APS Student TransportationBus Depot East

10 Shady Oak CircleTijeras, NM 87059

APS Student Transportation Bus Depot East Executive Summary

3. Summary of Spaces (Net SF):Building Support: 612 SF

Circulation: 2,219 SF

Maintenance: 4,565 SF

Operations: 3,572 SF

Fueling Canopy: 2,900 SF

Wash Bay: 1,107 SF

Wash Equipment: 280 SFProject Design TeamArchitectural: DWL Architects & Planners Inc. of NM Contact: Willard Eastman 505.242.6202

Civil: Miller Engineering Consultants Contact: Verlyn Miller 505.888.7500

Structural: RME ABQ, LLC Contact: Dave Sullens 505.889.3004

Mechanical, Electrical, Plumbing: Testudo Engineering Contact: Wayne Yevoli 505.554.1282 ext. 1002

1. New 11,839 square foot pre-engineered metal building will accommodate:a) APS Student Transportation Department satellite 50 Bus Maintenance & Operations function to serve the district’s east mountain community members and students. Support structures include a single bay bus wash building and an overhead canopy at the above ground fuel storage tank and dispensers.

2. Per Planning and Programming phase conducted in spring of 2017 and updated in September & October, 2020 this facility is required to:

a) Accommodate three distinct areas of work where the Administrative and Maintenance functions are secure and separated from the Drivers and Assistants spaces, but which all share common support & training spaces to be more efficiently supported with utilities, technology and media capacity.b) Accommodate streamlined spaces to support the running maintenance requirements for the bus fleet operating from this satellite facility with adequate secure storage areas and common work spaces.c) ) Incorporate bus maintenance equipment identified as Owner Furnished Contractor Installed (OFCI). The list of equipment to be located in the depot has been provided by the APS Student Transportation Department (STD).

4. Design Includes:a) The Administrative spaces per space standards established during Building ‘M’ & “O” renovationb) Private Officesc) Shared work stationsd) Dispatch/Schedulere) Conference roomf) Specialized spaces such as:

i) Drive through bus running maintenance baysii) Fluids and compressoriii) Parts, Common Work and Lift Storage

g) Shared Support Spaces:i) Work and Copy Roomsii) Break Roomiii) Restroomsiv) Locker Room & Showersv) Multipurpose Drivers Training/Lounge

5. Security:a) Single public entrance and parking area separated from single employee entrance

and secure parking and a secure bus fueling, maintenance, parking and wash area.b) Access control hardware at all exterior doors and identified interior 'secure' area doors.c) Cameras at building entrances and on site.d) Building wide fire sprinkler system.

6. Constructability:a) Maintain level of critical operation during constructionb) Construction will be accomplished utilizing the RFP process for awardc) Construction within Administrative areas will be done using modular “smart” wall sys-

tem similar to Building’s ‘M’ & “O”:i) Speeds up the construction scheduleii) “Clean” construction process for occupantsiii) Integrated technology

7. Sustainability:a) Exterior building envelope thermal insulationb) Low energy use appliances and LED light fixturesc) Low water use plumbing fixturesd) Pre-fabricated wall systems meet a variety of LEED criteriae) No VOC floor and wall finishesf ) Photo-voltaic panel protective canopies over bus parking

Project Building Committee Members

Karen Alarid, Executive Director, APS FD+CFaye Rogers, Staff Architect, APS FD+CChristopher Jiron, Construction Manager, APS FD+CRoyce Binns, Executive Director, APS TransportationNicholas Brook, Location Director, APS TransportationAmanda Velarde, APS Real EstateMargaret Callahan, APS Real EstateTony Otero, APS TechnologyAndy Brophy, SSR, Inc. LEED ConsultantJarret Pearl, SSR, Inc. Consultant

16' - 0"

14' - 0"

12' - 0"

2" / 1'-0"2" / 1'-0"

16' - 0" 16' - 0"

2" / 1'-0"

2" / 1'-0"

12' - 0"

GENERAL NOTES:

A. IF THIS SHEET IS NOT 24" X 36" IN SIZE THEN IT IS A REDUCED SIZE PLOT. USE GRAPHIC SCALE ACCORDINGLY.

B. FLOOR PLANS ARE DRAWN TO SCALE BASED UPON FIELD MEASUREMENTS AND AVAILABLE DRAWINGS.

C. GENERAL CONTRACTOR AND SUBCONTRACTORS SHALL FIELDVERIFY ALL DIMENSIONS. NOTIFY ARCHITECT/ENGINEER IMMEDIATELY OF ANY DISCREPANCIES FOUND. DWL Archite

Planners, Inc202 Central

East CourAlbuquer

New Mexico,

PH (505) 24Fax (505) 24

w.eastman@d

ISSUE/REVISION

PROJECT NUMBER:

CAD DWG FILE:

DRAWN BY:

CHECKED BY:

SHEET TITLE:

OF SHEE

1 2 3 4 5

1 2 3 4 5

A

B

C

D

A

B

C

D

50 B

US

FAC

ILIT

Y -E

AST

MO

UN

TAIN

S

NOVEMBER

DWL-NM_APS APS STUTRANSPORTATION BU

DESIGN DEVELODRAWINGS

NOT FOR CONSTR

20_1611.01

B. RAEL

W. EASTMAN

O&M EXTERELEVATIO

A 20

ALBU

QUE

RQUE

PUB

LIC

SCHO

OLS

STUD

ENT

TRAN

SPO

RTAT

IONS

DEP

OT

SCALE: 1/8" = 1'-0"1 O&M EXTERIOR WEST ELEVATION

SCALE: 1/8" = 1'-0"2 O&M EXTERIOR SOUTH ELEVATION

0' 4' 8' 16' 32'

1/8"=1'-0"

0' 4' 8' 16' 32'

1/8"=1'-0"

No. Description

16' - 0"

14' - 0"

12' - 0"

2" / 1'-0"2" / 1'-0"

16' - 0"

GENERAL NOTES:

A. IF THIS SHEET IS NOT 24" X 36" IN SIZE THEN IT IS A REDUCED SIZE PLOT. USE GRAPHIC SCALE ACCORDINGLY.

B. FLOOR PLANS ARE DRAWN TO SCALE BASED UPON FIELD MEASUREMENTS AND AVAILABLE DRAWINGS.

C. GENERAL CONTRACTOR AND SUBCONTRACTORS SHALL FIELDVERIFY ALL DIMENSIONS. NOTIFY ARCHITECT/ENGINEER IMMEDIATELY OF ANY DISCREPANCIES FOUND. DWL Architects

Planners, Inc. of 202 Central Ave.

East CourtyardAlbuquerque,

New Mexico, 871

PH (505) 242-62Fax (505) 242-41

w.eastman@dwlnm

ISSUE/REVISION

PROJECT NUMBER:

CAD DWG FILE:

DRAWN BY:

CHECKED BY:

SHEET TITLE:

OF SHEET

1 2 3 4 5

1 2 3 4 5

A

B

C

D

A

B

C

D

50 B

US

FAC

ILIT

Y -E

AST

MO

UN

TAIN

S

NOVEMBER, 20

DWL-NM_APS APS STUDENT TRANSPORTATION BUS DEPO

LOT

73-A

TIJ

ERAS

LAN

D E

STAT

ES, N

M 8

7059

DESIGN DEVELOPMENTDRAWINGS

NOT FOR CONSTRUCTIO

20_1611.01

B. RAEL

W. EASTMAN

O&M EXTERIORELEVATIONS

A 202

ALBU

QUE

RQUE

PUB

LIC

SCHO

OLS

STUD

ENT

TRAN

SPO

RTAT

IONS

DEP

OT

SCALE: 1/8" = 1'-0"1 O&M EXTERIOR EAST ELEVATION

SCALE: 1/8" = 1'-0"2 O&M EXTERIOR NORTH ELEVATION

0' 4' 8' 16' 32'

1/8"=1'-0"

0' 4' 8' 16' 32'

1/8"=1'-0"

No. Description D

16' - 0"

12' - 0"12' - 0"

16' - 0"

12' - 0"

12' - 0"

16' - 0"

12' - 0"

16' - 0"

GENERAL NOTES:

A. IF THIS SHEET IS NOT 24" X 36" IN SIZE THEN IT IS A REDUCED SIZE PLOT. USE GRAPHIC SCALE ACCORDINGLY.

B. FLOOR PLANS ARE DRAWN TO SCALE BASED UPON FIELD MEASUREMENTS AND AVAILABLE DRAWINGS.

C. GENERAL CONTRACTOR AND SUBCONTRACTORS SHALL FIELDVERIFY ALL DIMENSIONS. NOTIFY ARCHITECT/ENGINEER IMMEDIATELY OF ANY DISCREPANCIES FOUND. DWL Architec

Planners, Inc. 202 Central Av

East CourtyAlbuquerq

New Mexico, 8

PH (505) 242Fax (505) 242

w.eastman@dwl

ISSUE/REVISION

PROJECT NUMBER:

1 2 3 4 5

B

C

D

B

C

D

50 B

US

FAC

ILIT

Y -E

AST

MO

UN

TAIN

S

NOVEMBER,

DESIGN DEVELOPMDRAWINGS

NOT FOR CONSTRUC

20_1611.01

ALBU

QUE

RQUE

PUB

LIC

SCHO

OLS

STUD

ENT

TRAN

SPO

RTAT

IONS

DEP

OT

SCALE: 1/8" = 1'-0"1 WASH EXTERIOR WEST ELEVATION

SCALE: 1/8" = 1'-0"2 WASH EXTERIOR SOUTH ELEVATION

SCALE: 1/8" = 1'-0"3 WASH EXTERIOR EAST ELEVATION

SCALE: 1/8" = 1'-0"4 WASH EXTERIOR NORTH ELEVATION

No. Description

PERSPECTIVE AT BUS WASH BUILDING

1/4" / 1'-0"

POWER SUPPLY BOLLARD FOR ENGINE BLOCK HEATER

12' -

0"

50' - 0"

1/4" / 1'-0"

Planners, Inc.202 Central A

East CourtAlbuquerq

New Mexico,

PH (505) 242Fax (505) 242

w.eastman@dw

ISSUE/REVISION

PROJECT NUMBER:

CAD DWG FILE:

DRAWN BY:

CHECKED BY:

SHEET TITLE:

OF SHEET1 2 3 4 5

A

B

C

D

A

B

C

D

50 B

US

FAC

ILIT

Y -E

AST

MO

UN

TAIN

S

NOVEMBER

DWL-NM_APS APS STUTRANSPORTATION BUS

DESIGN DEVELOPDRAWINGS

NOT FOR CONSTRU

20_1611.01

B. RAEL

W. EASTMAN

FUELING & BUS CELEVATIONS/SEC

A 20

ALBU

QUE

RQUE

PUB

LIC

SCHO

OLS

STUD

ENT

TRAN

SPO

RTAT

IONS

DEP

OT

SCALE: 1/8" = 1'-0"1 FUELING CANOPY ELEVATION 1

SCALE: 1/8" = 1'-0"2 FUELING CANOPY ELEVATION 2

SCALE: 1/4" = 1'-0"3 PV CANOPY SECTION

No. Description

PERSPECTIVE AT BUS CANOPIES PERSPECTIVE AT FUELING

A. IF THIS SHEET IS NOT 24" X 36" IN SIZE THEN IT IS A REDUCED SIZE PLOT. USE GRAPHIC SCALE ACCORDINGLY.

B. FLOOR PLANS ARE DRAWN TO SCALE BASED UPON FIELD MEASUREMENTS AND AVAILABLE DRAWINGS.

C. GENERAL CONTRACTOR AND SUBCONTRACTORS SHALL FIELDVERIFY ALL DIMENSIONS. NOTIFY ARCHITECT/ENGINEER IMMEDIATELY OF ANY DISCREPANCIES FOUND.

2" / 1'-0"2" / 1'-0"

14' - 0"

DWL ArchPlanners, 202 Centr

East CoAlbuqu

New Mexic

PH (505) Fax (505)

w.eastman@

ISSUE/REVISION

PROJECT NUMBER:

CAD DWG FILE:

DRAWN BY:

CHECKED BY:

SHEET TITLE:

OF1 2 3 4 5

A

B

C

D

A

B

C

D

NOVEMBE

DWL-NM_APS APSTRANSPORTATION

DESIGN DEVDRAW

NOT FOR CON

20_1611.01

B. RAEL

W. EASTMAN

BUILDING S

A 3

ALBU

QUE

RQUE

PUB

LIC

SCHO

OLS

STUD

ENT

TRAN

SPO

RTAT

IONS

DEP

OT

SCALE: 1/8" = 1'-0"1 BUILDING SECTION @ MAINTENANCE BAY - 1 0' 4' 8' 16' 32'

1/8"=1'-0"

SCALE: 1/8" = 1'-0"2 BUILDING SECTION @ MAINTENANCE BAY - 2 0' 4' 8' 16' 32'

1/8"=1'-0"

No. Descripti

BIRDS EYE VIEW FROM SHADY OAK CIRCLE

PERSPECTIVE AT VISITOR ENTRANCE

(DIRTT - PREFABRICATED MODULAR WALL SYSTEM)

(DIRTT - PREFABRICATED MODULAR WALL SYSTEM)

(DIRTT - PREFABRICATED MODULAR WALL SYSTEM)

APS East Mountain Bus Depot Project No 909, Location 172

PROJECT NO 909 PRELIMINARY BUDGET PROJECTION Description Quantity Unit Cost Amount 030000 CONCRETE 13,360.00 sf 24.365/sf 325,516 040000 MASONRY 13,360.00 sf 2.508/sf 33,507 050000 METALS 13,360.00 sf 1.658/sf 22,150 060000 WOOD AND PLASTICS 13,360.00 sf 3.358/sf 44,863 070000 THERMAL PROTECTION 13,360.00 sf 3.287/sf 43,914 080000 OPENINGS 13,360.00 sf 10.700/sf 142,952 090000 FINISHES 13,360.00 sf 19.994/sf 267,120 100000 SPECIALTIES 13,360.00 sf 3.905/sf 52,171 110000 EQUIPMENT 13,360.00 sf 0.550/sf 7,348 120000 FURNISHINGS 13,360.00 sf 0.270/sf 3,607 130000 SPECIAL CONSTRUCTION 13,360.00 sf 25.735/sf 343,820 210000 FIRE SUPPRESSION 13,360.00 sf 3.217/sf 42,979 220000 PLUMBING 13,360.00 sf 14.591/sf 194,936 230000 HVAC 13,360.00 sf 32.000/sf 427,520 260000 ELECTRICAL 13,360.00 sf 26.845/sf 358,649 270000 COMMUNICATIONS 13,360.00 sf 5.673/sf 75,791 280000 ELEC SAFETY / SECURITY 13,360.00 sf 6.306/sf 82,248 310000 EARTHWORK 13,360.00 sf 4.128/sf 55,150 320000 EXTERIOR IMPROVEMENTS 13,360.00 sf 71.150/sf 950,564 330000 UTILITIES 13,360.00 sf 42.533/sf 568,241 Estimate Totals Description Amount Totals Rate Cost per Unit Subtotal 4,043,046 4,043,046 302.623 /sf General Requirements 485,165 12.000 % 36.315 /sf General Contractor OH&P 226,411 5.000 % 16.947 /sf Bonds and Insurance 113,205 2.500 % 8.897 /sf 4,873,487 4,873,487 364.782 /sf