 

connection permit to be applied for concurrently with a WEF 

application, and the two applications to be considered together.

4.2.2 Loss of Value

The submissions to the Panel by Mrs Stewien and Mr Randell both raised the 

issue of the loss of value of their property as a result of the presence of the 

WEF.  Mr Power addressed this issue in Part B of his submission to the 

Hearing, and quoted its conclusion in Acciona Energy Oceania Pty Ltd v 

Corangamite Shire Council14 as follows: 

It is a well established planning principle that depreciation of land values 

as a result of a proposed development is not a relevant ground by which to 

refuse a proposal.  That is, property value is not, in itself, a planning 

consideration.  Amenity is relevant and we have addressed potential 

amenity impacts in these reasons. 

Mr Power concluded that impact on property values as irrelevant to the 

assessment, and was not supported in any case by any evidence. 

The Panel agrees that the position Mr Power put is consistent with long‐term 

decision‐making by Planning Panels Victoria and VCAT, and has not further 

considered the issue of Loss of Value. 

14 [2008] VCAT 1617 at para 112

Page 32: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 30

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

4.3 ARRANGEMENT OF ISSUES IN THE REPORT

The issues identified in Section 4.1 above have been grouped into the 

following chapters of the report: 

Chapter 5  Flora and Fauna 

Chapter 6  Noise and Health Impacts 

Chapter 7  Landscape and Visual impacts 

Chapter 8  Roads and Traffic Management 

Chapter 9  Aviation Safety and Fire 

Chapter 10  Shadow Flicker, Blade Glint and EMI 

Chapter 11  Soil and Water Management 

Chapter 12  Social and Economic 

Chapter 13  Aboriginal Cultural Heritage 

Chapter 14  Administration and Enforcement 

Chapter 15  Environmental Management Plan 

Chapter 16  Recommended Permit Conditions 

Chapter 17  Conclusions 

Chapter 18  Recommendations 

Page 33: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 31

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

5. FLORA AND FAUNA

5.1 WHAT ARE THE ISSUES?

There are three main issues relating to flora and fauna: 

the extent to which native vegetation removal is avoided, minimised and 

offset; 

the impact of disturbance of habit, particularly as a result of the 

construction of access roads, power lines and other infrastructure through 

the site; and 

the potential for bird strike from turbine blades. 

The principles underlying these matters have been addressed in past Panel 

reports relating to wind energy facilities, but there are site‐specific issues that 

are addressed in this report. 

At the hearings, the Panel sought advice from the Department of 

Sustainability and Environment (DSE) about the relevance of the Land and 

Biodiversity White Paper (2009) regarding the proposal.  In particular, it 

requested advice on the implications of the threshold concepts of flagship 

areas, biolinks and resilience for consideration of the Ararat WEF. 

DSE responded by stating that the proposed facility is located in a biolink, 

between the Greater Grampians and Goldfields flagship areas.  It noted that 

the intention of establishing flagship areas and biolinks “is to enable high level 

targeted investment decisions to be made in the future, and as such, they 

should not be interpreted as being specific tools for decision makers to utilise 

in a planning context”.  DSE added: 

It is worth noting that wind farms by their very nature and design have 

potential to provide barriers to the values recognised by biolinks (i.e. 

ecological connectivity / movement of species).  However in the 

departments opinion these concerns can be dealt with via the planning 

tools and processes currently available in Victoria’s planning system. 

The Panel has noted the advice from DSE on the potential for wind farms to 

provide barriers to the values recognised by biolinks.  In the absence of any 

further advice, submissions or concern from DSE, or any other party, and the 

general evidence of low avifauna use in the wind farm area, this matter has 

not been taken further by the Panel. 

Page 34: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 32

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

5.2 BACKGROUND

The policy considerations relevant to flora and fauna have been detailed in 

Chapter 3 above, and in the VWEG15. 

The specialist assessment carried out by Brett Lane and Associates (BL&A)16 

sets out the principal investigations undertaken for the application.  In his 

expert witness statement17, Brett Lane described the methodology used in 

assessing flora and fauna impacts of the proposed facility: 

Mapping of the remnant vegetation and scattered trees within designated 

infrastructure zones on the two portions of the site and in surrounding 

roadsides based on air photo interpretation and ground‐truthing. 

Spring flora surveying (October 2007) for areas of the proposed footprint 

identified at that time as being suitable habitat for rare or threatened flora. 

An overview fauna survey of the site.  A survey of the entire site for ground 

fauna (e.g. reptiles and frogs) was not considered necessary. 

Two separate targeted surveys for the Powerful Owl in remnant treed 

vegetation adjacent to the northern portion of the site. 

A bird utilisation survey to detail bird life on the proposed wind farm site, 

including bird abundance, diversity, distribution, flight patterns and 

heights and general aspects of bird behaviour on the site (part of a Level one 

bird risk assessment as per the AusWEA interim standards). 

An Anabat® ultrasonic bat survey to detail bat diversity and activity levels 

on those parts of the proposed wind farm site where turbines are proposed to 

be located. 

A desktop flora and fauna assessment for a potential overhead powerline 

route. 

Following discussions with the DSE, four reports were prepared for the 

project: 

BL&A (2007) Proposed Ararat Wind Farm Preliminary Flora and Fauna 

Assessment, Report 7169 (1.3); 

BL&A (2009a) Proposed Ararat Wind Farm Flora and Fauna Assessment, 

Report 7169 (2.7); 

15 Policy and planning guidelines for development of wind energy facilities in Victoria, published by

the Victorian Government Department of Planning and Community Development Melbourne, September 2009, pages 13 and 14

16 Volume 2 of the Application Documentation, Flora and Fauna Assessment, Brett Lane & Associated Pty Ltd, September 2009 (Reports Numbers 7169 (2.7) and 7169 (3.1))

17 Proposed Ararat Wind Farm, Expert Witness Statement of Brett Lane, June 2010, Section 1.3

Page 35: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 33

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

BL&A (2009b) Ararat Wind Farm: Targeted Powerful Owl Survey, Report 

7169 (3.1); 

BL&A (2010b) Ararat Wind Farm: Potential Overhead Powerline Desktop Flora 

and Fauna Assessment, Report 7169 (6.0). 

The results of the surveys were summarised in Brett Lane’s expert witness 

statement on flora and fauna.  With regard to flora: 

A total of 101 flora species were recorded within the proposed 

Infrastructure Zone, 75 (74%) of which were indigenous, 24 were 

introduced species and two were planted non‐indigenous trees...Fifteen 

flora species of state and/or national conservation significance were 

identified in the FIS and EPBC Act Protected Matters Search Tool as 

occurring or having the potential to occur in the 20km search region that 

includes the proposed wind farm.  No species of conservation significance 

was recorded in the proposed Infrastructure Zone during the survey. 

The analysis of fauna at the site describes the species found in surveys: 

Based on the field assessment and the review of existing information, the 

study area is known to or is likely to support 165 species of fauna, 

including 25 species of mammals (six introduced), 122 species of birds 

(five introduced), 15 species of reptile and three species of frog... 

Table 5 of the Flora and Fauna Assessment Report... provides a list of 

threatened fauna species that are likely to occur in the study area.  None of 

the fauna species in Table 5 were recorded in the study area during the 

current investigation. 

Fauna investigations were carried out to determine the presence of the 

Powerful Owl.  The investigations were carried out and the Powerful Owl 

was not detected.  The results of these investigations are contained in the 

report for the Powerful Owl... 

The analysis of birds is particularly significant.  The bird utilisation surveys 

identified 38 bird species, with the most abundant species being Australian 

Magpie, Long‐billed Corella, Galah and raven spp (mainly Little Raven).  

These species, together with the Australasian Pipit and Sulphur‐crested 

Cockatoo, Yellow‐rumped Thornbill and White‐fronted Chat, accounted for 

90% of individual birds observed. 

The expert witness statement of Brett Lane from BL&A referred to the 

existence of raptors at the site: 

Birds of prey (or raptors) formed 2.6 percent of all individuals counted in 

the proposed wind farm and three percent of birds seen at RSA [rotor 

swept area] height.  The species most commonly observed at RSA height 

Page 36: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 34

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

was the Wedge‐tailed Eagle, followed by Brown Falcon and Nankeen 

Kestrel.  The utilisation rate of Wedge‐tailed Eagles at the site is very low 

(0.008 birds per hectare per hour) compared with the spring utilisation 

rate at a number of other wind farm sites in Victoria... 

The expert witness statement also addressed the issue of native vegetation 

removal, and the offset plan aimed at protecting and replacing native 

vegetation: 

A total of 8.53 hectares, (equivalent to 5.89 habitat hectares) of native 

vegetation is proposed to be removed from within the infrastructure zone.  

Prescribed offset targets for the removal of native vegetation within the 

infrastructure zone are summarised as follows: 

0.32 habitat hectares for the removal of 0.16 habitat hectares (0.31 

hectares) of Very High conservation significance vegetation; 

5.82 habitat hectares for the removal of 3.88 habitat hectares (5.58 

hectares) of High conservation significance vegetation; and 

1.85 habitat hectares for the removal of 1.85 habitat hectares (2.64 

hectares) of Medium conservation significance vegetation. 

A total of 8 habitat hectares is required to achieve the associated offset 

target for the removal of the above native vegetation. 

Based on previous experience, approximately 40 hectares of suitable native 

vegetation may be required to achieve this offset target.  This is based on a 

potential 20% improvement of the offset site (8 habitat hectares x 5 = 40 

hectares).  It should be noted that this is a highly conservative estimate, 

which for the most part is based on a default habitat score of 0.7 for Grassy 

Dry Forest EVC.  This assessment therefore represents a worst case 

scenario but it demonstrates the scale of the required offset.  Many hectares 

of native vegetation of the same EVC as that being removed occur within 

the properties in which the wind farm is to be built.  These areas are 

considered to be more than adequate to meet the offset target. 

Mr Lane concluded: 

Based on the initial vegetation mapping, the design of the wind farm 

layout has, for the most part, avoided impacts on minor roads known to 

support significant roadside vegetation, including Hopkins River Road, 

Warrak Road and Big Hill Road, identified in our report and in municipal 

roadside vegetation mapping. 

The wind farm footprint and proposed access tracks avoid the majority of 

intact native vegetation on the site.  A number of additional changes, 

namely re‐routing of various access tracks to avoid mapped areas of native 

Page 37: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 35

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

vegetation, have been implemented following discussions between Brett 

Lane & Associates Pty Ltd and RES Australia Pty Ltd (BL&A 2009a). 

Offsets for the removal of native vegetation have been prescribed in BL&A 

Report 7169 (2.7).  An offset plan will be prepared detailing vegetation to 

be removed, prescribed net gain targets, and details of the offset site.  Areas 

of remnant native vegetation within the properties involved in the project 

could provide the required offset (approx. 40 hectares) as these will meet 

like‐for‐like criteria.  The proponent proposes to discuss the use of these 

areas with the relevant landholders (p 19). 

The proponent thus relied heavily on the work of Brett Lane and Associates, 

and concluded that the proposed Ararat Wind Farm can be designed, 

constructed and operated in compliance with applicable legislation and 

policies relating to flora and fauna. 

During the site inspection Mr Power pointed out examples of where access 

roads to and within the site had been aligned to minimise clearing of native 

vegetation. 

5.3 EVIDENCE AND SUBMISSIONS

5.3.1 Native Vegetation Removal

In its written submission on the exhibited Application Documentation, DSE 

provided comments under the headings “In response to the section 55 

referral” and later in the submission under the heading “In response to the 

section 52 notice”. 

In accordance with Section 61 (2) of the Planning and Environment Act: 

The responsible authority must decide to refuse to grant a permit if a 

relevant referral authority objects to the grant of the permit. 

Comments provided under Section 52 do not carry the same requirement, and 

can be considered on their merit, and in conjunction with other aspects of the 

overall assessment. 

The DSE submission in response to the Section 55 referral stated that the 

Department believed that the application had not adequately addressed the 

‘avoid and minimise’ principles of Victoria’s Native Vegetation Management – A 

Framework for Action (2002), “particularly with respect to the location and 

alignment of hard standing areas and vehicular tracks impacting on areas of 

very high and high conservation significance”.  DSE explained at the Hearing 

that this is a general comment aimed at ensuring detailed discussions are held 

with the Department as the vegetation clearance requirements are subject to a 

Page 38: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 36

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

greater level of detail.  Should areas of very high conservation significance not 

be avoided, the Minister for Environment and Climate Change must approve 

(or reject) the offset plan.  As the DSE submission states: 

In this case the department requests that the Panel recommend that the 

Minister for Planning defer issue of a permit for removal of native 

vegetation of very high conservation significance until the Minister for 

Environment and Climate Change has approved that removal.18 

In relation to the remainder of the DSE comments under its Section 55 

responsibilities, three particular permit conditions are stated, namely: 

The approved (Named) Offset Plan will be endorsed and become part 

of the permit. 

Before the vegetation removal starts, the offsets documented in the 

approved (Named) Offset Plan must be initiated to the satisfaction of 

the Responsible Authority and the Department of Sustainability and 

Environment. 

Offsets must be completed according to the schedule of works in the 

(Named) Offset Plan, to the satisfaction of the Responsible 

Authority19. 

Comments provided under Section 52 included reference to turbines in 

proximity to State and regional Parks, Landscape and visual amenity, and the 

statement that the Department has no objection to the granting of a permit, 

subject to conditions based on DPCD’s Model Wind Energy Conditions February 

2009.  The issues raised by DSE have been addressed in the relevant chapters 

of the Panel report (Chapters 5 and 7 in particular). 

At the hearings, representatives of DSE contributed to the “without prejudice” 

discussions on permit conditions, and agreed that the Department’s concerns 

had been addressed by the proposed conditions. 

Ararat Rural City Council’s submission on the exhibited documents also noted 

that, “in addition to the vegetation offsets proposed any permit also addresses the 

damage or loss that may result from the yet to be determined transport routes”20. 

This was reinforced by W J and L O Stewien, who expressed concern about the 

impact of transport along Big Hill Road “with trees canopied over the transport 

corridor and the subsequent need to remove or damage such trees”.  Peter Woods 

also referred to Big Hill Road as a “treed wildlife corridor”, and submitted that 

18 Submission 14, p.2 19 Ibid, p.2 20 Submission 15

Page 39: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 37

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

the entry point for the project off the main Ararat/Warrak Road should be 

shifted “slightly west” to avoid damage to the corridor. 

The Expert Witness Report on Traffic by Ms G Austin of Aurecon Australia 

Pty Ltd provided a response to the issue raised by Ararat Rural City Council.  

Chapter 4 of her Expert Witness Statement (see pages 11 to 34) made a 

preliminary review of the likely damage to vegetation on the access routes.  It 

concluded (page 35) that: 

A preliminary analysis of the loss of vegetation on transport routes has 

been undertaken.  In general, vegetation loss is anticipated to be low, with 

the potential for up to 7 trees to be removed. 

It should be noted that this is a preliminary view and further route 

analysis will be undertaken to confirm routes and swept path 

requirements.  This will include a trial run to clearly identify issues.21 

5.3.2 Disturbance of Habitat

The Hamilton Field Naturalists Club submitted that in December 2009 “a 

viable population” of the Golden Sun Moth had been found in the vicinity of 

towers T49, T67 and T50, and that construction of these towers would lead to 

the removal of its habitat.  The Club considered that the surveys conducted in 

2008 had not covered these important areas.  Further, the Club was critical of 

aspects of the Flora and Fauna Assessment carried out by Brett Lane and 

Associates (BL&A), and stated in part: 

The land within tower number T67, appears to contain a diverse and 

species‐rich native ground flora ...This is not the low quality habitat 

claimed in the BL&A flora and fauna report...Apart from ad hoc 

‘incidental records’, the B&LA Flora and Fauna Assessment does not 

appear to have conducted rigorous assessment of cryptic species such as 

the Golden Sun Moth or Fat‐tailed Dunnart, despite the area in question 

clearly containing suitable habitat.22 

The Club was critical of the survey points used for the bird and bat surveys, 

under‐estimation of the significance of native vegetation in ground layers 

(such as native grasses and herbs), and failure to properly consider impacts on 

the Southern Bent‐wing Bat.  It recommended the removal of T49, T67 and T50 

from the plans, and use of the area as a “habitat offset area”. 

Mr Lane responded to the Club’s submission in his Expert Witness Report.  In 

particular, he drew attention to the site where the Golden Sun Moth was 

21 Gillian Austin, Aurecon Australia Pty Ltd, Expert Witness Report on Traffic, p.35 22 Hamilton Field Naturalists Club, submission 17

Page 40: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 38

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

found by club members (at a creek crossing on the Hopkins River Road), 

pointing out that habitat values further up the slope in the infrastructure zone 

are of much lower quality than those at the creek crossing on the road. 

The Glenelg Hopkins Catchment Management Authority noted the 

importance of avoiding the introduction of weed species through “poor 

machinery hygiene practices” and avoiding the use of hay bales for control of 

erosion and sediment, and proposed relevant permit conditions.  The potential 

for the introduction of weeds was also identified by K J Wilde, whose written 

submission refers to the farm’s current weed‐free status, and expresses 

concern about the need for cleaning machinery to avoid the introduction of 

weeds such as Paterson’s Curse.  The Panel notes that Mr Wilde’s submission 

related to the grid connection, which is not part of the proposal (see Section 

4.2.1 above). 

5.3.3 Potential bird strike

The potential for mortality of birds from strike by turbine blades was raised in 

two submissions on the exhibited application.  W J and L O Stewien expressed 

concern about the “survival opportunity” of a pair of Wedge‐tailed Eagles 

which nest in the area, while J Smithers‐Tomkin accurately described the birds 

as “majestic”, and was troubled that: 

This wind ‘farm’ would become part of a wedge‐tail eagle zone which 

covers an area from One Tree Hill – the Black Range – Dunneworthy 

Common and s‐east to Mount Langi Ghiran.23 

In its written submission on the application, DSE expressed concern about the 

proximity to the Langi Ghiran State Park and Ararat Regional Park.  In 

particular, it had “serious concerns” about the location of four proposed 

turbines (T32, T33, T64 and T65) near the Ararat Regional Park, because “the 

turbines are located on a ridge line highly utilised by avifauna moving 

between the park and another area of significant native vegetation located 

approximately 600 metres to the north east”.  The DSE submission on the 

exhibited documents recommended that no turbines be built in this area, but: 

...if turbines are approved in this location the department strongly 

recommends that each turbine be included in any monitoring program 

required under the Bat and Avifauna Management Plan, in conjunction 

with specific and targeted mitigation measures that address the high 

avifauna utilisation (and potential mortality/strike rate) of the site.24 

23 Submission 12 24 Submission 14, p.2

Page 41: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 39

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Mr Lane responded to the DSE concern in his Expert Witness Statement, 

detailing that “There was no evidence of regular usage of this part of the site by 

significant numbers of bird species moving between forested habitats, including to and 

from nearby conservation reserves25.”  In relation to the Bat and Bird Management 

Plan (BBMP), Mr Lane stated “The recommendation to ensure greater search effort 

at these turbines can be included in this plan.” 

At the hearings, representatives of DSE indicated that they were satisfied that 

the monitoring program under the BBMP within the EMP would meet the 

requirements of the Department.  The Department did not continue to pursue 

the removal of the turbines near the Ararat Regional Park. 

5.4 DISCUSSION

5.4.1 Native Vegetation Removal

The removal of native vegetation is clearly a significant issue, with an 

estimated 8.53 hectares proposed to be removed from within the infrastructure 

zone.  However, the Panel concluded that the principles of “avoid, minimise 

and offset” had been pursued in planning to date, and can be further refined 

as more detailed planning proceeds. 

Following discussion at the Panel hearing, the proposed permit was modified 

to include a requirement for a “Net Gain Offset Plan”, as detailed in Appendix 

C, Clauses 4, 5 and 6. 

The proposed Environmental Management Plan also includes the requirement 

for a Native Vegetation Offset Management Plan, repeating the steps listed in 

the proposed Permit. 

Following discussions at the hearings, the requirements of this Native 

Vegetation Offset Management Plan appeared satisfactory to key 

stakeholders.  The Panel agrees that it will achieve a net gain in quality and 

quantity of native vegetation in accordance with the principles and guidelines 

associated with the Native Vegetation Management: A Framework for Action (DSE 

2002). 

The Panel thus concluded that the proposed content of the Native Vegetation 

Offset Management Plan is satisfactory, but that its duplication in the Permit 

Conditions and the Environmental Management Plan is clumsy and 

confusing.  It considered that the detail should be described in the 

Environmental Management Plan, which is required to be endorsed as part of 

the Permit (Appendix F).  The Permit conditions (Appendix E) should be 

25 Proposed Ararat Wind Farm, Expert Witness Statement of Brett Lane, June 2010 p.18

Page 42: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 40

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

simplified to list the Native Vegetation Offset Management Plan as one of the 

plans incorporated within the EMP.  In this way, the requirements of DSE as a 

referral agency are met, and the permit Conditions are simplified. 

In relation to the request from DSE that that “the Panel recommend that the 

Minister for Planning defer issue of a permit for removal of native vegetation of very 

high conservation significance until the Minister for Environment and Climate 

Change has approved it” (see Section 5.3.1 above), as there is a single permit 

being considered (under each Scheme), there appears to be a potential 

difficulty.  The refinement of the proposal would normally require further 

detailed investigations at the pre‐construction phase.  However such work 

will not normally be undertaken without the security of a permit being issued. 

For this reason the Panel believes that a variation to the wording suggested by 

DSE is needed, to require that removal of native vegetation having very high 

conservation significance does not commence until the Minister for 

Environment and Climate Change has approved its removal. 

5.4.2 Disturbance of Habitat

The Panel assessed the significance of habitat that may be damaged during 

construction and operation of the facility.  In particular, it reviewed the 

possible impact of road access to the facility on roadsides of high conservation 

value, including those that may provide habitat for the threatened Powerful 

Owl and Golden Sun Moth. 

The Panel concluded that the location of access points to the site was 

consistent with “avoid and minimise” principles.  It supported the 

modifications to access points that minimised potential loss of native 

vegetation along Warrak Road that had been made by the proponent during 

the initial planning phase.  Further, it considered that any additional 

refinements to avoid and minimise vegetation loss can be addressed in 

detailed designs through the Environmental Management Plan. 

With regard to the concerns of W J and L O Stewien about the impact of 

transport along Big Hill Road, the Panel considered that the proposed access 

crossed Big Hill Road, but had very little impact on vegetation within the road 

reserve.  At the hearings, Ms Stewien indicated concern that access to the site 

would involve heavy vehicles travelling along Big Hill road, but this is not the 

case.  The Panel was satisfied that the high conservation quality of vegetation 

in this locality would not be compromised. 

The Panel reached similar conclusions regarding the special cases of the 

threatened Powerful Owl and Golden Sun Moth.  It is clear that there is 

Page 43: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 41

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

appropriate habitat for the Powerful Owl in the area, particularly in the Ararat 

Regional Park, and Brett Lane noted in his expert witness statement that: 

There are seven records (excluding duplicates) of Powerful Owl from the 

AVW search region, between 1995 and 1997.  Three of the records of 

Powerful Owl are from Ararat Hills Regional Park, close to the northern 

cluster of the proposed Ararat wind farm site.  The remaining records are 

from Mount Cole State Forest and Langi Ghiran State Park, south of the 

southern cluster of the wind farm site26. 

Despite the records of the Powerful Owl, the species was not detected during 

the surveys conducted by BL&A.  With regard to the Powerful Owl’s habitat: 

In the privately owned woodland abutting the northern sub‐section of the 

wind farm, hollow counts varied from 2 to 36 over five, 500 x 100 metre 

transects.  In Ararat Hills Regional Park, counts ranged from 34 to 67 

over four 500 x 100 metre transects.  The number of large, hollow‐bearing 

trees was also much greater in Ararat Hills Regional Park.  Powerful Owl 

habitat quality was considered high in Ararat Hills Regional Park and 

moderate in the privately owned woodland north of the wind farm site.  

This again support a conclusion that movement of the owl out of the 

regional park to the northern woodland is likely to be infrequent.27 

In the Panel’s view, the records of sightings of the Powerful Owl were 

sufficient to indicate that it is likely that the species may be found in the Ararat 

Regional Park and nearby woodlands.  However, there was insufficient 

evidence that the proposed Ararat WEF would impact on the birds or their 

habitat in any significant way, and was not convinced to reduce the number or 

change the location of any of the proposed turbines on the basis of impacts on 

the Powerful Owl. 

The Panel noted the submission of the Hamilton Field Naturalists Club that 

the Golden Sun Moth had been observed on Hopkins River Road in the 

vicinity of Turbines 49, 67 and 50 in December 2009.  It also considered the 

evidence of Brett Lane that his organisation’s surveys had not detected the 

species, and his view was that that “there are few if any sites within the study 

area that have sufficient cover of Austrodanthonia sp. (40%) to support this 

species” (Flora and Fauna Assessment, September 2009, p. 35).  In his expert 

witness statement, Brett Lane concluded: 

... Habitat [for the Golden Sun Moth] up the slope away from the road is of 

much lower quality than habitat along this road.  Should GSM occur in 

the area, it is unlikely that a large proportion of its population would occur 

26 Proposed Ararat Wind Farm, Expert Witness Statement of Brett Lane, June 2010, p.5 27 Ibid, p.13

Page 44: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 42

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

within the limited area of impact defined by the wind farm development 

footprint.  The proponent has indicated that the footprint in this area could 

be reduced below the 0.25 hectare removal threshold considered under the 

EPBC Act to represent a significant impact on the habitat of this species, if 

it were found in the area. 

The Panel concluded that a precautionary approach should be taken, and that 

habitat that may support the Golden Sun Moth should be protected.  

Nevertheless, it considered that the small amount of habitat damage likely in 

the Hopkins River Road area did not warrant reduction in the number or 

change the location of the proposed turbines on the basis of impacts on the 

Golden Sun Moth. 

The Panel noted concerns about the introduction of weed species, but 

concluded that this could be avoided through implementation of permit 

conditions proposed by the GHCMA.  These will be reinforced by the Pest 

Plant Management Plan and the Pest Animal Management Plan within the 

EMP. 

In the Draft Permit Conditions (see Appendix C), the proponent has 

questioned the inclusion of Clause 7 “Temporary fencing or tape must be installed 

around areas of native vegetation to be retained, to the satisfaction of the responsible 

authority.” and made the following note: 

[Note we have asked for DSE condition 7 to be removed, or ‘All offset sites 

must be legally secured in accordance with the offset plan.’] 

The Panel believes there is some confusion here about the intention of Clause 

7.  While it is within the group of clauses under the heading ‘Net gain offset 

plan’, the Panel believes it may also refer to the usual good site practice of 

marking vegetation on site that is to be preserved with tape, and indicating to 

contractors and others that these areas are ‘no go’ areas.  As such it would be 

better placed in the EMP under the ‘Native vegetation management plan’. 

The Panel believes that the alternative wording suggested by the proponent 

for Clause 7, to ensure legal security of the offsets, is covered in Clause (i) of 

the Recommended EMP (the Net Gain Offset Plan for the Construction Phase).  

The existing Clause 7, relating to good construction practice, should be 

included as part of the EMP (Construction Phase). 

Page 45: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 43

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

5.4.3 Potential bird strike

The Panel’s review of the submissions and evidence indicated that there is a 

likelihood that mortality of birds will occur as a result of strike from turbine 

blades.  However, the numbers are likely to be sufficiently low and the species 

most affected are relatively abundant, meaning that this issue is not serious 

enough to warrant reduction in the number or change in the location of 

turbines. 

The Panel noted evidence of bird collision rates from a range of European and 

North American wind farms, cited in the September 2009 BL&A Flora and 

Fauna Assessment (pp. 63‐65).  The collision rate varied between 0.04 and 4.5 

birds per turbine per year, with most wind farm bird mortality due to 

migrating birds.  With relatively few night‐migrating birds, it is likely that 

bird strike will be closer to the lower end of the range in Australia.  Further, 

the most abundant species in the area of the Ararat Wind Energy Facility are 

Australian Magpie, Long‐billed Corella, Galah, Raven, Australasian Pipit, 

Sulphur‐crested Cockatoo, Yellow‐rumped Thornbill and White‐fronted Chat, 

which are all relatively abundant. 

The Panel accepted the poignant and understandable concern expressed by 

submitters – particularly Mr Smithers‐Tomkins and Ms. Stewien – about the 

possible impact of the facility on Wedge‐tailed Eagles.  The Panel witnessed 

Wedge‐tailed Eagles within the area, and is aware of their iconic, if not 

endangered, status.  It concluded that the likelihood of collision will be 

reduced if carrion is removed from near the turbines, as proposed in the 

Environmental Management Plan.  There is a possibility that Wedge‐tailed 

Eagles may be struck by turbine blades in the future, but the probability is low 

and the mainland species is relatively abundant.  Consequently, there is not a 

case to reduce the number or change the location of turbines as a result of 

potential strike of Wedge‐tailed Eagles. 

The Panel also reviewed DSE’s initial concern about the proximity of the 

Ararat WEF to the Langi Ghiran State Park and Ararat Regional Park, 

especially the location of four proposed turbines near the Ararat Regional 

Park.  It also noted that DSE accepted that the requirements of the Bird and 

Bat Management Plan within the Environmental Management Plan addressed 

its concerns.  The Panel agreed with this conclusion, and considered that the 

requirements of the Bird and Bat Management Plan would provide a 

satisfactory outcome, providing the four turbines of concern to DSE (T32, T33, 

T64 and T65) are specifically cited in the relevant clause. 

In discussion at the Panel Hearing, the desirability of DSE bringing together 

the monitoring results of bird and bat strikes undertaken for all wind farms in 

Page 46: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 44

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Victoria, and to make the data available publicly, was canvassed.  There was 

general agreement concerning the value of such work. 

5.5 CONCLUSIONS AND RECOMMENDATIONS

The Panel concluded that flora and fauna issues were significant matters to be 

addressed in planning for the Ararat WEF.  Further, it considered that initial 

planning for the avoidance and mitigation of potentially damaging impacts on 

flora and fauna has been sound.  Further requirements of the EMP will refine 

this planning, and address any further flora and fauna issues if they arise. 

The Panel has also concluded that the request by DSE in relation to the 

removal of vegetation of very high conservation status can be satisfied with 

minor amendment.  Further, the Draft Permit Condition (Appendix C) relating 

to temporary fencing or tape that must be installed around areas of native 

vegetation to be retained should be included in the ‘Native vegetation 

management plan’ in the Construction Phase of the Recommended 

Environmental Management Plan at the Pre‐Construction Stage (Appendix F). 

A minor issue that was flagged at the hearings was the terminology of Bat and 

Bird Management Plan (BBMP), which was referred to as the Bat and 

Avifauna Management Plan (BAM Plan) in much of the documentation, and 

retained this title in the proposed EMP.  The Panel agrees with the Panel for 

Lal Lal Wind Energy Facility (February 2009), who preferred the term Bat and 

Bird Management Plan (BBMP), partly because avifauna means birds and bats.  

The Panel considers that “Bat and Bird Management Plan” is a more 

comprehensible title than the unfortunate acronym of “BAM Plan”. 

In relation to the wording proposed by the proponent for Clause 7 of the Draft 

Permit (Appendix C), the Panel concluded that the recommended wording to 

legally secure offset sites would be best placed in the Net Gain Offset Plan in 

the Construction Phase of the Recommended Environmental Management 

Plan at the Pre‐Construction Stage. 

The Panel also concluded that the compilation by DSE of all Victorian data on 

bird and bad strike from Victorian WEF’s is highly desirable.  Such data, when 

referenced with the conservation status of the various species, would provide 

clearer guidance to all parties on the likely cumulative impact of bat and bird 

strikes. 

The Panel therefore recommends that: 

DSE undertakes the task of collating, and progressively updating, all 

bird and bat strike data from Victorian WEF’s, and making the data 

publicly available. 

Page 47: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 45

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

6. NOISE AND HEALTH

6.1 THE ISSUES

The key issues with noise emerging from this Panel hearing are: 

Should NZS6808:2010 apply?; 

Will the predicted noise levels be below the standard?; 

Does wind turbine noise (including low frequency noise and infrasound) 

impact on human health?; and 

What permit conditions should be imposed? 

6.2 BACKGROUND

6.2.1 The application of NZS6808:2010

The revised New Zealand standard for wind farm noise (NZS6808:2010) 

includes a number of changes of a technical nature, and one change that 

reduces the acceptable noise limit (makes the limit more stringent) in a high 

amenity area.  NZS6808:2010 states that “A high amenity noise limit should be 

considered where a plan promotes a higher degree of protection of amenity related to 

the sound environment of a particular area.” 

VCAT ruled in ‘The Sisters Decision’ that NZS6808:2010 does apply in Victoria 

in lieu NZS6808:1998 specified in planning schemes and the Victorian 

Government Planning guidelines for wind farms, a decision which is currently 

under legal challenge.  This raises the issue of whether NZS6808:2010 should 

be applied to, or has relevance for, the Ararat WEF. 

Mr Power, for RES, argued strongly in his opening submission that 

NZS6808:2010 is clearly not the appropriate standard to apply and put 

forward a comprehensive series of legal arguments for his conclusion.  On the 

issue of whether NZS6808:2010 has relevance for the Ararat WEF even if it 

“...does not form part of the Victorian planning schemes...”, Mr Power submitted 

that it “is either irrelevant, or should be afforded very little weight.....  The simple 

reason for this is that the planning schemes expressly require wind farms to be 

assessed against NZS6808:1998, not the NZS6808:2010 version.” 

In its Directions, the Panel sought “…advice on the status of the Australian 

Standard for wind farm noise and the application of the 2010 revision of the New 

Zealand Standard.”  The proponent proceeded to carry out a noise assessment 

Page 48: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 46

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

of the Ararat WEF using both standards.  DPCD confirmed the applicability of 

NZS6808:1998 in its submission to the Panel. 

6.2.2 Do the predictions meet the NZS6808:1998 criteria?

Clause 52.32 of the Planning Scheme requires that in considering an 

application for a permit for a wind energy facility, the effects of noise on the 

surrounding area are to be investigated and requires that the application 

include an assessment of the noise impacts of the proposal on existing 

dwellings prepared in accordance with the New Zealand Standard NZS 

6808:1998 Acoustics – The Assessment and Measurement of Sound for Wind Turbine 

Generators (the Standard). 

The Standard includes recommended maximum noise levels to be received at 

dwellings near a wind farm and sets out: 

the method for the measurement of noise in the environment; 

the procedure for measuring existing background noise levels; 

procedures for predicting and assessing noise levels from the turbines taking account of existing background noise levels; and 

procedures for assessing compliance after the turbines are operational. 

A brief description of the provisions in the Standard, which have been 

described in detail in previous panel reports, is provided below. 

A summary of the provisions of the New Zealand Standard

In general, background noise levels and noise emitted by wind turbines both 

increase as the wind speed increases and under these circumstances, a fixed 

noise limit is not appropriate.  The Standard caters for these variations by 

specifying noise limits as a function of background noise and provides for a 

number of steps to be undertaken as follows: 

obtain noise power emission spectra for the wind turbine generators (WTG) 

for use in noise propagation modelling.  These are to be noise power levels 

guaranteed by the turbine manufacturer for the turbines proposed; 

generate noise contours for the surrounding environment by modelling 

wind farm noise with all turbines operating; 

monitor background noise levels (10 minute average L95) at residential 

locations that are within the 35 dBA contour based on the above modelling; 

monitor wind speeds (and wind direction) at the wind farm at the same 

time as the background noise measurements are taken at the dwellings; 

for each monitoring location plot sound levels against the corresponding 

wind speed at the wind farm site; 

Page 49: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 47

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

draw the line of best fit through the set of data points using least squares regression; 

continuous monitoring for a minimum of 10 to 14 days is typically required 

to have sufficient data that allows: 

- adequate correlations for separate daytime and night time periods; and 

- exclusion of extraneous noise events. 

the noise limit specified in the standard (the desirable limit) for each 

location, is the higher of the background level plus 5 dBA, or 40 dBA; 

for sound that has special audible characteristics, (for example clearly 

audible tones, impulses, or modulation of sound levels), 5 dB is added to 

the measured sound power level of the source.  In effect, this is equivalent 

to reducing the specified limits by 5 dBA.  The Standard acknowledges that 

at present there is no simple objective procedure available to quantify 

special audible characteristics and that a subjective assessment supported 

by objective evidence is necessary; and 

sound propagation modelling using the model specified in the Standard is 

undertaken for the final turbine configuration, to predict the expected noise 

levels at each location for the range of operating wind speeds. 

Compliance with the limit is assessed by comparing the predicted noise level 

with the limit at each wind speed. 

The acoustic assessment

The acoustic assessment28 was carried out by Sonus Pty Ltd, based on 

NZS6808:1998. 

Background noise measurements were undertaken at the following 

representative dwellings. 

Location  Label  Location  Label  Location  Label 

Hamilton  AH8  Hamilton  AH9  Mewburn  AH11

Kneebone  AH12  Moorfoot  AH39  Wandarna  AH52

Mooney’s Gap  AH52 

The location of these dwellings is shown on Figure 2 below: 

28 Volume 2 of Application Documentation, Acoustic Impact Assessment Report by Sonus Pty Ltd,

August 2009

Page 50: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 48

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Figure 2 Locations of background noise measurements29

 

Three separate sound propagation models were used.  Based on initial 

modelling, seven houses were selected for the background noise measurement 

representing individual houses and house clusters.  Model predictions were 

made of sound levels at 56 residences resulting from the operation of 75 Vestas 

V90 2 MW with wind speeds from 4 m/sec to 13 m/sec. 

Mr Christopher Turnbull, Principal of Sonus, gave expert evidence30 at the 

Panel hearing.  The Expert Witness Report contained a supplementary 

assessment using NZS6808:2010 for completeness.  The main technical 

differences in the methods specified in the two standards are that 

NZS6808:1998 specifies: 

different sound propagation models and input parameters; 

the hub height as the reference for wind speed; and 

use of L90 instead of L95. 

The supplementary assessment provided background noise measurements 

and criteria for the seven houses for wind speeds ranging from 6 m/s to 17 

m/sec, while predictions were made at all 56 houses for wind speeds from 6 

m/sec to 13 m/sec. 

29 Hearing Document 5, Environmental Noise overheads presented by Mr Turnbull. 30 Expert Witness Statement of Christopher Paul Turnbull, June 2010

Page 51: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 49

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

In response to a request by the Panel, Mr Turnbull made a further 

submission31, which included tabulated predictions for hub height wind 

speeds from 6m/sec to 25 m/sec, and using the NZS6808:1998 standard.  The 

analysis confirmed that noise criteria would be met at the higher wind speeds.  

Turbine noise power emissions and predicted receptor noise levels do not 

increases once the rated power of the turbine has been reached at a wind 

speed of 9 m/second and since the background noise keeps increasing with 

wind speed beyond this, background noise will increasingly dominate at the 

higher wind speeds. 

In his presentation Mr Turnbull concluded that “...for the layout and turbine 

selection, the noise criteria of NZS6808:1998 will be achieved at all residences”, and 

further “....the noise criteria of NZS6808:2010 will be achieved at all residences”. 

In relation to the high amenity areas warranting application of a lower noise 

limit, Mr Turnbull stated that all nearby residences were located in either a 

farming or a township zone and added that “To my knowledge, none of these 

zones are considered high amenity areas in accordance with NZS 2010 in that they do 

not promote a high degree of protection of amenity as it relates to the sound 

environment”. 

Poor noise wind speed correlations

The poor noise wind speed correlations have been noted in previous Panel 

reports.  Mr Turnbull explained that only noise components that are directly 

affected by wind can be expected to correlate with wind speed.  Poor 

correlations are not an indication of faulty data but a reflection of other 

sources of noise that are independent of wind such as traffic.  He did not think 

it appropriate that poor correlations in background noise measurements be a 

consideration in determining noise criteria on a case by case basis. 

Mr Turnbull undertook a re‐analysis of the background data by calculating 

and plotting the average noise levels in discrete wind speed intervals.  The 

plot of the averages generally coincides with the regression line for all the 

data, giving some confidence that the regression line is an adequate 

representation of the variation in average background noise levels.  An 

example of the plot is shown below in Figure 3. 

31 Supplementary Expert Witness Statement of Christopher Paul Turnbull, 12 July 2010

Page 52: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 50

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Figure 3 Background noise levels at House AH12, with average L95 noise levels superimposed32

 

6.2.3 Human health impact

The potential for noise from wind turbines to adversely impact on the health 

of nearby residents has been raised in previous wind farm hearings and 

dismissed.  Although not explicitly stated in submissions for this hearing, a 

linkage had been postulated to exist between low frequency noise emissions or 

infrasound and adverse health impacts. 

In his evidence Mr Turnbull expressed the view that: 

Much of the speculation regarding the potential health effects of the noise 

from wind farms is based on the assumption that the noise from wind 

turbines is unique and therefore has the potential to cause health effects 

that other noise sources cannot.  This assumption is not correct.  The 

frequency content, character and level of noise from wind turbines at 

typical setback distances to residences are similar to the noise from many 

naturally occurring and man‐made noise sources. 

32 Supplementary Expert Witness Statement of Christopher Paul Turnbull, 12 July 2010

Page 53: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 51

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

6.2.4 What permit conditions should be imposed?

The Draft Permit Conditions prepared by Mr Power at the conclusion of the 

Hearing are set out in Appendix C.  The text is based on the initial version 

prepared by DPCD, amended in discussions between DPCD and the 

proponent, and discussed at the without prejudice session at the end of the 

Hearing.  While Chapter 15 and 16 discuss the EMP and Permit Conditions 

generally, issues relating to noise are detailed in this section of the report. 

The relevant matters (relating to tracked changes that are not shown in 

Appendix C) are: 

a note immediately above Condition 24 (Noise Compliance Testing), 

suggests an alternative to Clause 24 preferred by the proponent, namely 

that noise compliance testing should only be done in response to 

complaints.  This alternative was supported by Mr Power at the Hearing; 

changes and deletions to Condition 24 (c) (ii), requiring determination of 

the maximum monthly proportions of the wind direction distribution that 

is from the wind energy facility to the dwelling (where noise compliance 

testing is being undertaken) plus or minus 22.5 degrees, and a further 

requirement that the compliance testing include periods where the wind is 

from the wind energy facility for at least 50% of the measurement period; 

minor editing to 24 (d), with the requirement for compliance testing to be 

repeated between 10 and 14 months after the first compliance test; and 

Condition 25 addresses Noise Compliance Enforcement, and Condition 

25(d) (ii) deletes the requirement deleted under Condition 24 (d) above. 

A further matter for the Panel arises from the approach being taken to make 

the EMP a statutory document that is part of the permit.  Consistent with that 

approach, the question arises as to how much of conditions 23, 24 and 25 need 

to be spelt out in detail in the permit, and how much can be simply included 

as procedural matters in the EMP. 

6.3 SUBMISSIONS

Three submitters expressed concern about low frequency vibration and noise, 

and the health effects of noise. 

In his witness statement Mr Turnbull explained that modern wind turbines are 

constructed with the blades upwind of the tower, which markedly reduces the 

levels of infrasound produced, to the point where it is well below the level of 

perception. 

Page 54: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 52

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

On the matter of the potential impact on human health, Mr Turnbull cited the 

expert panel formed by the US and Canadian Wind Energy Associations, 

which found no evidence that the audible or sub‐audible sounds emitted by 

wind turbines have any direct adverse physiological effects. 

6.4 DISCUSSION

6.4.1 The application of NZS6808:2010

As described above in Section 6.2.1, Mr Power submitted that no regard 

should be given to the VCAT decision in the “The Sisters Decision”.  The 

relevant standard for wind turbine noise is as set out in the Wind Energy 

Guidelines, the relevant Planning Schemes, and as further advised by DPCD, 

namely the NZS6808:1998 standard. 

Given the controversy that has arisen from the VCAT ‘The Sisters Decision’, 

the subsequent Supreme Court challenge, the advice from DPCD, and the 

persuasive argument by Mr Power, the Panel concluded that it would be 

unwise and unjustified to rely on the VCAT decision.  In any event, the 

proponent had already demonstrated conformance with the NZS6868:2010 

standard. 

6.4.2 Do the predictions meet the NZS6808:1998 criteria?

The Panel accepts that the predictions of noise at dwellings outside the site 

boundaries meet the NZS6808:1998 standard.  Further, even if NZS6808:2010 

were relevant, this tighter standard is also met. 

6.4.3 Human health impact

The Victorian Work Cover Authority in a letter33 to the Berrybank Panel Chair 

wrote: 

The Victorian Department of Health has examined both the peer reviewed 

and validated scientific research and also looked at the health aspects of the 

current planning process. 

Numerous international reviews on low frequency and infra sound noise, 

and case studies of actual wind farm noise emissions, have demonstrated 

that: 

there is insignificant infrasound generated from modern wind turbines; and 

33 Victorian Work Cover Authority, Correspondence 10 February 2010 relating to wind turbines and

health

Page 55: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 53

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

levels of low frequency sound emitted from modern wind turbines are not at the level that would lead to direct health effects. 

The issue was also examined by the National Health and Medical Research 

Council (NHMRC) who concluded that “Based on current evidence, it can be 

concluded that wind turbines do not pose a threat to health if planning guidelines are 

followed.”34 

There was  no  other  evidence  led  on  the  potential  health  impacts  of wind 

farms, and the Panel accepts the advice above.  

6.4.4 What permit conditions should be imposed?

There was little, if any, discussion on the matters raised above in Section 6.2.4 

by the proponent in response to the Permit Condition submitted by DPCD. 

In relation to the suggestion by the proponent that noise compliance testing 

only be done in response to complaints, the Panel has considered the 

requirements of NZS6808:1998, as set out in Section 5.1.2.  The relevant 

wording is “Once the WTG (or windfarm) is installed and operational, it may be 

necessary to monitor the sound level in the surrounding area.…” 

Where matters have the potential to adversely impact on human health or the 

environment, either source monitoring or ambient monitoring or in some 

cases, both is commonly required as a safeguard against breaches of 

requirements and potential health and environmental damage.  Where the 

matter concerns amenity impacts and source monitoring is difficult the 

general approach is to respond if complaints indicate that there may be a 

problem. 

In the present case, the Panel notes that it is predicted that the NZS6808:1998 

standard will be comfortably met, and the number of submissions from 

adjoining neighbours citing noise as a potential problem is remarkably small.  

The Panel also notes that ambient compliance monitoring is expensive. 

On the other hand the Panel is aware that there are a number of assumptions 

in the noise assessment procedures that result in uncertainties in the 

predictions.  Compliance monitoring provides verification of what are 

essentially model predictions, and can assist in resolving subsequent 

complaints. 

34 National Health and Medical Research Council, Wind Turbines and Health - a rapid review of the

evidence, July 2010

Page 56: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 54

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Overall, the Panel therefore agrees that noise compliance testing should be 

required in the permit conditions to validate the predictions made and test 

compliance of the constructed facility.  The Panel is also of the view that 

complaints should trigger further assessment including, if necessary, further 

measurements. 

Although construction noise was not addressed during the Hearing, the Panel 

is of the view that the permit should include conditions consistent with EPA 

noise guidelines.  In this case complaints can be used as an appropriate trigger 

for initiating construction noise measurements.  The standard construction 

noise condition was deleted at the meeting between the proponent, DPCD and 

the Councils.  The Panel, however, prefers to follow general practice for Wind 

Energy Facilities, and considers that the requirements for construction noise 

should be included in the permit. 

In relation to the specification of wind direction requirements in the 

compliance testing and enforcement, the Panel notes that Section 5.2.2 of the 

NZS6808:1998 standard states “Compliance level testing shall take place at the same 

positions and across a similar range of wind conditions for which background sound 

level data has been previously collected.” 

The Panel believes that NZS6808:1998 provides sufficient guidance on this 

matter. 

On the matter of repeated testing 14 months after the first compliance testing, 

the Panel does not see any reason to include such a requirement.  Should later 

complaints be made after the initial compliance testing, the investigation 

should establish if anything has changed since the initial compliance testing, 

and further compliance testing would proceed in response to a complaint 

where conditions have changed. 

On the last matter raised in 6.2.4 above, the Panel believes that the permit 

conditions 23, 24 and 25 should be restricted to a minimum, with detailed 

procedural matters listed as requirements in the EMP.  The Recommended 

Permit in Appendix E is formulated on that basis. 

Page 57: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 55

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

6.5 CONCLUSIONS AND RECOMMENDATIONS

The Panel has considered the evidence provided by the proponent in relation 

to  noise  and  statements  in  submissions  by  other  parties  and  makes  the 

following assessment. 

The panel is in general agreement with the proponent’s arguments in relation 

to the appropriate noise criteria.  Irrespective of the applicability or otherwise 

of NZS6808:2010, there has been no evidence led, and no obvious reason to 

consider that a Farming Zone or Township Zone warrants the high amenity 

protection from noise in the context of the Standard. 

The noise criteria in the New Zealand standard, the higher of background 

level plus 5 or 40 dBA, has been adopted for assessing wind farms in Victoria.  

This level defines what an acceptable level of noise intrusion from wind farms 

is.  This level is not intended to achieve inaudibility, but is one that provides 

adequate and reasonable protection of noise amenity. 

In relation to health, and in the absence of any contrary evidence, the Panel 

accepts the conclusions of the NHMRC that the turbines will not pose a threat 

to health. 

Accordingly, the Panel concludes that: 

the noise criteria of the greater of 40 dBA or background L95 plus 5 dB(A) as 

adopted by the proponent is appropriate; 

conforming with the criteria provides a reasonable degree of protection of 

noise amenity; 

operation of the turbines in accordance with permit noise criteria does not 

pose a threat to human health; and 

EPA Standards for Construction Noise should be referenced in the 

Recommended Permit. 

The Recommended Permit (Appendix E) makes provision for Construction 

Noise in Condition 10, while Permit Condition 11 addresses operational noise, 

which is further developed in the ‘Operational noise compliance testing plan’ 

and the ‘Operational noise compliance enforcement plan’ in the Construction 

Phase of the Recommended Environmental Management Plan at the Pre‐

Construction Stage (Appendix F).

Page 58: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 56

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

7. LANDSCAPE AND VISUAL IMPACTS

7.1 The issues

The key issues are: 

the landscape impacts caused by the WEF as seen from public viewing 

points and public roads; 

the visual impacts caused by the WEF as seen from dwellings within 3 km 

of the nearest turbine; 

cumulative impacts; and 

the potential visual impact from aviation obstacle lighting if it is installed 

and used. 

In addressing the first issue in particular, the Panel has considered the matter 

in a series of steps: 

What is the level of impact?; 

Is the impact ameliorated by screening?; 

How is the residual impact likely to be perceived by viewers?; and 

What weight should be given to visual impact? 

At the outset, the Panel wishes to state its general concern that the 

methodology used in the application and expert witness statement tends to 

minimise and obscure the likely landscape impacts.  Given the overall findings 

of public perception studies, and the support for renewable energy relative to 

visual impact in the policy guidelines for WEF’s, any Panel finding that the 

landscape impact has been understated does not imply that the proposal 

should be refused.  Nevertheless the Panel has a concern that any systematic 

understating of landscape impact may lead to a credibility issue in the 

assessment of WEF’s. 

7.2 Background

Mr Wyatt, who provided the specialist report in the application 

documentation, also submitted an Expert Witness Report and presented at the 

Hearing. 

Page 59: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 57

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

7.2.1 Landscape impacts

The steps taken in the assessment by Mr Wyatt are set out in the Landscape 

and Visual Report September 200935 and comprise: 

The visual components of the wind farm including, but not limited to, 

wind turbines, substations and access roads. 

The statutory context including policies, zoning and overlays. 

Perception studies which are noted as a factor “that needs to be considered 

when assessing the extent of visual impact”36, show ‘that they also provide the 

opportunity to gain a statistically valid understanding of a local communities’ 

attitude towards wind farms and not just those that dislike them’ and ‘the 

majority of those surveyed actually enjoy the view of wind turbines’.  37 The 

Ararat WEF perception study was undertaken within about 8 kilometres 

west and south of Ararat, extending 19 kilometres to Warrak to the east, 

and 10 kilometres to the north (though not extending as far as 

Crowlands).  71% of respondents accepted a wind farm set 1 kilometre 

from their home, and 71% of respondents accepted three ‘typical’ (30 to 

40 turbines) wind farms in the local rural area.38 

The viewshed and zones of Visual Influence with special reference to 

the 60° central field of vision.  25 publicly accessible viewpoints were 

identified, and six photo‐montages were prepared.  In addition, two of 

the photomontages from dwellings were cited as applicable for views 

from Warrak Road. 

Mr Wyatt cautioned in his report that while the photomontages 

reproduced in the report are technically correct, they do not portray a 

perceptually accurate image on which to assess the visual impact.  Mr 

Wyatt submitted that photomontages at A0 size, when held at arm’s 

length, give a more perceptually accurate assessment of the visual 

impact.  Such large photomontages were tabled at the Hearing, and a 

sample was used by the Panel to compare with actual landscapes in the 

field. 

35 Volume 2 of the Application Documentation, Landscape & Visual Assessment Report September

2009 page 1 36 Ibid page 1 37 Ibid page 10 38 Volume 2, Report on Community Perceptions towards Wind Farms in the Ararat Region, Victoria

May 2008 pages 65 and 66

Page 60: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 58

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Landscape units and sensitivity defined as primarily an assessment of 

the extent to which the landscape units can accept further change39. 

The landscape sensitivity assessment commenced with a classification of 

landscape units within the local area, as follows: 

Landscape Unit 1 ‐ Flat Farmland; 

Landscape Unit 2 ‐ Hilly Farmland; 

Landscape Unit 3 ‐ Forested Hills; 

Landscape Unit 4 ‐ Rural Townships; and 

Landscape Unit 5 – Recreational Areas. 

Mostly the landscapes were assessed as either Unit 1 (Flat Farmland) or 

Unit 2 (Hilly Farmland) for which the rating for public viewing points is 

“Low”.  Ararat National Park and Mount Langi Ghiran State Park were 

classified as Unit 3 (Forested Hills), while Green Lake was classified as 

Unit 5 (Recreational Reserves).  Both Unit 3 and Unit 5 are rated as 

having “High” landscape sensitivity.  Public views from Langi Ghiran 

State Park (Site 6), and across Green Hill Lake from the Camping Ground 

(Sites 13 and 14) were assessed as having High landscape sensitivity, 

while elevated sites on nearby hills and mountains (Sites 8 and 9 – One 

Tree Hill, 10 – Napoleon Hill, 15 – Mount Langi Ghiran, 24 – Crowlands 

and 25 – Mount Ben Nevis) were assessed as having “Low to High” 

landscape sensitivity.  The other 16 public viewing points were assessed 

as having Low landscape sensitivity. 

Seen area analysis using GIS software to map those areas from which 

the wind turbines are visible in whole or part. 

Assessment of publicly accessible viewpoints; based on photomontages 

and an evaluation of the three criteria40: 

The distance of the viewer from the development; 

The nature of the surrounding landscape (including the landscape units represented and their sensitivity) and 

The numbers of viewers able to see the development. 

The ratings of these criteria were set out in the report.  Table 4.141 shows 

zones of visual impact, and rated the visual impact at less than 1.5 km as 

“Highly visible and will always dominate the landscape”, at from 1.5 km to 3 

39 Volume 2 of the Application Documentation, Landscape & Visual Assessment Report September

2009, page 2 40 Ibid, page 2 41 Ibid, page 14

Page 61: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 59

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

km as ‘Noticeable and can dominate the landscape’, 3 to 8km as ‘Potentially 

noticeable, but will not dominate the landscape’, 8 to 17 km as ‘Discernable’, 

and greater than 17km (where the angle subtended by the eye is less than 

0.5°} as ‘Outside the viewshed’.  The text immediately below Table 4.1 notes 

that that ‘the visual impact of a wind farm is greatest within 3 km of the nearest 

wind turbine’). 

At the Hearing Mr Wyatt clarified that turbines within 1.5 km of a public 

viewing point were assessed under ‘distance’ as high, and that for a 

dwelling the distance for high impact was 3 km. Distances from 1.5 km to 

5 km were assessed as medium, while distances greater than 5 km were 

assessed as low. 

In terms of viewer numbers “Highways and roads within townships are 

assessed as having “high” numbers of users or viewers, while local connector 

roads are given a “medium” rating. “  Low” viewer numbers apply to small 

local roads and other infrequently visited viewing locations.’ 42 

In response to a question from the Panel at the Hearing, Mr Wyatt 

advised that the Perception Study findings were not used in assessing 

the visual impact from public viewing points, but were seen as 

supporting the assessed impacts. 

The rule for combining distance, landscape sensitivity and number of 

viewers used by Mr Wyatt is to assign the value of the lowest score.  If 

landscape sensitivity is low, any combination of the three criteria is low 

no matter how they rate.  An example of the description of the method is: 

If landscape sensitivity is low (i.e. within a highly man modified 

landscape) then even if the wind farm was in close proximity to the 

viewpoint and it was visible to a large number of viewers, the overall 

viewer impact would be minor because the viewpoint is not a 

landscape of such sensitivity that further change would be 

unacceptable.43 

Mr Wyatt selected 25 publicly accessible viewing points, considered to be 

‘worst case’ locations, as set out in Table 7.1 in Mr Wyatt’s Landscape 

and Visual Assessment Report, September 200944. 

42 Volume 2 of the Application Documentation, Landscape & Visual Assessment Report September

2009 page 31 43 Ibid page 32 44 Ibid Table 7.1

Page 62: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 60

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

The overall visual assessment tabulated by Mr Wyatt45 for the public 

viewpoints are low or nil for 23 viewing points, and medium for the two 

viewing points over Green Hill Lake. 

Residential dwelling viewpoints RVP03 (dwelling AH9) and RVP04 

(dwelling AH12) for which photo‐montages were prepared at A0 size, 

were said by Mr Wyatt to be substitutes for public viewing points, both 

being just off Warrak Road.  In terms of duration, Mr Wyatt cautioned 

that there was significant screening of the view from the road, and the 

visual impact would be low even when turbines were relatively close.  

The Panel noted that for most of the length of Warrak Road between 

Warrayadin Road and Warrak Township, a distance of some 11 km, the 

turbines will be sited to the north at distances not exceeding 1.5 km. 

Driving along this stretch of road, the Panel found the hills of the Great 

Dividing Range were in almost constant view, with the roadside 

vegetation not creating much of a visual barrier to the turbine vista 

shown in the photomontages for these two sites. 

Mitigation measures for publicly accessible viewpoints, where 

roadside planting was cited as an example.  No mitigation measures 

have been recommended by Mr Wyatt for the public viewing areas. 

7.2.2 Visual impacts

Figure 8.1 of the Landscape and Visual Assessment Report September 2009 shows 

the locations of residential dwellings in close proximity to the Ararat WEF, 

and the Main Report lists 56 dwellings within 3 km of a wind turbine.46  

Isopleths at 1.5, 3, 8 and 17 kilometres from the nearest turbine were drawn on 

Figure 8, and although it is not possible to accurately count the dwellings 

shown (because they overlap in places), there appear to be in excess of 10 

dwellings in the hamlet of Warrak, and about 30 elsewhere, which are within 

the 3 km isopleth. 

The Panel was invited to nominate residential viewpoints at which 

photomontages should be prepared, and did so at the Directions Hearing, 

nominating six locations, the houses AH9, AH11, AH12, AH39 and AH46 

(being also houses where background noise levels were measured) and the 

property of submitter 8 (Mr Randell).  With the exception of the property of 

Mr Randell, these photomontages were tabled at the Hearing, at both A3 and 

A0 sizes.  The Panel was advised that a photomontage from Mr Randell’s 

45 Volume 2 of the Application Documentation, Landscape & Visual Assessment Report September

2009 Table 7.2 46 Ararat Wind Farm Planning Permit Application Documentation, 2009 Volume 1 Main Report, pages

116 and 117.

Page 63: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 61

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

property would not be meaningful, given the shielding vegetation that existed 

in all directions from within the property. 

The assessment of the visual impact was undertaken using two of the three 

criteria detailed in the Assessment of publicly accessible viewpoints in Section 7.2.1 

above, namely landscape sensitivity and distance.  Landscape sensitivity from 

dwellings is taken as high in all cases.  The distance assessment is high within 

3 km, medium from 3 to 5 km, and low beyond 5 km. 

Screen planting is to be offered to owners of non‐host dwellings who may 

have a concern about wind turbines in their view from their house or garden.  

An indication of the Potential Landscape Mitigation measure for dwellings is 

shown in Figure 9.2.  Planting is shown that screens the views of the turbines 

from the house and shed, while views free of turbines remain unrestricted 

from the house. 

Mr Wyatt addressed the level of impact at the houses nominated by the Panel 

for which photomontages were to be prepared47, and the advice is summarised 

and tabulated in Table 2 below. 

Table 2 Visual assessment of residential viewpoints for which photomontages were done.

Residential viewpoints Distance to nearest Turbine

Qualifications Visual impact of turbines

RVP01 (house AH39 on Buangor-Ben Nevis Road)

1.8 km Existing vegetation and shed roof filter the views

Low to Medium

RVP02 ‘Wandana’ (house AH46 on Warrak Road).

1.08 km Assuming sheds adjacent to the courtyard were removed

Medium

RVP03 (house AH9 on Warrak Road)

1.07 km none High

RVP04 ‘Penzance’ (house AH12 on Warrak Road)

900 metres

none High

RVP05 ‘Mewburn’ (house on Big Hill Road)

900 metres

none High

RVP06 (property on Pyrenees Highway)

2.9 km No photomontage due to screening vegetation

Negligible

47 Expert Witness Statement of Allan Wyatt, Landscape and Visual Assessment, June 2010, Section

9.1

Page 64: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 62

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

7.2.3 Cumulative impacts

The key points made in Mr Wyatt’s treatment of Cumulative Visual Impact48 

are: 

Cumulative visual impact can occur either by: 

sequential and simultaneous views to wind turbines from publicly accessible viewpoints or from private viewing locations, or 

changes to a community’s or visitor’s perception of a region due to the presence of multiple wind farms in an area. 

Mr Wyatt took into account the existing Challicum Hills WEF (15 km south‐

east of Ararat WEF), the proposed Crowlands WEF (10 km to the north‐east of 

Ararat WEF) and the proposed Stockyard Hill WEF (50 km to the south‐east of 

Ararat WEF). 

He considered that: 

…the greatest possibility of cumulative visual impact lies with visitors 

travelling along the Western Highway between Beaufort and Ararat where 

they will pass the proposed Stockyard Hill Wind Farm, Challicum Hills 

Wind Farm (constructed) and then view towards the proposed Ararat 

Wind Farm, with the possibility of viewing the Crowlands Wind Farm in 

the background. 

Mr Wyatt considered that the there is limited road user viewing possibilities of 

the Ararat WEF from the Western Highway, which is often screened by 

vegetation.  He assessed cumulative visual impact, as a result of the Ararat 

WEF, from the Western Highway as minimal.  The cumulative visual impact 

for road users along the Pyrenees Highway, who will see both the Ararat WEF 

and the proposed Crowlands WEF, was moderated by the low landscape 

sensitivity of the landscape, and was low as a result. 

Mr Wyatt also considered the change in perception by the communities or 

visitors due to the presence of multiple wind farms in an area, and gave his 

opinion that such viewers would become more sensitive in their perception of 

wind farms.  While perceptions for those using the Western Highway would 

be little changed because of the limited views of the Ararat WEF, Mr Wyatt 

considered that, from the perspective of the multiple views  of Crowlands and 

Ararat WEFs from the Pyrenees Highway, a viewer’s perception of the Ararat 

area as one in which wind energy is a major element may change. 

48 Expert Witness Statement of Allan Wyatt, Landscape and Visual Assessment, June 2010 page 85

Page 65: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 63

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

7.2.4 Night lighting impacts

Mr Wyatt reviewed the trials of night lighting that have been undertaken at 

Challicum Hills (2005) and Wonthaggi (2005) in Victoria and the recently 

installed lighting at  Mt Millar in South Australia49.  In summary, the lights 

used were as shown in Table 3 below. 

Table 3 Visual impact of lights trialled and installed in Victoria and South Australia

Example Lights used Visual impact

Challicum Hills 2000 candella red flashing incandescent medium-intensity lights

Unacceptable(a)

Bright, and strobing on blades

Trial #1 at Wonthaggi

170 candella W-Red lights Acceptable

As low as car tail lights with no strobing

Trial #2a at Wonthaggi

2000 candella medium intensity MB80 Less visible than local display lighting, street lighting and light spill from domestic locations

Trail #2b at Wonthaggi

170 candella low intensity Sealite AV Generally as for Trial #2a above, while having less visual impact that Trial #2a above

Installed lights at Mt Millar WEF in South Australia

2000 candella red flashing medium intensity LED lights, unsynchronised, and baffled to ensure that the light spread is restricted to approximately 0.5° below the horizontal and 2.5° above.

Visual impact equivalent to Trial #1 at Wonthaggi using 170 candella lights

Note (a)  Quoted in Mr Wyatt’s report50 from the Yaloak Panel after viewing 

the Challicum Hills trial. 

Mr Wyatt concluded that if lights are required by CASA, lights similar to those 

constructed at Mt Millar provide an acceptable level of visual impact.  Further, 

any cumulative impact from night lighting from Ararat WEF and other WEF’s 

in the vicinity would be minimal. 

In his Expert Witness Statement, Mr Wyatt reviewed the Waubra lighting 

which uses un‐baffled Orga L350‐864‐G beam spread lights51, and further 

specified that lights similar to baffled FTB360i LED integrated L864 lights52 

49 Volume 2 of the Application Documentation, Landscape & Visual Assessment Report September

2009, pp. 89 to 94 50 Ibid page 89 51 Expert Witness Statement of Allan Wyatt, Landscape and Visual Assessment, June 2010, page 45 52 Ibid page 46

Page 66: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 64

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

would be proposed for Ararat WEF (if required) and their use would lead to a 

low visual impact. 

7.2.5 Powerlines within the site

The Main Report in the Application states that, in addition to a 33kV 

underground cable system used to collect the power produced by the wind 

turbines, there will be a number of overhead power lines within the site: 

Limited lengths of internal overhead power lines are also proposed on the 

subject site to carry generated power overhead once underground circuits 

reach capacity, or where the terrain is too steep for underground 

trenching53. 

These overhead power lines are described as follows: 

A number of 33kV overhead power lines will be required within the wind 

farm to connect the various wind turbines to the on‐site substation.  These 

overhead lines will operate at 33kV and will most likely be constructed 

using wooden poles, however steel and concrete pole options may be more 

appropriate at some or all locations.54  

The internal 33kV line will have vegetation clearance zones.  

7.3 Submissions and evidence

Five submissions were received that raised aspects of landscape and visual 

impact.  DSE, the Rural City of Ararat, Mr Randell and Mrs Stewien addressed 

the Panel, while Mr Woods was not able to, due to previous commitments 

interstate. 

DSE submitted that visitor numbers at Viewpoint 6, a lookout within Langi 

Ghiran State Park, were likely to be greater than the ‘Low” assessed by Mr 

Wyatt, and to be in fact ‘Medium’.  Such an assessment for visitor numbers 

would lead to a ‘Medium’ overall assessment of the visual impact at the site, 

and the need for a higher consideration of ameliorative measures. 

The ARC Council submission expressed concern about the potential impact of 

CASA or other requirements for obstacle lighting on surrounding ground 

level observation points such as Gum San and One Tree Hill Lookout.  It also 

expressed interest in ensuring that the community clearly understood the 

potential impact on view lines to Mt Langi Ghiran.  ARCC also presumed that 

obstacle lighting was not part of the proposal, and information on lighting was 

53 Volume 1 of the Application Documentation, p 12 54 Ibid., p.97

Page 67: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 65

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

provided for information only.  If obstacle lighting was later approved 

through a further permit or secondary consent, there should be opportunity 

for meaningful input from the community. 

Mr Randell expressed concern about visual amenity impacts, while Mr Woods 

was concerned at the bank of four towers within 1.5 km of his residence 

(AH11).  The submission by W J and L O Stewien strenuously opposed the 

proximity and confining nature of eleven turbines on two and a half sides of 

their house (AH43), with turbines being able to be sited as close as 1.2 km of 

their boundary.  They also expressed concern about the visual impact of the 

Ararat WEF on the tourism potential of the area, with the facility detracting 

from the views of and from vineyards in the area, and Mt Langi and Ben 

Nevis. 

Mr Wyatt, in his Expert Witness Statement, addressed these matters as 

described below. 

In relation to the DSE concern about visitor numbers, Mr Wyatt reiterated the 

treatment of the issue in his previous report55, which reported that ‘Low’ was 

the assessment against Visitor Numbers, and again concluded that he ‘did not 

believe there is any significant impact from these publicly accessible viewpoints.’ 

In relation to the concerns by Mr Randell about visual amenity, Mr Wyatt 

stated that although the nearest turbine would be 1.19 km from the property, 

and the landscape sensitivity was medium, existing vegetation would result in 

a negligible visual impact. 

In relation to the concerns by Mr Wood about the proximity of turbines, the 

photomontage requested by the Panel was prepared, and the two closest 

turbines (as close as 860 metres from the viewpoint) will be clearly ‘visible 

through a gap in the planting surrounding the residence’56. 

In relation to the concerns by Mrs Stewien about the proximity of turbines 

confining her vistas, no response was made in Mr Wyatt’s expert witness 

submission.  Although noting the Stewiens’ concerns57, and stating that the 

visual impact on residential properties is addressed in Chapter 958, Chapter 959 

did not address the concerns of the Stewiens, and restricted comment to the 

55 Volume 2 of the Application Documentation, Landscape & Visual Assessment Report September

2009, page 44 56 Expert Witness Statement of Allan Wyatt, Landscape and Visual Assessment, June 2010, page 36 57 Expert Witness Statement of Allan Wyatt, Landscape and Visual Assessment, June 2010, page 9 58 Ibid, page 10 59 Ibid, page 23

Page 68: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 66

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

six residential properties for which the Panel had directed that photomontages 

be prepared. 

In its Directions the Panel also sought responses on a number of matters.  The 

first of these relevant to landscape impact assessment sought a response by the 

proponent to the revised Policy and Planning Guidelines for Development of Wind 

Energy Facilities in Victoria(September 2009).  Mr Wyatt reviewed these 

guidelines in detail, in relation to landscape and visual impact assessment, 

and reported that the assessment had complied with them. 

The second matter on which the Panel sought responses was directed to both 

the proponent and the NGSC.  It concerned the second objective of the NGPS 

ES01 ‘to maintain the natural beauty and the landscape qualities of the ridge system’ 

and the decision guideline ‘to protect and enhance the landscape’. 

In his response Mr Wyatt stated  

The assumption that needs to be considered in addressing this question is 

whether wind turbines destroy the “natural beauty” of the ridge system or 

reduce the landscape qualities that are protected by this ESO1.  I believe 

that the wind turbines actually accentuate and articulate the subtleties of 

the underlying landscape pattern and as such comply with the 2009 

Guidelines which emphasise that “locating arrays of turbines to reflect 

dominant topographical and/or cultural features, such as ridgelines, the 

coastline, watercourses, windbreaks or transmission lines.60 

Mr Wyatt cited other Panel Reports and landscape experts views that all 

agreed that the location of wind turbines should reflect the underlying 

landscape character. 

Mr Douglas of NGS Council provided a written submission to the Panel in 

response to the Panel request.  In responding, Mr Douglas made a number of 

observations.  These included that: 

The ‘Environmental objectives to be achieved’ of the ESO introduce 

elements which are more commonly found in the Significant Landscape 

Overlay; 

It is likely that ‘wind energy facilities’ were not contemplated when the 

overlay was drafted; 

Wind turbines of the size proposed cannot be designed or managed to 

remove visual impact;  

60 Expert Witness Statement of Allan Wyatt, Landscape and Visual Assessment, June 2010, page 18

Page 69: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 67

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

If structures of this size (but without any beneficial purpose and without 

policy support) were proposed then it is my view that the Northern 

Grampians Shire would not support the application; and 

If the application was to be decided by the Northern Grampians Shire, then 

it is my view that the aspect of natural beauty would not prove fatal to the 

application. 

The Panel considered the second last dot point above to be a clear statement 

that the wind turbines would be detrimental to the natural beauty of the ridge 

system. 

The third matter on which the Panel sought advice from the proponent 

concerned the preparation of photomontages for specified views from 

dwellings, and Mr Wyatt’s response has been described in Section 7.2.2 above. 

The fourth matter concerned the impact of aviation obstacle lighting, and Mr 

Wyatt’s response has been described in Section 7.2.4 

The Panel followed up the advice received with DPCD, seeking to clarify how 

the secondary approval had been managed.  The advice from DPCD was 

received on 23 July 2010 by email, and included the following points: 

On 19 July 2007 Acciona Energy applied to amend the approved development 

plans for the Waubra Wind Farm. 

The proposed changes included the installation of medium intensity aviation 

safety lighting on 48 of the 128 turbines. 

CASA provided advice confirming that it could not require aircraft safety 

lighting for the wind farm as it is outside the obstacle limitation surface of any 

airfield.  However, CASA indicated its concern that the turbines would still be a 

hazard to aviation. 

Because CASA didnʹt require the lighting, the requirement of condition 4 to 

reduce turbine height to avoid lighting did not apply. 

Condition 5 of the permit requires that ʹno external lighting ... may be installed 

or operated... without further consent from the Minister for Planningʹ. 

On 16 October 2007, following an assessment of the potential visual impacts of 

the proposed lighting along with other matters, the Minister for Planning 

approved the amended development plan as provided for in Condition 3 and 

Condition 5 of the planning permits. 

Mr Herron gave evidence on aviation matters, and during cross‐examination 

he provided further expert advice on night lighting.  He confirmed that even if 

CASA had not withdrawn its circular, CASA has no legal power to enforce its 

guidelines.  The duty of care remains solely with the proponent or operator. 

Page 70: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 68

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

In reply to questions from Mr Randell, Mr Herron advised that options for 

night lighting, radar activated lights could be used.  A further option is the use 

of a system similar to that commonly used in aircraft, Pilot Activated Lighting 

(PAL), where pilots can turn on runway lighting 30 km out from the 

aerodrome. 

In reply to questions by the Panel about the practice of proponents 

commissioning independent quantitative risk assessments as a basis for 

discussions with CASA and their insurers, Mr Herron advised that conditions 

during both day and night were considered. 

7.4 Discussion

7.4.1 Landscape impacts

The four questions posed in Section 7.1 above will be addressed in turn.  The 

first and second questions were “What is the level of impact?” and “Is the 

impact ameliorated by screening?”  These two questions will be taken 

together for the publicly accessible viewpoints, as the existing screening has 

been considered in assessing the level of impact, and no further ameliorative 

screening is proposed by Mr Wyatt. 

Level of Impact (including existing screening)

The ratings and assessment by Mr Wyatt set out in Section 7.2.1 above can be 

queried in several respects.  Looking first at the elements in Table 2, Summary 

Assessment of publicly accessible viewpoints, the criteria are considered 

below in the order they appear in that table, namely Distance, Landscape 

sensitivity and Viewer numbers. 

Distance

As noted in Section 7.2.1, there is some ambiguity in the criteria adopted by 

Mr Wyatt in his 2009 Report and in answer to a question at the Hearing.  

While the 2009 Report describes the range from zero to 1.5 km as ‘Highly visible 

and will usually dominate the landscape’ and 1.5 km to 3 km as “Noticeable and can 

dominate the landscape’, this latter range was subsequently said to be included 

as ‘High’ only for visual assessment from non‐host dwellings.  The Draft 

National Wind Farm Development Guidelines61 report the likely visual impact 

of less than 1 km as ‘Will always be visually dominant in the landscape’ and at 1‐

2.5 km as ‘Highly visible and will usually dominate the landscape’.  Here the 

61 Draft National Wind Farm Development Guidelines 2 July 2010, see Table C-6 Determining the

likely visual impact of a wind turbine page 107 Source “Adapted from Peer Review Report: Dollar Wind Farm, ASPECT Studios, 2000.

Page 71: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 69

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

descriptor identical to that for Mr Wyatt’s zero to 1.5 km is extended to a 

distance of 2.5 km.  The Draft National Guidelines summarise the approach to 

distance in assessing multiple wind farms, and suggests the circles 

differentiating High, Medium and Low visual impact be drawn at 3 km and 12 

km.  That is, as noted above, less than 3 km is ‘High’, more than 12 km is 

‘Low’, and in‐between 3 and 12 km is ‘Medium’. 

In fact, when sections of Mr Wyatt’s 2009 report dealing with the viewpoints 

individually are examined, there is further ambiguity.  As shown in Table 1 in 

Section 7.2.1 above, one viewpoint in the range 1.5 to 3.0 km is assessed as 

Medium (VP1 at 2.17 km), while two other viewpoints in the range 1.5 to 3.0 

km are assessed as High (VP11 at 2.4 km & 17 at 2.95 km). 

The Panel considers that it would be more consistent to assign ‘High’ to public 

viewing point within 3 km, as has predominantly been done by Mr Wyatt, 

though that is in conflict with his verbal advice to the Panel.  In relation to the 

descriptor ‘Medium’, the Panel takes a more conservative view than the draft 

National Guidelines, and adopts Mr Wyatt’s 3 km to 8 km range set out in 

Table 4.1 of his 2009 Report (previously discussed in Section 7.2.1 above).  It is 

pertinent to record that at the site inspection, which was held on a clear, cold, 

sunny day, the view of Challicum Hills at a distance of 14 km from Telegraph 

Hill within the site was quite noticeable.  Though not dominant, it stood out 

against the sky. 

Landscape sensitivity

The general topography of the site is in the south‐western end of the Great 

Dividing Range, with run‐off going to north‐east to the Wimmera River and 

south to the Hopkins River.62  The ridges on which the turbines will be 

situated are the feature of the landscape. 

While it is common for landscape architects to assign ‘Low’ landscape 

sensitivity to Landscape Units 1 and 2, this is done in the absence of any 

Planning Scheme protection of the landscape.  In the case of Ararat WEF, and 

as described in Section 7.3, there is an objective of the ESO1 in the NGPS ‘to 

maintain and protect the natural beauty and the landscape qualities of the ridge 

system’.  As noted in Section 7.3, Mr Scott’s submission left no doubt in the 

Panel’s mind that the turbines would be detrimental to the view.  In the 

Panel’s view, Mr Wyatt’s response confused the natural beauty of the ridge 

system with visual impact reduction measures in the 2009 Wind Energy 

Guidelines, which includes “locating arrays of turbines to reflect dominant 

topographical and/or cultural features, such as ridgelines, the coastline, watercourses, 

62 Expert Witness Statement of David Tilley, page 2

Page 72: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 70

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

windbreaks or transmission lines.”  Mr Wyatt did not in fact address the issue of 

natural beauty in his response to the Panel. 

The issue for the Panel is whether the objective in the NGPS ESO1 should be 

considered in assessing the landscape significance within the Northern 

Grampians area of the WEF sites, and whether it should apply more generally 

throughout the Ararat WEF area, despite not being mentioned in the Ararat 

Planning Scheme. 

Mr Power also addressed this issue in his Part B Submission to the Panel, 

noting that the Ararat Planning Scheme does state that it is important that 

future developments do not detract from natural settings, but gave no special 

significance to landscape or environmental issues beyond those matters 

specifically addressed in the SLO (which only nominates State parks) and the 

VPO. 

On balance, and after repeated site visits with this issue in mind, the Panel 

considers that the landscape sensitivity of views towards the Great Dividing 

Range should be given a higher grading than ‘Low” for landscape sensitivity, 

and that a ‘Medium” landscape sensitivity would be more appropriate where 

the hills are within 3 km of the viewing point. 

Discussion at the Hearing turned to the matter of whether the objective of the 

ES01 Overlay ‘to maintain and protect the natural beauty of the ridge system’ 

would have been more appropriate in a Significant Landscape Overlay.  From 

this perspective, it could be argues that the first objective, protecting erosion, 

should be considered as the primary purpose of the overlay. 

The Panel notes that under the Decision Guidelines in Section 52.32‐3 of 

Victorian Planning Schemes, responsible authorities must consider the Policy 

and Planning Guidelines for Development of Wind Energy Facilities in Victoria.  

These guidelines, in providing guidance on the evaluation of landscape 

amenity (page 24) state: 

Wind energy facilities will usually have some degree of impact on the 

landscape.  In deciding whether or not the visual impact of a wind energy 

facility in the landscape is acceptable, it may be useful to consider 

planning scheme objectives for the landscape, including whether the land 

is subjected to an Environmental Significance Overlay, Vegetation 

Protection Overlay or a Significant Landscape Overlay in the relevant 

planning scheme. 

Consideration of the visual impact of a proposal should be weighted having 

regard to the Government’s Policy in support of renewable energy 

development. 

Page 73: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 71

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

The Guidelines, in relation to the visual impact of a wind energy facility in the 

landscape, makes no distinction between the different overlays, but rather 

looks at the objectives of any overlay.  The Panel has taken the same view. 

Visitor numbers

Mr Wyatt has adopted a rating of ‘Low’ for local roads, and ‘High’ for 

highways.  The traffic on the most significant local road adjoining the WEF 

site, Warrak Road, varies from 140 to 192 vehicles per day between Warrak 

Township and Warrayatkin Road.63  The Panel does not dispute the rating 

assigned by Mr Wyatt, but suggest that as it is not quite an order of magnitude 

less than the traffic on the Pyrenees Highway (1160 vpd) it might well be 

accorded a ‘Low to Medium’ rating.  The Panel makes this observation in the 

knowledge that most of the houses within 3 km of the WEF site are at the 

township of Warrak, or off Warrak Road. 

The Panel also supported the views of DSE in relation to visitor numbers, 

reported in Section 7.3 above. 

Combining the three ratings

Having examined the three criteria, the next task is to review how they are 

aggregated.  The Panel is aware that combining criteria which are quite 

different is not straightforward.  Mr Wyatt used the expression “When you mix 

apples with oranges you get fruit salad” and that succinctly states the problem.  

That statement, however, does not resolve the problem. 

Mr Wyatt’s approach to combining the ratings of visual impact for a public 

viewing point by is set out in Section 7.2.1 above, and consists of adopting the 

lowest rating for any one criterion. 

While other approaches to combining ‘apples with oranges’ are found in the 

extensive literature in Environmental Impact assessment and in the report by 

Helen Gibson Review of the Objectives‐Based Assessment Model: An assessment tool 

used by Planning Panels Victoria (October 2002), the Panel was interested to see 

how other landscape practitioners go about combining ratings for WEF’s. 

The approach taken by Urbis on the Berrybank WEF Report64 is set out in 

Section 1.5.1, Approach to Assessment.  It displays a two criteria matrix, with 

ratings of Low, Moderate and High.  The combined assessment is given as the 

mean of the ratings, rounded up where one parameter is ’High’, and rounded 

down where one parameter is ‘Low’. 

63 Ararat Wind Farm Traffic and Transport Report 24 July 2009, Table 1 page 9. 64 Berrybank VIA Final Report 030709, page 3

Page 74: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 72

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

The example given by the Shetland Islands Council65 is to consider the 

combination of ‘Sensitivity’ (capacity of a landscape to accommodate the type 

and scale of development without adverse effects on its character or value) 

and ‘Magnitude’ (a combination of the scale, extent and duration of any 

impact).  The table on page 12 sets out an overall assessment of ‘Slight’, 

‘Moderate’ and ‘Substantial’ which conforms to the schema used by Urbis 

(The example is taken from the Institute of Environmental Assessment and 

Landscape Institute, 1995, p.53). 

Mr Wyatt was asked for his opinion of these two alternative methodologies, 

and he robustly defended his method of combining ratings and rejected the 

alternative methodologies. 

The Panel has a concern that the approach taken by Mr Wyatt tends to 

minimise and obscure the likely visual impacts of the proposal.  Several 

statements by Mr Wyatt have assisted in clarifying the Panel’s approach, as set 

out at the beginning of the Chapter. 

The first of these was Mr Wyatt’s advice that the Perception Study findings 

were not used in assessing the visual impact from public viewing points, but 

were seen as supporting the assessed impacts (see Section 7.2.1 above). 

Mr Wyatt drew attention to earlier wind turbine structures that used lattice 

tower construction.  While they were smaller in height than modern wind 

turbine towers, the use of lattice towers has been abandoned in Victoria (and 

elsewhere) due to their adverse appearance. 

These reflections support the Panel’s approach in separating the initial 

assessment of impact and the next step of applying a cultural, or perception, 

filter.  Rather than relying on perception studies as mere support for the 

findings of visual impact analysis, the Panel believes that perception studies 

offer a separate and important aspect of visual assessment, and need to be 

used to moderate the initial assessment. 

The second statement of Mr Wyatt’s that has helped the Panel in clarifying its 

views (reported earlier in Section 7.2.1) was made in relation to his method for 

combining ratings: 

If landscape sensitivity is low (i.e. within a highly man modified 

landscape) then even if the wind farm was in close proximity to the 

viewpoint and it was visible to a large number of viewers, the overall 

viewer impact would be minor because the viewpoint is not a landscape of 

such sensitivity that further change would be unacceptable. 

65 Shetland Islands Council January 2006,Basic Principles of Landscape and Visual Impact

Assessment for Sponsors of Development, page 12

Page 75: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 73

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Turning to wind turbine towers in Victoria, the Draft National Guidelines 

describe the likely visual impact of a turbine as ‘Will always be visually dominant 

in the landscape’ and at 1‐2.5 km as ‘Highly visible and will usually dominate the 

landscape’, the latter being the identical descriptor used by Mr Wyatt for 

turbines within 1.5 km.  The Panel is at a loss to understand how an object that 

is visually dominating in the landscape can, by virtue of a ‘low’ Landscape 

sensitivity, have a Low visual impact.  It seems to the Panel that if viewers in a 

publicly accessible location such as a road are close to a wind tower, their 

appreciation of its visual impact will be moderated by their overall 

perceptions of wind farms rather than by the ‘Landscape sensitivity’. 

Review of the assessment summary

The Panel has re‐worked the assessment of the 25 publicly accessible 

viewpoints set out in Table 7.1 in Mr Wyatt’s Landscape and Visual 

Assessment Report, September 2009 (see Section 7.2.1 above), with the 

following changes: 

Distance: less than 3 km rated ‘Low’, 3 km to 8 km rated ‘Medium’, and 

greater than 8 km to 17 km ‘Low’.  No viewpoint should be considered if 

the turbines are at a greater distance than 17 km in the Panel’s opinion; 

Landscape sensitivity: rated medium for Landscape Units 1 and 2 in 

viewsheds of the hills comprising the western end of the Great Dividing 

Range, when the hills are in within 3 km of the viewing point; 

Visitor numbers: the ‘Low’ rating for Warrak Road needs to be treated 

with some caution, and a ‘Low to Medium’ rating seems more 

appropriate.  The DSE rating for visitor numbers at Viewpoint 6 (see 

Section 7.3) has also been adopted; and 

Combining the factors should follow the schema adopted by Urbis and 

others. 

Of the 25 public viewing points for which ‘Overall Visual Assessments’ were 

made by Mr Wyatt, the Panel has upgraded 19 as a result of the its review, 

using the Panel’s preferred ratings and combination rules.  The overall visual 

impact was changed in 19 of the 25 public viewing points; and in six cases the 

overall visual assessment of Low was maintained.  The changes were: 

from Nil to Low in one case; 

from Low to Medium in 13 cases; 

from Low to High, in three cases; and 

from Medium to High in two cases. 

However, as discussed above, it is not sufficient to merely take these results at 

face value.  The overall visual impact assessments need some closer 

examination to further review that they are in accord with general good sense.  

Page 76: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 74

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Rather than citing the Panel’s reasons for the review of the original assessment 

of every viewpoint, a few examples are provided below. 

In relation to Viewpoint 6 at Mt Langi Ghiran State Park, Mr Wyatt has 

assigned a Low overall impact, on the basis that the Ararat WEF cannot 

generally be seen from the park, and that the view from the lookout is largely 

screened by existing vegetation.  The Panel accepts this finding. 

Viewpoints 13 and 14 are from Green Hill Lake Park Lookout and Camping 

Area, and the ratings for Landscape Sensitivity and Visitor Numbers are both 

High and Medium for Distance.  In these cases the Panel has no hesitation in 

confirming a ‘High’ Overall visual impact, rather than the Medium assessed 

by Mr Wyatt. 

Viewpoint 17 is on the Pyrenees Highway to the west of the windfarm, and 

the ratings for Distance and Viewer Numbers are both High, and Low for 

Landscape sensitivity.  The overall visual impact assessment from has been 

upgraded by the Panel from Low to High.  A case could perhaps be made for 

assigning a Medium for the overall assessment, but the overall assessment of 

High is preferred.  The Panel sees no justification in agreeing with Mr Wyatt 

that the overall assessment from this viewpoint should be Low. 

Mr Wyatt’s Overall assessment for Viewpoint 18, Pyrenees Highway 2 

(looking south from the intersection with Woodlands Road) was Low, while 

the Panel has assessed it as High.  The difference comes both from the 

upgraded Landscape sensitivity and the combination rule.  With original 

assessments of High for both Distance and Visitor numbers, and a Low for 

Landscape sensitivity, the Panel would have found it should have been 

assessed as High in view of the combination rule.  With the increase in 

Landscape sensitivity from Low to Medium assessed by the Panel, the Overall 

assessment of High is confirmed and strengthened. 

The third question is “How is the residual impact likely to be perceived by 

viewers?” 

The Community Perception study undertaken by Environmental Resources 

Management Pty Ltd and Reark Pty Ltd is open to the criticism made by the 

Lal Lal WEF Panel, which found that the inclusion of a factually wrong 

statement about noise undermined the credibility of the study.  Mr Turnbull, 

the Expert Witness on Acoustics, was advised by the Panel of the finding of 

the Lal Lal WEF Panel. 

He was then asked for his opinion of the preamble to Question 15 in the 

Community Perceptions Survey for Ararat Wind Farm, namely that “Scientific 

tests conducted at wind farms have shown that people need to be less than 

Page 77: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 75

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

approximately 800 metres from the wind turbines for them to hear any significant 

turbine noise, even in extreme wind conditions.”  Mr Turnbull responded that “It 

is not a statement that I would make.  I’m not aware of any scientific tests to support 

that statement.” 

The Panel does not question the validity of the main findings of the 

Perceptions Study, providing caution is taken in drawing attention to the 

preamble to Question 15, and its potential to lessen the credibility of the study. 

With that proviso, the Panel accepts that there is broad support for wind farms 

in the general community, though that support may not translate to every 

local community. 

In view of the foregoing, it is likely that the degree of visual impact from 

public viewing points will be moderated by a general perception that wind 

farms are acceptable, providing the respondent is not in the immediate 

vicinity of a proposed wind farm. 

The fourth question is “What weight should be given to visual impact?” 

Clause 4.9.1 of the Policy and planning guidelines for development of wind energy 

facilities in Victoria states “Considerable weight should be given to the contribution 

to Government policy objectives in relation to the development of renewable energy.” 

and “Consideration of the visual impact of a proposal should be weighted having 

regard to the Government’s policy in support of renewable energy development.” 

The term visual impact in the above quote is taken to include both aspects 

commonly addressed by proponents, expert witnesses and Panels, Landscape 

Impacts and Visual impacts.  Clearly the level of Landscape impacts (i.e. those 

from publicly accessible viewing points) while being characterised by the 

Panel as Medium or High in more than half the viewpoints analysed by Mr 

Wyatt, should be given less weight than the advantage accrued from the wind 

farm through its provision of renewable energy by the policy support given 

through Victorian Planning Schemes. 

7.4.2 Visual impacts

The four questions posed in Section 7.1 will again be addressed in turn.  

Question 1 asks “What is the level of impact?”  Table 2 in Section 7.2.2 sets 

out Visual impact of the turbines on the six locations for which 

photomontages were requested by the Panel.  The results were that Mr Wyatt 

assessed three properties as having a ‘High’ visual impact, one as ‘Medium’, 

one as ‘Low to Medium’ and Mr Randell’s property as ‘Negligible’. 

Page 78: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 76

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

While both the Distance and the Landscape sensitivity was ‘High’ in all cases, 

the assessments were made on the basis of existing screening due to sheds and 

vegetation from the viewpoint. 

Question 2 asks “Is the impact ameliorated by screening?”.  The proponent 

has offered to provide screen planting to the owner of any existing dwelling 

within 3 km of the nearest turbine, regardless of the degree of impact that is 

assessed. 

At the without prejudice discussion at the Hearing on the draft Permit 

Conditions provided by DPCD, the draft planning permit condition 

concerning off‐site landscaping of non‐host dwellings (Condition 17 (a) in 

Appendix C)  was verbally extended to include (in part): 

…a program of voluntary landscape mitigation works must be made 

available to the owners of dwellings, built at the time a permit for the 

Ararat WEF is granted, within 3 kilometres of the nearest turbine. 

Mr Power submitted that the word granted should be replaced by lodged.  His 

argument was that there might be a number of dwellings for which planning 

permits (if necessary) and building permits were issued, and which were 

substantially completed, in the time taken for a permit for the Ararat WEF to 

be issued.  Such new dwellings could be in close proximity to the nearest wind 

turbine, and could result in a number of turbines having to be abandoned due 

to say noise impacts. 

DPCD and the two Councils maintained support for the word “granted”. 

The Panel notes the requirement in the Panel report for Berrybank does not 

specify anything apart from the fact that ameliorative landscaping works 

should be made to any dwelling existing at the time of the offer. 

The ameliorative planting offered may be taken up by owners, but by no 

means will vegetated screening return the visual amenity of the outlook to its 

pre‐wind farm state.  The views of the beautiful ridgelines of the western end 

of the Great Dividing Range will be compromised by the presence of one or 

more, and often many, wind turbines.  Whether the residual impact is still 

perceived by residents within 3 km will depend on the individual assessments 

by those residents.  The fact that so few residents within 3 km chose to make 

submissions on the matter may indicate that there is a general acceptance of 

the proposed wind farm.  Alternatively it may simply be as a result of people 

not feeling confident to submit, or not being aware that they have the right to 

make a submission, or not feeling that any submission they may make will be 

effective, or other reasons.  Overall the Panel would expect the offer of screen 

planting will be taken up by a number of owners, that it will provide some 

Page 79: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 77

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

further amelioration of the visual impact, but that the residual impacts may 

still be of serious concern to an unknown number of residents. 

On the matter as to whom the offer of off‐site landscaping works should be 

made, the Panel accepts the position taken in the Berrybank permit, namely to 

the owner of any dwelling existent at the time of the offer (which in turn is 

must be made within six months of endorsement of the development plan 

under Condition 1). 

Question 3 asks “How is the residual impact likely to be perceived by 

viewers?”  The answer to this question rests with the individual property 

owner, but the Panel is aware from submissions that at least three owners 

have significant concerns.  Others, of course, may find the presence of the 

wind farm quite acceptable. 

Question 4 asks “What weight should be given to visual impact?”  The last 

paragraphs of Section 7.4.1, Landscape visual impact, sets out the relevant 

policy: “Consideration of the visual impact of a proposal should be weighted having 

regard to the Government’s policy in support of renewable energy development.” 

7.4.3 Cumulative impacts

The evidence given by Mr Wyatt was not challenged, and is accepted by the 

Panel.  In essence Mr Wyatt concluded that, from the perspective of the 

multiple views of Crowlands and Ararat WEFs from the Pyrenees Highway, a 

viewer’s perception of the Ararat area as one in which wind energy is a major 

element may change.  The degree to which this may be an adverse impact will 

be moderated for many by the general acceptance of wind farms within the 

community. 

The approved Lexton Wind Farm some 20 km north west of Waubra is 

unlikely to be seen from either the Western Highway or from the west, being 

shielded by the Great Dividing Range and the Mount Cole / Mt Buangor 

range. 

7.4.4 Night lighting impacts

ARCC raised concerns about obstacle lighting being not part of the proposal.  

The Panel is satisfied that approval of obstacle lighting was sought in the 

application, subject to it being required.  Pages 95 & 174 of the Main Report 

and Mr Wyatt’s reports and the evidence presented make this matter quite 

clear. 

ARCC raised concerns about the secondary consent for aviation obstacle 

lighting, and the Panel pursued this matter to gain an understanding of how it 

Page 80: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 78

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

arose and was granted.  The advice received from DPCD is set out in Section 

7.3 above.  There is no detail of how the Minister reached his decision to allow 

the lighting, but clearly the decision was not accompanied by any requirement 

to baffle the lights, or to require any specification of the lights. 

The Panel drove along the Western Highway at night, and had the 

opportunity to observe the Waubra lights from a distance of perhaps 10 

kilometres.  The impact was high, with the hills lit up like a Christmas tree. 

The advice of Mr Wyatt was that if lights were required at Ararat WEF, the 

use of 2000 candella, red, flashing, medium intensity, baffled FTB360i LED 

integrated L864 lights (or similar) would result in a lower visual impact.  The 

Panel believes that if lights were required, they should be of the minimum 

intensity that would be consistent with safety requirements. 

Since the conclusion of the Ararat WEF Panel Hearing, the Minister for 

Planning has received the Panel Report for Berrybank, and has issued permits 

for that WEF.  Condition 7 of the Corangamite permit states: 

7.  Aviation obstacle lighting must not be installed unless the written 

consent of the Minister has been obtained. 

Condition 8 of the permit includes: 

8.  If consent to install aviation obstacle lighting is obtained, it must be 

installed under the following conditions: 

a) the aviation obstacle lighting must be installed such that it is 

activated only: 

i.   if at night, when an aircraft is in the immediate vicinity of 

the wind energy facility; and 

ii.  during low visibility daytime conditions such as the 

existence of smoke and fog; 

While parties to the Hearing have had no opportunity to make any comment 

on the outcome of the Berrybank permit application, the Panel notes that 

similar issues were canvassed at the Ararat Panel Hearing, as reported at the 

end of Section 7.3 above. 

The Panel believes that great care needs to be taken to limit the unnecessary 

use of nacelle lighting, and agrees with the requirement for on‐demand 

lighting in line with the Berrybank case. 

Page 81: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 79

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

7.4.5 Powerlines within the site

The landscape impacts of the internal power lines were not addressed in detail 

at the Panel hearing.  However, the Panel considers that the lines could 

potentially have detrimental landscape impacts, which need to be minimised 

in further detailed planning. 

7.5 Conclusions

7.5.1 Landscape impacts

The Panel concludes that the Landscape impact assessment by Mr Wyatt 

understates the level of Landscape impact for the following reasons: 

the criteria given by Mr Wyatt for distance are stated differently in 

different parts of his reports and expert evidence, and applied 

inconsistently within his assessment; 

the policy objective in the NGPS ES01 has not been given due regard and 

has led to a lower assessment of Landscape significance of many publicly 

accessible viewpoints; 

the assessment of visitor numbers on Warrak Road deserves a higher 

rating than Low; and 

the method adopted for combining criteria does not follow common 

practice and again, in a cumulative manner, further understates the 

actual overall impact. 

When all these matters have been taken into consideration, the Panel has 

assessed the significant overall visual impact at 5 sites to be High (compared 

to none in Mr Wyatt’s assessment) Medium in 13 cases (compared to 2 cases 

by Mr Wyatt), and Low for 7 cases (compared to 22 cases by Mr Wyatt, and 

one where he gave a Nil rating). 

While Mr Wyatt assessed only two (8%) of the public viewing points higher 

than Low, the Panel assessed 18 (72%) higher than Low. 

The Panel considers that systematic understatement of visual impact is likely 

to produce a public credibility issue in wind farm assessments. 

That is not to say that the higher level of impact assessed by the Panel should 

lead to rejection of the Ararat WEF.  Rather, that a higher degree of visual 

impact must be considered in relation to both general public perceptions of 

wind farms, and the policy guidelines.  This balancing of net community 

benefit is undertaken in Chapter 16. 

Page 82: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 80

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

7.5.2 Visual impacts

The Panel concludes that the photomontage representation of the turbines at 

A0 scale prepared by Mr Wyatt make a significant contribution to visual 

impact assessment, and provide a realistic portrayal of how they will ‘read’ in 

the landscape.  Some land owners will continue to have significant concerns 

about the visual impact of the turbines in the viewshed of their homes, even 

with the possibility of the mitigation resulting from screen planting.  However 

this level of concern is not sufficient (even in concert with the Landscape 

impacts) to cause the Panel to view them as unacceptable when compared to 

the significant contribution the Ararat WEF can make to sustainable energy. 

Provision for off‐site landscape ameliorative works for houses within 3 

kilometres of the site boundary are detailed in Appendix F, the Recommended 

Environmental Management Plan, under the Landscape and visual amenity 

plan in the Pre‐Construction Phase. 

7.5.3 Cumulative impacts

The Panel concludes that the cumulative impact caused by the construction 

and operation of the Ararat WEF will not cause any significant cumulative 

impact. 

7.5.4 Night lighting impacts

The Panel concludes that if the Minister for Planning, on the advice of a 

Quantitative Risk Assessment or the requirement of a regulatory authority, 

endorsed the use of lights at Ararat WEF, they should be of the lowest 

intensity consistent with safety. 

The further evidence of Mr Herron on options to minimise nacelle lighting, 

where it is required, and the use of on‐demand lighting required at Berrybank, 

leads the Panel to also favour on‐demand lighting. 

Provision for night lighting is made in Permit Conditions 3 (m) and 3(n) of the 

Recommended Permit (Appendix E), and in the Aviation Lighting Plan in the 

Pre‐Construction Phase of the Recommended Environmental Management 

Plan at the Pre‐Construction Stage (Appendix F). 

7.5.5 Powerlines within the site

The Panel concludes that, as far as possible, any internal powerlines should be 

underground.  However, it accepts that there may be circumstances when 

undergrounding may be totally impractical because of terrain or potential 

vegetation removal.  To achieve this objective, a process for justification and 

Page 83: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 81

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

approval of some internal overhead lines is required.  The Panel has added the 

following words to Condition 3 (i) in the recommended permit (Appendix E): 

All new electricity cabling and powerlines associated with the internal 

collector network within the wind energy facility must be underground 

unless overhead powerlines are demonstrated to be necessary, and be 

installed in accordance with the endorsed plans except with the further 

written consent of the Minister for Planning. 

Page 84: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 82

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

8. ROADS AND TRAFFIC MANAGEMENT

8.1 THE ISSUES

The issues arising from for traffic and transport are: 

Can the predicted volume off‐site traffic generated by the Ararat WEF 

during construction and operation be safely managed on the road 

system? 

Can the off‐site road network take the large heavy loads involved? 

The issue of the structural soundness of the on‐site access tracks is considered 

within Chapter 11 below.  The issue of the impact of construction traffic on 

existing vegetation is considered within Chapter 5 above. 

8.2 BACKGROUND

Traffic and Transport was reported in Volume 2 of the Application 

Documentation66.  In its Directions, the Panel sought further information on 

the quantities of materials required for internal access roads and their likely 

source.  In response, RES Australia provided an Expert Witness Report67 by 

Gillian Austin of Aurecon Australia Pty Ltd who undertook a peer review of 

the Traffic and Transport Report by RES Australia and provided greater detail 

on: 

the cut and fill balance on site; 

the road capping material deliveries to site (conservatively estimated); 

concrete foundation construction deliveries (using two scenarios: 

concrete batched on site, and ready‐mix concrete delivered from Ararat); 

electrical cable and turbine component deliveries; 

construction traffic routes and access points; and 

the impact of construction traffic on existing vegetation (considered in 

Chapter 5 above). 

In his Part B submission to the Panel, Mr Power drew attention to the close 

consultation between RES Australia, VicRoads and Ararat Rural City Council 

66 Volume 2 of the Application Documentation, Traffic and Transport Assessment Report September

2009 67 Traffic Assessment Panel Report, Ararat Wind Farm, RES Australia 18 June 2010 Revision 5

Page 85: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 83

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

to identify suitable access routes and to reduce traffic impacts on the local 

community. 

Site access points would be as generally shown in Figure 4 below. 

Figure 4 Site Access Points

 

The reports detailed that transport routes would be generally as follows: 

Route 1 – from Portland via the Hamilton to Ararat, north through Ararat  and 

either along the Pyrenees Highway to site entry points 1 and 2, or via Blake 

Street, Grano Road and Warrak Road to site entry points 3, 4 and 5.  

Route 2 – from Melbourne or Geelong using the Western Highway and 

turning into Warrayatkin Road (which is just east of Green Lake) and then 

either turning into Warrak Road for site entry points 3, 4 and 5, or continuing 

on Warrayatkin Road to the Pyrenees Highway for site entry 2 and further 

along the Pyrenees Highway to Woodlands Road for site entry 3. 

Route 3 – from Melbourne or Geelong using the Western Highway and 

turning into the Buangor‐Ben Nevis Road.  At Warrak the route would either 

turn left into Warrak Road to access site entry points 3, 4 and 5, or proceed 

north on Buangor‐Ben Nevis Road to the Pyrenees Highway, and turn left to 

access site entry points 1 and 2. 

The access roads are sealed roads in the main, though Warrayatkin Road, 

Woodlands Road (used for a distance of approximately one km), and 

Page 86: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 84

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Buangor‐Ben Nevis Road north of Iron Pot Creek Road (a distance of 

approximately 5 km) are unsealed. 

A one‐way traffic system68 is seen as one of the most effective mitigation 

measures for traffic impacts.  An example given is for a circulation system 

west on the Western Highway, north on Warrayatkin Road, east on Warrak 

Road for delivery vehicles to site entry points 3, 4 and 5, continuing east with 

unloaded vehicles along Warrak Road, turning south into Buangor‐Ben Nevis 

Road and then east onto the Pyrenees Highway.  If deliveries were made from 

Portland, it is presumed that the one way system would require the return 

journey on Warrak Road and Buangor‐Ben Nevis Road as described, but with 

a western leg on the Western Highway being used to return through Ararat. 

The Environmental Management Plan will include, under the Construction 

phase, a Transport Management Plan, to ensure the management of traffic and 

mitigate any potential problems. 

The peak construction traffic volume is associated with the construction of 

internal access roads, crane pads and concrete turbine foundations.  It is 

estimated to be of the order of 150 vehicle movements per day (round trips) 

spread between various routes, and these trips would include only standard 

road vehicles.  

Over sized vehicles would not be delivering wind turbine components in the 

peak traffic period. 

8.3 SUBMISSION AND EVIDENCE

RES Australia did not originally offer to present expert evidence on Traffic 

and Transport and on Geology and Hydrogeology.  In response to the requests 

for further information made by the Panel in its Directions, RES Australia 

submitted the Expert Evidence Statements Ms Austin (Traffic and Transport)69 

and by Mr Tilley (Geology and Hydrogeology) with additional reports by 

Douglas Partners attached.  In view of the general clarity of the information 

presented, the Panel did not require the attendance of either Ms Austin or Mr 

Tilley at the Hearings. 

Submissions were received from the Rural City of Ararat concerning the 

impact on vegetation on access routes which has yet to be assessed; from Mr 

Woods concerning the hazardous situation at the entry to Big Hill Road and 

68 Volume 2 of the Application Documentation, Traffic and Transport Assessment Report September

2009, page 31 69 Traffic Assessment Panel Report, Ararat Wind Farm, RES Australia 18 June 2010 Revision

Page 87: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 85

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

the impact on vegetation along Big Hill Road, and from Mrs Stewien 

concerning the impact on vegetation along Big Hill Road. 

Ms Austin70 addressed these submissions.  With respect to potential vegetation 

loss on the access routes, her preliminary view was addressed in Chapter 5.  

With respect to any potential for a traffic hazard to develop at the intersection 

of Big Hill Road with Warrak Road, and Site Entry 4 being located just a few 

metres further along Big Hill Road, Ms Austin concedes the general visibility 

issue, but notes that oversized vehicles will be accompanied by police and 

escort vehicles. 

With respect to concerns about vegetation along Big Hill Road, Ms Austin 

notes that Big Hill Road will not be used by construction traffic beyond Site 

Entry 4, and there will therefore be no impact beyond that point. 

At the Hearing, Mr Randell raised a concern about heavy traffic on the 

unsealed Warrayatkin Road, suggesting that in periods of rain heavy traffic 

would render it impassable to local traffic.  In response, Mr Power referred to 

the draft Planning Permit Condition requiring the proponent to include, 

during the construction period, a program of regular inspection to identify the 

need for maintenance works and agreed criteria that will trigger repair and 

maintenance works. 

8.4 DISCUSSION

The first issue identified by the Panel was: ‘Can the predicted volume off‐site 

traffic generated by the Ararat WEF during construction and operation be safely 

managed on the road system?’ 

The Panel believes that, subject to one further matter, the proposals by RES 

Australia and the latest version of the Planning Permit Conditions and EMP 

provided by RES Australia (see Appendices C and D) provide adequate 

management of the off‐site road network for the wind farm construction and 

operations. 

That further matter is the potential at Site Entry 4 adjacent to the intersection 

of Warrak Road and Big Hill Road to cause a traffic hazard.  While 

acknowledging that over‐sized vehicles will be accompanied by police and 

escort vehicles, no special traffic management provision has been made for the 

standard highway trucks carrying concrete, stone and other materials to the 

site and using Site Entry 4.  A requirement for warning signs either side of this 

location, to the satisfaction of the Ararat Rural City Council, should be 

included in the Traffic Management Plan within the EMP. 

70 Traffic Assessment Panel Report, Ararat Wind Farm, RES Australia 18 June 2010 Revision, page 35

Page 88: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 86

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

The second issue identified by the Panel was: ‘Can the off‐site road network take 

the large heavy loads involved?’  Again, the Panel believes that, subject to one 

further matter, the proposals by RES Australia and the latest version of the 

Planning Permit Conditions and EMP provided by RES Australia (see 

Appendices B and C) provide adequate protection for the repair and 

maintenance of the local road system. 

That further matter is the likelihood that the unsealed Warrayatkin Road will 

become impassable to local traffic during periods of wet weather.  The Panel 

shares the concerns of Mr Randell on this matter. 

If over‐dimensional traffic comes via Ballarat, the section of Warrayatkin Road 

between the Western Highway and Warrak Road will be used by over‐

dimensional traffic accessing Site Entries 1, 2, 3, 4 and 5, and the northern 

section from Warrak Road to the Pyrenees Highway will be used by over‐

dimensional traffic accessing Site Entries 1 and 2.  It is not known whether the 

route may also be attractive to standard heavy vehicles carrying concrete, 

aggregates or other construction materials.  This will depend, in part, on the 

origin of these materials. 

The use of a one way system along Warrak Road, as proposed, will also 

concentrate over‐dimensional traffic on the southern part of Warrayatkin 

Road. 

It would seem desirable for further consideration to be given to the need for 

sealing Warrayatkin Road, and discussion between RES Australia and the 

ARC Council, to reduce the inconvenience to local traffic during the 

construction of the facility, and to provide a long term benefit to road users.  

Clearly, further traffic management measures would need to be considered to 

prevent conflict between over‐dimensional vehicles and other traffic, light or 

heavy, on Warrayatkin Road when over‐dimensional vehicles were using it. 

The possibility of a one‐way system for Site Entries 1 and 2, using a clockwise 

circulation on Warrayatkin Road, Pyrenees Highway, Buangor‐Ben Nevis 

Road has not been specifically proposed by either RES Australia, VicRoads or 

Ararat Rural City Council.  The Panel neither advocates nor dismisses such a 

system, which would need further consideration of a range of factors, 

including safety, road maintenance and road user costs.  If such an outcome 

was found to be undesirable overall, the proposal for alternative access to Site 

Entries 1 and 2 via the Buangor‐Ben Nevis Road and the Pyrenees Highway 

could be reconsidered.  If the Buangor‐Ben Nevis Road was not used for over‐

dimensional traffic to Site Entries 1 and 2, the unsealed length of this road 

would not be subject to construction traffic damage. 

Page 89: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 87

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

8.5 CONCLUSIONS

The Panel concludes that: 

The potential hazard at Site Entry 4 arising from its proximity to the 

intersection of Big Hill Road with Warrak Road, and the limited site 

distance available, requires the use of site specific early warning signs to 

reduce the risk to road users. 

Further consideration of the need to seal Warrayatkin Road, and of the 

need for the alternative access to Site Entries 1 and 2 via Buangor‐Ben 

Nevis Road is warranted, and RES Australia should study the public risk 

in this respect, providing the findings of the study to the ARC Council. 

The stability and safety of on‐site access tracks needs further study, in 

respect both of the sealing of steep sections of those tracks, and the need 

to flatten batters to 2H:1V. 

The Recommended Environmental Management Plan at the Pre‐Construction 

phase, within the Transport and Traffic Management Plan, cover these 

conclusions. 

Page 90: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 88

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

9. AVIATION SAFETY AND FIRE

9.1 ISSUES

The main issues relating to aviation and safety emerging from the Panel 

hearing relate to the Ararat aerodrome and are: 

interference with current operations at the airport including use by Royal 

Flying Doctor Flying Service, Air Ambulance Service, and Country Fire 

Authirity (CFA); 

restricting potential expansion of the airport’s operation; 

safety need for aviation lighting; and 

fire risk from the WEF. 

The issues arose in written submissions and were responded to in writing and 

expert witness presentation.  The issue of the potential visual impact from 

aviation obstacle lighting if it is installed and used is addressed in Chapter 7. 

9.2 BACKGROUND

Because of their height, wind turbines can be a potential hazard to aircraft in 

the vicinity of airports.  Aviation safety is governed by the Civil Aviation 

Safety Authority (CASA).  The main rules for structures around airports are 

determined by CASA and a key variable is the Obstacle Limitation Surface 

(OLS) which is a defined space around an airport.  Obstacle height and 

marking, and other requirements apply within the OLS. 

A CASA advisory circular (now withdrawn) had advised that turbines that 

were beyond the OLS should be lit if higher than 110 metres.  The matter is 

under review by CASA, and the current advice is that wind farm proponents 

should assess their duty of care requirements in deciding whether to provide 

lighting. 

9.2.1 Interference with current operations

The Aviation Assessment Report71 documented the potential impacts of the 

WEF to aircraft safety set out in Section 4.9.1 of the VWEG.  The Aviation 

Assessment Report also provided copies of the considerable exchange of 

letters between RES Australia and relevant organisations, including Air 

71 Application Documentation Volume 2, Aviation Assessment Report, September 2009

Page 91: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 89

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Services Australia, Ararat and Stawell Aerodromes, the Civil Aviation Safety 

Authority, the Department of Defence, the Royal Australian Air Force and the 

Royal Flying Doctor Service. 

The report concluded that the consultations had ensured that the WEF does 

not infringe on any OLS, and that the WEF will not affect any aircraft 

navigation, communication or procedures. 

9.2.2 Interference with Future operations

The issue of future changes to operations at Ararat Aerodrome was not 

considered in the Application Documentation.  It was however addressed by 

Mr Herron in his expert witness statement72 which included a peer review of 

the RES Aviation Assessment Report. 

9.2.3 Aviation lighting

The Aviation Report73 addressed nacelle lighting.  A CASA endorsed nacelle 

lighting plan was provided74 on the basis that should lighting be required, the 

lighting plan would be followed. 

9.2.4 Fire risk from the WEF

The issue of fire risk resulting from the WEF was addressed in the Main 

Report75, within the summary of environmental mitigation and management 

measures. 

9.3 SUBMISSIONS AND EXPERT EVIDENCE

Four submissions addressed the issues of aircraft safety and fire (Submissions 

1, 11, 15 and 18).  CFA, acting as a Referral Authority pursuant to Section 52 of 

the Planning and Environment Ac 1987 had no objection providing and 

recommended that “the site be developed in accordance with CFA’s document 

‘Emergency Management Guidelines for Wind Farms’”. 

Mr O’Rorke made an extensive written submission on the exhibited 

application, raising concern about the threat to the present operations and the 

future potential expansion of Ararat Aerodrome posed by the WEF.  At the 

Directions Hearing, the Panel was informed of Mr O’Rorke’s tragic death. 

72 Aviation Expert Witness Statement by Syd Herron of The Ambidji Group, 18 June 2010 73 Application Documentation Volume 2, Aviation Assessment Report, September 2009, Section 3,

page 5 74 Ibid, Figure on page 27 75 Application Documentation, Volume 1 Main Report, Table 8,Bushfire, page 88

Page 92: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 90

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Ararat Rural City Council expressed concern about the potential impact of 

CASA or other requirements for obstacle lighting, particularly from public 

viewing points. 

The fourth submission raised general amenity concerns, including a mention 

of obstacle lighting. 

9.3.1 Interference with current operations

A principal contention was that the aerodrome is a Code 2 aerodrome with the 

potential to expand to Code 3.  Mr Herron, in his Expert Witness Report76 and 

in his Submission to the Hearing77, explained that in fact the aerodrome is a 

Code 1 aerodrome.  The main runway has sufficient length, but would need to 

be widened to allow for Code 2 or Code 3 status.  There is no CASA 

requirement for a 15 km separation of the aerodrome from a wind farm.  The 

nearest wind turbine is well beyond the OLS of the current aerodrome. 

In relation to the use of the aerodrome by the Royal Flying Doctor Service, Air 

Ambulance Service, Mr Herron states that the geometry of the OLS would not 

exclude fixed wing aircraft, and further, the wind farm as proposed would not 

inhibit the use of the aerodrome by either organisation.  Air Services Australia 

confirmed to RES that the proposed wind farm “...will not affect any procedures, 

including any published Lowest Safe Altitude (LSALT).....it will also not impact on 

Precision/Non‐Precision Nav Aids, HF/VHF Comms, Cables, ASMGC, Radar or 

Satellite/Links.” 

9.3.2 Interference with future operations

The issue was explored by Mr Herron.  He referred to conversations with the 

Airport Manager indicating low current demand and little foreseen change in 

future demand.  Mr Herron assesses the costs of upgrading the aerodrome to 

Code 3 as relatively high.  However, the wind farm would not create a 

restriction to upgrading the aerodrome since the nearest turbine would be 

outside the expanded OLS. 

9.3.3 Aviation lighting

The proponent has confirmed that, in accordance with its application, RES 

Australia is applying for a planning permit for a “lit” wind farm, although its 

preference is that it not be lit.  In its aviation assessment report RES Australia 

notes the following: 

76 Aviation Expert Witness Statement by Syd Herron of The Ambidji Group, 18 June 2010 77 Hearing Document No 9, Aviation Expert Witness Statement Presentation by Syd. Heron, 7 July

2010

Page 93: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 91

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

The Commonwealth Government recently (June 2009) released a 

discussion paper; Safeguards for Airports and the Communities around 

Them, Department of Infrastructure, Transport Regional development and 

local Government, June 2009 which addresses the safeguarding of aviation 

infrastructure. 

Of note, is the discussion on the potential impact of wind farms further 

than 30km from an aerodrome.  The paper identifies that wind turbines 

over 152m above ground may be a potential aviation hazard, as normal 

aircraft operations are permitted down to that height.  This height is 

therefore less stringent than the previous 110m height trigger under 

Advisory Circular AC 139‐18(0) that was recently withdrawn.  It is noted 

that the proposed wind turbines at Ararat Wind Farm would not exceed a 

maximum blade tip height of 135m. 

In his expert witness statement Mr Herron observes that that “...the reference to 

turbines over 152m being a potential hazard does not necessarily imply that this will 

be a future trigger height for CASA notifications.”  He points out that “... it is my 

view that any duty of care considerations by the proponent will be mainly focussed on 

whether to now proceed to light the wind farm.  In this regard and as a function of 

duty of care, there are now a number of wind farm proponents that are undertaking 

qualitative risk assessments to consider whether lighting of the wind farm is 

necessary.  Similarly, a number of operators of existing lit wind farms have turned 

their lights off or are having qualitative risk assessments prepared to consider turning 

the lights off.” 

Mr Herron provided a sample list of wind farms and the status of the aviation 

lights78 as follows: 

Facility Turbine Height Status of Lights

Alinta Wind Farm (WA), 54 turbines 118 Not lit

Hallett Wind Farm Stages 1 & 2 (SA) 124 Lights switched off

Snowtown Wind Farm (SA), 47 turbines 124 About to be switched off

Capital Hill Wind Farm (NSW), 67 turbines 125 Not lit

Cullerin Wind Farm (NSW), 15 turbines 125 Under consideration

Hallett Wind Farm Stages 3 & 4 (SA) 124 No lighting planned

Waubra Wind Farm (Vic) 110 - 120 Under consideration

78 Hearing Document No 19, letter from Syd Heron, 12 July 2010

Page 94: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 92

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

9.3.4 Fire risk from the WEF

CFA requirements are related to fire safety issues.  CFA have raised no general 

objections to the wind farm and recommended that the site should be 

developed in accordance with the CFA’s document ‘Emergency Management 

Guidelines for Wind Farms’.  The specific question as to whether turbines 

would restrict the use of fire fighting aircraft was addressed by Mr Herron.  

He points to the CFA submission that: 

Fire suppression aircraft operate under visual flight rules.  As such, fire 

suppression aircraft only operate in areas where there is no smoke and 

during daylight hours.  The standard distance of 300 meters between 

turbines would allow aircraft to operate around a wind farm given the 

appropriate weather. 

9.4 DISCUSSION AND CONCLUSIONS

The Panel has considered the evidence provided by the proponent in relation 

to Aviation Safety and Fire. 

The Panel concurs with the proponent’s conclusions in relation to the effects of 

the wind farm on the Ararat aerodrome’s current and future operations.  The 

construction of the wind farm will not intrude into the OLS of the aerodrome 

either in current or in upgraded form should this be considered, and hence 

will not affect aerodrome users. 

In relation to aviation lighting, the Panel is of the view that this should be 

avoided if possible.  Accordingly, the Panel concludes that lighting should 

only be allowed if informed by a risk assessment or required by a regulatory 

Authority, and then as a secondary consent.  The issue of nacelle lighting is 

also considered in Chapter 7 from a visual perspective, and a condition on 

aviation lighting is included in the Recommended Permit (Appendix E), 

Conditions 3(m) and 3(n). 

In relation to the potential for fires to be started due to the operation of the 

WEF, the detail specified in the EMP emailed by the proponent (Appendix D) 

has been adopted in the Recommended Environmental Management Plan at 

the Pre‐Construction Stage (Appendix F), with the inclusion of a reference to 

‘Emergency Management Guidelines for Wind Farms’ in the ‘Fire Prevention 

and emergency response plan’ in the Pre‐Construction Phase. 

Page 95: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 93

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

10. SHADOW FLICKER, BLADE GLINT & ELECTROMAGNETIC INTERFERENCE (EMI)

10.1 ISSUES

The main issues are as follows: 

shadow flicker causing annoyance; 

blade glint or unwanted reflections causing annoyance; and 

electromagnetic interference (EMI). 

10.2 BACKGROUND

The proposed wind farm will consist of 75 wind turbine generators.  The 

maximum hub height of each turbine is 94 metres, the maximum rotor 

diameter is 104 metres and the maximum height of the blade tip above ground 

is 135 metres.  The blades are stated to rotate at up to approximately 20 

revolutions per minute. 

The large number of tall structures with rotating blades has the potential to 

cast shadows and reflections on the surrounding landscape.  The rotating 

blades result in shadows that pass quickly by an observer, creating a flicker 

effect.  This can cause annoyance to residents.  Another phenomenon is blade 

glint, where reflections of the sun from a shiny blade surface can be annoying.  

The turbines also have the potential to cause interference with communication 

systems and signals, including radio and TV reception through signal 

attenuation, reflection and distortions. 

The VWEG specify that “The shadow flicker experienced immediately 

surrounding the area of a dwelling (garden fenced area) must not exceed 30 

hours per year as a result of the operation of the wind energy facility.”  

The proponent addressed the issues of shadow flicker and blade glint79, and 

electromagnetic interference80, in the exhibition documents. 

RES Australia concluded that only one house (AH11) would experience any 

shadow flicker, and the number of hours it would occur is theoretically 14.1 

79 Application Documentation Volume 2, Shadow flicker and blade glint, RES Australia, August 2009 80 Application Documentation Volume 2, Electromagnetic interference report, RES Australia, 30

September 2009

Page 96: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 94

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

hours per annum, well below the 30 hours per annum set in the Wind Energy 

Guidelines.  In practice, the actual number of hours where shadow flicker 

would be experienced at AH11 would be considerably less than the 14.1 hours 

predicted due to a range of factors including: 

vegetative screening; 

built structures between the house and the turbines; 

turbines not turning all the time; 

turbine rotor orientation; and 

cloud cover. 

RES Australia concluded that there are no known reports of reflected light 

from turbine blades being a significant problem at any existing wind farm.  

This was due to a number of mitigating factors, due in part to the use of a 

semi‐matt surface finish. 

The assessment report by RES included identifying and analysing four point 

to point microwave links and point to multipoint television broadcasting links.  

The point to point link analysis indicated no potential interference based on 

Fresnel zone analysis.  For television reception, a survey of aerials in the 

surrounds of the wind farm was undertaken along with predicted signal 

strengths from the Lookout Hill transmitter.  A total of 20 houses were 

identified as potentially affected by EMI, including 16 houses south of the 

wind farm. 

RES Australia concluded that; 

Based on Fresnel Zone analysis, all point‐to‐point microwave links that 

cross the site have sufficient clearance from turbines and no interference of 

any link is predicted. 

A prediction of interference to TV reception has been made around Ararat 

wind farm.  No widespread interference has been predicted and only 20 

houses are potentially at risk of being affected.  If required mitigation 

measures are available with the most likely solution being either 

installation of an improved aerial or conversion to a digital platform. 

Page 97: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 95

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

10.3 SUBMISSIONS AND EVIDENCE

10.3.1 Shadow Flicker

One submitter expressed concern at the potential effect of shadow flicker. 

Dr Trenton Gilbert of GL Garrad Hassan gave expert evidence to the Panel81.  

Dr Gilbert’s assessment was for a turbine diameter of 104 metres and hub 

height of 83 metres, as this represents the design with the greatest projection 

area and hence maximum shadow flicker. 

Dr Gilbert concluded that: 

....two dwellings are expected to experience some shadow flicker, but the 

durations are below the allowable limit of 30 hours per year.  Additionally, 

when turbine orientation and cloud cover are considered, the predicted 

actual shadow flicker durations are below the allowable limit of 10 hours 

per year. 

The Panel believes the reference to “the allowable limit of 10 hours per year” is an 

error, and the words “the allowable limit of” should be deleted. 

The issue of potential impacts of shadow flicker on health has been raised in 

previous wind farm panel hearings.  In their rapid survey of Health, the 

NHMRC conclude: 

In summary, the evidence on shadow flicker does not support a health 

concern (Chatham‐Kent Public Health Unit, 2008) as the chance of 

conventional horizontal axis wind turbines causing an epileptic seizure for 

an individual experiencing shadow flicker is less than 1 in 10 million 

(EPHC, 2009).  As with noise, the main impact associated with shadow 

flicker from wind turbines is annoyance. 

Dr Gilbert made several observations in response to questions from the Panel 

that assisted it in better understanding the issue.  He advised that outdoors 

shadow flicker is ameliorated by the general scatter and reflection of light – it 

is likely to be more of a problem for a person inside a dwelling, and near a 

window.  In such circumstances, the amelioration of scattered and reflected 

light is not present. 

Dr Gilbert also advised that there was presently no measurement method for 

shadow flicker, although a PhD student in Germany is working on the 

problem.  No doubt this work has been encouraged by the shadow flicker 

81 Expert Witness Statement of Trenton Gilbert of GL Garrad Hassan, 18 June 2010

Page 98: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 96

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

regulations of the German Ministry for Environment and Climate Change82, 

which prescribe limits of 30 hours/year and 30 minutes per day modelled 

shadow flicker, and 8 hours per day actual shadow flicker. 

10.3.2 Blade glint

Dr Gilbert concluded that “blade glint is not generally a problem for modern wind 

turbines provided the blades are coated with a non‐reflective paint.” 

10.3.3 Electromagnetic interference

Two submitters expressed concern at the potential effect on mobile phone, 

radio and television reception.  Mr Randell, who addressed the Panel and 

contributed to discussion on the issue, runs a business installing television 

aerials in rural areas, and has a good knowledge of television and radio 

reception issues, and some experience of the effect of wind farms on reception.  

Mr Randell was concerned that television and radio reception would be 

impacted by the wind farm beyond the immediate area of the site, based on 

his experience. 

Dr Trenton Gilbert of GL Garrad Hassan gave expert evidence to the Panel.  In 

his witness report83, Dr Gilbert reviewed the original work by RES Australia 

and a supplementary assessment was provided that included potential 

interference to broadcast radio, mobile phone, and GPS services. 

Dr Gilbert concurred with the RES analysis that showed that there was some 

potential for EMI to TV reception at a number of house locations.  Figure 5 

adapted from Figure 5 in Dr Gilbert’s expert witness statement, depicts the 

areas of potential interference with television reception. 

82 See EPHC National Wind Farm Development Guidelines-Draft, July 2010 Appendix E3, page 150 83 Expert Witness Statement of Trenton Gilbert, GL Garrad Hassan, 18 June 2010

Page 99: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 97

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Figure 5 Lookout Hill broadcast transmitter and proposed Ararat Wind Farm showing areas potentially affected by television interference.

 

For comparison, the signal to noise ratio (SNR) predicted by the RES 

Interference Model is shown in Figure 6, adapted from figure 12 in the RES 

Electromagnetic Interference Assessment Report84. 

84 Application Documentation Volume 2, Electromagnetic interference report, RES Australia, 30

September 2009, page 19

Page 100: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 98

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Figure 6 Potential interference zones predicted by the RES Interference Model

 

The report states that “Based on existing evidence and model validation the 

threshold of SNR below which TV interference is unacceptable is set to 10 dB μV/m.” 

Page 101: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 99

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

The report makes the following assessment85: 

Table 4 Summary of SNR output from the RES Interference Model 

Transmitter SNR Description 

Estimate of 

Number of 

Properties 

Affected 

Houses 

Identified from 

Survey 

West of wind 

farm 

There is a small area of 

interference around Mt Boswell 

and south of the Pyrenees 

highway down to the Warrak 

road. 

4  AH3, AH5, 

AH6, AH53 

North of 

wind farm 

East of wind 

farm 

There are a few places east of the 

wind farm with a low SNR due 

to signals reflected back from the 

wind farm.  This is for a few 

houses around Crowlands and 

Eversley.  Due to the initially 

excellent reception this type of 

interference is very unlikely. 

South of 

wind farm 

There is an area of predicted 

interference running from Ararat 

Aerodrome to Mount Langi 

Ghiran. 

16  Beyond scope of 

habitation survey 

Total  16 

This assessment differs from Dr Gilbert’s assessment in that it predicts areas of 

potential interference south (and east) of the wind farm which are not covered 

in Dr Gilbert’s report. 

It is noted that Mr Randell’s property is one of those identified as potentially 

affected by EMI by both assessments.  In this regard, Mr Randell and Dr 

Gilbert are in agreement.  Mr Randell does not believe that the potential 

85 Ibid, table 7, page 18

Page 102: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 100

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

interference in the location is easily remedied and would be expensive to 

remedy. 

Dr Gilbert outlined a number of potential remedies for TV reception issues 

including installing high quality antennae and repositioning or reorienting the 

antenna.  In relation to how the extent to which EMI could be attributed to the 

wind farm, Dr Gilbert stated that this required pre and post construction 

measurements. 

10.4 CONCLUSIONS AND RECOMMENDATIONS

The Panel has considered the evidence provided by the proponent in relation 

to shadow flicker and blade glint.  It concurs with the expert evidence and 

concludes that: 

the amount of shadow flicker that could be potentially experienced at 

nearby dwellings will be well below the guideline limit of 30 hours per 

annum; and 

blade glint will not be experienced because of the use of non‐reflective 

coatings. 

In relation to electromagnetic interference with television and radio reception, 

the Panel notes the potential for this to occur at a number of locations.  The 

Panel accepts that mitigation measures are available to remedy reception 

problems should they arise and that the appropriate way to assess the amount 

of interference is via pre and post construction measurements.  However the 

practical experience of Mr Randell in this area, and his knowledge of previous 

problems from other wind farms, persuaded the Panel to the view that a wider 

range of properties than shown in Figure 5 above have the potential to be 

affected by reception problems after the wind farm is in operation.  This is 

evident from Figure 6 above which is very helpful in this regard.  Dr Gilbert 

was not able to assist the Panel further in this respect. 

Accordingly the Panel concludes that the following measures should be taken: 

advertisement by the proponent of Pre‐Construction surveys of existing 

signal strength, to dwellings as shown on Figure 5, and also to 

representative dwellings within 6 km of the line between Ararat and 

Lookout Hill as shown on Figure 5; 

preconstruction measurement of signal strengths and quality at locations 

where potential EMI has been predicted or is anticipated, or where 

owners of dwellings from within the area encompassed by Figure 5 and 

the area within 6 km of the line between Ararat and Lookout Hill request 

such measurements; 

Page 103: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 101

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

identification of actual deterioration of signal strengths or other reception 

problems by post wind farm operation monitoring; and 

remediation of identified reception problems at the proponent’s expense. 

The conclusion regarding Shadow Flicker has been incorporated into Permit 

Condition 9 of the Recommended Permit (Appendix E).  Regarding EMI, the 

conclusions have been incorporated in the Television and Radio Reception 

Plan in the Pre‐Construction Phase of the Recommended Environmental 

Management Plan. 

Page 104: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 102

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

11. SOIL AND WATER MANAGEMENT

11.1 WHAT IS THE ISSUE?

The potential for significant soil erosion arising from construction and 

operation of the Ararat WEF was flagged in the documentation on geology 

and hydrology.  The area has evidence of existing erosion, with the potential 

to exacerbate problems as a result of construction and operation of access 

tracks and hardstandings, on‐site tracks and turbine foundations.  This 

concern was clear during the site inspections conducted by the Panel, who 

noted the serious examples of gully erosion in the valleys in the vicinity of the 

proposed turbines and access routes. 

The Panel therefore addressed three issues: 

What are the potential soil erosion hazards on the site?; 

Are the on‐site access roads likely to be structurally sound?; and 

Are the proposals for minimising and managing the soil erosion hazards 

satisfactory? 

11.2 BACKGROUND

RES Australia relied on two main sources of information for its case relating to 

soil and water management: 

RES, Ararat Wind Farm Geology and Hydrology Assessment Report, 

August 2009; and 

Expert Witness Statement of David Tilley, Douglas Partners, relating to 

geology and hydrology. 

The August 2009 Geology and Hydrology Assessment Report prepared by 

RES outlined the preliminary geotechnical investigations that have been 

carried out on the subject site.  It described the geology and hydrology relating 

to the two river catchments within the site – the Wimmera flowing to the north 

of the site, and the Hopkins to the south. 

This report identified the significance of erosion, particularly in waterways 

(creeks in the Wimmera catchment are described as “deeply incised”, and in the 

Hopkins catchment as “displaying erosion that appears to be somewhat stabilised by 

reaching bedrock”86).  It cites a letter from the Glenelg‐Hopkins Catchment 

86 RES, Ararat Wind Farm: Geology and Hydrology Assessment Report, August 2009, pp. 6-7

Page 105: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 103

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Management Authority (GHCMA), referring to the soils in this land unit as 

“highly susceptible to dispersive behaviour and water erosion.  The solodic soils 

(Chromosols) are susceptible to erosion because they have large amounts of gravel, a 

poor structure and consistence, a tendency to surface sealing, and they are readily 

dispersed in water as colloidal suspensions.”87  The GHCMA pointed out that this 

characteristic was exacerbated by the highly seasonal and intermittent nature 

of rainfall, and the removal of remnant native vegetation, grazing and rabbits. 

The RES Geology and Hydrology Assessment Report and Mr Tilley’s evidence 

identified the potential for exacerbation of erosion problems as a result of 

construction and operation of on‐site access tracks, hardstanding areas, and 

turbine foundations. 

The internal site access roads involve cuts up to 10 metres and fills of up to 5 

metres in depth, judging by the preliminary track design plans.88 Batter slopes 

on the access roads are shown as 1½ horizontal to 1 vertical.  Construction 

mitigation measures for access tracks and hard‐standing89 include the 

identification of erosion prone areas, and avoidance of them where possible, 

and the use of gypsum stabilisation where dispersive soils are encountered. 

The guidelines for restoration works for borrow areas90 include that 

permanent batters be at no steeper slope than 2H:1V (preferably flatter) to permit 

soil placement for re‐vegetation.  The depths of cuts are generally less than 10 

metres, though some deeper possible extension areas are shown in dashed 

lines. 

Mr Tilley advised91 with respect to the on‐site roads that: 

If imported rock is required for the base course it is worth considering 

sealing these roads as a combination of trafficking and rain would lead to a 

loss of base course over time if the road is left unsealed.  This is especially 

important if grades of up to 18% are to be adopted and heavy loads will be 

accessing the site.  I am advised that RES has indicated that certain steep 

sections of road may have to be sealed and is included within the Planning 

Application (see Figure 2.2 Infrastructure Drawing in Volume III Figures 

and Photomontages of RES’ Planning Application). 

87 RES, Ararat Wind Farm: Geology and Hydrology Assessment Report, August 2009, p. 9 88 Ararat Wind Farm Planning Permit Application Documentation, 2009 Volume III, Figures 6.5 to

6.12 89 Ararat Wind Farm Planning Permit Application Documentation, 2009 Volume II, Geology and

Hydrology Assessment Report, page 11 90 Report on Proposed Borrow Areas Ararat Wind farm by Douglas Partners July 2009, page 11

attached to the Expert Witness Statement of David Tilley. 91 Expert Witness Statement by Mr Tilley, June 2010, page 5

Page 106: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 104

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

The August 2009 Geology and Hydrology Assessment Report proposed a 

number of recommendations aimed at mitigating and managing erosion, 

including: 

Turbine positions and tracks have been located to avoid watercourses and 

dams on‐site where possible, micros ting of turbines and infrastructure 

should be undertaken with reference to drainage paths and distance to 

watercourses. 

Any watercourse crossing required for the development should be properly 

designed and the potential for erosion as a result of the new crossings should 

be mitigated through design and construction practises. 

Some of the soils found on‐site, particularly north of the Pyrenees Highway 

and within existing gully areas, have a high potential for erosion.  

Waterways may be impacted indirectly through turbid run‐off from the 

subject site, however by instigation of the mitigation measures and further 

studies..., it is believed that the impact would be low.  

Through careful management during construction, impacts to surface water 

can also be avoided.  Increased runoff is anticipated from access tracks and 

hardstand areas but it is anticipated that this additional water will drain on‐

site. 

Potential surface water contamination is perceived to increase when 

temporary concrete batching plant/s are proposed for use during 

construction.  Careful consideration of the placement and management 

practices of any temporary concrete batching plant/s will need to occur. 

No water quality impacts are anticipated to be generated during the 

operational phase due to the minimal use of tracks during operation of the 

wind farm. 

Continuous water quality sampling at strategic locations during 

construction.92 

In his expert witness statement, Mr Tilley supported these recommendations.  

He summarised the design criteria to avoid and mitigate erosion problems 

from access tracks and on‐site tracks, which have the greatest potential to 

create soil and water management problems: 

minimise length of on‐site track and position where possible on ridge crest 

to minimise catchment areas above cuttings and filled areas. 

avoidance of water courses; 

avoid scouring caused by significant velocities by minimising collected 

water flows and designing low velocity swale drains; 

92 Expert Witness Statement by Mr Tilley, June 2010, page 13

Page 107: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 105

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

discharge run‐off regularly from table drains through turn out drains in to 

sheet flow across well vegetated ground so that it does not have direct access 

to drainage lines; 

protect batters with uphill catch drains; and 

intercept subsurface flows where these seep from cut batters, and direct flow 

with safety to the table drain.93 

He also supported care in siting of the turbines to avoid natural low points, 

continual maintenance of drainage systems and track hardstanding surfaces 

during construction, and fitting erosion and sediment control devices down‐

slope of construction sites.94 

11.3 EVIDENCE AND SUBMISSIONS

The potential impact of the Ararat WEF on soils and water management was 

raised in two submissions on the exhibited documents. 

The GHCMA outlined the need for Works on Waterways Permits for access 

tracks and electrical conduit crossings over at least six designated waterways.  

It noted that the use of box culverts for the crossings “can be supported”, but 

“will be treated on a case‐by‐case basis”.  It also considered that the proposed 

mitigation and management measures are generally sound, but that a number 

of issues should be addressed.  With regard to potential soil and water 

management, these included: 

Relocated excess excavated material should not impinge on the likely floodplain, 

and not change surface water flow patterns. 

Track‐side drains in areas of steep gradients and erodible soils will be highly 

susceptible to rilling and erosion until grass cover in the cut drains can be 

established.  It is recommended that a product such as jute mat be used in steep 

drain sections to stabilise drains and encourage establishment of grass cover. 

A buffer of 100 metres between temporary concrete batching plants and 

waterways should be applied to the site construction plans. 

The use of geotextile silt fences and straw bales is preferred over hay bales for 

control of erosion and sediment.  The use of hay bales may introduce weed 

species into pastures or native vegetation swards.95

93 Expert Witness Statement of David Tilley, Douglas Partners, relating to geology and hydrology, p. 6 94 ibid., p. 6 95 Glenelg Hopkins Catchment Management Authority Submission, 8 April 2010, p. 2

Page 108: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 106

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

GHCMA did not object to the granting of a Permit, subject to a series of Permit 

Conditions to address these matters.  These have been incorporated into the 

draft Permit considered by the Panel. 

Peter Woods was concerned about the impact of on‐site access roads on 

existing dams on his property: 

... as one of the properties contributing to the Hopkins River catchment, I 

have also concerns that any connecting roads constructed within the 

complex should not interfere with the existing contours for runoffs of 

water collection and existing dams that are already in place which would if 

altered, will reduce existing flows for the Hopkins River present catchment 

as it stands. 

In addition to the two submissions, a letter from the WCMA dated 16 March 

2009 was included as an Appendix to the RES Geology and Hydrology 

Assessment Report (August 2009).  It stated that the report “adequately covers 

the concerns of the Wimmera CMA in regards to Environmental Management 

during project”. 

On the second last day of the Hearing, Mr Power advised that the Panel 

should recommend that on‐site access tracks be three metres in width. 

11.4 DISCUSSION

11.4.1 Potential Erosion Hazards

The Panel’s first issue was ‘What are the potential soil erosion hazards on the site?’ 

There was unanimity from the proponent, the expert witness (Mr Tilley), 

agencies such as the GHCMA and the Panel that the area is highly prone to 

erosion hazards.  The very poor state of the gullies was witnessed by the Panel 

in its site inspections, and the potential for sheet erosion had also been 

identified by the GHCMA. 

Thus, the Panel concluded that the management of soil and water during 

infrastructure construction and operation is a high priority. 

11.4.2 Structural soundness of on-site access roads

The second issue identified by the Panel was: ‘Are the on‐site access roads likely 

to be structurally sound?’  Here, the Panel’s concern centres on the erosion 

prone nature of the site, as shown by the presence of widespread gully 

erosion.  With access road cuts of up to 10 metres in depth, and grades of up to 

18%, the potential for instability resulting from local scour of the cut or fill 

faces and at the toe of the fill, combined with the potential impacts from heavy 

vehicles that may have difficulty in getting purchase in wet conditions, may 

Page 109: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 107

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

constitute an unacceptable risk.  Certainly the suggestion that those parts of 

the site access roads with steeper slopes might be sealed needs further 

consideration. 

The guideline for borrow pit batters being no steeper than 2H:1V (see Section 

8.2 above) may be equally applied to both cut and fill batters on the on‐site 

access roads, enabling the batters to be more easily stabilised.  Where the 

depths of cuts and fills are small, the extra volume of earthworks would be 

small.  Where the depths of cuts and fills are greater, the need for stability is 

also greater. 

The issues of the specification for sealing the steeper grades on the on‐site 

access roads, and the application of a maximum batter slope of 2H:1V to these 

roads, need further expert advice during the Pre‐Construction design phase.  

The Panel concluded that, when the study findings have been considered by 

the Responsible Authority, the Construction Management Plan within the 

EMP can be amended to the satisfaction of Responsible Authority. 

In relation to Mr Power’s advice to the Panel that it should recommend that 

the on‐site access tracks be three metres in width, the Panel is not inclined to 

that view.  The Panel notes that the CFA’s Emergency Management Guidelines for 

Wind Farms addresses the issue of access to and within wind farms, and states 

“Constructed roads should be a minimum of four (4) metres in trafficable width with a 

four metre (4m) vertical clearance for the width of the formed road surface.”  Beyond 

the trafficable width (often referred to as the ‘pavement’), there needs to be 

shoulders provided each side to allow a safety margin for operational and 

maintenance reasons. 

The width of the on‐site tracks was addressed in Section 6.3.2 of the Main 

Report, as follows: 

Typical access tracks will be a maximum of 6m wide running surface, 

depending on topographic constraints, which will widen at junctions and 

turning areas. 

11.4.3 Mitigation and Management of Erosion

The Panel’s third issue was: ‘Are the proposals for minimising and managing the 

soil erosion hazards satisfactory?’ 

In his expert witness statement, Mr Tilley concluded that the key to 

minimising the impact of roads “is to reduce the accumulation and 

channelling of water by dispersing it back into the usual catchment system at 

as many points as possible”96.  The Panel supports this conclusion, and 

96 Expert Witness Statement of David Tilley, Douglas Partners, relating to geology and hydrology, p.3

Page 110: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 108

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

assessed whether the plans for minimising and mitigating the potential for 

erosion (including impacts of construction and operation of all infrastructure) 

achieved this. 

Thus, the Panel reviewed the Conditions relating to soil and water 

management in the proposed Planning Permit, particularly the details of the 

Sediment, Erosion and Water Quality Management Plan required as part of 

the Environmental Management Plan. 

The Conditions of the proposed Permit largely reflect the DPCD Model 

Planning Permit Conditions for Wind Energy Facilities97, particularly the 

Conditions relating to the Sediment, Erosion and Water Quality Management 

Plan within the required EMP.  These Conditions outline the detailed 

requirements of the Sediment, Erosion and Water Quality Management Plan, 

providing details of the procedures for minimising land disturbance and the 

potential for erosion.  The Plan must be prepared in consultation with the 

relevant Catchment Management Authorities (and other authorities as may be 

directed by the Minister for Planning), and be approved by the Minister for 

Planning. 

As detailed in Appendix C, the Panel workshop version of the proposed 

Permit proposed a number of modifications to the Model Conditions.  Under 

the heading of Environmental Management Plan, it included the addition of a 

requirement for planning to “consider and generally be in accordance with” a 

series of EPA Guidelines and Codes of Practice relating to construction.  It also 

proposed the following addition to the Sediment, Erosion and Water Quality 

Management Plan, noting that it must include: 

(xiv) Management procedures to prevent pollution of the local waterways, 

particularly from wash water and waste concrete materials. 

The Panel noted the responses of the Glenelg Hopkins and Wimmera 

Catchment Management Authorities to the exhibited documentation that the 

proposed mitigation measures were sound, subject to some refinements 

described by the GHCMA. 

The Panel considered the refinements proposed by the GHCMA in the 

Sediment, Erosion and Water Quality Management Plan, specifically those 

relating to relocation of excess excavated material, use of a product such as 

jute mat in steep drain sections, inclusion of a buffer of 100 metres between 

temporary concrete batching plants and waterways, and the use of geotextile 

silt fences and straw bales rather than hay bales for control of erosion and 

sediment.  It concluded that these changes can be incorporated into the 

97 DPCD, Model Planning Permit Conditions for Wind Energy Facilities, February 2009, pp. 9-10

Page 111: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 109

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Sediment, Erosion and Water Quality Management Plan in the EMP, as 

detailed in Appendix F. 

The proposed EMP describes the techniques outlined in Chapters 4 to 7 of the 

August 2009 Geology and Hydrology Assessment Report, all aimed at 

achieving the requirements of the Permit Conditions.  The Panel concluded 

that these were consistent with the more general requirements described in the 

Permit Conditions. 

The Panel reviewed the details of the EMP following the Panel workshop, and 

concluded that some simplification was desirable.  In his expert witness 

statement, Mr Tilley concluded that the existing water flows into the Hopkins 

and Wimmera catchments “will be appropriately managed by a Soil and 

Water Management Plan within a future Environmental Management Plan to 

ensure the maintenance of the ongoing surface water flow patterns”98.  This in 

turn led to the proposed inclusion of a Soil and Water Management Plan 

within the Sediment, Erosion and Water Quality Management Plan, within the 

Environmental Management Plan.  The Panel considered that a separate Soil 

and Water Management Plan added too much complexity.  Its requirements 

would be covered in the Sediment, Erosion and Water Quality Management 

Plan, so reference to it in the EMP should be removed. 

The Panel was disappointed with the extent of soil erosion and the state of 

waterways at the site.  The planning system provides an excellent opportunity 

to avoid and mitigate future damage which may occur with the proposed 

Ararat WEF, and the Panel is confident that the measures that are proposed 

will achieve this.  However, there is a limit to the capacity of a Planning 

Permit application to address past damage.  This will be an ongoing challenge 

for landholders and organisations such as Landcare and the Catchment 

Management Authorities, and it is a challenge that the Ararat WEF proponent 

should also embrace. 

11.5 CONCLUSIONS

The Panel concluded that soil and water management issues are highly 

significant at this site, and have been generally addressed in the 

documentation to date.  Those parts of the Draft Permit (Appendix C) and the 

“Environmental Management Plan emailed by the Proponent” (Appendix D) 

that relate to the Sediment, Erosion and Water Quality Management Plan have 

been refined.  In their amended form, they are set out in Appendix E (the 

‘Recommended Permit’) and in Appendix F (the ‘Recommended 

Environmental Management Plan at the Pre‐Construction Stage’). 

98 Expert Witness Statement of David Tilley, Douglas Partners, relating to geology & hydrology, p 6-7

Page 112: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 110

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

12. SOCIAL AND ECONOMIC

12.1 WHAT IS THE ISSUE?

A variety of social and economic issues were raised in the application and 

submissions, and at the hearings.  These included: 

results of perception studies relating to wind farms; 

the quality of the consultation process conducted by the proponent; 

planning to minimise social disruption, particularly during the 

construction phase; 

potential damage to agriculture and the local tourism industry; 

maximising local economic benefits; and 

the contribution to sustainable energy generation. 

12.2 BACKGROUND

12.2.1 The Proponent’s Approach

With regard to social and economic issues, RES Australia relied on the 

information in its application, and provided little additional information at the 

Panel hearing.  Issues relating to the quality of the consultation process and 

the impacts of the proposal on the tourism industry were raised by some 

submitters, but were not explored in detail at the hearings. 

To a large degree, this reflected the relative lack of controversy associated with 

this wind farm proposal.  The majority of any community concerns relating to 

social and economic issues appear to have been flagged, considered and 

largely resolved in the pre‐application and application stages, leaving few 

matters of conflict at the Panel hearings. 

12.2.2 Results of Perception Studies

RES Australia relied on the results of perception studies conducted in Ararat99, 

other areas of Victoria and elsewhere gain an understanding of public 

opinions about wind farms.  It argued that the studies show that there was 

considerable community support for wind farms. 

99 ERM Pty Ltd and Reark Pty Ltd., Report on Community Perceptions towards Wind Farms in the

Ararat Region, Victoria, May 2008

Page 113: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 111

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Broadly, the studies showed that the large majority of respondents accepted 

that there was a concern about the threat of global warming, and that “[w]e 

need to use wind power as a source of clean energy even if it means changing 

the appearance of some landscapes”100.  Further, in the Ararat study: 

...when respondents were asked about the acceptability of a wind farm near 

where they lived, 83% supported a wind farm located 25 kilometres from 

home and 71% of respondents supported a wind farm within one kilometre 

of their home.101 

RES Australia stated that the results of these studies encouraged it to commit 

to the Ararat project. 

12.2.3 The Consultation Process

The consultation process adopted by RES Australia is described in its 

application102.  A range of State, Australian and local government agencies, 

local residents, identified stakeholders and the media were consulted.  

Consultation techniques included: 

... letters, e‐mails, letter‐box drops, home visits by RES representatives to 

all residents within a 3km radius, press releases, newspaper 

advertisements, radio interviews, meetings with Local Council officers, 

providing Councillors’ Briefing Sessions at Ararat Rural City Council and 

Northern Grampians Shire Council, meetings with government 

departments (DPCD, DSE, Sustainability Victoria), and landowners and 

will continue with respect to the re‐notification of this Referral Form 

application for the increased turbine numbers. RES Australia has also 

established an internet website (www.res‐australia.com.au) to publish 

regular updates, to keep interested parties informed of any developments 

on the proposal and to receive any comments.103 

The application states that RES Australia is committed to maintaining ongoing 

dialogue with the local communities, and describes a mix of information 

sharing processes aiming to achieve this. 

In his submission to the Panel, Mr Power argued that the lack of controversy 

and opposition relating to the Ararat WEF reflected the results of this 

consultation: 

100 RES Australia, Ararat Wind Farm Planning Permit Application Documentation, 2009 Volume 1,

p.21 101 ibid., p. 21 102 ibid., Chapter 5, Stakeholder Consultations & Community Engagement 103 ibid., p. 62

Page 114: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 112

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

...some wind energy facilities have attracted significant community 

opposition.  This proposal has not.  It is submitted that the small number 

of submissions and the limited issues raised in those submissions are 

indicative of the sensitive site‐responsive design of the proposed Ararat 

Wind Farm and of the strength of the local community support for the 

development of renewable energy projects in this region.104  

12.2.4 Minimising Social Disruption

The issue of managing potential disruption from the influx of construction 

workers to the area was not addressed in the application documents, or in 

submissions to the Panel by RES Australia.  Under “Community Impacts”, the 

application referred to “understanding the potential for community benefits; 

and mitigating against any potential adverse impacts upon the surrounding 

residents”105..  Nevertheless, it did not quantify the impact or explore methods 

to minimise disruption and maximise benefits. 

12.2.5 Impacts on Agriculture and the Tourism Industry

In its application, RES Australia stated that there would be economic benefits 

to the regional economy as a result of the establishment and operation of the 

facility. 

It considered that the facility will provide additional revenue to participating 

farmers, helping to “sustain the economic viability of the estate or farm 

business”106.  In its concluding submission to the Panel, it argued that the 

facility “will enable the existing agricultural activities that occur on the site 

and adjoining land to continue in a manner that will support the long term 

sustainable use of the land”.107 

With regard to tourism, it considered likely that tourism will not be adversely 

affected by the construction of the Ararat Wind Farm: 

The Ararat Wind Farm will become a feature of the area, and is likely to 

attract interest from locals and visitors alike.  Given the potential for local 

and visitor interest in the wind farm, RES Australia, in consultation with 

Ararat Rural City Council (ARCC) and Northern Grampians Shire 

104 RES Australia, Part A submission, 5 July 2010, Section 2.4 105 RES Australia, Ararat Wind Farm Planning Permit Application Documentation, 2009 Volume 1,

p66 106 ibid., p. 192 107 RES Australia, Part B submission, 21 July 2010, p. 4

Page 115: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 113

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Council (NGSC) may provide resources such as information boards and 

other interpretative material.108 

12.2.6 Maximising Local Economic Benefits

In its application, RES Australia argued that there would be net economic 

benefits to the local economy as a result of the facility. 

Construction and operation of the proposed Ararat Wind Farm will have a 

positive effect on the local economy, in terms of local employment during 

the construction phase, and also in the longer term from the landowner 

rentals, business rates, local services, and employment of operation and 

maintenance staff.  Demand for wind turbines and wind farms will help 

establish inward investment into the Ararat and Northern Grampians 

regions and also create long term skilled employment opportunities to 

serve the ongoing operational and maintenance requirements of the wind 

farm.109 (p. 192) 

In order to maximise local benefits, RES Australia proposed active policies to 

source goods and services locally.  It stated that its policy: 

... is to ensure that wherever possible local contractors and employees are 

used in all aspects of wind farm development.  The major opportunity lies 

during the construction phase when suitably qualified local firms are 

identified and invited to bid for a significant portion of the civil 

construction work, on roads, foundations and buildings.  Construction 

materials are normally sourced locally and local transport and plant hire 

companies used wherever possible.  During construction of the Ararat 

Wind Farm a temporary workforce will be required during the 26 month 

construction stage. 

It is anticipated that much of these construction jobs will be sourced 

locally.  The wind farm will also create permanent jobs relating to 

operation and maintenance of the wind farm.110 

Further, it indicated the direct benefit to Ararat and Northern Grampians 

Shire Councils.  Payments to the Councils under Section 94(5) of the Electricity 

Industry Act 2000 would be an aggregate of $175,000 (for 2 MW turbines) or 

$262,750 (for 3.3 MW turbines), distributed proportionally between the 

Councils.111 

108 RES Australia, Ararat Wind Farm Planning Permit Application Documentation, 2009 Volume 1, p.

193 109 ibid, p. 192 110 ibid., pp. 191-92 111 ibid., p. 192

Page 116: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 114

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

12.2.7 Sustainable Energy

The issue of the contribution of wind energy to the environmental 

sustainability of energy supply has been a feature of other Panels considering 

wind farms in Victoria, but was not questioned in the case of the proposed 

Ararat WEF. 

RES Australia submitted that the facility will: 

...  deliver a number of benefits, such as providing a new source of 

electricity generation that utilises an infinite and sustainable resource, 

thereby assisting Victoria to meet its energy requirements and assisting 

the Commonwealth and State Governments achieve their key policy 

objectives for climate change.112 

12.3 EVIDENCE AND SUBMISSIONS

12.3.1 The Nature of Submissions

Not all of the social and economic issues raised in the RES Australia 

application and at the Panel hearings were addressed in the submissions.  

However, several of the issues were raised by individuals or agencies. 

12.3.2 The Consultation Process

In their submission to the application, W J and L O Stewien criticised the 

response by RES Australia to communications from them and their legal 

representatives.  At the hearing, Mrs Stewien expanded on her concerns, 

explaining that she was critical of the timing and content of responses to 

queries raised with RES Australia by their legal representatives. 

12.3.3 Impacts on Agriculture and the Tourism Industry

In their written submission on the exhibited application, Paul and Wendy 

Harrington stated that they had “disinterest” in proposals from RES Australia 

to place turbines on their property: 

We do not wish to lose productive agricultural land to the installation and 

permanent placements of these units.  There are also the added risks 

associated with overhead powerlines situated where machinery operations 

are part of the business practices.  Losing an easement through the 

property and providing permanent access to that easement to another 

entity is a position we wish to avoid.113 

112 RES Australia, Part B submission, 21 July 2010, p. 4 113 Submission 10

Page 117: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 115

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

K J Wilde expressed concern that his farming property in the Eversley area 

operates under biosecurity constraints, and any vehicles entering it would be 

required to be steam cleaned to avoid introduction of seed.  Further, he 

considered that paddocks can be boggy in winter, and unsuitable for vehicles.  

The Panel notes that Mr Wilde’s submission related to the grid connection, 

which is not part of the proposal (see Section 4.2.1 above). 

With regard to tourism, W J and L O Stewien considered that: 

The towers will diminish (not enhance) the tourist potential of a 

significant and developing wine growing area.  The vineyards throughout 

the area and Mt Langi and Ben Nevis will be detracted by such towers.  It 

is noted that the projected tourist potential for the Challicum Hills Wind 

farm has not been forthcoming. 

DSE referred to the importance of the regional tourism industry in its 

submission on the exhibited application.  It considered that tourism 

significance should impact on the overall visual landscape ratings, specifically 

for Viewpoint 6, and this matter is considered in Chapter 7 above. 

12.3.4 Maximising Local Economic Benefits

A submission on the exhibited application was received from Mr Andrew 

Bradley of the Grampians Office of the Industry Capability Network (ICN).  

He outlined the role of ICN in supporting Australian industry, specifically 

including the facilitation of local industry participation in major projects. 

The submission described some of the potential local benefits of the project, 

including accommodation, catering, fencing, earthworks, onsite consumables 

such as office equipment, cleaning, safety equipment, vehicle hire, fuel 

supplies and the day to day usage of building materials.  It estimated that 

$40m of the total project cost of $350m would be spent within the region114. 

Mr Bradley submitted that ICN had been working closely with RES Australia 

“to ensure that any business or individual who has expressed an interest in 

working on this project are given the opportunity to have their details 

presented to prospective tenderers.”115 

Cheryl and Gerald Shea’s submission on the exhibited application supported 

the proposal.  They considered that: 

The employment opportunities will help to keep our town thriving and 

keep young people in the town rather than moving into the city looking for 

114 Industry Capability Network submission on the application, Submission 4, 30 March 2010, p. 2 115 ibid., p. 1

Page 118: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 116

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

employment.  This will benefit the football, cricket and other sporting clubs 

which are the heart & soul of all country towns.116 

12.3.5 Sustainable Energy

Sustainability Victoria provided a submission on the exhibited application, 

describing the Victorian Government policy support for wind energy, and 

estimating the greenhouse gas abatement outcomes from the proposed Ararat 

WEF.  Based on a capacity factor of 35%, Sustainability Victoria estimated that 

the facility would reduce Victoria’s carbon dioxide equivalent emissions by 

483,000 tonnes if 2 megawatt turbines are installed, or 797,000 tonnes if 3.3 

megawatt turbines are used.117 

Cheryl and Gerald Shea’s submission on the exhibited application noted that 

“while the wind power is probably not the whole solution it is certainly going 

to make a huge contribution to clean, green energy”.  This was supported by 

Mark A McKew, who stated that “our reliance on the ‘dirty’ coal industry 

must be scaled back, and a range of renewable energy systems encouraged”.  

Ararat Rural City Council’s submission referred to its support for the concept 

of renewable energy, and added that the municipality is “centrally located to 

take advantage of elements of the wind industry”. 

12.4 DISCUSSION

12.4.1 Results of Perception Studies

The perception studies conducted for RES Australia were not considered in 

depth at the Panel hearing.  They were not represented as providing more 

than background information that assisted the company in its decision to site 

its facility in Ararat, while the data on community support and opposition to 

wind energy was broadly consistent with other studies118.  The data showed 

that the majority of respondents supported the concept of wind energy 

generally, and a wind energy facility near Ararat in particular. 

The text quoted in Section 11.2.2 above cited from the Main Report does not 

appear to accurately represent the Report on Community Perceptions towards 

Wind Farms in the Ararat Region.  The responses to Question 3.3.10 refers to 

responses on the question about “A Wind Farm One Kilometre from Home”.  

116 Submission 5 by Cheryl and Gerald Shea, 2 April 2010 117 Submission 6 by Sustainability Victoria, 29 March 2010, p. 6 118 ERM Pty Ltd and Reark Pty Ltd, Report on Community Perceptions towards Wind Farms in the

Ararat Region, Victoria, May 2008, pp 5-15

Page 119: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 117

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

The Conclusion of the study119 makes clear that the 71% in favour are 

“accepting a wind farm set 1 kilometre from their home”, not within one 

kilometre of their home.  The error in the Main Report quotation probably 

comes from using the inaccurate paraphrasing of Question 15 in Figure 4.2. 

The Panel has criticised the Perception study undertaken for Ararat in Section 

7.4.1 above, in relation to the factually wrong statement about noise. 

While the results were of interest to the Panel, they were relevant to its 

considerations to a limited extent, as detailed in Chapter 7.  The task of the 

Panel is to assess the planning merits of the application and ensure that the 

conditions under which it may proceed ensure maximum net community 

benefit. 

12.4.2 The Consultation Process

The Panel was impressed with the consultation processes adopted by RES 

Australia to date.  It agreed with Mr Power that the lack of opposition to the 

proposal reflects effective engagement processes, avoiding the potential for 

community opposition based on misunderstandings. 

Clearly, the engagement processes will need to continue to be extensive and 

creative if the proponent is to maintain its community support. 

12.4.3 Minimising Social Disruption

The main report of the RES Australia application states that the construction 

workforce is likely to be around 180, comprising 80 involved with civil works, 

50 with electrical works, and 50 others involved with wind turbine works.  

These employment opportunities are described as being available for 

“residents and itinerant workers”120.  The operational workforce will be small: 

It is anticipated that for a 75 turbine development approximately two 

maintenance teams each consisting of two Specialist Service Technicians 

in each team will be required to service the turbines at specified intervals.  

There may also be a requirement for larger on‐site crews for major routine 

maintenance works.121 

119 ERM Pty Ltd and Reark Pty Ltd, Report on Community Perceptions towards Wind Farms in the

Ararat Region, Victoria, May 2008, page 65 120 RES Australia, Ararat Wind Farm Planning Permit Application Documentation, 2009 Volume 1,

p98 121 ibid., p. 99

Page 120: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 118

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

It is therefore likely that the facility would provide jobs for existing residents, 

but it is also probable that there will be some influx of construction workforce 

for the period of construction. 

The Panel was not convinced that the potential impacts of the influx of the 

construction workforce had been adequately addressed in the analysis to date.  

Australian Bureau of Statistics (ABS) census data show a population of 11,065 

in 5,102 dwellings in Ararat Rural City, and a population of 7,680 in 3,435 

dwellings in the town of Ararat at the 2006 census122.  The Panel considered 

that it is possible that a short‐term influx will be able to be managed without 

the need for a construction camp, but there is insufficient information for it to 

be certain that this will be the case123.  The project has achieved well‐earned 

community support to date, and this should not be risked through inadequate 

social planning. 

The Panel concluded that there is merit in requiring an assessment of the 

capacity of the area to cope with the accommodation requirements of the 

construction workforce, and a plan to ensure that this is achieved without 

significant disruption and without the need for separate construction camps.  

The use of such camps is unlikely to provide workers with any sense of being 

part of the wider community, and can have negative social consequences.  The 

Panel does not consider that the numbers involved in construction and 

operation of the wind energy facility requires a full‐blown Social Impact 

Assessment, but a study conducted in consultation with Ararat Rural City 

Council and Northern Grampians Shire Council and local community and real 

estate interests should provide a satisfactory plan for managing the 

accommodation impacts of the temporary surge in the construction workforce. 

12.4.4 Impacts on Agriculture and the Tourism Industry

The Panel did not consider that there was any evidence to suggest that the 

proposed facility would have negative impacts on agriculture or the tourism 

industry in the area.  Nor did it consider that there were likely to be 

substantial positive effects – additional income for participating farmers 

would have minor secondary benefits for farming operations, but would not 

fundamentally change the viability of agriculture.  The tourism benefits of the 

wind farm would be small, particularly as wind farms become more 

numerous throughout Victoria. 

122 ABS 2006 Census data, from Ararat Rural City Council website 123 The issue of the social impacts of a construction workforce were also addressed in the much larger

Wonthaggi desalination plant, see Report of the Inquiry, Victorian Desalination Project, Environment Effects Statement, 4 December 2008, pp. 76-79

Page 121: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 119

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

The Panel concluded that the concerns of Paul and Wendy Harrington 

regarding the impact of the facility on their farming operations were unlikely 

to be major.  The proposed Environmental Management Plan addresses 

farming matters such as fencing, weed control and pest animal control, which 

will ensure that any potential negative impacts are managed. 

12.4.5 Maximising Local Economic Benefits

The Panel supports the intent of the proponent to ensure that the local and 

regional economies achieve a substantial share of the economic benefits of the 

project.  It proposes that RES Australia continues to work with the Industry 

Capability Network and local economic development bodies to investigate 

further ways to maximise local input. 

12.4.6 Sustainable Energy

The issue of the contribution of wind energy to the sustainability of Victoria’s 

electricity industry was not contested in submissions or at the Panel hearings. 

The Panel considered the purpose of Clause 52.32: Wind Energy Facility of 

Planning Schemes, which is “To facilitate the establishment and expansion of 

wind energy facilities, in appropriate locations, with minimal impact on the 

amenity of the area”.  Further, Clause 52.32 references the VWEG, which 

clearly describe the Government’s commitment to reducing greenhouse gas 

emissions, and the role that wind energy plays in achieving this reduction. 

The Panel also accepted the case presented by Sustainability Victoria that the 

proposed Ararat facility would deliver significant greenhouse gas savings.  It 

concluded that the proposal would contribute to a more sustainable energy 

supply in Victoria. 

12.5 CONCLUSIONS

The Panel reached a number of conclusions relating to social and economic 

matters: 

Despite some objections, there appears to be substantial local support for 

the project, partly reflecting the support of Ararat Rural City Council for 

renewable energy development, the strengths of the site and the project, 

and an effective community engagement process that resulted in few 

objections based on misunderstandings. 

The project is likely to provide local economic benefits, but these will 

only be delivered if the proponent continues to work with local and 

regional economic development bodies with a program to maximise local 

Page 122: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 120

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

benefits.  Fears regarding the impact of the project on local agriculture 

and tourism are not supported by the evidence. 

The social impacts of the influx of the construction workforce have not 

been adequately assessed to date.  These are likely to be manageable, but 

require more serious analysis than has been provided to date.  At 

minimum, an analysis of appropriate management of accommodation for 

the construction workforce is required. 

The project will contribute to more sustainable electricity supply in 

Victoria. 

The Panel concluded that an additional plan should be added to the list of 

plans under Condition 7 of the Recommended Planning Permit (a construction 

workforce accommodation assessment), requiring an assessment of the 

capacity of the area to cope with the accommodation requirements of the 

construction workforce, and a plan to ensure that this is achieved without 

significant disruption and without the need for separate construction camps.  

The detail of the assessment is included in the Pre‐Construction Phase of the 

Environmental Management Plan. 

Page 123: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 121

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

13. ABORIGINAL CULTURAL HERITAGE

13.1 THE ISSUES

No submissions were received concerning Aboriginal cultural heritage.  The 

only issue that the Panel wished to explore was the commitment of RES 

Australia to complete the Complex Assessment and the Cultural Heritage 

Management Plan (CHMP), given that the preparation of the CHMP has been 

undertaken voluntarily by RES Australia. 

13.2 BACKGROUND

The Aboriginal cultural heritage standard assessment124 sets out when a 

CHMP is required, namely when all or part of an activity is in an area of 

cultural heritage significance, and the activity is a high impact activity.  While 

a WEF is defined as a high impact activity, the Ararat WEF is not in an area of 

cultural significance. 

Nevertheless, RES Australia has commenced the preparation of a voluntary 

CHMP with the first step being a Desktop Assessment.  That assessment 

found that it is reasonably possible that Aboriginal cultural heritage is present 

in the activity area.  As a consequence, the next step was the preparation of a 

Standard Assessment.  The Standard Assessment involved a cultural heritage 

site survey of some six days in duration.  The recommendations of the 

Standard Assessment are: 

the need for a Complex Assessment; 

the need for specialist assessment of the quart outcrops and eroding 

quartz fragments; 

the need for subsurface testing; and 

an estimate of the likely fieldwork duration and Registered Aboriginal 

Parties representation. 

124 Application Documentation Volume II, Aboriginal Cultural Heritage Standard Assessment, prepared

by Dr Tom Rymer of Tardis Enterprises Pty Ltd, July 2009

Page 124: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 122

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

13.3 DISCUSSION

In the Part B submission by Mr Power to the Hearing125, Section 10.1 

Aboriginal cultural heritage, states in part in sub‐section (c) that RES Australia 

engaged Tardis Enterprises Pty Ltd to prepare a voluntary CHMP.  Further, 

sub‐section (d) documents the commitment of RES Australia  Pty Ltd  to 

undertake the Complex Assessment as part of the voluntary CHMP. 

The modified EMP tabled by Mr Power on the last day of the Hearings 

included the recommendations of the Standard Assessment in full126.  The only 

matter not covered in the modified EMP is the commitment to complete the 

voluntary CHMP, which is clearly the intention of RES Australia Pty Ltd. 

13.4 CONCLUSIONS

The Panel concludes that commitment by the developer to complete the 

voluntary CHMP needs to be documented.  Provision for this matter is made 

in the Recommended Environmental Management Plan (see Appendix F), 

which enshrines it as a requirement for the project. 

125 Submissions on behalf of RES Australia Pty Ltd – Part B, Document 18 at the Hearing, page 32 126 Environmental Management Plan (mitigation, monitoring, enforcement and rehabilitation),

Document 28 at the Hearing, page 6

Page 125: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 123

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

14. ADMINISTRATION AND ENFORCEMENT

14.1 ISSUES

The advice from DPCD concerning WEF’s where the Minister determines the 

application is that ongoing administration and enforcement on the WEF is to 

be undertaken by Councils acting as Responsible Authorities. 

The issue for the Panel is to decide whether that advice is compelling. 

14.2 BACKGROUND

In making the opening submission on behalf of DPCD (for the Minister for 

Planning), Ms Grace‐Davis referred to the submission from ARC Council, 

which raised concerns about responsibilities for enforcement of any planning 

permit issued for the wind energy facility. 

Ms Grace‐Davis advised the Panel that ARC and NGS councils would be the 

responsible authorities for the administration and enforcement of the planning 

permits pursuant to Section 13(a) of the Planning and Environment Act 1987 

and the schedule to clause 61.01 of the planning schemes. 

The schedule to clause 61.01 provides that the Minister for Planning is the 

responsible authority for considering and determining applications and for 

approving matters required by the scheme to be done to the satisfaction of the 

responsible authority in relation to the use and development of land for the 

purpose of a wind energy facility with a capacity greater than 30 megawatts. 

The Schedule to Clause 61.01 in the Ararat Planning Scheme states: 

The Minister for Planning is the responsible authority for considering and 

determining applications, in accordance with Divisions 1, 1A, 2, and 3 of 

Part 4 of the Planning and Environment Act 1987 and for approving 

matters required by the scheme to be done to the satisfaction of the 

responsible authority in relation to: 

The use and development of land for the purpose of a Wind energy 

facility with a capacity of 30 megawatts or greater. 

The use and development of land for accommodation to which clause 

52.41 of the scheme applies. 

Page 126: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 124

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

The Minister for Planning is the responsible authority for approving 

matters required to be done to the satisfaction of the responsible authority 

under clause 52.40 of the Scheme. 

The Council of the Rural City of Ararat is the responsible authority for 

administering and enforcing the scheme for all other matters. 

The Panel notes that Section 52.40 contains provisions relating to government 

funded education facilities, while Section 52.41 contains provisions relating to 

government funded social housing.  These matters do not apply to the WEF. 

14.3 SUBMISSIONS

Submissions on administration and enforcement were made by ARC Council, 

the PS Council and the proponent (Mr Power for RES). 

The ARCC submission included a lengthy review of issues concerned with 

administration and enforcement. 

The issues of concern to ARCC include: 

whether any permit is issued with appropriate tools to quickly address 

community concerns; 

during the time between approval and construction, owners of farming 

lots greater than 40 ha (for which no planning approval is required for 

the construction of a dwelling) may be unaware of the Ararat WEF being 

located in the area; 

cross boundary issues, with the potential for a complainant to have 

difficulty in understanding to which authority the complaint should be 

addressed; 

arguments between authorities about the location of a particular breach, 

and arguments between authorities about the substance and merits of 

any complaint; 

a changing view by the Minister about the general issue of 

administration and enforcement.  Whereas the Minister has maintained 

these roles for some earlier WEF where call‐in powers were used (Mt 

Mercer was cited), the practice of late has been to nominate Councils as 

the administrator and enforcement authority in the Planning Permit 

preamble; 

when the permit preamble nominates Councils as the administrator and 

enforcement authority, there are usually a number of matters in the 

permit conditions that require the Minister’s, and or others satisfaction.  

Would Council be able to amend plans that have been approved by the 

Minister?; 

Page 127: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 125

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

the planning system does not facilitate a clear understanding of the roles 

and responsibilities of the Minister and or Council as their Responsible 

Authority functions cut across each other in the detail of the planning 

permit in a seemingly ambiguous manner; and 

the VWEG127 do not resolve the complexity and confusion about the 

enforcement issue. 

The ARCC referred to the recent discussions between the Municipal 

Association of Victoria (MAV), Councils and the Minister for Planning, with a 

view to resolving a range of issues.  A cooperative approach, making better 

use of resources, has some considerable support.  The ARCC submission 

provided extensive material about the discussions between the Minister for 

Planning, MAV and Councils, and a legal opinion on the issue of 

responsibility for administration and enforcement, in Appendices attached to 

its submission. 

In conclusion the ARCC submission requested that the Panel be cognisant of 

the Minister’s position on Planning Enforcement issues and its relationship to 

permit processes and conditions, but also to be aware of the proposed process 

changes being discussed with the Minister for Planning. 

The Pyrenees Shire Council made a submission following the exhibition of the 

Application Documentation which raised only the matter of the 

incompleteness of the application as it did not incorporate the connection to 

the grid (see Section 4.3.1 above).  Following the Hearing, the Pyrenees Shire 

Council emailed a further detailed submission which addressed the issue of 

the enforcement of permit conditions, setback of wind turbines from adjoining 

properties, aviation lighting and secondary consent.  While relevant to the 

discussion, the Panel has already considered the issues raised, and does not 

rely on the material presented by the Pyrenees Shire Council which was 

submitted after the Panel Hearing had concluded. 

A submission relevant to the enforcement issue from Mr Power was requested 

by the Panel during the Hearing.  In the event, it was received by the Panel on 

30 July 2010.  It is noted in Appendix B. Mr Power considered the matters 

relevant to WEFs of 30 MW or greater, and to those less than 30MW. 

Mr Power advised that the Victorian Environment and Natural Resources 

Committee of the Victorian Parliament had recognised the enforcement issue, 

and had recommended that “The Minister for Planning be the Responsible 

Authority for all commercial wind energy facilities”. 

127 Policy and Planning Guidelines for development of wind energy facilities in Victoria, September

2009, page 34

Page 128: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 126

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Mr Power then proceeded to clearly set out that, for WEF greater than 30 MW, 

while Section 61.01 of all Victorian Planning Schemes specifies (in part) “The 

(relevant) Council …is the responsible authority for administering and enforcing the 

scheme for all other matters.”, this provision relies on Section 13 of the Planning 

and Environment Act.  However Section 97A defines the party that is the “first 

responsible authority”, and Mr Power’s submission sets out why this is in fact 

the Minister.  Section 97H then applies once a permit is issued under Section 

97F, and Section 97H states “The first responsible authority becomes the responsible 

authority for the administration and enforcement of this Act and the relevant 

planning scheme in respect f the permit…” 

Mr Power addressed this apparent inconsistency, and relied on the relevant 

statutory rules to provide his opinion as to which clause of the Planning and 

Environment Act should prevail.  The rules state that specific clauses take 

precedent over general clauses, and that a provision inserted later in time is to 

be preferred if conflict arises with another part of the Act.  Section 97H is both 

a specific condition, and was inserted into the Act in 1993, while Section 13 is 

part of the original Act.  The result is that Mr Power’s advice is that for the 

Ararat WEF application, the Minister is the Responsible Authority for that part 

of the WEF within the ARC. 

In the case of that part of the Ararat WEF within the NGS, Section 61.01 does 

not apply.  In such cases the Council is the first responsible authority, and is 

thus the Responsible Authority under Section 97H of the Planning and 

Environment Act, except that the Minister remains the responsible authority in 

respect of: 

(a)  any matters which the permit specifies to be done by, approved 

by or done to the satisfaction of the Minister; 

(c)  any extension of time under section 69 in relation to the permit; 

(d)  the correction of the permit under section 71(1); 

14.4 DISCUSSION

The Panel notes that no final binding arrangement has emerged at the time of 

writing this report as a result of the discussion between the Minister for 

Planning, the MAV and Councils. 

The advice by Mr Power is the only legal advice put to the Panel, and would 

normally be given considerable weight.  However it has not been tested, as the 

Panel understands the situation, and remains an opinion about how the Act 

should be interpreted.  Further, it is contrary to the advice from DPCD, acting 

for the Minister.  The Panel can only conclude that the Minister concurs with 

the advice given on this important issue by his Department. 

Page 129: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 127

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

In the event, the position set out by DPCD was, to a very large extent, 

reluctantly acceded to by Councils in the without prejudice discussion of the 

potential Planning Permit conditions.  In doing this, the Councils did not resile 

from concern with the ongoing difficulties for administration and enforcement 

detailed in the submission from the ARCC. 

As a result of the considerations above, the Panel considers that the use of the 

word “Minister for Planning” is preferable to “Responsible Authority” for 

conditions that stipulate consideration by the Minister, for both permits. 

Concerning the potential difficulties that may arise about confusion as to 

which Council a person should contact if a breach of the permit conditions 

occurs, the Panel considers that the co‐operative arrangements between the 

two Councils discussed by them at the Hearing have much merit. 

The Panel anticipates that some further resolution of the difficulties 

enumerated by the ARCC (and others) may be forthcoming when the high 

level discussions are concluded and some form of agreement is reached. 

14.5 CONCLUSIONS

Given the high level discussions between the Minister, MAV and Councils 

that have not to date been concluded, and that there has been no court case to 

resolve the apparent inconsistency between Section 13 and 97H of the Planning 

and Environment Act 1987, the Panel can take no other view than that 

submitted by DPCD as to the statutory position on administration and 

enforcement that applies. 

The Panel concludes that the use of the word “Minister for Planning” is 

preferable to “Responsible Authority” for permit conditions that stipulate 

consideration by the Minister, and this wording has been adopted in the 

Recommended Permit (Appendix E). 

Page 130: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 128

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

15. PLANNING PERMIT AND ENVIRONMENTAL MANAGEMENT PLAN

15.1 ISSUES

Given the Panel’s conclusion that policy supports the establishment of wind 

farms in appropriate locations, and should the Panel conclude that there are 

no significant planning impediments to the establishment of the Ararat WEF, 

the Panel’s task is to review the conditions under which the facility should be 

planned, constructed, operated and eventually decommissioned. 

The primary issue for the Panel is a rationalisation of the content of the 

“permissions” summarised in the two Planning Permits that are the subject of 

this report, and the associated Environmental Management Plan. 

The proposed Planning Permit considered during the Panel hearings (with 

separate versions proposed for those parts of the WEF in Ararat Rural City 

and in Northern Grampians Shire) reflected the content and style of the Model 

Planning Permit conditions for wind farms prepared by DPCD.  The Panel felt 

it necessary to investigate a model that covered all the requirements for 

planning, constructing, operating and decommissioning the facility, but 

simplified and clarified the Permits. 

The key issue is the provision of an Environmental Management Plan (EMP) 

that is specific in documenting the commitments of the proponent at the time 

the Panel Report is submitted, and includes the recommended amendments 

made by the relevant authorities and the Panel.  For those matters where 

further investigations and detailed design must be undertaken before specific 

measures can be detailed, an outline of the matters to be detailed in the EMP 

has been provided. 

A further issue considered at the Panel hearings is the period of expiry of the 

Planning Permit.  RES Australia proposed that the Permit should expire if the 

development is not started within five years of the date of the permit, or if it is 

not completed within eight years.  In comparison, the Model Planning Permit 

Conditions prepared by DPCD propose expiry of the Permit if the 

development is not started within three years of the date of the permit, or if it 

is not completed within six years. 

Page 131: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 129

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

15.2 BACKGROUND

At the Panel hearings, the proponent, two municipalities and DPCD worked 

through the proposed Planning Permit, reaching accommodation on its 

content.  Following some discussion and amendment at the Hearing, this 

formed the basis of the version provided by Freehills to the Panel, and 

included as Appendix C of this report. 

The proponent also provided an outline of the EMP in the Application 

Documentation128.  In its Directions, the Panel directed (in part): 

5.  In submitting to the Panel, RES Australia should address the following 

particular matters at the hearing: 

a.  A response to the revised Policy and Planning Guidelines for Wind 

Energy Facilities (September 2009), both generally and in particular 

relating to the preparation of an EMP (see below under b); 

b.  Concerning the Pre‐Construction and construction phase, there is a 

summary treatment of “Environmental Mitigation and Management 

Measures” (pages 85 to 89), but no monitoring proposals.  The 

application requirements for a Wind Energy facility includes “An 

environmental management plan including any rehabilitation and 

monitoring” (quoted on page 141 of the Main Report).  No such plan 

has been provided for the operational phase, merely a commitment to 

make one at a later date.  The proponent is requested to provide 

further detail for the EMP at each of the Pre‐Construction and 

construction phase, and the operational Phase.  These EMPs will 

require progressive development as design and construction proceed, 

but should, at any point in time, provide a clear statement of the 

proponent’s commitments.  Where the detail is not yet available, 

principles or an indicative summary should be provided.  The 

recommendations in the consultant reports should be listed in the 

relevant part of the EMP and clarification provided whether the 

proponent commits to them, or merely notes them as being a matter 

for reference.  Monitoring measures should be detailed where possible.  

Turbine noise is one particular area where the proposed monitoring 

should be detailed.  The points raised in submissions, and particularly 

the requirements of referral authorities and agencies should also be 

considered in the EMP and detailed. 

RES Australia tabled the requested EMP129 at the Hearing.  The Panel made 

some further request for clarification of the EMP to make it conform to the 

128 Application Documentation Volume 1, Section 6.2.9 Environmental Management Plan, pages 83-90 129 Hearing Document 12

Page 132: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 130

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

definitive document sought by the Panel, and RES Australia responded with 

the version of the EMP130 now set out in Appendix D to this report.  The 

Panel’s introductory comment at the top of Appendix D draw attention to a 

comment in the accompanying email from Freehills, which stated (in part) 

“…please find attached the EMP (including the changes requested by the Panel)…”. 

The Panel has considered whether this caveat by the proponent “(including the 

changes requested by the Panel)”requires every tracked change in the EMP below 

to be individually reviewed, and new recommendations made.  These tracked 

changes are, in the main, text where the commitment to specific actions had 

been qualified in the earlier version (Hearing Document 12), and these 

qualifications removed in the later version (Hearing Document 28).  The 

determining factor (in the Panel’s view) is the commitment made by RES 

Australia in its preamble to the earlier version of the EMP, namely: 

In addition to the EMP Framework provided in Section 6.2.9 of the report 

titled Ararat Wind Farm, Planning Permit Application Documentation, 

Volume 1, dated January 2010, RES Australia is able to commit to the 

following plans, procedures, monitoring, enforcement and rehabilitation 

measures during each of the phases of development, being: 

Pre‐Construction Phase; 

Construction Phase; 

Operational Phase; and 

Decommissioning and Site Rehabilitation phase. 

In the revised version, the phrase “is able to commit” has been changed to 

“commits”, removing any uncertainty as to whether the commitment is 

qualified.  The fact that the version electronically supplied by Freehills had all 

track changes accepted, and the tone of the discussion at the Hearing, satisfy 

the Panel that the electronic version is a clear statement of the proponent’s 

commitments. 

The Panel is appreciative of the work undertaken by RES in meeting the 

Panel’s Directions, both generally, and specifically in relation to the EMP. 

The Panel wishes to stress that the Permit and EMP will be binding on any 

developer and operator of the Ararat WEF. 

130 Hearing Document 28

Page 133: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 131

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

15.3 SUBMISSIONS

Submissions on specific topics have been addressed in the relevant chapters 

above.

15.4 DISCUSSION

The issue identified by the Panel in Section 15.1 above is central to the 

structure of any EMP and any Permit that may be approved.  In particular, the 

Panel considers that the proposed structure and content of the Planning 

Permit and EMP as shown in Appendices C and D are complex and confusing.  

The duplication of much of their content raises the potential for error and 

misunderstanding, and does not adequately allow for inevitable refinements 

in plans as the project unfolds. 

The Panel sees the need for a clear statement of those consultant 

recommendations that the proponent will adopt to be integral with any 

approval of the proposal.  The means of giving effect to this will be a new 

permit condition that cites the “Environmental Management Plan at the Pre‐

construction Stage” as part of the permit (see Chapter 16 below). 

The “EMP emailed by the Proponent” in Appendix D makes a significant 

contribution to developing an EMP, going much further that the draft permit 

conditions that specify merely an outline to the EMP.  In terms of specificity, 

and a clear statement of the commitments by the proponent, it would be most 

undesirable to ‘lose’ the detailed EMP in a statutory sense.  To do so would 

mean than the Responsible Authority would have to sift through all the 

commitments and recommendations of the proponent and the proponent’s 

consultants, in the Application Documentation, Expert Witness Reports and 

other Hearing Documents supplied by the proponent and the consultants, and 

the submissions of the various authorities to determine if the EMP did in fact 

conform to what was committed. 

The Panel sets out below the changes that it believes are necessary to the 

Appendix D EMP should the permit for the Ararat WEF be granted: 

Replace the Heading: the new Heading is “Environmental Management 

Plan at the Pre‐Construction Stage”.  While the EMP contains within it 

the four “phases” listed above near the end of this chapter (Section 15.2 

above) there is a need to give a unique title to the EMP as the project 

moves through each stage, and the EMP goes through major updates. 

Replace the Preamble with the text shown in Appendix F. 

Page 134: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 132

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

DSE submission

The comments provided by DSE under Section 52 of the Planning and 

Environment Act (see Section 15.3 above) need to be considered in relation to 

the status of the EMP.  If the Panel’s approach to the EMP (see above) are 

adopted, then the EMP matters desired by DSE can be better located in the 

“Environmental Management Plan at the Pre‐Construction Stage”, which in its 

recommended form contains both prescriptive and outline material, and is 

referred to in the recommended permit (see Section 16.4). 

If this approach is taken, conditions 15, 16 and 17 can be deleted from the 

permit conditions, and included in the EMP to the extent that they are not 

already covered by specific conditions. 

The Panel has reconciled the variations between the detailed 

recommendations of Brett Lane and Associates already included in Appendix 

D and the more general matters requested by DSE.  Beyond this, the one point 

where comment by the Panel is necessary is on the nomination of turbines to 

be removed.  As discussed in Chapter 5 above, DSE initially had serious 

concerns with the location of four turbines (T32, T33, T64 and T65) near the 

Ararat Regional Park.  In its submission on the Application, DSE pointed out 

that the turbines are located on a ridge line highly utilised by avifauna moving 

between the park and another area of significant native vegetation located 

approximately 600 metres to the north east.  DSE recommended that no 

turbines be sited in this location.  However, if the turbines are approved in this 

location, DSE strongly recommends that each of the four turbines mentioned 

be included in any monitoring program required under the Bat and Avifauna 

Management Plan, in conjunction with specific and targeted mitigation 

measures. 

As detailed in Chapter 5, the Panel concluded that the four turbines should 

not be removed, but does support inclusion of these turbines in the BBMP 

monitoring recommended by DSE. 

With regard to the expiry date of the Permit, the Panel reviewed the 

experience of a number of recent WEF Panels, and found variation in 

approach.  For example, the Permit for the Lal Lal facility requires 

commencement within four years of the Permit, and completion within eight 

years, while the Permit for the Berrybank facility issued on 24 August 2010 

allows commencement within three years of the Permit, and completion 

within six years. 

The Panel concluded that the period adopted for Berrybank is reasonable, and 

that the proponent can apply for an extension to the Minister if necessary. 

Page 135: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 133

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Figure 7 below shows how the EMP will develop through the Stages of Pre‐

Construction, Construction, Operation and Decommissioning. 

Figure 7 Development of the EMP through its stages

Stages of the EMP

Pre-construction

Phase

Construction Phase

Operations Phase

Decommissioning Phase

Pre-construction Stage

Construction Stage

Operation Stage

Decommissioning Stage

 

 

 

KEY

The active Phase at any Stage, where investigations and requirements are listed

Future Phases, where known requirements are listed.

Past Phases, which are no longer relevant.

15.5 CONCLUSIONS

The Panel has concluded that it is appropriate to restructure the permissions 

to keep the Planning Permit conditions to a simple and clear list of 

requirements.  Reference to the Environmental Management Plan that was 

proposed as a condition of the Permit is retained, and a list of environmental 

planning requirements that are “called up” by the EMP condition is included.  

These include environmental requirements that were originally part of the 

EMP (Appendix D), but also includes others (such as the Net Gain Offset Plan) 

that were originally listed as separate Permit Conditions.  The Panel’s 

recommended approach to the EMP is shown as Condition 7 in Appendix E. 

Min

iste

rial A

ppro

val a

t th

ese

Stag

es Information Flow

Incr

easi

ng d

etai

l

Page 136: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 134

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

The Panel is aware of the need to ensure that the conditions required by 

referral authorities are faithfully included as part of the Planning Permit.  In 

the case of environmental requirements, it concluded that the best method to 

achieve this is to include them in the EMP, which is to be endorsed by the 

Minister for Planning and form part of the Permit.  In this way, the 

recommendations of the Panel are combined with the requirements of referral 

authorities and the commitments of the proponent in a detailed EMP. 

Thus, the detail of the environmental requirements is then listed in the EMP 

which, at this stage, is titled “Environmental Management Plan at the Pre‐

construction Stage”. 

The Panel concludes that the version of the EMP in Appendix D should be 

amended in the form detailed in Appendix F (“Environmental Management 

Plan at the Pre‐construction Stage”), which includes the changes outlined 

above in relation to the title of the EMP, the Preamble, and the detailed 

recommendations in the Chapters above. 

Page 137: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 135

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

16. CONCLUSIONS AND RECOMMENDATIONS

16.1 CONCLUSIONS

The principal issues arising from the Ararat WEF proposal are: 

medium to high landscape and visual impacts; 

the need for native vegetation removal and  the required offset works to 

achieve the Net Gain policy; 

the need for some further investigation of stability and safety issues on 

the on‐site and off‐site access routes; 

the need to take particular care to avoid erosion of the fragile soils 

encountered at the site. 

These issues, and a number of more minor matters, are addressed in the 

Recommended Permit Conditions (Appendix E) and the Environmental 

Management Plan at the Pre‐Construction Stage (Appendix F). 

The Panel acknowledges that although there are significant landscape impacts 

that in the main cannot be ameliorated, the presence of turbines along 

ridgelines will not be seen as a negative by a high proportion of viewers.  The 

Panel also acknowledges the significant contribution the Ararat WEF can 

make to sustainable energy. 

After considering the contribution that the WEF can make to sustainable 

energy supply, the Panel had no difficulty in concluding that the net 

community benefit was substantial, and the project should proceed. 

Other matters, with potential for wider application than just for the Ararat 

WEF are: 

the conclusion that the compilation by DSE of all Victorian data on bird 

and bad strike from Victorian WEF’s is highly desirable; and 

the approach taken in this report of having not merely an outline EMP, 

but  a developed EMP, which includes the recommendations of the 

Panel, all the detailed commitments of the proponent, including the 

recommendations of the experts it employed, and the detailed 

recommendations from other authorities. 

Page 138: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 136

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

16.2 RECOMMENDATIONS

The Panel recommends that the Minister for Planning: 

1. adopt the Recommended Permit Conditions (Appendix E) 

2. adopt the Recommended Environmental Management Plan at the Pre‐

Construction Stage (Appendix F).  

The Panel also recommends that: 

3. The Department of Sustainability and Environment undertakes the 

task of collating, and progressively updating, all bird and bat strike 

data from Victorian WEF’s, and making the data publicly available. 

 

Page 139: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Page 137

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

APPENDICES

Appendix A   Submissions 

Appendix B  Hearing Document List 

Appendix C   Draft Planning Permit (prepared by proponent) 

Appendix D  Environmental Management Plan (prepared by proponent) 

Appendix E  Recommended Planning Permit  

Appendix F  Recommended “Environmental Management Plan at the Pre‐

Construction Stage” 

 

Page 140: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix A Page 138

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

APPENDIX A SUBMISSIONS

A list of all written submissions to the proposal is included in the Table below.  

The Panel has considered all written and oral submissions and all material 

presented to it in connection with this matter.

Sub #. Submitter Organisation (if any)

1 Brendan Brown, Delegated Officer CFA, Grampians Regional Office

2 David O’Sullivan, Manager Program Development VicRoads

3 Jeff Rigby, Managing Director GWM Water

4 Andrew Bradley Industry Capability Network (Australia) Ltd

5 Cheryl & Gerald Shea Residents

6 Michael Williamson, Principal Strategic Adviser, Sustainable Energy

Sustainability Victoria

7 Marcus Little, Floodplain and Works Manager Glenelg Hopkins CMA

8 Ormond L Randell Resident

9 Mark A McKew Resident

10 Paul & Wendy Harrington Resident

11 P J & M H O’Rourke OAM Resident

12 J Smithers-Tomkins Resident

13 KJ Wilde Resident

14 Geoff Brooks, Manager Statutory Planning Services DSE

15 Stephen Chapple, Chief Executive Officer and Gwenda Allgood, Mayor

Ararat Rural City

16 Peter Woods Resident

17 P R Bird PhD OAM, Secretary Hamilton Field Naturalists Club

18 W John & Lorraine Stewien Resident

19 John Kerwan, Director Land Planning & Spatial Information Department of Defence

20 Stephen Cornish, Chief Executive Officer Pyrenees Shire Council

Page 141: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix B Page 139

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

APPENDIX B HEARING DOCUMENT LIST

Doc # Date Description Presented by

1 (a, b & c)

5/7/10 Proposed itinerary for site inspections, including maps and aerial image.

Ms Grace-Davis

2 5/7/10 Submission on behalf of Minister for Planning, including Appendices

Ms Grace-Davis and Mr Fadgyas

3 5/7/10 Opening submission on behalf of proponent, RES Australia Pty Ltd

Mr Power

4 5/7/10 Australian Government, National Health and Medical Research Council, Wind Turbines and Health: A Rapid Review of the Evidence, July 2010

Mr Power

5 5/7/10 Presentation by Mr Chris Turnbull, Sonus Pty Ltd, to Panel hearing on Environmental Noise, July 2010

Mr Power

6 6/7/10 A3 Plans (8) of proposed project, showing infrastructure, turbine layout, lighting plan and location of residences

Mr Power

7 6/7/10 A3 copies of photomontages from numerous viewpoints

Mr Wyatt

8 6/7/10 A0 copies of photomontages for selected locations

Mr Wyatt

9 6/7/10 Presentation by Ambidgi, to Panel hearing on aviation issues, 7 July 2010

Mr Herron

10 7/7/10 Map of Wildfire Management Overlay WMO 11020 C22

Mr McColl

11 7/7/10 Presentation by Mr Brett Lane, Brett Lane and Associates Pty Ltd, to Panel hearing on Flora and Fauna Assessment

Mr Lane

12 7/7/10 Proposed Environmental Management Plan Framework (mitigation, monitoring, enforcement and rehabilitation

Mr Power

Page 142: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix B Page 140

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Doc # Date Description Presented by

13 7/7/10 Presentation by GL Garrad Hassan, to Panel hearing on Shadow Glint, Blade Glitter and EMI

Dr Gilbert

14 13/7/10 Hard copy of presentation by Mr Alan Wyatt, ERM, to Panel hearing on Landscape and Visual Assessment

Mr Power

15 13/7/10 Selection from Section 40 of the Renewable Energy (Electricity ) Act 2000, showing required GWh per year of renewable source electricity between 2001 and 2030 (pp. 52-53)

Mr Power

16 13/7/10 Electronic copy of DPCD submission to Panel, with minor modifications including corrected numbering of Appendix 7

Ms Grace-Davis

17 13/7/10 Maps of Zones, Ararat and Northern Grampians Planning Schemes

Ms Grace-Davis

18 13/7/10 Submission on behalf of proponent, RES Australia Pty Ltd, including attachments

Mr Power

19 13/7/10 Letter from Syd Herron, Ambidgi, Expert Witness Statement: Post Planning Hearing Follow-up Advice, relating to aviation obstacle lighting, 12 July 2010

Mr Power

20 13/7/10 Submission by Lorraine Stewien to Panel, 13 July 2010, including attachments

Mrs Stewien

21 (a & b)

14/7/10 (a) Submission on behalf of Ararat Rural City Council, including attachments (b) Disc with electronic copies of documents

Mr McColl

22 14/7/10 Submission on behalf of Northern Grampians Shire Council, including attachments

Mr Douglas

23 14/7/10 Supplementary Expert Witness Statement of Chris Turnbull, Sonus, relating to noise queries from the Panel

Mr Power

Page 143: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix B Page 141

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Doc # Date Description Presented by

24 14/7/10 Track changes version of Draft Planning Permit following discussion between proponent, Ararat Rural City and Northern Grampians and DPCD, 13/7/2010

Mr Power

25 14/7/10 “Clean” version of Draft Planning Permit following discussion between proponent, Ararat Rural City and Northern Grampians and DPCD, 13/7/2010

Mr Power

26 14/7/10 DSE response on Panel query relating to Flagship areas and Biolinks, from Mr Geoff Brooks, Manager Statutory Planning Services, dated 14 July 2010

Mr Dekker

27 14/7/10 DSE “track changes” version of Draft Planning Permit for Ararat Planning Permit 09/004799

Mr Dekker

28 15/7/10 Track changes version of Modified Proposed Environmental Management Plan Framework (mitigation, monitoring, enforcement and rehabilitation) – modified version of Document 12

Mr Power

Documents provided after the Hearing Provided by

29 15/7/10 Submission from Pyrenees Shire

30 15/7/10 Pyrenees Amended Permit for the Waubra WEF

Ms Grace-Davis

31 20/7/10 Panel further direction Panel Chair

32 22/7/10 DPCD response to questions on notice

Ms Grace-Davis

33 28/7/10 Draft permit after panel discussion Ms Agius (Freehills)

34 28/7/10 EMP information final Ms Agius

35 30/7/10 RES’ response to DPCD’s submission on noise and reply to Pyrenees Shire Council submission

Ms Agius

36 30/7/10 Advice to Panel re Responsible Authority

Ms Agius

Page 144: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix C Page 142

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

APPENDIX C DRAFT PLANNING PERMIT (PREPARED BY THE PROPONENT)

Anna Williams of Freehills (acting for RES Australia) emailed Planning Panels 

Victoria on 28 July 2010, attaching a file titled “Draft Permit after panel 

discussion” and with the following relevant comment in the text of the email: 

“In response to your email below, please find attached the EMP 

(including the changes requested by the Panel) and the draft permit 

conditions.  In the draft permit conditions, text in mark‐up (without 

highlight) and text highlighted in yellow was discussed during the 

panel hearing.  Text highlighted in green has been inserted subsequent 

to the panel and reflects RES’ further submission.” 

The text of the electronic document is copied below.  The copying process has 

resulted in text exactly as received electronically by the Panel on 28 July 2010, 

with the following exceptions: 

The header to each page has not been copied.  It reads as follows: 

Planning and Environment Regulations 2005 Form 11

Section 97F

PLANNING PERMIT GRANTED BY THE MINISTER UNDER

DIVISION 6 OF PART 4 OF THE PLANNING AND ENVIRONMENT ACT 1987

The track‐changes details did not copy, and all tracked changes were 

automatically accepted in the copy. 

The watermark “Without Prejudice Permit Conditions” did not copy. 

The yellow and green highlights have been retained in the copy.

PLANNING PERMIT Permit No.: 09/004799

Planning Scheme: Ararat Planning Scheme

Responsible Authority for Administration and Enforcement of this Permit: Ararat Rural City Council

ADDRESS OF THE LAND:

Addresses provided by Freehills have been deleted by the Panel for conciseness

 

Page 145: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix C Page 143

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

THE PERMIT ALLOWS:  The use and development of a wind energy facility 

comprising 70 generators and associated infrastructure 

including access roads, cabling, permanent anemometers, 

internal powerlines, substations, excavation of rock 

material, earthworks, temporary concrete batching plants, 

maintenance and storage facilities, car parking, removal of 

native vegetation and alterations to roads and access to 

roads within a Road Zone Category 1. 

THE FOLLOWING CONDITIONS APPLY TO THIS PERMIT:

PLANS TO BE ENDORSED

1.  Before the development starts (following Pre‐Construction phase preliminary 

investigative works and the carrying out of detailed design works), plans must be 

prepared to the satisfaction of the Minister for Planning.  The plans must be drawn 

to scale with dimensions and three copies must be provided.  The plans may be 

submitted for approval in stages or for a particular grouping of wind turbines 

within the subject land.  When approved, the plans will be endorsed by the 

Minister for Planning and will then form part of this permit.  

The plans must show the location and layout of the wind turbines and all on‐site 

buildings and works generally in accordance with Figure 2.2 of the application 

plans. 

The plans must also include: 

(a)  A list of map coordinates for each wind turbine; 

(b)  The distance of each wind turbine from the nearest point on the site 

boundary as depicted in Figure 2.2 of the application plans; 

(c)  Details of the model and rated capacity of the wind turbines to be installed; 

(d)  Elevation drawings, showing dimensions, of the wind turbines and other 

permanent on‐site buildings (e.g. substation facilities); 

(e)  Drawings, showing the key physical dimensions, of all on‐site buildings and 

works including: 

(i)  Wind turbines; 

(ii)  Access tracks; 

(iii)  Internal collector network trenches; 

(iv)  Any temporary concrete batching plant(s); 

Page 146: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix C Page 144

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

(v)  The substation (including designated car parking areas, signage and 

landscaping); 

(vi)  Any ancillary works (e.g. temporary facilities and operations within the 

construction compounds); and 

(vii)  The infrastructure zone. 

(f)  A description of the materials and finishes of the wind turbine towers, 

nacelles, rotor blades and other permanent on‐site buildings.  The wind 

turbine towers, nacelles and rotor blades must be of a non‐reflective finish 

and colour; 

(g)  A description of the location, type and intensity of any aviation obstacle 

lighting to be installed; 

(h)  The locations of scattered native trees and the boundaries of any patches of 

native vegetation, in relation to all buildings and works, in all cases where 

such trees and patches are within 25 metres of the buildings or works; 

(i)  Drawings demonstrating that the placement of turbine locations will not 

interfere with the exclusion zones of any licensed communications links 

(j)  The location of all host dwellings and non‐host dwellings within 3km of the 

nearest turbine; and 

(k)  The permitted use and development must be conducted in accordance with 

all plans that are endorsed under this permit. 

2.  For the purposes of this permit, the carrying out of Pre‐Construction phase 

preliminary investigative works, including sub‐surface geotechnical 

investigations, for the purposes of gathering data or making other assessments 

necessary or desirable in order to prepare the plan(s) under Condition 1 or other 

plans specified in this permit, is approved and can be carried out before the 

plan(s) are endorsed under Condition 1. 

SPECIFICATIONS

3.  The wind energy facility must meet the following requirements: 

(a)  The wind energy facility must comprise no more than 70 wind turbines; 

(b)  The overall maximum height of the wind turbines (to the zenith of the sweep 

of the rotor blade tip) must not exceed 135 metres above foundation level; 

(c)  The wind turbines must be mounted on tubular towers; 

Page 147: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix C Page 145

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

(d)  The diameter of the rotor of the wind turbines must not exceed 104 metres; 

(e)  The hub height of the of the wind turbines must not exceed 94 metres; 

(f)  The rotor of the wind turbines must have only three rotor blades; 

(g)  Access tracks within the subject land must, to the satisfaction of the 

responsible authority: 

(i)  have a surface material that will not unduly contrast with the landscape 

except where tracks need to be sealed; 

(ii)  be designed to minimise impact on the farming activities on the land; 

and 

(iii)  have an effective trafficable width of not less than 3 metres. 

(h)  The transformer associated with each wind turbine must be enclosed within 

the tower / nacelle or be located beside each tower and pad mounted; 

(i)  All new electricity cabling and powerlines associated with the internal 

collector network within the wind energy facility must be installed in 

accordance with the endorsed plans except with the further written consent 

of the Minister for Planning; 

(j)  Except in the case of an emergency or to accommodate the requirements of 

the network service provider, no external lighting of infrastructure 

associated with the wind energy facility, other than low level security 

lighting and aviation obstacle lighting as provided for in condition 3(m), may 

be installed or operated without the further written consent of the Minister 

for Planning; 

(k)  All spare parts and other equipment and materials associated with the use of 

the wind energy facility must be located in locked storage areas that are 

inaccessible to the public to the satisfaction of the responsible authority; 

(l)  All turbines must be located within the infrastructure zones shown on the 

endorsed plan(s); 

(m)  If aviation obstacle lighting is required to be installed, the minimum number 

and type of lights required must be installed in accordance with an aviation 

lighting plan that has been endorsed by the Minister for Planning [Aviation 

obstacle lighting must not be installed unless endorsed by the Minister for 

Planning on the advice of a risk assessment prepared for the proponent or 

the requirement of a regulatory authority.  Any lights installed must be of 

an intensity and baffling endorsed by the Minister for Planning.] 

Page 148: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix C Page 146

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

NET GAIN OFFSET PLAN

4.  Before native vegetation is removed, a net gain offset plan must be prepared by a 

suitably qualified ecological specialist and submitted to and approved by the 

Minister for Planning in consultation with the Department of Sustainability and 

Environment.  Once approved, the plan will be endorsed and will then form part 

of the permit.  The offset plan must include the following: 

(i)  Details of the proposed offsets which will achieve a net gain in quality and 

quantity of native vegetation in accordance with the principles and 

guidelines associated with the Native Vegetation Management: A 

Framework for Action (DSE 2002); 

(ii)  Fully dimensioned plans (drawn to an appropriate scale), which clearly show 

the locations, boundaries and title details of all offset sites.  The plans must 

also clearly show the boundaries of any different management zones and the 

location of any proposed fencing; 

(iii)  Type of offsets to be provided for each location; 

(iv)  Details of revegetation including number of trees, shrubs and other plants, 

species mix and density (consistent with the characteristics of the relevant 

Ecological Vegetation Class); 

(v)  Methods of managing and restoring the vegetation, including revegetation, 

such as fencing, weed control, enhancement planting and other habitat 

management actions; 

(vi)  Pest plant and animal control methods; 

(vii)  A statement of the need to source local seed stock and options available for 

sourcing of local seed; 

(viii) A statement of the need for revegetation works to be carried out by a suitably 

qualified ecological specialist; 

(ix)  Methods of permanent protection for the offsets, such as the registration on 

title of an agreement under Section 173 of the Planning and Environment Act 

1987, an agreement under Section 69 of the Conservation Forests and Lands 

Act 1987, or a covenant under section 3A of the Victorian Conservation Trust 

Act 1972; 

(x)  Persons responsible for implementing and monitoring the offset plan; 

(xi)  A schedule of management actions, which documents how the net gain 

outcomes will be achieved within a 10 year timeframe. 

Page 149: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix C Page 147

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

5.  All offsets documented in the approved Offset Plan must be initiated to the 

satisfaction of the responsible authority and the Department of Sustainability and 

Environment. 

6.  All offsets must be completed according to the schedule of works in the approved 

Offset Plan, to the satisfaction of the responsible authority. 

7.  Temporary fencing or tape must be installed around areas of native vegetation to 

be retained, to the satisfaction of the responsible authority. 

[Note we have asked for DSE condition 7 to be removed, or ‘All offset sites must 

be legally secured in accordance with the offset plan.’] 

NATIVE VEGETATION PROTECTION WORKS

8.  Works must not cause damage to native vegetation stands to be retained.  

Vehicular access beneath large trees and habitat trees must be prevented. 

9.  Tree trimming operations must be undertaken using the natural target pruning 

‘three cut method’ as described in the ‘Roadside Handbook: An Environmental 

Guide for Road Construction and Maintenance’ (VicRoads 2006). 

10.  Any roadside areas disturbed by works associated with the wind energy facility 

must be revegetated as soon as practicable to minimise soil erosion. 

STAGING

11.  The use and development authorised by this permit may be completed in stages as 

shown on the endorsed plan(s) to the satisfaction of the responsible authority.  

Any corresponding obligation arising under this permit (including the preparation 

and approval of plans) may be similarly completed in stages or parts. 

LAYOUT NOT ALTERED

12.  The use and development shown on the plan(s) endorsed under this permit must 

not be altered or modified unless: 

(a)  the Minister for Planning has consented to the alteration or modification in 

writing; or 

(b)  the requirements of condition 13 are satisfied and complied with. 

13.  The use and development shown on the plan(s) endorsed under condition 1 may 

be altered or modified without the written consent of the Minister for Planning 

and will be regarded as generally in accordance with the endorsed plan(s) if: 

Page 150: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix C Page 148

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

(a)  The [Minister for Planning/responsible authority] is satisfied that it will not 

give rise to any material adverse change in landscape, vegetation, cultural, 

visual, shadow or noise impacts compared to the endorsed plan(s); 

(b)  The turbines and wind energy facility infrastructure are located within the 

infrastructure zone; 

(c)  A turbine is not moved to within 1 kilometre of any non‐host dwelling; 

(d)  A turbine location is altered by no more than 100 metres; and 

(e)  No turbine base is located within: 

(i)  100 metres from a Road Zone Category 1 or land in a Public Acquisition 

Overlay to be acquired for a road; 

(ii)  40 metres from a Road Zone Category 2; 

(iii)  20 metres from any other road; 

(iv)  5 metres from the site boundary; 

(v)  100 metres from a dwelling that is not a host dwelling; 

(vi)  50 metres from a waterway, wetlands or designated flood plain; or 

(vii)  within an exclusion zone of any licensed communications link. 

ENVIRONMENTAL MANAGEMENT PLAN

15.  Note: Having regard to the fact that there are two permits for this wind energy facility, 

where a management plan is referred to below, it is desirable that a single plan be prepared 

in consultation with both Councils. 

Before the development starts, an environmental management plan must be 

prepared to the satisfaction of the Minister for Planning by the wind energy 

facility operator in consultation with the relevant authorities. 

The environmental management plan may be prepared in sections or stages.  The 

first section of the environmental management plan is the [insert name of 

document], and must be complied with unless varied by a plan endorsed under 

this permit. 

The environmental management plan must include a copy of the endorsed plans. 

The environmental management plan must consider and generally be in 

accordance with: 

•  EPA Publication 480: Environmental Guidelines for Major Construction Sites 

Page 151: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix C Page 149

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

•  EPA Publication 275: Construction Techniques for Sediment Pollution 

Control 

•  EPA Publication 891.1: Code of Practice, Onsite Wastewater Management 

•  EPA Publication 628: Environmental Guidelines for the Concrete Batching 

  Industry 

•  EPA Publication 347: Bunding Guidelines. 

The environmental management plan should, where appropriate, address and 

include: 

(a)  A construction and work site management plan which must include: 

(i)  Procedures for access, construction noise control, dust emissions, spills 

and leaks from the handling of fuels and other hazardous materials and 

pollution management.  Such construction and work site procedures 

are to be in accordance with Environment Protection Authority (EPA) 

requirements; 

(ii)  The identification of all potential contaminants and hazardous 

materials used and/or stored on site in connection with the 

development and use; 

(iii)  The identification of all construction and operations processes that 

could potentially lead to water contamination; 

(iv)  The identification of appropriate storage, construction and operational 

methods to control any identified contamination risks; 

(v)  The identification of waste re‐use, recycling and disposal procedures; 

(vi)  Appropriate sanitary facilities for construction and maintenance staff in 

accordance with the EPA Publication 891.1 Septic Tanks Code of 

Practice; 

(vii)  A timetable, where practicable for the construction of turbine bases, 

access tracks and power cabling during warmer months to minimise 

impacts on local fauna and sediment mobilisation; 

(viii) Procedures to ensure that construction vehicles and equipment use, 

designated tracks and works area avoid impacts on native vegetation; 

(ix)  Procedures to ensure the covering of excavations, trenches and holes at 

night time and to fill trenches as soon as practical after excavation, to 

protect, as far as practicable, native fauna and domestic stock from 

being injured by or entrapped;  

Page 152: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix C Page 150

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

(x)  The removal of works, buildings and staging area on completion of 

construction of the project. 

(b)  A hydrocarbon and hazardous substances plan.  This plan must include: 

(i)  Procedures for the proper handling and storage of hazardous materials 

on‐site including procedures for any on‐site, permanent, post‐

construction storage of fuels, lubricants or waste oil to be in bunded 

areas; and 

(ii)  Design criteria for any hazardous materials storage facilities on‐site, 

and 

(iii)  Contingency measures to ensure that any spills or leaks of hazardous 

materials, chemicals or oils are contained on‐site and cleaned up in 

accordance with Environment Protection Authority requirements. 

(c) A sediment, erosion and water quality management plan.  This plan must 

be prepared in consultation with the relevant Catchment Management 

Authority/ies and other authorities as may be directed by the Minister for 

Planning.  The plan must include: 

(i)  Procedures to ensure that silt from batters, cut‐off drains, table drains 

and road works is retained on the site during and after construction and 

replaces as soon as possible. 

To this end: 

•  All land disturbances must be confined to a minimum practical 

working area; 

•  Soil to be removed must be stockpiled and separate soil horizons must 

be retained in separate stockpiles and not mixed and replaced as soon 

as possible in sequence; and 

•  Stockpiles must be located away from drainage lines; 

(ii)  Criteria for the siting and design of any temporary concrete batching 

plant associated with the development of the wind energy facility and 

the procedure for its operation, removal and reinstatement of the site 

once its use finishes.  The establishment and operation of any such 

temporary concrete batching plant must be designed and operated in 

accordance with the Environment Protection Authority Publication 628 

Environmental Guidelines for the Concrete Batching Industry;   

(iii)  The installation of geo‐textile silt fences (with sedimentation basins 

where appropriate) on all drainage lines from the site which are likely 

to receive run‐off from disturbed areas; 

Page 153: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix C Page 151

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

(iv)  Procedures to suppress dust from construction‐related activities.  

Appropriate measures may include water spraying of roads and 

stockpiles, stabilising surfaces, temporary screening and/or wind 

fences, modifying constructions activities during periods of heightened 

winds and revegetating exposed areas as soon as practicable;  

(v)  Procedures to ensure that steep batters are treated appropriately for 

sediment pollution control in accordance with Environmental 

Protection Authority Publication 275 Construction Techniques for 

Sediment Pollution Control;  

(vi)  Procedures for the management of contaminated waste water including 

waster water discharge;  

(vii)  The identification of waste reuse, recycling and disposal procedures; 

(viii) A process for overland flow management to prevent the concentration 

and diversion of waters onto steep or erosion prone slopes; 

(ix)  Pollution management measures for stored and stockpiled materials 

including waste materials, litter, contaminated run‐off and any other 

potential source of pollution to ground or surface waters; Procedures 

for the discharge of collected runoff; 

(x)  Incorporation of pollution control measures outlined in EPA 

Publication 480 Environmental Guidelines for Major Construction Sites; 

(xi)  Siting of concrete batching plant and any on‐site wastewater and 

disposal and disposal treatment fields at least 100 metres from any 

watercourse; 

(xii)  Appropriate capacity and an agreed program for annual inspection and 

regular maintenance of any on‐site wastewater management system 

constructed to service staff, contractors or visitors;  

(xiii) A program of inspection and procedures for the immediate remediation 

of localised erosion within a specified response time; and 

(xiv) Management procedures to prevent pollution of the local waterways, 

particularly from wash water and waste concrete materials. 

(d)  A blasting plan.  This plan is only required if blasting is proposed to be 

undertaken at the site as part of the construction of the wind energy facility.  

The plan must include the following: 

(i)  Name and qualification of the person responsible for blasting; 

(ii)  A description of the location of where the explosives will be used, and 

the location of every licensed bore on any property with an adjoining 

boundary within 1km of the location of the blasting; 

Page 154: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix C Page 152

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

(iii)  A requirement for the identification and assessment of any potentially 

sensitive site within 1km of the location of the blasting, including the 

procedure for pre‐blast and post‐blast qualitative measurement or 

monitoring at such site; 

(iv)  The procedure for site clearance and post blast reoccupation; 

(v)  The procedure for the storage and handling of explosives; 

(vi)  A requirement that blasting only occur after at least 48 hours prior 

notification in writing of the intention to undertake blasting has been 

given to the occupants of the properties which are located in whole or 

in part within 1km of the location of the proposed blasting; and 

(vii)  A requirement that blasting only be undertaken between the hours of 

8am and 4pm. 

(e)  Native Flora and Fauna Protection 

(i)  Require fauna habitat to be considered if there are any changes to the 

location of wind energy facility infrastructure; and 

(ii)  Procedures for the rehabilitation of construction zones with appropriate 

flora species. 

(f)  A pest animal management plan to be prepared in consultation with the 

Department of Sustainability and Environment and the Department of 

Primary Industries to the satisfaction of these departments. 

This plan must include: 

•  Procedures for the control of pest animals, particularly by avoiding 

opportunities for the sheltering of pests; and 

•  Follow‐up pest animal control for all areas disturbed by the wind 

energy facility construction works for a period of two years following 

the completion of the wind energy facility. 

(g)  A pest plant management plan developed in consultation with the owners 

of the relevant land, and the Department of Sustainability and Environment 

and the Department of Primary Industries to the satisfaction of these 

departments.  This plan must include: 

•  procedures to prevent the spread of weeds and pathogens from earth 

moving equipment and associated machinery including the cleaning of 

all plant and equipment before transport to the site and the use of road 

making material comprising clean fill that is free of weeds; 

•  revegetation of disturbed areas; and 

Page 155: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix C Page 153

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

•  a protocol to ensure follow up weed control is undertaken on all areas 

disturbed through construction of the wind energy facility for a 

minimum period of 2 years following completion of the works. 

(h)  An on‐site landscaping plan.  The on‐site landscaping plan must be 

prepared within six months of the endorsement of plans under condition 1. 

The on‐site landscaping plan must: 

(i)  Include plans drawn to scale showing the extent and layout of any 

landscape plantings to be used to visually screen or otherwise beautify 

any on‐site buildings or works other than the wind turbines; 

(ii)  Provide details of plant species proposed to be used in the landscape 

plantings, including height and spread at maturity; 

(iii)  Provide a timetable for implementation of all landscape plantings; and 

(iv)  Provide for maintenance and monitoring program such as the health 

and condition of planted material, replacement of plants. 

(i)  Road management plan.  Before the development starts a road management 

plan must be prepared, in consultation with the relevant road authority and 

VicRoads, to the satisfaction of the Minister for Planning for submission to 

and approval by the Minister for Planning. 

The road management plan must: 

(i)  Identify all public roads and access points that will be used in the 

construction and operation of the wind energy facility; 

(ii)  Provide for an existing conditions survey of public roads that will be 

used in the construction and operation of the wind energy facility 

including details of the suitability, design, construction standards and 

condition of the roads to enable, for sealed roads, the calculation of 

Total ESA (Equivalent Standard Axles) loading for comparison with the 

appropriate Austroads pavement design guide; 

(iii)  Establish the appropriate existing equivalent renewal pavement design 

and associated costs in conjunction with the relevant road authority and 

VicRoads and establish the calculated damage (if any) directly 

attributable to the wind energy facility and the amount (if any) to be 

reimbursed to the relevant road authority; 

(iv)  Include the designation of routes, operating hours and speed limits for 

oversize and overmass vehicles on routes accessing the site so as to 

avoid significant interference with the passage of school buses, and to 

provide for resident safety and the safe management of stock; 

Page 156: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix C Page 154

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

(v)  Provide details of any large over dimensional vehicles to be used (such 

as those used for the transport of the nacelles, blades and tower 

sections) and details of the routes to be taken, the proposed escort 

arrangements and requirements for over dimensional permits from 

VicRoads; 

(vi)  Specify the need for road and intersection upgrades to accommodate 

any additional traffic or site access requirements, whether temporary or 

ongoing, and the timing of when these upgrades are to be undertaken; 

(vii)  Include measures to be used to manage traffic impacts associated with 

the construction and ongoing operation of the wind energy facility 

(including temporary speed zones and times of operation in accordance 

with VicRoads ‘Roadworks Signing Code of Practice’) on the traffic 

volumes and flows on surrounding roads; 

(viii) Identify any areas of roadside native vegetation which need removal or 

pruning and the pruning practices to be followed; 

(ix)  Include identification and timing of any Pre‐Construction works; 

(x)  Include a program of regular inspections, to be carried out during the 

construction period, to identify the need for maintenance works 

necessary as a result of construction traffic; 

(xi)  Include agreed criteria that will trigger repair and maintenance works; 

and 

(xii)  Include a program to repair and maintain roads to the pre‐existing 

condition identified by the above surveys during the construction and 

operation phases. 

(j)  Emergency response plan.  Before the development starts an emergency 

response plan must be prepared. 

The emergency response plan must be generally in accordance with 

“Emergency Management Guidelines for Wind Farms” (Country Fire 

Authority April 2007). 

The emergency response plan must be prepared in consultation with and to 

the satisfaction of: 

(i)  Country Fire Authority; 

(ii)  Victoria Police; 

(iii)  Rural Ambulance Victoria; 

(iv)  State Emergency Service; and 

Page 157: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix C Page 155

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

(v)  The Ararat Rural City Council and the Northern Grampians Shire 

Council. 

The emergency response plan should generally conform to “AS 3745‐2002 

Emergency control organization and procedures for buildings, structures and 

workplaces”, or any subsequent replacement or amendment. 

The emergency response plan must include: 

(i)  Criteria for the provision of static water supply tanks, solely for fire 

fighting purposes, including minimum capacities, appropriate 

connections and signage; 

(ii)  Procedures for vegetation management, fuel control and the provision 

of fire fighting equipment during declared fire danger periods; 

(iii)  Minimum standards for access roads and tracks, to allow access for fire 

fighting vehicles, including criteria for access to static water supply 

tanks for fire fighting vehicles; 

(iv)  The facilitation by the wind energy facility operator, before or within 3 

months after the commencement of operation, of a familiarisation visit 

to the site and explanation of emergency services procedures for the 

relevant members of the Country Fire Authority, Rural Ambulance 

Victoria, Victoria Police, State Emergency Service and Ararat Rural City 

Council’s Emergency Management Committee; 

(v)  Subsequent familiarisation sessions for new personnel of those 

organisations on a regular basis and/or as required; and 

(vi)  If requested, training of Country Fire Authority personnel in relation to 

suppression of wind energy facility fires. 

(k)  Bird and bat management plan.  Before the development starts a bird and 

bat management plan (BBMP) must be prepared in consultation with the 

Department of Sustainability and Environment.  The use must accord with 

the plan and to the satisfaction of the Minister for Planning. 

The BBMP must include: 

(i)  A statement of the objectives and overall strategy for managing and 

mitigating any significant bird and bat strike arising from the wind 

energy facility operations; 

(ii)  A monitoring program of at least two years duration either 

commencing from the commissioning of the last turbine of the first 

stage of the approved development and use (if any) or alternatively 

such other time of commencement as is to the satisfaction of the 

Minister for Planning; 

Page 158: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix C Page 156

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

(iii)  Procedures for the reporting of any bird or bat strikes to the 

Department of Sustainability and Environment within 7 days of 

becoming aware of any strike identifying where possible whether the 

strike was by a lit or unlit turbine; 

(iv)  Information on the efficacy of searches for carcases of birds and bats, 

and where practical, information on the rate of removal of carcases by 

scavengers, so that correction factors can be determined to enable 

calculations of the total number of mortalities; 

(v)  Procedures for the regular removal of carcasses likely to attract raptors 

to areas near turbines; 

(vi)  Procedures for periodic reporting, within agreed timeframes, of the 

findings of the monitoring to the Department of Sustainability and 

Environment and the local community; 

(vii)  Recommendations in relation to a mortality rate for specified species 

which would trigger the requirement for responsive mitigation 

measures to be undertaken by the operator of the wind energy facility 

to the satisfaction of the Minister for Planning; and 

(viii) Implementation measures developed in consultation with the 

Department of Sustainability and Environment to offset any impacts 

detected during monitoring including turbine operation management 

and on‐site or off‐site habitat enhancement (including management or 

improvement of habitat or breeding sites). 

Following the completion of the monitoring program in accordance with the 

BBMP of at least 2 years duration, a report must be prepared by the operator 

of the wind energy facility setting out the findings of the monitoring 

program to the satisfaction of the Minister for Planning.  If, after 

consideration of this report, the Minister for Planning directs that further 

investigation of potential or actual impacts on birds and bats is to be 

undertaken, the extent and details of the further investigation must be to the 

satisfaction of the Department of Sustainability and Environment and the 

investigation must be carried out to the satisfaction of the Minister for 

Planning. 

(l)  In the event that impacts detected during the BBMP monitoring 

program are considered by the Minister for Planning to be ecologically 

significant, a monitoring and mitigation measures strategy must be 

prepared in consultation with the Department of Sustainability and 

Environment to the satisfaction of the Minister for Planning.  When 

approved the monitoring and mitigation measures strategy will be 

endorsed and will then form part of this permit. 

Page 159: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix C Page 157

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

The monitoring and mitigation measures strategy must include, for 

each species for which ecologically significant impacts have been 

detected: 

•  Further monitoring of the ‘targeted’ species; 

•  Mitigation measures for ‘targeted’ species; and 

•  all to be implemented to the satisfaction of the Minister for 

Planning. 

(m)  A training program for construction workers, permanent employees 

and contractors at the wind energy facility site including a site 

induction program relating to the range of issues addressed by the 

environmental management plan. 

(n)  Incident Management 

(i)  A procedure for the establishment and maintenance of an incident 

register for the recording of: 

•  Environmental incidents 

•  Non‐conformances, 

•  Corrective actions. 

(ii)  The register must contain advice on to whom the reports must be 

made and be available for inspection by the public during normal 

working hours and its contents should be reported to the 

responsible authority as required. 

(o)  A timetable for Implementation of all programs and works. 

(p)  A program for reviewing the operational phase of the endorsed 

environmental management plan.  The environmental management 

plan must be reviewed at least once every 5 years in consultation with 

the Ararat Rural City Council and the Minister for Planning, and if 

necessary amended to reflect operational experience and changes in 

environmental management standards and techniques.  Any 

amendment of the environmental management plan must be submitted 

to the Minister for Planning for re‐endorsement. 

COMPLAINTS MANAGEMENT PLAN 

16.  A complaints management plan designed in accordance with Australian Standard 

Customer satisfaction – Guidelines for complaints handling in organizations (ISO 

1002:2006) having regard to the guidance provided in The why and how of 

complaints handling HB 229‐2006, to the satisfaction of the responsible authority. 

The complaints management plan will include procedures for: 

Page 160: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix C Page 158

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

(i)  Readily accessible information on how complaints can be made free of cost to 

complainants 

(ii)  Immediate acknowledgement of complaints and regular and comprehensive 

feedback to complainants on actions proposed, their implementation and 

success or otherwise 

(iii)  Closure of complaints by agreement with complainants 

(iv)  Establishment and maintenance of a complaint register for the recording of 

receipt and acknowledgement of complaints, actions taken, success or 

otherwise of actions and complaint closure and for the register to be 

available to the public during normal working hours  

(v)  Reporting of the contents of the complaint register to the Ararat Rural City 

Council as required, and 

(vi)  Regular, at least annual, auditing of the implementation of the complaints 

management plan with audit results being reported to the responsible 

authority. 

OFF‐SITE MITIGATION LANDSCAPING PLAN 

17.   

(a)  Within 6 months of the date of endorsement of the plans under Condition 1 a 

program for voluntary landscape mitigation works must be made available 

to the owners of dwellings built at the time [the planning permit application 

is lodged [RES’ position][OR] the permit is granted [DPCD’s position] for the 

wind energy facility within 3 kilometres of the nearest turbine. 

(b)  The offers to landscape dwellings identified in the program referred to in 

condition (a)  must be made before development starts and available up until 

12 months after the commissioning of the last wind turbine of the 

development or relevant stage. 

(c)  If a program of voluntary landscape mitigation works is accepted by one or 

more owners under condition (a), as part of that program, an off‐site 

landscaping plan must be prepared in consultation with the landowners 

specified in condition (a) to the satisfaction of the Minister for Planning.  

When approved the plan will be endorsed and will then form part of this 

permit. 

(d)  The plan must provide details of planting or other treatments that will be 

used to reduce the visual impact of the wind turbines at the dwellings of the 

participating landowners. 

Substance 24(b) and (c) of original conditions to be included, ie: 

Page 161: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix C Page 159

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

24(b) of original off‐site landscaping condition relates to maintenance of 

landscaping for a period of two years.  [However, noting that RES cannot be 

held accountable for maintenance issues on neighbouring lands outside the 

site boundary]. 

24(c) of original condition relates to a timetable for implementation of 

landscaping works. 

ROADWORKS REQUIREMENTS (VICROADS) 

18.  The local roads identified in the Traffic and Transport Assessment Report (ref 

01732‐002820) that will be used to exit onto the arterial roads must be constructed 

to allow for the vehicle path and sealed back a minimum of 20 metres from edge of 

seal of the arterial road. 

19.  Prior to the start of the development the developer must: 

(a)  Submit final detailed construction drawings of the altered intersections 

including line marking to be approved by VicRoads. 

(b)  Prepare a specification for the works in accordance with the relevant sections 

of the VicRoads’ Standard Specification For Roadworks. 

20.  RES suggest combining these three roadwork conditions (18, 19 & 20) into a single 

condition.  All roadworks must be completed to the satisfaction of VicRoads prior 

to the commencement of the development.  The contractor must be VicRoads 

approved or prequalified at R1 level.  All works must be at the developers cost. 

TELEVISION AND RADIO RECEPTION AND INTERFERENCE 

21.  Before the development starts a television and radio reception plan must be 

prepared to the satisfaction of the Minister for Planning.  When approved, the 

plan will be endorsed and form part of the permit.     

The television and radio reception plan must include: 

(a)  A definition of the area to be covered by the television and radio reception 

plan (the defined area) based on the recommendations of a suitably qualified 

expert 

(b)  A Pre‐Construction survey to determine television and radio reception 

strength and quality at locations within the defined area, completed prior to 

the commissioning of any turbine.  The location of such monitoring is to be 

determined by an independent television and radio monitoring specialist 

appointed by the wind energy facility operator 

(c)  A procedure for post‐construction survey at any dwelling in the defined area 

that existed at the date of the Pre‐Construction survey in response to any 

complaint received regarding the wind energy facility having an adverse 

effect on television or radio reception 

Page 162: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix C Page 160

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

(d)  A procedure for the implementation of mitigation measures at any dwelling 

in the defined area that existed at the date of the Pre‐Construction survey if 

the post‐construction survey establishes any increase in interference to 

reception as a result of the wind energy facility operations.  The mitigation 

measures shall return the affected reception to Pre‐Construction quality and 

be undertaken at the cost of the wind energy facility operator, all to the 

satisfaction of the Minister for Planning 

BLADE SHADOW FLICKER 

22.  Shadow flicker from the wind energy facility must not exceed 30 hours per annum 

at any dwelling existing as at the date of this permit to the satisfaction of the 

Minister for Planning.  In determining compliance with this condition, the results 

of a geometric computer simulation model is evidence of compliance with this 

condition. 

Any dwelling within the Site Boundary will be exempt from this condition if it is 

the subject of an agreement with the landowner and is registered on title. 

NOISE LIMITS 

23.  Except as provided below in this condition, the operation of the wind energy 

facility must comply with the noise criteria specified in NZS6808:1998 ‘Acoustics ‐ 

The Assessment and Measurement of Sound from Wind Turbine Generators’ at 

any dwelling existing on land in the vicinity of the proposed wind energy facility 

as at the date of the issue of this permit, to the satisfaction of the Minister for 

Planning. 

Compliance must be assessed separately for all‐time and night time.  For the 

purpose of this requirement, night time is defined as 10.00pm to 7.00am. 

Any dwelling on the subject land may be exempt from this condition.  This 

exemption will be given effect through an agreement with the landowner that 

must apply to any occupant of the dwelling and must be registered on title.  Such 

dwellings will be known as host dwellings. 

NOISE COMPLIANCE TESTING 

Please note RES’ submission that noise compliance testing should only be done in 

response to complaints.  This is discussed further in RES’ response to the DPCD’s 

submission regarding this noise condition and an alternative condition to the existing 

condition 24 is proposed. 

24.  Before the development starts, a noise compliance testing plan must be prepared 

by a suitably qualified acoustics expert to the satisfaction of the Minister for 

Planning. 

Page 163: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix C Page 161

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

When approved, the noise compliance testing plan will be endorsed be the 

Minister for Planning and will then form part of this permit. 

(i)  The noise compliance testing plan must include: 

(a)  A prediction, by a suitably qualified acoustic expert, of the area within 

which the noise level from the wind energy facility during full 

operation will be 35dB(A) or greater; 

(b)  Identification of all dwellings, excluding host dwellings, within the area 

predicted in (a) above and a statement as to whether consent from the 

owner of each of the identified dwellings for compliance testing has 

been obtained or refused; 

(c)  A method or methods of testing compliance with the noise limits 

prescribed in Condition 23 of this permit for each dwelling or at a 

dwelling that is a representative sample of a group of dwellings 

identified in (b) above for which consent for the conduct of compliance 

testing has been obtained. 

The compliance testing method must be either: 

(i)  The method described in NZS6808:1998 ‘Acoustics – the 

Assessment and Measurement of Sound from Wind Turbine 

Generators’ with the following criteria being met: 

•  The regression curves required must be derived from a data 

set: 

- Of at least 500 noise level/wind speed data pairs; and 

- Including hub height wind speeds. or 

(ii)  A method, designed by a suitably qualified acoustics expert 

(d)  A process for compliance testing under which compliance testing at all 

dwellings identified under (c) for which consent for such testing has 

been obtained is performed at some time in the 14 months following the 

commissioning of the last turbine in a stage of the wind energy facility, 

if the development is in stages;  

(e)  A procedure for the assessment, by a suitably qualified acoustics expert, 

of the characteristics of the noise from the wind energy facility to 

determine if that noise has any special audible characteristics that 

require the addition of 5 dB(A) to the measured operating noise levels 

as required in Condition 23 of this permit; 

(f)  A procedure under which all results of compliance testing conducted in 

any month are reported to the Minister for Planning for approval by the 

15th day of the following month and made available upon request to 

Page 164: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix C Page 162

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

the owners and occupiers of particular dwellings as soon as results 

relating to that particular dwelling are available; and 

(g)  A procedure under which the implementation of the noise compliance 

testing plan is directed and supervised by a suitable qualified acoustic 

expert to the satisfaction of the Minister for Planning. 

NOISE COMPLIANCE ENFORCEMENT 

25.  If an exceedance of the noise limits prescribed in Condition 23 of this permit is 

detected, the wind energy facility operator must: 

(a)  Within 30 days of the confirmation of the exceedance, take sufficient actions 

to reduce the wind energy facility noise level at the subject dwelling as 

predicted using the prediction methodology contained in NS6808:1998 

‘Acoustics – the Assessment and Measurement of Sound from Wind Turbine 

Generators’ by an amount equal to or greater than the amount of exceedance 

(b)  Within 30 days of the confirmation of the exceedance, provide the 

responsible authority and the owner/occupier of the dwelling with: 

(i)  The results of the compliance testing measurements including the 

magnitude of the detected exceedance 

(ii)  Details of the actions taken to reduce the wind energy facility noise 

emissions, and 

(iii)  Evidence that the actions taken will produce a decrease in the wind 

energy facility noise level at the dwelling by an amount equal to the 

magnitude of the exceedance based on a prediction using the 

methodology of NZS6808:1998 ‘Acoustics – the Assessment and 

Measurement of Sound from Wind Turbine Generators’. 

(c)  Continue to operate the wind energy facility with the implemented actions 

until approval for a different mode of operation is given by the responsible 

authority under the provision of (d) below 

(d)  Within 60 days of the detection of an exceedance provide the responsible 

authority and owner/occupier of the dwelling with either: 

(i)  The result of compliance testing using the procedures prescribed in 

Condition 24 of this permit that demonstrate compliance, or 

(ii)  A program for the development and evaluation of an alternative mode 

of wind energy facility operation that can be reasonably be expected to 

result in continuing compliance with noise levels as allowed in 

Condition 23 of this permit. 

(iii)  The program will: 

Page 165: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix C Page 163

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

•  Be developed and implemented under the supervision of a 

suitably qualified acoustics expert; 

•  Include detailed descriptions of proposed actions; 

•  Include predictions of wind energy facility noise levels at the 

dwelling at each stage of the program; 

•  Not include any actions or combination of actions that are 

predicted to result in non‐compliance; 

•  Include compliance testing using the procedures prescribed in 

Condition 24 of this permit; and 

•  Include a program schedule that specifies the timing of each stage 

of the program, 

to the satisfaction of the responsible authority. 

If the responsible authority requires the program to be modified, the wind energy 

facility operator may either submit a modified program or immediately withdraw 

the program and conduct compliance testing using the procedures prescribed in 

Condition 24 of this permit. 

Following implementation of the program, the wind energy facility operator may 

provide the responsible authority and the owner/occupier with a detailed 

description of an alternative mode of operation of the wind energy facility 

together with evidence that under that mode of operation compliance can be 

expected, to the satisfaction of the responsible authority.  Given such information 

and evidence the responsible authority may approve the operation of the wind 

energy facility in the alternative mode and such approval will not be unreasonably 

withheld. 

DECOMMISSIONING 

26.  The wind energy facility operator must, no later than one month after all wind 

turbines have permanently ceased to generate electricity, notify the Minister for 

Planning in writing of the cessation of the use.  Within a further six months of this 

date, the wind energy facility operator, or in the absence of the operator, the 

owner of the land on which the relevant turbines(s) is/are located, must prepare a 

decommissioning plan to the satisfaction of the Minister for Planning.  When 

approved, the decommissioning plan will become part of this permit. 

27.  The decommissioning plan must provide for the following: 

(a)  The removal of all above ground operational equipment 

(b)  The removal and clean up of any residual spills or contamination 

Page 166: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix C Page 164

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

(c)  The rehabilitation of all storage, construction, access tracks and other areas 

affected by the project closure or decommissioning, if not otherwise useful to 

the on‐going management of the subject land 

(d)  A decommissioning traffic management plan 

(e)  A post decommissioning revegetation management plan  

The decommissioning plan must be implemented to the satisfaction of the 

responsible authority within 24 months of approval of the plan or within such 

other timeframe as may be specified by the responsible authority. 

EXPIRY 

28.  This permit will expire if one of the following circumstances applies: 

(i)  the development is not started within 5 years of the date of this permit; 

(ii)  the development is not completed within 8 years of the date of this permit. 

The Minister for Planning may extend the periods referred to if a request is made 

in writing before the permit expires, or within three months afterwards.  

 

Notes:  

If it is proposed to removal or destroy vegetation that is listed under the Flora and 

Fauna Guarantee Act 1988 or the Environment Protection and Biodiversity 

Conservation Act 1999, further consent in writing must be obtained from the 

Department of Sustainability and Environment.

Page 167: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix D Page 165

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

APPENDIX D ENVIRONMENTAL MANAGEMENT PLAN (PREPARED BY THE PROPONENT)

Anna Williams of Freehills (acting for RES Australia) emailed Planning Panels 

Victoria on 28 July 2010, attaching a file titled “EMP information final” and with 

the following relevant comment in the text of the email: 

“In response to your email below, please find attached the EMP (including 

the changes requested by the Panel) and the draft permit conditions.  In the 

draft permit conditions, text in mark‐up (without highlight) and text 

highlighted in yellow was discussed during the panel hearing.  Text 

highlighted in green has been inserted subsequent to the panel and reflects 

RES’ further submissions.” 

The text of the electronic document is copied below.  The copying process has 

resulted in text in Appendix B exactly as received electronically by the Panel on 

28 July 2010.  A hard copy of the same document was provided at the Panel 

Hearing (Document No 28) that had tracked changes in blue, but the tracked 

changes were accepted in the document emailed to the Panel on 28 July 2010. 

Ararat Wind Farm

Environmental Management Plan

(mitigation, monitoring, enforcement and rehabilitation)

Preamble

This Environmental Management Plan (EMP) is at the Panel Hearing stage and 

will be added to or revised as further information becomes available.  It is 

subject to the requirements of the permit conditions and it is anticipated that 

should the proposed Ararat Wind Energy Facility be approved, the planning 

permit conditions will require the review and updating of this EMP in 

accordance with any permit conditions. 

Furthermore, as a live document, the EMP will also be revised, where 

applicable, in response to any micro‐siting of wind farm infrastructure. 

Before the development starts, an environmental management plan (EMP) shall 

be prepared to the satisfaction of the Minister for Planning, in consultation with 

the Department of Sustainability and Environment, the Ararat Rural City 

Page 168: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix D Page 166

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Council, the Northern Grampians Shire, Country Fire Authority and other 

agencies as specified in the Planning Permit conditions or as further directed by 

the Minister for Planning.  The EMP shall be based on the approach outlined in 

Chapter 6.2.9 of the report titled Ararat Wind Farm, Planning Permit 

Application Documentation, Volume 1, dated January 2010.  The EMP may be 

prepared in sections or stages.  When approved, the plan will be endorsed by 

the Minister for Planning and will then form part of this permit. 

The EMP will require progressive development as design and construction 

proceed, but will at any point in time, provide a clear statement of the project’s 

environmental commitments. 

The Directions of the Panel for the Ararat Wind Farm Panel Hearing, dated 31 

May, 2010 states: 

“… Matters to be addressed at the Hearing 

5. In submitting to the Panel, RES Australia should address the following particular matters at the Hearing: 

a.  A response to the revised Policy and Planning Guidelines for 

Wind Energy Facilities (September 2009), both generally and in 

particular relating to the preparation of an EMP (see below 

under b); 

b.  Concerning the Pre‐Construction and construction phase, there 

is a summary treatment of “Environmental Mitigation and 

Management Measures” (pages 85 – 89), but no monitoring 

proposals.  The application requirements for a Wind Energy 

Facility includes “An environmental management plan 

including any rehabilitation and monitoring.” (quoted on page 

141 of the Main Report).  No such plan has been provided for 

the operational phase, merely a commitment to make one at a 

later date.  The proponent is requested to provide further detail 

for the EMP at each of the Pre‐Construction and construction 

phase, and the operational phase.  These EMPs will require 

progressive development as design and construction proceed, 

but should, at any point in time, provide a clear statement of the 

proponent’s commitments.  Where the detail is not yet available, 

principles or an indicative summary should be provided.  The 

recommendations in the consultant reports should be listed in 

the relevant part of the EMP and clarification provided whether 

the proponent commits to them, or merely notes them as being a 

matter for reference.  Monitoring measures should be detailed 

where possible.  Turbine noise is one particular area where the 

proposed monitoring should be detailed.  The points raised in 

Page 169: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix D Page 167

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

submissions, and particularly the requirements of referral 

authorities and agencies should also be considered in the EMP 

and detailed.  …”

In addition to the EMP Framework provided in Section 6.2.9 of the report titled 

Ararat Wind Farm, Planning Permit Application Documentation, Volume 1, 

dated January 2010, RES Australia commits to the following plans, procedures, 

monitoring, enforcement and rehabilitation measures during each of the phases 

of development, being: 

Pre‐Construction Phase; 

Construction Phase; 

Operational Phase; and 

Decommissioning and Site Rehabilitation phase. 

Furthermore, any monitoring programs, complaints and incidents registers will 

be provided to the DPCD at a time stipulated by this EMP or upon request by 

the DPCD to be made available for public inspection at the Department. 

Page 170: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix D Page 168

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Environmental Management Plan

Pre-Construction Phase (P-C) Content to include Requirement / Recommendation of

P-C Timetable for implementation of all programs and works.

The timetable will be in the form of a Gantt Chart that shows the programs and works to be completed during Pre-Construction phase.

It will be aimed to ensure safety in design principles are upheld throughout all programs and works.

Department of Sustainability and Environment

(Based on the DPCD’s Model Wind Energy Conditions, February 2009)

P-C Flowchart of responsibility The flowchart will show the persons (and their respective titles) responsible for managing the EMP and coordinating the project design

P-C Training and induction program

This program will be provided to the designers and people involved within the design and Pre-Construction phase and will detail any relevant site specific matters, such as European heritage, Aboriginal cultural heritage, areas of environmental sensitivity, fire issues, geology and hydrology, traffic and transport issues and Pre-Construction issues.

Department of Sustainability and Environment

(Based on the DPCD’s Model Wind Energy Conditions, February 2009)

P-C Landscape/visual amenity plan

An on-site landscape will be prepared to the satisfaction of the Minister for Planning. When approved, the plan will be endorsed and will then form part of the permit. The plan will include:

a) landscaping to screen the substation, switchyard and associated buildings other than the turbines;

b) details of plant species proposed to be used in the landscaping, including height and spread at maturity;

c) a timetable for implementation of all landscaping works;

d) a maintenance and monitoring program; and

e) surfacing of access tracks in a manner which does not unduly contrast

Department of Sustainability and Environment

(Based on the DPCD’s Model Wind Energy Conditions, February 2009

Page 171: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix D Page 169

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Pre-Construction Phase (P-C) Content to include Requirement / Recommendation of

with the landscape.

If an off-site program of voluntary landscape mitigation works is accepted by one or more owners as set out in the permit, RES will prepare an off-site landscaping plan in consultation with those landowners and to the satisfaction of the Minister for Planning. When approved the plan will be endorsed and will then form part of the permit.

The off-site landscaping plan will provide details of planting or other treatments that will be used to reduce the visual impact of the wind turbines at the dwellings of the participating landowners.

P-C Native Vegetation Offset Management Plan.

Prior to clearing any native vegetation, this plan be prepared by a suitably qualified ecological specialist and will identify appropriate offset options to achieve the offset targets recommended in the Flora and Fauna Assessment.

It will be submitted to the Department of Sustainability and Environment for approval and will include:

a) Details of the proposed offsets which will achieve a net gain in quality and quantity of native vegetation in accordance with the principles and guidelines associated with the Native Vegetation Management: A Framework for Action (DSE 2002) and the periodic updating of this work as necessary.

b) Fully dimensioned plans (drawn to an appropriate scale), which clearly show the locations, boundaries and title details of all offset sites. The plans must also clearly show the boundaries of any different management zones and the location of any proposed fencing.

c) Type of offsets to be provided for each location.

(Based on the DPCD’s Model Wind Energy Conditions, February 2009)

All of the recommendations in the Flora and Fauna Assessment by Brett Lane and Associates (set out in part 8) will be adopted by RES

Page 172: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix D Page 170

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Pre-Construction Phase (P-C) Content to include Requirement / Recommendation of

d) Details of revegetation including number of trees, shrubs and other plants, species mix and density.

e) Methods of managing and restoring the vegetation, including revegetation, such as fencing, weed control, enhancement planting and other habitat management actions.

f) A statement of the need for revegetation works to be carried out by a suitably qualified ecological specialist.

g) Persons responsible for implementing and monitoring the offset plan.

h) A time frame for implementing the offset plan

P-C Carry out further Aboriginal cultural heritage assessment

The further assessment will take approximately four to five weeks and will be carried out by a field team comprising two archaeologists and one Registered Aboriginal Party representative. If the fieldwork is unable to satisfactorily identify the nature, extent and significance of Aboriginal cultural heritage, additional assessment may be required to fulfil r.61 Aboriginal Heritage Regulations 2007. However, this is only to occur if unexpected Aboriginal cultural heritage is found during the further assessment.

The further assessment will involve carrying the following work:

• Carry out detailed mapping and investigation of surface features including:

- quartz outcrops which have some potential or superficial evidence of working; and

- high density scatters of coarse fragments.

• Site investigation will involve the detailed mapping of quartz distribution

All of the recommendations in Aboriginal Cultural Heritage Standard Assessment report (set out in part 6.2) will be adopted by RES.

Page 173: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix D Page 171

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Pre-Construction Phase (P-C) Content to include Requirement / Recommendation of

and detailed sampling and analysis of quartz fragments to determine their cultural / non-cultural status.

• A specialist in quartz quarries and stone artefact analysis will participate in this fieldwork and analysis.

• If any location is assessed to be an Aboriginal site, then subsurface testing may be carried out to determine if there are any subsurface archaeological remains.

• The following subsurface testing will be conducted:

- At depositional landforms assessed as having potential for the presence of subsurface stone artefact scatters. These areas include plains within 100m of watercourses and minor swamps / wetlands.

- A small control sample of subsurface testing at proposed development locations assessed as having very low potential archaeological sensitivity.

• Subsurface testing will comprise a combination of controlled hand excavated 1m x 1m test pits and 50cm x 50cm probes down to underlying substrate. Excavations will be conducted according to proper archaeological practise.

Archaeological works and plans to be monitored and approved by the Registered Aboriginal Party and Aboriginal Affairs Victoria.

P-C Traffic and transport management plan

The plan will be developed in consultation with Ararat Rural City Council, VicRoads and VicRail and must be approved by DPCD. It will include the following measures and information:

• Traffic movements of over-size and over-mass vehicles minimised during

All of the recommendations in the Traffic and Transport Assessment (set out in section 7) will be adopted by RES.

Page 174: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix D Page 172

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Pre-Construction Phase (P-C) Content to include Requirement / Recommendation of

peak times.

• Pilot and Escort vehicles will be used in accordance with VicRoads requirements.

• Access routes will be determined in consultation with the local Ararat Rural City Council and VicRoads. All over-size and over-mass vehicles are to use the approved routes.

• Existing and designated tracks and roads will be used for access (unless in an emergency) during all project activities.

• Appropriate signage will be erected, as required by relevant authorities in relation to the proposed Ararat Wind Farm.

• Materials and equipment will be sourced, where practical, from within the subject site and the surrounding local area, thus reducing total haulage traffic.

• Regular inspections of access roads and tracks will be carried out during construction activities and road maintenance work will be completed as required.

• Roads and access will be maintained during the construction phase of the project, and will be carried out in consultation with the Council and VicRoads, and to appropriate road standards.

• Site personnel will be instructed to employ safe driving and operating practices at all times.

• Appropriate public notice should be provided if significant public inconvenience is expected to occur during construction activities.

Page 175: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix D Page 173

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Pre-Construction Phase (P-C) Content to include Requirement / Recommendation of

• Temporary traffic control measures during the construction phase to accommodate oversize and overmass vehicle access (e.g. one-way operation of certain roads during times used by oversize or overmass delivery vehicles).

• Plans in accordance with VicRail consultations.

P-C Sediment, erosion and water quality management plan.

This plan will be developed in consultation with the relevant Catchment Management Authorities and must be approved by the DPCD. It will include:

• A soil and water management plan, which will outline a strategy for the management of soil and water resources within the project area.

• A water quality monitoring program to ensure erosion prevention measures and remedial actions are maintained and are effective.

• Detailed design of the site drainage system.

• Results of geotechnical investigations to identify soils of erosion or dispersion risk and enable safe and efficient design of turbine foundations, tracks, hardstandings and site buildings.

• Results of construction monitoring program.

• Requirements to:

- identify, prior to the on-ground siting of access tracks and earthworks, areas known to be particularly or potentially prone to erosion and avoid those areas where possible.

- stockpile topsoil requiring removal separately from excavation spoil, with spoil and topsoil backfilled in a manner which does not result in soil inversion (i.e. to ensure soil layers are backfilled in the correct

Department of Sustainability and Environment

(Based on the DPCD’s Model Wind Energy Conditions, February 2009)

All of the recommendations in the Geology and Hydrology Assessment (parts 4, 5, 6 and 7) will be adopted by RES

Page 176: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix D Page 174

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Pre-Construction Phase (P-C) Content to include Requirement / Recommendation of

order) or erosion.

- fit erosion and sediment control devices (e.g. hay bales) down slope of construction-sites (where required) to prevent erosion events and capture potential sediment wash and regularly maintain these devices.

- keep and maintain spill kits at storage areas and works areas where hazardous materials occur or are handled.

- regularly inspect construction sites to detect any erosion events. If such events occur, remedial action will be undertaken. This will include soil stabilisation measures such as revegetation or laying physical stabilisation material followed by revegetation.

- if an incident occurs that adversely impacts on soil or surface water, review management procedures to ensure no recurrence of the incident.

- manage hazardous materials, waste and sewage to ensure no contamination of soils occur.

- appropriately transport and store all hazardous products in accordance with relevant guidelines and regulations to avoid release to the environment.

- properly classify and appropriately store all hazardous materials, with incompatible materials stored separately from one another. Fuels and oils will be stored in bunded areas.

- handle and utilise all hazardous materials in accordance with statutory regulations and label instructions. All personnel handling and using hazardous chemicals will be appropriately trained.

Page 177: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix D Page 175

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Pre-Construction Phase (P-C) Content to include Requirement / Recommendation of

- train employees who handle, transport or utilise hazardous materials in emergency response for spill events.

- regularly inspect hazardous materials storage and usage areas, and equipment utilising hazardous materials, to detect leakage or misuse.

- investigate incidents involving the mishandling, transportation or inadequate storage of hazardous materials and implement appropriate remedial action.

- leave the amount of exposed earth as a result of clearing to a minimum.

- employ, during working times, specified dust suppression techniques to exposed surfaces potentially causing significant dust emissions, including:

- dust mitigation measures; and

- limiting traffic access across exposed surfaces.

- implement remedial action where vegetation is impacted by excessive dust emissions. In this event, also carry out a review of operational procedures and dust suppression techniques to avoid recurrence of the event.

- locate material Stockpiles on cleared agricultural land, wherever possible and no closer than 5m of trees, to avoid the effects of soil compaction upon trees and native vegetation understorey.

- avoid locating stockpiles where they can significantly affect native vegetation associations or in areas that threaten loss of stockpile

Page 178: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix D Page 176

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Pre-Construction Phase (P-C) Content to include Requirement / Recommendation of

material through natural processes.

- minimise stockpile numbers.

- reinstate compacted areas resulting from the storage of stockpiles, site facilities and wind farm components in consultation with relevant landowners.

P-C Television and radio reception survey

This survey will identify households that will/are experiencing television and/or radio reception difficulties as a result of the wind farm and will include a commitment to provide specified mitigation measures to rectify those difficulties where appropriate.

The survey will be provided to DPCD and will include as a minimum:

a) A definition of the area to be covered by the television and radio reception plan (the defined area) based on the recommendations of a suitably qualified expert

b) A Pre-Construction survey to determine television and radio reception strength at locations within the defined area, completed prior to the commissioning of any turbine. The location of such monitoring is to be determined by an independent television and radio monitoring specialist appointed by the wind energy facility operator

(Based on the DPCD’s Model Wind Energy Conditions, February 2009).

All of the recommendations set out in the Electromagnetic Interference Assessment (section 4.3) will be adopted by RES.

Page 179: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix D Page 177

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Construction Phase (C) Content to include Requirement / Recommendation of

C Training and induction program for workers

This program will be provided to the construction workers and will detail any relevant site specific matters, such as European heritage, Aboriginal cultural heritage, areas of environmental sensitivity, fire issues, geology and hydrology, traffic and transport issues and construction health, safety and quality issues.

The program will also involve providing site rules and enforcement measures to all workers.

Department of Sustainability and Environment

(Based on the DPCD’s Model Wind Energy Conditions, February 2009)

C Flowchart of responsibility. The flowchart will show the persons (and their respective titles) responsible for managing the EMP during the construction phase.

C Construction and work site management plan.

The timetable will be in the form of a Gantt Chart that shows the programs and works to be completed during construction phase.

The plan will include details of health, safety and quality management measures.

This plan will identify all EMP obligations that are required during the construction phase and will include:

• procedures for access, noise control, dust emissions, spills and leaks from the handling of fuels and other hazardous materials and pollution management. Such construction and work site procedures are to be in accordance with EPA requirements;

• the identification of all potential contaminants stored on site;

• the identification of all construction and operational processes that could potentially lead to water contamination;

Department of Sustainability and Environment

(Based on the DPCD’s Model Wind Energy Conditions, February 2009)

Page 180: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix D Page 178

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Construction Phase (C) Content to include Requirement / Recommendation of

• the identification of appropriate storage, construction and operational methods to control any identified contamination risks;

• the identification of waste re-use, recycling and disposal procedures;

• appropriate sanitary facilities for construction and maintenance staff in accordance with the EPA Publication 891.1 Septic Tanks Code of Practice;

• a timetable, where practicable for the construction of turbine bases, access tracks and power cabling during warmer months to minimise impacts on ephemeral wetlands, local fauna and sediment mobilisation;

• procedures to ensure that construction vehicles and equipment use designated tracks and works areas to avoid impacts on native vegetation

• procedures to protect, as far as practicable, native fauna and domestic stock from being injured by or entrapped in excavations or trenches and to fill trenches as soon as practical after excavation; and

• the removal of works, buildings and staging area on completion of construction of the project.

C Sediment, erosion and water quality management plan.

Prior to the Construction Phase, where relevant the matters listed for this area in the Pre-Construction phase will be repeated here, together with monitoring and compliance provisions

All of the recommendations in the Geology and Hydrology Assessment (parts 4, 5, 6 and 7) will be adopted by RES.

Page 181: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix D Page 179

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Construction Phase (C) Content to include Requirement / Recommendation of

C Blasting plan. The plan will include measures to control noise, dust and vibration impact of any blasting. It will also include remedial action where any complaints from blasting impacts are received and will include:

• name and qualification of the person responsible for blasting;

• a description of the location of where the explosives will be used, and the location of every licensed bore on any property with an adjoining boundary within 1km of the location of the blasting;

• a requirement for the identification and assessment of any potentially sensitive site within 1 km of the location of the blasting, including the procedure for pre-blast and post-blast qualitative measurement or monitoring at such site;

• the procedure for site clearance and post blast reoccupation;

• the procedure for the storage and handling of explosives;

• a requirement that blasting only occur after at least 48 hours prior notification in writing of the intention to undertake blasting has been given to the occupants of the properties which are located in whole or in part within 1km of the location of the proposed blasting; and

• a requirement that blasting only be undertaken between the hours of 8am and 4pm.

Department of Sustainability and Environment

(Based on the DPCD’s Model Wind Energy Conditions, February 2009)

C Fire prevention and emergency response plan

This plan will be prepared in consultation with and to the satisfaction of the Country Fire Authority, the Department of Sustainability and Environment, and the Ararat Rural City Council. This plan is to include:

• criteria for the provision of static water supply tanks solely for fire fighting

Department of Sustainability and Environment

(Based on the DPCD’s Model Wind Energy Conditions, February 2009)

Page 182: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix D Page 180

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Construction Phase (C) Content to include Requirement / Recommendation of

purposes, including minimum capacities, appropriate connections and signage,

• procedures for vegetation management, fuel control and the provision of fire fighting equipment during declared fire danger periods;

• minimum standards for access roads and tracks to allow access for fire fighting vehicles including criteria for access to static water supply tanks for fire fighting vehicles;

• the facilitation by the operator, within 1 month prior to the commencement of the operation of the wind energy facility, of a familiarisation visit to the site and explanation of emergency services procedures for the Country Fire Authority, Rural Ambulance Victoria, State Emergency Services, Department of Sustainability and the Environment, the Ararat Rural City Council Municipal Emergency Management Committee and Victoria Police;

• subsequent familiarisation sessions for new personnel of those organisations on a regular basis and/or as required; and

• if requested, training of authority personnel in relation to suppression of wind energy facility fires.

C Hydrocarbon and hazardous substances plan.

The plan will include:

• procedures for the control of pest animals, particularly by avoiding opportunities for the sheltering of pests; and

• follow-up pest animal control for all areas disturbed by the wind energy facility construction works for a period of two years following the completion of the wind energy facility.

Department of Sustainability and Environment

(Based on the DPCD’s Model Wind Energy Conditions, February 2009)

Page 183: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix D Page 181

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Construction Phase (C) Content to include Requirement / Recommendation of

C Native vegetation management plan.

The plan will include:

• protocols to achieve the required net gains if native vegetation disturbance and removal cannot be avoided for the construction, operation and decommissioning stages of the project;

• procedures for the rehabilitation of construction zones with appropriate pasture species or, if in areas of native vegetation, appropriate indigenous revegetation; and

• procedures for ensuring that native vegetation near turbines, access tracks, underground cabling and other wind farm infrastructure will not be adversely affected by construction and operation of the wind farm.

Department of Sustainability and Environment

(Based on the DPCD’s Model Wind Energy Conditions, February 2009).

All of the recommendations in the Flora and Fauna Assessment by Brett Lane and Associates (set out in part 8.1.5) and the BL&A Expert Witness Report (Section 4) will be adopted by RES.

C Pest animal management plan. The plan will include:

• procedures for the control of pest animals, particularly by avoiding opportunities for the sheltering of pests; and

• follow-up pest animal control for all areas disturbed by the wind energy facility construction works for a period of two years following the completion of the wind energy facility.

Department of Sustainability and Environment

(Based on the DPCD’s Model Wind Energy Conditions, February 2009).

The recommendations in Brett Lane’s Expert Witness Statement regarding pest management plan (set out in part 4) will be adopted by RES

Page 184: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix D Page 182

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Construction Phase (C) Content to include Requirement / Recommendation of

C Pest plant management plan. The plan will include:

• procedures to prevent the spread of weeds and pathogens from earth moving equipment and associated machinery including the cleaning of all plant and equipment before transport to the site and the use of road making material comprising clean fill that is free of weeds;

• revegetation of disturbed areas as described in Condition 11 f(ii); and

• a protocol to ensure follow-up weed control is undertaken on all areas disturbed through construction of the wind energy facility for a minimum period of 2 years following completion of the works.

Department of Sustainability and Environment

(Based on the DPCD’s Model Wind Energy Conditions, February 2009).

The recommendations in Brett Lane’s Expert Witness Statement regarding pest management plan (set out in part 4) will be adopted by RES

C Incident management plan This register will include any environmental incidents, non-conformances, complaints, corrective actions and notification requirements

The register will be attached to the EMP and provided to DPCD upon request and will include:

• A procedure for the establishment and maintenance of an incident register for the recording of: o Environmental incidents o Non�conformances, and o Corrective actions.

The register must be available for inspection by the public during normal working hours and its contents should be reported to the responsible authority as required.

Records of any complaints received and corrective actions undertaken will also be provided to DPCD upon request.

Department of Sustainability and Environment

(Based on the DPCD’s Model Wind Energy Conditions, February 2009)

Page 185: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix D Page 183

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Operation Phase (O) Content to include Requirement

O Training and induction program for workers.

This program will be provided to all employees, contractors and will detail any relevant site specific matters, such as European heritage, Aboriginal cultural heritage, areas of environmental sensitivity, fire issues, geology and hydrology, traffic and transport issues and construction health, safety and quality issues.

The program will also involve providing site rules and enforcement measures to all workers and visitors.

Department of Sustainability and Environment

(Based on the DPCD’s Model Wind Energy Conditions, February 2009)

O Flowchart of responsibility The flowchart will show the persons (and their respective titles) responsible for managing the EMP during the operation phase.

O Noise compliance testing plan Prior to operation, this plan will be prepared by a suitably qualified acoustic expert to the satisfaction of the Minister for Planning.

The plan will detail the results from the noise compliance assessment that show the wind farm’s level of compliance with applicable acoustic standards.

(Based on the DPCD’s Model Wind Energy Conditions, February 2009).

O Noise compliance enforcement procedures plan

This plan outline relevant individuals’ responsibilities in ensuring noise compliance, reporting protocols and procedures to investigate and report on noise complaints and require the implementation of corrective and preventative action as appropriate.

(Based on the DPCD’s Model Wind Energy Conditions, February 2009).

O Bat and avifauna management plan

A bat and Avifauna Management Plan (BAM Plan) will be prepared in consultation with the Department of Sustainability and Environment to the satisfaction of the Minister for Planning. The BAM Plan will include:

• a statement of the objectives and overall strategy for managing and mitigating any significant bird and bat strike arising from the wind energy facility operations;

Department of Sustainability and Environment

(Based on the DPCD’s Model Wind Energy Conditions, February 2009)

Page 186: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix D Page 184

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Operation Phase (O) Content to include Requirement

• a monitoring program of at least 2 years duration , either commencing upon the commissioning of the last turbine of the first stage of the approved development and use (if any) or alternatively such other time of commencement as is to the satisfaction of the Minister for Planning.

• the monitoring program must include surveys during breeding and migratory seasons to ascertain:

o the species, number, age, sex (if possible) and date of any bird or bat strike;

o the number and species of birds and bats struck at lit versus unlit turbines;

o any seasonal and yearly variation in the number of bird and bat strikes;

o whether further detailed investigations of any potential impacts on birds and bats are warranted.

• any such required further detailed investigations are to be undertaken in consultation with the Department of Sustainability and Environment and to the satisfaction of the Minister for Planning;

• procedures for the reporting of any bird and bat strikes to the Department of Sustainability and Environment within 7 days of becoming aware of any strike identifying where possible whether the strike was by a lit or unlit turbine;

• information on the efficacy of searches for carcasses of birds and bats, and, where practicable, information on the rate of removal of carcases by scavengers, so that correction factors can be determined to enable calculations of the total number of mortalities;

The recommendations in Brett Lane’s Expert Witness Statement regarding Bat and avifauna management plan (set out in part 4) will be adopted by RES

Page 187: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix D Page 185

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Operation Phase (O) Content to include Requirement

• procedures for the regular removal of carcasses likely to attract raptors to areas near turbines;

• procedures for periodic reporting, within agreed timeframes, of the findings of the monitoring to the Department of Sustainability and Environment;

• recommendations in relation to a mortality rate for specified species which would trigger the requirement for responsive mitigation measures to be undertaken by the operator of the wind energy facility to the satisfaction of the Minister for Planning; and

• implementation measures developed in consultation with the Department of Sustainability and Environment to offset any impacts detected during monitoring including turbine operation management and on-site or off-site habitat enhancement (including management or improvement of habitat or breeding sites).

• following the completion of the monitoring program, a report will be prepared by the operator of the wind energy facility setting out the findings of the program to the satisfaction of the Minister for Planning. If, after consideration of this report, the Minister for Planning directs that further investigation of potential or actual impacts on birds and bats is to be undertaken, the extent and details of the further investigation must be to the satisfaction of the Department of Sustainability and Environment and the investigation must be carried out to the satisfaction of the Minister for Planning.

Page 188: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix D Page 186

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Operation Phase (O) Content to include Requirement

O Television and radio reception plan

This plan will identify any households that are experiencing television and/or radio reception difficulties as a result of the wind farm and will include a commitment to provide specified mitigation measures to rectify those difficulties where appropriate.

The plan will be provided to DPCD and will include as a minimum:

a) A procedure for post-construction survey at any dwelling in the defined area that existed at the date of the Pre-Construction survey in response to any complaint received regarding the wind energy facility having an adverse effect on television or radio reception

b) A procedure for the implementation of mitigation measures at any dwelling in the defined area that existed at the date of the Pre-Construction survey if the post-construction survey establishes any increase in interference to reception as a result of the wind energy facility operations. The mitigation measures shall return the affected reception to Pre-Construction quality and be undertaken at the cost of the wind energy facility operator, all to the satisfaction of the Minister for Planning

(Based on the DPCD’s Model Wind Energy Conditions, February 2009).

All of the recommendations set out in the Electromagnetic Interference Assessment (section 4.3) will be adopted by RES.

O CASA-endorsed nacelle lighting plan, should night lighting of the wind farm be required

This plan will include a revised CASA-endorsed nacelle lighting plan that relates to the approved and constructed turbine layout.

A copy of the revised CASA-endorsed plan will be provided to DPCD, ARCC and NGSC.

All of the recommendations of the Aviation Assessment (particularly section 3) will be adopted by RES.

Page 189: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix D Page 187

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Operation Phase (O) Content to include Requirement

O Bushfire mitigation plan This plan will be developed in consultation with the CFA and in accordance with the Electricity Safety Act and will be provided to Energy Safe Victoria for approval.

It will detail operational activities that will employ best practice with regard to fire management.

Country Fire Association (in its submission to PPV).

O Sediment, erosion and water quality management plan.

Refer to content set out in the Pre-Construction phase above. All of the recommendations in the Geology and Hydrology Assessment (parts 5, 6 and 7) will be adopted by RES.

O Complaints and incidents register

This register will include any environmental incidents, non-conformances, complaints, corrective actions and notification requirements.

The register will be attached to the EMP and provided to DPCD upon request.

Records of any complaints received and corrective actions undertaken will also be provided to DPCD upon request.

Department of Sustainability and Environment

(Based on the DPCD’s Model Wind Energy Conditions, February 2009

Page 190: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix D Page 188

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Decommissioning Phase (C) Content to include Requirement

D Training and induction program This program will be provided to all employees and will detail any relevant site specific matters, such as European heritage, Aboriginal cultural heritage, areas of environmental sensitivity, fire issues, geology and hydrology, traffic and transport issues and construction health, safety and quality issues.

The program will also involve providing site rules and enforcement measures to all workers.

Department of Sustainability and Environment

(Based on the DPCD’s Model Wind Energy Conditions, February 2009)

D Decommissioning plan The timetable will be in the form of a Gantt Chart that shows the programs and works to be completed during decommissioning phase.

The plan will detail the methodology for removing all above-ground infrastructure and will include details on health, safety and quality management measures.

The plan will be submitted for to the Minister for Planning for approval.

(Based on the DPCD’s Model Wind Energy Conditions, February 2009)

D Site rehabilitation plan The plan will detail the methodology for removing infrastructure and return specified lands to pasture (i.e. turbine foundations, anemometer foundations, internal overhead powerline locations and electrical substation location). In particular, the plan will include:

Turbines: Removal of all turbine infrastructure and recycling of materials. Foundations to be covered with topsoil and returned to pasture.

Anemometers: Removal of Anemometer infrastructure. Foundations to be covered with topsoil and returned to pasture.

Underground Cabling: Will remain in-situ.

Proposed by RES

Page 191: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix D Page 189

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Decommissioning Phase (C) Content to include Requirement

Overhead Powerlines: Removal of internal powerline infrastructure within the wind farm.

Access Tracks: Will remain for the benefit of the landowner to maintain access throughout property.

Substation: Substation infrastructure to be removed. Foundations to be covered with topsoil and returned to pasture.

Maintenance and Servicing Facility: Decommission communications equipment. Building and storage facility can remain for benefit of landowner.

D Decommissioning traffic management plan

This plan will detail traffic and transport management measures for removal of oversize and overmass turbine components from the site to recycling / re-use and disposal facilities.

It will be prepared in consultation with VicRoads, ARCC and VicRail and will be submitted to the Minister for Planning for approval.

(Based on the DPCD’s Model Wind Energy Conditions, February 2009).

All of the recommendations in the Traffic and Transport Assessment (set out in section 7) will be adopted by RES.

D Complaints and incidents register

This register will include any environmental incidents, non-conformances, complaints, corrective actions and notification requirements.

The register will be attached to the EMP and provided to DPCD upon request.

Records of any complaints received and corrective actions undertaken will also be provided to DPCD upon request.

Department of Sustainability and Environment

(Based on the DPCD’s Model Wind Energy Conditions, February 2009)

Page 192: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix E Page 190

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

APPENDIX E RECOMMENDED PLANNING PERMIT

Note:  the permit covering that part of the Ararat WEF within the Northern Grampians 

Shire will be identical, save for the property addresses and the number of 

turbines being specified as 5 (rather than 70). 

 

PLANNING PERMIT  Permit No.: 09/004799 

Planning Scheme: Ararat Planning Scheme 

Responsible Authority for Administration and Enforcement 

of this Permit: Ararat Rural City Council 

ADDRESS OF THE 

LAND: 

Note to DPCD: Repeat the addresses previously provided 

THE PERMIT ALLOWS:  The use and development of a wind energy facility 

comprising 70 generators and associated infrastructure 

including access roads, cabling, permanent anemometers, 

internal powerlines, substations, excavation of rock 

material, earthworks, temporary concrete batching plants, 

maintenance and storage facilities, car parking, removal of 

native vegetation and alterations to roads and access to 

roads within a Road Zone Category 1. 

THE FOLLOWING CONDITIONS APPLY TO THIS PERMIT: 

DEVELOPMENT PLANS TO BE ENDORSED 

1.  Before the development starts (following Pre‐Construction phase preliminary 

investigative works and the carrying out of detailed design works), Development 

Plans must be prepared to the satisfaction of the Minister for Planning.  The plans 

must be drawn to scale with dimensions and graphic scale.  Three copies must be 

provided.  The plans may be submitted for approval in stages or for a particular 

grouping of wind turbines within the subject land.  When approved, the plans will 

be endorsed by the Minister for Planning and will then form part of this permit.  

The plans must show the location and layout of the wind turbines and all on‐site 

buildings and works generally in accordance with Figure 2.2 of the application 

plans. 

The plans must also include: 

Page 193: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix E Page 191

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

(a)  A list of map coordinates for each wind turbine; 

(b)  The distance of each wind turbine from the nearest point on the site 

boundary as depicted in Figure 2.2 of the application plans; 

(c)  Details of the model and rated capacity of the wind turbines to be installed; 

(d)  Elevation drawings, showing dimensions, of the wind turbines and other 

permanent on‐site buildings (e.g. substation facilities); 

(e)  Drawings, showing the key physical dimensions, of all on‐site buildings and 

works including: 

(i)  Wind turbines; 

(ii)  Access tracks; 

(iii)  Internal collector network trenches; 

(iv)  Any temporary concrete batching plant(s); 

(v)  The substation (including designated car parking areas, signage and 

landscaping);  

(vi)  Any ancillary works (e.g. temporary facilities and operations within the 

construction compounds); and 

(vii)  The infrastructure zone. 

(f)  A description of the materials and finishes of the wind turbine towers, 

nacelles, rotor blades and other permanent on‐site buildings.  The wind 

turbine towers, nacelles and rotor blades must be of a non‐reflective finish 

and colour; 

(g)  A description of the location, type and intensity of any aviation obstacle 

lighting to be installed 

(h)  The locations of scattered native trees and the boundaries of any patches of 

native vegetation, in relation to all buildings and works, in all cases where 

such trees and patches are within 25 metres of the buildings or works 

(i)  Drawings demonstrating that the placement of turbine locations will not 

interfere with the exclusion zones of any licensed communications links 

(j)  The location of all host dwellings and non‐host dwellings within 3km of the 

nearest turbine. 

(k)  The permitted use and development must be conducted in accordance with 

all plans that are endorsed under this permit 

2.  For the purposes of this permit, the carrying out of Pre‐Construction phase 

preliminary investigative works is approved and can be carried out before the 

plan(s) are endorsed under Condition 1.  The preliminary investigative works 

include sub‐surface geotechnical investigations for the purposes of gathering data 

Page 194: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix E Page 192

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

or making other assessments necessary or desirable in order to prepare the plan(s) 

under Condition 1 or other plans specified in this permit. 

SPECIFICATIONS 

3.  The wind energy facility must meet the following requirements: 

(a)  The wind energy facility must comprise no more than 70 wind turbines; 

(b)  The overall maximum height of the wind turbines (to the zenith of the sweep 

of the rotor blade tip) must not exceed 135 metres above foundation level; 

(c)  The wind turbines must be mounted on tubular towers; 

(d)  The diameter of the rotor of the wind turbines must not exceed 104 metres; 

(e)  The hub height of the of the wind turbines must not exceed 94 metres; 

(f)  The rotor of the wind turbines must have only three rotor blades; 

(g)  Access tracks within the subject land must, to the satisfaction of the 

responsible authority: 

(i)  have a surface material that will not unduly contrast with the landscape 

except where tracks need to be sealed;  

(ii)  be designed to minimise impact on the farming activities on the land; 

and 

(iii)  have an effective trafficable width of not less than 3 metres; 

(h)  The transformer associated with each wind turbine must be enclosed within 

the tower / nacelle or be located beside each tower and pad mounted; 

(i)  All new electricity cabling and powerlines associated with the internal 

collector network within the wind energy facility must be underground 

unless overhead powerlines are demonstrated to be necessary, and otherwise 

in accordance with the endorsed plans except with the further written 

consent of the Minister for Planning; 

(j)  Except in the case of an emergency or to accommodate the requirements of 

the network service provider, no external lighting of infrastructure 

associated with the wind energy facility, other than low level security 

lighting and aviation obstacle lighting as provided for in condition 3(m), may 

be installed or operated without the further written consent of the Minister 

for Planning; 

(k)  All spare parts and other equipment and materials associated with the use of 

the wind energy facility must be located in locked storage areas that are 

inaccessible to the public to the satisfaction of the responsible authority; 

(l)  All turbines must be located within the infrastructure zones shown on the 

endorsed plan(s); 

Page 195: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix E Page 193

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

(m)   Aviation obstacle lighting must not be installed unless the written consent of 

the Minister for Planning has been obtained. 

(n)  If, following the advice of a Quantitative Risk Assessment or the requirement 

of a regulatory authority, the Minister for Planning endorses the use of lights 

at Ararat WEF, they should be of the lowest intensity consistent with safety. 

Any lighting installed must conform with the requirements of the 

Environmental Management Plan. 

STAGING 

4.  The use and development authorised by this permit may be completed in stages as 

shown on the endorsed plan(s) to the satisfaction of the responsible authority.  

Any corresponding obligation arising under this permit (including the preparation 

and approval of plans) may be similarly completed in stages or parts. 

LAYOUT NOT ALTERED 

5.  The use and development shown on the plan(s) endorsed under this permit must 

not be altered or modified unless: 

(a)  the Minister for Planning has consented to the alteration or modification in 

writing; or 

(b)  the requirements of condition 13 are satisfied and complied with. 

6.  The use and development shown on the plan(s) endorsed under condition 1 may 

be altered or modified with the written consent of the Minister for Planning if: 

(a)  The Minister for Planning is satisfied that it will not give rise to any material 

adverse change in landscape, vegetation, cultural, visual, shadow or noise 

impacts compared to the endorsed plan(s); 

(b)  The turbines and wind energy facility infrastructure are located within the 

infrastructure zone;  

(c)  A turbine is not moved to within 1 kilometre of any non‐host dwelling;  

(d)  A turbine location is altered by no more than 100 metres; and 

(e)  No turbine base is located within: 

(i)  100 metres from a Road Zone Category 1 or land in a Public Acquisition 

Overlay to be acquired for a road; 

(ii)  40 metres from a Road Zone Category 2; 

(iii)  20 metres from any other road; 

(iv)  5 metres from the site boundary; 

(v)  100 metres from a dwelling that is not a host dwelling; 

Page 196: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix E Page 194

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

(vi)  50 metres from a waterway, wetlands or designated flood plain; or  

(vii)  within an exclusion zone of any licensed communications link. 

ENVIRONMENTAL MANAGEMENT PLAN 

7.  The “Environmental Management Plan at the Pre‐Construction Stage” must be 

endorsed by the Minister for Planning, and forms part of this permit.  Having 

regard to the fact that there are permits under each of two Planning Schemes for 

this wind energy facility, where a management plan is referred to below it applies 

equally to each permit. 

The environmental management plan must include a copy of the endorsed plans.  

The “Environmental Management Plan at the Pre‐Construction Stage” shall 

progressively be developed and renamed: 

(a) The Environmental Management Plan at the Construction Stage,  

(b) The Environmental Management Plan at the Operation Stage,  

(c) The Environmental Management Plan at the Decommissioning Stage,  

The “Environmental Management Plan at the Construction Stage” will delete the 

section titled “Pre‐Construction Phase” and include the outcomes of the Pre‐

Construction stage investigations and detailed design.  It must be endorsed by the 

Minister for Planning before any construction work commences. 

The “Environmental Management Plan at the Operation Stage” will delete the 

section titled “Construction Phase” and will include the outcomes of the 

construction stage.  It must be endorsed by the Minister for Planning before 

operation of the wind energy facility commences. 

The “Environmental Management Plan at the Decommissioning Stage” will delete 

the section titled “Operation Phase” and will include the outcomes of the 

operation stage.  It must be endorsed by the Minister for Planning before 

decommissioning commences. 

Prior to the endorsement of each of these renamed versions of the EMP by the 

Minister for Planning, the Department of Planning and Community Development 

will ensure that consultation with the relevant authorities including the 

Department of Sustainability and Environment, Ararat Rural City Council, 

Northern Grampians Shire Council, relevant Catchment Management Authorities 

and the Country Fire Authority has been undertaken. 

The “Environmental Management Plan at the Construction Stage” is arranged 

generally under a series of “plans”, which may include both specific measures 

(equivalent to permit conditions) and requirements for further development.  

Page 197: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix E Page 195

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

These plans cover the following (listed generally in the order they are addressed in 

the Report): 

a training and induction program; 

a native vegetation management plan; 

a Net Gain Offset management plan; 

a pest plant management plan; 

a bird and bat management plan; 

a pest animal management plan; 

an operational noise compliance testing plan; 

an operational noise compliance enforcement plan; 

a traffic and transport plan; 

a landscape and visual amenity plan; 

an aviation lighting plan, if lighting is approved by the Minister for Planning; 

a fire prevention and emergency response plan; 

a bushfire mitigation plan; 

a television and radio reception plan;  

a sediment, erosion and water quality management plan; 

a construction workforce accommodation assessment;  

the Aboriginal Cultural Heritage assessment; 

a construction and work site management plan; 

a blasting plan; 

a hydrocarbon and hazardous substances plan; 

an incident management plan; 

a decommissioning plan. 

ROADWORKS REQUIREMENTS (VICROADS) 

8.  The local roads identified in the Traffic and Transport Assessment Report (ref 

01732‐002820) that will be used to exit onto the arterial roads must be constructed 

to allow for the vehicle path and sealed back a minimum of 20 metres from edge of 

seal of the arterial road. 

Prior to the start of the development the developer must: 

(a)  Submit final detailed construction drawings of the altered intersections 

including line marking to be approved by VicRoads. 

(b)  Prepare a specification for the works in accordance with the relevant sections 

of the VicRoads’ Standard Specification For Roadworks. 

Page 198: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix E Page 196

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

All roadworks must be completed to the satisfaction of VicRoads prior to the 

commencement of the development.  The contractor must be VicRoads approved 

or prequalified at R1 level.  All works must be at the developers cost. 

BLADE SHADOW FLICKER 

9.  Shadow flicker from the wind energy facility must not exceed 30 hours per annum 

at any dwelling existing as at the date of this permit to the satisfaction of the 

Minister for Planning.  In determining compliance with this condition, the results 

of a geometric computer simulation model is evidence of compliance with this 

condition. 

Any dwelling within the Site Boundary will be exempt from this condition if it is 

the subject of an agreement with the landowner and is registered on title. 

NOISE LIMITS 

10  Construction of the wind energy facility must comply with noise criteria specified 

in the Interim  Guidelines for Control of Noise from Industry in Country Victoria, 

N3/89.  Compliance testing must be undertaken which conforms to State 

Environment Protection Policy (Control of Noise from Commerce, Industry and 

Trade) No N‐1 and the ‘Guide to the Measurement and Analysis of Noise’ 

accompanying the policy.  Compliance testing will be activated when a noise 

complaint is received during construction of the facility. 

11.  Except as provided below in this condition, the operation of the wind energy 

facility must comply with the noise criteria specified in NZS6808:1998 ‘Acoustics ‐ 

The Assessment and Measurement of Sound from Wind Turbine Generators’ at 

any dwelling existing on land in the vicinity of the proposed wind energy facility 

as at the date of the issue of this permit, to the satisfaction of the Minister for 

Planning. 

Compliance must be assessed separately for all‐time and night time.  For the 

purpose of this requirement, night time is defined as 10.00pm to 7.00am. 

Any dwelling on the subject land may be exempt from this condition.  This 

exemption will be given effect through an agreement with the landowner that 

must apply to any occupant of the dwelling and must be registered on title.  Such 

dwellings will be known as host dwellings. 

Prior to commencement of operations, an Operational Noise Compliance Testing 

Plan and an Operational Noise Compliance Enforcement Plan must be developed. 

12.  When a final turbine type is selected, the noise assessment, other than background 

noise monitoring, must be repeated.  The results of the new assessment must 

demonstrate compliance with the noise limits described in Condition 11 and be 

submitted to and approved by the Minister for Planning. 

Page 199: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix E Page 197

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

DECOMMISSIONING 

13.  The wind energy facility operator must, no later than one month after all wind 

turbines have permanently ceased to generate electricity, notify the Minister for 

Planning in writing of the cessation of the use.  Within a further six months of this 

date, the wind energy facility operator, or in the absence of the operator, the 

owner of the land on which the relevant turbines(s) is/are located, must develop 

the Decommissioning Plan to the satisfaction of the Minister for Planning.  

EXPIRY 

14.  This permit will expire if one of the following circumstances applies: 

(i)  the development is not started within 3 years of the date of this permit; 

(ii)  the development is not completed within 6 years of the date of this permit. 

The Minister for Planning may extend the periods referred to if a request is made 

in writing before the permit expires, or within three months afterwards.  

 

Notes: 

If it is proposed to removal or destroy vegetation that is listed under the Flora and 

Fauna Guarantee Act 1988 or the Environment Protection and Biodiversity 

Conservation Act 1999, further consent in writing must be obtained from the 

Department of Sustainability and Environment. 

Page 200: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix F Page 198

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

APPENDIX F RECOMMENDED “ENVIRONMENTAL MANAGEMENT PLAN AT THE PRE-CONSTRUCTION STAGE”

Preamble

This Environmental Management Plan (EMP) is at the Pre‐Construction (Permit 

Approval) stage and will be added to or revised as further information becomes 

available.  It is subject to the requirements of the permit conditions and should the 

Ararat Wind Energy Facility permit be amended or endorsed with a secondary 

consent, updating of this EMP in accordance with those amendments or 

endorsements will be required. 

Furthermore, as a live document, the EMP will also be revised, where applicable, in 

response to any micro‐siting of wind farm infrastructure. 

Before the development starts, the EMP shall be amended to the satisfaction of the 

Minister for Planning, in consultation with the Department of Sustainability and 

Environment, the Ararat Rural City Council, the Northern Grampians Shire Council, 

Country Fire Authority and other agencies as required as a result of the Pre‐

Construction investigations and detailed design, or as further directed by the 

Minister for Planning.  The EMP will require progressive development as design and 

construction proceed, but will at any point in time, provide a clear statement of the 

project’s environmental commitments. 

RES Australia commits to the following plans, procedures, monitoring, enforcement 

and rehabilitation measures during each of the phases of development, being: 

Pre‐Construction Phase; 

Construction Phase; 

Operational Phase; and 

Decommissioning and Site Rehabilitation phase. 

Furthermore, any monitoring programs, complaints and incidents registers will be 

provided to the DPCD at a time stipulated by this EMP or upon request by the 

DPCD, and will be made available for public inspection at the DPCD Ballarat Office. 

Page 201: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix F Page 199

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Environmental Management Plan

Pre-Construction Phase (PC) Content to include

PC Timetable for implementation of all programs and works.

The timetable will be in the form of a Gantt Chart that shows the programs and works to be completed during Pre-Construction phase.

It will be aimed to ensure safety in design principles are upheld throughout all programs and works.

PC Flowchart of responsibility The flowchart will show the persons (and their respective titles) responsible for managing the EMP and coordinating the project design

PC Training and induction program

This program will be provided to the designers and people involved within the design and Pre-Construction phase and will detail any relevant site specific matters, such as European heritage, Aboriginal cultural heritage, areas of environmental sensitivity, fire issues, geology and hydrology, traffic and transport issues and Pre-Construction issues.

PC Net Gain Offset Management Plan

Following the detailed design of all aspects of the facility, including the micro siting of turbines, the required roadworks on and off-site, and the final selection of access routes, a thorough review of the vegetation to be removed will be undertaken. In relation to clearing on access routes off-site, further route analysis will include trial runs to clearly identify native vegetation to be trimmed or removed. Prior to clearing any native vegetation, this plan will be prepared by a suitably qualified ecological specialist and will identify appropriate offset options to achieve the offset targets recommended in the Flora and Fauna Assessment, as amended by the review.

It will be prepared in consultation with the Department of Sustainability and Environment and will include:

a) Details of the proposed offsets which will achieve a net gain in quality and quantity of native vegetation in accordance with the principles and guidelines associated with the Native Vegetation Management: A Framework for Action (DSE 2002) and the periodic updating of this work as necessary.

b) Fully dimensioned plans (drawn to an appropriate scale), which clearly show the locations, boundaries and title details of all offset sites. The plans must also clearly show the boundaries of any different management zones and the location of any proposed fencing.

Page 202: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix F Page 200

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

c) Type of offsets to be provided for each location.

d) Details of revegetation including number of trees, shrubs and other plants, species mix and density (consistent with the characteristics of the relevant Ecological Vegetation Class).

PC Traffic and transport management plan

A specialist study of the risks associated with unsealed on-site access roads will be prepared, with recommendations for lengths of access roads that should be sealed for stability and safety. A copy of the report will be provided to the Responsible Authority, and its recommendations will be implemented.

A specialist study on the need to adopt minimum slopes for cut and fill of 2H:1V will be prepared, giving special consideration to the height of a number of the cuts and fills, the poor soil conditions, and the existing recommendation for such treatment of borrow pit batters. Its recommendations will be implemented.

A specialist study on the off-site access roads will be prepared, to determine whether alternative access to Site Entries 1 and 2 via Ben Nevis Road is warranted, and the need (taking into consideration both public safety and the likely deterioration of unsealed roads in wet weather) to seal Warrayatkin Road and also the unsealed portion of Buangor-Ben Nevis Road if it is determined that Buangor-Ben Nevis Road will be used for overmass vehicular access. Its recommendations will be implemented.

The Traffic and transport management plan will be guided by the outcomes of the three specialist studies above, and developed in consultation with Ararat Rural City Council, VicRoads and V/Line.

It will include the following measures and information:

• Traffic movements of over-size and over-mass vehicles minimised during peak times.

• Pilot and Escort vehicles will be used in accordance with VicRoads requirements.

• Access routes will be determined in consultation with the Ararat Rural City Council and VicRoads. All over-size and over-mass vehicles are to use the approved routes.

• Existing and designated tracks and roads will be used for access (unless in an emergency) during all project activities.

Page 203: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix F Page 201

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

• Appropriate signage will be erected, as required by relevant authorities in relation to the proposed Ararat Wind Farm.

• Site personnel will be instructed to employ safe driving and operating practices at all times.

• Materials and equipment will be sourced, where practical, from within the subject site and the surrounding local area, thus reducing total haulage traffic.

• Regular inspections of access roads and tracks will be carried out during construction activities and road maintenance work will be completed as required.

• Roads and access will be maintained during the construction phase of the project, and will be carried out in consultation with the Council and VicRoads, and to appropriate road standards.

• Site personnel will be instructed to employ safe driving and operating practices at all times.

• Appropriate public notice should be provided if significant public inconvenience is expected to occur during construction activities.

• Temporary traffic control measures during the construction phase to accommodate oversize and overmass vehicle access (e.g. one-way operation of certain roads during times used by oversize or overmass delivery vehicles). In particular, specific provision of early warning signs at Site Entry 4 will be provided and displayed during times when overmass vehicles are anticipated.

• Plans in accordance with V/Line consultations

PC Landscape and visual amenity plan

The Landscape and visual amenity plan will include the on-site program and the off-site program(s).

The on-site landscape program will be prepared to the satisfaction of the Minister for Planning. When approved, the program will be endorsed and will then form part of the permit. The program will include:

a) landscaping to screen the substation, switchyard and associated buildings other than the turbines;

b) details of plant species proposed to be used in the landscaping, including height and spread at maturity;

c) a timetable for implementation of all landscaping works;

Page 204: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix F Page 202

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

d) a maintenance and monitoring program; and

e) surfacing of access tracks in a manner which does not unduly contrast with the landscape.

The off-site landscaping program(s) will provide details of planting or other treatments that will be used to reduce the visual impact of the wind turbines at the dwellings of the participating landowners.

If an off-site program of voluntary landscape mitigation works is accepted by one or more owners as set out in the permit, the wind farm developer / operator will document the program in consultation with those landowners and to the satisfaction of the Responsible Authority. When approved the program(s) will be endorsed and will then form part of the permit. The developer / operator may leave the implementation of the landscaping works to the owner, providing a sum sufficient to pay for the landscaping works by an independent contractor is provided.

PC Aviation Lighting Plan If consent to install aviation obstacle lighting is obtained, it must be installed under the following conditions.

(i) the aviation obstacle lighting must be installed such that it is activated only at night, when an aircraft is in the immediate vicinity of the wind energy facility; and during low visibility daytime conditions such as the existence of smoke or fog;

(ii) for each lit turbine, the lighting must consist of a pair of lights mounted above the nacelle so that one is visible from an aircraft approaching from any direction;

(iii) each light must be a red medium intensity (or preferably low intensity), flashing light as defined by the Civil Aviation Safety Authority (CASA); each light must be shielded (baffled) so as to restrict the vertical spread of light to not more than 3 degrees and light spread below the horizon to not more than 1 degree;

(iv) all lights must flash in unison;

(v) the duration of the light flash must be the minimum period recommended by CASA and the duration of the period between the flashes must be the maximum period recommended by CASA;

(vi) aviation lighting must only be installed on those turbines marked on an endorsed drawing;

(vii) The requirements for lighting maintenance must be developed and included in this plan before the wind farm is commissioned.

Page 205: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix F Page 203

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

PC Fire prevention and emergency response plan

This plan will be prepared having regard to the CFA’s Emergency Management Guidelines for Wind Farms, and in consultation with and to the satisfaction of the Country Fire Authority, the Department of Sustainability and Environment, the Ararat Rural City Council and the Northern Grampians Shire Council. This plan is to include:

• criteria for the provision of static water supply tanks solely for fire fighting purposes, including minimum capacities, appropriate connections and signage,

• procedures for vegetation management, fuel control and the provision of fire fighting equipment during declared fire danger periods;

• minimum standards for access roads and tracks to allow access for fire fighting vehicles including criteria for access to static water supply tanks for fire fighting vehicles.

PC Television and radio reception plan

This plan will identify households that may experience television and/or radio reception difficulties as a result of the wind farm and will include a commitment to provide specified mitigation measures to rectify those difficulties where they are found to exist.

The plan will include as a minimum:

a) The area to be covered by the television and radio reception plan (the defined area) which shall include all dwellings shown on Figure 5 (see the Panel Report, Section 10.3.3) together with dwellings in the area within 6 km either side of the line between Ararat and Lookout Hill;

b) Advertisement in the Ararat local paper and in the developer / operator’s newsletter at the appropriate time of the period when signal strengths and quality will be undertaken, and a request that owners or occupiers of the dwellings within the area defined in (a) above, and clearly delineated in the advertisement, contact the proponent if they are concerned about the possibility that the wind farm might have a detrimental effect on their reception.

c) A Pre-Construction survey to determine television and radio reception strength at locations within the defined area, at those dwellings where requests were made in response to (b) above, to be completed prior to the commissioning of any turbine.

Page 206: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix F Page 204

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

PC Sediment, erosion and water quality management plan.

This plan will outline a strategy for the management of soil and water resources within the project area, be developed in consultation with the relevant Catchment Management Authorities, and must be approved by DPCD. It will include:

• A water quality monitoring program to ensure erosion prevention measures and remedial actions are maintained and are effective.

• Detailed design of the site drainage system.

• Results of geotechnical investigations to identify soils of erosion or dispersion risk and enable safe and efficient design of turbine foundations, tracks, hardstandings and site buildings.

• Results of construction monitoring program.

• Requirements to:

- identify, prior to the on-ground siting of access tracks and earthworks, areas known to be particularly or potentially prone to erosion and avoid those areas where possible.

- include a buffer of 100 metres between temporary concrete batching plants and waterways.

- relocate excess excavated material to avoid impinging on the floodplain, and not change surface water flow patterns.

- stockpile topsoil requiring removal separately from excavation spoil, with spoil and topsoil backfilled in a manner which does not result in soil inversion (i.e. to ensure soil layers are backfilled in the correct order) or erosion.

- fit erosion and sediment control devices (e.g. use of a product such as jute mat in steep drain sections, geotextile silt fences and straw bales) down slope of construction-sites (where required) to prevent erosion events and capture potential sediment wash and regularly maintain these devices.

- keep and maintain spill kits at storage areas and works areas where hazardous materials occur or are handled

- regularly inspect construction sites to detect any erosion events. If such events occur, remedial action will be undertaken. This will include soil stabilisation measures such as revegetation or laying physical stabilisation material followed by revegetation.

Page 207: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix F Page 205

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

- if an incident occurs that adversely impacts on soil or surface water, review management procedures to ensure no recurrence of the incident.

- manage hazardous materials, waste and sewage to ensure no contamination of soils occur.

- appropriately transport and store all hazardous products in accordance with relevant guidelines and regulations to avoid release to the environment.

- properly classify and appropriately store all hazardous materials, with incompatible materials stored separately from one another. Fuels and oils will be stored in bunded areas.

- handle and utilise all hazardous materials in accordance with statutory regulations and label instructions. All personnel handling and using hazardous chemicals will be appropriately trained.

- train employees who handle, transport or utilise hazardous materials in emergency response for spill events.

- regularly inspect hazardous materials storage and usage areas, and equipment utilising hazardous materials, to detect leakage or misuse.

- investigate incidents involving the mishandling, transportation or inadequate storage of hazardous materials and implement appropriate remedial action.

- leave the amount of exposed earth as a result of clearing to a minimum.

- employ, during working times, specified dust suppression techniques to exposed surfaces potentially causing significant dust emissions, including:

- dust mitigation measures;

- limiting traffic access across exposed surfaces;

- implement remedial action where vegetation is impacted by excessive dust emissions. In this event, also carry out a review of operational procedures and dust suppression techniques to avoid recurrence of the event;

- locate material Stockpiles on cleared agricultural land, wherever possible and no closer than 5m of trees, to avoid the effects of soil compaction upon trees and native vegetation understorey;

Page 208: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix F Page 206

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

- avoid locating stockpiles where they can significantly affect native vegetation associations or in areas that threaten loss of stockpile material through natural processes;

- minimise stockpile numbers;

- reinstate compacted areas resulting from the storage of stockpiles, site facilities and wind farm components in consultation with relevant landowners.

PC Construction Workforce Accommodation Assessment

Before the development starts, an assessment of the accommodation requirements of the construction workforce and the capacity of the local area to cope with the demand, and a plan to ensure that accommodation needs are met without significant social disruption, must be prepared to the satisfaction of the Minister for Planning by the wind energy facility operator in consultation with Ararat Rural City Council and Northern Grampians Shire Council.

PC Aboriginal cultural heritage assessment

The CHMP commenced on behalf of the operator must be completed.

The further assessment required will take approximately four to five weeks and will be carried out by a field team comprising two archaeologists and one Registered Aboriginal Party representative. If the fieldwork is unable to satisfactorily identify the nature, extent and significance of Aboriginal cultural heritage, additional assessment may be required to fulfil r.61 Aboriginal Heritage Regulations 2007. However, this is only to occur if unexpected Aboriginal cultural heritage is found during the further assessment.

The further assessment will involve carrying the following work:

• Carry out detailed mapping and investigation of surface features including:

- quartz outcrops which have some potential or superficial evidence of working; and

- high density scatters of coarse fragments.

• Site investigation will involve the detailed mapping of quartz distribution and detailed sampling and analysis of quartz fragments to determine their cultural / non-cultural status.

• A specialist in quartz quarries and stone artefact analysis will participate in this fieldwork and analysis.

• If any location is assessed to be an Aboriginal site, then subsurface testing may be carried out to determine if there are any subsurface archaeological remains.

Page 209: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix F Page 207

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

• The following subsurface testing will be conducted:

- At depositional landforms assessed as having potential for the presence of subsurface stone artefact scatters. These areas include plains within 100m of watercourses and minor swamps / wetlands.

- A small control sample of subsurface testing at proposed development locations assessed as having very low potential archaeological sensitivity.

• Subsurface testing will comprise a combination of controlled hand excavated 1m x 1m test pits and 50cm x 50cm probes down to underlying substrate. Excavations will be conducted according to proper archaeological practice.

- Archaeological works and plans to be monitored and approved by the Registered Aboriginal Party and Aboriginal Affairs Victoria

C Training and induction program for workers

This program will be provided to the construction workers and will detail any relevant site specific matters, such as European heritage, Aboriginal cultural heritage, areas of environmental sensitivity, fire issues, geology and hydrology, traffic and transport issues and construction health, safety and quality issues.

The program will also involve providing site rules and enforcement measures to all workers.

C Flowchart of responsibility. The flowchart will show the persons (and their respective titles) responsible for managing the EMP during the construction phase.

C Native vegetation management plan.

The plan will include:

• temporary fencing or tape must be installed around areas of native vegetation to be retained on-site, to the satisfaction of the responsible authority;

• procedures for the rehabilitation of construction zones with appropriate pasture species or, if in areas of native vegetation, appropriate indigenous revegetation; and

• procedures for ensuring that native vegetation near turbines, access tracks, underground cabling and other wind farm infrastructure will not be adversely affected by construction and operation of the wind farm.

Page 210: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix F Page 208

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Construction Phase (C) Content to include

C Net Gain Offset Management Plan

Update the plan in accordance with the results of Pre-Construction work, and supplement with the following requirements:

Before the vegetation removal starts, the offsets documented in the approved Net Gain Offset Management Plan must be initiated to the satisfaction of the Responsible Authority and the Department of Sustainability and Environment

Offsets must be completed according to the schedule of works in the Net Gain Offset Management Plan, to the satisfaction of the Responsible Authority

Before the vegetation removal starts, the offsets documented in the approved Net Gain Offset Management Plan must be initiated to the satisfaction of the Responsible Authority and the Department of Sustainability and Environment.

All offset sites must be legally secured in accordance with the offset plan

C Pest plant management plan. The plan will include:

• procedures to prevent the spread of weeds and pathogens from earth moving equipment and associated machinery including the cleaning of all plant and equipment before transport to the site and the use of road making material comprising clean fill that is free of weeds;

• revegetation of disturbed areas as described in Condition 11 f(ii); and

• a protocol to ensure follow-up weed control is undertaken on all areas disturbed through construction of the wind energy facility for a minimum period of 2 years following completion of the works.

C Pest animal management plan The plan will include:

• procedures for the control of pest animals, particularly by avoiding opportunities for the sheltering of pests; and

• follow-up pest animal control for all areas disturbed by the wind energy facility construction works for a period of two years following the completion of the wind energy facility.

Page 211: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix F Page 209

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Construction Phase (C) Content to include

C Operational noise compliance testing plan

Prior to operation, this plan will be prepared by a suitably qualified acoustic expert.

The plan will detail the results from the noise compliance assessment that show the wind farm’s level of compliance with NZS6808:1998.

The operational noise compliance testing plan must include:

(a) A method or methods of testing compliance with the noise limits prescribed in Permit Condition 11 for the dwellings for which background noise measurements were made.

The compliance testing method must be either:

(i) The method described in NZS6808:1998 with the regression curves required derived from a data set using hub height wind speeds; or

(ii) A method, designed by a suitably qualified acoustic expert;

(b) A process for compliance testing under which compliance testing at all dwellings identified under (a) for which consent for such testing has been obtained is performed at some time in the 14 months following the commissioning of the last turbine in a stage of the wind energy facility, if the development is in stages;

(c) A procedure for the assessment, by a suitably qualified acoustics expert, of the characteristics of the noise from the wind energy facility to determine if that noise has any special audible characteristics that require the addition of 5 dB(A) to the measured operating noise levels as required by NZS6808:1998;

(d) A procedure under which all results of compliance testing conducted in any month are reported to the Minister for Planning for approval by the 15th day of the following month and made available upon request to the owners and occupiers of particular dwellings as soon as results relating to that particular dwelling are available; and

(e) A procedure under which the implementation of the noise compliance testing plan is directed and supervised by a suitable qualified acoustic expert to the satisfaction of the Minister for Planning.

Page 212: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix F Page 210

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Construction Phase (C) Content to include

C Operational noise compliance enforcement plan

This plan is to be updated to outline relevant individuals’ responsibilities in ensuring noise compliance, reporting protocols and procedures to investigate and report on noise complaints and require the implementation of corrective and preventative action as appropriate

If an exceedance of the noise limits prescribed in the conditions of the permit under the heading NOISE LIMITS is detected, the wind energy facility operator must:

(a) Within 30 days of the confirmation of the exceedance, take sufficient actions to reduce the wind energy facility noise level at the subject dwelling as predicted using the prediction methodology contained in NS6808:1998 ‘Acoustics – the Assessment and Measurement of Sound from Wind Turbine Generators’ by an amount equal to or greater than the amount of exceedance

(b) Within 30 days of the confirmation of the exceedance, provide the responsible authority and the owner/occupier of the dwelling with:

(i) The results of the compliance testing measurements including the magnitude of the detected exceedance

(ii) Details of the actions taken to reduce the wind energy facility noise emissions, and

(iii) Evidence that the actions taken will produce a decrease in the wind energy facility noise level at the dwelling by an amount equal to the magnitude of the exceedance based on a prediction using the methodology of NZS6808:1998 ‘Acoustics – the Assessment and Measurement of Sound from Wind Turbine Generators’.

(c) Continue to operate the wind energy facility with the implemented actions until approval for a different mode of operation is given by the responsible authority under the provision of (d) below

C Traffic and Transport Management Plan

The detailed outcomes of the plans and further reports required under the Pre-Construction Phase will be set out here and implemented.

C Landscape and visual amenity plan

The plans required under the Pre-Construction Phase will be set out here and implemented progressively.

Page 213: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix F Page 211

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Construction Phase (C) Content to include

C Aviation lighting plan The plan will be consistent with the requirements of the Pre-Construction phase plan, and incorporate the outcomes of that plan.

C Fire prevention and emergency response plan

Update the plan in accordance with the results of Pre-Construction work, and supplement with the following additional requirements:

• the facilitation by the operator, within 1 month prior to the commencement of the operation of the wind energy facility, of a familiarisation visit to the site and explanation of emergency services procedures for the Country Fire Authority, Rural Ambulance Victoria, State Emergency Services, Department of Sustainability and the Environment, the Ararat Rural City Council Municipal Emergency Management Committee and Victoria Police;

• subsequent familiarisation sessions for new personnel of those organisations on a regular basis and/or as required; and

• if requested, training of authority personnel in relation to suppression of wind energy facility fires.

C Sediment, erosion and water quality management plan

The plan will be consistent with the requirements of the Pre-Construction phase plan, and incorporate the outcomes of that plan.

C Construction Workforce Accommodation Assessment

The findings of the assessment required in the Pre-Construction phase will be implemented.

C Construction and work site management plan.

The timetable will be in the form of a Gantt Chart that shows the programs and works to be completed during construction phase.

The plan will include details of health, safety and quality management measures.

This plan will identify all EMP obligations that are required during the construction phase and will include:

• procedures for access, noise control, dust emissions, spills and leaks from the handling of fuels and other hazardous materials and pollution management. Such construction and work site procedures are to be in accordance with EPA requirements;

• the identification of all potential contaminants stored on site;

Page 214: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix F Page 212

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Construction Phase (C) Content to include

• the identification of all construction and operational processes that could potentially lead to water contamination;

• the identification of appropriate storage, construction and operational methods to control any identified contamination risks;

• the identification of waste re-use, recycling and disposal procedures;

• appropriate sanitary facilities for construction and maintenance staff in accordance with the EPA Publication 891.1 Septic Tanks Code of Practice;

• a timetable, where practicable for the construction of turbine bases, access tracks and power cabling during warmer months to minimise impacts on ephemeral wetlands, local fauna and sediment mobilisation;

C Blasting plan The plan will include measures to control noise, dust and vibration impact of any blasting. It will also include remedial action where any complaints from blasting impacts are received and will include:

• name and qualification of the person responsible for blasting;

• a description of the location of where the explosives will be used, and the location of every licensed bore on any property with an adjoining boundary within 1km of the location of the blasting;

• a requirement for the identification and assessment of any potentially sensitive site within 1 km of the location of the blasting, including the procedure for pre-blast and post-blast qualitative measurement or monitoring at such site;

• the procedure for site clearance and post blast reoccupation;

• the procedure for the storage and handling of explosives;

• a requirement that blasting only occur after at least 48 hours prior notification in writing of the intention to undertake blasting has been given to the occupants of the properties which are located in whole or in part within 1km of the location of the proposed blasting; and

• a requirement that blasting only be undertaken between the hours of 8am and 4pm.

Page 215: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix F Page 213

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Construction Phase (C) Content to include

C Hydrocarbon and hazardous substances plan.

The plan will include:

• procedures for the control of pest animals, particularly by avoiding opportunities for the sheltering of pests; and

• follow-up pest animal control for all areas disturbed by the wind energy facility construction works for a period of two years following the completion of the wind energy facility.

C Incident management plan The plan will detail procedures for the recording and processing of all environmental incidents, non-conformances and complaints. It will establish protocols for corrective actions and notification of the outcomes to the complainant.

A register will be maintained that documents all environmental incidents, non-conformances, complaints, corrective actions and notification requirements.

The register will be attached to the EMP and provided to DPCD upon request.

Records of any complaints received and corrective actions undertaken will also be provided to DPCD weekly.

The register of complaints and incidents will be available for public inspection at the DPCD Ballarat Office.

Page 216: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix F Page 214

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Operation Phase (O) Content to include

O Flowchart of responsibility The flowchart will show the persons (and their respective titles) responsible for managing the EMP during the operation phase.

O Training and induction program for workers.

This program will be provided to all employees, contractors and will detail any relevant site specific matters, such as European heritage, Aboriginal cultural heritage, areas of environmental sensitivity, fire issues, geology and hydrology, traffic and transport issues and construction health, safety and quality issues.

The program will also involve providing site rules and enforcement measures to all workers and visitors.

O Bat and Bird management plan A Bat and Bird Management Plan (BBMP) will be prepared in consultation with the Department of Sustainability and Environment to the satisfaction of the Minister for Planning. The BBMP will include:

• a statement of the objectives and overall strategy for managing and mitigating any significant bird and bat strike arising from the wind energy facility operations;

• a monitoring program of at least 2 years duration , either commencing upon the commissioning of the last turbine of the first stage of the approved development and use (if any) or alternatively such other time of commencement as is to the satisfaction of the Minister for Planning.

• The monitoring program must include surveys during breeding and migratory seasons to ascertain:

o the species, number, age, sex (if possible) and date of any bird or bat strike;

o the number and species of birds and bats struck at lit versus unlit turbines;

o any seasonal and yearly variation in the number of bird and bat strikes;

o whether further detailed investigations of any potential impacts on birds and bats are warranted.

• any such required further detailed investigations are to be undertaken in consultation with the Department of Sustainability and Environment and to the satisfaction of the Minister for Planning;

• procedures for the reporting of any bird and bat strikes to the Department of Sustainability and Environment within 7

Page 217: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix F Page 215

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Operation Phase (O) Content to include days of becoming aware of any strike identifying where possible whether the strike was by a lit or unlit turbine;

• information on the efficacy of searches for carcasses of birds and bats, and, where practicable, information on the rate of removal of carcases by scavengers, so that correction factors can be determined to enable calculations of the total number of mortalities;

O Operational noise compliance testing plan

The plan will be consistent with the requirements of the construction phase plan, and incorporate the outcomes of that plan.

O Operational noise compliance enforcement plan

This plan is to be updated to outline relevant individuals’ responsibilities in ensuring noise compliance, reporting protocols and procedures to investigate and report on noise complaints and require the implementation of corrective and preventative action as appropriate

If an exceedance of the noise limits prescribed in the conditions of the permit under the heading NOISE LIMITS is detected, the wind energy facility operator must:

(a) Within 30 days of the confirmation of the exceedance, take sufficient actions to reduce the wind energy facility noise level at the subject dwelling as predicted using the prediction methodology contained in NS6808:1998 ‘Acoustics – the Assessment and Measurement of Sound from Wind Turbine Generators’ by an amount equal to or greater than the amount of exceedance

(b) Within 30 days of the confirmation of the exceedance, provide the responsible authority and the owner/occupier of the dwelling with:

(i) The results of the compliance testing measurements including the magnitude of the detected exceedance,

(ii) Details of the actions taken to reduce the wind energy facility noise emissions, and

(iii) Evidence that the actions taken will produce a decrease in the wind energy facility noise level at the dwelling by an amount equal to the magnitude of the exceedance based on a prediction using the methodology of NZS6808:1998 ‘Acoustics – the Assessment and Measurement of Sound from Wind Turbine Generators’.

Page 218: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix F Page 216

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Operation Phase (O) Content to include

(c) Continue to operate the wind energy facility with the implemented actions until approval for a different mode of operation is given by the responsible authority under the provision of (d) below

(d) Within 60 days of the detection of an exceedance provide the responsible authority and owner/occupier of the dwelling with either:

(i) The result of compliance testing using the procedures prescribed in “ of this permit that demonstrate compliance, or

(ii) A program for the development and evaluation of an alternative mode of wind energy facility operation that can be reasonably be expected to result in continuing compliance with noise levels as allowed in Permit Condition 11. The program will:

• Be developed and implemented under the supervision of a suitably qualified acoustics expert;

• Include detailed descriptions of proposed actions;

• Include predictions of wind energy facility noise levels at the dwelling at each stage of the program;

• Not include any actions or combination of actions that are predicted to result in non-compliance;

• Include compliance testing using the procedures prescribed in the “Operational noise compliance testing plan” above; and

• Include a program schedule that specifies the timing of each stage of the program,

to the satisfaction of the Responsible Authority.

If the responsible authority requires the program to be modified, the wind energy facility operator may either submit a modified program or immediately withdraw the program and conduct compliance testing using the procedures prescribed in the “Operational noise compliance testing plan” above.

Page 219: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix F Page 217

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Operation Phase (O) Content to include

Following implementation of the program, the wind energy facility operator may provide the responsible authority and the owner/occupier with a detailed description of an alternative mode of operation of the wind energy facility together with evidence that under that mode of operation compliance can be expected, to the satisfaction of the responsible authority. Given such information and evidence the responsible authority may approve the operation of the wind energy facility in the alternative mode and such approval will not be unreasonably withheld.

O Traffic and Transport Management Plan

The detailed outcomes of the plans and further reports required under the Construction Phase, as in other areas, will be set out here, together with monitoring and compliance provisions.

O Landscape and visual amenity plan

Implementation and maintenance of the work specified in the plans required under the Construction Phase will be completed.

O Aviation lighting plan The plan will be consistent with the requirements of the construction phase plan, and incorporate the outcomes of that plan.

O Fire prevention and emergency response plan

Update the plan in accordance with the results of construction experience.

O Bushfire mitigation plan This plan will be developed in consultation with the CFA and in accordance with the Electricity Safety Act and will be provided to Energy Safe Victoria for approval.

It will detail operational activities that will employ best practice with regard to fire management.

O Television and radio reception plan

The results of the Pre-Construction survey of dwellings nominated in that plan will form the basis of post commissioning testing. Post commissioning testing will be undertaken at the cost of the wind energy facility operator, for those households within the area specified in the Pre-Construction phase of the EMP, and who notify the proponent that they are experiencing television and/or radio reception difficulties as a result of the wind farm. Where testing shows that the reception has deteriorated, mitigation measures to rectify those difficulties will be undertaken. The mitigation measures shall return the affected reception to Pre-Construction quality and be undertaken at the cost of the wind energy facility operator, all to the satisfaction of the Minister for Planning.

Page 220: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix F Page 218

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Operation Phase (O) Content to include

O Sediment, erosion and water quality management plan.

Develop from the content set out in the construction phase above.

O Incident management plan The plan will be consistent with the requirements of the construction phase plan, and incorporate the outcomes of that plan, including the maintenance of the Register.

Page 221: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix F Page 219

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Decommissioning Phase (D) Content to include

D Training and induction program for workers.

This program will be provided to all employees and contractors, and will detail any relevant site specific matters, such as European heritage, Aboriginal cultural heritage, areas of environmental sensitivity, fire issues, geology and hydrology, traffic and transport issues and construction health, safety and quality issues.

The program will also involve providing site rules and enforcement measures to all workers and visitors.

D Traffic and Transport Management Plan

The detailed outcomes of the plans and further reports required under the Construction Phase, as in other areas, will be set out here, together with monitoring and compliance provisions.

This plan will also detail traffic and transport management measures for removal of oversize and overmass turbine components from the site to recycling / re-use and disposal facilities.

It will be prepared in consultation with VicRoads, ARCC and V/Line.

D Complaints and incidents register

This register will include any environmental incidents, non-conformances, complaints, corrective actions and notification requirements.

The register will be attached to the EMP and provided to DPCD upon request.

Records of any complaints received and corrective actions undertaken will also be provided to DPCD upon request.

D Decommissioning Plan Prior to decommissioning, a Decommissioning Plan will be developed that includes:

(a) A schedule in the form of a Gantt Chart that shows the program of works to be completed during the decommissioning phase

(b) The methodology for removing all above-ground operational equipment and infrastructure (e.g. turbines, anemometers, internal overhead powerlines and electrical substation) and will include details on health, safety and quality management measures, and measures to return the land to sustainable use

(c) The covering of foundations with topsoil

Page 222: Ararat Wind Farm Panel Report - Planning · ararat planning scheme permit application 09/004799 and northern grampians planning scheme permit application 5.2009.94.1 ararat wind energy

Appendix F Page 220

ARARAT WIND ENERGY FACILITY PANEL REPORT SEPTEMBER 2010

Decommissioning Phase (D) Content to include

(d) The retention of underground cabling in-situ

(e) The removal and clean up of any residual spills or contamination

(f) The rehabilitation of all storage, construction, access tracks and other areas affected by the project closure or decommissioning, if not otherwise useful to the on-going management of the subject A post decommissioning revegetation management plan

(g) A post decommissioning revegetation management plan

(h) Details of proposed recycling of materials.

(i) The retention of underground cabling in-situ

(j) The removal and clean up of any residual spills or contamination

(k) The rehabilitation of all storage, construction, access tracks and other areas affected by the project closure or decommissioning, if not otherwise useful to the on-going management of the subject A post decommissioning revegetation management plan

(l) Details of proposed recycling of materials.

(m) It will include a schedule of revegetation management and works, and a timetable for the implementation of the works.

Subject to the agreement of the landowner:

(a) Access tracks may remain for the benefit of the landowner to maintain access throughout property

(b) Building and storage facility may remain for benefit of landowner.

The decommissioning plan must be implemented to the satisfaction of the responsible authority within 24 months of approval of the plan or within such other timeframe as may be specified by the responsible authority.