ANA2017 Conference, Sydney, 6 Oct 2017 11
Presentation 6 – Session 2
APR1400 Program in UAE
Young Hoon KIM
General Manager, KHNP’s UAE Project Office
Biography
Young Hoon Kim is the General Manager of
KHNP’s UAE Project Office. He received his
Bachelor's degree in Mechanical Engineering from
Konkuk University in 1997 and his MBA from
KAIST Graduate School of Management in 2010.
Since joining KEPCO in 1996, he had worked at a
nuclear power plant site for more than 15 years. After
having served as General Manager in Shin Hanul
NPP Project Management Office, he is currently
working on the UAE Barakah Project.
Abstract
This presentation will introduce to you the UAE NPP
Project that KHNP joined as a key partner, providing an overall understanding of project details
including project progress, project structures, construction opportunities and challenges,
construction site factors, time & project management, and project costs, etc.
.
Korea Hydro & Nuclear Power Co., Ltd. (KHNP) is Korea’s largest power generation company producing approximately 31% of the nation’s electricity supply with the mission of “enriching the lives of citizens and providing a foundation for the nation’s economic development through the stable supply of power”
KHNP owns and operates 24 units of nuclear power plants, 35 units of hydro power plants, 16 units of pumped-storage power plants, photovoltaic power plants and so on, having roughly 11,500 employees.
While safely operating nuclear power plants in order to eliminate the nation’s concerns over power supply, KHNP also aims to successfully construct new nuclear power plants.
Introduction of UAE Project 1
Contract Structure2
Site-specific Characteristics4
3
Opportunities and Challenges5
Current Project Status
Time & Project Management
Project Cost
6
7
1/28
Owner/Contractor ENEC / KEPCO
Ref. Plant
Scope
Contract Date Dec. 27, 2009
APR1400 x 4 Unit (5,600MW)
Nuclear Fuel (3 Cycles)
Operating Support Service
Shin-Kori 3&4 in Korea
APR1400 4Units Fuel Supply OSSSimulator
2/28
▪ (EOSA) Early Operating Support Agreement
▪ (OSSA) Operating Support Services Agreement
▪ (EOSA) July 2016 ~ SCD of Unit 4 (to be finished after completion of each unit)
▪ (OSSA) SCD of Unit 1 ~ 10 years after completion of Unit 4 (2030)
▪ Dispatch experienced and qualified personnel to UAE NPP
Operating Support Services
▪ July 20, 2016
3/28
Abu Dhabi
Dubai
Barakah
Doha
Ruwais
270km
390km
4/28
5/28
6/28
Joint PM
Agreement
Prime Contract
Subcontract
EAA : Executive Affairs Authority
EAD : Environment Agency - Abu Dhabi
HAAD : Health Authority – Abu Dhabi
NCEMA : National Crisis and Emergency Management
Authority
CICPA : Critical Infrastructure and Coastal Protection
Authority
FANR : Federal Authority of Nuclear Regulation
ADWEC : Abu Dhabi Water Electricity Company
ENEC : Emirates Nuclear Energy Corporation
KEPCO : Korea Electric Power CorporationCICPASite Protection and Security
FANRNuclear Regulation
EAD, NCEMA,
HAAD etc.,EAA
Nuclear Policy
ENECShare Holding(82%)
KEPCOShare Holding(18%)
Barakah OneProject Co.
Nawah EnergyOperation & Maintenance Company
ADWECPower Purchase
7/28
8/28
9/28
Licensing
Design
Manufacturing
Construction
Commissioning
10/28
11/28
Drilling Investigation
Drilling Machine
Geophysical Prospecting
Trench Investigation
12/28
Low seismicity
Tectonically inactive for nearly
100 million years
No Tsunami activity
“Seismic Design Value : 0.3g (7.0M)”
13/28
Barakah Site
[Over 6.0M, 1900~2005]
14/28
❖ Working time should be modified for improving productivity and efficiency.
Description Site Working Time Office Working Time
Morning 05:30 ~ 12:00 (6.5 hrs) 06:00 ~ 12:00 (6.0 hrs)
Afternoon 15:00 ~ 18:30 (3.5 hrs) 14:00 ~ 18:00 (4.0 hrs)
Night / Overnight
(2 shifts)19:30 ~ 04:30(+1) (If necessary)
UAE Labor Law(Federal Law No. 8 of 1980)
15 June - 15 September 2017
12:00 pm – 3:00 pm
15/28
[Muslim & Non Muslim Labor Status]
Muslim 3,206 MD (23%)
Total 14,003 MD
Description Non Muslim’s Working Time Muslim’s Working Time
Morning05:30 ~ 12:00
(6.5 hrs)
05:30 ~ 12:00
(6.5 hrs)
Afternoon15:00 ~ 18:30
(3.5 hrs)-
Night / Overnight
(2 shifts)
19:30 ~ 04:30(+1)
(If necessary)-
Working Schedule
[27 May ~ 25 June 2017]
16/28
Protection Measures
Moving dust in the air Piled-up sand by sandstorm
Arabian Gulf
UAE
17/28
Transport Route
Transport Schedule
D-25 D D+10 D+45D-40
Shipping
Notification
Shipping
Documents
Distribution
ShippingVessel
Booking
D+48
Unloading
at BNPP site
Discharging
in Abu Dhabi
Barakah
NPPContainer Cargo
Busan Port, NY Port,
Yokohama Port, etc.
Khalifa Port
thru Dubai Port
Oversized/
Heavy Cargo
Masan Port, Portsmouth
Port, etc.
Khalifa port/
Musaffah Port
Air Cargo
Incheon Airport,
NY Airport, Narita
Airport, etc.
Abu Dhabi Airport/
Dubai Airport
Major Shipping
(Air)Port
Discharging
(Air)PortClassification
Approx. 440Km
Khalifa Port
BNPP
Road Map (Khalifa Port to Barakah)
Abu Al Abyad
(Stopover No. 1)
ICAD-3
(Stopover No. 2)
18/28
Global Leadership & Competence
19/28
Global Standards
Global Cooperation
➢ Regulatory Review from Multinational workforce
➢ Cooperation in various fields
➢ Enhancing global competence of employees
20/28
Procedures for Project Management- Project Procedure Manual (PPM)
- Site Internal Procedure (SIP)
- Overseas Office Internal Procedures (NOIP, POIP)
Project Management System (NPCMS, PPMS)
Experienced and dedicated Personnel
21/28
- Materials Lists
- Design Information
- Technical Specifications
Design
- Procurement Schedule
- Contract Change
- Suppliers’ Information
Procurement
- Installation History
- Installation Status
- Turnover Information
Construction/Commissioning
- Receiving / Releasing
- Storage / Inventory
- Maintenance, repair
Materials on site
A/E
- Materials Lists
- Design Information
- Bill of Material
NSSS Supplier
- Materials List- Technical Specification
Work Supervision Team
- Materials Request- Materials Installation- Turnover
Procurement Contract Team
- Invitation to Bid- Suppliers Selection- Contracts Signing- Delivery Information
Procurement Control Team
- Technical Evaluation- Manufacturing Check- Delivery Management
Materials Team on site
- Receiving / Storing- Releasing / Re-receiving- NCRs
Overseas Office
- Overseas materials
Materials Management System
22/28
[Licensing Portal]
Document Control & Information Sharing System
[BOK] [e-Portal(External Portal)]
23/28
Regular Project Meetings
Reference Plant’s Lessons Learned
24/28
Remote Technical Support Center
RTSC(KHNP HQ)
KHNP Eng. Center
SKN3,4Engineers
ExternalVendors
KHNPCRI
Commissioning and Subsequent Operations Interface
Construction Operation
Kick-off C to C T/O F/L
SCDCommissioning
Prime ContractOSS
OSSA
HSJV KHNP NE NE
C to O T/O
25/28
KEPCO
HSJV
Construction
KHNP
Commissioning
OWNER
NE
OperationT/O T/O
Const. Plant
System T/O Mechanism
26/28
Project Cost
EPC Cost
Fuel SupplyDesign & Eng. Procurement ConstructionPM
Owner Cost
Other Services
T/G
BOP
NSSS
Contract ChangeOSS
27/28
Fixed Price
Fixed Rate
Cost Reimbursable
Over 40 years experience in NPP Construction
Project Management
Experienced and Qualified Personnel
Supply Chain Management
The World’s Best !
28/28