APPROACH TO PROJECT

11
INDOT RFP 1609 ITEM 02: BRIDGE DEVELOPMENT SERVICES - INSPECTION AND ASSESSMENT FOR US 50 EBL AND WBL BRIDGES OVER THE WABASH RIVER BORDER WITH ILLINOIS WSP | PARSONS BRINCKERHOFF SEPTEMBER 27, 2016 1 AN EXPERIENCED LOCAL TEAM WSP | Parsons Brinckerhoff has assembled a proven design team to successfully complete each of the requirements listed in the RFP. Our team has extensive experience with bridge inspections, destructive/non-destructive testing, life cycle analysis, hydraulic analysis, and environmental planning and permitting. This team combines the local knowledge and technical expertise to layout the most efficient design elements as well as provide the management capability to successfully deliver the project. Bridge Inspection: With USI as a partner, we are able to provide INDOT with a highly experienced Fracture Critical Bridge Inspection teams. This allows us to provide a detailed report that will identify any current or potential problems. Bridge Testing: GSI has the technology to perform non-destructive testing of the superstructure, and the substructure if required. The final product will allow our team to map out exact locations of full/partial depth patching. Environmental: Our hydraulics group will work closely with Kaskaskia to determine the best methods for debris removal at the pier locations. Hydraulic Analysis: Our Hydraulics group will lead the effort for the scour analysis of the existing bridge piers, and also work with the environmental group in developing all required permits for construction. Bridge Design: Our bridge group has had recent experience on several Indiana projects that deal with bridge restoration and complex bridge analysis. LEADERSHIP TEAM Our team’s proposed Project Manager (PM) Charles Boltz, a structural engineer with a diverse engineering background, will bring a well-rounded perspective to the design and layout of this project. Experience being the PM on projects both roadway and bridge oriented provides Charles an understanding of the communication that is required between each discipline in order to deliver the best product possible to INDOT. Having a deep bench and multiple design teams under one overall project manager will provide a greater opportunity to serve the Central Office and make certain that we are available for you, whenever you need us. Charles has been working with the Central office to complete several bridge rehabilitation projects, and he has several connections to ensure the project moves smoothly. APPROACH TO PROJECT Budget: WSP | Parsons Brinckerhoff has a proven record providing designs that save INDOT money, and stay at or below the construction budget set. Schedule: Our in-house policy is to deliver each design package a minimum of one month before the date required. This allows INDOT more time to review and or finalize packages for letting. Responsiveness: One day turn around for questions is our goal, and this can be seen from our past performance on projects. Constructability: With in-house construction inspection staff, we have the ability to complete internal constructability checks before submitting plans to INDOT. Quality: As one of the most important items, we take pride in the product we make and make every attempt to eliminate errors that would require change orders during construction. WE ARE READY TO WORK FOR YOU! WSP | Parsons Brinckerhoff is proud to present a team of experienced staff under the leadership of proven project manager, Charles Boltz, PE to complete these bridge project development services. This team was strategically selected based on their ability to leverage past lessons learned that may be relevant to the design tasks assigned in the Central Office. Shelby A. Swango, PE, Vice President and Area Manager AUTHORIZED NEGOTIATOR 317.287.3413 | [email protected]

Transcript of APPROACH TO PROJECT

INDOT RFP 1609 ITEM 02: BRIDGE DEVELOPMENT SERVICES - INSPECTION AND ASSESSMENT FOR US 50 EBL AND WBL BRIDGES OVER THE WABASH RIVER BORDER WITH ILLINOIS

WSP | PARSONS BRINCKERHOFF SEPTEMBER 27, 2016 1

AN EXPERIENCED LOCAL TEAMWSP | Parsons Brinckerhoff has assembled a proven design team to successfully complete each of the requirements listed in the RFP. Our team has extensive experience with bridge inspections, destructive/non-destructive testing, life cycle analysis, hydraulic analysis, and environmental planning and permitting. This team combines the local knowledge and technical expertise to layout the most efficient design elements as well as provide the management capability to successfully deliver the project. Bridge Inspection: With USI as a partner, we are able to provide INDOT with a highly experienced Fracture Critical Bridge Inspection teams. This allows us to provide a detailed report that will identify any current or potential problems.Bridge Testing: GSI has the technology to perform non-destructive testing of the superstructure, and the substructure if required. The final product will allow our team to map out exact locations of full/partial depth patching.Environmental: Our hydraulics group will work closely with Kaskaskia to determine the best methods for debris removal at the pier locations. Hydraulic Analysis: Our Hydraulics group will lead the effort for the scour analysis of the existing bridge piers, and also work with the environmental group in developing all required permits for construction.Bridge Design: Our bridge group has had recent experience on several Indiana projects that deal with bridge restoration and complex bridge analysis.

LEADERSHIP TEAMOur team’s proposed Project Manager (PM) Charles Boltz, a structural engineer with a diverse engineering background, will bring a well-rounded perspective to the design and layout of this project. Experience being the PM on projects both roadway and bridge oriented provides Charles an understanding of the communication that is required between each discipline in order to deliver the best product possible to INDOT. Having a deep bench and multiple design teams under one overall project manager will provide a greater opportunity to serve the Central Office and make certain that we are available for you, whenever you need us. Charles has been working with the Central office to complete several bridge rehabilitation projects, and he has several connections to ensure the project moves smoothly.

APPROACH TO PROJECTBudget: WSP | Parsons Brinckerhoff has a proven record providing designs that save INDOT money, and stay at or below the construction budget set.Schedule: Our in-house policy is to deliver each design package a minimum of one month before the date required. This allows INDOT more time to review and or finalize packages for letting.Responsiveness: One day turn around for questions is our goal, and this can be seen from our past performance on projects.

Constructability: With in-house construction inspection staff, we have the ability to complete internal constructability checks before submitting plans to INDOT.Quality: As one of the most important items, we take pride in the product we make and make every attempt to eliminate errors that would require change orders during construction.

WE ARE READY TO WORK FOR YOU!WSP | Parsons Brinckerhoff is proud to present a team of experienced staff under the leadership of proven project manager, Charles Boltz, PE to complete these bridge project development services. This team was strategically selected based on their ability to leverage past lessons learned that may be relevant to the design tasks assigned in the Central Office.

Shelby A. Swango, PE, Vice President and Area ManagerAUTHORIZED NEGOTIATOR317.287.3413 | [email protected]

INDOT RFP 1609 ITEM 02: BRIDGE DEVELOPMENT SERVICES - INSPECTION AND ASSESSMENT FOR US 50 EBL AND WBL BRIDGES OVER THE WABASH RIVER BORDER WITH ILLINOIS

WSP | PARSONS BRINCKERHOFF SEPTEMBER 27, 2016 2

PROPOSED TEAM QUALIFICATIONSWSP | Parsons Brinckerhoff has assigned people you can trust, who are technically experienced, local and schedule-driven. Project Manager Charles Boltz will be the main point of contact for INDOT and will foster communication with all project participants. WSP | Parsons Brinckerhoff’s Indianapolis-based staff will provide local, technical support as well as local knowledge and a link to a number of important past projects.PARSONS BRINCKERHOFF , INC. (55%)8.1 Non-Complex Roadway Design9.2 Level 2 Bridge Design11.1 Right of Way Plan Development

KASKASKIA (K) (4% DBE)5.2 Environmental Document Preparation - CE5.6 Waterway Permits

PCS ENGINEERS (PCS) (5% DBE)6.1 Topographic Survey Data Collection

GS INFRASTRUCTURE (GS) (3%)6.1 Topographic Survey Data Collection

WOODCO ENTERPRISES, LTD (W) (.5%)12.2 Title Research

USI CONSULTANTS, INC. (USI) (32.5%)8.1 Non-Complex Roadway Design9.2 Level 2 Bridge Design

ORGANIZATION CHART

AVAILABLE CAPACITY When considering recent wins with INDOT, WSP | Parsons Brinckerhoff has current workload forecast in the range of 50% over the next two years. The reason for this availability is the recent completion of past projects with INDOT. With consideration that over the next year INDOT will be releasing several more jobs for design, we are still confident that we have the capacity to now and in the future to give this job all of the attention that it requires and deserves.

PRINCIPAL-IN-CHARGEShelby Swango, PE

INDOT CENTRAL DISTRICT PROJECT MANAGER

PROJECT MANAGERCharles Boltz, PE

QA/QCDandi Prasad, PE

ENVIRONMENTAL DOCUMENT PREPARATION

Kent Ahrenholtz, PE [K]

WATERWAY PERMITSRobyn Toole, PE

TOPOGRAPHIC SURVEYGrant Niemeyer, PS [PCS]

ROADWAY AND MOT SERVICES

John Bowen, PEDuane McKinney, PE

RIGHT OF WAY PLAN DEVELOPMENT

Patrick McCallister, RWAJeff Bislich, PE, PS

TITLE RESEARCHSue Ann Wood [W]

BRIDGE DESIGN / PLAN DEVELOPMENTCharles Boltz, PE Beth Carter, PE

Karl Krukenberg, PEDivya Mamidala

NON-DESTRUCTIVE TESTING

Kim Klender [GS] Gary Howard [GS]

BRIDGE INSPECTION

INSPECTION TEAM 1Michael Obergfell, PE [USI]

Bonnie Money, PE [USI]Brett Longenecker, EI [USI]

INSPECTION TEAM 2Rob Coop, PE [USI]

George Watson, PE [USI]

INSPECTION TEAM 3Beth Carter, PE

Karl Krunkenberg, PE

LEGENDGS Infrastructure (GS)Kaskaskia (K)PCS Engineers (PCS)USI Consultants, Inc. (USI)Woodco Enterprises, LTD (W)

QUALITY ASSURANCE AND ACCOUNTABILITYRegardless of the assignment or project size, the WSP | Parsons Brinckerhoff team has a longstanding commitment to quality. Our team develops a QA/QC plan that requires a rigorous process of checking and back checking every calculation and plan sheet prior to every submittal. We have made the strategic decision to conform our existing quality management system to the requirements of International Organization for When considering recent wins with INDOT, WSP | Parsons Brinckerhoff has current workload forecast in the range of 50% over the next two years. The reason for this availability is the recent completion of past projects with INDOT. With consideration that over the next year INDOT will be releasing several more jobs for design, we are still confident that we have the capacity to now and in the future to give this job all of the attention that it requires and deserves.

INDOT RFP 1609 ITEM 02: BRIDGE DEVELOPMENT SERVICES - INSPECTION AND ASSESSMENT FOR US 50 EBL AND WBL BRIDGES OVER THE WABASH RIVER BORDER WITH ILLINOIS

WSP | PARSONS BRINCKERHOFF SEPTEMBER 27, 2016 3

YEARS OF EXPERIENCE14EDUCATIONM.S., Civil Engineering, 2002; B.S., Civil Engineering, Purdue University, 2001

PROFESSIONAL ENGINEERIndiana, 2008 (10810132)

WHY CHARLES?

» Experience with and extensive knowledge of INDOT policies and processes

» Proven commitment in meeting expectation for quality, schedule, and budget

CHARLES BOLTZ, PEPROJECT MANAGERCharles is a lead structural engineer for the WSP | Parsons Brinckerhoff Indianapolis office. Charles’ experience is in the structural analysis and design of transportation related structures, specializing in bridges and transit structures. He has extensive experience in designing and detailing a wide variety of steel and concrete structural elements for bridge rehabilitation. Charles also has a proven track record in the design of steel and concrete structures to meet AASHTO LRFD Specifications.

RELEVANT EXPERIENCE » Fracture Critical Inspection of Ohio River Bridges, Southern Indiana: team member for the inspection of several Ohio River Bridges. Bridges that were inspected include the Bi-State Vietnam Gold Star Bridges at Henderson, KY; the Glover Cary Bridge at Owensboro, KY; John A. Roebling Suspension Bridge at Covington, KY; and the Earle C. Clements bridge at Shawneetown, IL. The inspections ranged from 1 to 4 weeks in time, and involved an arms length inspection of all fracture critical elements.

» Mill and overlay for I-94 Corridor: 3.5 miles of the I-94 corridor are to be mill and overlayed with pavement patching. This portion included both pavement design and roadway design.

» NICTD Rehab: The I-94 bridges over NICTD Railroad are to have a full deck replacements, and will be converted into semi-integral bridges to eliminate deck joints in the structures.

» County Line Road over I-94: This bridge originally was scoped for a full deck replacement, and then modified to receive only a mill and overlay on the deck after the field inspection with INDOT.

» CSX Rehab: The I-94 bridges over CSX Railroad were originally scoped for full deck replacements, and then modified to receive only a mill and overlay on the decks after the field inspection with INDOT.

» Fort Wayne Design/Build Bridge Rehabilitation, Fort Wayne, Indiana: project task lead in charge of the design/production efforts for each bridge, and cross coordination with other disciplines such as hydraulics and utilities. SR 3 over the Wabash River is a seven span continuous structure that was converted to have semi-integral abutments (to remove deck joints) with a full deck replacement. SR 930 over NS Railroad was a six span structure that was converted to a continuous semi-integral structure by replacing the last concrete span with a continuous steel girder span and placement of a new deck. Railroad, utility, and hydraulic coordination were also key for this project in order to allow for it to be constructed within its accelerated construction time line.

» I-465 Over US40/Washington Street (Accelerate I-465), Indianapolis, Indiana: designer of the bridge piers for this structure. Pier geometry was two multicolumn piers each approximately 120’ long with an incorporated crashwall between columns.

KEY STAFF

INDOT RFP 1609 ITEM 02: BRIDGE DEVELOPMENT SERVICES - INSPECTION AND ASSESSMENT FOR US 50 EBL AND WBL BRIDGES OVER THE WABASH RIVER BORDER WITH ILLINOIS

WSP | PARSONS BRINCKERHOFF SEPTEMBER 27, 2016 4

YEARS OF EXPERIENCE26EDUCATIONMasters, Business Administration, Virginia Tech, 1999; B.S., Civil Engineering, Bangalore University, 1984PROFESSIONAL ENGINEERIndiana, 2010 (#10911087); Virginia, 1995 (#026032)

YEARS OF EXPERIENCE25EDUCATIONB.S., Civil Engineering (Structural), Purdue University, 1988PROFESSIONAL ENGINEERIndiana (#19300383)

MICHAEL OBERGFELL, PEUSI INSPECTIONMike has spent the last 25 years in the industry focused solely on bridge inspection, rehabilitation and replacement design projects. As a principal of USI, Mike oversees USI’s Bridge Design and Inspection Department, ensuring that adequate resources are available to meet each and every demand our clients bless us with the opportunity to work on. Mike’s expertise in the bridge design and rehabilitation fields allow him to be an integral part of the design team on all projects from a high level review standpoint, so that necessary decisions can be made quickly during the development of the project. Mike has completed hundreds of bridge rehabilitation projects in his career, and completed thousands of bridge inspections for INDOT and Indiana LPA’s. This experience allows Mike to assist our team in providing cutting edge, yet practical solutions based on years of insight in the bridge engineering community. Mike has dedicated, and continues to do so, a lot of his time to furthering the mission of improving our infrastructure statewide, by having served on numerous INDOT Structural and Liaison Committees over his career. He is currently leading a campaign through ACEC Indiana to promote further investment in our infrastructure through legislative action in the coming year, and commits to bringing this dedication to each and every project.He possesses the expertise and working knowledge of INDOT, federal aid, and locally funded LPA projects. In addition to designing and managing countless bridge projects for INDOT and Local Public Agencies throughout Indiana, Mike has completed numerous bridge engineering assessment studies for the Indiana Department of Transportation (INDOT).

DANDI PRASAD, PEQA/QCDandi is a senior supervising structural engineer experienced in the structural analysis and design of transportation-related structures, specializing in bridges and transit structures. He has extensive experience in the project management of large complex projects, designing and detailing a wide variety of steel and concrete structural elements for bridge rehabilitation projects, and developing type studies to evaluate an optimal bridge type for a particular location. Mr. Prasad has a proven track record in the design of steel and concrete structures to meet AASHTO LRFD Specifications.Dandi has led major bridge rehabilitation and replacement projects such as the SR 930 Bridge over the NS RR & SR 3 Bridge Over Wabash River for INDOT. On both projects, Dandi served as project manager for developing the bridge rehabilitation plans. SR 930 over NS RR was a six span structure that included deck reconstruction, replacement of existing concrete beams for the end span with a steel girder to make it continuous steel superstructure over the entire bridge, converting existing abutments to semi-integral end bents. The construction had to be completed within a seven-month window and it required phased construction, RR and utility coordination. The SR 3 Bridge over Wabash River is a seven span continuous structure that was converted to semi-integral end bents and a full deck replacement. The SR 3 bridge was closed to traffic but the closure period was restricted and had to be constructed with an accelerated construction timeline. Both these bridges will be completed within schedule and budget.

INDOT RFP 1609 ITEM 02: BRIDGE DEVELOPMENT SERVICES - INSPECTION AND ASSESSMENT FOR US 50 EBL AND WBL BRIDGES OVER THE WABASH RIVER BORDER WITH ILLINOIS

WSP | PARSONS BRINCKERHOFF SEPTEMBER 27, 2016 5

YEARS OF EXPERIENCE10EDUCATIONM.S., Civil Engineering, Purdue University, 2005B.S., Physics, Purdue University, 2003

YEARS OF EXPERIENCE23EDUCATIONAssociates Degree of Applied Sciences, Vincennes University, 1992

YEARS OF EXPERIENCE14EDUCATIONB.S., Civil Engineering, Rose-Hulman Institute of Technology, 2002

PATRICK MCCALLISTER, RWARIGHT OF WAY DEVELOPMENTPatrick McCallister has managed and produced numerous right-of-way engineering and right-of-way acquisition projects in his more than 20 years in the survey/engineering industry. Mr. McCallister joined WSP | Parsons Brinckerhoff in 2013 as right-of-way acquisition manager. Mr. McCallister is responsible for managing the entire acquisition process for the project. He assigns and sets schedules for the title researchers, appraisers and buyers and closely monitors the progress of each parcel during the acquisition process. He has extensive experience in right-of-way plan development, legal descriptions, right-of-way parcel plats, transfer documents, and other documents related to the land acquisition process. He also has experience in deed research, obtaining subdivision plats and assessor maps to determine existing right-of-way, and preparing Location Control Route Survey Plat in accordance with INDOT requirements and Title 865 of the Indiana Administrative Code.

ROBYN TOOLE, PENON-DESTRUCTIVE TESTINGRobyn Toole is a civil engineer with WSP | Parsons Brinckerhoff’s Indianapolis office specializing in hydraulic and hydrologic analysis with experience in drinking water, waste water, storm water, and water resources planning and design. Her experience includes hydraulic modeling, surge analysis, flood modeling, master planning, pump station design, storage facility design, utility relocation, infrastructure inspections and management of various types of projects. Ms. Toole has also been involved in environmental site assessment and remediation, NPDES and state level permitting, and storm water pollution prevention plan preparation.

JOHN BOWEN, PEROADWAY AND MOT SERVICESJohn is a lead engineer with WSP | Parsons Brinckerhoff, experienced in roadway design. John’s experience includes managing roadway reconstruction projects for the Indiana Department of Transportation (INDOT) and various local public agencies (LPA) within the state of Indiana. John has experience in road design, intersection design, roundabout design, urban interstate design, and small structure replacement projects. In addition to his experience in roadway design, John has also worked on developing NEPA documents, permitting, and utility coordination in the course of his career. This knowledge allows him to understand how all the pieces must fit together to produce a successful project. Whether the project is addressing intersection safety in Indianapolis; creating a pedestrian friendly environment in downtown North Vernon; or providing a safer roadway alignment for a new bridge crossing in Monroe County, John has the knowledge, drive, and experience to apply this expertise to US50 EBL and WBL Bridge project.

INDOT RFP 1609 ITEM 02: BRIDGE DEVELOPMENT SERVICES - INSPECTION AND ASSESSMENT FOR US 50 EBL AND WBL BRIDGES OVER THE WABASH RIVER BORDER WITH ILLINOIS

WSP | PARSONS BRINCKERHOFF SEPTEMBER 27, 2016 6

PROJECT APPROACH

ENVIRONMENTALThe WSP | Parsons Brinckerhoff team has prepared environmental documents for projects of all sizes,

from Level 1 Categorical Exclusions (CEs) to Environmental Assessments (EAs) and FONSIs to Environmental Impact Statements (EISs) on some of the most challenging projects in the state. These include projects as diverse as single bridge replacement/rehabilitation to roadway rehabilitations to new location interstate construction, such as I-69.The professionals with WSP | Parsons Brinckerhoff and Kaskaskia Engineering Group have already done some basic research about the environmental issues concerning the US 50 project, and expect that some level of Categorical Exclusion will be appropriate. The exact level will be determined based on the alternative treatments that are proposed following completion of the bridge inspection report. Based on a review of similar work to the I-64 bridges over the Wabash River, it is expected that debris removal under the existing structure will also require

construction of scour protection at the base of the piers. Besides any deck rehabilitation, the placement of sheet pile and granular material around the piers will most likely necessitate preparation of a Waters of the US report and submission of Section 404/401 permit applications.The team’s efforts will begin by conducting an early Red Flag Investigation (RFI) to identify potential issues and corresponding avoidance, minimization, or mitigation measures. Following acceptance and approval of the RFI, the level of environmental documentation will be finalized and the Early Coordination Packets (ECP) will be distributed to the appropriate Federal, state and local agencies. Once the 30-day comment period is complete, the team can proceed with preparation of the environmental document and submittal for INDOT review and approval. Timelines can be critical in the analysis of environmental impacts because of the length of time required for reviews, so it will be the goal of the environmental efforts to stay off the critical path.

Slopewall deterioration

Fracture Critical End Span Details

Fracture Critical Main Span Details

Debris Collection at bridge piers

Bird Nesting

Fracture Critical End Span Details

Slopewall deterioration

INDOT RFP 1609 ITEM 02: BRIDGE DEVELOPMENT SERVICES - INSPECTION AND ASSESSMENT FOR US 50 EBL AND WBL BRIDGES OVER THE WABASH RIVER BORDER WITH ILLINOIS

WSP | PARSONS BRINCKERHOFF SEPTEMBER 27, 2016 7

BRIDGE INSPECTIONOur team will perform the Fracture Critical Inspection of US-50 Eastbound and Westbound bridges over

the Wabash River by following a well detailed Plan of Action. The inspection will require the use of an under bridge access vehicle to allow full access to the 2-girder system for the hands-on inspection to be conducted. The use of an under bridge access vehicle will require to the right lane of each structure to be closed to traffic. Since both structures are two lanes flowing in a single direction, closing one lane of traffic will require proper traffic control devices, but no additional personnel for flagging. A four to five-person team, consisting of at least two Professional Engineers and one Commercially Licensed Driver, should be able to perform the Fracture Critical Inspection on both bridges within 3 to 4 days, depending on weather, traffic, mobilization and demobilization of equipment, etc.

The main spans of both structures are comprised of a 2-girder system, which are non-redundant load path systems. Fracture Critical Members are steel members in tension or with a tension element, subject to tensile stress variations, whose failure would likely result in a partial or entire collapse of the structure. The FCM’s would include the non-redundant girders and the floorbeams if they are spaced greater than 14’-0”. Our inspectors will also look carefully at any and all problematic and fatigue prone details that include but are not limited to tri-axial constraint details, riveted connections, field welded stiffeners, attachments or repairs and cantilevered details that could result in out-of-plane bending. Nondestructive testing techniques will be utilized during this inspection as to not inflict any damage onto the structures. Visual and audible inspection techniques will be used, as well as, dye-penetrant testing to more accurately locate and evaluate cracks in the steel girders, welds, connection members, etc.

Our team has performed Fracture Critical Inspections on numerous structures throughout Indiana. One particular structure that is similar to the US-50 structures is Shelby County Bridge 73-00032 (NBI: 7300032). The 110’ structure is a Fracture Critical, 2-girder through truss that carries CR 500 North over the Little Blue River. The steel deck is supported by a stringer-floorbeam system that is connected into the two through girders. The floorbeams are spaced at 15’-3” and so are considered fracture critical. They also have welded cover plates attached to their bottom flanges, which is a fatigue prone detail 3.7 that corresponds to a Fatigue Category “E.” Most of connections are mechanically fastened using rivets, which is a fatigue prone detail 2.3 that has a Fatigue Category “D” rating.

Caption

PRACTICAL DESIGN AND CONSTRUCTABILITYOur experiences partnering with contractors on design-build pursuits has enhanced our design mindset with an in-depth understanding of constructability issues. Charles and the project staff understand that practical design has the most impact early in the design process. The team will weave practical design and constructability reviews from the beginning of the project development process and throughout the life of the project. Practical design is a shift in thinking to be utilized throughout the life of a project that we have adopted as the norm. We have learned to continually challenge the standard and ask if there is an equally safe solution that will ultimately give INDOT and the tax payers more for their money.Constructability reviews will also be incorporated into each deliverable. Charles will include experienced WSP | Parsons Brinckerhoff staff, such as Kevin Hall, PE, from our construction inspection team who has over 33 years overseeing construction projects for INDOT, as well as the expertise of the local Vincennes District personnel to ensure that our approach is thorough, our plans are clear, and our design can be efficiently constructed.

INDOT RFP 1609 ITEM 02: BRIDGE DEVELOPMENT SERVICES - INSPECTION AND ASSESSMENT FOR US 50 EBL AND WBL BRIDGES OVER THE WABASH RIVER BORDER WITH ILLINOIS

WSP | PARSONS BRINCKERHOFF SEPTEMBER 27, 2016 8

NON DESTRUCTIVE TESTING

Our team will use GSI as a sub consultant which strives to be a leading service provider of non-destructive testing (NDT). GSI’s non-destructive testing of bridge decks uses infrared thermography (IRT) and ground penetrating radar (GPR) to scan non-visible locations. Traditional methods use manual sounding and collection techniques, which can be time consuming. They can also lead to cost overruns from inaccuracies due to human interpretation, and discrepancies from background noise. In addition, traditional methods most often require lane closures. With IRT and GPR, GSI certified technicians retrieve visual and thermal images and collect this data with an automated software program, from inside a vehicle traveling at highway speeds. This all occurs in significantly less time, and without the need for lane closures.

DATA COLLECTIONSpecified elements of the bridge will be scoped, utilizing the method required. This includes capturing data from a vehicle at highway speeds, maritime vessel or ground when accessible, using a vehicle mounted GPR, IRT, and/or a hand held IRT and HD visual camera. These approaches all take place without the need for traffic control. For maritime collection, two technicians will be on-site at all times with the assistance of a captain for operation of the maritime vessel. Conventional methods of sounding will be performed as part of the Quality Control (QC) process by GSI on portions of each bridge element during off peak times. Information collected will be used to verify data collection times and data is consistent with the NDT findings.

ANALYSISDuring the analysis phase, indications of delaminations, patches, spalls, deterioration and significant cracking will be identified, quantified and compiled in percentages based on total square foot area. The results will be comprehensive and assembled in a manner that can be easily incorporated into bridge inspection reports, work recommendations, and/or detailed scoping documents.The final phase of the project is to communicate the NDT findings and results in the report form. GSI will compile and present the data in a useful manner, to aid in future programming and asset management decisions by the client. The analysis, report development, and QC measures will take place at GSI facilities. For the deck, the report shall cover the area and depth of deck delamination, voids, patches, cracks and spalls. Results will be reported in native CAD formats.

Company Confidential – GS Infrastructure, Inc. Page 3 of 7

Infrared Thermography

Infrared thermography imaging utilizing natural diurnal cycle for detection of defects by temperature differential through materials. Scoping of concrete surfaces and various overlays (HMA, LMC, etc) at highway speeds. Underdeck and sub/superstructure scanning from ground or maritime platform to 100’ away. No lane closures GPS for defect location on deck-top surveys. ASNT TC-1A Level I Thermographers.

Ground Penetrating Radar

Ground penetrating radar with multi-antenna array penetrates multiple feet through various materials. GPR uses electromagnetic energy to sense differing dielectric constants of materials or voids. High Speed condition assessments for delamination indication, rebar depth, deck and overlay thickness measurements. Ground and Air-Coupled antenna arrays are used for optimal scoping of roads, bridges, sidewalks, slope integrity, abutments and substructure elements.

High Definition Visual Camera

High Speed HD image collection for condition assessments by locating and quantifying patches, spalls and cracks. R&D licensed analysis software. AASHTO-Compliant crack mapping - ability to detect AASHTO stages 1, 2 & 3. Automated deliverables for Pavement Condition Index (PCI) for roads, parking lots and airports.

2. Non-Destructive Testing - What we do.

“GS Infrastructure is building and preserving for the future – building relationships, building customer confidence, building customer satisfaction, inspecting infrastructure for preserving the past and building the future.” –Lynn Eliason, President- GS Infrastructure

INDOT RFP 1609 ITEM 02: BRIDGE DEVELOPMENT SERVICES - INSPECTION AND ASSESSMENT FOR US 50 EBL AND WBL BRIDGES OVER THE WABASH RIVER BORDER WITH ILLINOIS

WSP | PARSONS BRINCKERHOFF SEPTEMBER 27, 2016 9

BRIDGE REHABILITATIONAfter the completion of both the arms-length

bridge inspection, and the non-destructive testing, WSP | Parsons Brinckerhoff will develop a proposal for the bridge rehabilitation. Depending on the results this may be as simple as deck patching and slope wall repair, or as complicated as a deck replacement and fracture critical element repairs. At this time we do not have a proposal for work to be done, but instead we can show the qualifications our team has to handle any structural repair that may be needed on the structure. Our team currently has several active bridge rehabilitation jobs active with INDOT, and several more that have been recently completed. Each of these jobs has required unique structural solutions that have saved INDOT both time on money.

» Deck Replacement: Our team has completed deck replacement jobs all across Indiana from Fort Wayne, LaPorte, Evansville, and Crawfordsville. These jobs have ranged from simply replacing the existing deck, to a full deck replacement where the concrete end spans have been removed and new continuous end spans added.

» Structural Analysis: The existing structure is composed of approach bridges, and a two-girder bridge spanning over the Wabash river. If required, the two-girder structure is going to require a more specialized model to properly calculate the forces being transmitted through each element (both cross frames and transverse stiffeners). Proper modeling of the structure will be crucial in order to design and corrections that the bridges require.

» Slope Walls: From our site visit, it is obvious that the slope walls are in need of repair. Several of our recent projects have required similar repairs including crack repair, and settlement

issues due to washout under the slopewalls. With our in house geotechnical group we will also be able to confirm all stability aspects of the slope walls after repairs are made.

DEVELOPMENT OF FRACTURE CRITICALDetails for potential repairs to the bridge:The WSP | Parsons Brinckerhoff team has extensive prior experience with providing fracture critical repair details to bridges similar to the US 50 bridges. On the I-65 Approach bridges to the JFK bridge (now part of the ORB project) we were involved in producing details and drawings pertaining to the floor beam- stringer type structure. This experience can be directly applied to this project. Most of the details pertained to drilled holes to prevent propogation of fatigue cracks as shown in the graphics here . Most of the details developed were location specific and developed with constructability in mind. The lessons learned on the I-65 project included:1. The repair details have to be developed wre meant to be as

simple as possible. 2. Access to the repair locations has to be carefully considered.

This was particularly complicated with MOT aspects on a heavily traveled bridge.

3. As part of the repair details details such as blocking and temporary supports have to be developed to ensure constructability.

4. This project may require several unique special provisions to given the structure type.

Every project is unique and requires an approach and team specifically tailored to the needs of the project. With this project there will be a scoping phase for the inspection work, then a follow-up scoping phase for bridge repair. Charles will work with the INDOT PM during all of these phases to help ensure a scope and budget is developed that meet INDOT’s needs. With the information obtained from the meetings, Charles then will assign the appropriate teams to start work for each phase.

NTP1 2 3 5 6 7 8

$4

Open Roads, QA/QC, and Periodic Progress Reports & Meetings are Continuous

PROJECT DEVELOPMENT PROCESS

1. Meeting with INDOT Central District PM 2. Assign Appropriate Discipline Leads & Support Staff3. Develop Draft Scope & Fee4. Notice to Proceed

5. Site Visit with Team Leads6. Submit Draft Deliverables as Defined in Scope7. Incorporate Comments & Submit Final Deliverable8. Post Assignment Briefing

EXPERIENCE

I-65 OVER RIVERVIEW DRIVE REHABILITATION PROJECT (INDIANA APPROACH BRIDGE TO JFK BRIDGE)CLARK COUNTY, INDIANAWSP | Parsons Brinckerhoff provided engineering design services for the I-65 Bridge over Riverview Drive Rehabilitation project for INDOT/KYTC. The existing 7-span structure included 3 end spans that had a fracture critical steel stringer-floor beam detail. A major part of this project included fracture critical repair details to be developed in the end spans. WSP | Parsons Brinckerhoff developed the complex structural steel repair details to ensure that the structural life of these spans was extended. Lane closures were limited during construction and innovative repair schemes had to be developed so that construction could be completed during lane closures. During finger-joint replacement construction, after the deck had been removed the structural steel stringer and floor beams were found to be in an advanced state of disrepair. WSP | Parsons Brinckerhoff along with HMB provided emergency repair details so that the bridge could be open to traffic as soon as possible. The coordination between INDOT, KYTC, contractor, HMB and WSP | Parsons Brinckerhoff was critical to ensure that the appropriate repairs were completed in a short time frame and safety was not compromised.

INDOT RFP 1609 ITEM 02: BRIDGE DEVELOPMENT SERVICES - INSPECTION AND ASSESSMENT FOR US 50 EBL AND WBL BRIDGES OVER THE WABASH RIVER BORDER WITH ILLINOIS

WSP | PARSONS BRINCKERHOFF SEPTEMBER 27, 2016 10

US 41 OVER UPPER PIGEON CREEK TRUSS BRIDGE REHABVANDERBURGH COUNTY, INDIANAWSP | Parsons Brinckerhoff is currently providing engineering services for the rehabilitation of a 200’ steel truss bridge in the Vincennes District of INDOT as part of an on-call project. The existing truss structure currently does not pass load rating requirements. Failure for the structure to achieve load rating is due to certain elements either failing, or other elements being undersized for the current truck traffic. This structure is currently being considered to become historic, but at this time it is neither “Select” nor “Non-Select”.Planned repair work on the structure includes a full deck replacement which will allow access to complete repair on the supporting steel superstructure. Floor beams at the abutments are currently undersized and will be replaced along with all stringers that have failed at the connection to the floor beams. After all steel elements have been repaired or replaced the steel truss will be cleaned to remove existing pack rust and painted.Additional elements that will be repaired include the roadway safety features, and the existing floodwall will be brought back to working condition.

INDOT RFP 1609 ITEM 02: BRIDGE DEVELOPMENT SERVICES - INSPECTION AND ASSESSMENT FOR US 50 EBL AND WBL BRIDGES OVER THE WABASH RIVER BORDER WITH ILLINOIS

11WSP | PARSONS BRINCKERHOFF SEPTEMBER 27, 2016

SOUTH STREET & COLUMBIA STREET OVER WABASH RIVER (LESLIE BRIDGE)TIPPECANOE COUNTY, INDOT CRAWFORDSVILLE DISTRICT, INDIANAWSP | Parsons Brinckerhoff provided routine & special in-depth bridge inspection services for a segmental cast-in-place post-tensioned box girder (Spans 1-4) and post-tensioned concrete voided slab (Spans E-H) bridge. The routine inspection included visual inspection of all accessible superstructure bridge elements, as well as all above ground substructure elements, while paying particular attention to previously noted issues. The inspection required the use of an under bridge inspection unit to assess the outside of the superstructure. The interior of the box girders were also accessed during the inspection. WSP | Parsons Brinckerhoff coordinated with railroad flagmen from CSX and NS to perform the inspection, as well as having a water rescue plan for the above water portions.The special in-depth inspection included all elements of the routine inspection, as well as crack mapping of the box girders and tendon bore scoping, which utilized Ground Penetrating Radar (GPR) to locate tendon ducts.

UNION COUNTY BRIDGE 81-00033 (NBI: 8100020)The 467’ structure is a Fracture Critical, 4-girder bridge with pin & hangers and trilateral constraint details that carries Dunlapsville Road over Brookville Lake. The steel girders have pin and hanger connections in the center span which complex details for inspection. The girders also have trilateral constraint details, also called Hoan details, requiring a special inspection using underbridge inspection equipment. USI has inspected this bridge several times at arm’s length to check all of the complex details.

WHY WSP | PARSONS BRINCKERHOFF?

COMMUNICATION

EFFICIENCY

DEPENDABILITY

COLLABORATION

INNOVATIONThe WSP | Parsons Brinckerhoff Team strives for innovative thinking from all team members. Our team may request design Exceptions where appropriate and only if resulting in a direct benefit (cost or time savings) to INDOT. Every project has site-specific constraints and certain design criteria which may limit an idea that could possibly benefit the project.

WSP | Parsons Brinckerhoff has partnered with local subconsultants who we feel complement our skill set, providing INDOT with the “best of the best”. We know and trust our partners to collaborate and communicate openly, which is essential for the successful and timely delivery of any project.

The WSP | Parsons Brinckerhoff Team recognizes that this project requires a multi-disciplinary approach to ensure project success. It will be critical for us to establish a reliable communication protocol with the INDOT PM. Charles is committed to optimizing the time and resources of INDOT in whatever manner is most convenient.

WSP | Parsons Brinckerhoff is an industry leader and has a proven track record of meeting or exceeding project schedules. Former INDOT Commissioner Mike Cline said, “Parsons Brinckerhoff always delivers on their promises”. This is our commitment to every project.

The WSP | Parsons Brinckerhoff Team focuses on accountability and commitment. Our commitment to INDOT is to develop every project on-schedule and on-budget. We know that you are accountable for all project decisions and our job is to support INDOT in those decisions with proper engineering documentation.