Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental...

86
Roads Branch PublicWorks Department Malaysia Jalan Sultan Salahuddin 50582 Kuala Lumpur An Effective Approach To Prepare Bill of Quantities For Environmental Protection And Enhancement

Transcript of Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental...

Page 1: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Roads BranchPublic Works Department Malaysia

Jalan Sultan Salahuddin50582 Kuala Lumpur

An Effective Approach To

Prepare Bill of Quantities

For Environmental

Protection And

Enhancement 5.0m5.0m

7.0m7.0m

Page 2: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 1

Page 3: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 2ARAHAN TEKNIK ( JALAN ) 16 / 03

AN EFFECTIVE APPROACH TO PREPARE BILL OF QUANTITIES FOR

ENVIRONMENTAL PROTECTION AND ENHANCEMENT

Preface

There is an urgent need for the construction industry to address the issues ofenvironmental problems arising from the accelerated infrastructure develop-ment. In this aspect, Jabatan Kerja Raya (JKR) Malaysia has moved forwardin defining the environmental requirements by incorporating EnvironmentalManagement Plan (EMP) into tender documents. However, the success andeffectiveness of this approach does not rely solely on the EMP but also onthe need to enhance the commitment and awareness of all parties involved,particularly the developers/contractors, designers, consultants, academiciansand decision makers.

It is of utmost importance to produce tender documents which are clear andcomprehensive. A revision on environmental protection and enhancements inJKR Tender Documents has been done by itemising the environmental worksinto the Bill of Quantities to allow contractors to tender a realistic price.

This Arahan Teknik provides changes to the items in the Tender Documentwith regards to the Condition of Contracts, Instructions to Tenderers,Specification to Environmental Protection and Enhancements, Preamble toBill of Quantities, Bill of Quantities and Drawings.

The draft version of this Arahan Teknik had been presented during theNational Engineering Conference of Awam 2001 organized by UniversitiSains Malaysia in February 2002, Seminar on Best Earthworks ManagementPractices in Construction Industry which was jointly organized byConstruction Industry Development Board, Department of Environment andJKR Malaysia in March 2002, and during the Assistant Directors (Road)Meeting in Mac 2002. It was also presented during the Workshop onEnvironmental Consideration in Road Projects in April 2002 organized by theRoad Engineering Association of Malaysia (REAM) and JKR Malaysia.

Page 4: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 3ARAHAN TEKNIK ( JALAN ) 16 / 03

ACKNOWLEDGEMENT

ENVIRONMENTAL MANAGEMENT PLAN

The idea of incorporating Environmental Management Plan(EMP) into con-tract documents was conceived in November 1999 through the sub-commit-tee of environmental management which was chaired by Tn. Hj. Abu Harithbin Shamsuddin of Unit Rekabentuk Jalan, Cawangan Jalan. This sub-com-mittee comprises thirteen (13) multi-disciplinary personnel as listed below:-

1. Tn. Hj. Abu Harith Shamsuddin : Cawangan Jalan (Chairman)2. Dr. Roslan Md Taha : Cawangan Alam Sekitar3. Cik Sutina Ghazali : Cawangan Kerja Pendidikan4. Pn. Aishah Othman : Cawangan Jalan4. Cik Lee Bee Chew : Cawangan Arkitek 5. Pn. Hjh. Halimaton Che Wan : Cawangan Kerja Bangunan

Am6. Pn. Maselawati Shamsuddin : Cawangan Kontrak dan Ukur

Bahan7. Pn. Norazizah Modiran : JKR Selangor8. Pn. Mastura Shaari : Cawangan Kerja Bangunan

Am9. En. Ahmad Zaidi Mat Said : Cawangan Alam Sekitar10. En. Iza Rosman Zainal : Cawangan Pakar dan

Kejuruteraan Awam11. En. Romzi Mat Zainul : HSSI Integrated Sdn. Bhd12. En. Norman Md. Rabani : Cawangan Jalan

Page 5: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 4ARAHAN TEKNIK ( JALAN ) 16 / 03

EXECUTIVE SUMMARY

Arahan Teknik (Jalan) 22/01 - A Practical Guide To Prepare Bill Of QuantitiesFor Environmental Protection And Enhancements provides some guidelinesfor the preparation of Tender Documents. It comprises the Instructions toTenderers, Condition of Contracts, Specification to Environmental Protectionand Enhancements, Preamble to Bill of Quantities, Bill of Quantities andDrawings.

Guidelines on the preparation of an Environmental Management Plan (EMP)and Bulk Fuel Storage Tanks and an example of Needs Statement are pre-sented. Photographs of environmental mitigating measures such as silt traps,silt fences, sediment basins, slope protection works, green/animal crossingsand by passes, salvaging of protected species and proper management ofscheduled waste and skid tanks are enclosed. In addition, monitoring ofwater, air and noise as well as the good and bad practices of environmentalmanagement during construction locally and abroad are highlighted.

Page 6: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 5ARAHAN TEKNIK ( JALAN ) 16 / 03

CONTENTS

CONTENTS

1.0 INTRODUCTION

2.0 OBJECTIVES

3.0 INSTRUCTION TO TENDERERS3.1 Environmental Management Plan (EMP).

4.0 CONDITION OF CONTRACT4.1 Environmental Management Plan (EMP)

5.0 SPECIFICATION : ENVIRONMENTAL PROTECTION AND ENHANCEMENTS5.1 Introduction 5.2 Legislation And Regulation5.3 Site Office And Accommodation

5.3.1 Site Office, Workshop And Store5.3.2 Accommodation for Workmen5.3.3 Utilities

5.3.3.1 Water Supply 5.3.3.2 Sanitary Facilities5.3.3.3 Garbage disposal

5.4 Environmental Management Plan5.5 Site Clearing, Earthworks And Excavation

5.5.1 Site clearing5.5.2 Earthworks And Excavation

5.6 Access Roads And Existing Road5.7 Pollution Controls

5.7.1 Dust Control5.7.2 Noise Control 5.7.3 Noise Barrier 5.7.4 Water Pollution5.7.5 Air Quality

5.8 Preservation Of Flora And Fauna 5.8.1 Flora5.8.2 Fauna

5.9 Requirements In Relation To Waterways

Page 7: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 6ARAHAN TEKNIK ( JALAN ) 16 / 03

5.10 Permanent Drainage Works5.11 Revegetation Vertiver Hedgerow Grass

5.11.1 General5.11.2 Plant Materials 5.11.3 Starting Materials 5.11.4 Container Plants

5.11.4.1 Roots 5.11.4.2 Tops (shoot system)5.11.4.3 Age of container plant5.11.4.4 Site Nursery 5.11.4.5 Field Planting 5.11.4.6 Establishment And Maintenance5.11.4.7 Quality On Delivery On

Hedgerows5.12 Erosion Control Measurement

5.12.1 Silt Fences 5.12.2 Silt Trap

5.12.2.1 Gabion Wall 5.12.3 Sediment Basin

6.0 PREAMBLE6.1 Silt Fences 6.2 Silt Traps and Sediment Basin6.3 Gabion Walls 6.4 Lorry Wash Troughs 6.5 Noise Barrier 6.6 Flora Survey

7.0 BILL OF QUANTITIES7.1Environmental Protection Works

8.0 DRAWINGS 8.1 Silt Fence 8.2 Gabion Silt Traps8.3 Gabion Wall at Steep Slope8.4 Gabion Sediment Basin on Flat Ground (Type 1)8.5 Gabion Sediment Basin on Slope (Type 2)8.6 Gabion Arrangement8.7 Lorry Wash Trough8.8 Skid Tank

Page 8: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 7ARAHAN TEKNIK ( JALAN ) 16 / 03

9.0 APPENDICES

APPENDIX A - GENERAL GUIDELINES for the PREPARATION of the ENVIRONMENTAL MANAGEMENT PLAN (EMP)

APPENDIX B - GUIDELINES FOR BULK FUEL STORAGE TANKS

APPENDIX C - EXAMPLE OF NEEDS STATEMENT FOR ROAD PROJECTS

APPENDIX D - DEPARTMENT OF ENVIRONMENTAL (DOE’s) FORMAT FOR PREPARATION OF EMP

APPENDIX E - PHOTOGRAPHS OF MITIGATION MEASURES

APPENDIX F - PHOTOGRAPHS OF ENVIRONMENTALMONITORING

10.0 REFERENCES

Page 9: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 8ARAHAN TEKNIK ( JALAN ) 16 / 03

1.0 INTRODUCTION

This Arahan Teknik (Jalan) 16/03 is a reference for the incorporation of environmentalprotection and enhancements measures in executing con-tracts. The designer shall choose only relevant sections in this Arahan Teknik which are applicable to his/her proj-ect.

2.0 OBJECTIVES

The objectives of this Arahan Teknik (Jalan) 16/03 are as follow:

(i) To assist contractors to price environmental protection measures accordingly.

(ii) To provide relevant information for the amount of work to be carried out as per requirements.

(iii) To instill good environ-mental management and monitoring prac-tices during construc-tion.

(iv) To protect, restore and enhance quality of the environment due to project construction.

3.0 INSTRUCTION TO TENDERERS

3.1 Environmental Management Plan (EMP)

As stated in the Contract Specification issued by the Jabatan Kerja Raya on behalf of the Government of Malaysia, the Contractor shall comply with all legal duties and obligations regarding the protection of the environment as laid down in the Environmental Quality Act 1974 (Act 127). Before the commencement of works Contractor shall submit to the Superintendent Officer (S.O.), Environmental Management Plan (EMP), detailing the Contractor’s proposed arrangement for the abate-ment and mitigation measuresfor environmental protection, environmental monitoring, testing programme and report-ing, and his organisation chart.

Page 10: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 9ARAHAN TEKNIK ( JALAN ) 16 / 03

4.0 CONDITION OF CONTRACT

4.1 ENVIRONMENTALMANAGEMENT PLAN (EMP)

Tenderers are required to comply with all legal duties and obligations regarding the protection of the environment as laid down in the Environment Quality Act 1974 (Act 127).

Within thirty (30) days from the Letter of Acceptance the successful tenderer shall sub-mit for the S.O.’s approval a detailed Environmental Management Plan (EMP) based on the general guide-lines for the preparation of theEnvironmental Management Plan (EMP) as given in Appendix A. The EMP shall include the Contractor’s pro-posed arrangements of struc-tural organisation, work pro-gram chart related to environ-ment, abatement and mitiga-tion measures for environ-mental protection, environ-mental monitoring programmeand reporting. The cost of preparing the EMP including the cost involved obtaining theservices of Environmental Consultant shall be deemed tobe borne by the Contractor.

The Environmental Impact Assessment (EIA) report and the Conditions of Approval given by the Department of Environment (DOE), where applicable, will be made avail-able by the Government to assist the Contractor in preparing the EMP.

Page 11: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 10

SPECIFICATION

Page 12: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 11

ENVIRONMENTAL PROTECTION AND ENHANCEMENTS

ARAHAN TEKNIK ( JALAN ) 16 / 03

5.0 ENVIRONMENTALPROTECTION AND ENHANCEMENTS

5.1 INTRODUCTION

This section contains the specifications relating to envi-ronmental matter in the exe-cution of this contract. Where these matters appear also at other sections of this docu-ment, this specification shall take precedence.

5.2 LEGISLATION AND REGULATION

The Contractor shall at all times adhere to all existing statutes regarding the protec-tion of the Environment.

The Contractor shall be awareof the followings legislation and subsidiary legislations made thereunder and take all measures necessary to ensure compliance.

a) Environmental Quality Act, 1974 (Act 127) andsubsidiary legislations made thereunder

b) Environmental Quality (Sewage and Industrial Effluents) Regulations 1979

c) Environmental Quality (Clean Air) Regulations1978

d) Environmental Quality (Scheduled Wastes) Regulations 1989

e) Sewerage Services Act1993 – Act 580

f) Street, Drainage and Building Act, 1974: Act 133

g) Protection of Wildlife Act, 11972 (Act 1976)

h) Land Conservation Act,1960

i) Drainage Work Ordinance 1954

j) Water Enactment – Chapter 146: Water (1935)

The Contractor shall be liable for and shall indemnify the Government against any dam-age, expense, liability, loss, claim, prosecution, proceed-ing, fine, penalty caused by non-compliance or contraven-tion of above legislation.

Page 13: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 12

ENVIRONMENTAL PROTECTION AND ENHANCEMENTS

ARAHAN TEKNIK ( JALAN ) 16 / 03

5.3 SITE OFFICE AND ACCOMMODATION

5.3.1 Site office, workshop and store

a) The Contractor shall provide and maintain atthe Site, suitable and sufficient offices for his own use and that of theS.O. and his represen-tative.

b) The Contractor shall also provide and main-tain at the Site suitable workshops and stores for him to carry out his works.

c) The Contractor is pro-hibited from discharg-ing oil and grease to any watercourses. Any spilled oil and grease shall be promptly removed by the Contractor. The Contractor shall collect and store used oil and grease and dispose them according to methods approved by Department of Environment.

5.3.2 Accommodation for Workmen

a) The Contractor shall provide and maintain atthe Site, suitable and sufficient accommoda-tion and camps for his workmen and supervi-sory staff as required inthe Contract.

b) The locations of the workmen’s accommo-dation shall be agreed beforehand with the S.O. and shall be such as to avoid obstruction and nuisance to the Works and public and shall be laid out in an approved and orderly manner.

c) The Construction and habitation of the accommodation shall comply with the local statutory or other Government authoritiesand subjected to the approval of the S.O.

d) Sufficient toilet facilitiesshall be provided to thesatisfaction of the S.O. and in accordance with Ministry of Health Regulations. Proper provision shall be madefor the disposal of all waste and refuse and there shall be adequatesupply of water for washing, cooking and drinking purposes. The

Page 14: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 13

ENVIRONMENTAL PROTECTION AND ENHANCEMENTS

ARAHAN TEKNIK ( JALAN ) 16 / 03

sleeping quarters shall be properly ventilated and lighted.

e) The Contractor shall bewholly responsible for the workmen at the accommodation provid-ed. Activities such as hunting/ trapping of wildlife should be strict-ly forbidden and fines/ penalties shall be imposed on the Contractor by the rele-vant Government Departments.

5.3.3 Utilities

5.3.3.1 Water Supply

a) The Contractor shall design, supply, install, operate and maintain a system for potable water supply to his facilities in the con-struction work area including site offices. The supply shall be taken from sources approved by the S.O.

b) The Contractor shall submit his plans for thewater supply and retic-ulation system, includ-ing filtration, chlorina-tion and other pro-posed treatment, to theS.O for approval, not less than thirty (30) days before commenc-

ing construction of the installation. The Contractor shall providean adequate supply of potable water on the Site. The quality, num-ber, capacity and loca-tion of the drinking points shall be to the satisfaction of the S.O.

c) Potable water shall comply with the requirements of World Health Organization Standards.

5.3.3.2 Sanitary Facilities

a) The Contractor shall supply, construct, oper-ate and maintain tem-porary toilet facilities at appropriate locations on site. Facilities shall be complete with ade-quate water closets, urinals and hand-basins, and proper san-itary system. The loca-tion of these facilities and their construction shall be as approved by the S.O.

b) The Contractor shall maintain the Site and toilet in a clean and sanitary condition shall comply with all require-ments of the Ministry ofHealth.

Page 15: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 14

ENVIRONMENTAL PROTECTION AND ENHANCEMENTS

ARAHAN TEKNIK ( JALAN ) 16 / 03

c) All waste-waters must be treated such that its discharged effluent meet the requirements of all existing regula-tions and legislations.

5.3.3.3 Garbage disposal

a) The Contractor shall undertake the collectionand disposal of garbage from the area. Garbage collection shall be made at least twice each week at times approved by the S.O. and the services shall be continued until completion of the Works.

b) Garbage or construc-tion waste materials shall be disposed off in a locally available land-fill or hauled to disposalsites approved by the S.O.

5.4 ENVIRONMENTALMANAGEMENT PLAN

When necessary as stipulatedin the instructions to tenderer, the Contractor shall submit forthe S.O. approval a detailed Environmental Management Plan (EMP) as described in the General Guideline for the Environmental Management Plan (EMP) – by the Contractor.

5.5 SITE CLEARING, EARTH-WORKS AND EXCAVATION

5.5.1 Site Clearing

Should be read in conjunction to specification in Standard Specification For Road Works.

a) Site clearing should be done in stages and no burning of cleared veg-etation and debris shallbe allowed unless approval has been obtained from the Director General of Department of Environment.

b) Cleared vegetation anddebris should be dis-posed off in designatedspoil tips which must be approved by the S.O. The method of depositing the spoil tipsmust be properly engi-neered, designed and approved by the S.O. Unless otherwise stat-ed, the Contractor shallbe responsible for iden-tifying these disposal areas. The dump site/disposal areas are to be finalised before any site clearing is allowed to be carried out.

Page 16: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 15

ENVIRONMENTAL PROTECTION AND ENHANCEMENTS

ARAHAN TEKNIK ( JALAN ) 16 / 03

c) On no account should cleared vegetation, debris and spoils be deposited or pushed into water-courses, streams and rivers.

d) Trees and vegetation identified for conserva-tion must be protected by the Contractor at all costs.

e) Other clearing activitiessuch as access road construction, site office and work-camp con-struction, etc shall pro-ceed with minimal cut-ting of trees and site clearing. The intended area shall be marked out for the S.O.’s inspection and approvalprior to any site clear-ing works.

f) Site clearing should be from the centre of the road outwards towards the right-of-way bound-ary to enable escape ofwildlife into neighboringjungles.

g) Holes and cavities resulting from the clear-ing, grubbing, destump-ing and de-rooting shallbe backfilled with acceptable materials and compacted to approximate densities of adjacent areas.

h) Erosion mitigating measures are to start before commencement of site clearing and earthworks. This include planning for ‘work in stages’ and also plans for diverting as much as possible surface runoff from the work areas.

i) The Contractor shall provide all necessary temporary drainage for keeping the site and other areas free of standing water. Effort must be made to chan-nel the surface runoff as much as possible away from the work areas.

j) If due to unforseen cir-cumstance turfing can-not be carried out immediately to the slope exposed areas, temporary protection/cover (e.g. plastic sheet or equiva-lent) shall be applied toexposed surfaces by the Contractor.

k) Should the Contractor fail to ensure all the above, the S.O. will appoint other Contractors to carry outthe said work and all costs incurred will be charged to the default-ing Contractor and deducted from monies due to him.

Page 17: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 16

ENVIRONMENTAL PROTECTION AND ENHANCEMENTS

ARAHAN TEKNIK ( JALAN ) 16 / 03

5.5.2 Earthworks And Excavation

a) All silt traps, sedimen-tation basins, erosion control measures and drainage system as shown in Drawings must be constructed in stages and maintained by the Contractor. The locations of these miti-gating measures shall be detailed and shown on plan as required by the S.O.

Water discharging fromthe silt trap/sedimenta-tion basin should have total suspended solids level of 150 mg/l or as specified in the Condition of Approval of EIA. The monitoring schedule is as stated inthe Environmental Management Plan (EMP).

b) The Contractor shall provide all necessary temporary drainage for keeping the site and other areas free of standing water before and during any earth-works started. Effort must be made to chan-nel the surface runoff as much as possible away from the work areas.

c) All temporary drainage,mitigation measures (e.g. silt traps and silt fence) must be con-structed before any earthworks is to be car-ried out and maintainedthroughout constructionperiod to ensure their effectiveness.

d) Unsuitable materials and surplus earth shall be disposed off in des-ignated spoil tips. The method of depositing the spoil tips must be properly engineered designed and approvedby the S.O. Unless oth-erwise stated, the Contractor shall be responsible for identify-ing these disposal areas. The dump site/ disposal areas are to be finalised and approved by the S.O. before any earthworks allowed to be carried out. In the event addi-tional disposal areas (spoil tips) are required,the Contractor shall be responsible for identify-ing these disposal areas which shall be approved by the S.O.

e) Unsuitable materials and surplus earth need to be sufficiently grad-ed, leveled and revege-tated. No tipping is to be allowed.

Page 18: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 17

ENVIRONMENTAL PROTECTION AND ENHANCEMENTS

ARAHAN TEKNIK ( JALAN ) 16 / 03

f) The Contractor shall schedule as much as possible of the earth-works to be carried out during dry weather periods.

g) The Contractor shall also carry out earth-works in a systematic/orderly manner to minimise earth surfaces from being exposed bare for long periods. The sequence of earth-works should be in compliance with the Environmental Management Plan.

h) Turfing or hydroseedingmust be carried out immediately after earth-works and before work on other berm/lift com-mences. If due to unforseen circum-stances turfing cannot be carried out immedi-ately, temporary protec-tion/cover (e.g. plastic sheets or equivalent) shall be applied to the exposed slopes by the Contractor.

Should the Contractor fail to ensure the above, the S.O. will appoint other Contractors to carry out the said work and all costs incurred will be charged to the defaulting Contractor and deducted frommonies due to him.

5.6 ACCESS ROADS AND EXISTING ROAD

a) All access roads to the site shall be paved for a distance of at least 10 metres from where these access roads jointhe existing roads.

b) The Contractor shall maintain all existing roads, bridges, drains, culverts, roadside furni-ture, and all other appurtenances and services on such roads and shall be responsi-ble for any damages caused by any work carried out by him or byconstruction period andshall repair and reinstate the same to their original condition to thesatisfaction of the S.O.

c) All temporary diversion affecting public/private roads must be approved by the Government, private landowner and the S.O.All such diversions must have temporary diversion signs to the requirements of ArahanTeknik (Jalan) 2C/85 of JKR. Adequate work-men for controlling traf-fic diversion must be provided.

Page 19: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 18

ENVIRONMENTAL PROTECTION AND ENHANCEMENTS

ARAHAN TEKNIK ( JALAN ) 16 / 03

5.7 POLLUTION CONTROLS

5.7.1 Dust Control

a) The Contractor shall provide suitable spray-ing equipment for regu-lar spraying of water over the existing roads,tracks and access roads, completed as well as incomplete roadand other barren areas of the site used by the contractor and as and when directed by the S.O.

b) The Contractor shall provide for the prompt removal of all dirt and other materials spilled from his or his sub-con-tractor’s vehicles on public or private road-ways over which such materials are hauled or on to which such mate-rials are dumped, washed or otherwise deposited by reason of his work carelessness in execution of the works and avoid inter-fering with drainage or creating a traffic hazardto vehicles or impeding the passage of pedes-trians.

c) When the Contractor’s trucks or equipment utilises public or privateroadways, all dirt and materials shall be

removed from the trucks/ equipments by hosing, lorry wash-trough, etc. before leaving the site.

d) For Contractor’s trucks carrying sand, aggre-gates, earth and other loose construction materials liable to spillage, tarpaulin must be used to cover such open trucks when pass-ing through villages and settlements or on all roadways.

5.7.2 Noise Control

a) All work shall be car-ried out without unrea-sonable noise and dis-turbance. The Contractor shall indem-nify and keep indemni-fied the Government, S.O. and the S.O.’s Representatives against any liability for damages on account ofnoise or other distur-bances created while or in carrying out of theworks and from and against all claims, demands, proceedings,damages, costs charges and expenses whatsoever in regard orin relation to such liabil-ity.

Page 20: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 19

ENVIRONMENTAL PROTECTION AND ENHANCEMENTS

ARAHAN TEKNIK ( JALAN ) 16 / 03

b) The Contractor shall ensure that all equip-ment and machinery are in proper working condition so as to min-imise the amount of noise generated. The Engineer may require the Contractor to replace any machinery that to his discretion, is emitting excessive noise.

c) The Contractor shall comply with the generalrecommendations set out in BS 5228: Code of Practice for Noise Control on Constructionand Demolition Sites together with any spe-cific requirements described in the Contract.

d) The Contractor shall ensure that noise levelsof Leq = 55 dBA shouldnot be exceeded at set-tlements and villages.

5.7.3 Noise Barrier

a) Noise barrier shall be provided in sensitive areas such as housing situated beside busy roads or highways, schools and hospitals.

b) The type of noise barri-er used shall be either absorptive, reflective, dispersive or mixed

depending upon the noise level survey con-ducted and recommen-dations made by noise barrier experts.

c) The Contractor shall supply and install noisebarrier including main-tenance during the con-struction and defects liability period.

5.7.4 Water pollution

a) All silt fence, silt traps, sedimentation basins and other erosion con-trol measures as shown in Drawings must be constructed and maintained by the Contractor.

Water discharging fromthe silt traps/ sedimen-tation basin should have total suspended solids levels of 150 mg/l or specified by other approving author-ities. The monitoring schedule is as stated inthe Environmental Management Plan (EMP) in this docu-ment.

Page 21: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 20

ENVIRONMENTAL PROTECTION AND ENHANCEMENTS

ARAHAN TEKNIK ( JALAN ) 16 / 03

b) The Contractor is pro-hibited from discharg-ing oil and grease to any watercourse. Any spilled oil and grease shall be promptly removed by the Contractor. The Contractor shall collect,label and store used oiland grease and other scheduled wastes according to methods approved by the Department of Environment.

All used oil and grease and other scheduled waste shall be removedfrom site by a licensed Contractor.

c) All wastewater (sewage, sullage) mustbe treated such that theeffluent complies with all existing regulations/legislations.

d) Water Quality Monitoring and TestingThe Contractor shall carry out water quality monitoring at positions on an existing streams as indicated in the Environment Management Plan (EMP).

Parameters to be test-ed shall include:-

Biochemical Oxygen Demandat 5 days (BOD5)

Total SuspendedSolid (TSS)

Oil and Grease

E-Coli

pH

Dissolved Oxygen (DO)

5.7.5 Air Quality

No open burning of cleared vegetation, debris and con-struction waste etc, would be allowed unless approval obtained from the Director General of the Department of Environment.

Page 22: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 21

ENVIRONMENTAL PROTECTION AND ENHANCEMENTS

ARAHAN TEKNIK ( JALAN ) 16 / 03

5.8 PRESERVATION OF FLORAAND FAUNA

5.8.1 Flora

a) Upon the possession ofsite, the Contractor withthe assistance of the forester and/or botanist shall furnish to the S.O.a report on tree conser-vation plan including trees classified as rare,endemic and endan-gered, method of preservation, proce-dure, course of action to be taken and other conservation require-ment deemed neces-sary for the preserva-tion of the flora.

b) Prior to site clearing, the forester and/or botanist shall assist thesurveyor to identify anytrees of rare, endemic or endangered species which need to be con-served or relocated. Trees which are classi-fied as rare, endemic and endangered, or having girth of 800mm and above shall be conserved and marked (crossed) red. Trees which are rare, endem-ic or endangered and need to be relocated shall be marked (crossed) white. Shouldrelocation be required, trees shall have girth of300mm and below.

c) The Contractor is responsible for the transportation of trees to nearby sites, arbore-tum or other alterna-tives, as advised by theforester. The Contractorshall ensure that relo-cated trees are well kept.

d) The botanist/ forester/ horticulture shall pro-duce a status report during construction on the effectiveness of thetree conservation, preservation and actionplan as proposed in thefirst report.

e) The report shall also cover aspects of new findings left out during the earlier investigationand propose any rectifi-cation plan required.

f) Reports shall be sub-mitted from early study.

g) The felling of trees shall be confined withinthe construction limit.

h) The Contractor shall refrain all his and his sub-contractor’s employees from destroying, removing orclearing trees, timber, shrub and other flora toany extent greater thanthat is approved by the S.O. as being necessary for the execution of the contract.

Page 23: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 22

ENVIRONMENTAL PROTECTION AND ENHANCEMENTS

ARAHAN TEKNIK ( JALAN ) 16 / 03

i) The Contractor shall refrain from disposing waste materials amongst vegetation within or outside the work site. Any and all waste materials dis-posed amongst vegeta-tion for any purpose or reason, except as may be directed by the S.O and whether or not dueto the fault of the Contractor, shall be recovered at the expense of the Contractor.

5.8.2 Fauna

a) The Contractor shall take such measures asmay be necessary to prevent his employees from hunting, disturb-ing, capturing or destroying stock and such fauna as may be protected by relevant statutes.

b) The Contractor shall take reasonable pre-cautions to prevent his employees from remov-ing or damaging bird nests or eggs which may be discovered in the work site or adja-cent areas.

c) The Contractor shall take all necessary pre-cautions to prevent his and his sub-contractors

employees, agents andany other persons employed in connectionwith the Works from:

i) beating, kicking, infuriating, terri-fying or torturing any wild animal or wild bird

ii) housing, confin-ing or breeding any wild animal or wild bird in such a manner so as to cause itunnecessary pain or suffering,including the housing, confin-ing or breeding of any wild ani-mal or wild in any cage, enclo-sure or hut which is not suit-able for or con-ducive to the comfort or healthof the wild ani-mal or wild bird

iii) using any wild animal for per-forming or assisting in the performance of any work or labour which by reasons of any infirmity, wound disease or any other incapacity it is unfit to per-form

Page 24: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 23

ENVIRONMENTAL PROTECTION AND ENHANCEMENTS

ARAHAN TEKNIK ( JALAN ) 16 / 03

The Contractor shall take all necessary precaution to pre-vent his and his sub-Contractor’s employees from waiting in any place, building any platform or shelter or placing any snare, poison, poisoned bait, birdlime or net for the purpose of shooting, killing or taking any wild ani-mal or wild bird.

5.9 REQUIREMENTS IN RELATION TO WATERWAYS

a) The Contractor shall ensure that his pro-gramme for the whole of the Works executed under the Contract is compatible with the requirements of the Jabatan Pengaliran & Saliran (JPS) so that the continued operationand safety of rivers, water-courses and related structures are not adversely affected by the works. During the execution of the Works, he shall coordi-nate all operations in close liaison with the JPS and shall make such adjustments to hisprogramme as are fromtime to time necessary to accommodate the actual progress achieved with the tem-porary and permanent diversions programme.

b) The Contractor shall keep the S.O fully informed of this negoti-ations with the JPS. Noworks, diversions, mod-ifications replacements and/or relocation of rivers, watercourses and related structures shall be carried out without prior approval in writing from the JPS.Adequate notice together with such design calculations anddrawings as are appli-cable shall be given by the Contractor to the JPS to enable the Department to considerand if necessary give effect or amend any design as may be required.

c) The Contractor shall ensure that temporary diversions of any rivers and/or water courses shall be capable of sus-taining such flows throughout the year at such levels and rates as are specified by the JPS as the rivers and/or watercourses which they replace irre-spective of the antici-pated periods of use of the diversions by the Contractor.

Page 25: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 24

ENVIRONMENTAL PROTECTION AND ENHANCEMENTS

ARAHAN TEKNIK ( JALAN ) 16 / 03

d) The Contractor shall indemnify and keep indemnified the Government against alllosses and claims for injuries or damage to any person or property whatsoever which may arise out of or in conse-quence or the construc-tion and maintenance of the drainage works and against all claims, demands, proceedings,damage costs, chargesand expenses whatso-ever in respect thereof or in relation thereto.

e) The Contractor shall construct all culverts crossing underneath road and their outfall and all drainage com-ponents before diver-sion of streams/drainage occurs.

5.10 PERMANENT DRAINAGE WORKS

a) The Contractor shall immediately construct all permanent drainage and ancillaries works upon reaching earth-work formation/finished levels in order to miti-gate surface erosion.

b) The Contractor shall maintain the drainage system from clogging and silting throughout construction period.

5.11 REVEGETATION VETIVER HEDGEROW GRASS

5.11.1 General

The Vetiver is used as bio-engineering system to com-plement structural works. Therefore it shall be of good and consistent quality.

5.11.2 Plant Materials

The plant shall be Vetiver Zizanioodes (Rumput Wangi) of the South Indian domesti-cated type. Only non-seeding types shall be used. It is criti-cal that the North Indian wild types, which flowers regularly and set fertile seeds, shall be absolutely avoided.

5.11.3 Starting Materials

Vigorously growing young tillers derived from tissue cul-ture or micro propagation method shall be used. The plantlets to be supplied shall be at least an aggregate of 5 plantlets when they are taken out of the test tubes prior to packing. The roots at the basal end of the aggregate of plantlets shall be at least 3 cmlong.

Page 26: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 25

ENVIRONMENTAL PROTECTION AND ENHANCEMENTS

ARAHAN TEKNIK ( JALAN ) 16 / 03

5.11.4 Container Plants

i) Vetiver hedgerows shallnever be planted from cut-root (bare-root) slips. Only container plants shall be used.

ii) Unless otherwise speci-fied, site nursery is required to receive the plantlets from tissue culture laboratory. The plantlets shall be imme-diately planted in black polyethylene bags uponarrival and appropriate irrigation and fertilizers shall be used.

5.11.4.1 Roots

The container plants must have active root-mass regen-erated in the container media during field planting.

The polybag shall be 12.7 cm x 17.7 cm (5” x 7”) dimension filled with good quality topsoil. The root-mass shall complete-ly bind the soil so that the soil core does not collapse when the polybag is removed prior to field planting.

5.11.4.2 Tops (shoot system)

The tops shall have 5 or moreactively growing tillers that have been regenerated and produced in-situ in the con-tainer. Old tillers extracted from the ground nursery and

senescent (decaying) tillers must not be included in the count. At delivery to site nurs-ery, the tops should be cut to a height of 30 cm.

5.11.4.3 Age of container plant

Any container plants which is ‘bag-bounded’ and with aged roots shall be rejected.

5.11.5 Site nursery

Unless the plant materials areproduced in central supply nursery near the work site, a site nursery is mandatory. Maximum care shall be exercised in handling and trans-porting of container plants to minimise transporting distur-bances.

The site nursery shall be irri-gated. Quality container plantsfrom the central supply nurs-ery shall be arranged at 15 cm x 1-meter spacing.

Plants shall be reconditioned in site nursery not less than 7 days prior to field planting. Only those plants, which havefully recovered from transport-ing disturbances, shall be used for field planting. To enhance transplanting suc-cess the use of anti-trans-parence and pre planting fer-tilizer application are encour-aged.

Page 27: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 26

ENVIRONMENTAL PROTECTION AND ENHANCEMENTS

ARAHAN TEKNIK ( JALAN ) 16 / 03

5.11.6 Field Planting

Quality Vetiver container plants shall be planted in rowsas specified in the drawings oras directed by the S.O.

i) A 15 cm width x 23 cm depth (6” x 9”) trench shall be excavated to receive the container plants.

ii) In difficult soil types, borrowed topsoil may be required to refill the trench.

iii) The between-plant dis-tance (center to center)shall be 15 cm or less.

An appropriate fertilizer pro-gramme, applied at the time of field planting, to ensure good continuous nutrient sup-ply for 2 years shall be used.

5.11.7 Establishment and Maintenance

All failures and washouts shallbe reinstated within the first month after field planting.

i) All slow growing clumps, which do not recover, from trans-planting disturbance shall be replaced. This is shown by lack of growth of the topped tillers and non-forma-tion of new tillers.

ii) Topping (grass cutting) to maintain 40-cm verti-cal height should be carried out at 2,4 and 6months after field plant-ing. Thereafter, the interval between top-pings would be deter-mined by needs, as directed by S.O.

iii) To ensure the good growth of Vetiver hedgerows, it shall not be shaded by other weeds especially scramblers.

5.11.8 Quality on Delivery on Hedgerows

i) At 3 months after plant-ing, the plants should be actively growing. The hedgerows should have no failures and norunts.

ii) At 6 months after plant-ing, the hedgerows should be fully function-al with uniform growth and basal tillers between clumps closedover, all to the satisfac-tion of S.O.

Page 28: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 27

ENVIRONMENTAL PROTECTION AND ENHANCEMENTS

ARAHAN TEKNIK ( JALAN ) 16 / 03

5.12 EROSION CONTROLMEASUREMENT

The vegetation cover is nor-mally used to minimise runoff and to keep the flow velocitiesthat can cause erosion. Detail of the protective vegetation shall be read in clause 2.2.8 Section 2 of Standard Specification for Roadwork.

This section only addresses on the construction and the maintenance of control ero-sion measures and to be usedin accordance to the size of respective catchment area.

The gabion walls used shall be constructed is accordance to the drawings and clause 3.6 of Standard Specification for Roadwork.

The methods of filtering the velocities of the sediment as used in this section are silt fences.

5.12.1 Silt Fences

A silt fence is a temporary barrier used for trapping silt and sediment from disturbed area during construction. It is a vertical barrier of geotextile supported by poles at regular interval. The geotextile shall be made of non-woven mate-rial with minimum properties of 200 g/m² or tensile strength15 kN/m.

Silt fences are generally effec-tive in locations where the flow is concentrated and are only applicable for sheet or overland flows.

They shall be placed at cleared areas in construction site especially below the toe of a cleared slope, along streams and channels with disturbed adjacent slope, around temporary stockpiles and across swales.

The fence should be inspect-ed after every rain and when a sediment accumulation of approximately 2/3 of the fenceheight is observed. The silt should be removed and dis-posed properly. The geotextileshould be checked for rips, tears and other types of dete-rioration and replaced as needed.

5.12.2 Silt Trap

A silt trap is a small temporaryponding area, usually with an outlet or channel formed by excavation and/ or construc-tion of gabion wall.

Its purpose is to collect and store sediment from sites cleared and/ or graded during construction. It is intended for use on small catchment areas( less than 2 hectares ). With no unusual drainage features, construction of silt trap shall be completed in a reasonably short period of time.

Page 29: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 28

ENVIRONMENTAL PROTECTION AND ENHANCEMENTS

ARAHAN TEKNIK ( JALAN ) 16 / 03

The trap is to be maintained regularly throughout the con-tract period including desilting when full or as directed by theS.O including making good of any damage portions during the course of the works. The desilted material shall be transported to disposal site approved by the S.O.

Silt trap shall be placed: -

1. Along the perimeter of the site at locations where sediment laden runoff is discharged off-site.

2. At any point within the site where sediment laden runoff can enter natural areas or water-ways including ponds, lakes, rivers and wet-lands.

5.12.2.1 Gabion Wall

A gabion wall consists of layer(s) of gabions used to trap sediments in catchment area of less than 1.0 acre or place in difficult terrain.

A series of gabion wall shall be required in difficult terrain.The gabion walls shall be constructed as shown on the drawing and accordance to the clause 3.6.9 Standard Specification of Roadwork.

5.12.3 Sediment Basin

A sediment pond or sediment basin is a structure formed by excavation and/or constructionof an embankment across a waterway or other suitable location.

Its purpose is to collect and trap sediment before it leaves the construction site.

A sediment basin should be used for areas greater than 2 hectares and maintained when a sediment accumula-tion of approximately 1/3 of the basin depth exist.

Page 30: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 29

PREAMBLE

Page 31: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 30

PREAMBLE

ARAHAN TEKNIK ( JALAN ) 16 / 03

6.0 PREAMBLE

6.1 Silt Fences

Units

The unit rate for measurementof silt fence shall be per metrerun (m/run).

Measurement

The measurement of silt fenceshall be based on per metre run (m/run).

Item Coverage

The item coverage shall be in accordance to Preamble to the Bill of Quantities

General Description including:

a) Clear site for silt fence area.

b) Construct silt fence including driving 1.8m long wooden post into ground, 1.5m apart, digging a 150mm deep trench along the fence and backfilling trench over base of geotextile.

c) Inspect after every rain.

d) The geotextile should be checked for rips, tears and other types ofdeterioration and replaced as needed.

e) Removal of sediment accumulated to approx-imate 2/3 of filter heightincluding disposal.

f) Provision of all requiredplant, equipment, mate-rial and labour.

6.2 Silt Traps and Sediment Basin

Units

The unit rate for measurementof silt trap and sediment basinshall be in number.

Measurement

The measurement for silt trap and sediment basin shall be innumber.

Item Coverage

The item coverage shall be in accordance to Preamble to the Bill of Quantities General Description including:-

a) Clear site for silt trap and weir.

b) Construct gabion over-flow including geotex-tile, filter stones, drain pipe and weir.

c) Reinstatement of silt trap.

d) Excavation to maintain required volume.

Page 32: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 31

PREAMBLE

ARAHAN TEKNIK ( JALAN ) 16 / 03

e) Removal of sediment accumulated to approx-imate 2/3 of filter heightincluding disposal.

f) Regular maintenance of silt trap throughout the contract period including desilting whenfull or as directed by the S.O and making good of any damaged portions of the silt trap during the course of theworks.

g) Provision of all requiredplant, equipment, mate-rial and labour.

6.3 Gabion Walls

Units

The unit rate for measurementof gabion wall shall be in cubic metres (m³).

Measurement

The measurement for gabion wall shall be in cubic metres (m³).

Item Coverage

The item coverage shall be in accordance to Preamble to the Bill of Quantities General Description including: -

a) Clear site for gabion wall area.

b) Trimming and levelling of foundation.

c) Construct gabions overflow including geot-extile and filter stones.

d) Excavation to maintain required depth for gabion wall.

e) Stonework.

f) Assembling, tying, fix-ing, staking and ten-sioning.

g) Placing under water, dewatering and pump-ing.

h) Geotextile fabric work.

i) Disposal of soil, surplusmaterial and reinstate-ment of sand filling.

j) Supply of perforated riser wrapped with geo-textile, if any.

k) Installation of drain pipes.

l) Removal of sediment accumulated of approx-imate 2/3 of filter heightincluding disposal.

m) Provision of all requiredplant, equipment, mate-rial and labour.

Page 33: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 32

PREAMBLE

ARAHAN TEKNIK ( JALAN ) 16 / 03

6.4 Lorry Wash Troughs

Units

The unit of measurement for lorry wash troughs shall be in number.

Measurement

The measurement for lorry wash troughs shall be as shown in the drawings.

Item Coverage

The item coverage shall be in accordance to the Preamble to the Bill of Quantities General Description including:

a) Preparation of site and approaches.

b) Excavation in whateverground except rock.

c) Disposal of excavated and desilted materials to dumping site.

d) Construction of wash trough.

e) Provision of all requiredplant, equipment, mate-rial and labour.

f) Filling and regular maintaining of water during the course of theworks.

g) Maintaining wash trough and surroundingareas clean.

h) On completion of the work, remove and dis-posed all rubbish, debris and surplus material from the site tothe satisfaction of the S.O.

6.5 Noise Barrier

Units

The unit rate for measurementof Noise Barrier shall be square metre (m²)

Measurement

The rate for the Noise Barrier shall be the barrier plane areain square metres to which the barrier is secured.

Item Coverage

The item for Noise Barrier shall include: -

a) Fabrication and prepa-ration.

b) Painting, and galvaniz-ing, if necessary.

c) Steel columns where necessary

Page 34: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 33

PREAMBLE

ARAHAN TEKNIK ( JALAN ) 16 / 03

6.6 Flora Survey

Units

The unit of measurement for the Flora Survey shall be in number.

Measurement

The measurement for the Flora Survey shall be based on the number of reports pro-duced.

Item Coverage

The item coverage shall be in accordance to the Preamble to the Bill of Quantities General Description including:

a) Flora Survey shall be carried out by either a professional Horticulturist or Botanist.

b) Cover the contract peri-od, maintenance periodand such time that is deemed necessary by the Department of Environment.

c) All mobilisation, living allowances and trans-portation charges.

d) Produce complete report on tree conser-vation plan, method of preservation and course of action to be taken.

Page 35: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 34

BILL OF QUANTITIES

Page 36: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 35

BILL OF QUANTITIES

ARAHAN TEKNIK ( JALAN ) 16 / 03

7.1 Environmental Protection Works

Item Description Unit Quantity Rate Amount

1.0

1.11.21.3

EIAPreparation of the :-EIA ReportSupplementary EIAUpdating of Data

LSLSLS

2.0

2.1

2.2

ENVIRONMENTAL MANAGEMENT PLAN (EMP)Preparation for the Environmental Management

Plan (EMP) Documents and execution of EMSISO 14001

To provide a full time Environmental Officerthroughout contract period

LS

man-mth

3.03.1

3.2

DUST AND MUD CONTROLWater Browser TruckSupply Browser Truck including operators, pump-ing of water, water tank and other necessaryequipments needed to carry out water spraying, 3times a day along existing road and near settle-ments as directed by the S.O.

Tyres Washing FacilitiesSupply portable water jet including operators,water tanks and other necessary equipmentsneeded to carry out cleaning tyres of vehicles atvarious exits from the worksites to be approved bythe S.O. Tyres washing shall be carried out onfirm surface (crusher run) prior to public roadentry.

No.

No.

Page 37: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 36

BILL OF QUANTITIES

ARAHAN TEKNIK ( JALAN ) 16 / 03

Item Description Unit Quantity Rate Amount

3.3 Wash TroughConstruct 250mm deep water-filled wash troughincluding excavation, backfill and disposal of sur-plus materials, formwork, reinforcement, hardcoreand placement of aggregate layer as directed bythe S.O. No.

4.04.1

4.1.1

4.1.2

4.24.2.1

4.2.2

4.3

EROSION CONTROLSilt fenceSupply and construct 1.0m height silt fenceincluding non-woven geotextile and wooden postwith dimension as shown on the drawing or asdirected by the S.O

Maintainance of silt fence

Silt Trap and Sediment BasinSupply and lay gabion box including excavation,jointing, backfilling and disposal of surplus materi-als as shown in the drawing and as directed bythe S.O all in accordance with the Specification tosuit with site condition1) Overall size 7.0 x 4.0 x 2.0 m height2) Overall size 15.0 x 4.0 x 2.0 m height3) Overall size 15.0 x 7.0 x 2.0 m height4) Overall size 25.0 x 9.0 x 2.0 m height

Maintenance of silt trap/sediment basin includingdesilting, repair and replacement ofdamaged/worn parts and materials as per specifi-cation

Gabion ProtectionSupply and construct 1.0 x 1.0 x 1.0 m height ofgabion boxes at the steep slope including bedpreparation, assembling, typing, staking, tension-ing and approved stone as shown on the drawingor as directed by the S.O.

lin.m

lin.m

No.No.No.No.

No.

M3

Page 38: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 37

BILL OF QUANTITIES

ARAHAN TEKNIK ( JALAN ) 16 / 03

Item Description Unit Quantity Rate Amount

5.05.1

OIL AND GREASE CONTROLSkid TankProvide labour and material to construct impervi-ous concrete base 10m x 5m x 0.125m with vari-able height sufficient to contain 110% volume ofstored oil including grease trap to prevent spilledoils overflow into natural streams. Demolish thesame and cart away debris upon completion ofthe project.

No.

6.06.1

6.2

6.36.3.1

6.3.2

6.3.3

ENVIRONMENTAL MONITORINGAir Quality MonitoringTo conduct air quality monitoring for the TotalSuspended Particulate (TSP) including windvelocity and the direction.

Noise Quality MonitoringTo conduct noise monitoring quarterly for thenoise monitoring (8 hours ave.) inc. Leq, L10 andL90.

Water Quality MonitoringTo conduct river water quality monitoring for thefollowing parameters: pH, Total Suspended Solids(TSS), Biochemical Oxygen Demand (BOD),Chemical Oxygen Demand (COD), DissolvedOxygen (DO), Oil & Grease, E. Coli andAmmoniacal Nitrogen

To conduct water quality monitoring at the effluentdischarge of accommodation area for the follow-ing parameters: pH, Total Suspended Solids(TSS), Biochemical Oxygen Demand (BOD),Chemical Oxygen Demand (COD), DissolvedOxygen (DO), Oil & Grease, E. Coli andAmmoniacal Nitrogen

To conduct water quality monitoring at outlet of silttrap area for Total Suspended Solid (TSS) param-eter

No.

No.

No.

No.

No.

Page 39: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 38

BILL OF QUANTITIES

ARAHAN TEKNIK ( JALAN ) 16 / 03

Item Description Unit Quantity Rate Amount

7.0 NOISE BARRIERDesign, supply and install noise barrier where andwhen necessary.

m2

8.08.1

8.2

FLORATo conduct flora survey throughout the contract.

To relocate, maintain and transport trees with girth300mm and below :

a) to nearby sites approved by forester or botanist

b) to arboretum

No.

No.

No.

9.0 FAUNATo conduct fauna survey and produce statusthroughout the contract period

L.S

10.0 ENVIRONMENTAL MONITORING REPORTTo submit monthly monitoring report No.

11.0 ENVIRONMENTAL AUDIT REPORTTo conduct and submit quarterly environmentalaudit report

No.

Page 40: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 39

DRAWINGS

Page 41: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 40

DRAWINGS

ARAHAN TEKNIK ( JALAN ) 16 / 03

Page 42: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 41

DRAWINGS

ARAHAN TEKNIK ( JALAN ) 16 / 03

Page 43: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 42

DRAWINGS

ARAHAN TEKNIK ( JALAN ) 16 / 03

Page 44: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 43

DRAWINGS

ARAHAN TEKNIK ( JALAN ) 16 / 03

Page 45: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 44

DRAWINGS

ARAHAN TEKNIK ( JALAN ) 16 / 03

Page 46: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 45

DRAWINGS

ARAHAN TEKNIK ( JALAN ) 16 / 03

Page 47: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 46

DRAWINGS

ARAHAN TEKNIK ( JALAN ) 16 / 03

Page 48: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 47

DRAWINGS

ARAHAN TEKNIK ( JALAN ) 16 / 03

Page 49: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 48

APPENDIX A

GENERAL GUIDELINES for the PREPARATION of the ENVIRONMENTAL

MANAGEMENT PLAN (EMP)By the CONTRACTOR.

Page 50: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 49

GENERAL GUIDELINES for the PREPARATIONof the EMP by the CONTRACTOR

ARAHAN TEKNIK ( JALAN ) 16 / 03

1.0 INTRODUCTION

This Guideline is for the Contractor to prepare site specific Environmental Management Plan (EMP) as aproper environmental man-agement approach during project implementation. This Guideline is in conformation and to be read in conjunction with the following documents:

- The EIA report for the project - approved by the Department of Environment DOE (if any).

- EIA Condition's of Approval from DOE (attached if any).

- JKR Contract Specifications: Section 1 - General

- Shall be as an adden-dum to the Condition ofContract

It should be clearly noted the EMP is a document for practi-cal use on site by nominated personnel and thus should be concise, updated and site specific. This guideline has been prepared in line with Environmental Management System (EMS).

The Contractor shall submit the EMP prepared to the S.O. within 30 days in compliance with item (XX) in the Condition of Contract/ Special Provision.

2.0 OBJECTIVE

The main objectives of the Environmental Management Plan (EMP) are to set out a comprehensive programme which will form the basis for implementing environmental mitigation measures, environ-mental monitoring and envi-ronmental auditing of the con-struction works by the Contractor as appended below:

i. To set out various envi-ronmental protection/ conservation measuresthat conform with the environmental condi-tions stipulated in the Contract Specifications,EIA report and by otherrelevant authorities (e.g. the Department ofEnvironment - DOE) in the EIA Conditions of Approval.

GENERAL GUIDELINES for the PREPARATION of the ENVIRONMENTALMANAGEMENT PLAN (EMP) - By the CONTRACTOR.

Page 51: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 50

GENERAL GUIDELINES for the PREPARATIONof the EMP by the CONTRACTOR

ARAHAN TEKNIK ( JALAN ) 16 / 03

ii. To ensure that the Contractor engaged by the Government com-ply with all applicable environmental standardand guidelines, legisla-tive requirements, limit values and other rele-vant conditions related to environments in the implementation of the project.

iii. To specify a detailed environmental monitor-ing and auditing pro-gramme to ensure that the Contractor and all Sub-contractors complywith all stipulated requirements through-out the duration of the project.

iv. To streamline the differ-ent functions of varioussections and authoritiesrelated to the environ-mental matters during the construction.

3.0 SCOPE OF ENVIRONMENTALMANAGEMENT PLAN (EMP)

The scope of the EMP shall cover all activities and opera-tions of the Contractor that can cause environmental impacts throughout the con-struction phase of the project. It shall also include environ-mental monitoring, conservation and preservation and auditing activities.

4.0 SUMMISSION OF ENVIRON-MENTAL MANAGEMANT PLAN

The preparation of the EMPshall take into consideration ofthe following: -

Summary of Key Environmental issues.

This section shall com-prise a concise site specific list of key envi-ronmental issues for the awarded package. It should also include sensitive environmentalreceptors like down-stream water intakes, orang asli settlements, etc. The purpose is to clearly highlight the main impacts and the sensitive environmentalreceptors.

List of Legal and Other Requirements.

This section shall list allthe relevant legislation that the Contractor has to comply which are applicable to the envi-ronmental aspects of the project activities. This shall include the specified environmentalstandards for air, water and noise quality.

Page 52: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 51

GENERAL GUIDELINES for the PREPARATIONof the EMP by the CONTRACTOR

ARAHAN TEKNIK ( JALAN ) 16 / 03

The structure of the EMP dur-ing the construction stage shall include but not be limitedto the following:

4.1 Project Schedule and Sequence of Construction

A detailed project schedule which integrate environmental mitigation measures within theoverall project schedule and astatement of how the Contractor intends to sequence the construction works including temporary work to minimise environmen-tal impacts i.e. minimise earth surfaces from being exposed bare for long periods, carry out turfing, construct mitiga-tion measures, etc. This schedule shall be in line with the main overall Project Implementation Schedule.

4.2 Roles and Responsibility

The Contractor shall specify the person(s)/parties employed/engaged for the duration of the contract who are responsible for implement-ing the actions specified in theEMP. An organization chart shall be provided for environ-mental management teams, which shall include.

i. Environmental Officer.ii. An independent

Environmental Auditoriii. An Accredited

Analytical Laboratory.

4.3 Communication

This section shall include a flow diagram for internal and external communication of environmental related matters including channels for public complaints, correspondence with regulatory authorities, monitoring and audit reports, etc. It shall include a list of updated contacts number of key personnel responsible for environmental management.

4.4 Implementation of Mitigation Measures

This section shall specify the methods and mitigation meas-ures which the Contractor will provide/carry out to satisfy thestipulated environmental requirements. These shall be preventive where applicable. Itshall include but not be limitedto the following:

Disposal of Surplus Cut MaterialThis section shall state the Contractor's method of disposal andmanagement of dispos-al sites to minimise environmental damage,i.e. erosion and silta-tion, etc. The locations of the disposal sites shall be clearly indicat-ed and approved by theS.O.

Page 53: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 52

GENERAL GUIDELINES for the PREPARATIONof the EMP by the CONTRACTOR

ARAHAN TEKNIK ( JALAN ) 16 / 03

Soil Erosion and Silt Control Plan This will include a drainage plan showing temporary drains, silt traps and all other measures to control erosion and siltation and a description of themethods used com-plete with an effective maintenance regime.

Liquid/Solid Waste ManagementThis shall include meth-ods and locations for disposal of constructionwaste materials, excess materials, etc.

Schedule Waste Management This shall specify col-lection, storage and disposal methods of waste oil from vehicle maintenance.

Turfing This section will specifythe methods used and the timing of executing turfing or hydroseeding activities, i.e. immedi-ately after earthwork and before work on other berm/lift com-mences.

Other Site Specific Mitigation Measures This section shall spec-ify methods to address all other mitigation measures specified in Section 1 (in the Contract Specification) as well as any other environmental issues identified during projectimplementation.

4.5 Emergency Preparedness

This section shall set out emergency response proce-dures, plans and communica-tions in the event of an emer-gency e.g. landslides, traffic accidents etc.

4.6 Environmental Monitoring Programme

The main objective of carryingout environmental monitoring is to assess the effectiveness of the mitigation measures and to provide a trigger for action should the stipulated environmental standards be breached. The Contractor shall carry out the data collec-tion monitoring as specified in Section 5.5 below.

Page 54: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 53

GENERAL GUIDELINES for the PREPARATIONof the EMP by the CONTRACTOR

ARAHAN TEKNIK ( JALAN ) 16 / 03

4.7 Non-conformance Corrective and Preventive Action

This section shall stipulate corrective as well as preven-tive actions that will be initiat-ed if environmental non-com-pliances are detected from monitoring data or environ-mental audits.

4.8 Records

All environmental monitoring and audit reports as well as correspondence related to environmental management shall be retained at the site throughout the duration of the project. Records shall be stored securely and protected from damage. Records shall be made available to JKR or any other regulatory agencies upon request. The records are : -

Monitoring data.Audit reports.Management Review Records.

4.9 Environmental Audits

This section shall include the auditing procedure and set outan auditing schedule. The audit will focus on implemen-tation of the EMP and the other environmental manage-ment elements in the imple-mentation of the project. The

Contractor shall appoint an independent Professional Environmental Auditor to undertake the following tasks:

Carry out environmen-tal compliance audits quarterly to check implementation of the EMP.Interpret monitoring data.Verify implementation of corrective and pre-ventive action.Prepare a comprehen-sive environmental auditing report.

The environmental auditor selected shall have the neces-sary expertise and experienceto execute the work diligently and professionally in accor-dance to the requirements of ISO 14000. The environmen-tal auditor shall be registered with DOE.

Compliance audits shall be carried out quarterly.

4.10 Management Review

The Contractor shall seek the S.O. approval to arrange a management review on a peri-odic basis on the effective-ness of the Environmental Management Plan (EMP).

Page 55: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 54

GENERAL GUIDELINES for the PREPARATIONof the EMP by the CONTRACTOR

ARAHAN TEKNIK ( JALAN ) 16 / 03

5.0 ENVIRONMENTALMONITORING

The Contractor shall carry out environmental monitoring for the parameters stipulated in the Bill of Quantities. The actual sampling locations on site shall be stipulated in the EMP and will be subject to confirmation by the S.O. prior to commencement. All equip-ment shall be calibrated prior to use and monitoring shall bedone according to the follow-ing methods:

5.1 Air Quality

Ambient air quality monitoring shall be carried out to monitor for Total Suspended Particulates (TSP) using a High Volume Air Sampler. Thefollowing meteorological parameters shall be recorded during the sampling period to allow interpretation of the data:

Wind speed and direc-tionDetermination of weather conditions (cloudy, rainy, etc.)

Analysis of samples shall be carried out by an independentaccredited laboratory stated inthe EMP.

5.2 Water Quality

Water quality of streams, rivers and outlets of mitigationponds shall be monitored for the parameters: pH, Total Suspended Solids (TSS), Oil & Grease, Dissolved Oxygen (DO), Biological Oxygen Demand (BOD), E. coli and Chemical Oxygen Demand (COD), where applicable.

All field sampling shall be car-ried out by trained field per-sonnel and the samples shall be analysed in an accredited laboratory. The results from the laboratory shall be signed by a registered chemist. The analytical methods used shall be in accordance to the latest edition of 'Standard Methods for the Analyses of Water and Wastewater' as required underthe Environmental Quality Act (1974).

5.3 Noise

Ambient noise level (8 hour average) shall be carried out by a qualified person at sensi-tive locations such as schools,hospitals, residential areas and orang asli settlements as stated in the EMP. These noise measurements shall be taken at the boundary of respective sensitive areas.

Page 56: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 55

GENERAL GUIDELINES for the PREPARATIONof the EMP by the CONTRACTOR

ARAHAN TEKNIK ( JALAN ) 16 / 03

7.0 QUANTITIES AND COSTS

The quantities set out in the Bill of Quantities are estimat-ed quantities of works to be executed by the Contractor and are provided for the pur-pose of comparing tenders.

The actual payment to be made to the Contractor shall be the actual quantity of work carried out and accepted by the S.O. for each item of workdescribed in the Bill of Quantities and the rate or price inserted therein.

6.0 DELIVERABLES

The following documents shall be submitted by the Contractor throughout the construction phase of the project:

Note : A baseline set of environment monitoring shall be carried out prior to the preparation of the EMP.

Documents No. of Copies

ReportingFrequency

Timing

EnvironmentalManagement Plan (EMP)

8 Once only Within 30 days from thedate of the Letter ofAcceptance

Environmental MonitoringReports

8 Monthly 2 weeks after monitoring

Environmental AuditReports

8 Quarterly 2 weeks after audits

Page 57: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 56

APPENDIX BGUIDELINES FOR BULK FUEL STORAGE TANKS

Page 58: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 57

GUIDELINES FO BULK FUELSTORAGE TANKS

ARAHAN TEKNIK ( JALAN ) 16 / 03

1. General

a) The contractor shall storage fuel (diesel, petrol) in proper bulk storage tanks/skid tanks. This tank should be placed in one loca-tion only for each work package and must be within the maintenance yard area. The tanks must be properly bund-ed and maintained properly.

b) The Contractor shall store all chemicals and hazardous materials in suitable containers withappropriate labelling. Acopy of the Material Safety Data Sheet (MSDS) must be kept on Site at all times.

c) The Contractor must comply with the Classification, Labelling& packaging (CLP) Regulations under the OSHA.

2. Location

a) In general, the storage tanks cannot be sited near the following areas

i) Close to water-ways (rivers/drains) or drinking water sources

ii) Close to weldingworkshops / naked flames

iii) Close to public areas

iv) Close to labour camps

v) Close to over-head high ten-sion cables

b) All tanks shall be aboveground. Underground tanks are strictly pro-hibited.

c) Tanks must be located at least 25m away fromthe site office and 50m away from labour camp. Where multiple tanks are present, the tanks must be spaced at least 2m apart.

GUIDELINES FOR BULK FUEL STORAGE TANKS

Page 59: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 58

GUIDELINES FO BULK FUELSTORAGE TANKS

ARAHAN TEKNIK ( JALAN ) 16 / 03

3. Containment bund

a) The Contractor must construct a perimeter bund around the stor-age tank to contain the contents of the tank in the event of spillage. The bund should be made of concrete or bricks and should be atleast 0.5m high.

b) The floor area within the bund wall must be constructed using impermeable material to prevent the product from seeping into the ground. Concrete floor-ing is recommended. The Floor must be even.

c) The bund-wall around the storage tanks should have a capacity to contain the worst spillage condition (110% of the capacity of the largest contain-er).

d) The bunded area shall be graded to a sump where an oil-water sep-arator should be installed and regularly maintained. There should not be any opening in the bund wall that may allow sur-face water run-off from the entering the stor-age site.

e) A safety barrier should be erected between thebund-wall and discharge bay to prevent trucks from knocking into the bund wall.

4. Hazard identification

a) At the entrance to the storage site, a sign-board should be set up with the words "BAHAYA" and "DAN-GER” , painted with a letter size of 30cm on abright yellow back-ground. The words "DILARANG MEROKOK" and 'NO SMOKING" must also be clearly displayed.

b) The Contractor must comply with the Classification, Labelling& Packaging (CLP) Regulations under the Occupational Safety and Heath Act 1994 (OSHA).

Page 60: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 59

GUIDELINES FO BULK FUELSTORAGE TANKS

ARAHAN TEKNIK ( JALAN ) 16 / 03

5. Routine maintenance

a) Surface oil from the sump/oil interceptor shall be skimmed off at regular intervals. The skimmed oil must be transferred to the wasteoil storage drums.

b) The Contractor must ensure that all joints, pipes and hoses used to load and unload the fuel from the tanks are not leaking. All leaks should be repaired immediately.

c) The tanks must be checked weekly for leakage. Any leakage so detected shall be attended to immediate-ly.

d) Truck movement near the tanks shall be con-trolled. The truck speedshall be limited to no more than 5 km/hr. Alltrucks parking next to the tanks shall be supervised. Lorry driv-ers should not be allowed to reverse or park their vehicles with-out supervision from the ground.

e) If the tanks are placed on an earth mound, regular checks must becarried out to ensure that soil beneath the tanks is not eroding.

6. Fire prevention & fire fighting

a) Dry powder fire extin-guishers shall be madereadily available at the storage tank area for use in the event of a fire.

b) No welding / hot works should be carried out within 50m of the stor-age tanks. No naked flame should for any reason be brought close to the tanks.

c) The telephone numbersof Jabatan Bomba shallbe displayed promi-nently at the site office and on the tanks.

d) In the event of a fire, the Contractor shall activate Emergency Response Plan.

Page 61: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 60

GUIDELINES FO BULK FUELSTORAGE TANKS

ARAHAN TEKNIK ( JALAN ) 16 / 03

7. Oil and chemical spillage

a) All spillage incidents of oil, diesel, petrol and chemicals must be reported to the DOE within 24 hours of their occurrence.

b) If the spill involves large quantities of petrol or diesel spillage,is should be consideredas an Emergency and the Emergency Response Plan should be activated.

c) If a minor spill occurs, efforts must be made tocontain the spill imme-diately. Sawdust or sand should be used tocontain the spill from spreading. When the spill has been con-tained, the spilled material must be removed immediately using appropriate means and stored in storage drums. None ofthe spill shall be flushed into the drainage system.

d) For the purpose of spill containment 20kg pails containing sand or saw-dust must always be placed next to all bulk storage tanks.

Soil contaminated by fuel and oil must not be washed with water. The contaminated soil should be removed and storedin waste storage drums and labelled accordingly.

Page 62: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 61

APPENDIX C

NEEDS STATEMENT

Page 63: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 62

NEEDS STATEMENT

ARAHAN TEKNIK ( JALAN ) 16 / 03

1.0 PROTECTION OF THE ENVIRONMENT

The Contactor shall limit and control site clearing works to construction areas only. Existing trees are to be retained as much as possible and minimum tree cutting is allowed unless they impose danger to the public and trafficafter completion of the project.

Topsoil from construction areas are to be transported to an area approved by the P.D. and reused for turfing, hydroseeding and landscapingpurposes.

Turfing / hydroseeding is to bedone immediately to slopes upon reaching their formation levels. To provide growth on cut slopes, hydroseeding shallbe carried out together with bio-degradable or equivalent materials. Landscaping works shall commence early as per direction of the P.D.

The Contractor shall take nec-essary precautions to prevent the deposition of any debris, rubbish, silt, waste materials, foul water, chemicals, etc. arising from the execution of the Works into existing streams/waterways. This pro-vision may be varied only withthe written approval of the P.D.

The Contractor shall divert existing drains, waterways, etc. encountered during the progress of the Works without disrupting their flow system and if such diversion is tem-porary, he shall subsequently reinstate the same subject to the P.D.'s approval.

The Contractor shall constructberm drains, interceptor drains and other related drainage works to slopes which have reached the required formation levels. Temporary cover, for example,polythene or plastic cover shall be provided by the Contractor to exposed cut slopes.

The Contactor shall provide soil erosion control measures including silt fences, silt traps, sedimentation basins, etc. throughout the construction of the Works and restore and landscape sedimentation basins upon completion of contract.

The Contractor shall take nec-essary precautions to ensure that tyres of all vehicles leav-ing the site are free of mud.

The Contractor shall not carry out any open burning on the site without the written approval of the P.D.

EXAMPLE OF NEEDS STATEMENT FOR ROAD PROJECT

Page 64: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 63

NEEDS STATEMENT

ARAHAN TEKNIK ( JALAN ) 16 / 03

The Contractor shall be held solely responsible for the suffi-ciency of precautions taken byhim to protect the environmentand shall entirely at his own cost comply with requirementsimposed by the relevant Authority.

The Contractor shall supply and lay at least to the base layer immediately to roads which have reached the required formation levels including the required drainage system.

The Contractor shall take the necessary measures and actions for the conservation and protection of the environ-ment.

(i) Environment Quality Act 1974

The Contractor shall comply with all aspects of the Environmental Quality Act 1974 which has relevance to the design, construction, equipping and commis-sioning of the proposedproject.

(ii) Other Related Environmental Legislations

The Contractor shall beaware of the following legislation and take all measures necessary toensure compliance.

(a) Environmental Quality (Clean Air) Regulations,1978

(b) Street, Drainage and Building Act,1974: Act 133 and Amendment,1978

(c) Protection of Wildlife Act, 1972 (Act 1976)

(d) Land Conservation Act, 1960

(e) Drainage Ordinance Act 1954

(f) Water Enactment - Chapter 146: water (1935)

(iii) Environmental Impact Assessment (EIA) and Environmental Management Plan (EMP)

Where EIA is required by the said Act, the Contractor shall pre-pare, submit and obtainapproval from the Department of Environment (DOE) and shall incorporate inhis Works all the abate-ment and mitigation measures for environ-mental protection and environmental monitor-ing as required by the DOE.

Page 65: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 64

NEEDS STATEMENT

ARAHAN TEKNIK ( JALAN ) 16 / 03

Should EIA be found not mandatory, an Environmental Management Plan (EMP) shall be required. In this case, the scope and cover-age of all abatement and mitigating meas-ures for environmental protection and monitor-ing which are deemed to be covered as in Appendix A.

The Contractor shall beliable for and shall indemnify the Government in respect of any claim or pro-ceeding arising from his neglect of his provi-sion. All costs associat-ed therewith shall be deemed to be included in the Contract Sum.

(iv) Accommodation For Workmen In Relation To Safety and Health Requirements

The Contractor shall provide and maintain atthe Site, suitable and sufficient shelters, mess rooms and camps for his workmenand supervisory staff asare customary and nec-essary.

The locations of the workmen's accommo-dation shall be agreed beforehand with the P.D. and shall be such as to avoid obstruction and nuisance to the Works and public and shall be laid out in an approved and orderly manner.

The construction and habitation of the accommodation shall comply with the local statutory or other Government authoritiesand subjected to the approval of the P.D.

Sufficient toilet facilitiesshall be provided to thesatisfaction of the P.D. and Government Health Officer. Proper provision shall be madefor the disposal of all wastes and refuse and there shall be an ade-quate supply of water for washing, cooking and drinking purposes.The sleeping quarters shall be properly venti-lated and lighted.

The Contractor shall maintain the Site in a clean and sanitary con-dition and shall comply with all requirements ofGovernment, Health and Sanitary Authorities.

Page 66: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 65

NEEDS STATEMENT

ARAHAN TEKNIK ( JALAN ) 16 / 03

The Contractor shall bewholly responsible for the workmen at the accommodation provid-ed. Activities such as hunting/trapping of wildlife should be strict-ly forbidden and fines/penalties shall be imposed on the Contractor by the rele-vant Government Departments.

2.0 ENVIRONMENTALMANAGEMENT PLAN (EMP)

The Contractor shall comply with all legal duties and obli-gations regarding the protec-tion of the environment as laiddown in the Environmental Quality Act 1974 (Act 127). Before commencement of works the Contractor shall submit to the Cawangan AlamSekitar (in JKR HQ) an envi-ronmental management plan, detailing the Contractor's pro-posed arrangement for the abatement and mitigation measures for environmental protection, environmental monitoring, testing pro-grammes and reporting, and his organisation chart. A copyof the EMP shall be submittedto Department of Environment(DOE) in the Headquarters while another copy to the State DOE. The Contractor shall also comply with all con-ditions laid out by all relevant authority including the Department of Environment.

The Contractor shall engage the following qualified person-nel on site:

a. Environmental Officer (Full Time)

b. Safety and Health Officer (Full Time)

c. Horticulturist / Plant / Tree Expert (Part Time)

d. Fauna Expert (Part Time)

All bakau areas shall be pre-served because of its impor-tance in preventing of erosion of the shoreline and also its role as and area for the growth of marine life. Cutting of bakau trees shall be limitedto areas necessary for the construction of the Works only, subject to prior approval of the appropriate authorities, namely the DOE, Forestry department, Local Authority, Land Office, etc. No bakau piles are allowed to be used for this project.

Page 67: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 66

NEEDS STATEMENT

ARAHAN TEKNIK ( JALAN ) 16 / 03

3.0 ENVIRONMENTAL AUDITING

The Contractor shall engage aregistered and Third Party Environmental Auditor to auditall activities on site as per ISO14001 requirements. The tasks of the Auditor among others are:

a. To carry out environ-mental compliance audits quarterly to check implementation of the EMP.

b. To interpret monitoring data.

c. To verify implementa-tion of corrective and preventive action.

d. To prepare a compre-hensive environmental auditing report.

Reports shall be submitted to Cawangan Alam Sekitar in JKR HQ.

4.0 TRAINING

The contractor shall provide training for three (3) officers inthe field of environment. This training shall include Environmental Conservation, Post EIA and Environmental Monitoring, and EnvironmentalManagement System in Project Construction. The training shall be conducted and given by an established organization, which gives pri-ority in environment during project management and con-

struction including the transferof technology relevant to suchdevelopment.

Page 68: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 67

APPENDIX DDEPARTMENT OF ENVIRONMENTAL FORMAT FOR

PREPARATION OF ENVIRONMENTAL MANAGEMENTALPLAN (EMP)

Page 69: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 68

DOE’S FORMAT FORPREPARATION OF EMP

ARAHAN TEKNIK ( JALAN ) 16 / 03

1. PENGENALAN2. POLISI3. CARTA ORGANISASI,

TANGGUNGJAWAB & BUDGET IMPLEMENTASI

4. KEPERLUAN ALAM SEKITAR

5. PROGRAM PENGAWASAN6. IMPAK KETARA DAN

LANGKAH-LANGKAH KAWALAN PENCEMARAN

7. PELAN KONTIGENSI ALAM SEKITAR

PENGENALAN

1. Konsep projek yang telah diluluskan oleh Pihak Berkuasa Tempatan

2. Jadual Pelaksanaan Kerja

POLISI

1. Matlamat syarikat dalam memulihara alam sekitar

2. Komitmen pihak pengu-rusan secara berteru-san dalam memastikanpematuhan ke atas keperluan alam sekitar

CARTA ORGANISASI / BELANJAWAN

1. Pihak pengurusan tert-inggi dan nama-nama pegawai yang bertang-gungjawab dalam men-guruskan hal ehwal alam sekitar (senarai iniperlu dikemaskini bila ada sebarang peruba-han)

2. Nama perunding atau makmal bertauliah yang menjalankan kerja-kerja pen-gawasan atau yang bertanggungjawab untuk membuat sebarang analisa atau laporan alam sekitar

3. Kekerapan dan latihan berkaitan dengan alam sekitar dan kesela-matan kepada pekerja

4. Anggaran belanjawan untuk melaksanakan Pelan Pengurusan Alam Sekitar

FORMAT PELAN PENGURUSAN ALAM SEKITAR (EMP)(Plan, Implement, Check and Review)

Page 70: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 69

DOE’S FORMAT FORPREPARATION OF EMP

ARAHAN TEKNIK ( JALAN ) 16 / 03

KEPERLUAN ALAM SEKITAR

1. Syarat-syarat Kelulusan EIA dan Rayuan Ubah-Syarat (Jika ada)

2. Standard dan peratu-ran-peraturan yang ter-libat

3. Laporan-laporan pen-gawasan dan kekera-pannya

4. Salinan sebarang kebe-naran atau kelulusan bertulis yang telah dikeluarkan oleh JAS

PROGRAM PENGAWASAN

1. Kajian garisdasar bagi kualiti air, udara dan bunyi bising sebelum kerja-kerja bermula sebagai perbandingan terhadap data-data pemantauan yang akandikemukakan seterus-nya

2. Stesen-stesen pen-gawasan hendaklah ditetapkan dan ditun-jukkan di dalam peta - justifikasi pemilihan kawasan hendaklah dikemukakan

3. Takat pelepasan effelu-en hendaklah ditun-jukkan

4. Kekerapan pen-gawasan dijalankan

5. Kaedah-kaedah yang digunakan dalam per-sampelan.

IMPAK KETARA DAN LANGKAHLANGKAH KAWALAN PENCEMARAN

1. Impak yang ketara hen-daklah dikemukakan dan diikuti dengan langkah-langkah kawalan yang spesifik seperti lokasi perangkap mendap yang dicadangkan, cerun-cerun yang telah dikenalpasti akan men-galami hakisan dan cadangan pemuli-haraan cerun yang lebih spesifik, pemilihankawalan pelepasan udara dan sebagainya.

2. Sistem perawatan air buangan dan kawalan pencemaran udara jugahendaklah telah dike-nalpasti dan ringkasan konsep hendaklah dike-mukakan

3. "Abandonment Plan" sekiranya projek ter-tangguh

Page 71: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 70

DOE’S FORMAT FORPREPARATION OF EMP

ARAHAN TEKNIK ( JALAN ) 16 / 03

PELAN KONTIGENSI ALAM SEKITAR

1. Tindakan sekiranya berlaku kecemasan seperti tanah runtuh, tumpahan minyak atau bahan-bahan kimia merbahaya, kegagalan sebarang alat kawalan pencemaran

2. Organisasi yang terlibatdalam menguruskan pelan tersebut.

PENUTUP

Secara keseluruhan, EMP ini akan membantu dalam memudahkan perancangan, kawalan, pengawasan, langkah-langkah pembaikan dan penguatkuasaan oleh JAS dalam memastikan semua syarat-syarat dipatuhi apabila pelan ini dilaksanakansepenuhnya.

EMP ini juga mestilah berse-dia untuk diubahsuai bagi keadaan-keadaa yang berke-mungkinan

Nota:Semua Perunding EIA dan Penggerak Projek hendak-lah mengikut dan mengguna-pakaicontoh format EMP ini.

Page 72: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 71

APPENDIX EEXAMPLES OF MITIGATION MEASURES

Page 73: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 72

EXAMPLE OF MITIGATION MEASURES

ARAHAN TEKNIK ( JALAN ) 16 / 03

Examples of mitigation measures practised on site.

1. Silt Trap

Page 74: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 73

EXAMPLE OF MITIGATION MEASURES

ARAHAN TEKNIK ( JALAN ) 16 / 03

2. Sediment Basin

3. Silt Fence

Page 75: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 74

EXAMPLE OF MITIGATION MEASURES

ARAHAN TEKNIK ( JALAN ) 16 / 03

4. Lorry Browser Truck

5. Slope and Shoulder Protection

Page 76: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 75

EXAMPLE OF MITIGATION MEASURES

ARAHAN TEKNIK ( JALAN ) 16 / 03

5. Slope and Shoulder Protection ( condt... )

6. Skid Tank

Page 77: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 76

EXAMPLE OF MITIGATION MEASURES

ARAHAN TEKNIK ( JALAN ) 16 / 03

7. Scheduled Waste Management

Examples of Animal Crossings in Malaysia and Overseas

Culvert cum animal bypass Squirrel Crossing, Australia

Page 78: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 77

EXAMPLE OF MITIGATION MEASURES

ARAHAN TEKNIK ( JALAN ) 16 / 03

Animal bypass - Austria

Animal bypass cum green belt

Page 79: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 78

EXAMPLE OF MITIGATION MEASURES

ARAHAN TEKNIK ( JALAN ) 16 / 03

Fish Light

Flora Salvaging

Protected species salvaged and send to arboretum

Page 80: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 79

APPENDIX FEXAMPLES OF ENVIRONMENTAL MONITORING

Page 81: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 80

EXAMPLES OF ENVIRONMENTALMONITORING

ARAHAN TEKNIK ( JALAN ) 16 / 03

1. Examples of Water Quality Monitoring

Page 82: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 81

EXAMPLES OF ENVIRONMENTALMONITORING

ARAHAN TEKNIK ( JALAN ) 16 / 03

2. Examples of Air Quality Monitoring

Page 83: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 82

EXAMPLES OF ENVIRONMENTALMONITORING

ARAHAN TEKNIK ( JALAN ) 16 / 03

3. Example of Noise Monitoring

Page 84: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 83

EXAMPLES OF ENVIRONMENTALMONITORING

ARAHAN TEKNIK ( JALAN ) 16 / 03

Good and bad practices during construction

Bad practice Good practice

Pushing of earth to the edge of river Installation of gabions to minimize that can cause an impact to the water pollution to the river and can ecosystem and high turbidity of act as a silt trap. water quality.

Improper management of site Fixing of slope protection using clearing and slope cutting "Fibromat" and hydroseeding

immediately when the slope formation is ready

Page 85: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 84

EXAMPLES OF ENVIRONMENTALMONITORING

ARAHAN TEKNIK ( JALAN ) 16 / 03

Good and bad practices during construction

Bad practice Good practice

Scene of soil erosion and slope Turf immediately after public utilitiesfailure laid

Improper management of scheduled Construction of concrete base andwaste. perimeter bund around skip tanks

to avoid spillage

Page 86: Arahan Teknik (Jalan) 16-03 - An Effective Approach to Prepare Bill of Quantities for Environmental Protection

Page 85ARAHAN TEKNIK ( JALAN ) 16 / 03

REFERENCES

a. Environmental Quality Act 1974 (Act 127) & Subsidiary Legislations.

b. Guideline For The Environmental Impact Assessment of Highway/ Road Project.

c. Jabatan Kerja Raya EMS ISO 14001 Environmental Manual & Procedure

d. Nota Teknik (Jalan) 22/01 : A Practical Guide To Prepare Bill OfQuantities For Environmental Protection & Enhancement.

e. Cawangan Jalan, Ibu Pejabat JKR, 50582 Kuala Lumpur, Standard Specification For Road Works: JKR/SPJ/1988.

f. Document Contract for Cadangan Jalanraya Simpang Pulai -Lojing - Gua Musang - Kuala Berang, Pakej 3- Ladang Blau Valley ke Lojing Project.

g. Manual Saliran Mesra Alam Malaysia.

h. Environmental Impact Assessment Guidelines For Forestry.