APQP-GM

download APQP-GM

of 31

Transcript of APQP-GM

  • 8/9/2019 APQP-GM

    1/73

    Phone on

    “Vibrate”

      Ground Rules

    GM Global APQP for Suppliers

    Manuel YamadaTel Aviv, Israel

    April 12th, 2010

    This is your class, feel freeto ask questions at any time!

  • 8/9/2019 APQP-GM

    2/73

    • Introductions

    • APQP Process and Expectations

    • Project Plan

    • Customer vs Supplier Monitored APQP

    • APQP management in GQTS

    • APQP Requirements

    GM Requirements• Q & A

    AGENDA

  • 8/9/2019 APQP-GM

    3/73

    Global APQP Vision

    • Become more proactive, by moving right side activities to the left

    QSB for suppliers upfront after sourcing

    Schedule early cross functional blitz audits on high risk suppliers

    • Streamline the APQP Process to be more effectiveIdentify key deliverables for each quality gate during the APQP

    process

    Track and report the results of the agreed deliverables, not just

    PPAP and R@R

  • 8/9/2019 APQP-GM

    4/73

    The goal of a successfulprogram launch and mass

    production is to provide:

    “Quality @ Rate On Time”

    Supplier Responsibility

  • 8/9/2019 APQP-GM

    5/73

    GM

    Global

    APQP

    AIAG APQP

    ISO/TS 169497.1

    Planning of Product Realization

    Linkages of the ISO/TS 16949:2002, AIAG

    APQP and Global Supplier Quality Manual

    Background

  • 8/9/2019 APQP-GM

    6/73

    Global APQP Team Goals & Results

    Identify Quality Indicators

    Develop Quality Tasks (17 total)

    Develop Global Supplier Quality Manual, GM-1927

    Reason: Global Sourcing and “World Vehicles”

    GM APQP Global Process

    Background

  • 8/9/2019 APQP-GM

    7/73

    GM-1927

    Global SupplierQuality Manual is

    the General MotorsCommon Global APQP

    Manual

    GM’s commondirection for thedevelopment andimplementation of anAPQP plan

    Download fromGMSupplyPower 

    Global APQP

    Advanced Product Quality Planning

    Worldwide Purchasing

    November 2000

    General Motors Corporation

    GM

  • 8/9/2019 APQP-GM

    8/73

    Ordering:

    Ordering information for all documents and manuals listed or referenced

    throughout this manual (GM 1927) is contained on page II

    Electronic Copies:

    This manual and all documents that are part of this manual (this

    includes any document with a GM 1927 number) can be found through

    the internet at the GMSupplyPower website

    The address is www.gmsupplypower.com, then follow these steps:

    • Log in 

    • Select Qual i ty Pow er 

    • Select L ibrary 

    • Select Suppl ier Qual i ty 

    • Select APQP Manual & Documents 

    GM 1927 Documents and Forms

  • 8/9/2019 APQP-GM

    9/73

    Summary Points

    • Global APQP driven by ISO TS 16949 and AIAG APQP

    • Common Global APQP Process for GM Worldwide- All GM Divisions and Regions will use the Same Process

    - Common Requirements for Suppliers

    - Common Forms and Charts

    • Common Direction and “One Voice” from all GM Supplier

    Quality Engineers

    • Supports Global SQ Communication Structure

    - Supplier Program Status is shared between Regions- All Information Available on GMSupplyPower website at

    www.gmsupplypower.com

    Global APQP

  • 8/9/2019 APQP-GM

    10/73

    Customer Monitored

    SQE – work closely with supplier 

    Supplier – work closely with GM SQE

    Supplier Monitored

    SQE – paper/electronic review of supplier 

    Supplier – keep GM aware

    Customer Monitored APQP

    Supplier Monitored APQP

    Global APQP

  • 8/9/2019 APQP-GM

    11/73

    GM Global APQP Monitoring

    • Customer Monitored – SQE Responsibilities• Assure quality @ rate on time

    • Drive the supplier’s progress in the developmentof all quality related documents listed on APQP

    Project Plan

    • Raise issues that might jeopardize a quality partwithin the program timing – either to supplier’s or

    GM’s upper management, as appropriate

    • Participate in the remaining Supplier GateReview meetings• Adhere to supplier manufacturing site protocol

    when in the manufacturing facility

    • Attend PDT and associated program meetings• Drive/Enforce the process of supplier’s quality

    system development

    • Apply APQP Workbook Audits and upload all KeyDeliverables to GQTS• Supplier Monitored – SQE Responsibilities• Monitor the supplier’s adherence to program

    timing and track open issues addressing

    • Customer Monitored – Supplier Responsibilities• Execute the content and provide updates per the

    APQP Project Plan

    • Implement an advanced product qualityplanning process with all sub-tier suppliers

    • Invite and conduct all remaining Gate Reviews• Work closely with GM SQE

    • Supplier Monitored – Supplier Responsibilities• Execute the content of the APQP Project Plan• Implement an advanced product qualityplanning process with all sub-tier suppliers

    • Responsible for meeting quality, timing andcapacity requirements

    • Provide parts for all GM build events• Present tasks and deliverables of APQP

    Workbook internally in a management review andsubmit the results to GM

    • Notify SQE when quality issues arise that mightaffect program timing

    SQE is the responsible for invite and conduct Gate #1 (Kick-Off Meeting) for all parts on both Customer orSupplier Monitored APQP

  • 8/9/2019 APQP-GM

    12/73

    There is an inverse relationship –

    Customer monitoring means moreresponsibility for the SQE

    Supplier monitoring means more

    responsibility for the Supplier

    Customer Monitored APQP vs

    Supplier Monitored APQP

    Global APQP

  • 8/9/2019 APQP-GM

    13/73

    Global APQP Tasks changed as following:

    01-Commodity Key Stakeholders Mtg

    02-Technical Reviews

    03-Supplier Eligibility04-Gate Reviews

    05-Timing Charts / Open Issues

    06-QSB

    07-Flow Chart

    08-DFMEA

    09-Design Reviews

    10-Tooling & Equipment Reviews

    11-Gage Development & Approval

    12-PFMEA

    13-Control Plan

    14-GP-12

    15-PPAP

    16-Run @ Rate

    17-Lessons Learned

    01-Commodity Sourcing Strategy Mtg

    02-Technical Reviews

    03-Risk Assessment / Sourcing

    04-Supplier Gate Reviews

    05-Timing Charts / Open Issues

    06-Feasibility / Assessment Letters

    07-Flow Chart

    08-DFMEA

    09-Design Reviews

    10-Gage, Tooling and Equipment Reviews

    11-GP-11

    12-PFMEA

    13-Control Plan

    14-GP-12

    15-PPAP

    16-Run @ Rate

    17-Lessons Learned

  • 8/9/2019 APQP-GM

    14/73

    Corporate Planning sets time frames

  • 8/9/2019 APQP-GM

    15/73

    START OF

    PRODUCTION 

    RUN @ RATE (GP-9)

    PRODUCTION PART

     APPROVAL (PPAP)

    PROTOTYPE SAMPLE

     APPROVAL (GP-11)

    PRE-PRODUCTION MEETING

     ADVANCED PRODUCT

    QUALITY PLANNING (APQP)

    SOURCING DECISION

    POTENTIAL SUPPLIER

     ASSESSMENT

    GPSC SUPPLIER QUALITY IMPROVEMENT PROCESS

    LIFE

    OF PART 

    TIME LINE EARLY PRODUCTION

    CONTAINMENT (GP-12)

    GLOBAL SOURCING

    IMPROVEMENT MEETING

    QUALITY WORKSHOP

    LEVEL II CONTROLLED SHIPPING

    LEVEL I CONTROLLED SHIPPING

    SUPPLIER QUALITY PROCESSES & MEASURES (GP-5)

    PERFORMANCE MONITORING

    CONTINUOUS IMPROVEMENT (GP-8)

    GM Global APQP

    Combination of the Best Processes

  • 8/9/2019 APQP-GM

    16/73

    1. Commodity Sourcing Strategy Meetings

    The Commodity Sourcing Strategy Meeting is the responsibility of the Buyer – Internal GM people only

    The first time the SQE becomes “officially” involved in the APQP process

    Commodity Sourcing Strategy Meeting is the first task that is tracked by the

    APQP Project Plan

    APQP Project Plan

    GM GVDP  

    APQP Task

     Gate

    Reviews

    Sourcing

    Activities   G   R  -   1

       G   R  -   2

       G   R  -   3

       G   R  -   4

    1

    Commodity Sourcing

    Strategy Mtg GR-1 o------o o

    2 Technical Reviews GR-1 o- --- --o o

    3

    Risk Assessment /

    Sourcing GR-1,3 TR o o o

    4Supplier GateReviews

    5

    Timing Charts /

    Open Issues GR-1,2,3,4 o o o o o o o o o o o o o o o o o o o o o o o o o o o o

    6

    Feasibility /

     Assessment Letters GR-1,2,3,4 o o o o

    7 Flow Chart GR-1,2,4 o o o o o o

    8 DFMEA GR-1,2,4 o o o o o o o

     

    AIAG

    APQP

    Pilot / Pre-LaunchPrototype Launch /

    Feedback, Assessment and Corrective Action

    Production

    Product Design and Development

    Planning

    Process Design and DevelopmentProduct and Process Validation

     

    ProductionInitial -TR

     

    Initial-TR

     

    Initial-TR

    Update Risk

     

    Structure

    Vehicle

    Integration

    Vehicle

    Validation

    Vehicle

    MVBs SOPMVBns

     

    Letter 2 Letter 3 Letter 4

    UpdateDFMEA RPN Reduction

    Prototype

     

  • 8/9/2019 APQP-GM

    17/73

    Key points

    Introduce and establish Key Stakeholder ownership, identifyprogram-specific strategies in the Engineering & AdvancePurchasing Sourcing Process (E&APSP) and ensure that the RFQ-package contains all information needed to receive comparablequotes.

    Review potential bidders list proposed by Buyer to restrict Requestfor Quotation (RFQ) distribution to suppliers that meet GM criteria.

    Identify suppliers that will require Quality Business Case actionplans and start planning any required audits.

    Review the requirements stated in the SQ SOR GM1927-3, and the

    Part-Specific Quality & Process SOR (if applicable) to ensure thatthey are be included in the Request For Quotation package(suppliers must be capable to meet those specific requirements ifavailable).

    1. Commodity Key Stakeholders Meeting (CKSM)

    http://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xls

  • 8/9/2019 APQP-GM

    18/73

    Available Data for Supplier Performance

    - CT Bid List

    - PSA/PCPA audit report

    - GMSupplyPower (Six Panel Chart and Box Chart)

    Supplier Commitment Letter is required for anysuppliers to be sourced with not Green status

    1. Commodity Key Stakeholders Meeting (CKSM)

  • 8/9/2019 APQP-GM

    19/73

    Supplier Quality Statement of Requirements 

    Please sign, date and return page 5 of this document w ith your bid p ackage as 

    record of your understanding of these requirements. Powertrain suppliers please 

    sign, date and return page 6 also.

    1.   All suppliers are expected to supply parts to General Motors with zero defects. Funding is tobe identified in the initial quote and subsequent quotes to reflect error occurrence detection (pokayoke, error proofing devices, etc) and defect outflow prevention to customers. Controlsimplemented at a later date are the financial responsibility of the supplier.

    2. ISO/TS 16949 or QS-9000 - Quality System Requirements

      All suppliers to General Motors must be certified to one of these standards and have a currentcertificate available demonstrating compliance to GM supplements. These standards requirean extensive, formal, audited evaluation of suppliers’ quality and manufacturing methods.The evaluation is conducted by a third party certified registrar.

       Suppliers not certified to ISO/TS 16949 or QS-9000, or those suppliers constructing or 

    purchasing facilities to manufacture the parts being quoted, must include an outline of their certification attainment plan with their quote for f urther consideration.

     

    3. General Motors Procedures and Reference Documents 

      Suppliers are to adhere to the requirements contained in the following documents:  Advanced Product Quality Planning & Control Plan Reference Manual (AIAG)

      Potential Failure Mode and Effects Analysis (FMEA) Reference Manual (AIAG)  Fundamental Statistical Process Control (SPC) Reference Manual (AIAG)  Measurement Systems Analysis (MSA) Reference Manual (AIAG)  Production Part Approval Process (PPAP) Manual (AIAG)  Key Characteristics Designation System (KCDS) GM-1805QN  GP-5 Supplier Quality Processes and Measurements Procedure. GM-1746  GP-7 Component Verification and Traceability Procedure. GM-1730  GP-8 Continuous Improvement Procedure. GM-1747  GP-9 Run @ Rate. GM-1960  GP-10 Evaluation and Accreditation of Supplier Test Facilities. GM-1796  GP-11 General Procedure for Pre-Prototype and Prototype Material. GM-1820  GP-12 Early Production Containment. GM-1920  GM-Supplier Technical Information GM-1825  Traceability Identifier Requirement TIR-15-300. GM-1731  Supplier Quality Weld Support Manual  Shipping Parts Identification Label Standard. GM-1724  Fixture Standards Requirement GM-1925  Operating Guide for Suppliers of Prototype Material NAO-0065

    Signature of Supplier epresentative

    Supplier Quality SOR

    • Supplier Quality has a Global

    Statement of Requirements thatapplies to all suppliers.

    • SOR Included in the GM RFQ.

    • Supplier Quotations to GMmust include a signed copy of

    the SOR, indicating compliance to

    these requirements.

  • 8/9/2019 APQP-GM

    20/73

    2. Technical ReviewsReview manufacturability, timing, design, manufacturing

    capability, packaging, etc., issues related to a commodity.

    NOTE: There may be situations where a TR is not held. SQEmust take responsibility for a review of the Quality info. This

    should be done prior to performing the GPSC APQP

    Assessment.

    Attendees: Buyer, Engineer, SQE, Supplier, Manufacturing

    Engineer, Other pertinent organizations

    Outcome:

    - Identifying suppliers that should not continue in the sourcing

    process

    - Initial GQSC APQP Assessment signed by the buyer, DRE and

    SQE (this is required prior to signing the Sourcing

    Recommendation form).

    - Initial APQP Open issues list

  • 8/9/2019 APQP-GM

    21/73

    Technical Review Checklist

  • 8/9/2019 APQP-GM

    22/73

    Risk

    Assessment

    CustomerMonitored APQP

    or

    SupplierMonitored APQP

    Risk Assessment

  • 8/9/2019 APQP-GM

    23/73

    3. Sourcing Eligibility For a supplier location to be eligible to receive a new business

    award from GM the manufacturing location to be sourced must

    either be:

    • Green on the GM Creativity Team Bid List (CTBL) for Quality

    for the specific commodity, OR

    • Have a supporting Quality Business Case (QBC) QUAD report

    approved according to the criteria outlined in this task.

    Supplier is requested to provide necessary information as

    required and support audit requests at short notice.

    - Identifying suppliers that should not continue in the sourcing

    process

    - Initial GQSC APQP Assessment signed by the buyer, DRE andSQE (this is required prior to signing the Sourcing

    Recommendation form).

    - Initial APQP Open issues list

  • 8/9/2019 APQP-GM

    24/73

    109 Part J

    4. Gate Reviews

    The purpose of the Gate Reviews is to review the progress of all

    APQP Tasks as stated on the APQP Project Plan GM1927-1 andtrack the status and progress of items listed on the APQP Timing

    Chart GM1927-2.

    These review meetings are intended as an APQP team review of

    the part and process development and to capture the lessons

    learned from each build event. The Gate Review #1 (Kick-OffMeeting) is coordinated by the GM SQE for all APQP parts.

    Used to review the progress of items according to the APQP

    Project Plan (GM1927-1) and track the status and progress of

    items listed on the APQP Timing Chart (GM1927-2)

  • 8/9/2019 APQP-GM

    25/73

    Key points

    Intended as a Readiness Review of the supplier’s abilityto support specific GM build events and achieve both Full

    PPAP and R@R according to the program requirements

    Coordinated by the SQE

    Conducted by the SQE on all parts tracked as

    customer-monitored APQP

    Conducted internally by the Supplier if the parts are

    supplier monitored APQP

    Aligned with GM build events

    4. Gate Reviews

    http://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xls

  • 8/9/2019 APQP-GM

    26/73

    4. Gate Review

  • 8/9/2019 APQP-GM

    27/73

    Key Deliverables

    The Key Deliverable documents (see chart) are to be uploadedinto GQTS. All other APQP documents and forms (referenced inthe GM Global APQP Supplier Status Summary WorkbookGM1927-34) are to be retained at the supplier location.

    The Key Deliverables related to PPAP (e.g. GM1411,Dimensional Report, GM3660), must contain the GQTS PPAPactivity code as reference.

    4. Gate Reviews

    http://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xls

  • 8/9/2019 APQP-GM

    28/73

    Key Deliverables

    4. Gate Reviews

    Gate

    Deadline

    Time from

    SORP in

    weeks)

    GVDP 5.0 timingreference

    Review KeyDeliverables

    Form/Document

    ALLGM Global APQP Supplier Status Summary

    WorkbookGM1927-34

    Within 30 days of

     business nomination

    advice / contract

    Gate 1

    QSB Audit (Gap Analysis) or Greenfield

    Checklist (Action Plan)

    GM1927-30

    GM1927-31

    Timing Plan GM1927-2

    Kick-Off Check list GM1927-14

    -78Initiated after CVER

    and completed 5

    weeks after IVER

    Gate 2PFMEA Check list GM1927-37RPN Reduction Summary GM1927-21

    Subcontractor Status GM1927-25

    -52Completed 10 weeks

     prior Matching 1 GAGate 3

    Supplier ADV Plan (ADVP&R) showing

    execution statusGM1829

    QSB Audit (Compliance) or Greenfield Checklist

    (Complete)

    GM1927-30

    GM1927-31

    Run @ Rate Capacity Workbook GM1927-35

    -35Completed 3 weeks

     prior PPV MRD Gate 4

    Dimensional Report GM1927-32

    PPAP Worksheet (if not fully approved) GM1411GP12 Audit GM1927-33

    -15Completed 1 week

     prior MVBs MRDPPAP PPAP Approval

    -8Run @

    Rate

    Run @ Rate Execution R@R Module

    PCPA GM1927-16

  • 8/9/2019 APQP-GM

    29/73

    Kick off checklist (GM 1927-14)

    Program team contact list (GM 1927-17)

    APQP Timing chart

    APQP open issue list

    Initial PFD/PFMEA/PCP

    Lessons learned

    QSB Audit (Gap Analysis) or Greenfield Checklist (Action Plan)

    Major disruption prevention plan

    Delivery

    Gate Review # 1 - APQP Kick Off Meeting

  • 8/9/2019 APQP-GM

    30/73

    Who toContact?

    GM1927-17

    List the Key

    Positionsneeded to

    Manage New

    Programs

     

    Part name:   Part number:  GM Program:   Model Year:  

    Supplier Name:   DUNS #:  

    Manufacturing Location Address:  

    Supplier Mfg. Plant Manager:   Phone:  

    GM SUPPLIER

    Position Name Phone (fax,mobile) E-mail Position Name Phone (fax,mobile) E-mail

    Advance

    SQE

    Project

    Manager 

    Buyer Sales Mgr  

    Design

    Engineer 

    Design

    Engineer 

    VLE PPM Quality

    Manager Proto PE Laboratory

    Supv.

    Manuf.

    Engineer 

    GM Plant

    Rep

    GD&T

    Readiness

    Coord.

    Container-

    ization

    Packaging

    Engineer 

    Reliab.

    Engineer 

    1st Shift

    ContactPaint

    Engineer 

    2nd

     Shift

    Contact

    Current

    SQE

    3rd

     Shift

    Contact

    Sub-

    Contractor 

    GM AND SUPPLIER PROGRAM CONTACTS

    APQP Kick Off Meeting

    G t i

  • 8/9/2019 APQP-GM

    31/73

    Updated timing plans

    Updated Open Issues

    PFMEA checklist

    RPN reduction summary

    Subcontractor planning

    Lessons Learned and best practice review

    Major disruption prevention plan

    Gate Review # 2

    G t R i # 3

  • 8/9/2019 APQP-GM

    32/73

    On-tracking timing chart, PFD/PFMEA/PCP, Qualityimprovement activities, tier supplier improvement status etc

    Open issue review – Identify high risk open issues

    QSB Audit (Compliance) or Greenfield Checklist (Complete)

    Run @ Rate Capacity Workbook

    Supplier ADV Plan (ADVP&R) showing execution status

    PPAP plan and requirements

    Gate Review # 3

    G t R i # 4

  • 8/9/2019 APQP-GM

    33/73

    Updated timing plans, PFD/PFMEA/PCP, Open Issues, Qualityimprovement activities, tier supplier improvement status etc

    Dimensional Report

    PPAP Worksheet (if not fully approved)

    GP12 Audit

    Conduct Supplier Launch Day assessment

    Gate Review # 4

  • 8/9/2019 APQP-GM

    34/73

    Gate Reviews 2 3 4

    • APQP Major/Open Issues List

    • APQP Timing Chart Updates• Progress of Tooling/Fixtures/Gages

    • Lessons Learned

    • Design Issues

    • RPN Reduction Plans

    • AIAG New Equipment Checklist (A-3)• AIAG Process Flow Checklist (A-6)

    • AIAG PFMEA Checklist (A-7)

    • AIAG Control Plan Checklist (A-8)

    • GP-12 Plan

    •Identify build issues/concerns

    Meeting Subjects Include:

    G t R i D li

  • 8/9/2019 APQP-GM

    35/73

    Global APQP for SQEs

    Gate Review Delivery

    G t R i D li

  • 8/9/2019 APQP-GM

    36/73

    Gate Review Delivery

    5 Ti i Ch t / O I

  • 8/9/2019 APQP-GM

    37/73

    5. Timing Charts / Open Issues

    Key points

    Supplier timing chart match GM master timingrequirement / MRD requirement

    Supplier shall understand the logic consequence for

    each activity and milestone

    Supplier timing shall have high confidence of timingachievability

    Supplier shall identify potential risk by this “report

    card”, and usage of escalation process

    Use updated “Open issue list” as meeting minutes

    and program management tool

    APQP Ti i Ch t

    http://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xls

  • 8/9/2019 APQP-GM

    38/73

    APQP Timing Chart

  • 8/9/2019 APQP-GM

    39/73

    APQP Ti i Ch t

  • 8/9/2019 APQP-GM

    40/73

    Key Elements:

    - Data/Sample comparison

    - ADVP&R- Engineering approval

    - Material substitution/approval

    - Tier supplier plan

    - New facility, M&E

    - Tooling building

    - Gage/fixture building- FOS

    - A-B-C Comparison (GS)

    - ETO

    - PPAP SPR & Submission

    - PTR

    - GP12 GP9

    - Acceleration and pipeline/inventorybuild up plan

    APQP Timing Chart

    APQP Timing Chart

  • 8/9/2019 APQP-GM

    41/73

    APQP Timing Chart breakdown

    Tooling list and timing chart

    M&E timing chart

    Sub-contractor timing chart

    People Hiring and Training planning

    Green/Brown field building planning

    ADVP&R

    APQP Timing Chart

    Open Issue List

    http://localhost/var/www/apps/conversion/02%20HSR&A/00%20GD/Timinghttp://localhost/var/www/apps/conversion/tmp/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://localhost/var/www/apps/conversion/tmp/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://localhost/var/www/apps/conversion/tmp/Iris_APQP%20T3/HSR&A/M&E/GM%20M&E%20SCHEDULE_070305.xlshttp://localhost/var/www/apps/conversion/tmp/Iris_APQP%20T3/HSR&A/M&E/GM%20M&E%20SCHEDULE_070305.xlshttp://localhost/var/www/apps/conversion/tmp/Iris_APQP%20T3/HSR&A/Subcontractor/Subcontractor_Prog_Status_Matrix_070305.xlshttp://localhost/var/www/apps/conversion/tmp/Iris_APQP%20T3/HSR&A/Subcontractor/Subcontractor_Prog_Status_Matrix_070305.xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Subcontractor/Subcontractor_Prog_Status_Matrix_070305.xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Subcontractor/Subcontractor_Prog_Status_Matrix_070305.xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Subcontractor/Subcontractor_Prog_Status_Matrix_070305.xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Subcontractor/Subcontractor_Prog_Status_Matrix_070305.xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Subcontractor/Subcontractor_Prog_Status_Matrix_070305.xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Subcontractor/Subcontractor_Prog_Status_Matrix_070305.xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Subcontractor/Subcontractor_Prog_Status_Matrix_070305.xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Subcontractor/Subcontractor_Prog_Status_Matrix_070305.xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Subcontractor/Subcontractor_Prog_Status_Matrix_070305.xlshttp://localhost/var/www/apps/conversion/tmp/Iris_APQP%20T3/HSR&A/Subcontractor/Subcontractor_Prog_Status_Matrix_070305.xlshttp://localhost/var/www/apps/conversion/tmp/Iris_APQP%20T3/HSR&A/M&E/GM%20M&E%20SCHEDULE_070305.xlshttp://localhost/var/www/apps/conversion/tmp/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://localhost/var/www/apps/conversion/02%20HSR&A/00%20GD/Timinghttp://localhost/var/www/apps/conversion/02%20HSR&A/00%20GD/Timinghttp://localhost/var/www/apps/conversion/02%20HSR&A/00%20GD/Timing

  • 8/9/2019 APQP-GM

    42/73

    Open Issue List

    6 QSB (Quality Systems Basics)

  • 8/9/2019 APQP-GM

    43/73

    Supplier is requested to work in QSBimplementation from the beginning of the

     program development (Gate Review # 1)

    Action plan for implementation to be updatedon a regular basis according to the actions

    taken based on the plan dates

    6. QSB (Quality Systems Basics)

    APQP QSB Task must becompliant by Gate Review # 4

  • 8/9/2019 APQP-GM

    44/73

    7 Flow Chart

  • 8/9/2019 APQP-GM

    45/73

    7. Flow Chart

    Inspection

    Rework

    Scrap

    Packaging

    Shipping

    KCC

    Example: Initial process flow chart

  • 8/9/2019 APQP-GM

    46/73

    Example: Initial process flow chart

    Nonconforming part shall be reintroduced into the process stream ator prior to the point of removal

    9 Design Review

  • 8/9/2019 APQP-GM

    47/73

    9. Design Review

    Purpose: Ensure that the Design has been adequately Defined to Build Tools

    and Gauges

    Key points

    Ensure engineering data is the latest version Ensure supplier get SOR and engineering spec.

    Ensure supplier understand the engineering data/specand testing method

    Review KPC/PQC list and control method

    ADVP should be approved by GM

    BOM

    Material substitution and approval

    Minimum validation requirement for salable PPAP

    Example: KPC/PQC and corresponding control method

  • 8/9/2019 APQP-GM

    48/73

    N

    OKPC Value KCC Control Method

    1 Length

    VE:3060±7.5mm Extrusion: Cutting

    Aging: Temperature; time

    Finishing: End cutting

    Extrusion: Automatic

    cutting

    Aging: PLC

    Finishing: 100% DIM

    check & SPCWM:3118±7.5mm

    2Compr 

    ession

    Load

    VE/WM:

    10.75mm

    8~14N

    Mixing: Ingredient quantity

    Extrusion: Temperature;

    Line speed

    Aging: Temperature; time

    Mixing: Bar code

    Extrusion: PLC

    Aging: PLC control

    SPC

    Example: KPC/PQC and corresponding control method

  • 8/9/2019 APQP-GM

    49/73

    Example: BOM

  • 8/9/2019 APQP-GM

    50/73

    Example: BOM

    10 Tooling & Equipment Reviews

  • 8/9/2019 APQP-GM

    51/73

    10. Tooling & Equipment Reviews

    Purpose:

    To conduct reviews of a Tooling and/or Equipment to ensurethat the manufacturing process is:

    • designed to the latest drawing change level

    • built

    • certifiedso as to produce:

    • quality parts

    • at rate

    • according to GM program requirements

    11 Gage Development and Approval

  • 8/9/2019 APQP-GM

    52/73

    SQE approve gage per GM 1925 Fixture Standards, including:

    •Ensure that any part changes are incorporated into gages.

    •Evaluate Coordinate Measuring Machine (CMM) report to ensuregage accuracy.

    •Ensure gage instructions (ODS) are available at themanufacturing operation.

    •Verify integrity of gage for fit and function and GR&R (referenceMSA AIAG).

    •Verify that it is properly identified as GM property.

    11. Gage Development and ApprovalPurpose:

    To design, build and certify gages according to latest GD&T

    release and per GM requirements.

    11. Gage Development and Approval

  • 8/9/2019 APQP-GM

    53/73

    Supplier Responsibility:

    Design, build, certify gage dimensionally (including a third partycertification), perform complete AIAG MSA (GR&R and Biasstudy) and meet all requirements established by GM1925. A lean

    gage (pull ahead CMM holding fixture) should be available forfirst IVER build.

    11. Gage Development and Approval

    12 PFMEA

  • 8/9/2019 APQP-GM

    54/73

    12. PFMEA

    TOP 5 RPN Reduction Plan (Correct RPN value) !

    IT’S A LIVING DOCUMENT!

    Top RPN Reduction Plan

  • 8/9/2019 APQP-GM

    55/73

    Top RPN Reduction Plan

    13. Control Plan

  • 8/9/2019 APQP-GM

    56/73

    13. Control Plan

    Define the Method being used to Control all KPCs,PQC and KCCs for Parts being Manufactured forVehicle Builds.

    Prototype Control Plan

    Pre-Launch (GP-12) Control Plan

    Implementing from the first production part ship to

    GM assembly line

    Production CP: shall be verified by Pre-launch PCP

    Control Plan

  • 8/9/2019 APQP-GM

    57/73

    SQE shall define PCPA schedule andfrequency based on the risk priority of part and

    process (Based on risk assessment)

    It’s a living document to address any

    change in product/process and reflect

    updated control for quality issue

    Supplier and SQE shall verify final inspection to

    ensure a robust inspection method

    Key points

    Control Plan

    14. GP-12

  • 8/9/2019 APQP-GM

    58/73

    14. GP 12

    Prototype

    Pre-Launch (GP-12)

    Production: shall be validated by Pre-launch PCP

    Establish a Containment Plan during Start-upand acceleration that will Quickly IdentifyQuality Issues at the Supplier’s Facility; i.e., aPre-Launch Control Plan

    GP-12

  • 8/9/2019 APQP-GM

    59/73

    GP12 Audit/Verification and take corrective action

    Layered Audits by supervisor/Manager

    Proactive Controlled Shipping Strategy and Execution

    A. Failure to execute GP-12 will result in Controlled

    Shipping Level 2 and other possible consequences.

    B. Shipment of non-conforming material will result inControlled Shipping Level 2.

    GP 12

    Duration of GP-12

  • 8/9/2019 APQP-GM

    60/73

    GP-12 must be implemented for a period of timeor quantity of parts as specified by the customer oruntil the Production Control Plan has beenvalidated, whichever is longer.

    If time or quantity is not specified, GP-12 willremain in effect through acceleration or aminimum of 2 weeks, whichever is longer.

    15. PPAP

  • 8/9/2019 APQP-GM

    61/73

    Indicates the process can consistently meet the

    requirements at production rate

    Indicates the supplier’s understanding of the

    engineering design record and specifications

    requirements

    Defines generic requirements for production andbulk materials

    Production Part Approval Process

    15. PPAP

    PPAP

  • 8/9/2019 APQP-GM

    62/73

    Applies to all internal and externalsupplier sites of production and service

    parts unless otherwise specified by theauthorized customer representative

    Applicability

    PPAP

    PPAP

  • 8/9/2019 APQP-GM

    63/73

    Supplier Production Trial Run

    PPAP pre-production

    PPAP SPR

    PPAP is not one day job

    PPAP

    Key points

    Supplier Production Trial Run

  • 8/9/2019 APQP-GM

    64/73

    - Supplier has to proof their process stability before PPAPproduction

    - Walk through the manufacturing process to verify thePFD/PFMEA/Control Plan and error proofing

    - Make sure KPC and KCC are clearly identified andcommunicated at the shop floor

    - Make sure operators are properly trained- Review error proofing application in the process

    - Verify the results of the production trial run to determine anyactions required before going to next step

    - Verify GM engineering approval status and possible designchange status

    pp

    Significant Production Run

  • 8/9/2019 APQP-GM

    65/73

    For production parts, product for PPAP shall be taken

    from a significant production run:

    From 1 to 8 hours of production

    To total a minimum of 300 consecutive parts

    Produced at the production site  at the production rate 

    using production tooling gages operators etc.

    Each unique manufacturing process shall be represented

      ulk material samples shall be taken from “steady state”

    operation

    g

    Customer Notification

  • 8/9/2019 APQP-GM

    66/73

    The organization shall notify the authorized

    customer representative SQE of any planned changesto design, process, or site

    Upon notification and approval, and after changeimplementation, submission is required unless

    otherwise specified

    PPAP Submission levels

  • 8/9/2019 APQP-GM

    67/73

    Level 5 - Warrant, product samples and data for

    review at supplier’s location

    Level 4 - Warrant and customer requirements

    Level 3 - Warrant, product samples and data

    (cons idered the default level)

    Level 2 - Warrant with product samples

    Level 1 - Warrant only

    All required information shall be available or included in thesubmission (levels 2-4) regardless of submission level!

    16. Run @ Rate GP – 9

  • 8/9/2019 APQP-GM

    68/73

    Verifies capability

    1 Day production at supplier site

    = 1 Day usage in GM

    Required for all new parts

    Must meet: QTC on contract

    Five working days per week

    @

    Run @ Rate GP – 9

  • 8/9/2019 APQP-GM

    69/73

    Begin from program Kick-Off (Initial GP-9)

    No later than 8 weeks prior to SORP

    Need to verify from time to time

    - Tooling/M&E review

    - FOS

    - PPAP SPR

    - After Salable PPAP (According to “Hours per day”)

    Key points

    Run @ Rate Approval Decisions

  • 8/9/2019 APQP-GM

    70/73

    Fail

    Pending PPAP

    Pass (FULL PPAP)

    17. Lessons Learned

  • 8/9/2019 APQP-GM

    71/73

    Key points

    SQE shall review Lessons learned from the everybeginning of a program

    SQE shall ensure countermeasure in place to prevent

    repeating same problem (Error-proofing, 100%

    inspection, SPC) SQE shall share Lessons Learned of similar

    part/process with supplier 

    SQE shall drive supplier to implement Lessons

    Learned as a systematic tool for continuousimprovement

    http://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xlshttp://c/00%20IRIS/APQP%20APO/Iris_APQP%20T3/HSR&A/Tooling/GM%20TOOL&MOLD%20LIST(070405).xls

  • 8/9/2019 APQP-GM

    72/73

  • 8/9/2019 APQP-GM

    73/73

    Gl b l APQP f SQE

    Driving GM to be the BEST!!!

    Thank You